washington, dc construction schedule … between each delay event and its impact on the project...
TRANSCRIPT
Federal Publications - Construction Schedule Delays
Washington,DC
November,
2014
CONSTRUCTIONSCHEDULE DELAYS
Jessica Haire
Fox Rothschild LLP
Phone: 202-461-3109
E-mail: [email protected]
What We Will Cover:
• Chapters 1, 3, 4, & 5
• Define Key Terminology
• Identify and Evaluate Defenses to Delay Claims– No-Damages-for-Delay Clauses
– Concurrent Delay
– Trade to Trade Clauses
• Explore Delay Damages– The Current State of the Eichleay Formula
The Nature of Delay Claims
• The basis for delay claims arise fromeither an express contractual obligation toperform within a given timeframe or theimplied obligation not to delay, hinder orinterfere with the performance of the otherparty.
Types of Delays - Continued
Excusable Compensable Delays
• Remedy granting clause
• Implied duty breach
• Contractor must be “free of fault”
8.3 Delays & Extensions of Time
1997/2007 AIA General Conditions
• 8.3.1 If the Contractor is delayed at anytime in the . . . progress of the Work by anyact or neglect of the Owner or Architect, …or by changes ordered in the work, or bylabor disputes, fire, unusual delay indeliveries … or other causes beyond thecontractor’s control, … then the ContractTime shall be extended by Change Orderfor such reasonable time as the Architectmay determine.
Federal Acquisition Regulation52.249-14 (Excusable Delays)
• The contractor shall not be in default … ifthe failure arises from causes beyond thecontrol … of the contractor. Examples ofthese causes are (1) acts of God or of thepublic enemy, (2) acts of government …,(3) fires, (4) floods, (5) epidemics, (6)quarantine restrictions, (7) strikes, (8)freight embargoes, and (9) unusuallysevere weather.
Typical Causes ofCompensable Delays:
• Defective Drawings or Specifications.
• Failure to Provide Access
• Improper Site Preparation
• Failure to Supply Materials or Labor
• Failure to Provide Plans/Approve ShopDrawings.
• Failure to Coordinate Parallel PrimeContractors
Typical Causes ofCompensable Delays: Cont’d
• Failure to Give Timely Work Orders.
• Failure to Make Timely Payment toContractors
• Failure to Inspect/Over-inspection
• Work Suspensions
• Excessive Change Orders
• Failure to Accept Completed Work
• Acceleration
Figure 1-1
Owner Delay
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
Path B
Path A
ScheduledCompletion
30 dayownerdelay
30 dayprojected delay
0 Float
0 Float+30 Float
0 Float
0 Float+60 Float
30 day owner causeddelay to 0 float path
30 day delay toprojected completion
Delay is excusable,compensable
30 day extension torequired completiondate
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
Types of Delays - Continued
Excusable Non-Compensable Delays
• Unforseeable
• Absence of control
• Typically enumerated in contract
Typical Causes of NoncompensableExcusable Delays (Force Majeure)
• Weather
• Acts of God
• Labor Problems
Figure 1-2
Force Majeure Delay
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
Path B
Path A
ScheduledCompletion
30 dayforce majeure
delay
30 dayprojected delay
0 Float
0 Float+30 Float
0 Float
0 Float+60 Float
30 day force majeuredelay to 0 float path
30 day delay toprojected completion
Delay is excusable,non-compensable
30 day extension torequired completiondate
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
Figure 1-3
Contractor Delay
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
Path B
Path A
ScheduledCompletion
30 daycontractor
delay
30 dayprojected delay
0 Float
0 Float+30 Float
-30 Float
-30 Float+30 Float
30 day contractorcaused delay to 0 floatpath
30 day delay toprojected completion
Delay is non-excusable
No change to requiredcompletion date
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
Expert Testimony
• Daubert v. Merrell Dow Pharmaceuticals,Inc., 509 U.S. 579 (1993)
• FRE 702
• Four-Part Test
• Whether testimony rests on a reliablefoundation and is relevant
Expert Testimony - Continued
Four-Part Test
• Specialized knowledge that is helpful
• Based in sufficient facts/data
• Reliable methods
• Reliable application
Expert Testimony - Continued
• CPM schedule generally accepted
– See Weaver-Bailey Contractors, Inc. v. U.S.,19 Cl. Ct. 474 (1990)
• Cautionary Note
– See Mega Const. Co., Inc. v. U.S., 29 Fed. Cl.(1993)
Legal Issues
• Burden of Proof
• Suspensions versus delays
• Right to finish early
• Acceleration
• Concurrency
• Waiver
Legal Issues – Burden of Proof
• Burden on contractor
• Must show:
– Extent of delay (CPM preference)
– Proximate cause
– Harm
The Claims Process
• A CPM analysis is required to show therelationship between each delay event and itsimpact on the project schedule;
• Types of Analyses:
– Contemporaneous CPM Schedule
– Windows Analysis
– Impacted, As-Planned Schedule
– Collapsed, As-Built/But For Schedule
The Claims Process – Cont’d
• The 1984 & 1987 Santa Fe, Inc. decisions indicated theVABCA’s preference for contemporaneous scheduleswhen assessing delay claims.
