wangchhu basin - nec · held on june 25, 2015 endorsed the framework and te rms of reference for...
TRANSCRIPT
National Environment Commission
Royal Government of Bhutan
WANGCH H U BASINMANAGE ME NT P L AN 2 0 1 6
WANGCHHU BASIN MANAGEMENT PLAN
2016
National Environment Commission
Supported by:
DISCLAIMER
International boundaries shown on maps are not necessarily authoritative.
i
FOREWORD
May 30, 2016
Th e scope of water management has greatly expanded over the decades, from water to water +
ecology, then to water + ecology + institutions, and now to water + ecology + institutions + other
concerns - all encompassed in the concept of Integrated Water Resource Management (IWRM).
Th e Water Act of Bhutan 2011 mandates the National Environment Commission (NEC) to
form River Basin Committee (RBC) to manage and develop water resources in the country. In
pursuing the provisions of the Act, the National Environment Commission Secretariat (NECS)
has initiated formation of RBC and preparation of River Basin Management Plan. Th e fi rst RBC
is being piloted in Wangchhu Basin. In facilitating this process, the NEC during the 41st meeting
held on June 25, 2015 endorsed the framework and terms of reference for RBC. Accordingly, the
Wangchhu Basin Committee (WBC) was established in April 2016 for the purpose of preparing
the basin management plan and fostering a coordinated approach to management of water
resources in the basin.
Th e Wangchhu Basin Management Plan (WBMP) is the fi rst plan prepared at a basin level. A
detailed climatic, hydrological, socio-economic and institutional assessments have been carried
out to provide the socio-economic and environmental context of the Wangchhu basin. Th e plan
aims to increase and sustain water security in the basin which will be monitored through Bhutan
Water Security Index. Th e plan was prepared through participatory process and the proposed
interventions need to be mainstreamed into respective Dzongkhags, Gewogs and Th omdes fi ve
year development plans and programs. Th e NECS strongly urges respective agencies to pursue this
integration.
Th e NECS is cognizant of the likely challenges and issues that the WBC, as a new institution
with limited capacity, may face in the process of operationalization and implementation of the
plan. As the apex coordinating body for fostering water security in the country, NECS is fully
committed to provide support and cooperation in the successful operationalization of WBC and
implementation of the WBMP.
Th e formation of WBC and preparation of WBMP were supported by the technical team of ADB.
ii
Th e NECS would like to sincerely thank the Asian Development Bank and Japan fund for Poverty
Reduction for the technical and fi nancial support.
I am hopeful that the experiences and lessons learned from operationalization of WBC and
implementation of WBMP will pave the way for replication in other basins.
(Chencho Norbu)
Secretary
iii
FOREWORD
Th e Water Act of Bhutan 2011 requires that the water resources of Bhutan are managed in an
integrated manner. Th is approach is to be pursued at the level of river basin and coordinated
by river basin committees. In an eff ort to implementing the Water Act, the Wangchhu basin
was identifi ed as the fi rst basin to pilot coordinated planning and implementation of river basin
management plan towards the goal of water security.
Th e Wangchhu basin is perhaps the most dynamic of the basins in the country considering the
diversity of stakeholders in the use and management of its water resources. As the host to the
capital city and the only international airport, the basin is the hub of governance, administration
and economy of the country. It is also economically vibrant with signifi cant use of water for
agriculture and hydropower. Managing the water resources of this basin is therefore not an easy
task.
Th e Wangchhu Basin Committee is the fi rst ever river basin committee to be established in
Bhutan. It is with immense honour and anxiety that we take on this uncharted responsibility of
coordinating management of water resources in the basin. In pursuing our primary function of
preparing the Wangchhu Basin Management Plan, the stakeholders and members have constantly
engaged with technical experts in consultations and planning exercises. It is a matter of pride for us
to have come up with the fi rst river basin management plan in the country, which we expect will
require regular updates based on experience gained during implementation.
Given that both the Wangchhu Basin Committee and the management plan are new, there is
much ‘learning by doing’ to be done. We expect that there will be a need to strengthen the position
and authority of the committee while ensuring that the plan is regularly oriented to suit the needs
for eff ective planning and implementation over time.
On behalf of the Wangchhu Basin Committee, I request concerned authorities, Ministries,
funding agencies, stakeholders and the Dzongkhag and Gewog administrations in the basin to
cooperate with and support the basin committee and its Secretariat to eff ectively coordinate the
interventions towards the goal of enhancing water security in the basin.
Tashi Delek!
Kinzang Dorji
Dzongdag, Haa Dzongkhag
Chairman, Wangchhu Basin Committee
iv
ACKNOWLEDGEMENT
Th e Wangchhu Basin Management Plan (WBMP)) is the fi rst river basin management plan in
Bhutan that was conceived in keeping with the Water Act of 2011 and the 11th FYP (2013-2018).
Under the umbrella of the National Integrated Water Resources Management Plan (2016), it was
prepared by the National Environment Commission Secretariat (NECS) with inputs from the
Wangchhu Basin Committee (WBC) and supported by a Technical Assistance from the Asian
Development Bank (ADB TA 8623), with the goal to enhance water security in Wangchhu basin
through improved planning and eff ective coordination among Dzongkhag administrations and
agencies involved in water resources management in the basin.
Th e NECS and the WBC would like to thank in particular the Asian Development Bank and the
Japan Fund for Poverty Reduction. Without their technical and fi nancial support, this WBMP
would not have materialised.
Th e NECS also likes to thank the Wangchhu Basin Committee for its contribution to the planning,
especially with respect to setting priorities and assessing the budget requirements.
Lastly, the NECS is grateful to the Technical Assistance team of Egis (France) in joint venture
with the Royal Society for the Protection of Nature and the Bhutan Water Partnership for their
dedicated technical guidance and support towards the realization of the WBMP.
v
TABLE OF CONT ENTS
Foreword by Secretary, National Environment Commission Secretariat i
Foreword iii
Acknowledgement iv
Acronyms vii
Glossary x
EXECUT IVE SUMMARY 1
1. INT RODUCT ION 9
1.1. Background 9
1.2. Objectives of the WBMP 9
1.3. Methodology followed to prepare the WBMP 10
1.4. Structure of WBMP 12
2. WANGCHHU BASIN 15
2.1. General description 15
2.2. Water resources of Wangchhu basin 33
2.3. Basin governance and management structure 43
2.4. Water resource management eff orts in the basin 44
2.5. Basin Management Scheme 46
3. SIT UAT ION ANALYSIS 49
3.1. Stress factors in water management 49
3.1.1. Climate cxhange and its impacts on hydrology 49
3.1.2. Anecdotal Water-scarcity 52
3.1.3. Flood-prone areas 63
3.1.4. Critical watersheds 73
3.1.5. Limitations and impacts of hydropower development 74
3.1.6. Water quality 75
3.1.7. Governance 76
3.1.8. Lack of understanding of dimensions of water management 78
3.1.9. Other water-related fi ndings 79
vi
3.2. Problem analysis and strategy development 84
4. WANGCHHU BASIN PLAN 85
4.1. Introduction 85
4.2. Wangchhu Basin Plans and targets 86
4.3. Strengthen governance and institutional capacity
for coordinated planning, implementation and monitoring
of basin management plan 99
4.3.1. Empowerment of Wangchhu WBC for eff ectiveness 99
4.3.2. Capacity of partners in IWRM concepts and river
basin management enhanced 99
4.3.3. Capacity of Dzongkhag, Gewog and Th romde
administrations strengthened 100
4.3.4. Water User Associations formally registered and monitored 101
5. BASIN MANAGEMENT AND IMPLEMENTAT ION
ARRANGEMENTS 103
5.1. Basin Management Structure 104
5.2. Overall framework for basin planning and implementation 106
5.3. Explore possibility of reorienting the water related prioities
of the 11th FYP to priorities of the WBMP 107
5.4. Ensure water security priorities are integrated into the
Guidelines for preparation of FYPs. 107
5.5. Implementation of basin plans 107
5.6. Monitoring and reporting progress on water security index 108
5.7. Financing the operation of WBC and its basin wide
programmes and priorities 108
REFERENCES 110
APPENDICES 111
APPENDIX 1 112
APPENDIX 2 114
APPENDIX 3 120
APPENDIX 4 133
vii
ACRONYMS
ADB Asian Development Bank
AWDO Asian Water Development Outlook
BhWP Bhutan Water Partnership
BLSS Bhutan Living Standard Survey
BNWRI Bhutan National Water Resources Inventory
BTFEC Bhutan Trust Fund for Environmental Conservation
CD Capacity Development
CDTA Capacity Development Technical Assistance
CFO Chief Forestry Offi cer
CMIP5 Coupled Model Inter-comparison Project Phase 5
DAO Dzongkhag Agricultural O ffi cer
DDM Department of Disaster Management
DEC Dzongkhag Environment Committee
DEO Dzongkhag Environment O ffi cer
DES Department of Engineering Services
DGM Department of Geology and Mines
DHPS Department of Hydropower & Power Systems
DMF Design & Monitoring Framework
DOA Department of Agriculture
DOFPS Department of Forest & Park Services
DHMS Department of Hydro Met Services
DWS Drinking Water Supply
ESD Environment Service Division of NECS
FAO Food & Agricultural Organization (of the United Nations)
FEMD Flood Engineering Management Division (MOWHS)
FGD Focus Group Discussion
GIS Geographical Information System
GLOF Glacier Lake Outburst Flood
GNHC Gross National Happiness Commission
GNHCS Gross National Happiness Commission Secretariat
HP Hydropower Plants
IEC Information, Education and Communication
IT Information Technology
IWRM Integrated Water Resources Management
viii
JICA Japan International Cooperation Agency
KPI Key Performance Indicator
KRA Key Result Area
MASL Meter above sea level
MOAF Ministry of Agriculture & Forest
MOEA Ministry of Economic Aff airs
MOF Ministry of Finance
MOH Ministry of Health
MOHCA Ministry of Home & Cultural Aff airs
MOWHS Ministry of Works & Human Settlements
MPR Monthly Progress Report
NEC National Environment Commission
NECS National Environment Commission Secretariat
NIIS National Irrigation Information System
NIMP National Irrigation Master Plan
NIWRMP National Integrated Water Resources Management Plan
NLC National Land Commission
NWRB National Water Resource Board
ODE Organizational Development Exercise
PES Payment for Environmental Services
PHED Public Health Engineering Division
PlaMS Plan Monitoring System
PPT Power Point (Presentation)
RBC River Basin Committee
RBMP River Basin Management Plan
RCSC Royal Civil Service Commission
RGOB Royal Government of Bhutan
RNR Renewable Natural Resources
RSPN Royal Society for Protection of Nature (Bhutan)
TA Technical Assistance
TNA Training Needs Assessment
TOR Terms of Reference
UNESCO United Nations Educational, Scientifi c and Cultural Organization
WBC Wangchhu Basin Committee
WBMP Wangchhu Basin Management Plan
WEAP Water Evaluation And Planning, tool for water accounting
WMD Watershed Management Division
ix
WQMS Water Quality Monitoring Section of WRCD
WRCD Water Resources Coordination Division of NECS
WUAs Water Users Associations
x
GLOSSARY
Drainage basin A drainage basin or catchment basin is an extent or an area of land wherein all
surface water from rain, melting snow, or ice converges to a single point at a
lower elevation, usually the exit of the basin, where the waters join another body
of water, such as a river, lake, reservoir, estuary, wetland, sea, or ocean.i
Or, a drainage basin or catchment basin is an extent or an area of land where
all surface water from rain, melting snow, or ice converges to a single point at a
lower elevation.
Falkenmark index According to the Falkenmark Water Stress Indicator, a country or region is said
to experience “water stress” when annual water supplies drop below 1,700 cubic
metres per person per year. At levels between 1,700 and 1,000 cubic metres per
person per year, periodic or limited water shortages can be expected. When water
supplies drop below 1,000 cubic metres per person per year, the country faces
“water scarcity”ii
Hydrological water
balance
Any water entering a system (via precipitation) must be transferred into either
evaporation, surface runoff (eventually reaching the channel and leaving in
the form of river discharge), or stored in the ground as groundwater and on
the ground as snow or ice. Th is balance requires the system to be a closed
hydrological unit.iii
Integrated
Water Resources
Management
(IWRM)
IWRM is defi ned as ‘a process which promotes the coordinated development
and management of water, land and related resources in order to maximise
economic and social welfare in an equitable manner without compromising the
sustainability of vital ecosystems’.iv
IWRM components Th e components of IWRM are as follows:
1. Managing water at the basin or watershed level
Th is includes integrating land and water, upstream and downstream,
groundwater, surface water, and coastal resources.
2. Optimizing supply
Th is involves conducting assessments of surface and groundwater supplies,
analysing water balances, adopting wastewater reuse, and evaluating the
environmental impacts of distribution and use options.
3. Managing demand
Th is includes adopting appropriate water/scarcity pricing and investment
cost recovery policies, utilizing water-effi cient technologies, and establishing
decentralized water management authorities.
4. Providing equitable access
Th is may include support for eff ective water users’ associations, involvement of
marginalized groups, and consideration of gender issues.
5. Establishing policy
Examples are implementation of the polluter-pays principle, water quality norms
and standards, and market-based regulatory mechanisms.
6. Inter-sectoral approach
Utilizing an inter-sectoral approach to decision-making, where responsibility or
authority for managing water resources is coordinated well and stakeholders have
a share in the process.
i. https://en.wikipedia.org/wiki/Drainage_basin
ii. https://en.wikipedia.org/wiki/Water_scarcity
iii. https://en.wikipedia.org/wiki/Water_balance
iv. Global Water Partnership: http://www.gwp.org/Th e-Challenge/What-is-IWRM/
xi
IWRM pillars Th e three IWRM pillars relate to: (i) enabling environment (suitable policies,
strategies, and legislation); (ii) capable institutional mechanisms; and (iii)
management instruments.
IWRM spiral Th e traditional one-track approach of “predictàplanàcontrol” is no longer
appropriate. Rather, an approach that incorporates iterative learning and
fl exibility is needed to make water development plans robust to an uncertain
future faced with a variety of change drivers and challenges. Th is can be achieved
within the context of IWRM, in particular through a process of continual
evolution and improvement – which in the IWRM literature is referred to as the
“spiral approach”, see fi gure below.
From AWDO, 2013
Each spiral describes the cycle of (1) recognizing/ identifying the issues at stake;
(2) conceptualizing the mitigating strategies; (3) coordination & planning of
activities; (4) implementing, monitoring and evaluation. Each cycle typically
takes about 5 years, and thus corresponds well with the fi ve-year planning
practice of the GNHC in Bhutan. Conclusions from the evaluation of previous
round of activities will lead to renewal or adjustment of plans in the next cycle.
River basin A river basin can be defi ned as:v
Th e geographical area determined by the watershed limits of the system of waters,
including surface and underground waters, fl owing into a common terminus (cf.
Helsinki Rules, International Law Association, 1966, article II).
Or
A river basin is the portion of land drained by a river and its tributaries. It
encompasses the entire land surface dissected and drained by many streams and
creeks that fl ow downhill into one another, and eventually into the river and
exiting the area at one point, see fi gure below.
v. https://docs.google.com/a/universitywatersectorpartnership.org
xii
Schematic presentation of a river basin
NB: A (drainage) basin is basically the same as catchment area or watershed. Th e
distinction is mainly based on the scale of the area being referred to.
Th e Dublin principles
for IWRM
IWRM strategies are based on the four principles formulated at a water
conference in Dublin in 1992 (referred to as the Dublin Principles of IWRM)
and presented to world leaders at the World Summit in Rio de Janeiro in 1992.
Th e four principles are: (i) water is fi nite and vulnerable resource; (ii) need for a
participatory approach in water management; (iii) the role of women is stressed;
and (iv) water has social and economic value. Later, a fi fth principle is added: (v)
integration of the three E’s: economic effi ciency – social equity – environmental
sustainability.
Water accounting Th e systematic study of the current status and future trends in water supply,
demand, accessibility and use within a given spatial domain.vi
Water availability Th e hydrologic capacity of a water source (surface water body, groundwater,
municipal water) to sustain additional water demands after considering other
current water uses and water conditions. (GEMI, 2012) vii
In the context of this basin plan the water availability in an area has been
determined as runoff generated from precipitation within the concerned area
augmented with the infl ow from upstream areas after deducting consumption.
Water security Defi ned as “the capacity of a population to safeguard sustainable access to
adequate quantities of acceptable quality water for sustaining livelihoods, human
well-being, and socio-economic development, for ensuring protection against
water-borne pollution and water-related disasters, and for preserving ecosystems
in a climate of peace and political stability.”viii Water security may be viewed in
physical or economic terms. Physical water security is a situation wherein water is
abundant enough to meet all demands, whereas economic water security depends
on providing adequate investments in water infrastructure and services delivery.
vi. Godfrey, J. and K. Chalmers (editors). Water Accounting: International Approaches to Policy and Decision-making. Edward Elgar
Publishing, 2012.
vii. http://www.iadclexicon.org/water-availability/
viii. UN-Water: http://www.unwater.org/topics/water-security/en
xiii
Watershed A geographic area of land, water and biota within the confi nes of a drainage
divide. Watershed boundaries defi ne the aerial extent of surface water drainage
to a point. Watershed boundaries always follow the highest ridgeline around the
stream channels and meet at the bottom or lowest point of the land where water
fl ows out of the watershed. Th e boundary between watersheds is defi ned as the
topographic dividing line from which water fl ows in two diff erent directions.
However, the scale at which the land scape is examined is relevant for identifying
and defi ning watersheds. A watershed may be small and represent a single
tributary within a larger system, or be quite large and cover thousands of miles
(i.e. Mississippi River Watershed).ix
Wetlands “Wetland” is a generic term for all the diff erent kinds of wet habitats--
implying that it is land that is wet for some period of time, but not necessarily
permanently wet.x
Th ere are various defi nitions, they usually highlight three aspects: (i) the
hydrological regime (depth of fl ooding or soil saturation; (ii) the type of
plant growth (hydrophytes); and (iii) Soil development (hydric soils). Not all
defi nitions include deep permanent lakes and/or glaciers.
Wetlands are areas where water covers the soil, or is present either at or near
the surface of the soil all year or for varying periods of time during the year,
including during the growing season. Water saturation (hydrology) largely
determines how the soil develops and the types of plant and animal communities
living in and on the soil. Wetlands may support both aquatic and terrestrial
species. Th e prolonged presence of water creates conditions that favour the
growth of specially adapted plants (hydrophytes) and promote the development
of characteristic wetland (hydric) soils. xi
Wetlands vary widely because of regional and local diff erences in soils,
topography, climate, hydrology, water chemistry, vegetation and other factors,
including human disturbance.
Inland wetlands, like in Bhutan, are non-tidal and can comprise fl oodplains
along rivers and streams; isolated depressions surrounded by dry land along the
margins of lakes and ponds, and in other low-lying areas where the groundwater
intercepts the soil surface or where precipitation suffi ciently saturates the soil
(vernal pools and bogs); marshes and wet meadows dominated by herbaceous
plants, swamps dominated by shrubs, and wooded swamps dominated by trees.
NB: Perennially irrigated areas are not necessarily defi ned as wetlands under this
generic defi nition.
ix. http://www.nrcs.usda.gov/Internet/FSE_DOCUMENTS/stelprdb1042207.pdf
x. https://water.usgs.gov/nwsum/WSP2425/defi nitions.html
xi. http://www.epa.gov/wetlands/what-wetland
xiv
1
EXECUT IVE SUMMARY
1. Th e Wangchhu Basin Management Plan (WBMP) was prepared in accordance with the
requirements laid down in the Water Act (2011) and the Water Regulation (2014), giving a
prominent role to the River Basin Committee (RBC) to be established in each of the main river
basins. Accordingly, an Executive Order was issued on 14 April 2016 establishing the Wangchhu
Basin Committee (WBC). Th e WBC is composed of chairpersons of the Dzongkhag Tshogdu
(district development council), Dzongdags (district governors), Dzongkhag environment
offi cers (DzEOs) of the four Dzongkhags of Chhukha, Haa, Paro, and Th imphu and the
Environmental O ffi cer and Th ompon (Mayor)of Th imphu city. Th e position of WBC
chairperson will be rotated annually among the Dzongdags covered by the basin, and a chief
of the WRCD, NECS will be designated as interim member secretary until the time when the
WBCs are able to have their own Secretariat.
Th e Executive Order, in accordance with the provisions of Water Act, mandates the WBC to
coordinate water resource management in the basin. In particular, the WBC is a coordinating
body responsible for preparation and updating of river basin management plan, integration of
priorities in respective Dzongkhag plans, monitoring implementation of plans and reporting
on the level of water security in the basin. Th e structure and institutional linkages of the
Wangchhu Basin Committee is shown in Figure 1.
Figure 1: Structure of the WBC
2
Prior to formal establishment of the WBC, the designated members of the WBC were involved
in the preparation of the WBMP through a series of meetings and workshops. Th ese were held
from May 2015 to April 2016 and were facilitated under the Asian Development Bank fi nanced
technical assistance project “Adapting to Climate Change through IWRM.” Th e WBC was
formally established by Executive Order of the Prime Minister on 14 April 2016 (Appendix 1)
Th e WBMP was prepared in line with the NIWRMP as well as the UNESCO guidelines for
IWRM at the river basin level. It was endorsed by the WBC in its meeting on 21 April 2016.
2. Th e overall goal of the WBMP is to increase and sustain water security in Wangchhu basin through
improved planning and coordination among agencies involved in water resources management
along the framework of the Bhutan Water Security Index System (BWSIS). As with the national
level, the BWSIS at basin level comprises fi ve key dimensions: (i) rural drinking water supply
and sanitation; (ii) economic water security; (iii) urban drinking water supply, sanitation and
drainage; (iv) environmental water security; and (v) resilience to disaster and climate change. Each
dimension is scored by an index value in the range from 1 (poor) to 5 (very good), from which an
overall average score is obtained. For Bhutan the present average score is 3.08, and for Wangchhu
basin the score is 3.34 (Figure 2).
Figure 2: Present Water Security Index for Bhutan and Wangchhu basin
Th is goal of improved basin water security shall be achieved through iterative and adaptive
planning spirals matching the Five Year Plan periods, as illustrated in Figure 3. Th e time horizon
is 2033, which coincides with the end of the 14th FYP.
3
Figure 3: Schematic presentation of the IWRM spiral
(Adapted from Asian Water Development Outlook 2013)
3. Th e WBMP was prepared on the basis of climatic, hydrological, and socio-institutional
assessments as shown in the simplifi ed diagram in Figure 4.
Figure 4: Simplifi ed diagram showing methodology of preparation of the WBMP
4
4. Wangchhu basin occupies almost 12% of Bhutan’s area, and its share in forest land (10.0%),
agricultural area (12.1%), wetland (9.2%) and livestock (12.3%), as well as capital outlay (13.1%)
is in the same order of percentage. However, the percentage of population relative to the whole
country is much higher at 24%. Th e number of contract fi rms (19%) and revenue generated from
hydropower (47%) are also high for Wangchhu basin. Th e literacy rate for Wangchhu is about
10% higher than the average for Bhutan.1
5. Per the IWRM approach, the Wangchhu basin comprises one drainage basin, which is also
considered as one management unit and thus the area of jurisdiction of the WBC.2 It was sub-
divided into 19 sub-basins for hydrological assessments covering four Dzongkhags (Chhukha,
Haa, Paro, and Th imphu) and 30 Gewogs.3
6. Monthly water balances were established as the diff erence between water availability and water
consumption at present and in the 2030s for all Gewogs. Potential water shortage was assessed
using three criteria: (i) total amount of water resource per capita per year (also known as the
Falkenmark Index), (ii) total volume of water available resulting from the monthly water balance
per Gewog, and (iii) the monthly ratio of future water consumption over water availability per
Gewog. None of these criteria showed any physical water shortage in the basin. However at village
level at least 65 cases of water scarcity were reported by the Gewogs.
Th e Gewogs of Chang (Th imphu Dzongkhag), Wangchang, Hungrel and Shari (all in Paro
Dzongkhag ) might develop potential water stress beyond 2033 from increased population and
consumptive demand.
7. Climate change modelling projects that temperature and rainfall will increase in Wangchhu basin,
resulting in higher monsoon outfl ows (Figure 5)4.5
1 Th e information is obtained from Statistical Yearbook of Bhutan 2014. Contract fi rms are licensed private fi rms or contractors.
2 A drainage basin or catchment basin is an extent or an area of land where all surface water from rain, melting snow, or ice converges
to a single point at a lower elevation.
3 Five percent (%) of Dagana Dzongkhag comprising two Gewogs is also located in Wangchhu basin.
4 RCP 8.5 stands for a climate change scenario with increased greenhouse gas emissions following ‘business as usual’.
5 From the Coupled Atmosphere-Ocean General Circulation Models (GCM) MRI-CGCM3 and CCSM4 were used for downscaling,
using the APHRODITE dataset.
5
Figure 5: Monthly average maximum fl ows for RCP 8.5
It follows that the magnitude of the basin outfl ow with 50-year return period is expected to increase
by around a quarter of its present value during the 2060s. Th is is signifi cant because studies done
during the preparation of the WBMP found numerous areas that are prone to fl ooding, as shown
in Figure 6. Th ey include areas in Haa town, near the base of Rimpung Dzong in Paro, and
parts of the urban road after the Lingkarna bridge / royal garage, Centenary farmers market, and
Chanjji football stadium in Th imphu.
Figure 6: Flood-prone areas in Wangchhu basin
6
8. Two areas in particular require watershed protection and improvement. Th e Watershed
Management Division (WMD) classifi ed watershed ‘Nr. 158’, covering 71,000 ha in the lower
part of Wangchhu basin as critical. It classifi ed watershed ‘Nr. 67’ comprising 22,500 ha in and
around Th imphu Dzongkhag as ‘critical by function’ because it provides the urban centre of
Th imphu with drinking water. Th e other watersheds are in good condition and do not require
other measures than monitoring.
9. As discussed in the NIWRMP 2016, the institutional capacity for basin management needs to be
strengthened with respect to coordination between central agencies and with local administrations.
In particular, the River Basin Committee needs to assume its role in basin-level planning and
coordination among the Dzongkhags, but also the Dzongkhag and Gewog administrative units
need strengthening in order to cope with the work related to documenting the fragmented water
sources and their use, and the formal registration of Water Users Associations (WUAs) as required
by the Regulation.
Th e WUAS will have a major role in local water management at the village level, in particular
by looking after the water source, equitably allocating the supply of water among its members as
per priorities laid down in the Water Act, resolving confl icts, and maintaining the distribution
system.6
10. Th e WBMP formulates in Chapter 4 the strategies and targets for increasing the water security
along the indicators defi ned under the fi ve dimensions of the BWSI. For the Wangchhu basin, the
main thrusts are on improving the rural and urban drinking water supply and sanitation, rural
water storage, irrigation development, and fl ood protection measures. Cost estimates were also
established for the respective interventions. Th e total amount until 2033 is estimated at almost
Nu. 113 Billion evenly spread over the 12th, 13th and 14th FYP.
Once implemented, the plans refl ecting the main thrusts above would increase the average score
of water security for Wangchhu basin from the present 3.34 to 3.60 by 2033 (Figure 7).
Figure 7: Score of Water Security in Wangchhu basin
6 Article 38 of the Water Act states the following priorities in water use: 1. Water for drinking and sanitation, 2. Agriculture, 3.energy,
4. Industry, 5. Tourism and recreation, 6. Other uses
7
11. Th e priority steps for the WBC are: (i) review and refi ne the plans described in Chapter 4, and
(ii) Incorporation of the WBMP in the 12th FYP in terms of result-based programs of central line
agencies and local governments.
12. Lastly the implementation arrangements for the WBMP were elaborated in terms of institutional
capacity building, coordinated planning, implementation and monitoring of the basin management
plans, and fi nancing.
8
9
1. INT RODUCT ION
1.1. Background
Th e National Integrated Water Resource Management Plan (NIWRMP) 2016 promulgates the
importance of water security as an important development goal for Bhutan. For the purpose of
ensuring that this goal is pursued at the level of river basins, the plan defi nes fi ve management basins
namely i) Amochhu, ii) Wangchhu, iii) Punatsangchhu, iv) Mangdechhu and v) Drangmechhu.
Drawing on the requirements of the Water Act of 2011 and its regulations, each of these management
basins will have a committee to coordinate among the districts and central agencies the planning,
implementation, monitoring and reporting progress towards the goal of water security in the basin.
Th e NIWRMP also defi nes the Bhutan Water Security Index (BWSI) comprised of fi ve dimensions
and 57 indicators that provide the framework for coordinated planning, implementation, monitoring
and reporting progress.
Th is Wangchhu Basin Management Plan (WBMP) has been prepared in keeping with the Water
Act 2011, the Water Regulation 2014 and the 11th Five Year Plan (FYP) 2013-2018. Th e plan was
prepared by the Wangchhu Basin Committee (WBC) with support from the National Environment
Commission Secretariat (NECS). Considering that this is the fi rst river basin management plan
for the country, the National Environment Commission (NEC) has availed technical assistance
from Asian Development Bank to assist the NECS and the WBC in preparing the plan. As per the
requirements of the Water Act and Regulations, the WBC was established in 2016 vide Executive
Order of the Prime Minister who is also the Chairman of the NEC. For the purpose of preparing the
WBMP, NECS has (i) carried out technical assessment of water resources and issues in the basin and
(ii) constantly involved the Dzongkhag offi cials and stakeholders of Wangchhu basin in (a) training
and orientation to IWRM concepts and (b) consultations for preparation of the WBMP.
As per Water Act 2011 clause 24a, the NECS with the assistance of the WBC is responsible for
preparing and periodically updating the WBMP. Since there is not one agency entirely responsible
for the implementation of the plan, it may be noted that the WBMP is still a framework document
that will serve as a reference to dzonkghag administrations and central agencies for integration of
the identifi ed interventions in their respective plans. Owing to lack of specifi c baseline information,
this plan must be maintained as a living document with regular updates to baseline information and
targets, preferably carried out at least once every fi ve years in time for integration into the next FYP.
1.2. Objectives of the WBMP
Guided by the national goal of water security as per the NIWRMP, the goal of the WBMP is to
improve water security in Wangchhu basin through improved planning and eff ective coordination
among Dzongkhag administrations and agencies involved in water resources management in the
basin. Th is will be achieved using the frameworks of both the Bhutan Water Security Index System and
10
the iterative and adaptive planning cycles or “spirals” of Integrated Water Resources Management
(IWRM).
Specifi c objectives are:
• to assess the current situation and future prospects of water resources of Wangchhu basin;
• to defi ne intervention strategies and targets for the water security indicators for, respectively,
the 12th, 13th and 14th FYPs, and to assess the cost involved; and
• to propose institutional arrangements for eff ective implementation of the plan within the
overall institutional framework as per NIWRMP and terms of reference of the WBC.
