waste management model

237
A Local Authority Waste Management Mass Balance Model David W.J. Greenfield A thesis submitted in partial fulfilment of the requirements of the University of Brighton, for the degree of PhD. May 2010

Upload: others

Post on 25-May-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Waste management model

A Local Authority Waste Management

Mass Balance Model

David W.J. Greenfield

A thesis submitted in partial fulfilment of the

requirements of the University of Brighton, for

the degree of PhD.

May 2010

Page 2: Waste management model

2

ABSTRACT

The pressure at the turn of the 21

st century for Waste Disposal Authorities to change their

waste disposal systems was both urgent and comprehensive, with emphasis being placed on

moving towards the 3Rs; Reducing, Recycling and Recovering value from Municipal Wastes.

This thesis explores how a mass balance model was created for the Brighton & Hove City

and East Sussex County council Private Finance Initiative (PFI) contract, in response to the

pressures for change and need for investment up to 2002. An identification and evaluation of

the drivers for change at the time has been undertaken; with it being demonstrated that

legislation, lack of landfill space and underlying public pressure were the stimulus for

change. A review of the technologies available to implement a systematic overhaul of the

waste facilities is presented with a rationale for chosen technologies. A critical review was

made of tools available to assist local authority waste managers plan for new technologies;

concluding that there were no models fit for purpose. A Mass Balance Model (MBM) is

presented which was developed to allow the councils to plan for a new system of

technologies while meeting the pressures of legislation and public opinion. The MBM

enabled users to model for twenty five years. The model embraces waste growth, numerous

current and future technologies incorporating capacity, throughputs, efficiencies and residuals

to predict recycling, recovery rates, diversion from to landfill and void space required. The

MBM was further developed between 2005 and 2007 to incorporate the impact of new

legislation that required diversion of biodegradable municipal waste from landfill this was the

Landfill Allowance Scheme (LATS). The results from the models conclude that the councils

have had to adopt a mixture of systems and technologies to manage municipal waste whilst

being flexible to future drivers and trends.

Page 3: Waste management model

3

Contents

LIST OF FIGURES ................................................................................................................. 9

LIST OF TABLES ................................................................................................................. 11

ACKNOWLEDGEMENTS .................................................................................................. 12

AUTHOR’S DECLARATION ............................................................................................. 13

DEFINITIONS ....................................................................................................................... 14

1. AN INTRODUCTION TO WASTES MANAGEMENT ............................................ 16

1.1. Aim ............................................................................................................................... 17

1.2. Objectives ..................................................................................................................... 17

1.3. What is waste? .............................................................................................................. 18

1.1. Definition of Municipal Solid Waste (MSW) ............................................................... 19

1.2. Definition of Household Waste (HW) .......................................................................... 20

1.3. Waste collection responsibilities................................................................................... 21

1.3.1. Waste Collection Authority (WCA) ............................................................................. 21

1.3.2. WCA responsibility for recycling household waste ..................................................... 23

1.4. Responsibility for disposing of household waste.......................................................... 23

1.4.1. Waste Disposal Authorities (WDA) ............................................................................. 23

1.4.2. Unitary Authorities ....................................................................................................... 24

1.4.3. Civic Amenity sites ....................................................................................................... 24

1.5. Quantity and the mass flow of MSW arising in England in 2002/03 ........................... 25

1.6. Composition of MSW ................................................................................................... 26

1.7. Conclusion .................................................................................................................... 28

2. DRIVERS FOR CHANGE......................................................................................... 29

2.1. East Sussex and Brighton & Hove Councils................................................................. 29

2.2. Arrangements for the treatment, processing of HW & MSW prior to 2002 ................. 30

2.3. Recycling ...................................................................................................................... 31

2.3.1. Kerbside collection and recycling schemes .................................................................. 31

2.3.2. Civic Amenity (CA) Sites ............................................................................................. 33

2.4. Waste transfer stations .................................................................................................. 34

2.5. Densified Refuse Derived Fuel (dRDF) production ..................................................... 34

2.6. Landfill .......................................................................................................................... 35

2.7. The Legislative drivers for change in East Sussex and Brighton and Hove ................. 35

2.7.1. Making Waste Work ..................................................................................................... 35

Page 4: Waste management model

4

2.7.2. The Landfill Tax ........................................................................................................... 36

2.7.3. A Way with Waste ........................................................................................................ 37

2.7.4. Waste Strategy 2000 ..................................................................................................... 38

2.7.5. Guidance on Municipal Waste Management Strategies (March 2001) ........................ 38

2.7.6. Waste Not, Want Not .................................................................................................... 39

2.8. European Legislation .................................................................................................... 40

2.8.1. The EU Landfill Directive ............................................................................................ 41

2.8.2. The European Waste Incineration Directive (WID) ..................................................... 42

2.9. Public perception .......................................................................................................... 42

2.10. Next steps for ESCC & BHC ........................................................................................ 42

2.11. The Private Finance Initiative (PFI) contract................................................................ 43

2.12. Summary of pressures ................................................................................................... 43

3. THE ALTERNATIVES TO LANDFILL DISPOSAL AVAILABLE TO ESCC

AND BHC IN 2002 ................................................................................................................. 45

3.1. Managing MSW according to The Waste Hierarchy .................................................... 45

3.2. Level 1: Waste reduction .............................................................................................. 46

3.3. Level 2: Re-use ............................................................................................................. 47

3.4. Level 3a: Recycling ...................................................................................................... 47

3.4.1. Kerbside sort ................................................................................................................. 48

3.4.2. Co-mingled collection with separation ......................................................................... 49

3.4.3. Two stream co-mingling ............................................................................................... 50

3.4.4. Maximising recycling from household collections ....................................................... 50

3.5. Level 3b: Composting ................................................................................................... 51

3.5.1. Home composting ......................................................................................................... 52

3.5.2. Open composting from source segregated MSW ......................................................... 52

3.5.3. Closed composting ........................................................................................................ 53

3.5.4. The case for composting waste ..................................................................................... 54

3.6. Level 4: Energy recovery with heat and power ............................................................ 54

3.6.1. Mass burn incineration .................................................................................................. 55

3.6.1.1. The process of energy recovery from mass burn incineration............................... 57

3.6.1.2. Emission Control from EFW ................................................................................. 57

3.6.1.3. Case Study: SELCHP ............................................................................................ 58

3.6.2. Anaerobic Digestion ..................................................................................................... 59

3.6.2.1. The Valorga system ............................................................................................... 61

Page 5: Waste management model

5

3.6.2.2. The Dranco (Dry Anaerobic Composting) system ................................................ 62

3.6.2.3. The Kompogas system........................................................................................... 62

3.6.2.4. Discussion .............................................................................................................. 63

3.6.3. Pyrolysis and thermal gasification ................................................................................ 64

3.6.4. Preferred energy recovery technology .......................................................................... 64

3.7. Level 4 and 5: Landfill and landfill with energy .......................................................... 64

3.7.1. Landraise ....................................................................................................................... 67

3.7.2. The use of landfill gas for the production of energy ..................................................... 67

3.8. Development of a specification for the award of the ESCC & BHC PFI contract ....... 68

3.9. Summary ....................................................................................................................... 70

4. CRITIQUE OF CURRENT WASTE PLANNING MODELS ................................... 71

4.1. Needs analysis for a novel waste flow model ............................................................... 71

4.2. Critical review of existing MSW balance models ........................................................ 73

4.2.1. Cost benefit analysis (CBA) model .............................................................................. 73

4.2.2. Life Cycle Assessment (LCA) models ......................................................................... 74

4.2.3. Multi-criteria decision analysis (MCDA) ..................................................................... 76

4.3. Assessment of critical review and relevancy to needs of local authorities ................... 77

4.4. Summary of CBA, LCA and MCDA ............................................................................ 79

5. DEVELOPMENT OF THE MASS BALANCE MODEL (MBM)......................... 80

5.1. The Development of the MBM ..................................................................................... 80

5.2. MBM description .......................................................................................................... 81

5.2.1. Input sheet ..................................................................................................................... 82

5.2.2. The MBM Calculation Sheet ........................................................................................ 84

5.2.3. Results sheet.................................................................................................................. 86

5.3. The Creation of a Reference Scenario .......................................................................... 87

5.4. Reference Scenario 1 (RS1) .......................................................................................... 88

5.5. Stage 1: Initial waste mass data (starting data and growth modelling)......................... 88

5.5.1. Raw data for the base year ............................................................................................ 89

5.5.2. Waste growth profiling ................................................................................................. 89

5.5.2.1. Lifestyle choices of the individual......................................................................... 90

5.5.2.2. Exogenous contributing factors ............................................................................. 91

5.5.3. Historical data ............................................................................................................... 91

5.5.4. Generation of a growth profile ...................................................................................... 92

Page 6: Waste management model

6

5.6. Stage 2: Individual facility and process throughputs .................................................... 94

5.6.1. Material Recycling Facilities (MRFs) .......................................................................... 95

5.6.2. Open composting .......................................................................................................... 97

5.6.3. In-vessel composting .................................................................................................... 97

5.6.4. Energy recovery ............................................................................................................ 98

5.6.4.1. Anaerobic Digestion (AD)..................................................................................... 98

5.6.4.2. Energy from Waste (EFW) .................................................................................. 100

5.6.4.3. Landfill ................................................................................................................ 102

5.6.5. Bring banks ................................................................................................................. 103

5.6.6. Non governmental organisation (NGO) recycling ...................................................... 104

5.6.7. Beneficial use and diversion from landfill .................................................................. 104

5.7. Stage 3: Relative contributions of facilities and processes to overall outputs ............ 104

5.7.1. Use of targets for comparison ..................................................................................... 105

5.7.2. Calculation of the recycling and composting rate....................................................... 106

5.7.3. Calculation of the recovery rate .................................................................................. 106

5.7.4. Comparator of outputs vs. required outcomes ............................................................ 107

5.7.5. Calculation of landfill volume requirements .............................................................. 107

5.8. Stage 4: Testing the MBM .......................................................................................... 108

5.8.1. Mathematical correctness............................................................................................ 108

5.8.2. MBM flexibility .......................................................................................................... 108

5.9. Stage 5: The MBM results sheet and graphical outputs ............................................. 110

5.9.1. Discussion of the results from Scenario RS1 .............................................................. 114

5.9.1.1. Recycling ............................................................................................................. 117

5.9.1.2. Recovery .............................................................................................................. 118

5.9.1.3. Description of operational characteristics of EfW .............................................. 118

5.9.2. Landfill ........................................................................................................................ 119

5.10. Summary ..................................................................................................................... 120

6. THE DEVELOPMENT, TESTING AND ANALYSIS OF RESULTS OF THE

LATS MASS BALANCE MODEL (LMBM). ................................................................... 121

6.1. New Legislation .......................................................................................................... 121

6.1.1. The Waste and Emissions Trading (WET) Act .......................................................... 122

6.1.2. The Landfill Allowances and Trading Scheme (England) Regulations 2004 ............ 124

6.1.3. Landfill Allowances and Trading Scheme (England) (Amendment) Regulations 2005

125

Page 7: Waste management model

7

6.2. The LATS targets ........................................................................................................ 125

6.3. Introduction of new concepts to the MBM ................................................................. 127

6.3.1. Concept 1: To build sufficient facilities to meet the LATS targets ............................ 127

6.3.2. Concept 2: Trading LATS to meet the targets ............................................................ 128

6.4. Adding new concepts to the MBM, constructing and testing the LMBM .................. 128

6.5. Assumptions used with the testing of the LMBM ...................................................... 129

6.5.1. Waste growth .............................................................................................................. 129

6.5.2. Composition of the waste stream ................................................................................ 129

6.5.3. Completion of key facilities ........................................................................................ 129

6.5.4. Recycling and recovery performance ......................................................................... 130

6.6. Descriptions of scenarios tested through the LMBM ................................................. 130

6.7. Scenario 1.................................................................................................................... 131

6.7.1. Scenario 1A: Base Case with £150 fines and £10 sales.............................................. 131

6.7.2. Scenario 1B Base case with £100 fines and £25 sales ................................................ 133

6.7.3. Scenario 1C Base Case with £50 fines and £50 sales ................................................. 134

6.8. Scenario 2.................................................................................................................... 135

6.8.1. Scenario 2A: one year delay of the EFW with £150 fines and £10 sales ................... 135

6.8.2. Scenario 2B: one year delay of the EFW with £100 fines and £25 sales ................... 137

6.8.3. Scenario 2c: one year delay of the EFW with £50 fines and £50 sales ...................... 137

6.9. Scenario 3.................................................................................................................... 138

6.9.1. A Planning delay of two years .................................................................................... 138

6.10. Analysis of the three scenarios ................................................................................... 140

6.11. Conclusion .................................................................................................................. 141

7. SUMMARY AND DISCUSSION ............................................................................ 142

7.1. Objectives ................................................................................................................... 143

7.1.2. Objective 2: Explore the drivers for change for local authorities ............................... 146

7.1.2.1. The changing composition of MSW .................................................................... 148

7.1.2.2. The Pre budget reports ......................................................................................... 149

7.1.3. Objective 3: Describe the available technologies for management of wastes ............ 150

7.1.4. The ESCC & BHC PFI facilities ................................................................................ 152

7.1.5. Objective 4: Use the drivers and responsibilities to create a mass balance model

(MBM) and describe the process of building the MBM and testing it .................................. 153

7.1.6. Objective 5: Describe the impact of new legislation on the results of the MBM and the

requirement for a revised model to take account of new drivers. .......................................... 154

Page 8: Waste management model

8

7.1.7. Objective 6: Explain the improvements & difficulties found whilst undertaking this

thesis 154

7.1.7.1. Improvement no 1: Enabling facilities to be added other than the options given155

7.1.7.2. Improvement no 2: Developing a model comparison system ............................. 155

7.1.7.3. Improvement no 3: Develop a waste composition element ................................. 155

7.2 Further research opportunities .................................................................................... 156

7.2.1 Research option 1: Climate change and green house gas emissions .......................... 156

7.2.2 Research Option 2: Funding commitments and risk posed by entering into a PFI

contract ................................................................................................................................... 157

7.2.3 Research option 3: Waste as a Resource ..................................................................... 157

7.2.4 Research opportunity summary .................................................................................. 158

7.2. Conclusion .................................................................................................................. 159

References ............................................................................................................................. 161

Appendix 1 Local Authority Officer Questionnaire ......................................................... 171

Appendix 2: RS1 .................................................................................................................. 173

The RS1 Calculation sheet: ................................................................................................. 175

Appendix 3: The MBM test mass flow diagrams: ............................................................. 185

Appendix 4: The MBM USER MANUAL ......................................................................... 193

Appendix 5: RS1 Calculations sheet formulas .................................................................. 212

Appendix 6: National LATS Survey .................................................................................. 234

Page 9: Waste management model

9

LIST OF FIGURES

Figure 1.1: Percentage distribution of types of waste (by weight) in the UK ………….........

Figure 1.2: Percentage distribution of types of MSW, by weight, in 2002/03 ………………

Figure 1.3: The English Waste Collection Authority political boundary areas……………...

Figure 1.4: Percentage distribution of management of MSW, by weight, in 2002/03 .................

Figure 1.5: Composition of MSW (Parfitt 2002) ..........................................................................

Figure 1.6: An indication of the change in MSW composition over time ....................................

Figure 2.1: The political boundaries within the case study area ...................................................

Figure 2.2: MSW generated by householders in ESCC & BHC between 1995/6 &

2001/2 .......................................................................................................................................

Figure 2.3 Location of civic amenity sites in the East Sussex area 2001 .....................................

Figure 3.1: The Waste Hierarchy (Waste Not want Not 2002) ....................................................

Figure 3.2: MSW composting options (adapted from ETSU 1999) .............................................

Figure 3.3: Le-Harve Open composting site (Greenfield 2001 ....................................................

Figure 3.4: Varen Jarcy Enclosed composting windrows (Greenfield 2001) ...............................

Figure 3.5: A Schematic of a generic EFW Facility (Mercia Waste) ...........................................

Figure 3.6: The VESTA Energy from Waste facility at Rouen (Greenfield 2001) ......................

Figure 3.7. Schematic representation of the single-step process. (Wellinger, 1999)....................

Figure 3.8: Brecht II - DRANCO exterior view (Greenfield 2000) .............................................

Figure 3.9: The profile of double lined landfill (Shevon & Damas 1986) ...................................

Figure 3.10: Beddingham Landfill site base construction (Greenfield 2000) ..............................

Figure 3.11 Beddingham landfill site: view into a new cell being prepared for lining ................

Figure 3.12: Le-Harve landraise site cell construction (Greenfield 2001) ...................................

Figure 3.13 Beddingham landfill site gas extraction pipe network (Greenfield 2000) ................

Figure 4.1: System boundaries for measuring and regulating environmental

performance ...............................................................................................................................

Figure 4.2: Elements from which a national separation strategy can be compiled. .....................

Figure 5.1: The components of the integrated waste management system for RS1 .....................

Figure 5.2: Decision tree for the mass flow of MSW through the facilities .................................

Figure 5.3 Housing growth scenario for ESCC and BHC ............................................................

Figure 5.4 Growth rate scenarios used for sensitivity analysis……………………………..

Figure 5.5 AD mass balance diagram (Organic Waste Systems 2000) ........................................

Figure 5.6: Mass flow diagram for parameters to be used in EFW section RS1 ..........................

Figure 5.7: Mass Flow diagram for Option 1 (t= tonnes)…………………………...………

Figure 5.8: MBM Results for RS1: Total recycling and recovery rate per annum………....

Figure 5.9: MBM Results for RS1: The total waste treated annually through all facilities...

Figure 5.10: RS1 Recovery targets for VSD solution ..................................................................

Figure 5.11: Landfill void space required for RS1 .......................................................................

Figure 6.1: BMW needed to be diverted to meet LATS targets in England at 2% per

annum waste growth ..................................................................................................................

Figure 6.2: A comparison of BMW required to be diverted from landfill to meet LATS

targets for a 2% and 3% waste growth scenario ........................................................................

19

20

22

25

26

27

29

30

33

46

51

52

53

56

57

60

62

65

66

67

67

68

75

77

82

85

93

94

98

100

109

115

116

118

119

123

124

Page 10: Waste management model

10

Figure 6.3: Summary of Scenario 1 modelling for LATS ............................................................

Figure 6.4: Scenario 2A LATS deficit or surplus in ESCC if the EFW is delayed by 1

yr...

Figure 6.5: Comparison of BMW to landfill and LATS allowances if the EFW is

delayed by 2 years .....................................................................................................................

Figure 6.6: Sensitivity analysis results of scenario 3 cost of LATS if the EFW is

delayed by 2 years .....................................................................................................................

Figure 6.7: The fine or income attributable each year as a result of scenario 1A, 2A

&3A..

Figure 7.1 Mass flow of 2007/8 English MSW arisings (tonnes per annum)……….......

Figure 7.2: An illustration of the potential Mechanical Biological Treatment

options…….....................................................................................................................

132

135

139

140

141

144

151

Figure 7.3: The EfW and MBT construction pipeline (IESE 2009)…………………… 152

Figure 7.4: Artists impression of the new ERF at

Newhaven…………................................

153

Page 11: Waste management model

11

LIST OF TABLES

Table 1.1: Collection authority responsibilities…………………………………………….. 22

Table 1.2: Comparison of recycling activities in England between 2001 & 2003…………. 26

Table 2.1: Summary of recycling schemes in the area…………………………………… 32

Table 2.2: ESCC & BHC HWRS statistics for 2000/01……………………………………. 33

Table 2.3: Key Commitments in ―A Way with Waste‖……………………………………. 37

Table 2.4: Statutory Performance Standards for the WCAs and WDAs…………………… 39

Table 2.5: Recommendations for a new strategy…………………………………………... 40

Table 2.6: The Landfill Directive Targets for the UK ……………………………………... 41

Table 3.1: Measures of emission pollution control………………………………………… 58

Table 3.2: Commercial high-solids anaerobic digestion plants……………………………. 61

Table4.1: Priority factors for ease of use by local authority officers ……………………… 72

Table 4.2: A critical view of existing waste management models ………………………… 78

Table 5.1: The components of the integrated waste management system for MBM ……. 83

Table 5.2: Base-data used in MBM …................................................................................... 85

Table 5.3: An extract from the MBM results sheet ………………………………………

Table 5.4: MSW arising and growth rates for all ESCC and BHC authorities 1997-2002 ...

86

91

Table 5.4: The MBM Base Data Table (BDT)……………………………………............... 92

Table 5.5: Facility capacity and efficiencies used within RS1……………………………..

Table 5.6: EFW parameter assumption for RS1 for the year 2015/16 ……………..………

95

101

Table 5.7: Volume of one tonne of waste being sent to landfill …………………………… 103

Table 5.8: Output categories found in RS1………………………………………………… 105

Table 5.9: Summary of results from MBM Scenario 1-8 testing ….………………………. 109

Table 5.10: The MBM Result sheet for the RS1 scenario (part 1)………………………... 111

Table 5.11: The MBM Result sheet for the RS1 scenario (part 2)………………………... 112

Table 5.12: The MBM Result sheet for the RS1 scenario (part 3)………………………... 113

Table 5.13: The facilities procured through the PFI contract using RS1…………………. 117

Table 6.1: The English Landfill Directive targets ………………...……………………….. 123

Table 6.2: The rules for Banking and Borrowing LATS…………………………………… 126

Table 6.3: Base case capacity and construction timelines………………………………….. 130

Table 6.4: The scenarios tested to demonstrate the impact of LATS price & facility delay.. 131

Table 6.5: Scenario 1A results: fines £150 per tonne & sales at £10 per tonne……………. 132

Table 6.6: Scenario 1B results: fines £100 per tonne & sales at £25 per tonne……………. 133

Table 6.7: Scenario 1C results: fines £50 per tonne and sales at £50 per tonne…………… 134

Table 6.8: Scenario 2A results: fines £150 per tonne & sales at £10 per tonne…………… 136

Table 6.9: Scenario 2B results: fines £100 per tonne & sales at £25 per tonne……………. 137

Table 6.10: Scenario 2C results: fines £50 per tonne and sales at £50 per tonne………….. 138

Table 7.1: Analysis of Kerbside collection types ………………………………………….. 145

Table 7.2 Table of actions and potential for waste minimisation…………………………... 147

Table 7.3: The size of the waste to energy opportunity…………………………………….. 151

Page 12: Waste management model

12

ACKNOWLEDGEMENTS

There are many people to whom I am indebted to for support during the course of this work,

to all of them I am very grateful, in particular, I would like to thank:

• Prof Marie Harder, for believing in me when many did not and encouraging and

supporting me throughout the many years,

• My wife Julie Greenfield, for her patience, love and support throughout the long

weekends and nights,

• Prof Alison Bruce, as a supervisor and critical analyser who was not afraid to

speak her mind and without whom I would not have completed the thesis,

• Dr Ryan Woodard, for his assistance in the structure of the thesis and his honesty

as a colleague and friend,

• Prof Chris Coggins, for his critical assessment that proved most useful,

• East Sussex County Council and Brighton & Hove City Council staff and

colleagues for their insights and openness, and finally,

• Dr Andrew Larner for allowing me the opportunity to complete this thesis, whilst

holding down a full time job.

Page 13: Waste management model

13

AUTHOR’S DECLARATION

I declare that the research contained in this thesis, unless otherwise formally indicated within

the text, is the original work of the author. The thesis has not been previously submitted to

this or any other university for a degree, and does not incorporate any material already

submitted for a degree.

Signed

David W. J. Greenfield

Date: 1st May 2010

Page 14: Waste management model

14

DEFINITIONS

“Aerobic Digestion” the decomposition of waste under microbial action in the presence of

oxygen

“Anaerobic Digestion” the decomposition of waste under microbial action in the absence of

oxygen

“Bring Bank” a facility provided for the deposition of recyclable materials by the general

public

“Clinical Waste” has the meaning given in paragraph (2) of the Controlled Waste

Regulations 1992

“Commercial Waste” has the meaning given in section 75 (7) of the EPA

“Composting” the autothermic and thermophilic decomposition of separately collected

biodegradable waste in the presence of oxygen and under controlled conditions by the action

of micro- and macro-organisms in order to produce compost

“DEFRA” the Department of Environment, Food and Rural Affairs

“Digestate” the solid compost-like material resulting from the processing of waste by

anaerobic digestion

“dRDF” densified refuse derived fuel

“Energy Recovery” recovery of energy from Waste by:

(a) incineration; or

(b) any other combustion process; or

(c) by anaerobic digestion

“EPA” the Environmental Protection Act 1990

“Household Waste”

(a) waste from the household collection rounds which the WCAs have a duty to collect

under s45 (1)(a) of the EPA

(b) waste from bulky household waste collection, hazardous household waste collection,

household clinical waste collection and separate garden waste collection;

Page 15: Waste management model

15

(c) waste from street sweeping and litter collections collected by or on behalf of councils

under s89 (1)a and 89(2) of the EPA; and

(d) waste from Household Waste Recycling Sites excluding construction and demolition

waste deposited by the general public at any household waste recycling site;

“Kerbside Schemes” any regular collection of recyclable materials by house-to-house

collection from households (excluding services provided on demand)

“Landfill” has the meaning attributed to it by section 65(1) of the Finance Act 1996

“MRF” a materials recovery facility where such of the recyclable materials are either

mechanically or manually separated and bulked up prior to reprocessing

“PFI” HM Government‘s Private Finance Initiative

“Recovery” either or recycling, composting; and energy recovery

“Recycled Materials” materials resulting from the reprocessing of waste physically,

chemically or biologically into a product whether for the original purpose or not and which

material has been delivered to an end market

“Recycling Credit” a payment made under Section 52(1), (3) and/or (5) of the EPA

“WCA” a Waste Collection Authority as defined by section 30(2) of the EPA within the

Councils‘ Area

“WDA” a Waste Disposal Authority as defined by section 30(3) of the EPA

Page 16: Waste management model

16

1. AN INTRODUCTION TO WASTES MANAGEMENT

Ever since humans have lived in organised communities, waste management has been a

necessity of human life (Fenton 1975, Rushbrook & Finnecy 1987). Disposing of waste has

always been a challenge, early attempts included the use of a midden; an old English word,

derived from Norse, meaning rubbish dump (Gray 2002). The East Chisenbury midden

situated on Salisbury Plain dates back to the first millennium B.C. (McOmish 1996) and

would be classified under current legislation as a landfill site. Waste management techniques

have changed over time from the midden to the industrial revolution: hills consisting of slate

and oil-shale wastes (Gray 2002), having given way to present day techniques of landfill,

incineration and the opportunity to recycle.

Waste has always been seen as a potential income, indeed the phrase ―where there‘s muck

there‘s brass‖ is universally known. However, gaining this value is more difficult; Fenton

described finding the ―gold in waste‖ as being as elusive as a cure for cancer (Fenton 1975).

In twenty-first century Britain the cost of waste management to the public purse is high. It is

estimated that collectively, the responsible bodies within local authorities spend nearly £3

billion a year on managing waste from households (DEFRA 2002). This cost is set to increase

significantly as legislation drives waste away from landfills.

This thesis contextualises the drivers for change, researches and explores the pressures and

solutions. It introduces a case study area and presents two iterations of a new Mass Balance

Model (MBM) developed by the author for one of the responsible authorities; a waste

disposal authority (WDA). The model enables planning for the management of wastes

through disposal, or treatment of wastes generated by homo-sapiens‘ daily living practices.

The first three chapters will present the drivers, metrics and technologies considered up to

2004 that gave rise to development of the MBM, this described in chapter four. The

remaining chapters will contextualise the impacts of new legislation and the requirement for a

revised MBM.

Page 17: Waste management model

17

1.1. Aim

Waste is defined by the UK government as any ―substance which constitutes scrap material

or an effluent or other unwanted surplus substance arising from the application of a process,

or any substance or article which requires to be disposed of as being broken, worn out,

contaminated or otherwise spoiled‖ (EPA 1990). This definition applied to over 330 million

tonnes of material in the UK in 2002/3.

The focus of the research is waste generated by households and the small proportion of

commercial and industrial waste that are collected and disposed of by local authorities in the

UK. This material is commonly defined as Municipal Solid Waste (MSW) (Read 1999), and

amounted to 29.39 million tonnes in 2002/3 (Environment Agency 2003), representing

approximately 10% of total gross waste. Managing nearly 30million tonnes per annum

requires exceptional planning and logistical input. To support this, the aim of this thesis is to

create, test and apply a Local Authority Mass Balance Model (MBM) that will enable

responsible local authority officers to plan for the future management of municipal solid

waste with a greater degree of understanding of the risks and logitistics.

1.2. Objectives

To plan for the management of waste, an understanding of the options, drivers, barriers and

concepts is required. The generation and disposal of waste has become an important policy

concern in all industrialised economies (Read 1999). Considerable work has been undertaken

since the early 1900‘s to manage waste and the systems and technologies that have been

implemented by councils range from the rag and bone man to waste destructors (Woodard

2002). Waste management is an important, complex and necessary service to ensure the

environment that we dwell in is clean and safe, the thesis has the following objectives:

Objective 1: Indentify the roles and responsibilities of wastes management and

impacts thereof

Objective 2: Explore the drivers for change for local authorities

Objective 3: Explore the available technologies for management of wastes in 2002

Page 18: Waste management model

18

Objective 4: Use the drivers and responsibilities to create a mass balance model

(MBM) and describe the process of building the MBM and testing it

Objective 5: Identify the impact of new legislation on the results of the MBM and the

requirement for a revised model to take account of new drivers.

Objective 6: Explain the improvements and difficulties found whilst undertaking this

thesis

An analysis of whether these objectives were achieved during the research will be presented

in Chapter 7.

1.3. What is waste?

Waste is defined as ―any substance or object which the holder disposes of or is required to

dispose of pursuant to the provisions of national law in force‖ (Council Directives

75/442/EEC and 78/319/EEC). The UK government interpretation was set out the in the

Environmental Protection Act 1990 as:

(a) any substance which constitutes a scrap material or an effluent or other unwanted

surplus substance arising from the application of any process; and

(b) any substance or article which requires to be disposed of as being broken, worn

out, contaminated or otherwise spoiled (EPA 1990)

By 1991 the EU had amended this definition to ―any substance or object in the categories set

out in Annex 1 to the Directive 91/156/EEC, which the holder discards or intends to discard‖

(DOE Circular 1992). Waste in the UK is split into eight categories, as shown in Figure 1.1.

The waste is shown as a percentage of weight arising, and not volume, which is sometimes

used for quantifying wastes. If volume were to be used, then the proportional split of waste in

Figure 1.1 would change. For example, plastic agricultural film is exceptionally light, but

extremely voluminous (Lee 2002). The largest sources of waste in the UK are from mining,

quarrying, construction and demolition activities, collectively responsible for creating 61% of

all waste. In 1990 the EEC introduced the definition of ―controlled waste‖, which defined

household, industrial and commercial wastes (DOE circular 1992). It can be seen by Figure

1.1 that controlled waste, which has subsequently become colloquially known as Municipal

Solid Waste (MSW), equates to 21% of all wastes or 114 million tonnes arising per annum.

Page 19: Waste management model

19

The proportion of MSW managed by councils in England is 9%, the MSW arising and

management of wastes now and into the future, in one geographical area, will be the focus of

thesis.

Figure 1.1: Percentage distribution of types of waste (by weight) in the UK (DEFRA 2004)

To understand the proportion of MSW that WDAs manage, it is necessary to examine the

definitions of waste. Defining waste is important to allow an understanding of who is

responsible for managing that waste, calculating targets and allowing comparisons of costs

and service on like-for-like basis. Until the definition is confirmed ambiguity will remain

over who is responsible for what.

1.1. Definition of Municipal Solid Waste (MSW)

There has been much comment on the definitions of MSW, Burnley states that MSW is

defined in terms of the waste collection operation rather than in terms of source or

composition (Burnley 2001), Read defines MSW as any ―substance or object which the

holder discards or intends to discard‖ (Read 1991). The European Commission defines MSW

as ―waste from households, as well as other waste, which, because of its nature or

composition, is similar to waste from households‖ (Council Directive 1999/31/EC).

The EC definition has been accused of being too ambiguous (Reed 2004, Burnley 2001) as it

does not qualify waste by type rather by source, defining waste by composition would allow

Page 20: Waste management model

20

for a much greater analysis of materials and possible uses. DEFRA used the Council

Directive 1999/31/EC definition in the Waste Emissions Trading Act 2003 (WET act 2003),

however, section 6 of the LATS Guidance published by DEFRA in August 2004 stated that

"The Government's view is that the definition … encompasses all waste under the control of

the local authorities be they waste disposal, waste collection or unitary authorities‖ (DEFRA

2004). This research will use the 2004 definition of MSW; waste under the control of the

local authority as defined by DEFRA, as that is the definition that WDAs will use for

reporting and managing waste. MSW is divided into different generation categories to

understand the source and subsequent composition of the wastes, figure 1.2 shows the seven

categories usually used.

Figure 1.2: Percentage distribution of types of MSW, by weight, in 2002/03 (DEFRA 2004)

The proportional split of the components of the 29.3 million tonnes MSW collected in

England in 2002/03 are shown in Figure 1.2, an increase of 1.8 per cent over the 28.8 million

tonnes collected in 2001/02.

