· web viewstatus quo: ream properties are currently in a poor condition with numerous complaints...
TRANSCRIPT
SUPPLY CHAIN MANAGEMENT
SCOPE OF WORK
PROJECT DESCRIPTION: APPOINTMENT OF A QUALIFIED CONTRACTOR FOR
NATIONAL STATIONS IMPROVEMENT PROGRAMME
(NSIP) AT SILVERTON VACANT LAND FOR THE
CONSTRUCTION OF CONCRETE PALISADE FENCEING,
GATES AND A GUARDHOUSE
TRANSACTION: APPROVAL TO PROCURE A QUALIFED CONTRACTOR
WITH A CIDB GRADING OF 6 GB
END USER: PRASA CRES
(REGION / DEPARTMENT): PRASA CRES /SPPM NORTHERN GAUTENG REGION
(NGR)
1. Introduction
Silverton PRASA Station is situated approximately 25 km from PRASA CRES NGR
offices in Pretoria, Paul Kruger Street. The station consists of the following:
Vacant Land
Trespassing or SquattingA major vacant property concern is trespassing or squatting. Homeless people looking
for easy shelter may seek out vacant properties. In the process, they can cause damage
to the building and may reside there for an extended period of time. Homeless people
are not the only trespassing threat for vacant property; people often break into vacant
Page 1 of 12
properties to engage in more nefarious, illicit activity. The longer a squatter stays in a
vacant property, the higher the possibility that large levels of trash and waste will be left
behind.
The main strategic objectives to be achieved under this programme are the operational effectiveness, risk management and strengthening of the financial position of PRASA.
2. Background Information
Status quo: o REAM properties are currently in a poor condition with numerous complaints
received from the End-User. o End-User has thus identified vacant land that requires intervention of the
National Station Improvement Programme.
Problem statemento REAM assets are currently in poor condition and require intervention through
NSIP.
3. Objective of the Proposed Project
The request is to acquire a qualified and well capacitated main contractor with a CIDB grading of 6 GB to assist with the repairs and renovations of the facility.
The design and costing (Stage 1 to 4), have been completed. Therefore, the requisition is to appoint the contractor for implementation of the project.
The request based on the above therefore is to acquire a qualified and well capacitated
main contractor at CIDB Grade 6GB to undertake the abovementioned works and
complete the project by 5 months.
4. Scope of Works and Areas of Focus
4.1. Palisade Fence Scope of Works
1.1 EARTHWORKS Site Clearance
Classification and nature of materials to be excavated
Excavations (Bulk)
Removal of services
Carting away of excavated materials
Risk of collapse of excavations
Keep Excavation Free from Water (KEFFW)
Page 2 of 12
Compaction of surfaces
Dewatering
Filling
Foundation Courses
Weed killers and insecticides etc.
1.2 CONCRETE, FORMWORK AND REINFORCEMENT CONRETE
Concrete footings;
Concrete surface beds;
Concrete components such as, lintels, hollow blocks, prefabricated beams and
spacing tiles etc.
Concrete Palisade Fencing
4.2. Guard House Scope of Works
1.3 PRECAST CONCRETE precast concrete components
Coping, sills, etc.
Slab paving
1.4 MASONRY Erection of the superstructure face brick walls
Reinforcement
Window sills
1.5 WATERPROOFING
Install waterproofing to walls
1.6 ROOF COVERINGS
IBR Roof Sheeting
Roof Trusses;
Eaves and Verges.
Page 3 of 12
1.7 CARPENTRY AND JOINERY
Installation of doors;
Installation of timber skirting;
Installation of fascias and barge boards.
1.8 CEILINGS, PARTITIONING AND ACCESS FLOORING
Installation of ceilings and cornice.
1.9 IRONMONGERY
Supply and install toilet roll holders, towel holders, and soap dispensers.
Supply and install 4-lever lockset;
Supply and install door stops.
Supply and install vehicle gate and pedestrian gate
1.10 METALWORK
Supply and installation of steel window frames;
Supply and installation of steel door frames;
1.11 PLUMBING AND DRAINAGE
Supply and installation of wash hand basins;
Supply and installation of water closets;
Supply and installation of urinals;
Supply and installation of sewage systems;
Supply and installation of rain water goods;
1.12 PLASTERING
Plastering to be applied to face brick wall
Page 4 of 12
1.13 GLAZING
Supply and installation of aluminium windows.
1.14 TILING
Supply and installation of wall tiling to plastered walls
Supply and installation of floor tiling to finished floors.
1.15 PAINTING
Supply and apply painting to plastered wall;
Ceiling boards;
Metalwork;
Timber doors
1.16 ELECTRICAL WORKS Supply and install lighting
Supply and install Distribution Board
Supply and install wiring
Motivate why is this the preferred option
The motivation to go out on open tender is to source the most competitive and
capacitated bidder through vigorous SCM processes. The process based on the
SCM policy and guidelines will assist to appoint a reliable and reputable contractor.