• Santa Fe, Inc., VABCA No. 2168, 87-3 BCA ¶ 20,104 –“in the absence of compelling evidence of actual errorsin the CPMs, we will let the parties ‘live or die’ by theCPM applicable to the relevant time frames.”
P.J. Dick, Inc. v. Principi, 324 F.3d1364 (Fed. Cir. 2003)
• Commented that the CPM used during the course of theproject were “properly constituted in its logic andassiduously and properly maintained throughout thecourse of the project. This circumstance is in sharpcontrast to the usual problems we encounter in dealingwith CPMs where warring as-built schedules areconstructed by the parties after the fact because the CPMwas either never properly prepared or was not updated in
accordance with the contract scheduling requirements.”
Suspensions
• Definition: A suspension is a form ofdelay that results from the owner’spurposeful interruption of work.
• Two Types:
• Directed Suspension.
• Constructive Suspension.
Suspension of Work ClauseFAR 52.242-14
• (a) The Contracting Officer may order theContractor in writing, to suspend, delay orinterrupt all or any part of the work …
• (b) If the performance of all or any part ofthe work is, for an unreasonable period oftime, suspended, delayed … anadjustment shall be made for theincrease in the cost of performance ofthis contract ….
Constructive Suspension
• (b) If the performance of all or any part ofthe work is, for an unreasonable period oftime, suspended, delayed or interrupted(1) by an act of the Contracting Officer inthe administration of the contract, or (2) bythe Contracting Officer’s failure to actwithin the time specified in this contract (orwithin a reasonable time if not specified)…
Suspension - Elements
Contractor must show:
• Proximate cause of delay
• Delay was unreasonable
• Harm
Right to Finish Early
Contractor must show:
(1) it intended to completion the project early;
(2) it had the capability to do so; and
(3) It actually would have completed early, but for theGovernment’s actions.
See Interstate General Gov’t Contractors v. West, 12 F.3d 1053 (Fed.Cir. 1993)
Practice Tip: define float ownership in contract
Figure 3-2
Early Completion
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
0 Float
0 Float0 Float
Project scheduledfor early completion inMonth 4, one monthbefore requiredcontract completion inMonth 5
Contractor has theright to finish a projectearly
Owner shares inbenefit of earlycompletion
30 days betweencontractor’s
scheduled earlycompletion and
required contractcompletion date
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
Figure 3-3
Early Completion Contractor Delay
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
Path B
Path A
ScheduledCompletion
0 Float
0 Float0 Float
0 Float
0 Float+30 Float
30 daycontractor
delay
30 day Contractordelay
30 day projecteddelay is non-excusable
Required contractcompletion dateunchanged
Project stillscheduled for requiredcompletion date
30 dayprojected delay
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
Figure 3-4
Early Completion Owner Delay
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
Path B
Path A
ScheduledCompletion
0 Float
0 Float0 Float
0 Float
0 Float+30 Float
30 dayownerdelay
30 dayprojected delay
30 day Owner delay
30 day projecteddelay is excusable,compensable
Entitles contractor to30 day extension torequired contractcompletion
Puts Contractor backin the position it wouldhave been, but for theOwner delay
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
Directed Acceleration
• The FAR Changes Clause (48 C.F.R. § 52.243-4(a)) provides:
• The Contracting Officer may, at any time … bywritten order … may make any change in thework within the general scope of the contract,including changes:
• (4) Directing acceleration in the performance ofthe work.