1.3. Methodology followed to prepare the WBMP
Th e formulation of the WBMP was guided by the NIWRMP and follows the Dublin principles of
IWRM: (i) water is fi nite and vulnerable resource; (ii) need for a participatory approach in water
management; (iii) the role of women is stressed; (iv) water has social and economic value.7 Th e
three pillars of IWRM are also considered: (i) enabling environment (suitable policies, strategies,
and legislation); (ii) capable institutional framework; and (iii) management instruments.
Th e WBMP also follows the UNESCO guidelines for IWRM at river basin level. Th e basin level
approach to water management enables integration of upstream and downstream issues, and to
quantify and characterize water resources and their uses based on a water balance approach. Th is
is particularly important when considering the impact of climate change, and the response of
the hydrological cycle on the supply side and water demand side resulting from changing land
use, urbanization and industrial/ hydropower development. Risk management and climate
change adaptation strategies, such as managing extreme fl oods and droughts, are also taken into
consideration. Within an IWRM system, water availability shall be systematically monitored and
all major water abstractions shall be registered as per the Water Regulation 2014. It is essential that
diff erent basin stakeholders work together and share information. Th e roles of the stakeholders are
specifi ed in the 2014 Water Regulation further elaborated in the functions of the multi-sectoral
river basin committees to be formed, as described in the NIWRMP.
Furthermore the WBMP incorporates the concepts of ‘Methodology for Eff ective Decision-
making on Impacts and Adaptation’ (MEDIATION), which includes activities such as: (i) analysis
of the decision-making context, (ii) inventory, review and further development of methods for
impacts and vulnerability analysis, (iii) inventory, review and further development of methods
for costing of impacts and adaptation options, (iv) the development of an overarching integrated
methodology, (v) the development of a fl exible, interactive common platform for knowledge
sharing, and (vi) disseminating this knowledge by communication and training program.8
7 Th ese four principles were formulated in a water conference in Dublin in 1992, see http://www.gwp.org/en/Th e-Challenge/What-
is-IWRM/IWRM-Principles/. Later a fi fth principle was added with integration of the three E’s: economic effi ciency, social equity,
and environmental sustainability.
8 MEDIATION represents new concepts in Europe to reduce vulnerability to climate change in the most cost-eff ective way. It
needs scientifi c and technical information about climate change impacts, vulnerability and adaptation options.
11
It is emphasized that IWRM is an iterative, evolutionary and adaptive process conceptualized as a
‘spiral’ which builds on understanding of the prevailing conditions, enables immediate action where
appropriate, and fosters stakeholder ownership. For Bhutan, each cycle represents a period of fi ve
years, corresponding with the government’s FYPs. Th e IWRM process starts with recognizing and
examining the present situation under the fi ve key dimensions of water security (pertaining to (i)
rural household, (ii) economic, (iii) urban, (iv) environment, and (v) resilience), and then moves
to conceptualizing what needs to be done, followed by setting up of coordination mechanisms
under which planning is undertaken with sustained stakeholder involvement. Th is is followed by
implementation of water security measures, combined with monitoring and evaluation of progress
so as to understand the starting point for the next cycle. Consecutive cycles move the system closer
to the goal of water security. Th e process is depicted in Figure 8.
Figure 8: Schematic presentation of the IWRM spiral (Adapted from AWDO 2013)
Th e process followed in formulating the WBMP is schematically presented in Figure 9. A brief
explanation is given below.
Figure 9: Roadmap for the preparation of the WBMP
12
According to the Water Act and its regulations, the river basin management plan shall be prepared
by the river basin committee. Hence, the fundamental requirement for preparation of river basin
management plan is the establishment of river basin committee. For this, the structure and terms
of reference for formation of river basin committees was approved by the NEC. For the purpose
of facilitating preparation of the WBMP, the NEC established the WBC on 14 April 2016 vide
Executive Order by Prime Minister who is also the Chairman of NEC. Although the committee
was established only in April 2016, the process of preparing the basin plan began a year ago with
the constant involvement of the members as well as other stakeholders. Th e methodology followed
in preparing the plan is briefl y provided as follows.
Technical assessment of water availability and issues in the basin: River basin modelling was
conducted to assess the hydrological status of the Wangchhu basin. Attempts were made to analyse
water availability at the Gewog level. Water scarcities as well as 100-year return period fl oods were
assessed. Surveys were also conducted to collect information on water issues at the Gewog level.
Further, the 11th FYP water related interventions for the Dzongkhags as well as sector plans in
Wangchhu basin were reviewed.
Training and consultative planning workshops: Th e members of the WBC, Dzongkhag planning
offi cers and engineers were oriented to the concept of IWRM and Bhutan Water Security Index
(BWSI) as per the NIWRMP. Th e trainings and planning workshops provided the platform
for progressive consultations and participatory planning involvement of the WBC and the
stakeholders to assess the situation of water resources, issues, and institutional gaps and identify
priority interventions for management of the basin. Th is entailed group exercises to analyse cause
and eff ects of water issues and converting them to intervention activities and strategies, which
form the basis for the proposed plans. Cost analysis and estimates for the proposed interventions
were conducted with the assistance of Dzongkhag planning offi cers and engineer.
WBC meetings and endorsement of the plan: Although the WBC was offi cially established in
April 2016, the incumbent members were trained and constantly involved in the consultation
process. Th e draft WBMP was shared and deliberated at the fi rst WBC meeting held on 20 April
2016. Th e plan was reviewed and revised over a period of two days and endorsed on 21 April 2016.
1.4. Structure of the WBMP
Guided by the NIWRMP, this plan provides a comprehensive description of the geographical,
social, economic, and environmental context of the Wangchhu basin. Based on climate change and
hydrological assessments carried out for the country, the water availability and water balance for
the basin have been assessed. Th is is followed by statement of water related issues based on which
interventions, strategies and implementation arrangements are proposed. Detailed description of
subsequent chapters is given below:
Chapter 2 introduces the Wangchhu basin providing general description of its geography and
climate, administrative boundaries and socio-economic conditions. It also describes the water
13
resources of Wangchhu basin, the status of the BWSI for the basin, and the composition and role
of the WBC.
Chapter 3 focuses on the analyses of issues and stress factors related to water management in
Wangchhu basin. Th e areas covered include basin-specifi c impact of climate change, water scarcity
at Gewog level, fl ood-prone areas, critical watersheds, limitations and impacts of hydropower
development, and water governance issues. Th e chapter also presents a problem analysis and
strategy development based on a participatory logical framework analysis carried out by WBC
members and stakeholders.
Chapter 4 presents the plan based on the BWSI and expressed in terms of Key Result Areas and
Key Performance Indicators. Baseline values and targets are presented, with an explanation of the
next steps to be taken. Th e latter are expected to be used as a guide to preparing water resource
development plans in the series of FYPs formulated by the Gross National Happiness Commission
(GNHC) in coordination with competent authorities and local administrations. Th e WBMP’s
planning horizon is 2033, the end of the 14th FYP.
Chapter 5 deals with implementation arrangements for implementation of the WBMP. Th is
includes institutional capacity building, fi nancial modalities, and monitoring and reporting
mechanisms.
Position of WBMP relative to other documents
Legally, the WBMP is positioned under the NIWRMP as required under the Water Act (Figure
10). Whereas the NIWRMP provides the overall planning and coordination framework of water
resources management in Bhutan, the WBMP aims at guiding the formulation of annual and
FYPs for the districts and central agencies, per the requirements of the GNHC. As such, the plans
and targets laid-out in the WBMP are not binding for the Basin Committee, also because there is
no guarantee that the necessary resources for implementation of the plans will be available.
14
Vision
Gives an
aspirational
description of
longer-term goals.
Policy
The basic principles
by which the
government is
guided
NIWRMP
Outlines a
framework for
coordinated
approach to IWRM
with a defined role
for stakeholders
Legal framework
Water Act of
Bhutan (2011),
Water Regulation
of Bhutan (2014)
and water-related
legislation
RBMP
Plan for achieving
the protection,
improvement and
sustainable use of
the water
environment in the
river basin
Five Year Plans
Articulate the
outcomes and
outputs to be
achieved over the
concerned period
BWSI
Describes the
degree of water
security achieved or
pursued in five key
dimensions
Figure 10: Diagram showing the relation between diff erent documents
15
2. WANGCHHU BASIN
Th is chapter introduces the Wangchhu basin with respect to its geography and climate,
administrative boundaries and socio-economic conditions. Th e state of the basin in terms of its
water resources and current level of water security based on Bhutan Water Security Index are
also described. Hydrological assessment, water resources of the basin are described at the level of
Dzongkhags and Gewogs. After briefl y presenting previous plans and studies undertaken in the
basin, this chapter gives a general description of Wangchhu basin It also describes the, the status
of the Bhutan Water Security Index for Wangchhu, and the composition and role of the WBC.
2.1. General description
Geography
Th e Wangchhu basin is located in the western part of Bhutan between Amochhu basin in the
extreme west of the country and Punatsangchhu basin to the east. It borders China to the north
and India to the south (Figure 11).
Figure 11: Location of Wangchhu basin in Bhutan
Th e total area is 4,596 km2, almost 12% of the country. Th e elevation of the terrain varies from
below 750 meters above sea level (m.a.s.l.) to over 5,000 m.a.s.l. (Figure 12).
Th e land cover map is presented in Figure 13 and shows the distribution of snow and glaciers,
water bodies, shrub and grasslands, forest by type, agricultural and urban areas.
16
Figure 14 shows the protected areas and wildlife corridors facilitating free passage of wildlife
between them for nature conservation in Wangchhu basin.
Figure 12: Topography of Wangchhu basin Figure 13: Land cover map of Wangchhu basin
17
Figure 14: Protected areas and corridors in Wangchhu basin
Administrative boundaries
Th e Wangchhu basin comprises primarily of the Dzongkhags of Chhukha, Haa, Paro, Th imphu
and a small part of Dagana with a total of 32 Gewogs as shown in Figure 15 and Table 1.
18
Figure 15: Local Government units in Wangchhu Basin
Table 1: Gewogs in the Wangchhu basin
Dzongkhag GewogTotal Area
km2
Area inside
Wangchhu basin
km2
Area inside Wangchhu
basin %
Haa Bjee 747.3 283.3 37.9
Haa Gakiling 338.7 - -
Haa Katsho 40.6 40.6 100.0
Haa Samar 200.6 200.6 100.0
Haa Sangbay 507.4 - -
Haa Uesu 66.3 66.3 100.0
19
Haa Total 1,900.9 590.8 31.1
Dzongkhag Gewog NameTotal Area
km2
Area inside
Wangchhu basin
km2
Area inside Wangchhu
basin %
Chhukha Bjachho 140.2 140.2 100.0
Chhukha Bongo 398.5 398.5 100.0
Chhukha Chapcha 128.9 128.9 100.0
Chhukha Darla 135.2 111.4 82.4
Chhukha Dungna 202.0 58.5 29.0
Chhukha Geling 221.4 81.3 36.7
Chhukha Getana 241.1 241.1 100.0
Chhukha Loggchina 71.8 - -
Chhukha Metakha 129.4 30.0 23.2
Chhukha Phuentsholing 133.2 - -
Chhukha Samphelling 73.8 - -
Chhukha Total 1,875.6 1,189.9 63.4
Dzongkhag Gewog NameTotal Area
km2
Area inside
Wangchhu basin
km2
Area inside Wangchhu
basin %
Paro Dokar 105.8 105.8 100.0
Paro (Dop)shari 33.8 33.8 100.0
Paro Doteng 194.4 194.4 100.0
Paro Hungrel 10.4 10.4 100.0
Paro Lamgong 48.9 48.9 100.0
Paro Lungney 75.6 75.6 100.0
Paro Naja 136.4 136.4 100.0
Paro Shaba 80.0 80.0 100.0
Paro Tsento 578.7 578.7 100.0
Paro Wangchang 20.6 20.6 100.0
Paro Total 1,284.7 1,284.7 100.0
Dzongkhag Gewog NameTotal Area
km2
Area inside Wangchhu
basin km2
Area inside Wangchhu
basin %
Th imphu Chang 156.6 156.6 100.0
Th imphu Dagala 203.8 203.8 100.0
20
Th imphu Geney 60.8 60.8 100.0
Th imphu Kawang 297.2 297.2 100.0
Th imphu Lingzhi 386.2 49.3 12.8
Th imphu Mewang 229.7 229.7 100.0
Th imphu Naro 280.9 280.9 100.0
Th imphu Soe 177.6 177.6 100.0
Th imphu Total 1,792.8 1,455.9 81.2
Dzogkhag Gewog NameTotal Area
km2
Area inside Wangchhu
basin km2
Area inside Wangchhu
basin %
Dagana Dorona 107.47 36.93 28.5
Dagana Dzingkha 105.09 37.79 35.96
Grand total 8,567.0 4,589.7
Socio-economic and other conditions
A profi le of Wangchhu basin is presented in Table 2. As can be seen, the Wangchhu basin occupies
almost 12% of Bhutan’s total area. Its share in forest land (10.0%), agricultural area (12.1%),
wetland (9.2%) is more or less in the same proportion. Livestock holding in Wangchhu basin is
12.3% of the total in the country, and the share of capital outlay under the 11th FYP is 13.1%.
However, the percentage of population relative to the whole country is much higher at 24%, and
so are the number of contract fi rms and revenue generated from hydropower, which make up 19%
and 47% respectively of the national total9. Th ese data show the socio-economic importance of
Wangchhu basin.
9 Th e information is obtained from the Statistical Yearbook of Bhutan 2014. Th e term “contract fi rms” is understood to include
licensed private fi rms and contractors.
21
Tab
le 2: P
rofi
le of W
ang
chh
u b
asin
Area
Fractio
n o
f
area located
in W
ang
chh
u
basin
To
tal area F
orest
Ag
ric. areaW
etland
Livesto
ckR
ainfall
GL
OF
po
tential*
Po
pu
lation
Co
ntract
firm
s
Hyd
ro-
po
wer
revenu
e
Cap
ital
ou
tlay
11
th
FY
P
ratio[h
a][h
a]%
[ha]
%[h
a]%
[nu
mb
er][m
m]
[nu
mb
er][n
um
ber]
[nu
mb
er][m
illion
un
its]
[millio
n
Nu
]
Ch
hu
kh
a0
.42
21
88
,13
11
61
,25
58
69
,24
14
.91
,79
90
.96
30
,87
08
72
-3,0
41
08
8,3
20
1,0
16
1,9
07
56
0
Haa
0.5
54
18
6,5
95
12
1,7
09
65
2,7
80
1.5
88
0.0
51
7,8
51
81
40
13
,41
73
25
4,9
14
34
9
Paro
11
25
,16
47
6,0
20
61
6,3
40
5.1
1,7
53
1.4
01
7,6
24
49
0-2
,52
20
42
,82
36
87
47
7
Thim
ph
u0
.78
51
74
,69
37
4,8
68
43
2,2
74
1.3
45
80
.26
16
,66
25
05
-60
90
12
3,2
25
4,8
21
35
0
Dagan
a0
.05
17
1,3
00
Wan
gchh
u
basin
45
3,6
28
27
0,2
68
60
13
56
53
.02
92
00
.64
53
62
05
05
-3,0
41
01
84
,25
95
,08
03
,52
71
,18
1
Bh
utan
3,8
39
,40
02
,70
5,2
41
70
11
2,5
49
2.9
31
,91
00
.83
43
7,5
75
50
0-5
,00
02
47
63
,97
71
3,1
44
7,5
50
9,0
00
% fo
r
Wan
gchh
u/
Bh
utan
11
.81
0.0
-1
2.1
-9
.2-
12
.3-
0.0
24
.13
8.7
46
.71
3.1
• G
LO
F =
Glacial L
ake O
utb
urst F
loo
d. S
ou
rce: Statistical yearbo
ok
Bh
utan
(20
14
)
22
Wangchhu basin has a population of 184,259, which is 24% of the national population. Th e
distribution is shown in Figure 16. Th e population of Wangchhu basin is expected to grow by
almost 30% to 240,000 by 2033.
Figure 16: Population in Wangchhu (2015)
Table 3 shows the gender-segregated participation of men and women in the labour force and their
respective share in unemployment. As can be seen, the total labour force participation is highest
in Chhukha (61.5%) and Paro (59.6%), both slightly above national average. Th e labour force
participation for men is some 20% higher than for women in Wangchhu basin and at national
23
level. Th e highest diff erence is in Th imphu (35%) and the lowest is in Haa (8%).
Table 3: Dzongkhag-wise labour force participation by gender
DzongkhagLabour Force Participation Rate Unemployment Rate
Male Female Total Male Female Total
Chhukha 74.7 48.3 61.5 1.9 2.9 2.3
Haa 61.3 53.5 57.4 1.4 2.0 1.7
Paro 65.3 54.5 59.6 3.3 2.3 2.8
Th imphu 71.7 35.9 53.0 4.3 11.5 6.9
Wangchhu 68.3 48.1 57.9 2.7 4.7 3.4
Bhutan 69.5 49.9 59.4 2.4 3.2 2.7
Source: Bhutan Living Standard Survey, 2012
In Wangchhu basin, Th imphu (61.8%) has the highest proportion of income derived from wages
and salaries followed by Chhukha at 58%. Haa at 39.7% and Paro at 38.4% have much lower
proportion of income derived from wages amongst the four Dzhonkhags and also when compared
to Bhutan’s average of 57.2%. Agricultural income is highest in Haa at 39.7% much above the
Bhutan average of 10.2% with Th imphu having the lowest proportion – at 1.1%.10 See Table 4.
Table 4: Dzongkhag-wise annual household income in Ngultrum by source
Dzongkhag Income Source % of Household income
Wages Agric. Non-Agric. Total Wages Agric. Non-
Agric.
Chhukha 150,731 12,051 97,205 259,988 58.0 4.6 37.4
Haa 45,604 50,493 31,181 127,278 35.8 39.7 24.5
Paro 77,483 34,542 89,798 201,823 38.4 17.1 44.5
Th imphu 189,022 3,420 113,333 305,775 61.8 1.1 37.1
Bhutan 94,275 16,894 53,660 164,829 57.2 10.2 32.6
Source: Bhutan Living Standard Survey, 2012
Th e status of poverty in the Gewogs of Wangchhu is presented in Table 5.11 It appears that Paro
has the least poverty (all Gewogs less than 15%), followed by Th imphu (two Gewogs 16-26%).
Chhukha has the most poverty with (two Gewogs above 52%, and another two Gewogs with 37-
51%.
10 Refer to standalone supporting document titled: Social aspects of water resource management in Bhutan
11 Bhutan poverty assessment, National Statistics Bureau, RGOB, 2014: Poverty is defi ned as a consumption level of less than US$
1.25 per capita per day.
24
Table 5: Status of poverty in Gewogs of Wangchhu basin
DzongkhagGewogs inside Wangchhu
basin
Class of Poverty in Gewog Poverty Head Count12
1. Chhukha
Bjachho 1 0% -15%
Bongo 2 16%-26%
Chapchha 1 0% -15%
Darla 3 27%-36%
Geling 3 27%-36%
Getana 5 52%-69%
Metakha 4 37%-51%
2. Haa
Bjee 1 0% -15%
Katsho 1 0% -15%
Samar 2 16%-26%
Uesu 1 0% -15%
3. Paro
Dokar 1 0% -15%
(Dop)shari 1 0% -15%
Doteng 1 0% -15%
Hungrel 1 0% -15%
Lamgong 1 0% -15%
Lungney 1 0% -15%
Naja 1 0% -15%
Shaba 1 0% -15%
Tsento 1 0% -15%
Wangchang 1 0% -15%
4. Th imphu
Chang 1 0% -15%
Dagala 1 0% -15%
Geney 2 16%-26%
Kawang 1 0% -15%
Lingzhi 1 0% -15%
Mewang 1 0% -15%
Naro 2 16%-26%
Soe 1 0% -15%
Poverty head count classes: 1=0% -15%; 2=16%-26%; 3=27%-36%; 4=37%-51%; 5=52%-69%
25
Hydropower
Hydropower generation is the biggest earner of revenue in Wangchhu basin. Th e location of
existing and planned hydropower stations is shown in Figure 17.
Figure 17: Existing and planned hydropower stations in Wangchhu basin
26
Large hydropower stations
Existing hydropower stations
Th ere are two large existing hydropower stations in Wangchhu basin at Tala (1,020 MW) and at
Chhukha (336 MW). Th ese are run-of- river power stations that do not have large reservoirs.
New hydropower stations
Two new hydropower plants are planned in Wangchhu basin. Th ey are the Wangchhu Hydro
Electric Project with a proposed installed capacity of 570 MW. It will have a head race tunnel of
12.4 km length and storage dam of 134 meter height above foundation, with a crest level of 498
m.a.s.l. Th e full reservoir level will be set at 494 m.a.s.l. and the live storage of the reservoir will be
14.5 million cubic meters (MCM).
Th e second planned project is at Bunakha, also in Chhukha Dzongkhag located in Geling and
Chapcha Gewogs. Its planned installed capacity will be 180MW and it is proposed to be a reservoir
scheme project with some seasonal storage. Th e generators will be located at the toe of the storage
dam, hence there will be no head race tunnel. Th e dam height will be 197 m above foundation,
with a crest level of 2,010 m.a.s.l. Th e live storage of the reservoir will be 250.6 MCM.
Small hydropower stations
Th e status of existing small hydropower stations is given in Table 6.12
Table 6: Status of existing small hydropower stations
District Location Output in KW Built/ Renovated
Th imphu Gidakom 250x5 1973/ 2001
Th imphu Mini 100x4 1967/ 1998
Th imphu Lingzhi 8x1 1999
Th imphu Th inleygang 30x1 1987/ Shut down
Th ree additional small run-of-the-river hydropower stations are under consideration in the
Wangchhu basin. Investigations have been done to check whether these plants could be equipped
with a multi-purpose reservoir in order to level-out the seasonal variation of power generation, and
to supply drinking and irrigation water. Th e fi ndings are summarized in Table 7.
12 Data collection renewable energy, JICA, 2013
27
Table 7: Proposed small hydropower stations and their potential for multi-purpose reservoir.
District LocationAnnual output in
MWh
Potential for multi-
purpose reservoir
Haa Nagu 3 Yes
Chhukha Chapcha 23 No
Chhukha Tamachu 10 No
Th ere may be a potential for a multi-purpose reservoir in connection with the proposed small
hydropower stations only in Haa district.
Agriculture
Existing agricultural areas and irrigation infrastructure are shown in Figures 18 and 19. As elsewhere
in the country, farming system in the Wangchhu basin includes crop production, horticulture,
livestock and forestry. Th e basin has a total of 13,565 ha of arable land. Th ere are 4,291 ha of dry-
land (Khamzhing), 3,428 ha of slash and burn practiced agriculture (tseri/pangzhing), 2,114 ha of
wetlands, 1,169 ha of orchards and 166 ha of kitchen gardens.13 In the Wangchhu basin, Chhukha
has around 9.3% of land under cultivation followed by Paro (6.3%), Haa (2.8%) and Th imphu
(2.3%). Together they have 3% of the area under cultivation which is the same as the average of
Bhutan (2.9%) as shown in Table 2.
13 Tshering et al., 2009
28
Figure 18: Agricultural areas in Wangchhu basin
29
Figure 19: Irrigation infrastructure in Wangchhu basin
Common crops grown in Wangchhu basin are paddy, maize, wheat, barley, millet. Fruits like
apples, oranges, plums, pears and vegetables like caulifl ower, potato, carrot, tomato, and chillies
are also grown.
Membership of groups for agriculture, irrigation and other purposes is presented in Table 8. As
shown, agricultural groups are much stronger developed in Chhukha (8.7%) than in other districts
of Wangchhu basin (less than 2%), but water user associations (WUAs) are most developed in
Paro district (15.75%) but not in other districts (0%).
30
As per Water Act and Regulations, WUAs shall be registered with the Gewog administration. In
the past however, water users groups were formed as a cooperative group under the Marketing
Act and they were expected to have an income-generating activity. Th ey have been trained and
operated a bank account, but most of them are in fact not functioning because the leaders became
disconnected from the community.14
Th e existing water management groups are not registered with the government or under any
offi cial system; therefore, they do not have formal government recognition. Members often pay
a contribution to employ a water tender for maintenance of the water supply system. Table 9
presents the number of informal water groups found in the primary survey conducted.15
Table 8: Percentage of household membership in groups as per primary survey
Groups Percentage of household members
Chhukha Haa Paro Th imphu
Agriculture Group or Association 8.7 0.0 0.0 1.6
Community Forest Group 2.5 18.9 0.7 2.1
Credit or Saving Group 0.0 0.0 0.0 7.5
Dairy Production Group 3.3 0.0 6.7 0.0
Education Service Group 15.8 0.0 0.0 0.0
Farmer Group–Other 32.3 0.0 0.0 0.0
Farmer Group–Production 0.0 2.8 0.0 5.8
Games, Sports, and Entertainment 38.5 0.0 0.0 47.4
Health Care and Cleaning Club/Group 36.8 0.0 0.0 8.7
Livestock Association or Group 9.6 0.0 0.0 0.0
Local Development Group 19.3 0.0 0.0 0.0
Occupation Group 5.9 0.0 11.9 43.5
Other Group 27.7 0.0 0.0 22.5
Spiritual Group or Association 6.1 0.8 4.5 4.2
Village or Community Group 0.0 0.0 0.0 24.7
Water User Association 0.0 0.0 15.8 0.0
Welfare and Charity Group 11.2 4.1 5.8 17.4
Women‘s Association 13.5 5.7 6.3 2.9
All 8.7 5.5 2.9 6.4
14 Feed-back from the national stakeholder consultation workshop held in Th imphu on 4 February 2016.
15 See stand-alone supporting document: Social aspects of Water Resources Management in Bhutan
31
Table 9: Informal water groups found in primary survey
DzongkhagVillages
Existence of WUAs Other Associations and groups
Chhukha Gewog: Bjachho
Mebesa No Vegetable group, farmers group
(male)
Tashigatshel No No
Gewog: Bongo
Meritsemo One water caretaker -
paid
Vegetable association. Male,
women’s group
Pakshingkha One water care taker -
paid
No
Gewog: Darla
Nimgang Yes – 5 members Vegetable association - Male;
farmers association - women
Taptangbu No Farmers group (men & women)
Paro Gewog: Tsento
Namji No Farmers group (men & women),
milk association (men & women)
Phangdo No Farmers group (men & women)
Gewog:Shaba
Zhen-kha-na
Yes, 3 members Farmers group (men & women)
Bara One caretaker - paid Farmers group (men & women)
Gewog: Naja
Wanakha Yes, 2 members Farmers group (men & women)
Tokha Yes, 2 members Gyalpo Zimpon for poor families
only, framers group (men &
women)
Haa
Gewog: Samar
Balamna Yes, 3 members No
Puduna No No
Gewog: Katsho
Ingo Yes, 3 members No
32
DzongkhagVillages
Existence of WUAs Other Associations and groups
Naktsho Yes, 2 members & one
paid plumber
No
Gewog:Bjee
Tokey Yes, 3 members
Yangthang Yes, 3 members No
Th imphu Gewog: Mewang
Jamdo Yes – 2 persons Farmers group (male & female)
Tshenden Dhapsa No Farmers group (male)
Gewog: Kawang
Chokhor No Farmers group (male & female),
milk association
Zhoshie Water caretaker - paid No
Gewog:Geney
Chesing Water caretaker – paid No
Wangbama Water care taker - paid No
Literacy and education
Th e gender-segregated literacy rate and educational attainment are given by Dzongkhag in Tables
10 and 11, respectively. Th is shows that the Wangchhu basin population has a higher literacy rate
compared to the national average.
Table 10: Dzongkhag-wise gender segregated literacy status
DzongkhagGeneral Literacy
Male Female Total
Chhukha 79.5 61.4 70.5
Haa 79.5 56.8 68.6
Paro 77.7 57.5 67.3
Th imphu 87.4 73.3 80.0
Average 81.0 62.3 71.6
Bhutan 71.6 54.7 63.0
Source: Bhutan Living Standard Survey, 2012
33
Table 11: Dzongkhag-wise educational attainment rate
DzongkhagPrimary School Completion Secondary School Completion
Male Female Total Male Female Total
Chhukha 101.5 77.5 90.5 63.4 87.8 74.5
Haa 128.2 204.3 156.2 61.0 85.2 71.5
Paro 63.0 95.3 78.4 107.5 82.0 90.4
Th imphu 82.5 87.6 85.2 104.3 80.4 91.4
Bhutan 85.8 92.6 89.0 68.8 74.2 71.4
Source: Bhutan Living Standard Survey, 2012
2.2. Water resources of Wangchhu basin
Climate pattern in Wangchhu basin
A summary of climatic data is given in Table 12.
Table 12: Summary of climatic data
Dzongkhag
(Station)
Altitude
(m)
Temperature (0/C)Rainfall
(mm)
Relative
humidity
(%)
Wind
speed
(m/s)
Sunshine
duration
(hr)Max Min
Haa (Namjeyling) 2,751 16.3 4.9 866 72.8 0.9 5.5
Chhukha
(Phuentsholing)270 29.8 19.8 3,888 79.1 0.9 4.8
Paro (DSC) 2,406 19.9 8.2 661 70.2 0.6 4.8
Th imphu
(Simtokha ) 2,310 22.0 8.2 597 67.8 1.0 5.7
Source: Department of Hydro-Met Services (DHMS)
Th e pattern of precipitation and evaporation over Wangchhu basin is shown in Figure 20 and 21.
Th e monthly distribution is shown in Table 13 and Figure 22.
34
Figure 20: Annual precipitation over Wangchhu basin
Table 13: Monthly 80%-dependable rainfall and evaporation (Eo) per district
Month
StationJan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Haa rain 10.4 14.2 25.5 46.7 62.9 108.8 155.3 148.5 106.3 58.6 2.2 3.5 742.9
Haa E0 47.1 52.6 75 87 98.6 91.8 97.7 96.1 83.4 75.3 57 47.4 909
35
Paro rain 5.9 8.8 14.4 22.3 40.4 58.5 120.5 79.3 62.2 35.5 6.4 2.8 457
Paro E0 45.3 54.9 78.4 90.6 103.5 96 97.3 97.3 84.9 78.7 55.2 42.5 924.6
Chhukha rain 13 23.3 55.8 159.9 285.2 628.4 669 553.9 317.8 117.6 9.3 8.5 2841.7
Chhukha E0 59.2 72 103.5 112.8 119 101.4 99.5 102.9 92.4 100.1 80.7 66 1109.5
Th imphu rain 5.5 8.5 13.8 22.3 40.1 82.1 120.8 105.6 56.2 37.6 1.4 3.2 497.1
Th imphu E0 53 62.2 89.6 102.9 115 108 113.8 110.4 96.9 88 65.4 53.9 1059.1
Figure 21: Annual evapotranspiration over Wangchhu basin
Source: National Irrigation Master Plan, 2016
36
Figure 22: Graphical presentation of monthly 80%-dependable rainfall versus evaporation in mm
Th e present irrigation water demand per hectare for each agro-climatic zone is derived from the
National Irrigation Master Plan, and is given per district in Table 14. Th ese fi gures are used for
calculating the present irrigation water demands of existing irrigated areas as well as proposed
expansion areas.