1.2. Definition of Household Waste (HW)

Household Waste (HW) comprises 88% of MSW and accounts for 9% of all wastes in the

UK (DEFRA 2004). The Controlled Waste Regulations (CWR) 1992, Section 1 and 2 define

household waste as waste from:

Page 21: Waste management model

21

(a) Domestic property, that is to say, a building or self-contained part of a building

which is used wholly for the purposes of living accommodation;

(b) a caravan (as defined in section 29(1) of the [1960 c. 62.] Caravan Sites and

Control of Development Act 1960) which usually and for the time being is situated on

a caravan site (within the meaning of that Act);

(c) a residential home;

(d) premises forming part of a university or school or other educational

establishment;

(e) premises forming part of a hospital or nursing home

Further to this definition, in the 1992 DOE circular, clarification of what was meant by

premises was given as everything from a charity to a Royal Palace (DOE 1992). It is not

necessary to explore the intricate details of the definition, suffice to say that the definition of

household waste can be interpreted in many ways. For the purpose of this research household

waste will constitute any waste that fits the criteria in the Controlled Waste Regualtions 1992

and is under the control of the local authority or its agent, again as this is the definition that

will be needed to calculate and report on targets.

1.3. Waste collection responsibilities

Once the definition of waste has been defined, it is necessary to understand who is

responsible for the collection of MSW. Waste collection has its origins in the 1936 Public

Health Act (Price 2001), where it was the responsibility of councils to collect potentially

polluting waste, the responsibility evolved so that Waste Collection Authorities (WCAs) now

have the statutory duty of collecting household waste free of charge (DoE, 1975).

1.3.1. Waste Collection Authority (WCA)

A Waste Collection Authority (WCA) is defined in the EPA 1990 Part II Para 30 (3) as ―any

district or borough in England, and any borough in London, including the City of London”.

In 2002 there were 354 WCAs in England, as shown in Figure 1.3, of these 81 were unitary

authorities and the remaining 273 were situated within the 40 County Council areas that are

Page 22: Waste management model

22

WDAs. Figure 1.3 shows the political boundaries of all WCA‘s and indicates the diverse

geographical size which can lead to significant variation in application of responsibility.

Figure 1.3: The English Waste Collection Authority political boundary areas (including

unitary councils) (LGA 2000)

The responsibilities for WCAs are contained within the EPA; Part II Para 45 (1); Table 1.1

shows the extent of responsibility for collecting waste.

It shall be the duty of each waste collection authority—

(a) to arrange for the collection of household waste in its area except waste—

(i) which is situated at a place which in the opinion of the authority is so isolated or

inaccessible that the cost of collecting it would be unreasonably high, and

(ii) as to which the authority is satisfied that adequate arrangements for its disposal

have been or can reasonably be expected to be made by a person who controls the

waste; and

(b) if requested by the occupier of premises in its area to collect any commercial waste from

the premises, to arrange for the collection of the waste.

Table 1.1: Collection authority responsibilities (EPA, 1990, Part II Para 45 (1))

Page 23: Waste management model

23

WCAs therefore have a duty to collect waste from everywhere that generates household

waste, unless inaccessible, as well as waste from commercial premises, if requested.

1.3.2. WCA responsibility for recycling household waste

The EPA 1990 states that each WCA will have a duty, as respects household and commercial

waste arising in its area – to (a) carry out an investigation with a view to deciding what

arrangements are appropriate for dealing with the waste by separating, baling or otherwise

packaging it for the purpose of recycling it (EPA, 1990, Part II Para 49, 1). This gives the

WCA the duty to recycle waste arising in its area and consequently recycle it. Questions

remain over who is responsible for and how municipal solid waste should be collected and

recycled and will be explored in Section 1.4.

1.4. Responsibility for disposing of household waste

The responsibility for disposing of the waste presented by the WCAs is set out in EPA, where

it states that Waste Disposal Authorities (WDA) will be responsible (a) for the disposal of the

controlled waste collected in its area by the waste collection authorities; (EPA Part II Para

51 (1)). This allows Waste Disposal Authorities (WDAs) to configure a solution for

disposing of waste that is of a larger scale and has the potential to benefit from economies of

scale in any forward purchasing plans.

1.4.1. Waste Disposal Authorities (WDA)

Waste Disposal Authorities (WDAs) in their current configuration were created as a result of

the EPA 1990 and are defined as any non-metropolitan county in England, the area of the

London Waste disposal authority, the city of London, the Metropolitan County of Greater

Manchester and the greater Metropolitan area of Merseyside (EPA Part II Para 30 (1)). The

responsibility for the management of the disposal of waste lies with the WDAs, and in the

twentieth century the predominant technique for treatment has been to landfill it (Fenton

1975, Petts 1991, Read 1999). There are alternative technologies and systems available for

Page 24: Waste management model

24

the management of wastes, but they have previously been considered unproven and costly.

Drivers to move away from landfill will be explored in Chapter 3.

1.4.2. Unitary Authorities

Between 1992 and 2002, the Local Government Commission for England reviewed the

structure of local government. The results of the Commission were controversial and by 1998

had resulted in the abolition of five county councils; Avon, Berkshire, Cleveland,

Hereford and Worcester and Humberside and the creation of unitary authorities covering

many urban areas of England, including cities like Bristol, Brighton & Hove, Hull, Leicester,

Derby, Nottingham, Stoke-on-Trent and Plymouth (Jones et al, 2004), by 2002/03 there were

81 Unitary Authorities. The significant difference in structure is that a Unitary Authority is

both a WCA and a WDA, meaning they were now responsible for the collection and disposal

of wastes (Read 1990). The implications for waste management were significant as these

new authorities had, in most cases previously only been responsible for collecting waste.

There was a real risk that the Unitary Authorities would not have the skill set to manage the

disposal of MSW.

1.4.3. Civic Amenity sites

The Civic Amenity Act 1967, updated and amended by the Refuse Disposal (Amenity) Act of

1978 created the responsibility to provide Civic Amenity sites (CAS) The aim was to avoid

fly-tipping of bulky wastes (including private abandoned vehicles) in the countryside

(Coggins 2002). After 1974 responsibility passed to WDAs (including Unitary Authorities)

and as a result of the EPA Part II Para 51 (1), it was necessary for WDAs to allow ―for places

to be provided at which persons resident in its area may deposit their household waste and

for the disposal of waste so deposited‖. The waste generated at a CAS does not require

collection as it is presented to the council by the public, but separation and treatment on site

are required, which means management of the public is essential to ensure sufficient division

of materials. In 2002/3 4.2 million tonnes of waste was managed by CAS in England,

equating to 15% of MSW a relatively large quantity of waste that is delivered by the

householder to a site, giving operators the opportunity to dictate what waste is recycled. At

this time there was also a propensity at this time to change the name to Household Waste

Page 25: Waste management model

25

Recycling Site or Centre (HWRS or HWRC), to reflect the move towards recycling, rather

than disposal.

1.5. Quantity and the mass flow of MSW arising in England in 2002/03

The definition of MSW has been stated as that in the control of the local authorities. To

understand the total amount of waste that local authorities have responsibility for it is

necessary to look at the source of the data. Each WCA and WDA is required to submit a

quarterly return to the Environment Agency and DEFRA categorising the amount and method

of management per material and system of collection. Figure 1.4 shows the final destination

for the 29.3 million tonnes of MSW collected (DEFRA 2004)

Figure 1.4: Percentage distribution of management of MSW, by weight, in 2002/03 (DEFRA

2004)

Analysis of Figure 1.4 shows that 22 million tonnes of MSW went to landfill; 2.6 million

tonnes were recovered through incineration, whilst 4.6 mtpa were recycled or composted.

Table 1.2 compares the recycling achieved in 2002/03 with 2001/02 and shows that all

variables are interdependent and that change in recycling practice has a huge impact on waste

being treated by other methods, this could potentially alter some of the need for some of the

technologies:

Page 26: Waste management model

26

Table 1.2: Comparison of recycling activities in England between 2001 and 2003 (DEFRA

2004)

Analysis of Table 1.2 shows that an extra 700,000 tonnes of MSW was recycled or

composted in 2002/03 compared to the previous year, this equates to a 18% increase in one

year, a feat that would need to be replicated in a number of years to meet the targets set out in

Section 2.4

1.6. Composition of MSW

The MSW collected and disposed of in England is broadly categorised as collection,

recycling and disposal, as per the responsibilities for collecting it. However these categories

can be further sub-divided into biological waste, paper, plastics, metal, textiles and other.

Figure 1.5: Composition of MSW (Parfitt 2002)

20%

19%

17%

9%

7%

5%

5%

4%

3%

3%

3% 3% 2%

Garden waste

Paper and board

Kitchen waste

General household sweepings

Glass

Wood/Furniture

Scrap metal/white goods

Dense plastic

Soil

Plastic film

Textiles

Metal cans/foil

Disposable nappies

Page 27: Waste management model

27

Figure 1.5 shows that 37% of the waste discarded by households is garden and food waste,

whilst 19% is paper and cardboard and 9% is glass.

The use of a compositional analysis is crucial to preparing plans for the collection and

disposal of waste because it enables councils to target the materials that are most common or

have the highest value. Brunner and Ernst (1985) conclude that analysis of waste is essential

to:

Understand the potential for recycling or for treatment and disposal capacities

Design waste treatment processes properly

Quantify the emissions to the environment from waste management practice

However, with the responsibilities for recycling meaning individual materials can be targeted,

it would appear that different collection practices need to be used for different wastes (Read

1999). Figure 1.6 shows a historical waste analysis of the way composition of the waste

generated by households has changed over the 20th

century.

Figure 1.6: An indication of the change in MSW composition over time (Wastewatch 2004)

Interpretation of Figure 1.6 indicates that the majority of waste generated at the end of the

nineteenth century was dust and cinders. By the end of the twentieth century, this category of

waste no longer existed and had been replaced by a significant increase in organic and paper

Page 28: Waste management model

28

wastes. Indeed in a sixteen year period between 1986 -2002 the proportion of dust and

cinders changed from being 10% of the waste stream to 0%, this demonstrates a major

societal change, resulting from evolution a coal or wood fire to central heating in households.

A comparison between Figure 1.5 and Figure 1.6 shows the percentage of kitchen organic

waste rose from 25% in 1985/6 to 39% in 2002, this highlights how quickly individual

materials can become more significant in the way waste should be collected. The two figures

show the waste composition changes over time, to enable management of waste in such a

way that systems for collection and disposal are relevant, it is therefore necessary to

continually monitor the composition of wastes, indeed, Tyson et al states that in planning for

new infrastructure the need to analyse waste generated is essential (Tyson et al 1996). The

analysis of waste is crucial to anticipate future changes and the fact the snapshot in time when

the composition analysis was made is not certain but only indicative.

1.7. Conclusion

Waste is a substance that is a result of our daily life. It has been demonstrated that waste has

been managed since at least the first century BC and that techniques have changed over that

period. In the UK, the 30 million tonnes of MSW generated by householders are the

responsibility of local government, with WCAs and WDAs needing to manage waste

according to the ―waste hierarchy‖ prevent, reuse, recycle, recover and dispose. Waste has

been shown to be difficult to define, leading to various interpretations, some of which are in

the process of being clarified by government. The potential investment in waste infrastructure

has been shown to be very significant and planning for the future needs of the community is

paramount given the way waste composition can change.

The next chapter will explore the drivers for change facing councils in England at the turn of

the twentieth century and present a case study area; East Sussex County Council and

Brighton & Hove City Council.

Page 29: Waste management model

29

2. DRIVERS FOR CHANGE

This chapter will present the area where the research was undertaken; East Sussex County

Council (ESCC) and Brighton & Hove Unitary Council (BHC) who decided to work together

to benefit from economies of scale. An overview of the case study area and the status of

waste management services and facilities in 2001 will be presented; the drivers for change

will then be explored up to 2002. Having established the drivers for change, chapter three

will explore the technical options available to the councils. The drivers for change and

facilities in place in 2002 will then be used to demonstrate the conditions that led to the

councils needing the author to create the Mass Balance Model, presented in chapter four.

2.1. East Sussex and Brighton & Hove Councils

The two WDAs of ESCC and BHC have responsibility for disposing of waste produced by

households within their boundaries (EPA 1990), the geographical area is shown in Figure 2.1.

The combined population in July 2000 was approximately 758,700 (ONS) and was expected

to grow to 786,000 by 2015 (WLP). It is an area that is characterised by coastal towns and

cities; Eastbourne, Hastings and Brighton & Hove, with the 58% of the county area residents

living in these areas (WLP 2001).

Figure 2.1: The political boundaries within the case study area (ESCC 2001)

The councils have over 50 miles of coastline, 6 of which are designated as Heritage Coast.

East Sussex has 86 Conservation Areas and nearly 5,700 listed buildings with an additional

Brighton & Hove

Lewes

Wealden

Eastbourne

Hastings

Rother

Page 30: Waste management model

30

308 Scheduled Ancient Monuments and a further 670 sites designated as Archaeologically

Sensitive Areas (WLP 2001). East Sussex is made up of six local authorities; the County

Council and five district and borough councils (Eastbourne, Hastings, Lewes, Rother and

Wealden). Brighton Borough Council & Hove Borough Council merged to form Brighton &

Hove Unitary Council in 1997. The area is regarded as affluent; the House prices in East

Sussex almost doubled between 1997 and 2002 to a county average of nearly £128,000 for a

semi-detached property in 2002. Average prices remain highest in Lewes (£151,300) where

they are 50% higher than the lowest priced area, Hastings (£100,800) (ESCC).

The population of East Sussex is are predominantly white and the percentage of ethnic

minorities is changing ever so slightly, in 1991 the percentage of non-white residents was 1.3,

compared to a national average of 6.2, by 2001, this had grown to 2.3% in East Sussex and

9.1% in England, this would indicate that while East Sussex has a predominantly lower

proportion of non-whites, the rate of increase in that population is faster than in England.

2.2. Arrangements for the treatment, processing of HW & MSW prior to 2002

The two authorities have been managing waste since 1974, however it only since 1997 that

both were WDAs and responsible for disposing of waste. Most of the existing waste

management infrastructure was based in the county area of East Sussex as they had

responsibility for the waste arising from Brighton & Hove prior to 1997. By 2002/3 MSW

arising had reached 388,453 tonnes, of which approximately 371,000 tonnes was HW. Prior

to then the amount of waste generated by households in the area is shown in Figure 2.2;

Figure 2.2: MSW generated by householders in ESCC and BHC 1995/6 and 2001/2 (ESCC

2001)

Page 31: Waste management model

31

Interpretation of figure 2.2 shows that MSW in the area grew by 9.5% between 1995 and

2002; a trend of waste growth of 1.2% per annum. The reality is that the waste growth profile

year by year cannot be characterised as a trend, rather, as demonstrated in Figure 2.2, an

intermittent growth profile. The cause of these anomalies are many and varied and are

explored in chapter 4, however the underlying trend for waste arisings in the area does show

that waste generated is growing. The graph does not show the underlying practices in the way

that waste is managed; the following sections will indicate the management practices and

facilities available at the end of the century, re-use and minimisation are not explored in this

section, due to minimal activity.

2.3. Recycling

There are no reprocessing facilities for metal, paper, cardboard, glass, plastics, or textiles

within the area and with the exception of paper taken to Kent, materials are generally

transported to plants in Wales, the Midlands and the North. However, the activities

undertaken in 2000 resulted in recycling rates for the area of around 11% (DEFRA 2002).

Both Wealden District Council and Lewes District Council operate a Material MRF in their

own Districts, with little opportunity to expand on their existing sites (WLP 2000). The

licensed MRF‘s in East Sussex are at Bellbrook, in Uckfield, able to handle 13,500 tonnes per

annum (tpa) and North Street in Lewes, capable of handling 7,000 tpa (PFI OBC 2000).

Some recyclables from the Councils‘ area are taken to West Sussex, where they were bulked

up at Sompting MRF for long-haul transport to reprocessing plants (WLP 2000).

2.3.1. Kerbside collection and recycling schemes

A summary of the materials collected by the WCAs and WDA is given in Table 2.1. The

districts and boroughs had different systems in place for collecting recycling; Wealden DC

had two kerbside collection schemes serving a total of 23,600 properties, known as the

Compost and Recycle Our Waste Now (―CROWN‖) scheme (Wealden DC 2001). In

Eastbourne BC a kerbside scheme for paper and cans covering 8,600 properties was in

operation. Rother DC had no kerbside scheme in place prior to 2003. Hastings BC had

operated a kerbside collection scheme for paper serving 26,500 properties from 2001, whilst

Lewes DC introduced a fortnightly kerbside collection scheme to cover 2,500 properties in

Lewes on 1st March 2002.

Page 32: Waste management model

32

BHC commenced a pilot kerbside opt-in scheme for paper only in May 2001 (Paperchasers),

which initially targeted 11,000 households and extended to another 9,000 households in

November 2001 (PFI OBC 2000). Magpie, a not-for-profit organisation, provided a kerbside

scheme for a range of recyclables. It was an ―opt-in‖ scheme and customers paid Magpie

direct, it was unusual at the time as the cost to the resident was outside of their Council Tax.

Table 2.1: Summary of recycling schemes in the area (WLP, 2000 & PFI OBC 2000)

Home composting is actively encouraged in some areas, with some councils providing

subsidised composting bins and advice on composting. The levels of recycling and facilities

available to the councils are limited and account for a small proportion of the management of

the wastes in the area. Most MSW is collected in black bags or bins and transported to

disposal facilities. It is difficult to get decision makers to fund recycling schemes (A. Peacock

2000)

Green Waste Green Garden Waste is collected in dedicated skips at most Household Waste

Recycling Sites.

Metal Scrap Metal is collected in dedicated skips at most Household Waste Sites

Food and Drinks Cans: are collected through a variety of schemes. Cans collected in

Rother District Council‘s area and Hastings Borough Council‘s area are collected by

SITA and delivered, for sorting, to the MRF at Sompting in West Sussex. Both

Lewes DC and Wealden DC‘s Direct Service Organisations (DSOs) collect mixed

cans and sort them at their respective MRF‘s. Wealden DC also collects cans in

Eastbourne Borough and sorts them at their depot. Brighton and Hove cans from

‗Bring‘ sites are collected and taken to Wealden DC‘s MRF.

Aluminium Foil: is collected at Lewes Civic Amenity Sites. It is passed to a local

scrap metal merchant for recycling.

Glass Glass: is mostly collected by Wealden DC DSO who are contractors for the East

Sussex Recycling Consortium (this includes Brighton and Hove) bottle bank scheme.

The glass is sorted at Wealden DC‘s Depot at Uckfield. Clear, green and amber glass

is sent to either Industrial Reclamations in Kent or to the British Glass Recycling

Company Essex to be recycled

Paper Newspapers and Magazines: there are collection schemes for newspapers and

magazines. They are collected and delivered to Aylesford Newsprint Ltd in Kent.

Cardboard: Brighton and Hove has 11 ‗bring sites‘ for card. In Brighton & Hove

and at Eastbourne and Seaford household waste (Civic Amenity) sites card is

collected by SCA Recycling and taken to Aylesford in Kent. In Hastings cardboard

is currently collected by the site operatives who also arrange for its recycling.

Plastic Plastic Bottles: are collected in Eastbourne, Hastings and Lewes and Rother District

and at Eastbourne Household Waste Site by SITA and taken to the MRF at Sompting

to be sorted, baled and sent for reprocessing. Lewes DC collects plastic bottles and

bales them at their MRF.

Plastic Carrier Bags: There are collection points for plastic carrier bags provided by

Safeway at their stores in Crowborough, Lewes, Eastbourne and Hastings. The

material is back hauled to their distribution centres.

Textiles Textiles: are collected by the Salvation Army. About 20% are reused, as second hand

clothing for local needs, sold through Salvation Army charity shops, jumble sales

and to third world countries. The remainder is non-wearable and is processed and

used to make cleaning and wiper cloths, mattress fillings, blankets and carpets.

Other Waste Soil and Hardcore: Hardcore is collected in dedicated skips at some HWRS

Page 33: Waste management model

33

2.3.2. Civic Amenity (CA) Sites

There were fourteen Civic Amenity sites in the area 2002, which were renamed Household

Waste Recycling Sites (HWRSs), to re-emphasis the recycling agenda, of these; two were in

Brighton & Hove. At the HWRSs, separate dedicated containers for green waste have been

provided at most sites since April 1999, with recycling banks and bulky waste sections being

made available. The green waste was processed at small scale ―on farm‖ facilities or

delivered to the composting facility at Pebsham Landfill site. A summary of the waste

entering and leaving the HWRS is shown in Table 2.2:

HWRS MSW

delivered to sites

MSW to

landfillMSW composted MSW recycled

Recycling and

composting rate

ESCC HWRSs 62,574 49,618 6,700 6,255 20.7%

ESCC & BHC HWRSs 83,891 66,984 9,225 7,682 20.2%

Table 2.2: ESCC & BHC HWRS statistics for 2000/01 (DETR 2001)

The recycling rates of 20 -21% shown by Table 2.2 indicate that a reasonable amount of

recycling is already undertaken at the HWRSs. The location of the HWRSs are shown in

Figure 2.3 as orange boxes, each site is located in or near to an urban centre.

Figure 2.3 Location of civic amenity sites in the East Sussex area 2001 (ONYX 2002)

Page 34: Waste management model

34

2.4. Waste transfer stations

There were two waste transfer stations in the Brighton & Hove area and none in East Sussex.

The Household Waste Site at Leighton Road, Hove doubled up as a waste transfer station

facility that has the same opening hours as the HWRS and bulked the paper from the kerbside

collection scheme. Transfer stations are designed to reduce the amount of time spent by

refuse collection vehicles (RCVs) on a landfill and bulk up waste collected for onward

transportation (Read 1999). The Council‘s in-house refuse collection and street cleansing

contractor used Hollingdean depot in Brighton as a transfer station for the services in BHC.

2.5. Densified Refuse Derived Fuel (dRDF) production

East Sussex County Council has a contract with Reprotech (Pebsham) Ltd for the production

of densified Refuse Derived Fuel (dRDF) in pellet form, due to end in June 2007, but the

facility suffered a major fire in August 2002 (Hastings Observer 2002) and the future of the

plant is unsure. The plant contributed towards diverting from landfill a small proportion of

waste arising in the county area, but was seen by council managers as an unstable solution

and expensive for its diversion capabilities (R. Thomas Interview 2001).

East Sussex County Council directed Eastbourne, Hastings and Rother and Wealden as

WCAs to deliver 75,000 tonnes per annum of collected municipal solid waste to this facility

which was processed and diverted approximately 26,250 tonnes per annum from landfill. The

RDF Plant at Pebsham was built in 1988 (ESCC 2000/01). This ability for the WDA to direct

WCAs comes from the EPA para 48: ―it shall be the duty of each waste collection authority

to deliver for disposal all waste which is collected by the authority under section 45 above to

such places as the waste disposal authority for its area directs‖.

Under normal operating conditions the plant produced approximately 19,000 tonnes of dRDF

pellets, which were not burned on site but transported to Slough Heat & power (ESCC 2000).

As part of the process, approximately 2,000 tonnes of metals (mainly steel cans) were

extracted for recycling. During the drying process prior to pellet production, the moisture

content of the waste was reduced resulting in approximately 5,250 tonnes evaporating as

steam. The rejected material (up to 48,750 tonnes per year) from the pellet making process

was landfilled at the adjacent Pebsham landfill site. (ESCC 2000).

Page 35: Waste management model

35

2.6. Landfill

Landfill is the most commonly used disposal route for MSW, varying from 67% in the North-

East region of England, to 95% in the North-West region (A.D Read 1998). Waste

management in East Sussex and Brighton and Hove relied primarily on two landfills within

the area, Beddingham, near Lewes and Pebsham in Hastings. There was also a landfill site at

Horton in West Sussex that received waste from Brighton & Hove Council. Approximately

306,000 tonnes per annum (85%) of MSW was disposed of via landfill in 2002 to all three

sites (BHC 2002). The contracts for disposal of waste at the landfill sites at Beddingham,

operated by Viridor Waste Management Ltd, and Pebsham, operated by Biffa Waste Services

Ltd, were meant to expire in 2003 when it was projected that the sites would be full.

The 2nd

Deposit of the Waste Local Plan identified ―two sites for non-inert waste in the east

and west to serve the whole Plan Area or one central site to take mainly residues from other

processes, towards the end of the Plan period.‖ The sites were Ashdown Brickworks at

Bexhill with a potential 1.0 million cubic metres (mcm) of void and Beddingham Land

Disposal Site, near Lewes, with an option for an extra 0.8 mcm of void (WLP 2002). There

were no other plans for extending the operation of the sites meaning that the councils had a

limited capacity to dispose of waste generated in their area.

2.7. The Legislative drivers for change in East Sussex and Brighton and Hove

Having established the waste practices and physical limitations of the area, it is necessary to

look at the legislative drivers that were influencing decision making up to 2002. December

1995 saw the start of the modern legislation for WDAs and WCAs with the publication of the

first strategy in England and Wales to be aimed at local government.

2.7.1. Making Waste Work

The White Paper, ‗Making Waste Work‘, was the first attempt at preparing a national waste

strategy (Read 1999) that could be achieved by local government. This was published in

1995 and came at a time when the pressure was increasing to manage the waste generated

within the UK more effectively (Burnley 2001). The main aims of ‗Making Waste Work‘

were based on three key objectives:

Page 36: Waste management model

36

a) to reduce the amount of waste society produces;

b) to make best use of the waste that is produced; and

c) to choose waste management practices which minimise the risks of

immediate and future environmental pollution and harm to human health.

The White Paper set the first specific targets for the recycling and recovery of value from the

waste stream, they were:

a) ―to recycle 25% of household waste by the year 2000‖ and

b) ―to recover value from 40% of municipal solid waste by 2005‖

By 1997 it was evident that the targets would not be met (Burnley 2001) and thus in June

1998 DETR issued a consultation paper on the Waste Strategy for England and Wales,

entitled ―Less Waste, More Value‖ (DETR 1998). The consultation paper emphasized the

importance of managing waste in a more sustainable way. The majority of the 719

individuals and organisations responding to the consultation paper agreed with the

Government‘s vision of waste management for the future (DETR 1998). As a result of the

consultation, government developed a draft Waste Strategy,

―A Way with Waste‖.

2.7.2. The Landfill Tax

The UK's first environmental tax was the Landfill Tax introduced in 1996 by Conservative

government as Statutory Instrument 1996 No. 1527. Landfill tax is seen as a key mechanism

in enabling the UK to meet its targets set out in the European Landfill Directive for the

landfilling of biodegradable waste. Through increasing the cost of landfill, other advanced

waste treatment technologies with higher gate fees are made to become more financially

attractive. The amount of tax levied is calculated according to the weight of the material

disposed of and whether it is active or inactive waste:

Active waste covers all other forms of waste such as wood, ductwork, piping and

plastics.

Page 37: Waste management model

37

Inactive (or inert) waste covers most materials used in a buildings fabric as well as

earth excavated for foundations. Most forms of concrete, brick, glass, soil, clay and

gravel are classified as inactive.

In 1996 the rate of landfill tax per tonne was £7 per tonne on active waste with a lower rate

for inactive waste of £2 tonne. The standard rate increased to £10 per tonne from 1 April

1999 and will in future rise by £1 per tonne per year (DOE 1998), by 2002 the rate of landfill

tax was £13 per tonne.

2.7.3. A Way with Waste

The Draft strategy was published in June 1999, and set out various non-mandatory goals for

future waste management within England and Wales. The commitments were seen as a step

towards a more progressive strategy for England and Wales and are summarised in Table 2.3.

Table 2.3: Key Commitments in ―A Way with Waste‖ (DETR 1998)

The commitments sent a message to local authorities and decision makers that change was at

hand. Commitments 1 and 3 were seen as drivers for significant change and would act as one

of the key factors in making councils across England move away from landfill. Whilst the

white paper was welcomed, it was deemed by many to be a collection of polices rather than a

strategy. In response to the consultation, the Society of Chemical Engineers stated: ―Overall

the document is very good at setting targets; indeed it is liberally sprinkled with them.

However targets do not themselves constitute a strategy.‖ (SoCE) To formalise the seven

commitments and to silence some of the critics, the government launched a new strategy in

2000.

1. Substantial increases in recycling and energy recovery

2. Engagement of the public in increased reuse and recycling of

household waste

3. A long term framework with challenging targets underpinned

by realistic programmes

4. A strong emphasis on waste minimisation

5. Using the waste hierarchy as a guide, not a prescriptive set of

rules

6. Responding to economic incentives like the Landfill Tax

7. Increased public involvement in decision making

Page 38: Waste management model

38

2.7.4. Waste Strategy 2000

In May 2000, The Department of the Environment, Transport and the Regions published a

new Waste Strategy, entitled ―Waste Strategy 2000‖, for the management of Waste in

England & Wales over the next 20 years. The strategy set the following targets for the UK

Government to achieve:

By 2005 to recycle or compost at least 25% of Household Waste, and to

recover value from 40% of Municipal solid waste

By 2010 to recycle or compost at least 30% of Household Waste and to

recover value from 45% of Municipal solid waste

By 2015 to recycle or compost at least 33% of Household Waste and to

recover value from 67% of Municipal solid waste

The strategy also stated that authorities would be required to meet statutory standards for

2003 and 2005. The targets were seen by local authorities as ambitious whilst pressure

groups such as the Friends of the Earth stated that the targets were not high enough to divert

sufficient waste from landfill to meet the demands of the Landfill Directive (FOE 2000). The

House of Commons‘ Environment, Transport and Regional Affairs Committee were

unimpressed and saw the 30% and 33% recycling targets for 2010 and 2015 as ‘depressingly

un-ambitious’ (FOE 2000). Undeterred, government released a further white paper in 2001

that clarified the way forward for local authorities.

2.7.5. Guidance on Municipal Waste Management Strategies (March 2001)

As a follow up to ―Waste Strategy 2000‖, in March 2001 DETR published ―Guidance on

Municipal Waste Management Strategies‖. Within this document the Government set the

Statutory Performance Standards for each WCA and WDA, at a level to ensure that each

authority contributed proportionately to the achievement of the national targets set in Waste

Strategy 2000 (DETR 2001). The Statutory Performance Standards were based on the

recycling and composting rates calculated from the all Councils‘ responses to the 1998/99

Municipal Waste Survey, where that figure was doubled and then trebled for the two target

years. For the case study area, the targets are shown in Table 2.4, where it is bluntness of the

policy is demonstrated, for example, B&HCC performed well and had to increase their

Page 39: Waste management model

39

recycling by 20 percentage points in 5 years, whereas Eastbourne performed badly in 1998/99

and only had to increase their performance by 12 percentage points, investment in new

schemes would therefore be very different.

Table 2.4: Statutory Performance Standards for the WCAs and WDAs (Adapted from

Guidance on Municipal Waste Management Strategies, 2001)

As an added pressure to the targets being statutory there was a mechanism for intervention by

the government if the targets were missed. ―The Secretary of State has powers under Section

15 of the Local Government Act 1999 to act where authorities are failing to deliver best

value‖ (DETR 2001). The powers would be used predominantly to achieve improvements in

service delivery, as opposed to tackling procedural failures. The sanctions that could be

applied to local government caused many a local authority to look to alternative ways of

managing waste, but the relentless pressure of government on authorities had not abated,

indeed, within a year, a review of the 2000 waste strategy would start.

2.7.6. Waste Not, Want Not

A Home Office Strategy Unit was tasked at the end of 2001 with carrying out a review of the

waste strategy in England. The aim of the review had been to devise a strategy, with practical

and cost-effective measures for addressing the challenge, which would put England on a

sustainable path for managing future streams of household waste (Cabinet Office 2002). The

Strategy Unit's final report, "Waste not, want not" was published on 27 November 2002 and

contained a number of recommendations and policies to meet the aim of developing a

sustainable strategy.

Recycling rate

Statutory performance

standards

WCA 1998/99 2003/04 2005/06

Eastbourne BC 6% 12% 18%

Hastings BC 6% 12% 18%

Lewes DC 9% 18% 27%

Rother BC 8% 16% 24%

Wealden DC 8% 16% 24%

WDA 1998/99 2003/04 2005/06

Brighton & Hove CC 10% 20% 30%

East Sussex CC 9% 18% 27%

Page 40: Waste management model

40

In responding to the strategy review, DEFRA were supportive of the document and enacted a

number of recommendations prior to doing a formal response; these are summarised in Table

2.5. Generally the white paper was seen as a success, but the 1st recommendation increased

the pressure on councils to move away from landfill. The implications of the rise in landfill

tax were very clear; the cost was going to rise quickly to bring more expensive technologies

onto a par with landfill disposal costs. What this also meant was that landfill costs would

increase significantly until a council had an alternative.

Table 2.5: Recommendations for a new strategy (Cabinet Office 2002)

Waste Not Want Not ended a period of concerted central government pressure on local

authorities to increase recycling. Following publication, government actively gave authorities

support which included the formation of a new delivery team, a new performance reward

grant and a new sustainable waste programme. However, it was decided by government that

clarification of the challenges set in the white paper ―Limiting Landfill‖ in 1999 were

required and the concept of tradable landfill permits was consulted upon. The concept of

landfill permits will be addressed in Chapter 6.

2.8. European Legislation

A significant proportion of UK legislation is determined by European Legislation. There are

numerous current and future directives that are designed to control the management of waste

Landfill Tax will be increased by £3 per tonne in 2005/06 and by at least £3 per tonne

in the years thereafter, on the way to a medium to long term rate of £35 per tonne.

The Landfill Tax Credit Scheme has been reformed and a proportion of the funding

will be re-directed to a new Sustainable Waste Management Programme in England

in 2003/04, 2004/05 and 2005/06;

A new Sustainable Waste Management Programme managed by Defra will

concentrate on improving waste minimisation, recycling and composting, and

researching new technologies for dealing with those wastes which are not readily

reduced, reused or recycled.

A new Delivery Team and Steering Group is being established in Defra to drive

forward implementation of the new programmes of work in Defra and WRAP;

Local authority funding of £90m each year for 2004/05 and 2005/06 has been

provided for the Waste Minimisation and Recycling Fund or its successor

Performance Reward Fund.

