· web vieworder placed on bhel for stg and on bgr for sg. levelling and grading work is in...
TRANSCRIPT
GOVERNMENT OF INDIA
MINISTRY OF POWER
LOK SABHA
UNSTARRED QUESTION NO 1627
ANSWERED ON 05.03.2015
COMPLETION OF POWER PROJECTS
1627 . S.R. Shri Vijay Kumar
Will the Minister of POWER be pleased to state:-
(a) the details of power projects undertaken in the country during Eleventh and Twelfth Plan with their capacity including current their status alongwith the steps taken to complete the projects under construction, State/UT/project-wise;
(b) the State/UT-wise details of projects whose capacity is proposed to be increased along with the action taken by the Government in this regard; and
(c) whether the Government intends to undertake more power projects in near future and if so, the details thereof?
ANSWER
THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL AND NEW & RENEWABLE ENERGY
( SHRI PIYUSH GOYAL )
(a) : State/Union Territory (UT)/Project-wise details of power projects taken up during the Eleventh and Twelfth Plan are placed at Annex-IA for thermal projects and Annex-IB for hydro projects. To ensure timely completion of these projects, regular monitoring is done by the Central Electricity Authority (CEA)
through frequent site visit, and interaction with developers and equipment suppliers. A Power Project Monitoring Panel (PPMP) has also been set up to monitor the hydro and thermal generation projects along with the associated transmission system. Regular reviews are taken at various levels, including joint review by Secretary (Power) and Secretary (Heavy Industry) to identify the problem areas and facilitate expeditious resolution of outstanding issues.
(b) : Extension units aggregating 28,071 Mega Watt (MW) are being installed to increase the station capacity of 30 thermal power stations. The State/UT /Project-wise details are at Annex-II.
(c) : To take up power projects in the near future, CEA has prioritized 166 thermal projects aggregating 1,91,621.4 MW for Coal linkage. CEA has also accorded concurrence to 41 hydro power projects aggregating 26,332 MW.
ANNEXURE
ANNEX-IA
ANNEX REFERRED TO IN REPLY TO PART (a) OF UNSTARRED QUESTION NO.1627 TO BE ANSWERED IN THE LOK SABHA ON 05.03.2015.
State/UT/Project-wise details of Thermal Power Projects taken of during the Eleventh and Twelfth Plan
State Project Name
Order/ Zero Date
Implementing Agency
Unit No
Capacity (MW)
Actual(A)/ Anticipated Date of Commission-ing
Brief Status
CENTRAL SECTOR
Assam
Bongaigaon TPP
02/2008
NTPC U-1
250 06/2015
HT done in 01/11 & BLU done on 29/11/14. EDTA completed on 29/12/14. SBO started
in 01.03.15. TG erection started in 3/11/14& boxed up in 01/15. Oil flushing started on 16/01/15. Civil contract was terminated due to very slow progress of work. Now for the balance civil and structural works NTPC has placed order on NBCC on 29/09/14.
U-2
250 16-17 Boiler Drum lifted in 10/10. HT done in 04/12.
U-3
250 16-17 Boiler Drum lifted on 25/2/13. HT done on 21/03/14.
Bihar Barh STPP-II
11/2008
NTPC U-4
660 30/11/13(A)
Commissioned
U-5
660 03/2015
Boiler erection started in 2/10 & HT done in 11/13. BLU completed in 6/14 & SBO in 01/15 . TG erection started in 12/11 & boxed up in 04/14. TG put on barring gear. Synchronized on 01.03.15.
Bihar New Nabi Nagar TPP
01/2013
NTPC U-1
660 06/2017
Boiler erection started in 06/14.
U-2
660 09/2017
Boiler erection started on 29/11/14.
U-3
660 01/2018
Boiler erection is to start shortly.
Bihar Muzaffarpur TPP Exp
04/2010
NTPC U-3
195 03/2015
HT done on 25/02/13 & BLU completed on 08/11/14. SBO completed. TG erection started on 29/01/13 & boxed up in 09/14. TG oil
flushing in progress. U-
4 195 12/201
5 HT done on 04/08/13. TG erection started in 09/13.
Bihar Nabi Nagar TPP
01/2008
NTPC U-1
250 12/2015
Drum Lifted in 10/12 & HT done on 11/04/14.TG erection started in 01/14.
U-2
250 12/2016
Drum lifted on 03/13.
U-3
250 06/2016
Drum lifted on 10/06/13.
U-4
250 06/2017
Boiler erection started on 7/12/12. Drum lifted on 16/9/13.
Chhattisgarh
Lara STPP 12/2012
NTPC U-1
800 11/2016
Boiler erection started in 12/13.
U-2
800 05/2017
Boiler erection started in 04/14.
Haryana
Indira Gandhi TPP
07/2007
APCPL U-1
500 31/10/10(A)
Commissioned
U-2
500 05/11/11(A)
Commissioned
U-3
500 07/11/12(A)
Commissioned
Jharkhand
BokaroTPS "A"Exp.
06/2008
DVC U-1
500 12/2015
HT done on 10/12/13. BLU done on 28/9/14. SBO started on 30.02.15. TG erection started in 10/12 & boxed up in 30/06/14. Oil flushing started on 6/9/14 and is in progress.
Jharkhand
North Karanpura TPP
02/2014
NTPC U-1
660 02/2018
Order for EPC contract placed on BHEL (except external CHP, Make up water system and Ash dyke) in 02/14.
U-2
660 08/2018
U-3
660 02/2019
Jharkhand
Koderma TPP
06/2007
DVC U-1
500 20/07/11(A)
Commissioned
U-2
500 15/02/13(A)
Commissioned
Karnataka
Kudgi STPP Ph-I
02/2012
NTPC U-1
800 05/2016
Boiler erection started on 04.05.13 & HT done on 01/15. TG erection started in 06/14.
U-2
800 09/2016
Boiler erection started in 20/08/13.
U-3
800 05/2017
Boiler erection started in 09/13.
Maharashtra
Mouda TPP
09/2008
NTPC U-1
500 19/04/12(A)
Commissioned
U-2
500 29/03/13(A)
Commissioned
Maharashtra
Solapur STPP
04/2012
NTPC U-1
660 05/2017
Boiler erection started on 7/5/13. TG erection started in7/14.
U-2
660 11/2017
Boiler erection started on 29/09/13. HT expected in 01/16.
MP Vindhyachal TPP-IV
02/2009
NTPC U-11
500 14/06/12(A)
Commissioned
U-12
500 22/03/13(A)
Commissioned
MP Gadarwara STPP
03/2013
NTPC U-1
800 06/2017
Boiler erection started in 06/14.
U-2
800 12/2017
Boiler erection started on 30/11/14.
MP Vindhyachal TPP-V
05/2012
NTPC U-13
500 10/2015
Boiler erection started in 06/13. Drum lifted in 11/13 & HT done in 08/14. TG erection started in 04/14 & boxed up in 01/15.
Orissa Darlipali STPP
02/2014
NTPC U-1
800 02/2018
U-2
800 06/2018
TN Tuticorin JV
01/2009
NLC U-1
500 03/2015
Drum lifted on 29/09/11& HT done on 28/09/12. BLU done
on 19/03/14 & SBO completed on 19/06/14. TG erection started on 29/09/12 & boxed up on 23/10/13. Oil flushing completed on 06/06/14. Valve floating in 12/16. SVF completed. The unit was synchronized on 18.02.15.
U-2
500 06/2015
Drum lifted on 22/09/11 &. HT done on 09/11/12. BLU completed on 23/09/14. SBO completed on 28/02/15. TG erection started on 29/04/13 & boxed up on 11/04/14. Oil flushing completed on 05/12/14.
TN Vallur TPP Ph I
08/2007
NTECL U-1
500 28/03/12(A)
Commissioned
U-2
500 28/02/13(A)
Commissioned
TN Vallur TPP-II
07/2009
NTECL U-3
500 28/02/14(A)
Commissioned
Tripura Monarchak CCPP
07/2010
NEEPCO GT 61.3
05/2015
Erection of all major equipments completed. Gas turbine is ready for Synchronization in open cycle. GTG final cranking done on 24.02.15. Erection of STG, HRSG, BFP DM plant etc. are in progress. Main chimney is ready. Gas supply made available at site on 04/02/15 by ONGC and commissioning activities are in
progress. ST 39.
7 07/201
5
Tripura Tripura Gas
06/2008
OTPC Module-1
363.3
03/01/13(A)
Commissioned
Module-2
363.3
16/11/14(A)
Commissioned
Tripura Agartala CCPP
09/2012
NEEPCO ST-1
25.5
06/2015
Erection work in HRSGs, STGs, Chimneys etc. are in progress. ST-2 synchronized on 10/2/15 and resynchronised on 17/2/15 & achieved a load of 10.3 MW. HRSG-4 pipe leakage repair work is in progress.
ST-2
25.5
03/2015
UP Rihand STPS- III
01/2009
NTPC U-5
500 25/05/12(A)
Commissioned
U-6
500 07/10/13(A)
Commissioned
UP Meja STPP
04/2012
JV of NTPC & UPRVUN
L
U-1
660 05/2017
Boiler erection started in 06/13 . TG erection started in 09/14.
U-2
660 11/2017
Boiler erection started on 30/06/14.
UP Tanda TPS -II
09/2014
NTPC U-1
660 05/2018
Order for Boiler placed on L&T - Mitshubhishi and TG on Alstom- Bharat Forge.
U-2
660 11/2018
UP Unchahar TPS St-IV
08/2013
NTPC U-6
500 11/2017
WB Durgapur Steel TPS
07/2007
DVC U-1
500 29/07/11(A)
Commissioned
U-2
500 23/03/12(A)
Commissioned
WB Raghunathpur TPP, Ph-I
12/2007
DVC U-1
600 24/08/14(A)
Commissioned
U-2
600 08/2015
HT done on 25/05/12. TG erection started in 09/13 & boxed up on 20/09/14. Oil flushing is in progress. NDCT-1 Interconnection work completed mechanical work is in progress. Work on water corridor and Ash pond is very slow due to frequent disruption by locals.
WB Raghunathpur TPP Ph-II
09/2012
DVC U-1
660 10/2018
Order placed on BHEL for STG and on BGR for SG. Boiler foundation work is in progress but progress is slow due to fund problem in DVC.
U-2
660 03/2019
Order placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC.
STATE SECTOR AP Damoda
ram Sanjeevaiah TPS
06/2008
APPDL U-1
800 28/08/14(A)
Commissioned
U-2
800 03/2015
Boiler erection started in 04/11. HT done & BLU completed in 06/14. Boiler EDTA completed and SBO completed on 20/11/14. TG erection started in 07/12 and boxed up in 11/13.
Synchronized on 16/12/2014. Coal firing done on 11/02/15. 255 MW load achieved.
AP Rayalseema St-IV U-6
10/2010
APGENCO
U-6
600 12/2016
Boiler erection started on 04/02/13. Drum lifted on 30/11/13. HT completed on 30/11/14. TG raft casting completed. BOPs civil works are lagging behind schedule.
AP Rayalseema TPP St-III
06/2007
APGENCO
U-5
210 31/12/10(A)
Commissioned
Assam Namrup CCGT
02/2009
APGCL GT 70 03/2016
HRSG work started in 01/12. GT placed on foundation. Order on NBPPL terminated. Order for balance civil work placed on 13/03/14 and work started on 05/5/14. BHEL again engaged NBPPL for balance work of EPC package on 22/11/14.
