GOVERNMENT OF INDIA MINISTRY OF POWER LOK SABHA UNSTARRED QUESTION NO 1627 ANSWERED ON 05.03.2015 COMPLETION OF POWER PROJECTS 1627 . S.R. Shri Vijay Kumar Will the Minister of POWER be pleased to state:- (a) the details of power projects undertaken in the country during Eleventh and Twelfth Plan with their capacity including current their status alongwith the steps taken to complete the projects under construction, State/UT/project-wise; (b) the State/UT-wise details of projects whose capacity is proposed to be increased along with the action taken by the Government in this regard; and (c) whether the Government intends to undertake more power projects in near future and if so, the details thereof? ANSWER THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL AND NEW & RENEWABLE ENERGY

Upload: lynguyet

Post on 13-Mar-2018

213 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

GOVERNMENT OF INDIA

MINISTRY OF POWER

LOK SABHA

UNSTARRED QUESTION NO 1627

ANSWERED ON 05.03.2015

COMPLETION OF POWER PROJECTS

1627 . S.R. Shri Vijay Kumar

Will the Minister of POWER be pleased to state:-

(a) the details of power projects undertaken in the country during Eleventh and Twelfth Plan with their capacity including current their status alongwith the steps taken to complete the projects under construction, State/UT/project-wise;

(b) the State/UT-wise details of projects whose capacity is proposed to be increased along with the action taken by the Government in this regard; and

(c) whether the Government intends to undertake more power projects in near future and if so, the details thereof?

ANSWER

THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL AND NEW & RENEWABLE ENERGY

( SHRI PIYUSH GOYAL )

(a) : State/Union Territory (UT)/Project-wise details of power projects taken up during the Eleventh and Twelfth Plan are placed at Annex-IA for thermal projects and Annex-IB for hydro projects. To ensure timely completion of these projects, regular monitoring is done by the Central Electricity Authority (CEA)

Page 2: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

through frequent site visit, and interaction with developers and equipment suppliers. A Power Project Monitoring Panel (PPMP) has also been set up to monitor the hydro and thermal generation projects along with the associated transmission system. Regular reviews are taken at various levels, including joint review by Secretary (Power) and Secretary (Heavy Industry) to identify the problem areas and facilitate expeditious resolution of outstanding issues.

(b) : Extension units aggregating 28,071 Mega Watt (MW) are being installed to increase the station capacity of 30 thermal power stations. The State/UT /Project-wise details are at Annex-II.

(c) : To take up power projects in the near future, CEA has prioritized 166 thermal projects aggregating 1,91,621.4 MW for Coal linkage. CEA has also accorded concurrence to 41 hydro power projects aggregating 26,332 MW.

ANNEXURE

 

ANNEX-IA

 

ANNEX REFERRED TO IN REPLY TO PART (a) OF UNSTARRED QUESTION NO.1627 TO BE ANSWERED IN THE LOK SABHA ON 05.03.2015.

State/UT/Project-wise details of Thermal Power Projects taken of during the Eleventh and Twelfth Plan

State Project Name

Order/ Zero Date

Implementing Agency

Unit No

Capacity (MW)

Actual(A)/ Anticipated Date of Commission-ing

Brief Status

CENTRAL SECTOR

           

Assam

Bongaigaon TPP

02/2008

NTPC U-1

250 06/2015

HT done in 01/11 & BLU done on 29/11/14. EDTA completed on 29/12/14. SBO started

Page 3: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

in 01.03.15. TG erection started in 3/11/14& boxed up in 01/15. Oil flushing started on 16/01/15. Civil contract was terminated due to very slow progress of work. Now for the balance civil and structural works NTPC has placed order on NBCC on 29/09/14.

        U-2

250 16-17 Boiler Drum lifted in 10/10. HT done in 04/12.

        U-3

250 16-17 Boiler Drum lifted on 25/2/13. HT done on 21/03/14.

Bihar Barh STPP-II

11/2008

NTPC U-4

660 30/11/13(A)

Commissioned

        U-5

660 03/2015

Boiler erection started in 2/10 & HT done in 11/13. BLU completed in 6/14 & SBO in 01/15 . TG erection started in 12/11 & boxed up in 04/14. TG put on barring gear. Synchronized on 01.03.15.

Bihar New Nabi Nagar TPP

01/2013

NTPC U-1

660 06/2017

Boiler erection started in 06/14.

        U-2

660 09/2017

Boiler erection started on 29/11/14.

        U-3

660 01/2018

Boiler erection is to start shortly.

Bihar Muzaffarpur TPP Exp

04/2010

NTPC U-3

195 03/2015

HT done on 25/02/13 & BLU completed on 08/11/14. SBO completed. TG erection started on 29/01/13 & boxed up in 09/14. TG oil

Page 4: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

flushing in progress.         U-

4 195 12/201

5 HT done on 04/08/13. TG erection started in 09/13.

Bihar Nabi Nagar TPP

01/2008

NTPC U-1

250 12/2015

Drum Lifted in 10/12 & HT done on 11/04/14.TG erection started in 01/14.

        U-2

250 12/2016

Drum lifted on 03/13.

        U-3

250 06/2016

Drum lifted on 10/06/13.

        U-4

250 06/2017

Boiler erection started on 7/12/12. Drum lifted on 16/9/13.

Chhattisgarh

Lara STPP 12/2012

NTPC U-1

800 11/2016

Boiler erection started in 12/13.

        U-2

800 05/2017

Boiler erection started in 04/14.

Haryana

Indira Gandhi TPP

07/2007

APCPL U-1

500 31/10/10(A)

Commissioned

        U-2

500 05/11/11(A)

Commissioned

        U-3

500 07/11/12(A)

Commissioned

Jharkhand

BokaroTPS "A"Exp.

06/2008

DVC U-1

500 12/2015

HT done on 10/12/13. BLU done on 28/9/14. SBO started on 30.02.15. TG erection started in 10/12 & boxed up in 30/06/14. Oil flushing started on 6/9/14 and is in progress.

Jharkhand

North Karanpura TPP

02/2014

NTPC U-1

660 02/2018

Order for EPC contract placed on BHEL (except external CHP, Make up water system and Ash dyke) in 02/14.

        U-2

660 08/2018

 

        U-3

660 02/2019

 

Page 5: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Jharkhand

Koderma TPP

06/2007

DVC U-1

500 20/07/11(A)

Commissioned

        U-2

500 15/02/13(A)

Commissioned

Karnataka

Kudgi STPP Ph-I

02/2012

NTPC U-1

800 05/2016

Boiler erection started on 04.05.13 & HT done on 01/15. TG erection started in 06/14.

        U-2

800 09/2016

Boiler erection started in 20/08/13.

        U-3

800 05/2017

Boiler erection started in 09/13.

Maharashtra

Mouda TPP

09/2008

NTPC U-1

500 19/04/12(A)

Commissioned

        U-2

500 29/03/13(A)

Commissioned

Maharashtra

Solapur STPP

04/2012

NTPC U-1

660 05/2017

Boiler erection started on 7/5/13. TG erection started in7/14.

        U-2

660 11/2017

Boiler erection started on 29/09/13. HT expected in 01/16.

MP Vindhyachal TPP-IV

02/2009

NTPC U-11

500 14/06/12(A)

Commissioned

        U-12

500 22/03/13(A)

Commissioned

MP Gadarwara STPP

03/2013

NTPC U-1

800 06/2017

Boiler erection started in 06/14.

        U-2

800 12/2017

Boiler erection started on 30/11/14.

MP Vindhyachal TPP-V

05/2012

NTPC U-13

500 10/2015

Boiler erection started in 06/13. Drum lifted in 11/13 & HT done in 08/14. TG erection started in 04/14 & boxed up in 01/15.

Orissa Darlipali STPP

02/2014

NTPC U-1

800 02/2018

 

        U-2

800 06/2018

 

TN Tuticorin JV

01/2009

NLC U-1

500 03/2015

Drum lifted on 29/09/11& HT done on 28/09/12. BLU done

Page 6: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

on 19/03/14 & SBO completed on 19/06/14. TG erection started on 29/09/12 & boxed up on 23/10/13. Oil flushing completed on 06/06/14. Valve floating in 12/16. SVF completed. The unit was synchronized on 18.02.15.

        U-2

500 06/2015

Drum lifted on 22/09/11 &. HT done on 09/11/12. BLU completed on 23/09/14. SBO completed on 28/02/15. TG erection started on 29/04/13 & boxed up on 11/04/14. Oil flushing completed on 05/12/14.

TN Vallur TPP Ph I

08/2007

NTECL U-1

500 28/03/12(A)

Commissioned

        U-2

500 28/02/13(A)

Commissioned

TN Vallur TPP-II

07/2009

NTECL U-3

500 28/02/14(A)

Commissioned

Tripura Monarchak CCPP

07/2010

NEEPCO GT 61.3

05/2015

Erection of all major equipments completed. Gas turbine is ready for Synchronization in open cycle. GTG final cranking done on 24.02.15. Erection of STG, HRSG, BFP DM plant etc. are in progress. Main chimney is ready. Gas supply made available at site on 04/02/15 by ONGC and commissioning activities are in

Page 7: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

progress.         ST 39.

7 07/201

5  

Tripura Tripura Gas

06/2008

OTPC Module-1

363.3

03/01/13(A)

Commissioned

        Module-2

363.3

16/11/14(A)

Commissioned

Tripura Agartala CCPP

09/2012

NEEPCO ST-1

25.5

06/2015

Erection work in HRSGs, STGs, Chimneys etc. are in progress. ST-2 synchronized on 10/2/15 and resynchronised on 17/2/15 & achieved a load of 10.3 MW. HRSG-4 pipe leakage repair work is in progress.

        ST-2

25.5

03/2015

 

UP Rihand STPS- III

01/2009

NTPC U-5

500 25/05/12(A)

Commissioned

        U-6

500 07/10/13(A)

Commissioned

UP Meja STPP

04/2012

JV of NTPC & UPRVUN

L

U-1

660 05/2017

Boiler erection started in 06/13 . TG erection started in 09/14.

        U-2

660 11/2017

Boiler erection started on 30/06/14.

UP Tanda TPS -II

09/2014

NTPC U-1

660 05/2018

Order for Boiler placed on L&T - Mitshubhishi and TG on Alstom- Bharat Forge.

        U-2

660 11/2018

 

UP Unchahar TPS St-IV

08/2013

NTPC U-6

500 11/2017

 

WB Durgapur Steel TPS

07/2007

DVC U-1

500 29/07/11(A)

Commissioned

Page 8: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

        U-2

500 23/03/12(A)

Commissioned

WB Raghunathpur TPP, Ph-I

12/2007

DVC U-1

600 24/08/14(A)

Commissioned

        U-2

600 08/2015

HT done on 25/05/12. TG erection started in 09/13 & boxed up on 20/09/14. Oil flushing is in progress. NDCT-1 Interconnection work completed mechanical work is in progress. Work on water corridor and Ash pond is very slow due to frequent disruption by locals.

WB Raghunathpur TPP Ph-II

09/2012

DVC U-1

660 10/2018

Order placed on BHEL for STG and on BGR for SG. Boiler foundation work is in progress but progress is slow due to fund problem in DVC.

        U-2

660 03/2019

Order placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC.

STATE SECTOR             AP Damoda

ram Sanjeevaiah TPS

06/2008

APPDL U-1

800 28/08/14(A)

Commissioned

        U-2

800 03/2015

Boiler erection started in 04/11. HT done & BLU completed in 06/14. Boiler EDTA completed and SBO completed on 20/11/14. TG erection started in 07/12 and boxed up in 11/13.

Page 9: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Synchronized on 16/12/2014. Coal firing done on 11/02/15. 255 MW load achieved.