Page 41: Waste management model

41

in the EU, some of which have been incorporated into the preceding UK legislation. A

summary of the most influential European directives follows.

2.8.1. The EU Landfill Directive

The European Landfill Directive (ELD) 99/31/EC ―seeks to prevent or reduce possible

negative environmental effects from landfilling of waste by introducing uniform high

standards throughout the EU‖ (Burnley 2001). The ELD is the most influential piece of

waste management legislation to have been produced for some time (Taşeli, 2007).

The most important requirements of the Directive were: to treat most wastes before

landfilling, and by 2001, ban co-disposal of wastes, liquid wastes, infectious clinical waste

and certain types of hazardous waste (e.g. explosive, highly flammable) (ELD 1999). Of most

relevance to councils in the UK was the introduction of targets for the reduction of

biodegradable municipal waste (BMW) to landfill. The specific targets the ELD set were

introduced to English law as part of Limiting Landfill and later incorporated in Waste

Strategy 2000 as shown by Table 2.6:

(a) by 2010, to reduce biodegradable wastes landfilled by 25% of 1995 baseline

landfill Figures;

(b) by 2013 to reduce biodegradable wastes landfilled by 50% of 1995 baseline

landfill Figures; and

(c) by 2020, to reduce biodegradable wastes landfilled by 65% of 1995 baseline

landfill Figures.

Table 2.6: The Landfill Directive Targets for the UK (DEFRA 2002)

The targets are onerous because they are calculated as a percentage of a base line figure and

therefore do not allow for waste growth. Biodegradable waste is estimated to make up 62.5%

of MSW (Limiting Landfill 1999); meaning that if there was 1 million tonnes of MSW

landfilled in 1995, by 2020 only 218,750 tonnes of BMW could be landfilled. The enormity

of the task for achieving the targets was summarised by Corker and Davies, who estimated

that 123 million tonnes of waste would have to be diverted from landfill over 20 years in the

UK (Corker and Davies 1999).

Page 42: Waste management model

42

The driver for the two councils in 1999 was to move from a system whereby they landfilled

over 300,000 tonnes of MSW per annum, to one where they could only landfill 65,625 tonnes

of BMW in 2019/20. The councils saw this as the significant pressure for changing their

waste disposal regime. When this was combined with the lack of void space it meant the

current method of waste management couldn‘t continue.

2.8.2. The European Waste Incineration Directive (WID)

The Directive 2000/76/EC on the incineration of waste was published on 28 December 2000

in the Official Journal of the European Communities (L332, p.91). The Directive introduced

far stricter provisions than those found in the previous Municipal Waste Incineration

Directives (89/369/EEC and 89/429/EEC) and Hazardous Waste Incineration Directive

(94/67/EC). The requirements of the directives meant that if councils were to move towards

incineration as a way to change the management of waste, they would need to meet new

emission limit. The WID was estimated to have added a third to the cost of incinerator (Riley

2001)

2.9. Public perception

The view of the public towards the environment was starting to change at the turn of the

century. Petts thought that effective waste management was dependent upon achieving

informed consensus amongst interested parties (Petts 1994). The term interested parties had

previously meant regulators, but in an increasingly environmentally aware area such as the

south coast of England, interested parties became the public, who believed that landfill sites

were bad for the environment. Some of this opinion had been stoked by Dolk, who suggested

that living near landfill sites would produce birth defects or increase your chances developing

cancer (Dolk et al 1998). The councils considered the pressure of the public as being one the

greatest factors in influencing the future structure of waste management, and not to be

underestimated (Carter 2001).

2.10. Next steps for ESCC & BHC

Between 1997 and 1999 East Sussex County Council and Brighton & Hove Council were

concerned by the emerging pressures of ―Making Waste Work‖ and ―A Way with Waste‖,

whilst also conscious of the emerging Landfill Directive (Carter 2001). To mitigate these

Page 43: Waste management model

43

pressures as well as the shortage of landfill, a decision was taken by ESCC and BHC to work

together to benefit from economies of scale and shared officer resource. A joint project team

was set up in 1999 to procure a long term contract that would allow the councils to plan for

the future.

2.11. The Private Finance Initiative (PFI) contract

The EPA 1990 gave the power for WDAs to procure a contract from a private contractor

(EPA 1990). The Private Finance Initiative was first introduced to the public sector in 1992

with the primary objective of securing benefits from the involvement of the private sector in

the delivery of services. In 1995, the first wave of major PFI development projects was

launched, but these were not for waste projects, the first waste project was the 1996 Isle of

Wight PFI contract. Accounting rules allowed assets to be kept ‗off balance sheet‘, provided

that the contract demonstrated sufficient transfer of risk to the private sector through the

delivery of a wide range of services as part of the deal. The other main requirement for

approval was that the contract represented value for money when measured against an

equivalent project delivered through public funding via a public sector comparator (Allene

HM Treasury).

The Councils submitted an Outline Business Case (OBC) bid to the Government in 1999, for

Private Finance Initiative (PFI) Credits to help offset some of the anticipated increased costs

associated with moving to more sustainable waste management operations. On 17 January

2000 the Councils received a letter from the Department of the Environment Transport and

the Regions (DETR) stating that the Department would support the PFI application for £49

million spread over 25 years. The award of the PFI was dependent on the successful delivery

of an integrated contract that demonstrated value for money and an appropriate transfer of

risk to the private sector. By July 2000 members of the ESCC Cabinet Committee and

B&HCC Joint Integrated Waste Contract Sub-Committee had agreed a shortlist of companies

to be invited to tender for the joint Integrated Waste Management Services Contract.

2.12. Summary of pressures

By 2002 the two councils were in no better position than the majority of councils in the UK.

Burnley stated that for authorities to meet the Landfill Directive all parts of the UK would

Page 44: Waste management model

44

―need to develop intensive national recycling schemes and expand their incineration

capacity‖ (Burnley 2001). The preceding sections have shown that there was significant

pressure on the councils in the East Sussex and Brighton & Hove area to change from the

current landfill based management methods to a more sustainable long-term integrated

approach. This chapter has highlighted the main pressures on moving to a new strategy are as

a result of the following factors:

Lack of future landfill void

EU legislation aimed at reducing reliance on landfill

UK legislation aimed at increasing recycling and recovery

Indirect pressures such as the landfill tax increasing the cost of the common

method of disposal

Public pressure in ensuring the new solution is environmentally friendly

Having decided that a partnership was the sensible approach to procuring a PFI contract that

was both lengthy and costly, the council‘s considered the technical options crucial and

formed a joint team to procure a solution. The following chapter will describe the

technological solutions available to the councils at the turn of the century to enable them to

meet their objective of diverting more MSW from landfill.

Page 45: Waste management model

45

3. THE ALTERNATIVES TO LANDFILL DISPOSAL AVAILABLE TO ESCC

AND BHC IN 2002

The previous chapter has shown that as a result of numerous drivers Brighton & Hove and

East Sussex Councils decided to procure a long term PFI contract for the disposal of waste.

This chapter introduces the Waste Hierarchy and examines the main technologies and

treatment practices available to the Councils in 2002. All are alternatives to landfill, but each

may in part result in some of the wastes going to landfill or other technologies as residue

from the process, meaning that a complex logistical management method may need to be

employed. The technologies will be rigorously assessed to determine which are suitable for

mitigating the impact of the drivers and the final choice of facility will be presented.

3.1. Managing MSW according to The Waste Hierarchy

In 2001 there was nearly 30 million tonnes of MSW in England, managed by WCAs and

WDAs and consisting of a mix of organic and inert substances. MSW was managed by four

predominant methods, recycling, composting, incineration or landfill, although disposal to

landfill is deemed to be bad for the environment (Mattson 2002). The waste hierarchy was

first introduced in the European Union‘s Waste Framework Directive of 1975 (Directive

75/442/EEC) to quantify the relative importance of each method of treatment. In 1989 it was

formalised into a hierarchy of management options in the European Commission‘s

Community Strategy for Waste Management, and further endorsed in the Commission‘s

review of this strategy in 1996 (COM(96)0399 - C4-0453/96). The precautionary principle

had been established as a method for preventing pollution to the environment and the waste

hierarchy focused on this by prioritising the prevention and reduction of waste, then its reuse

and recycling and lastly the optimisation of its final disposal. The concept is described by the

―3Rs‖ – Reduce, Reuse, Recover – followed by unavoidable disposal. The hierarchy is

designed to demonstrate the Best Practicable Environmental Option (BPEO) in managing

waste generated by households and commercial premises (Adams et al 2000). The Hierarchy

has been visualised in many ways, in 2002 the Government‘s Strategy Unit produced Figure

3.1.

Page 46: Waste management model

46

Figure 3.1: The Waste Hierarchy (Waste Not want Not 2002)

The hierarchy demonstrates which options are most desirable, the higher up, the better for the

environment (Waste Not want Not 2002). Reading of the hierarchy would show that disposal

is least favourable with waste reduction being most encouraged. There follows an explanation

of the five tiers of the waste hierarchy and a quantification of the technologies chosen for the

PFI contract.

3.2. Level 1: Waste reduction

Municipal solid waste increased by approximately 54% in the OECD area between 1980 and

2000 (OECD 2004) and is one of the main factors in increasing council budgets in the UK

(LGA 2004). Waste reduction is referred to as prevention as well as minimisation and is the

preferred method of waste management and involves eliminating and reducing the amount of

waste at source. It is considered to be the most important management technique to be

applied to solid waste (Phillips et al 1998). Read proposes that prevention and minimisation

are one and the same concept and defines it as: Prevention and/or reducing the generation of

waste, improving the quality of waste generated, including reduction of hazard and

encouraging re-use, recycling and recovery. MSW reduction has been somewhat neglected

compared to industrial waste reduction as it is the most difficult to implement, due to the

involvement of individuals, businesses, local authorities and other public bodies. It is

essential to examine current practices and try to alter the social norms to reduce the amount

of waste produced (Maycox 2003). The impact of reduction may be important, but will never

reduce waste to zero, therefore further activities are required that require technical

Page 47: Waste management model

47

manipulation of waste. For the PFI contract, an allowance should be made for a waste

minimisation programme that focus on prevention of waste, combined the promotion of re-

use of materials

3.3. Level 2: Re-use

The re-use of waste materials is placed second in the hierarchy of waste management options.

The potential to reuse the waste has been demonstrated for years by returnable product

schemes and scrap shops at civic amenity sites (Read 1999), whilst charity shops, car boot

sales and the collections made by NGOs such as the Salvation Army and The Scouts show

that there is public support for re-use. There are two distinct types of re-use. The first is

conventional re-use in which products, such as milk bottles, are designed to be used a

maximum number of times before becoming obsolete. The second form of re-use is where

new uses are found for items once their original use has been fulfilled. Both types of reuse are

limited in their capacity to divert waste as the applications are both diverse and insignificant

in scale.

In 1978, Breakspere was concerned about the vast quantities of potentially useful materials

discarded as waste (Breakspere et al 1978) and suggested reuse was necessary. Historically,

re-using potential waste materials played an important part in both commercial life and in the

household, thereby reducing the material requiring disposal. The 'throw away society' that has

permeated society in the last two decades has led to a decline in such practices. One must

question the potential for reuse in the future and how it will be reincorporated into society,

the concept of buying new products means that re-use will only enable a small proportion of

MSW to be diverted from landfill, meaning the use of discarded material needs another

option; recycling. To reduce the amount of waste the councils should manage through the

PFI, a focus must be place on re-using and preventing the waste arising, as highlighted in 3.2,

this would be best achieved through a formalised programme for waste minimisation and re-

use, which must be incorporated into the main body of the PFI.

3.4. Level 3a: Recycling

In the 1990 White Paper ‗This Common Inheritance‘ the Government set a target of recycling

25% of all household waste by the year 2000 (DOE 1990), this was supported by Section

49 of the 1990 Environmental Protection Act requiring every WCA to prepare a waste-

Page 48: Waste management model

48

recycling plan (DOE 1995). Recycling involves the collection of materials for reprocessing

to create a useable material or product. Recycling can, in principle, enable raw materials to be

used many times, with the method of collection crucial in determining quality and type of

reprocessing (Evison & Read 2001). Kerbside recycling schemes developed in the UK

through the 1990‘s were essentially modelled on US and Canadian programmes established

in the previous decade. Two basic types of operation were emulated:

a) Sorting at the kerbside into specially developed collection vehicles, backed by a

simple recycling transfer station;

b) Collecting commingled materials in conventional compaction vehicles for sorting at a

more sophisticated Materials Recycling Facility (MRF).

The first schemes to take off in the UK involved kerbside sorting and were facilitated by

small trials which avoided the need for capital investment in large plants and associated

planning (Evison & Read 2001). The types of recycling can be categorised as: Kerbside sort,

Single stream Co-mingled and Co-mingled Two Stream, an explanation of each follows.

3.4.1. Kerbside sort

Kerbside sort involves the sorting of materials at kerbside into different compartments of a

specialist collection vehicle. This has proved to be the easiest to introduce as the capital

outlay for vehicles and equipment is relatively low and can be undertaken in stages, whereas

the capital cost of constructing a MRF is high. The first kerbside sort processes were

supported by ―mini-MRFs‖ or local recycling transfer stations (ideally located at existing

depots/waste transfer stations) incorporating external storage bays for glass, covered storage

for paper and plastics/cans. Materials could then be bulked straight to processors in 20-25

tonne loads.

Kerbside sorting is best facilitated by the use of two recycling boxes (Evison & Read 2001),

as it allows paper, card, plastics and metals to be separately collected from glass, which has

the propensity to contaminate paper and card and therefore reduce the quality of recycled

materials. These are generally well received by householders; can be stored inside or out,

and most importantly, can be carried through the house conveniently. Modern ―kerbsider‖

vehicles have low-level side ―troughs‖ that elevate hydraulically into multi-compartments

Page 49: Waste management model

49

with adjustable divisions, facilitating efficient collection and good payloads. Box schemes

collecting multi-materials can be operated successfully in rural and suburban areas. Urban

environments can and do create special problems for recycling, though arguably no more than

the establishment of an efficient refuse collection operation (Juniper 2002). Issues of

vehicular access and traffic congestion can influence collection operations.

Multi-occupancy/high rise dwellings are best approached on an individual basis to

accommodate material specific recycling bins supported by local bring banks for other

materials (Thomas 2001, Tucker et al 1997, Mattsson 2003)

3.4.2. Co-mingled collection with separation

Co-mingled collection with separation involves the collection of materials in a single

compartment vehicle with the sorting of these materials occurring at a Material Recycling

Facility (MRF) (Lewes DC 2001). A MRF is a specialised plant which separates, processes

and stores recyclables which have been collected either separately from waste (a 'clean' MRF)

or co-mingled with it (a 'dirty' MRF). Recycled materials are then sent to the materials

processor and any residual material not suitable for processing goes on for disposal. MRF's

are important to achieving higher levels of recycling and to make sure it is of a high enough

quality that it will have a ready market and a net environmental gain.

The sorting of materials in a MRF is done by a combination of hand picking, automatic

sieving and screening through the use of magnets and electric fields to remove the metals

(Juniper 2002). MRF's are usually housed in large warehouse-type buildings and need to be

located so as to optimise collection and minimise transport. Like other waste facilities, MRF's

are not always easy to site as they do require good road access and do lead to an increase in

local traffic. Arrangements for providing MRF's are important, as too is setting defined input

and output quality standards. Often economies of scale can be achieved by waste collection

and waste disposal authorities working together on a regional initiative. (ETSU 1999). The

required capacity of MRFs to enable recycling to take place will be higher than the amounts

that will be recovered, because of the level of contamination and rejected materials from the

processes. The recovery rate of MRFs will range from 80 – 90% in segregated MRFs (Onyx

2001) but far lower rates for dry recyclables are achieved in mixed waste MRFs. The levels

of contamination are far higher in mixed waste MRFs but because mixed collection systems

can be used, the overall amounts entering the process will be higher.

Page 50: Waste management model

50

3.4.3. Two stream co-mingling

Two stream co-mingling is where residents are provided with two recycling containers and

are asked to place different materials in each container, typically paper/card (fibre) in one and

plastics, glass and cans (containers) in the other. These materials are kept separate but

collected in one vehicle which has two chambers.

3.4.4. Maximising recycling from household collections

WCAs that want to achieve recycling rates above of 33% and above will need to collect both

dry recyclables and green wastes. Here follows the four factors that influence the recycling

rate achieved, with an example of the equation and assumptions for material composition

shown in Figure 1.3, without the collection of green waste:

Householder coverage (HC) = 80%

Materials collected (paper card, glass, metals) (MC) = 32%

Householder participation (HP) = 85%

MRF recycling rate (MR) = 90%

To calculate the potential amount of waste recycled for a WCA with 100,000 tonnes of MSW

collected from households the following calculation needs to be made:

Potential Recycling = ((((MSW * HC)*MC)*HP)*MR)

or

Potential Recycling = ((((100,000 * 80%)*32%)*85%)*90%)

Potential Recycling = 22,032 tonnes or 22%

The calculation shows that high coverage of a scheme with high participation alone doesn‘t

equate to a high recycling rate, additional material needs to be collected to increase the rate.

The obvious material for collection would be that of highest composition, the pie chart in

Figure 1.5 shows that garden/green waste accounts for 20% of the composition of MSW,

adding this material to the collection scheme and recalculating the formula above would

indicate that a recycling rate of 35.8% could be achieved.

Page 51: Waste management model

51

To achieve these theoretically high recycling rates, education, advertising and promotional

campaigns are essential to encourage high levels of public participation (Evison & Read

2001). This implies driving materials sorting up the chain to household and kerbside,

supported by a high-profile collection system that changes public perception of waste

operations, prioritising recycling versus rubbish disposal. One methodology that has been

extremely successful is the switch to alternate week collections of green compostable and

residual waste. If the materials recycling collection is made weekly, then refuse operations

are turned on their head – recycling is prioritised in real life experience and cultural change is

effected, albeit that there is major public perception issues with food waste being left in a bin

for two weeks, especially in the summer.

3.5. Level 3b: Composting

Composting is a controlled biological process that uses natural aerobic processes to increase

the rate of biological decomposition of organic materials (Renkow & Rubin 1998). Slater and

Frederickson suggested that composting had a ―vital role to play in meeting the obligations of

the Landfill Directive‖ (Slater and Frederickson 2001). Industrial scale composting appears to

have started in Holland in 1927, but it wasn‘t until the 1970‘s that MSW was used as a

feedstock (Gray and Biddlestone 1980, Slater and Frederickson 2001). Composting

technologies can be categorised three ways; back yard, open and closed, each has sub

categories that are identified in Figure 3.2:

Figure 3.2: MSW composting options (adapted from ETSU 1999)

Composting techniques use the natural biological processes to break down the biodegradable

waste streams into humus or soil conditioner, but wastes that decompose, particularly the

more putrescible household wastes, generate gases and leachate which are potentially

Page 52: Waste management model

52

polluting. The benefits outweigh the potential deficits, for example, the need for natural

fertilisers, such as peat, will be reduced if more waste can be recovered in this way.

3.5.1. Home composting

The two councils decided on a policy that enabled them to sell or give home composters to

the residents of their area, on the basis that they would have less waste to collect (ESCC &

B&HCC websites). This is a system of composting that can divert the biodegradable element

of MSW, garden and green waste and food peeling, excluding cooked kitchen waste and

bulky green garden waste. It can be seen by Figure 1.5 that approximately 37% of the MSW

arising per household is of this fraction; however, the inputs to a compost bin will be limited

to approximately 100-200kg per annum or 10-20 of the MSW. Home composting is

immeasurable due to the inability to measure every bit of material that enters the composting

unit. It is because of this latter point that home composting is encouraged in so much as to

decrease the waste presented to the councils at the kerbside rather than to count it.

3.5.2. Open composting from source segregated MSW

Open composting is only allowed to be used for source segregated green waste, due to the

Animal By–Products Regulations (ABPR) introduced by the EU in 2002. Open composting

relates to two methods of treatment; windrows and aerated static piles. Windrows are defined

as regularly turned elongated piles, shaped like a haystack in cross section and up to a

hundred metres or more in length (Richard 1996); a windrow is shown in Figure 3.3.

Figure 3.3: Le-Harve Open composting site (Greenfield 2001)

Windrow

Impermeable concrete slab

Page 53: Waste management model

53

The Animal By-Products Regulation 2002, states that particle size must not be greater than

40cm, and that a minimum temperature of 60C should be achieved 8 days. (ABPR 2002).

Most MSW windrows are 1 to 3 metres high and 3 to 6 metres wide, opinion varies, but the

optimal size is considered to be 3 to 5 m at the base and 2 to 3 m in height and somewhat

triangular in shape. (Richard 1996, Kuhlman 1989). Windrows will take days and sometimes

weeks to construct, but are usually each managed as a single batch (Renkow & Rubin 1998).

Windrows composed of MSW are required to be located on an impermeable surface, which

greatly improves equipment handling under inclement weather conditions (Kulman 1989) and

allows leachate to be captured and treated. Windrows will take between 4 and 12 weeks to

turn into compost through planned turning and will produce a product that can be compliant

with the publically available specification (PAS) 100 (Composting Association 2001). To

ensure composting in windrows occurs, oxygen is required; this is achieved by physical

mixing of the mass and natural convection. Aerated static piles take the same shape and

concept of process as windrow, but use forced aeration to further oxygenate the pile. Aerated

piles are normally over 4 metres high, and housed in silos (Kulman 1989).

3.5.3. Closed composting

Closed composting can also be referred to as centralised composting and described as ‗In-

Vessel‘ or ‗Tunnel‘ and can be broadly categorised into three types: vertical flow, horizontal

flow and batch, Figure 3.4 shows an example of a horizontal flow system based in France.

Figure 3.4: Varen Jarcy Enclosed composting windrows (Greenfield 2001)

Page 54: Waste management model

54

These systems are normally in the range of 8,000-20,000 tonnes per annum, are capital

intensive, have on-site weighing facilities and capable of taking uncooked food as well as

garden wastes. The process will produce a compost that is of a good quality and saleable, but

there will also be a process waste residue, which will normally only be fit for disposal by

landfill or EfW (Slater & Frederickson 2001). The Environment Agency regard composting

as an industrial process that requires suitable planning to mitigate the impact of traffic, air

emissions, dust, odour, noise, litter, water usage and visual intrusion (Environment Agency

2001).

3.5.4. The case for composting waste

Composting should be seen as a simple choice for the councils, it is relatively cheap, and

could divert up to 30% of the MSW waste stream from landfill, also reflected in legislation.

Green waste and food waste collected together from households should be composted in an

enclosed facility, where temperatures must exceed 70oC for between 2hrs and 2days

(depending on the technology) whereas green waste from HWRS can be composted in open-

air facilities 60oC, for a minimum of 8 days (ABPR 2002). It is preferable to separate green

waste and food waste where feasible as the product generated will be of a higher quality and

more saleable.

3.6. Level 4: Energy recovery with heat and power

Some facilities are designed to maximise the recovery of energy from the treatment of non-

inert wastes. Energy recovery is a catch all term for a number of different technologies; mass-

burn incineration, anaerobic digestion pyrolysis and gasification, all may have a public

perception of limited pollution control (Petts 1991) and are therefore deemed to difficult to be

deliver. The control of emissions as an issue arises primarily in relation to mass-burn

incineration, where waste is burnt under controlled conditions (Porteous 2005). Other EfW

technologies, such as gasification, involve processes where emissions to the atmosphere are

limited or non-existent (Braekman-Danheux et al 1998).

The following sections encapsulate the assessment of the technologies and the suitability of

each for the ESCC and BHCA PFI contract. The conclusion to the chapter will identify the

Page 55: Waste management model

55

technologies chosen, based upon commercial track record and ability to meet the targets set

out in review of the predominant energy recovery technologies follows:

3.6.1. Mass burn incineration

Mass burn incineration is commonly referred to as Energy from Waste (EfW) or as an Energy

Recovery Facility (ERF), it has also been defined as Waste to Energy (WtE), mainly to

overcome negative public attitude to the term incineration (Miranda and Hale 1998, Carlsson

1996, A. Hegberg et al 1985). For the purposes of this section, the term EfW will be used to

describe mass burn incineration.

An EfW facility is designed for the combustion of waste in a single-stage chamber unit where

complete combustion or oxidation occurs, under controlled conditions in which heat is

released and recovered for a beneficial purpose (Williams 2005). Production of steam or hot

water for industrial or domestic users, or for electricity generation is the main output of the

facility, whilst combined heat and power (CHP) incinerators provide both heat and electricity.

The fuel value (calorific value) of Municipal solid waste is about one third that of coal: as a

rough guide, for every 100,000 tonnes of EfW capacity about 7 megawatts (MW) of

electricity could be exported to the grid to meet the needs of about 11,000 homes (ETSU

1999). Although energy is an important and valuable by-product, the technology exists

primarily as a waste disposal means. The basic components of an EfW are the:

Waste bunker and reception building

Combustion unit(s) which burn the waste

Heat recovery and power generation plant

Emission Pollution Control

Ash collection facility

Exhaust stack which discharges the cleaned combustion gases to the air.

The generic process is that MSW is received into a pit where an overhead crane mixes the

waste, to evenly distribute combustible materials and moisture, and remove oversized

materials. The crane feeds waste into a charging hopper, usually by means of a hydraulic

ram, from here, the waste falls onto the moving grate system into the combustion chamber.

Air for combustion is introduced from under the grate (under fire air) and from nozzles

located in the furnace above the grate (over fire air). Under fire air initiates combustion and

keeps the grate cool. Over fire air helps to mix the combustion gases and ensure more

Page 56: Waste management model

56

complete combustion of volatiles (A. Hegberg et al 1985). Additional fuelling with natural

gas or oil may be required to maintain specified combustion conditions, especially during

shutdown or start-up (Miranda and Hale 1998). Various designs of grate are available but all

have the purpose of agitating and transporting the burning waste through the furnace so that it

can be discharged as a sterile (biologically inactive), non-combustible (inert) ash which can

be used in construction or disposed of to landfill. The schematic in Figure 3.5 shows the main

components of an EfW:

Figure 3.5: A Schematic of a generic EFW Facility (Mercia Waste)

These main components are typically supported by facilities such as a gatehouse and

weighbridge, storage facilities and silos for process materials, maintenance stores etc (Juniper

2001) and can be seen in Figure 3.5. The significant benefit of EFW is the ability for it to

divert nearly 70% of the fuel stock from landfill; if the residual materials are used for

secondary recovery diversion from landfill can reach nearly 100%. The exterior design of an

EfW is modern and high tech, as demonstrated by the field trip photo shown in Figure 3.6:

Page 57: Waste management model

57

Figure 3.6: The VESTA Energy from Waste facility at Rouen (Greenfield 2001)

3.6.1.1. The process of energy recovery from mass burn incineration

The hot gases from the combustion chamber are directed to a boiler to recover heat. Energy is

transferred from the hot flue gases to water in the boiler tubes, generating hot water and

steam and cooling the flue gases. These boilers normally comprise super heaters and

economisers to increase energy recovery. The steam is used to turn a turbine and generate

electricity. It is possible to use the steam as a heat source for space heating or industrial

processes, as well as for electricity generation. The cooled flue gases pass through pollution

abatement plant before exhausting to air via a stack. ―A nominal 550-650 kilowatt hours

(kWh) of electricity or approximately 2,000 kWh of heat per tonne of waste burned can be

recovered (ETSU 1999).

The efficiency of energy recovery depends upon the use - electricity or heat supply - and the

plant design. Typically, about 10% of the electricity produced is used in running the systems

within the plant and the rest - 90% - is available for export.‖ (ETSU 1999)

3.6.1.2. Emission Control from EFW

After the combustion process the gases are cleaned. There is a range of designs for emission

pollution control (EPC), but the system for a modern plant is likely to consist of the

following, demonstrated in Table 3.1:

Page 58: Waste management model

58

Table 3.1: Measures of emission pollution control (ETSU 1999)

EPC equipment can account for 40% of the capital cost of a modern EFW plant (Riley 2001)

but is a fundamental part of a facility that will only be acceptable to the public if the

emissions are controlled.

3.6.1.3. Case Study: SELCHP

In 1986, faced with the increasing scarcity and environmental problems of landfill, the

London boroughs of Lewisham, Southwark, and Greenwich came together to search for an

identify a realistic alternative. In 1988, they formed the South East London Combined Heat

and Power Consortium (SELCHP) that uses mass-burn incineration technology for the

combustion of 420,000 tonnes of municipal solid waste a year.

In the SELCHP facility, MSW is fed by crane from the storage bunker into one of the two

identical incinerator streams, each capable of burning 29 tonnes per hour (tph). The two

furnaces use Martin reverse-acting stoker grates to agitate the waste during combustion, and

energy recovery will be achieved via integral CNIM three-pass membrane-wall boilers and

economisers, nominally producing 152 tph of superheated steam at 47 bar 395°C. The steam

fed to a single medium-pressure steam turbine driving a four-pole synchronous 31 MW

alternator with automatic regulators at a nominal 11 kV. Exhaust steam from the turbine is

condensed by means of air- cooled condensers. This full system redundancy gives operating

flexibility in the event of a shutdown of one system, and enhances the reliability of the 24

hours a day, 7 days a week operation (SELCHP 2002).

Acid gas scrubbing using a lime mixture injected into the gas stream, which reacts to

neutralise the acid gases such as sulphur dioxide, hydrogen fluoride and hydrogen chloride.

Activated carbon injection to remove organic compounds such as dioxins and volatile

metals such as mercury and cadmium.

Particulate (dust) removal using an electrostatic precipitator or filters. These fine

particulates are known as ‘fly ash’.

Measures to reduce emissions of oxides of nitrogen. Those measures available range from

controlling combustion conditions, e.g. by recycling some of the flue gas through the boiler.

These simple measures will not, however, meet the limit proposed in the draft EC

Incineration Directive. To achieve these higher standards will require techniques such as

Selective Catalytic Reduction (SCR) and selective Non-Catalytic Reduction (SNCR). Both

are widely developed elsewhere in Europe. They rely on chemicals such as ammonia or

urea injected into the flue gas to destroy oxides of nitrogen. SCR requires the use of special

catalysts and natural gas burners to re-heat the flue gas to promote the reaction.

Page 59: Waste management model

59

3.6.2. Anaerobic Digestion

Anaerobic digestion has been used for over 100 years to treat sewage sludge and farm

slurries, it is only since the 1970‘s that MSW has been considered as an input fraction. One of

the first full scale plants was the Pompano Beach, Florida Solid Waste Reduction Centre site

(RefCom), which was operated from 1978 to 1985 (Braber 1985). Household waste is made

up of a range of materials including paper, card, plastics, textiles, glass, metal and

putrescibles (organic material that is easily degraded such as fruit and foodstuffs) (Bruner &

Ernst 1985). Of these, only putrescibles and paper are ideally suited to anaerobic digestion

and the process will be easier to manage if these wastes comprise the only feed to the system

(Zhang et al 2006). Garden waste may also be treated by anaerobic digestion, but the extent

of degradation will vary according to the type of material, for example, grass cuttings are

more easily treated than woody material. The purity of the material fed into the AD process

dictates the quality of the horticultural product at the end of the process (Al Seadi 2002).

Some facilities are designed to remove as many other materials as possible, for example

ferrous metals, before digestion while others are designed to optimise gas collection for

energy production, and soil conditioner production is not their main objective. Other plants

might choose to optimise the horticultural product, seeing the energy as a less important by-

product. Having separated any recyclable or unwanted materials from the incoming wastes,

the organic material is shredded and fed into the digestor. If very wet wastes, like sewage

sludge, are included, then the addition of further water may not be necessary, but in the case

of household organic wastes, water is added (Gim et al 2001). Different systems can handle

different percentages of solid to liquid, and while average ratios are 15-25%, certain

technologies can cope with solids as high as 30%. The wastes remain in the heated digestor at

temperatures around 35-37oC (known as the mesophilic range) for varying periods of 10-20

days, the duration being dictated by differing technologies, external temperature fluctuations,

and other variables like the waste composition itself (G. Kiely et al. 1996).

Some newer processes operate at the higher (thermophilic) temperature of 55oC, and this

offers better rates of degradation (Al Seadi 2002). Gases given off during the decomposition

are continuously drawn off. A flow diagram of the AD single phase process is shown in

Figure 3.7.

Page 60: Waste management model

60

Figure 3.7. Schematic representation of the single-step composting process. (Wellinger,

1999).

After the accelerated in-vessel biological degradation is complete, the solid residue known as

'digestate' is removed and usually `cured' aerobically as well as being screened to remove

oversized and unwanted items like glass shards or pieces of plastic. The degree of screening

required varies according to the intended use of the final product. This process results in a

waste residue that has potential for composting, depending upon input to the plant (Six & De

Beare 1990).

Although it is widely recognised that one of the benefits of the AD process is the production

of methane gas (Kiely et al 1985, Fricke et al 2007), what is often forgotten is that there will

also be a process residue. If this can be successfully used as horticultural product then the

economics of the process are likely to be much more favourable together with a far higher

diversion from landfill, otherwise there is likely to be on-going disposal costs at the end of

the process. There are a number of available AD systems at different stages of commercial

status, but the predominant and most relevant to MSW are the High-solids anaerobic

digestion systems, this will be demonstrated through the evidence in Table 3.2 that shows that

commercially proven facilities are of this type. High-solids anaerobic digestion systems have

been developed to handle the digestion of solid wastes (particularly MSW) at solids contents

of 30% or greater (Cecchi et al 1986). High-solids systems enable the reactor size to be

reduced, require less process water and have lower heating costs (Cecchi et al 1991). A

number of commercial and pilot scale plants have been developed which include: the Valorga

process, the Drano process and the Kampongs process. A summary of the commercial plants

up to 1999 is shown in Table 3.2 a description of each of the technologies will follow.