ST 30 06/2016
Bihar Barauni TPS Extn
03/2011
BSEB U-1
250 11/2015
Boiler drum lifted in 06/13 & HT done on 21/08/14. BLU expected in 04/15. TG erection is in progress.
U-2
250 02/2016
Boiler drum lifted in 09/13 and HT done on 21/09/14.
Chhattisgarh
Korba West St-III.
04/2008
CSPGCL U-5
500 22/03/13(A)
Commissioned
Chhattisgarh
Marwa TPP
04/2008
CSPGCL U-1
500 30/03/14(A)
Commissioned
U- 500 03/201 HT done on 06.09.12.
2 5 BLU completed on 08.05.14. HBO completed 03.10.14.TG box up completed. TG put on barring gear on 16.01.15.
Delhi Pragati CCGT - III
05/2008
PPCL GT-1
250 24/10/10(A)
Commissioned
GT2
250 16/02/11(A)
Commissioned
GT-3
250 27/06/12(A)
Commissioned
GT-4
250 07/05/13(A)
Commissioned
ST-1
250 29/02/12(A)
Commissioned
ST-2
250 26/02/14(A)
Commissioned
Gujarat Bhavnagar CFBC TPP
02/2010
Bhavnagar
Energy
U-1
250 06/2015
Boiler drum lifted in 06/12. HT done on 01/06/13 & BLU completed on 28.02.15.TG oil flushing is in progress. ST charged on 25/1/15. TG erection started in 06/13 & boxed up on 27/06/14. Oil flushing is in progress.
U-2
250 09/2015
Boiler drum lifted on 12/10/12. HT done on 21/6/14. TG erection started in 08/13 & boxed up on 26/12/14. TG oil flushing in progress.
Gujarat
Dhuvaran CCPP-III
03/2011
GSECL Block-1
376.1
21/05/14(A)
Commissioned
Gujarat
Hazira CCPP Extn.
12/2007
GSECL GT+ST
351
18/02/12(A)
Commissioned
Gujarat
Pipavav CCPP
03/2008
GSECL Block-1
351
05/02/14(A)
Commissioned
Block-2
351
27/03/13(A)
Commissioned
Gujarat
Sikka TPS Extn.
05/2007
GSECL U-3 250
03/2015
Boiler erection started on 24/10/11. Drum lifted on 29/03/12. HT completed in 03/13. BLU done on 22/03/14. SBO completed on 29/12/14. TG erection started on 15/01/13 and boxed up on 06/6/14. Synchronized on oil on 09/2/15.
U-4 250
07/2015
Boiler erection started on 09/01/12 and drum lifted on 23/05/12. HT completed on 30/06/13 & BLU done on 18/10/14. TG erection started in 01/13 & boxed up on 14/03/14. Oil flushing is in progress.
Gujarat
Ukai TPP Extn.
09/2007
GSECL U-6 500
05/03/13(A)
Commissioned
Gujarat
Utran CCPP Extn
04/2007
GSECL GT 240
08/08/09(A)
Commissioned
ST 134
10/10/09(A)
Commissioned
Gujarat
Wankbori TPS Extn
10/2014
GSECL U-8 800
10/2018
EPC contract awarded to BHEL on 21.10.14. Topographical and soil investigation of BTG area completed.
Karnataka
Bellary TPP St-III
09/2010
KPCL U-3 700
09/2015
Boiler erection started on 26/11/12 and HT completed on 30/11/14. Non drainable HT done on 02/02/15 . Condenser
and TG erection started on 12/11/13 .
Karnataka
Yermarus TPP
04/2010
KPCL U-1 800
11/2015
Boiler erection started on 29/10/12. HT done on 10/09/14.TG erection started on 14.01.14.
U-2 800
03/2016
Boiler erection started in 12/12. TG erection started on 31/05/14.
Maharashtra
Chandrapur TPS
07/2008
MSPGCL
U-8 500
03/2015
Boiler erection started in 03/11. HT done in 06/12 & BLU done on 30/3/14. SBO completed on 17/10/14 & normalized in 11/14. TG erection started in 03/12 & boxed up on 30/06/14. TG put on barring gear on 15/12/14. Synchronization done with oil on 11/01/15.
U-9 500
08/2015
Boiler drum lifted in 09/11. HT completed on 29/10/12 . TG erection started on 14/11/13 .
Maharashtra
Koradi TPS Expn.
09/2009
MSPGCL
U-8 660
03/2015
Boiler erection started in 03/11 & HT completed in 06/13. BLU completed in 09/14. SBO completed on 11/02/15. TG erection started in 04/12 & boxed up in 06/13. TG put on Barring Gear on 31/03/14. Synchronization on 25.02.15.
U-9 660
07/2015
HT completed on 04/01/14. TG erection started in 11/12 & boxed up in 05/14.
U-10 660
02/2016
Boiler erection started in 02/12 and HT done in 07/14. TG erection started in 06/13.
Maharashtra
Parli TPS Expn.
01/2009
MSPGCL
U-8 250
08/2015
Drum lifted in 04/11. HT completed in 12/12. TG erection started in 04/12.
MP Malwa TPP (Shree Singa ji TPP)
12/2008
MPGENCO
U-1 600
18/11/13(A)
Commissioned
MP Malwa TPP (Shree Singa ji TPP)
12/2008
MPGENCO
U-2 600
15/10/14(A)
Commissioned
MP Satpura TPS Extn
03/2008
MPPGCL
U-10 250
22/03/13(A)
Commissioned
U-11 250
25/12/13(A)
Commissioned
MP Shree Singaji TPP Phase-II
09/2014
MPGENCO
U-3 660
07/2018
Order placed on M/s. L&T on 04/09/14.
U-4 660
11/2018
Rajasthan
Chhabra TPS Extn
08/2008
RRVUNL
U-3 250
14/09/13(A)
Commissioned
U-4 250
30/06/14(A)
Commissioned
Rajasthan
Kalisindh TPP
07/2008
RRVUNL
U-1 600
02/05/14(A)
Commissioned
U-2 600
03/2015
HT done on 15/12/11. BLU done & SBO completed on 14/11/14. TG erection started on 25/08/11 & boxed up. Oil flushing completed & TG put on barring gear on 29/10/14. Synchronised on 27.02.15.
Rajasthan
Ramgarh CCPP Extn. -III
07/2009
RRVUNL
GT 110
20/03/13(A)
Commissioned
ST 50 01/05/14(A)
Commissioned
Rajasthan
Chhabra TPP Extn.
03/2013
RRVUNL
U-5 660
04/2017
Boiler erection started on 17/02/14. TG raft casting completed and Column casting is in progress.
U-6 660
08/2017
Environment clearance obtained.
Rajasthan
Suratgarh TPS
05/2013
RRVUNL
U-7 660
04/2017
Boiler erection started on 26/03/14 & further work under progress.
U-8 660
07/2017
Boiler erection started in 06/14.
Telangana
Kakatiya TPS Extn
10/2008
T GENCO
U-1 600
02/2016
Boiler erection started on 05/05/11. Drum lifted on 07/04/12. HT done on 24/06/13. TG erection started in 05/13.
Telangana
Singareni TPP
11/2011
Singareni
Collieries Co.
Ltd
U-1 600
11/2015
Boiler drum lifted on 12/09/13. HT done on 27/08/14. TG erection started on 16/08/14.
U-2 600
03/2016
Boiler drum lifted on 14/12/13. HT done on 03/11/14. TG erection started.
TN Mettur TPP Ext
06/2008
TANGEDCO
U-1 600
11/10/12(A)
Commissioned
TN North Chennai Extn, U-2
08/2008
TANGEDCO
U-2 600
09/03/13(A)
Commissioned
TN North Chennai TPS Extn, U-1
02/2008
TANGEDCO
U-1 600
13/09/13(A)
Commissioned
Tripura Baramura GT Extn.
03/2008
TSECL U-5 21 03/08/10(A)
Commissioned
Tripura Rokhia 08/2 Govt.of GT-9 21 31/08/1 Commissioned
CCPP 010 Ttipura 3(A) UP Anpara-D
TPS 10/2007
UPRVUNL
U- 6 500
03/2015
Boiler erection started on 02/08/10. HT done on 09/04/13. BLU done in 12/14. TG erection started on 15/03/13 and boxed up on 20/02/14. Oil flushing completion expected in 03/15.
U-7 500
08/2015
Boiler erection started on 02/11/10. HT done on 03/07/13. TG erection started on 31/07/13 and boxed up in 07/14.
WB Durgapur TPS Extn U-8
07/2010
DPL U-8 250
31/03/14(A)
Commissioned
WB Sagardighi TPS-II
02/2011
WBPDCL
U-3 500
06/2015
Boiler erection started in 04/03/12. Drum lifted in 13/09/12. HT done on 31/08/13, BLU done on 30/01/15. SBO started on 01.03.15. TG erection started on 15/07/13 & boxed up in 07/14. Oil Flushing started in 01/15 and is in progress . Work in AHP & CHP is slow.
U-4 500
09/2015
Boiler erection work is in progress. Drum lifted on 25/01/13. HT done on 21/03/14. TG erection started on 10/10/13. Work in AHP & CHP is slow.
PRIVATE SECTOR
AP Bhavanpadu TPP
09/2009
M/s East
Coast Energy
U-1 660
03/2017
Work was suspended due to MOEF order & due to site conditions. Work resumed at site
Ltd. from 04/12. Boiler erection started in 03/14. HT expected by 12/15. TG raft casted and column casting is in progress. Switchyard and CHP area are in progress. ESP erection started.
U-2 660
10/2017
Boiler foundation work completed.Piling work in TG area is also completed.
AP Lanco Kondapalli Ph-II (GT)
11/2007
Lanco Kondap
alli
GT 233
05/12/09(A)
Commissioned
AP Lanco Kondapalli Ph-II (ST)
11/2007
Lanco Kondap
alli
ST 133
19/07/10(A)
Commissioned
AP Lanco Kondapalli CPP Expn. St.III
01/2010
Kondapalli
Power Pvt. Ltd.
Module-1
371
– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.
Module-2
371
– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.
AP NCC TPP 02/2012
NCC Power Projects Ltd
U-1 660
04/2016
Boiler erection started on 10/05/13. TG erection started in 07/14.
U-2 660
08/2016
Boiler erection started in 11/13. TG erection started in 12/14.
AP Painampuram TPP
09/2010
Thermal Power Tech
Corporation
U-1 660
07/02/15(A)
Commissioned
Ltd U-2 66
0 06/201
5 Boiler erection started on 24/05/12. HT (Non-drainable) completed in 07/14. . TG erection started in 11/13.
AP Panduranga CCPP
05/2010
Panduranga Power
Ltd
Module-1
110.3
– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.
AP RVK Gas Engine
06/2010
RVK (Rajahmundry) Pvt.Ltd
GE: 5-8
38 – Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.
GE:1-4
38 – Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.
AP RVKCCPP 07/2010
RVK (Rajahmundry) PVT.Ltd
Module-1
120
– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.
Module-2
120
– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.
Module-3
120
– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.
AP Samalkot CCPP-II
07/2010
Reliance
Power
Module-1
400
– Work held up due to non availability of Gas. Commissioning
schedule would be assessed after restart of work.