Constructive Acceleration
(1) excusable delay;
(2) notice and request for a time extension
a) such notice is not necessary if the Gov’t orderdirects compliance with a given schedule expresslywithout regard to the existence of an excusabledelay
b) The supporting information is unnecessary if it isalready reasonably available to the Government
Constructive Acceleration
(3) failure or refusal to grant the requestedextension within a reasonable time
(4) a Gov’t order; either express or implied … totake steps to overcome an excusable delay orcomplete the work by the earliest possible date
(5) reasonable efforts by the contractor toaccelerate the work, resulting in added costs,even if the efforts are not successful
Figure 3-5
Constructive Acceleration
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
Path B
Path A
ScheduledCompletion
0 Float
0 Float0 Float
-30 Float
-30 Float0 Float
30 dayexcusable
delay
30 day excusabledelay event
Contractor requeststime extension
Owner deniesrequest for timeextension
Contract completiondate not appropriatelyadjusted
30 dayprojected delay
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
Figure 3-6
Constructive Acceleration (cont’d)
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
Path B
Path A
ScheduledCompletion
0 Float
0 Float0 Float
Owner threatensliquidated damages orinsists contractcompletion date mustbe met
Contractoraccelerates to meetrequired completion
Owner liable forcontractor’s costs
-30 Float
-30 Float0 Float
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
Acceleration Damages
• Overtime or shift work
• Added crews or increased crew sizes
• Additional tools & equipment
• Additional supervision
• Jobsite Overhead
• Labor inefficiency
Concurrent Delay
• Two or more independent causes
• Attributable to different parties
• That (1) overlap or (2) affect the same timeperiod
• Presents complex legal issues if:
– Delay periods are different lengths;
– Delay periods are not completely concurrent;
– Delay periods have different impacts on thework activities.
Concurrent Delay – Cont’d
• Traditional View – Neither party allowed anaffirmative recovery from the other party.
– No causation
• J.A. Jones Constr. Co. v. Greenbriar ShoppingCenter– Prime caused delay through failure of subs to timely perform &
owner caused delay by design changes & late issuance of therevised plans.
Figure 3-7
Concurrent Delay
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
Path B
Path A
ScheduledCompletion
0 Float
0 Float0 Float
0 Float
0 Float0 Float
30 daycontractor
delay
30 dayownerdelay
30 dayprojected delay
30 day owner andcontractor delays areconcurrent and critical
30 day delay to projectedcompletion
Delay is excusable, non-compensable
30 day extension torequired completion date
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
Concurrent Delay - Continued
Pacing
• Adjust pace of work to match delay
• Defense to alleged concurrency
• Contemporaneous records
Figure 3-8
Pacing Delay
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
Path B
Path A
ScheduledCompletion
0 Float
0 Float0 Float
0 Float
0 Float+30 Float
30 dayownerdelay
30 day owner causeddelay to projectedcompletion
30 day excusable,compensable timeextension
30 day extension torequired completiondate
Owner delay creates+30 float on alternatepath of work
30 dayprojected delay
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
Figure 3-9
Pacing Delay (cont’d)
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
Path B
Path A
ScheduledCompletion
0 Float
0 Float+30 Float
0 Float
0 Float0 Float
30 daycontractor
delay
30 day contractordelay to +30 float pathabsorbs float
No delay to projectedcompletion
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
Delay Absorbing Float
• Float Definition: The amount of time by whichan activity can be delayed without affecting theproject’s completion date. See Blinderman Constr. Co.,
Inc. v. U.S., 39 Fed. Cl. 529, 579-580 (1997).
• An activity that has “float” is not on the project’scritical path.
• Two Types: Free Float & Total Float
Figure 3-1
Non-critical Delay Absorbing Float
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
Path B
Path A
ScheduledCompletion
30 daydelay toPath B
0 Float
0 Float+30 Float
0 Float
0 Float0 Float
Any party delay to activitywith float does not impactthe required contractcompletion date
Project still scheduled tofinish on time until all floatabsorbed
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
Allocating Ownership of Float
• Unless otherwise provided in the contract, floatbelongs to the to the project and either partymay consume that float without liability to theother on a first come, first served basis. See
Weaver-Bailey Contractors, Inc. v. U.S., 19 Cl.Ct. 474, 481-482 (1990).