Page 61: Waste management model

61

Process Location Feedstock Capacity tonnes/y On-line date Description

Grenoble, France 16,000 1984

Amiens, France 85,000 1988

Papeete, Tahiti 90,000 1996

Tilburg, NL 52,000 1991

Tamara (French

Polynesia).

91,000 1994

Engelskirchen, Germ. 35,000 1998

Ghent, Belgium 800 1984

Brecht, Belgium 12,000 1992

Salzburg, Austria 20,000 1993

Bassum, Germ. 13,500 1997

Aarberg, Switz. 11,000 1997

Kaiserslautern, Germ. 20,000 1998

Rumlang, Switz. 4,000 1992

Bachenbulach, Switz 10,000 1994

Samstagern, Switz. 10,000 1995

Kempton, Germ. 10,000 1995

Otelfingen, Switz. 12,000 1996

Braunschweig, Germ 10,000 1997

Munchen, Germ. 20,000 1997

Lustenau, Aust. 10,000 1997

Hunstruck, Germ 10,000 1997

Niederuzwil, Switz. 6,000 1997

Kyoto, Japan 1,000 UC

Kompogas Source sep. MSW

or green garden

waste

Thermophilic

horizontal plug-flow

Valorga Mechanically

separated MSW

Mesophilic gas-mixed

reactor

Dranco Source sep. MSW

+ garden waste

Thermophilic vertical

plug-flow reactor

Table 3.2: Commercial high-solids anaerobic digestion plants (IEA Bioenergy, 1996,

updated 1999)

Most of the facilities had been open for more than two years in 1999 and were over 10,000

tpa, meaning that these three systems of anaerobic digestion could be considered as

commercially operational. The councils could therefore consider anaerobic digestion as a

viable alternative to landfill.

3.6.2.1. The Valorga system

Developed in France, the installation at Amiens combines four mesophilic high-solids

reactors with the incineration of residues and non-digested matter (Valorga 2000). Mixing

within the reactor is carried out by reverse circulation under pressure of a small proportion of

the biogas. Biogas produced has a methane content of 55-60%. The biogas can be purified to

a methane content of 97% which can then be fed into the gas network used to raise steam for

an industrial process or for heating and electricity production (Al Seadi 2002). The specific

methane yield is between 220 - 250 m3/tonne of total volatile solids (TVS) or between 80 -

160 m3/tonne of waste fed, depending on the waste. The process operates at solids contents

typically 25 - 35% with residence times between 18-25 days (Fruteau de Laclos et al 1997).

The Valorga system has the highest number of large scale facilities and could therefore be

considered to be a sensible option for the Councils as it has already been commercially

proven, unlike some of its competitors.

Page 62: Waste management model

62

3.6.2.2. The Dranco (Dry Anaerobic Composting) system

Developed in Gent, Belgium, the system operates at high solids content and thermophilic

temperatures. Feed is introduced daily into the top of the reactor, and digested material is

removed from the base at the same time. Part of the digestate is recycled as inoculation

material, whilst the rest is de-watered to produce an organic compost material (Al Seadi

2002). There is no mixing within the reactor, other than that brought about by the downward,

plug-flow movement of the waste.

Figure 3.8: Brecht II - DRANCO exterior view (Greenfield 2000)

The total solids content of the digester shown in Figure 3.8 depends on the source of the

waste material but is in the range 15 - 40%. Reactor retention time is between 15 - 30 days,

the operating temperature is in the range 50-58oC and the biogas yield is between 100- 200

m3 / tonne of waste feedstock. (Six & De Beare 1990). The gas is captured and used for

generation of energy through a turbine or can be used as fuel. Similar to the Valorga process,

this technology could be considered by the Councils as large scale plants have been

operational for at least 10 years.

3.6.2.3. The Kompogas system

It is a high solids thermophilic digestion system developed in Switzerland. The reaction

vessel is a horizontal cylinder into which feed is introduced daily. Movement of material

through the digester is in a horizontal plug-flow manner with digested material being

Page 63: Waste management model

63

removed from the far end of the reactor after approximately 20 days (Al Seadi 2002). An

agitator within the reaction vessel mixes the material intermittently. The digestate is de-

watered, with some of the press water being used as an inoculum source and the remainder

being sent to an anaerobic wastewater treatment facility, which also produces biogas.

(Endelmann & Engeli 2005). The Kompogas system has a number of much smaller reference

facilities and would be unlikely to be suitable for the PFI contract.

3.6.2.4. Discussion

Anaerobic Digestion is quantified as energy recovery in the in Best Value Indicators

Consultation Paper 2000/2001 BVP182c and defined as:

―Percentage of the total tonnage of household waste arisings which has been

used to recover heat, power and other energy sources.‖ Used to recover heat,

power and other energy sources means the biological degradation of organic

wastes by anaerobic digestion.

This is interpreted by the author, as every tonne of waste that is used as feedstock for an AD

plant will count as recovery of household waste. This argument is fairly rigid with only one

cause of concern, as with the case of EfW whereby the base ash residue is discounted from

the input tonnage to calculate the recovery tonnage. In a process which uses un-segregated

MSW the level of contamination may be such that it becomes difficult to find a beneficial use

for the digestate (Al Seadi 2002). Under these circumstances, it will be disposed of to

landfill, where because it has been pre-treated, it will present a lower risk of pollution than

raw waste. If this happened, the feasibility of a mixed waste Anaerobic Digestion facility

would be compromised as it would be a very costly option just to dewater the raw MSW.

Digestate produced from pre-segregated waste may have application as a soil conditioner, but

will often require further treatment (composting - ‗maturation‘) to reduce its silage like

odour. Public acceptance of the finished product will determine whether or not there is a

market for anaerobically digested waste and therefore control over contamination is

particularly important. All of the issues relating to marketing compost derived from waste

also relate to digestate. Therefore AD should be seen as a part of the recovery chain rather

than composting.

Page 64: Waste management model

64

3.6.3. Pyrolysis and thermal gasification

Pyrolysis and thermal gasification are related technologies. Pyrolysis is the thermal

decomposition of organic material at elevated temperatures in the absence of gases such as air

or oxygen (DEFRA 2006). The process, which requires heat, produces a mixture of

combustible gases (primarily methane, complex hydrocarbons, hydrogen and carbon

monoxide), liquids and solid residues. Thermal gasification of MSW is different from

pyrolysis in that the thermal decomposition takes place in the presence of a limited amount of

oxygen or air. The gas which is generated can then be used in either boilers or cleaned up and

used in combustion turbine/generators. The primary area of research for this technology is the

scrubbing of the producer gas of tars and particulates at high temperatures in order to protect

combustion equipment downstream of the gasifier and still maintain high thermal efficiency

(Juniper 2001). Both of these technologies are in the development stage with a limited

number of units in operation. The Hyperion Energy Recovery System operated by the City of

Los Angeles had a system designed to fire dried sewage sludge in a staged fluidized bed

combustor. The resulting gas was then combusted in stages, and the heat was used to turn

water into steam, driving a 10 MW steam turbine-generator. (Lewis et al 2007)

3.6.4. Preferred energy recovery technology

The critical presentation and assessment of EfW, AD, pyrolysis and gasification in the

preceding sections suggests that the best facilities for energy recovery with combined heat

and power would be an EfW facility and an anaerobic digestion facility.

3.7. Level 4 and 5: Landfill and landfill with energy

The last two levels of the waste hierarchy refer to the same method of management, albeit

that there is a favourable distinction towards the utilisation of gases generated in the course of

landfill management, therefore the two levels will be presented as one in this section. Landfill

is a method of solid waste disposal in which waste is buried between layers of soil or

hardcore, as part of a daily management routine, to fill in or reclaim low-lying ground

(Newton 1983). The by products of landfill are leachate and a mixture of gases, to capture

these elements engineering solutions are employed; Figure 3.9 shows one version of the

criteria for landfill construction, Figure 3.10 shows the exposed protective filter medium and

inert material that forms a base layer that allows leachate to move through.

Page 65: Waste management model

65

Figure 3.9: The profile of double lined landfill (Shevon & Damas 1986)

In the UK, landfill was the predominant method of disposal for MSW in the twentieth

century. As the composition of waste changed over the century, the inputs to landfills

changed from inert wastes, to a much higher proportion of biodegradable municipal wastes

(BMW), BMW has been defined in the Landfill Directive as waste that is capable of

undergoing anaerobic or aerobic decomposition. The burying of BMW in a relatively air tight

environment results in degradation and the creation of multiple gases, commonly known as

landfill gas (LFG) (Allen 2001, Price 2001).

The diagram in Figure 3.9, shows that on top of the lining waste/refuse is deposited. Waste

needs to be landfilled in a certain way to ensure stable construction, and an area for

landfilling is usually identified for a given period, this is area is called a cell, demonstrated by

Figure 3.11. Landfilling in the cell occurs by the waste being deposited and then spread out in

a thin layer in the where it is levelled, compacted and covered periodically with soil or

another inert material. Ditches all around the site capture the surface water before it comes in

contact with the waste. As for rainwater that infiltrates itself into the waste, where it mixes

with contaminants to create a liquid by-product called leachate. This is collected at the

bottom of the cells and is sent to the lagoons for treatment.

Page 66: Waste management model

66

Figure 3.10: Beddingham Landfill site base construction (Greenfield 2000)

The construction of cells for lining is shown in Figure 3.10 and preparation of the base of a

cell, prior to lining and use is shown and Figure 3.11, the latter figure gives a perspective of

the size of a landfill cell, this cell is predicted that to take 5 years to fill the cell (Wright

2000).

Figure 3.11 Beddingham landfill site: view into a new cell being prepared for lining

(Greenfield 2000)

Protective medium Inert

material

Page 67: Waste management model

67

3.7.1. Landraise

Landfill sites are predominantly situated in disused mining activities (Qin et al 2001),

however in areas where there are no suitable sites, the method of land raising is employed,

many countries rely on land-raising as the geomorphology is not suitable for anything else,

for example Holland and parts of France. Figure 3.12 shows the creation of a landraise cell in

Le Harve.

Figure 3.12: Le-Harve landraise site cell construction (Greenfield 2001)

3.7.2. The use of landfill gas for the production of energy

LFG is comprised of approximately equal amounts of, CO2 and CH

4a, as well as trace

amounts of other organic compounds generated through decomposition of biodegradable

waste in landfills (Qin et al 2001),. Municipal solid waste landfills were the largest human-

generated source of methane emissions in the UK in 2000 (DETR 2001).Landfill gas is a very

potent greenhouse gas that is a key contributor to global climate change (over 21 times

stronger than CO2), landfill gas also has a short (10-year) atmospheric life. Because methane

is both potent and short-lived, reducing methane emissions from MSW landfills is one of the

best ways to achieve a near-term beneficial impact in mitigating global climate change.

Because of this it makes sense to use the gas for the beneficial purpose of energy generation

rather than emitting it. The capture of LFG is essential to maximise energy recovery. This is

usually undertaken by laying a network of perforated pipelines within the landfill site in the

Page 68: Waste management model

68

cycle of filling and extracting the gas to a treatment house, whereby removal of most of the

trace organic compounds can occur. Figure 3.13 shows the exposed pipe network at the

Beddingham landfill site in 2000, subsequent management would mean this was buried.

Figure 3.13 Beddingham landfill site gas extraction pipe network (Greenfield 2000)

Once cleaned LFG can be used as fuel in internal combustion engines and gas turbines for

generation of heat and electricity (Qin et al 2001), in many cases, electricity is generated on

site and fed to the national grid, the Beddingham landfill site in Lewes, East Sussex produces

2MW of electricity and exports it to the national grid (M Wright 2000).

3.8. Development of a specification for the award of the ESCC & BHC PFI contract

Analysis of the Waste Hierarchy technologies that could be employed as part of the PFI

process to meet future needs has been made in this chapter. The knowledge gained through

this analysis was used by ESCC and BHC to create a specification to enable the PFI contract

to be awarded. The technical specification for the ESCC & BHC PFI contract was developed

by the author in 1999 taking account of all the drivers and options presented so far and

refined over time up to 2003 when a Service Delivery Plan was created.

The specification for the contract stated that ―the contractor shall develop and implement an

integrated waste management system (IWMS) to receive, treat and dispose of all wastes for

which the Councils have a statutory responsibility‖. The Councils also wanted to pass the risk

of achieving the recovery targets of 40% of Municipal Solid Waste (MSW) by 2005 and 66%

Gas flare stack

Gas pipeline

Compacted soil landfill base lining

Landfill daily cover on active site

Page 69: Waste management model

69

of Household Waste by 2015 to the contractor. In order to award the contract, the councils

set some criteria for evaluating the responses from contractors, these were:

To focus on positive action to protect and improve the environment and prevent

pollution, including measures for the efficient use of energy and the achievement of

sustainable development.

To carry out the Councils‘ statutory duty as WDA‘s under the EPA at least cost to the

environment and the community and maximising the use of waste as a resource.

To integrate waste minimisation, recycling, recovery and composting initiatives into a

future waste disposal contract to reduce the proportion of waste going to landfill and

to conserve energy and raw materials.

To use and promote the waste hierarchy,

The hierarchy was seen to not be a rigid order of priorities, and options provided by the

contractor were considered in the light of Best Practicable Environmental Option (BPEO) and

Best Available Techniques Not Entailing Excessive Cost (BATNEEC). The following

chapter will incorporate some of these principles in the assessment of the existing models and

structure of a new model.

The author would consider that for the PFI contract the following technologies could be

employed to mitigate the target of diverting waste away from landfill:

Waste minimisation programme

a MRF,

open windrow composting,

an In-vessel composting facility,

an Aerobic Digestion facility and

an EfW facility

The application of these facilities is not feasible at this point as there interaction between the

facilities and the waste generated is not understood. A method of planning the application of

these treatment methods is therefore required.

Page 70: Waste management model

70

3.9. Summary

This chapter has presented the alternatives to landfill available to ESCC and BHC up to 2002.

Each technology has been described and considered as a suitable option for meeting the

drivers to move away from landfill. The chapter has also presented the principles and

objectives it required contractors to fulfil. The next chapter will examine the waste planning

models that could be employed to determine the optimum combination of the technologies

that have been deemed to be suitable to ESCC and BHC for diverting waste from landfill

under a PFI contract.

Page 71: Waste management model

71

4. CRITIQUE OF CURRENT WASTE PLANNING MODELS

The previous chapters have given an overview of the current waste management structure

within the sub region of East Sussex, the drivers for change and the technologies that could

be utilised to divert waste away from the traditional route of waste disposal, landfill. This

chapter considers how ESCC & BHC can plan the right infrastructure, through a PFI contract,

to move from reliance upon landfill. The chapter will consider the tools that existed in 2002

to help the authorities to make decisions in light of the targets national government have set

as statutory and aspirational. To achieve this, there is a critical review of models for the

modelling of waste mass flow, facility utilisation and the achievement of recycling and

recovery targets. The flaws and merits will be assessed and evaluated against the needs of the

East Sussex sub-region. The need for a new model will be proposed that will enable ESCC

and BHC to make a decision for the construction of infrastructure capable of meeting the

requirements of legislation whilst understanding the complexities and unique characteristics

of the sub-region. The structure, components and assumptions of the new model will be

presented and articulated in chapter 5.

4.1. Needs analysis for a novel waste flow model

Most waste-flow models can be categorised into one of three categories— ―those based on

cost benefit analysis, those based on life cycle analysis (LCA) and those based on the use of a

multi-criteria decision analysis (MCDA)‖ (A.J. Morrissey and J. Browne, 2003). These

categories are clearly related to the analysis methods used by modellers rather than

characteristics used in the local authorities (LA‘s) by planners and mangers.

It is thus useful to determine which characteristics of the models will be essential to the needs

of the local authority. A workshop session and questionnaire was conducted by the author in

June 2000. The 20 officers in attendance identified the key factors in the workshop and were

asked to individually rank in order of preference the factors they felt should be employed by a

waste mass-flow model. The survey asked each to rank against a 1-5 scoring system, 1 being

highest priority. Table 4.1 summarises the results contained within Appendix 1, by showing

the average priority score, expressed as the mode value.

Page 72: Waste management model

72

Key factors for optimal model for usage by Local

Authorities

Priority for ease of usage

Format and usability of model 4.2

High quality data input and presentation 2.1

Demonstration of outputs and interactions between

facilities2.0

Evidence and processes included in the collection

service2.0

Understanding of processes to be used 1.6

Ease of data entry aligned to current reporting 1.3

Ease of analysis 1.0

Table 4.1: Priority factors for ease of use by local authority officers (Greenfield 2002)

It can be concluded from Figure 4.1 that usability and presentation of data and results is of

highest priority and these will be used in the comparison of existing models to benchmark

whether a model is suitable for ESCC and BHC purposes

Much research has been conducted on mass-flow models and the complexity of many

technical processes, Abou Najm, (2002) acknowledges ―the variety of management processes

and the existence of uncertainties associated with the number of system components and their

interrelations‖ means the understanding accountability for these individual factors is critical

to obtaining a realistic and accurate model. Tucker and Smith consider that ―in the UK,

diversion of materials from the domestic waste stream still relies on the combined voluntary

behaviours of individual householders‖ (Tucker & Smith 1999). Stypka considers that ―The

collection stage is the most expensive and the most environmentally demanding stage of the

whole process of waste disposal‖ (Stypka 2001), implying that a good model needs to include

components to model the collection stage. It was essential that a model was ―user friendly

and showed results that the user required‖ (Powell 2000), this reinforces the results shown in

Table 4.1.

To populate a model, the user requires accurate data and parameters to model; MSW data

should be evaluated at the beginning of the investigation. An example of the consequences

for planning when using inaccurate date can be found in China, where there were not accurate

weight evaluation systems for MSW in most cities or regions and MSW amounts were

estimated by average payloads of the collecting trucks. Analysis in 2001 showed that

Page 73: Waste management model

73

changing from estimates to recordable and accurate figures changed the initial calculation of

2 kg/capita/day to 0.78 kg/capita/day, a decrease of 61%% (Kun and Zhiqiang 2001).

The preceding sections show some of the variables that could invalidate results from any

mass-flow model used for planning the PFI contract. With an understanding of the

prioritisation of factors for an optimal model, indentified in Table 4.1, section 4.2 will

critique five existing models.

4.2. Critical review of existing MSW balance models

The following sections review existing MSW mass balance models, using the three categories

Morrissey and Browne suggested, these are considered against the priority factors identified

in Table 4.1. It is not possible to test these models personally as many are costly and require

many months of work to populate, therefore the assessment of the models will be based upon

reviews published in journals and papers.

4.2.1. Cost benefit analysis (CBA) model

A cost benefit analysis is a way of helping to appraise, or assess, the case for a project or

proposal. The process involves, whether explicitly or implicitly, weighing the total expected

costs against the total expected benefits of one or more actions in order to choose the best or

most profitable option. The formal process is often referred to as either CBA (Cost-Benefit

Analysis) or BCA (Benefit-Cost Analysis) (Clift et al 2000, Flyvberg et al 2002).

The Integrated Municipal Waste Model IWM1 developed by White P.R., Franke M., and

Hindle P is considered a tool which seems to meet all the requirements for a cost benefit

analysis (Stypka 2004). The IWM1 model was used by Stypka for the cities of Stockholm

and Krakow, with the intention to ―develop, master and implement a simple, but reliable tool

that will help the decision makers in the analysis process‖. Stypka stated the following points

were the key outcomes of his modelling process using the IWM1 model:

In all analysed cases the environmental burden of the MSW system is significantly

smaller than the economic one.

Page 74: Waste management model

74

The collection stage is the most expensive and the most environmentally demanding

stage of the whole process of waste disposal.

The model clearly shows recycling has environmental benefits.

Comparison studies of his model with others is very difficult, because in different

systems there are different definitions of the waste and there are different statistical

methods employed,

If the emission integration procedures are improved and verified the model could be a

very useful tool for decision makers.

The model does not take into account the social impact of the MSW management system,

which is the key driving force in the process of decision-making for LA‘s.

Stypka concluded that the results of the analysis from the IMW1 model gave vast amounts of

information, but were rather fragmented and indiscernible. A lot of time and effort was

needed to run the model and with the fragmented and indiscernible results being contrary to

the needs of the criteria in Table 4.1, one must regard this as an unsuitable model. However,

aspects of the model should be utilised, principally the evaluation of financial and

environmental burdens.

4.2.2. Life Cycle Assessment (LCA) models

The International Organisation for Standardisation (ISO) defines an environmental Life Cycle

Assessment (LCA) study as the environmental interventions and potential impacts throughout

a product‘s life (i.e., from cradle-to-grave) (Clift et al 2000). LCAs are seen as the solution

for the assessment of the impact of a new infrastructure system on the wider environment.

McDougall et al. (2001) qualifies this as ―they generally offer a system map that sets the

stage for a holistic approach for waste management systems ensuring environmental

improvements can be made‖. Many LCA models recognise that a waste management model

or strategy needs to be sustainable, and it must consider environmental, economic and social

aspects. The model presented by Clift in 2000 and shown in Figure 4.1, demonstrates the

concept of an LCA, the rectangle referred to as no. 2 encapsulates the processes of the mass

balance and the generation of energy, material and waste. It can be concluded that many

factors need to be taken into account for an LCA to be viable, most of this information would

not be available at the start of the PFI process and it would therefore be difficult to run the

LCA.

Page 75: Waste management model

75

Figure 4.1: System boundaries for measuring and regulating environmental performance

(Clift et al 2000)

Morrissey et al (2003) stated that no model examined considered all three aspects together in

the application of the model and none considered the intergenerational effects of the

strategies proposed. It is evident that Morrissey considers the LCA models already in

existence as being insufficient for enabling an all encompassing view on the impacts of new

infrastructure. Taking this as read would mean that there are no models that would have

sufficient capabilities of meeting the needs of ESCC and BHC, but one cannot consider alone

one interpretation, therefore the following sections analyse existing models.

One LCA model, GaBi4, is described as being most suitable for integration of all

sustainability criteria on a corporate, plant, process or product life-cycle level, indeed it was

seen by them as already being a standard tool for life-cycle evaluations in several branches of

local government worldwide (PE Europe 2003). In their review they concluded that GaBi4

was a powerful, fully-featured sustainability data management and evaluation system. Upon

evaluation GaBi4 doesn‘t consider the sizing criteria against targets and fails to account for

public opinion and perception. This is therefore a model that has significant merits but fails to

deliver on the differentiation of sizing of facilities and targets for recycling and recovery and

will not be suitable for the criteria desired in Table 4.1.

1- Process or plant;

2 -Life Cycle assessment;

M -Material;

E – Energy;

W-Wastes and emissions.

Page 76: Waste management model

76

The Waste-Integrated Systems for Assessment of Recovery and Disposal (WIZARD) was

developed by Ecobilan in 2000, to easily model alternative waste management systems,

including landfilling, incineration, sorting - recycling, composting and anaerobic digestion, it

was incorporated into the requirements for a PPC permit in 2002 and was considered to be

very technical and unintelligible to the waste officer, let alone a decision maker (Aumonier

2001).

In 2002 the Strategy Unit (SU) Report published by the Cabinet Office developed a

management and evaluation model for MSW. They identified that the availability of up-to-

date and reliable information was a key problem, making the building of MSW Strategy

Models difficult. This resulted in the SU team making assumptions in areas of the model,

―from limited evidence and small scale studies but often supplemented with further assertions

and assumptions‖ Cabinet Office (2002). They concluded that model results would need to be

handled with great care. It is clear from this report and the work undertaken by Kun and

Zhiqiang (2001), that evidence based modelling is crucial and that accurate base data is the

key to having a reasonable chance of modelling an estimate of the impacts of infrastructure

for the future. It would be wrong to rule out the SU model, but it is clear that the model itself

is weak, due to data inadequacies, resulting in a model that hasn‘t been tested to the criteria

the SU team would have wished. Given that the SU team has stated they would want to re-

build the model if new accurate data were to be available, it is therefore the author‘s intention

not to consider this model for the East Sussex sub-region.

4.2.3. Multi-criteria decision analysis (MCDA)

In Finland, Tanskanen and Melanen, (2000) reviewed the ―Tool for Analysing Separation

Actions and Recovery‖ (TASAR), and stated that a ―national separation strategy can be

established from 1-4 regional strategies, which all consist of separate strategies for residential

properties and commercial establishments‖. This is very unlike England where there has been

a severe lack of structure for the development of detailed national strategy down to the local

level; this is compounded by those strategies that have been written fail to consider

commercial and industrial waste, the opposite is true when one looks at local development

plans, but again not every sub region or region has a high level of detail.

Page 77: Waste management model

77

The TASAR model overview is given in Figure 4.2, and when considered alongside the

outcomes of the SU report and Kun and Zhiqiang (2001) report which both show that

accurate data is crucial, it is evident that TASAR has a level of detail that is lacking in

English local authorities.

Figure 4.2: Elements from which a national separation strategy can be compiled in the

TASAR model (R.P. = residential properties, C.E. = commercial establishments) (Tanskanen

and Melanen, 2000).

To support this, East Sussex County Council Waste Local Plan manager Ian Blake, stated that

the ―data on commercial and industrial waste in East Sussex had an accuracy factor of plus or

minus 25%‖. Given that TASAR uses both Commercial and Household waste data, the model

would be inappropriate for use in the East Sussex sub-region, but the concept of the flows in

Figure 4.2 will be essential if no other model is found to be of use.

4.3. Assessment of critical review and relevancy to needs of local authorities

The preceding critique explains the diversity of LCA models and sometime complex

interpretation of the subsequent results, whilst Table 4.1 and the commentary through the

critique shows that users rank ease of analysis and ease of data entry, aligned to current

Page 78: Waste management model

78

reporting as the highest priorities. The question; ―Is one of the existing LCA models suitable

for local authority use?‖ needs to be answered. To contextualise one must compare

parameters used in existing models against the ease of data entry and subsequent analysis.

Table 4.2 has been created to determine which model, if any, is fit for purpose in relation to

local authority officers in terms of its modelling rigour and applicability. The key parameters

for optimal mass-flow modelling has been developed by analysing the outputs of the five

critiqued models and the needs of local authority, focussing on data entry and the

requirements for achieving delivery of national and local drivers. To achieve a high level of

suitability

Key parameters for optimal mass-flow

modelling IWM1 WISARD GABI 4

Waste growth Yes Yes Yes

Composition of waste stream Yes Yes Yes

What can be recycled Yes Yes Yes

Collection costs Yes Yes Yes

Residual waste management Yes Yes Yes

Process residues Yes Yes Yes

Operating costs Yes Yes Yes

Facilities Yes Yes Yes

capital cost of facilities Yes Yes Yes

Concept of Social aspects Yes Yes Yes

Concept of Public perception No No No

LA Officer compatible without training No No No

Understanding of processes to be used Yes Yes Yes

Ease of data entry aligned to current

reporting No Yes No

Ease of analysis No No No

Suitability as a mass-flow model for

LA use Low Medium Low

Table 4.2: A critical view of existing waste management models compared to the needs of the

East Sussex Sub- Region

The models that have been reviewed in this chapter are complex and non-transparent to the

users; Table 4.2 demonstrates that none of the models are suitable for the requirements of the

local authority, primarily based on the concepts of ease of entry and analysis. It is the opinion

of the author that a new model needs to be developed for the East Sussex area that takes

account of the entire waste management cycle from collection to disposal as well as the

progress, attributes and limitations of current models, but that separates the social and

Page 79: Waste management model

79

economic variables and focuses on the impact of the facilities on the waste stream. The

evaluation of the social and environmental impacts can then be modelled separately on the

desired scenarios, in a clear and concise model. Most importantly a model needs to be

developed with high visibility of mass balance and the potential capacities of processing

facilities that will be required over the long term, which the user can understand and

manipulate to enable different scenarios to be modelled in a timely and accurate manner.

4.4. Summary of CBA, LCA and MCDA

All the published documents and models reviewed in this chapter show that there is not a

tailored, easy to use, and easily adaptable model, for ESCC and BHC to use to decide which

processes need to be implemented to deliver the drivers identified in chapter 2. Morrissey et

al (2001) identified two important steps in decision making in the area of municipal solid

waste management: the formulation of the problem and the involvement of all relevant

stakeholders in the decision-making process. In the context of East Sussex, the latter process

has been delivered via the Waste Local Plan (1998-2006), and considered alongside existing

models, GABI 4, IWMM, IWM2, WARM and WISARD, would appear to be sufficient to

meet Morrissey‘s criteria. Looking at these models though, most are concerned only with

refining the actual multi-criteria technique itself or of comparing the environmental aspects of

waste management options (recycling, incineration, and disposal). Many of the LCA models

thus focus on complex parameters concerned only with the environmental data, which were

not the criteria highlighted as being most important in Table 4.1. The models then prioritise

the financial data rather than the environmental data and may be forced to base decisions on

those sections they understand rather than the results of the model (Powell 2000). None of the

models can present an easy to use model that allows an authority to size a combination of

facilities to meet a set of targets for the future.

There therefore, appears to be a clear need for a tool that can deliver a strategic overview for

the aid of decision making, which incorporates rigorous modelling assumptions but is also

usable by staff in local authorities who do not have modelling experience but who do have

waste management experience. The next chapter focuses on the results of the construction of

a MSW Mass Balance Model that was designed to meet the criteria of Tables 4.1 and 4.2.

Page 80: Waste management model

80

5. DEVELOPMENT OF THE MASS BALANCE MODEL (MBM)

The previous chapters have introduced waste, the focus this thesis has on municipal solid

waste and the complexities of managing MSW through collection and disposal. A critical

analysis of the drivers for change, the alternative technical options and the reasoning and

need for the development of a new bespoke Mass Balance Model (MBM) has been presented.

This chapter will explain the development of the MBM, the assumptions used and the results

that were generated and how they were subsequently used for East Sussex County Council

and Brighton & Hove City Council in procuring the PFI contract, up to 2003.

5.1. The Development of the MBM

The MBM was created over a period of three years, between 1999 and 2002 with the purpose

providing a model that allowed East Sussex County Council and Brighton & Hove City

Council to make decisions about the infrastructure it needed to provide for the future

management of MSW and to meet statutory and aspirational waste targets it has set itself. The

results of the MBM would be used to influence the financing of a long term Private Finance

Initiative (PFI) contract. The MBM that is presented here is the final iteration of model and

is the conclusion of many mistakes and format changes. A demonstration of the development

of the model stage by stage and test of the robustness of the MBM will be described in this

chapter through the creation of a reference scenario.

In acknowledging ―the expertise and the data to use complex mathematical models‖ Powell,

(2000) in designing his model states, that it was essential that it was user friendly and showed

results that the user required. In the process of using a model, Nie, states that the user will

requires certain data and information to enable the model to work to achieve the ultimate

goal, and that the reported MSW data should be evaluated at the beginning of the

investigation to allow for the most accurate data (Yongfeng Nie 2004). The MBM has been

designed with these goals as objectives. In addition, users will be able to model different

waste growth scenarios that might occur and scenarios whereby a number of facilities are

utilised in order to determine whether a certain configuration of facilities, plotted against

varying growth profiles, will enable councils to the EU and UK government targets for the

management of Municipal waste.

Page 81: Waste management model

81

The complexities and subtle issues in interpreting and inputting data into each sub-section of

the MBM are described in full detail in this chapter. However it is useful for the user to have

an overview of the major calculations and assumptions before looking at the details and

information that would be required to run the model.

5.2. MBM description

The MBM was developed to enable any local authority to use the model for the same

purposes, but was built specifically for the use of Brighton & hove City council and East

Sussex County Council. The user should have a desired outcome to model against, for

example, a recovery rate of 67% by the year 2015/16, or landfill void to last 25 years but has

only 4,000,000 m3 of void space. The user can provide any of the following for comparison

against the modelled results:

Recycling rate year by year to be achieved

Recovery rates year by year (including recycling) to be achieved

Total void space available

For example, if the user requires a recovery rate of 67% by 2025, alongside recycling,

composting and anaerobic digestion assumptions, the size of the energy from waste facility

required to meet the waste growth scenario in future years will be able to be determined. The

MBM allow users to understand the implications of facility size and throughput in relation to

available waste for management over the 25 years the MBM can model.

The process map in Figure 5.1 shows all the technologies that can be modelled through the

MBM. The interrelation of the technologies and systems in Figure 5.1 form the principles of

the MBM and allow the user to model a set of scenarios that will determine which scenario is

best to meet the outputs determined. Figure 5.1 demonstrates the interrelation and flow of

waste between different waste treatment technologies or practices. On the left of the figure

there are five categories; home separation, collection, treatment, recovery & marketing and

final disposal, these indicate the methods for managing municipal wastes. Each treatment

method has different applications, which are shown as generic processes, colour coded to the

method, with the specific applications of the method detailed under the generic heading, for

example, a material recycling facility, is a treatment methodology and the practices used in

that technology are separation and screening of materials, with other materials being sorted

through the use of infrared colour separation technologies.

Page 82: Waste management model

82

Figure 5.1: The components of the integrated waste management system for MBM

The model is constructed in Microsoft Excel and to enable a user to understand the model,

the full MBM is presented in Appendix 2 with a user manual presented in appendix 4. The

MBM is split into 3 principle sections;

Input Sheet,

Calculation sheet and

Results sheet

The three sections for the MBM are clear for the user when modelling but do not allow for

easy description of the process of creating the MBM, nor the interaction between the three

sheets. To allow the user to understand the creation of the MBM, it is necessary to give an

explanation of each stage and the sub-calculations and assumptions contained within.