Module-2
400
– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.
Module-3
400
– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.
Module-4
400
– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.
Module-5
400
– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.
Module-6
400
– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.
AP Simhapuri Energy Pvt Ltd Ph-II
05/2010
Madhucon
Projects Ltd.
U-3 150
21/02/14(A)
Commissioned
AP Simhapuri Energy Pvt Ltd Ph-II
05/2010
Madhucon
Projects Ltd.
U-4 150
03/2015
Boiler erection started in 05/11. HT completed on 02/03/12. BLU completed in 10/14. SBO completed in 12/14.TG erection started on 01/02/12
and boxed up on 08/13. TG put on barring gear. Synchronized on 30/12/14. Coal firing done on 16/02/15 and a load of 105 MW has been achieved.
AP Simhapuri Energy Pvt.Ltd Ph-I
01/2009
Madhucon
Projects Ltd
U-1 150
24/03/12(A)
Commissioned
U-2 150
02/07/12(A)
Commissioned
AP Thamminapatnam TPP-I
08/2009
Meenakshi
Energy Pvt. Ltd
U-1 150
09/09/12(A)
Commissioned
U-2 150
17/04/13(A)
Commissioned
AP Thamminapatnam TPP-II
12/2009
Meenaksha
Energy Ltd.
U-3 350
08/2016
Boiler erection started on 16/11/11. Boiler drum lifted on 16/05/14. HT expected in 04/15. TG civil works started in 07/11.
U-4 350
11/2016
Boiler erection started on 22/09/14. TG civil works are in progress.
AP Vemagiri CCPP-II
09/2009
GMR Rajahmundry Energy
Ltd.
Block-I
384
– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.
Block-II
384
– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.
AP Vizag TPP
06/2010
Hinduja National Power
U-1 525
09/2015
Boiler drum lifted in 01/12. HT done on 28/12/12. BLU done in
Corp. Ltd
03/14. EDTA completed & SBO works affected due to cyclone. SBO re-start expected in 03/15. TG erection started on 25/07/12 & boxed up in 09/13. TG on barring gear since 08/14. Works has been affected due to hud-hud cyclone.
U-2 525
12/2015
Boiler erection started in 09/11. HT done on 28/03/13. BLU done in 07/14. Condenser erection started on 23/11/12 and that of TG started on 04/03/13 .
Bihar Jas Infra TPP Ph-I
03/2011
JICPL U-1 660
– Civil works for boiler foundation completed and boiler erection started. TG raft casted. * No work is in progress. Commissioning schedule would be assessed after the restart of work.
U-2 660
– Boiler foundation work was started. * No work is in progress. Commissioning schedule would be assessed after the restart of work.
U-3 660
– Civil works yet to start. * Commissioning schedule would be assessed after the restart of work.
U-4 660
– Civil works yet to start. * Commissioning schedule would be assessed after the
restart of work. Chhattisgarh
Akaltara (Nariyara) TPP
04/2009
KSK Mahan
di Power Company Ltd
U-1 (3rd)
600
13/08/13(A)
Commissioned
U-2 (4th)
600
22/08/14(A)
Commissioned
U-3 (2nd
)
600
12/2015
Boiler erection started in 04/11. Boiler drum lifted on 29/04/12. Condenser & TG erection started in 02/15.
U-4 (5th)
600
11/2016
Boiler erection started on 08/12/11.TG deck casted.
U-5(1s
t)
600
03/2017
Boiler erection started on 06/02/12.
Chhattisgarh
Akaltara (Nariyara) TPP
04/2009
KSK Mahan
di Power Company Ltd
U-6 600
09/2017
Chhattisgarh
Avantha Bhandar TPP, U-1
04/2009
Korba West Power
Co. Ltd.
U-1 600
31/03/14(A)
Commissioned
Chhattisgarh
Badadarha TPP
06/2010
D.B. Power
Ltd
U-1 600
23/02/14(A)
Commissioned
U-2 600
08/2015
Synchronized on 30/03/14.
Chhattisgarh
Balco TPP
08/2007
Bharat Aluminium Co.
Ltd
U-1 300
04/2015
Unit Synchronized on 22/05/12. Concerned to operate obtained.
U-2 300
06/2015
Unit Synchronized on 06/09/11. Concerned to operate obtained.
Chhatti Bandakh 06/2 M/s U-1 30 03/201 Boiler drum lifted on
sgarh ar TPP 011 Maurti Clean Coal & Power
Ltd
0 5 06/01/13. HT completed on 30/08/13 & BLU done on 22/ 09/14. SBO completed & Chemical cleaning completed on 17/8/14. TG boxed up on 22/02/14. Oil flushing completed.
Chhattisgarh
Binjkote TPP
03/2011
M/s SKS Power
Generation
(Chhattisgarh)
Ltd.
U-1 300
12/2015
Boiler Drum lifted in 05/13. HT completed on 20/06/14. TG erection started in 05/14.
U-2 300
03/2016
Boiler Drum lifted in 05/13. HT done on 03/11/14. TG erection started in 09/14.
U-3 300
– *Commissioning dates would be assessed after start of work at site.
U-4 300
– *Commissioning dates would be assessed after start of work at site.
Chhattisgarh
Chakabura TPP
09/2011
ACB India
U-1 30 28/03/14(A)
Commissioned
Chhattisgarh
Deveri TPP (Visa TPP) Raigarh
06/2010
Visa Power
Ltd
U-1 600
– Boiler erection started on 30.09.11. * Work held up due to financial crunch.
Chhattisgarh
Kasaipalli TPP
11/2008
ACB India Ltd.
U-1 135
13/12/11(A)
Commissioned
U-2 135
21/06/12(A)
Commissioned
Chhattisgarh
Katghora TPP
10/2007
Vandana
Energy & Steel
Ltd
U-1 35 14/02/12(A)
Commissioned
Chhatti Lanco 11/2 LAP U-3 66 – Boiler erection started
sgarh Amarkantak TPS-II
009 Pvt. Ltd.
0 in 09/10. TG erection started on 5/12/11. Work held up due to financial constraint. * Commissioning schedule would be assessed after restart of work.
U-4 660
– Boiler erection started in 12/10. Work held up due to financial constraint. * Commissioning schedule would be assessed after restart of work.
Chhattisgarh
Nawapara TPP (TRN Energy TPP)
01/2011
M/s TRN
Energy Pvt. Ltd.
U-1 300
01/2016
Boiler erection started in 01/10/12 & drum lifted on 28/02/13. HT completed on 28/3/14. Chemical cleaning is in progress. TG erection started in 05/14.
U-2 300
04/2016
Boiler erection started in 05/13 & drum lifted on 21/09/13.
Chhattisgarh
Raikheda TPP
01/2010
GMR U-1 685
27/02/15(A)
Commissioned
U-2 685
07/2015
Boiler erection started on 03/04/12. HT done in 30/07/14. TG erection started on 24/03/13 & boxed up on 31/10/14. Oil flushing completed on 10/12/2014.
Chhattisgarh
Ratija TPP
07/2009
Spectrum Coal
& Power
Ltd
U-1 50 04/02/13(A)
Commissioned
Chhattisgarh
Salora TPP
09/2009
M/s Vandan
a
U-1 135
10/04/14(A)
Commissioned
Vidyut U-2 13
5 05/201
5 Boiler drum lifted in 04/11. HT done in 10/12 & BLU completed in 01/15. TG erection started in 11/11& boxed up.
Chhattisgarh
Singhitarai TPP
12/2009
Athena Chhattisgarh Power Ltd.
U-1 600
03/2016
Boiler erection started in 07/12. Drum lifted on 07/04/13. HT completed on 28.02.15. TG erection started in 07/13.
U-2 600
08/2016
Boiler erection started in 10/12. Drum lifted on 30/10/13. TG erection started in 11/13.
Chhattisgarh
Swastic TPP
03/2010
M/s ACB
U-1 25 03/2015
SBO started on 01/02/15. TG boxed up on 10/03/13.
Chhattisgarh
Tamnar TPP (Raigarh)
12/2008
O.P.Jindal
U-1 600
10/03/14(A)
Commissioned
U-2 600
30/03/14(A)
Commissioned
U-3 600
07/01/15(A)
Commissioned
U-4 600
06/2015
Boiler erection started. Drum lifted on 18/10/13. SBO start expected in 03/15. Consent to operate has been received. TG on barring gear by 15.03.15.
Chhattisgarh
Uchpinda TPP
07/2007
RKM Powergen Pvt.
Ltd
U-1 360
04/2015
Drum lifted on 24/04/12. HT done in 09/13. BLU done on 08/11/14. SBO completed in 01/15. TG erection started in 09/13 & boxed up in 07/14. TG oil flushing completed in 07/14 TG
put on BG in 1/15 & synchronized on 28.02.15.
U-2 360
07/2015
Drum lifted on 07/05/12. HT done in 12/13. BLU completed on 05/02/15. TG erection started in 03/14 & boxed up in 01/15.
U-3 360
12/2015
Boiler erection started on 12/01/12. Drum lifted on 18/08/12. HT done in 01/14. TG erection started in 10/14. oil flushing completion expected in 06/15.
U-4 360
04/2016
Boiler erection started on 30/04/12. Drum lifted on 30/12/12. HT done on 20/01/15. TG erection started in 11/14.
Delhi Rithala CCPP
05/2008
NDPL GT-1 35.75
09/12/10(A)
Commissioned
GT-2 35.75
04/10/10(A)
Commissioned
ST 36.5
04/09/11(A)
Commissioned
Gujarat
DGEN Mega CCPP
07/2010
Torrent Energy
Ltd
Module-1
400
12/01/14(A)
Commissioned
Module-2
400
23/04/14(A)
Commissioned
Module-3
400
09/03/14(A)
Commissioned
Gujarat
Mundra TPP Ph-II
09/2007
Adani Power
Ltd
U-1 660
26/12/10(A)
Commissioned
Gujarat
Mundra TPP Ph-II
09/2007
Adani Power
Ltd
U-2 660
20/07/11(A)
Commissioned
Gujarat
Mundra TPP Ph-III
01/2008
Adani Power
U-1 660
07/11/11(A)
Commissioned
Ltd U-2 66
0 03/03/1
2(A) Commissioned
U-3 660
09/03/12(A)
Commissioned
Gujarat
Mundra UMTPP
08/2007
Tata Power
Co.
U-1 800
25/02/12(A)
Commissioned
U-2 800
25/07/12(A)
Commissioned
U-3 800
16/10/12(A)
Commissioned
U-4 800
16/01/13(A)
Commissioned
U-5 800
18/03/13(A)
Commissioned
Gujarat
Salaya TPP
09/2009
Essar Power
Gujarat Ltd.
U-1 600
22/02/12(A)
Commissioned
U-2 600
13/06/12(A)
Commissioned
Gujarat
Unosugen Mega CCPP
07/2010
Torrent Energy
Ltd
Module-1
382.5
20/01/13(A)
Commissioned
Haryana
Jajjar TPP (Mahatama Gandhi TPP)
03/2009
CLP Power India
Pvt. Ltd
U-1 660
12/01/12(A)
Commissioned
U-2 660
11/04/12(A)
Commissioned
Jharkhand
Mahadev Prasad TPP Ph-I
05/2009
Adhunik Power Co.Ltd
U-1 270
19/11/12(A)
Commissioned
U-2 270
29/03/13(A)
Commissioned
Jharkhand
Maithon RB TPP
10/2007
DVC U-1 525
30/06/11(A)
Commissioned
U-2 525
23/03/12(A)
Commissioned
Jharkhand
Mata shri Usha TPP-Ph-I
12/2009
M/s Corpor
ate Power
U-1 270
– HT completed. TG boxed up in 10/12. Work held up due to payment issue with
Ltd BHEL. U-2 27
0 – Drum lifted & Boiler
erection in progress. Work held up due to payment issue with BHEL.
