Page 1: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

VT State Highway On-Road Bicycle Facilities Plan

Public Meeting – 30 April 2015

Page 2: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

204.30.2015RSG ● Alta ● Local Motion

Today’s Agenda

• Welcome and Introductions• Logistics of Tonight’s Meeting

- Check in with sites• Formal Presentations

- Jon Kaplan (VTrans Bicycle & Pedestrian Program Manager)

- Erica Wygonik (RSG Consultant Team Project Manager)

• Receive Public Comments on Methodology• Review Draft Map Results

- Breakout Sessions to Review the Map- Receive Public Comments on the Draft Map Results

• 7:50 P.M. Wrap Up & Next Steps

Page 3: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

304.30.2015RSG ● Alta ● Local Motion

Steering Committee

This project relies on input from a diverse group of stakeholders. To ensure we are planning around the needs of ALL cyclists, our steering committee represents many interests and has reviewed the work we are about to share.

EXTERNAL• Rutland Regional Planning Commission• Northeastern Vermont Development

Association• Tourism & Marketing• Agency of Commerce & Community

Development• VT Bike & Ped Coalition / Local Motion• VBT Bicycling & Walking Vacations• Green Mountain Bicycle Club• American Council of Engineering Consultants

VTrans• Planning & Policy• Bicycle and Pedestrian• Operations & Maintenance• Paving & Roadway• Asset Management

Page 4: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

404.30.2015RSG ● Alta ● Local Motion

Project Purpose

Overall Project Goal:

Develop a comprehensive improvement plan that identifies opportunities to enhance bicycle accommodations on the highest-ranked bicycle corridors on the State highway system.

Page 5: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

504.30.2015RSG ● Alta ● Local Motion

• Phase I (current phase):Classify the state highway system into three bicycle route tiers based on their location, connectivity, and desirability.

Project Purpose

Most DesirableModerately DesirableLeast Desirable

Page 6: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

604.30.2015RSG ● Alta ● Local Motion

Project Purpose

THREE KEY OUTCOMES

• This project helps prioritize investment decisions

• It identified important state roadways for bicycling

• Public input was a big part of how these are chosen

Page 7: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

704.30.2015RSG ● Alta ● Local Motion

Phase 1 Project Schedule

Title Aug-Sept

Oct-Nov

Dec-Jan

Feb-March

April-May

Project Kickoff

Preliminary Assessment

Public Outreach

Categorization Framework

2nd Public Outreach

Final Documentation

Steering Committee Meeting

Public Meeting

We are here

Internal Working Group

Page 8: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

804.30.2015RSG ● Alta ● Local Motion

Where do Vermonters want to Ride?

• Potential Travel Demand– Access to Bikeable Land Uses

• Work, Leisure, Errands, School • Public Opinion

– WikiMap• Recreational Demand

– Strava– Bicycle Tourists

Page 9: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

904.30.2015RSG ● Alta ● Local Motion

Desirability Equation

𝐴𝑐𝑐𝑒𝑠𝑠 𝑆𝑐𝑜𝑟𝑒 × 𝑃𝑢𝑏𝑙𝑖𝑐 𝐼𝑛𝑝𝑢𝑡 +𝑅𝑒𝑐𝑟𝑒𝑎𝑡𝑖𝑜𝑛 𝑆𝑐𝑜𝑟𝑒

Page 10: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

1004.30.2015RSG ● Alta ● Local Motion

Desirability Equation

𝐴𝑐𝑐𝑒𝑠𝑠 𝑆𝑐𝑜𝑟𝑒 × 𝑃𝑢𝑏𝑙𝑖𝑐 𝐼𝑛𝑝𝑢𝑡 +𝑅𝑒𝑐𝑟𝑒𝑎𝑡𝑖𝑜𝑛 𝑆𝑐𝑜𝑟𝑒

• Using bicycles to access destinations– Work, Leisure, Errands, School

Page 11: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

1104.30.2015RSG ● Alta ● Local Motion

Where do Vermonters want to ride?

Consider destinations within typical trip length(VT 100 Example)

DESTINATION TYPES– Homes– Employment– Shopping– Schools– Transit– Libraries– Trails

Page 12: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

1204.30.2015RSG ● Alta ● Local Motion

Destination Category Threshold Distances

From the literature and the National Household Travel Survey data, we developed the following threshold distances for the analysis.

Errands Leisure Work School

Threshold (miles) 1 1 2.5 1.5

Page 13: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

1304.30.2015RSG ● Alta ● Local Motion

Total Access Score

• Based on destination locations and weights

• Larger scores in urban areas/town centers

Page 14: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

1404.30.2015RSG ● Alta ● Local Motion

Desirability Equation

𝐴𝑐𝑐𝑒𝑠𝑠 𝑆𝑐𝑜𝑟𝑒 × 𝑃𝑢𝑏𝑙𝑖𝑐 𝐼𝑛𝑝𝑢𝑡 +𝑅𝑒𝑐𝑟𝑒𝑎𝑡𝑖𝑜𝑛 𝑆𝑐𝑜𝑟𝑒

• Weight Access Score by up to 30% based on Public Input

Page 15: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

1504.30.2015RSG ● Alta ● Local Motion

Public Input: Wikimap

• Users could draw points or lines• Users could add comments• Others could LIKE or DISLIKE

• Excellent participation – THANK YOU!