Table 14: Irrigation water demand in l/s/ha
Station\Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Haa -
Namjeyling0.00 0.00 0.11 0.29 0.38 0.13 0.00 0.00 0.00 0.00 0.00 0.00
Paro DSC 0.23 0.34 0.45 0.30 1.88 2.92 1.76 1.59 1.51 0.97 0.07 0.31
Chhukha -
Phuentsholing 0.56 0.90 0.74 0.37 1.36 1.17 0.37 0.29 1.42 1.42 0.52 0.19
Th imphu -
Simtokha0.27 0.38 0.51 0.34 1.93 2.92 1.88 1.57 1.61 1.01 0.08 0.34
Source: National Irrigation Master Plan 2016
As shown in Table 13, the 80%-dependable rainfall in Wangchhu basin ranges from 457 mm in
Paro to 2,842 mm in Chhukha. Analysis of rainfall data over Wangchhu basin over the last two
decades shows a negligible decreasing trend for Haa, Paro and Th imphu, but a clearly decreasing
trend for Chhukha as shown in Figure 23.
37
Figure 23: Rainfall trends in Wangchhu basin over the last two decades
Th e number of consecutive dry days (less than 1 mm precipitation per day) was investigated for
diff erent elevation zones in Bhutan over the last three decades. Th ey fell slightly around values of
35 days for the southern foothills, 40 days for the inner Himalayas, and 60 days for the higher
Himalayas, and these fi ndings are also representative for the Wangchhu basin.
Fresh water resources
Th e entire drainage basin of Wangchhu is discharging an annual 5,200 MCM, or 7.4% of Bhutan’s
total river fl ow into India (Table 15). Th e Wangchhu is the main drainage channel of the basin
(Figure 24). Th e main tributaries are Tangochhu, Bjemirongchhu in Th imphu , Deochhu and
Parochhu in Paro , Haachhu in Haa , and Pipingchhu in Chhukha. Th e overall length of rivers in
the basin is about 553 km comprising the Wangchhu, Parochhu and 19 tributaries. Th e longest
river is Parochhu at 173 km. For hydrological assessments the river basin has been sub-divided
into 19 sub-basins.
Table 15: Average net monthly outfl ow (MCM and %) per basin
Basin Wangchhu Bhutan
Jan 82 1,028
Feb 102 1,336
Mar 144 1,512
Apr 265 3,115
38
Basin Wangchhu Bhutan
May 397 4,713
Jun 713 10,002
Jul 1,132 16,382
Aug 965 13,410
Sep 723 10,392
Oct 441 5,769
Nov 143 1,792
Dec 103 1,126
Total MCM 5,209 70,576
Total in % 7.4% 100.0%
Figure 24: Sub-basins (19) delineated in hydrological modelling of Wangchhu basin
Th e average water availability per Gewog was assessed on the basis of hydrological modelling and
the results are shown in Table 16.
39
Table 16: Average water availability per Gewog over the year
Area
(km2) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1 Soe 174.16 2.12 1.79 3.56 10.45 11.49 16.10 27.61 28.18 17.70 12.35 4.20 3.48
2 Tsento 573.13 7.45 7.89 11.65 29.91 34.95 50.67 86.81 87.91 56.95 42.51 14.64 11.30
3 Lamgong 48.99 0.78 1.16 0.99 1.50 2.33 3.81 6.48 6.43 4.59 4.10 1.45 0.91
4 Loong-nyi 75.71 1.45 1.94 2.14 3.21 4.12 6.32 10.85 11.44 8.53 6.35 2.15 1.69
5 Wangchang 20.65 0.37 0.48 0.56 0.86 1.07 1.61 2.79 2.95 2.20 1.61 0.54 0.43
6 Doteng 194.77 2.84 3.07 3.70 5.47 8.30 12.36 21.13 20.52 14.05 13.23 5.42 4.10
7 Dopshar-ri 33.89 0.46 0.51 0.62 0.91 1.37 2.05 3.51 3.40 2.33 2.20 0.88 0.67
8 Hoongrel 10.46 0.21 0.24 0.29 0.44 0.56 0.86 1.45 1.53 1.14 0.86 0.29 0.24
9 Sharpa 80.21 1.55 2.06 2.36 3.53 4.45 6.74 11.57 12.32 9.23 6.70 2.28 1.85
10 Dokar 106.04 2.25 2.88 3.00 4.33 6.00 8.76 15.83 15.80 11.38 8.49 3.86 3.56
11 Lingzhi 49.34 0.75 1.35 2.44 3.29 4.87 8.94 13.42 12.83 9.31 6.32 2.20 1.12
12 Naro 279.46 4.15 6.80 12.32 16.67 24.67 44.06 68.00 65.57 48.76 33.40 12.00 6.21
13 Kawang 297.17 4.63 6.65 8.22 11.66 18.13 30.46 49.34 52.12 37.69 29.27 12.10 6.21
14 Chang 156.38 2.52 3.05 2.89 4.46 6.99 11.69 21.78 23.36 15.06 11.22 4.35 3.32
15 Meedwang 230.09 3.70 4.14 3.99 6.19 9.62 16.07 31.71 33.40 21.12 14.89 5.42 4.90
16 Dakarla 202.56 3.78 4.28 4.82 7.70 12.27 21.46 35.97 32.06 22.89 15.16 7.34 5.60
17 Ge-nyen 60.93 0.96 1.09 1.07 1.63 2.54 4.25 8.38 8.84 5.60 3.94 1.43 1.31
18 Chapchcha 129.18 2.79 3.39 3.80 5.83 9.27 15.24 24.96 20.86 15.50 10.69 6.58 5.46
19 Bij 283.31 5.54 5.30 6.43 9.75 8.54 18.66 34.02 43.10 28.49 23.28 9.98 4.87
20 Kar-tshog 40.65 0.78 0.72 0.88 1.34 1.18 2.59 4.71 5.97 3.96 3.24 1.40 0.70
21 Uesu 66.46 0.86 1.94 2.01 3.29 4.66 7.23 11.49 11.68 8.01 5.79 1.17 0.88
22 Samar 199.74 3.00 5.03 7.69 11.02 13.37 22.42 35.84 37.50 26.67 21.51 6.22 4.04
23 Nagya 136.66 3.40 4.38 4.50 6.48 7.98 11.82 20.46 20.86 15.42 16.63 8.71 5.70
24 Doongna 58.53 1.42 1.84 1.96 2.85 3.43 5.18 8.84 9.16 6.69 7.66 4.17 2.62
25 Meedtabkha 29.98 0.83 1.09 1.50 2.80 4.79 8.86 13.39 10.02 7.98 4.39 1.24 0.96
26 Geling 81.29 1.58 1.98 2.71 4.98 8.57 15.91 23.78 17.46 14.10 7.47 2.64 1.98
27 Bjagchhog 139.56 4.07 5.35 8.04 16.10 29.22 55.60 82.76 58.63 47.67 21.24 3.73 3.54
28 Bongo 398.93 8.57 11.30 21.80 52.00 87.93 174.00 262.83 178.89 150.13 60.96 7.96 7.50
29 Darla 111.42 3.11 4.23 8.01 18.87 32.19 63.84 95.06 65.14 53.84 21.96 2.88 2.79
30 Getana 240.89 5.68 6.22 9.64 17.83 31.79 65.11 97.12 66.93 56.14 23.86 5.42 5.30
31 Dorona 30.63 0.72 0.80 1.23 2.26 4.04 8.27 12.32 8.49 7.13 3.03 0.70 0.67
32 Lhamoi Dzingkha 37.79 0.94 1.16 1.90 3.78 6.78 13.71 19.58 13.74 10.91 4.63 0.88 0.88
Monthly flows (MCM)Geog
As shown in Table 17 and Figure 25, there are 56 glaciers in the northern part of the basin. Due to
global warming, glaciers are decreasing in thickness and area thus contributing to the river fl ow.16
However, glacial retreat due to climate change is likely to threaten the long-term sustainability of
water fl ows.17
Table 17: sGlaciers in Wangchhu basin
Basin Sub-basin Number of Glaciers Glacier Area (km2)Largest
Glacier
CI DC CI DC Total km2
Wangchhu
Th imphuchhu 19 0 5.2+0.1 0.0+0.0 5.2±0.1 1.5
Parochhu 37 2 22.2+0.4 5.4+0.0 27.6±0.5 7.2
Subtotal 56 2 27.4+0.6 5.4+0.0 32.8±0.7 7.2
CI= Clean Ice, DC= Debris Covered
16 NSDIC 2015: www.nsidc.org
17 Bajracharyaet al., 2014. See also the stand-alone supporting document: Hydrological modelling and assessment for Bhutan.
40
Figure 25: River network and glaciers in Wangchhu
basin
Figure 26: Glacial lakes in Wangchhu basin
Th ere are also a few glacial lakes (Figure 26) in the northern part of Wangchhu basin, but none of
them were classifi ed as at risk of outburst.18
Hydrological basin as management unit
Th e Wangchhu drainage basin also serves as the management unit. It is the area of jurisdiction
of the WBC that has a broad mandate to coordinate policies and actions concerning basin
planning and management of water resources, including preparation and periodic updating of
the basin plan. Th e WBC is specifi cally tasked with resolving inter-district issues related to water
management such as upstream-downstream eff ects of interventions related to water abstraction,
effl uent discharge and pollution. Th e WBC also coordinates the water-related planning and
management involving national agencies and the four Dzongkhags within the basin to arrive at a
balanced water resource allocation. 19
18 Mool et al., 2001. See also the stand-alone supporting document: Hydrological modelling and assessment for Bhutan
19 Water security is defi ned as “the capacity of a population to safeguard sustainable access to adequate quantities of acceptable
quality water for sustaining livelihoods, human well-being, and socio-economic development, for ensuring protection against
water-borne pollution and water-related disasters, and for preserving ecosystems in a climate of peace and political stability.” Water
security may be viewed in physical or economic terms. Physical water security is a situation wherein water is abundant enough
to meet all demands, whereas economic water security depends on providing adequate investments in water infrastructure and
services delivery.
41
Monitoring stations
Th e location of river gauging and meteorological stations in Wangchhu basin is given in Figure 27.
Th e historical records from these stations have been used in the basin hydrological assessments.20
Figure 27: Rainfall and discharge monitoring stations in Wangchhu basin
At present, the ambient water quality is being monitored by the Water Quality Monitoring Section
(WQMS) of the Water Resources Coordination Division (WRCD) of NECS. Th e locations of
ambient water quality sites and effl uent sampling points along Th imphuchhu and its tributaries
are shown in Figures 28 and 29. Measurements on other locations in the basin are done ad-hoc.
20 For details see the stand-alone supporting document: Hydrological modelling and assessment for Bhutan
42
Figure 28: Ambient water quality sampling points along Th imphuchhu
Figure 29: Figure 29: Effl uent sampling points along Th imphuchhu
Th e thematic maps for Wangchhu basin are available in the Bhutan Water Security Information
Management System, which is posted in the following website: www.nec.gov.bt.
43
2.3. Basin governance and management structure
Governance mechanisms to promote management and accounting of water resources at the basin
level has been an aspiration of the Royal Government and eff orts are being made to institutionalize
it with the preparation of the NIWRMP and WBMP. Although the need for coordinated and
integrated approach to water resources has been acknowledged since early 2000 and integrated
into policy and legislation, the concept of managing water resources at the level of basin is relatively
new. Th e concept of river basin has been applied more at technical levels in assessing hydrology
and water availability for hydropower development and less by Dzongkhag, Gewog and central
level agencies in planning, implementation and monitoring of water resources. Like in the case
of other development interventions, planning and management of water resources are carried out
from the perspective of Dzongkhags and not the basin as a whole.
Other than planning and execution of large projects such as hydropower projects by Ministry of
Economic Aff airs at the central level, interventions in other areas of water resource management
such as drinking, irrigation, fl ood management and pollution abatement initiatives are carried
out by both the central agencies as well as the Dzongkhag administrations. Th e central agencies
primarily engage in national level policy and planning, engage in execution of large scale projects
and programmes and provide technical backstopping tolocal governments. For example, the
Ministry of Agriculture and Forest is responsible for planning irrigation at the national level as well
as executes large irrigation schemes while also providing technical support to Dzongkhags through
the Research and Development Centres. Dzongkhag and Gewog Administrations implement
repair and maintenance of existing irrigation systems and development of small scale irrigation
systems. Th rough its Department of Forest and Park Services, the Ministry is also mandated
to promote watershed management in the country. Th e Ministry of Health is responsible for
national level policy and planning of rural drinking water and sanitation while also assisting the
local government in implementing the programmes. For urban areas, the Ministry of Works and
Human Settlements is responsible for national level urban development policy and planning. In
relation to water management, the Ministry through its Department of Engineering Services is
responsible for planning urban water supply, sanitation, (sewerage, waste water treatment) and
fl ood management.
While mechanisms exist to plan and implement water programmes and projects at central and
Dzongkhaglevels, eff orts to foster coordinated management of water resources at the basin level
are new. Bhutan's fi rst river basin committee was put in place in April 2016 with the establishment
of the WBC. Th e framework, composition, and terms of reference for the committee provide
the basis for coordination of water resource management in the basin. Considering that the
committee is the fi rst of its kind in the country, it will be necessary to constantly review and orient
the committee based on experiences and lessons learnt to evolve into an eff ective institution (see
governance and implementation arrangements chapter).
44
2.4. Water resource management eff orts in the basin
Th ere have been several independent eff orts to investigate and implement water resource
management programmes in the Wangchhu basin. Some of the prominent ones include:
Water Resources Management Plan 2003:21 Th e study was the fi rst to provide nation-wide
overview of Bhutan’s water resources. Th e study was carried out by Norconsult for the Department
of Energy, Ministry of Trade & Industry and completed in 2003. Focusing on the three main
north-south rivers basins, the study provides a wealth of information water for drinking an
irrigation and hydropower. Aspects of the study that are specifi c to Wangchhu include:
• Base maps in ARC GIS format established in the Land Use Planning Section of the Planning
and Policy Division of the Ministry of Agriculture, Th imphu.
• Possible sources of water pollution from local sanitary effl uents and use of herbicides,
pesticides, fertilisers n the agricultural sector.
• Th ere may be competition between irrigation and hydropower, and some sub-basins could
reach water stress situation in the future.
• Multi-purpose storage schemes are generally not feasible for economic and fl ood control
purposes.
• Need for improved coordination between municipalities and agencies involved in rural water
supply, urban water supply, irrigated agriculture, pollution abatement, and fl ood protection
• Need for improved irrigation effi ciencies (only) in Paro and Th imphu valleys
• Future river basin management must take care not to override Dzongkhag and Gewog level
decision-making frameworks
Wang Watershed Management Project: Th e European Union supported Wang Watershed
Management Project was implemented in the four Dzongkhags of Wangchhu basin from September
2000 to July 2007. Th e purpose of the project was to develop, test and institutionalize practical
watershed, land, and farm management techniques and procedures. Th e project was envisaged
to benefi t 10,000 rural households in the Dzongkhags of Chhukha, Haa, Paro and Th imphu.
Th e project was implemented by Ministry of Agriculture. Th e Royal Society for Protection of
Nature (RSPN) was the implementing partner for the Environmental Education and Advocacy
component of the project. Th e project cost was Euros 9.2 million.
Environmental Impact Assessment for Bunakha Hydropower station:22 Th e report describes
the hydropower project, water and environment, physical environment, bio-diversity, and socio-
economic environment. It gives an identifi cation, prediction and evaluation of impacts of the
project. Th e report has been endorsed by NECS.
Environmental Impact Assessment for Wangchhu Hydropower station:23 Th e report gives 21 Water Resources Management plan, Department of Energy, Ministry of Trade and Industry, 2003.
22 Comprehensive Environmental Impact Assessment for the proposed Bunakha Hydro-Electric Project (180 MW), THDC, India,
2013
23 Comprehensive Environmental Impact Assessment Studies for Wangchhu HEP (570 MW), Bhutan, WAPCOS India, October
45
project details, an environmental baseline status with physic-chemical aspects, ecological aspects,
and socio-economic aspects. It also predicts the impacts of the project on water quality; air, noise
and land environment; ecology; and socio-economic environment. It proposes an environmental
management plan, and a resettlement and rehabilitation, as well as a monitoring plan. It also
contains a disaster management plan and cost estimates. Th e report was endorsed by NECS.
Assessment of vulnerability to climate change:24 Vulnerability to climate change and possible
adaptation options in Bhutan were assessed under the National Adaptation Program of Action
(NAPA), supported by ADB. It did not specifi cally target Wangchhu basin, but Wangchhu was
included in the study. Th e study identifi ed three high risks areas and screened adaptation options
based on set criteria. A Multi-Sectoral Technical Committee on Climate Change was established
as a national technical forum for coordinating all climate change issues in Bhutan. It became the
task force for revising the NAPA documents. Th e Multi-Criteria Analysis (MCA) was used in
the NAPA 2006 document to screen, select and rank the projects. Out of the nine prioritized
adaptation measures, three projects are being implemented with fi nancing from the LDC Fund
and other donors. Th ey are (i) Artifi cial Lowering of Th orthomi lake, implemented by DGM, (ii)
GLOF hazard zoning- Disaster, implemented by Department of Disaster Management, and (iii)
Installation of early warning system for Phochhu, implemented by DHMS. Th e other six projects
that were reviewed and integrated in the NAPA-2 program for implementation include (i) fl ood
and landslides risk reduction in Phuentsholing, (ii) enhancing community resilience to climate
risks through building or rehabilitating water harvesting structures, water storage and distribution
facilities in water-scarce villages, and improving the information base for water management,
and (iii) Improving the quality, analysis and dissemination of climate information. A project
on gathering detailed information for local water management is being piloted in the districts
of Mongar, Pemagatshel, Samtse and Tsirang. Th ough these projects are not specifi cally located
in Wangchhu basin, the experiences and outcomes are relevant for local water management in
Wangchhu basin too.
Wang Integrated River Basin Management Plan:25 Th e Social Forestry Division of the
Department of Forest in the Ministry of Agriculture and Forest prepared the Wang Integrated
River Basin Management Master Plan in 2008, with the stated objective to give strategic guidance
to policies, decision-making and lobbying. It identifi ed all stakeholder agencies and provided
directions on the role of each agency, as well as coordination arrangements needed for successful
achievement of objectives. Th e Plan provided broad strategic actions, whereas the individual
agencies were expected to identify suitable implementation activities.
However, the Master Plan was not implemented and has in fact been superseded by a system
of rapid watershed classifi cation done for Wangchhu in 2011 by the Watershed Management
Division under the Department of Forests and Park Services of the Ministry of Agriculture and
Forests (see Chapter 3.1.4.).
2014
24 National Adaptation Program of Action (NAPA), http://www.adaptation-undp.org/search/node/bhutan
25 Wang Integrated River Basin Management Plan, Social Forestry Division, Department of Forest, MOA, 2008
46
Sensitization workshops:26 A great number of sensitization workshops were held for local leaders
throughout the country including Wangchhu basin in the period 2013-2015, and an inventory
was prepared of water-related issues. Th e fi ndings for Wangchhu basin showed that nearly all
Gewogs in the basin do experience one or another issue related to water, mostly related to lack of
water (access). Th e causes and extent of the problems have not been stated.
Paro Valley Geo-technical Investigation:27 A geo-technical investigation was completed in 2015.
It studied the nature of slopes, the types of exposed rocks, ground conditions such as presence of
sinking and marshy areas, and risks that the site is exposed to due to fl ooding and landslides. It
concluded that Paro valley is topographically stable and is not likely to experience landslides in the
near future with possible exception at the periphery near Satsam and Chorten. No groundwater
was encountered in the soil pits, but there was no indication of their depth. It was mentioned
however that in the lower parts of Paro valley water seeped into construction pits at a depth of 4
meter with coarse-grained (not clayey soils).
It was concluded that the soils are suitable for development activities, and no major settlement
problems are expected in Paro valley. Th e main risks identifi ed to development related to inundation
from the river and earthquakes. Th e criteria recommended for hazard mapping were fl ood map,
geological map, river buff er and slope variables.
Th e study established a need to complement the existing river training works such as repair of the
Reno mattress gabion along high impact zones along Pachhu and Dochhu. Th e cost was estimated
at Nu. 133.6 million.
2.5. Basin Management Scheme
Coordination through the Water Security Index
Th e coordination framework is provided by the Bhutan Water Security Index (BWSI) system. It
measures on a scale of 1 (poor) to 5 (very good) the degree to which water resources and related
services are developed, as measured across fi ve key dimensions:28
1. Rural drinking water supply, sanitation and hygiene
2. Economic water utilization for agriculture, industries and hydropower
3. Urban water supply, sanitation and drainage
4. Environmental water security
5. Disaster preparedness and climate change resilience
26 RSPN, 2015
27 Paro Valley geotechnical investigation, Budes, MOWHS, 2015
28 See the National IWRM Plan, and the stand-alone supporting documents titled: Bhutan Water Security Index, and Bhutan Water
Security Index System: User’s Manual.
47
Th e present score of the Bhutan Water Security Index under the fi ve key dimensions is given
for Wangchhu basin and at national level in Table 18 and Figure 30. As can be seen, the average
score for Bhutan across the fi ve water security dimensions is 3.08, and for Wangchhu basin the
average score is 3.34.
Table 18: Score of the Water Security Index 2016
Key Dimension Wangchhu basin National level
1. Rural household water supply, sanitation and hygiene 4.5 3.5
2. Economic water security 2.1 2.0
3. Urban water supply and drainage 2.8 2.8
4. Environmental water security 3.4 4.0
5. Resilience to climate change and water-related disasters 3.9 3.1
Average Score 3.34 3.08
Figure 30: Water Security Index 2016
48
49
3. SIT UAT ION ANALYSIS
Th is chapter fi rst analyses a number of stress factors related to water management in Wangchhu
basin, ranging from basin-specifi c impact of climate change, water scarcity at Gewog level, fl ood-
prone areas, critical watersheds, limitations and impacts of hydropower development, to water
governance issues. Th e chapter also presents a problem analysis and strategy development based
on a participatory logical framework analysis with the incumbent WBC members and other
stakeholders.
3.1. Stress factors in water management
3.1.1. Climate cxhange and its impacts on hydrology
Climate change
Th e longer-term climate change projections derived from climate modelling, show an increasing
trend in annual rainfall toward the 2060s, especially in the south as shown in Figure 31.29
Figure 31: Projected long-term change in precipitation for RCP 4.5
According to the climate change projections, the average temperature is also expected to rise, as
shown in Figure 32.
29 RCP4.5 stands for a climate scenario with curbed greenhouse gas emissions
50
Figure 32: Projected rise in average temperature for RCP 4.5
Th e number of consecutive dry days (precipitation less than 1 mm/ day) is expected to increase
very little until 2040 with values around 35 days for the southern foothills, 40 days for the inner
Himalayas and 60 days for the higher Himalayas.
Th ere was no clear trend found in future evapotranspiration.
Impacts on hydrology
Th e average monthly and maximum outfl ows of the Wangchhu basin are expected to increase
(Figure 33 and 34), based on hydrological assessments with increased rainfall and temperature
following from climate change projections. Th e fi gures represent two climate change scenarios,
RCP 4.5 and RCP 8.5.30, 31
(a) RCP 4.5 (b) RCP 8.5
Figure 33: Average monthly outfl ows of Wangchhu basin over time
30 RCP stands for Representative Concentration Pathway, a climate change scenario which depends on the quantity of greenhouse
gases emitted into the atmosphere. RCP 4.5, one of the scenarios, represents stabilization of greenhouse gas emissions, whereas
RCP8.5 stands for a signifi cantly larger increase in such emissions.
31 For details, see stand-alone supporting document: Hydrological modelling and assessments for Bhutan.
51
(a) RCP 4.5 (b) RCP 8.5
Figure 34: Monthly maximum outfl ows of Wangchhu basin over time
Th e impact of climate change on high fl ows can also be expressed in terms of frequency of
occurrence, as shown in Table 19 and Figure 35. For example: the 100-year return-period fl ood
event for the period 1976-2005 is projected to occur once every fi ve years on average by the 2060s
because of climate change. An alternative perspective is that historically there was a 1% chance on
average that a peak fl ow of 1,275 m3/s would be experienced annually however in the future, with
the impacts of climate change, there will be a 20% chance the same peak fl ow will be experienced
annually. Similarly, a once-in-fi fty-year fl ood (2% chance) is projected to increase from 1,189 m3/s
at present to a projected 1,498 m3/s in 2030s and further to 1,818 m3/s by 2060s.
Th e implication is that fl ood zonation and fl ood protection measures that are traditionally designed
as per present return periods would under-estimate future fl ows by about 50% during the 2060s!
Table 19: Outfl ows of Wangchhu and
corresponding return periods
Return Period
(yr)
Flow in m3/s
1976-
2005
2016-
2045
2046-
2075
5 895 1,112 1,280
10 987 1,233 1,448
25 1,103 1,385 1,661
50 1,189 1,498 1,818
100 1,275 1,611 1,975
Figure 35: Present and projected monsoon outfl ows of
Wangchhu for various return periods
Conversely, for the lean season there is no clear change in monthly minimum outfl ow (Figure
36). But Figure 37 shows that smaller fl ows will occur more frequently in future, although the
minimum fl ow itself (32 m3/s) would not decrease.
52
(a) RCP 4.5 (b) RCP 8.5
Figure 36: Monthly minimum outfl ows of Wangchhu basin over time
(a) RCP 4.5 (b) RCP 8.5
Figure 37: Frequencies of minimum outfl ows of the Wangchhu basin during the lean season
Figure 37 shows for example for the worse-case scenario (RCP 8.5) the minimum fl ow will remain
at 32 m3/s, but its frequency of occurring increases from 4 to 9, whereas the frequency of fl ows of
35m3/s would decrease from 3 to 1. However, this shift towards lesser fl ows is accompanied by a
low frequency of high outfl ow (39 m3/s) that so far did not occur.
Given the limited number of climatic stations, the impact of climate change on hydrology could
realistically only be assessed at basin level, and not at sub-basin level.32
3.1.2. Anecdotal Water-scarcity
Water scarcity in the basin has been widely reported in the media. Th is issue has been investigated
in four ways:
2. A questionnaire survey in all Gewogs in Wangchhu.
3. Calculation of the total amount of water available per person per year (Falkenmark Index).
4. Calculation of the total volume of water available per Gewog.
5. Calculation of the fraction of water consumed in future as compared with water available per Gewog.
32 Bhutan is represented by only 21 Aphrodite stations.
53
Th is issue is elaborated in the following paragraphs.33
Gewog questionnaire
An IWRM questionnaire was completed by all Gewogs in Wangchhu basin in 2015. Th e Gewogs
reported that 65 villages in the basin were experiencing seasonal water shortage. Paro district
suff ers most with 40 villages reporting seasonal water scarcity (see Figure 38). In particular, the
Gewogs of Wangchang, Dogar, and Shaba in Paro stand-out as the most water scarce, followed by
Mewang Gewog in Th imphu.
It should be noted that this is only a qualitative inventory; it does not assess the magnitude or
frequency of the scarcity.
Figure 38: Number of villages having seasonal water shortage per Gewog
Information about groundwater is sparse and inconclusive not just for Wangchhu but also at
the national level. Consequently, the government does not encourage groundwater exploitation34.
Nevertheless, there are various reports of groundwater potential, concentrated in Paro district in
the Gewogs of Shari (5), Lango (4), Shaba (3), Wangchang (1 in Bondey town). In Th imphu
district the use of groundwater has been reported in Mewang Gewog (1 for a school), see Figure
39. It appears that groundwater is being tapped in areas that have been assessed in this report as
potentially water-scarce.
33 Th e details of calculations are given in the stand-alone supporting document: Hydrological modelling and assessments for Bhutan.
34 Geo-electrical survey in Paro area, Bhutan, CEGR-Kathmandu, 2015?
54
Figure 39: Th e number of villages per Gewog reportedly exploiting groundwater
UN-Falkenmark index
Th e United Nations (UN) has adopted the Falkenmark (1989) criterion which assumes that a
region is experiencing overall water abundance when the average amount of water per capita per
year is over 1,700 m3. Th ere is stress when annual water supplies drop below 1,700 m3 per person.
When annual water supplies drop below 1,000 m3 per person, the population faces water scarcity,
and below 500 m3 per year there is “absolute scarcity”.35 Th is is given in Table 20, along with the
litre/capita/day equivalent values.
Table 20: UN-Falkenmark criteria for water availability
Classifi cationWater available
(m3/capita/year)
Water available
(litre/capita/day)
Abundance > 1,700 > 4,657
Stressed < 1,700 < 4,657
Scarcity < 1,000 < 2,740
Absolute scarcity < 500 < 1,370
Th is index is typically used in assessments on a regional scale where the data is readily available
and provides results that are easy to understand.36 However, the use of regional averages tends to
obscure important scarcity information at smaller time intervals and local spatial variations.37
Hence in deviation of the standard practice, the index was applied under the following conditions:
• Th e driest month of the year (January) instead of the whole year.
• At Gewog level instead of at national level.
35 http://www.un.org/waterforlifedecade/scarcity.shtml
36 Amber Brown and Marty D. Matlock. A Review of Water Scarcity Indices and Methodologies, University of Arkansas, Th e
Sustainability Consortium, White Paper #106, April 2011.
37 Rijsberman, 2006
55
• For the 80%-dependable water availability (minimum fl ow expected to occur on average
four out of fi ve years) instead of the average water availability (occurring on average once
every two years).
• Th e index was calculated for the year 2015 and 2030, taking into account the growth of
population as indicated in Section 2, and rate of economic development.
• Th e water availability at Gewog level in 2030 was assumed to be the same as in 2015,
because future hydrological assessments proved inaccurate at smaller scale than basin level.
Given the expected impact of climate change on hydrology this assumption was considered
to be sound.
• Infl ow from upstream of the areas was not considered.
Th e results of the dependable water availability per Gewog in the basin per capita per day during
the driest month (January) for 2015 and projected for 2030 are given in Table 21.
Table 21: Falkenmark index for 80%-dependable water availability per capita during the lean month of January
in 2015 and 2030
UN-Falkenmark index for internal dependable runoff water
2015 2030 Legend
CHUKA CHUKHA stre ss < 1,700 m3/ c/ yr or < 4657 l/c/d
scarce < 1,000 m3/ c/ yr or < 2740 l/c/d
ab solute scarce < 500 m3/ c/ yr or < 1400 l/c/d
Haa Haa NB Inflow from upstream is not cons idered
Katsho
Paro Paro
Hungrel Hungrel
Lango Lango
Shari Shari
Wangchang Wangchang
THIMPHU THIMPU
Chang Chang
Kawang Kawang
Basin Basin
Table 21 allows for the following observations:
• Th ere would be absolute scarcity in Wangchang in 2015 and 2030.
• Chang would have scarcity in 2015 that worsens to absolute scarcity in 2030.
