volume 2 - part 2_boq_10 february 2014

Upload: abdul-rahuman

Post on 01-Jun-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    1/317

    NEW NKONKWANA JUNIOR SECONDARY

    SCHOOL

    AT

    WILLOWVALE

    IDC

    BILLS OF QUANTITIES

    FOR

    FOR

    OSMOND LANGE ARCHITECTS HRN QUANTITY SURVEYORS

    Registered Quantity Surveyors

    70 Frere Road

    Vincent

    EAST LONDON

    5247

    043 - 726 5404043 - 726 5437

    First Floor, Pilot Mill House

    ARCHITECT QUANTITY SURVEYORS

    Tel.Fax.

    043 - 721 0033043 - 721 0038

    Tel.Fax.

    The Quarry

    EAST LONDON

    5201

    per Notes to [email protected]

    Consulting Engineers

    EVANS CONSULTING ENGINEERS

    043 - 721 3192

    043 - 721 1553

    [email protected]

    Tel.

    Fax.

    E-mail

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    2/317

    Nkonkwana Jss

    E13/691

    Bill No Page No

    INDEX TO BILLS OF QUANTITIES

    SECTION NO. 1: PRELIMINARIES 1

    SECTION NO. 2: BUILDING COMPLEX 28

    1 EARTHWORKS (PROVISIONAL) 29

    Trade Preambles 29

    Supplementary Preambles 29

    Excavation Other Than Bulk 30

    Carting Away. 31

    Earth Filling, Etc. 31

    Keeping Excavations Free Of Water 31

    Soil Poisoning 32

    2 CONCRETE, FORMWORK REINFORCEMENT 34

    Trade Preambles 34

    Supplementary Preambles 34

    Unreinforced Concrete Cast Against Excavated Surfaces 35

    Unreinforced Concrete 35

    Reinforced Concrete Cast Against Excavated Surfaces 35

    Reinforced Concrete 35

    Test Blocks 36

    Finishing Top Surface Of Concrete 36

    Rough Formwork (Degree Of Accuracy ii) (Cpap Work Group No 111) 36

    Movement Joints, Etc. 36

    Reinforcement (Provisional) (Cpap Work Group No 114) 37

    3 MASONRY 39

    Trade Preambles 39

    (i)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    3/317

    Nkonkwana Jss

    E13/691

    Brickwork 39

    Brickwork In Foundations (Provisional) 40

    Brickwork In Superstructure 40

    Brickwork Sundries 41

    Face Brickwork Internally 41

    Face Brickwork Externally 42

    Sundries 42

    4 WATERPROOFING 44

    Trade Preambles 44

    Dampproofing Of Walls And Floors 44

    5 ROOF COVERINGS 45

    Trade Preambles 45

    Supplementary Preambles 45

    Ribbed Metal Sheeting And Accessories 45

    Roof And Wall Lining And Insulation 46

    6 CARPENTRY AND JOINERY 48

    Trade Preambles 48

    Supplementary Preambles 48

    Eaves, Verges, Etc. 49

    Skirtings 50

    Framed Doors, Etc. 50

    Semi Solid Core Flush Doors 50

    Solid Core Flush Doors 51

    Framed Frames, Etc. 51

    Beads, Architraves, Etc. 51

    7 CEILINGS, PARTITIONS, ETC. 53

    (ii)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    4/317

    Nkonkwana Jss

    E13/691

    Trade Preambles 53

    Supplementary Preambles 53

    Ceiling Construction, Cornices, Etc. (Cpap Work Group No 126) 53

    Nailed Up Ceilings (Cpap Work Group No 126) 54

    8 FLOOR COVERINGS 56

    Trade Preambles 56

    Needle Punch Carpet Sheeting And Tiles 56

    Skirtings, Nosings, Etc. 56

    Floor Coverings 56

    Polish, Sealers, Etc. 56

    9 IRONMONGERY 57

    Trade Preambles 57

    Supplementary Preambles 57

    Hinges, Floor Spring Hinges, Bolts, Panic Bolts, Etc. 57

    Locks 57

    Bathroom Fittings 58

    Sundries 58

    Pinning Boards, Writing Boards, Projection Screens, Etc. 58

    10 METALWORK 60

    Trade Preambles 60

    Supplementary Preambles 60

    Galvanised Welded Screens, Gates, Etc. 60

    Galvanized Pressed Steel Door Frames 61

    Galvanised Pressed Steel Combination Doors And Frames 62

    Aluminium Windows, Doors, Glazed Screens. (Cpap Work Group No 140) 62

    Chromadek Roller Doors, Etc. 63

    (iii)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    5/317

    Nkonkwana Jss

    E13/691

    11 PLASTERING 65

    Trade Preambles 65

    Supplementary Preambles 65

    Screeds 65

    Granolithic 65

    Internal Plaster 66

    External Plaster 66

    Corner Protectors, Dividing Strips, Etc. (Cpap Work Group No 136) 66

    12 TILING 68

    Trade Preambles 68

    Supplementary Preambles 68

    Ceramic Wall Tiling 70

    Sandstone Floor Tiles 70

    13 GLAZING 72

    Trade Preambles 72

    Glazing To Steel With Putty 72

    14 PAINTWORK 73

    Trade Preambles 73

    Supplementary Preambles 73

    On Floated Plaster 73

    On Plaster Board 74

    On Fibre-cement 74

    On Metal 75

    On Wood, Wood Board 75

    SECTION SUMMARY 78

    SECTION NO. 3: ADJUSTMENT TO FOLDING DOOR 79

    (iv)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    6/317

    Nkonkwana Jss

    E13/691

    1 CONCRETE FORMWORK REINFORCEMENT 80

    Trade Preambles 80

    Supplementary Preambles 80

    Reinforced Concrete 81

    Test Blocks 81

    Rough Formwork (Degree Of Accuracy ii) (Cpap Work Group No 111) 81

    Movement Joints. Etc. 81

    Reinforcement (Provisional) (Cpap Work Group No 114) 82

    2 MASONRY 84

    Trade Preambles 84

    Brickwork 84

    Brickwork In Superstructure 85

    Brickwork Sundries 85

    Face Brickwork Internally 85

    3 CARPENTRY AND JOINERY 87

    Trade Preambles 87

    Supplementary Preambles 87

    Skirtings 87

    4 FLOOR COVERINGS 88

    Trade Preambles 88

    Floor Coverings 88

    Polish, Sealers, Etc. 88

    5 PLASTERING 89

    Trade Preambles 89

    Screeds 89

    Internal Plaster 89

    (v)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    7/317

    Nkonkwana Jss

    E13/691

    6 PAINTWORK 90

    Trade Preambles 90

    Supplementary Preambles 90

    On Floated Plaster 90

    On Wood, Wood Board 91

    SECTION SUMMARY 93

    SECTION NO. 4: 6 PIT LATRINE 94

    1 EARTHWORKS (PROVISIONAL) 95

    Trade Preambles 95

    Supplementary Preambles 95

    Excavation Other Than Bulk 96

    Carting Away 97

    Earth Filling, Etc. 97

    Keeping Excavations Free Of Water 97

    2 CONCRETE FORMWORK REINFORCEMENT 99

    Trade Preambles 99

    Supplementary Preambles 99

    Unreinforced Concrete Cast Against Excavated Surfaces 100

    Reinforced Concrete 100

    Reinforced Concrete Cast Against Excavated Surfaces 100

    Test Blocks 100

    Finishing Top Surface Of Concrete 101

    Rough Formwork (Degree Of Accuracy ii) (Cpap Work Group No 111) 101

    Movement Joints, Etc. 101

    Reinforcement (Provisional) (Cpap Work Group No 114) 101

    3 MASONRY 104

    (vi)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    8/317

    Nkonkwana Jss

    E13/691

    Trade Preambles 104

    Supplementary Preambles 104

    Brickwork In Foundations (Provisional) 105

    Brickwork In Superstructure 105

    Face Brickwork Internally 106

    Face Brickwork Externally 106

    Face Brickwork Copings, Sills, Etc. 106

    Brickwork Sundries 106

    4 WATERPROOFING 108

    Trade Preambles 108

    Dampproofing Of Walls And Floors 108

    Joint Sealants, Etc. 108

    5 ROOF COVERINGS 109

    Trade Preambles 109

    Supplementary Preambles 109

    Roof Coverings, Etc. 109

    Roof And Wall Lining And Insulation 110

    6 CARPENTRY AND JOINERY 112

    Trade Preambles 112

    Supplementary Preambles 112

    Roof Sundries 113

    Eaves, Verges, Etc. 113

    Framed Doors, Etc. 113

    Solid Core Flush Doors 114

    Framed Frames, Etc. 114

    Beads, Architraves, Etc. 114

    (vii)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    9/317

    Nkonkwana Jss

    E13/691

    7 CEILINGS, PARTITIONS, ETC. 116

    Trade Preambles 116

    Supplementary Preambles 116

    Insulation 116

    Nailed Up Ceilings (Cpap Work Group No 126) 117

    8 IRONMONGERY 119

    Trade Preambles 119

    Supplementary Preambles 119

    Hinges, Floor Spring Hinges, Bolts, Panic Bolts, Etc. 119

    Locks 119

    Handles, Flush Pulls, Etc. 119

    Bathroom Fittings 120

    Sundries 120

    9 METALWORK 122

    Trade Preambles 122

    Supplementary Preambles 122

    Metalwork 122