5.2.1. Input sheet

The input sheet is for entering data for modelling and is shown in Table 5.1, it consists of

four sections; facility throughputs, facility efficiencies, MSW and HW base data and waste

growth scenarios. The sections are colour coded by title and input cells, the dark colour is the

section heading, the yellow cells are for the user to input their data. The parameters

described in Sections 5.4, 5.5 and 5.6 are entered into the MBM through this table. The input

sheet in Table 5.1 uses a the base year of 2002/3, this being first contract year for the ESCC

& B&HCC contract, but this is flexible and other councils can change the start date.

Open

composting

screening

maturation

Reprocessing and

Marketing

Energy Recovery: Mass Burn EFW

blending of input MSWCombustion and energy

generation

Fin

al

Dis

po

sal Landfill

Landfill Landraise

(sub-boxes indicate process employed by

activity

Ho

me

sep

erat

ion

Co

llect

ion Kerbside Collection

AWC Residual

Infrared

Home

Composting

Food

Digestion

Hazardous

Bring Banks

recycling WEEE

Household Waste Recycling

Centre

timber Residual green

Hazardous

Material Recycling Facility (MRF) Anaerobic Digestion (AD)

WEEE

Bulky

recyclingclothes, shoes

and books

In-Vessel

Composting

Screening

Tre

atm

ent

Rec

ove

ry a

nd

Mar

ketin

g

Seperation Screening screening

maturation

maturationSeperation

tran

sfer

&

bu

lkin

g

tran

sfer

&

bu

lkin

g

dry recyclables

Re-Use

Page 83: Waste management model

83

MRF1 MRF2On-farm

Composting

Anaerobic

DigestorIVC 1

Third

Party

waste

RDF

Plant

Household

Waste

diverted by

use of bring

banks

HWS Bring

banks

Throughput of

EfW 1

EfW 1

residuals

EfW 2

esiduals

85% 85% 100% 50% 100% N/A 35% 100% 100% 69% Base Ash 28% 28%

15% 15% N/A 50% 0% 65% N/A N/A 31%Base ash to

landfill50% 50%

50% 50% N/A 50% 0% 50% 100% N/A N/A 50%

50% 50% N/A 50% 0% 50% 0% N/A N/A 50%

0% 0% N/A 0% 0% 0% 0% N/A N/A 0% Fly ash 3% 3%

(Percentage) (Percentage)Financial

Year

Contract

Year0.00% 0.00% 2002/3 1 - - 5,000 - 19,114 75,000 15,044 - -

2.00% 2.00% 2003/4 2 40,000 - 15,000 - 19,496 75,000 3,836 6,905 -

2.00% 2.00% 2004/5 3 40,000 - 15,000 - 19,886 75,000 3,913 7,044 -

2.00% 2.00% 2005/6 4 40,000 16,000 5,000 60,000 30,000 20,284 75,000 3,991 7,184 -

2.00% 2.00% 2006/7 5 40,000 16,000 5,000 60,000 30,000 20,690 75,000 4,071 7,328 -

1.00% 1.00% 2007/8 6 40,000 16,000 5,000 60,000 30,000 20,897 18,750 4,112 7,401 -

1.00% 1.00% 2008/9 7 40,000 62,000 5,000 60,000 30,000 21,105 - 2,076 7,475 150,000

1.00% 1.00% 2009/10 8 40,000 62,000 5,000 60,000 30,000 21,317 - 2,097 7,550 150,000

1.00% 1.00% 2010/11 9 40,000 62,000 5,000 60,000 30,000 21,530 - 2,118 7,626 150,000

1.00% 1.00% 2011/12 10 40,000 62,000 5,000 60,000 30,000 21,745 - 2,139 10,269 150,000

0.50% 0.50% 2012/13 11 40,000 62,000 5,000 60,000 30,000 21,854 - 2,150 10,321 150,000

0.50% 0.50% 2013/14 12 40,000 62,000 5,000 60,000 30,000 21,963 - 2,161 10,372 150,000

0.50% 0.50% 2014/15 13 40,000 62,000 5,000 60,000 30,000 22,073 - 2,172 10,424 150,000

0.50% 0.50% 2015/16 14 40,000 62,000 5,000 60,000 30,000 22,183 - 2,183 13,095 180,000

0.50% 0.50% 2016/17 15 40,000 62,000 5,000 60,000 30,000 22,294 - 2,193 13,161 180,000

0.50% 0.50% 2017/18 16 40,000 62,000 5,000 60,000 30,000 22,406 - 2,204 13,226 180,000

0.50% 0.50% 2018/19 17 40,000 62,000 5,000 60,000 30,000 22,518 - 2,215 13,293 180,000

0.50% 0.50% 2019/20 18 40,000 62,000 5,000 60,000 30,000 22,630 - 2,227 13,359 180,000

0.50% 0.50% 2020/21 19 40,000 62,000 5,000 60,000 30,000 22,743 - 2,238 13,426 180,000

0.50% 0.50% 2021/22 20 40,000 62,000 5,000 60,000 30,000 22,857 - 2,249 13,493 180,000

0.50% 0.50% 2022/23 21 40,000 62,000 5,000 60,000 30,000 22,971 - 2,260 13,560 180,000

0.50% 0.50% 2023/24 22 40,000 62,000 5,000 60,000 30,000 23,086 - 2,271 13,628 180,000

0.50% 0.50% 2024/25 23 40,000 62,000 5,000 60,000 30,000 23,202 - 2,283 13,696 180,000

0.50% 0.50% 2025/26 24 40,000 62,000 5,000 60,000 30,000 23,318 - 2,294 13,765 180,000

Input column for MW &

HW growth0.0%

Residue to

Beneficial

Use

50% 50%

Waste Growth

Facility efficiencies

Facility Throughputs

Facility parametersTHE MASS

BALANCE MODEL

(MBM) Efficiency of plantEfficiency of plant

0%HW growth

Base figure HW 376,112

Total residues

residues to landfill

residues to efw

residues to benefical

use

Base year MSW & HW figures

Base figure MW 393,271

Table 5.1: The MBM input sheet, with raw data from RS1

Page 84: Waste management model

84

In table 5.1, data has been entered for annual waste growth projection, two MRFs, an on-farm

composting facility, an anaerobic digestion facility, an IVC composting plant, third party

waste, a RDF facility, bring banks at both the kerbside and in household waste sites and an

EFW. Using the EFW as an example, the percentage of the input tonnage that will become

base ash and fly ash is required, and for the base ash, the percentage of the base ash that will

be used is required. The EFW has residues of 31% (total of both ashes) and 50% of the bash

ash is reused (including metals) and 50% is landfilled. It can also be seen in table 5.1, that

between 2002/3 and 2007/8 there is no tonnage entering the EFW, between 2008/9 and

2014/15, 150,000 tpa will enter the EFW and after that date 180,000 tpa. This level of detail

is required for each facility to enable the MBM to calculate the results the user requires.

5.2.2. The MBM Calculation Sheet

The MBM calculation sheet consists of an Microsoft Excel worksheet containing 116

columns (some formatted columns and others hidden) by 35 rows (including the twenty-five

different years, more or fewer years can be added), these are shown in Appendix 2 as screen

shots. Each column either references an input from the input sheet or is a built in calculation

(which has a set equation or an equation that can be changed depending on the assumption

relevant to the particular equation). The Calculations sheet consists of seven main sections

and is presented in appendix 5, but summarised below:

o Years

o Waste and Waste growth

o Targets and meeting targets

o Recycling and composting

o Energy recovery

o Beneficial Use, and

o Disposal to land.

Each section includes calculations and data input columns, and most sections are calculated

and inputted on a yearly basis. It is important to note that in most cases each component has

its own inherent assumptions that have been explained in chapter 4, or will be expanded in

the follow sections.

Page 85: Waste management model

85

A decision tree has been developed to show the questions and answers that form the basis of

the calculations within the MBM. Figure 5.4 shows a simplified version of how msw waste

will be treated through the MBM.

Figure 5.2: Decision tree for the mass flow of MSW through the facilities

The MBM uses units of mass or percentages derived from mass to enable comparison of

outputs against targets. Base data was used to generate calculations; the sources are shown in

Table 5.2.

Base data Source of Information Reference in thesis

Waste Data for base year ESCC & B&HCC Waste Team Chapter 1

Waste arising profile ESCC Demographics team Chapter 4

Targets ESCC, DEFRA and European Union Chapter 1

Estimated Landfill capacity ESCC, Viridor and BIFFA Chapter 3

Landfill compact rate BIFFA and Viridor Chapter 3

MRF efficiency Project Integra Chapter 3

On farm composting residual rate KPS composting Chapter 3

Enclosed composting plant residual rate Hampshire waste Services MD Keith Riley Chapter 3

RDF recycling and residual rate ESCC Waste Management Statistics Chapter 3

EFW diversion rate An Introduction to Household Waste

Management - ETSU for the DTI. Chapter 3

EFW residual residue usage Technical Brief from Residua & Warmer

Bulletin - EFW Chapter 3

Table 5.2: Base-data used in MBM

Page 86: Waste management model

86

5.2.3. Results sheet

The results sheet is a single worksheet that presents the results of the numerous calculations

undertaken by the MBM in a format that enables the user to understand whether the desired

outcome has been achieved. Table 5.3 presents an extract of the results as a list, with the

lower order definition of the result shown, for example, there are eight ways that the amount

of MSW is categorised. A full analysis of the results will be explored in section 5.10.

Result category Lower order definition

What Year? Financial Year

Contract Year

Does the Solution meet the Targets set by the user? Are the Recycling targets met?

Are the Recovery targets met?

Waste Arising

Total Municipal Waste arising per year

Total Household Waste per year

Total Municipal waste other than Household Waste

Total Municipal Waste arising Total Municipal Waste

Contract waste arising

Total Contract Waste

Contract Household Waste

Contract Waste other than Household Waste

Third party waste arising Third party waste

Total Recycling of Municipal Waste Total Municipal Waste

Contract waste recycled

Total contract waste Recycled

Contract Household Waste Recycled

Contract Waste other than Household Waste Recycled

Third Party Waste Recycling Third Party Waste (inc Recycling)

Total Recovery of Municipal Waste Total Municipal Waste

Contract waste recovered Contract Household Waste Recovery

Contract Waste other than Household Waste Recovered

Third party Household Waste recovered Third party waste recovered

Contract Waste put to Beneficial Use Total Municipal Waste

Total amount of Municipal Waste going to Landfill

Total Municipal Waste

Active waste

Inactive waste

Household Waste, Recycling

Number of tonnes of Household Waste Recycled

Percentage of the Total Household Waste Recycled

Contract targets for Recycling

Energy Recovery (EFW) Total Household Waste

Total Household Waste (%)

Total Recovery

Number of tonnes of Municipal Waste Recovered

Percentage of the total Municipal Waste Recovered

Contract targets for Recycling

Total Capacity of all facilities including Bring Banks Total Municipal Waste

Total tonnage not treated by any of the facilities Total Municipal Waste

Table 5.3: An extract from the MBM results sheet (see pages 99-103 for full detail)

Page 87: Waste management model

87

The use of the assumptions and starting data enabled the modelling of a waste profile over a

25 year timeframe, the flows of different sub-streams of waste through different technologies,

and the determination of the ultimate processing capacities and calculation of the total void

space required from landfills for the residual waste, whilst calculating performance against

targets are demonstrated in the results sheet.

5.3. The Creation of a Reference Scenario

To demonstrate how the MBM was practically used, and to describe the detailed calculations,

assumptions and results, a reference scenario is presented in the following sections. The

scenario was modelled by the author and used by the Brighton & Hove City Council and East

Sussex County Council procurement team, over the period of 2002 to 2003, as the tool for

evaluating the technical submission of five contractors during the procurement of ESCC and

BHC PFI Integrated Waste Management Services Contract (IWMSC).

In 2003, Brighton & Hove and East Sussex Councils awarded a twenty-five year contract to

the waste management company Veolia, for the provision of an integrated waste management

service entitled the ―Integrated Waste Management Services Contract (IWMSC)‖. Veolia set

up a special purpose vehicle (SPV), called Veolia South Downs (VSD) to manage the service

over the lifetime of the contract. This is similar to a franchise, whereby a guarantee would

satisfy the contracting party (councils) that any debt or problems will be covered by the

parent company (Veolia Environmental). The contract was signed with VSD on 31st March

2003 for a contract sum of £1 billion over a 25 year period by means of a Private Finance

Initiative (PFI) agreement. This was underwritten by DEFRA who committed to releasing

£49 million of funding to the Councils over the contract period, in order to supplement the

capital cost of the facilities.

During 2002 and 2003 the MBM was used to test 8 different scenarios, based upon 8

different technical solutions for diverting waste from landfill and five waste growth profiles

as shown in Figure 5.2; High, High-Medium, Medium, Low and base case. A total of 40

scenarios were run through MBM in the period 2002-2003. Rather than describing all 40

models, one set of parameters will be used to show how the MBM was created and used; the

Page 88: Waste management model

88

scenario chosen also demonstrates how the MBM was practically used. The reference

scenario shown is the technical solution agreed through the PFI process and will be described

as RS1 throughout the remainder of the chapter.

5.4. Reference Scenario 1 (RS1)

To demonstrate RS1, the model has been broken down into five distinct stages of collation or

calculation, these relate to the three parts of the MBM, but in addition describe some of the

assumptions, correlations and calculations used. The five stages are:

Stage 1: Initial Waste Mass Data (Starting data and growth modelling)

Stage 2: Individual Facility and Process Throughputs

Stage 3: Calculation of targets and required landfill void

Stage 4: Testing the MBM

Stage 5: The MBM results sheet and graphical outputs

There follows an explanation of each stage and the sub-calculations and assumptions.

5.5. Stage 1: Initial waste mass data (starting data and growth modelling)

The first stage of the RS1 describes the parameters that are used to determine the amount of

waste that arises each year in the model. This stage is critical as all assumptions about facility

capacity will be determined by how much waste is modelled. The information required for

this stage is:

raw data for the base year

waste growth profiling

As demonstrated by the critique in section 4.2, accurate raw data is crucial, but it will be

demonstrated that the accurate projection of waste mass arising through a considered waste

growth profile is also essential. The timescale (number of years the model will project

forward) for modelling is also required, the IWMSC uses a 25 year projection and this

timeframe is modelled in RS1.

Page 89: Waste management model

89

5.5.1. Raw data for the base year

The base year for the model needs to be set to allow the model to operate and should be the

last set of accurate figures the authority has recorded for a year. RS1 is based on the

information required to model the facilities required for the PFI contract (IWMSC) and

2002/03 will be used as the base year (Chapter 5 will present a second reference model with

updated Figures). The ESCC & BHC historical data required for the model is as follows:

Tonnes of HW in 2002/3

Tonnes of MSW in 2002/3

Tonnes of HW & MSW recycled in 2002/3

Tonnes of HW & MSW composted in 2002/3

Tonnes of HW & MSW sent to landfill in 2002/3

Most up-to-date compositional analysis

5.5.2. Waste growth profiling

The year on year generation of MSW is unlikely to grow at a steady rate and the prediction of

future MSW mass is an inexact science. DEFRA states ―It is not statistically robust to make

forward projections for twenty years on the basis of even ten years‘ data‖. The conventional

approach to forecasting reflects the limited understanding of exactly how many of the

underlying factors influence waste growth with profiles being based more on the historical

profiles than the impacts of future decisions.

A waste growth profile is normally expressed as a percentage increase or decrease for every

year to be modelled, except the base year. The mass of MSW and HW is calculated from the

―base year‖ using the growth percentage for each subsequent year. In the MBM separate

growth profiles for HW and MSW can be modelled, in RS1, the assumption has been made

that both will grow at the same rate. The three distinct contributing factors associated with

generating a waste growth profile, lifestyle choices of the individual, exogenous factors and

historical data. The following sections will explore each factor that will influence the

generation of a single percentage point figure for one year.

Page 90: Waste management model

90

5.5.2.1. Lifestyle choices of the individual

In 2006, Maunder et al, after extensive consultation compiled ―twelve key drivers and trends

that would have greatest impact (either negatively or positively) on household volume and

waste‖ up to 2020, these are:

Increase in consumer affluence

Increase in single society living

Culture of lifestyle change (e.g. house moves, divorce retirement etc)

Growth of the ‗experience‘ economy (e.g. spending on experiences

rather than goods)

Shortening product lifestyle

Growth of tele-working and the knowledge economy

Increasing longevity

Lifestyle choices of the ‗Baby Boom‘ generation

Growth of online convenience shopping

New regulations and legislation

Perceived effect of climate change

Increase in ethical consumption

These are factors that are very difficult to quantify in real terms and considerable research,

going back to the sixteenth century for some factors, population increase, for example, has

shown that predictions are difficult. One of the most famous population researchers was

Thomas Malthus, who studied population growth in the 1770s. In his 1798 Essay on the

Principle of Population; Malthus argued that human populations tend to grow exponentially,

while food production is limited by land available for agriculture. The impact of population

growth on generation of waste, whilst being difficult to predict, apparently does show an

empirical link. If a household generates 1 tonne of waste per annum, it can be concluded that

if a hundred new homes were to be built in a given area, an increase in waste generated of

100 tonnes would occur every year. For the purposes of RS1 these factors will be

incorporated where feasible and explained in further detail in Section 5.4.4.

Page 91: Waste management model

91

5.5.2.2. Exogenous contributing factors

These are much broader in their nature but have correlations with the life style factors; all are

annually changeable and difficult to predict, therefore for the development of RS1, these

factors have not been included. The exogenous impacts are defined as:

Public Holidays

Weather

Council waste prevention activities

Sporting events and consumption of food and drink

5.5.3. Historical data

Using historical data will enable a ―waste growth trend‖ to be determined; the term ‗trend‘

should not be taken to mean ‗growth over the last year‘, but stable patterns over a period of

years. A trend in growth needs to be measured over a period of years, ideally 4 – 5 years;

Table 5.4 shows that the total MSW generated per annum has increased in East Sussex over a

seven year period.

Authority 1997/98 1998/99 1999/00 2000/01 2001/02

Average

increase over 5

years

Difference in waste

between 1997/98

and 2001/2

383,958 380,473 388,241 376,779 377,743

105,362 102,232 90,571 89,237 89,304

38,118 33,871 37,602 22,331 23,418

143,480 136,102 129,843 113,339 114,232

26,392 29,981 30,828 32,135 31,603

29,737 31,175 31,834 33,322 33,394

57,668 61,286 63,579 65,806 62,399

32,819 33,885 35,148 37,171 33,572

26,727 27,504 28,683 30,503 30,727

173,343 183,831 190,072 198,937 192,104

67,135 59,239 66,024 64,120 71,407

ESCC Total 240,478 244,370 258,398 263,440 263,511 2.4% 9.6%

2.7%

1.6%

10.8%

6.4%

4.9%

3.1%

2.1%

12.3%

-0.4%

-3.8%

-9.6%

-5.1%

-15.2%

-38.6%

-20.4%

-1.6%

Wealden

Rother

Hastings

ESCC HWRS

19.7%Eastbourne

2.3%

15.0%

0.6%

3.7%

Total ESCC & BHC MSW

BHC collected

BHC HWRS

ESCC collected

BHC Total

8.2%

Lewes

Table 5.4: MSW arising and growth rates for all ESCC and BHC authorities 1997-2002

(ESCC 2002)

Analysis of Figure 5.4 shows there are anomalies to the figures that may look extreme if

looked at individually. In 1999/00, the level of MSW arising in ESCC and BHC is much

larger than any other year; this is partly due to the amount of trade waste entering the CA

sites in both authorities being unrestricted and increasing significantly possibly due to the

Page 92: Waste management model

92

impact of the increase in landfill tax meaning companies wanted to dispose of waste for free

at the HWRS. This general increase in waste is also seen in amount collected by all the

WCAs, with the exception of BHC, who had imposed a ban on trade waste being collected

with household waste. This policy was introduced to kerb the practice of commercial

premises paying for two bags of waste to be collected and then putting out 10. The impact of

the under payment was both financial and data compromising, the latter meaning that the

extra 8 bags would count as household waste, rather than commercial waste. The impact of

this policy resulted in 12,000 tonnes of waste not being counted as household waste.

The following year, the authorities banned trade waste from entering the HWRSs and that is

demonstrated by a 40% reduction in waste entering the BHC HWRS. The historical data will

be used to influence the generation of the waste growth profile, but due to the impact of

policies and categorisation will not form the fundamental base data for prediction. The main

data set that appears to be consistent is the waste arising in the WCAs (except Brighton) grew

2.7% over five years; this growth rate will be used for generating a future growth model.

5.5.4. Generation of a growth profile

Each of the three waste growth factors have perceived and very real impacts on waste growth.

Rather than model one scenario which is assumed to definitively predict the total amount of

waste generated in 2028/29 (RS1 end year) it is more prudent to have a range of scenarios

that will allow the opportunity for sensitivity analysis. The factor that influenced the waste

growth scenarios the most was household growth. The planning authorities developed three

housing growth scenario in 1999, Low – policy based model, Medium – housing based model

and High – migration led model. These profiles were influenced by government targets for

new housing and reflected the difference between council policies and anticipated high

migration level. The three profiles are shown in Figure 5.3.

Page 93: Waste management model

93

Figure 5.3: Housing growth scenario for ESCC and BHC (ESCC 1999)

The housing growth scenarios were used in the creation of the RS1 growth profiles. The

information available was combined with knowledge of factors that would impact waste

collected, for example, home composting and with historical waste growth figures, shown in

Table 5.4, to generate a base case waste growth profile.

Five blended growth profiles were created that took account of all the factors demonstrated in

Table 5.4 and Figure 5.3, with two additional extreme scenarios created to try to reflect every

eventuality. The trend of the baseline scenario was that the increase in waste per annum

would diminish over the period up to 2025 and that the significant reduction in the increase in

waste would occur after 2011, when the effect of the landfill directive would begin to tell.

Figure 5.4 shows the five profiles that were developed to test the impacts of waste arising on

deliverability of targets and flexibility of capacity size:

0.0%

0.1%

0.2%

0.3%

0.4%

0.5%

0.6%

0.7%

0.8%

0.9%

1.0%

1.1%

Bas

e

98

/99

99

/00

00

/01

01

/02

02

/03

03

/04

04

/05

05

/06

06

/07

07

/08

08

/09

09

/10

10

/11

11

/12

12

/13

13

/14

14

/15

15

/16

16

/17

17

/18

18

/19

19

/20

20

/21

21

/22

22

/23

23

/24

24

/25

25

/26

26

/27

An

nu

al

Gro

wth

(%

)

Finacial Year

Low - Policy Based Model

Mid - Building Led Model

High - Migration Led Model

Page 94: Waste management model

94

Figure 5.4 Growth rate scenarios used for sensitivity analysis

The base scenario in Figure 5.4, taking account of all factors, would be considered the most

likely growth profile and was used as the reference scenario for RS1.

5.6. Stage 2: Individual facility and process throughputs

The MBM has been developed on a Microsoft Excel platform, some of the calculations that

are explained in this section are based on the mathematical solutions that are unique to Excel.

Figure 5.1, identifies the facilities and treatments that can be modelled in the MBM, however,

for RS1, only the six major facilities are required to be explained and will be modelled in

RS1. Each facility has been described in chapter 3 and will perform differently depending

on the configuration of the individual facility. The six facilities to be modelled in RS1 are:

Material Recycling Facility (MRF)

On-farm Composting

In-Vessel composting (IVC)

Anaerobic Digester (AD)

EfW (Mass Burn Incineration)

Refuse Derived Fuel (RDF)

Page 95: Waste management model

95

In addition to the six facilities, the amount of space required for waste to be landfilled will be

determined by the MBM. For modelling purposes each facility needs to have capacity from

the outset to enable achievement of a future target, the facility should therefore be large

enough from the date of construction to allow for waste growth. In some cases this will result

in the years preceding the target year achieving a much higher performance than is necessary.

As MBM is a mathematical model, the types of the facility are immaterial, but, the

assumptions used for each facility are crucial.

Facilities size and mass

balance assumptionsUnits MRF

On-farm

Composting

Enclosed

composter

(IVC)

RDF PlantAnaerobic

Digester EfW

Capacity of facility tpa 40,000 5,000 30,000 75,000 60,000 180,000

Efficiency of facility % 85% 100% 95% 35% 50% 69%

Total residues % 15% 0% 5% 65% 50% 31%

residues to landfill % 0% 0% 0% 100% 40%

residues to EFW % 100% 0% 100% 0% 0%

residues to BU % 0% 0% 0% 0% 0%

Residues to Recycling

or further processing %0% 0% 0% 0% 60%

Base Ash (inc metals) % 28%

Base ash to landfill % 50%

Base Ash to BU % 50%

Fly ash to Haz landfill % 3%

Table 5.5: Facility capacity and efficiencies used within RS1

For RS1 individual facility types are modelled against the facilities proposed as a solution

under the PFI procurement and the evaluation of facilities undertaken in chapter 3. In the

RS1 each of the facilities has a section of calculations that will be contextualised as a

description of the excel model and the calculations contained within that section. Table 5.5

shows each of the facilities used within RS1 and the percentage efficiencies for each process.

Shaded cells are not required for that facility. The facilities and efficiencies shown within

Table 5.5 exclude assumptions on landfill and this will be explained later in the chapter.

5.6.1. Material Recycling Facilities (MRFs)

The MBM has made created to allow for four possible MRFs, this assumption is made as

larger scale MRFs are be built to benefit from economies of scale, and for an area the size of

ESCC and BHC, two MRFS would be sufficient, but to allow for use by other larger

authorities four have been included. Each has the ability to have a different efficiency or to

Page 96: Waste management model

96

not be used at all, for RS1 two medium sized MRFs of 40,000 and 62,000 t.p.a. have been

modelled. The MRF section determines three outputs; mass of recycled waste, mass of

residual waste and destination of residual waste. For each year in the model relating to

recycling there are two calculations used. The amount of waste recycled is determined from

the efficiency of the MRF and the mass of household waste delivered to the MRF as follows:

HWR = HWD * HEF

Where:

HWD = Household Waste delivered to MRF

HWR = Household waste recycled

HEF = Efficiency of MRF

For MRF One, with a capacity of 40,000 tpa, the calculation is thus:

Total HW recycled: 40,000 * 0.85 = 34,000tpa

For this MRF, 34,000 t.p.a. would be sent for recycling and 6,000 tpa would be classed as

residual and would need to be allocated for in the MBM. The model allocates the residues

from the MRF depending on availability of other facilities to either landfill or EFW on a year

by year basis. If the EFW is operational; all residues from the MRF will be delivered to the

EFW, when not operational, the residue will be delivered to landfill

In the MBM the equation that translates the previous section uses an ―IF‖ statement (MS

Excel), it is necessary to demonstrate how the ―IF‖ statement is used in the MBM so that if

other modellers wishing to replicate the equation outside of Excel can. The explanation of the

equation is a follows:

MRFR = IF (EFW1+ EFW2=0, 0, HWD-HWR)

where:

MRFR = MRF Residue to EFW

EFW1 = Throughput of EFW 1 in tonnes;

EFW2 = Throughput of EFW 2 in tonnes;

HWD = Total MRF throughput; and

HWR = Household waste recycled at MRF

Page 97: Waste management model

97

The equation if converted to text would read as:

―The MRF residue to EFW equals; if the total capacity of EFW1 and EFW2 equals nought,

then the answer will be nought, if however EF1 plus EFW2 is greater than nought, then the

answer for the cell will be the total MRF throughput, minus household waste recycled at the

MRF”

Numerically, if EFW1 had a capacity of 100,000 tpa in 2011/12, and the MRF had a capacity

of 40,000tpa, with an efficiency of 85%, 6,000 tpa would be sent to the EFW. This equation

would be calculated in one cell on the spreadsheet and would read as 6,000. Each of the

variables would be contained in the input sheet and be linked to be cell references using

letters and numerals.

5.6.2. Open composting

Composting has been identified in chapter 3 of being of various technologies, enclosed, open

and on farm. For the base case, an enclosed compost facility and an open facility (windrow)

have been modelled. In RS1, windrow composting accounts for diversion of 15,000 tpa of

MSW, the model uses the efficiency figure of 100% to undertake a simplistic calculation of

mass multiplied by efficiency, thus for every tonnes deemed to enter the windrow composter,

all will be counted by the model as being composted.

5.6.3. In-vessel composting

In-vessel composting systems vary according to type, feedstock and operator capability,

chapter 3 describes the attributes of the systems available commercially with reference to the

most suitable feedstock for particular solutions. RS1 has modelled an IVC to have the same

impact as a windrow system, thus, every tonne entering the facility is assumed to be diverted

completely with no solid residues, giving the simple equation:

Composted = Mass * Efficiency

In the case of a 30,000 IVC facility the amount of composting entering the facility and being

composted would equate to:

30,000 * 1 = 30,000 tpa

Page 98: Waste management model

98

5.6.4. Energy recovery

The section in the model relating to energy recovery is probably one of the most contentious

issues, not in terms of the way the model works, but because of public perception, discussed

in chapter 3. Following this discussion it was decided that only two commercially proven

types of energy recovery (excluding landfill gas reclamation) anaerobic digestion and energy

from waste (mass burn incineration), would be used for RS1. A description of the parameters

for each follows.

5.6.4.1. Anaerobic Digestion (AD)

An AD plant can vary a great deal in efficiency; which is entirely dependant on the quality of

the input to the facility. If a good quality feed stock is used, the production of recyclable

material and energy will be high. If a mixed MSW fraction is used the resultant biodegraded

product will be sufficient only for landfill cover and non-compost uses (composting

association 2000). In RS1, the assumption is made that the AD uses mixed MSW for the

input, with a reference capacity of 60,000 tpa. This is the only economically amount viable

for this input, as under current collection methods, there would not be enough biodegradable

waste separated from the household stream using projections to have a dedicated bio-waste

input. The material balance in Figure 5.5 shows flow of materials through one type of

anaerobic digestion system, this will be used in RS1.

Figure 5.5 AD mass balance diagram (Ostrem 2004)

Page 99: Waste management model

99

The moisture content of MSW is normally between 50 and 65%, and with normal AD

operating conditions needing 75%, water must be added. This is provided by dewatering the

final solid digestate and recirculation back to the mixing tank. Figure 5.5 shows that this

amount of additional water can be supplied entirely by recycled process water, thereby saving

money and resources for the plant. The disadvantage of using strictly recycled process water,

however, is that salts can concentrate in the water and remain in the resultant digestate. Most

plants use a combination of fresh and process water (Cluff, 2003). The exception is in

locations where water is a valuable commodity, such as Israel (Finstein, 2003).

RS1 includes one facility of 60,000 tpa, with an input mixed waste MSW. This will mean that

a separation process will need to be undertaken prior to the waste being fed into the AD

facility. The assumption has been made that following processing in a DANA drum 50% of

the MSW will be sent to the AD, with remainder being processed for recycling or sent to

landfill (OWS 2000). The DANO drum is a large scale separation process and is assumed to

take 100% of the MSW sent to the AD facility, process it and divert two fractions, one to the

AD facility and one for further recycling or landfill. Of the material that does enter the AD

facility, 42.3% is assumed to be diverted from landfill as digestate (OWS 2000). As with the

MRF calculations, there is a basic calculation for each year of the model, followed by a

complex calculation to distribute the residual waste amongst other facilities.

MSWAD = ADM * AEF

Where:

MSWAD = MSW sent for anaerobic digestion

ADM = MSW delivered to AD facility

AEF = Efficiency of DANO Drum

IN RS1 the MSW sent to the AD facility is 60,000 resulting in the following calculation:

MSWAD: 60,000 * 0.5 = 30,000tpa

Of the 30,000 tpa sent to the AD facility 42.3% is recovered as digestate

Page 100: Waste management model

100

Digestate: 60,000 * 0.423 = 25,380tpa

The result of this equation means that 34,620 tpa residual material of a largely combustible

nature needs to either landfilled or recovered as biogas. RS1 assumes that 13% of the residual

material is bio gas and the remaining 43.7% is process loss, as waste water. For the purpose

of calculating the recovery target in the MBM, recovery means biodegradable waste that

enters the digestion process and thus this distinction is not relevant for reporting targets.