AP Rayalseema St-IV U-6

10/2010

APGENCO

U-6

600 12/2016

Boiler erection started on 04/02/13. Drum lifted on 30/11/13. HT completed on 30/11/14. TG raft casting completed. BOPs civil works are lagging behind schedule.

AP Rayalseema TPP St-III

06/2007

APGENCO

U-5

210 31/12/10(A)

Commissioned

Assam Namrup CCGT

02/2009

APGCL GT 70 03/2016

HRSG work started in 01/12. GT placed on foundation. Order on NBPPL terminated. Order for balance civil work placed on 13/03/14 and work started on 05/5/14. BHEL again engaged NBPPL for balance work of EPC package on 22/11/14.

        ST 30 06/2016

 

Bihar Barauni TPS Extn

03/2011

BSEB U-1

250 11/2015

Boiler drum lifted in 06/13 & HT done on 21/08/14. BLU expected in 04/15. TG erection is in progress.

        U-2

250 02/2016

Boiler drum lifted in 09/13 and HT done on 21/09/14.

Chhattisgarh

Korba West St-III.

04/2008

CSPGCL U-5

500 22/03/13(A)

Commissioned

Chhattisgarh

Marwa TPP

04/2008

CSPGCL U-1

500 30/03/14(A)

Commissioned

        U- 500 03/201 HT done on 06.09.12.

Page 10: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

2 5 BLU completed on 08.05.14. HBO completed 03.10.14.TG box up completed. TG put on barring gear on 16.01.15.

Delhi Pragati CCGT - III

05/2008

PPCL GT-1

250 24/10/10(A)

Commissioned

        GT2

250 16/02/11(A)

Commissioned

        GT-3

250 27/06/12(A)

Commissioned

        GT-4

250 07/05/13(A)

Commissioned

        ST-1

250 29/02/12(A)

Commissioned

        ST-2

250 26/02/14(A)

Commissioned

Gujarat Bhavnagar CFBC TPP

02/2010

Bhavnagar

Energy

U-1

250 06/2015

Boiler drum lifted in 06/12. HT done on 01/06/13 & BLU completed on 28.02.15.TG oil flushing is in progress. ST charged on 25/1/15. TG erection started in 06/13 & boxed up on 27/06/14. Oil flushing is in progress.

        U-2

250 09/2015

Boiler drum lifted on 12/10/12. HT done on 21/6/14. TG erection started in 08/13 & boxed up on 26/12/14. TG oil flushing in progress.

Gujarat

Dhuvaran CCPP-III

03/2011

GSECL Block-1

376.1

21/05/14(A)

Commissioned

Gujarat

Hazira CCPP Extn.

12/2007

GSECL GT+ST

351

18/02/12(A)

Commissioned

Page 11: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Gujarat

Pipavav CCPP

03/2008

GSECL Block-1

351

05/02/14(A)

Commissioned

        Block-2

351

27/03/13(A)

Commissioned

Gujarat

Sikka TPS Extn.

05/2007

GSECL U-3 250

03/2015

Boiler erection started on 24/10/11. Drum lifted on 29/03/12. HT completed in 03/13. BLU done on 22/03/14. SBO completed on 29/12/14. TG erection started on 15/01/13 and boxed up on 06/6/14. Synchronized on oil on 09/2/15.

        U-4 250

07/2015

Boiler erection started on 09/01/12 and drum lifted on 23/05/12. HT completed on 30/06/13 & BLU done on 18/10/14. TG erection started in 01/13 & boxed up on 14/03/14. Oil flushing is in progress.

Gujarat

Ukai TPP Extn.

09/2007

GSECL U-6 500

05/03/13(A)

Commissioned

Gujarat

Utran CCPP Extn

04/2007

GSECL GT 240

08/08/09(A)

Commissioned

        ST 134

10/10/09(A)

Commissioned

Gujarat

Wankbori TPS Extn

10/2014

GSECL U-8 800

10/2018

EPC contract awarded to BHEL on 21.10.14. Topographical and soil investigation of BTG area completed.

Karnataka

Bellary TPP St-III

09/2010

KPCL U-3 700

09/2015

Boiler erection started on 26/11/12 and HT completed on 30/11/14. Non drainable HT done on 02/02/15 . Condenser

Page 12: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

and TG erection started on 12/11/13 .

Karnataka

Yermarus TPP

04/2010

KPCL U-1 800

11/2015

Boiler erection started on 29/10/12. HT done on 10/09/14.TG erection started on 14.01.14.

        U-2 800

03/2016

Boiler erection started in 12/12. TG erection started on 31/05/14.

Maharashtra

Chandrapur TPS

07/2008

MSPGCL

U-8 500

03/2015

Boiler erection started in 03/11. HT done in 06/12 & BLU done on 30/3/14. SBO completed on 17/10/14 & normalized in 11/14. TG erection started in 03/12 & boxed up on 30/06/14. TG put on barring gear on 15/12/14. Synchronization done with oil on 11/01/15.

        U-9 500

08/2015

Boiler drum lifted in 09/11. HT completed on 29/10/12 . TG erection started on 14/11/13 .

Maharashtra

Koradi TPS Expn.

09/2009

MSPGCL

U-8 660

03/2015

Boiler erection started in 03/11 & HT completed in 06/13. BLU completed in 09/14. SBO completed on 11/02/15. TG erection started in 04/12 & boxed up in 06/13. TG put on Barring Gear on 31/03/14. Synchronization on 25.02.15.

        U-9 660

07/2015

HT completed on 04/01/14. TG erection started in 11/12 & boxed up in 05/14.

Page 13: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

        U-10 660

02/2016

Boiler erection started in 02/12 and HT done in 07/14. TG erection started in 06/13.

Maharashtra

Parli TPS Expn.

01/2009

MSPGCL

U-8 250

08/2015

Drum lifted in 04/11. HT completed in 12/12. TG erection started in 04/12.

MP Malwa TPP (Shree Singa ji TPP)

12/2008

MPGENCO

U-1 600

18/11/13(A)

Commissioned

MP Malwa TPP (Shree Singa ji TPP)

12/2008

MPGENCO

U-2 600

15/10/14(A)

Commissioned

MP Satpura TPS Extn

03/2008

MPPGCL

U-10 250

22/03/13(A)

Commissioned

        U-11 250

25/12/13(A)

Commissioned

MP Shree Singaji TPP Phase-II

09/2014

MPGENCO

U-3 660

07/2018

Order placed on M/s. L&T on 04/09/14.

        U-4 660

11/2018

 

Rajasthan

Chhabra TPS Extn

08/2008

RRVUNL

U-3 250

14/09/13(A)

Commissioned

        U-4 250

30/06/14(A)

Commissioned

Rajasthan

Kalisindh TPP

07/2008

RRVUNL

U-1 600

02/05/14(A)

Commissioned

        U-2 600

03/2015

HT done on 15/12/11. BLU done & SBO completed on 14/11/14. TG erection started on 25/08/11 & boxed up. Oil flushing completed & TG put on barring gear on 29/10/14. Synchronised on 27.02.15.

Page 14: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Rajasthan

Ramgarh CCPP Extn. -III

07/2009

RRVUNL

GT 110

20/03/13(A)

Commissioned

        ST 50 01/05/14(A)

Commissioned

Rajasthan

Chhabra TPP Extn.

03/2013

RRVUNL

U-5 660

04/2017

Boiler erection started on 17/02/14. TG raft casting completed and Column casting is in progress.

        U-6 660

08/2017

Environment clearance obtained.

Rajasthan

Suratgarh TPS

05/2013

RRVUNL

U-7 660

04/2017

Boiler erection started on 26/03/14 & further work under progress.

        U-8 660

07/2017

Boiler erection started in 06/14.

Telangana

Kakatiya TPS Extn

10/2008

T GENCO

U-1 600

02/2016

Boiler erection started on 05/05/11. Drum lifted on 07/04/12. HT done on 24/06/13. TG erection started in 05/13.

Telangana

Singareni TPP

11/2011

Singareni

Collieries Co.

Ltd

U-1 600

11/2015

Boiler drum lifted on 12/09/13. HT done on 27/08/14. TG erection started on 16/08/14.

        U-2 600

03/2016

Boiler drum lifted on 14/12/13. HT done on 03/11/14. TG erection started.

TN Mettur TPP Ext

06/2008

TANGEDCO

U-1 600

11/10/12(A)

Commissioned

TN North Chennai Extn, U-2

08/2008

TANGEDCO

U-2 600

09/03/13(A)

Commissioned

TN North Chennai TPS Extn, U-1

02/2008

TANGEDCO

U-1 600

13/09/13(A)

Commissioned

Tripura Baramura GT Extn.

03/2008

TSECL U-5 21 03/08/10(A)

Commissioned

Tripura Rokhia 08/2 Govt.of GT-9 21 31/08/1 Commissioned

Page 15: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

CCPP 010 Ttipura 3(A) UP Anpara-D

TPS 10/2007

UPRVUNL

U- 6 500

03/2015

Boiler erection started on 02/08/10. HT done on 09/04/13. BLU done in 12/14. TG erection started on 15/03/13 and boxed up on 20/02/14. Oil flushing completion expected in 03/15.

        U-7 500

08/2015

Boiler erection started on 02/11/10. HT done on 03/07/13. TG erection started on 31/07/13 and boxed up in 07/14.

WB Durgapur TPS Extn U-8

07/2010

DPL U-8 250

31/03/14(A)

Commissioned

WB Sagardighi TPS-II

02/2011

WBPDCL

U-3 500

06/2015

Boiler erection started in 04/03/12. Drum lifted in 13/09/12. HT done on 31/08/13, BLU done on 30/01/15. SBO started on 01.03.15. TG erection started on 15/07/13 & boxed up in 07/14. Oil Flushing started in 01/15 and is in progress . Work in AHP & CHP is slow.

        U-4 500

09/2015

Boiler erection work is in progress. Drum lifted on 25/01/13. HT done on 21/03/14. TG erection started on 10/10/13. Work in AHP & CHP is slow.

PRIVATE SECTOR

           

AP Bhavanpadu TPP

09/2009

M/s East

Coast Energy

U-1 660

03/2017

Work was suspended due to MOEF order & due to site conditions. Work resumed at site

Page 16: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Ltd. from 04/12. Boiler erection started in 03/14. HT expected by 12/15. TG raft casted and column casting is in progress. Switchyard and CHP area are in progress. ESP erection started.

        U-2 660

10/2017

Boiler foundation work completed.Piling work in TG area is also completed.

AP Lanco Kondapalli Ph-II (GT)

11/2007

Lanco Kondap

alli

GT 233

05/12/09(A)

Commissioned

AP Lanco Kondapalli Ph-II (ST)

11/2007

Lanco Kondap

alli

ST 133

19/07/10(A)

Commissioned

AP Lanco Kondapalli CPP Expn. St.III

01/2010

Kondapalli

Power Pvt. Ltd.

Module-1

371

– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.

        Module-2

371

– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.

AP NCC TPP 02/2012

NCC Power Projects Ltd

U-1 660

04/2016

Boiler erection started on 10/05/13. TG erection started in 07/14.

        U-2 660

08/2016

Boiler erection started in 11/13. TG erection started in 12/14.

AP Painampuram TPP

09/2010

Thermal Power Tech

Corporation

U-1 660

07/02/15(A)

Commissioned

Page 17: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Ltd         U-2 66

0 06/201

5 Boiler erection started on 24/05/12. HT (Non-drainable) completed in 07/14. . TG erection started in 11/13.

AP Panduranga CCPP

05/2010

Panduranga Power

Ltd

Module-1

110.3

– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.

AP RVK Gas Engine

06/2010

RVK (Rajahmundry) Pvt.Ltd

GE: 5-8

38 – Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.

        GE:1-4

38 – Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.

