1documents.worldbank.org/curated/pt/931041468219883688/e... · web viewsince then, the city’s gas...

71
E1714 v.4 Environmental Management Plans for Reconstruction and Expansion Project for Gas Facilities of Yingkou City Loaded from World Bank 1

Upload: buinguyet

Post on 20-Mar-2018

214 views

Category:

Documents


1 download

TRANSCRIPT

E1714

v.4

Environmental Management Plans for

Reconstruction and Expansion Project

for Gas Facilities of Yingkou City

Loaded from World Bank

Design Unit: Yingkou Coal Gas Company Liaoning Academy of Environmental Sciences

January 2007

1

CONTENTS

1 PROJECT DESCRIPTION................................................................................................................2

1.1BACKGROUND OF THE PROJECT...............................................................................................................21.2NAME, LOCATION, NATURE, AND PROJECT PLAN.....................................................................................21.3CONSTRUCTION CONTENTS OF PROJECT.................................................................................................2

2 DESIGN BASIS OF EMP...........................................................................................................................1

2.1 PERFORMANCE CRITERIA........................................................................................................................12.2DESIGN BASIS..........................................................................................................................................3

3 POLLUTANT DISCHARGE.....................................................................................................................4

3.1 WASTE GAS EMISSION OF THE PROJECT................................................................................................43.2 WASTE WATER.........................................................................................................................................43.3 NOISE SOURCE........................................................................................................................................43.4 SOLID WASTE...........................................................................................................................................43.5PULLUTANT REDUCTION BY THE NEWER FOR THE REPLACEMENT OF THE OLD ONE...............................4

4 ANALYSIS OF THE ENVIRONMENTAL IMPACT..............................................................................6

4.1 STATUS QUO OF ENVIRONMENT QUALITY..............................................................................................64.2 ENVIRONMENTAL IMPACT ANALYSIS IN CONSTRUCTION PERIOD..........................................................74.3 ANALYSIS OF THE ENVIRONMENTAL IMPACT IN OPERATION................................................................11

5 ENVIRONMENTAL RISK ASSESSMENT...........................................................................................14

5.1 ENVIRONMENTAL PROTECTION TARGET................................................................................................145.2 ENVIRONMENTAL RISK TYPES..............................................................................................................145.3 RISK PROBABILITY AND THE CONFIRMATION OF THE SOURCES............................................................155.4 CONSEQUENCE CALCULATION..............................................................................................................165.5 RISK CALCULATION AND ASSESSMENT.................................................................................................185.6 RISK CONTROL MEASURE AND EMERGENCY RESPONSE PLAN............................................................195.7 CONCLUSION.........................................................................................................................................25

6 THE ENVIRONMENTAL AFFECTION REDUCTION METHODS.................................................26

7 MONITORING PLAN AND ORGANIZATION ARRANGEMENT..................................................30

7.1MONITORING PLAN................................................................................................................................307.2ENVIRONMENTAL SUPERVISION DURING THE CONSTRUCTION...............................................................307.3MONITORING ORGANIZATION ARRANGEMENT......................................................................................307.4 CATEGORY AND CONTENT OF MONITORING REPORT...........................................................................368.1.1CATEGORY AND CONTENT OF MONITORING REPORT.........................................................................367.5 SUBMITTING TIME AND MONITORING REPORT ACCEPTER...................................................................367.6 FEEDBACK REQUIREMENT OF MONITORING REPORT...........................................................................36

8.REINFORCEMENT PLAN OF ENVIRONMENT MANAGING ORGANIZATION...................37

9 PUBLIC PARTICIPATION PLAN..........................................................................................................37

9.1 CONTINUOUS PUBLIC PARTICIPATION PLAN.........................................................................................379.2 CHANNELS FOR COMPLAINS OF DISSENSION.........................................................................................38

10 EMP Executive Fees................................................................................................................................40

1

1 Project Description

1.1Background of the Project

Yingkou City Gas Company was founded in1986, which is the only pipe-gas public

utility enterprise in Yingkou. The resource of the company is natural gas from Liaohe Oil

Field. It has been transferred to the gas source plant located at Laobian District, Yingkou

City, via a 45-km pipeline from Liaohe Oil Field. After the pressure adjustment, it has

been sent to the whole city. The pipes and gas tanks have been aged after many years’

usage and the gas system is unable to meet the request of the expanding city of Yingkou.

Since then, the city’s gas system needs to be updated; the energy consumption of the

city needs to be optimized in order to assure the city’s demand. The pipelines of the gas

system of Yingkou have been using for many years; the geological condition of the city is

not good enough; the accessory is not enough; the rate of gas loss keeps at high level; and

there are some serious hidden trouble in the system. So Yingkou City Gas Company takes

out this project.

The route of the pipeline and location of Yingkoou Coal Gas Company are described

as figure 1-1.

1.2Name, Location, Nature, and project plan

Name: Reconstruction and Expansion Project for Gas Facilities of Yingkou City

Location: Yingkou City

Nature: Reconstruction and Expansion

Investment: RMB 82,845,000 yuan, of which 31,204,000 yuan from World Bank

Loan and the other from self-funded

Construction Plan: September 2008 – November, 2009

1.3Construction Contents of Project

Three contents in this construction project

1. Overhaul of the wet-style storage cabinet of the gas source plant (one is 20,000

m3, the other is 50,000m3) and build a new dry-style storage cabinet (50,000 m3)

2

2. Set up an intelligent gas management system

3. Gas pipeline rehabilitation: rehab of 9km natural gas transmission pipeline

(DN200), upgrading of middle pressure pipeline of 20km (DN200-DN300) and of low

pressure pipeline of 15km (DN200). Rehabilitation of 20 (middle pressure) and installing

of 40 (low pressure) new valves, and build cathodic protection system of about 280 poles.

The details is as followed,

1.3.1 Overhaul and building of storage cabinets in the gas source plant

Overhaul for the wet-style storage cabinet of the gas source plan (one is 20,000 m3,

the other is 50,000m3), including:

Change the rotten steel board;

Amend some of the wall board;

Adjust tower guide pulley;

Stabilize the entrance and exit of the pipes.

Besides, build a new dry style storage cabinet of 50,000 m3 at the free space in the

gas source plan.

1.3.2 The construction of Gas Intelligent Management System

Set up a Control Center with gas intelligent Management System. Transfer the

signals and commands between different units and controlling points via Supervisory

Control And Data Acquisition (SCADA) System; Transfer the signal and commands in

the pressure-adjustment stations and valve of the urban area’s gas system; Transfer the

parameters of the user gap consumption; Load or save the documents such as the

company’s files or original data.

1.3.3 Pipeline system reconstruction

1. Make a 20km-long steel pipe of medium-pressure (0.4MPa) as the main pipe from

Zhuanglin Road to Qinghua Street, which will be made of PE pipe. This pipe will connect

the natural gas distance transferring pipe in Hanhe Bridge. Pressure does not need to be

readjusted in natural gas plants.

3

2. Three pressure adjustment stations will be setup on the new 0.4MPa main pipe,

which locates at Lianmeng Road Cross, Guanghua Road Cross, and Qinghua Road Cross.

The stations will transfer gas to the urban medium-pressure pipe (0.15MP), which will

expand the gas supply area and gas supply ability.

3. Change the pipeline with 9km length, from Liaohe Oil Field Gas Station to the

south bank of Daliaohe River, Tianzhuangtai Town. The part from Liaohe oil field gas

station to Xintun Pressure Adjustment Station Dawa County will be changed to Spiral

submerged arc - welded steel pipe which has been strengthened by 3 layers PE pipe and

the part from Xintun Pressure Adjustment Station Dawa County to the south bank of

Daliaohe River Tianzhuangtai Town will choose PE pipe.