Jharkhand
Mata Shri Usha TPP-Ph-II
03/2011
Corporate
Power Ltd
U-3 270
– Boiler drum lifted in 11/11. TG erection started in 10/12. Work held up due to payment issue with BHEL.
U-4 270
– Boiler drum lifted in 04/12. Work held up due to payment issue with BHEL.
Jharkhand
Tori TPP 08/2008
Essar Power
U-1 600
04/2017
Boiler erection started in 04/12.
U-2 600
10/2017
Boiler erection started in 06/12.
Maharashtra
Amravati TPP Ph-I
11/2009
Ratan India Power
Pvt Ltd.
U-1 270
25/03/13(A)
Commissioned
U-2 270
17/02/14(A)
Commissioned
U-3 270
29/01/15(A)
Commissioned
Maharashtra
Amravati TPP Ph-I
11/2009
Ratan India Power
Pvt Ltd.
U-4 270
03/2015
Drum lifted in 11/11. HT completed in 03/13. BLU completed in 12/14.SBO completed on 28/01/15 & normalisation is under progress. TG erection started in 02/12 & boxed up in 11/14. TG put on barring gear on 02/12/14.
U-5 270
09/2015
Drum lifted in 01/12. HT done on 11/14. TG erection started in 11/12.
Maharashtra
Amravati TPP Ph-II
10/2010
Ratan India Power
Pvt Ltd.
U-1 270
– * No work is going on at site.
U-2 270
–
U-3 270
–
U-4 270
–
U-5 270
–
Maharashtra
Bela TPP-I
12/2008
IEPL U-1 270
20/03/13(A)
Commissioned
Maharashtra
Butibori TPP Ph-II
12/2009
Vidarbha
Industries
Power
U-1 300
17/08/12(A)
Commissioned
U-2 300
31/03/14(A)
Commissioned
Maharashtra
Dhariwal Infracture TPP
04/2010
Dhariwal
Infrastructure (P)
Ltd
U-1 300
03/11/13(A)
Commissioned
U-2 300
28/05/14(A)
Commissioned
Maharashtra
EMCO Warora TPP
09/2009
EMCO Energy
Ltd.(GMR)
U-1 300
07/02/13(A)
Commissioned
U-2 300
27/08/13(A)
Commissioned
Maharashtra
GEPL TPP 04/2009
GEPL U-1 60 08/09/12(A)
Commissioned
U-2 60 28/04/12(A)
Commissioned
Maharashtra
JSW Ratnagiri TPP
07/2007
JSW Energy(Ratnagir
i) Ltd
U-1 300
24/08/10(A)
Commissioned
U-2 300
09/12/10(A)
Commissioned
U-3 30 06/05/1 Commissioned
0 1(A) U-4 30
0 08/10/1
1(A) Commissioned
Maharashtra
Lanco Vidarbha TPP
11/2009
Lanco Vidarbh
a
U-1 660
– Boiler erection started in 8/11. Work held up due to financial constraint.
U-2 660
– Boiler erection started in 12/11. Work held up due to financial constraint
Maharashtra
Mangaon CCPP
12/2011
PGPL Block-1
388
– Work held up.
Maharashtra
Mihan TPS
05/2008
Abhijeet MADC
Nagpur Energy Pvt Ltd
U-1 61.5
09/02/12(A)
Commissioned
U-2 61.5
09/02/12(A)
Commissioned
U-3 61.5
09/02/12(A)
Commissioned
Maharashtra
Mihan TPS
05/2008
Abhijeet MADC
Nagpur Energy Pvt Ltd
U-4 61.5
09/02/12(A)
Commissioned
Maharashtra
Nasik TPP Ph-I
11/2009
Ratan India Nasik Power
Pvt Ltd.
U-1 270
25/02/14(A)
Commissioned
U-2 270
03/2015
Drum lifted in 07/11. HT completed in 07/12 & BLU completed in 11/13. EDTA completed on 05/01/14. SBO completed on 14/03/14. TG erection started in 12/11 & boxed up in 01/14. TG put on barring gear in 04/14.
U-3 27 06/201 Boiler drum lifted in
0 7 12/11. TG erection started in 04/12. No work is going on at site.
U-4 270
11/2017
Drum lifted in 12/11. TG erection started in 07/12. No work is going on at site.
U-5 270
03/2018
Drum lifted in 03/12. TG erection started in 09/12. No work is going on at site.
Maharashtra
Nasik TPP Ph-II
11/2009
Ratan India Nasik Power
Pvt Ltd.
U-1 270
– No work is going on at site.
U-2 270
–
U-3 270
–
U-4 270
–
U-5 270
–
Maharashtra
Tirora TPP Ph-I
02/2008
Adani Power
Ltd
U-1 660
11/09/12(A)
Commissioned
U-2 660
25/03/13(A)
Commissioned
Maharashtra
Tirora TPP Ph-II
02/2008
Adani Power
Ltd
U-1 660
10/06/13(A)
Commissioned
U-2 660
23/03/14(A)
Commissioned
U-3 660
25/09/14(A)
Commissioned
Maharashtra
Wardha Warora TPP
05/2007
WPCL U-1 135
05/06/10(A)
Commissioned
U-2 135
10/10/10(A)
Commissioned
U-3 135
13/01/11(A)
Commissioned
U-4 13 30/04/1 Commissioned
5 1(A) MP Anuppur
TPP Ph-I 11/2010
MB Power
MP
U-1 600
03/2015
Boiler drum lifted on 06/11/12. HT done in 10/13. BLU done in 9/14. TG erection started in 05/13 & boxed up in 09/14.
U-2 600
07/2015
Boiler erection started in 02/12. Boiler drum lifted in 06/13. HT done on 31/03/14. TG erection started in 12/13.
MP Bina TPP 09/2008
Bina Power Supply Co. Ltd
U-1 250
12/08/12(A)
Commissioned
U-2 250
31/03/13(A)
Commissioned
MP Gorgi TPP ( DB Power)
03/2011
D.P Power ( MP) Ltd
U-1 660
Order for main plant equipment has not been placed so far. Erection yet to start.
MP Mahan TPP
09/2008
Essar Power MP Ltd
U-1 600
24/02/13(A)
Commissioned
U-2 600
06/2015
HT done in 2/12.
MP Nigri TPP 08/2009
Jaiprakash
Power Venture
s Ltd
U-1 660
29/08/14(A)
Commissioned
U-2 660
17/02/15(A)
Commissioned
MP Niwari TPP
04/2011
BLA Power
Ltd
U-1 45 10/12/13(A)
Commissioned
U-2 45 2015-16
Boiler erection started in 01/13. Drum lifted in 09/13.
MP Sasan UMPP
06/2008
Reliance Power Ltd.
U-1 660
21/05/14(A)
Commissioned
U-2 66 18/12/1 Commissioned
0 3(A) U-3 66
0 30/05/1
3(A) Commissioned
U-4 660
25/03/14(A)
Commissioned
U-5 660
24/08/14(A)
Commissioned
U-6 660
03/2015
Unit synchronized on 01/02/15.
MP Seioni TPP Ph-I
02/2010
Jhabua Power
Ltd
U-1 600
08/2015
Boiler erection started in 04/11. Drum lifted in 01/12. HT done on 26/12/12. BLU completed in 12/03/14. SBO expected in 03/15. TG erection started in 11/11. TG boxed up in 12/13. Oil Flushing started in 11/14.Presently work is in progress with very slow pace.
Orissa Derang TPP
07/2009
JITPL U-1 600
10/05/14(A)
Commissioned
U-2 600
24/01/15(A)
Commissioned
Orissa Ind Bharat TPP ( Orissa)
05/2009
Ind. Bharat
U-1 350
06/2015
HT done on 24/05/12. BLU done in 01/15. TG erection started in 05/12 & boxed up on 21/05/14. Oil flushing completed on 14/01/15.
U-2 350
09/2015
Boiler drum lifted in 12/11 & HT done on 20/05/14. TG erection started in 9/12
Orissa Kamalanga TPP
06/2009
GMR U-1 350
28/03/13(A)
Commissioned
U-2 350
28/09/13(A)
Commissioned
U-3 350
21/03/14(A)
Commissioned
Orissa KVK 11/2 KVK U-1 35 02/201 Hon'ble High Court of
Nilanchal TPP
009 Nilachal 0 7 Odisha has cleared the case. Now the project authority is mobilizing various contractors for restarting works at site.
U-2 350
2017-18
U-3 350
2017-18
Orissa Lanco Babandh TPP
11/2009
Lanco Babandh Power
Ltd
U-1 660
– Boiler erection started in 05/11. TG deck casting completed. Work held up due to financial constraint.
U-2 660
– Boiler structure erection started in 09/11. TG deck column casting completed. Work held up due to financial constraint.
Orissa Malibrahmani TPP ( Monnet Ispat)
06/2010
MPCL U-1 525
12/2015
Boiler erection started in 18/08/11. Boiler drum lifted on 21/03/12. HT done on 03/04/13.TG erection started on 28/01/13. Progress is very slow. BHEL stopped work at site due to financial issues.
Orissa Malibrahmani TPP ( Monnet Ispat)
06/2010
MPCL U-2 525
03/2016
Boiler erection started in 10/10/11. Boiler drum lifted on 21/07/12.
Punjab Goindwal Sahib TPP
08/2008
GVK Power
U-1 270
10/2015
Unit synchronized on 06/07/13. No further progress due to financial problem.
U-2 270
02/2016
Unit synchronized on 04/03/14. No further progress due to financial problem.
Punjab Rajpura TPP (Nabha)
07/2010
Nabha Power
Ltd
U-1 700
24/01/14(A)
Commissioned
U-2 70 06/07/1 Commissioned
0 4(A) Punjab Talwandi
Sabo TPP 07/2009
M/s Sterlite
U-1 660
17/06/14(A)
Commissioned
U-2 660
03/2015
Boiler erection started on 25/06/11. HT done on 11/3/14. BLU completed on 26/11/14. SBO completed on 30/11/14. TG erection started in 15/03/13 & boxed up in 05/14. Oil flushing completed in 10/09/14. Unit synchronized in 01/15.
U-3 660
07/2015
Boiler erection started on 25/12/11. HT done on 28/05/14. TG erection started on 08/04/13. TG boxed up in 05/14.
Rajasthan
Kawai TPP
04/2010
Adani Power Ltd.
U-1 660
28/05/13(A)
Commissioned
U-2 660
24/12/13(A)
Commissioned
TN Melamaruthur TPP
08/2009
Coastal Energen
U-1 600
02/12/14(A)
Commissioned
U-2 600
07/2015
HT done in 07/13. TG erection started in 12/11.
TN Tuticorin TPP (Ind- Barath TPP)
05/2010
IBPIL U-1 660
09/2017
Boiler foundation completed & erection started in 08/14. TG raft completed. Column casting is in progress.