AP RVKCCPP 07/2010

RVK (Rajahmundry) PVT.Ltd

Module-1

120

– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.

        Module-2

120

– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.

        Module-3

120

– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.

AP Samalkot CCPP-II

07/2010

Reliance

Power

Module-1

400

– Work held up due to non availability of Gas. Commissioning

Page 18: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

schedule would be assessed after restart of work.

        Module-2

400

– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.

        Module-3

400

– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.

        Module-4

400

– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.

        Module-5

400

– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.

        Module-6

400

– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.

AP Simhapuri Energy Pvt Ltd Ph-II

05/2010

Madhucon

Projects Ltd.

U-3 150

21/02/14(A)

Commissioned

AP Simhapuri Energy Pvt Ltd Ph-II

05/2010

Madhucon

Projects Ltd.

U-4 150

03/2015

Boiler erection started in 05/11. HT completed on 02/03/12. BLU completed in 10/14. SBO completed in 12/14.TG erection started on 01/02/12

Page 19: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

and boxed up on 08/13. TG put on barring gear. Synchronized on 30/12/14. Coal firing done on 16/02/15 and a load of 105 MW has been achieved.

AP Simhapuri Energy Pvt.Ltd Ph-I

01/2009

Madhucon

Projects Ltd

U-1 150

24/03/12(A)

Commissioned

        U-2 150

02/07/12(A)

Commissioned

AP Thamminapatnam TPP-I

08/2009

Meenakshi

Energy Pvt. Ltd

U-1 150

09/09/12(A)

Commissioned

        U-2 150

17/04/13(A)

Commissioned

AP Thamminapatnam TPP-II

12/2009

Meenaksha

Energy Ltd.

U-3 350

08/2016

Boiler erection started on 16/11/11. Boiler drum lifted on 16/05/14. HT expected in 04/15. TG civil works started in 07/11.

        U-4 350

11/2016

Boiler erection started on 22/09/14. TG civil works are in progress.

AP Vemagiri CCPP-II

09/2009

GMR Rajahmundry Energy

Ltd.

Block-I

384

– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.

        Block-II

384

– Work held up due to non availability of Gas. Commissioning schedule would be assessed after restart of work.

AP Vizag TPP

06/2010

Hinduja National Power

U-1 525

09/2015

Boiler drum lifted in 01/12. HT done on 28/12/12. BLU done in

Page 20: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Corp. Ltd

03/14. EDTA completed & SBO works affected due to cyclone. SBO re-start expected in 03/15. TG erection started on 25/07/12 & boxed up in 09/13. TG on barring gear since 08/14. Works has been affected due to hud-hud cyclone.

        U-2 525

12/2015

Boiler erection started in 09/11. HT done on 28/03/13. BLU done in 07/14. Condenser erection started on 23/11/12 and that of TG started on 04/03/13 .

Bihar Jas Infra TPP Ph-I

03/2011

JICPL U-1 660

– Civil works for boiler foundation completed and boiler erection started. TG raft casted. * No work is in progress. Commissioning schedule would be assessed after the restart of work.

        U-2 660

– Boiler foundation work was started. * No work is in progress. Commissioning schedule would be assessed after the restart of work.

        U-3 660

– Civil works yet to start. * Commissioning schedule would be assessed after the restart of work.

        U-4 660

– Civil works yet to start. * Commissioning schedule would be assessed after the

Page 21: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

restart of work. Chhattisgarh

Akaltara (Nariyara) TPP

04/2009

KSK Mahan

di Power Company Ltd

U-1 (3rd)

600

13/08/13(A)

Commissioned

        U-2 (4th)

600

22/08/14(A)

Commissioned

        U-3 (2nd

)

600

12/2015

Boiler erection started in 04/11. Boiler drum lifted on 29/04/12. Condenser & TG erection started in 02/15.

        U-4 (5th)

600

11/2016

Boiler erection started on 08/12/11.TG deck casted.

        U-5(1s

t)

600

03/2017

Boiler erection started on 06/02/12.

Chhattisgarh

Akaltara (Nariyara) TPP

04/2009

KSK Mahan

di Power Company Ltd

U-6 600

09/2017

 

Chhattisgarh

Avantha Bhandar TPP, U-1

04/2009

Korba West Power

Co. Ltd.

U-1 600

31/03/14(A)

Commissioned

Chhattisgarh

Badadarha TPP

06/2010

D.B. Power

Ltd

U-1 600

23/02/14(A)

Commissioned

        U-2 600

08/2015

Synchronized on 30/03/14.

Chhattisgarh

Balco TPP

08/2007

Bharat Aluminium Co.

Ltd

U-1 300

04/2015

Unit Synchronized on 22/05/12. Concerned to operate obtained.

        U-2 300

06/2015

Unit Synchronized on 06/09/11. Concerned to operate obtained.

Chhatti Bandakh 06/2 M/s U-1 30 03/201 Boiler drum lifted on

Page 22: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

sgarh ar TPP 011 Maurti Clean Coal & Power

Ltd

0 5 06/01/13. HT completed on 30/08/13 & BLU done on 22/ 09/14. SBO completed & Chemical cleaning completed on 17/8/14. TG boxed up on 22/02/14. Oil flushing completed.

Chhattisgarh

Binjkote TPP

03/2011

M/s SKS Power

Generation

(Chhattisgarh)

Ltd.

U-1 300

12/2015

Boiler Drum lifted in 05/13. HT completed on 20/06/14. TG erection started in 05/14.

        U-2 300

03/2016

Boiler Drum lifted in 05/13. HT done on 03/11/14. TG erection started in 09/14.

        U-3 300

– *Commissioning dates would be assessed after start of work at site.

        U-4 300

– *Commissioning dates would be assessed after start of work at site.

Chhattisgarh

Chakabura TPP

09/2011

ACB India

U-1 30 28/03/14(A)

Commissioned

Chhattisgarh

Deveri TPP (Visa TPP) Raigarh

06/2010

Visa Power

Ltd

U-1 600

– Boiler erection started on 30.09.11. * Work held up due to financial crunch.

Chhattisgarh

Kasaipalli TPP

11/2008

ACB India Ltd.

U-1 135

13/12/11(A)

Commissioned

        U-2 135

21/06/12(A)

Commissioned

Chhattisgarh

Katghora TPP

10/2007

Vandana

Energy & Steel

Ltd

U-1 35 14/02/12(A)

Commissioned

Chhatti Lanco 11/2 LAP U-3 66 – Boiler erection started

Page 23: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

sgarh Amarkantak TPS-II

009 Pvt. Ltd.

0 in 09/10. TG erection started on 5/12/11. Work held up due to financial constraint. * Commissioning schedule would be assessed after restart of work.

        U-4 660

– Boiler erection started in 12/10. Work held up due to financial constraint. * Commissioning schedule would be assessed after restart of work.

Chhattisgarh

Nawapara TPP (TRN Energy TPP)

01/2011

M/s TRN

Energy Pvt. Ltd.

U-1 300

01/2016

Boiler erection started in 01/10/12 & drum lifted on 28/02/13. HT completed on 28/3/14. Chemical cleaning is in progress. TG erection started in 05/14.

        U-2 300

04/2016

Boiler erection started in 05/13 & drum lifted on 21/09/13.

Chhattisgarh

Raikheda TPP

01/2010

GMR U-1 685

27/02/15(A)

Commissioned

        U-2 685

07/2015

Boiler erection started on 03/04/12. HT done in 30/07/14. TG erection started on 24/03/13 & boxed up on 31/10/14. Oil flushing completed on 10/12/2014.

Chhattisgarh

Ratija TPP

07/2009

Spectrum Coal

& Power

Ltd

U-1 50 04/02/13(A)

Commissioned

Chhattisgarh

Salora TPP

09/2009

M/s Vandan

a

U-1 135

10/04/14(A)

Commissioned

Page 24: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Vidyut         U-2 13

5 05/201

5 Boiler drum lifted in 04/11. HT done in 10/12 & BLU completed in 01/15. TG erection started in 11/11& boxed up.

Chhattisgarh

Singhitarai TPP

12/2009

Athena Chhattisgarh Power Ltd.

U-1 600

03/2016

Boiler erection started in 07/12. Drum lifted on 07/04/13. HT completed on 28.02.15. TG erection started in 07/13.

        U-2 600

08/2016

Boiler erection started in 10/12. Drum lifted on 30/10/13. TG erection started in 11/13.

Chhattisgarh

Swastic TPP

03/2010

M/s ACB

U-1 25 03/2015

SBO started on 01/02/15. TG boxed up on 10/03/13.

Chhattisgarh

Tamnar TPP (Raigarh)

12/2008

O.P.Jindal

U-1 600

10/03/14(A)

Commissioned

        U-2 600

30/03/14(A)

Commissioned

        U-3 600

07/01/15(A)

Commissioned

        U-4 600

06/2015

Boiler erection started. Drum lifted on 18/10/13. SBO start expected in 03/15. Consent to operate has been received. TG on barring gear by 15.03.15.

Chhattisgarh

Uchpinda TPP

07/2007

RKM Powergen Pvt.

Ltd

U-1 360

04/2015

Drum lifted on 24/04/12. HT done in 09/13. BLU done on 08/11/14. SBO completed in 01/15. TG erection started in 09/13 & boxed up in 07/14. TG oil flushing completed in 07/14 TG

Page 25: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

put on BG in 1/15 & synchronized on 28.02.15.

        U-2 360

07/2015

Drum lifted on 07/05/12. HT done in 12/13. BLU completed on 05/02/15. TG erection started in 03/14 & boxed up in 01/15.

        U-3 360

12/2015

Boiler erection started on 12/01/12. Drum lifted on 18/08/12. HT done in 01/14. TG erection started in 10/14. oil flushing completion expected in 06/15.

        U-4 360

04/2016

Boiler erection started on 30/04/12. Drum lifted on 30/12/12. HT done on 20/01/15. TG erection started in 11/14.

Delhi Rithala CCPP

05/2008

NDPL GT-1 35.75

09/12/10(A)

Commissioned

        GT-2 35.75

04/10/10(A)

Commissioned

        ST 36.5

04/09/11(A)

Commissioned

Gujarat

DGEN Mega CCPP

07/2010

Torrent Energy

Ltd

Module-1

400

12/01/14(A)

Commissioned

        Module-2

400

23/04/14(A)

Commissioned

        Module-3

400

09/03/14(A)

Commissioned

Gujarat

Mundra TPP Ph-II

09/2007

Adani Power

Ltd

U-1 660

26/12/10(A)

Commissioned

Gujarat

Mundra TPP Ph-II

09/2007

Adani Power

Ltd

U-2 660

20/07/11(A)

Commissioned

Gujarat

Mundra TPP Ph-III

01/2008

Adani Power

U-1 660

07/11/11(A)

Commissioned

Page 26: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Ltd         U-2 66

0 03/03/1

2(A) Commissioned

        U-3 660

09/03/12(A)

Commissioned

Gujarat

Mundra UMTPP

08/2007

Tata Power

Co.

U-1 800

25/02/12(A)

Commissioned

        U-2 800

25/07/12(A)

Commissioned

        U-3 800

16/10/12(A)

Commissioned

        U-4 800

16/01/13(A)

Commissioned

        U-5 800

18/03/13(A)

Commissioned

Gujarat

Salaya TPP

09/2009

Essar Power

Gujarat Ltd.

