victorian advanced metering infrastructure roll-out ami budgets 2009-11 and charges 2010-11 aer...
TRANSCRIPT
Victorian advanced metering infrastructure roll-out
AMI budgets 2009-11 and charges 2010-11
AER draft determination
Public forum Melbourne
21 August 2009
Presentation outline
• Introduction• AMI budgets
– Order in Council tests and AER processes– areas of initial concern to the AER and its draft
determination • AMI charges
– Order in Council requirements– AER considerations and indicative prices resulting
from draft determination for each DNSP• Process from here• Opportunity for comments/ discussion
Introduction• 2006 Victorian government decision to roll-out
AMI to all Victorian electricity customers• ESC/AER’s role set out in an August 2007 Order
in Council (OIC) and subsequent revisions• OIC provides for a pass-through of expenditures,
AER determines expenditure budgets• Metering charges set in relation to building block
calculation, includes budgeted and actual expenditures
• Metering charges regulated under separate process from general distribution charges
• January 2009 – AER framework and approach paper
• February 2009 – DNSPs submitted budget applications
• June 2009 – DNSPs submitted charges applications
• July 2009 – AER issued draft determination on charges to inform further consultation
• AER final determination on budgets and charges due 31 October 2009
Introduction
Order in Council tests
• OIC sets out tests for the expenditure:– scope test– prudent tests
• competitive tender test• expenditure incurred test• commercial standard test
• For costs to be rejected, AER must establish costs are outside scope or not prudent
• Costs associated with ‘above scope’ activities can be accepted if net benefits determined
Order in Council tests
Note: OIC presumes “yes” in each decision point unless AER establishes otherwise
Scope test 5C.2
Budget application
Is activity within scope?
Did contract arise out of a competitive tender process?
AER must approve
Is it a contract cost?
Is it more likely than not that expenditure will be incurred, or
expenditure does not substantially depart from the commercial standard?
AER not obliged to approve, but may do so if DNSP justifies
net benefit of activity
AER must approve AER not obliged to accept, but may do so if DNSP justifies net
benefit of activity
Yes
Yes
Yes
No
No
No
Yes
No
Prudent test 5C.3
AER approach to assessment
• Review of:– DNSPs’ proposals to AER and ESCV (2008)– RFP/RFT documents, procurement strategy
documents, signed contracts– internal business case documents– DNSP presentations to AER staff– further information on specific areas requested by AER
• AER engaged Energeia to provide advice on technical aspects and application of OIC tests
• Comparison of costs across expenditure categories to focus review on material areas
Scope test
• OIC contains lists of activities for each DNSP that are inside and outside scope
• In-scope activities very broad
• AER established that SP AusNet’s direct load control costs are outside scope – all other activities were found to be in-scope
Prudent tests
• Contract costs - Competitive tender test– procurement strategy documents, RFTs,
contracts– Framework and approach sets out elements
considered by the AER– contract costs = 38% of all proposed costs– AER did not receive contract information
relating to $16.3 million of SP AusNet’s proposed contract costs – assessed as non contract costs
Prudent tests• Non-contract costs – Expenditure incurred test
– implications for DNSPs of not incurring costs– CitiPower, Powercor and SP AusNet proposed costs for customer
response trials – AER established unlikely to be incurred– United Energy Distribution’s (UED) self insurance and equity
raising costs unlikely to be incurred
• Non-contract costs – Commercial standard test– categories of expenditure proposed– circumstances of DNSP, as compared to reasonable commercial
business in the circumstances– AER unable to establish any proposed costs reflected substantial
departure from the commercial standard that a reasonable business would exercise in the circumstances
2-element meters
• Proposed by SP AusNet and Powercor • above OIC minimum specifications• AER’s Framework and approach – out of scope
activities need to be justified on net benefit grounds
• time of use pricing – only available when AMI communications operational (est. 2012)
• tariff reassignments – high transitional costs• short-term net benefit demonstrated – however
may not be necessary in second budget period once AMI communications are fully operational
WiMAX
• SP AusNet communications solution, very large bandwidth• Potential to support unregulated services, which are
outside scope• further information showed lower ongoing opex costs than
alternative mesh radio solution• Energeia considered WiMAX a reasonable choice, given
AMI requirements and SP AusNet’s circumstances• Using only bandwidth required to meet AMI functionality• AER unable to establish that SP AusNet is using WiMAX
to provide communications services beyond AMI, therefore inside scope
Direct load control
• SP AusNet proposed a utility managed load control relay in all meters
• outside scope – AER requested net benefit assessment in accordance with Framework and Approach
• SP AusNet stated concern that minimum functionality specifications are not detailed enough to ensure its load control plans
• technology provided for in the minimum functionality specifications is cheaper than SP AusNet’s proposal, and provides more customer choice
