28.9.-3.10.02, M oscow V. Korbel, Report on my v isit 1 Visit at ITEP Discussion on TFS tests: ---LY (problem with 7x7 cm 2 TFS) ---uniformity ---TFS optimisation ---prototype module design construction TFS tests: ---uniformity (5x5cm 2 ) with -source, ITEP scanner, 400 points dA/A: ~ 6%, (DESY: similar results) need to improve? Simulation studies? ---ITEP will test more DESY-TFS samples, conditions: to mark groove side all sticky tape on bottom side no additional reflector or other material on top side (add. material dE/dx for source) WLS-fibre: LY: circle aside 5x5 270 125 7x7 370 150 9x9, 16x16 decreasing as expected need simulation studie Some (small) disagreement in absolute LY as measured in DESY and ITEP Micha Danilov, Vladimir Rusinov, Eugeny Tarkowsky

Upload: warren-wynn

Post on 03-Jan-2016

46 views

Category:

Documents


0 download

DESCRIPTION

Visit at ITEP. Micha Danilov, Vladimir Rusinov, Eugeny Tarkowsky. WLS-fibre: LY: circle aside 5x5 270 125 7x7 370 150 9x9, 16x16 decreasing as expected need simulation studies. Discussion on TFS tests: ---LY ( problem with 7x7 cm 2 TFS ) - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 1

Visit at ITEP

Discussion on TFS tests:---LY (problem with 7x7 cm2 TFS)---uniformity---TFS optimisation---prototype module

designconstruction

TFS tests:---uniformity (5x5cm2) with -source,

•ITEP scanner, 400 points•dA/A: ~ 6%, (DESY: similar results)•need to improve? Simulation studies?

---ITEP will test more DESY-TFS samples, conditions:•to mark groove side•all sticky tape on bottom side•no additional reflector or other material on top side (add. material dE/dx for source)

WLS-fibre:LY: circle aside5x5 270 1257x7 370 1509x9, 16x16 decreasing as expected need simulation studies

Some (small) disagreement in absolute LY as measured in DESY and ITEP

Micha Danilov, Vladimir Rusinov, Eugeny Tarkowsky

Page 2: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 2

Visit at ITEP

tile plates:which sizes to cast? 15x15cm2?Than machining of the smaller tile profiles, e.g. 9 tiles of 5x5cm2 ?Impossible to make >38 different tile sizes by castingre-evaluate the DESY test beam results:

•is the ratios correct?•total sum outside hit tile?

Study machined prototype with grooves filled with reflective glue?

tiles:cleaning procedurereflector: mating vs. “silver-$”

fibres:fibre cutting with TiO2 knife, produce one device for DESY?fibre end in tile side wall covered with small 3M mirror foil, glued to tilehot loop bending (110-120 degree)test LY of Y11(100, 150,200)study again some Bicron fibres?Interest on fibre-fibre fusing, device from DESY >>> ITEP

Page 3: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 3

Visit at ITEP

Which scintillator to use?Small tiles from Russian scintillator? Homogeneity ok.Larger tiles show wide dips around fibre position (at loops)and lower LY.

Optimisation, use:•BASF-136 for small tiles (~70% of total area, ~80% of tiles)•BC-408 or BC-404 for large tiles (~30% of area), 15/38 layers

Page 4: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 4

Visit at ITEP

Discussion on TFS teststo do:DESY:

more 3M reflector to ITEP, also more Y11 fibres,some Silver -$ paint for fibre end coating

ITEP:•LY and uniformity for the DESY and Protvino TFS, X-check!•Study optimal doting of WLS: Y11(100)...(300)•Study TFS readout with fixed loop diameter but increasing tile dimensions (also simulation?)• Silver -$ paint and glued 3M as fibre reflector• fibre end || to tile border, finishing polish for both together•fibre/fibre fused connections, (DESY orders glass tubes)

Page 5: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 5

Visit at ITEP

Discussion on module construction:

---split ss absorber plate in 2 parts, e.g.:•17 mm structure plate•3 mm TFS support plate, to be inserted in stack structure after assembly need special rigid inter-connections ? (grooved rails and special fixing bolts)---to improve design of 38 plate prototype next 3 month! thicker absorber plates towards module end ?

> less tile layers, less scintillator better granularity with same number of channels?

Page 6: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 6

Visit at MEPHI

Development of Si-PMs People involved:Boris Dolgoshein, Elena Popova, Serge Smirnov (MEPHI), ~5 more peopleSergei N. Klemin, PULSAR enterprise

--signal shape: 1ns slope, 10ns FWHM--photocathode :

15% efficiency, 1x1 mm2 or 2x2 mm2,3x3 mm2 to many rejects >> increase of costs

--operation voltage ~ 55 V, --all signals can be adjusted in amplitude:

• by -source to same gain, using the very narrow 1,2,3,4 Poisson distributed p.e. peaks. size of -signal ~ 1.35 MeV, near to MIP signal !