Page 16: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

1604.30.2015RSG ● Alta ● Local Motion

Quantitative

Page 17: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

1704.30.2015RSG ● Alta ● Local Motion

Quantitative

Page 18: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

1804.30.2015RSG ● Alta ● Local Motion

Public Input: Wikimap

• Users could draw points or lines• Users could add comments• Others could LIKE or DISLIKE

• Increase Access Score based on public input up to 30%

Page 19: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

1904.30.2015RSG ● Alta ● Local Motion

Desirability Equation

𝐴𝑐𝑐𝑒𝑠𝑠 𝑆𝑐𝑜𝑟𝑒 × 𝑃𝑢𝑏𝑙𝑖𝑐 𝐼𝑛𝑝𝑢𝑡 +𝑅𝑒𝑐𝑟𝑒𝑎𝑡𝑖𝑜𝑛 𝑆𝑐𝑜𝑟𝑒

Page 20: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

2004.30.2015RSG ● Alta ● Local Motion

Recreational Demand

• Strava– Total Trips: September 2013 – August 2014

– Based on Strava App

• Some bias towards recreational/training rides

• Capturing these rides valuable to this project

• Bicycle Tourism– interviews

Page 21: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

2104.30.2015RSG ● Alta ● Local Motion

Total Recreation Trips

• Includes Strava data and bicycle tourism data

• More trips recorded on rural or mountain roads in the middle of the state

Page 22: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

2204.30.2015RSG ● Alta ● Local Motion

Combining Access and Recreation

Page 23: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

2304.30.2015RSG ● Alta ● Local Motion

Desirability Equation

𝐴𝑐𝑐𝑒𝑠𝑠 𝑆𝑐𝑜𝑟𝑒 × 𝑃𝑢𝑏𝑙𝑖𝑐 𝐼𝑛𝑝𝑢𝑡 +𝑅𝑒𝑐𝑟𝑒𝑎𝑡𝑖𝑜𝑛 𝑆𝑐𝑜𝑟𝑒

Page 24: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

2404.30.2015RSG ● Alta ● Local Motion

Desirability Scores

Mileage PercentageMost Desirable 457 19%

Moderately Desirable 783 32%

Least Desirable 1186 49%

Page 25: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

Questions about Methodology?

Page 26: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

2604.30.2015RSG ● Alta ● Local Motion

Desirability Scores

• Some areas have variation across small segments

• Locations where scores are similar

• Segments will be treated consistently within a corridor

Page 27: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

2704.30.2015RSG ● Alta ● Local Motion

Prioritization

• Use to help prioritize bicycle-sensitivity in projects

• Prioritize maintenance and operations

• Use it to set performance targets

– BLOS scores for different categories

Page 28: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

2804.30.2015RSG ● Alta ● Local Motion

Desirability Scores

Does this look reasonable to you?

Page 29: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

2904.30.2015RSG ● Alta ● Local Motion

Accessing the Mapat Home

• Go to the project website:

http://vtransplanning.vermont.gov/bikeplan

• Download the Draft map:

http://www.aot.state.vt.us/resources/bikeplan/DraftTierScores34x44Final.pdf

Page 30: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

3004.30.2015RSG ● Alta ● Local Motion

Accessing the Mapat Home

http://www.aot.state.vt.us/resources/bikeplan/DraftTierScores34x44Final.pdf

• Comment in chat window

• Or email: [email protected]

Page 31: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

Review Draft Results Map

Page 32: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

3204.30.2015RSG ● Alta ● Local Motion

Anticipated Next Steps

• Documentation for Phase 1

• Phase 2: Identify critical gaps in the most desirable bicycle corridors.

• Phase 3: Identify specific areas to be considered for improvements (e.g. signage, striping, widening, etc.) to address the identified gaps in the most-desirable bicycle corridors.

Page 33: VT State Highway On-Road Bicycle Facilities Plan...Apr 30, 2015  · 04.30.2015 32 RSG Alta Local Motion Anticipated Next Steps •Documentation for Phase 1 •Phase 2: Identify critical

http://vtransplanning.vermont.gov/bikeplan

[email protected]

Erica WygonikProject Manager, RSG

Sommer BucossiAmy BellCo-Project Managers

VT State Highway On-Road Bicycle Facilities Plan

802.828.2678 VTRANS ON-ROAD BIKE PLAN Policy & Planning DivisionVT Agency of Transportation1 National Life DriveMontpelier, VT 05633-5001