U-1 600

22/02/12(A)

Commissioned

        U-2 600

13/06/12(A)

Commissioned

Gujarat

Unosugen Mega CCPP

07/2010

Torrent Energy

Ltd

Module-1

382.5

20/01/13(A)

Commissioned

Haryana

Jajjar TPP (Mahatama Gandhi TPP)

03/2009

CLP Power India

Pvt. Ltd

U-1 660

12/01/12(A)

Commissioned

        U-2 660

11/04/12(A)

Commissioned

Jharkhand

Mahadev Prasad TPP Ph-I

05/2009

Adhunik Power Co.Ltd

U-1 270

19/11/12(A)

Commissioned

        U-2 270

29/03/13(A)

Commissioned

Jharkhand

Maithon RB TPP

10/2007

DVC U-1 525

30/06/11(A)

Commissioned

        U-2 525

23/03/12(A)

Commissioned

Jharkhand

Mata shri Usha TPP-Ph-I

12/2009

M/s Corpor

ate Power

U-1 270

– HT completed. TG boxed up in 10/12. Work held up due to payment issue with

Page 27: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Ltd BHEL.         U-2 27

0 – Drum lifted & Boiler

erection in progress. Work held up due to payment issue with BHEL.

Jharkhand

Mata Shri Usha TPP-Ph-II

03/2011

Corporate

Power Ltd

U-3 270

– Boiler drum lifted in 11/11. TG erection started in 10/12. Work held up due to payment issue with BHEL.

        U-4 270

– Boiler drum lifted in 04/12. Work held up due to payment issue with BHEL.

Jharkhand

Tori TPP 08/2008

Essar Power

U-1 600

04/2017

Boiler erection started in 04/12.

        U-2 600

10/2017

Boiler erection started in 06/12.

Maharashtra

Amravati TPP Ph-I

11/2009

Ratan India Power

Pvt Ltd.

U-1 270

25/03/13(A)

Commissioned

        U-2 270

17/02/14(A)

Commissioned

        U-3 270

29/01/15(A)

Commissioned

Maharashtra

Amravati TPP Ph-I

11/2009

Ratan India Power

Pvt Ltd.

U-4 270

03/2015

Drum lifted in 11/11. HT completed in 03/13. BLU completed in 12/14.SBO completed on 28/01/15 & normalisation is under progress. TG erection started in 02/12 & boxed up in 11/14. TG put on barring gear on 02/12/14.

        U-5 270

09/2015

Drum lifted in 01/12. HT done on 11/14. TG erection started in 11/12.

Page 28: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Maharashtra

Amravati TPP Ph-II

10/2010

Ratan India Power

Pvt Ltd.

U-1 270

– * No work is going on at site.

        U-2 270

        U-3 270

        U-4 270

        U-5 270

Maharashtra

Bela TPP-I

12/2008

IEPL U-1 270

20/03/13(A)

Commissioned

Maharashtra

Butibori TPP Ph-II

12/2009

Vidarbha

Industries

Power

U-1 300

17/08/12(A)

Commissioned

        U-2 300

31/03/14(A)

Commissioned

Maharashtra

Dhariwal Infracture TPP

04/2010

Dhariwal

Infrastructure (P)

Ltd

U-1 300

03/11/13(A)

Commissioned

        U-2 300

28/05/14(A)

Commissioned

Maharashtra

EMCO Warora TPP

09/2009

EMCO Energy

Ltd.(GMR)

U-1 300

07/02/13(A)

Commissioned

        U-2 300

27/08/13(A)

Commissioned

Maharashtra

GEPL TPP 04/2009

GEPL U-1 60 08/09/12(A)

Commissioned

        U-2 60 28/04/12(A)

Commissioned

Maharashtra

JSW Ratnagiri TPP

07/2007

JSW Energy(Ratnagir

i) Ltd

U-1 300

24/08/10(A)

Commissioned

        U-2 300

09/12/10(A)

Commissioned

        U-3 30 06/05/1 Commissioned

Page 29: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

0 1(A)         U-4 30

0 08/10/1

1(A) Commissioned

Maharashtra

Lanco Vidarbha TPP

11/2009

Lanco Vidarbh

a

U-1 660

– Boiler erection started in 8/11. Work held up due to financial constraint.

        U-2 660

– Boiler erection started in 12/11. Work held up due to financial constraint

Maharashtra

Mangaon CCPP

12/2011

PGPL Block-1

388

– Work held up.

Maharashtra

Mihan TPS

05/2008

Abhijeet MADC

Nagpur Energy Pvt Ltd

U-1 61.5

09/02/12(A)

Commissioned

        U-2 61.5

09/02/12(A)

Commissioned

        U-3 61.5

09/02/12(A)

Commissioned

Maharashtra

Mihan TPS

05/2008

Abhijeet MADC

Nagpur Energy Pvt Ltd

U-4 61.5

09/02/12(A)

Commissioned

Maharashtra

Nasik TPP Ph-I

11/2009

Ratan India Nasik Power

Pvt Ltd.

U-1 270

25/02/14(A)

Commissioned

        U-2 270

03/2015

Drum lifted in 07/11. HT completed in 07/12 & BLU completed in 11/13. EDTA completed on 05/01/14. SBO completed on 14/03/14. TG erection started in 12/11 & boxed up in 01/14. TG put on barring gear in 04/14.

        U-3 27 06/201 Boiler drum lifted in

Page 30: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

0 7 12/11. TG erection started in 04/12. No work is going on at site.

        U-4 270

11/2017

Drum lifted in 12/11. TG erection started in 07/12. No work is going on at site.

        U-5 270

03/2018

Drum lifted in 03/12. TG erection started in 09/12. No work is going on at site.

Maharashtra

Nasik TPP Ph-II

11/2009

Ratan India Nasik Power

Pvt Ltd.

U-1 270

– No work is going on at site.

        U-2 270

        U-3 270

        U-4 270

        U-5 270

Maharashtra

Tirora TPP Ph-I

02/2008

Adani Power

Ltd

U-1 660

11/09/12(A)

Commissioned

        U-2 660

25/03/13(A)

Commissioned

Maharashtra

Tirora TPP Ph-II

02/2008

Adani Power

Ltd

U-1 660

10/06/13(A)

Commissioned

        U-2 660

23/03/14(A)

Commissioned

        U-3 660

25/09/14(A)

Commissioned

Maharashtra

Wardha Warora TPP

05/2007

WPCL U-1 135

05/06/10(A)

Commissioned

        U-2 135

10/10/10(A)

Commissioned

        U-3 135

13/01/11(A)

Commissioned

        U-4 13 30/04/1 Commissioned

Page 31: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

5 1(A) MP Anuppur

TPP Ph-I 11/2010

MB Power

MP

U-1 600

03/2015

Boiler drum lifted on 06/11/12. HT done in 10/13. BLU done in 9/14. TG erection started in 05/13 & boxed up in 09/14.

        U-2 600

07/2015

Boiler erection started in 02/12. Boiler drum lifted in 06/13. HT done on 31/03/14. TG erection started in 12/13.

MP Bina TPP 09/2008

Bina Power Supply Co. Ltd

U-1 250

12/08/12(A)

Commissioned

        U-2 250

31/03/13(A)

Commissioned

MP Gorgi TPP ( DB Power)

03/2011

D.P Power ( MP) Ltd

U-1 660

  Order for main plant equipment has not been placed so far. Erection yet to start.

MP Mahan TPP

09/2008

Essar Power MP Ltd

U-1 600

24/02/13(A)

Commissioned

        U-2 600

06/2015

HT done in 2/12.

MP Nigri TPP 08/2009

Jaiprakash

Power Venture

s Ltd

U-1 660

29/08/14(A)

Commissioned

        U-2 660

17/02/15(A)

Commissioned

MP Niwari TPP

04/2011

BLA Power

Ltd

U-1 45 10/12/13(A)

Commissioned

        U-2 45 2015-16

Boiler erection started in 01/13. Drum lifted in 09/13.

MP Sasan UMPP

06/2008

Reliance Power Ltd.

U-1 660

21/05/14(A)

Commissioned

        U-2 66 18/12/1 Commissioned

Page 32: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

0 3(A)         U-3 66

0 30/05/1

3(A) Commissioned

        U-4 660

25/03/14(A)

Commissioned

        U-5 660

24/08/14(A)

Commissioned

        U-6 660

03/2015

Unit synchronized on 01/02/15.

MP Seioni TPP Ph-I

02/2010

Jhabua Power

Ltd

U-1 600

08/2015

Boiler erection started in 04/11. Drum lifted in 01/12. HT done on 26/12/12. BLU completed in 12/03/14. SBO expected in 03/15. TG erection started in 11/11. TG boxed up in 12/13. Oil Flushing started in 11/14.Presently work is in progress with very slow pace.

Orissa Derang TPP

07/2009

JITPL U-1 600

10/05/14(A)

Commissioned

        U-2 600

24/01/15(A)

Commissioned

Orissa Ind Bharat TPP ( Orissa)

05/2009

Ind. Bharat

U-1 350

06/2015

HT done on 24/05/12. BLU done in 01/15. TG erection started in 05/12 & boxed up on 21/05/14. Oil flushing completed on 14/01/15.

        U-2 350

09/2015

Boiler drum lifted in 12/11 & HT done on 20/05/14. TG erection started in 9/12

Orissa Kamalanga TPP

06/2009

GMR U-1 350

28/03/13(A)

Commissioned

        U-2 350

28/09/13(A)

Commissioned

        U-3 350

21/03/14(A)

Commissioned

Orissa KVK 11/2 KVK U-1 35 02/201 Hon'ble High Court of

Page 33: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Nilanchal TPP

009 Nilachal 0 7 Odisha has cleared the case. Now the project authority is mobilizing various contractors for restarting works at site.

        U-2 350

2017-18

        U-3 350

2017-18

Orissa Lanco Babandh TPP

11/2009

Lanco Babandh Power

Ltd

U-1 660

– Boiler erection started in 05/11. TG deck casting completed. Work held up due to financial constraint.

        U-2 660

– Boiler structure erection started in 09/11. TG deck column casting completed. Work held up due to financial constraint.

Orissa Malibrahmani TPP ( Monnet Ispat)

06/2010

MPCL U-1 525

12/2015

Boiler erection started in 18/08/11. Boiler drum lifted on 21/03/12. HT done on 03/04/13.TG erection started on 28/01/13. Progress is very slow. BHEL stopped work at site due to financial issues.

Orissa Malibrahmani TPP ( Monnet Ispat)

06/2010

MPCL U-2 525

03/2016

Boiler erection started in 10/10/11. Boiler drum lifted on 21/07/12.

Punjab Goindwal Sahib TPP

08/2008

GVK Power

U-1 270

10/2015

Unit synchronized on 06/07/13. No further progress due to financial problem.

        U-2 270

02/2016

Unit synchronized on 04/03/14. No further progress due to financial problem.

Punjab Rajpura TPP (Nabha)

07/2010

Nabha Power

Ltd

U-1 700

24/01/14(A)

Commissioned

        U-2 70 06/07/1 Commissioned

Page 34: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

0 4(A) Punjab Talwandi

Sabo TPP 07/2009

M/s Sterlite

U-1 660

17/06/14(A)

Commissioned

        U-2 660

03/2015

Boiler erection started on 25/06/11. HT done on 11/3/14. BLU completed on 26/11/14. SBO completed on 30/11/14. TG erection started in 15/03/13 & boxed up in 05/14. Oil flushing completed in 10/09/14. Unit synchronized in 01/15.

        U-3 660

07/2015

Boiler erection started on 25/12/11. HT done on 28/05/14. TG erection started on 08/04/13. TG boxed up in 05/14.

Rajasthan

Kawai TPP

04/2010

Adani Power Ltd.

U-1 660

28/05/13(A)

Commissioned

        U-2 660

24/12/13(A)

Commissioned

TN Melamaruthur TPP

08/2009

Coastal Energen

U-1 600

02/12/14(A)

Commissioned

        U-2 600

07/2015

HT done in 07/13. TG erection started in 12/11.

TN Tuticorin TPP (Ind- Barath TPP)

05/2010

IBPIL U-1 660

09/2017

Boiler foundation completed & erection started in 08/14. TG raft completed. Column casting is in progress.