5.6.4.2. Energy from Waste (EFW)

The EFW section of the model is very similar to that of the AD, but, in the case of the EFW,

the recovery of energy is very high at 69% (CNIM 2000). Where metal recycling is possible

this normally accounts for 2% of the inputs, the remainder is base ash 26%, which can reused

or put to beneficial use, and fly ash (3%), which has to be disposed of in special waste landfill

sites. The mass flows used in the RS1 are contained in Figure 5.6:

Figure 5.6: Mass flow diagram for parameters to be used in EFW section RS1 (adapted from

CNIM 2000)

In RS1, two EFW facilities are modelled; the principles of the calculations are the same and

therefore only one explanation of the calculations is required. EFW1 has a maximum capacity

of 180,000, with the energy recovery efficiency stated in Tables 5.5 and 5.6 resulting in the

following calculation:

MSWEF = EFM * EEF

Page 101: Waste management model

101

where:

MSWEF = MSW having energy recovered

EFM = MSW delivered to EFW

EEF = Efficiency of Anaerobic Digestion facility

MSWEF: 180,000 * 0.69 = 124,200 tpa

The 124,200 tpa will be contribute to the calculation of energy recovery whilst the remaining

55,800 tpa will need to be subdivided into component parts to demonstrate onward movement

of residual materials. The calculation that separates these fractions is similar to that of the

AD, but with an extra permutation. There are five possible destinations for the residual post

combustion; three are determined by the type of facility and two are dependant on availability

of markets for inert material and hazardous alkaline fly ash for neutralisation of acids, the

five are:

Base ash to landfill

Base ash to road base construction

Fly ash to acid neutralisation

Fly ash to landfill

Metals for recycling

The relative efficiencies for the five are summarised in Table 5.5 and apply for every year of

the model, with the exception of the throughput which may vary according to MSW delivered

to the facility. Table 5.6 uses the example of 2015/16 when the EFW is assumed to be fully

operational:

Facilities size and mass

balance assumptions

Units EfW

Capacity of facility tpa 180,000

Throughput of the facility tpa 180,000

Energy recovered % 69%

Total residues % 31%

Base Ash % 26%

Base ash to landfill % 50%

Base Ash to BU % 50%

Metals from Base ash % 2%

Fly ash to Haz landfill % 2%

Fly ash to beneficial use % 1%

Table 5.6: EFW parameter assumption for RS1 for the year 2015/16 (CNIM 2000)

Page 102: Waste management model

102

For 2015/16 these assumptions yield the following:

MSW recovered: 180,000 * 0.69 = 124,200

Base ash generated: 180,000 * 0.26 = 46,800

Metals generated: 180,000 *0.02 = 3,600

Fly ash generated: 180,000 *0.03 = 5,400

The bash and fly ash can then be further subdivided:

Incinerator Bottom Ash (IBA) to landfill: 46,800*0.6 = 28,080

IBA to beneficial use 46,800*0.6 = 18,720

Fly ash to hazardous landfill: 5,400*0.33 = 3,618

Fly ash to beneficial use: 5,400*0.67 = 1,782

The series of calculations shown above are undertaken in eight different cells, for every year

modelled in RS1, with subsequent safeguard checks and summarising cells, similar to that

shown for the AD plant.

5.6.4.3. Landfill

Landfill is the sump for all untreated MSW or for the residues of processes with no further

treatment capabilities. Once the total number of tonnes requiring landfill has been identified,

the total landfill void required for the waste needs to be calculated. This is done in two steps.

Firstly the density of MSW is calculated and then the void required for engineering works, is

added to give an overall void capacity for the waste. Three streams of MSW are landfilled in

RS1; bulky HWRS residue, domestic collected waste, and residual treatment waste. The

streams have different compaction characteristics which influences the mass/m3, which in

turn influences the amount of void space required. To calculate the landfill void required for a

tonne of waste being sent to landfill, the following factors for each of the three streams need

to be calculated:

Mass per m3

Percentage of 1 tonne of MSW sent to landfill

Page 103: Waste management model

103

The assumption is from a waste compositional analysis made at Beddingham landfill, Lewes,

in 1999, and are summarised in Table 5.7. The Table estimates the content of one tonne of

MSW in 2010/11, when there will still be a large element of untreated waste being sent to

landfill. This is represented by the HWRS and MSW rows, these percentages will change

over the course of the 25 years as the amount of untreated waste reduces.

Source of waste Percentage of total

stream Tonnes per m

3 Calculation Tonnes per m

3

HWRS 25% 0.5 0.5 * 25% 0.125

Domestic 60% 0.8 0.8 * 60% 0.480

Residual 15% 1.5 1.5 * 15% 0.225

100% 0.83

Table 5.7: Volume of one tonne of waste being sent to landfill (Viridor 1999)

The density of MSW has been assumed to be 0.83 tonnes per m3 meaning that for every

100,000 tonnes of waste landfilled 120,482 m3 of void will be required. To protect the

environment, the void space needs to be engineered with a lining of composite, as described

in section 3.4 and then an additional 10% of inert material will be required for engineering

purposes (Viridor 1999). Thus for every tonne of waste landfilled, 1.22 m3 of void space will

actually be required. The total void capacity required, is therefore:

Volume of waste (m3) *1.22

Once the equations for the density and engineering have been calculated, a cumulative total

of void required over the lifetime needs to be calculated, this will be demonstrated in section

5.7.5. Stage 2 has so far shown the detail required for some of the main facilities within the

model, there are a few minor facilities or streams of waste/recyclables that do not need

detailed investigation, they are summarised below:

5.6.5. Bring banks

There are two types of bring banks site, those operated by the WCAs at dedicated sites in

their individual areas, and banks placed in HWRSs by the WDAs. For RS1, the assumption

has been made that current facilities will remain and usage will increase because once the

public recycle at the kerbside they tend to use bring facilities more (Read 1999). After the

MRF is modelled to open, a substantial amount of bring bank collected waste would be

Page 104: Waste management model

104

delivered to the MRF instead of being bulked up at a depot and being sent directly to a

reprocessing facility. A small percentage of bring bank material will still go direct to market

and the prudent view is that 1% of the total HW arising will be bring banks delivered material

direct to market (Read 1999).

5.6.6. Non governmental organisation (NGO) recycling

The concept of NGO recycling is not an unusual one in local authorities, normally the

recycling is undertaken by charities, for example OXFAM, the Salvation Army and the Scout

Association, but in Brighton the community recycling group MAGPIE collect recyclables. If

a NGO recycles MSW and therefore diverts it from landfill the WDA is obliged to pay the

NGO a recycling credit for the each tonne they collect and recycle (DETR 2002). In RS1 it is

assumed that all NGO recycling is waste that has been recycled which the WDA then pays a

recycling credit for.

5.6.7. Beneficial use and diversion from landfill

The beneficial use and diversion from landfill section is a small section of RS1 that calculates

the total amount of waste diverted away from landfill, other than by being recycled or

recovered. This is calculated by adding the total number of tonnes recovered to the amount of

waste put to beneficial use from the AD and EFW facilities. The model uses the assumption

that all materials classified as beneficial use will be sent directly to market with no residue,

thereby meaning there is no calculation, only a sum.

5.7. Stage 3: Relative contributions of facilities and processes to overall outputs

The fundamental purpose of the development of the MBM has been to allow practitioners to

model a set of assumptions against drivers for change; in this case targets set by government.

Stage 2 described the detailed calculations and resultant outputs for each of the facilities

modelled within RS1. Stage 3 collates the outputs from each of the facilities that are the

same, to allow categorisation as recycling, energy recovery or landfill. These categories

reflect the national indicators for performance measurement for WDAs and WCAs.

Page 105: Waste management model

105

Table 5.8 shows the categories that the outputs from stage 2 will be summarised as, the

demonstration of the calculations to achieve the types of output shown is not required as they

are a series of basic additions, but will be used in RS1.

Category of output Type of output units

Recycling

Facility throughput tpa

Total recycling tpa

Total residues to EFW tpa

Diversion of Waste from landfill via recycling %

Energy recovery

Facility throughput tpa

Total energy recovery tpa

Residues to beneficial use tpa

Total Municipal (Contract) recovered %

Landfill

Total Waste going to landfill tpa

Percentage of Waste Landfilled tpa

Total void space required m3

Table 5.8: Output categories found in RS1

An explanation of how each output is calculated follows and the detailed calculations

showing the agglomeration of the outputs can be found in appendix 2:

5.7.1. Use of targets for comparison

In RS1, the targets used are those applicable to ESCC and BHC as described in chapter 2 and

as set by national government (DETR 2000b), they are summarised below:

By 2005 to recycle or compost at least 25% of Household Waste, and to

recover value from 40% of Municipal solid waste

By 2010 to recycle or compost at least 30% of Household Waste and to

recover value from 45% of Municipal solid waste

By 2015 to recycle or compost at least 33% of Household Waste and to

recover value from 67% of Household Waste

The recycling and recovery calculations used are standardised throughout the country by

DEFRA, the process for calculating each of these targets is described in the following

sections:

Page 106: Waste management model

106

5.7.2. Calculation of the recycling and composting rate

The recycling rate for the area is the result of all activities that divert waste through recycling

and composting technologies. There are 7 contributors to the total recycling rate, they are:

Household Waste recycled at the MRF's,

Household Waste recycled at the IVC,

Household Waste recycled at the open composter

Household Waste recycled at the WCA bring banks,

Household Waste recycled at the HWRS Bring banks,

Household Waste recycled by NGOs, and

Recycling undertaken at the RDF plant

The recycling rate is defined as:

Recycling rate = Total household waste recycled (tonnes)

Total amount of household waste arising (tonnes)

In RS1, the result of this equation is compared in the summary sheet to see if the recycling

target for that year has been achieved. This equation is used in RS1 to determine the

predicted recycling rate for the configuration of facilities modelled for a period of 25 years.

5.7.3. Calculation of the recovery rate

The recovery rate is calculated by adding the recycled and composted materials to the mass

of MSW used to generate energy in that year and dividing by either the total household waste

arising or the total municipal solid waste arising, depending on the year. The targets in 5.7

show that the recovery rate should be calculated against municipal solid waste up to 2014,

after that point household waste should be used.

The numerators for recovery rate pre 2014 are:

The seven contributors to total household waste recycled and composted

Any non-household waste recycled or composted

The MSW diversion from landfill (excluding residues) from EFW

The MSW diversion from landfill (excluding residues) from AD

The MSW diversion from landfill (excluding residues) from RDF

Page 107: Waste management model

107

The recovery rate is then defined as:

Recovery Rate Post 2015/16 = Total municipal solid waste recovered (tonnes)

Total amount of municipal solid waste arising (tonnes)

The results for the recovery rate will also be compared to government targets in the summary

sheet. The values generated are then used by the WDA to sculpt a strategy that is based upon

numerous different technologies to divert MSW away from landfill.

5.7.4. Comparator of outputs vs. required outcomes

The model has been designed to allow a user to see at a glance whether the particular set of

inputs to the model (efficiencies, facility throughout and waste growth scenarios) meet the

targets entered. In order to enable this, the model calculates the recycling, composting and

recovery rates and uses the following equation to determine whether the target has been met:

AOT = RRR -PRR

where:

AOT = Achievement of target

RRR = Required recycling rate

PRR = Predicted recycling rate

If the answer to the equation is positive, the model will show ―OK‖ under the column

heading ―are the recycling targets met?‖ for that particular year, if negative, it will show

―NO‖, this function meets one of the fundamental criteria requested in Table 4.1.

5.7.5. Calculation of landfill volume requirements

In stage 2 it was demonstrated that the summation of the residual outputs from all facilities

equated to the total amount of MSW being sent to landfill. The total may have been derived

from five or six different facilities/streams and is not deemed to be homogenous, as

demonstrated in section 5.6.4.3. The calculation in RS1 for the total void space required in a

single year is the addition of the following parameters:

MSW residue from the MRF's,

MSW residue from the IVC,

Page 108: Waste management model

108

MSW residue from the open composter

MSW residue from the RDF plant

MSW residue from the EFW

MSW residue from the AD

The total void required then needs to be compared to the void space left in the area, RS1 will

model the total void available in East Sussex to be 2.7 million m3 (WLP).

5.8. Stage 4: Testing the MBM

As part of the construction process of the MBM a testing regime was undertaken to ensure

that the MBM had been created to deliver accurate results. To achieve this, a set of scenarios

and tests were run through the MBM to ensure the robustness of the parameters of the model.

The MBM was tested over a four month period, in two stages; mathematical correctness and

MBM flexibility.

5.8.1. Mathematical correctness

The first stage of the testing involved undertaking a check that every equation worked; this

was a process that checked every equation in the EXCEL model to ensure accuracy, in

addition, a safety equation was also built into the model to ensure the results of significant

multiple calculations were compared to the original number, thus ensuring that all elements

of the calculations were captured. For example, the individual throughputs and efficiencies

for all facilities, including landfill, should total the MSW projected to be managed in that

year. All the tests were conducted using the 5 waste growth scenarios shown in Figure 5.4

and all showed that the MBM was capable of be flexible for different growth rate scenarios.

A series of tests were also run that compared manually calculated results with the results

from the MBM, accuracy to 4 decimal places was deemed to accurate.

5.8.2. MBM flexibility

The second stage of the testing was to run a set of scenarios that was plausible to the

authorities, to achieve this; eight scenarios with different technical configurations were run

through the MBM. These 8 options were designed to test each of the input categories and

again were compared to manually calculated results. To ensure that results were comparable,

Page 109: Waste management model

109

a single base waste growth scenario was used, this was the same scenario used within the

RS1 option. The MBM was run for 25 years with varying technical solutions in each year; the

results from one year of modelling are shown in Table 5.9.

2015/2016 Scenario 1 Scenario 2 Scenario 3 Scenario 4 Scenario 5 Scenario 6 Scenario 7 Scenario 8

TOTAL WASTE (tpa) 443,270 443,270 443,270 443,270 443,270 443,270 443,270 443,270

LANDFILL (tpa) 79,789 146,279 146,279 88,654 296,991 146,279 79,789 88,654

RECYCLING (tpa) 87,767 87,767 106,385 106,385 87,767 87,767 87,767 106,385

COMPOSTING (tpa) 58,512 58,512 70,923 70,923 58,512 58,512 58,512 70,923

EFW (tpa) 217,202 150,712 119,683 120,033 - - 217,202 -

AD (tpa) - - - 57,275 - - - 177,308

Table 5.9: Summary of results from MBM Scenario 1-8 testing

The results show that the MBM is capable of running a mass balance flow over 8 options and

comparing the results, it should be noted that Table 5.8 does not show the full results from

the MBM, only the relevant information for demonstration of the results. For each of the

scenarios shown in Table 5.8, a mass flow diagram was created; Figure 5.7 shows the

diagram for option 1.

Figure 5.7: Mass Flow diagram for Option 1 (t= tonnes)

Page 110: Waste management model

110

The interrelation between facilities is shown in Figure 5.7; the total tonnage entering the EfW

can be seen to be 53,758 tonnes from CA waste and 163,445 tonnes from the Transfer

Station. The remaining mass flow diagrams for the other seven options are shown in

Appendix 3.

5.9. Stage 5: The MBM results sheet and graphical outputs

The construction of the components and testing of the MBM been demonstrated in stages 1-4,

it is important to show how the model will use the inputs to generate a set of results that are

able influence the local authority decision makers. To do this, stage 5 will show the results of

entering the parameters used in the scenario RS1 into the MBM. The MBM results for RS1

are shown in Tables 5.10, 5.11 and 5.12:

Page 111: Waste management model

111

Total Municipal

Waste

Third party

waste

Validation

Check

Financial

Year

Contract

Year

Are the

Recycling

targets met?

Are the

Recovery

targets

met?

Total Municipal Waste

arisisng per year

(including Third Party

Waste)

Total Household Waste

per year (including Third

Party Waste)

Total Municipal waste

other than Household

Waste (including

Third Party Waste) Total Municipal Waste Total Contract Waste

Contract Household

Waste

Contract Waste

other than

Household Waste Third party waste

Total

Municipal

Waste

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

1 2 3 4 5 6 7 8 9 10 11 12 13

2002/3 1 YES YES 393,271.0 376,112.0 17,159.0 393,271.0 299,157.0 281,998.0 17,159.0 94,114.0 OK

2003/4 2 YES YES 401,136.4 383,634.2 17,502.2 401,136.4 306,640.4 289,138.2 17,502.2 94,496.0 OK

2004/5 3 YES YES 409,159.1 391,306.9 17,852.2 409,159.1 314,273.1 296,420.9 17,852.2 94,886.0 OK

2005/6 4 YES NO 417,342.3 399,133.1 18,209.3 417,342.3 322,058.3 303,849.1 18,209.3 95,284.0 OK

2006/7 5 YES NO 425,689.2 407,115.7 18,573.5 425,689.2 329,999.2 311,425.7 18,573.5 95,690.0 OK

2007/8 6 YES NO 429,946.1 411,186.9 18,759.2 429,946.1 390,299.1 371,539.9 18,759.2 39,647.0 OK

2008/9 7 YES YES 434,245.5 415,298.8 18,946.8 434,245.5 413,140.5 394,193.8 18,946.8 21,105.0 OK

2009/10 8 YES YES 438,588.0 419,451.7 19,136.2 438,588.0 417,271.0 398,134.7 19,136.2 21,317.0 OK

2010/11 9 YES YES 442,973.9 423,646.3 19,327.6 442,973.9 421,443.9 402,116.3 19,327.6 21,530.0 OK

2011/12 10 YES YES 447,403.6 427,882.7 19,520.9 447,403.6 425,658.6 406,137.7 19,520.9 21,745.0 OK

2012/13 11 YES YES 449,640.6 430,022.1 19,618.5 449,640.6 427,786.6 408,168.1 19,618.5 21,854.0 OK

2013/14 12 YES YES 451,888.8 432,172.2 19,716.6 451,888.8 429,925.8 410,209.2 19,716.6 21,963.0 OK

2014/15 13 YES YES 454,148.3 434,333.1 19,815.2 454,148.3 432,075.3 412,260.1 19,815.2 22,073.0 OK

2015/16 14 YES YES 456,419.0 436,504.8 19,914.2 456,419.0 434,236.0 414,321.8 19,914.2 22,183.0 OK

2016/17 15 YES YES 458,701.1 438,687.3 20,013.8 458,701.1 436,407.1 416,393.3 20,013.8 22,294.0 OK

2017/18 16 YES YES 460,994.6 440,880.7 20,113.9 460,994.6 438,588.6 418,474.7 20,113.9 22,406.0 OK

2018/19 17 YES YES 463,299.6 443,085.1 20,214.5 463,299.6 440,781.6 420,567.1 20,214.5 22,518.0 OK

2019/20 18 YES YES 465,616.1 445,300.6 20,315.5 465,616.1 442,986.1 422,670.6 20,315.5 22,630.0 OK

2020/21 19 YES YES 467,944.2 447,527.1 20,417.1 467,944.2 445,201.2 424,784.1 20,417.1 22,743.0 OK

2021/22 20 YES YES 470,283.9 449,764.7 20,519.2 470,283.9 447,426.9 426,907.7 20,519.2 22,857.0 OK

2022/23 21 YES YES 472,635.3 452,013.5 20,621.8 472,635.3 449,664.3 429,042.5 20,621.8 22,971.0 OK

2023/24 22 YES YES 474,998.5 454,273.6 20,724.9 474,998.5 451,912.5 431,187.6 20,724.9 23,086.0 OK

2024/25 23 YES YES 477,373.5 456,545.0 20,828.5 477,373.5 454,171.5 433,343.0 20,828.5 23,202.0 OK

2025/26 24 YES YES 479,760.3 458,827.7 20,932.7 479,760.3 456,442.3 435,509.7 20,932.7 23,318.0 OK

2026/27 25 YES YES 482,159.1 461,121.8 21,037.3 482,159.1 458,725.1 437,687.8 21,037.3 23,434.0 OK

Totals 11,225,618 10,735,828 489,790 11,225,618 10,286,272 9,796,482 489,790 939,346

Does the Solution meet

the Targets?Waste Arising Contract waste

Answer

Total Waste

Type of Year

Year Categories of waste to be used in conjunction with the Contract

Table 5.10: The MBM Result sheet for the RS1 scenario (part 1)

Page 112: Waste management model

112

Total Recycling of

Municipal Waste

Third Party Waste

(inc Recycling)

Total Recovery of

Municipal Waste

Third party

Household Waste Total

Contract Waste put to

Beneficial Use

Contract Waste

other than

Household Waste

put to Beneficial

Use

Validation

Check

Total Municipal Waste

Total contract waste

RecycledContract Household

Waste Recycled

Contract Waste

other than

Household Waste

Recycled

Third Party Waste

(inc Recycling) Total Municipal Waste Contract Household

Waste Recovery

Contract Waste

other than

Household Waste

Recovered

Third party waste

recovered Total

Total Municipal

Waste

Total Municipal

Waste Active waste Inacative waste

Is each

tonne of

MW

catered

for?

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

14 15 16 17 18 19 20 21 22 23a 23 24 25 26 27 28

39,158.480 20,044.480 19,757.691 286.789 19,114.000 39,158.480 19,757.691 286.789 45,364.000 - - - 305,362.520 305,362.520 - YES

79,237.759 59,741.759 56,944.975 2,796.783 19,496.000 79,237.759 56,944.975 2,796.783 45,746.000 - - - 273,148.661 273,148.661 - YES

79,842.594 59,956.594 57,173.159 2,783.435 19,886.000 79,842.594 57,173.159 2,783.435 46,136.000 - - - 280,566.555 280,566.555 - YES

114,059.726 93,775.726 89,105.499 4,670.227 20,284.000 144,059.726 117,409.290 6,366.435 46,534.000 - - - 224,532.606 224,532.606 - YES

114,689.240 93,999.240 89,350.237 4,649.003 20,690.000 144,689.240 117,661.737 6,337.503 46,940.000 - - - 232,249.938 232,249.938 - YES

115,010.233 94,113.233 90,143.177 3,970.055 20,897.000 145,010.233 118,701.269 5,411.964 27,459.500 - - - 272,748.337 272,748.337 - YES

152,356.871 131,251.871 125,670.664 5,581.208 21,105.000 285,856.871 253,048.303 11,703.568 21,105.000 21,000.000 20,036.932 963.068 127,388.659 106,388.659 21,000.000 YES

152,664.390 131,347.390 125,766.170 5,581.220 21,317.000 286,164.390 253,143.796 11,703.594 21,317.000 21,000.000 20,036.930 963.070 131,423.596 110,423.596 21,000.000 YES

152,973.864 131,443.864 125,862.646 5,581.218 21,530.000 286,473.864 253,240.274 11,703.590 21,530.000 21,000.000 20,036.930 963.070 135,500.002 114,500.002 21,000.000 YES

155,853.599 134,108.599 128,527.385 5,581.214 21,745.000 289,353.599 255,905.017 11,703.581 21,745.000 21,000.000 20,036.931 963.069 137,050.005 116,050.005 21,000.000 YES

156,024.642 134,170.642 128,589.424 5,581.218 21,854.000 289,524.642 255,967.053 11,703.589 21,854.000 21,000.000 20,036.930 963.070 139,115.980 118,115.980 21,000.000 YES

156,195.995 134,232.995 128,651.781 5,581.214 21,963.000 289,695.995 256,029.413 11,703.582 21,963.000 21,000.000 20,036.931 963.069 141,192.830 120,192.830 21,000.000 YES

156,368.660 134,295.660 128,714.443 5,581.217 22,073.000 289,868.660 256,092.073 11,703.587 22,073.000 21,000.000 20,036.931 963.069 143,279.610 122,279.610 21,000.000 YES

159,160.667 136,977.667 131,396.455 5,581.212 22,183.000 313,360.667 278,524.780 12,652.887 22,183.000 25,200.000 24,044.318 1,155.682 117,858.344 92,658.344 25,200.000 YES

159,348.055 137,054.055 131,472.842 5,581.213 22,294.000 313,548.055 278,601.165 12,652.890 22,294.000 25,200.000 24,044.317 1,155.683 119,953.051 94,753.051 25,200.000 YES

159,536.826 137,130.826 131,549.606 5,581.220 22,406.000 313,736.826 278,677.920 12,652.905 22,406.000 25,200.000 24,044.316 1,155.684 122,057.786 96,857.786 25,200.000 YES

159,725.980 137,207.980 131,626.760 5,581.219 22,518.000 313,925.980 278,755.075 12,652.904 22,518.000 25,200.000 24,044.316 1,155.684 124,173.605 98,973.605 25,200.000 YES

159,915.520 137,285.520 131,704.308 5,581.212 22,630.000 314,115.520 278,832.632 12,652.887 22,630.000 25,200.000 24,044.318 1,155.682 126,300.563 101,100.563 25,200.000 YES

160,106.447 137,363.447 131,782.237 5,581.210 22,743.000 314,306.447 278,910.564 12,652.883 22,743.000 25,200.000 24,044.318 1,155.682 128,437.716 103,237.716 25,200.000 YES

160,298.764 137,441.764 131,860.551 5,581.214 22,857.000 314,498.764 278,988.873 12,652.891 22,857.000 25,200.000 24,044.317 1,155.683 130,585.119 105,385.119 25,200.000 YES

160,491.473 137,520.473 131,939.263 5,581.210 22,971.000 314,691.473 279,067.590 12,652.883 22,971.000 25,200.000 24,044.318 1,155.682 132,743.830 107,543.830 25,200.000 YES

160,685.576 137,599.576 132,018.364 5,581.212 23,086.000 314,885.576 279,146.688 12,652.887 23,086.000 25,200.000 24,044.318 1,155.682 134,912.904 109,712.904 25,200.000 YES

160,881.073 137,679.073 132,097.855 5,581.219 23,202.000 315,081.073 279,226.170 12,652.903 23,202.000 25,200.000 24,044.316 1,155.684 137,092.399 111,892.399 25,200.000 YES

161,076.969 137,758.969 132,177.750 5,581.219 23,318.000 315,276.969 279,306.066 12,652.903 23,318.000 25,200.000 24,044.316 1,155.684 139,283.371 114,083.371 25,200.000 YES

161,273.264 137,839.264 132,258.052 5,581.212 23,434.000 315,473.264 279,386.377 12,652.887 23,434.000 25,200.000 24,044.318 1,155.682 141,485.877 116,285.877 25,200.000 YES

3,546,936.665 3,001,340.665 2,876,141.291 125,199.375 545,596.000 6,421,836.665 5,618,497.953 257,742.713 683,408.500 449,400.000 428,790.321 20,609.679 4,098,443.863 3,649,043.863 449,400.000

LandfillRecycling Recovery Beneficial Use

Contract waste Contract waste Total amount of Municipal Waste going to Landfill

Table 5.11: The MBM Result sheet for the RS1 scenario (part 2)

Page 113: Waste management model

113

Total Capacity of all

facilities including Bring

Banks

Total tonnage not

treated by any of the

facilities

Number of tonnes of

Household Waste

Recycled

Percentage of

the Total

Household

Waste

Recycled

Contract

targets for

Recycling

Total

Household

Waste

Total

Household

Waste

Number of tonnes

of Municipal Waste

Recovered

Perecntage

of the total

Municipal

Waste

Recovered

Contract

targets for

Recycling

Total Municipal

Waste

Total Municipal

Waste

(tonnes) (Percentage) (Percentage) (tonnes) (Percentage) (tonnes) (Percentage) (Percentage) (tonnes) (tonnes)

29 30 31 32 33 34 35 36 37 38

39,158.480 10.4% - 0.0% 39,158.480 10.0% 95,044.480 298,226.520

79,237.759 20.7% 20% - 0.0% 79,237.759 19.8% 140,741.759 260,394.661

79,842.594 20.4% 20% - 0.0% 79,842.594 19.5% 140,956.594 268,202.555

114,059.726 28.6% 25% 30,000 7.2% 144,059.726 34.5% 40% 237,175.726 180,166.606

114,689.240 28.2% 25% 30,000 7.0% 144,689.240 34.0% 40% 237,399.240 188,289.938

115,010.233 28.0% 25% 30,000 7.0% 145,010.233 33.7% 40% 181,263.233 248,682.837

152,356.871 36.7% 30% 133,500 30.7% 285,856.871 65.8% 45% 356,551.871 92,993.659

152,664.390 36.4% 30% 133,500 30.4% 286,164.390 65.2% 45% 356,647.390 97,240.596

152,973.864 36.1% 30% 133,500 30.1% 286,473.864 64.7% 45% 356,743.864 101,530.002

155,853.599 36.4% 30% 133,500 29.8% 289,353.599 64.7% 45% 359,408.599 103,295.005

156,024.642 36.3% 30% 133,500 29.7% 289,524.642 64.4% 45% 359,470.642 105,469.980

156,195.995 36.1% 30% 133,500 29.5% 289,695.995 64.1% 45% 359,532.995 107,655.830

156,368.660 36.0% 30% 133,500 29.4% 289,868.660 63.8% 45% 359,595.660 109,852.610

159,160.667 36.5% 33% 154,200 33.8% 313,360.667 71.8% 67% 392,277.667 79,441.344

159,348.055 36.3% 33% 154,200 33.6% 313,548.055 71.5% 67% 392,354.055 81,647.051

159,536.826 36.2% 33% 154,200 33.4% 313,736.826 71.2% 67% 392,430.826 83,863.786

159,725.980 36.0% 33% 154,200 33.3% 313,925.980 70.9% 67% 392,507.980 86,091.605

159,915.520 35.9% 33% 154,200 33.1% 314,115.520 70.5% 67% 392,585.520 88,330.563

160,106.447 35.8% 33% 154,200 33.0% 314,306.447 70.2% 67% 392,663.447 90,580.716

160,298.764 35.6% 33% 154,200 32.8% 314,498.764 69.9% 67% 392,741.764 92,842.119

160,491.473 35.5% 33% 154,200 32.6% 314,691.473 69.6% 67% 392,820.473 95,114.830

160,685.576 35.4% 33% 154,200 32.5% 314,885.576 69.3% 67% 392,899.576 97,398.904

160,881.073 35.2% 33% 154,200 32.3% 315,081.073 69.0% 67% 392,979.073 99,694.399

161,076.969 35.1% 33% 154,200 32.1% 315,276.969 68.7% 67% 393,058.969 102,001.371

161,273.264 35.0% 33% 154,200 32.0% 315,473.264 68.4% 67% 393,139.264 104,319.877

3,546,936.665 2,874,900 6,421,836.665 8,252,990.665 3,263,327.363

Meeting the Targets in the ContractCapacitiesRecycling

Household Waste, Recycling Total RecoveryEnergy Recovery (EFW)

Energy Recovery Recovery

Table 5.12: The MBM Result sheet for the RS1 scenario (part 3)

Page 114: Waste management model

114

5.9.1. Discussion of the results from Scenario RS1

The results presented in the preceding tables demonstrate the significant level of detail

produced by the MBM to plot the mass flow through a given scenario. The three tables would

be seen as one worksheet in MS EXCEL and are divided into two sections, tonnes per

recycling, recovery and landfill, with total MSW arising and a quick check column to see if

the targets have been met. The second section is for determining what the targets are and

what the actual performance is, the latter section shown in Table 5.12.

Table 5.10 shows the first stage of the MBM results, indicating whether the targets set by the

user have been achieved by the configuration of facilities inputted by the user. In the case of

RS1, the recycling targets are met in every year, but three of the recovery targets are missed.

The latter is due to the delay in the energy from waste facility being built, the implications of

this delay will be explored in chapter six. Table 5.10 also shows that RS1 MSW to be

managed each rose by nearly 83,000 tonnes per annum from 393,271 tonnes in 2002/3 to

482,159 tonnes in 2027/28; this is an average increase per annum of 0.07%. As stated in

section 5.7.1, a validation check was built into the MBM; this can be seen in both Table 5.10

and 5.11, the cell answer changes depending on the validation required. In Table 5.10, the

question is ―is every tonne of waste accounted for?‖ in every row the answer is yes, meaning

the check is doing its job.

Due to the many columns and rows in the results sections, it is difficult to determine easily

what the MBM has shown; therefore the MBM also produces two graphs that depict the

tabular results, these can be seen in Figures 5.8 and 5.9. The first Figure shows the results of

Table 5.11 by depicting the recycling and recovery rates achieved by the solution entered into

the MBM, in this case RS1. It can be seen that for both recycling and recovery, the RS1

solution meets and exceeds the contract targets set.

Figure 5.8 shows the sum of all modelled waste through the cumulative total of the facilities

proposed, for RS1, it can be seen that by 2008/9 over 350,000 tonnes per annum of MSW

would be treated through the facilities, in 2014/15, this would rise to 392,277 tonnes per

annum, with the introduction of the Anaerobic Digestion facility.

Page 115: Waste management model

115

Figure 5.8: MBM Results for RS1: Total recycling and recovery rate per annum

0.0%

10.0%

20.0%

30.0%

40.0%

50.0%

60.0%

70.0%

80.0%

20

02

/3

20

03

/4

20

04

/5

20

05

/6

20

06

/7

20

07

/8

20

08

/9

20

09

/10

20

10

/11

20

11

/12

20

12

/13

20

13

/14

20

14

/15

20

15

/16

20

16

/17

20

17

/18

20

18

/19

20

19

/20

20

20

/21

20

21

/22

20

22

/23

20

23

/24

20

24

/25

20

25

/26

20

26

/27

per

cen

tage

of

toat

l was

te a

rsiin

g p

er a

nn

um

Percentage of the Total Household Waste Recycled

Contract targets for Recycling

Percentage of the total Municipal Waste Recovered

Contract targets for Recovery

Page 116: Waste management model

116

Figure 5.9: MBM Results for RS1: The total waste treated annually through all facilities

0

50,000

100,000

150,000

200,000

250,000

300,000

350,000

400,000

450,000

20

02

/3

20

03

/4

20

04

/5

20

05

/6

20

06

/7

20

07

/8

20

08

/9

20

09

/10

20

10

/11

20

11

/12

20

12

/13

20

13

/14

20

14

/15

20

15

/16

20

16

/17

20

17

/18

20

18

/19

20

19

/20

20

20

/21

20

21

/22

20

22

/23

20

23

/24

20

24

/25

20

25

/26

20

26

/27

Ton

nes

per

an

nu

m

Total Capacity of all facilities including Bring Banks

Total tonnage not treated by any of the facilities

Page 117: Waste management model

The results and the graphs shown by the Tables 5.10 -12 and Figures 5.8 & 5.9 give a

detailed breakdown of all the results from RS1, it is necessary to look at each section of the

results and the flow of materials through each processing type in detail. To do this an

analysis of the proposals by Veolia South Downs (VSD) will be undertaken. The Contract

was signed with a clause that VSD would be responsible for meeting the targets and having

sufficient capacity for between 300,000 tpa and 550,000 tpa of MSW arising, the lowest and

highest perceived affordable tonnages. VSD was contracted to build a mixture of facilities as

well as a network of transfer stations and local recycling facilities as shown in Table 5.13,

the operational dates and capacities are all subject to planning being granted.