TN Tuticorin TPP-II(Ind barath)
12/2009
Ind Barath
U-1 150
10/03/13(A)
Commissioned
U-2 150
30/12/13(A)
Commissioned
UP Anpara-C 11/2007
Lanco Anpara
U-1 600
15/11/11(A)
Commissioned
Power Pvt. Ltd.
U-2 600
12/11/11(A)
Commissioned
UP Barkhera TPP
12/2009
Bajaj Energy Pvt. Ltd
U-1 45 06/11/11(A)
Commissioned
U-2 45 28/01/12(A)
Commissioned
UP Khamberkhera TPP
12/2009
Bajajb Energy Pvt. Ltd
U-1 45 17/10/11(A)
Commissioned
U-2 45 28/11/11(A)
Commissioned
UP Kundarki TPP
12/2009
Bajaj Energy Pvt. Ltd
U-1 45 10/01/12(A)
Commissioned
U-2 45 29/02/12(A)
Commissioned
UP Lalitpur TPP
03/2011
Lalitpur power
Generation Co.
Ltd
U-1 660
03/2015
Boiler erection started on 23/03/12. HT done on 12/3/14. BLU done in 01/15. TG erection started on 15/12/13 & boxed up in 12/14.
U-2 660
07/2015
Boiler erection started on 30/07/12 . HT done in 20/6/14.TG erection started on 10/3/14.
U-3 660
06/2016
Boiler erection started on 27/11/12. TG deck casting completed.
UP Maqsoodpur TPP
12/2009
Bajaj Energy Pvt Ltd
U-1 45 03/11/11(A)
Commissioned
U-2 45 21/01/12(A)
Commissioned
UP Prayagraj (Bara ) TPP
10/2009
Prayagraj power
Gen. Co.Ltd
(J.P. Power
Venture
U-1 660
10/2015
Boiler erection started on 12/07/11. HT done on 24/10/13. TG erection started in 01/13 & boxed up in 02/14.
s) U-2 66
0 01/201
6 Boiler erection started on 12/09/11. HTdone in 12/14. TG erection started in 10/13.
U-3 660
04/2016
Boiler erection started on 05/09/11. HT done in 11/14.
UP Rosa TPP Ph-II
03/2008
Reliance Power Ltd.
U-3 300
27/12/11(A)
Commissioned
U-4 300
28/03/12(A)
Commissioned
UP Utrala TPP
12/2009
Bajaj Energy Pvt. Ltd
U-1 45 21/02/12(A)
Commissioned
U-2 45 19/03/12(A)
Commissioned
Uttarakhand
Beta CCPP
12/2010
BIPL GT+ST
225
– Work held up due to non availability of Gas.
Uttarakhand
Gama CCPP
07/2010
GIPL GT+ST
225
– Work held up due to non availability of Gas.
Uttarakhand
Kashipur CCPP-I
04/2010
Sravanthi
Energy Pvt. Ltd
Block-I
225
– Work held up due to non availability of Gas.
Uttarakhand
Kashipur CCPP-II
11/2010
Sravanthi
Energy Pvt. Ltd
GT+ST
225
– Work held up due to non availability of Gas.
WB Haldia TPP-I
09/2011
M/s Haldia Energy
Ltd.
U-1 300
14/01/15(A)
Commissioned
U-2 300
16/02/15(A)
Commissioned
HT- Hydro Test RO/DM- Reverse Osmosis / Demineralised
BLU- Boiler Light UP GTG- Gas Turbine Generator TG- Turbine Generator STG- Steam Turbine Generator
AWPH- Ash Water Pump Home EDTA- Ethylene Damien Tierra Acetic Acid
BOP- Balance of Plant RWPH- Raw Water Pump Home
SBO- Steam Blowing Off HRSG- Heat Recovery Steam Generator
CHP- Coal andling Plant BTG- Boiler Turbine Generator EPC- Engineering Procurement & Construction NGT- National Green Tribunal
ANNEX-IB
ANNEX REFERRED TO IN REPLY TO PART (a) OF UNSTARRED QUESTION NO.1627 TO BE ANSWERED IN THE LOK SABHA ON 05.03.2015.
State/UT/Project-wise details of Hydro Power Projects taken of during the Eleventh and Twelfth Plan Sl. No
Name of Project
Executing Agency
Date of CEA clearance/ Approval
Capacity (MW)
Broad Features
Cost (original/latest)
Date of award of 1 st civil
package
Comm. Sch.
(original/ Now Ant.
Broad Present Status
Remarks/issues
Arunachal Pradesh 1 Pare
NEEPCO
4.12.2008
31.08.09
2013-14
Civil Works:
Diversion Tunnel: DT and construction of u/s and d/s coffer
-Slow progress due to bad geology.
-Concreting of Dam, associated
Sl. No
Name of Project
Executing Agency
Date of CEA clearance/ Approval
Capacity (MW)
Broad Features
Cost (original/latest)
Date of award of 1 st civil
package
Comm. Sch.
(original/ Now Ant.
Broad Present Status
Remarks/issues
2x55 = 110 MW
Broad Features:
Dam : 78m High, Con. Gravity
Spillway – 3 nos. gates
Size of gate:
10.4m (w)X 12 m(H)
Crest Level: 216 m
HRT: Dia – 7.5 M
Length– 2810.75M
Pressure Shaft: Dia: 6.4 M
Length: 220M
Bifucation Penstock
2016-17 dams completed.
Dam: Excavation - 365708 cum out of 398000 cum completed. Concreting started w.e.f. November, 14 and 5474 cum out of 183000 cum completed..
Head Race Tunnel: Boring completed & 1220 m overt lining out of revised lining length of 1250m in face-II completed.
High Pressure Tunnel : Boring completed.
Surge shaft: Open excavation, boring and lining completed.
Power House: Excavation in pit completed. Concreting 24327
HM works and transmission line works are critical.
Sl. No
Name of Project
Executing Agency
Date of CEA clearance/ Approval
Capacity (MW)
Broad Features
Cost (original/latest)
Date of award of 1 st civil
package
Comm. Sch.
(original/ Now Ant.
Broad Present Status
Remarks/issues
Dia: 4.5 M
Power House: Surface
P.H. Size: 68 mX 25m
Type of Turbine: VF
TRC: Open channel
60.62 M wide 49M long
Cost: 573.99
1128.38
/35000 cum completed.
Hydro Mechanical Works:
Erection of steel liner – 92.3m out of 230.50 m completed.
Erection of DT inlet gate completed.
Electrical & Mechanical Works:
Erection of DT Liners of Unit I & Unit II has been completed.. Erection of spiral case of Unit - I completed.
Erection & Commissioning of
Sl. No
Name of Project
Executing Agency
Date of CEA clearance/ Approval
Capacity (MW)
Broad Features
Cost (original/latest)
Date of award of 1 st civil
package
Comm. Sch.
(original/ Now Ant.
Broad Present Status
Remarks/issues
EOT crane completed.
2 Gongri
Dirang Energy Pvt. Ltd.
04.02.13
2x72= 144 MW
Broad Features :
Barrage-H-29m, L-216.5m MDDL- EL 1447m
Spillway-2nos.
Radial Gates; 2 Nos.
10.5m x 13m
Intake: EL1438m
Desilting Chambers : 2 nos.
22.12.11
2017-18
2017-18
EPC contract for all works awarded to Patel Engineering Ltd., Mumbai on 22-11-2011. TEC accorded on 04-02-2013 & Financial closure achieved on 15-02-13. Consent to establish from State Pollution Control Board was issued on 19-05-2014.
Infrastructural works are in progress.
Sl. No
Name of Project
Executing Agency
Date of CEA clearance/ Approval
Capacity (MW)
Broad Features
Cost (original/latest)
Date of award of 1 st civil
package
Comm. Sch.
(original/ Now Ant.
Broad Present Status
Remarks/issues
(260Lx13Wx16H)
HRT- modified horse shoe, 5.8 m dia & 7137m length ,
Surge Shaft- 92 m High & 13m dia.
Pressure Shaft : 4.4m dia, 647.26m length bifurcating into 3.1m dia & 28.51m & 34.5m length
P.House-Surface
Turbine- Vertical Francis
Cost : Original: 1436.27
Latest :1436.27
Himachal Pradesh
3 Kashang-I
H.P. Power Corpn. Ltd.
31.07.08
65 MW
Broad Features:
HRT-3.5m x 4.115, 2 km long
S.Shaft- 2.6m dia & 0.5 m backfill and 1346 m long
TRT: 335 m combined
6/4.5 m D. stream
Cost: Original: 478.02
Latest: 478.02
09.04.09
2013-14
2015-16
Trench Weir: 3879 cum out of 3978 cum concreting completed.
HRT: Excavation and lining completed. Grouting yet to start. Pressure Shaft: Ferrule erection in top horizontal portion– 21m / 35m, low including limb - 41m / 536m completed. Ferrule erection upper inclined limb & bottom horizontal portion completed. Ferrule erection at horizontal portion at intermediate adit yet to start. Backfill concreting 649 m / 1346 m completed.
E&M works: Laying of earth mat is in progress. Model test completed.
Power House & Transformer hall concreting is in progress.
TRT concrete lining 197 m out of 335 m completed.
- Slow progress of Civil & E&M works.
- Approach roads washed off during heavy rains in Monsoon 2013.
4 Kashang-II & III
H.P. Power Corpn. Ltd.
1x65 + 1x65= 130 MW
Cost: Original: 601.78
Latest: 601.78
11.11.10
2013-14
2016-17
Works of Kerang-Kashang link (KK Link) tunnel awarded to M/s Patel Engineering Ltd.
-Works getting delayed due to continuous agitation by Lippa villagers.
-The matter is sub-judice.
5 Sainj 02.08.10 Barrage: Concreting in - HRT works &
H.P. Power Corpn. Ltd.
2 X50=100 MW
29.12.2010
Cost:Original 784.56
Latest 784.56
2014-15
2016-17
2-bays out of 6 bays completed.
HRT: 935 m of overt lining completed in Face-I. Face-II 926 m/2010m and Face-IV 72m/1406m completed
Main Access Tunnel to Power House excavation is completed.
Power House: Excavation completed. 2nd
stage concreting for Unit #1 & #2 completed.
TRT: Excavation and Concreting completed.
barrage works.
6 Swara Kuddu
H.P. Power Corpn. Ltd.
Clearance: 10.11.2004
3x37= 111 MW
Broad Features:
Diversion Structure: 10.45m high Piano Key Weir.
HRT- D-Shaped, 5m dia, 11.145Km long.
Power House- Under ground
Turbine- 500
17.07.07
2010-11
2016-17
HRT: 9722 m out of 11764 m from all faces of HRT excavation completed and 1777 m out of 11364 m concreting is completed.
Surge Shaft: 70.38 m completed out of 77 m of shaft lining.
Power House: Excavation completed and concreting 7127cum out of 7850cum completed.
TRT: lining completed.
E&M Works: Ist, 2nd and 3rd stage embedment’s installation of all units completed. Installation of stator, rotor, lower bracket & upper bracket for unit no.3 completed
- Works badly suffered due to encounter of poor geology.
- Progress of HRT lining is slow.
- Contractual Issues.
-Contract for HRT package terminated on 9.1.14. Fresh award yet to be placed.
rpm VF.
Switchyard: 220 Kv.
Cost: Original: 558.53
Latest: 1181.90
and for Unit #2 is in progress.