TN Tuticorin TPP-II(Ind barath)

12/2009

Ind Barath

U-1 150

10/03/13(A)

Commissioned

        U-2 150

30/12/13(A)

Commissioned

UP Anpara-C 11/2007

Lanco Anpara

U-1 600

15/11/11(A)

Commissioned

Page 35: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Power Pvt. Ltd.

        U-2 600

12/11/11(A)

Commissioned

UP Barkhera TPP

12/2009

Bajaj Energy Pvt. Ltd

U-1 45 06/11/11(A)

Commissioned

        U-2 45 28/01/12(A)

Commissioned

UP Khamberkhera TPP

12/2009

Bajajb Energy Pvt. Ltd

U-1 45 17/10/11(A)

Commissioned

        U-2 45 28/11/11(A)

Commissioned

UP Kundarki TPP

12/2009

Bajaj Energy Pvt. Ltd

U-1 45 10/01/12(A)

Commissioned

        U-2 45 29/02/12(A)

Commissioned

UP Lalitpur TPP

03/2011

Lalitpur power

Generation Co.

Ltd

U-1 660

03/2015

Boiler erection started on 23/03/12. HT done on 12/3/14. BLU done in 01/15. TG erection started on 15/12/13 & boxed up in 12/14.

        U-2 660

07/2015

Boiler erection started on 30/07/12 . HT done in 20/6/14.TG erection started on 10/3/14.

        U-3 660

06/2016

Boiler erection started on 27/11/12. TG deck casting completed.

UP Maqsoodpur TPP

12/2009

Bajaj Energy Pvt Ltd

U-1 45 03/11/11(A)

Commissioned

        U-2 45 21/01/12(A)

Commissioned

UP Prayagraj (Bara ) TPP

10/2009

Prayagraj power

Gen. Co.Ltd

(J.P. Power

Venture

U-1 660

10/2015

Boiler erection started on 12/07/11. HT done on 24/10/13. TG erection started in 01/13 & boxed up in 02/14.

Page 36: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

s)         U-2 66

0 01/201

6 Boiler erection started on 12/09/11. HTdone in 12/14. TG erection started in 10/13.

        U-3 660

04/2016

Boiler erection started on 05/09/11. HT done in 11/14.

UP Rosa TPP Ph-II

03/2008

Reliance Power Ltd.

U-3 300

27/12/11(A)

Commissioned

        U-4 300

28/03/12(A)

Commissioned

UP Utrala TPP

12/2009

Bajaj Energy Pvt. Ltd

U-1 45 21/02/12(A)

Commissioned

        U-2 45 19/03/12(A)

Commissioned

Uttarakhand

Beta CCPP

12/2010

BIPL GT+ST

225

– Work held up due to non availability of Gas.

Uttarakhand

Gama CCPP

07/2010

GIPL GT+ST

225

– Work held up due to non availability of Gas.

Uttarakhand

Kashipur CCPP-I

04/2010

Sravanthi

Energy Pvt. Ltd

Block-I

225

– Work held up due to non availability of Gas.

Uttarakhand

Kashipur CCPP-II

11/2010

Sravanthi

Energy Pvt. Ltd

GT+ST

225

– Work held up due to non availability of Gas.

WB Haldia TPP-I

09/2011

M/s Haldia Energy

Ltd.

U-1 300

14/01/15(A)

Commissioned

        U-2 300

16/02/15(A)

Commissioned

 

 

 

 

HT- Hydro Test   RO/DM- Reverse Osmosis / Demineralised

Page 37: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

BLU- Boiler Light UP   GTG- Gas Turbine Generator TG- Turbine Generator   STG- Steam Turbine Generator

AWPH- Ash Water Pump Home   EDTA- Ethylene Damien Tierra Acetic Acid

BOP- Balance of Plant   RWPH- Raw Water Pump Home

SBO- Steam Blowing Off   HRSG- Heat Recovery Steam Generator

CHP- Coal andling Plant   BTG- Boiler Turbine Generator EPC- Engineering Procurement & Construction   NGT- National Green Tribunal

 

 

ANNEX-IB

 

ANNEX REFERRED TO IN REPLY TO PART (a) OF UNSTARRED QUESTION NO.1627 TO BE ANSWERED IN THE LOK SABHA ON 05.03.2015.

State/UT/Project-wise details of Hydro Power Projects taken of during the Eleventh and Twelfth Plan Sl. No

 

Name of Project

Executing Agency

Date of CEA clearance/ Approval

Capacity (MW)

Broad Features

Cost (original/latest)

Date of award of 1 st civil

package

Comm. Sch.

(original/ Now Ant.

Broad Present Status

Remarks/issues

Arunachal Pradesh       1 Pare

NEEPCO

4.12.2008

31.08.09

 

2013-14

Civil Works:

Diversion Tunnel: DT and construction of u/s and d/s coffer

-Slow progress due to bad geology.

-Concreting of Dam, associated

Page 38: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Sl. No

 

Name of Project

Executing Agency

Date of CEA clearance/ Approval

Capacity (MW)

Broad Features

Cost (original/latest)

Date of award of 1 st civil

package

Comm. Sch.

(original/ Now Ant.

Broad Present Status

Remarks/issues

2x55 = 110 MW

Broad Features:

Dam : 78m High, Con. Gravity

Spillway – 3 nos. gates

Size of gate:

10.4m (w)X 12 m(H)

Crest Level: 216 m

HRT: Dia – 7.5 M

Length– 2810.75M

Pressure Shaft: Dia: 6.4 M

Length: 220M

Bifucation Penstock

2016-17 dams completed.

Dam: Excavation - 365708 cum out of 398000 cum completed. Concreting started w.e.f. November, 14 and 5474 cum out of 183000 cum completed..

Head Race Tunnel: Boring completed & 1220 m overt lining out of revised lining length of 1250m in face-II completed.

High Pressure Tunnel : Boring completed.

Surge shaft: Open excavation, boring and lining completed.

Power House: Excavation in pit completed. Concreting 24327

HM works and transmission line works are critical.

Page 39: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Sl. No

 

Name of Project

Executing Agency

Date of CEA clearance/ Approval

Capacity (MW)

Broad Features

Cost (original/latest)

Date of award of 1 st civil

package

Comm. Sch.

(original/ Now Ant.

Broad Present Status

Remarks/issues

Dia: 4.5 M

Power House: Surface

P.H. Size: 68 mX 25m

Type of Turbine: VF

TRC: Open channel

60.62 M wide 49M long

Cost: 573.99

1128.38

/35000 cum completed.

 

Hydro Mechanical Works:

Erection of steel liner – 92.3m out of 230.50 m completed.

Erection of DT inlet gate completed.

 

Electrical & Mechanical Works:

Erection of DT Liners of Unit I & Unit II has been completed.. Erection of spiral case of Unit - I completed.

 

Erection & Commissioning of

Page 40: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Sl. No

 

Name of Project

Executing Agency

Date of CEA clearance/ Approval

Capacity (MW)

Broad Features

Cost (original/latest)

Date of award of 1 st civil

package

Comm. Sch.

(original/ Now Ant.

Broad Present Status

Remarks/issues

EOT crane completed.

2 Gongri

Dirang Energy Pvt. Ltd.

04.02.13

2x72= 144 MW

Broad Features :

Barrage-H-29m, L-216.5m MDDL- EL 1447m

Spillway-2nos.

Radial Gates; 2 Nos.

10.5m x 13m

Intake: EL1438m

Desilting Chambers : 2 nos.

22.12.11

 

 

2017-18

2017-18

EPC contract for all works awarded to Patel Engineering Ltd., Mumbai on 22-11-2011. TEC accorded on 04-02-2013 & Financial closure achieved on 15-02-13. Consent to establish from State Pollution Control Board was issued on 19-05-2014.

 

Infrastructural works are in progress.

 

Page 41: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Sl. No

 

Name of Project

Executing Agency

Date of CEA clearance/ Approval

Capacity (MW)

Broad Features

Cost (original/latest)

Date of award of 1 st civil

package

Comm. Sch.

(original/ Now Ant.

Broad Present Status

Remarks/issues

(260Lx13Wx16H)

HRT- modified horse shoe, 5.8 m dia & 7137m length ,

Surge Shaft- 92 m High & 13m dia.

Pressure Shaft : 4.4m dia, 647.26m length bifurcating into 3.1m dia & 28.51m & 34.5m length

P.House-Surface

Turbine- Vertical Francis

Cost : Original: 1436.27

Latest :1436.27

Himachal Pradesh

     

Page 42: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

3 Kashang-I

H.P. Power Corpn. Ltd.

31.07.08

65 MW

Broad Features:

HRT-3.5m x 4.115, 2 km long

S.Shaft- 2.6m dia & 0.5 m backfill and 1346 m long

TRT: 335 m combined

6/4.5 m D. stream

Cost: Original: 478.02

Latest: 478.02

09.04.09

 

2013-14

2015-16

Trench Weir: 3879 cum out of 3978 cum concreting completed.

HRT: Excavation and lining completed. Grouting yet to start. Pressure Shaft: Ferrule erection in top horizontal portion– 21m / 35m, low including limb - 41m / 536m completed. Ferrule erection upper inclined limb & bottom horizontal portion completed. Ferrule erection at horizontal portion at intermediate adit yet to start. Backfill concreting 649 m / 1346 m completed.

E&M works: Laying of earth mat is in progress. Model test completed.

Power House & Transformer hall concreting is in progress.

TRT concrete lining 197 m out of 335 m completed.

- Slow progress of Civil & E&M works.

- Approach roads washed off during heavy rains in Monsoon 2013.

4 Kashang-II & III

H.P. Power Corpn. Ltd.

1x65 + 1x65= 130 MW

Cost: Original: 601.78

Latest: 601.78

11.11.10

 

2013-14

2016-17

Works of Kerang-Kashang link (KK Link) tunnel awarded to M/s Patel Engineering Ltd.

-Works getting delayed due to continuous agitation by Lippa villagers.

-The matter is sub-judice.

5 Sainj 02.08.10 Barrage: Concreting in - HRT works &

Page 43: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

H.P. Power Corpn. Ltd.

2 X50=100 MW

29.12.2010

Cost:Original 784.56

Latest 784.56

 

2014-15

2016-17

 

2-bays out of 6 bays completed.

HRT: 935 m of overt lining completed in Face-I. Face-II 926 m/2010m and Face-IV 72m/1406m completed

Main Access Tunnel to Power House excavation is completed.

Power House: Excavation completed. 2nd

stage concreting for Unit #1 & #2 completed.

TRT: Excavation and Concreting completed.

barrage works.

 

6 Swara Kuddu

H.P. Power Corpn. Ltd.

Clearance: 10.11.2004

3x37= 111 MW

Broad Features:

Diversion Structure: 10.45m high Piano Key Weir.

HRT- D-Shaped, 5m dia, 11.145Km long.

Power House- Under ground

Turbine- 500

17.07.07

 

2010-11

2016-17

 

 

HRT: 9722 m out of 11764 m from all faces of HRT excavation completed and 1777 m out of 11364 m concreting is completed.

Surge Shaft: 70.38 m completed out of 77 m of shaft lining.

Power House: Excavation completed and concreting 7127cum out of 7850cum completed.

TRT: lining completed.

E&M Works: Ist, 2nd and 3rd stage embedment’s installation of all units completed. Installation of stator, rotor, lower bracket & upper bracket for unit no.3 completed

- Works badly suffered due to encounter of poor geology.

- Progress of HRT lining is slow.

- Contractual Issues.

-Contract for HRT package terminated on 9.1.14. Fresh award yet to be placed.

 

Page 44: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

rpm VF.

Switchyard: 220 Kv.