4. Replace the medium or low pressure cast iron pipe and its accessory (such as

valves) with hidden safety trouble. The total length of the pipe is about 15 km.

5. Replace about 30 rotten valves, meanwhile, we will choose valves with distance

controlling in order to cater for the gas intelligent management system.

6. Add up sacrificial anodes cathode protection equipment in the areas of serious

corrosion problem. The total number is about 280 (70 sets).

7. Add up about 40 valves in some key point of the low-pressure pipes and the pipe

entrances or exits in the living areas where accident often happens.

4

2 Design basis of EMP

2.1 Performance criteria

2.1.1 Environmental quality standard

(1) Ambient Air Quality Standard

The normal pollutants of environmental air quality shall apply Ambient Air Quality

Standard Grade Ⅱ. (GB3095-1996). See Table2-1 for the detailsTable 2-1 ambient air quality standardGrade Item TSP PM10 SO2 NO2

Ⅱhour average 0.50 0.24Daily average 0.30 0.15 0.15 0.12Annual average 0.20 0.10 0.06 0.08

(2) Quality Standard of Surface WaterDaliaohe River in Yingkou: Grade V of Environmental quality Standard for Surface

Water (GB2939-2002)

Laobianhe River: Grade IV of Environmental quality Standard for Surface Water

(GB2939-2002)

Table2-2 Quality Standard of Surface Water (GB3838-2002) (mg/L, except pH)River Level pH petroleum CO BOD5 NH4

+/NH3

Daliaohe Ⅳ 6~9 0.5 30 6 1.5Laobianhe Ⅴ 6~9 1.0 40 10 2.0

(3) Standard of Environmental Noise

Standard of Environmental Noise in different functional zone should adopt Standard

of Environmental Noise of Urban city (GB3096-93). See table2-3 for the details:

Table2-3 Standard of Environmental Noise of Urban city (GB3096-93) Leq[dB(A)]Grade Daytime Nighttime

1 55 452 60 553 65 55

1

3 70 55

2.1.2 Discharge Standard for Pollutants

(1) Discharge Standards for waste gas

The existing boiler of the gas source plant should adopt Emission Standard of Air

Pollutants for Coal-Burning Oil-burning Gas-fired Boiler (GB13271-2001)in the second periods

is compliance with the maximum allowable emission standard and the second period

limit after the reconstruction.

Table 2-4 Emission Standard of Air Pollutants for Boiler Unit:mg/m3Pollutant Limit in first Period Limit in secondPeriod

Smoke and dust 250 200SO2 1200 900

(2) Discharge Standard for Waste Water

Waste water of the factory Executes the Level II standard of Waste Water and gas

Emission Standard, Liaoning Province (DB21-60-89); after the update, executes new

Level II Standard; Waste water in the urban office area executes the standard of Water

Treatment Unit of Water Quality Standard of the Sewage Discharged into Urban Sewer

(CJ3082-1999).

Table 2-5 Discharge Standard of Waste Water Unit: mg/l(Except pH)

Pollutant

Present Level II standard of Waste Water and gas Emission

Standard, Liaoning Province (DB21-60-89)

Water Quality Standard of the Sewage Discharged into

Urban Sewer (CJ3082-1999)

PH 6.0-9.0 6.0-9.0COD 100 150

petroleum 10 -BOD5 60 100

SS 150 150

(3) Discharge Standard for Noise

Boundary noise of the gas source plant should adopt Standard for Noise at Boundary of Industrial Enterprises Grade Ⅱ(GB12348-90) and the pipeline in different functional zone should adopt Standard for Noise at Boundary of Industrial Enterprises Grade Ⅱ(GB12348-90) Noise during construction should perform The standard of noise limits of construction site (GB12523-90). See Table 2 – 6 and 2-7 for details

2

Table2-6 Standard for Noise at Boundary of Industrial Enterprises Leq[dB(A)]Group Daytime Nighttime

Ⅰ 55 45Ⅱ 60 50Ⅲ 65 55Ⅳ 70 55

Table2-7 The standard of noise limits of construction site Leq[dB(A)]Construction phase Main noise source

Noise limitsDay time

Earthwork Bulldozer, Excavator, Loader etc, 75 Earthwork

Piling Various pile driver 85 Piling

Framework Concrete mixer, vibrating needle, Electric saw etc, 70 Framework

Decoration Crane, Elevator etc, 65 Decoration

(4)Discharge Standard for Solid Wastes

-----Standard for Pollution Control on the Industrial Solid Wastes in Liaoning Province (DB21-777-94)-----Standard for Pollution Control on the Storage and Disposal Site for General Solid Wastes (GB18599-2001)

2.2Design Basis

This Environmental Management Plan is designed according to the laws and regulations

of environmental protection in People’s Republic of China; World Bank Safeguard

Operation Policy; related environment protection rules and structured documents in

Yingkou city; the design documents of this project; technical documents on the

construction project’s environmental impact assessment of PRC Environmental

Protection Agency; international environment protocols that signed by China; etc.

3 Pollutant Discharge

3.1 Waste Gas Emission of the Project

No atmospheric pollutant will be produced while the project runs normally. If the

pipe pressure were over the normal, the adjustment stations will activate the safety valve.

Since this program aims to the amendment of medium-low pressure pipe, and automatic

protection unit will be setup, over-pressure problems will seldom appear, so the nature

gas leak will be little.

3

3.2 Waste water

The waste water during the project’s running is mainly the daily domestic waste

water. Since no new workers needed in this project, the water consumption keeps the

same as before.

3.3 Noise source

The noise source of this project is the new gas pressurization machine’s noise (85-

90dB(A)). Besides, if the new pressure adjustment station’s pressure is over the normal

range, the safety valve will be activated, just at the moment the gas released, noise will be

burst out at the maximum of 85 dB(A).

3.4 Solid waste

The solid waste of this project is the 3 new adjustment station’s used filter, which

will be replaced on time. Usually, filter will be changed ever 3 months. The weight of a

filter is about 0.5kg, so the yearly solid waste is about 0.006t/a.

3.5Pullutant reduction by the newer for the replacement of the old

one

The main method of using the new to replace the old in this project is to solve the

over release of smoke and dust from the factory’s boiler and daily waste water. By means

of the update of the boiler’s dust remover and water treatment system, the correct smoke

filter system and waste water treatment system will help the factory reduce pollutant and

reach the limit , so that the amount of pollutant will be reduced. After this method, the

pollutant of Yingkou Coal Gas Company will be as follow table 3-1.

Table3-1 The change of pollutant amount Unit:t/a

Waste Pollutant Present Amount Project Amount

Reduction by the

methods

Future Amount

Amount change

Gas Smoke 15.4 0 12.3 3.1 -12.3

SO2 10.5 0 0 10.5 0

Water

CODCr 2.56 0 0.26 1.30 -0.26

SS 1.5 0 0.15 1.35 -0.15

Animal/ 0.08 0 0.005 0.075 -0.005

4

Vegetable OilNH4

+/NH3 0.08 0 0.005 0.075 -0.005

Solid

Boiler Ash 250 0 -12.3 262.3 +12.3

Daily solid waste 66 0 0 66

Wasted filter 0.16 0.006 0 0.166 +0.006

5

4 Analysis of the Environmental Impact

4.1 Status Quo of Environment Quality

(1)Ambient Air Quality

According to Yingkou City Environment Report 2006, The air quality of

Yingkou city is as table 4-1.