    Galvanized Pressed Steel Door Frames 122

    Aluminium Windows, Doors, Etc. (Cpap Work Group No 149) 122

    10 PLASTERING 125

    Trade Preambles 125

    Supplementary Preambles 125

    Screeds 125

    Internal Plaster 125

    External Plaster 125

    Corner Protectors, Dividing Strips, Etc. (Cpap Work Group No 136) 125

    (viii)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    10/317

    Nkonkwana Jss

    E13/691

    11 TILING 126

    Trade Preambles 126

    Supplementary Preambles 126

    Ceramic Wall Tiling 128

    Sandstone Floor Tiles 128

    12 PAINTWORK 130

    Trade Preambles 130

    Supplementary Preambles 130

    Painting 130

    On Floated Plaster 130

    On Fibre-cement, Etc. 131

    On Metal 131

    On Wood, Wood Board 131

    13 PLUMBING AND DRAINAGE 134

    Trade Preambles 134

    Supplementary Preambles 134

    Sanitary Fittings (Cpap Work Group No. 148) 134

    Waste Unions, Etc. 134

    Traps, Etc. 134

    Taps, Valves, Etc. 135

    SECTION SUMMARY 137

    SECTION NO. 5: 10 PIT LATERINE 138

    1 EARTHWORKS (PROVISIONAL) 139

    Trade Preambles 139

    Supplementary Preambles 139

    Excavation Other Than Bulk 140

    (ix)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    11/317

    Nkonkwana Jss

    E13/691

    Carting Away. 141

    Earth Filling, Etc. 141

    Keeping Excavations Free Of Water 141

    2 CONCRETE, FORMWORK, REINFORCEMENT 143

    Trade Preambles 143

    Supplementary Preambles 143

    Concrete, Formwork & Reinforcement 144

    Unreinforced Concrete Cast Against Excavated Surfaces 144

    Reinforced Concrete 144

    Reinforced Concrete Cast Against Excavated Surfaces 144

    Test Blocks 144

    Finishing Top Surface Of Concrete 145

    Rough Formwork (Degree Of Accuracy ii) (Cpap Work Group No 111) 145

    Movement Joints, Etc. 145

    Reinforcement (Provisional) (Cpap Work Group No 114) 145

    3 MASONRY 148

    Trade Preambles 148

    Supplementary Preambles 148

    Brickwork 148

    Brickwork In Foundations 149

    Brickwork In Superstructure 149

    Face Brickwork Internally 150

    Face Brickwork Externally 150

    Brickwork Sundries 150

    4 WATERPROOFING 152

    Trade Preambles 152

    (x)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    12/317

    Nkonkwana Jss

    E13/691

    Dampproofing Of Walls And Floors 152

    Joint Sealants, Etc. 152

    5 ROOF COVERINGS 153

    Trade Preambles 153

    Supplementary Preambles 153

    Roof Coverings, Etc. 153

    Roof And Wall Lining And Insulation 154

    6 CARPENTRY AND JOINERY 156

    Trade Preambles 156

    Supplementary Preambles 156

    Roof Sundries 157

    Eaves, Verges, Etc. 157

    Skirtings 157

    Framed Doors, Etc. 158

    Solid Core Flush Doors 158

    Framed Frames, Etc. 158

    Beads, Architraves, Etc. 158

    7 CEILINGS, PARTITIONS, ETC. 160

    Trade Preambles 160

    Supplementary Preambles 160

    Insulation 160

    Nailed Up Ceilings (Cpap Work Group No 126) 161

    8 IRONMONGERY 163

    Trade Preambles 163

    Supplementary Preambles 163

    Hinges, Floor Spring Hinges, Bolts, Panic Bolts, Etc. 163

    (xi)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    13/317

    Nkonkwana Jss

    E13/691

    Locks 163

    Bathroom Fittings 163

    Sundries 164

    9 METALWORK 166

    Trade Preambles 166

    Supplementary Preambles 166

    Galvanised Welded Screens, Gates, Etc. 166

    Galvanized Pressed Steel Door Frames 166

    Aluminium Windows, Doors, Etc. (Cpap Work Group No 149) 167

    10 PLASTERING 169

    Trade Preambles 169

    Supplementary Preambles 169

    Screeds 169

    Granolithic 169

    Internal Plaster 169

    External Plaster 169

    Corner Protectors, Dividing Strips, Etc. (Cpap Work Group No 136) 170

    11 TILING 172

    Trade Preambles 172

    Supplementary Preambles 172

    Sandstone Floor Tiles 174

    12 PAINTWORK 176

    Trade Preambles 176

    Supplementary Preambles 176

    On Floated Plaster 176

    On Fibre-cement, Etc. 177

    (xii)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    14/317

    Nkonkwana Jss

    E13/691

    On Metal 177

    On Wood, Wood Board 177

    13 PLUMBING AND DRAINAGE 180

    Trade Preambles 180

    Supplementary Preambles 180

    Sanitary Fittings (Cpap Work Group No. 148) 180

    Taps, Valves, Etc. 180

    SECTION SUMMARY 181

    SECTION NO. 6: PLUMBING AND DRAINAGE (PROVISIONAL) 182

    1 RAINWATER DISPOSAL 183

    Trade Preambles 183

    Supplementary Preambles 183

    Rainwater Disposal (Cpap Work Group No 148): 183

    2 STORMWATER DRAINAGE 184

    Trade Preambles 184

    Supplementary Preambles 184

    Stormwater Channels (Cpap Work Group No 146) 185

    Expansion Joints: 186

    Joint Sealants, Etc. (Cpap Work Group No 120) 186

    Stormwater Drainage (Cpap Work Group No 146) 186

    3 SUB-SOIL DRAINAGE 190

    Trade Preambles 190

    Supplementary Preambles 190

    Subsoil Drainage (Cpap Work Group No 146) 191

    4 SOIL DRAINAGE 193

    Trade Preambles 193

    (xiii)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    15/317

    Nkonkwana Jss

    E13/691

    Supplementary Preambles 193

    Soil Drainage (Cpap Work Group No 146) 194

    Testing: 197

    5 SANITARY FITTINGS 199

    Trade Preambles 199

    Supplementary Preambles 199

    Sanitary Fittings (Cpap Work Group No. 148) 200

    Waste Unions, Etc. 200

    Traps, Etc. 201

    Taps, Valves, Etc. 201

    6 SANITARY PLUMBING 203

    Trade Preambles 203

    Supplementary Preambles 203

    Sanitary Plumbing (Cpap Work Group No. 148) 203

    7 WATER SUPPLY IN GROUND 204

    Trade Preambles 204

    Supplementary Preambles 204

    Water Supplies In Ground (Cpap Work Group No. 148) 205

    Testing: 207

    8 WATER SUPPLY IN BUILDING 209

    Trade Preambles 209

    Supplementary Preambles 209

    Water Supplies In Building (Cpap Work Group No. 148) 210

    Electric Water Heaters 211

    Testing 211

    9 FIRE SERVICE 213

    (xiv)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    16/317

    Nkonkwana Jss

    E13/691

    Trade Preambles 213

    Supplementary Preambles 213

    Water Supplies To Fire Appliances (Cpap Work Group No 148) 215

    Fire Appliances, Etc. 215

    Sundries 216

    Testing: 217

    10 LAGGING, HOLES, ETC 219

    Trade Preambles 219

    Lagging (Cpap Work Group No 148) 219

    Sleeves (Cpap Work Group No 148) 219

    SECTION SUMMARY 220

    SECTION NO. 7: EXTERNAL WORKS (PROVISIONAL) 221

    1 SITE PREPERATION 222

    Trade Preambles 222

    Demolitions (Cpap Work Group 104) 222

    Site Clearance, Etc. (Cpap Work Group 104) 223

    2 BULK EARTHWORKS 225

    Trade Preambles 225

    Supplementary Preambles 225

    Site Clearance, Etc. (Cpap Work Group No 104) 225

    Bulk Excavation (Cpap Work Group No 104) 226

    Earth Filling, Etc. 226

    Tests (Cpap Work Group No 104) 227

    3 TEMPORARY CLASSROOMS 230

    Trade Preambles 230

    Demolitions (Cpap Work Group No 104) 230

    (xv)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    17/317

    Nkonkwana Jss

    E13/691

    Earthworks (Cpap Work Group No 104) 231

    Earth Filling, Etc. 231

    Surface Preparation: 232

    Concrete (Cpap Work Group No 110) 232

    Reinforced Concrete 232

    Reinforced Concrete Cast Against Excavated Surfaces 232

    Test Blocks 232

    Finishing Top Surface Of Concrete 232

    Rough Formwork (Degree Of Accuracy ii) (Cpap Work Group No 111) 232

    Reinforcement (Cpap Work Group No 114) 233

    Corrugated Metal Sheeting And Accessories (Cpap Work Group No 124) 233

    Carpentry And Joinery (Cpap Work Group No 124) 233

    Roof Construction 233

    Roof Sundries 234

    Framed Doors, Etc. 234

    Timber Wall Cladding, Etc. (Cpap Work Group No 124) 234

    Ceiling Construction, Cornices, Etc. (Cpap Work Group No 126) 235

    Hinges, Floor Spring Hinges, Bolts, Panic Bolts, Etc. (Cpap Work Group No 132) 235