7 Sorang
Himachal Sorang Power corporation Ltd.
June, 2006/
2x50= 100 MW
Broad Features:
HRT- 1.5 km
Trench Weir-59 m
P.House- underground
Turbine- Pelton
Gross Head-626 m
SWYD- 11/400 kV (GIS)
Cost: Original: 586.00
Latest: 586.00
06/2007
2012-13
2015-16
Almost all Civil Works completed.
Transmission line stringing between tower no. 6&7 is yet to be completed.
Both the units are boxed up. During the filling of water conductor system in 1st week of Nov., 2013, leakage occurred in penstock due to cracks. Remedial measures are under progress.
- Completion of Transmission line works.
- Failure of penstock during filling.
8 Tidong-I 07.11.0 Barrage: Excavation Slow progress
M/s NSL Tidong Power Gen. Ltd.
2x50 = 100 MW
28.07.2006
Broad Features:
HRT – D- 3.5m L- 8461 m
P.H. Surface
Turbine – Vertical Pelton
Cost: Original 543.15
Latest 543.15
8
2013-14
2016-17
completed. 31215 cum out of 33355 cum concreting done.
HRT: 7.7 km out of 8.6 km excavation completed. 425m concreting completed
Surge Shaft: open excavation top 15984 cum / 38500 cum completed. Underground excavation 90m/110m completed.
Pressure Shaft: Excavation completed
Power house- 87446 cum out of 92500 cum excavation completed.
8971 cum out of 14025 cum concreting completed.
of works
9 Tangnu Romai-I
M/s Tangnu Romai Power generation
2x22= 44 MW
30.11.2007 (HPSEB)
Broad Features:
Barrage at EL + 2555 m
HRT-3.1m dia
14.06.10
2014-15
2016-17
Civil works awarded on 14.06.2010 to M/s Sai Urja Hydel Project (P) Ltd.
Diversion Cannel: 26164 cum out of 93800 cum excavation completed.
Desilting Chambers & SFTPC: Excavation completed. SFT excavation 420 / 450.66 m completed.
HRT –2796m out of 6323m excavation completed.
Power House, Switchyard & Misc. – 62500 m3 out of
Slow progress of works
HRT critical, poor geology.
& 7.220 km length
Surge Shaft- 5m dia, Top Level 2570 m & Bottom Level 2520 m
Penstock- 2 m dia & 609.3 m length
P.House- Surface
Turbine – Vertical Francis
Cost:
Original: 255.00
Latest: 255.00
72000 m3 excavation completed.
10
Chanju-I
M/s IA Energy
24.04.2010
3x12=36 MW
Cost :Original : 295.09
Latest : 295.09
23.07.11
2017-18
2017-18
Barrage: 267500 cum excavation out of 287700 cum has been completed.
Desilting Basin including Flash arrangement: 20340 cum excavation out of 20800 cum has been completed. 2000 cum concreting out of 3510 cum completed.
HRT: Excavation 3900 m out of 4615 m completed.
Surge Shaft: Excavation completed (532 m)
Penstock/Pressure Shaft: 196 m excavation out of 720 m has been completed.
Power House: 134760 cum excavation out of 152147 cum completed. 4000 cum/6640 cum concreting completed.
E&M Works: Awarded. 11
Bajoli Holi
M/s GMR Bajoli Holi Hydro Power Pvt. Limited
31.12.2011
3x60= 180 MW
Broad Features
Dam Height-66 M
Dam Length-178 M
Desilting Chamber- 2 Nos.
240 Mx14.5 MX 10.8 M
HRT- Length-15.538 Km., 5.6 M dia
29.05.13
2017-18
2017-18
Civil Works awarded to M/s Gammon India ltd. on 29.05.2013.
Works are in initial stages of construction
P.H. –Surface
Cost: Original 1696.93
Latest 1696.93
12
Shongtong Karcham
H.P. Power Corpn. Ltd.
Clearance: 16.08.2012
3x150= 450 MW
Broad Features:
Intake Tunnel: 4 Nos. Horse shoe 6.4m dia 192 to 280m length
HRT- Circular, 10.5m dia, 8096m long.
Power House- Under ground
Turbine- VF.
Switchyard: 400 Kv.
Cost: Original: 2807.83
Latest: 3316.35
04.08.12
2017-18
2017-18
Works awarded on 30.06.2012. CEA, concurrence accorded on 16.08.2012.
Civil Works:
Excavation of Adit – II : 103m out of 422m completed.
Road to Adit- III : Completed.
Excavation of Adit – III : 41m out of 418m completed.
Excavation of Adit – IV : 350m out of 403m completed.
Excavation of Main Access Tunnel (MAT) : 173m out of 188m completed.
Excavation of Ventilation Tunnel (VT) & Access tunnel to Transformer Hall : completed.
Diversion tunnel : Approach road / removal of muck at inlet portal is under progress.
E&M: Not yet awarded.
-Issues with Army authorities for shifting of ammunition depot.
-Award of E&M works.
Works hampered in some portion of HRT : - To sort out the issues with Army Authorities, a meeting between Secretary (Defence) to Govt. of India, Chief Secretary to GoHP, Army Authorities and HPPCL representatives was held on 06.06.2014, wherein it has been decided to sign a tri-partite MoU between Army, GoHP & HPPCL. Further, DC Kinnaur has been asked to find out the suitable location for shifting the ammunition depot from Powari. Draft MoU has been sent to Army Authorities for their consent.
Jammu & Kashmir
13
Kishanganga
NHPC
14.01.2009
3x110 = 330 MW
Broad Features :
Dam – 77m High,
concrete gravity
HRT- 5.3m x 24 km long
22.01.09
2015-16
2016-17
Diversion Works: – River diversion achieved on 21.06.2012.
Dam & Intake works:- Spillway concreting- 9950 cum completed out of 47000 cum.
CFRD Embankment- 116500 Cum completed out of 254000 Cum. Construction of Cut off Wall-1620 Sqm completed out of 2600 Sqm..
HRT:- Excavation completed by TBM/ DBM.
-Law and order problems viz frequent bandhs and curfew.
-Local agitation due to people demanding employment in NHPC.
S.Shaft-15m dia x 127m H
P.House- Underground
103mx 21m x 45.5m.
Turbine- Pelton wheel
Swyd.- 220 kV
Cost: Original:3642.04
Latest: 5497.72
Lining of TBM portion (14.7 km) completed and 2132m lining of DBM portion completed out of 8437m.
Surge Shaft:- 62m Concreting completed out of 100m.
Pressure Shaft upper limb liner:- 227 m liner completed out of 233 m.
Power House:- 7977 cum concreting completed out of 10800 cum.
TRT : -Excavation completed. 342m lining out of 849m completed.
E&M: - Erection of pit liner & central frame in Unit-1 completed.
Assembly of Stator & rotor of Unit-1 in service bay is in progress.
Erection of EOT crane in Unit # 2 is in progress.
-R&R plan is pending with state cabinet for approval needs to be expedited.
-Completion of Power evacuation arrangement.
14 Baglihar-II
JKPDC
19.03.2012
3x150= 450 MW
Broad Features:
HRT – 10.15 m
31.03.12
2015-16
2015-17
Baglihar-II H.E. Project was conceived along with Baglihar-I H.E. Project. Works associated with dam and some portion of HRT was completed along with Baglihar Stage-I project.
HRT: Excavation completed. Lining almost completed.
E & M Works are critical.
dia circular & 1888.8 m long
Surge Shaft: 27.5 m dia
& 97.5 m high restricted orifice type
Power House: Underground TRT: D-10.05 m L-342.6 m
Cost: Original: 3113.19
Latest: 3113.19
Surge Shaft: Excavation completed Lining also almost completed.
Penstock: Lining almost completed 254 out of 283 nos. ferrule erection completed.
PH: Excavation completed. Concrete lining under progress. Spiral casing for all three units completed. Installation of rotor hub under progress
TRT: 13,652 cum out of 15200 cm concreting completed.
15 Ratle
Ratle Hydro Electric Project Pvt. Ltd.
19.12.2012
4x205+1x30= 850 MW
Broad Features :
Dam Height-133m
Length-194.8m
Spillway-Radia Gate-5 No.
04.07.13
2017-18
2017-18
EPC Contract for Civil & HM works awarded to M/s GVK Projects & Technical Services Limited on 04.07.2013. The infrastructure works of Road & Bridges is under progress and erection of upstream Bridge completed & downstream Bridge is in progress.
Works are in initial stages of construction
Size-10.75x1420 m
Diversion Tunnel:2 Nos., Circular (Right back)
Pressure Tunnel:11m dia each.
Pressure Shaft : 6.6 m each steel lined.
P.House-Underground
Turbine- Francis
Average Gross Head-100.39m
Addl. Unit(30MW) Housed in Main P.H. Cavity)
Rated Head-98.9m
Cost : Original: 5517.02
Latest : 5517.02
Kerala 16 Thottiyar
KSEB
1x30 + 1x10=
22.12.08
Civil Works:
Weir: 3258 cum excavation out of total 5850 cum and 155.83
The works of weir & approach channel were hampered
40 MW
05.06.2008
Broad Features:
Weir: 222m Long 11 blocks 7.5m height
Tunnel: Circular 2.6m dia 199m long.
Power House: Surface
Turbine : Vertical Pelton
Cost: Original: 136.79
Latest: 150.02
2012-13
2016-17
Cum concreting out of 8690 Cum completed.
Approach Channel & Intake: 3184 cum out of 9100 cum done.
Power Tunnel : Excavation completed.
Power House, switchyard & allied works: 31390 cum excavation out of 44500 cum and 1588 cum concreting out of 15675 m done.
E&M and HM Works: Supply of equipment in progress.
since 2010 due to land acquisition issues by local people and injuction order by Hon’ble municif court.The works resumed on 9-4-13.
Maharashtra 17 Koyna Left
Bank PSS
WRD, Mah.
20.02.2004
2x40 = 80 MW
Broad Features:
Water from the existing Shivaji Sagar Lake
(Koyna
20.06.07
2017-18
2017-18
Civil Works:
Excavation of intake structure 3987 cum out of 11097 cum and lining 2485 cum out of 9700 cum completed.
Excavation of Switchyard completed. Excavation of Approach tunnel & Ventilation tunnel is in progress.
Tail surge shaft : Excavation in soft strata completed. Excavation for inclined / vertical / lateral shafts in hard rock 7476 / 47320
Slow progress of works.
reservoir)
is to be utilized for generation.
Intake Tunnel: Dia–7.20 M
Length – 235.5 M
(including Lake tap)
HRT: Dia – 7.20 M
Length – 80 M
Penstock – 2 nos Dia – 2.9M
Length – 10 M each
P.House – Underground
Turbine – Reversible
Cost: Original: 226.40
Latest: 379.78
cum completed.
TRT : 364 / 24003 cum excavation completed.
Machine Hall : Underground Excavation is under progress. 22600 cum excavation out of 55050 cum completed.
E&M works:
The contract for details engineering manufacturing supply, supervision erection, testing commissioning and putting into commercial use of pump turbine, generator motor and associated equipments is signed with M/s IVRCL Ltd., Pune on 16.12.2010. Further TG set has been ordered as under:
Turbine/Pump: M/s Litosroj Power, Slovenia (European Union)
Generator/Motor: M/s Koncar Power, Plant & Electric Traction Engineering, Croatia (European Union).