Table 4-1 Air Quality in Yingkou City Unit:mg/m3

Pollutant

Annual

Average

Exceeding standard

multiple

Functional Area Season

Industry

Residents

Traffic Clean Winter SpringSumme

rAutum

n

Heating

Period

Non-heating Period

TSP 0.170 - 0.190 0.220 - 0.120 0.190 0.180 0.160 0.160 0.190 0.170

SO2 0.016 - 0.025 0.014 - 0.002 0.050 0.007 0.005 0.004 0.050 0.005

NO2 0.022 - 0.024 0.028 - 0.017 0.032 0.032 0.012 0.014 0.032 0.019

According to the above table, The annual average of TSP, SO2 , and NO2 in

Yingkou’s different season and area will satisfies Grade II of National Ambient Air

Quality (GB3095-1996), the air quality is quite good.

(2)Water Environmental Quality

According to Yingkou City Environment Report 2006, the water quality of

Daliaohe River in Yingkou is as table 4-2.

table4-2 the water quality of Daliaohe River in Yingkou,2004 Unit: mg/L

Place COD BOD5NH4

+/NH3

MnO4- volatile

phenolpetroleu

mWater quality

Level

Heiyingtai - 4.96 3.43 11.0 0.001 0.030 Worse than V

Liaohe Park - 5.15 3.46 12.6 0.001 0.020 Worse than V

Average - 5.06 3.44 11.8 0.001 0.025 Worse than V

According to it, we know the water quality of Yingkou part of Daliaohe River is

heavy polluted.

(3)Acoustic Environmental Quality

According to Yingkou City Environment Report 2006, the information of

functional zone noise is as table 4-3.

6

Table 4-3 Noise Monitoring Data of Each Functional Zone Noise in Yingkou Unit: dB(A)

City

Noise in different functional areas

0 1 2 3 4

Daytime

Nighttime

Daytime

Nighttime

Daytime

Nighttime

Daytime

Nighttime

Daytime

Nighttime

Yingkou - - 49.8 43.5 53.2 47.3 53.9 52.2 66.1 53.6

Standard 50.0 40.0 55.0 45.0 60.0 50.0 65.0 55.0 70.0 55.0

According to the above date, all the areas of Yingkou City’s noise reaches the

standard, the Sound Environment Quality is good.

4.2 Environmental Impact Analysis in Construction Period

4.2.1 Analysis of Ambient Air Impact

The air pollution during this project comes from the following activities: dust

during the pipe channel digging by the bulldozer; dust spread by the basic contraction

of the storage cabinet, vehicles, road digging, and mechanical running; the dust and

splash of the mechanical materials (such as cement, lime, and sands) during the

transportation, and the waste gas from the mechanics, vehicles and generators.

1. Flying Dust Impact Analysis during Construction

Reference by general contraction fields’ data, the daily TSP can be within the

standard in the places, where is 50 m away of the field pipeline

The new storage cabinet will be built in the yard of the gas source plant, and the

nearest residential place in Laobian District is 400m away from the factory. With the

above method, the dust during the cabinet construction will affect the residents little.

2. Exhaust Waste Gas Impact from the Vehicle Analysis during Construction

The amount of waste gas from the vehicle is minor; most of the pipes will be

built near the main traffic line in the urban area, and the gas source plant locates by

the Yingkou-Dalin Road. These roads are quite busy; the additional volume of traffic

flow is not too much. So, the additional air pollution by the vehicles can be ignored.

7

4.2.2 Analysis of the Water Environmental Impact

The waste water during the construction includes the waste water from the

pipeline construction and gas source plant construction.

1. Waste water from the pipeline construction

-waste water for the pipe installation

Most of the pipelines will be installed in the urban area. The possibility to touch

the underground water level is quite low. So the waste water is mainly the cooling

water for the mechanics, and washing water for the transportation, and the waste

water with oil dropped by the mechanics, the total volume of waste water is minor. If

it rains, the water resistant instrument in the construction field can reduce the flow to

take the dust, sands, rubbish, and waste soil away. The waste water fits the standard of

the treatment factory, so it will be sent to the drainage treatment plant for treatment.

So, the minor amount of waste water can be controlled in the limits of the standard by

means of the above methods.

- Waste water while across the pipeline

The main pipe will come across the rivers for 7 times, except the pipe with

bridge installation will be used in the Bohai Street across Qinbai River, the directional

digging methods will be used in the rest places.

During the directional digging methods, a little waste mud and solid waste will

be produced. The main component of the mud is bentonite and a little addition agent,

which are non-poisonous and harmless. But if the mud comes into surface water

directly during the rainy season, it may raise the percent of sands in the nearby rivers,

canals or drainage pipelines; increase the amount of suspended particle in the river

and the turbidity degree. This report requests mud-collecting and disposal pool set up

by the borer, only the supernatant fluid is allowed to be discharge. With the above

methods, the affection to the water quality during the construction can be limited in

the acceptable range and no obvious affection appears in the water environment.

Pipe with bridge installation will be used in the Bohai Street across Qinbai River,

since no ships needed, there will be no affection to the water environment.

2. Waste water in gas source plant during construction

The construction of this plant is a general construction, which waste water is the

8

cooling water for the mechanics, and washing water for the transportation, the

waste water with oil dropped by the mechanics, and domestic waste water

produced by the constructors. This construction area is quite small, waste water

produced by mechanics is not much; most of the waste water is domestic waste

water. The report requests Yingkou Coal Gas Company to install a whole set of

domestic waste water treatment before the cabinet construction, which can

make the domestic waste water fit Grade II of LiaoNing local standard on

discharge of wastewater and exhaust gases (DB12-60-89).

With those methods, the waste water during the construction of the plant can be

controlled in the acceptable range.

4.2.3 Analysis of the Acoustic Environmental Impact

Most of the pipelines located at the main streets or road of Yingkou City, which

will affect the daily life of the citizens. So, nighttime construction is forbidden,

besides, even in the daytime, strict methods will be carry out to reduce the noise

affection to the environment. The project should adopt the method of segmental

construction to reduce the impact the surrounding residential area. the impact is

temporary and acceptable.

The noise in different stage of the construction will be controlled between 85-

100dB (A), the noise source is intermittent during the construction. Since there are not

residential areas or other environmental hot places within 1000 m of the field, and

only daytime construction allowed, there will be no affection to the residential.

4.2.4 Analysis of the Ecological Environmental Impact

This cabinet construction will be built in the existing plant, no new land

occupied.

1. Temporary Land Occupation

Pipelines reconstruction will be done to the original pipe places, no trees will be

felled; new pipes will be done in the pavement’s reserved gas pipe areas of the new

roads; suburbs pipe reconstruction areas are mainly dry lands. Since the construction

will be made from January to April, affection to the plants is little. In the urban area,

9

people and the mechanics dig together, the stage excavation method is adopted in the

cultivatable land and protect the former ecological environment for the landfill with

the bottom soil which is separated from the surface soil when digging. In addition, the

accumulated landslide should be reserve to prevent the ground surface sink and soil

and water loss for the runoff and rainfall. The soil used for the landfill is the deserted

soil and disposal properly in the field. The environmental impact on the ecological

will be reduced with the above methods.

2 River-crossing impact

The river-crossing methods of the project are pipe with bridge installation and

directional digging methods. Since directional digging method will not touch the

water, and pipe with bridge will not use a ship, there will be no affection to the river.

And the affection to the water environment is temporary, so this minor affection will

become less and less, and disappear finally.

4.2.5 Analysis of Solid Environmental Impact

Solid waste during construction includes: waste pipes and valves, domestic waste

produced by the constructors, waste soil during pipe construction, dry-mud during the

digging, and the building waste during the construction of gas source reconstruction.

1. The weight of waste pipes and valves is about 1400t, can be recycled and sold

out, which will not affect the environment.

2. The total amount of domestic waste of the pipe and factory construction is

about 130kg/d, which will be collected by Yingkou Environmental Sanitation

Department, there will be little environmental affection.