    Locks 235

    Pinning Boards, Writing Boards, Projection Screens, Etc. 235

    Galvanised Steel Windows, Doors, Etc. (Cpap Work Group No 136) 235

    Paintwork (Cpap Work Group No 152) 236

    On Fibre-cement, Etc. 236

    On Metal 236

    On Wood, Wood Board 236

    Precast Concrete Block Paving And Road Surfacing (Cpap Work Group No 112) 236

    (xvi)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    18/317

    Nkonkwana Jss

    E13/691

    Stock Fencing And Gates 238

    Sundries 238

    4 WALKWAYS 240

    Trade Preambles 240

    Supplementary Preambles 240

    Earthworks (Cpap Work Group No 104) 240

    Earth Filling, Etc. 241

    Surface Preparation: 241

    Soil Poisoning 241

    Concrete (Cpap Work Group No 110) 241

    Unreinforced Concrete 241

    Unreinforced Concrete Cast Against Excavated Surfaces 242

    Reinforced Concrete 242

    Reinforced Concrete Cast Against Excavated Surfaces 242

    Test Blocks 242

    Finishing Top Surface Of Concrete 242

    Rough Formwork (Degree Of Accuracy ii) (Cpap Work Group No 111) 242

    Movement Joints, Etc. 242

    Reinforcement (Cpap Work Group No 114) 243

    Waterproofing (Cpap Work Group No 120) 243

    Dampproofing Of Walls And Floors 243

    Joint Sealants, Etc. 243

    Ribbed Metal Sheeting And Accessories (Cpap Work Group No 124) 243

    Sheet Metal Flashings, Linings, Coping, Etc. (Cpap Work Group No 148) 244

    Carpentry And Joinery (Cpap Work Group No 124) 244

    Prefabricated Roof Trusses, Etc. 244

    (xvii)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    19/317

    Nkonkwana Jss

    E13/691

    Roof Construction 244

    Eaves, Verges, Etc. 244

    Galvanised Steel Columns And Beams (Cpap Work Group No 136) 245

    Sundry Galvanized Steelwork 245

    Screeds (Cpap Work Group No 142) 245

    Sandstone Floor Tiles (Cpap Work Group No 144) 245

    Paintwork (Cpap Work Group No 152) 246

    On Fibre-cement, Etc. 246

    On Wood 246

    Rainwater Disposal (Cpap Work Group No 148): 246

    5 PAVINGS, ROADWORK, ETC. 248

    Trade Preambles 248

    Excavations (Cpap Work Group 104) 248

    Bitumen Pavings (Cpap Work Group No 154) 249

    Precast Concrete Block Paving And Road Surfacing (Cpap Work Group No 112) 250

    Road Marking On Concrete Pavers: 251

    Road Signs 251

    Budgetary Allowances 251

    6 CONCRETE APRONS, ETC. 253

    Trade Preambles 253

    Earthworks (Cpap Work Group No 104) 253

    Earth Filling, Etc. 254

    Surface Preparation: 254

    Soil Poisoning 254

    Concrete (Cpap Work Group No 110) 254

    Unreinforced Concrete Cast Against Excavated Surfaces 254

    (xviii)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    20/317

    Nkonkwana Jss

    E13/691

    Reinforced Concrete 254

    Reinforced Concrete Cast Against Excavated Surfaces 255

    Test Blocks 255

    Rough Formwork (Degree Of Accuracy ii) (Cpap Work Group No 111) 255

    Movement Joints, Etc. 255

    Reinforcement (Cpap Work Group No 114) 255

    Waterproofing (Cpap Work Group No 120) 255

    Dampproofing Of Walls And Floors 255

    Joint Sealants, Etc. 256

    Screeds (Cpap Work Group No 142) 256

    Sandstone Floor Tiles (Cpap Work Group No 144) 256

    7 RETAINING WALLS, SEATING, ETC. 258

    Trade Preambles 258

    Excavations (Cpap Work Group No. 104) 258

    Earth Filling, Etc. 259

    Unreinforced Concrete Cast Against Excavated Surfaces (Cpap Work Group No 110) 259

    Smooth Formwork (Degree Of Accuracy ii) (Cpap Work Group No 111) 259

    Brickwork In Foundations (Cpap Work Group No 118) 259

    Brickwork In Superstructure 260

    Face Brickwork Externally 260

    Dampproofing Of Walls And Floors (Cpap Work Group No 120) 261

    External Plaster (Cpap Work Group No 142) 261

    On Floated Plaster (Cpap Work Group No 152) 261

    8 WATER TANKS AND STANDS 263

    Trade Preambles 263

    Supplementary Preambles 263

    (xix)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    21/317

    Nkonkwana Jss

    E13/691

    Earthworks (Cpap Work Group No. 104) 263

    Carting Away. 264

    Unreinforced Concrete Cast Against Excavated Surfaces (Cpap Work Group No. 110) 264

    Reinforced Concrete Cast Against Excavated Surfaces (Cpap Work Group No. 110) 264

    Reinforcement (Cpap Work Group No. 114) 264

    Masonry (Cpap Work Group No. 118) 264

    Face Brickwork Externally 265

    Plastering (Cpap Work Group No. 142) 265

    Water Tanks (Cpap Work Group No 148) 265

    9 HIGH RISE WATER TANK 267

    Trade Preambles 267

    Galvanised Mild Steel Water Supply Pipes (Cpap Work Group No 148) 267

    Builders Work To Plumbing Installation (Cpap Work Group No 148) 269

    10 FENCING 272

    Trade Preambles 272

    Supplementary Preambles 272

    Security Fencing (Cpap Work Group No 136) 272

    Site Preperation (Cpap Work Group No 104) 273

    Stock Fencing And Gates (Cpap Work Group No 136) 273

    Welded Mesh Fencing (Cpap Work Group No 136) 274

    Sundries (Cpap Work Group No 136) 276

    SECTION SUMMARY 279

    SECTION NO. 8: PROVISIONAL SUMS 280

    1 BUILDERS WORK (PROVISIONAL) 281

    Trade Preambles 281

    Supplementary Preambles 281

    (xx)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    22/317

    Nkonkwana Jss

    E13/691

    Builders Work In Connection With Electrical Installation: 281

    2 BUDGETARY AMOUNTS AND BUILDERS WORK 284

    Budgetary Allowances: 284

    3 PROVISIONAL AMOUNTS 285

    Selected Sub-contract Works 285

    Electrical 286

    Mechanical 286

    4 CONTINGENCIES, ESCALATION, ETC. 290

    Monetary Allowances 290

    SECTION SUMMARY 291

    ANNEXURES

    ANNEXURE A - Site plan, detail drawings and schedules

    (xxi)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    23/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION A) Each Item Carried to Collection1

    SECTION 1

    MEANING OF TERMS TENDER / TENDERER

    Any reference to the words Tender" or "Tenderer" herein and/or in any other documentationshall be construed to have the same meaning as the words "Bid" or "Bidder"

    PRELIMINARIES

    The JBCC Preliminaries Code 2103, May 2005 edition for use with the JBCC PrincipalBuilding Agreement Edition 4.1 Code 2101, March 2005 is taken to be incorporated herein.The tenderer is deemed to have referred to these documents for the full intent and meaning ofeach clause. These clauses are referred to by number and heading only. Where standardclauses or options are not applicable to the contract such modifications or corrections as arenecessary are given under each relevant clause. Where an item is not relevant to this specificcontract such item is marked "N/A" signifying "Not Applicable".

    PRICING OF PRELIMINARIES

    Should Option A, as set out in clause B10.3.1 hereinafter be used for the adjustment ofpreliminaries then each item priced is to be allocated to one or more of the three categoriesFixed, Value Related or Time Related and the respective amounts entered in the spaces

    provided under each item

    Items not priced in these Preliminaries shall be deemed to be included elsewhere in these Billsof Quantities.

    SECTION A: JBCC PRINCIPAL BUILDING AGREEMENT

    DEFINITIONS

    A1.0 DEFINITIONS AND INTERPRETATION

    Clause 1.0

    Clause 1.1 Definition of Commencement Date is added:

    COMMENCEMENT DATE means the date that the agreement, made in terms of the Formof Offer and Acceptance, comes into effect

    Clause 1.1 Definition of Construction Guarantee is amended by replacing it with thefollowing:

    CONSTRUCTION GUARANTEE means a guarantee at call obtained by the contractor from

    an institution approved by the employer in terms of the employers construction guarantee

    form as selected in the schedule

    Clause 1.1 Definition of Construction Period is amended by replacing it with the following:

    CONSTRUCTION PERIOD means the period commencing on the commencement date

    and ending on the date of practical completion

    Clause 1.1 Definition of Corrupt Practice is added:

    CORRUPT PRACTICE means the offering, giving, receiving or soliciting of anything of valueto influence the action of a public official in the procurement process or in contract execution.

    Clause 1.1 Definition of Fraudulent Practice is added:

    FRAUDULENT PRACTICE means a misrepresentation of facts in order to influence aprocurement process or the execution of a contract to the detriment of any tenderer andincludes collusive practice among tenderers (prior to or after the tender submission) designedto establish tender prices at artificial non-competitive levels and to deprive the tenderer of the

    benefits of free and open competition.

    Clause 1.1 Definition of "Interest" is amended by replacing it with the following:

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    24/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION A) Each Item Carried to Collection2

    INTEREST means the interest rates applicable on this contract, whether specificallyindicated in the relevant clauses or not, will be the rate as determined by the Minister ofFinance, from time to time, in terms of section 80(1)(b) of the Public Finance ManagementAct, 1999 (Act No. 1 of 1999).Clause 1.1 Definition of Principal Agent is amended by replacing it with the following:

    PRINCIPAL AGENT means the person or entity appointed by the employerand named in

    the schedule. In the event of a principal agent not being appointed, then all the duties and

    obligations of a principal agent as detailed in the agreement shall be fulfilled by a

    representative of the employeras named in the schedule

    Clause 1.1 Definition of Security is amended by replacing it with the following:

    SECURITY means the form of security provided by the employeror contractor, as stated in

    the schedule, from which the contractoror employermay recover expense or loss

    Clause 1.6 is amended by replacing the words prepaid registered post, telefax or e-mail withprepaid registered post or telefax

    Clause 1.6.4 is amended by replacing it with the following:

    No clause

    Fixed:____________ Value related:____________ Time related:____________

    Item

    OBJECTIVE AND PREPARATION

    A2.0 OFFER, ACCEPTANCE AND PERFORMANCE

    Clause 2.0

    Fixed:____________ Value related:____________ Time related:____________Item

    A3.0 DOCUMENTS

    Clause 3.0

    Clause 3.2.1 is amended by replacing 14.1 with 14.0

    Clause 3.7 is amended by the addition of the following:

    The contractor shall supply and keep a copy of the JBCC Series 2000 Principal Building

    Agreement and Preliminaries applicable to this contract on the site, to which the employer,

    principal agent and agents shall have access at all times

    Clause 3.10 is amended by replacing the second reference to principal agent with the word

    employer

    Fixed:____________ Value related:____________ Time related:____________Item

    A4.0 DESIGN RESPONSIBILITY

    Clause 4.0

    Clause 4.3 is amended by replacing it with the following:

    No clause

    Fixed:____________ Value related:____________ Time related:____________

    Item

    A5.0 EMPLOYERS AGENTS

    Clause 5.0

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    25/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION A) Each Item Carried to Collection3