Facility Location Capacity TPA Operational dates

Materials Recycling Facility

(MRF) Hollingdean, Brighton 100,000 Sep-05

Waste Transfer Stn. West Hollingdean, Brighton 100,000 Sep-05

Composting Plant Golden Cross, Hailsham 45,000 Apr-06

Waste Transfer Stn. North Maresfield Camp, Uckfield 40,000 Apr-06

Energy from Waste North Quay, Newhaven 225,000 Oct-09

Waste Transfer Stn. East Pebsham 75,000 Apr-12

(Anaerobic Digestion) Pebsham 75-150,000 Apr-12

New HWRS Crowbrough, Uckfield and

Pebsham N/A

Between Feb 04 and June

2012

Table 5.13: The facilities procured through the PFI contract and using RS1

The performance and efficiency levels of these facilities have been designed to enable the

contractor to achieve the recycling and recovery targets set out in the contract. With regard to

the recovery target, the fixed size of the plant would mean a greater proportion of total waste

would be recovered early on in the contract period and thus the recovery rate would reduce as

waste increases.

5.9.1.1. Recycling

By building a MRF capable of processing up to 100,000 tpa of commingled dry recyclable

materials, sufficient capacity has been secured to enable a large proportion of the waste

stream to be separated and bulked up for transport to end markets. Once the recyclable

materials that have been collected at the three waste transfer stations (located in the West,

East and North of the Councils‘ area) have been bulked up and transferred to end markets or

Page 118: Waste management model

118

composted, are combined with the recyclable materials separated and bulked up at the MRF,

a recycling rate in excess of the 33% target should be achieved by 2015/16.

5.9.1.2. Recovery

VSD propose to build an Energy from Waste plant (EfW) with a capacity of 225,000 tpa.

This will divert 145,000 tpa from landfill by a process of energy recovery generating 17 MW

of electricity for export to the grid. VSD also propose to put to beneficial use (for re-use as

aggregate) 60,000 tpa of bash ash. In total the EfW will divert from landfill approximately

205,000 tonnes of waste per annum.

5.9.1.3. Description of operational characteristics of EfW

The EfW will comprise a single stream design for 28 tonnes per hour (tph) or 225,000 tonnes

per annum (tpa), generating 20MW of electricity (17 MW of which will be exported). The

plant will operate 24 hours per day; 7 days a week, all year round except for planned periods

of closure for maintenance purposes. The design will aim to enable generation of the

maximum amount of electricity under the full load operating conditions. The combination of

the recovery achieved at the EfW and recycling will mean that over 60% of the waste stream

will be diverted by 2010/11, this is shown by Figure 5.10, which indicates how the contractor

will perform in relation to the targets set by the councils.

Figure 5.10: RS1 Recovery targets for VSD solution

0%

10%

20%

30%

40%

50%

60%

70%

80%

2002/3

20

03/4

2004/5

2005/6

2006/7

2007/8

2008/9

20

09/1

0

20

10/1

1

20

11/1

2

20

12/1

3

20

13/1

4

20

14/1

5

20

15/1

6

20

16/1

7

20

17/1

8

20

18/1

9

20

19/2

0

20

20/2

1

20

21/2

2

20

22/2

3

20

23/2

4

20

24/2

5

20

25/2

6

20

26/2

7

Rec

over

y r

ate

contract year

Contract targets

Onyx Aurora targets

Page 119: Waste management model

119

Analysis of Figure 5.10 shows that, during the years between 2010/11 and 2015/16,

depending on the date of commissioning of the EfW, the recovery rate could be between 20%

and 23% above the minimum rates stated in the contract.

This will enable the Councils to achieve maximum diversion of waste from landfill at an

early stage of the contract and reduce to a minimum the requirement to export waste to

landfill outside the Councils‘ area.

5.9.2. Landfill

The VSD solution results in MSW, treated or untreated, ultimately ending up in landfill,

using the principles in section 5.5, the landfill void required each year was calculated in RS1

and then aggregated to give the total landfill void required in the contract period,

demonstrated in Table 5.11, which shows in detail the number of tonnes required to be

deposited in landfill each year. This range is from 385,302 tonnes in 2008/9 to 141,485

tonnes in 2026/27. The total cumulative landfill void required over the contract period would

be just under 4.1million m3, this can be used to determine the lifetime of existing landfill

void. This 4.1 million m3 was plotted against the estimated ESCC and BHC total landfill void

available. Figure 5.11 shows that landfill void is exhausted in mid 2010/11.

Figure 5.11: Landfill void space required for RS1

-3

-2

-1

-

1

2

3

Bas

e yea

r

20

02

/3

20

03

/4

20

04

/5

20

05

/6

20

06

/7

20

07

/8

20

08

/9

20

09

/10

20

10

/11

20

11

/12

20

12

/13

20

13

/14

20

14

/15

20

15

/16

20

16

/17

20

17

/18

20

18

/19

20

19

/20

20

20

/21

20

21

/22

20

22

/23

20

23

/24

20

24

/25

20

25

/26

La

nd

fill

m3

(mil

lio

ns)

SURPLUS/SHORTFALL …

Page 120: Waste management model

120

The lack of landfill void space after 2011 is the responsibility of VSD and they will have to

provide a solution to the problem, the assumption has been made that local landfill outside of

the councils area will be used.

5.10. Summary

The process, assumptions and key equations used in the building of that model have been

explored. The construction and testing of the model and it uses for comparison against targets

was investigated and its ultimate usage in a real situation was shown. It has been shown that

the MBM was used for ―real‖ through RS1 and that the outputs from the model were

significant factors in the agreement to a solution that enabled the councils of East Sussex and

Brighton & Hove to alleviate the pressure of national targets and real capacity issues.

The next chapter will look at how the MBM needed to be modified and developed to take

account of pieces of legislation which were uncertain at the time of signing the PFI Contract;

the Landfill Allowance Trading Scheme (LATS). It will also consider the implications this

will have on a national and local perspective.

Page 121: Waste management model

121

6. THE DEVELOPMENT, TESTING AND ANALYSIS OF RESULTS OF THE

LATS MASS BALANCE MODEL (LMBM).

Chapter four reviewed the waste management life cycle tools and models available to local

authorities prior to 2004; it demonstrated that there wasn‘t a model that met all the needs of

local authority officers. Chapter five continued by describing the process of building a new

Mass Balance Model (MBM) and its subsequent testing with five scenarios for. This included

presenting the complex and diverse factors and calculations used to construct the MBM. The

chapter concluded by demonstrating the use of the MBM to determine the solution for a 25

year waste disposal contract, contracted by the ESCC and BHC to Veolia South Downs,

worth £1billion.

This chapter describes how new legislation; the Landfill Allowances Trading Scheme

(LATS), impacts on the MBM. The subsequent further development required to produce a

new model is explained and a new model, the LATS Mass Balance Model – LMBM is

presented. There is a description of new concepts to be incorporated into the model, the

process testing of the model, and a presentation and analysis of the results from three

scenarios; showing the financial impacts as a result of the new legislation over a 15 year

period. This chapter will only focus on the impact of LATS on East Sussex County Council,

as unlike the recycling and recovery targets, which can be shared, the LATS responsibilities

are for an individual WDA.

6.1. New Legislation

Chapter 2 described the legislation that pressured local government in England to move from

landfill to a technical solution for disposing of waste. Included in that chapter was the EU

Landfill Directive (99/31/EC) that had been published in 1999 and subsequently transposed

into UK law as The Landfill (England and Wales) Regulations 2002 (DETR). The objective

of the Directive was "to prevent or reduce as far as possible negative effects on the

environment, in particular the pollution of surface water, groundwater, soil and air, and on the

global environment, including the greenhouse effect, as well as any resulting risk to human

health, from the landfilling of waste, during the whole life-cycle of the landfill" (EU Landfill

Directive (99/31/EC)).

Page 122: Waste management model

122

In England, between 2003 and 2005, DEFRA introduced legislation designed to transpose

responsibility to individual waste disposal authorities for meeting the Landfill Directive

targets. The primary legislation was The Waste and Emissions Trading (WET) Act 2003, this

was followed by two secondary pieces of legislation; The Landfill Allowances and Trading

Scheme (England) Regulations 2004 and The Landfill Allowances and Trading Scheme

(England)(Amendment) Regulations 2005. An explanation of the WET act and secondary

legislation follows:

6.1.1. The Waste and Emissions Trading (WET) Act

When the WET Act received Royal Assent on 13 November 2003, it provided the framework

for the Landfill Allowance Trading Scheme (LATS), designed to implement Article 5(2) of

the Landfill Directive and to apportion the UK landfill targets to each country of the UK.

However, it didn‘t apportion individual targets to authorities in England, but it did provide for

a Trading Scheme to be put in place in order to enable the targets to be met in the most cost-

effective way. This was set out in The Landfill Allowances and Trading Scheme (England)

Regulations 2004 and finalised in the Landfill Allowances and Trading Scheme (England)

(Amendment) Regulations 2005.

The WET act has two significant differences to the original EU Landfill Directive for the

UK; it defines the base year as 2000/01 rather than the 1995 Eurostat data. This is because

changes in local authority structure and not enough accurate data meant that there was not a

consistent dataset pre 2000. The target years are also different as the government took the

opportunity to use the derogation on the targets allowed under the EU Landfill Directive.

This allowed the UK to move the date for meeting the targets back by four years as the UK

sent more than 80% of its MSW to landfill in 1995/6 (DEFRA 2005).

Table 2.6 shows the challenging targets for the UK to reduce the amount of biodegradable

municipal solid waste sent to landfill. The targets are expressed as percentages, but, this is

misleading, because in waste management nearly all statistics are calculated in tonnes per

annum (tpa). To reflect this, the DETR set the targets for the amount of Biodegradable

Municipal Waste (BMW) allowed to be landfilled in The Landfill (England and Wales)

Regulations 2002 as definitive numbers. The UK targets were subdivided between the four

Page 123: Waste management model

123

countries, England, Northern Ireland, Scotland, and Wales, this chapter will only refer to the

English targets.

In the base year of 2001/02, 23.7million tonnes per annum (Mtpa) of MSW were generated

by households (DEFRA 2003); the maximum amount of BMW allowed to be taken to landfill

by English WDAs in target years is shown in Table 6.1:

EU Target Year Maximum BMW to landfill (tpa)

2009/10 11,200,000

2012/13 7,460,000

2019/20 5,220,000

Table 6.1: The English Landfill Directive targets (DEFRA 2003)

The targets have been as static numbers, this means that the impact of waste growth is not a

consideration. The impact of the targets on MSW management is shown in Figure 6.1, which

shows the results of a waste growth scenario with a 3% per annum increase in waste, based

on government Figures (DETR 2000). The figure illustrates that the amount of BMW that

needs to be diverted from landfill to hit the targets is increasing.

Figure 6.1: BMW needed to be diverted to meet LATS targets in England at 2% per annum

waste growth

0.0

5.0

10.0

15.0

20.0

25.0

30.0

20

01

/2

20

05

/6

20

06

/7

20

07

/8

20

08

/9

20

09

/10

20

10

/11

20

11

/12

20

12

/13

20

13

/14

20

14

/15

20

15

/16

20

16

/17

20

17

/18

20

18

/19

20

19

/20

Mtp

a

Finacial year

LATS allowances

BMW arising 3% growth

BMW to be diverted

Page 124: Waste management model

124

Interpretation of the Figure 6.1 shows that for 2009/10 there is a requirement to divert

6.93Mtpa from landfill to hit the target, and by 2019/20, this has risen to 19.8 mtpa. As a

country England therefore needs to have sufficient infrastructure to treat nearly 20mtpa of

MSW per annum by 2019/10.

Figure 6.2 shows the same information, but using uses a lower waste growth factor of 2% per

annum; the Figure shows the amount of BMW to be diverted for the 3% and 2% waste

growth scenarios.

Figure 6.2: A comparison of BMW required to be diverted from landfill to meet LATS

targets for a 2% and 3% waste growth scenario

The decrease in MSW as a result of assuming a 2% growth rate corresponds to a reduction of

BMW needed to be diverted in 2019/20 of 3.3mtpa. This simple analysis shows that a 1%

decrease in waste growth per annum leads to a 17% decrease in required capacity by

2019/2020. The impact of waste growth can therefore not be underestimated, as a making an

incorrect assumption in 2005/6 could lead to a very different requirement in 2019/20.

6.1.2. The Landfill Allowances and Trading Scheme (England) Regulations 2004

The Landfill Allowances and Trading Scheme (England) Regulations 2004 was announced

by the Secretary of State on 21 July 2004 and came into force the following day. They

15.0

16.0

17.0

18.0

19.0

20.0

21.0

22.0

23.0

24.0

25.0

20

01

/2

20

05

/6

20

06

/7

20

07

/8

20

08

/9

20

09

/10

20

10

/11

20

11

/12

20

12

/13

20

13

/14

20

14

/15

20

15

/16

20

16

/17

20

17

/18

20

18

/19

20

19

/20

Mtp

a

Finacial year

BMW arising 3% growth

BMW arising 2% growth

Page 125: Waste management model

125

provide the detail for the operation of the Landfill Allowances Trading Scheme (LATS) in

England. This includes rules on the banking, borrowing and transfer of allowances;

responsibilities on waste disposal authorities, including allowances per WDA and landfill

operators for the retention and submission of certain information; a system of penalties;

provisions relating to the monitoring of LATS and the maintenance of registers.

6.1.3. Landfill Allowances and Trading Scheme (England) (Amendment) Regulations 2005

The Landfill Allowances and Trading Scheme (England) (Amendment) Regulations 2005

reduced the financial penalty for a waste disposal authority that fails in a scheme year to

comply with its duty not to landfill more BMW than the landfill allowances available to it.

That financial penalty is reduced from £200 per tonne to £150 per tonne.

6.2. The LATS targets

Between the launch of the WET act in 2003 and the publication of the final allowances on 3rd

February 2005, a letter from the Secretary of State indicated that there were no specific

targets for WDAs. In that time period the most appropriate method to allocate LATS

allowances and thus targets to individual authorities was deliberated. The author developed a

sub-model as part of this work to indicate how the targets shown in Table 6.1 could be

allocated to all English WDAs, based on the proportion of MSW they were responsible for in

England. The questionnaire used to gather data in shown Appendix 6. To allow WDAs to

understand the potential targets the results of the model were published nationally as an

official Local Government Association document in late 2004. DEFRA then published its

own official set of targets in 2005 following consultation these had only very minor

differences to those of the author. The DEFRA targets are used in this chapter.

LATS was not just about setting targets for diverting biodegradable municipal waste away

from landfill, it was also novel in that it enabled councils to use two different methods to hit

the targets; trading of allowances and construction of facilities. The aim of the LATS was to

enable local authorities to meet the reductions required by the EC Landfill Directive in the

most cost effective way. A system of transferable allowances was introduced to allow the

greatest amount of waste diversion or reduction to occur in areas where, consistent with a

Page 126: Waste management model

126

high level of environmental protection, recycling, composting, incineration and waste

minimisation are cheapest and most practicable.

The LATS operates in a number of phases separated by target years. During these phases

permits can be sold, banked or borrowed but deficits and surpluses cannot be carried forward

across target years. A summary of the rules is shown in Table 6.2.

Period Financial Year Can LATS be Banked? Can LATS be Borrowed?

Phase

1

LATS Banking and Borrowing Rules

2005/6 Yes 5%

2006/7 Yes 5%

2007/8 Yes 5%

2008/9 No No

Target Year 2009/10 No No

Phase

1

Phase

2 2010/11 Yes 5%

2011/12 No No

Target Year 2012/13 No No

Phase

2

Phase

3

2013/14 Yes 5%

2014/15 Yes 5%

2015/16 Yes 5%

2016/17 Yes 5%

2017/18 Yes 5%

2018/19 No No

Target Year 2019/20 No No

Phase

3

Table 6.2: The rules for Banking and Borrowing LATS (adapted from DEFRA LATS

Guidance on Trading, Banking and Borrowing)

After accounting for any banking or borrowing, any authority which needs to landfill more

biodegradable waste than they have allowances for, can either buy from another council, or,

if there are no allowances available, pay a fixed fine of £150 per tonne to DEFRA.

The research shown in Appendix 3 highlighted that by 2009/10 England as a whole would be

very close to being in deficit, whilst individual WDAs would be between 120,000 tonnes in

deficit and 1.3million tonnes in surplus. The reason for this range was that the targets were

allocated against 2000/01 MSW Figures, and any change in facilities post that date was not

included. For example, an authority that landfilled 85% of its MSW in 2001/02 and then had

an EfW become operational in 2002/3, meaning MSW to landfill dropped to 50% would have

a huge surplus in allowances.

Page 127: Waste management model

127

If, as the research suggested, England would be close to being in deficit, it is expected that

the cost of purchasing permits would rise sharply to match higher demand in allowances. To

monitor and ensure that the scheme is transparent, Waste Disposal Authorities are required to

provide the Environment Agency with a quarterly return which separates waste sent to

landfill from waste diverted through recycling and recovery. From this, the Environment

Agency will then calculate the number of tonnes of biodegradable waste sent to landfill and

compare it to the authorities‘ allocation of allowances.

6.3. Introduction of new concepts to the MBM

The uncertainty of LATS at the time of constructing the MBM meant that the detailed targets

for councils for landfill diversion were not included, but the high level EU Landfill Directive

Targets were. The requirement under LATS is to determine whether the council has sufficient

allowances to landfill the waste it manages or whether it has to embark on a trading strategy

to ensure compliance with LATS targets. There are two main concepts that result from the

LATS regulations; to trade LATS or to construct facilities. The next section will explore the

concepts and their incorporation in a new model which is a development of the MBM from

Chapter 5; The LATS Mass Balance Model (LMBM).

6.3.1. Concept 1: To build sufficient facilities to meet the LATS targets

To achieve the targets under LATS, councils have the option to model the impact of waste

growth, waste composition and recycling and recovery performance to estimate the amount

of waste that will be left to manage; ostensibly this is what the MBM does. The MBM then

gives the user the opportunity to model the size of facility required to meet recovery targets.

With the introduction of LATS, councils are faced with having to meet targets of 33%

recycling and 67% recovery by 2015/16 (DEFRA 2000) and then ensure that they have

diverted enough BMW to meet the targets. The legislation was designed to ensure that the

two were interconnected and this will be tested by the LMBM. One factor that will affect the

delivery of these facilities is the planning process since there is evidence that shows that the

major energy from waste facilities have experienced construction delays of 1 – 2 years as a

result of the planning process (I. Blake, 2001). This factor will be explored as part of the

testing and modelling in section 6.6.

Page 128: Waste management model

128

6.3.2. Concept 2: Trading LATS to meet the targets

The unique concept of LATS is that authorities can utilise the banking, borrowing, buying

and selling capabilities of the regulations to construct a strategy that allows them take account

of their infrastructure programme. There are many variables that contribute to the

development of this strategy and they will be considered separately to the concept of building

facilities. The complexity of the trading principles is not considered in this thesis as that is a

different model and would require lengthy explanation. The remainder of this chapter will

therefore define the LMBM and the concept of meeting the LATS targets by building

infrastructure.

6.4. Adding new concepts to the MBM, constructing and testing the LMBM

The MBM required significant changes not only to ensure that it took into account the new

dimensions of LATS, but also to produce outputs that are directly useable to those who do

not understand the inner complexities of the legislation. The MBM was re-profiled from one

all-encompassing model to one that was separated into distinct segments that allowed users

greater transparency and flexibility. The LATS-MBM (LMBM) contains the following

segments:

o Data Input

o Calculation, and

o Results

In addition to the new segments, the following criteria were introduced as part of the LMBM:

The model allowed for the calculation of the biodegradable content of the waste

stream and subsequent impact of that BMW passing through different facilities

The base year for the model was changed from 1995/6 to 2001/02 and the most

accurate data available at the time was added (2003/4)

The results indicate whether there was a surplus or deficit in the allowances,

measured against BMW landfilled.

The results were presented in a graphical format to display the surplus or deficit of

LATS

Page 129: Waste management model

129

6.5. Assumptions used with the testing of the LMBM

The key assumptions required to undertake the modelling of the future costs of waste and

LATS are changes in the amount of waste arising, the composition of the waste stream i.e.

the element that is biodegradable, the timing of the completion of waste treatment facilities

and estimates of recycling and recovery.

6.5.1. Waste growth

RS1 used five different waste growth scenarios. The testing of the new LMBM used the

same five scenarios (low, medium/low, base, medium and high), but only two will be

presented in this chapter; base and high. This is because the low, medium/low and medium

/high growth scenarios are comparable to the base scenario. The LMBM will only use East

Sussex County Council as the study area as LATS targets are more applicable to one

authority than a partnership of authorities as discussed in chapter 5.

6.5.2. Composition of the waste stream

The amount of BMW present in the waste is assumed to be 68% (DEFRA 2005), but research

by Network Recycling in the East Sussex WCAs shows that there is a considerable amount of

―untapped‖ BMW in the residual bins, significantly kitchen waste. The results indicate that

58% of the kerbside residual waste stream is made up of LATS countable material. The

results, when combined with the recycling and composting Figures, indicate that 73% of the

material collected by WCAs is considered BMW. This is 5% higher than DEFRA percentage,

but for the council its impact is that the higher figure equates to higher tonnages of BMW and

there more BMW to target for diversion making achievement of the target possibly easier.

For consistency, the LMBM will use a BMW Figure of 68%.

6.5.3. Completion of key facilities

The facilities presented in Table 5.8 have been updated following the signing of the PFI

contract, as some of the operational dates have slipped. The data in Table 6.3 shows the dates

used for the base case LMBM for planning, construction and operation of the key facilities,

as well as the operational capacity for each facility.

Page 130: Waste management model

130

Facility Final capacity

(tpa)

Planning

application

Constructio

n start Operational

Material Recovery Facility

Hollingdean, Brighton 80,000 Jul-04 May-05

Late Apr-

06

Composting Facility

Whitesmith (Near Uckfield) 45,000 Mar-04 Late Jan-05 Apr-06

Energy Recovery Facility

North Quay, Newhaven 225,000 Jul-04 Oct-06 Sep-09

New Technology Pebsham Up to 150,000 May-08 May-10 Apr-12

Table 6.3: Base case capacity and construction timelines

6.5.4. Recycling and recovery performance

The recycling performance was calculated assuming the current service level, plus any agreed

improvements with the district and borough councils, for which the resources required have

already been identified and included in existing budgets. Without new investment it is

anticipated that WCA recycling will be about 27% in 2005/6, and 29% in 2006/7. The overall

recycling rate for the County without further investment is therefore assumed to be 27% in

2005/6 and approximately 29% thereafter.

6.6. Descriptions of scenarios tested through the LMBM

A series of tests are required to prove that the new LMBM works as predicted and can be

adjusted to introduce the new concepts described in section 6.4. Due to the uncertain nature

of sale and purchase of LATS, it is prudent to assume that if an authority does not have

sufficient allowances in any given year they may have to pay anything up to the price of the

fine; £150 per tonne. Equally, if an authority has surplus allowances and wishes to sell them

it is hard to quantify how much they will be worth, so a prudent income price of £10 per

tonne will be assumed. The scenario testing will assume that trading, through buying banking

or borrowing is not undertaken. These assumptions form the base case and will be referred to

as Scenario 1A and will demonstrate the worst case scenario for buying LATS allowances

against the dates set out in Table 6.3. Scenario 1A will then be rerun with the price and

income parameters being changed to base case with £100 fines and £25 sales (scenario 1B)

and base case with £50 fines and £50 sales (scenario 1C). These scenarios will test the price

sensitivity of LATS, with a view to understanding the implications on the council‘s budget.

Page 131: Waste management model

131

Having tested that the LMBM works correctly on one scenario with three price and income

parameters, it is necessary to analyse one of the concepts introduced to the model, delay of

the construction of new facilities. Two further scenarios will therefore be run through the

model to understand the impact delay of one major facility on meeting the LATS targets. The

assumptions will be exactly the same as scenario 1, with the only variable being the EfW

completion date, which will be delayed by 1 year and then 2 years, from the base year. The

matrix in Table 6.4 shows the nine scenarios that will be modelled:

Table 6.4: The scenarios tested to demonstrate the impact of LATS price assumption and

facility delay

6.7. Scenario 1

Scenario 1 uses all the assumptions from RS1 to demonstrate the implications of purchasing

or selling LATS allowances to meet the targets set for ESCC as a WDA. The scenario is

designed to indicate how LATS will impact the newly signed PFI contract on the East Sussex

County Council budget. LATS was not part of the budgeted amount when the contract was

signed; therefore the extent of the extra burden to the council needs to be understood.

6.7.1. Scenario 1A: Base Case with £150 fines and £10 sales

The first scenario modelled through LMBM uses all the assumptions described in section 6.5

of this chapter. Figure 6.3 shows the results of the LMBM and indicates whether the council

would have a deficit of surplus of LATS allowances for every year of the scheme. The graph

shows that the council will have a deficit for the first five years of the scheme and a

decreasing surplus over the last nine years of the scheme, with the final year being in deficit.

The jump in 2009/10 is due to the EFW being constructed, tested and finally made

operational, thereby combusting waste over a 9 month period that continues into the financial

year 2010/11.

Sale of

£10

Purchase

of £150

Sale of

£25

Purchase

of £100

Sale of

£50

Purchase

of £50

no delay

1 year delay

2 year delay

Scenario 2A Scenario 2B Scenario 2C

Scenario 3A Scenario 3B Scenario 3C

LATS Value LATS Value LATS Value

Scenario 1A Scenario 1B Scenario 1C

Page 132: Waste management model

132

Figure 6.3: Summary of Scenario 1 modelling for LATS

The LATS surplus reduces over time because the EFW has a static capacity and therefore,

any positive waste growth over time will mean that more waste will end up in landfill. Table

6.5 shows the surplus or deficit of LATS allowances and the subsequent fines and income the

Council would attract under scenario 1A.

Financial

Year

Surplus deficit of

allowances (tpa)

Cost of allowances per

annum

Cumulative cost of

allowances

2005/6 17,984- 2,697,554-£ 2,697,554-£

2006/7 21,405- 3,210,798-£ 5,908,351-£

2007/8 27,477- 4,121,549-£ 10,029,900-£

2008/9 31,124- 4,668,666-£ 14,698,566-£

2009/10 2,293- 343,946-£ 15,042,512-£

2010/11 36,607 366,070£ 14,676,442-£

2011/12 32,812 328,116£ 14,348,326-£

2012/13 20,632 206,318£ 14,142,008-£

2013/14 16,889 168,888£ 13,973,120-£

2014/15 13,141 131,408£ 13,841,712-£

2015/16 11,562 115,624£ 13,726,088-£

2016/17 7,810 78,103£ 13,647,984-£

2017/18 4,053 40,534£ 13,607,451-£

2018/19 291 2,914£ 13,604,537-£

2019/20 3,476- 521,346-£ 14,125,883-£

Table 6.5: Scenario 1A cost analysis results: fines £150 per tonne and sales at £10 per tonne

The data shows that failure to have sufficient LATS permits in the first five years of the

scheme at a cost of £150 per tonne would mean that ESCC would need to pay a cumulative

-40,000

-30,000

-20,000

-10,000

0

10,000

20,000

30,000

40,000

20

05

/6

20

06

/7

20

07

/8

20

08

/9

20

09

/10

20

10

/11

20

11

/12

20

12

/13

20

13

/14

20

14

/15

20

15

/16

20

16

/17

20

17

/18

20

18

/19

20

19

/20

Ton

nes

per

an

nu

m

Year

Page 133: Waste management model

133

cost of over £15 million. As the county moves from deficit to surplus an income is generated

which peaks at nearly £370,000 in 2010/11. The surplus continues, but at a declining rate

until 2018/19, and the income generated counters the deficit to a certain level. However, it

still results in a net deficit income of over £14million for the period of the scheme.

6.7.2. Scenario 1B Base case with £100 fines and £25 sales

Scenario 2B uses the same assumptions as scenario 1A, but with the income modelled at £25

per tonne for the sale of LATS and the cost of buying LATS set at £100 per tonne. Table 6.6

shows the results from the LMBM.

Financial

Year

Surplus deficit of

allowances

Cost of allowances per

annum

cumulative cost of

allowances

2005/6 17,984- 1,798,369-£ 1,798,369-£

2006/7 21,405- 2,140,532-£ 3,938,901-£

2007/8 27,477- 2,747,699-£ 6,686,600-£

2008/9 31,124- 3,112,444-£ 9,799,044-£

2009/10 2,293- 229,297-£ 10,028,341-£

2010/11 36,607 915,175£ 9,113,167-£

2011/12 32,812 820,291£ 8,292,876-£

2012/13 20,632 515,795£ 7,777,081-£

2013/14 16,889 422,219£ 7,354,861-£

2014/15 13,141 328,521£ 7,026,340-£

2015/16 11,562 289,059£ 6,737,281-£

2016/17 7,810 195,259£ 6,542,022-£

2017/18 4,053 101,334£ 6,440,689-£

2018/19 291 7,284£ 6,433,404-£

2019/20 3,476- 347,564-£ 6,780,969-£

Table 6.6: Scenario 1B cost analysis results: fines £100 per tonne and sales at £25 per tonne

The pattern of income and payment stays the same as in scenario 1A, but the cumulative

income increases by from just under £1.5million to over £3.5million. The cost of buying

LATS allowances does drop significantly over the lifetime of the scheme compared to

scenario 1A. The cumulative net cost to the council in this scenario is nearly £7 million, 50%

less than the scenario 1A.

Page 134: Waste management model

134

6.7.3. Scenario 1C Base Case with £50 fines and £50 sales

The third scenario uses the same assumptions as both scenario 1A and 1B, but models the

sale and purchase price of at £50. The result of running the assumptions through the LMBM

is demonstrated in Table 6.7:

Financial

Year

Surplus deficit of

allowances (tpa)

Cost of allowances per

annum

cumulative cost of

allowances

2005/6 17,984- 899,185-£ 899,185-£

2006/7 21,405- 1,070,266-£ 1,969,450-£

2007/8 27,477- 1,373,850-£ 3,343,300-£

2008/9 31,124- 1,556,222-£ 4,899,522-£

2009/10 2,293- 114,649-£ 5,014,171-£

2010/11 36,607 1,830,349£ 3,183,822-£

2011/12 32,812 1,640,582£ 1,543,240-£

2012/13 20,632 1,031,591£ 511,649-£

2013/14 16,889 844,438£ 332,789£

2014/15 13,141 657,042£ 989,831£

2015/16 11,562 578,118£ 1,567,950£

2016/17 7,810 390,517£ 1,958,467£

2017/18 4,053 202,668£ 2,161,135£

2018/19 291 14,568£ 2,175,703£

2019/20 3,476- 173,782-£ 2,001,921£

Table 6.7: Scenario 1C cost analysis results: fines £50 per tonne and sales at £50 per tonne

Scenario 1C has the same pattern of surplus and deficit, but a net cumulative surplus of just

over £2 million would be received by the council in this scenario, a change of £9 million

compared to scenario 1B and £16 million compared to scenario 1A.

The three scenarios show the impact that LATS can have in changes in price per tonne on

purchasing and trading. This is from a cumulative deficit of nearly £15 million in scenario 1A

to an cumulative income of £2 million in 1C. The extremes of individual years are also

demonstrated, income of £1.83 million in scenario 1C and a net payment of £4.67million in

scenario 1A.

Page 135: Waste management model

135

6.8. Scenario 2

The modelling in scenarios 1A, B and C has shown what will happen if the facilities are

delivered on time according to the base case PFI scenario. Petts states that the ―siting decision

process for new plant is being substantially lengthened as local communities object to

proposals and force more open discussion of the risks and benefits‖ (Petts 1992). Most

construction processes will allow for delay, but a prudent assumption of 1 year delay is

necessary to understand the financial implications of LATS. The concept of delay is not

unheard of therefore scenario 2 will explore the implications of a 1 year construction delay to

the 225,000 tpa EfW facility. As shown by Table 6.4, three scenarios will be looked at in

scenario 2, each exploring the impact of the same price assumptions shown in Scenario 1.

6.8.1. Scenario 2A: one year delay of the EFW with £150 fines and £10 sales

The results of running the parameters set out in Table 6.4, through the LMBM, for scenario

2A are shown in Figure 6.4.

Figure 6.4: Scenario 2A LATS deficit or surplus in ESCC if the EFW is delayed by 1 year

Comparison of the graphs in Figure 6.3 and 6.4 demonstrates that a one year delay will have

the effect of significantly increasing the deficit of allowances in 2009/10 and turning 2010/11

from a surplus to a deficit year. At this stage it would appear prudent to concentrate on the

-50,000

-40,000

-30,000

-20,000

-10,000

0

10,000

20,000

30,000

40,000

20

05

/6

20

06

/7

20

07

/8

20

08

/9

20

09

/10

20

10

/11

20

11

/12

20

12

/13

20

13

/14

20

14

/15

20

15

/16

20

16

/17

20

17

/18

20

18

/19

20

19

/20

Ton

nes

per

an

nu

m

Year

Page 136: Waste management model

136

years that are affected by the delay; however, to understand the impact on the whole scheme,

modelling has been undertaken on price sensitivity over the 15 year. Modelling of three price

scenarios for a one year delay is undertaken in scenario 2A.