3. Most of the pipe working is old pipe update and the digging soil equals to

refilling, the new medium-pressure gas pipe locates at the new road of Zhuanglin

Road and Qinghua Street, the solid waste can be used as the roadbed, the construction

waste can be used to pave the road.

With the above treatments, the solid waste cannot affect the environment

seriously.

4.2.6 Analysis of the Society and Traffic Impact

The range of this project’s pipeline is quite broadly, especially in the main road

10

of the urban area of Yingkou. Since these streets are busy, and many passengers

nearby, the construction field will occupy the non-vehicle roads and pavement, which

will affect the traffic seriously. The noise of it will affect the residential. After the

construction plan has been made, it should be declared to the public in advance, to

minimize the affection of the citizen’s daily life and traffic.

But the pipe construction is step by step, and the affection is temporary and part,

as soon as the construction finishes, the impact will be disappear. By the conversation

with the residence, and get the understanding, the impact to the society and traffic can

be acceptable.

4.3 Analysis of the Environmental Impact in Operation

4.3.1 Analysis of the Ambient Air Impact

This project can not only change the rotten and old gas pipes of Yingkou city,

which will reduce the gas loss, but also will raise the natural gas consumption of the

city, so that change the energy consumption structure, reduce the consumption of coal,

so that the SO2 and dust can be reduced, which will clear the atmosphere of Yingkou

City.

Besides, according the requests of the evaluation, as the building of 50,000 m3

dry-style gas storage cabinet, the 2 old 4 ton steam boils’ dust remover will be

updated. As the engineering analysis, after the update of the dust remover, the smoke

can be limited as lower than 97 mg/m3 which fit the standard. The reduction of smoke

discharge is 12.3t/a, or 80%. It can improve the air condition around the gas source

plant.

4.3.2 Analysis of the waste water impact

As the construction analysis, this project will not increase the waste water

discharge of Yingkou Coal Gas Company, and as the request of this evaluation, the

plant should install a whole set of domestic waste water treatment, which can make

the domestic waste water fit Grade II of LiaoNing local standard on discharge of

11

wastewater and exhaust gases (DB12-60-89). all the pollutants in the waste water will

be lowered. It can improve the water quality of Laobianhe River.

4.3.3 Analysis of Noise Environment Impact

The Noise of the project is the running noise of the new gas compression

machine (85-90dB(A)). The new machine located inside the original machine room,

which can reduce the noise at about 25dB(A), the noise value after the distance decay

to the plant boundary and superimposed the existing boundary noise is as table 4-4.

Table4-4 Forecasting results of the boundary noise of gas source plant Unit: dB(A)

New Noise Source

Source Noise

Noise mitigation measure

Noise source

after themitigation measure

Forecasting point

Distance to the noise source

Abatement value

Influence value

Background value

Forecast value

Gas Compression

Machine90

Closed-gas Compression

machine Room

65

West Border 27 28.6 36.4

daytime57.0 daytime57.0

nighttime48.1 nighttime48.4

North Border 42 32.5 32.5

daytime63.9 daytime63.9

nighttime53.7 nighttime53.7

East Border 290 49.2 15.8

daytime57.7 daytime57.7

nighttime47.6 nighttime47.6

South Border 412 52.1 12.9

daytime48.7 daytime48.7

nighttime41.3 nighttime41.3

As table 4-4, the boundary noise of the gas source plant will keep the existed

level and do little impact on the boundary noise and meet the requirement of Standard

for Noise at Boundary of Industrial Enterprises Grade Ⅱ(GB12348-90).

And, the instant noise while the new pressure adjustment station pipe’s pressure

is too high, noise reduction instruments and methods are applied. The new stations

located at the main crossroad with the equipment of the overpressure exhaust pipe

fitting the mufflers meet the requirement of Standard of Environmental Noise of Urban city

Gradeⅳ(GB3096-93)4.3.4 Analysis of Solid Waste Environment Impact

The solid waste of this project is the old filter of the 3 new adjustment stations.

12

The amount is about 0.006t/a. the waste filters are general solid waste, and the amount

is minor, which will be sent to Yingkou Solid Waste Treatment Plant, which will not

affect environment.

13

5 Environmental Risk Assessment

According to environment impact assessment documents, considering the project

features and Identification of major hazard installations (GB18218-2000), the

functional unit of the project is gas tank and pipeline of the natural gas; hazardous

substance is natural gas.

5.1 Environmental protection target

According to the geographical locations, there are two parts –gas source plant

and gas pipes – in this project.

1) Gas source plant

The air protection residential area is a circle within a radius of 3km, which centered at

the gas tank according to the regional environment situation. The detailed information

is as table 5-1.

Table 5-1 Residences distribution within the3k scope of the gas source plant

Code Redisence Name Type Resident Population

Orientation Direct

distance(m)Oritatio

n 1# Laobian Jiedao Urban 28000 1000 NW

2# Laoyemiao Villiage Countryside 1800 2100 SSW

3# Zhaoping Villiage Countryside 1100 1100 S

4# Chenjiadianzi Countryside 1100 2600 SSW

5# Guojiapuzi Countryside 1500 1600 NE

6# Wangjiapuzi Countryside 1700 2200 NNE

7# Sidongfang Countryside 700 400 NNW

Total 35900

2) Gas pipeline

The natural gas has been transferred from Dapingfang Gas Staion, Liaohe Oil Field to

the gas source plant and the urban area via underground pipes. The length of the high-

pressure pipe (0.6MPa) is 6 km, middle-pressure pipe is about 51.8km (0.4Mpa:

37.1km, 0.15Mpa: 14.7km). Considering the different danger of the pressures, the

range of the evaluation includes the above middle and high pipeline only.

14

5.2 Environmental Risk Types

As the techniques of storage and transfer of natural gas have been adopted in this

project, the environmental risk types are are as table 5-2.

Table 5-2 possible impacts and their features

Technique Types Danger Possible reasons

Natural gas tank

Gas Leaking

Fire/Explosion

Human Health

1 tank, joint pipes, valves broken 2 Misoperation

FireExplosio

n

Property damageDeath

Environmental Pollution

1 gas leaking2 leaking gas has been lit up by fire, explosion3 leaking gas has been lit up by mechanics or electricity, explosion

Natural gas pipline

Gas Leaking

Fire/Explosion

Human Health

1 pipe corruption/Perforation2 leaking because of the flaw3 Construction Quality4 joint valve, shim, or sealed accessories are broken5 Misoperation6 damaged by the force

FireExplosio

n

Property damageDeath

Pollution

1 gas leaking2 leaking gas has been lit up by fire, explosion

5.3 Risk probability and the confirmation of the sources

(1) Storage Unit

The probability of the fire/explosion of the natural gas tank in this project is

4.0×10-7/a, referenced by domestic statistics.

The ordinary banks leak usually occurs at the jointing of the tank and the pipe, or

the valve. Here, we presume that the jointing part of the gas-in pipe/gas-out pipe

break in one of 50,000 m3 tank, and the natural gas leaks, the operators have stopped

the gas leaking within 30 minutes. After calculation, if the gas-in pipe is broken, the

leaking rate of the gas is 0.046kg/s, the amount of leaking gas is 82.8kg; if the gas-out

pipe is broken, the leaking rate is 0.062kg/s, the amount of leaking gas is 111.6kg.

(2) Transportation units

15

After the construction, the length of the high-pressure pipe (0.6MPa) is 6 km,

middle-pressure pipe (0.4Mpa) is 37.1km. We presume that two kinds of pipes are

broken, the leaking part is 60% of the diameter with 20mm perforation. The

calculation result for 30 minutes’ leaking is: for 0.6Mpa pipe, the leaking rate is

2.01kg/s, the amount of leaking gas is 3618kg; for 0.4Mpa pipe, the leaking rate is

1.34kg/s, the amount of leaking gas is 2412kg.