Cost: Original: 558.53

Latest: 1181.90

and for Unit #2 is in progress.

7 Sorang

Himachal Sorang Power corporation Ltd.

June, 2006/

2x50= 100 MW

Broad Features:

HRT- 1.5 km

Trench Weir-59 m

P.House- underground

Turbine- Pelton

Gross Head-626 m

SWYD- 11/400 kV (GIS)

Cost: Original: 586.00

Latest: 586.00

06/2007

 

2012-13

2015-16

 

 

Almost all Civil Works completed.

 

Transmission line stringing between tower no. 6&7 is yet to be completed.

Both the units are boxed up. During the filling of water conductor system in 1st week of Nov., 2013, leakage occurred in penstock due to cracks. Remedial measures are under progress.

- Completion of Transmission line works.

- Failure of penstock during filling.

8 Tidong-I 07.11.0 Barrage: Excavation Slow progress

Page 45: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

M/s NSL Tidong Power Gen. Ltd.

2x50 = 100 MW

28.07.2006

Broad Features:

HRT – D- 3.5m L- 8461 m

P.H. Surface

Turbine – Vertical Pelton

Cost: Original 543.15

Latest 543.15

8

 

2013-14

2016-17

completed. 31215 cum out of 33355 cum concreting done.

HRT: 7.7 km out of 8.6 km excavation completed. 425m concreting completed

Surge Shaft: open excavation top 15984 cum / 38500 cum completed. Underground excavation 90m/110m completed.

Pressure Shaft: Excavation completed

Power house- 87446 cum out of 92500 cum excavation completed.

8971 cum out of 14025 cum concreting completed.

of works

9 Tangnu Romai-I

M/s Tangnu Romai Power generation

2x22= 44 MW

30.11.2007 (HPSEB)

Broad Features:

Barrage at EL + 2555 m

HRT-3.1m dia

14.06.10

 

2014-15

2016-17

Civil works awarded on 14.06.2010 to M/s Sai Urja Hydel Project (P) Ltd.

Diversion Cannel: 26164 cum out of 93800 cum excavation completed.

Desilting Chambers & SFTPC: Excavation completed. SFT excavation 420 / 450.66 m completed.

HRT –2796m out of 6323m excavation completed.

Power House, Switchyard & Misc. – 62500 m3 out of

Slow progress of works

HRT critical, poor geology.

Page 46: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

& 7.220 km length

Surge Shaft- 5m dia, Top Level 2570 m & Bottom Level 2520 m

Penstock- 2 m dia & 609.3 m length

P.House- Surface

Turbine – Vertical Francis

Cost:

Original: 255.00

Latest: 255.00

72000 m3 excavation completed.

 

 

 

10

Chanju-I

M/s IA Energy

24.04.2010

3x12=36 MW

Cost :Original   : 295.09

Latest : 295.09

 

 

23.07.11

 

2017-18

2017-18

 

Barrage: 267500 cum excavation out of 287700 cum has been completed.

Desilting Basin including Flash arrangement: 20340 cum excavation out of 20800 cum has been completed. 2000 cum concreting out of 3510 cum completed.

HRT: Excavation 3900 m out of 4615 m completed.

Surge Shaft: Excavation completed (532 m)

 

Page 47: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Penstock/Pressure Shaft: 196 m excavation out of 720 m has been completed.

Power House: 134760 cum excavation out of 152147 cum completed. 4000 cum/6640 cum concreting completed.

E&M Works: Awarded. 11

Bajoli Holi

M/s GMR Bajoli Holi Hydro Power Pvt. Limited

31.12.2011

3x60= 180 MW

Broad Features

Dam Height-66 M

Dam Length-178 M

Desilting Chamber- 2 Nos.

240 Mx14.5 MX 10.8 M

HRT- Length-15.538 Km., 5.6 M dia

29.05.13

 

2017-18

2017-18

Civil Works awarded to M/s Gammon India ltd. on 29.05.2013.

Works are in initial stages of construction

Page 48: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

P.H. –Surface

Cost: Original 1696.93

Latest 1696.93

12

Shongtong Karcham

H.P. Power Corpn. Ltd.

Clearance: 16.08.2012

3x150= 450 MW

Broad Features:

Intake Tunnel: 4 Nos. Horse shoe 6.4m dia 192 to 280m length

HRT- Circular, 10.5m dia, 8096m long.

Power House- Under ground

Turbine- VF.

Switchyard: 400 Kv.

Cost: Original: 2807.83

Latest: 3316.35

04.08.12

 

2017-18

2017-18

 

Works awarded on 30.06.2012. CEA, concurrence accorded on 16.08.2012.

Civil Works:

Excavation of Adit – II : 103m out of 422m completed.

Road to Adit- III : Completed.

Excavation of Adit – III : 41m out of 418m completed.

Excavation of Adit – IV : 350m out of 403m completed.

Excavation of Main Access Tunnel (MAT) : 173m out of 188m completed.

Excavation of Ventilation Tunnel (VT) & Access tunnel to Transformer Hall : completed.

Diversion tunnel : Approach road / removal of muck at inlet portal is under progress.

E&M: Not yet awarded.

-Issues with Army authorities for shifting of ammunition depot.

 

-Award of E&M works.

Page 49: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

 

Works hampered in some portion of HRT : - To sort out the issues with Army Authorities, a meeting between Secretary (Defence) to Govt. of India, Chief Secretary to GoHP, Army Authorities and HPPCL representatives was held on 06.06.2014, wherein it has been decided to sign a tri-partite MoU between Army, GoHP & HPPCL. Further, DC Kinnaur has been asked to find out the suitable location for shifting the ammunition depot from Powari. Draft MoU has been sent to Army Authorities for their consent.

  Jammu & Kashmir

     

13

 

Kishanganga

NHPC

14.01.2009

3x110 = 330 MW

Broad Features :

Dam – 77m High,

concrete gravity

HRT- 5.3m x 24 km long

22.01.09

 

2015-16

2016-17

Diversion Works: – River diversion achieved on 21.06.2012.

Dam & Intake works:- Spillway concreting- 9950 cum completed out of 47000 cum.

CFRD Embankment- 116500 Cum completed out of 254000 Cum. Construction of Cut off Wall-1620 Sqm completed out of 2600 Sqm..

HRT:- Excavation completed by TBM/ DBM.

-Law and order problems viz frequent bandhs and curfew.

 

-Local agitation due to people demanding employment in NHPC.

 

Page 50: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

S.Shaft-15m dia x 127m H

P.House- Underground

103mx 21m x 45.5m.

Turbine- Pelton wheel

Swyd.- 220 kV

Cost: Original:3642.04

Latest: 5497.72

Lining of TBM portion (14.7 km) completed and 2132m lining of DBM portion completed out of 8437m.

Surge Shaft:- 62m Concreting completed out of 100m.

Pressure Shaft upper limb liner:- 227 m liner completed out of 233  m.

Power House:- 7977 cum concreting completed out of 10800 cum.

TRT : -Excavation completed. 342m lining out of 849m completed.

E&M: - Erection of pit liner & central frame in Unit-1 completed.

Assembly of Stator & rotor of Unit-1 in service bay is in progress.

Erection of EOT crane in Unit # 2 is in progress.

-R&R plan is pending with state cabinet for approval needs to be expedited.

 

-Completion of Power evacuation arrangement.

14 Baglihar-II

JKPDC

19.03.2012

3x150= 450 MW

Broad Features:

HRT – 10.15 m

31.03.12

 

2015-16

2015-17

Baglihar-II H.E. Project was conceived along with Baglihar-I H.E. Project. Works associated with dam and some portion of HRT was completed along with Baglihar Stage-I project.

HRT: Excavation completed. Lining almost completed.

E & M Works are critical.

Page 51: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

dia circular & 1888.8 m long

Surge Shaft: 27.5 m dia

& 97.5 m high restricted orifice type

Power House: Underground TRT: D-10.05 m L-342.6 m

Cost: Original: 3113.19

Latest: 3113.19

Surge Shaft: Excavation completed Lining also almost completed.

Penstock: Lining almost completed 254 out of 283 nos. ferrule erection completed.

PH: Excavation completed. Concrete lining under progress. Spiral casing for all three units completed. Installation of rotor hub under progress

TRT: 13,652 cum out of 15200 cm concreting completed.

  15 Ratle

Ratle Hydro Electric Project Pvt. Ltd.

19.12.2012

4x205+1x30= 850 MW

Broad Features :

Dam Height-133m

Length-194.8m

Spillway-Radia Gate-5 No.

04.07.13

 

2017-18

2017-18

 

EPC Contract for Civil & HM works awarded to M/s GVK Projects & Technical Services Limited on 04.07.2013. The infrastructure works of Road & Bridges is under progress and erection of upstream Bridge completed & downstream Bridge is in progress.

Works are in initial stages of construction

Page 52: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Size-10.75x1420 m

Diversion Tunnel:2 Nos., Circular (Right back)

Pressure Tunnel:11m dia each.

Pressure Shaft : 6.6 m each steel lined.

P.House-Underground

Turbine- Francis

Average Gross Head-100.39m

Addl. Unit(30MW) Housed in Main P.H. Cavity)

Rated Head-98.9m

Cost : Original: 5517.02

Latest : 5517.02

  Kerala       16 Thottiyar

KSEB

1x30 + 1x10=

22.12.08

 

Civil Works:

Weir: 3258 cum excavation out of total 5850 cum and 155.83

The works of weir & approach channel were hampered

Page 53: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

40 MW

05.06.2008

Broad Features:

Weir: 222m Long 11 blocks 7.5m height

Tunnel: Circular 2.6m dia 199m long.

Power House: Surface

Turbine : Vertical Pelton

Cost: Original: 136.79

Latest: 150.02

2012-13

2016-17

Cum concreting out of 8690 Cum completed.

Approach Channel & Intake: 3184 cum out of 9100 cum done.

Power Tunnel : Excavation completed.

Power House, switchyard & allied works: 31390 cum excavation out of 44500 cum and 1588 cum concreting out of 15675 m done.

E&M and HM Works: Supply of equipment in progress.

since 2010 due to land acquisition issues by local people and injuction order by Hon’ble municif court.The works resumed on 9-4-13.

  Maharashtra       17 Koyna Left

Bank PSS

WRD, Mah.

20.02.2004

2x40 = 80 MW

Broad Features:

Water from the existing Shivaji Sagar Lake

(Koyna

20.06.07

 

2017-18

2017-18

Civil Works:

Excavation of intake structure 3987 cum out of 11097 cum and lining 2485 cum out of 9700 cum completed.

Excavation of Switchyard completed. Excavation of Approach tunnel & Ventilation tunnel is in progress.

Tail surge shaft : Excavation in soft strata completed. Excavation for inclined / vertical / lateral shafts in hard rock 7476 / 47320

Slow progress of works.

Page 54: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

reservoir)

is to be utilized for generation.

Intake Tunnel: Dia–7.20 M

Length – 235.5 M

(including Lake tap)

HRT: Dia – 7.20 M

Length – 80 M

Penstock – 2 nos Dia – 2.9M

Length – 10 M each

P.House – Underground

Turbine – Reversible

Cost: Original: 226.40

Latest: 379.78

cum completed.

TRT : 364 / 24003 cum excavation completed.

Machine Hall : Underground Excavation is under progress. 22600 cum excavation out of 55050 cum completed.

E&M works:

The contract for details engineering manufacturing supply, supervision erection, testing commissioning and putting into commercial use of pump turbine, generator motor and associated equipments is signed with M/s IVRCL Ltd., Pune on 16.12.2010. Further TG set has been ordered as under:

Turbine/Pump: M/s Litosroj Power, Slovenia (European Union)

Generator/Motor: M/s Koncar Power, Plant & Electric Traction Engineering, Croatia (European Union).