• Critical to update the schedule in regularintervals in order to use it as a time managementtool and to analyze time impacts.
Figure 3-10
Critical v Non-critical Delays
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
Path B
Path A
ScheduledCompletion
30 daycontractor
delay
30 dayownerdelay
0 Float
0 Float+30 Float
0 Float
0 Float+30 Float
30 dayprojected delay
30 day owner delay to0 float path is critical
30 day contractordelay to path with +30float is non-critical
30 day delay toprojected completion
Delay is excusable,compensable
30 day extension torequired completiondate
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
Figure 3-11
Critical v Non-critical Delays
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
Path B
Path A
ScheduledCompletion
30 daycontractor
delay
30 dayownerdelay
0 Float
0 Float+30 Float
-30 Float
-30 Float0 Float
30 dayprojected delay
30 day contractordelay to 0 float path iscritical
30 day owner delay topath with +30 float isnon-critical
30 day delay toprojected completion
Delay is non-excusable
No change to requiredcompletion date
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
Concurrent Delay – Continued
Offsetting Delay
• Not on longest path
• No available float
• Offsets LDs
Figure 3-12
Offsetting Delay
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
Path B
Path A
ScheduledCompletion
0 Float
0 Float0 Float
-90 Float
-90 Float-30 Float
90 daycontractor
delay
90 day and 30 daycontractor delays toprojected completion arenon-excusable
No change in contractcompletion date,liquidated damages startaccruing
No float created due tonon-excusable delay
1 day left on path B
90 day projected delay
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
30 daycontractor
delay
As-Planned
Month 3 Schedule
Figure 3-13
Offsetting Delay
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
-90 Float
-90 Float-30 Float
30 day owner delay (e.g.extra work) to path B
No change to projectedcompletion date (longestpath through path A)
After expiration ofcontract time whileassessed liquidateddamages
Contractor would havebeen finished with path Bwork but for owner extrawork
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
Path B
Path A
ScheduledCompletion
-90 Float
-90 Float-60 Float
Month 3 Schedule
Month 4 Schedule
30 dayownerdelay
Figure 3-14
Offsetting Delay
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
-90 Float
-90 Float-30 Float
Cannot assessliquidated damages whilesimultaneously addingextra work (waiver ofcompletion)
30-day non-compensable timeextension to offset 30days of LDs
Puts contractor back insame float positionwould have been but forowner delay
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
Path B
Path A
ScheduledCompletion
-60 Float
-60 Float-30 Float
30 day offsetting delay
30 dayownerdelay
Month 3 Schedule
Month 4 Schedule
Concurrent Delay – Continued
Apportionment
• Original rule: Nullification– See Acme Process Equipment Co. v. U.S., 171 Ct. Cl.
324 (1914)
• Trending: segregating and apportioningsequential delays– See eg Utley-James, Inc., GSBCA No. 5370, 85-1
BCA ¶17816 (1984), aff’d 14 Cl. Ct. 804 (1988)
Figure 3-15
Apportioned Delays (owner then contractor)
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
Path B
Path A
0 Float
0 Float0 Float
30 dayownerdelay
30 day excusable,compensable timeextension
30 day extension torequired completiondate
30 day non-excusable delay, cancharge LD’s iffinishes as projected
30 daycontractor
delay
ScheduledCompletion
-30 Float
-30 Float
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
Figure 3-16
Apportioned Delays (contractor then owner)
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Path B
Path A
ScheduledCompletion
Path B
Path A
ScheduledCompletion
0 Float
0 Float0 Float
-30 Float
-30 Float
30 daycontractor
delay
30 day excusable,compensable timeextension
30 day extension torequired completiondate
30 day non-excusable delay, cancharge LD’s iffinishes as projected
30 dayownerdelay
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
Delay Damages
• REA vs. Claim
• Mitigation
• Types of Delay Damages
• Disruption vs. Delay
• LDs
• Proof
Owner Damages
• Liquidated damages or;
• Actual Damages such as:
– Lost revenues due to delayed occupancy