• no net benefit was established for the proposal• AER established proposed costs are outside scope
Other areas under scope test
• Number of other items of proposed AMI technology above AMI minimum specifications
• most recommended by independent technical experts
• AER and Energeia considered these are reasonably required to enable the DNSPs to meet required AMI functionalities
Related party margins
• CitiPower, Powercor, Jemena and United Energy engaged related parties to manage AMI roll-outs
• not competitively tendered (non-contract costs)• no efficient cost review permitted in OIC• AER unable to establish costs were not prudent
under OIC tests• draft decision indicated AER will examine related
party margins as part of next reset, results may inform second budget period determination
Self insurance, equity raising costs
• Self insurance– United Energy proposed $0.4m over 2009-11– vendor insurance requirements built into AMI contracts– self insurance also provided in ESCV’s EDPR
• Equity raising costs– United Energy proposed $7.1m over 2009-11– effective double recovery of capital raising costs for 43% of
proposed capex– substantial departure from recent AER benchmark rates– AER considered United Energy likely to fund capital using less
expensive capital raising methods
• AER established costs unlikely to be incurred
Customer response trials
• CitiPower, Powercor and SP AusNet proposed a total of $4 million for customer response trials
• DPI advised that the trials are unlikely to go ahead in 2009 nor 2010
• AER rejected costs under the expenditure incurred test
AER draft decision - budgets
DNSPTotal proposed
budget ($m)AER draft decision ($m)
Difference
CitiPower 147.92 147.17 -0.5%
Jemena 146.72 146.72 0.0%
Powercor 330.01 328.25 -0.5%
SP AusNet 311.80 304.18 -2.4%
United Energy 234.56 227.09 -3.2%
OIC requirements
• OIC sets out calculation of building block revenue requirements and how these are translated into metering charges
• The DNSPs’ AMI charges for 2010 and 2011 recover– AMI opex and capex budgets for 2009-11; and– IMRO and AMI related costs incurred from 1 January
to 2006 to 31 December 2008
• Charges will be updated annually when budgeted costs are substituted with actual expenditures
Building block revenue requirementBuilding blocks include:• Return on capital (some WACC parameters
based on AER WACC review)• Depreciation• Operation & Maintenance costs• Corporate tax allowance• Costs incurred over 2006-08:
– IMRO costs– AMI net revenue or costs from 2006-08– DUoS tax liability– Efficiency carryover– Costs relating to AMI trials, IT systems integration, project
management, exchange and interest rate hedging expenditure
Charges adjustments
• Annual “true up” of charges to reflect actual costs incurred and revenue received
• Actual costs to be reported in regulatory accounts• Future charges also reflect budget revisions
– Actual expenditure can vary by 120% of initial budget; will drive future charges
• OIC permits DNSP’s to propose charges that result in under-recovery of revenues in early years, to minimise price shock– AER flagged this in F&A– Where DNSP proposed 2010 charges over recovered draft
determination revenues, the AER reduced 2010 charges to ensure NPV neutrality with draft determination revenue requirement
– Where DNSP proposed 2011 charges over recovered draft determination revenues, the AER reduced 2011 charges to ensure NPV neutrality with draft determination revenue requirement
Regulatory accounts
• Issues with all DNSPs charges applications• Reported actual costs (2006-08) that departed
from audited regulatory accounts, which the AER did not accept under the requirements of the revised Order
• AER did not accept allocations of costs by the DNSPs which affected the size of benefits under the efficiency carryover mechanism in their favour
WACC – Debt Risk Premium
• DNSPs jointly proposed measurement of debt risk premium from Tabcorp bond– Issued four months after OIC required averaging period– Maturity of 5 years, OIC requires 10 years– variable rate bond, OIC requires fixed coupon Commonwealth
Government bonds
• DNSPs proposed adjustments to reflect inconsistencies with OIC requirements
• DNSP proposal considered to be inconsistent with OIC• AER re-examined Bloomberg data, finding it appropriate• DNSPs’ proposed AMI WACC of 10.01 per cent vs draft
determination AMI WACC at 8.96 per cent
CitiPower issues
• AER did not accept regulatory accounts data for 2006-08• AER reduced CitiPower revenues by $4.4m for 2009-11• CitiPower chose to under recover revenue in 2010 –
requires compensating increase in 2011 charges– Consistent with revised OIC approach– AER did not smooth 2011 price, as not permitted to compel a
DNSP to under recover in any one year
• AER therefore reduced proposed 2011 charges (-12.3%)– to align with draft determination revenues in NPV terms
CitiPower metering charges proposed vs draft decision
Annual metering charge ($/NMI) 2010 2011
proposed Decision proposed Decision
Single phase 104.79 104.79 128.79 113.00
3 phase direct connected 136.98 136.98 168.36 147.72
3 phase current Transformer connected 172.99 172.99 212.62 186.55
CitiPower metering chargesindicative price change from 1 January
Meter type 2010 2011
Single phase non-off peak 236% 8%
Single phase off-peak 166% 8%
3 phase direct connected 76% 8%
3 phase CT connected 64% 8%
Note: Under AMI, peak and off-peak now become single phase.