    Clause 5.1.2 is amended to include clauses 32.6.3, 34.3, 34.4 and 38.5.8

    Fixed:____________ Value related:____________ Time related:____________Item

    A6.0 SITE REPRESENTATIVE

    Clause 6.0

    Fixed:____________ Value related:____________ Time related:____________

    Item

    A7.0 COMPLIANCE WITH REGULATIONS

    Clause 7.0

    Note: The provisions herein include inter alia, compliance with all the requirements set out inthe Construction Regulations, 2003 issued under the Occupational Health and Safety Act,1993 (Act No 85 of 1993), and in particular with Regulation 5(1) requiring the compilation of ahealth and safety plan, as well as Regulation 6(1) requiring the appointment of a constructionsupervisor

    See also clause C10 of Section C Specific Preliminaries

    Fixed:____________ Value related:____________ Time related:____________Item

    A8.0 WORKS RISK

    Clause 8.0

    Fixed:____________ Value related:____________ Time related:____________

    Item

    A9.0 INDEMNITIES

    Clause 9.0

    Fixed:____________ Value related:____________ Time related:____________Item

    A10.0 WORKS INSURANCES

    Clause 10.0

    Clause 10.0 is amended by the addition of the following clauses:

    10.5 Damage to the Works

    (a) Without in any way limiting the contractors obligations in terms of the contract, the

    contractor shall bear the full risk of damage to and/or destruction of the works by

    whatever cause during construction of the works and hereby indemnifies and holds

    harmless the employer against any such damage. The contractor shall take such

    precautions and security measures and other steps for the protection and security of theworks as the contractormay deem necessary

    (b) The contractor shall at all times proceed immediately to remove or dispose of any debris

    arising from damage to or destruction of the works and to rebuild, restore, replace and/or

    repair the works

    (c) The employershall carry the risk of damage to or destruction of the works and material

    paid for by the employerthat is the result of the excepted risks as set out in 10.6

    (d) Where the employer bears the risk in terms of this contract, the contractor shall, if

    requested to do so, reinstate any damage or destroyed portions of the works and the costsof such reinstatement shall be measured and valued in terms of 32.0 hereof

    10.6 Injury to Persons or loss of or damage to Properties

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    26/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION A) Each Item Carried to Collection4

    (a) The contractor shall be liable for and hereby indemnifies the employer against anyliability, loss, claim or proceeding whether arising in common law or by statute, consequentupon personal injuries to or the death of any person whomsoever arising out of or in thecourse of or caused by the execution of the works unless due to any act or negligence of

    any person for whose actions the employeris legally liable

    (b) The contractor shall be liable for and hereby indemnifies the employer against anyliability, loss, claim or proceeding consequent upon loss of or damage to any moveable orimmovable or personal property or property contiguous to the site, whether belonging to or

    under the control of the employeror any other body or person, arising out of or in thecourse of or by reason of the execution of the works unless due to any act or negligence of

    any person for whose actions the employeris legally liable

    (c) The contractor shall, upon receiving a contract instruction from the principal agent,cause the same to be made good in a perfect and workmanlike manner at his own cost andin default thereof the employer shall be entitled to cause it to be made good and to

    recover the cost thereof from the contractor or to deduct the same from amounts due to

    the contractor

    (d) The contractorshall be responsible for the protection and safety of such portions of the

    premises placed under his control by the employerfor the purpose of executing the works

    until the issue of the certificate of practical completion

    (e) Where the execution of the works involves the risk of removal of or interference withsupport to adjoining properties including land or structures or any structures to be altered oradded to, the contractor shall obtain adequate insurance and will remain adequatelyinsured or insured to the specific limit stated in the contract against the death of or injury topersons or damage to such property consequent on such removal or interference with thesupport until such portion of the works has been completed

    (f) The contractorshall at all times proceed immediately at his own cost to remove or disposeof any debris and to rebuild, restore, replace and/or repair such property and to execute theworks

    10.7 High risk insurance

    In the event of the project being executed in a geological area classified as a High Risk Area,that is an area which is subject to highly unstable subsurface conditions that might result incatastrophic ground movement evident by sinkhole or doline formation the following will apply:

    10.7.1 Damage to the works

    The contractor shall, from the commencement date of the works until the date of the

    certificate of practical completion bear the full risk of and hereby indemnifies and holds

    harmless the employeragainst any damage to and/or destruction of the works consequent

    upon a catastrophic ground movement as mentioned above. The contractor shall take such

    precautions and security measures and other steps for the protection of the works as he may

    deem necessary

    When so instructed to do so by the principal agent, the contractorshall proceed immediately

    to remove and/or dispose of any debris arising from damage to or destruction of the works

    and to rebuild, restore, replace and/or repair the works, at the contractors own costs

    10.7.2 Injury to persons or loss of or damage to property

    The contractor shall be liable for and hereby indemnifies and holds harmless the employeragainst any liability, loss, claim or proceeding arising at any time during the period of thecontract whether arising in common law or by statute, consequent upon personal injuries to orthe death of any person whomsoever resulting from, arising out of or caused by a catastrophicground movement as mentioned above

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    27/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION A) Each Item Carried to Collection5

    The contractorshall be liable for and hereby indemnifies the employeragainst any and allliability, loss, claim or proceeding consequent upon loss of or damage to any moveable orimmovable or personal property or property contiguous to the site, whether belonging to or

    under the control of the employeror any other body or person whomsoever arising out of orcaused by a catastrophic ground movement, as mentioned above, which occurred during theperiod of the contract

    10.7.3 It is the responsibility of the contractor to ensure that he has adequate insurance to

    cover his risk and liability as mentioned in 10.7.1 and 10.7.2. Without limiting the contractors

    obligations in terms of the contract, the contractorshall, within twenty-one (21) calendardays of the commencement date but before commencement of the works, submit to the

    employerproof of such insurance policy, i f requested to do so

    10.7.4 The employer shall be entitled to recover any and all losses and/or damages of

    whatever nature suffered or incurred consequent upon the contractors default of hisobligations as set out in 10.7.1; 10.7.2 and 10.7.3. Such losses or damages may be recoveredfrom the contractor or by deducting the same from any amounts still due under this contract

    or under any other contract presently or hereafter existing between the employer and the

    contractorand for this purpose all these contracts shall be considered one indivisible whole

    Fixed:____________ Value related:____________ Time related:____________

    ItemA11.0 LIABILITY INSURANCES

    Clause 11.0

    Fixed:____________ Value related:____________ Time related:____________Item

    A12.0 EFFECTING INSURANCES

    Clause 12.0

    Fixed:____________ Value related:____________ Time related:____________

    ItemA13.0 No Clause

    A14.0 SECURITY

    Clause 14.0

    Clauses 14.1 - 14.8 are amended by replacing them with the following:

    14.1 In respect of contracts with a contract sum up to R1 million, the security to be provided

    by the contractor to the employerwill be a payment reduction of five per cent (5%) of the

    value certified in the payment certificate (excluding VAT)

    14.1.1 The payment reduction of the value certified in a payment certificate shall be mutatismutandiin terms of 31.8(A)

    14.1.2 The employer shall be entitled to recover expense and loss from the payment

    reduction in terms of 33.0 provided that the employercomplies with the provisions of 33.4 in

    which event the employers entitlement shall take precedence over his obligations to refund

    the payment reduction security or portions thereof to the contractor

    14.2 In respect of contracts with a contract sum above R1 million, the contractorshall have

    the right to select the security to be provided in terms of 14.3, 14.4, 14.5, 14.6, or 14.7 as

    stated in the schedule. Such security shall be provided to the employerwithin twenty-one

    (21) calendar days from commencement date. Should the contractor fail to select the

    security to be provided or should the contractor fail to provide the employer with the

    selected security within twenty-one (21) calendar days from commencement date, the

    security in terms of 14.7 shall be deemed to have been selected.

    14.3 Where security as a cash deposit of ten per cent (10%) of the contract sum (excludingVAT) has been selected:

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    28/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION A) Each Item Carried to Collection6

    14.3.1 The contractorshall furnish the employerwith a cash deposit equal in value to ten

    per cent (10%) of the contract sum (excluding VAT) within twenty-one (21) calendar days

    from commencement date

    14.3.2 Within twenty-one (21) calendar days of the date of practical completion of the

    works the employershall reduce the cash deposit to an amount equal to three per cent (3%)

    of the contract value (excluding VAT), and refund the balance to the contractor

    14.3.3 Within twenty-one (21) calendar days of the date of final completion of the works

    the employershall reduce the cash deposit to an amount equal to one per cent (1%) of thecontract value (excluding VAT) and refund the balance to the contractor

    14.3.4 On the date of payment of the amount in the final payment certificate, the

    employershall refund the remainder of the cash deposit to the contractor

    14.3.5 The employershall be entitled to recover expense and loss from the cash deposit in

    terms of 33.0 provided that the employercomplies with the provisions of 33.4 in which event

    the employers entitlement shall take precedence over his obligations to refund the cash

    deposit security or portions thereof to the contractor

    14.3.6 The parties expressly agree that neither the employernor the contractorshall be

    entitled to cede the rights to the deposit to any third party

    14.4 Where security as a variable construction guarantee of ten percent (10%) of the

    contract sum (excluding VAT) has been selected:

    N/A

    14.4.1 The contractor shall furnish the employer with an acceptable variable

    construction guarantee equal in value to ten per cent (10%) of the contract sum (excluding

    VAT) within twenty-one (21) calendar days from commencement date

    N/A

    14.4.2 The variable construction guarantee shall reduce and expire in terms of the Variable

    Construction Guarantee form included in the invitation to tender

    N/A

    14.4.3 The employer shall return the variable construction guarantee to the contractor

    within fourteen (14) calendar days of it expiring

    N/A

    14.4.4 Where the employerhas a right of recovery against the contractorin terms of 33.0,

    the employershall issue a written demand in terms of the variable construction guarantee

    N/A

    14.5 Where security as a fixed construction guarantee of five per cent (5%) of the

    contract sum (excluding VAT) and a five per cent (5%) payment reduction of the value

    certified in the payment certificate (excluding VAT) has been selected:

    14.5.1 The contractor shall furnish a fixed construction guarantee to the employerequal

    in value to five per cent (5%) of the contract sum (excluding VAT)