– Increased engineering & inspection costs
– Increased financing costs
– Interest
Contractor Damages
• Labor– Escalation and premiums
– inefficiencies
• Equipment
• Extended field office overhead
• Unabsorbed home office overhead
• Material
• Interest
• Loss of profits
• Loss of bonding capacity
CONSTRUCTION COST ELEMENTS
TOTAL COST
DIRECT COST OVERHEAD (OH)
EQUIP-MENT
CATEGORY
• Leased
• Owned
MATERIAL
FACTORS
• Direct Material
• Sales Tax
• Shipping &Handling
•Storage
Material typically 15-30% of direct cost
DIRECTOH
GENERALCONDITIONS
• On-Site Staff
• On-Site Facilities
• Permits & Fees
Based onanticipated project
duration
INDIRECTOH
HOME OFFICEOVERHEAD
• General &Administrative
• Sales &Marketing
NETPROFIT
Profittypically5-10% oftotal cost
DAMAGES
DELAY Escalation Standby Escalation Extended Performance
Lost Productivity / EfficiencyDISRUPTION
Additional Resources / Inefficiency ExpeditingACCELERATION Add’l staff
LABOR
DIRECT LABOR
• Craft Labor
• Supervision
PAYROLLBURDENS
• Fringe Benefits
• Insurance & Taxes
Burdens typically 80-120% of direct labor
Labor & burdens typically 30-40% of total cost
Indirect OH and profittypically 10-20% of
direct cost and direct OH
Figure 4-1
Recovery of Overhead – Cont’d
• Field Office Overhead,– also referred to as extended general conditions
– jobsite overhead costs such as project supervision,management, engineering, secretarial assistance,temporary field office trailers, electric and telephonebills, clean-up and other miscellaneous expenses.
• See Clark Concrete Contractors, 99-1 BCA ¶ 30,280 at 149,755-56; seealso 48 C.F.R. § 31.105(d)(3).
Field Office Overhead
• Allocable as either direct or indirect costs.
• FAR 31.105(d)(3) provides that field overhead isallowable as direct or indirect costs, provided theaccounting practice used is in accordance withthe contractor’s established and consistentlyfollowed cost accounting practices for all work.
• Per Diem Rate v. Percentage Mark-Up forchanges that do not extend the schedule.
Figure 4-2
Direct Overhead Damage Rate: Equal Length
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Causation and entitlementalready determined
30-day owner delay caused30-day delay to projectcompletion
Three typical options fordaily/weekly/monthly overheadrate to apply to delay period
Escalation typically appliedonly to Rate 2 (some blendedinto Rate 3)
After project typically useRate 2 (rate during damagedperiod)
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
30 dayowner delay 30 day late
completion
Rate 1
Rate 2
Rate 3
Overhead Rate#1: Average
month 2
Overhead Rate#2: Average
month 5
Overhead Rate#3: Averagemonths 1-6
Figure 4-3
Direct Overhead Damage Rate: Low Early Rate
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Causation and entitlementalready determined
60-day owner-caused late startresulted in a 30-day delay toproject completion
Rate 4 lower than Rate 5 due tolower cost for late start andescalation on Rate 5
Typically use Rate 5 (indamage period), but withpotential credit for lower rateduring non-work period (latestart) during delay cause
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
60 dayowner-caused
late start
30 day latecompletion
Rate 4
Rate 5
Rate 6
Overhead Rate#4: Averagemonths 1-2
Overhead Rate#5: Average
month 5
Overhead Rate#6: Averagemonths 1-5
Figure 4-4
Months
1 2 3 4 5 6 7 8
Required ContractCompletion Date
Overhead Rate#7: Average
month 2
Overhead Rate#8: Averagemonths 5-7
Overhead Rate#9: Averagemonths 1-7
Causation andentitlement alreadydetermined
30-day owner delayresulted in a 90-daydelay to completion dueto non-work period inmonths 5 and 6
Rate 8 lower than Rate7 due to limited costsduring non-work period
Typically use Rate 8applied to 90-day periodto closer match actualdamages
ActivityCritical Activity
As-BuiltOwner Delay
Contractor DelayAs-Built Critical Path
30 dayowner delay
Rate 7
Rate 8
Rate 9
90 day late completion
Direct Overhead Damage Rate: Low Late Rate
Recovery of Overhead
• Home Office Overhead– indirect costs
– expended for the benefit of the business as a whole
– Includes administrative staff salaries, accounting &payroll services, general insurance, office supplies,telephone charges, depreciation, taxes and utilitycosts.