EOT Crane :- Works awarded to M/s Pedvak Cranes Private Limited Hyderabad on 12.04.2013.
Meghalaya 18 New Umtru 20.12.07 Dam: Excavation 61998
MePGCL,
2x20=40
Broad Features:
Diversion Structur-Gated structure (FRL-130.1m, MDDL-123.3m)
HRT- 5m dia, 750m long
P.House- Deep Set
SWYD- 132 kV
Cost: 226.40
461.27
2011-12
2016-17
cum out of 208685 cum completed. Concreting 32773 cum out of 73488 cum completed.
Intake: Excavation of 26984 cum out of 30000 cum completed. Concreting done which is more than estimated quantity of 13000 cum.
HRT: Excavation completed. Concreting 16,686 cum out of 20,888 cum completed.
Pressure Shaft: 421 tons of steel lining out of 525 tons completed.
Surge shaft: Open excavation completed and concreting done which is more than estimated quantity of 6166 cum.
Power House: Excavation completed & concreting is in progress.
TRT: Open excavation & tunnel boring completed & lining also almost completed.
E&M Draft tube erection completed for both units.
Turbine erection of embedded of both the units completed.
Punjab 19
Shahpurkandi 11.02.1 Civil works of Main Dam and Hydel Channel
Irrigation Deptt. &PSPCL
04.05.2011
3x33+3x33+1x8=206 MW
Cost: Original: 2285.81
Latest 2285.81
3
2017-18
2017-18
awarded and are under construction
Sikkim 20
Teesta-III
Teesta Urja Ltd. (TUL)
12.05.2006
6x200=1200 MW
Broad Features:
Dam-Concrete with chute spillway 60m high.
HRT- 7.5m dia, 13.325Km long.
Press. Shaft- 3nos. 3.8m dia.
Power House- Under ground
Turbine- Pelton
Cost: Original 5705.55
Latest
18.04.07
2011-12
2014-17
Dam: CFRD, 11.13 lacs cum material placed out of 11.5 lacs cum.
HRT: Excavation completed. 13653 M overt lining completed out of 13824 M and 12416 M invert lining completed out of 13824 M.
Surge Shaft: Excavation completed. 79.7m conc. Lining out of 154.5m completed.
Pressure Shaft-Vertical portion: Erection of steel liner 310.75m ouit of 659.70m for left pressure shaft and 178.65m out of 659.80m for right pressure shaft completed.
Power House: Civil works almost
- Earthquake in Sikkim in September., 11
- Completion of balance works after Earthquake
- Financial crunch with the developer. Works held up since October-2014.
- Power evacuation arrangement.
- Erection of vertical pressure shaft.
- Work
11382.00 completed.
TRT: Excavation completed. 1315 m overt lining out of 1336 m completed.
Unit Erection:
Unit#1,2 &6- Stator & Rotor lowered.
Unit# 3&5: Stator lowered.
Unit#4- Stator assembly in service bay is in progress.
stopped since Sept, 2014 due to fund constraints, likely to restart by Mar, 2015.
21
Rangit-IV
Jal Power corp. Ltd. 06.07.2007
3x40= 120 MW
Broad Features:
Dam: Concrte 44m high .HRT : D- 6.4m L- 6.5km
Power House : Surface
Turbine: Francis
Power House- Under ground
Turbine- Francis
Cost: Original:726.17
22.11.07
2012-13
2016-17
Dam & Intake works: Excavation 290733/519887 cum completed and concreting 61008.5 cum out of 145413 cum completed. Excavation of road diversion tunnel has been completed.
HRT: Excavation in progress and 3557 m out of 6488 m completed.
Surge Shaft: Excavation has been completed & concreting is in progress.
Power House: The work of approach road to power house completed. Excavation in Power House is in
- Work hampered due to earthquake in September, 2011.
- Poor geology in HRT.
- Right bank slope failure at Dam site.
- Financial crunch with the developer.
Latest : 726.17
progress.
Desilting chamber: Excavation 2121 m out of 3360 m completed.
22
Jorethang Loop
M/s DANS Energy
2x48 = 96 MW
Broad Features:
Barrage: Gravity Floor on
Permeable Foundation
15 m High .
HRT : D- 7m L- 6.780km
Surge Shaft :59m Height & 25m dia.
Pressure Shaft : 172.60m length & 6m dia.
Power House : Surface
TR-Cut & Cover Conduit & 46.4m length.
Switchyard: Outdoor, 220 KV/11KV
Cost: Original: 543.15
09.03.09
2012-13
2015-16
HRT: Excavation completed. Concrete lining works are under progress.
Barrage : All major civil works are completed.
Surge Shaft: Excavation completed and lining upto EL 366.00 (55 m) completed. Chipping of gate grooves was also completed.
Upstream of Surge Shaft gate is concreted and 9m upstream part of Surge Shaft slab also concreted. Installation of Surge Shaft Gate is completed.
Pressure Shaft: Excavation completed. Ferrule erection in progress.
Power House: Structural civil works completed including roof installation.
Tail Race Channel: Excavation & Concreting completed. Draft tube gates for the
- Lining of HRT.
- Power evacuation arrangement.
Latest : 543.15
both units were lowered, installed and erection of the hoisting is also completed.
E&M works:
Unit-1 & 2: Both the units boxed up
HM Works: Fabrication of all Gates & associated ferrules for all portions has been completed. Both testing of spillways & under Sluice service gates are erected. Erection of surge shaft gates assembly has been completed. Penstock erection, alignment & welding of ferrules has been completed.
Dry Testing of Draft tube Gates for both units has been completed.
23
Bhasmey
Gati Infrastructure
3x17= 51 MW
Broad Features :
Dam-33.2m High,
Symmetrical gravity
12.04.10
2012-13
2017-18
Diversion tunnel completed.
HRT: Adits 309.85 Rm/781.97 Rm completed.
Power House: Excavation 181117/216147 cum completed.
- Slow progress of works
- Financial crunch with the developer.
HRT-5.3m dia &5.132 km length , Circular.
Surge Shaft- 89.8m Hight & 14m dia.
P.House-Outdoor
Turbine-VF
TRT-2 Nos, L- 50m each.
Swityard- 132/11 KV
Cost :Original : 408.5
Latest : 408.5
Pressure Tunnel/Shaft: Excavation 40Rm out of 559.84 Rm completed.
24
Tashiding
M/s Shiga Energy Pvt. Ltd.
28.03.2011
2x48.5 = 97 MW
Broad Features :
Barrage-EL 917m
HRT-4.5 m dia & 5.437 km length ,
Surge Shaft- 61.058m Height & 8.5m dia.
Penstock- Length upto Bifucation 441.53 m
28.03.11
2017-18
2017-18
HRT (Total- 5437m): Excavation on Face-1: 1343.40 m,
Face-2: 765.00 m, Face-3: 1181.48 m, Face-4: 1119.10 m, Face-5:634.95m, Face-6:243.34m
Surge Shaft: Surface preparation for Adit to Surge Shaft has been completed.
E&M Works: The contract for E & M works was awarded to M/s ALSTOM Projects India Ltd. M/s ALSTOM Projects India Ltd. has submitted the model test report and same
- Poor geology.
- Local issues.
After bifurcation 25 m & 30 m long
P.House-Surface
TRT- Open Channal & 78.5 m length.
Swityard- Outdoor, 220 KV
Cost :Original : 465.95
Latest : 465.95
has been accepted.
Power House: Power House open excavation along with slope protection was completed in the month of Feb’ 2014. Thereafter, 1st stage concreting of both the units completed. Up to EL 682.50m. 2nd stage concreting of both the units completed up to EL682.50m. Raft of concrete Draft tube of both the units completed.
25
Dikchu
Sneha Kinetic Power Projects Pvt. Ltd.
21.10.2011
3x32= 96 MW
Broad Features :
Dam-35m High,
Concrete Gravity
HRT-4m dia &4.6 km length
Circular.
Surge Shaft- 65m High & 9m dia.
P.House-Underground
22.03.11
2017-18
2017-18
Dam: Excavation 54000 cum out of 86762 cum completed.
HRT: Excavation 72 RM out of 5456 RM completed.
Power House: Excavation 22317 cum out of 43570 cum completed.
TH: Excavation 8914 cum out of 9177 cum completed.
TRT: Excavation 195 Rm out of 295 Rm completed.
Main Access Tunnel: Excavation completed.
Slow progress of works
Turbine-Vertical Francis
TRT-4m dia & 1000m length
Swityard- 60mx30m size
Cost : Original :639.57
Latest : 639.57
26
Rangit-II
Sikkim Hydro Power Limited
10.02.2010
2x33= 66 MW
Broad Features :
Dam-47m High,
Concrete Gravity
HRT-3.9m dia &4.745 km length ,
Surge Shaft- 65.5m High & 10m dia.
Underground Pressure Shaft : 1.7 m dia &2.5 km length.
24.10.11
2017-18
2017-18
EPC contract awarded to M/s Coastal in February, 2012. Works of approach roads and excavation of adits are in progress.
Protection wall works under progress.
Adit to HRT: Underground excavation is in progress.
Diversion Tunnel: Excavation is under progress.
Surge Shaft: Excavation is under progress.
Power House: Excavation of surface power house is being taken up.
Slow progress of works
P.House-Outdoor
Turbine- Pelton Vertical
Swityard- GIS, 132/11KV
Cost : Original : 498.00
Latest : 498.00
27
Rongnichu
Madhya Bharat Power Corporation Ltd.
01.10.2008
2x48= 96 MW
Cost : Original : 491.32
Latest : 491.32
07.04.10
2015-16
2017-18
The civil works have been awarded to M/s SEW Infrastructure Ltd. and E&M works to M/s Voith Hydro Power Pvt. Ltd. Award of HM works is likely to be placed by August, 2012. Pre-construction activities and excavation of adits are in progress.
- Land acquisition.
- Poor geology.
28
Panan
Himagiri Hydro Energy Pvt. Ltd.
07.03.2011
4x75= 300 MW
Broad Features :
Dam-115m from deepest
22.02.14
2018-19
2018-19
Civil works awarded on 22.02.2014. Infrastructural works and geological investigations are in progress.
foundation level
Desilting Chambers : Underground, 2
Size (14Lx22Wx2.5H)
HRT- modified horse shoe, 6 m dia & 9549m length ,
Surge Shaft- 102 m High & 15m dia.
Pressure Shaft : 2/4, 3.4/2.4m dia & 707.4 m high.
P.House-Surface
Turbine- Vertical Francis
Cost : Original: 1833.05
Latest :1833.05
Telengana 29
Lower Jurala
TSGENCO,
TEC in July 2007
6x40=240 MW (120 MW likely to slip)
10.02.08
2011-13
2014-17
Weir: Excavation completed. 203966/219040 cum concreting completed.
Power House: Excavation completed. 218018 cum concreting against total quantity of
- Power House flooded on 30.07.2014 during synchronization process for Unit# 1 to Unit# 3.
Broad Features:
Intake: 18 vents (3 vents for each unit) 4.7m width,
P.House- Surface,
Turbine- Bulb
Design Head- 20m
SWYD- 220 kV
Cost: Original: 908.34
Latest: 1474.83
(likely to slip)
225550 cum done.