• Kawang has scarcity in 2015 and 2030.
56
• Hungrel, Lango and Shari have stress in 2015 and 2030.
• Katsho would have water stress in 2030.
However, all Gewogs have ample water supply if infl ow from upstream is also considered. But
accessibility may be a problem.
Net water balance by 2030
Th e 2030 net water balance simply deducts the additional future water demand from the
80%-dependable available water.38 Th e bigger the balance amount expressed in million m3
(MCM), the larger volume of water is left un-used. Since there is no objective norm for the
net water balance it has been assumed generously that 1 MCM per month is the threshold for
potential water stress.39 Only the months of January, May and June were considered; January
because it is the driest month of the year, May and June because high irrigation water demand for
transplanting paddy may exceed the natural increase of water availability.
Th e fi gures have been plotted for the months of January, May and June in Figures 40 to 42.
Th e Gewogs
of Bongo
and Getena
appear to have
ample water,
but Metakha,
Dungna and
Geling are low
on water.
Th e Gewogs
of Bjee and
perhaps Samar
have ample
water, but
Katsho and
Eusu have little
water.
38 For details see supporting document: Hydrological modelling and assessment for Bhutan.
39 One MCM is enough water to supply 740,000 people with drinking water for the period of one month at the present rural norm
@ 45 litres per capita per day.
57
Only Tsento
Gewog appears
to have ample
water. Hungrel,
Wangchang,
and Shari are
low on water.
Th e balance is
most favorable
in Naro
Gewog.
Lingzhi and
Geney have
little water.
Figure 40: Water balance per Gewog in January (critical for drinking water supply).
Th e Gewogs
of Bongo,
Dala and
Getena have
some surplus,
whereas
Dungna and
Metakha have
less.
Katsho Gewog
seems stressed,
but Samar has
surplus.
58
Only Tsento
Gewog has
ample water in
May.
Hungrel,
Lango,
Shari and
Wangchang
have less water.
Geney, Chang
and Lingzhi
are tight. Only
Naro has some
surplus.
Figure 41: Water balance per Gewog for May (critical for irrigation)
Th e balance
in Dungna
and Metakha
Gewog is
very low,
whereas
Bongo has
surplus.
Th e water
is tight in
Katsho
Gewog
59
Only Tsento
Gewog has
surplus,
whereas
Hungrel,
Wangchang,
Shari are low.
Naro Gewog
is best off ,
Geney worst.
Figure 42: Water balance per Gewog for June (critical for irrigation)
Figures 40 to 42 serve to locate areas suff ering from water shortages and where opportunities
may exist for water development for drinking supply or irrigation, subject to further detailed
hydrological and engineering investigations.
Percentage of dependable water used for consumption by 2030
Th is approach assesses water scarcity by expressing the additional demand for water by 2030 as
a percentage of the 80% dependable net water presently available (water generated within each
Gewog per month minus present demand). Delivery effi ciency has been assumed for irrigation
water (40%) as well as domestic water (40%). In the absence of a generally accepted norm it has
been assumed that 10% is the threshold value for potential water stress. Th e results are given
for January (critical month for drinking water supply) and May and June (critical months for
irrigation) in Table 22.
60
Table 22: Percentage of 80%-dependable water used for consumption by 2030
Area JAN MAY JUN
Chhukha 3.7 1.0 0.5
peak Gewog demand 5.2 Dala 1.9 Dungna 1.4 Dungna
Haa 0.4 0.3 0.15
peak Gewog demand 6.2 Samar 6.1 Katsho 3.3 Katsho
Paro 3.4 5.5 5.4
peak Gewog demand 30.2 Wangchang 16.6 Wangchang 15.7 Wangchang
with infl ow 0.7 Wangchang 0.4 Wangchang 0.8 Wangchang
Th imphu 4.6 3.0 2.6
peak Gewog demand 19.6 Chang 11.6 Chang 10.8 Chang
with infl ow 4.4 Chang 1.5 Chang 1.1 Chang
Basin 3.4 2.2 1.6
Th e table shows that:
• At basin-level the additional water consumption by 2030 would take only a few percent of
the dependable water.
• At district-level the additional consumption by 2030 would be about 5.5% of the dependable
water in Paro during the months of May and June.
• At Gewog-level the additional consumption would consume up to 30% of runoff in
Wangchang and 20% in Chang in January.
• None of the Gewogs has any water stress if infl ow from upstream areas into the Gewog is
also considered and can be accessed.
Interpretation of results
Th e diff erent approaches yield the ranked (potential) water-scarce areas as given in Tables 23 and
24. As can be seen, Wangchang, Chang, Hungrel and Shari rank high in potential water scarcity,
but other Gewogs like Kawang and Katsho should not be discarded. Th e ranking should not be
over-rated because diff erent assumptions (most notably regarding irrigated areas) can signifi cantly
change the ranking.
61
Table 23: Ranked potentially water-stressed Gewogs identifi ed under diff erent methodologies
RankingScarcity
survey
Groundwater
survey
Water
disputes
survey
Falkenmark
Index
Demand
ratio >10%
Water
balance
< 1 MCM
1 Wangchang Shari Shari Wangchang Wangchang Hungrel
2 Dogar Lango Lango Chang Chang Wangchang
3 Mewang Shaba Wangchang Kawang Shari
4 Shaba Wagchang Mewang Lango Lango
5 Shari Mewang Hungrel Metakha
6 Lango Katsho Lingzhi
7 Shari Katsho
8 Eusu
9 Geney
Table 24: Gewogs in Wangchhu basin with the highest potential for water stress
Rank
Method1 2 3 4
Questionnaires Wangchang Dogar Mewang Shaba
Falkenmark Wangchang Chang Kawang Shari
Hungrel
Demand ratio Wangchang Chang Shari Kawang
Water balance Hungrel Wangchang Shari Katsho
Overall Wangchang Chang Hungrel Shari
Th e Gewogs with highest potential for water stress are given in Table 24, and depicted in Figure
43.
62
Figure 43: Gewogs with potential for water stress
Th e results shown in Table 23 and Table 24 show that water scarcity is not obvious when looking
at larger areas, notably basins and districts. Overall there may be suffi cient water at the basin and
district scale, however it may not be accessible at all locations within the district, as shown in the
large diff erences in available water at Gewog level (Table 16). Th e fact that water stress within a
Gewog can easily be compensated by infl ow from upstream areas proves that this water is only
available in the main streambed of the river – which may be tens of kilometres away and/ or
hundreds of meters below the hill sites where people need it. Th is shows the diff erence between
physical and economic water scarcity. Possible mitigating measures: (i) pump water over the
required distance/ elevation; (ii) store water at upstream locations for local use by means of small
dams or ponds; (iii) tap groundwater if the geology and terrain permit; (iv) improve the effi ciency
of water use in order to reduce the demand; and (v) reduce the demand itself.
Potential sites for check-dams
Th e Water Resources Management Plan of 2003 stated that multi-purpose reservoirs are generally
not feasible.40 Th is also seems to be the conclusion that will be drawn by the Water Risk Assessment
40 Water Resources Management Plan and Update of the Power System Master Plan of Bhutan, Department of Energy, Ministry of
63
study recently being undertaken under the ‘Living Himalayas Initiative’ sponsored by the World
Wildlife Foundation (document not yet published at this point).
On the other hand, the Environmental Impact Assessment study for the proposed Wangchhu
hydropower plant has suggested a considerable number of potential sites for small dams throughout
the basin as part of the catchment treatment measures, see Figure 44.41
Source: Comprehensive Environmental Impact Assessment Studies for Wangchhu HEP (570 MW) Bhutan, Wapcos, 2014, Volume 2 – Final EMP
Figure 44: Proposed catchment area treatment measures, including check-dams.
3.1.3. Flood-prone areas
Areas that are prone to monsoon fl ooding have been determined in three ways:
i. by Gewog questionnaire
Trade and Industries, RGOB, 2003.
41 Comprehensive Environmental Impact Assessment Studies for Wangchhu HEP (570 MW) Bhutan, Wapcos, 2014, Volume 2 –
Final EMP.
64
ii. by hydrological modelling in HEC-RAS
iii. by using Geographical Information System (GIS)
Th e fi ndings are presented in the following paragraphs.
Gewog questionnaire
Th e Gewogs in Wangchhu basin reported in an IWRM questionnaire in 2015 that, in total,
45 locations in Wangchhu basin are susceptible to fl ooding. Th e number of villages aff ected by
fl ooding is shown in Figure 45.
Figure 45: Diagram showing number of fl ood-prone areas reported per Gewog.
As can be seen, the Gewogs of Doteng, Lango, Shaba and Tsento in Paro district; and Gewog
Bjee in Haa district reported the highest number of fl ood incidences. Th is, however, provides no
information on the extent or severity of fl ooding (depth and duration).
Flood modelling
Hydrological models such as HEC-HMS (for stream fl ow analysis) and HEC-RAS (for water
levels) were used in the study to assess fl ood prone areas.42 Th e simulated fl ood fl ows corresponding
to return periods of 25, 50 and 100 years for Haachhu at Haa, Parochhu at Nyemezampa, and
Th imphuchhu at Lungtenphug were used to estimate water levels. Th e vicinity of the towns of Haa,
Paro and Th imphu were chosen to assess fl ood hazard, given their proximity to rivers. Chhukha
was ignored as it does not have any fl ood risk from the main river. Details of each of these locations
and the results are discussed below. A summary of fl ood-prone areas per district is given in Table
25. Th e 100 year return period was taken as the worst case scenario, based on historic fl ow records.
42 Refer to standalone supporting document titled: Hydrological Modelling and water resource assessment in Bhutan
65
It does not account for the impacts of projected climate change which require further analysis.43
Table 25: Summary of fl ood-prone areas in Wangchhu
DistrictGewog Flood-prone area
Haa Uesu• Some schools, residential homes, agricultural fi elds
• Haa proper town is also shown to have some risk
Paro
Tsento • Th e villages behind Drukgyel Dzong
Hungrel• Downstream the confl uence towards the base of the Rimpung
Dzong
Shaba • Near the riverside
Th imphuChang/
Kawang
• Lower parts of Pamtsho by the river
• Hejo near the Crematorium
• Langjophakha near Ludrong Garden opposite to the Dzong
• part of the urban road after the Lingkarna bridge/ royal garage
• Part of Centenary Farmers’ Market and Changlimithang
Stadium
• Coronation Park
• Chanjiji Football stadium
• Pelkhil School ground
• lower part of Olakha workshop complex
• Hotel Terma Linca
• Lower parts of Ramtokto and
• Lower agricultural land in Kharsadrapchu area.
Flood Hazard of Haa district
For Haa, the stretch of river starting from Damthang to the end of Haa valley at Tshaphel village
of Uesu Gewog was modelled in HEC RAS with a river length of about 20 km. Th e image for
Haa was from Google Earth as no other satellite image was available. Th e Digital Elevation Model
(DEM) used was based on the 90m resolution Shuttle Radar Topography Mission satellite imagery.
Based on the projected 100 year fl ood of 62.5 m3/s, the HEC RAS model was set up and the
fl ooding hazard was assessed. According to the observations in Figure 46, some schools, residential
homes, agricultural fi elds fall under the yellow zone with fl ood depths of up to 2 meters. Haa
town is also shown to have some risk. It should be noted that most parts of the town now have a
river embankment, which was not there when the digital elevation map was produced. In any case
43 Th e impact of climate change cannot be reliably assessed at scale smaller than the basin with the data presently available. Th at is
why local fl ood hazards caused by climate change were not assessed in the context of the WBMP.
66
the hazard map does give an indication that there are a number of potentially dangerous places
along the Haa River that require protection. It is recommended that a more in-depth hazard
assessment be carried out as part of the basin plan implementation, with fi eld measurements of
river banks, courses and confi rmation of the digital terrain. Th e fi ndings presented here were based
on desk study and they need fi eld confi rmation before fl ood protection works are considered to be
implemented. Indeed, the Department of Engineering Services under the Ministry of Works and
Human Settlement has recently started working on some fi eld measurements and in-depth fl ood
modelling in the area.44
Figure 46: Map of fl ood-prone areas in Haa district
Flood Hazard in Paro district
Th e peak fl ows at Nyemezampa in Paro, which is on the main river, after the confl uence of
Dotengchhu and main Parochhu, was analyzed. Th e 100 year fl ood of magnitude 378 m3/s was
used to determine the extent of fl ooding. Th e stretch of Parochhu from Gunitsawa to Tshongdue,
44 Personal Communication with Ms. Kunzang Choden, TAC Member, Flood Engineering and Management Division, DES,
FEMD, June 2015.
67
Dotey (near Kuenga HSS) to Tshongdue and Tshongdue to Isuna with a total length of about
45 km was analyzed. Based on the analysis it is found that a lot of the Paro valley is under fl ood
threat, although parts of the river banks are fairly well protected. However, there are defi nitely
parts of the valley that need more attention and study, such as the villages in Tsento Gewog behind
Drukgyel Dzong, Parts of Hungrel Gewog after the confl uence towards the base of the Rimpung
Dzong, parts of Woochu, and Shaba near the riverside. A fl ood hazard assessment of the valley
has been done by Department of Human Settlement. It showed almost the same areas at risk. Th e
fl ood hazard map for Paro is shown in Figures 47 and 48.
Figure 47: Map of fl ood-prone areas in Paro district
68
Figure 48: Flood-prone areas in Paro district
Flood Hazards in Th imphu district
Th e projected 100-year fl ood of magnitude 512 m3/s at Lungtenphug was used to determine the
fl ood extent and depth in Th imphu valley. A DEM of 5m resolution with ortho-corrected satellite
image for Th imphu was used for working on the stretch of Th imphuchhu from Dechencholing to
Kharsadrapchu.45 46 Th e stretch Olarungchhu from Semtokha to Olakha was also analysed which
makes the total length of the river analysed to about 26 km.
45 Courtesy Th imphu Th romde, GIS Section.
46 Courtesy Department of Human Settlement, MOWHS, Th imphu.
69
According to the fl ood extent mapping it is clear that quite a few places in Th imphu are prone
to a 100 year fl ood (a fl ood with return period of 100-year has 1% chance of occurrence in any
given year). Some of the notable places include parts of Pamtsho by the river, Hejo near the
Crematorium, Langjophakha near Ludrong Garden opposite to the Dzong, part of the urban road
after the Lingkarna bridge/ royal garage, Part of Centenary Farmers’ Market and Changlimithang
Stadium along with Coronation Park, Chanjiji Football stadium, Pelkhil School ground, lower part
of Olakha workshop complex, Hotel Terma Linca and parts of Ramtokto and some agricultural
land in Kharsadrapchu area. Th e fl ood hazard map for Th imphu is shown in Figures 49 to 52.
Th e analysis above was based on historical records. Th e impact of climate change will worsen
the fl ood risks as explained in section 3.1.1 and should be taken into account when mitigating
measures are considered.
Figure 49: Map of fl ood-prone areas in Th imphu town
70
Figure 50: Field view of fl ood-prone area near Jang-Ji sports ground in Th imphu
Figure 51: Existing River bank protection near Coronation Park, Th imphu
Coronation Park/ Changlimithang National Stadium’s river protection by Thimphu chhu
71
Figure 52: Flood-prone areas in Th imphu district
72
GIS-based method
Th e fl ood modelling methodology described above was supplemented by simpler analysis using
GIS in order to cover a larger study area.47 Th e GIS results appear to match well with the fi ndings
of hydrological fl ood modelling. Th e results of the GIS-based method for identifying fl ood-prone
areas are given in Figure 53.
Figure 53: Map showing fl ood-prone areas in Wangchhu basin, based on GIS method
47 For details see supporting document: Hydrological modelling and assessment for Bhutan.
73
3.1.4. Critical watersheds
As replacement for the Watershed Master Plan mentioned in Chapter 2, the Watershed
Management Division under the Department of Forests and Park Services of the Ministry of
Agriculture and Forests prepared a system of rapid watershed classifi cation for Wangchhu in 2011.
Th e main objectives were:
• to identify critical watersheds within the Wangchhu basin,
• to set up a baseline for water discharge from various streams, and
• to prepare a Critical Watershed Management Plan for each of the critical watersheds identifi ed.
Th e report states that most of the watersheds in Bhutan are in pristine condition, hence there is no
need to develop a master plan for each basin. A more cost-eff ective strategy would be to focus on
‘critical’ watersheds where attention is most needed, and to periodically monitor the watersheds
that are still in “normal” condition. Together, the watersheds management plan for the critical
watersheds would constitute a master plan. Th e report concludes the following for Wangchhu
basin:48
• Th e upstream watershed conditions (Haa, Paro, Th imphu) are much better than the
downstream (Chhukha).
• Th e sub-watersheds under Haa Dzongkhag are mostly in pristine conditions and only need
a precautionary approach.
• Th e sub-watersheds under Paro Dzongkhag need periodical monitoring as they are mostly
in the “normal” class.
• Th e sub-watersheds under Th imphu Dzongkhag need strong periodical monitoring; a
precautionary management approach is recommended, including need to develop critical
watershed management plan.
• Th e sub-watersheds under Chhukha Dzongkhag need more attention especially watershed
number 158 which requires critical watershed management plan to be prepared.
• Only two watersheds are classifi ed as critical: number 158 and 67.
Th e watersheds in Wangchhu basin identifi ed by WMD are shown in Figure 54.49
48 Rapid classifi cation of watersheds in Wangchhu basin, Watershed Management Division, Department of Forests and Parks
Services, MOAF, 2011
49 Th e watersheds identifi ed by WMD correspond reasonably well with the sub-catchment areas delineated for hydrological
assessments mentioned in chapter 2.
74
Figure 54: Watersheds in Wangchhu basin as delineated by WMD
Watershed 158
Th is watershed covers most of downstream of Wangchhu. It has an area of 712 km2 (71,196
ha). It covers the township of Tshimasham, Chhukha Hydropower Project, Gedu town, Tala
Hydropower Project, and Bhutan Board Products in Darla in addition to numerous communities.
It covers 8 Gewogs of Bongo, Bjachho, Darla, Geling, Chapcha, and portions of Metap, Getana
and Dungna under Chhukha Dzongkhag.
Watershed 67
Th is watershed is classifi ed as “critical by function”, because it is used as a drinking water source
for Th imphu; it is not critical by conditions of the watershed. It falls under Th imphu Dzongkhag
and has an area of 225 km2 (22,487 ha). It covers the capital city of Th imphu and its surrounding
areas. Th e two Gewogs that are located in the watershed are Kawang (18,480 ha) and Chang
(3952 ha); parts of Mewang, Kabjisa and Toepisa are also located in this watershed.
3.1.5. Limitations and impacts of hydropower development
Th ere are two large existing run-off -the river power plants in the Wangchhu basin at Tala (1,020
MW) and Chhukha (336 MW). Th e hydrographs on those locations have been plotted in Figure
55, along with the fl ow requirements of the respective turbines.
75
Figure 55: Th e hydrographs at Tala and Chhukha (Chimakoti) power stations compared with the requirements
of their generators
Figure 55 shows that the stream fl ow varies strongly over the year. During the wet season there is
enough fl ow to drive all six generators from June up to October. From November to April not all
generators can be operated and around February there may not be enough fl ow to drive even one
generator. Th is shows that the large seasonal variation of stream fl ow limits the effi ciency of power
generation. Th is could be improved by building large water storage dams, but these would have
negative side eff ects on the natural environment, such as inundation of land with decomposition
of vegetation, interrupting the movement of migratory fi sh, changing the temperature and silt
content of the water. Large dams could also pose a risk of failure considering that Bhutan is prone
to earthquakes.
For the hydropower station under construction at Bongo, 439 ha will be acquired of which 388 ha
is forest land and 50 ha is private. Th irty four hectares of agricultural land will be lost, including
0.8 ha of irrigated area.50
For the proposed hydropower station at Bhunakha, 820 ha of land would have to be acquired, of
which 796 ha is forest area, 2 ha is government land and 23 ha is agricultural land.
3.1.6. Water quality
Water quality is generally good, but is deteriorating within and downstream of the Th imphu and
Paro urban centres. Th e causes of water pollution are car workshops spilling oil and waste water,
insuffi cient sewage water treatment, and solid waste disposal.
50 Comprehensive Environmental Impact Assessment Studies For Wangchu HEP (570 MW), WAPCOS, India, 2014
76
At present there is no regular and systematic monitoring of ambient water quality in Bhutan. Th e
WQMS of WRCD, NECs is a two-person section that started basic operations in 2011-2012.
Th e section has a water quality laboratory capable of doing all necessary basic water quality tests.
It does conduct random and isolated water quality measurements around the country, and more
regular and focused in Th imphu but this is not adequate. Sites for water quality sampling are given
in Figure 28 and 29 for respectively ambient and effl uent water. Th ere is also lack of manpower,
equipment and systems in place to meet the requirements. Th erefore, it is proposed that NECS
work with competent authorities in order to establish a network of water quality monitoring
stations across the country and collect water quality data on a regular basis.51
3.1.7. Governance
While the concept of water resource management at the basin level has been there for a while,
the eff orts to institutionalize planning and implementation at the basin level is new. Until now,
no governance and institutional mechanisms exist to assess, plan and sustainably manage water at
the basin level. Planning and implementation of water use and management are sector based and
driven at the level of central agencies and district administrations. Th e practice of assessing water
resources for the basin as a whole and prioritizing allocations and interventions on the basis of water
balance is yet to be institutionalized. Focus of interventions in the water sector is primarily issue
based. Issues identifi ed at the local village levels are apprised through the Gewog Administration,
deliberated and prioritized at the district level for integration in the plans. However, long term
plans and large scale project interventions that require huge budget and skilled human resources
are handled by Ministries and agencies at the central level. Smaller projects dealing primarily with
construction of small water infrastructures, repair and maintenance of existing drinking water and
irrigation facilities are implemented by Dzongkhag and Gewog administrations. Th ese include
initiatives to address drinking water, sanitation and irrigation for rural villages and implemented
on cost sharing basis where local people provide manual labour while raw materials are procured
under the government's budgetary support.
Villages generally have traditional mechanisms of organizing into groups for addressing common
needs. In recent times, eff orts were made by the government to formalize such groups into Water
User Associations. However, not much progress has been achieved in sustaining such groups.
In urban areas, water supply and sanitation services are planned and provided by municipalities
under cost recovery mechanism through water pricing and service fees.
Budget for project interventions by central agencies and Dzongkhag administrations are based
on priorities outlined in the Five Year Plans. Annual budgets are prepared by respective agencies
and Dzongkhag and gewog administrations based on agreed Key Result Areas (KRAs) and Key
Performance Indicators). Funds are channelled to central agencies and to the Dzongkhag and
Gewog Administrations based on annual budgets passed by the National Assembly.
With recent initiatives of the government to foster IWRM as per the Water Act and regulations,
the river basin has become the most logical unit for coordinated management of water resources
51 Refer to the stand-alone supporting document: Hydrological modelling and assessments in Bhutan.
77
(e.g., for proper water resources accounting and allocation). As such, a basin organization is the
most appropriate institutional mechanism for ensuring such coordination at the basin level. Th e
aim of coordination is to ensure that policies and programs in the basin—involving multiple
actors and stakeholders--are characterized by minimal redundancy, incoherence, confl ict and gaps.
Given that basin level planning, implementation and management of water resources are just
being initiated, institutional and governance mechanisms in the Wangchhu basin are constrained
by:
• Lack of coordination between agencies involved in, or aff ecting water management.
• Lack of capacity of agencies involved in water management.
• Lack of capacity in local government to deal with their work load.
• Subordinate role of Water Users Associations.
• Lack of data/ information and exchange.
Wangchhu is the fi rst basin where a RBC has been formed for improved planning, coordination
and management related to water resources. Strengthening the position of the RBC is of utmost
importance for the success of IWRM.
For instance, the RBC shall ensure that district-level plans do not compete for water and that they
remain within the total water available within the basin. If development plans are set to draw more
water than is available, RBC can fl ag the issue at NEC and GNHC – who in turn could block
certain plans so as to remain within the water available.
Chapter 6 of the Water Act mandates that RBCs shall be set up for the “purpose of proper
management of water resources.” Coordinated planning and development is the underlying
IWRM principle, and through a multi-stakeholder approach this coordination task is assigned to
an organization at the basin level.
Chapter 2, Section 6 of the Water Act states that a national integrated water resources management
plan shall be formulated for the “coordinated development, management, conservation and
effi cient use of water resources” and this shall serve as “a binding guideline for the preparation of
river basin management plans” (Chapter 5, Section 24).
Accordingly, the framework, composition, and terms of reference of RBCs was endorsed by the
NEC during its forty fi rst meeting held on 25 June 2015. An Executive Order to this eff ect was
issued on 14 April 2016 by the Prime Minister who is also the Chairman of NEC. Th e fi fteen-
member Wangchhu Basin Committee (WBC) is composed of the Chairperson of the Dzongkhag
Tshogdu (district development councils), Dzongdag (district governor) , DzEOs each from the
four Dzongkhags of Chhukha, Haa, Paro and Th imphu, the Th rompon (Mayor) and Chief
Environment O ffi cer of Th imphu Th romde (municipality) . Th e Chief Environment O ffi cer of
the WRCD of NECS,has been directed to serve as the member Secretary until further notice.
According to the Executive Order, the position of Chairperson shall rotate annually among the
78
four Dzongdags beginning with Haa Dzongdag. Th e NECS shall serve as the Secretariat to the
WBC with the understanding that (i) the WBC may have their respective Secretariat in the long
term; and (ii) the WBC shall report to NEC. A diagram showing the structure of the WBC is
shown in Figure 56.
Figure 56: Diagram of the WBC
3.1.8. Lack of understanding of dimensions of water management
IWRM sensitization workshops for local leaders
Sensitization workshops were held for local leaders throughout the country in the period 2013-
2015, and an inventory has been prepared of water-related issues. Th e list shows that nearly all
Gewogs in Wangchhu basin do experience one or another issue related to water, but it does not
provide any analysis or solution.
Role of local government and WUAs
Gewog administration and Water Users Associations (WUAs) take care of local water management
in daily practice, but at this level all dimensions of water-related issues are not always fully
understood. Climate change as a concept is unknown to many rural people. However, people
79
stated that there are adverse changes in the availability of water. Sustainable use, ensuring quality
of water, relationship with climate change, etc. are not issues of concern to the community as long
as there is water in the pipes.
Th ere is a need to make people more aware of water being a resource in wider socio- economic and
environmental perspective through information, education, and communication (IEC).52
3.1.9. Other water-related fi ndings
River bank protection works
Th e Gewogs responded in a questionnaire in 2015 about the number of river bank protection
works and their nearest village in the Gewog. Th e result is presented in the column chart in Figure
57.
Figure 57: Th e number of river bank protection works reported per Gewog
As can be seen, most riverbank protection works are concentrated in Paro district, particularly in
the Gewogs of Wangchang (9), Tsento (5), and Lango (5). Th ese Gewogs are all along the main
Paro river (Parochhu) without much elevation diff erence.
Th ere are eight riverbank protection works in Haa district. Th ese are also captured in the fl ood
hazard mapping carried out through the HEC RAS Flood Modelling work done by the TA.
Th e fl ood risks associated with the Parochhu and Haachhu are quite prominent and riverbank
protection works are already being carried out. Th ere also is a risk of fl ooding in Th imphu, but
most of the concerned areas are being taken care of by individual agencies and have been missed
by the survey respondents. More precise on-site investigations are required to assess the need for
future river training work.
Major water abstractions
According to the Gewog questionnaire survey, there are numerous major river water abstractions
for drinking water and/or irrigation, most notably in Haa district with Bjee Gewog (8) , in Paro
52 Th e details are given in the supporting stand-alone document: Social aspects of water management.
80
district in Doteng (6) and Lango (6) Gewog (Figure 58). Th ese abstractions need to be quantifi ed
and entered into the water accounting system (WEAP) that was established in NECS.
Figure 58: Th e number of major river water abstraction points reported per Gewog
Major water diversions
Th e Gewogs that reported existing water diversions are as follows: in Chukha district in Bjacho
Gewog (3) for hydropower stations; in Paro district in Hungrel Gewog (2) for drinking water and
Th imphu Gewog in Dagala (1 for drinking water) and Mewang (1 for mini hydropower station)
Gewog (Figure 59). Th e water diverted for consumptive use needs to be quantifi ed and entered
into the water accounting system (WEAP) that was established in NECS.
Figure 59: Th e number of major river water diversions reported per Gewog
Effl uent discharge
Untreated effl uent discharge has been reported in Chukha district in Darla Gewog (5), Paro
district in Lango (7), and Hungrel, Shaba, Tsento Gewog (1 each), and Haa district in Katsho
Gewog (2) as shown in Figure 60.
81
Figure 60: Th e number of effl uent discharge points reported per Gewog
Glacial Lake Outburst Floods (GLOF)
Th e risk of Glacial Lake Outburst Floods was reported in several Gewogs during the 2015 fi eld
survey. In Paro district, the risk was reported in seven villages of Doteng Gewog and in four villages
of Tsento Gewog (Figure 61). However, as indicated earlier in section 2.2, none of the glacial lakes
in the northern part of Wangchhu basin have been classifi ed as being at risk of outburst, and there
is no historical record of this happening before. Th e responses provided during the Gewogs survey
may be explained by the fact that the two tributaries of the Parochhu originate from glaciers. Th e
Gewogs of Doteng and Tsento are both the most upstream Gewogs and it is conceivable that
survey respondents did not diff erentiate between GLOF and monsoon fl ooding in glacier fed
rivers. Th e same explanation is valid for other Gewogs in Haa (Bjee) and Chhukha (Chapcha) and
Hungrel with one respondent in each of these Gewogs indicating a risk of GLOF. In Th imphu
district, the Gewogs of Lingzhi and Soe are located in altitude above 4000 m.a.s.l. and have glacial
lakes areas that local people might consider a threat.
Figure 61: Th e number of villages with GLOF-risk reported per Gewog
82
Water-related disputes
As shown in Figure 62, a number of disputes have been reported in the Gewog questionnaire,
concentrated in Paro district with Wangchang (5), Shaba (3) and Hungrel (3), Doteng, Lango,
Shari Geney, and Mewang (2 each). Th e disputes relate mostly to water sharing between old and
new settlements and between drinking water and irrigation. Th ey are concentrated in areas that
have been assessed as potentially water-scarce.
Figure 62: Number of water-related disputes reported per Gewog
Suitability of geological formations for groundwater aquifers
Th e geological map of Bhutan can be viewed on the internet.53 A snapshot showing Wangchhu basin
is given in Figure 63. Experience in cross-border areas in India and in similar geological formations
occurring in other regions of the Himalayas has shown that several geological formations have
varying potential of ground water availability depending upon their porosity, permeability and
hydro-geomorphological characteristics. Based on that experience, a very preliminary assessment
of the potential for groundwater development, based on the type of geological formation, from
higher to lower potential was reported as follows:54
1. Quaternary sediment.
2. Lesser Himalayan Zone-Gondwana succession (Permian) & Baxa Group (for spring
lines).