5.4 Consequence Calculation

5.4.1 Consequence calculation for the explosion range after

leaking

1. Diffusion pattern of the natural gas

The calculation of the diffusion pattern of the natural gas should adopt the non-nomal

emission pattern Technical guidelines for environmental impact assessment (HJ/T2.1-

93)

2. The estimation of the range of the flammable explosion

Take longest distance at the lower explosion limit concentration for the natural gas in

the Leeward approaches – 33g/m3, as the longest dangerous radius. In different

meteorological condition, time, and the leeward distance from the incident place. The

result is as table 5-3.

Table 5-3 The forecast for natural gas expansion

Incident Time (min) Wind speed(m/s) Stability Downwind distance from the leaking point

Jointing for the tank and gas-in

pipe broken30

3.3 D -

1.0 B -High

pressure(0.6MPa ) pipe broken

303.3 D -

1.0 B 6Middle

pressure(0.4MPa) pipe broken

303.3 D -

1.0 B 5

As table 5-3, if the jointing for the tanks and gas-in pipe has been broken for 30

16

min, the density of the leaking gas cloudy cannot reach the explosion limit if it is

windy or breezy; if the High pressure(0.6MPa ) pipe or Middle pressure(0.4MPa) pipe has

been broken for 30 min, the density of the leaking gas cloudy cannot reach the explosion

limit if it is windy, the leeward explosion distance will be 6m and 5m if it is breezy.

5.4.2 Consequence calculation for the fire explosion after leaking

This part takes TNT equivalent method with over-pressure & stamping criteria

to estimate the impact range of the natural gas cloud. The result is as table 5-4.

table5-4 Estimating result for the tank explosion Unit: m

Incident WTNT, kgFatal

RadiusGBH Radius

slight wound Radius

Property damage Radius

Tank explosion after

gas leaking1405.94 27 40 72 83

0.6MPa pipe broken,

then fire causes the

explosion

2882.11 38 56 101 116

0.4MPa pipe broken,

then fire causes the

explosion

1921.41 33 49 88 101

As table 5-4,

If the explosion incident happens after the tank’s gas leaking, the Fatal Radius,

GBH radius, slight wound radius, and property damage radius are 27m, 40m, 72m.

and 83m. As the investigation, the closest residential point is 100m away from the

point, so the tank explosion will damage little outside the factory.

When 0.6MPa pipe is broken, then fire causes the explosion, the Fatal Radius, GBH

radius, slight wound radius, and property damage radius are 38m, 56m, 101m, and

116m.

When 0.4MPa pipe is broken, then fire causes the explosion, the Fatal Radius, GBH

radius, slight wound radius, and property damage radius are 33m, 49m, 88m, and

17

101m.

5.5 Risk Calculation and Assessment

5.5.1The acceptable level of the environmental risk

The environmental incident is quite unstable, so the estimation to the aftermath is

very uncertain.

According to the definition of venture:

During the procedure of the calculation, the following equation is used to

calculate the incidental risk (death/year):

Venture=Half lethal percentage area population * 50% * incident probability * weather

probability

The unit for risk is “death/year”. The level of the common incident can be

divided into max acceptable level and ignorable level. In industry and other activities,

the risk levels are as table 5-5.

Table 5-5 Risk level and the acceptable level

Risk (death/year) Risk level Acceptable level

10-3 Very dangerous, equal to the nature death rate unacceptable

10-4 Medium Must be improved

10-5 As the swimming incident or Gas poisoning

People concern it, and would like to take some preventing methods

10-6 As earthquake or other natural disasters People do not concern on it

10-7~10-8 As the meteorite hurts people No one would like to prevent this kind of incident

Chemical-engineering industry is high-risk. The evaluation takes some

recommendation acceptable level according to different country’s situation, as table 5-

6.

18

Table 5-6 Acceptable Risk level of chemical engineering industry(death/year)

reference level Reference Standard

USA 7.14× 10-5

8.33× 10-5UK 9.52× 10-5

China (1980s) 8.81× 10-5

5.5.2 Calculation for the acceptable level of environmental risk

The acceptable level of environmental risk in this project is as table 5-7.

Table 5-7 Acceptable level of environmental riskProject Tank fire explosion Pipe fire explosion

Incident probability 4.0×10-7 1×10-5

Fatal Radius(m) 23.2 74.4

Fatal Range(m2) 1690 17381

Population

Death in the affect area 2×1% 16×1%

Venture (year-1) 2.0×10-7 1.6×10-6

Max risk for the project (Year-1) 3.7×10-6

Acceptable Venture(year-1) 8.33×10-5

As table 5-7, the max venture for the project is 3.7×10-6, which is lower than the

acceptable risk 8.33×10-5.

5.6 Risk Control Measure and Emergency Response Plan

5.6.1 Risk Control Measure

This project is going to set up an SCADA management system for the safety

running of the gas pipe and reduce the potential risks. This system will be controlled

by the administration center at the Yingkou Coal Gas Company’s building. Here, the

standard, layout, equipment models, fire control, automatic management, and running

19

management will be analyzed for the risk control.

(1) Design Standard

The standard of the gas pipe and gas source plant are Code for design of urban and

rural gas supply (GB50028-93, version 2002) and Code for fire protection design of the

buildings(GBJ16-87, version 2001). They are the criteria general acceptable in China,

the existing cases have confirmed the security. So the standard of the pipes and

factory is guaranteed.

(2) Layout for the tank and pipes

Dry-type storage tank

A new 50,000 m3 Dry-type storage tank will be set up to the east of the existing

50,000 m3 wet-type storage tank, the safely distance to the around buildings accord

with Code for design of urban and rural gas supply and Code for fire protection design of the

buildings The width and Radius of turn for the road in the raw gas factory cater to the

requests of fire prevention and transportation.

The new 50,000m3 Dry-type storage tank is more than 150m away from the hot

points outside the factory, such as the resident points. According to the estimation, the

tank explosion affects little outside the factory.

Gas Pipeline

The pipeline from Dapingfang Station to Laobian gas source plant is the existing

pipe. This time, only the pipes from Dapingfang Station to Xintun Pressure-

adjustment station and the part which will come across the Daliaohe River will be

replaced. The routine of the pipe is unchanged. The new middle pressure pipe will be

laid along Zhuanglin Road and Qinghua Street; the middle pressure and low pressure

pipe in the urban areas will be replaced without routine change. Because of the need

of gas supply, the working in residential area is unavoidable and the risk will be

prevented during construction and management.

(3) Equipment models

Type of the tanks

20

A new 50,000m3 Dry-type storage tank, and the accessories, such as pressure

adjustment instrument, flow meter, pipes, compressor, and valves. As the reports, all the new

equipments will be in according with Law of the Peoples Republic of China on Bid Invitation

and Bidding: for the high equality and stability.

Height measurement to the 50,000m3 Dry-type storage tank without height alarm

if the height is above the alarm line sound and light alarm will start.

Combustible gas detector will be set up in the factory’s tank valve room, because

the raw gas factory is the explosion prevent Area, Class A.

Emergency amputation valve and safety out-spreading valve will be set up at the

entrance and exit to the tank, when the tank pressure reaches the level, the valve will

be closed automatically, when the pressure is over the safety valve’s point, the safety

valve will be released automatically, so that the tank can run safety.

Types of the pipeline

According to the report, the update part from Dapingfang to Xintun Pressure

Adjustment Station will take Spiral Submerged Arc Welded Steel, the other new or

update part will use PE pipes. For the steel part, 3 layerss PE corruption-preventing

method will be taken, and 100% Inspection will be made. Valves will be set up every

2km.At all the crossing important rivers parts, and middle pressure start points, valves

will be set up in valve wells or directly. The materials for the pipes and valves will be

in accordance with the standard. All the pipes are underground, so that the damage

from traffic incidents can be avoided.