EOT Crane :- Works awarded to M/s Pedvak Cranes Private Limited Hyderabad on 12.04.2013.

  Meghalaya       18 New Umtru 20.12.07 Dam: Excavation 61998  

Page 55: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

MePGCL,

2x20=40

Broad Features:

Diversion Structur-Gated structure (FRL-130.1m, MDDL-123.3m)

HRT- 5m dia, 750m long

P.House- Deep Set

SWYD- 132 kV

Cost: 226.40

461.27

 

2011-12

2016-17

 

cum out of 208685 cum completed. Concreting 32773 cum out of 73488 cum completed.

Intake: Excavation of 26984 cum out of 30000 cum completed. Concreting done which is more than estimated quantity of 13000 cum.

HRT: Excavation completed. Concreting 16,686 cum out of 20,888 cum completed.

Pressure Shaft: 421 tons of steel lining out of 525 tons completed.

Surge shaft: Open excavation completed and concreting done which is more than estimated quantity of 6166 cum.

Power House: Excavation completed & concreting is in progress.

TRT: Open excavation & tunnel boring completed & lining also almost completed.

E&M Draft tube erection completed for both units.

Turbine erection of embedded of both the units completed.

  Punjab       19

Shahpurkandi 11.02.1 Civil works of Main Dam and Hydel Channel

 

Page 56: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Irrigation Deptt. &PSPCL

04.05.2011

3x33+3x33+1x8=206 MW

Cost: Original: 2285.81

Latest 2285.81

3

 

2017-18

2017-18

awarded and are under construction

  Sikkim       20

Teesta-III

Teesta Urja Ltd. (TUL)

12.05.2006

6x200=1200 MW

Broad Features:

Dam-Concrete with chute spillway 60m high.

HRT- 7.5m dia, 13.325Km long.

Press. Shaft- 3nos. 3.8m dia.

Power House- Under ground

Turbine- Pelton

Cost: Original 5705.55

Latest

18.04.07

 

2011-12

2014-17

 

Dam: CFRD, 11.13 lacs cum material placed out of 11.5 lacs cum.

HRT: Excavation completed. 13653 M overt lining completed out of 13824 M and 12416 M invert lining completed out of 13824 M.

Surge Shaft: Excavation completed. 79.7m conc. Lining out of 154.5m completed.

Pressure Shaft-Vertical portion: Erection of steel liner 310.75m ouit of 659.70m for left pressure shaft and 178.65m out of 659.80m for right pressure shaft completed.

Power House: Civil works almost

- Earthquake in Sikkim in September., 11

- Completion of balance works after Earthquake

- Financial crunch with the developer. Works held up since October-2014.

- Power evacuation arrangement.

- Erection of vertical pressure shaft.

- Work

Page 57: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

11382.00 completed.

TRT: Excavation completed. 1315 m overt lining out of 1336 m completed.

Unit Erection:

Unit#1,2 &6- Stator & Rotor lowered.

Unit# 3&5: Stator lowered.

Unit#4- Stator assembly in service bay is in progress.

stopped since Sept, 2014 due to fund constraints, likely to restart by Mar, 2015.

21

Rangit-IV

Jal Power corp. Ltd. 06.07.2007

3x40= 120 MW

Broad Features:

Dam: Concrte 44m high .HRT : D- 6.4m L- 6.5km

Power House : Surface

Turbine: Francis

Power House- Under ground

Turbine- Francis

Cost: Original:726.17

22.11.07

 

2012-13

2016-17

Dam & Intake works: Excavation 290733/519887 cum completed and concreting 61008.5 cum out of 145413 cum completed. Excavation of road diversion tunnel has been completed.

HRT: Excavation in progress and 3557 m out of 6488 m completed.

Surge Shaft: Excavation has been completed & concreting is in progress.

Power House: The work of approach road to power house completed. Excavation in Power House is in

- Work hampered due to earthquake in September, 2011.

- Poor geology in HRT.

- Right bank slope failure at Dam site.

- Financial crunch with the developer.

 

Page 58: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Latest : 726.17

progress.

Desilting chamber: Excavation 2121 m out of 3360 m completed.

22

Jorethang Loop

M/s DANS Energy

2x48 = 96 MW

Broad Features:

Barrage: Gravity Floor on

Permeable Foundation

15 m High .

HRT : D- 7m L- 6.780km

Surge Shaft :59m Height & 25m dia.

Pressure Shaft : 172.60m length & 6m dia.

Power House : Surface

TR-Cut & Cover Conduit & 46.4m length.

Switchyard: Outdoor, 220 KV/11KV

Cost: Original: 543.15

09.03.09

 

 

2012-13

2015-16

 

HRT: Excavation completed. Concrete lining works are under progress.

Barrage : All major civil works are completed.

Surge Shaft: Excavation completed and lining upto EL 366.00 (55 m) completed. Chipping of gate grooves was also completed.

Upstream of Surge Shaft gate is concreted and 9m upstream part of Surge Shaft slab also concreted. Installation of Surge Shaft Gate is completed.

Pressure Shaft: Excavation completed. Ferrule erection in progress.

Power House: Structural civil works completed including roof installation.

Tail Race Channel: Excavation & Concreting completed. Draft tube gates for the

- Lining of HRT.

- Power evacuation arrangement.

Page 59: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Latest : 543.15

 

 

both units were lowered, installed and erection of the hoisting is also completed.

E&M works:

 

Unit-1 & 2: Both the units boxed up

HM Works: Fabrication of all Gates & associated ferrules for all portions has been completed. Both testing of spillways & under Sluice service gates are erected. Erection of surge shaft gates assembly has been completed. Penstock erection, alignment & welding of ferrules has been completed.

Dry Testing of Draft tube Gates for both units has been completed.

23

Bhasmey

Gati Infrastructure

3x17= 51 MW

Broad Features :

Dam-33.2m High,

Symmetrical gravity

12.04.10

 

2012-13

2017-18

 

Diversion tunnel completed.

HRT: Adits 309.85 Rm/781.97 Rm completed.

Power House: Excavation 181117/216147 cum completed.

- Slow progress of works

- Financial crunch with the developer.

 

Page 60: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

HRT-5.3m dia &5.132 km length , Circular.

Surge Shaft- 89.8m Hight & 14m dia.

P.House-Outdoor

Turbine-VF

TRT-2 Nos, L- 50m each.

Swityard- 132/11 KV

Cost :Original   : 408.5

Latest  : 408.5

Pressure Tunnel/Shaft: Excavation 40Rm out of 559.84 Rm completed.

24

Tashiding

M/s Shiga Energy Pvt. Ltd.

28.03.2011

2x48.5 = 97 MW

Broad Features :

Barrage-EL 917m

HRT-4.5 m dia & 5.437 km length ,

Surge Shaft- 61.058m Height & 8.5m dia.

Penstock- Length upto Bifucation 441.53 m

28.03.11

 

2017-18

2017-18

 

HRT (Total- 5437m): Excavation on Face-1: 1343.40 m,

Face-2: 765.00 m, Face-3: 1181.48 m, Face-4: 1119.10 m, Face-5:634.95m, Face-6:243.34m

Surge Shaft: Surface preparation for Adit to Surge Shaft has been completed.

E&M Works: The contract for E & M works was awarded to M/s ALSTOM Projects India Ltd. M/s ALSTOM Projects India Ltd. has submitted the model test report and same

- Poor geology.

- Local issues.

Page 61: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

After bifurcation 25 m & 30 m long

P.House-Surface

TRT- Open Channal & 78.5 m length.

Swityard- Outdoor, 220 KV

Cost :Original   : 465.95

Latest  : 465.95

has been accepted.

Power House: Power House open excavation along with slope protection was completed in the month of Feb’ 2014. Thereafter, 1st stage concreting of both the units completed. Up to EL 682.50m. 2nd stage concreting of both the units completed up to EL682.50m. Raft of concrete Draft tube of both the units completed.

25

Dikchu

Sneha Kinetic Power Projects Pvt. Ltd.

21.10.2011

3x32= 96 MW

Broad Features :

Dam-35m High,

Concrete Gravity

HRT-4m dia &4.6 km length

Circular.

Surge Shaft- 65m High & 9m dia.

P.House-Underground

22.03.11

 

2017-18

2017-18

 

Dam: Excavation 54000 cum out of 86762 cum completed.

HRT: Excavation 72 RM out of 5456 RM completed.

Power House: Excavation 22317 cum out of 43570 cum completed.

TH: Excavation 8914 cum out of 9177 cum completed.

TRT: Excavation 195 Rm out of 295 Rm completed.

Main Access Tunnel: Excavation completed.

 

Slow progress of works

Page 62: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Turbine-Vertical Francis

TRT-4m dia & 1000m length

Swityard- 60mx30m size

Cost : Original   :639.57

Latest : 639.57

26

Rangit-II

Sikkim Hydro Power Limited

10.02.2010

2x33= 66 MW

Broad Features :

Dam-47m High,

Concrete Gravity

HRT-3.9m dia &4.745 km length ,

Surge Shaft- 65.5m High & 10m dia.

Underground Pressure Shaft : 1.7 m dia &2.5 km length.

24.10.11

 

2017-18

2017-18

 

EPC contract awarded to M/s Coastal in February, 2012. Works of approach roads and excavation of adits are in progress.

Protection wall works under progress.

Adit to HRT: Underground excavation is in progress.

Diversion Tunnel: Excavation is under progress.

Surge Shaft: Excavation is under progress.

Power House: Excavation of surface power house is being taken up.

Slow progress of works

Page 63: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

P.House-Outdoor

Turbine- Pelton Vertical

Swityard- GIS, 132/11KV

Cost : Original   : 498.00

Latest  : 498.00

27

Rongnichu

Madhya Bharat Power Corporation Ltd.

01.10.2008

2x48= 96 MW

Cost : Original   : 491.32

Latest  : 491.32

07.04.10

 

2015-16

2017-18

 

The civil works have been awarded to M/s SEW Infrastructure Ltd. and E&M works to M/s Voith Hydro Power Pvt. Ltd. Award of HM works is likely to be placed by August, 2012. Pre-construction activities and excavation of adits are in progress.

- Land acquisition.

- Poor geology.

28

Panan

Himagiri Hydro Energy Pvt. Ltd.

07.03.2011

4x75= 300 MW

Broad Features :

Dam-115m from deepest

22.02.14

 

2018-19

2018-19

Civil works awarded on 22.02.2014. Infrastructural works and geological investigations are in progress.

 

Page 64: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

foundation level

Desilting Chambers : Underground, 2

Size (14Lx22Wx2.5H)

HRT- modified horse shoe, 6 m dia & 9549m length ,

Surge Shaft- 102 m High & 15m dia.

Pressure Shaft : 2/4, 3.4/2.4m dia & 707.4 m high.

P.House-Surface

Turbine- Vertical Francis

Cost : Original: 1833.05

Latest :1833.05

Telengana       29

Lower Jurala

TSGENCO,

TEC in July 2007

6x40=240 MW (120 MW likely to slip)

10.02.08

 

2011-13

2014-17

Weir: Excavation completed. 203966/219040 cum concreting completed.

Power House: Excavation completed. 218018 cum concreting against total quantity of

- Power House flooded on 30.07.2014 during synchronization process for Unit# 1 to Unit# 3.

Page 65: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Broad Features:

Intake: 18 vents (3 vents for each unit) 4.7m width,

P.House- Surface,

Turbine- Bulb

Design Head- 20m

SWYD- 220 kV

Cost: Original: 908.34

Latest: 1474.83

(likely to slip)

225550 cum done.