• and by cosmic MIPs: for calibration to equal signal amplitude for each tile in a cell.• since cells have different # of tiles: cell signals have to be adjusted to the optimal range in the ADC

Page 7: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 7

Visit at MEPHIProposed: to connect single Si-PM’s to each individual tile: >>>>- ~5000 Si-PM’s for HCAL prototype,- ~800000 Si-PM’s for TESLA HCAL.

Alternatives:1. Connection to each single clear fibre at end of tile-plate:

-optical connector needed to connect optical fibre with Si-PM,-connector adapted to a Si-PM array with pitch distance ~1.5 mm, -photodetector mask similar to mask for APD-array? -to develop such array-connector mask with holes for fibres, -each fibre in hole fixed by little droplet of “Sekundenkleber”-Si-PM photocathode needs mechanical protection from optical-fibre end by a thin plastic disk probably,

2. Connection in tile: (see V. Rusinov, ITEP)-Si-PM inserted in milled groove, 2x2x5 mm3 -and directly glued to the tile and a short WLS fibre,-maximum optical LY expected.

-inefficient tile volume: 20/12500 = < 2%o -nuclear counter effect small, 2 m thick sensitive layer only3. No WLS -fibre at all, direct view of scintillator (studies in ITEP)

Page 8: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 8

Visit at MEPHI

Signal RO from Si-PM: see also Vladimir Rusinovs talk•via twisted pair cables, •plus a common ground line for all Si-PM on tile-plate•signal from 50 Ohm to ground, capacitive RO possible?

Such a wire RO is •thinner and easier to arrange than optical RO fibres•less attenuation losses of signal•summing of tile signals to cell signals in electrical adder/shaper, allows to equalise MIP signals from all tiles in a cell!

Page 9: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 9

Visit at MEPHI

Development in MEPHI and Pulsar:Presented were large integrated multi-layer plates with various Si-PM types on it, several hundredsplate ~ 300mm thick, about 10 multilayers, ~80 subsequent production stepsdevelopment of waver with appropriate masks, ion inplantations, aluminisation, with polysilicon resistor readout,pixel structure with guard rings for x-talk protection,

The multilayer parameters for the production process are definedusing special software from ISE (Switzerland)signal development also studied, with SPICE.

Production in PULSAR factory, ~900 (300) people, (produce transistors, APD’s, multilayer boards..)optical inspection/selection with scope and special devices to idetify rejectsby looking for shorts on final multilayer before cutting out individualsplanned are 2000 pixels /mm2, now 600 pixels/mm2

it is possible to produce required quantities for prototype next year!

Page 10: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 10

Visit at MEPHI

Discussion on our needs:-- 30 Si-PM’s now, to test in minical-- 150-200 Si-PM’s March 2003, no additional costs-- 5000 more Si-PM’s are needed for the prototype

Estimated costs on base of this quantities:•mass production price (5000) is 7 Euro/PM.•for 800 000 Si-PM, price estimate is 2 Euro/PM.

Front end electronic:•preamp/shaper needs no large gain, but shaping! about 1 (<2) Euro per piece expected•adder/shaper and S&H, investigations have to start soon •need connection with LAL and British DAQ group

Page 11: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 11

Visit at MEPHI

Information from MEPHI needed soon:--optimal sensitive ADC range needed: 1pe > 2mV(50 Ohm)>ADC-channel 15-20 ???--gain vs. bias voltage, typical--noise contribution to MIP peak:

•noise rate vs. fraction of MIP threshold•noise rate vs. MIP efficiency

needed for minical studies at DESY:1. Testing of 5 pieces at DESY, soon

without external amplificationwith simple amplifiers/summers from MEPHI (?)

2. Testing 30 pieces at DESY up to 1.1.2003still with CAMAC-ROwith different tile couplings,with different fibre connections, compare performance with MA-PM’s.

To contact:•Orsay/Prague•Minsk/Protvino

Page 12: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 12

Visit at Uniplast, VladimirExperience in Shashlik production for LHC-B, ECAL

~ 2000 modules, 23 layers, ~25 kg eachcast tiles, 10x10cm2, 64 fibre holesPolystyrene > BASF-143 popob + ptb We need:

1. Better Polystyrene from Dow-Chemical: STYRON-663, “optical clean” (!)longer atten. length, price ~ 1.3xwe will order 25 kg for teststests with:

5x5cm2, 10x10cm2 tile sizes, 4mm tick, existing form usedstandard and optical clean PS

LY and uniformity measurement in ITEP2. For our production special size molds needed, max. mold size is 40x40cm2,pressure to withstand is~ 500atm. cost/mold ~5000-7000$production time for molds: ~ 3 month!! >>> decision on tilesizes up to end 2002!!