    14.5.2 The fixed construction guarantee shall come into force on the date of issue and shallexpire on the date of practical completion

    14.5.3 The employershall return the fixed construction guarantee to the contractorwithin

    fourteen (14) calendar days of it expiring

    14.5.4 The payment reduction of the value certified in a payment certificate shall be in terms

    of 31.8 (A) and 34.8

    14.5.5 Where the employerhas a right of recovery against the contractorin terms of 33.0,

    the employershall be entitled to issue a written demand in terms of the fixed construction

    guarantee or may recover from the payment reduction or may do both

    14.6 Where security as a cash deposit of five per cent (5%) of the contract sum (excludingVAT) and a payment reduction of five per cent (5%) of the value certified in the payment

    certificate (excluding VAT) has been selected:

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    29/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION A) Each Item Carried to Collection7

    14.6.1 The contractor shall furnish the employerwith a cash deposit equal in value to five

    per cent (5%) of the contract sum (excluding VAT) within twenty-one (21) calendar days

    from commencement date

    14.6.2 Within twenty-one (21) calendar days of the date of practical completion of the

    works the employershall refund the cash deposit in total to the contractor

    14.6.3 The payment reduction of the value certified in a payment certificate shall be mutatismutandiin terms of 31.8(A)

    14.6.4 Where the employerhas a right of recovery against the contractorin terms of 33.0,

    the employermay issue a written notice in terms of 33.4 or may recover from the paymentreduction or may do both

    14.7 Where security as a payment reduction of ten per cent (10%) of the value certified in

    the payment certificate (excluding VAT) has been selected:

    14.7.1 The payment reduction of the value certified in a payment certificate shall be mutatismutandiin terms of 31.8(B)

    14.7.2 The employer shall be entitled to recover expense and loss from the payment

    reduction in terms of 33.0 provided that the employercomplies with the provisions of 33.4 inwhich event the employers entitlement shall take precedence over his obligations to refund

    the payment reduction or portions thereof to the contractor

    14.8 Payments made by the guarantor to the employer in terms of the fixed or variable

    construction guarantee shall not prejudice the rights of the employeror contractorin terms

    of this agreement

    14.9 Should the contractor fail to furnish the security in terms of 14.2, the employer, in his

    sole discretion and without notification to the contractor, is entitled to change the

    contractors selected form of security to that of a ten per cent (10%) payment reduction of

    the value certified in the payment certificate (excluding VAT), whereafter 14.7 shall bea licable

    Fixed:____________ Value related:____________ Time related:____________Item

    EXECUTION

    A15.0 PREPARATION FOR AND EXECUTION OF THE WORKS

    Clause 15.0

    Clause 15.1.1 is amended by replacing it with:

    No clause

    Clause 15.1.2 is amended by replacing it with:

    The security selected in terms of 14.0

    Clause 15.1 is amended by the addition of the following clause:

    15.1.4 An acceptable health and safety plan, required in terms of the Occupational Health andSafety Act, 1993 (Act 85 of 1993), within twenty-one (21) calendar days of commencement

    date

    Clause 15.2.1 is amended by replacing it with the following clause:

    Give the contractorpossession of the site within ten (10) working days of the contractorcomplying with the terms of 15.1.4

    Fixed:____________ Value related:____________ Time related:____________Item

    A16.0 ACCESS TO THE WORKS

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    30/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION A) Each Item Carried to Collection8

    Clause 16.0

    Fixed:____________ Value related:____________ Time related:____________Item

    A17.0 CONTRACT INSTRUCTIONS

    Clause 17.0

    Clause 17.1.11 is amended by deleting the words and the appointment of nominated andselected subcontractors

    Fixed:____________ Value related:____________ Time related:____________Item

    A18.0 SETTING OUT OF THE WORKS

    Clause 18.0

    Fixed:____________ Value related:____________ Time related:____________Item

    A19.0 ASSIGNMENT

    Clause 19.0

    Fixed:____________ Value related:____________ Time related:____________Item

    A20.0 NOMINATED SUBCONTRACTORS

    Clause 20.0

    Clause 20.1.3 is amended by replacing it with the following:

    No clause

    Note: See item B9.1 hereinafter for adjustment of attendance on nominated subcontractorsexecuting work allowed for under provisional sums

    Fixed:____________ Value related:____________ Time related:____________Item

    A21.0 SELECTED SUBCONTRACTORS

    Clause 21.0

    Clause 21 is amended by replacing it with:

    No clause

    Fixed:____________ Value related:____________ Time related:____________

    Item

    A22.0 EMPLOYERS DIRECT CONTRACTORS

    Clause 22.0

    Fixed:____________ Value related:____________ Time related:____________Item

    A23.0 CONTRACTORS DOMESTIC SUBCONTRACTORS

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    31/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION A) Each Item Carried to Collection9

    Clause 23.0

    Fixed:____________ Value related:____________ Time related:____________Item

    COMPLETION

    A24.0 PRACTICAL COMPLETION

    Clause 24.0

    Fixed:____________ Value related:____________ Time related:____________Item

    A25.0 WORKS COMPLETION

    Clause 25.0

    Fixed:____________ Value related:____________ Time related:____________Item

    A26.0 FINAL COMPLETION

    Clause 26.0

    Clause 26.1.2 is amended by inserting # next to 26.1.2

    Fixed:____________ Value related:____________ Time related:____________Item

    A27.0 LATENT DEFECTS LIABILITY PERIOD

    Clause 27.0

    Fixed:____________ Value related:____________ Time related:____________Item

    A28.0 SECTIONAL COMPLETION

    Clause 28.0

    Fixed:____________ Value related:____________ Time related:____________Item

    A29.0 REVISION OF DATE FOR PRACTICAL COMPLETION

    Clause 29.0

    Clause 29.2.5 is amended by replacing it with:

    No clause

    Fixed:____________ Value related:____________ Time related:____________Item

    A30.0 PENALTY FOR NON-COMPLETION

    Clause 30.0

    Fixed:____________ Value related:____________ Time related:____________Item

    PAYMENT

    A31.0 INTERIM PAYMENT TO THE CONTRACTOR

    Clause 31.0

    Clause 31.5.2 is amended by replacing 14.7.1 with 14.0

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    32/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION A) Each Item Carried to Collection10

    Clause 31.8 is amended by replacing it with the following two alternative clauses:

    Alternative A

    31.8(A) Where a security is selected in terms of 14.1; 14.5 or 14.6, the value of the works in

    terms of 31.4.1 and materials and goods in terms of 31.4.2 shall be certified in full. The

    value certified shall be subject to the following percentage adjustments:

    31.8(A).1 Ninety-five per cent (95%) of such value in interim payment certificates issued up

    to the date of practical completion

    31.8(A).2 Ninety-seven per cent (97%) of such value in interim payment certificates issued

    on the date of practical completion and up to but excluding the date of final completion

    31.8(A).3 Ninety-nine per cent (99%) of such value in interim payment certificates issued on

    the date of final completion and up to but excluding the final payment certificate in terms of

    34.6

    31.8(A).4 One hundred per cent (100%) of such value in the final payment certificate in

    terms of 34.6 except where the amount certified is in favour of the employer. In such an event

    the payment reduction shall remain at the adjustment level applicable to the final payment

    certificate

    Alternative B

    31.8(B) Where security as a payment reduction in terms of 14.7 has been selected, the value

    of the works in terms of 31.4.1 and materials and goods in terms of 31.4.2 shall be certifiedin full. The value certified shall be subject to the following percentage adjustments:

    31.8(B).1 Ninety per cent (90%) of such value in interim payment certificates issued up to

    the date of practical completion

    31.8(B).2 Ninety-seven per cent (97%) of such value in interim payment certificates issued

    on the date of practical completion and up to but excluding the date of final completion

    31.8(B).3 Ninety-nine per cent (99%) of such value in interim payment certificates issued on

    the date of final completion and up to but excluding the final payment certificate in terms of34.6

    31.8(B).4 One hundred per cent (100%) of such value in the final payment certificate in terms

    of 34.6 except where the amount certified is in favour of the employer. In such an event the

    payment reduction shall remain at the adjustment level applicable to the final payment

    certificate

    Clause 31.12 is amended by deleting the following:

    Payment shall be subject to the employergiving the contractora tax invoice for the amount

    due

    Fixed:____________ Value related:____________ Time related:____________Item

    A32.0 ADJUSTMENT TO THE CONTRACT VALUE

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    33/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION A) Each Item Carried to Collection11

    Clause 32.0

    Clauses 32.5.1, 32.5.4 and 32.5.7 are amended by the addition of the following at the end ofthe sentence:

    "due to no fault of the contractor"

    Fixed:____________ Value related:____________ Time related:____________Item

    A33.0 RECOVERY OF EXPENSE AND LOSS

    Clause 33.0

    Fixed:____________ Value related:____________ Time related:____________

    Item

    A34.0 FINAL ACCOUNT AND FINAL PAYMENT

    Clause 34.0

    Clause 34.1 is amended by removing # next to 34.1

    Clause 34.2 is amended by inserting # next to 34.2

    Clause 34.8 is amended by deleting the words where security as a fixed construction

    guarantee in terms of 14.4 has been selected or where payment reduction has been applied interms of 14.7.1

    Clause 34.13 is amended by replacing seven (7) calendar days with twenty-one (21)

    calendar days and deleting the words subject to the employergiving the contractor a taxinvoice for the amount due

    Fixed:____________ Value related:____________ Time related:____________

    Item

    A35.0 PAYMENT TO OTHER PARTIES

    Clause 35.0

    Fixed:____________ Value related:____________ Time related:____________Item

    CANCELLATION

    A36.0 CANCELLATION BY EMPLOYER CONTRACTORS DEFAULT

    Clause 36.0

    Clause 36.1 is amended by the addition of the following clauses:

    36.1.3 refuses or neglects to comply strictly with any of the conditions of contract

    36.1.4 estate being sequestrated, liquidated or surrendered in terms of the insolvency laws inforce within the Republic of South Africa

    36.1.5 in the judgement of the employer, has engaged in corrupt orfraudulent practices incompeting for or in executing the contract

    Clause 36.3 is amended by removing the reference to No clause and replacing the wordsprincipal agent with employer

    Clause 36.0 is amended by the addition of the following clause:

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    34/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION A) Each Item Carried to Collection12

    36.7 Notwithstanding any clause to the contrary, on cancellation of this agreement either by

    the employeror the contractor; or for any reason whatsoever, the contractorshall on written

    instruction, discontinue with the works on a date stated and withdraw himself from the site.

