w a s s a m i n e d e v e l o p m e n t p r o j e c t...
TRANSCRIPT
— Acquired in 2002 and in operation as open pit mine since 2005
— Historically mined smaller oxide pits
— Consolidated into large single Wassa Main pit in 2013
— High grade satellite pits previously supplemented ore feed and increased head grade
— Single large CIL processing plant with installed capacity of 2.7mtpa
— 500m from Wassa Main pit
— Non-refractory ore with high recoveries
— Large mine license are with 6 km of lease along strike
BACKGROUND AND HISTORY
May 2015 Site Visit2
Indicated Resource Inferred Resource
WASSA RESOURCE DEVELOPMENT 2013
May 2015 Site Visit4
— Two year LOM in 2011, two year drilling campaign increased this by 148%, despite reducing gold price
— Subsequent infill and step out drilling demonstrated high grade orebody plunging southeast and open at depth
— Infill drilling shows wide zones of significant grades between high grade intercepts
— 2013 mine plan was for open pit mining over 12 years, cash flows weighted to later years due to increasing grade at depth
Indicated Resource Inferred Resource
WASSA RESOURCE DEVELOPMENT H1 2014
May 2015 Site Visit5
— Opportunity to accelerate cash flows with underground mining motivated Company to enter into PEA
— Decision taken to do step out drilling to determine strike length
— Longer strike length allows for higher underground tonnage
— PEA delayed to allow for assessment of larger scale underground mine
Indicated Resource Inferred Resource
WASSA RESOURCE DEVELOPMENT H2 2014
May 2015 Site Visit6
— Deposit remains open in all directions
— Concession extends for over 5 kilometers to the south in the direction of strike
— Positive PEA results in November 2014 motivated progress to FS and procurement of underground development equipment
— FS results released March 2015 confirmed high IRR and quick payback on project
WASSA FEASIBILITY STUDY RESULTS MARCH 2015
INVESTMENT
MININGLong hole stoping below
existing open pit
PROCESSINGMinor upgrades to
existing Wassa processing plant
SUPPORT INFRASTRUCTURE
Fully in place
CAPEX $39M
FIRST GOLD H1 2016
*Assumption of a gold price of $1,200 per ounce used in these calculations. For further critical assumptions used in these assessments, please refer to the reports titled “NI 43-101 Technical Report on a Preliminary Economic Assessment of the Wassa Open Pit Mine and Underground Project in Ghana” and “NI 43-101 Technical Report on Preliminary Economic Assessment of Shrinkage Mining of the West Reef Resource, Prestea Underground Mine, Ghana” both of which are filed on SEDAR.
RETURN
COC PER OZ $780
AISC PER OZ $938
IRR 83%
NPV5% $176M
PAY BACK PERIOD 3.25 years
May 2015 Site Visit7
9 May 2015 Site Visit
859 RL
808 RL
Cut 2
Cut 1
Second cut expected to commence September 2015 - $1,200 pit shell
WASSA MAIN PIT DESIGN
10 May 2015 Site Visit
242 Pit
Cut 1
Cut 2
Cut 3
808 RL
739 RL
1060 RL
1030 RL
850 RL
859 RL
Third cut expected to commence September 2017 and 242 pit in 2019 -$1,200 pit shell
WASSA MAIN PIT DESIGN
May 2015 Site Visit11
— 2015 exploration decline constructed, first stopes reached
— 2016 ‘half-way pod’ reached, potential to deliver 5.6k oz of early production
— Commercial production underground reached late 2016, max production reached 2019
— Open pit mining expected to complete in 2022
— Total project life of 9 years
— Total ore mined of 24.1Mt at 2.04 g/t Au for 1.47M oz
— FS production schedule excludes any Inferred Mineral Resource
WASSA UNDERGROUND DEVELOPMENT & PRODUCTION SCHEDULE
May 2015 Site Visit14
Decline
Ore Longhole Stopes
Ore Access Drift
Exhaust Decline
WASSA EXPLORATION DECLINE – ‘HALF-WAY POD’
16
Twin decline portals from Starter Pit
Ventilation raisebore
Escape raises
Ventilation drop-raises
WASSA PROJECT DEVELOPMENT - PRIMARY INFRASTRUCTURE
May 2015 Site Visit16
May 2015 Site Visit18
WASSA PROCESS PLANT SPECIFICATIONS
— 2.7 Mtpa throughput
— 4 Stage Crushing circuit
— 2 x 5.1m x 6.7m Ball Mills
— Grind 75% -75 micron
— Mills rated at 3 MW each
— Gravity recovery 20%
— 25.0m diameter Pre-Leach Thickener
— Cyanide introduced post ball mill
— 800m Pipe Reactor – 80% dissolution
— 6 x 2500 m3 CIL Leach Tanks
— Metallurgical recovery of ~93%
WASSA MINE PRODUCTION
May 2015 Site Visit
Total 2015 2016 2017 2018 2019 2020-2024
Avg open pit ROM (Ktpd1) 5.6 7.4 6.9 5.9 4.3 5.5 4.9
Avg underground ROM (Ktpd1) 1.9 N/A 1.5 1.9 2.2 2.3 2.0
Daily tonnes processed (Kt) 7.5 7.5 7.5 7.5 7.5 7.5 7.5
Avg mill feed grade (g/t Au) 2.04 1.47 1.51 2.14 2.53 2.76 1.98
Avg recoveries 93% 93% 93% 93% 94% 94% 93%
20
114,000 120,000
169,000
200,000
218,000
175,000
176,000 171,000
114,000
11,000
$929
$1,024
$844
$747
$673
$824
$744 $629
$739 $948
$-
$200
$400
$600
$800
$1,000
$1,200
-
50,000
100,000
150,000
200,000
250,000
2015 2016 2017 2018 2019 2020 2021 2022 2023 2024
Oz Produced CoC per oz
— Mineral Reserve and Resource estimates updated
— Mineral Reserves declined as low grade ore excluded, grade increased to 2.04 g/t
— M&I Mineral Resources increased to 3.5M oz at higher grade of 2.21 g/t
— Dramatic increase in Inferred Mineral Resources to 1.4M oz at 3.79 g/t
— Q1 2015 Feasibility Study results announced
— Senior management team hired and on site
— Equipment, including underground mining fleet, either in transit or on site
— Platform for exploration decline complete
— Construction to start July 2015, open pit mining not impacted
— $7.3M of $28M budget for 2015 spent to date
2015 YTD WASSA PROJECT UPDATE
May 2015 Site Visit21
Commercial production achieved underground
Construction of exploration decline commences
First stopes reached
TIMELINE TO DELIVERY
Q3’15
First production from Wassa underground stopes
July 2015 Q2’16 Q3’16Q2’16
Underground mining permit received
May 2015 Site Visit22
May 2015 Site Visit23
SAK > 1.5 g/t blocks defining 3
shoots
242 > 2.5 g/t blocks defining shoot BS folded
around F4?