3. Siwalik Group (Miocene-Pliocene) - Upper member & Middle member.
4. Greater Himalayan Zone- Structurally-lower Greater Himalayan section (for spring
lines).53 http://www.pitt.edu/~nmcq/Long_etal_2011_JOM_Bhutan_Map_1-500k.pdf
54 M. Mehta, former Commissioner of the Ministry of Water Resources, GoI, e-mail communication 2 March 2016
83
5. Tethyan Himalayan Zone -Undiff erentiated (Paleozoic-Eocene).
Th e locations of the two most-promising formations have been investigated, and the results
are presented in Table 26. Th e geological subsoil and supposed potential for groundwater in
Dzongkhag capitals in Wangchhu basin is given in Table 27.
Table 26: Occurrence of geological formations with supposedly promising groundwater potential
Nr. Main Formation Symbol Wangchhu Bhutan
1 Quaternary sediment Qt No Sipsu area
2a Lesser Himalayan
Gondwana Pzg NoNarrow strip in extreme south -central east,
including Deothang
Jaishidanda PzjNarrow strip
passing GeduNarrow belt in the south
2b Baxa group
Phuentsholing Pzph NoNarrow strip in extreme south west, incl uding
Phuentsholing
Manas PzmBelt in the
south
Southern belt, including Sarpang, Gonphu,
Panbang, Pemagatshel
Table 27: Dzongkhag capitals in Wangchhu basin with their geological subsoil and supposed groundwater
potential
Nr. City Symbol on geological mapRank for groundwater
development
1 Haa Pzpu -
2 Chhukha GHlml 4
3 Paro Pzpu -
4 Th imphu GHlml 4
84
Figure 63: Snapshot of geological map of Bhutan for Wangchhu basin
3.2. Problem analysis and strategy development
Two Logical Framework Analysis workshops were held for Wangchhu basin with members of the
WBC and basin representatives. Th e fi rst workshop was held on 13-15 July on preparing problem
trees and solution trees related to the fi ve water security dimensions. Th e second workshop was
held on 14-16 October 2015 on formulating goals and objectives. Th e problem and strategy trees
against the fi ve Key Dimensions of water security, and for Th romdes as a separate group are given
in Appendix 3.
Th e success of interventions is measured along Key Performance Indictors. Th is logic is further
elaborated into plans and targets for each Key Dimension as discussed in the next chapter.
85
4. WANGCHHU BASIN PLAN
Th is chapter presents the plan expressed in Key Result Areas and Key Performance Indicators.
Baseline values and targets are provided with an explanation of the next steps to be taken.
4.1. Introduction
Th e plan formulation is based on the results of the participatory logical framework analysis that
was carried-out specifi cally for the Wangchhu basin. It is structured along the fi ve key dimensions
of the BWSI. Th e qualitative results are described in the following tables, specifying for each
Key Dimension of water security the Goal, Specifi c Objectives, Key Result Areas, Performance
Indicators (KPIs) and Main interventions at basin level. Th e KPIs following from the BWSI are
in italic font, to distinguish them from other performance indicators that have been identifi ed by
stakeholders during the Logical Framework Analysis exercise. Th e priority interventions are also
in italic font.
A number of the indicators of the BWSI are not actionable. An obvious example is the Coeffi cient
of Variation of rainfall. Th ese are used only for monitoring purposes and have not been elaborated
in the action plans and cost estimates.
Th e plans for the actionable indicators are elaborated for each district in Appendix 4, specifying
their baseline values, target values, estimated workload involved, and cost estimate against current
prices for respectively the 12th, 13th, and 14th FYP. Th e cost estimates were prepared by the District
Engineers and Planning Offi cers, and vetted by the Dzongdags and Tshogdus of the respective
districts in Wangchhu basin during a two-day workshop held on 20 and 21 April 2016.
Th e main quantitative fi ndings are summarized per intervention and per district under the tables
describing the qualitative plans. Th e tables are self-explanatory.
Th e role of the RBC is prominent in formulating the assumptions for planning across the basin
and for coordinating between stakeholders. An equitable development is pursued among the
district in most water security domains, but diff erentiation is accepted for example with respect to
hydropower development, expansion of irrigated areas in the respective districts.
Th e responsibilities of the Dzongkhag Administration and central agencies are in preparing and
implementing the FYPs. It may be noted that the budget estimates provided in this plan needs
to be reviewed and mobilized through GNHC for implementation. Th e proposed fi nancial
mechanism is to follow the existing process of planning and budgeting system. Once the priorities
are integrated into the FYPs, MOF will transfer the approved amounts to the respective districts
and central agencies. Th e role of WBC in coordinating the integration of the plans and securing
budget through district and line agencies and mechanism to mobilize resources for priorities that
emerge during the FYP implementation period is described later under section 4.3.
86
4.2
. W
ang
chh
u B
asin
Pla
ns
and
tar
get
s
Tab
le 2
8:
Pla
n f
or
KD
1-R
ura
l w
ater
sec
uri
ty
1.
Ru
ral
ho
use
ho
ld w
ate
r
secu
rity
Key
Res
ult
Are
asK
ey P
erfo
rman
ce I
nd
icat
ors
Mai
n I
nte
rven
tio
ns/
Pro
ject
s
Go
al: T
o i
mp
rove
an
d
pro
tect
ru
ral
dri
nk
ing
wat
er a
nd
san
itat
ion
in
Wan
gch
hu
bas
in
Spec
ific
ob
ject
ives
: •
Red
uce
mo
rbid
ity
and
mo
rtal
ity
rate
s
• Im
pro
ve t
he
qu
anti
ty a
nd
qu
alit
y o
f h
ou
seh
old
wat
er
sup
ply
• R
edu
ce t
he
inci
den
ce o
f
wat
er r
elat
ed d
isp
ute
s
• R
edu
ce d
rud
gery
in
wat
er
fetc
hin
g am
on
g w
om
en
and
ch
ild
ren
• Im
pro
ved
co
nd
itio
n
of
wat
er s
ou
rces
an
d
catc
hm
ents
• Im
pro
ved
acc
ess
to
alte
rnat
ive
dri
nk
ing
wat
er
sou
rces
• Im
pro
ved
man
agem
ent
of
rura
l w
ater
su
pp
ly
• In
crea
sed
acc
ess
to
imp
rove
d s
anit
atio
n
• P
erce
nt
of p
opu
lati
on w
ith
acc
ess
to p
iped
wa
ter
sup
ply
• P
erce
nt
of p
eop
le w
ith
wa
ter-
sea
led
sa
nit
ati
on
• In
cid
ence
of
dia
rrh
oea
• N
um
ber
of
wat
er s
ou
rces
revi
ved
• A
cces
s to
dri
nk
ing
wat
er i
n h
rs/
day
(%
)
• N
um
ber
of
wat
er u
ser
asso
ciat
ion
fo
rmed
• N
um
ber
of
smal
l re
serv
oir
s
and
rai
n w
ater
har
vest
ing
un
its
esta
bli
shed
• E
xpa
nd
pip
ed w
ate
r co
nn
ecti
ons
• E
xpa
nd
im
pro
ved
sa
nit
ati
on f
aci
liti
es
• D
evel
op a
nd
ap
ply
wa
ter
ha
rves
tin
g
tech
nol
ogie
s
• C
onst
ruct
wa
ter
rese
rvoi
rs a
nd
wel
ls
• C
arry
ou
t m
ass
affo
rest
atio
n a
nd
ref
ore
stat
ion
pro
gram
• C
arry
ou
t p
ub
lic
edu
cati
on
an
d a
war
enes
s o
n
catc
hm
ent
man
agem
ent
law
s an
d r
egu
lati
on
s
• Im
pro
ve l
ives
tock
man
agem
ent
to r
edu
ce t
he
imp
act
of
over
-gra
zin
g
• Im
pro
ve k
no
wh
ow
an
d t
ech
no
logy
to
acc
ess
wat
er s
ou
rces
• Im
pro
ve d
esig
n o
f w
ater
su
pp
ly s
yste
ms
to
red
uce
lo
sses
• O
rgan
ize
and
tra
in w
ater
use
r as
soci
atio
ns
87
Tab
le 29
: Estim
ated b
ud
get req
uirem
ents (M
illion
Ng
ultru
m) p
er interven
tion
for K
D1
- Ru
ral water secu
rity
Ma
in In
terv
en
tion
s for K
D1
: Ru
ral w
ate
r sec
urity
12
th F
YP
13
th F
YP
14
th F
YP
To
tal
Re
spo
nsib
le A
ge
nc
yR
em
ark
Exp
an
d p
iped
wa
ter c
on
nectio
ns
12
7.7
12
7.7
12
7.7
38
3.1
De
pa
rtme
nt o
f Pu
blic
He
alth
, MO
H
- Chukha
53
.65
3.6
53
.61
60
.8
- Haa
8.3
8.3
8.3
24
.9
- Paro
49
.24
9.2
49
.21
47
.7
- Thim
phu
16
.61
6.6
16
.64
9.7
Imp
ro
ve fu
nctio
na
lity o
f pip
ed
wa
ter s
yste
m9
5.3
95
.39
5.3
28
5.9
De
pa
rtme
nt o
f Pu
blic
He
alth
, MO
H
- Chukha
25
.92
5.9
25
.97
7.6
- Haa
4.9
4.9
4.9
14
.7
- Paro
60
.96
0.9
60
.91
82
.6
- Thim
phu
3.7
3.7
3.7
11
.1
Exp
an
d im
pro
ved
sa
nita
tion
facilitie
s4
59
.44
59
.44
59
.41
37
8.2
De
pa
rtme
nt o
f Pu
blic
He
alth
, MO
H
- Chukha
17
0.1
17
0.1
17
0.1
51
0.3
- Haa
35
.63
5.6
35
.61
06
.7
- Paro
21
5.9
21
5.9
21
5.9
64
7.6
- Thim
phu
37
.93
7.9
37
.91
13
.6
Develo
p a
nd a
pply
wate
r harv
estin
g te
chnolo
gie
s
Constru
ct w
ate
r reserv
oirs
and w
ells
Carry
out m
ass a
ffore
sta
tion a
nd re
fore
sta
tion p
rogra
m
Carry
out p
ublic
educatio
n a
nd a
ware
ness o
n c
atc
hm
ent
managem
ent la
ws a
nd re
gula
tions
Impro
ve liv
esto
ck m
anagem
ent to
reduce th
e im
pact o
f over-g
razin
g
Impro
ve k
now
how
and te
chnolo
gy to
access w
ate
r sourc
es
Impro
ve d
esig
n o
f wate
r supply
syste
ms to
reduce lo
sses
Org
aniz
e a
nd tra
in w
ate
r user a
ssocia
tions
Su
bto
tal
68
2.4
68
2.4
68
2.4
20
47
.2
Se
e K
D5
Provid
ing ru
ral ho
useh
old
s with
pip
ed w
ater sup
ply is a ro
utin
e activity of D
PH
-MO
H an
d th
e En
gineerin
g Secto
r of th
e Dzo
ngk
hag as
laid d
ow
n in
the F
YP
s. The sam
e ho
lds fo
r rural san
itation
, bu
t the b
enefi
ciaries shall b
ear half th
e cost. In
rural areas th
e focu
s is so far o
n
imp
roved latrin
es. A start w
ill be m
ade w
ith in
trod
uctio
n o
f water-sealed
toilets.
88
Tab
le 3
0:
Pla
n f
or
KD
2-E
con
om
ic w
ater
sec
uri
ty
2.
Eco
no
mic
Wat
er S
ecu
rity
Key
Res
ult
Are
asK
ey P
erfo
rman
ce I
nd
icat
ors
Mai
n I
nte
rven
tio
ns/
Pro
ject
s
Go
al: T
o m
axim
ize
eco
no
mic
ben
efits
der
ived
fro
m u
se o
f
wat
er r
eso
urc
es i
n W
angc
hh
u
bas
in,
and
en
sure
ad
equ
ate
and
sust
ain
able
ava
ilab
ilit
y
Spec
ific
ob
ject
ives
:
Max
imiz
e ag
ricu
ltu
ral
pro
du
ctiv
ity,
co
ntr
ibu
tin
g to
enh
ance
d f
oo
d s
ecu
rity
Sust
ain
gro
wth
in
rev
enu
e fr
om
hyd
rop
ow
er g
ener
atio
n,
alo
ng
wit
h e
nh
ance
men
t o
f en
ergy
secu
rity
En
han
ce i
nd
ust
rial
dev
elo
pm
ent,
par
ticu
larl
y fo
r
smal
l an
d m
ediu
m e
nte
rpri
ses
Max
imiz
e an
d s
ust
ain
po
ten
tial
reve
nu
es f
rom
wat
er-b
ased
tou
rism
• In
crea
sed
dep
end
ab
le a
vail
ab
ilit
y
an
d a
cces
s to
wa
ter
for
agr
icu
ltu
ral
use
• E
nh
an
ced
ab
ilit
y to
gen
era
te
hyd
rop
ower
at
full
ca
pa
city
an
d
min
imiz
e p
ower
im
por
ts d
uri
ng
the
lea
n s
easo
n
• In
crea
sed
uti
liza
tio
n o
f
wat
er r
eso
urc
es f
or
ind
ust
rial
dev
elo
pm
ent
pu
rpo
ses
• E
nh
ance
use
of
wat
er r
eso
urc
es
for
tou
rism
att
ract
ion
• P
erce
nt
of a
rab
le l
an
d
irri
gate
d
• P
erce
nt
of w
ate
r st
ored
in s
ma
ll r
eser
voir
s fo
r
agr
icu
ltu
ral
use
• P
erce
nta
ge i
ncr
ease
in
agr
icu
ltu
ral
reve
nu
e
• P
erce
nt
incr
ease
in
hyd
rop
ow
er g
ener
atio
n
du
rin
g le
an s
easo
n
• P
erce
nt
incr
ease
in
in
du
stry
con
trib
uti
on
to
GD
P
• P
erce
nta
ge i
ncr
ease
in
tou
rism
rev
enu
e
• C
onst
ruct
res
ervo
irs
an
d i
ncr
ease
wa
ter
rech
arg
e in
ca
tch
men
ts
• D
evel
op i
nfr
ast
ruct
ure
to
tap
ava
ila
ble
wa
ter
reso
urc
es i
n d
eep
va
lley
s u
sin
g
ap
pro
pri
ate
tec
hn
olog
ies
(an
d t
ap
pin
g
inte
rna
tion
al
clim
ate
fu
nd
s fo
r
fin
an
cin
g)
• C
on
stru
ct h
ydro
po
wer
res
ervo
irs
to
sust
ain
po
wer
gen
erat
ion
by
sto
rin
g
wat
er f
or
lean
per
iod
s, a
nd
to
ad
apt
to
clim
ate
chan
ge
• P
rovi
de
suit
able
tec
hn
olo
gies
an
d
sup
po
rt i
nfr
astr
uct
ure
to
in
crea
se t
he
ben
efici
al u
se o
f w
ater
fo
r ag
ricu
ltu
ral
and
in
du
stri
al d
evel
op
men
t
• Im
pro
ve w
ater
res
ou
rce
info
rmat
ion
syst
ems
89
Tab
le 31
: Estim
ated b
ud
get req
uirem
ents (M
illion
Ng
ultru
m) p
er interven
tion
for K
D2
-Eco
no
mic w
ater security
Ma
in In
terv
en
tion
s for K
D2
: Ec
on
om
ic w
ate
r sec
urity
12
th F
YP
13
th F
YP
14
th F
YP
To
tal
Re
spo
nsib
le A
ge
nc
yR
em
ark
Constru
ct re
servo
irs a
nd in
cre
ase w
ate
r recharg
e in
catc
hm
ents
Se
e K
D5
Deve
lop
infra
stru
ctu
reto
tap
ava
ilab
lew
ate
rre
sourc
es
indeep
valle
ysusin
gappro
pria
tete
chnolo
gie
s(a
nd
tappin
gin
tern
atio
nal
clim
ate
funds fo
r financin
g)
Constru
ct h
ydro
pow
er re
serv
oirs
to s
usta
in p
ow
er g
enera
tion b
y
sto
ring w
ate
r for le
an p
erio
ds, a
nd to
adapt to
clim
ate
change
36
,37
83
6,3
78
36
,37
81
09
,13
5D
OH
PS
of M
OE
A
Co
st o
f res
erv
oirs
are
inc
lud
ed
in to
tal
de
ve
lop
me
nt c
os
t
- Chukh
a2
3,3
78
23
,37
82
3,3
78
70
,13
5
- Haa
- Paro
6,0
00
6,0
00
6,0
00
18
,00
0
- Thim
phu
7,0
00
7,0
00
7,0
00
21
,00
0
Pro
vid
e s
uita
ble
technolo
gie
s a
nd s
upport in
frastru
ctu
re to
incre
ase
the b
enefic
ial u
se o
f wate
r for a
gric
ultu
ral a
nd in
dustria
l develo
pm
ent
12
8.7
12
8.7
12
8.7
38
6.1
DO
A o
f MO
AF
Imp
lem
en
tatio
n o
f
the
NIM
P
- Chukh
a4
4.5
44
.54
4.5
13
3.6
- Haa
1.1
1.1
1.1
3.2
- Paro
68
.66
8.6
68
.62
05
.7
- Thim
phu
14
.51
4.5
14
.54
3.6
Impro
ve w
ate
r resourc
e in
form
atio
n s
yste
ms
Su
bto
tal
36
,50
73
6,5
07
36
,50
71
09
,52
1
Exp
ansio
n o
f irrigated agricu
lture fo
llow
s the N
ation
al Irrigation
Master P
lan (2
01
6), in
creasing th
e irrigated area b
y 50
% b
y 20
33
and
facilitated b
y the D
OA
.
Hyd
rop
ow
er develo
pm
ent p
lans o
f the D
HP
S h
ave been
inco
rpo
rated in
the W
BM
P.
90
Tab
le 3
2:
Pla
n f
or
KD
3-U
rban
wat
er s
ecu
rity
an
d d
rain
age
3.
Urb
an w
ater
sec
uri
tyK
ey R
esu
lt A
reas
Key
Per
form
ance
In
dic
ato
rsM
ain
In
terv
enti
on
s/P
roje
cts
Go
al:
To
im
pro
ve t
he
effici
ency
of
urb
an w
ater
sup
ply
sys
tem
, an
d p
rote
ct
wat
er q
ual
ity
and
dra
inag
e
cap
acit
y o
f w
ater
way
s in
urb
an a
reas
of
Wan
gCh
hu
bas
in
Sp
ecifi
c o
bje
ctiv
es:
• A
void
wat
er l
oss
es
• R
edu
ce h
ealt
h c
are
cost
s
fro
m m
orb
idit
y an
d
mo
rtal
ity
rela
ted
to
wat
er
safe
ty
• M
inim
ize
dis
pu
tes
over
wat
er s
ou
rces
, an
d e
nh
ance
soci
al c
oh
esio
n
• S
ecu
re v
ital
wat
er s
ou
rces
• In
crea
sed
wat
er s
up
ply
cap
acit
y an
d
imp
rove
d c
on
dit
ion
of
exis
tin
g p
iped
wat
er s
up
ply
net
wo
rk
• W
ater
qu
alit
y d
egra
dat
ion
in
urb
an
wat
erw
ays
pre
ven
ted
• R
edu
ced
wat
er l
oss
es f
rom
th
e w
ater
sup
ply
sys
tem
• In
crea
sed
co
ntr
ol
over
ill
egal
tap
pin
g
of
wat
er,
and
mo
re e
qu
itab
le w
ater
dis
trib
uti
on
• R
edu
ced
in
cid
ence
of
urb
an fl
oo
din
g
• Im
pro
ved
sew
erag
e an
d s
anit
atio
n
syst
ems
• P
erce
nta
ge
of
ho
use
ho
lds
wit
h
pip
ed w
ater
su
pp
ly
• P
erce
nta
ge
of
ho
use
ho
ld s
ewer
con
nec
tio
ns
• P
erce
nta
ge
red
uct
ion
in
pip
ed
wat
er l
oss
es
• P
erce
nta
ge
of
ho
use
ho
lds
wit
h
soli
d w
aste
dis
po
sal
• R
edu
ctio
n i
n fl
oo
d d
amag
e
• N
um
ber
of
Thro
md
e w
ater
sup
ply
mas
ter
pla
ns
pre
par
ed
• N
um
ber
or
urb
an d
rain
age
pla
ns
dev
elo
ped
• L
engt
h o
f d
rain
s co
nst
ruct
ed
(tar
get
10
0%
cov
erag
e o
f st
orm
wat
er d
rain
s)
• U
rban
sew
erag
e m
aste
r p
lan
s
dev
elo
ped
• L
engt
h o
f se
wer
lin
es
con
stru
cted
• N
um
ber
of
add
itio
nal
urb
an
wat
er s
ou
rces
id
enti
fied
, an
d
new
in
tak
es c
on
stru
cted
• E
xp
and
pip
ed w
ater
sy
stem
• E
xp
and
sew
erag
e co
vera
ge
• Im
pro
ve d
rain
age
net
wo
rk,
foll
ow
ing
a m
aste
r p
lan
• R
epla
ce l
eak
y w
ater
su
pp
ly p
ipes
• In
itia
te w
ater
met
erin
g,
com
bin
ed w
ith
pu
bli
c aw
aren
ess
rais
ing
on
th
e ai
ms
of
pro
per
wat
er p
rici
ng
• E
stab
lish
mo
nit
ori
ng
sy
stem
to
min
imiz
e il
leg
al w
ater
tap
pin
g
• T
ap a
lter
nat
ive
wat
er s
ou
rces
to e
xpan
d u
rban
wat
er s
up
ply
(Gro
un
dw
ater
su
rvey
)
• C
on
stru
ct w
ater
sto
rage
faci
liti
es,
incl
ud
ing
for
rain
wat
er
har
vest
ing
• Im
pro
ve t
he
man
agem
ent
of
soli
d
was
tes
• Im
pro
ve u
rban
pla
nn
ing,
incl
ud
ing
stre
ngt
hen
ing
of
coo
rdin
atio
n a
nd
hu
man
reso
urc
es
• Im
pro
ve c
on
stru
ctio
n a
nd
mai
nte
nan
ce s
tan
dar
ds
91
Expansion and maintenance of the urban piped water and sewerage system is a routine program
of the WSD-DES-MOWHS as laid down in the FYPs.
Solid waste collection and disposal is a routine program under the District Administration.
Table 33: Estimated budget requirements (Million Ngultrum) per intervention for KD3-Urban water security
and drainage
Main Interventions for KD3: Urban water security 12th FYP 13th FYP 14th FYP Total Responsible Agency Remark
Expand piped water system 34.2 34.2 34.2 102.6Water & Sanitation
Division, DES, MOWHS
- Chukha 3.3 3.3 3.3 9.8
- Haa 1.6 1.6 1.6 4.9
- Paro 1.8 1.8 1.8 5.5
- Thimphu
Urban drinking water treatment 6.7 6.7 6.7 20.1Water & Sanitation
Division, DES, MOWHS
- Chukha 1.7 1.7 1.7 1.7
- Haa 1.7 1.7 1.7 1.7
- Paro 1.7 1.7 1.7 1.7
- Thimphu 1.7 1.7 1.7 1.7
Expand sewerage coverage4.2 4.2 4.2 12.6
Water & Sanitation
Division, DES, MOWHS
- Chukha 0.6 0.6 0.6 1.7
- Haa 0.3 0.3 0.3 0.8
- Paro 0.2 0.2 0.2 0.7
- Thimphu 3.1 3.1 3.1 9.3
Improve drainage network, following a master plan
Replace leaky water supply pipes
Initiate water metering, combined with public awareness raising on
the aims of proper water pricing
- Chukha 3.4 3.4 3.4 10.1
- Haa 1.3 1.3 1.3 4.0
- Paro 1.5 1.5 1.5 4.5
- Thimphu 41.6 41.6 41.6 124.9
Establish monitoring system to minimize illegal water tapping
Tap alternative w ater sources to expand urban w ater supply
(Groundw ater survey)
Construct w ater storage facilities, including for rain w ater harvesting See KD5
Improve the management of solid w astes 3.3 3.3 3.3 9.9Water & Sanitation
Division, DES, MOWHS
- Chukha 0.3 0.3 0.3 0.8
- Haa 0.1 0.1 0.1 0.4
- Paro 0.2 0.2 0.2 0.5
- Thimphu 2.7 2.7 2.7 8.2
Improve urban planning, including strengthening of coordination and
human resources
Improve construction and maintenance standards
Subtotal 96.2 96.2 96.2 288.6
47.8 47.8 47.8 143.4Water & Sanitation
Division, DES, MOWHS
92
Tab
le 3
4:
Pla
n f
or
KD
4-E
nv
iro
nm
enta
l w
ater
sec
uri
ty
4.
En
viro
nm
enta
l w
ater
secu
rity
Key
Res
ult
Are
asK
ey P
erfo
rman
ce I
nd
icat
ors
Mai
n I
nte
rven
tio
ns/
Pro
ject
s
Goa
l: T
o p
reve
nt
deg
rad
atio
n
of
catc
hm
ent
area
s in
th
e b
asin
,
and
rem
edia
te e
xist
ing
dam
age
Sp
ecifi
c ob
ject
ives
:
• R
edu
ce t
he
inci
den
ce o
f
wat
er-r
elat
ed c
on
flic
ts b
y
pre
ven
tin
g th
e d
ryin
g u
p o
f
wat
er s
ou
rces
• P
reve
nt
aban
do
nm
ent
or
exce
ssiv
e fa
llo
win
g o
f
pro
du
ctiv
e la
nd
s
• R
edu
ce o
ccu
rren
ces
of
lan
dsl
ides
an
d f
ore
st fi
res
• Im
pro
ve t
he
qu
alit
y o
f w
ater
for
vari
ou
s p
urp
ose
s
• N
egat
ive
imp
acts
of
dev
elo
pm
ent
acti
viti
es i
n t
he
wat
ersh
ed a
re
pre
ven
ted
• D
egra
dat
ion
of
wat
ersh
eds
red
uce
d
• A
dap
tati
on
to
clim
ate
chan
ge
effec
ts e
nh
ance
d
(par
ticu
larl
y d
ue
to
tem
per
atu
re r
ise
and
mo
re e
rrat
ic r
ain
fall
pat
tern
)
• P
erce
nta
ge c
ropp
ed l
and
• P
erce
nta
ge o
f b
uil
t ar
ea
• P
erce
nta
ge w
etla
nd
are
a
• Su
spen
ded
sol
ids
in w
ater
• B
OD
of
surf
ace
wat
ers
• P
erce
nta
ge w
ater
con
sum
ed i
n J
anu
ary
• P
erce
nta
ge w
ater
con
sum
ed i
n M
ay
• N
um
ber
non
-nat
ive
fish
spe
cies
• P
erce
nta
ge n
on-n
ati
ve fi
sh s
pec
ies
• N
um
ber
of
awar
enes
s-ra
isin
g p
rogr
ams
con
du
cted
fo
r w
ater
shed
pro
tect
ion
• N
um
ber
of
trai
nin
g p
rogr
ams
con
du
cted
on
wat
ersh
ed-f
rien
dly
agr
icu
ltu
ral
pra
ctic
es
• N
um
ber
of
regu
lati
on
s d
evel
op
ed t
o r
egu
late
use
of
farm
ing
chem
ical
s
• N
um
ber
of
regu
lati
on
s d
evel
op
ed t
o m
on
ito
r
min
ing
and
in
du
stri
al a
ctiv
itie
s in
wat
ersh
eds
• N
um
ber
of
area
s w
her
e P
ES
(p
aym
ent
for
envi
ron
men
tal
serv
ices
) is
pra
ctic
ed
• A
mo
un
t o
f fi
nes
an
d p
enal
ties
co
llec
ted
• L
engt
h o
f fo
rest
fire
lin
es c
on
stru
cted
• N
um
ber
of
wea
ther
mo
nit
ori
ng
stat
ion
s
esta
bli
shed
, in
clu
din
g d
ata
pro
cess
ing
and
dis
sem
inat
ion
• N
um
ber
of
fore
st p
atro
ls s
et u
p
• R
emed
iate
for
est
loss
an
d
deg
rad
ati
on
• E
nfo
rce
rule
s a
nd
reg
ula
tion
s
to p
reve
nt
lan
d c
onve
rsio
n i
n
crit
ica
l a
rea
s
• P
rom
ote/
pil
ot s
ust
ain
ab
le
pa
stu
re d
evel
opm
ent
to p
reve
nt
over
-gra
zin
g
• S
top
ill
ega
l lo
ggin
g, a
nd
reg
ula
te
extr
act
ion
of
fore
st p
rod
uct
s
• C
arry
ou
t p
rop
er p
lan
nin
g
and
im
ple
men
tati
on
of
infr
astr
uct
ure
an
d a
gric
ult
ura
l
dev
elo
pm
ent
• E
nfo
rce
EF
RC
met
ho
ds
for
road
con
stru
ctio
n
• E
nfo
rce
com
pli
ance
to
pla
ns
• Id
enti
fy a
nd
dem
arca
te c
riti
cal
area
s fo
r m
anag
emen
t
• R
aise
aw
aren
ess
on
use
of
fert
iliz
ers
and
pes
tici
des
• E
nfo
rce
envi
ron
men
tal
regu
lati
on
s o
n m
inin
g ac
tivi
ties
• S
et u
p a
deq
uat
e n
etw
ork
of
wea
ther
sta
tio
ns
to m
on
ito
r
chan
ges
in c
lim
ate
93
None of the BWSI indicators for KD4-Environmental water security are presently actionable
and therefore they are not elaborated in the WRBM. However, the following activities shall be
implemented:
1. NECS shall establish ambient and effl uent water quality standards along with a
monitoring system within the 12th FYP.
2. WMD shall implement watershed conservation programs particularly in watershed Nr.
158 and 67 within the 12th FYP (cost estimates are in preparation).
3. DHMS shall expand its climate and river discharge monitoring network as per existing
plans (supported by WB).
4. MoAF will implement a national conservation program for the wildlife protection areas
and corridors over the next 15 years with a total value of Nu. 103 million (including
international co-funding under Bhutan for Life), of which a proportional amount
pertains to Wangchhu basin.
94
Tab
le 3
5:
Pla
n f
or
KD
5-R
esil
ien
ce t
o d
isas
ter
and
cli
mat
e ch
ang
e
5.