Big chemical factory,207 km north-east from Moscow

Example:various tile sizesin a single mold

Page 13: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 13

Visit at Uniplast, Vladimir

Examplehow to produce our tiles in cast procedure together with grooves:

1 mould only:N tile sizes with same loop dimensions

To studyuniformity

Page 14: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 14

Visit at Uniplast, Vladimir

We will have about 30 different tile sizes in barrel at present 38, to be redesigned (VK) soon it seems possible to reduce the number of casting forms to 6-8 ?

Number of Tiles we need:next year (2003) ~ 200 tiles, march, minical, problem with mould cost ~ 5 000 tiles, autumn, production is some weeksfor TESLA HCAL ~ 800 000 tiles, production after 2003, full quantity in 4 years

Page 15: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 15

Visit at Uniplast, VladimirTo do:1. cleaner PS than STYRON-663 (1.3E/k) or 637 (1.3E/kg) needed for large tile sizes:>> STYRON-2262 (1.5E/kg)>> DESY tries to buy, problem delivery outside US !

2. produce some new tiles (10x10cm2, directly with grooves)•compare with old PS at ITEP

3. re-design tile-plate structures (in barrel)•number of tile layers,•define the various tile sizes•exact tile thickness, tolerances ?

4. final decision on groove shapes (geometrical configuration)

5. order 1. casting form for HCAL-prototype, should cover many tile sizes from 5x5 to 8x8cm2,

6. larger tiles to be machined from cast plates (40x40cm2, Uniplast) and from BC-408, several m2 more to order?

Page 16: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 16

Visit at Protvino

With Valentin Kozlov, LPINew division for plastic production on PS pressure casting basefinancial support from government: “new technology support”use many production parameters, computer controlled--2 high pressure (~800 kg/cm2) injection machines (DEMAG, new)--1 extrusion machine (Koch GmbH)they produce:•commercial products•plastic scintillators (KOPIO, Phenix,HERA-B, Hermes, many Russian clients)•medical products, clean room set up

•Alexander Soldatov•Vladimir Vasilchenko

Page 17: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 17

Visit at Protvino

Scintillator material:PS, Popop, PTBI bought and brought 5 new scintillator cooking ingredients to shift optimally scintillator light to the WLS sensitivity rangetest are in preparation to improve LY special for Y11-WLS fibreInjection moulding from granulate,max 600 cm2 area or 600 cm3 volume,each casting mould costs ~7000$.to be optimised: mold temperature, pressure, heating/cooling cycles (Protvino+LPI) e.g. 5x5 cm2 tiles: 40 s maximal sizes need: 2-3 min/tile

2 y needed for all TESLA tiles, as a ISTC fund?Total cost ~ 800 000 Euro, 20 E/kg

Page 18: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 18

Visit at Protvino

Discussion on tile arrangement in tile-plates:---> 4 tile-plate, produced in 1 casting stepwith ~1 mm connection bridges kept, ~ 2% X-talk expected,up to 20x20 cm2 moulds can be used!

Sub-tile plates

Page 19: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 19

Visit at Protvino

0.7 mm holes

Ideas for tile-plate arrangement from individual tiles:

Page 20: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 20

Visit at Protvino

Clamping method, individual. tiles: easier for diagonal curved, much easier for centre groovesMulti tile-plate moulding: not flexible enough for various tile sizes

To be discussed: cassettes for tile plates--Support plate needed on both surfaces of tile plate: to carry the tiles (below, 3-5 mm ss?)--to protect the fibres: and make assembly light tight for tests and gain adjustment (on top thin carbon fibre material?)--closing on sides: light tight closing to get light shield and carry the photodetectors (in case of 1 Si-PM/fibre)To fix very soon:--tile sizes, # of tiles per tile size,--grouping of tiles in common moulding forms, --geometrical fibre-groove shapes,--number of casting moulds needed.

Page 21: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 21

Visit at Protvino

To do:Protvino:•improve TFS-LY

with new doping ingredients,with new granulate from DOW Chemical,

•try to include fibre grooves in casting,•define # of matrices needed,•produce ca 30 tiles of 5x5 cm2 for minical tests,•work out cost and time plan for HCAL prototype.

ITEP/DESY:•more studies on inserted WLS and clear RO fibre

glue WLS/clear fibre connection, fix on tile try 1.0 and 1.1 mm clear fibre (to study with LPI?)fuse WLS/clear fibre connection

Page 22: Visit at ITEP

28.9.-3.10.02, Moscow V. Korbel, Report on my visit 22

Visit at Protvino

Preamplifiers for use with APD’sYouri Guilitsski, group of Sergei Denissov:

--ITEP/Minsk type, charge sensitive,--1 preamp ready--end Nov.02: some preamps to DESY for minical tests

gain to regulate (by screw driver) up to 5mV/fCsame noise level as from CERN testscapacity range 20-30 pF

--larger quantity (~ 30 pieces) at 1.1.03--PC board with 16 channels (prototype) needs 1/2y production time.--decision meeting which preamp(s) to choose for prototype at DESY in Febr.03, Youri comes to DESY