The possible reasons of the other domestic gas pipe incident are pipe’s quality, or

the not-enough protection to the nearby gas pipe during the other underground

construction. So, after the installation, marked alarm signs with the gas company’s

and police telephone must be set along the pipeline.

Besides, leakage inspection and emergent repairing instruments must be set up,

so that the leaking points can be found quickly and exactly, and emergency repairing

will be possible.

(4) fire control,

21

As Code for fire protection design of the buildings, after the new 50,000 m3 Dry-type

storage tank’s construction, the storage ability for the factory will be 1,200,000 m3,

the fire control water is 30L/s(108m3/h). As 3 hours calculation, the total fire control

water is 324m3.

There is a 600 m3 fire hydrant reservoir to the south of the new tank, which fits

the request of the fire controlling. Fire controlling pipes will be set up as a circle, the

diameter is DN150. 3 and fire hydrants will be set up outside the reservior.

The damage of fire in the raw gas factory is quite dangerous, and the fire caused

by gas is difficult to be controlled, so the most effective way for this kind of fire is to

cut the gas. To ensure the safe running of the factory, combustible gas inspectors, fire

controlling system, and mobile fire extinguishers are quite important for the fire

happen. The other fire extinguishment can rely on the local fire station.

(5) Automatic management

Automatic management is quite an important part for the city gas supply. To

ensure the stable running of the natural gas network and reduce the potential risks, a

SCADA management system will be set up for this project. This system is a 3-level

distributed control system, a controlling center will be set up in the Gas company’s

office building, which is a system administrator in charge of data monitoring; the

SCS, High-middle-low pressure adjustment stations and middle-low pressure

adjustment stations are the 2nd level; RTU System in the network, data collection and

system control are the 3rd level. The 3 layers system combined with cable or wireless

network to work as a SCADA System. 3 SCS will be set up independently along the

high pressure pipes: High-middle pressure adjustment station at Lianmeng Road,

Huanghua Road, and Qinghua Road. 30 valves updated in the middle pressure

network will be set up as distance RTU terminations. These automatic management

systems are not only to ensure the gas supply, but to keep the pipes and factory safe.

(6) Operation management

The operation management includes:

22

Safe and fire protection committee: Voluntary fire brigade, gear groups, Rescue crew, and

Public security Crew. Anti-fire drills will be practiced on time, anti fire plans will be constituted

with the guidance of local fire stations.

Rules, such as safety operation regulation, Fire protection responsibility system, post

responsibility system, daily and preventive maintenance system, and the regular System of

examining and assessment for the staff

Staff safety and technique education, all the worker at the production line will pass the exams

first

Technical document management, regular and daily check/fix

Direct line telephones set in important section for the emergency help

Fire alarm, notice the staff and nearby units as soon as the incident happens

Post set at the entrance to the working area. Post with “Smoking and lighting fires strictly

prohibited.” set on the wall to the working areas and in the living area/

Strictly obey the national and gas industry’s rules and regulation for safety

Regular inspect, management, and maintenance to the fire-fighting equipments

Put out the initial fire in time: operate the firefighting pump, water system, and

use powder fire extinguishers to put out the fire promptly

Cut off the electricity as soon as the leaking gas fire in the station’s workshops.

Close all the related equipment, pipes (close the emergency valves at the entrance and

exit), and take effect methods, report it to the local fire station and controlling center.

The above methods are the existing management methods, system, and

organizations in Yingkou Coal Gas Company.

5.6.2 Emergency Response plan

Natural gas is a kind of inflammable and explosive substances. Although strict

risk preventing methods are taken for the storage and transferring, leaking incidents

are still possible. The leaking gas explosion will be possible with the open fire, which

23

will endanger the nearby people and buildings. So as Technical Guidelines for

Environmental Risk Assessment, Accident emergency predetermined plan must be

made for this program.

The Emergency response plan of accidental risk in this project is as table 5-8.

Table 5-8 Emergency response plan of accidental risk

program Content

1Emergency

Planning Area

Mainly Dangerous Source: Natural gas tank, pipes;environmental protect target: residential areas, hospitals, and schools near the factory and pipes

2Emergency

Organization

Emergency Organizations set by the company. The manager will be in charge of the plan and coordination. The members must be practical workers with certificates; the area emergency organization should include the local government, experts, hospitals and related units, under the local government's dispatch.

3

Level of the plan

Response conditions

Different levels’ emergency predetermined plans and the responses should be made with the severe level of the indicants

4guarantee of emergency

rescueEmergency equipments, gears

5Alarm,

Communication

The alarm/contacts of the emergency staff’s principal departments: contact methods, place, telephone numbers and the traffic, surveillance, firefighting contacts. Keep in touch with the above environmental departments about the area's environment problems and report the latest information to get the supports in different region.

6Emergency

environmental monitoring

Organize a professional team to detect the incident scene, and make an professional evaluation to the incident's characters, parameter, and the effects. The data will be provided to the administrator to make the decision.

7Emergency dealing and

rescue measure

Strictly define the accident-prone locations, incident scene, nearby area, fire-prevention area. Pollution cleanup, enough Equipments, user guides, and operators.

8Emergencyevacuation

Natural gas concentration limits for the people near the incident scene, raw gas factory, pipes, areas. Emergency aid plan, public health protection

24

9RescueClosing program

Setting the related emergency closing program for the dealing of the incidental scene and affected scope and recovery measurement. after the alarm

10Emergency

trainingRegular training and drilling

11Public

Education and information

Public education, training and information release to the place near the factory and pipe lines

5.7 Conclusion

(1) The reference substance is natural gas belong to a kind of flammable gas. There is

the risk of natural gas leaking, fire, and explosion in the process of storage and

transportation.

(2) According to Chinese statistics, the probability of the fire/explosion of the natural

gas tank in this project is 4.0*10-7/a. Compare with the European statistics, the

probability of the fire/explosion of the natural gas tank in this project is 5.7*10-

4/km·a.

(3) If the jointing for the tanks and gas-in pipe has been broken for 30 min, the

density of the leaking gas cloudy cannot reach the explosion limit if it is windy or

breezy; if the High pressure(0.6MPa ) pipe or Middle pressure(0.4MPa) pipe has been broken

for 30 min, the density of the leaking gas cloudy cannot reach the explosion limit if it is

windy, the leeward explosion distance will be 6m and 5m if it is breezy.

(4) If the explosion incident happens after the tank’s gas leaking, the Fatal

Radius, GBH radius, slight wound radius, and property damage radius are 27m, 40m,

72m. and 83m.

When 0.6MPa pipe is broken, then fire causes the explosion, the Fatal Radius, GBH

radius, slight wound radius, and property damage radius are 38m, 56m, 101m, and

116m.

When 0.4MPa pipe is broken, then fire causes the explosion, the Fatal Radius, GBH

radius, slight wound radius, and property damage radius are 33m, 49m, 88m, and

25

101m.

(5) The max venture for the project is 3.7×10-6, which is lower than the acceptable risk

8.33×10-5.

As the above conclusion, this project’s location and construction can be accepted

in the view of environmental protection with strict risk control, environmental risk

control, and emergency response plan.

26

6 The environmental affection reduction

methods According to environment impact assessment documents, considering the project

features and based on pollution discharge process of project construction phase and

operation phase, the environment impact mitigation plans for different phase are given

as table 6-1 and table 6-2.