    The contractor shall not be entitled to refuse to withdraw from the works on the grounds ofany lien or right of retention or on the grounds of any other right whatsoever

    Fixed:____________ Value related:____________ Time related:____________Item

    A37.0 CANCELLATION BY EMPLOYER LOSS AND DAMAGE

    Clause 37.0

    Clause 37.3.5 is amended by replacing ninety (90) with one-hundred and twenty (120)

    Clause 37.0 is amended by the addition of the following clause:

    37.5 Notwithstanding any clause to the contrary, on cancellation of this agreement either by

    the employeror the contractor; or for any reason whatsoever, the contractorshall on written

    instruction, discontinue with the works on a date stated and withdraw himself from the site.

    The contractor shall not be entitled to refuse to withdraw from the works on the grounds of

    any lien or right of retention or on the grounds of any other right whatsoever

    Fixed:____________ Value related:____________ Time related:____________Item

    A38.0 CANCELLATION BY CONTRACTOR EMPLOYERS DEFAULT

    Clause 38.0

    Clause 38.5.4 is amended by replacing ninety (90) with one-hundred and twenty (120)

    Clause 38.0 is amended by the addition of the following clause:

    38.7 Notwithstanding any clause to the contrary, on cancellation of this agreement either by

    the employeror the contractor; or for any reason whatsoever, the contractorshall on written

    instruction, discontinue with the works on a date stated and withdraw himself from the site.The contractor shall not be entitled to refuse to withdraw from the works on the grounds of

    any lien or right of retention or on the grounds of any other right whatsoever

    Fixed:____________ Value related:____________ Time related:____________Item

    A39.0 CANCELLATION CESSATION OF THE WORKS

    Clause 39.0

    Clause 39.3.5 is amended by the addition of the following at the end of the sentence: withinone hundred and twenty (120) working days of completion of such a report

    Fixed:____________ Value related:____________ Time related:____________Item

    DISPUTE

    A40.0 DISPUTE SETTLEMENT

    Clause 40.0

    Clause 40.2.2 is amended by replacing one (1) year with three (3) years

    Clause 40.6 is amended by removing the reference to:

    No clause

    Clause 40.7.1 is amended by replacing (10) with (15) and by the addition of the following:

    Whether or not mediation resolves the dispute, the parties shall bear their own cost concerningthe mediation and equally share the costs of the mediatorand related costs

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    35/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION A) Each Item Carried to Collection13

    Fixed:____________ Value related:____________ Time related:____________Item

    SUBSTITUTE PROVISIONS

    A41.0 STATE CLAUSES

    Clause 41.0

    Fixed:____________ Value related:____________ Time related:____________Item

    CONTRACT VARIABLES

    THE SCHEDULE (C1.2: CONTRACT DATA)

    A42.0 PRE-TENDER INFORMATION

    Clause 42.0

    Tenderers are referred to the document C1.2: Contract Data for variables pertaining to thiscontract

    Fixed:____________ Value related:____________ Time related:____________Item

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    36/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION B) Each Item Carried to Collection14

    SECTION B: JBCC PRELIMINARIES

    B1.0 DEFINITIONS AND INTERPRETATION

    B1.1 Definitions and interpretation

    See also clause A1.0 of Section A for additional and/or amended definitions which shall applyequally to this Section

    Fixed:____________ Value related:____________ Time related:____________Item

    B2.0 DOCUMENTS

    B2.1 Checking of documents

    Fixed:____________ Value related:____________ Time related:____________Item

    B2.2 Provisional bills of quantities

    Fixed:____________ Value related:____________ Time related:____________Item

    B2.3 Availability of construction documentation

    Fixed:____________ Value related:____________ Time related:____________Item

    B2.4 Interests of agents

    Fixed:____________ Value related:____________ Time related:____________Item

    B2.5 Priced documents

    Fixed:____________ Value related:____________ Time related:____________Item

    B2.6 Tender submission

    Clause 2.6 is amended by replacing JBCC Form of Tender with Form of Offer andAcceptance (C1.1)

    Fixed:____________ Value related:____________ Time related:____________Item

    B3.0 THE SITE

    B3.1 Defined works area

    Fixed:____________ Value related:____________ Time related:____________Item

    B3.2 Geotechnical investigation

    Fixed:____________ Value related:____________ Time related:____________Item

    B3.3 Inspection of the site

    Tenderers shall complete the Site Inspection Certificate (T2.2k) included in the tenderdocuments and return the same with the tender submission.

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    37/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION B) Each Item Carried to Collection15

    Fixed:____________ Value related:____________ Time related:____________Item

    B3.4 Existing premises occupied

    Fixed:____________ Value related:____________ Time related:____________Item

    B3.5 Previous work dimensional accuracy

    Fixed:____________ Value related:____________ Time related:____________Item

    B3.6 Previous work defects

    Fixed:____________ Value related:____________ Time related:____________Item

    B3.7 Services known

    Fixed:____________ Value related:____________ Time related:____________Item

    B3.8 Services unknown

    Fixed:____________ Value related:____________ Time related:____________Item

    B3.9 Protection of trees

    Fixed:____________ Value related:____________ Time related:____________Item

    B3.10 Articles of value

    Fixed:____________ Value related:____________ Time related:____________

    Item

    B3.11 Inspection of adjoining properties

    Fixed:____________ Value related:____________ Time related:____________Item

    B4.0 MANAGEMENT OF CONTRACT

    B4.1 Management of the works

    Fixed:____________ Value related:____________ Time related:____________Item

    B4.2 Programme for the works

    Fixed:____________ Value related:____________ Time related:____________Item

    B4.3 Progress meetings

    Fixed:____________ Value related:____________ Time related:____________

    Item

    B4.4 Technical meetings

    Fixed:____________ Value related:____________ Time related:____________

    Item

    B4.5 Labour and plant records

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    38/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION B) Each Item Carried to Collection16

    Fixed:____________ Value related:____________ Time related:____________Item

    B5.0 SAMPLES, SHOP DRAWINGS AND MANUFACTURERS INSTRUCTIONS

    B5.1 Samples of materials

    Fixed:____________ Value related:____________ Time related:____________Item

    B5.2 Workmanship samples

    Fixed:____________ Value related:____________ Time related:____________Item

    B5.3 Shop drawings

    Fixed:____________ Value related:____________ Time related:____________Item

    B5.4 Compliance with manufacturers instructions

    Fixed:____________ Value related:____________ Time related:____________Item

    B6.0 TEMPORARY WORKS AND PLANT

    B6.1 Deposits and fees

    Fixed:____________ Value related:____________ Time related:____________Item

    B6.2 Enclosure of the works

    Fixed:____________ Value related:____________ Time related:____________Item

    B6.3 Advertising

    Fixed:____________ Value related:____________ Time related:____________Item

    B6.4 Plant, equipment, sheds and offices

    Fixed:____________ Value related:____________ Time related:____________Item

    B6.5 Main notice board

    Fixed:____________ Value related:____________ Time related:____________Item

    Subcontractors notice board

    Fixed:____________ Value related:____________ Time related:____________Item

    B7.0 TEMPORARY SERVICES

    B7.1 Location

    Fixed:____________ Value related:____________ Time related:____________Item

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    39/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION B) Each Item Carried to Collection17

    B7.2 Water

    Fixed:____________ Value related:____________ Time related:____________Item

    B7.3 Electricity

    Fixed:____________ Value related:____________ Time related:____________Item

    B7.4 Telecommunication facilities

    Fixed:____________ Value related:____________ Time related:____________Item

    B7.5 Ablution facilities

    Fixed:____________ Value related:____________ Time related:____________Item

    B8.0 PRIME COST AMOUNTS

    B8.1 Responsibility for prime cost amounts

    Fixed:____________ Value related:____________ Time related:____________Item

    B9.0 ATTENDANCE ON N/S SUBCONTRACTORS

    B9.1 General attendance

    Fixed:____________ Value related:____________ Time related:____________

    Item

    B9.2 Special attendance

    Fixed:____________ Value related:____________ Time related:____________Item

    B9.3 Commissioning fuel, water and electricity

    Fixed:____________ Value related:____________ Time related:____________

    Item

    B10.0 FINANCIAL ASPECTS

    B10.1 Statutory taxes, duties and levies

    Fixed:____________ Value related:____________ Time related:____________

    Item

    B10.2 Payment for preliminaries

    Fixed:____________ Value related:____________ Time related:____________

    Item

    B10.3 Adjustment of preliminaries

    Clauses B10.3.1 and B10.3.2 are amended by replacing within fifteen (15) working days oftaking possession of the site with in his priced bills of quantities / lump sum documentsubmitted with his tender offer

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    40/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION B) Each Item Carried to Collection18

    Fixed:____________ Value related:____________ Time related:____________Item

    B10.4 Payment certificate cash flow

    Fixed:____________ Value related:____________ Time related:____________

    Item

    B11.0 GENERAL

    B11.1 Protection of the works

    Fixed:____________ Value related:____________ Time related:____________Item

    B11.2 Protection / isolation of existing / sectionally occupied works

    Fixed:____________ Value related:____________ Time related:____________Item

    B11.3 Security of the works

    Fixed:____________ Value related:____________ Time related:____________Item

    B11.4 Notice before covering work

    Fixed:____________ Value related:____________ Time related:____________

    Item

    B11.5 Disturbance

    Fixed:____________ Value related:____________ Time related:____________Item

    B11.6 Environmental disturbance

    Fixed:____________ Value related:____________ Time related:____________

    Item

    B11.7 Works cleaning and clearing

    Fixed:____________ Value related:____________ Time related:____________

    Item

    B11.8 Vermin

    Fixed:____________ Value related:____________ Time related:____________Item

    B11.9 Overhand work

    Fixed:____________ Value related:____________ Time related:____________Item

    B11.10 Instruction manuals and guarantees

    Fixed:____________ Value related:____________ Time related:____________Item

    B11.11 As built information

    Fixed:____________ Value related:____________ Time related:____________Item

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    41/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION B) Each Item Carried to Collection19

    B11.12 Tenant installations

    Fixed:____________ Value related:____________ Time related:____________Item

    B12.0 SCHEDULE OF VARIABLES

    B12.1 Pre-tender information

    Fixed:____________ Value related:____________ Time related:____________

    Item

    This schedule contains all variables referred to in this document and is divided into pre-tenderand post-tender categories. The pre-tender category must be completed in full and included inthe tender documents. Both the pre-tender and post-tender categories form part of thesePreliminaries.