Unit Erection:
The Units 1,2,3 which were completed and units 4,5,6 which are under different stages of erection were completely submerged in water on 30.07.2014 due to sudden gush of water through the upstream gate of Unit No.4. It was dewatered by 03.09.2014. Re-conditioning of Units is in progress by M/s Alstom. Rectification works of stator and rotor for U#1,2,4&5 at service bay are in progress.
U#1 – Rotor lowered,
U#2 – Rotor is ready for lowering ,
U#4 – Main shaft cleaning, assembly of bearing with shaft is completed and ready for lowering.
Commissioning is likely to slip to 2015-17.
Restoration works in power house is under process.
30
Pulichintala
TSGENCO
120 MW (4x30 MW)
01.08.07
2009-11
Dam is under construction by Irrigation Department.
Power House: The excavation of power house completed and 70351 cum concreting
- The civil works were hampered from Sept.-11 to May-13 due to contractual issues. Works resumed by the contractor on
25.04.2007
Broad Features:
Design Head: 24 M
Power House: Surface
Turbine : V. Kaplan
Annual Energy: 220 MU
Cost: Original: 380.00
Latest: 396.00
2016-17
done against 89850 cum..
E&M Works:
EOT Crane: Erection completed.
Unit #1 : stay ring and spiral casing erection completed.
Unit #2 : stay ring erection completed. Spiral casing segments erection is in progress.
Unit #3 & 4: Erection of draft tube cone & welding completed and released for concreting.
16-06-2013.
Uttarakhand 31
Shrinagar
AHPC Ltd..
14/06/2000/ FC
4x82.5=330
Broad Features:
Dam –66.5m High, concrete gravity
HRT- 13m x 889m
06/2007
2005-06
2015-16
Civil Works: Completed.
Electro Mechanical Works: Unit # 1 to #3 boxed up. (Spinning earlier done.)
Unit # 4 to be boxed up by Feb ‘2015.
- Agitation by locals.
- Financial constraints.
Penstock-4x 5.6m x 114m
P.House- Surface
Turbine- Francis
Cost: Original: 1699.12
Latest: 2069.00
32
Phata Byung
M/s Lanco
06.10.2008
2x38 MW = 76 MW
Broad Features:
Dam – 26m high
HRT- 3.2 m dia &
9.38 km length
Turbine – Frances
Cost: Original: 720.00
Latest: 720.00
12.04.08
2013-14
2017-18
Diversion Tunnel: River diverted.
Dam concreting: 17800/18000 cum concreting completed.
P.H.: Excavation completed & Concreting in progress.
HRT: Excavation 8474/9228 m completed.
Excavation and lining of Intake-I & Intake-II completed.
Cable tunnel: Completed.
TRT: Excacation 178/235m completed.
E&M Works: Pit liner erection of units completed.
- Poor geology in HRT.
- Power evacuation system.
- Flash flood in June-2013.
- Works yet to commence after floods.
33
Singoli Bhatwari 20.06.0 River diversion – - Poor geology
M/s L&T
11.07.2008
3x33 MW = 99 MW
Broad Features:
Barrage-FRL 1017 m, MDDL 1009 m,
Barrage Top 1020m
HRT- 4.65m dia & 11.870m length
Surge Shaft-10 m dia & 102.85 m length
Pressure Shaft-One, 3.80m dia & 358m length
Penstock- 3 Nos., 2.20 m dia & 34m, 42m, 48m long.
P. House-Surface
Turbine-Vertical Francis
TRT- Open Channel, 650m length
8
2015-16
2017-18
Completed.
Dam & Dykes/Barrage: Excavation 69692/90744 cum and concreting 47311/76500 cum completed.
HRT: Excavation 8653/11255 m completed.
Pressure Shaft: Excavation 440.5/558 m completed.
PH: Excavation completed & concreting 6517/18000 cum completed.
Surge Tank: Excavation completed.
in HRT.
- Agitation by Local people.
- Flash flood in June-2013 in Uttarakhand.
- Works commenced after flash floods in September-14.
Cost : Original : 666.47
Latest : 666.47
34
Tehri PSS,
THDC,
18.7.06
Nov-11 (Revised CCEA)
4x250=1000 MW
Broad Features :
Surge Shaft: U/s – 2 nos.
D/s – 2 nos
Power House: U/G
TRT: 2, Dia 9m and Lenghth 1070m + 1160m
Turbine: VF reversible pump turbine
Cost: Original: 1657.60
Latest: 2978.86
23.06.11
2011-12
2018-19
EPC contract has been awarded on 23.06.11 with commencement date from 27.07.11.
Upstream (Tehri Dam) and Downstream (Koteshwar Dam), intake and Head Race Tunnels (2 Nos.) already completed alongwith Tehri Stage-I works.
Surge Shafts upstream (2nos- 140m).: Pilot shaft excavation for both shafts completed.
Butterfly Valve Chamber (BVC): Crown slashing with steel ribs completed. Benching will start after treatment of deformation observed in drainage gallery.
Penstock Assembly Chamber (PAC): Crown slashing with steel ribs completed. Benching will start after two benches of BVC.
PH: Underground excavation of PH upto EL 582m: 87.5 Th. Cum out of 130 Th. Cum completed.
Surge Shafts downstream (2nos).: Pilot shaft excavation for both the shafts completed. Excavation of drainage gallery around surge also completed.
TRT (2 Nos- 1070m &
- Poor Geology in under ground works of BVC & PSAC, TRT, PH Cavern etc.
- Due to poor geology encountered during investigation, it was decided to shift service bay at other end of machine hall and accordingly power house layout has been revised.
- Poor preparedness of contractor w.r.t. finalization of design & drawing, inadequate deployment of resources at project works.
- Ban by DM, Tehri on mining activities in Asena Quarry since 1-4-2013. Environment
1160m).): Heading in 327.5m and drift in 94m out of 1070m in TRT-1 and Heading in 220.5m and drift in 228.4m out of 1160 RM in TRT-2 has been achieved.
E&M Works: Manufacturing & supplies are in progress.
clearance modified by State Level Env. Impact Assessment Authority (SEIAA) in Jan-2015.
Uttarakhand 35
Lata Tapovan,
NTPC
Aug-2012
3x57= 171 MW
Broad Features :
Barrage–14 bays of 11m each
HRT- 7.51 Km, 4.7m dia
P.House- underground
Turbine- V.Francis
Cost: Original: 1527.00
Latest: 1527.00
17.08.12
2017-18
2018-19
Pre-construction activities & infrastructure works are in progress.
EPC contract for Civil & HM works awarded to M/s L&T on
17-08-2012. E&M package awarded to M/s BHEL on 07.12.12.
- Flash flood in June-2013.
- Works of barrage & HRT yet to start due to protest by villagers.
-Construction work stopped vide Hon’ble Supreme Court order dated 7.5.14.
36
Vishnugad Pipakoti
THDC
17.01.14
2013-14
Civil and HM works awarded on 17.01.2014.
E&M works awarded on
-Disruption of works by local people.
21.08. 2008
4x111= 444 MW
Broad Features :
Dam – 65m High, 89.3m long, concrete gravity
HRT- 13.4 Km, 8.8m dia Horse shoe shape
P. House-Underground 127mx 20.3mx 50m
Turbine- Francis
SWYD- 13.8/420 kV
Cost:Original: 2491.58
Latest: 3745.08
2018-19 18.11.2014.
Heading excavation in 215m out of 490m for Diversion Tunnel completed.
Construction of Adits and infrastructure works are under prgroess.
ANNEX-II
ANNEX REFERRED TO IN REPLY TO PART (b) OF UNSTARRED QUESTION NO.1627 TO BE ANSWERED IN THE LOK SABHA ON 05.03.2015.
***********
EXPANSION THERMAL PROJECTS UNDER CONSTRUCTION
AS ON 02-Mar-2015
Sector Project Name Impl. Unit Cap. Ant. comm
State Agency No. (MW) Date
CENTRAL SECTOR
Bihar Barh STPP-II NTPC U-4 660 30.11.13
U-5 660 03/2015
Bihar Muzaffarpur TPP Exp NTPC U-3 195 03/2015
U-4 195 12/2015
Jharkhand BokaroTPS "A"Exp.DVC U-1 50012/2015
Maharashtra Mouda STPP-II NTPC U-3 66012/2016
U-4 660 06/2017
MP Vindhyachal TPP-V NTPC U-13 500 10/2015
Tripura Agartala CCPP NEEPCO ST-1 25.5 05/2015
ST-2 25.5 03/2015
UP Tanda TPS -II NTPC U-1 660 05/2018
U-2 660 11/2018
UP Unchahar TPS St-IV NTPC U-6 500 11/2017
WB Raghunathpur TPP Ph-IIDVC U-1 660 10/2018
U-2 660 03/2019
STATE SECTOR
AP Rayalseema St-IV U-6APGENCO U-6 600 12/2016
Bihar Barauni TPS Extn BSEB U-1 250 11/2015
U-2 250 02/2016
Gujarat Sikka TPS Extn. GSECL U-3 250 03/2015
U-4 250 07/2015
Gujarat Wankbori TPS Extn GSECL U-8 800 10/2018
Karnataka Bellary TPP St-III KPCL U-3 70012/2015
Maharashtra Chandrapur TPS MSPGCL U-8 50003/2015
U-9 500 08/2015
Maharashtra Koradi TPS Expn. MSPGCL U-10 66002/2016
U-8 660 03/2015
U-9 660 07/2015
Maharashtra Parli TPS Expn. MSPGCL U-8 25008/2015
MP Shree Singaji TPP MPGENCO U-3 660 07/2018
Phase-II
U-4 660 11/2018
Rajasthan Chhabra TPP Extn. RRVUNL U-5 66004/2017
U-6 660 10/2017
Rajasthan Suratgarh TPS RRVUNL U-7 660
04/2017
U-8 660 07/2017
Telangana Kakatiya TPS Extn T GENCO U-1 60002/2016
UP Anpara-D TPS UPRVUNL U- 6 500 03/2015
U-7 500 08/2015
WB Sagardighi TPS-II WBPDCL U-3 500 06/2015
U-4 500 09/2015
PRIVATE SECTOR
AP Simhapuri Energy Pvt Madhucon Projects Ltd. U-3 150 21.02.14
Ltd Ph-II U-4 150 03/2015
AP Thamminapatnam TPP-Meenaksha Energy Ltd. U-3 35008/2016
U-4 350 11/2016
Chhattisgarh Lanco Amarkantak TPS- LAP Pvt. Ltd. U-3 66006/2017
II
U-4 660 01/2018
Sector Project Name Impl. Unit Cap. Ant. comm
State Agency No. (MW) Date
Chhattisgarh Tamnar TPP ( Raigarh) O.P.Jindal U-1 60010.03.14
U-2 600 30.03.14
U-3 600 07.01.15
U-4 600 06/2015
Jharkhand Mata Shri Usha TPP-Ph- Corporate Power LtdU-3 27004/2018
II
U-4 270 08/2018
Maharashtra Amravati TPP Ph-II Ratan India Power Pvt U-1 27007/2017
Ltd.
U-2 270 10/2017
U-3 270 04/2018
U-4 270 07/2018
U-5 270 10/2018
Maharashtra Nasik TPP Ph-II Ratan India Nasik Power U-1 27005/2017
Pvt Ltd.
U-2 270 09/2017
U-3 270 02/2018
U-4 270 06/2018
U-5 270 10/2018
Total : 28071