27

Table 6-1 Mitigation measures for the environmental impact of gas source plantStage

Environmental Affection Mitigation Measures Cost Responsible

UnitStarting

DateImpletion

DateConstruction Noise

1. Arrange reasonable construction time from 7:00 am-6:00 pm, night construction is forbidden 2. To choose the low noise equipments, as the request of table 2-73. Track Monitor the environmental sensitive point and construction boundary, once a day

Small constructor

2008.9 2009.10

Dust

1.Establish the system of the sprinkling water and dust prevention. On the condition of the drying and heavy wind, it must be increase the times of sprinkling water.

2. Setting closed fence around the construction materials piling is not lower than the height of the piles of materials.

3. Setting cleanout equipment of the wheels clay at the entrance and exit of the construction site in order to drive out of the site without the clay on the wheels.

4.Transportation of the Bulk materials will adopt the canned and covered with felt tent linen.5.Setting storeroom for bulk materials or covered the materials with dust screen in order

to stop the open piles up of the bulk materials.6.Clean up building waste in time. Forbid the waste-burning inside the construction site. 7.Setting fence around construction site in order to reduce the diffusing scale of the dust.

minor constructor

solid waste Domestic wastes and construction wastes should be timely collected and transported to the landfill of pointed by the sanitary department in Yingkou covered with felt tent linen..

minor constructor

Waste water

Mainly domestic waste water produced by the constructor should be treated by the integration treatment facility and .meet the requirement Grade II of Liaoning local standard on discharge of wastewater and exhaust gases (DB21-60-89) and be used to control the dust with sprinkling water.

minorconstructo

r

Passage Construction/Usage

Use the roads in existence without building extra transporting passage.minor constructo

rLand leveling/Change the

runoff mode

No minor constructor

28

Stage

Environmental Affection Mitigation Measures Cost Responsible

UnitStarting

DateImpletion

Date

Cultural Heritage

1. Stop the construction as soon as the finding of any cultural heritage, keep the scene, and report it to the administration of cultural heritage.2. Waiting for the identification and treatment of the administration of cultural heritage.3. After the treatment, apply for resume the construction to the administration of cultural heritage.4. With the permission of the administration of cultural heritage, resume the construction with the experts’ advice

Minor Constructor

Air Quality /Plant Site Selection Update the existing boiler’s dust catcher to ensure the standard. Minor Construct

or

Operation

Atmosphere The smog in the boiler comes out of the ceramic multi-tube dust cleaner, 95% of the dust has been taken. Small Yingkou

Noise

To lower the noise in the factory, indecent room should be set for the high-noisy instruments. Independent basic or vibrating isolation methods, such as soft interchange, should be taken for the high-vibrating methods, such as compression machine. The fadeout of the noise and the direction of the noise source should be considered in the allocation plan.

Minor

Yingkou

Waste Water Domestic waste water can be used to prevent the dust after treatment. Part of it can be sent to the urban drainage pipeline network. Minor Yingkou

Solid Waste The solid waste of this project is the 3 new adjustment station’s used filter, which will be replaced on time. The yearly solid waste is about 0.006t/a.

Yingkou

Stage Environmental Affection Mitigation Measures Cost Responsible

UnitStarting

Date Impletion Date

29

Constructi

on

Noise

1 . Arrange reasonable construction time from 7:00 am to 6:00 pm, night construction is forbidden.

2.Choose equipment with low noise.3.Track and monitor.4.Temporary noise barrier shall be built in area near to hospital, residential area and etc.

Minor constructor

2009.3 2009.11

Dust

1. Establish the system of the sprinkling water and dust prevention. On the condition of the drying and heavy wind, it must be increase the times of sprinkling water.

2. Setting cleanout equipment of the wheels clay at the entrance and exit of the construction site in order to drive out of the site without the clay on the wheels.

3.Transportation of the Bulk materials will adopt the canned and covered with felt tent linen.6 . Clean up building waste in time. Forbid the waste-burning inside the construction site.

Minor constructor

Traffic interruption1 This project is constructed closed and do not occupy the lanes when digging in the sideway.2. Shorten the time limit of the road crossing construction .

Minor constructor

Passage Construction/Usage Use the roads in existence without building extra transporting passage. Minor constructor

Vegetation Damage Vegetation quantity and category shall be recovered conforming to original one. Small Yingkou City Gas Company

Cultural Heritage

1. Stop the construction as soon as the finding of any cultural heritage, keep the scene, and report it to the administration of cultural heritage.2. Waiting for the identification and treatment of the administration of cultural heritage.3. After the treatment, apply for resume the construction to the administration of cultural heritage.4. With the permission of the administration of cultural heritage, resume the construction with the experts’ advice

Minor constructor

Excavated materials Management

Storing the excavated materials (for backfill use) in pointed place, preventing from erosion with the covering. Sell the old pipeline to the producing enterprise. Minor constructor

Non-dangerous Waste Removal(Rock and etc.)

Building waste shall be removed to eastern part of the Haicheng waste landfill in Wangshi town. Minor constructor

Solid waste Domestic waste should be collected in the landfill pointed by the government. Minor constructor

Waste water Mainly domestic waste water should be discharge to the urban drainage pipeline network. Minor constructor

30

Table 6-2 Mitigation measures for the environmental impact of pipeline network

31

7 Monitoring Plan and Organization

Arrangement

7.1Monitoring Plan

Yingkou Coal Gas Company must sign the monitoring contracts with Yingkou

Environment Monitoring Station during both the project’s construction period and

operation period. The monitoring station will monitor it according to the plan listed in

Table 7-1~Table 7-2.

7.2Environmental Supervision during the construction

Yingkou Coal Gas Company must sign a environmental supervision contract with a

qualified environmental supervision company (with the certificate of Environment

Protection Bureau). The Environmental Supervision company will supervise the project.

7.3Monitoring Organization Arrangement

To effectively control or relieve different bad environment influence, the whole

process of this project shall be tracked strictly and scientifically. Environment

management and monitoring shall also be carried out conforming to certain criteria,

monitoring and respective managing organization as follows:

32

Contract

1.Monitoring in site, data analyse and statistic and compiling of monitoring report

will be finished by monitoring organization with the qualification commissioned by

Yingkou environmental monitoring station.

2.Environmental official of WB, project office subordinated to Liaoning Province

development and reform commission and the owner (Yingkou Coal Gas Company) will

be in charge of the report receipt.

4 Yingkou Coal Gas Company. Yingkou Thermal Heating CO. Ltd. has authority to

take environment impact mitigation measures during operation period . Contractor of

construction will answer for mitigation measuresof of construction period which will be

supervised by the specific environmental supervision company with the qulification

commissioned by Heating company of Ynag jiazhangzi economic development

Loaner: World BankLoaner Representative: Environmental Official of WB

Client Representative: Yingkou Coal Gas Company

Yingkou environmental monitoring station: Monitor according to monitoring plan of this section and compile monitoring report.

Administrative Dept. of Environmental Protection: Liaoning Environmental Protection Bureau,Yingkou Environmental Protection Bureau

Project owner(Responsible for mitigation

measures for the environmental pollution in operation phase)

Environment protection supervision company: responsible for the supervision of mitigation measures for the environmental pollution during construction and operation period.