Dis
aste
r re
sili
ence
an
d
clim
ate
chan
ge
secu
rity
Key
Res
ult
Are
asK
ey P
erfo
rman
ce I
nd
icat
ors
Mai
n I
nte
rven
tio
ns/
Pro
ject
s
Goa
l: T
o r
edu
ce a
nd
pre
ven
t
soci
o-e
con
om
ic l
oss
du
e
to w
ater
-rel
ated
nat
ura
l
dis
aste
rs,
par
ticu
larl
y fl
oo
din
g
and
lan
dsl
ides
in
Wan
gCh
hu
bas
in
Sp
ecifi
c ob
ject
ives
:
• A
void
lo
ss o
r d
amag
e to
infr
astr
uct
ure
• A
void
red
uct
ion
of
hyd
rop
ow
er g
ener
atio
n
cap
acit
y
• A
void
co
mm
un
ity
dis
pla
cem
ent
• A
void
ad
vers
e im
pac
t o
n
bio
-div
ersi
ty
• A
void
dam
age
to
agri
cult
ura
l la
nd
s,
incl
ud
ing
live
sto
ck l
oss
es
• Im
ple
men
ted
flo
od
an
d
dis
aste
r m
itig
atio
n m
easu
res
• D
isas
ter
resi
lien
ce
mai
nst
ream
ed i
nto
dev
elo
pm
ent
pla
nn
ing
• Im
pro
ved
pla
nn
ing
and
dev
elo
pm
ent
of
infr
astr
uct
ure
an
d m
inin
g
acti
viti
es
• Su
stai
nab
le l
and
man
agem
ent
• R
elia
ble
wea
ther
fo
reca
stin
g
and
war
nin
g sy
stem
esta
bli
shed
• P
erce
nta
ge c
ha
nge
in
for
est
cove
r
• P
erce
nta
ge-p
oin
t d
evia
tion
fro
m
ma
nd
ato
ry f
ores
t co
ver
• N
o. o
f E
mer
gen
cy R
esp
onse
Un
its
• W
ate
r st
ora
ge c
ap
aci
ty
• F
lood
ha
zard
zon
ati
on
• F
lood
/ G
LO
F E
arl
y W
arn
ing
• N
o. o
f d
isas
ter
mit
igat
ion
mea
sure
s p
ut
in p
lace
• N
o. o
f ag
enci
es m
ain
stre
amin
g d
isas
ter
mit
igat
ion
an
d r
esil
ien
t in
th
eir
pla
ns
• A
crea
ge o
f d
egra
ded
lan
d u
nd
er
sust
ain
able
lan
d m
anag
emen
t
• N
um
ber
of
dis
aste
r-p
ron
e si
tes
and
area
s id
enti
fied
• N
um
ber
of
trai
nin
gs a
nd
aw
aren
ess
pro
gram
s co
nd
uct
ed
• N
um
ber
of
fore
st fi
re i
nci
den
ces
red
uce
d (
bas
elin
e: 1
5 fi
re i
nci
den
ces
as
of
20
14
)
• F
un
ctio
nal
an
d r
elia
ble
co
mm
un
icat
ion
syst
ems
pu
t in
pla
ce
• A
pp
ly r
emed
ial
mea
sure
s in
ha
zard
pro
ne
are
as
(e.g
., r
efor
esta
tion
, b
io-
engi
nee
rin
g w
ork
s, l
an
d t
rea
tmen
ts,
con
trol
led
gra
zin
g)
• Im
ple
men
t a
ctiv
itie
s to
red
uce
fore
st fi
re i
nci
den
ce (
fore
st l
ines
,
com
mu
nit
y or
gan
iza
tion
an
d
tra
inin
g)
• C
on
du
ct fl
oo
d m
od
elli
ng,
haz
ard
map
pin
g an
d a
sses
smen
t
• D
evel
op
cap
acit
y fo
r d
isas
ter-
resi
lien
t u
rban
pla
nn
ing
• P
rom
ote
an
d u
se E
FR
C m
eth
od
s in
road
co
nst
ruct
ion
• St
ren
gth
en m
inin
g re
gula
tio
ns
and
thei
r en
forc
emen
t
• E
xpan
d n
etw
ork
of
wea
ther
mo
nit
ori
ng
stat
ion
s, a
nd
im
pro
ve
info
rmat
ion
man
agem
ent
and
shar
ing
95
Tab
le 36
: Estim
ated b
ud
get req
uirem
ents (M
illion
Ng
ultru
m) p
er interven
tion
for K
D5
-Resilien
ce to d
isaster and
climate ch
ang
e
Ma
in In
terv
en
tion
s for K
D5
: Re
silien
ce
12
th F
YP
13
th F
YP
14
th F
YP
To
tal
Re
spo
nsib
le A
ge
nc
yR
em
ark
Apply re
media
l measure
s in
hazard
pro
ne a
reas (e
.g., re
fore
sta
tion,
bio
-engin
eerin
g w
ork
s, la
nd tre
atm
ents
, contro
lled g
razin
g)
1.7
1.6
71
.67
5.0
WB
CJo
int re
vo
lvin
g fu
nd
for 4
Dis
tricts
Imple
ment
activitie
sto
reduce
fore
st
firein
cid
ence
(fore
st
lines,
com
munity o
rganiz
atio
n a
nd tra
inin
g)
Conduct flo
od m
odellin
g, h
azard
mappin
g a
nd a
ssessm
ent, P
aro
13
3.6
13
3.6
FE
MD
, DE
S, M
OW
HS
Flo
od
pro
tec
tion
me
as
ure
s P
aro
Develo
p c
apacity
for d
isaste
r-resilie
nt u
rban p
lannin
g
Pro
mote
and u
se E
FR
C m
eth
ods in
road c
onstru
ctio
n
Stre
ngth
en m
inin
g re
gula
tions a
nd th
eir e
nfo
rcem
ent
Expand n
etw
ork o
f weath
er m
onito
ring s
tatio
ns, a
nd im
pro
ve
info
rmatio
n m
anagem
ent a
nd s
harin
g8
08
01
60
DH
MS
, MO
EA
Ea
rly W
arn
ing
Sy
ste
m
Rura
l wate
r sto
rage
59
55
95
Wa
ter &
Sa
nita
tion
Div
isio
n, D
ES
, MO
WH
S
- Chukh
a1
74
- Haa
68
- Paro
35
2
- Thim
phu
1
Su
bto
tal
81
0.3
81
.71
.78
93
.6
Gra
nd
tota
l of in
terv
en
tion
s3
8,0
96
37
,36
73
7,2
87
11
2,7
50
96
Th e Wangchhu RBC, assisted by NECS, shall establish a revolving fund of Nu. 5 million in order
to be able to deal swiftly with any water related disaster. Th is amount is proposed to be put in
place under the 12 FYP and therefore fi nanced by the government. Depending on the amount
expended, the fund is proposed to be replenished every FYP. Hence, replenishment amounts will
be proposed for subsequent FYPs.
As a pilot project, it is planned to provide water storage facilities to 10% of the neediest rural families
(at least 65 villages) who have diffi culties with domestic water supply during the lean season.
Th e project would be implemented by the Water & Sanitation Division (WSD) -Department of
Engineering Services –Ministry of Works & Human Settlements in the 12th FYP.
Flood-prone areas have been identifi ed in the WBMP. WSD will follow-up demarcating the
areas on the ground for public awareness. It will also follow-up with detailed fi eld surveys for
identifi cation of fl ood-protection measures such as building embankments or raising the ground
level with spoil from road construction on specifi c sites.
DHMS will complete its on-going work with respect to fl ash fl ood forecasting and early warning
within the 12th and 13th FYP, with a preliminary cost estimate of Nu. 160 million based on similar
work done in Punakha.
Expected increase in basin water security score (2016-2033)
Based on the interventions given above, the average score of water security in Wangchhu basin
across the fi ve key dimensions is expected to increase from 3.3 at present to 3.6 by 2033, see Table
38 and Figure 64.
Table 37: Expected increase in Wangchhu water security score 2016-33
Key Dimension/ Year Wangchhu 2016 Wangchhu 2033
Rural 4.5 4.8
Economic 2.1 2.6
Urban 2.8 3.2
Environment 3.4 3.4
Resilience 3.9 4.0
Average 3.3 3.6
97
Figure 64: Expected increase in Wangchhu water security score 2016-2033
Next steps in the planning process
Review and refi nement of the overall WBMP
Guided by the RBC, the Dzognkhags of Wangchhu Basin shall review and refi ne the WBMP
particularly with respect to the value of the baseline data on the indicators, the assumptions used
in the plans, and the targets that have been set against these assumptions.
Review and refi nement of the cost estimates
Th e cost estimates in the WBMP are preliminary only. Review and refi nement of the cost estimates
shall therefore follow the review of the planning assumptions by the WBC.
Adjustment of the 11 th FYP
Th e current 11th FYP is due for mid-term adjustment in 2016. Th e WBMP can provide planning
guidelines to that eff ect, for example by putting the resources there where they are most needed
and have the most impact in terms of increasing water security.
Preparation of the GNHC guidelines for preparation of the 12 th FYP
Th e WBMP shall serve as a reference when the GNHC formulates its guidelines for preparation
of the 12th FYP.
98
Preparation of the 12 th and following FYPs
Th e WBMP shall also serve as a reference during the preparation of the 12th and following FYPs.
Iterative process
It is emphasized that the WBMP 2016 is just the starting point of the IWRM planning spiral
discussed in this report. Th is fi rst iteration has taken stock of the present state of the water
resources in terms of water availability, water demand, and impacts of climate change, population
growth, agricultural and economic development, environment and resilience. A concept has
been elaborated for water security along 57 indicators for which the baseline values have been
determined. Diff erent agencies involved in, or aff ecting water management, play a coordinated
role in achieving water security. Initial targets have been set for each of them. Th e plan shall
now be implemented and monitored along the specifi ed indicators in order to be able to take
stock of progress, re-assess conditions or priorities at appropriate time intervals, such as mid-term
adjustment of the FYP, and preparation of the next FYP. Th e IWRM spiral towards water security
is again depicted in Figure 65.
Figure 65: IWRM spiral
(from ADB/ AWDO 2013)
99
4.3. Strengthen governance and institutional capacity for
coordinated planning, implementation and monitoring of
basin management plan
Eff ective implementation of the Wangchhu basin management plan not only requires strong
coordination and cooperation between the four districts administrations and the sectors within
them. Considering that the implementation of basin management plans will ultimately contribute
to enhanced water security at the national level, it is also equally important for the WBC to
synergize and synchronize the priorities with sectoral priorities.
As presently stated in the Water Act and Regulation, the WBC is not a regulatory body. Th e Water
Act does not authorize or mandate it to promulgate standards and regulations, or even to enforce
existing regulations (the latter is the responsibility of the competent authorities). However, note
again the prerogative for NEC to expand the WBC’s functions.
Th e goals, objectives and strategies are defi ned below:
Goal: To promote eff ective and effi cient implementation of WBMP.
4.3.1. Empowerment of Wangchhu WBC for eff ectiveness
Other priority activities for the WBC include:
• Develop and update operational guidelines for the operation of WBC, including procedures
and timetable for granting water permits and procedures for WUA registration based on the
guidelines prepared by NEC.
• In accordance with the requirements outlined in the Government’s Executive Order, the
WBC shall hold at least three basin committee meetings a year to discuss among many
others, matters related to water resource management and water security in the basin.
• With assistance from RBC Secretariat, generate the water security statistics and score for the
Wangchhu basin on an annual basis.
• Adopt mechanism of learning by doing and seeking to constantly apprise the NEC on the
constraints and challenges that lie in the way of eff ective coordination and where necessary
seek to enhance its mandate and authority within the provisions of the law for eff ective
implementation of the basin plan.
4.3.2. Capacity of partners in IWRM concepts and river basin management
enhanced
Strategies:
• Train the designated member secretary of the Wangchhu RBC in agenda preparation,
100
drafting of minutes, and record keeping.
• provide orientation and training to members of RBC, relevant staff of district and Gewog
Administrations in IWRM and river basin management concepts through:
- Orientation to the IWRM principles and pillars; Bhutan Water Security Index;
hydrological and management basins of Bhutan, framework for planning,
implementation and monitoring of water security; institutional linkages between
basin level authorities and agencies (RBC, district administrations, sectors and Gewog
administrations) and national level sectoral agencies, TAC, NECS and GNHC); fl ow
of information between basin level players and national level agencies.
- Provide technical training on water balance accounting and monitoring systems (such
as WEAP).
- conduct study visits for RBC members to functional river basin committees.
- BWSI indicator monitoring at Gewog and district levels, timely reporting and
consolidation of information at basin levels.
4.3.3. Capacity of Dzongkhag, Gewog and Th romde administrations
strengthened
Within the basin, the district and Gewog administrations are crucial coordinating and monitoring
entities. Th e district administration in particular is the agency that coordinates planning as well as
implements, monitors and reports progress. Th e district planning offi cer and district environmental
offi cers play an important role in ensuring that plans for enhancing water security at the district
and Gewog levels are integrated in the fi ve year plans priorities. Further, basin wide programmes
identifi ed by the RBC must be integrated in respective district plans for adequate human and
fi nancial resources. Particularly the DzEO will play a crucial role in implementation of IWRM.
For this, capacity of Dzongkhag, Th romde and Gewog level offi cials should be enhanced in the
following areas:
• Collection of information on water resources at the Gewog and Th romde levels. Concerned
offi cials and community leaders should be trained in collecting and recording information
on various sources of water, names, discharge and abstractions.
• Incorporating RBC determined basin wide programmes and activities into Dzongkhag,
Th romde and Gewog level plans.
• Cooperating and collaborating with sectors within the Dzongkhag administration to gather
and update information on BWSI indicators.
• Collating Gewog and Th romde level data to prepare Dzongkhag level water security
information and submitting to Wangchhu Basin Committee Secretariat through the
Dzongdags.
101
It is proposed to design and implement these trainings before the end of the 11th FYP.
4.3.4. Water User Associations formally registered and monitored
Th e Gewog Administration is the level most appropriate for offi cial registration of Water User
Associations. Th e Gewog Administration, in accordance with the requirements set by the RBC:
• • Guidelines for registration of WUAs developed and approved by NEC.
• RBC and Dzongkhag/ Gewog Administrations oriented to the legal requirements and
process for registration of WUAs.
• Conduct advocacy and education for communities at the Gewog level on the importance
of WUA, its nomenclature, legal requirements and obligations, and process of registering
WUAs.
• Process the applications for registration of WUAs (including those that already exist in some
form).
• Maintain and update an inventory of WUAs, their allocated abstraction amounts, and the
purpose of abstraction.
• Monitor WUA compliance to the provisions of their 'Articles of Association' and water
permits.
102
103
5. BASIN MANAGEMENT AND
IMPLEMENTAT ION ARRANGEMENTS
Th is chapter describes the management mechanisms and institutional arrangements for
implementation of the WBMP. Th e governance mechanisms under the newly established WBC,
institutional capacity building, fi nancial aspects, and monitoring are described here.
Th e WBC is the mandated entity for coordinating implementation of WBMP. In doing so, the
committee, through the support and cooperation of the Dzongkhag and Th romde representatives
ensure that the targets identifi ed in the basin plan are deliberated and translated into Dzongkhag
and Th romde targets for integration in the Five Year Plans. Once the plans fi nd their way into
the FYPs, the WBC shall coordinate monitoring of the water related plans that are implemented
by various central agencies and local government. Progress shall be monitored in terms of the
Bhutan water security dimensions and indicators and results analysed and annually reported in
the form of Water security score for the basin. Within this overall framework of prioritizing and
integrating basin plans into existing planning system, the following implementation arrangements
are proposed.
Given that the WBC is more a coordinating than implementing body, the budgets for carrying
out the priorities will need to be secured through annual allocation by transfer of funds from
MOF to the Dzongkhags or the concerned central agency. It may be noted here that the existing
system of budget ceiling will limit the extent to which WBMP priorities can be taken up by
local government. As a result, the WBC will need to coordinate integration of the priorities and
activities into respective Dzongkhags, gewogs and central line agencies plans and programmes.
Th is however will be only be possible under two conditions:
1. Th e WBMP priorities are integrated into the fi ve year plans. Th e WBC has to ensure
that the WBMP priorities are discussed with local government and central line
agencies for integration into their FYP priorities.
2. Once the priorities are integrated into the FYPs, the concerned agencies andlocal
government will need to prepare progressive annual plans and budget. How each of
the Dzongkhags and central agencies will integrate is also something that the WBC
can coordinate.
Th e option of mobilizing resources for activities and interventions not covered by the FYPs need
to be explored. It is possible that the WBC will identify interventions to be taken up during the
FYP implementation period. Considering that the WBC is not a budget entity, its resource needs
should be mobilized through its Secretariat i.e the WRCD of NECS. Funds to be secured for the
WBC through its Secretariat include:
• Annual WBC operational funds: Th e WRCD, as the Secretariat to the WBC, shall ensure
that the funds required for WBC are integrated in the plans and budget secured on an
104
annual basis. Th is should include resources required for periodical stakeholder consultations
and updating of the basin management plan.
• Mobilization of resources for those priorities not covered under FYP and associated
annual plans or budget: Th e Secretariat shall facilitate development of project concepts,
identifi cation of funding agencies and secure required offi cial approval for mobilization of
resources and support from donors, funding agencies and partner organizations.
5.1. Basin Management Structure
Th e management of the basin rotates around the concept of coordination as contained in the terms
of reference of the WBC. Th e fi fteen member WBC comprised of the Dzongdags, Dzongkhag
Tshogdu chairpersons, and Dzongkhag environmental offi cers of the four districts of Chhukha,
Haa, Paro and Th imphu, the Th rompon and Chief Environment O ffi cer of Th imphu Th romde,
and the Chief Environment O ffi cer of WRCD, NECS as the interim member Secretary will play
an important role in coordinating the implementation of the river basin management plan. Until
further revision by the NEC, the extent of implementation of the Wangchhu basin management
plan will be governed by the mandate and authority wrested in the WBC as per the Executive
order of the Honourable Prime Minister of Bhutan and Chairman of NEC issued on 14 April
2016. Th is is prescribed by the following functions of the WBC:
1. To promote community participation in the protection, use, development, conservation,
management and control of water resources in its area of operation through education and
other relevant activities, specifi cally through:
• Formulating rules and procedures for the establishment and operation of community-level
Water Users Associations;
• Promoting and rewarding positive behavioural changes toward effi cient water use and
protection/maintenance of water sources;
• Raising community awareness on water-related issues, such as wasteful water consumption,
unhygienic sanitation, improper disposal of solid and liquid wastes, water borne diseases,
and environmental damage;
• Awareness-creation on the various technical options of effi cient water distribution and
avoidance of losses;
• Encouraging users to pay for water-related services within the scope of existing regulations;
• Promoting community adherence to directives from the RBC in resolving water-related
disputes;
• Provide regular (say annual or bi-annual) platform to inform and hear from stakeholders on
matters related to water management in the basin.
2. To prepare a River Basin Management Plan
• Assemble information required to prepare the basin plan;
• Consolidate water resources management plans prepared at the Gewog level, and ensure
105
that these are refl ected in the basin plan (i.e., checking that the plans do not draw more
water than is available);
• Provide detailed specifi cations of programs and projects incorporated in the basin plan,
including a proposed “responsibility framework” that identifi es the appropriate level of plan
implementation (i.e., by national agency or local administration);
• Ensure that the basin plan is consistent with the principles and objectives of the National
Integrated Water Resources Management Plan (NIWRMP), and that the water-related Key
Result Areas (KRAs) and Key Performance Indicators (KPIs) incorporated in the GNHC’s
medium term planning guidelines are refl ected in the basin plan.
3. To monitor and report to the Commission on the eff ectiveness of policies and action in
achieving sustainable management of water resources in its area of operation
• Review the district-level integrated water use management and safety plans prepared by
the respective Dzongkhag administrations based on the basin plan, and monitor their
implementation for reporting to the NEC;
• Review the management/safety plans prepared by the Class A Th romde Administrations
in the basin to ensure effi cient urban water supply and effl uent disposal, including urban
drainage systems, and monitor their implementation for reporting to the NEC and the
Ministry of Works and Human Settlements.
4. To collect, manage and share such data as are necessary to properly manage the basin in
coordination with the Commission
• Establish baseline data on the water security indicators for the basin, following the framework
set up by the NEC and GNHC for a national water security indicator system;
• Based on the basin plan implementation reports of the Dzongkhag and Th romde
administrations, consolidate data to periodically update the water security indicators for the
river basin, and report these to the NEC and GNHC, as well as to the basin consultative
council;
• Facilitate the exchange of data and information among agencies operating in the river basin,
and among the district and Gewog level administrations.
5. To help resolve cross-sectoral and Dzongkhag trans-boundary issues relating to water resources
in its area of operation
• Serve as forum through which issues/disputes related to water sharing and distribution
among districts and Gewogs within the basin can be discussed and resolved in an informed
and consultative manner;
• Establish procedures/rules for hearing and resolving trans-boundary water allocation issues;
• Monitor and report to the NEC on adherence of parties to agreed trans-boundary water
resources sharing.
6. To perform any such additional functions as the NEC may direct.
Th e WRCD has been designated as the interim Secretariat until further notice by the NEC.
106
Th e functions of the RBC Secretariat will be assigned in the interim period to the NECS-WRCD.
Th e secretariat shall prepare the meeting agenda for the basin committee, gather information
needed to brief the committee on issues to be tackled, document proceedings, and consolidate
the water plan for the basin (derived from the district and Gewog plans). As mandated by the
RBC chairperson, the secretariat may summon representatives from the sectoral competent
authorities to serve as resource persons. Th e latter shall give advice on technical matters, and
ensure coordination of the basin plan with sector-level plans and programs for water resources
development and management. Th e Secretariat will draw support from sectoral Competent
Authorities on technical matters.
Th e RBC secretariat shall also act as an administrative support unit to the basin committee. It will
be responsible for following through and monitoring implementation of measures authorized or
directed by the basin committee; it will also work with the district and Gewog administrations
to monitor water use/issues in the basin, including water infrastructure activities and related
programs in the basin (in coordination with sectoral competent authorities). Th e DEOs of
respective districts in the basin, coordinated by the member Secretary of the RBC, will assist in
carrying out Secretariat functions.
Th e detailed terms of reference of the River Basin Committee and its Secretariat issued by the
NEC is given in Appendix 2.
5.2. Overall framework for basin planning and
implementation
Based on the fi ve-year basin plan, each year in accordance with the local planning procedure and
timetable mandated by the GNHC, the WBC secretariat assisted by competent sectoral authorities
and DEOs will assess the current water situation and emerging issues in the basin, and brief the
basin committee on its fi ndings. Th e current situation will be compared with targets set in the
basin plan, which coincides with the national FYP, and referring to monitoring data assembled by
the basin committee secretariat.
Gewog and Dzongkhag stakeholders will deliberate water concerns through their respective
development councils, and raise basin-level issues and actions requiring inter-district coordination
or confl ict resolution to the RBC. Th e RBC, through the secretariat, will review proposed water
development activities of the district administrations and ensure that there are no confl icts in
water use with other districts. If the district plans are in harmony with the WBMP, as checked
by the basin committee, then the district plans can be submitted to GNHC following existing
planning procedures. Th e Wangchhu basin committee will liaise closely with GNHC to hold the
district administrations responsible for achieving the KRAs and KPIs for water security in their
respective jurisdictions.
107
Th e RBC will provide guidelines on how the prioritized water resources development activities
in the basin are to be diff erentiated between Gewog, Dzongkhag and central responsibilities (i.e.,
how are the priority activities to be divided between district and sub-district levels, and which ones
should be assigned to competent sector agencies/authorities).
Plans and proposed budgets/fi nancing for these activities will then be prepared at the assigned
level, after which they will be reviewed and consolidated at the basin level by the basin committee
through its secretariat—then endorsed to the GNHC. Hence the basin plan is converted into
corresponding district plans, for which the RBC will ensure that they are in harmony with the
river basin management plan.
5.3. Explore possibility of reorienting the water related
priorities of the 11th FYP to priorities of the WBMP
Considering that the WBMP is prepared midway through the 11 FYP, eff orts must be made to
orient or adjust the water related priorities for the remaining period of the plan to the priorities
set out in the basin plan.
5.4. Ensure water security priorities are integrated into the
Guidelines for preparation of FYPs.
Th is is a priority under the National IWRM Plan. However, it is equally important that guidelines
for preparation of subsequent fi ve year plans integrate water security priorities if basin plans are to
be mainstreamed and supported by the government.
Within the framework of the guidelines, the WBC shall, through respective Dzongdags,
Th rompons and members ensure that the basin committee determined basin plans and priorities
(as specifi ed in the river basin management plan) are integrated into Dzongkhag, Th romde and
Gewog level plans and priorities for integration in FYPs.
5.5. Implementation of basin plans
Once the plans are integrated in the national FYPs, the respective Dzongkhags and Th romdes are
expected to implement and monitor progress towards the targets under existing mechanisms. Th e
budgets for the planned priorities would automatically be provided through the existing planning
and budgeting processes.
On an annual basis, the targets identifi ed in the basin plan, the WBC will agree on specifi c
targets to be adopted by the respective Dzongkhags and Th romdes in the basin. Th e respective
Dzongkhags and Th romde administrations in the basins are obliged to:
108
• pursue implementation of the planned water security interventions, and
• ensure that concerned offi cials at the Gewog and Th romde levels collect, maintain and
provide information on sources of water, discharge, and abstractions and support water
balance
5.6. Monitoring and reporting progress on water security
index
Monitoring of the plans will automatically be part of the government's plan monitoring system.
However, the river basin committee has a special responsibility of coordinating the implementation
as well as monitoring the water related plans in the context of ensuring that the water resources in
the basin are optimally utilized for basic human needs and health, socio-economic advancement,
environmental sustainability and resilience to disasters. In view of this, the dzonkghags through
their Dzongdags and representative have the obligations to:
• Cooperate and collaborate with sectors within the district administration to gather and
update information on BWSI indicators.
• Collate Gewog and Th romde level data to prepare Dzongkhag level water security information
and submitting to Wangchhu Basin Committee Secretariat through the Dzongdags.
• Provide regular information on the progress to the basin committee secretariat i.e., the
WRCD, NECS that will assist the basin committee in computing the annual water security
score for the basin.
• Th e basin committee will formally submit the report on the status of water security in the
basin to the National Environment Commission. Th is is to be facilitated by the WRCD of
NECS.
5.7. Financing the operation of WBC and its basin wide
programmes and priorities
Th e operational budget for WBC will be integrated into NECS's annual budget during an interim
period. Specifi cally, the budget line should be refl ected under the WRCD as the Secretariat of the
WBC. Th e budget should include no less than three basin committee meetings, the associated
travel and logistics cost; furniture and equipment for the Secretariat; stationery and consumables;
travel and logistic support for Secretariat staff to the basin. In addition, considering that the
WRCD of NECS is understaff ed, it is necessary that a dedicated staff is either provided by the
government or resources are mobilized to recruit one staff in the interim period. Based on the
above, a sum of about Nu. 12 million i.e., about US $ 182,000 is estimated over a period of fi ve
years. Around Nu. 2.5 million is required for the fi rst year of operation considering the need for
initial establishment costs for the WBC secretariat.
Th e Chief, WRCD has the responsibility to ensure that the budgets are endorsed by the basin
109
committee and incorporated in the fi ve year plans budgets as well as in the annual budget request
to the GNHC and MoF. In the event of inability to secure government funding considering that
these activities and associated costs are not covered under the current 11 FYP, the Secretariat
should facilitate resource mobilization from relevant funding agencies and partners. From the 12
FYP onwards, the cost of operating the river basin committee and that of updating the basin plan
will need to be fi nanced directly from GNHC/MOF. For this, the WBC with support from the
Secretariat should ensure that the plans are adequately incorporated in the 12 FYP. However, in
the long term, it is expected that WBC will become more independent with potential sources of
funds coming from general taxes and water-related tariff s collected within the basin (e.g., from
water use permits), and even levies/royalties from hydropower operations.
Table 38: Estimated operational cost for Wangchhu Basin Committee for fi rst Year and for Five Years
Budget Head
Estimate (Nu.)
Unit
Cost
Qty. per year First Year Total (5 Yrs)
WBC meetings
Travel and DSA for WBC
members and Secretariat400,320 4 meetings 160,1280 800,6400
Working Lunch, Tea/ snacks
(Nu. 1000 per person)20,000 4 meetings 80,000 400,000
Support staff at Secretariat (Nu.
25,000 per month)25,000
15 months (12
months + LTC, leave
encashment, gratuity)
per year with 3%
annual increment
375,000 2,072,112
Furniture and Equipment
(computer and printer)20,000
Nu. 200,000 for fi rst
year and Nu. 50,000
for subsequent years
200,000 450,000
Travel and DSA 50,000 Lump-sum per year 50,000 250,000
Stationery/ consumables (lump-
sum)50,000 Lump-sum per year 50,000 250,000
Utilities (Nu. 5000 per month) 60,000 Nu. 5000 per month 60,000 300,000
2,416,280 11,647,326
It is expected that the WBC will identify basin wide programmes that may not be covered by
the FYP. Provisions should be made for mobilization of resources from sources outside of the
government for programmes and activities to foster water security of the basin. In this respect, the
WRCD as the Secretariat for the basin committee shall facilitate preparation of project concepts
and proposals, liaising with donors and partners, and securing GNHC approvals and support for
resource mobilization. Th e WRCD may also facilitate receipt and expenditure of funds for the
basin.
110
REFERENCES
1. EGIS and RSPN/ BhWP, 2016. Bhutan Water Security Index System: User’s Manual. A
technical report prepared under ADB technical assistance to Bhutan: Adapting to Climate Change
through Integrated Water Resource Management. Th imphu Bhutan.
2. EGIS and RSPN/ BhWP, 2016. Hydrological Modelling and Assessment for Bhutan. A
technical report prepared under ADB technical assistance to Bhutan: Adapting to Climate Change
through Integrated Water Resource Management. Th imphu Bhutan.
3. EGIS and RSPN/ BhWP, 2016. Social Aspects of Water Resource Management in
Bhutan. A technical report prepared under ADB technical assistance to Bhutan: Adapting to
Climate Change through Integrated Water Resource Management. Th imphu Bhutan.
4.EGIS and RSPN/ BhWP, 2016. Th ematic Atlas of Wangchhu Basin. A technical report
prepared under ADB technical assistance to Bhutan: Adapting to Climate Change through
Integrated Water Resource Management. Th imphu Bhutan.
5. A Review of Water Scarcity Indices and Methodologies, Amber Brown Marty D. Matlock,
University of Arkansas, Th e Sustainability Consortium, White Paper #106 | April 2011
6. Comprehensive Environmental Impact Assessment Studies for Wangchhu HEP (570 MW)
Bhutan, Wapcos, 2014, Volume 2 – Final EMP.)
7. Data collection renewable energy, JICA, 2013
8. Geo-electrical survey in Paro area, Bhutan, CEGR-Kathmandu, 2015?
9. National Integrated Water Resources Management Plan (NIWRM), Gross National
Happiness Commission, RGOB, 2016.