Jemena issues• Jemena provided letters to corroborate data but these
were inconsistent with regulatory accounts, therefore not accepted
• 2008 costs data not consistent with regulatory accounts• Jemena cost allocation for efficiency carryover not
substantiated, large revenue impact- $22m reduction• Jemena proposed under recovery of $6.6m in 2010 and
2011– Consistent with revised OIC approach
• AER reduced Jemena’s proposed revenue requirements by $27.9m over 2009–11
• AER therefore reduced 2010 proposed charges (-49.6%) and 2011 charges (-4.5%)– to align with draft determination revenues in NPV terms
Jemena metering charges proposed vs draft decision
Annual metering charge ($/ NMI) 2010 2011
proposed Decision Proposed decision
Single phase single element 134.63 67.79 136.70 130.52
Single phase single element, with contactor
134.63 67.79 136.70 130.52
3 phase direct connected 165.46 83.31 167.99 160.39
3 phase current Transformer connected
183.95 92.62 186.77 178.32
Jemena metering chargesindicative price change from 1 January
Meter type 2010 2011
Single phase single element 151% 93%
Single phase single element with contactor 8% 93%
3 phase direct connected -6% 93%
3 phase CT connected 278% 93%
Single phase single element and single phase single element with contactor replace single phase non off peak and single phase off peak.
Powercor issues
• AER did not accept Powercor 2006, 2007 data, as not consistent with regulatory accounts
• Powercor requested changes to 2006 regulatory accounts via letters – not accepted by AER
• Powercor under recovered revenues by $18.5m in 2010. This delivered higher charges for 2011– Consistent with revised OIC approach
• AER reduced Powercor’s revenues by $8.5m over the 2009–11
• The AER therefore reduced proposed 2011 charges (-10.9%)– to align with draft determination revenues in NPV terms
Powercor metering chargesproposed vs draft decision
Annual metering charge ($/NMI)
2010 2011
proposed decision proposed decision
Single phase 96.67 96.67 125.17 111.48
3 phase direct connected 127.50 127.5 165.09 147.04
3 phase current Transformer connected
168.94 168.94 218.74 194.82
Powercor metering chargesindicative price change from 1 January
Meter type 2010 2011
Single phase non-off peak 177% 15%
Single phase off-peak 100% 15%
3 phase direct connected 40% 15%
3 phase CT connected 31% 15%
Note: Under AMI, peak and off-peak now become single phase.
SP AusNet issues
• Minor issues with provisions• Adjustment to efficiency carryover amount for customer service
costs• SP AusNet chose to under recover revenues by $7.1m in
2010. Results in higher 2011 charges– Consistent with revised OIC approach
• AER reduced SP AusNet’s revenues by $11.1m over the 2009–11
• AER reduced proposed charges in 2010 (-1.4%) and 2011 (-14.5%) to align with draft determination revenues in NPV terms
SP AusNet metering chargesproposed vs draft decision
Annual metering charge ($/NMI) 2010 2011
proposed decision proposed decision
Single phase, single element with contactor
76.96 75.88 110.18 94.23
Single phase, 2 element with contactor
87.92 86.69 125.87 107.66
Multi-phase, 1 contactor (1 load control)
102.12 100.69 146.19 125.04
Multi-phase, 2 contactors (2 load controls)
113.29 111.70 162.18 138.71
Multi-phase Current Transformer connected
145.87 143.82 208.82 178.60
SP AusNet metering chargesindicative price change from 1 January
Meter type 2010 2011
Single phase single element 1 contactor (1 load control)
110% 24%
Single phase, 2 element 2 contactors (2 load controls)
101% 24%
Multi phase, 1 contactor (1 load control) 0% 24%
Multi phase, 2 contactor (2 load controls) 0% 24%
Multi phase CT connected 40% 24%
Note: single phase 1 element and 2 element replace single phase non off peak
and single phase off peak.
United Energy issues
• Minor adjustment to efficiency carryover amount – for customer service costs
• UED proposed revenue neutrality for both 2010 and 2011 charges– Consistent with revised OIC approach
• AER reduced UED revenues by $12.7m over the 2009–11
• AER therefore reduced 2010 charges to align with draft determination revenues in NPV terms
• AER reduced proposed charges in 2010 (-18.8%) and 2011 (-3.2%) to align with draft determination revenues in NPV terms
United Energy metering chargesproposed vs draft decision
Annual metering charge ($/ NMI) 2010 2011
proposed decision proposed decision
Single phase single element 88.44 71.80 95.12 92.12
Single phase single element, with contactor
90.29 73.30 97.09 94.02
3 phase direct connected 99.78 81.01 107.28 103.89
3 phase current Transformer connected
106.42 86.40 114.43 110.82
United Energy metering chargesindicative price change 1 January
Meter type 2010 2011
Single phase single element 222% 28%
Single phase single element with contactor
180% 28%
3 phase direct connected 120% 28%
3 phase CT connected 86% 28%
Note: single phase single element, and single phase single element withcontactor replace single phase non off peak and single phase off peak.
Price impacts summary
• Across all DNSPs, 2010 charges represent an average increase of $53 on 2009 metering charges[1], with a further $25 increase in 2011
• [1] Based on single phase single element non off-peak meter, read quarterly in 2009, approved by the ESCV
Process from here• DNSPs must submit amended Submitted
budgets for AER approval by 28 August (AER will publish)
• Stakeholders’ submissions due 11 September
• AER final determination on budgets and charges due 31 October 2009
• New metering charges apply from 1 January 2010