Contractor(responsible for mitigation measures for the environmental pollution in construction phase

Report Monitoring ResultReport Supervising Result

Contract

Supervising

Contract

33

34

Table 7-1 Environment Monitoring Plan for the gas source plant

Phase Monitoring factor Monitoring Location Monitoring Method Monitoring Frequency

Monitoring Cost

(10000RMB)

Responsibleunit

Starting Date

Impletion Date

Construction

Noise Closest Residential point

Noise monitormodel HE5623

Once a monthor monitor after complaint 0.3

Yingkou Environme

ntal Monitoring Station

2008.9 2009.10

Dust Construction field Visual survey Daily

6.0

Environmental

Protection Supervising Company

Transport road Along the road Visual survey Daily

solid waste Plant site Visual survey Daily

Waste waterEntrance and exit of the treatment

equipment

Suspended particle: gravimetric analysis method BOD5: dilution vaccination

NH3-N: Nash reagent spectrophotometric method

Petroleum: infrared spectrophotometric method

Once a month 6.0

Operation

Atmosphere emission–dust

Boiler chimney(entrance and exist of the dust

remover)Pitot sample – gravimetric analysis method

Monitoring once when acceptance or after complaint

0.8(Approval

Check)

Atmosphere discharge –

SO2

Boiler chimney(entrance and exist of the dust

remover)Pitot sample – wet chemical analysis method

Monitoring once when acceptance or after complaint

0.8(Approval

Check)

Noise 1m outside the factory

Noise monitor model HE5623

Monitoring once when acceptance or after complaint

0.2(Approval

Check)

35

Waste water Entrance and exit of the treatment

equipment

Suspended particle: gravimetric analysis method BOD5: dilution vaccination

NH3-N: Nash reagent spectrophotometric method

Petroleum: infrared spectrophotometric method

Monitoring once when acceptance or after complaint

0.6(Approval

Check)

Solid waste Plant site Visual survey Monitoring once when acceptance or after complaint 0.1

Table 7-2 Environment Monitoring Plan for the pipe system reconstruction

Phase Monitoring factor Monitoring Location Monitoring Method Monitoring Frequency

Monitoring

Cost(10000RMB)

Responsibleunit

Starting Date

Impletion Date

Construction

Noiseclosest dense

population area to the pipe and road cross

Noise measuring instrument

model HE5623

Once a monthor monitor after complaint 0.3

Yingkou Environme

nt Monitoring

Station

2009.3 2009.11

Dust On the way of transporting passage

Visual survey Daily Check

6.0Environmental Protection Supervising Company

Traffic interruption(pavement to the

business points)

On the way of transporting passage and

business points

Visual survey Daily Check

Passage Construction/Usage

On the way of transport road Visual survey Daily Check

Land: Bared/ erosion

pipe / road cross and the way of it Visual survey During or after storm

36

Cultural Heritage

Building Site or on the way of passage

construction-any place where dig is done

Visual survey Daily

Excavated material Management

Pipe/road crossAny place of digging

At dumping siteVisual survey Daily

Non-dangerous Waste Removal (eg. Stone) At dumping site Visual survey Daily

37

7.4 Category and Content of Monitoring Report

8.1.1Category and Content of Monitoring Report

Monitoring report consists of construction and operation monitoring report.

Perform analysis, assessment on the results during the construction and operation

monitoring period in accordance with relevant standard, with the explanation of

monitoring site, sampling time and monitoring factor.

Assess the result of environment mitigation measures conforming to monitoring results.

Discuss or negotiate with environment supervision organization, environment impact

assessment group to improve or replacement for the bad mitigation measures.

7.5 Submitting Time and Monitoring Report Accepter

(1)Submission of Monitoring Report

In construction phase, monitoring report shall be submitted each month with the

phase of the construction. Comprehensive report shall be submitted after construction

accomplishment.

(2)Monitoring Report Acceptor:

Monitoring report shall be submitted to Yingkou Environmental Protection Bureau,

Liaoning Environmental Protection Bureau, Yingkou Coal Gas Company and World

Bank.

7.6 Feedback Requirement of Monitoring Report

Each acceptor shall give their feedback in a month after receiving the report.

Acceptor shall analyze and assess report content within feedback time limit; confirm

whether the environment mitigation measures are effective or not; arrange following

work and bring forward relevant requirements.

Acceptor also shall bring forward improving advice and regulatory scheme (if

applicable)on environment mitigation measures within feedback time limit.

38

8.Reinforcement Plan of Environment Managing Organization

All employees shall be trained with environmental protection knowledge and skills

especially the constructors in order to carry out this project smoothly and effectively.

Training includes not only the importance and meaning of the pilot project, but also

different training emphasis for employees in different position according to the

management level and the importance of the environmental protection position. See

details in Table 8-1.

Table 8-1 Training Plan for Environmental Protection Technician

Personnel Training Content Mode Number of Trainee Time(Day) Expense( Unit in

10000RMB)RMB

Constructors of Environmental

Protection

Environment Basic Theory, Monitoring Method, Compiling Monitoring Report and Position Training

Domestic 10 2 2.0

Environment Protection Supervising

Engineer and Environment

Managing Staff of Contractor

Environmental Protection Code, Construction Programming, Environment Monitoring Rule and Criterion.

Domestic

1-2 for each construction phase, 2-4 of

contractor

32.0

Noise monitoring and control technology Domestic 6 4

9 Public Participation Plan

9.1 Continuous Public Participation Plan

A random callback survey should be conducted each quarter during the construction

period and within 3 years after the project comes into operation. Besides, on-site

investigation meeting where there is a public participation should be held annually in

the area where environment-sensitive targets are centralized.

Based on the quarterly survey and annul findings, appraise the public and perfect the

environmental mitigation measures if necessary.

9.2 Channels for complains of dissension

Establishment and composition of complaint organizations

39

A complaint system will be established to better secure the legal rights of the

affected person and provide an easy, transparent, fair and effective channel for complaint.

Therefore, The Leading Group For Accepting The Environmental Impacts Complaints

occurred under this project has been set up, which consists of the group leader who are

working in Yingkou Environmental Protection Administration, and the members from

Environmental Monitoring Station and other organizations for environmental impact

assessment. Office for Accepting Complaints, which is affiliated with the Leading Group

for Accepting the Environmental Impacts Complaints, is set up in Yingkou Environment

Protection Administration. The daily complaints should be accepted and sorted by the

Office for Accepting Complaints which shall, after negotiating with the relevant

organizations reliable for the complaints, put forward treatment opinions.

Complaint procedures

The Leading Group and the Office for Accepting Complaints will accept the

complaints filed by the public within one week after the construction starts. Bulletin

boards should be erected in all construction sites during the construction periods and

personnel responsible for the safety & environmental protection should be appointed.

Meanwhile, special lines and mailbox should be opened for complaint. The detailed

procedures for complaints are stated as follows:

In case that the affected person deems that his own right involved in the

environmental protection have been violated, he may file a complaint thereof to the

Complaint Acceptance Office, in written or verbal form. If a verbal complaint is filed by

the affected person, members working in the Complaint Acceptance Office shall make

detailed records of the complaint, sort those records afterwards, and submit treatment

opinions within two weeks.

In the event that the complainer is not satisfied with the solution provided by

Complaint Acceptance Office, he may file a complaint in writing to Yingkou

Environmental Protection Administration which will make opinions for handing with this

complaint within three weeks.

In the event that the complainer remained unsatisfied with the proposals by Yingkou

Environmental Protection Administration, he may, upon receipt of the proposals, bring

his complaint to the local court, to be judged by the court pursuant to The Civil Procedure

Law of the People s Republic of China.

40

10 Implementation Fee of EMP Implementation Fee of EMP includes the cost of employee training, environmental superintendence and environmental monitoring during conduction. See chart 10-1 and 10-2 for details.

Table 10-1 Budget for the EMP and Capital source Unit: RMB10,000 yuan

Item 1 year

(construction) budget

1 year (operation) budget Capital source

Salary 15 15

Domestic matched fund

Office cost 3 3

Traffic cost 2 2Supervision cost 6.6 2.9

Supervision engineer budget 12 0Budget for the whole

environmental management plan

38.6 22.9

Table10-2 Training Cost Unit: RMB10,000 yuan

members Fee Capital source

Constructors of Environmental protection 6 3

Domestic mathed fund

Supervision engineer during the construction, and

environmental mangers during the operation period

5 2.5

Total - 5.5

As the budget, total EPM fee is RMB 441,000 yuan, which is the domestic matched fund.

41