10. Rapid classifi cation of watersheds in Wangchhu basin, Watershed Management
Division, Department of Forests and Parks Services, MOAF, 2011
11. Water Resources Management Plan and Update of the Power System Master Plan of
Bhutan, Department of Energy, Ministry of Trade and Industries, RGOB, 2003.
http://www.nec.gov.bt
http://www.pitt.edu/~nmcq/Long_etal_2011_JOM_Bhutan_Map_1-500k.pdf
http://www.un.org/waterforlifedecade/scarcity.shtml
111
APPENDICES
Executive Order for Establishing Wangchhu Basin Committee 112
Terms of Reference for the Wangchhu Basin Committee and its Secretariat 114
Problem and Strategy Trees for Wangchhu Basin 120
Overview of Plans, Targets and Cost Estimates 133
112
APPENDIX 1
Executive Order for Establishing Wangchhu Basin Committee
113
114
APPENDIX 2
Terms of Reference for the Wangchhu Basin Committee and its Secretariat
1. THE RATIONALE
Th e boundaries of Water Resource Management (WRM) has greatly expanded over the
decades (from water to water+ecology, then to water+ecology+institutions, and now to
water+ecology+institutions+other concerns). Th ere remains a strong sense that the most logical
unit for management is the river basin, hence the need to set up basin-scale organizations for
management and coordination. Th e coordination model being developed here does not necessary
(actually, not politically realistic) aim for creating unitary basin organizations that take over the role
of water resource management from existing administrative institutions, even as eff orts continue
to streamline the patchwork of such institutions. Standalone basin organizations would also be
against the concept of cross-sectoral ‘integration’ and holistic views propagated by Integrated
Water Resource Management (IWRM).
In IWRM, the river basin is the most logical unit for coordinated management of water resources
(eg. for proper water resource accounting and allocation). A river basin organization is the most
appropriate institutional mechanism for ensuring such coordination at the basin level. Th e aim
of coordination is to ensure that policies and programs in the basin- involving multiple actors
and stakeholders - are characterized by minimal redundancy, incoherence, confl ict and gaps.
Coordinated planning and development is, thus, the underlying IWRM principle adopted in
Bhutan; and through a multi-stakeholder approach this coordination task is assigned to the River
Basin Committee (RBC) at the basin level.
Th e Water Act of Bhutan 2011, mandates National Environment Commission (NEC) to establish
RBC for each basin for the purpose of proper coordinated development, management, and
conservation of water resources. Th e Water Act 2011 and Water Regulation of Bhutan 2014,
provides broad guidelines on the composition of the RBC and their functions.
Th e terms of reference have been elaborated based on the guidelines in the Water Act and
Regulation. Th e discussion from the stakeholders recommends that the members of the RBC shall
be drawn from within the basin and shall comprise of incumbent chairperson of the Dzongkhag
Tshogdu, Dzongdags, and Th rompons of class A Th romde, Dzongkhag environment offi cers and
a representative from the National Environment Commission Secretariat (NECS). Individual
stakeholders shall be invited by the RBC during deliberation of matters relevant to the stakeholders’
specifi c concern. A representative from NECS shall serve as member-secretary.
115
Th e composition of RBC, terms of reference and its secretariat’s functions have been endorsed
by the NEC during the 41st Commission meeting held on June 25, 2015. Th e Commission also
approved to establish Wangchhu Basin Committee as fi rst RBC for piloting proper coordination
and management of water resources within the Basin.
2. COMPOSITION OF WANGCHHU BASIN COMMITTEE
(WBC)
As approved by the NEC during its 41st Commission meeting held on 25 June 2015, the WBC
shall comprise the following members:
1. DashoDzongda, Dzongkhag Administration, Haa, Chairman
2. DashoDzongda, Dzongkhag Administration, Paro, member
3. DashoDzongda, Dzongkhag Administration, Th imphu, member
4. DashoDzongda, Dzongkhag Administration, Chhukha, member
5. Chairman, Dzongkhag Tshogdu, Haa, member
6. Chairman, Dzongkhag Tshogdu, Paro, member
7. Chairman, Dzongkhag Tshogdu, Th imphu, member
8. Chairman, Dzongkhag Tshogdu, Chhukha, member
9. Dasho Th rompon, Th imphu Th romde, member
10. Environment O ffi cer, Dzongkhag Administration, Haa, member
11. Environment O ffi cer, Dzongkhag Administration, Paro, member
12. Environment O ffi cer, Dzongkhag Administration, Th imphu, member
13. Environment O ffi cer, Dzongkhag Administration, Chhukha, member
14. Environment O ffi cer, Th imphu Th romde, member
116
15. Chief Environment O ffi cer, Water Resource Coordination Division, NECS, member
secretary.
Th e Commission appoints Dasho Dzongdag, Haa as the fi rst Chairperson of the WBC, however,
the position of WBC chairperson shall be rotated annually among the Dzongdags of the districts
covered by the basin, and Chief Environment O ffi cer of Water Resource Coordination Division
shall serve as member secretary. Th e WBC shall meet at least once every four months and the
quorum of the meeting shall be two third. Th e WBC is expected to take a consensus approach in
adopting policy positions and making decisions.
3. FUNCTIONS OF THE WANGCHHU BASIN COMMITTEE
Th e functions of the WBC are as follows:
1. Promote community participation in the protection, use, development, conservation,
management and control of water resources in its area of operation through education and
other relevant activities, specifi cally through:
• Formulating rules and procedures for the establishment and operation of community-level
Water Users Associations;
• Promoting and rewarding positive behavioural changes toward effi cient water use and
protection/maintenance of water sources;
• Raising community awareness on water-related issues, such as wasteful water consumption,
unhygienic sanitation, improper disposal of solid and liquid wastes, water borne diseases,
and environmental damage;
• Awareness-creation on the various technical options of effi cient water distribution and
avoidance of losses;
• Encouraging users to pay for water-related services within the scope of existing regulations;
• Promoting community adherence to directives from the WBC in resolving water-related
disputes;
• Provide regular (say annual or bi-annual) platform to inform and hear from stakeholders on
matters related to water management in the basin.
2. Prepare a River Basin Management Plan
• Assemble information required to prepare the basin plan;
• Consolidate water resources management plans prepared at the Gewog level, and ensure
that these are refl ected in the basin plan (i.e., checking that the plans do not draw more
water than is available);
• Provide detailed specifi cations of programs and projects incorporated in the basin plan,
including a proposed “responsibility framework” that identifi es the appropriate level of plan
117
implementation (i.e., by national agency or local administration);
• Ensure that the basin plan is consistent with the principles and objectives of the National
Integrated Water Resources Management Plan (NIWRMP), and that the water-related Key
Result Areas (KRAs) and Key Performance Indicators (KPIs) incorporated in the GNHC’s
medium term planning guidelines are refl ected in the basin plan;
3. Monitor and report to the Commission on the eff ectiveness of policies and action in achieving
sustainable management of water resources in its area of operation
• Review the district-level integrated water use management and safety plans prepared by
the respective Dzongkhag administrations based on the basin plan, and monitor their
implementation for reporting to the NEC;
• Review the management/safety plans prepared by the Class A Th romde Administrations
in the basin to ensure effi cient urban water supply and effl uent disposal, including urban
drainage systems, and monitor their implementation for reporting to the NEC and the
Ministry of Works and Human Settlements;
4. Collect, manage and share such data as are necessary to properly manage the basin in
coordination with the Commission
• Establish baseline data on the water security indicators for the basin, following the framework
set up by the NEC and GNHC for a national water security indicator system;
• Based on the basin plan implementation reports of the Dzongkhag and Th romde
administrations, consolidate data to periodically update the water security indicators for the
river basin, and report these to the NEC and GNHC, as well as to the basin consultative
council;
• Facilitate the exchange of data and information among agencies operating in the river basin,
and among the district and Gewog level administrations.
5. Help resolve cross-sectoral and Dzongkhag trans-boundary issues relating to water resources
in its area of operation
• Serve as forum through which issues/disputes related to water sharing and distribution
among districts and Gewogs within the basin can be discussed and resolved in an informed
and consultative manner;
• Establish procedures/rules for hearing and resolving trans-boundary water allocation issues;
• Monitor and report to the NEC on adherence of parties to agreed trans-boundary water
resources sharing.
6. Perform any such additional functions as the NEC may direct.
118
4. FUNCTIONS OF WBC SECRETARIAT
Th e functions of the WBC Secretariat are assigned in the interim period to the Water Resource
Coordination Division in NECS. Th e secretariat shall prepare the meeting agenda for the basin
committee, gather information needed to brief the committee on issues to be tackled, document
proceedings, and consolidate the water plan for the basin (derived from the district and Gewog
plans). As mandated by the WBC chairperson, the secretariat may summon representatives from
the sectoral competent authorities to serve as resource persons. Th e latter shall give advice on
technical matters, and ensure coordination of the basin plan with sector-level plans and programs
for water resources development and management. Th e Secretariat shall draw support from
sectoral Competent Authorities on technical matters.
Th e secretariat shall also act as an administrative support unit to the WBC. It is responsible
for following through and monitoring implementation of measures authorized or directed by
the basin committee; work with the district and Gewog administrations to monitor water use/
issues in the basin, including water infrastructure activities and related programs in the basin
(in coordination with sectoral competent authorities). Th e Dzongkhag Environment O ffi cers of
respective Dzongkhags in the basin, coordinated by the member Secretary of the WBC, shall assist
in carrying out secretariat functions.
Specifi cally, the functions of the WBC secretariat are as follows:
8. Assist the Chairperson of the WBC in preparation of annotated agenda of WBC
meetings; draft minutes of the meetings and maintain records of meetings;
1. Prepare and propose annual operational budget for WBC, seek WBC approval and
submit to WRCD, NECS for timely inclusion in the annual budget proposal;
2. Assist the WBC in applying the water security performance indicator system for the
basin;
3. Coordinate with the concerned Dzongkhag administrations and national sectoral
agencies to ensure that basin plan items are being implemented;
4. Advise the WBC in evaluating impacts of development plans or actions proposed by
local administrations and national sectoral agencies operating in the basin;
5. Assist the WBC in preparing water security and water-related reports to the NEC
and GNHC;
6. Facilitate conveyance of advisories or directives of the WBC to the district and
Gewog administrations, as well as collate responses;
7. In coordination with the NECS, maintain a water database for the basin, and
coordinate the updating of information collected by local administrations and
sectoral agencies operating in the basin;
8. Establish a “knowledge hub” for matters pertaining to basin water resources
management and coordination;
119
9. Document successful IWRM interventions in the basin for reporting to the WBC, as
well as dissemination to national policy-makers, stakeholders and the media;
10. Facilitate networking and partnerships with NGOs, communities, state enterprises
and private organizations operating in the basin;
11. Identify needs and facilitate training and capacity building (with assistance from the
NECS) among local administration staff on integrated water resources planning and
management;
12. Coordinate with the Dzongkhag and Gewog administrations to collect, compile,
check, sort and analyse data about the status of water resources in the basin, and the
on-going implementation of basin plans;
13. Prepare necessary M&E forms and formats to collect data and information on the
status of water resources and water security in the basin;
14. Monitor performance of local administrations in implementing their assigned roles
under the river basin plan, and report to the WBC.
As noted above, the WBC shall convene a consultative assembly to deliberate on the basin plan
and, on need basis consult stakeholders on specifi c water management issues that arise and that
have basin-wide implications.
120
APPENDIX 3
Problem and Strategy Trees for Wangchhu Basin
As mentioned in Section 3.4 the problem and strategy trees against the fi ve Key Dimensions of
water security, and for Th romdes as a separate group are given below.
Th e diagrams are read as follows. In the problem tree, the central box contains the core statement
related to the concerned Key Dimension. Th e boxes below analyse the causes of the central
problem down to three levels. Th e boxes above the central statement mention the impact of the
central statement. Hence, the total diagram provides a logical cause-eff ect relationship.
Th e strategy tree is organised in a similar fashion. Interventions on the ground lead to Key Result
Areas and then to the goal formulated in the central box, with their specifi c objectives/ impacts
on top of the diagram.
121
Incre
asin
g th
reat to
drin
kin
g w
ate
r
su
pp
ly in
rura
l are
as, c
om
bin
ed
with
po
or
san
itatio
n
Incre
ased
morb
idity
and
morta
lity ra
te
Dis
pute
s o
ver
wate
r sourc
es a
nd
access
Incre
ased h
ealth
care
cost
Loss o
f socia
l
cohesio
n
Incre
ased d
rudgery
am
ong w
om
en a
nd
child
ren in
colle
ctin
g
wate
r
Loss o
f
opportu
nitie
s
Degra
datio
n o
f
wate
r sourc
es
(quantity
and
quality
)
Inadequate
access to
alte
rnativ
e w
ate
r
sourc
es
Managem
ent
weaknesses
Advers
e c
limate
change
Excessiv
e
extra
ctio
n o
f
wate
rshed
resourc
es
Land
fragm
enta
tion
into
incom
patib
le
uses
Over-g
razin
g in
wate
r catc
hm
ent
are
as
Econom
ically
-
driv
en a
ctiv
ities
Resourc
e
constra
ints
Lack te
chnolo
gy
and in
fra to
tap
alte
rnativ
e
wate
r sourc
es
Excessiv
e
wate
r losses
Poor
imple
menta
tion
of g
overn
ment
polic
ies
Lack o
f public
aw
are
ness
Inadequate
institu
tional
capacity
Poorly
desig
ned w
ate
r
conveyance
syste
ms
Poor
main
tenance
Seasonal w
ate
r
shorta
ges
Degra
datio
n o
f
wate
r sourc
es
Pro
blem
tree for K
ey D
imen
sion
1: R
ural h
ou
seho
ld w
ater security, san
itation
and
hy
gien
e
Eff
ects
Pro
blem
statemen
t
Cau
ses
Ro
ot cau
ses
122
Reduced h
ealth
care
cost
Reduced
morb
idity a
nd
mort
alit
y r
ate
Enhanced w
ate
r
security
Impro
ved q
uantity
and q
ualit
y o
f w
ate
r
Impro
ved c
om
munity
vitalit
y
Enhanced s
ocia
l
harm
ony in the
com
munity
Min
imiz
ed w
ate
r
rela
ted d
ispute
s
Incre
ased incom
e
and im
pro
ved liv
ing
sta
ndard
s
Incre
ased tim
e u
sed
for
gain
ful econom
ic
activitie
s
Decre
ased d
rudgery
am
ong w
om
en a
nd
child
ren
Impro
ve c
onditio
n o
f
wate
r sourc
es a
nd
catc
hm
ents
Min
imiz
e e
xtr
action
and fra
gm
enta
tion
of re
sourc
es in
wate
r catc
hm
ents
Str
ictly
imple
ment ru
les
under
the n
on
-
tim
ber
fore
st
pro
ducts
pro
gra
m (
NT
FP
)
Initia
te m
ass
affore
sta
tion a
nd
refo
resta
tion
pro
gra
m
Reduce
impact of
over
gra
zin
g
Rais
e
com
munity
aw
are
ness
Impro
ve
livesto
ck
managem
ent
pra
ctices
Impro
ve a
ccess to
altern
ative d
rinkin
g
wate
r sourc
es
Pro
vid
e a
dequate
infr
astr
uctu
re a
nd
appro
priate
technolo
gy
Enfo
rced s
trin
gent
imple
menta
tion o
f
polic
ies a
nd
regula
tions
Tra
in local
govern
ment
offic
ials
Rais
e p
ublic
aw
are
ness
Form
wate
r user
associa
tions in a
ll
com
munitie
s
Impro
ve
managem
ent of
wate
r supply
Encoura
ge
com
munitie
s to
uphold
local
belie
fs in
conserv
ing
environm
ent
Reduce s
easonal
wate
r short
ages
Build
sm
all
reserv
oirs a
nd
check d
am
s
Intr
oduce r
ain
wate
r
harv
esting
Imp
rove a
nd
pro
tect
dri
nkin
g
wate
r su
pp
ly a
nd
san
itati
on
Reduce w
ate
r
losses
Impro
ve k
now
how
and technolo
gy to
access w
ate
r
sourc
es
Impro
ve d
esig
n
of w
ate
r
conveyance
syste
ms
Impro
ve w
ate
r
supply
syste
m
main
tenance
Rais
e
aw
are
ness o
f
clim
ate
change
impacts
Str
ateg
y t
ree
for
Key
Dim
ensi
on
1:
Ru
ral
ho
use
ho
ld w
ater
su
pp
ly,
san
itat
ion
an
d h
yg
ien
e
Imp
acts
Key
Res
ult
Ind
icat
or
Stra
tegi
es
Act
ion
s
123
Ec
on
om
ic v
alu
e/b
en
efits
of B
hu
tan
’s
wa
ter re
so
urc
es
is n
ot m
ax
imiz
ed
Ag
ricu
ltura
l
pro
du
ctiv
ity n
ot
ma
xim
ize
d
Fo
od
inse
cu
rity
Po
ten
tial g
row
th in
go
ve
rnm
en
t reve
nu
e
an
d n
atio
na
l GD
P n
ot
rea
lize
d
Po
ten
tial fo
r ind
ustria
l
de
ve
lop
me
nt n
ot
ma
xim
ize
d
Dim
inis
hin
g a
va
ilab
ility a
nd
diffic
ulty
of a
cce
ss to
wa
ter fo
r
ag
ricu
lture
Se
aso
na
l wa
ter
sh
orta
ge
s
Dry
ing
up
of
exis
ting
wa
ter
so
urc
es
Wa
ters
he
d
de
gra
da
tion
co
mb
ine
d
with
Incre
ase
d
de
ma
nd
for w
ate
r
La
ck o
f ad
eq
ua
te
infra
stru
ctu
re to
tap
exis
ting
wa
ter s
ou
rce
s
in d
ee
p v
alle
ys
La
ck o
f ap
pro
pria
e
an
d a
fford
ab
le
tech
no
log
y
Clim
ate
ch
an
ge
(rain
fall v
aria
bility
an
d e
xtre
me
s)
Ina
bility
to g
en
era
te
hyd
rop
ow
er a
t full
ca
pa
city
La
ck o
f fun
din
g fo
r
inve
stm
en
ts
La
ck/a
bse
nce
of
rese
rvo
irs (to
sto
re
wa
ter fo
r lea
n flo
w
pe
riod
s)
La
ck fin
an
cin
g a
nd
an
d te
ch
no
log
y
Incre
ase
d
fluctu
atio
n in
vo
lum
e o
f wa
ter
Insu
fficie
nt u
tiliza
tion
of w
ate
r
reso
urc
es fo
r ind
ustria
l
de
ve
lop
me
nt p
urp
ose
s
La
ck o
f su
itab
le
tech
no
log
ies a
nd
su
pp
ortin
g
infra
stru
ctu
re
Po
ten
tial re
ve
nu
es
from
wa
ter-b
ase
d
tou
rism
no
t
ma
xim
ize
d
Insu
fficie
nt u
se
of
wa
ter re
so
urc
es
for to
uris
m
activ
ities
Ina
de
qu
ate
rule
s
an
d e
nfo
rce
me
nt
of e
nviro
nm
en
tal
flow
s
Pro
blem
tree for K
ey D
imen
sion
2: E
con
om
ic water secu
rity
124
Maxim
ize e
co
no
mic
valu
e/b
en
efi
ts o
f
Wan
gC
hu
basin
wate
r re
so
urc
es
Agricultura
l
pro
ductivity is
maxim
ized
Food s
ecurity
is
enhanced
Pote
ntial gro
wth
in
govern
ment re
venue
and n
ational G
DP
is
realiz
ed
Pote
ntial fo
r in
dustr
ial
develo
pm
ent is
maxim
ized a
nd
susta
ined
Incre
ase d
ependable
availa
bili
ty
and a
ccess to w
ate
r fo
r agriculture
Addre
ss c
urr
ent
pro
ble
m o
f
seasonal w
ate
r
short
ages
Incre
ase r
echarg
e
of w
ate
r sourc
es
Wate
rshed
pro
tection
measure
s
Pro
vid
e a
dequate
infr
astr
uctu
re to tap
exis
ting w
ate
r sourc
es
in d
eep v
alle
ys
Apply
appro
priae
and a
fford
able
technolo
gy
Assess c
limate
change e
ffects
(rain
fall
variabili
ty
and e
xtr
em
es)
Enhance a
bili
ty to
genera
te
hydro
pow
er
at fu
ll
capacity
Adequate
fundin
g
for
investm
ents
Constr
uct
reserv
oirs (
to s
tore
wate
r fo
r le
an flo
w
periods)
Access fin
ancin
g
and a
nd
technolo
gy
Anticip
ate
and
manage
fluctu
ation in
volu
me o
f w
ate
r
Incre
ase the u
tiliz
ation o
f
wate
r re
sourc
es for
industr
ial
develo
pm
ent purp
oses
Pro
vid
e s
uitable
technolo
gie
s a
nd
support
ing
infr
astr
uctu
re
Pote
ntial re
venues fro
m
wate
r-based tourism
is
maxim
ized a
nd s
usta
ined
Enhance u
se o
f w
ate
r
resourc
es for
tourism
attra
ction a
nd w
ate
r-based
activitie
s
Dete
rmin
e a
nd
enfo
rce m
inim
um
environm
enta
l
flow
s
Constr
uct
reserv
oirs
Conduct re
searc
h
and testing/
develo
pm
ent
Tap into
inte
rnational
clim
ate
funds
Technolo
gy
researc
h a
nd
monitoring
Impro
ve w
ate
r
resourc
e
info
rmation
syste
ms
Str
ateg
y t
ree
for
Key
Dim
ensi
on
2:
Eco
no
mic
wat
er s
ecu
rity
125
Ineffic
ien
t urb
an
wate
r su
pp
ly s
yste
m a
nd
incre
asin
g
thre
at to
qu
ality
of u
rban
wate
rways
Rapid
incre
ase
in u
rban
popula
tion
Incre
ased
mig
ratio
n fro
m
rura
l are
as
Poor a
ccess to
alte
rnativ
e
sourc
es o
f wate
r
Dete
riora
ting
wate
r quality
in
urb
an
wate
rways
Hig
h ra
tes o
f
loss in
wate
r
supply
syste
m
Illegal ta
ppin
g o
f
wate
r pip
es
Unequal w
ate
r
dis
tributio
n
Mis
use o
f
auth
ority
Inadequate
imple
menta
tion o
f
sew
era
ge p
lan
Lack o
f
resourc
es a
nd
technolo
gy
Insuffic
ient
wate
r sto
rage
facilitie
s
Conta
min
atio
n
by s
olid
waste
Conta
min
atio
n
by in
dustria
l
efflu
ents
Lack o
f
adequate
sew
era
ge
covera
ge
Weaknesses in
urb
an p
lannin
g
Poor
constru
ctio
n a
nd
main
tenance
sta
ndard
s
Lack o
f
infra
stru
ctu
re
to ta
p
alte
rnativ
e
wate
r sourc
es
Lack o
f
managem
ent
coord
inatio
n
Incre
asin
g
dem
and fo
r
limite
d w
ate
r
Incre
ased
morb
idity
and
morta
lity ra
te
Dis
pute
s o
ver
wate
r sourc
es a
nd
access
Incre
ased h
ealth
care
cost
Loss o
f socia
l
cohesio
n
Pro
blem
tree for K
ey D
imen
sion
3: U
rban
water secu
rity, sanitatio
n an
d d
rainag
e
126
Imp
roved
eff
icie
ncy o
f u
rban
wate
r su
pp
ly s
yste
m
an
d p
rote
cti
on
of
qu
ality
of
urb
an
wate
rways
Wate
r
mete
ring a
nd
pricin
g
initia
tives
Incre
ase w
ate
r
supply
Pre
vent w
ate
r qualit
y
degra
dation in u
rban
wate
rways
Reduce w
ate
r
losses fro
m u
rban
wate
r supply
syste
m
Contr
ol ill
egal
tappin
g o
f w
ate
r
pip
es
Pro
mote
equitable
wate
r
dis
trib
ution
Monitor
wate
r
dis
trib
ution s
yste
m to
avoid
ille
gal w
ate
r
tappin
g
Imple
ment
sew
era
ge p
lan
pro
perly
Pro
vid
e
resourc
es a
nd
appro
priate
technolo
gy
Pro
vid
e w
ate
r
sto
rage
facili
ties
Impro
ve
managem
ent of
solid
waste
and
dis
posal
Pre
vent
conta
min
ation
by industr
ial
efflu
ents
Incre
ase
sew
era
ge
covera
ge
Impro
ve u
rban
pla
nnin
g
Impro
ve
constr
uction a
nd
main
tenance
sta
ndard
s
Tap
altern
ative
wate
r sourc
es
Str
ength
en
coord
ination a
nd
hum
an r
esourc
es
Manage
incre
asin
g
dem
and for
wate
r
Reduced m
orb
idity
and m
ort
alit
y r
ate
Min
imiz
ed
dis
pute
s o
ver
wate
r sourc
es a
nd
access
Reduced h
ealth
care
cost
Main
tenance o
f
socia
l cohesio
n
Encoura
ge
and e
nable
wate
r
harv
esting
Rais
e p
ublic
aw
are
ness
Impro
ve
monitoring
Str
ateg
y t
ree
for
Key
Dim
ensi
on
3:
Urb
an w
ater
sec
uri
ty,
san
itat
ion
an
d d
rain
age
127
Ina
de
qu
ate
an
d in
effic
ien
t urb
an
wa
ter s
up
ply
sy
ste
ms
Un
ne
ce
ssa
ry
wa
ter lo
sse
s
Artific
ial s
ho
rtag
e
of w
ate
r
Lo
ss o
f eco
no
mic
op
po
rtun
ities
Un
hyg
ien
ic liv
ing
co
nd
ition
s
Ou
tbre
ak o
f
dis
ea
se
s
Po
or c
on
ditio
n o
f
pip
e w
ate
r
dis
tribu
tion
Hig
h le
aka
ge
(15
-20
%)
Old
ne
two
rk o
f
pip
es
(25
-30
yrs
old
)
Co
nta
min
atio
n o
f
lea
ky p
ipe
s fro
m
su
rface
wa
ter
Ina
de
qu
ate
dra
ina
ge
syste
m
Urb
an
floo
din
g
Lo
w c
arry
ing
ca
pa
city
Ina
de
qu
ate
co
ve
rag
e a
nd
po
or
co
nd
ition
of
se
we
rag
e s
yste
m
Ove
rflow
of
efflu
en
t from
se
we
r line
s
Blo
cka
ge
of
se
we
rag
e lin
es
Lim
ited
wa
ter a
t
so
urc
e
Incre
ase
in
de
ma
nd
Ra
pid
urb
an
iza
tion
Po
or w
ate
r qu
ality
at s
ou
rce
Clo
gg
ing
of d
rain
sP
oo
r ma
inte
na
nce
Po
or s
olid
wa
ste
ma
na
ge
me
nt
Pro
blem
tree for K
ey D
imen
sion
3: Th
rom
de w
ater security
128
Impro
ve c
onditio
n o
f
the p
ipe w
ate
r
supply
netw
ork
Reduce incid
ence
of urb
an flo
odin
g
Impro
ve the
sew
era
ge a
nd
sanitation s
yste
m
Pro
tect th
e w
ate
r
at sourc
e
Develo
p w
ate
r
supply
maste
r
Pla
n
Tim
ely
inspection
of w
ate
r supply
line
Purc
hase o
f
leakage d
ete
cto
r
equip
ment
Routine
Main
tenance
Repla
cem
ent of
old
pip
es
Tre
atm
ent and
chlo
rination
Fre
quent
inspection o
n
dra
inage c
onditio
n
Routine
main
tenance
Develo
p U
rban
dra
inage m
aste
r
Pla
n
Incre
ase tim
e
period o
f daily
wate
r supply
Tim
ely
inspection
and m
ain
tenance
of sew
er
line
Pro
tect w
ate
r
catc
hm
ents
Explo
re
additio
nal w
ate
r
sourc
es
Pro
vid
e a
deq
uate
an
d e
ffic
ien
t u
rban
wate
r su
pp
ly
syste
ms
Avoid
unnecessary
wate
r lo
sses
Avoid
art
ific
ial
short
age o
f w
ate
r
Enhance
econom
ic
opport
unitie
s
Enhanced
hygie
nic
liv
ing
conditio
ns
Outb
reak o
f
dis
eases a
re
pre
vente
d
Str
ateg
y t
ree
for
Key
Dim
ensi
on
3:
Thro
md
e w
ater
sec
uri
ty
129
Ne
ga
tive
imp
acts
of d
eve
lop
me
nt
activ
ities in
wa
ters
he
ds
Acce
lera
ted
infra
stru
ctu
re
de
ve
lop
me
nt
Exp
an
din
g
ag
ricu
ltura
l
activ
ities
Incre
asin
g
ind
ustria
l an
d
min
ing
activ
ities
Incre
asin
g ra
te o
f
fore
st lo
ss a
nd
de
gra
da
tion
Ne
ga
tive
effe
cts
of
tem
pe
ratu
re
incre
ase
an
d
erra
tic ra
infa
ll
Wa
ters
he
d d
eg
rad
atio
n
Dry
ing
up
of w
ate
r
so
urc
es
Incre
ase
d
incid
en
ce
of
wa
ter-re
late
d
co
nflic
ts
Mo
re la
nd
s
follo
we
d o
r
ab
an
do
ne
d Incre
ase
in h
ea
lth
issu
es
Fo
od
sca
rcity
Incre
ase
in
po
ve
rty
Co
mm
un
ity
dis
ha
rmo
ny
Co
nstru
ctio
n o
f
roa
ds
(no
t follo
win
g
EF
RC
me
tho
ds)
Va
riou
s a
d-h
oc o
r
un
pla
nn
ed
wa
ters
he
d
dis
turb
an
ce
s
Incre
ase
d u
se
of
fertiliz
ers
an
d
pe
stic
ide
s
De
gra
da
tion
of
ag
ricu
ltura
l lan
ds
La
nd
co
nve
rsio
n
activ
ities
Ove
r gra
zin
gIlle
ga
l log
gin
g
activ
ities
Incre
ase
d
extra
ctio
n o
f
fore
st p
rod
ucts
Incre
ase
d
occu
rren
ce
s o
f
lan
dslid
es
Glo
ba
l clim
ate
ch
an
ge
Incre
asin
g
nu
mb
er o
f sm
all
en
terp
rise
s a
nd
co
ttag
e
ind
ustrie
s
Incre
ase
d
occu
rren
ce
of fire
s
Po
or w
ate
r qu
ality
an
d h
igh
se
dim
en
t
loa
d
Ad
ve
rse
effe
cts
on
irriga
tion
an
d
hyd
rop
ow
er
facilitie
s
Ris
ing
co
st o
f
wa
ter tre
atm
en
t
Incre
ase
in p
ub
lic
sa
fety
ha
za
rds
Pro
blem
tree for K
ey D
imen
sion
4: E
nv
iron
men
tal water secu
rity
130
Pre
vent negative im
pacts
of develo
pm
ent activitie
s in
wate
rsheds
Pla
n a
nd m
anage
infr
astr
uctu
re
develo
pm
ent pro
perly
Pla
n a
nd m
anage
agricultura
l develo
pm
ent
pro
perly
Pla
n a
nd m
anage
industr
ial and m
inin
g
activitie
s p
roperly
Reduce a
nd
rem
edia
te fore
st lo
ss
and d
egra
dation
Adapt to
effects
of
tem
pera
ture
incre
ase
and e
rratic r
ain
fall
Pre
ve
nt
furt
he
r d
eg
rad
ati
on
of
wa
ters
he
ds, a
nd
rem
ed
iate
ex
isti
ng
da
ma
ge
Pre
vent dry
ing u
p o
f
wate
r sourc
es
Reduced incid
ence
of w
ate
r-re
late
d
conflic
ts
Pre
vent m
ore
lands
from
bein
g follo
wed
or
abandonedA
void
negative
health im
pacts
and issues
Pre
vent fu
ture
food
scarc
ity
Reduce p
overt
y
incid
ence
Main
tenance o
f
Com
munity h
arm
ony
Constr
uct ro
ads
follo
win
g E
FR
C
meth
ods a
nd
safe
guard
s
Avoid
ad
-hoc o
r
unpla
nned
dis
turb
ances in
wate
r sourc
e
are
as
Rais
e a
ware
ness
on u
se o
f fe
rtili
zers
and p
esticid
es,
encoura
ge o
rganic
farm
ing
Pro
mote
susta
inable
agricultura
l la
nd
managem
ent
Dis
coura
ge land
convers
ion in
critical are
as
Pro
mote
pastu
re
develo
pm
ent to
pre
vent over
gra
zin
g
Sto
p ille
gal
loggin
g a
ctivitie
s
Manage
extr
action o
f
fore
st pro
ducts
Reduce o
ccurr
ences
of la
ndslid
es
Monitor
changes d
ue
to c
limate
change
Monitor
and
regula
te s
mall
ente
rprises a
nd
cottage industr
ies
Reduce o
ccurr
ence
of fire
s
Impro
ve w
ate
r qualit
y
and r
educe s
edim
ent
loads
Reduced e
ffects
on
irrigation a
nd
hydro
pow
er
facili
ties
Reduced c
ost of
wate
r tr
eatm
ent
Reduce p
ublic
safe
ty
hazard
s
Identify
and
decla
re c
ritical
are
as for
managem
ent
Pro
per
pla
nnin
g
and s
ite s
ele
ction
Enfo
rce
com
plia
nce to
pla
ns
Pro
per
pla
nnin
g
and s
ite
sele
ction, avoid
critical are
as
Str
ict m
onitoring
and e
nfo
rcem
ent
of environm
enta
l
law
s
Monitor
and
enfo
rce
environm
enta
l
rule
s a
nd
regula
tions
Set up a
dequate
netw
ork
of w
eath
er
monitoring s
tations
Str
ateg
y t
ree
for
Key
Dim
ensi
on
4:
En
vir
on
men
tal
wat
er s
ecu
rity
131
Ec
on
om
ic v
alu
e/b
en
efits
of B
hu
tan
’s
wa
ter re
so
urc
es
is n
ot m
ax
imiz
ed
Ag
ricu
ltura
l
pro
du
ctiv
ity n
ot
ma
xim
ize
d
Fo
od
inse
cu
rity
Po
ten
tial g
row
th in
go
ve
rnm
en
t reve
nu
e
an
d n
atio
na
l GD
P n
ot
rea
lize
d
Po
ten
tial fo
r ind
ustria
l
de
ve
lop
me
nt n
ot
ma
xim
ize
d
Dim
inis
hin
g a
va
ilab
ility a
nd
diffic
ulty
of a
cce
ss to
wa
ter fo
r
ag
ricu
lture
Se
aso
na
l wa
ter
sh
orta
ge
s
Dry
ing
up
of
exis
ting
wa
ter
so
urc
es
Wa
ters
he
d
de
gra
da
tion
co
mb
ine
d
with
Incre
ase
d
de
ma
nd
for w
ate
r
La
ck o
f ad
eq
ua
te
infra
stru
ctu
re to
tap
exis
ting
wa
ter s
ou
rce
s
in d
ee
p v
alle
ys
La
ck o
f ap
pro
pria
e
an
d a
fford
ab
le
tech
no
log
y
Clim
ate
ch
an
ge
(rain
fall v
aria
bility
an
d e
xtre
me
s)
Ina
bility
to g
en
era
te
hyd
rop
ow
er a
t full
ca
pa
city
La
ck o
f fun
din
g fo
r
inve
stm
en
ts
La
ck/a
bse
nce
of
rese
rvo
irs (to
sto
re
wa
ter fo
r lea
n flo
w
pe
riod
s)
La
ck fin
an
cin
g a
nd
an
d te
ch
no
log
y
Incre
ase
d
fluctu
atio
n in
vo
lum
e o
f wa
ter
Insu
fficie
nt u
tiliza
tion
of w
ate
r
reso
urc
es fo
r ind
ustria
l
de
ve
lop
me
nt p
urp
ose
s
La
ck o
f su
itab
le
tech
no
log
ies a
nd
su
pp
ortin
g
infra
stru
ctu
re
Po
ten
tial re
ve
nu
es
from
wa
ter-b
ase
d
tou
rism
no
t
ma
xim
ize
d
Insu
fficie
nt u
se
of
wa
ter re
so
urc
es
for to
uris
m
activ
ities
Ina
de
qu
ate
rule
s
an
d e
nfo
rce
me
nt
of e
nviro
nm
en
tal
flow
s
Pro
blem
tree Key
Dim
ensio
n 5
: Resilien
ce to clim
ate chan
ge an
d w
ater-related d
isasters
132
Red
uce s
ocio
-eco
no
mic
lo
ss d
ue t
o w
ate
r
rela
ted
natu
ral
dis
aste
rs, p
art
icu
larl
y f
loo
din
g
an
d l
an
dsli
des
Imp
lem
en
t flo
od
an
d d
isa
ste
r
mitig
atio
n
me
asu
res
Co
nd
uct
flo
od
mo
de
ling
, h
aza
rd
ma
pp
ing
an
d
asse
ssm
en
t
Ma
instr
ea
m
dis
aste
r re
sili
en
ce
in d
eve
lop
me
nt
pla
nn
ing
Pro
pe
r u
rba
n
pla
nn
ing
Ca
pa
city
de
ve
lop
me
nt
an
d
ad
eq
ua
te b
ud
ge
t
allo
ca
tio
n
Imp
rove
pla
nn
ing
an
d
de
ve
lop
me
nt
of
infr
astr
uctu
re a
nd
min
ing
activitie
s
Use
of
EF
RC
me
tho
ds in
ro
ad
co
nstr
uctio
n
Str
en
gth
en
reg
ula
tio
ns a
nd
mo
nito
rin
g o
f
min
ing
activitie
s
Su
sta
ina
ble
la
nd
ma
na
ge
me
nt
En
forc
e h
aza
rd
ma
pp
ing
an
d r
em
ed
ial
me
asu
res in
la
nd
slid
e
pro
ne
are
as
Esta
blis
h r
elia
ble
we
ath
er
fore
ca
stin
g a
nd
wa
rnin
g
Re
du
ce
in
cid
en
ce
of
fo
rest
fire
s
Te
rra
cin
g
an
d s
lop
e
sta
bili
ty
me
asu
res
Re
fore
st
de
nu
de
d
are
as
Bio
-
en
gin
ee
rin
g
wo
rks
Re
du
ce
ove
r-g
razin
g
Esta
blis
h n
etw
ork
of
we
ath
er
mo
nito
rin
g
sta
tio
ns
Esta
blis
h in
form
atio
n
ma
na
ge
me
nt
an
d d
ata
sh
arin
g s
yste
ms
Fire
lin
e
co
nstr
uctio
n
Co
mm
un
ity
org
an
iza
tio
n
an
d
co
ord
ina
tio
n
Co
nd
uct
aw
are
ne
ss
pro
gra
ms a
nd
tra
inin
g
Avo
id
dis
pla
ce
me
nt
of
co
mm
un
itie
s
Avo
id lo
sse
s o
r
da
ma
ge
to
infr
astr
uctu
re
Avo
id r
ed
uctio
n o
f
hyd
rop
ow
er
ge
ne
ratio
n c
ap
acity
Pre
ve
nt
ad
ve
rse
imp
act
on
bio
-
div
ers
ity
Pre
ve
nt
da
ma
ge
to
ag
ricu
ltu
ral la
nd
s
an
d lo
ss o
f
live
sto
ck
Str
ateg
y t
ree
for
Key
Dim
ensi
on
5:
Res
ilie
nce
to
cli
mat
e ch
ang
e an
d w
ater
-rel
ated
dis
aste
r
133
AP
PE
ND
IX 4
Overview
of P
lans, T
argets an
d C
ost E
stimates
KD
1R
ura
l ho
use
ho
ld w
ate
r se
cu
rity
AS
SU
MP
TIO
NS
Nr.