Unit Erection:

The Units 1,2,3 which were completed and units 4,5,6 which are under different stages of erection were completely submerged in water on 30.07.2014 due to sudden gush of water through the upstream gate of Unit No.4. It was dewatered by 03.09.2014. Re-conditioning of Units is in progress by M/s Alstom. Rectification works of stator and rotor for U#1,2,4&5 at service bay are in progress.

U#1 – Rotor lowered,

U#2 – Rotor is ready for lowering ,

U#4 – Main shaft cleaning, assembly of bearing with shaft is completed and ready for lowering.

Commissioning is likely to slip to 2015-17.

Restoration works in power house is under process.

30

Pulichintala

TSGENCO

120 MW (4x30 MW)

01.08.07

 

2009-11

Dam is under construction by Irrigation Department.

Power House: The excavation of power house completed and 70351 cum concreting

- The civil works were hampered from Sept.-11 to May-13 due to contractual issues. Works resumed by the contractor on

Page 66: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

25.04.2007

Broad Features:

Design Head: 24 M

Power House: Surface

Turbine : V. Kaplan

Annual Energy: 220 MU

Cost: Original: 380.00

Latest: 396.00

 

2016-17

 

done against 89850 cum..

E&M Works:

EOT Crane: Erection completed.

Unit #1 : stay ring and spiral casing erection completed.

Unit #2 : stay ring erection completed. Spiral casing segments erection is in progress.

Unit #3 & 4: Erection of draft tube cone & welding completed and released for concreting.

16-06-2013.

 

Uttarakhand       31

Shrinagar

AHPC Ltd..

14/06/2000/ FC

4x82.5=330

Broad Features:

Dam –66.5m High, concrete gravity

HRT- 13m x 889m

06/2007

 

2005-06

2015-16

 

Civil Works: Completed.

Electro Mechanical Works: Unit # 1 to #3 boxed up. (Spinning earlier done.)

Unit # 4 to be boxed up by Feb ‘2015.

 

- Agitation by locals.

- Financial constraints.

Page 67: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Penstock-4x 5.6m x 114m

P.House- Surface

Turbine- Francis

Cost: Original: 1699.12

Latest: 2069.00

32

Phata Byung

M/s Lanco

06.10.2008

2x38 MW = 76 MW

Broad Features:

Dam – 26m high

HRT- 3.2 m dia &

9.38 km length

Turbine – Frances

Cost: Original: 720.00

Latest: 720.00

12.04.08

 

2013-14

2017-18

 

Diversion Tunnel: River diverted.

Dam concreting: 17800/18000 cum concreting completed.

P.H.: Excavation completed & Concreting in progress.

HRT: Excavation 8474/9228 m completed.

Excavation and lining of Intake-I & Intake-II completed.

Cable tunnel: Completed.

TRT: Excacation 178/235m completed.

E&M Works: Pit liner erection of units completed.

 

- Poor geology in HRT.

- Power evacuation system.

- Flash flood in June-2013.

- Works yet to commence after floods.

33

Singoli Bhatwari 20.06.0 River diversion – - Poor geology

Page 68: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

M/s L&T

11.07.2008

3x33 MW = 99 MW

Broad Features:

Barrage-FRL 1017 m, MDDL 1009 m,

Barrage Top 1020m

HRT- 4.65m dia & 11.870m length

Surge Shaft-10 m dia & 102.85 m length

Pressure Shaft-One, 3.80m dia & 358m length

Penstock- 3 Nos., 2.20 m dia & 34m, 42m, 48m long.

P. House-Surface

Turbine-Vertical Francis

TRT- Open Channel, 650m length

8

 

2015-16

2017-18

 

Completed.

Dam & Dykes/Barrage: Excavation 69692/90744 cum and concreting 47311/76500 cum completed.

HRT: Excavation 8653/11255 m completed.

Pressure Shaft: Excavation 440.5/558 m completed.

PH: Excavation completed & concreting 6517/18000 cum completed.

Surge Tank: Excavation completed.

in HRT.

- Agitation by Local people.

- Flash flood in June-2013 in Uttarakhand.

- Works commenced after flash floods in September-14.

 

Page 69: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Cost : Original : 666.47

Latest : 666.47

34

Tehri PSS,

THDC,

18.7.06

Nov-11 (Revised CCEA)

4x250=1000 MW

Broad Features :

Surge Shaft: U/s – 2 nos.

D/s – 2 nos

Power House: U/G

TRT: 2, Dia 9m and Lenghth 1070m + 1160m

Turbine: VF reversible pump turbine

Cost: Original: 1657.60

Latest: 2978.86

23.06.11

 

2011-12

2018-19

EPC contract has been awarded on 23.06.11 with commencement date from 27.07.11.

Upstream (Tehri Dam) and Downstream (Koteshwar Dam), intake and Head Race Tunnels (2 Nos.) already completed alongwith Tehri Stage-I works.

Surge Shafts upstream (2nos- 140m).: Pilot shaft excavation for both shafts completed.

Butterfly Valve Chamber (BVC): Crown slashing with steel ribs completed. Benching will start after treatment of deformation observed in drainage gallery.

Penstock Assembly Chamber (PAC): Crown slashing with steel ribs completed. Benching will start after two benches of BVC.

PH: Underground excavation of PH upto EL 582m: 87.5 Th. Cum out of 130 Th. Cum completed.

Surge Shafts downstream (2nos).: Pilot shaft excavation for both the shafts completed. Excavation of drainage gallery around surge also completed.

TRT (2 Nos- 1070m &

- Poor Geology in under ground works of BVC & PSAC, TRT, PH Cavern etc.

- Due to poor geology encountered during investigation, it was decided to shift service bay at other end of machine hall and accordingly power house layout has been revised.

- Poor preparedness of contractor w.r.t. finalization of design & drawing, inadequate deployment of resources at project works.

- Ban by DM, Tehri on mining activities in Asena Quarry since 1-4-2013. Environment

Page 70: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

1160m).): Heading in 327.5m and drift in 94m out of 1070m in TRT-1 and Heading in 220.5m and drift in 228.4m out of 1160 RM in TRT-2 has been achieved.

E&M Works: Manufacturing & supplies are in progress.

clearance modified by State Level Env. Impact Assessment Authority (SEIAA) in Jan-2015.

Uttarakhand       35

Lata Tapovan,

NTPC

Aug-2012

3x57= 171 MW

Broad Features :

Barrage–14 bays of 11m each

HRT- 7.51 Km, 4.7m dia

P.House- underground

Turbine- V.Francis

Cost: Original: 1527.00

Latest: 1527.00

17.08.12

2017-18

2018-19

Pre-construction activities & infrastructure works are in progress.

EPC contract for Civil & HM works awarded to M/s L&T on

17-08-2012. E&M package awarded to M/s BHEL on 07.12.12.

- Flash flood in June-2013.

- Works of barrage & HRT yet to start due to protest by villagers.

-Construction work stopped vide Hon’ble Supreme Court order dated 7.5.14.

36

Vishnugad Pipakoti

THDC

17.01.14

2013-14

Civil and HM works awarded on 17.01.2014.

E&M works awarded on

-Disruption of works by local people.

 

Page 71: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

21.08. 2008

4x111= 444 MW

Broad Features :

Dam – 65m High, 89.3m long, concrete gravity

HRT- 13.4 Km, 8.8m dia Horse shoe shape

P. House-Underground 127mx 20.3mx 50m

Turbine- Francis

SWYD- 13.8/420 kV

Cost:Original: 2491.58

Latest: 3745.08

2018-19 18.11.2014.

Heading excavation in 215m out of 490m for Diversion Tunnel completed.

Construction of Adits and infrastructure works are under prgroess.

ANNEX-II

 

ANNEX REFERRED TO IN REPLY TO PART (b) OF UNSTARRED QUESTION NO.1627 TO BE ANSWERED IN THE LOK SABHA ON 05.03.2015.

***********

EXPANSION THERMAL PROJECTS UNDER CONSTRUCTION

Page 72: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

AS ON 02-Mar-2015

Sector Project Name Impl. Unit Cap. Ant. comm

State Agency No. (MW) Date

CENTRAL SECTOR

 

Bihar Barh STPP-II NTPC U-4 660 30.11.13

U-5 660 03/2015

Bihar Muzaffarpur TPP Exp NTPC U-3 195 03/2015

U-4 195 12/2015

Jharkhand BokaroTPS "A"Exp.DVC U-1 50012/2015

Maharashtra Mouda STPP-II NTPC U-3 66012/2016

U-4 660 06/2017

MP Vindhyachal TPP-V NTPC U-13 500 10/2015

Tripura Agartala CCPP NEEPCO ST-1 25.5 05/2015

ST-2 25.5 03/2015

UP Tanda TPS -II NTPC U-1 660 05/2018

U-2 660 11/2018

UP Unchahar TPS St-IV NTPC U-6 500 11/2017

WB Raghunathpur TPP Ph-IIDVC U-1 660 10/2018

U-2 660 03/2019

Page 73: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

STATE SECTOR

 

AP Rayalseema St-IV U-6APGENCO U-6 600 12/2016

Bihar Barauni TPS Extn BSEB U-1 250 11/2015

U-2 250 02/2016

Gujarat Sikka TPS Extn. GSECL U-3 250 03/2015

U-4 250 07/2015

Gujarat Wankbori TPS Extn GSECL U-8 800 10/2018

Karnataka Bellary TPP St-III KPCL U-3 70012/2015

Maharashtra Chandrapur TPS MSPGCL U-8 50003/2015

U-9 500 08/2015

Maharashtra Koradi TPS Expn. MSPGCL U-10 66002/2016

U-8 660 03/2015

U-9 660 07/2015

Maharashtra Parli TPS Expn. MSPGCL U-8 25008/2015

MP Shree Singaji TPP MPGENCO U-3 660 07/2018

Phase-II

U-4 660 11/2018

Rajasthan Chhabra TPP Extn. RRVUNL U-5 66004/2017

U-6 660 10/2017

Rajasthan Suratgarh TPS RRVUNL U-7 660

Page 74: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

04/2017

U-8 660 07/2017

Telangana Kakatiya TPS Extn T GENCO U-1 60002/2016

UP Anpara-D TPS UPRVUNL U- 6 500 03/2015

U-7 500 08/2015

WB Sagardighi TPS-II WBPDCL U-3 500 06/2015

U-4 500 09/2015

PRIVATE SECTOR

 

AP Simhapuri Energy Pvt Madhucon Projects Ltd. U-3 150 21.02.14

Ltd Ph-II U-4 150 03/2015

 

AP Thamminapatnam TPP-Meenaksha Energy Ltd. U-3 35008/2016

U-4 350 11/2016

Chhattisgarh Lanco Amarkantak TPS- LAP Pvt. Ltd. U-3 66006/2017

II

U-4 660 01/2018

Page 75: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

Sector Project Name Impl. Unit Cap. Ant. comm

State Agency No. (MW) Date

 

 

Chhattisgarh Tamnar TPP ( Raigarh) O.P.Jindal U-1 60010.03.14

U-2 600 30.03.14

U-3 600 07.01.15

U-4 600 06/2015

Jharkhand Mata Shri Usha TPP-Ph- Corporate Power LtdU-3 27004/2018

II

U-4 270 08/2018

Maharashtra Amravati TPP Ph-II Ratan India Power Pvt U-1 27007/2017

Ltd.

U-2 270 10/2017

U-3 270 04/2018

U-4 270 07/2018

U-5 270 10/2018

Maharashtra Nasik TPP Ph-II Ratan India Nasik Power U-1 27005/2017

Pvt Ltd.

U-2 270 09/2017

U-3 270 02/2018

Page 76: · Web viewOrder placed on BHEL for STG and on BGR for SG. Levelling and grading work is in slow progress due to fund problem in DVC. STATE SECTOR AP Damodaram Sanjeevaiah TPS 06/2008

U-4 270 06/2018

U-5 270 10/2018

Total : 28071