FS > 2.5 g/t blocks
defining BS parallel shoot?
BS > 2.5 g/t blocks Down plunge needs further testing
WASSA RESOURCE DEVELOPMENT - HIGH GRADE TARGETS
— Recent focus was on increasing Mineral Reserves to justify the development of underground mine
— Future exploration focused on building this Mineral Reserve
— Targeting zones closest to existing infrastructure
May 2015 Site Visit24
BS MI&I resource ~ 1 M oz
BS Inf resource ~ 1 M oz
BS 400 m step out drilling ~ 1 M
oz ?
− B Shoot mineralization is controlled by isoclinal 3rd generation folds
− The last step out drilling on 19100N intersected the projected zone which remains open down plunge
− Every 200m step out drill fence has potential to add another 500k oz of Inferred Mineral Resource
WASSA RESOURCE DEVELOPMENT – B-SHOOT EXTENSION
WASSA RESOURCE DEVELOPMENT – F-SHOOT TARGET
May 2015 Site Visit25
Halfway
pod
( F shoot)
B Shoot
ore body
— F shoot interpreted to be associated with another B Shoot parallel F3 fold closure
— Under drilled to date, but where holes intersected zones significant grades and widths were encountered
— Step out fence BSDD315M 70.5 m @ 5.85 g/t Au from 742 m
— Exploration drilling success along F shoot could increase underground tonnage from planned underground infrastructure with very little additional capex
Wassa Main Grade Thickness Image gram meters
NEFEB’15 EOM Pit
M2NDD013:14.0m @ 25.8g/t
242DD029:16.9m @ 7.6g/t
SW242RC003: 8.0m @ 11.3g/t
Legend ppm Au
242DD068:21.1m @ 10.0g/t
242DD054: 26.2m @ 2.4g/t
242DD022:12.7m @ 12.2g/t
242DD012:12.5m @ 4.3g/t
242DD023:8.2m @ 10.1g/t
242RC049:11.8m @ 4.5g/tM2NDD011:
3.8m @ 18.1g/t
242RC036:5.0m @ 17.3g/t
M2NRC011:31.9m @ 4.4g/t
STDD002:12.5m @ 5.4g/t
Drilling needed to test down
plunge extension of
242
May 2015 Site Visit26
WASSA RESOURCE DEVELOPMENT - 242 TARGET
May 2015 Site Visit27
WASSA RESOURCE DEVELOPMENT - 242 TARGET
— Located in south west oriented limb of the large deposit scale F4 fold
— Likely 242 and B shoot zones are same ore body
— F3 folding controls high grade mineralization along 242 trend, plunge to south west not yet tested at depth
— Exploration and grade control drilling intersected grades and thicknesses amenable to underground mining
— Exploration success could result in additional high grade underground ore source - however new underground development would be needed
Wassa SAK Grade Thickness Contour (g\t)*m
NSAKRC005:10.9m @ 9.4g/t
SAKRC100:59.5m @ 2.8g/t
S SAKDD052: 23.1m @ 9.5g/t
Au GT (g/t*m)
SAKRC107:9.7m @ 9.6g/t
SAKDD015: 16.4m @ 4.4g/t
SAKRC105:26.3m @ 4.9g/t
SAKRC084:23.5m @ 6.3g/t
SAKRC133:1.7m @ 67.3g/t
SAKDD060:4.8m @ 11.2g/t
SAKDD023:13.3m @ 4.4g/t
SAKDD003:20.9m @ 4.8g/t
SAKRC003:24.4m @ 3.9g/t
SAKDD031:20.0m @ 4.9g/t
SAKDD051:16.9m @ 5.7g/t
SAK1SAK2
SAK3
WASSA RESOURCE DEVELOPMENT SAK TARGET
May 2015 Site Visit28
— Three SAK pits situated on fold closures mapped during mining
— Folding controls higher grades at SAK
— North and south plunges between deposits yet to be understood
— SAK shoots are lower priority targets
— Exploration success could delineate further underground high grade ore feed