The Eichleay Formula
1. Total Contract Billings X Total Home Office OHTotal Billings f/ Cont. Period for Cont. Period
= OH Allocable to Contract
2. Allocable OH = Daily Cont. OHTotal Days of Performance
3. Daily Cont. OH X Days of Delay= Amount Recoverable
Government Defenses to Eichleay
1) The Standby Requirement: The Governmentrequired the contractor to standby during agovernment caused delay of indefiniteduration; and
2) The Replacement Work Requirement: While,and as a result of standing by, the contractorwas unable to take on other work.
See Interstate General Gov’t Contractors v. West, 12 F.3d 1053 (Fed.Cir. 1993)
Presented by: Reginald M. Jones, Esq., Smith Currie & Hancock, LLP
Government Defenses to Eichleay
Once the contractor satisfies those requirements,the burden shifts back to the Government toprove:
1) That it was not impractical for the contractor toobtain “replacement work” during the delay, or
2) That the contractor’s inability to obtain suchwork, or to perform it, was not caused by theGovernment’s suspension
P.J. Dick, Inc. v. Principi,324 F.3d 1364 (Fed. Cir. 2003)
Court determined that in order to meet the standbyrequirement, the contractor must show:
1) The Gov’t caused delay was not only substantial, butwas of indefinite duration;
2) During the delay, the contractor was required toresume work on the contract at full speed, as well asimmediately, and
3) Work on much, if not all of the contract was suspendeddue to the delay.
Disruption vs. Delay
• Disruption
– Increased labor and equipment due to loss ofefficiency
• Delay
– Increased labor and equipment due toextended time for performance
Contractual & Other LegalLimitations to Recovery
• Notice Provisions
• No-Damages for Delay Clauses
• Concurrent Delay
• Float Allocation Provisions
• Waiver/Release
– Change Orders
– AIA A201 Waiver of Consequential Damages
• Trade to Trade Provisions
No-Damages-for-Delay Clauses
Majority View:
• Because no-damages-for-delay clauses areexculpatory, in that they insulate bad actors fromotherwise culpable conduct, most courts haveadopted a policy of strict construction indetermining whether to enforce a particular clause.
• Traveler’s Casualty & Surety Co. v. DormitoryAuthority-State of New York, 735 F.Supp.2d 42(S.D.N.Y. 2010); See Chapter 5, page 257.
No-Damages-for-Delay Clauses
Majority View: Enforceable, but a contractor may recoverdespite the clause provided that the delay:
1) Was of a kind not contemplated by the parties,
2) Was such as to amount to an abandonment of thecontract,
3) Was the result of fraud, bad faith or arbitrary action,
4) Was the result of active interference with thecontractor’s work on the part of the owner, or
5) Was unreasonable
No-Damages-for-Delay Clauses
Recent Trend: Several states have enacted legislation thatinvalidates the enforcement of no-damages-for-delayclauses in private as well as public contracts.
Example: “any clause that purports to waive, release, orextinguish the rights of a contractor … to damages …arising out of an unreasonable delay… is void andunenforceable.” Wash. Rev. Code § 4.24.360 (1998)
J.A. Jones Constr. Co. v. Lehrer McGovernBovis, Inc., 89 P.3d 1009 (Nev. May 2005)
– At the time of the contract, Nevada had notrecognized any of the federal exceptions;
– Court reversed trial court that refused to giveproposed jury instruction;
– Court recognized three exceptions based on theimplied covenant of good faith & fair dealing;
– Nevada Revised Statute §108.2453 (Oct. 1, 2003)includes an exceptions for delays not contemplatedby the parties, but appears to make them cumulative.
Jackson Constr. Co., Inc. v. UnitedStates, 62 Fed.Cl. 84 (Sept. 15, 2004)
– COFC held that executed change orders barred acontractor’s claims for early completion delay and forcumulative impact of numerous changes;
– “It is agreed that this adjustment constitutes fullcompensation . . . for all costs, including extendedoverhead . . . attributable to the change order fordelays related thereto, and for performance of thechange within the time frame stated.”
– Court based its decision on the doctrine of accordand satisfaction; Rejected contractor’s notations.
Federal Publications - Construction Schedule Delays
Washington,DC
November,
2014
CONSTRUCTIONSCHEDULE DELAYS
Jessica Haire
Fox Rothschild LLP
Phone: 202-461-3109
E-mail: [email protected]