Ind
ica
to
rB
ase
line
1
2th
FY
P1
3th
FY
P1
4th
FY
PA
ssu
mp
tio
ns
Un
it C
ost
To
ta
l Co
st in
Mln
Ng
u1
2th
FY
P1
3th
FY
P1
4th
FY
P1
2th
FY
P1
3th
FY
P1
4th
FY
P
1%
ho
us
eh
old
s w
ith p
ipe
d w
ate
r
su
pp
ly b
y in
ve
stm
en
ts%
inv
es
t%
inv
es
t%
inv
es
t%
inv
es
t1
00
% c
ov
era
ge
ac
hie
va
ble
in 1
2th
FY
P - b
as
ed
on
inv
es
tme
nts
Nr. H
Hs
20
15
Ad
d'l H
Hs
20
33
Nr o
f HH
to c
on
ne
ct b
y
20
33
Co
st p
er H
H in
Mln
Ng
uT
ota
l Co
st in
Mln
Ng
uN
r H
Hs
N
r H
Hs
N
r H
Hs
M
ln N
gu
Mln
Ng
uM
ln N
gu
63
%C
hu
kh
a9
2.0
10
01
00
10
08
,14
61
,88
82
,54
00
.06
31
60
.88
47
84
78
47
53
.65
3.6
53
.6
31
%H
aa
96
.41
00
10
01
00
2,0
60
72
88
02
0.0
31
24
.92
67
26
72
67
8.3
8.3
8.3
10
0%
Pa
ro
96
.51
00
10
01
00
8,3
83
1,1
84
1,4
77
0.1
00
14
7.7
49
24
92
49
24
9.2
49
.24
9.2
81
%T
him
ph
u9
6.3
10
01
00
10
02
,50
35
20
61
20
.08
14
9.7
20
42
04
20
41
6.6
16
.61
6.6
21
,09
24
,31
95
,43
10
.07
13
83
.01
81
01
81
01
81
01
27
.71
27
.71
27
.7
2%
ho
us
eh
old
s w
ith fu
nctio
na
l
pip
ed
wa
ter s
up
ply
% fu
nc
tion
%
fun
ctio
n
%
fun
ctio
n
%
fun
ctio
n
10
0%
co
ve
ra
ge
ac
hie
va
ble
in 1
4th
FY
P - b
as
ed
on
fun
ctio
na
lityN
r. H
Hs
Ad
d'l H
Hs
20
33
Nr o
f co
nn
ec
tion
s to
imp
ro
ve
by
20
33
Cost of rehab/ H
H in
Mln
Ng
uT
ota
l Co
st in
Mln
Ng
uN
r H
Hs
N
r H
Hs
N
r H
Hs
M
ln N
gu
Mln
Ng
uM
ln N
gu
63
%C
hu
kh
a6
3.0
75
88
10
0G
ap
pro
po
rtio
na
lly c
los
ed
ov
er tim
e8
,14
61
,88
84
,90
20
.02
57
7.6
16
34
16
34
16
34
25
.92
5.9
25
.9
31
%H
aa
43
.06
28
11
00
2,0
60
72
81
,90
20
.02
51
4.7
63
46
34
63
44
.94
.94
.9
10
0%
Pa
ro
27
.05
17
61
00
8,3
83
1,1
84
7,3
03
0.0
25
18
2.6
24
34
24
34
24
34
60
.96
0.9
60
.9
81
%T
him
ph
u9
9.0
99
10
01
00
2,5
03
52
05
45
0.0
25
11
.11
82
18
21
82
3.7
3.7
3.7
21
,09
24
,31
91
4,6
52
0.0
20
28
6.0
48
84
48
84
48
84
95
.39
5.3
95
.3
3%
ho
us
eh
old
s w
ith w
ate
r-s
ea
led
sa
nita
tion
%%
%%
90
% c
ov
era
ge
ac
hie
va
ble
in 1
4th
FY
PN
r. H
Hs
Ad
d'l H
Hs
20
33
Nr o
f se
ale
d to
ilets
to
pu
t in b
y 2
03
3
Un
it Co
st in
Mln
Ng
uT
ota
l Co
st in
Mln
Ng
uN
r H
Hs
N
r H
Hs
N
r H
Hs
M
ln N
gu
Mln
Ng
uM
ln N
gu
63
%C
hu
kh
a5
8.2
69
79
90
Ga
p p
ro
po
rtio
na
lly c
los
ed
ov
er tim
e8
,14
61
,88
84
,47
90
.18
51
0.3
14
93
14
93
14
93
17
0.1
17
0.1
17
0.1
31
%H
aa
32
.55
27
19
0p
re
se
ntly
pit +
imp
ro
ve
d la
trin
es
2,0
60
72
81
,91
20
.18
10
6.7
63
76
37
63
73
5.6
35
.63
5.6
10
0%
Pa
ro
61
.27
18
09
0b
as
elin
e fig
ure
s to
be
ch
ec
ke
d8
,38
31
,18
43
,59
80
.18
64
7.6
11
99
11
99
11
99
21
5.9
21
5.9
21
5.9
81
%T
him
ph
u7
9.7
83
87
90
2,5
03
52
07
77
0.1
81
13
.62
59
25
92
59
37
.93
7.9
37
.9
21
,09
24
,31
91
0,7
66
0.1
28
01
74
28
13
78
.23
58
93
58
93
58
94
59
.44
59
.44
59
.4
68
9.1
SU
B T
OT
AL K
D1
20
47
.21
0,2
83
10
,28
31
0,2
83
68
26
82
68
2
CO
ST
TO
TA
L T
AR
GE
TT
OT
AL C
OS
T E
ST
IMA
TE
SIN
DIC
AT
OR
SP
HY
SIC
AL T
AR
GE
TS
KD
2E
con
om
ic wa
ter se
curity
AS
SU
MP
TIO
NS
Nr.
Ind
icato
rB
ase
line
1
2th
FY
P1
3th
FY
P1
4th
FY
PA
ssum
ptio
ns
To
tal C
ost in
Mln
Ng
u1
2th
FY
P1
3th
FY
P1
4th
FY
P1
2th
FY
P1
3th
FY
P1
4th
FY
P
1%
ara
ble
lan
d irrig
ate
d%
%%
%Irrig
ate
d a
rea
inc
rea
se
d b
y 5
0%
in 1
4th
FY
P - a
s p
er
NIM
P
Irriga
ted
are
a, in
ac
res
Inc
rea
se
in a
cre
sU
nit C
os
t in
Ngu/ acreT
ota
l Co
st M
ln B
TN
Ac
res
Ac
res
Ac
res
Mln
Ng
uM
ln N
gu
Mln
Ng
u
63
%C
hu
kh
a1
6.2
19
22
24
.3G
ap
pro
po
rtion
ally
clo
se
d o
ve
r time
44
43
.53
2,2
22
95
,00
01
33
.61
74
17
41
74
14
4.5
44
.54
4.5
31
%H
aa
14
.21
71
92
1.3
21
9.8
31
10
95
,00
03
.24
37
37
37
1.1
1.1
1.1
10
0%
Pa
ro2
83
33
74
24
32
9.9
12
,16
59
5,0
00
20
5.6
77
22
72
27
22
68
.66
8.6
68
.6
81
%T
him
ph
u2
0.9
24
28
31
.35
11
31
.26
56
69
5,0
00
43
.63
18
91
89
18
91
4.5
14
.51
4.5
5,0
62
38
6.1
51
68
71
68
71
68
71
28
.71
28
.71
28
.7
2%
of p
ote
ntia
l hy
dro
po
we
r
de
ve
lop
ed
%%
%%
Fo
llow
pla
ns
MO
EA
se
e p
lan
s
DH
PS
-MO
EA
Un
it co
st in
Mln
Ng
uT
ota
l Co
st in
Mln
Ng
uM
ln N
gu
Mln
Ng
uM
ln N
gu
10
0%
Ch
uk
ha
60
73
87
10
0W
an
gc
hh
u (5
70
MW
) + B
un
ak
ha
(18
0 M
W)
40
,60
8 +
29
,52
77
0,1
35
23
37
8.3
23
37
8.3
23
37
8.3
10
0%
Ha
a0
00
00
.00
.00
.0
10
0%
Pa
ro0
33
67
10
0P
ac
hh
u (1
14
MW
)1
8,0
00
18
,00
06
00
0.0
60
00
.06
00
0.0
10
0%
Th
imp
hu
03
36
71
00
Th
imp
hu
ch
hu
(57
MW
) + C
he
rich
hu
(76
MW
)9
,00
0 +
12
,00
02
1,0
00
70
00
.07
00
0.0
70
00
.0
10
9,1
35
36
37
8.3
36
37
8.3
36
37
8.3
UB
TO
TA
L KD
21
09
,52
13
6,5
07
36
,50
73
6,5
07
IND
ICA
TO
RS
TO
TA
L TA
RG
ET
TO
TA
L CO
ST
ES
TIM
AT
ES
PH
YS
ICA
L TA
RG
ET
SC
OS
T
134
KD
3U
rba
n w
ate
r se
curi
ty a
nd
dra
ina
ge
AS
SU
MP
TIO
NS
Nr.
Ind
ica
tor
Ba
seli
ne
1
2th
FY
P1
3th
FY
P1
4th
FY
PA
ssu
mp
tio
ns
To
tal
Co
st i
n
Mln
Ng
u1
2th
FY
P1
3th
FY
P1
4th
FY
P1
2th
FY
P1
3th
FY
P1
4th
FY
P
1%
of
urb
an
ho
use
ho
lds
wit
h
pip
ed
wa
ter
sup
ply
%%
%%
10
0%
co
ve
rag
e i
s p
os
sib
le i
n 1
4th
FY
P -
ba
se
d o
n
inv
es
tme
nts
Nr
of
HH
s
20
15
Ad
d'l
HH
s
by
20
33
Nr
HH
to
be
co
nn
ec
ted
Co
st
pe
r H
H i
n
Mln
Ng
uT
ota
l C
os
t in
Mln
Ng
uN
r H
Hs
N
r H
Hs
N
r H
Hs
M
ln N
gu
Mln
Ng
uM
ln N
gu
10
0%
Ch
uk
ha
92
95
97
10
0G
ap
pro
po
rtio
na
lly
clo
se
d o
ve
r ti
me
1,8
54
34
14
90
0.0
29
.80
16
31
63
16
33
.33
.33
.3
10
0%
Ha
a9
69
79
91
00
64
62
20
24
50
.02
4.9
18
28
28
21
.61
.61
.6
10
0%
Pa
ro9
69
79
91
00
73
22
44
27
30
.02
5.4
69
19
19
11
.81
.81
.8
10
0%
Th
imp
hu
96
97
99
10
02
3,9
02
3,1
71
4,1
27
0.0
28
2.5
41
37
61
37
61
37
62
7.5
27
.52
7.5
27
,13
43
,97
65
,13
50
.02
10
2.7
01
71
21
71
21
71
23
4.2
34
.23
4.2
2%
of
ho
use
ho
lds
wit
h t
rea
ted
pip
ed
wa
ter
sup
ply
%%
%%
90
% c
ov
era
ge
is
po
ss
ible
in
14
th F
YP
- b
as
ed
on
inv
es
tme
nts
Nr
of
HH
sA
dd
'l H
Hs
by
20
33
Nr
HH
to
ha
ve
tre
ate
d
wa
ter
Un
it C
os
t in
Mln
Ng
uT
ota
l C
os
t in
Mln
Ng
uN
r. H
Hs
Nr.
HH
sN
r. H
Hs
Mln
Ng
uM
ln N
gu
Mln
Ng
u
10
0%
Ch
uk
ha
56
67
79
90
Ga
p p
rop
ort
ion
all
y c
los
ed
ov
er
tim
e1
,85
43
41
1,1
57
55
38
63
86
38
61
.67
1.6
71
.67
10
0%
Ha
a2
74
86
99
06
46
22
06
91
55
23
02
30
23
01
.67
1.6
71
.67
10
0%
Pa
ro7
35
62
90
73
22
44
92
45
53
08
30
83
08
1.6
71
.67
1.6
7
10
0%
Th
imp
hu
90
90
90
90
23
,90
23
,17
15
,56
15
51
85
41
85
41
85
41
.67
1.6
71
.67
27
,13
43
,97
68
,33
40
.00
22
02
77
82
77
82
77
86
.76
.76
.7
6,7
84
2,0
83
0.0
02
5
3U
rba
n w
ate
r lo
st (
no
t
acc
ou
nte
d f
or)
%%
%%
No
ba
se
lin
e d
ata
av
ail
ab
le.
Nr
of
HH
sA
dd
'l H
Hs
by
20
33
Ta
rge
tCo
st/ y
r in
Mln
N
gu
To
tal
co
st
in M
ln N
gu
Nr.
HH
sN
r. H
Hs
Nr.
HH
sM
ln N
gu
Mln
Ng
uM
ln N
gu
10
0%
Ch
uk
ha
?1
,85
43
41
2,1
95
0.6
75
10
.12
57
32
73
27
32
3.4
3.4
3.4
10
0%
Ha
a?
64
62
20
86
60
.27
4.0
28
92
89
28
91
.31
.31
.3
10
0%
Pa
ro?
73
22
44
97
60
.34
.53
25
32
53
25
1.5
1.5
1.5
10
0%
Th
imp
hu
?2
3,9
02
3,1
71
27
,07
38
.33
12
4.9
90
24
90
24
90
24
41
.64
1.6
41
.6
27
,13
43
,97
63
1,1
10
14
3.5
10
37
01
03
70
10
37
04
7.8
47
.84
7.8
4%
ho
use
ho
lds
wit
ho
ut
sew
ag
e t
rea
tme
nt
%%
%%
Bri
ng
fig
ure
be
low
10
% b
y 1
4th
FY
PN
r o
f H
Hs
Ad
d'l
HH
s
by
20
33
Nr
HH
s t
o b
e c
on
ne
cte
dU
nit
Co
st
To
tal
Co
st
in M
ln N
gu
Nr.
HH
sN
r. H
Hs
Nr.
HH
sM
ln N
gu
Mln
Ng
uM
ln N
gu
10
0%
Ch
uk
ha
22
18
14
10
Ga
p p
rop
ort
ion
all
y c
los
ed
ov
er
tim
e1
,85
43
41
56
42
01
.66
18
81
88
18
80
.60
.60
.6
10
0%
Ha
a1
81
51
31
06
46
22
02
71
20
0.8
09
09
09
00
.30
.30
.3
10
0%
Pa
ro2
27
32
24
42
44
20
0.7
28
18
18
10
.20
.20
.2
10
0%
Th
imp
hu
77
23
,90
23
,17
13
,17
12
09
.35
10
57
10
57
10
57
3.1
3.1
3.1
6,7
84
20
27
,13
43
,97
64
,25
01
2.5
31
41
71
41
71
41
74
.24
.24
.2
5%
ho
use
ho
lds
wit
h s
oli
d
wa
ste
dis
po
sal
%%
%%
Inc
rea
se
fig
ure
by
10
%-p
oin
t b
y 1
4th
FY
PN
r o
f H
Hs
Ad
d'l
HH
s
by
20
33
Nr
HH
s t
o b
e s
erv
ed
Un
it C
os
tT
ota
l C
os
t in
Mln
Ng
uN
r. H
Hs
Nr.
HH
sN
r. H
Hs
Mln
Ng
uM
ln N
gu
Mln
Ng
u
10
0%
Ch
uk
ha
34
37
41
44
Ga
p p
rop
ort
ion
all
y c
los
ed
ov
er
tim
e1
,85
43
41
52
71
00
.78
17
61
76
17
60
.30
.30
.3
10
0%
Ha
a2
52
83
23
56
46
22
02
84
10
0.4
29
59
59
50
.10
.10
.1
10
0%
Pa
ro1
61
92
32
67
32
24
43
17
10
0.4
71
06
10
61
06
0.2
0.2
0.2
10
0%
Th
imp
hu
71
01
41
72
3,9
02
3,1
71
5,5
61
10
8.2
01
85
41
85
41
85
42
.72
.72
.7
6,7
84
10
22
30
22
30
22
30
3.3
3.3
3.3
27
,13
43
,97
66
,68
99
.86
SU
B T
OT
AL
KD
32
89
18
50
61
85
06
18
50
69
69
69
6
IND
ICA
TO
RS
TO
TA
L T
AR
GE
TT
OT
AL
CO
ST
ES
TIM
AT
ES
PH
YS
ICA
L T
AR
GE
TS
CO
ST
NB
: K
D4
- E
nvi
ron
men
tal
wat
er s
ecu
rity
in
dic
ato
rs a
re p
rese
ntl
y n
ot
acti
on
able
, h
ence
use
d f
or
mo
nit
ori
ng
on
ly
135
KD
5R
esilie
nce
to w
ate
r-rela
ted
disa
ster
AS
SU
MP
TIO
NS
Nr.
Ind
icato
rB
ase
line
1
2th
FY
P1
3th
FY
P1
4th
FY
PA
ssum
ptio
ns
To
tal C
ost in
Mln
Ng
u1
2th
FY
P1
3th
FY
P1
4th
FY
P1
2th
FY
P1
3th
FY
P1
4th
FY
P
4E
me
rge
ncy
resp
on
se
Me
cha
nism
Nr.
Nr.
Nr.
Nr.
Ba
sin
-lev
el re
vo
lvin
g fu
nd
@ N
gu
5 m
illion
Nr. E
OC
s to
se
t-up
Un
it Co
st
To
tal C
os
t in M
ln N
gu
Mln
Ng
uM
ln N
gu
Mln
Ng
u
10
0%
Ch
uk
ha
0
10
0%
Ha
a0
10
0%
Pa
ro7
10
0%
Th
imp
hu
0
5(R
ura
l) wa
ter sto
rag
eM
CM
MC
MM
CM
MC
MC
rea
te s
tora
ge
for 1
0%
ne
ed
y H
Hs
for 2
mo
nth
s
do
me
stic
wa
ter s
up
ply
Sto
rag
e
Vo
lum
e m
3U
nit C
os
tT
ota
l Co
st in
Mln
Ng
uS
tora
ge
Vo
lum
e m
3M
ln N
gu
Mln
Ng
uM
ln N
gu
10
0%
Ch
uk
ha
17
,36
1to
be
de
term
ine
d1
7,3
61
se
e w
ork
sh
ee
t1
74
17
,36
11
74
10
0%
Ha
a6
,76
36
,76
36
86
,76
36
8
10
0%
Pa
ro3
5,2
49
35
,24
93
52
35
,24
93
52
10
0%
Th
imp
hu
14
41
44
11
44
1
59
,51
75
9,5
17
59
55
9,5
17
59
5
6F
loo
d h
aza
rd zo
na
tion
Nr.
Flo
od
ha
zard
zon
atio
n m
ap
s d
on
e b
y B
hu
-86
23
to b
e
ela
bo
rate
dX
XX
Xh
ah
ah
aM
ln N
gu
Mln
Ng
uM
ln N
gu
10
0%
Ch
uk
ha
1M
ore
de
taile
d e
lab
ora
tion
ne
ed
ed
Ba
sin
figu
re
10
0%
Ha
a1
De
ma
rka
tion
on
the
gro
un
d n
ee
de
d
10
0%
Pa
ro1
Ac
tion
ran
ks
un
de
r floo
d p
rote
ctio
n m
ea
su
res
10
0%
Th
imp
hu
1p
en
din
g
7F
loo
d p
rote
ction
me
sasu
res
pe
nd
ing
Nr.
Imp
lem
en
t floo
d-p
rote
ctio
n m
ea
su
res
ba
se
d o
n flo
od
-
pro
ne
are
as
as
se
ss
ed
un
de
r Bh
u-8
62
3
Un
it Co
st in
Mln Ngu/m
To
tal C
os
t in M
ln N
gu
m le
ng
thm
len
gth
m le
ng
thM
ln N
gu
Mln
Ng
uM
ln N
gu
10
0%
Ch
uk
ha
00
.12
6tb
atb
atb
atb
atb
atb
atb
a
10
0%
Ha
a1
depending on workload/ cost
tba
10
0%
Pa
ro1
by
12
th, 1
3th
or 1
4th
FY
P1
33
.64
50
01
33
.6
10
0%
Th
imp
hu
1tb
a
13
3.6
45
00
13
3.6
8Flood/ GLO
F Early Warning
Imp
lem
en
t Ea
rly W
arn
ing
Sy
ste
m(s
) T
ota
l Co
st in
Mln
Ng
uM
ln N
gu
Mln
Ng
uM
ln N
gu
10
0%
Ch
uk
ha
31
23
depending on workload/ cost
Se
e D
HM
S a
ctiv
ities
10
0%
Ha
a0
by
12
th, 1
3th
or 1
4th
FY
P
10
0%
Pa
ro0
10
0%
Th
imp
hu
0
16
08
08
0
UB
TO
TA
L KD
58
94
81
0.4
81
.71
.7
GR
AN
D T
OT
AL O
F P
LAN
NE
D E
XP
EN
DIT
UR
ES
TILL 2
03
3 IN
FO
UR
DZ
ON
GK
HA
GS
(INC
LUD
ING
INC
RE
AS
E O
F P
OP
ULA
TIO
N) IN
MILLIO
N N
GU
LTR
UM
11
2,7
51
38
,09
63
7,3
67
37
,28
7
1.6
7
IND
ICA
TO
RS
TO
TA
L TA
RG
ET
TO
TA
L CO
ST
ES
TIM
AT
ES
PH
YS
ICA
L TA
RG
ET
SC
OS
T
16
08
08
0
51
.67
1.6
7
136
(Footnotes)
1 https://en.wikipedia.org/wiki/Drainage_basin
2 https://en.wikipedia.org/wiki/Water_scarcity
3 https://en.wikipedia.org/wiki/Water_balance
4 Global Water Partnership: http://www.gwp.org/Th e-Challenge/What-is-IWRM/
5 https://docs.google.com/a/universitywatersectorpartnership.org
6 Godfrey, J. and K. Chalmers (editors). Water Accounting: International Approaches to Policy and Decision-making. Edward Elgar
Publishing, 2012.
7 http://www.iadclexicon.org/water-availability/
8 UN-Water: http://www.unwater.org/topics/water-security/en
9 http://www.nrcs.usda.gov/Internet/FSE_DOCUMENTS/stelprdb1042207.pdf
10 https://water.usgs.gov/nwsum/WSP2425/defi nitions.html
11 http://www.epa.gov/wetlands/what-wetland
137
138
139
National Environment Commission
Royal Government of Bhutan.
P.O. Box: 466
Th imphu - 11001, Bhutan.
Tel No: +975 2 323384 / 324323 / 326386 / 326993
Fax No: +975 2 323385
Toll Free No: 149
Website: www.nec.gov.bt