    Spaces requiring information must be filled in, shown as not applicable or deleted and not leftblank. Where choices are offered, the non-applicable items are to be deleted. Whereinsufficient space is provided the information should be annexed hereto and cross-referenced

    to the applicable clause of the schedule. Key cross reference clauses are italicised in [ ]brackets

    12.1 PRE-TENDER INFORMATION12.1.1 Provisional bills of quantities

    [2.2] The quantities are provisional (yes/no) no

    12.1.2 Availability of construction documentation

    [2.3] Construction documentation is complete (yes/no) yes

    12.1.3 Interests of agents

    [2.4] Details:

    12.1.4 Defined works area

    [3.1] Details:

    12.1.5 Geotechnical investigation[3.2] Details:

    12.1.6 Existing premises occupied[3.4] Specific requirements:

    12.1.7 Previous work dimensional accuracy[3.5] Details:

    12.1.8 Previous work - defects[3.6] Details:

    12.19. Services - known[3.7] Details:

    12.1.10 Protection of trees[3.9] Specific requirements:

    12.1.11 Inspection of adjoining properties[3.11] Specific requirements:

    12.1.12 Enclosure of the works

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    42/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION B) Each Item Carried to Collection20

    [6.2] Specific requirements:

    12.1.13 Offices

    [6.4.3] Specific requirements:The contractorshall provide, maintain and remove on completion of the works an

    office for the exclusive use of the principal agent, minimum size 4 x 3 x 3m highinternally, suitably insulated and ventilated, provided with electric lighting and fittedwith boarded floor, desk, chair, drawing stool, drawing board and lock-up drawers

    for drawings. The office shall be kept clean and fit for use at all times.

    12.1.14 Main notice board[6.5] Specific requirements:

    The contractor shall provide, erect where directed, maintain and remove on

    completion of the works a notice board size 3 x 3m as type Drawing GEN 063,constructed of suitable boarding with flat smooth surface and with edging bead19mm thick round outer edges and projecting 12mm from face of boarding androunded on front edge. The board shall be securely fixed to hoarding, wherehoarding is provided, or fixed to and including a suitable supporting structure of

    timber or tubular posts and braces. The board is to be painted ivory white and thebead and 12mm wide dividing lines dark green. All wording shall be inscribed indark green as per the coat of arms for SA. All wording shall be inscribed in darkgreen painted sans serif lettering.

    12.1.15 Subcontractors notice board

    [6.6] Specific requirements: (yes/no) no

    12.1.16 Water

    [7.2] Option A (by contractor) (yes/no) yes

    Option B (by employer - free of charge) (yes/no) no

    Option C (by employer- metered) (yes/no) no

    12.1.17 Electricity

    [7.3] Option A (by contractor) (yes/no) yes

    Option B (by employer - free of charge) (yes/no) no

    Option C (by employer- metered) (yes/no) no

    12.1.18 Telecommunications

    [7.4] Telephone (yes/no) yes

    Facsimile (yes/no) no

    E-mail (yes/no) no

    12.1.19 Ablution facilities

    [7.5] Option A (by contractor) (yes/no) yes

    Option B (by employer) (yes/no) no

    12.1.20 Protection of existing/sectionally occupied works

    [11.2] Protection is required (yes/no) yes

    12.1.21 Special attendance[9.2] Subcontractor(1) details:

    Subcontractor(2) details:

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    43/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION B) Each Item Carried to Collection21

    Subcontractor(3) details:

    Subcontractor(4) details:

    12.1.22 Protection of the works[11.1] Specific requirements:

    12.1.23 Disturbance[11.5] Specific requirements:

    The contractorshall keep the site, structures, etc well watered during operations to

    prevent dust and shall provide and erect and remove on completion of the works

    all necessary temporary dust screens all to the satisfaction of the principal agent

    12.1.24 Environmental disturbance[11.6] Specific requirements:

    12.2 POST-TENDER INFORMATION12.2.1 Payment of preliminaries

    [10.2] Option A (prorated) (yes/no) Yes

    Option B (calculated) (yes/no) No

    12.2.2 Adjustment of preliminaries

    [10.3] Option A (three categories) (yes/no) Yes

    Option B (detailed breakdown) (yes/no) No

    12.2.3 Additional agreed preliminaries items

    Details:

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    44/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION B) Each Item Carried to Collection22

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    45/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION C) Each Item Carried to Collection23

    SECTION C: SPECIFIC PRELIMINARIES

    Section C contains specific preliminary items which apply to this contract except where N/A(Not Applicable) appears against an item

    C1 CONTRACT DRAWINGS

    * Select relevant paragraph and delete whichever is not applicable depending on whether thecontract is based on a bills of quantities or lump sum document

    * The drawings issued with the tender documents do not comprise the complete set but serveas a guide only for tendering purposes and for indicating the scope of the work to enable thetenderer to acquaint himself with the nature and extent of the works and the manner in whichthey are to be executed

    * A full set of drawings is issued with the tender documents indicating the full scope of thework to enable the tenderer to acquaint himself with the nature and extent of the works andthe manner in which they are to be executed

    Should any part of the drawings not be clearly understood by the tenderer he shall, beforesubmitting his tender, obtain clarification in writing from the principal agent

    Fixed: ____________ Value related:____________ Time related:____________Item

    C2 GENERAL PREAMBLES

    The document Model Preambles for Trades (1995 edition) is obtainable on request fromPrincipal Agent, and shall be read in conjunction with the bills of quantities / lump sum

    document and be referred to for the full descriptions of work to be done and materials to beused

    Fixed: ____________ Value related:____________ Time related:____________Item

    C3 TRADE NAMES

    Wherever a trade name for any product has been described in the bills of quantities / lump

    sum document, the tenderers attention is drawn to the fact that any other product of equal

    quality may be used subject to the written approval of the principal agent being obtained priorto the closing date for submission of tenders

    If prior written approval for an alternative product is not obtained, the product described shallbe deemed to have been tendered for

    Fixed: ____________ Value related:____________ Time related:____________Item

    C4 IMPORTED MATERIALS AND EQUIPMENT

    Where imported items are listed in the tender documents, the tenderer shall provide all theinformation called for, failing which the price of any such item, materials or equipment shall beexcluded from currency fluctuations. (refer to Schedule of Imported Materials and Equipment(T2.2q) to be completed by tenderer)

    Notwithstanding any provisions elsewhere regarding the adjustment of contract prices, theprice of any item, material or equipment listed in terms of this clause shall be excluded fromthe Contract Price Adjustment Provisions (if applicable)

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    46/317

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    47/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION C) Each Item Carried to Collection25

    It is required of the contractor to thoroughly study the HIV/AIDS Specification (PW 1544) ofthe Department that must be read together with and is deemed to be incorporated under thisSection of the bills of quantities / lump sum document. Provision for pricing of HIV/AIDSawareness is made under items C10.1 to C10.5 hereafter and it is explicitly pointed out that allrequirements of the aforementioned specification are deemed to be priced hereunder, as thesaid items represent the only method of measurement and no additional items or extras to thecontract in this regard shall be entertained

    The contractor must take note that compliance with the HIV/AIDS Specification is

    compulsory. In the event of partial or total non-compliance, the principal agent,notwithstanding the provisions of Clause A 31 of Section 1: Preliminaries (Section A) or anyother clause to the contrary, reserves the right to delay issuing any progress payment

    certificate until the contractor provides satisfactory proof of compliance. The contractorshall not be entitled to any compensation of whatsoever nature, including interest, due to suchdelay of payment

    C10.1 AWARENESS CHAMPION

    Selection, appointment, briefing and making available of an Awareness Champion includingprovision of all relevant services, all in accordance with the HIV/AIDS Specification

    Fixed:_____________ Value related:____________ Time related:______________

    Item

    C10.2 AWARENESS WORKSHOPS

    Selection and appointment of a competent Service Provider approved by the principal agent,provision of a Service Provider Workshop Plan and a suitable venue, conducting ofawareness workshops by means of traditional and/or modern multi-media techniques,including follow-up courses, making available all tuition material and performing assessmentprocedures, all in accordance with the HIV/AIDS Specification

    Fixed:_____________ Value related:____________ Time related:______________

    Item

    C10.3 POSTERS, BOOKLETS, VIDEOS, ETC.