5. Specifications of the Work or Products or Services Required
Page 5 of 12
The Specification that will be applied for this project is as per the PRASA Office
specification Blue Print. See attached.
The project will require a Contractor that is graded on the CIBD as 6GB and above. The
contractor required should be able to deliver works as per the specifications.
The following sample pictures depict the current status of the stations, earmarked for
improvement under NSIP.
Pictorials
Page 6 of 12
Page 7 of 12
Location Map
6. Evaluation Criteria
The evaluation should be done in three stages as follows:
Stage 1: Compliance Requirements
Bidders shall comply with the following requirements and failure to comply may lead to disqualification: [List of project specific compliance requirements].
a) Valid Tax Clearance Certificate (must be valid on closing date of submission of the proposal);
b) Valid BBBEE Certificate from a SANAS accredited rating agency
c) Completed and signed Bid Forms of PRASA with all the annexures thereto;
d) Certificate for Attendance of Compulsory Briefing Session;
e) Retention or Guarantees
f) Company Registration Documents;
g) Letter of Good Standing (i.e. COID);
h) Contents of Register of Directors as issued by CITC;
i) Joint Venture or Consortium Agreement (whichever is applicable);
j) Proof of UIF registration;
Page 8 of 12
k) Proof of Bank Account (i.e. cancelled cheque or letter issued by the bank);
l) Copies of Directors’ ID documents; and
m) Company Letter Head.
n) CSD Registration
Stage 2: Technical / Functionality Requirements
NOTE: The Technical or Functionality criteria must be guided by the project scope of works and area of focus.
Scoring of Functionality:
Bidders that meet the stipulated compliance requirements will be further evaluated on functionality. The minimum score for functionality is 70% and bidders who score below this minimum will not be considered for further evaluation in terms of price and B-BBEE.
Page 9 of 12
Evaluation Criteria
Application
1 = Poor; 2 = Average; 3 = Good; 4 = Very Good; 5 = Excellent
Weights
Completion for building and construction projects of similar scope and budget (CIDB 6 GB Grading), or higher. References should be accompanied by completion certificates from the Client)
Score will be based on successfully executed and completed similar projects in the Civil Engineering and Construction environment over the last five years of which details are provided:
Submit proof of :
Similar Type – Office Blocks, Tenant Installation, Houses, Building Refurbishments, Building Renovation, each project equal or exceeding the value of project on tender
Attach letters of Appointment and Completion Certificates
5 = proof of 5 projects and above
4 = Proof of 4 Projects with similar CIDB Grading
3 = Proof of 3 Projects with similar CIDB Grading
2 = Proof of 2 Projects with similar CIDB Grading
1 = Proof of 1 Projects with similar CIDB Grading
35
Experience key staff (assigned site personnel) in relation to the scope of work
Submit proof of :
At least one registered professional or Candidate Construction Manager with 5 year experience with CVs and qualifications
Supporting Site personnel – Lower Qualifications such as National Diploma, N3-N6 Certificates, Trade qualifications (Relevant to Construction Projects)
5 = CV with qualifications, BSC Eng or B-TECH and Professional Registration supported by lower qualifications
4 = CV with qualifications, National Diploma Professional Registration supported by lower qualification including trades qualifications
3 = CV with qualifications, National Diploma supported by lower qualifications including trades qualifications
2 = CV with qualifications, N3-N6 including trade qualification
1 = In adequate qualifications and experience (CV only)
25
Page 10 of 12
Stage 3: Pricing and BBBEE
Only Bidders who have achieved the 70% minimum threshold for Technical / Functional
evaluation will be evaluated for the Price and B-BBE components.
Pricing Evaluation: A maximum of 80 points is allocated for price. The evaluation for price will be done based on
the following formula:
Ps=80[1−Pt−PminPmin]
Where:Ps = Points scored for price of tender under considerationPt = Rand value of tender under considerationPmin = Rand value of lowest acceptable tender
B-BBEE Evaluation:
A maximum of 20 points is allocated for B-BBEE. The allocation of points for B-BBEE is as
follows:
B-BBEE Status Level of
Contributor
Number of points( 90/10
system) above R50 Million
Number of points (80/20
system) below R50 Million
1 10 20
2 9 18
3 6 14
4 5 12
5 4 8
6 3 6
7 2 4
8 1 2
Non-Compliant Contributor 0 0
Page 11 of 12
Evaluation criteria Weighting
Stage 1: Compliance Requirements
Security Screening Compliance
CIDB Grading 6 GB
Bank Rating Compliance
Stage 2: Technical / Functionality Requirements
Technical Threshold of 70 %
Stage 3: Pricing and B-BBEE
BBBEE 20
Price 80
TOTAL 100
Page 12 of 12