    Provision, displaying, maintaining and replacing when necessary of four plastic laminatedposters, booklets and educational videos, etc. for the duration of the construction period, allin accordance with the HIV/AIDS Specification

    Fixed:_____________ Value related:____________ Time related:______________

    Item

    C10.4 ACCESS TO CONDOMS

    Provision and maintenance of condom dispensers fixed in position, including male and femalecondoms, replenishing male and female condoms on a daily basis as required for the durationof the construction period, all in accordance with the HIV/AIDS Specification

    Fixed:_____________ Value related:____________ Time related:______________

    Item

    C10.5 MONITORING

    Monitoring HIV/AIDS awareness of workers, providing the principal agent with access toinformation including making available all reports, thoroughly completed and reflecting thecorrect information, for the duration of the construction period and close out, all inaccordance with the HIV/AIDS Specification

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    48/317

    R

    c

    SECTION 1: PRELIMINARIES (SECTION C) Each Item Carried to Collection26

    Fixed:____________ Value related:____________ Time related:____________

    Item

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    49/317

    R

    c

    SECTION 1: PRELIMINARIES: COLLECTION 27

    SECTION 1

    PRELIMINARIES

    COLLECTION

    AMOUNT

    Item Page

    R c

    SECTION A: JBCC PRINCIPAL BUILDING AGREEMENT

    DefinitionsA1.0 Definitions and interpretation 1

    Objective and Preparation

    A2.0 Offer, acceptance and performance 2

    A3.0 Documents 2

    A4.0 Design responsibility 2

    A5.0 Employers agents 2

    A6.0 Site representative 3

    A7.0 Compliance with regulations 3

    A8.0 Works risk 3

    A9.0 Indemnities 3

    A10.0 Works Insurances 3

    A11.0 Liability insurances 5

    A12.0 Effecting insurances 5

    A13.0 No clause 5

    A14.0 Security 5

    Execution

    A15.0 Preparation for and execution of the works 7

    A16.0 Access to the works 7

    A17.0 Contract instructions 7

    A18.0 Setting out of the works 8

    A19.0 Assignment 8

    A20.0 Nominated subcontractors 8

    A21.0 Selected subcontractors 8

    A22.0 Employers direct contractors 8

    A23.0 Contractors domestic subcontractors 8

    Completion

    A24.0 Practical completion 8

    A25.0 Works completion 8

    A26.0 Final completion 9

    A27.0 Latent defects liability period 9

    A28.0 Sectional completion 9

    A29.0 Revision of date for practical completion 9

    A30.0 Penalty for non-completion 9

    Carried forward R

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    50/317

    R

    c

    SECTION 1: PRELIMINARIES: COLLECTION 28

    Payment

    A31.0 Interim payment to the contractor 9

    A32.0 Adjustment to the contract value 10

    A33.0 Recovery of expense and loss 10

    A34.0 Final account and final payment 10

    A35.0 Payment to other parties 11

    Cancellation

    A36.0 Cancellation by employer contractors default 11

    A37.0 Cancellation by employer loss and damage 11

    A38.0 Cancellation by contractor employers default 11

    A39.0 Cancellation cessation of the works 12

    Dispute

    A40.0 Dispute settlement 12

    Substitute Provisions

    A41.0 State clauses 12

    Contract Variables

    A42.0 Pre-tender information 12

    SECTION B: JBCC PRELIMINARIES

    B1.0 Definitions and interpretation

    B1.1 Definitions and interpretations 13

    B2.0 Documents

    B2.1 Checking of documents 13

    B2.2 Provisional Bills of Quantities 13

    B2.3 Availability of construction documentation 13

    B2.4 Interests of agents 13

    B2.5 Priced documents 13

    B2.6 Tender submission 13

    B3.0 The Site

    B3.1 Defined works area 13B3.2 Geotechnical investigation 13

    B3.3 Inspection of the site 13

    B3.4 Existing premises occupied 14

    B3.5 Previous work dimensional accuracy 14

    B3.6 Previous work defects 14

    B3.7 Services known 14

    B3.8 Services unknown 14

    B3.9 Protection of trees 14

    B3.10 Articles of value 14

    B3.11 Inspection of adjoining properties 14

    B4.0 Management of contract

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    51/317

    R

    c

    SECTION 1: PRELIMINARIES: COLLECTION 29

    B4.1 Management of the works 14

    Carried forward R

    Brought forward

    B4.2 Programme for the works 14

    B4.3 Progress meetings 14

    B4.4 Technical meetings 14

    B4.5 Labour and plant records 14

    B5.0 Samples, shop drawings and manufacturers instructions

    B5.1 Samples of materials 15

    B5.2 Workmanship samples 15

    B5.3 Shop drawings 15

    B5.4 Compliance with manufacturers instructions 15

    B6.0 Temporary works and plant

    B6.1 Deposits and fees 15

    B6.2 Enclosure of the works 15

    B6.3 Advertising 15

    B6.4 Plant, equipment, sheds and offices 15

    B6.5 Main notice board 15

    B6.6 Subcontractors notice board 15

    B7.0 Temporary services

    B7.1 Location 15

    B7.2 Water 15

    B7.3 Electricity 16B7.4 Telecommunication facilities 16

    B7.5 Ablution facilities 16

    B8.0 Prime cost amounts

    B8.1 Responsibility for prime cost amounts 16

    B9.0 Attendance on N/S subcontractors

    B9.1 General attendance 16

    B9.2 Special attendance 16

    B9.3 Commissioning fuel, water and electricity 16

    B10 Financial aspects

    B10.1 Statutory taxes, duties and levies 16

    B10.2 Payment for preliminaries 16

    B10.3 Adjustment of preliminaries 16

    B10.4 Payment certificate cash flow 16

    B11.0 General

    B11.1 Protection of the works 17

    B11.2 Protection / isolation of existing / sectionally occupied works 17

    B11.3 Security of the works 17

    B11.4 Notice before covering work 17

    B11.5 Disturbance 17

    B11.6 Environmental disturbance 17

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    52/317

    R

    c

    SECTION 1: PRELIMINARIES: COLLECTION 30

    B11.7 Works cleaning and clearing 17

    Carried forward R

    Brought forward

    B11.8 Vermin 17

    B11.9 Overhand work 17

    B11.10 Instruction manuals and guarantees 17

    B11.11 As built information 17

    B11.12 Tenant installations 17

    B12.0 Schedule of Variables

    B12.1 Pre-tender information 17

    SECTION C: SPECIFIC PRELIMINARIES

    C1 Contract drawings 21

    C2 General preambles 21

    C3 Trade names 21

    C4 Imported materials and equipment 21

    C5 Viewing the site in security areas 22

    C6 Commencement of works in security areas 22

    C7 Entrance permits to security areas 22

    C8 Security check of personnel 22

    C9 Prohibition on taking of photographs 22

    C10 HIV / AIDS awareness

    C10.1 Awareness champion 23

    C10.2 Awareness workshops 23C10.3 Posters, booklets, videos, etc 23

    C10.4 Access to condoms 23

    C10.5 Monitoring 23

    SECTION 1

    PRELIMINARIES

    CARRIED TO FINAL SUMMARY R

    SUBTOTALS: R C

    Category: Fixed R

    Category: Value R

    Category: Time R

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    53/317

    Nkonkwana Jss

    E13/691

    SECTION NO. 2

    BUILDING COMPLEX

    28

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    54/317

    Nkonkwana Jss

    E13/691

    Unit Quantity Rate Amount

    EARTHWORKS (PROVISIONAL)

    SECTION NO. 2

    BUILDING COMPLEX

    (CPAP WORK GROUP NO. 104 UNLESS

    OTHERWISE STATED)

    Bill No. 1

    TRADE PREAMBLES

    Trade Preambles:

    For Trade Preambles refer to 'Model Preambles for Trades'

    (1995 edition) for the full descriptions of material to be used

    and work to be done in this Bill.

    SUPPLEMENTARY PREAMBLES

    Nature of ground:

    The nature of the ground is assumed to be loose sandy

    material, therefore earth, but possibly interspersed with hard

    rock or soft rock.

    Carting away of excavated material:

    Descriptions of carting away of excavated material shall be

    deemed to include loading excavated material onto trucks

    directly from the excavations or, alternatively, from stockpiles situated on the building site.

    Excavations, Filling , etc.

    The Contractor shall notify the Principal Agent as soon as the

    excavations are ready to receive foundations and no building

    work may be started until the Principal Agent has approved

    the excavations.

    Over excavations taken beyond the levels and sizes shown or

    required to obtain a solid foundation shall be filled by the

    contractor, at his own expense, with 15MPa concrete.

    Should the Contractor consider that any of the excavations are

    more difficult in nature than excavations in "earth" he shall

    immediately notify the Quantity Surveyor in writing. Failing

    such notification the excavations shall be deemed to be in

    "earth" and shall be measured and valued accordingly.

    The Contractor may use any method he chooses to excavate

    any class of material, but his chosen method of excavations

    shall not determine the classification of the material

    excavated.

    Section No. 2TOTAL CARRIED TO BILL SUMMARY R

    Bill No. 1

    Earthworks (provisional)

    29

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    55/317

    Nkonkwana Jss

    E13/691

    Unit Quantity Rate Amount

    Blasting:

    No blasting will be allowed without the written permission ofthe Principal Agent.

    Should blasting be necessary, the Contractor shall take every

    precaution to protect the Works and persons, animals and

    property in the vicinity of the Works. The Contractor will be

    held responsible for any injury or damage caused by any

    blasting operations and shall make good such damage at his

    own expense.

    Testing:

    Prices for filling are to include for all necessary density tests

    in accordance with SANS 1200D.

    Prescribed density tests:

    NOTE: The Contractor is specifically referred to the SANS

    1200 clause regarding the number of density tests required on

    the layer work, filling, etc. The tests as prescribed are deemed

    to be included in the appropriate rates for the layer work,

    filling, etc. and will not be paid for separately. The following

    density tests measured are over and above those normally

    required by SANS 1200 and is for the use of the Engineer

    only and will only be paid for if instructed in writing and

    approved as acceptable by the Engineer.

    EXCAVATION OTHER THAN BULK

    Excavation in earth not exceeding 2m deep:

    Trenches.1 m 334

    Reduce levels under floors.2 m 46

    Bases.3 m 5

    Extra over excavations other than bulk in earth for

    excavation in:

    Soft rock.4 m 34

    Hard rock.5 m 47

    Risk of collapse of excavations other than bulk:

    Sides of trench and hole excavations not exceeding 1,5m deep.6 m 913

    Section No. 2TOTAL CARRIED TO BILL SUMMARY R

    Bill No. 1

    Earthworks (provisional)

    30

  • 8/9/2019 Volume 2 - Part 2_BoQ_10 February 2014

    56/317

    Nkonkwana Jss

    E13/691

    Unit Quantity Rate Amount

    CARTING AWAY.

    Extra over all excavations for loading, carting andd