Financial

Year

Surplus/deficit of

allowances

Cost of allowances

per annum

Cumulative cost

of allowances

2005/6 17,984- 2,697,554-£ 2,697,554-£

2006/7 21,405- 3,210,798-£ 5,908,351-£

2007/8 27,477- 4,121,549-£ 10,029,900-£

2008/9 31,124- 4,668,666-£ 14,698,566-£

2009/10 39,372- 5,905,752-£ 20,604,318-£

2010/11 15,351- 2,302,609-£ 22,906,927-£

2011/12 32,812 328,116£ 22,578,810-£

2012/13 20,632 206,318£ 22,372,492-£

2013/14 16,889 168,888£ 22,203,605-£

2014/15 13,141 131,408£ 22,072,196-£

2015/16 11,562 115,624£ 21,956,572-£

2016/17 7,810 78,103£ 21,878,469-£

2017/18 4,053 40,534£ 21,837,935-£

2018/19 291 2,914£ 21,835,022-£

2019/20 3,476- 521,346-£ 22,356,368-£

Table 6.8: Scenario 2A cost analysis results: fines £150 per tonne and sales at £10 per tonne

The results from the LMBM are shown in Table 6.8; the construction delay means that the

first six years of the scheme are in deficit, an increase of one year compared to scenario 1A.

Interpretation of Tables 6.5 and 6.8 shows the impact of a one year delay under scenario 2A

is disproportionate to the delay, under scenario 1A. In Scenario 1A, the average cost for

failure to meet the targets was under £1 million per annum, suggesting that a delay of one

year would move the financial deficit from £14 million to £15 million.

The result of that one year as modelled by the LMBM is that there is a cumulative deficit of

nearly £23million to the councils; this is an increase of nearly £9million from scenario 1.

The reason for this disproportionate increase is found in the detail of the results, there are

only two years affected by the one year delay, 2009/10 and 2010/11. In scenario 1A for the

year 2009/10, there was a minor deficit of 2,293 tonnes, in scenario 2A this changed to a

deficit of 39,372 tonnes. In scenario 1A for 2010/11 there was a surplus of 36,607 tonnes,

compared to a deficit of 15,351 tonnes in scenario 2A, this results in a change from a

cumulative surplus of 34,314 tonnes in scenario 1A to a cumulative deficit of 54,723 tonnes,

a change of 89,037 tonnes. The cost of buying nearly 90,000 allowances at £150 per tonne

indicates why the price is so much higher in Scenario 2A.

Page 137: Waste management model

137

6.8.2. Scenario 2B: one year delay of the EFW with £100 fines and £25 sales

The impact of the one year delay has been demonstrated to be financially disproportionate

under scenario 2A. Scenario 2B uses a £100 purchase price if there is a deficit in allowances

and a £25 sale price if there is a surplus; Figure 6.9 shows the results from the LMBM.

Financial

Year

Surplus/deficit of

allowances (tpa)

Cost of allowances

per annum

Cumulative cost of

allowances

2005/6 17,984- 1,798,369-£ 1,798,369-£

2006/7 21,405- 2,140,532-£ 3,938,901-£

2007/8 27,477- 2,747,699-£ 6,686,600-£

2008/9 31,124- 3,112,444-£ 9,799,044-£

2009/10 39,372- 3,937,168-£ 13,736,212-£

2010/11 15,351- 1,535,072-£ 15,271,284-£

2011/12 32,812 820,291£ 14,450,994-£

2012/13 20,632 515,795£ 13,935,198-£

2013/14 16,889 422,219£ 13,512,979-£

2014/15 13,141 328,521£ 13,184,458-£

2015/16 11,562 289,059£ 12,895,399-£

2016/17 7,810 195,259£ 12,700,140-£

2017/18 4,053 101,334£ 12,598,806-£

2018/19 291 7,284£ 12,591,522-£

2019/20 3,476- 347,564-£ 12,939,086-£

Table 6.9: Scenario 2B cost analysis results: fines £100 per tonne and sales at £25 per tonne

In this scenario, the price assumptions are more conservative and therefore the impact

reduces, from a cumulative cost of over £22 million in scenario 2A to nearly £13million.

This is still double the impact under scenario 1B and shows that a one year delay can be a

very real financial problem.

6.8.3. Scenario 2c: one year delay of the EFW with £50 fines and £50 sales

The analysis of buying and selling LATS at £50 a tonne through the LMBM gives a

conservative financial position, which is summarised in Table 6.10:

Page 138: Waste management model

138

Financial

Year

Surplus/deficit of

allowances

Cost of allowances per

annum

Cumulative cost of

allowances

£ 50 £ 50

2005/6 17,984- 899,185-£ 899,185-£

2006/7 21,405- 1,070,266-£ 1,969,450-£

2007/8 27,477- 1,373,850-£ 3,343,300-£

2008/9 31,124- 1,556,222-£ 4,899,522-£

2009/10 39,372- 1,968,584-£ 6,868,106-£

2010/11 15,351- 767,536-£ 7,635,642-£

2011/12 32,812 1,640,582£ 5,995,061-£

2012/13 20,632 1,031,591£ 4,963,470-£

2013/14 16,889 844,438£ 4,119,031-£

2014/15 13,141 657,042£ 3,461,989-£

2015/16 11,562 578,118£ 2,883,871-£

2016/17 7,810 390,517£ 2,493,353-£

2017/18 4,053 202,668£ 2,290,686-£

2018/19 291 14,568£ 2,276,118-£

2019/20 3,476- 173,782-£ 2,449,900-£

Table 6.10: Scenario 2C cost analysis results: fines £50 per tonne and sales at £50 per tonne

In scenarios 2A, 2B and 2C, the council does not show a cumulative income from the sale or

purchase of LATS in any of the 15 years. Although these changes only occur in 2 of the

scheme years, the delay in planning has a knock-on impact for subsequent years. This is

because for those two years the council has a surplus of allowances of 40,038 in scenario 1,

whilst scenario 2 has a net deficit of allowances of 48,998 over the 15 years.

6.9. Scenario 3

It has been indicated that major waste treatment facilities are subject to long delays at the

planning stage (Petts 1992, Qviström 2007), section 6.8 shows that a net deficit in allowances

over a period of time results in a net cost to councils. Therefore scenario 3 will focus on the

cumulative number of allowances over the 15 year trading period, rather than the cost of

buying and selling.

6.9.1. A Planning delay of two years

The surplus/deficit of allowances for the case of a two year planning delay are shown in

Figure 6.5 and show the net allowances against the net BMW to landfill taken from the data

modelled in the LMBM with the 2 year delay. There is a distinct pattern to Figure 5.6, a

continuous deficit of allowances compared to BMW landfilled. There is a small anomaly, a

Page 139: Waste management model

139

decrease in the deficit post 2010/11 as a result of the delayed EFW becoming operational and

reversing the deficit trend.

Figure 6.5: Comparison of BMW to landfill and LATS allowances if the EFW is delayed by

2 years

The cumulative deficit in 2019/20 for the total period is 136,174 tonnes, compared to +

40,038tonnes in scenario 1 and -48,998 for scenario 2. Figure 6.6 shows the results of the

calculations for scenarios 3A, 3B and 3C. The results demonstrate the impact of changing the

purchase price in any given year. For example, in 2010/11, the cost to the council as a result

of the three scenarios‘ would be between £7.8 million and £2.3 million, a budgeting

difference of £5.5 million. This difference is nearly 30% of the annual cost of the PFI

contract (£18 million per annum) and is not a sustainable amount for prudent financial

management. The extreme of the two year delay is shown by comparing the results of

scenario 3A with scenario 2A; there is again significant increase in deficit, as expected, with

the cumulative financial deficit increasing by over £8 million to £30.8 million.

-

200

400

600

800

1,000

1,200

1,400 2

00

5/6

20

06

/7

20

07

/8

20

08

/9

20

09

/10

20

10

/11

20

11

/12

20

12

/13

20

13

/14

20

14

/15

20

15

/16

20

16

/17

20

17

/18

20

18

/19

20

19

/20

ton

nes

per

an

nu

m (

Th

ou

san

ds)

CumulativeLATS allowances

Cumulative BMW to landfill

Page 140: Waste management model

140

Figure 6.6: Sensitivity analysis results of scenario 3 cost of LATS if the EFW is delayed by 2

years

6.10. Analysis of the three scenarios

The three scenarios have demonstrated that the financial impact on ESCC is immense if a

major facility is delayed. This is demonstrated in Figure 6.7, whereby the impact of delay can

seen over the period 2008/9 – 2012/13.

If there is a surplus of allowances over the fifteen year period, there will be an income for the

council. This ignores the impact of year to year buying and selling and how this affects cash

flow for the Councils, e.g. in scenario 3A the councils would have to spend £7.9million in

2010/11 to have sufficient LATS to meet the target whilst they would receive £1.83million in

2009/10 under scenario 1C.

The annual cost for ESCC of the PFI contract scenario, using the LMBM scenario, is

£15million on average over the first ten years. The scenarios show that the councils would

need to budget for anywhere up to 52% of its annual budget to buy and sell LATS; this is a

risk that has many implications, which could include reducing services in other parts of the

council.

-£9.0

-£8.0

-£7.0

-£6.0

-£5.0

-£4.0

-£3.0

-£2.0

-£1.0

£0.0

£1.0

£2.0

20

05

/6

20

06

/7

20

07

/8

20

08

/9

20

09

/10

20

10

/11

20

11

/12

20

12

/13

20

13

/14

20

14

/15

20

15

/16

20

16

/17

20

17

/18

20

18

/19

20

19

/20

Mil

lion

s

Scenario 3A buying at £150 per tonne

and selling at £10 per tonne

Scenario 3B buying at £100 per tonne

and selling at £25 per tonne

Scenario 3C buying at £50 per tonne and

selling at £50 per tonne

Page 141: Waste management model

141

Figure 6.7: The fine or income attributable each year as a result of scenario 1A, 2A and 3A

6.11. Conclusion

This chapter demonstrates how new legislation has been incorporated into the MBM - to form

the LMBM. An analysis of the results of three scenarios has been undertaken, focussing on

the budget impact on East Sussex County Council. The results of these scenarios are useful to

the councils in demonstrating the potential impact the LATS targets has on their budget, but

all fail to make use of all of the aspects of the trading potential of LATS. The true result of

these scenarios will not be understood until at least 2015/16, when the second EU target year

is approached, in the interim, ESCC has the opportunity to use the banking and borrowing

system. Whilst this is not described in this thesis, there is much scope for avoiding some of

the huge fines that could be levelled by DEFRA.

-£9

-£8

-£7

-£6

-£5

-£4

-£3

-£2

-£1

£-

£1

20

05

/6

20

06

/7

20

07

/8

20

08

/9

20

09

/10

20

10

/11

20

11

/12

20

12

/13

20

13

/14

20

14

/15

20

15

/16

20

16

/17

20

17

/18

20

18

/19

20

19

/20

Fin

e

(

Mil

lion

s)

Inco

me

Year

Scenario 1A

Scenario 2A

Scenario 3A

Page 142: Waste management model

142

7. SUMMARY AND DISCUSSION

The beginning of the 21st century saw a dynamism unseen in municipal solid wastes

management previously, a plethora of targets, new technologies and a changing public

attitude put pressure on the continuation of the ―truck and dump‖ regime that had endured for

the 20th

Century. There was a requirement for a new solution, with local authorities having

the facilitation role. The need for local government to change their own systems meant new

contracts and facilities that could meet the new demands. Intrinsic within the planning for the

future was a requirement to plan the right technology and fundamentally the right size that

would endure over the perceived 25 year life time of new facilities.

The aim of the thesis was to ―enable local authority officers to plan for the future

management of wastes for which they have responsibility‖. It has been demonstrated, that

there was insufficient clear and easy to use prediction tools for the local authority officers to

use that enabled modelling of future requirement; indeed, many passed the obligation to

consultants and future contractors. The Mass Balance Model (MBM) was therefore

developed to be used for this purpose; it drew upon the needs of both the local authority

officer and academics by using a combination of easy to use but complex calculations,

structured to demonstrate the size of facilities and ability to achieve required targets. The

MBM was developed as a quantitative tool for procuring an integrated waste management

contract through the mechanism of a Private Finance Initiative (PFI) and was rigorously

tested by the author. Indeed the MBM was considered robust enough to be used by Brighton

& Hove City Council and East Sussex County Council as the predictive model for the

procurement of their joint £1billion twenty five year contract with Veolia South Downs

signed in 2003.

Subsequent legislative changes not in place at time of contract signature required a new

model; the LATS MBM (LMBM) was developed as a second phase, incorporating the new

Landfill Allowance Trading Scheme (LATS). Research was undertaken in 2005 through a

national questionnaire to ascertain the impact of LATS and the ability for councils to trade. A

further refinement was made to the LMBM; a trading strategy, to allow councils to enter a

trading market for LATS with sufficient intelligence to ensure financial stability, this was not

described in this thesis, but the results indicated that the councils would not need to budget

for such large fines.

Page 143: Waste management model

143

7.1. Objectives

In concluding the research and development undertaken to inform this thesis, it is cognisant

to review the objectives of this thesis set out in chapter one and consider the learning

achieved through focussing on said objectives.

7.1.1. Objective 1: Identify the roles and responsibilities of wastes management and impacts

thereof

Responsibility for wastes management in ESCC and BHC has been demonstrated to be split

between local authorities and the private sector. The focus of the research being the wastes

managed by local authorities; Municipal Solid Waste (MSW). Local government waste

management can be categorised by three levels of responsibility; waste collection, waste

disposal and unitary authorities. The former two are arranged as ―two tier‖ government, a

county council (WDA) will have a number of district or boroughs within its area (WCA). In

many cases the tension between authorities is significant in these areas; the collection

authorities want to have their own sovereign solution, whilst the WDA wants to control the

waste as much as it can. The subsequent dialogue can sometimes lead to an ineffective

solution for collection and disposal, meaning a higher cost to the tax payer. The Unitary

council has responsibility for both collection and disposal and can therefore have to synergise

the two services. However, some authorities will be of insufficient size to develop their own

disposal solutions and will need to work with other authorities, thereby creating a possible

tension through partnership working.

During the course of research and authoring, the way MSW is managed has changed. The

cost of managing waste has increased to pay for the new facilities and services; however,

Banks and Venture Capitalists are entering the waste sector (DEFRA 2007), with the

European Investment Bank budgeting to spend €75 billion in 2009/10 compared to €55

billion in 2008/09 on wastes management (EIB 2008). This is a major shift from the 20th

century when investment in facilities was poor (Peacock 1999).

An interpretation of the 2007/8 statistics is shown in Figure 7.1; it indicates that councils in

England managed 29,144,185 tonnes of MSW. The Figure shows the subdivision of waste

and the management practices employed by local authorities in England through collection,

treatment and disposal of MSW.

Page 144: Waste management model

Figure 7.1 Mass flow of 2007/8 English MSW arisings (tonnes per annum) (Greenfield 2009)

Page 145: Waste management model

The management by local authorities of nearly 30 million tonnes of waste is shown to be

complicated and can go through many applications. However, Figure 7.1 shows that just over

half of the waste generated in England in 2007/8 went to landfill. This is significantly less

than in 2000/01, when 82% of MSW was sent to landfill.

A seismic shift in the way waste is managed has occurred. By 2009, recycling rates in

England in certain authorities were over 50% and indeed in ESCC were nearing 30%, a

significant change in 9 years. Between the turn of the century and 2009 collection methods

matured and councils introduced a plethora of collection systems that can be characterised in

three main systems; kerbside sort, single stream co-mingled with separation at a Material

Recycling Facility (MRF) and two stream co-mingling (WRAP 2009). An overview of each

of the three predominant methods and their components is shown in Table 7.1.

Interpretation of Table 7.1 shows that the most commonly used type of collection

methodology is kerbside sort (44%) followed by single stream Co-mingled (35%) and two-

stream co-mingled (37%).

Type of

collection

Recycling Container and Refuse

Frequency

Total

Number

% of English

LA’s

Kerbside Sort

Sack and/or box, fortnightly refuse 59 17

Sack and/or box, weekly refuse 95 27

Total Kerbside Sort 154 44

Single stream

Co-mingled

Wheeled Bin, fortnightly refuse 59 17

Wheeled Bin, weekly refuse 24 7

Sack and/or box, fortnightly refuse 7 2

Sack and/or box, weekly refuse 31 9

Total Single Stream Co-mingled 121 35

Two Stream

Co-mingled

Sack and/or box, fortnightly refuse 17 5

Sack and/or box, weekly refuse 20 6

Total Two Stream Co-mingled 37 11

No Recycling

scheme No recycling scheme 32 10

Table 7.1: Analysis of Kerbside collection types by number and percentage of English Local

Authorities (Adapted from WRAP 2009)

Page 146: Waste management model

146

7.1.2. Objective 2: Explore the drivers for change for local authorities

The immense pressure on local authorities for change has been demonstrated by the plethora

of legislation from Europe and the UK over the last decade; this has been shown to be the

catalyst for change and has led to the exploration of various new technologies for the

management of waste. Public interest and perception of the environment has also been shown

to have increased and the need to recycle has been ever increasing, indeed. Twenty years ago,

the tip was exactly that, nowadays it is somewhere to exploit your green credentials by

recycling and buying from the scrap store. Huge pressure has been applied by the NGOs with

the public now regarding waste as a problematic service. Planning for facilities has become a

full time job, demonstrated by the million plus comments made against the ESCC & B&HCC

Waste Local Plan. Waste has always used acronyms, but the public perception agenda has led

to ―Not In My Back Yard‖ (NIMBY), ―Not In My Term of Office‖ (NIMTO) and ―Build

Absolutely Nothing Anywhere Near Anybody‖ (BANANA), all are symptomatic of the

approach both the public and politicians sometimes have to waste facilities.

In 2009, a pressure that was identified in section 1.1; the definition of MSW, has been

reinvigorated, with debate between the Department for Environment, Food and Rural Affairs

(DEFRA) and Local Authorities (LAs) (Letsrecycle 2009). DEFRA is reacting to this by

clarifying the definition of MSW by consulting on the definitions in 2010 with a view to

publishing guidance in 2010/1.

The existing definition of MSW can be interpreted differently, for example if a local

authority collects waste from a school; it would be defined as MSW under the LATS

guidance, but would not be MSW under the WET act definition. DEFRA further clarified this

guidance in 2007 by stating that ―Collected municipal solid waste‖ is waste which ―comes

into the possession or under the control of (a) a waste disposal authority, or (b) a waste

collection authority within the area of the disposal authority, whether or not the waste is in

possession or under the control of that authority under or by virtue of the Environmental

Protection Act 1990‖ (DEFRA 2007).

The drivers for change are stated above but exclude a common cause of change; lack of

facilities or landfill void, the latter being the common factor; albeit for the southern

Page 147: Waste management model

147

authorities of England. To address this latter factor, much emphasis has been placed on

minimising waste; this is demonstrated by national and regional campaigns.

In 2008 the Association of Cities and Regions for Recycling and sustainable Resource

management (ACR+) launched a 100 kg challenge for all European countries. They identified

4 categories of waste that deserved most attention for waste prevention (ACR+); Organic,

Paper, packaging and bulky wastes. The detail of the intervention measures to be

implemented by those authorities signing up to the voluntary agreement is shown by Table

7.2.

From the initiative put forward by ACR+ and many other promotional campaigns including;

the ―Love food Hate waste‖, ―Recycle Now‖ and the ―Home composting‖ campaigns

promoted by the Waste Resources Action Programme (WRAP), it is evident that waste

minimisation is being taken far more seriously. However, it is also clear that campaigns may

only reduce waste arising by 16% of the targeted material and 10% of the average 1 tonne of

waste produced by English households annually (DEFRA 2006).

Table 7.2 Table of actions and potential for waste minimisation (ACR +)

Actions for the 4 flowsAmount

(kg/inhab./year)

Potential waste

reduction

(kg/inhab./year)*

1 Organic waste : 220 40

• Promote composting at source(at home, local, in

green spaces…) 180 30

• Fight against food waste 30 8

• Promote reusable nappies 10 2

2 Paper waste : 100 15

• Fight against unwanted flyers or newspapers 20 5

• Encourage dematerialisation (schools and offices) 80 10

3 Packaging : 150 25

• Choose products whose packaging can be returned

to place of purchase 35 12

• Promote tap water 6 2

• Develop reusable bags 2 1

• Fight against over-packaging 107 10

4 Bulky or other waste : 130 20

• Promote reuse of clothes 8 4

• Promote reuse of furniture, EEE, toys, other bulky

waste 110 13

• Fight against excess buying 12 3

Total 600 100

* Sources : Internal working groups 2006– ACR+ 600 100

Page 148: Waste management model

148

In 2008, the UK was hit by the longest recession since records began, the impact on waste

companies was highlighted by the 2009 Veolia half yearly report that claimed that waste

management divisions had been ―characterised by a decline in the volumes of mainly

industrial and hazardous waste processed‖ and also falls in the prices of recycled materials,

most noticeably paper and metals. Veolia said this had a ―significant impact‖ on the operating

performance of the division (Veolia 2009).The recession has had a different impact on

business, where the challenging economic climate appears to be creating a new mindset,

where sustainability goes hand-in-hand with profitability and where waste equals higher costs

(Envirowise 2009). Whilst many authorities have looked to increase recycling, to minimise

landfill tax costs, increased recycling can of itself have an impact on the cost of the service,

for example, to cope with more recycling streams and hence potential increases in service

costs.

7.1.2.1. The changing composition of MSW

In order to develop a well-integrated and cost-effective system for managing MSW, planners

must evaluate how well each potential piece of the system meshes with other existing or

proposed system components. The fit of a particular component can be measured in terms of

its purpose, size, location, ownership, operation, system of financing, and relationship to

administrative and regulatory agencies. Specifically, individual components of the system

should be: (a) chosen so they do not overlap or compete excessively; (b) sized so they can

handle the portion of the waste stream they were designed for, without competing with other

components; (c) located so that transportation costs between management facilities are

minimized and appropriate transportation networks are used; (d) owned, operated, and

financed to minimize overall public costs, while ensuring responsible management and

cooperation with other system components; and (e) administered by appropriate agencies,

with adequate public oversight (UNEP 1999). The PFI programme undertaken by the two

councils achieved all of these factors; however one factor that is not included by the UNEP is

the impact of MSW composition. Figure 1.6 shows a historical waste analysis of the way

composition of the waste generated by households has changed over the 20th century; it is up

to the planner of a 25 year PFI programme to be able to adapt to the changing composition of

this MSW.

Page 149: Waste management model

149

It has been predicted that the major change in composition will be due to the production,

consumption and inclusion in waste streams of more and more complex products.

Personalized medicine, new computers and gadgets, networked homes and full home

management systems, fully customized consumer products, personal security and personal

energy products are coming or are already here (Mavropoulos 2008). The impact on the

composition of the MSW collected from the households will change accordingly, waste is

getting more valuable.

The use of nano-materials will impact the composition of waste over the next quarter of a

century; indeed, nano-bio and e-technologies will create a whole spectrum of new artificial

materials. Major breakthroughs within the next two decades will provide inexpensive ways to

produce mass quantities of those materials. In addition, the function of such materials will

move from ‗passive‘ to ‗active‘ with the integration of nanoscale valves, switches, pumps,

motors and other components (Mavropoulos 2008). The impact will be that greater quantities

of these materials will be discarded, will the facilities procured be able to adapt to these

changes. The problem for waste planners is timing; new goods are launched, purchased and

presented as new kinds of waste before a waste management solution has been created. The

catch up time for waste management processing is slow compared to the creation of new

products; it is this point alone that requires producer responsibility. It is imperative that

producers liaise with waste managers to ensure that waste from products can be managed and

waste managers have adequate funding to react to changing composition.

7.1.2.2. The Pre budget reports

The impact of the recession on local authorities has seen government spend cut targets, with

the 2009 pre budget report stating that councils must save £550 million in 2010/11, some of

which must come from waste management activities.

Since the PFI contract was signed, the landfill tax has emerged as the main economic policy

for diverting MSW from landfill, indeed the 2008 report stated that as announced in Budget

2007, from 1 April 2008 and until at least 2010/11, the standard rate of landfill tax will

increase by £8 per tonne each year. Importantly, the report confirmed that the government

expects the standard rate to continue to increase beyond 2010/11. The current financial

Page 150: Waste management model

150

situation means that waste minimisation is necessary, as even a miniscule reduction in

tonnage collected will reduce costs.

7.1.3. Objective 3: Describe the available technologies for management of wastes

The main technologies feasible for the systematic shift away from reliance on landfill are

described in chapter three. These included proven technologies such as mass burn

incineration, windrow composting and recycling. Innovative technologies were suggested to

have a place due the public perception issues with incineration, these included pyrolysis,

gasification and anaerobic digestion. It was concluded that no single technology could be

employed to deliver significant diversion from landfill with maximum beneficial use of waste

materials; rather a mix of technologies, targeting specific waste items should be used.

Between the PFI contract being signed and 2009, there has been a move towards more

localised and less capital intensive waste management facilities whilst also considering the

carbon burden of MSW management (Mühle et al 2009). In England, there has been a move

towards Mechanical Biological Treatment (MBT), as alternative to EfW to appease public

opinion. MBT is a residual waste treatment process that involves both mechanical and

biological treatment processes, it can be configured in many ways and the common

applications are:

The ‗M‘ refers to sorting, separation, size reduction and sieving technologies in

varying configurations to achieve mechanical separation waste fractions into

potentially useful products and /or streams for biological processing.

The ‗B‘ refers to aerobic or anaerobic biological process which converts the BMW

into a compost like output (CLO) and, in the case of AD, biogas.

The T‘ relates to the fact that process elements can integrated to create an MBT

process.

The application of MBT has been designed to compliments other waste management

technologies such as recycling and composting as part of an integrated waste management

system. A process description is shown in Figure 7.2:

Page 151: Waste management model

151

Figure 7.2: An illustration of the potential Mechanical Biological Treatment options (DEFRA

2007)

The move towards MBT has also been prompted by the need for sustainable energy

generation. The case for using MSW for energy generation is good; the following factors

highlight the demand:

A 10% reduction in fossil fuel demand ~20.5mT oil equivalent

Currently energy from biodegradable municipal waste 0.5mT oil equivalent

Potential 7mT oil equivalent from waste

~2mT oil equivalent from BMW

~3.5mT oil equivalent from C&I bio

+ 1-1.5mT oil equivalent from non bio?

Security of supply (imports currently at 149mT oil equivalent)

Table 7.3: The size of the waste to energy opportunity (Derived from Defra waste data flow

statistics and DUKES aggregate energy balance)

The opportunity to generate energy from 7 million tonnes oil equivalent is identified in Table

7.3; this will come from both EfW and biogas or CLO generated through MBT. The WDAs

Page 152: Waste management model

152

in England have the following facilities in the pipeline of construction which indicates that

huge investment is being made:

Figure 7.3: The EfW and MBT construction pipeline (IESE 2009)

The 52 plants have a combined 14.2 million tonnes total treatment capacity planned by 2015,

with 4.6 mtpa for MBT solutions and >1.5mT for no technology preference despite MBT

reference.

Given all of the financial and technical pressures, councils in England have coped well with

the conflicting demands of waste minimisation, diversion of waste from landfill, and

increased collection of recyclates. The average cost of the refuse collection service per

household has shown a steady increase from £40.01 in 2002-03 to £69.02 in 2008-09.

However, this investment in the service has shown a corresponding increase in the percentage

of total domestic waste collected which is sent for recycling from 11.15% in 2002-03 to

37.13% in 2008-09 – more than triple that of 6 years ago (DEFRA 2009).

7.1.4. The ESCC & BHC PFI facilities

All of the sites and facilities identified in Table 5.8, have been completed or are in

construction. The last remaining facility to be completed will be the Energy Recovery

Facility which was started at the end of April 2008. The site selected for development is

situated at North Quay, Newhaven, between the River Ouse and the railway line and will

have the capacity to handle 210,000 tonnes of waste a year. The artist‘s impression of the

Page 153: Waste management model

153

new facility is shown in Figure 7.4, it took three years to obtain planning permission, a

contributing factor to the delay:

Figure 7.4: Artists impression of the new energy recovery facility at Newhaven (Veolia

2009).

7.1.5. Objective 4: Use the drivers and responsibilities to create a mass balance model

(MBM) and describe the process of building the MBM and testing it

Extensive research was undertaken between 1999 and 2002 on the models available for mass

flow prediction, coupled with an in depth survey of a number of senior officers. It was

concluded that there were models available but that all were too specialised for the needs of

the local authority officers. The construction of a new spreadsheet Mass Balance Model

(MBM) was described in chapter four, with the emphasis being placed on usability and

understanding of results. The MBM allowed users to find the optimum mix of technologies

for a defined target, incorporating the ability to manipulate the efficiencies of the

technologies, the waste growth scenario, the targets set and the type of waste managed. The

MBM was used by two councils (East Sussex County Council and Brighton & Hove City

Council) for the procurement of their £1biilion integrated waste management contract in

2003.

Page 154: Waste management model

154

7.1.6. Objective 5: Describe the impact of new legislation on the results of the MBM and the

requirement for a revised model to take account of new drivers.

New legislation was introduced in 2004 that meant a revision to the MBM was required. The

Landfill Allowances Trading scheme required waste disposal authorities to collectively meet

European targets imposed nationally for the diversion of Biodegradable Municipal waste

(BMW) in 2009/10, 2012/13 and 2019/20. The government solution was to have a 15 year

trading programme allowing councils to decide upon a construction programme or trading

strategy, most went for both. The revised model was called the LATS MBM (LMBM) and

could take allowance of these new regulations. It was demonstrated through a number of

scenarios that the impact on a council of missing targets was huge, with fines of £ 150 per

tonne being applied for failure to have a valid permit for sending BMW to landfill, at the

extreme, the council would have to commit 52% of its annual budget to buy and sell LATS

given the lack of clarity in the market and the impact of delay on progressed facilities. The

LMBM enabled East Sussex County Council to predict the impact of LATS and a trading

strategy was developed that is in use at the moment.

The delay in the major facility, as postulated in chapter 6, did occur, but the identified fines

were not imposed by DEFRA. ESCC adopted a strategy of buying LATS permits from

Hampshire County Council for the first four years of the scheme, whilst borrowing from

future years. The stabilisation of waste growth also meant that exposure to deficit of LATS

was not as great as first modelled. By 2009 LATS was been seen by many as having achieved

its task and there were considerations into its future, especially as the landfill tax escalator

had reached £45 per tonne and was deemed to be a more potent driver.

7.1.7. Objective 6: Explain the improvements and difficulties found whilst undertaking this

thesis

The MBM and LMBM have been built such that they are fit for purpose, in that they can be

used to run permutations of the waste flow and different facilities to enable the user to reach

desired targets. The models do however exclude certain variables that a local authority officer

may require should they wish to undertake an Integrated waste management system of this

scale, namely;

Cost of facilities,

Page 155: Waste management model

155

Environmental impact,

Land take for facilities, and

Transport infrastructure required

These are all issues that the model cannot at present show, but with development could go a

long way to addressing, either by incorporating within this model or by linking to other

models that already exist. Before any of these improvements can be made there are a number

of other improvements to the current model that can be made to enable a more user friendly

and understandable approach;

7.1.7.1. Improvement no 1: Enabling facilities to be added other than the options given

Both the MBM and LMBM have the option of inputting a set number of facilities, based

upon the development of the model with ESCC and B&HCC. For larger authorities, further

facilities would be required. The adaptation would require redesigning the whole model to

have a user specific drop down menu of facilities to be modelled. Whilst not difficult, the

improvement would be time consuming and would not detract from the outputs for the

councils given in the case study.

7.1.7.2. Improvement no 2: Developing a model comparison system

If a user wants to model numerous scenarios they must manually compare the results from

every version of the model. Whilst time consuming this again does not distract from the out

put of the LMBM. The solution would be to rebuild the model as a set number of scenarios,

with a summary page for all scenarios, again this would be a time consuming piece of work

and would only enhance the usability, rather than the accuracy of the results.

7.1.7.3. Improvement no 3: Develop a waste composition element

At present, all waste is deemed to be 68% biodegradable, and the input to each facility will

use this assumption. The major part of the LMBM development was allowing the model to

calculate what proportion of BMW was remaining after the waste had been through the

facility, this principle could be used at a category level, for example, paper and glass. This

adaption to the model would be complex, but would enable users to get a more accurate

understanding of the proportions of waste available for treatment by different facilities.

Page 156: Waste management model

156

7.2 Further research opportunities

The construction of the MBM and subsequent LMBM has shown the need for a mass balance

model that enables waste management planners to understand the interrelation of facilities

and waste arising. The models have been found to be requiring improvements, as

demonstrated in Section 7.1.7, however, it is also clear that there are opportunities for further

research. The changes in legislation that have occurred during the development of the MBM

and LMBM have occurred in parallel to the emergence of more knowledgeable public, with a

greater understanding of environmental concerns, it is this topic area that presents some of

the potential future research opportunities.

7.2.1 Research option 1: Climate change and green house gas emissions

Waste management treatment through incineration, composting and landfilling generates

carbon dioxide and methane, as household waste contains readily biodegradable carbon based

organic matter such as kitchen waste, garden waste, and paper, and slowly biodegradable

organic materials such as lignin (Burnley 2007). The most important waste gases produced by

incinerators are carbon dioxide (CO2), sulfur dioxide (SO2), and oxides of nitrogen (NO and

NO2, together known as NOx) (Steadman 1996). The major problem with carbon dioxide is

through its contribution to the enhancement of Earth's greenhouse effect. The impact of

climate change and the need to reduce emissions of carbon dioxide and other greenhouse

gases are increasingly recognised as serious issues for Local Authorities and their supply

chains.

With emerging policies and regulations controlling emissions, rising energy prices and

increasing public and investor interest, no local authority can ignore the strategic and

operational implications of climate change and the new carbon economy. Addressing the

impact of waste management on climate change has implications for the modeling performed

by the MBM and LMBM, as they do not take account of the impact of the management of

facilities and subsequent environmental emissions.

Further research is required to identify whether councils should focus on just meeting the

targets set out in UK environmental legislation, as described in Chapter 4, or focus on

diverting waste from landfill with the least impact of emissions to the environment.

Page 157: Waste management model

157

7.2.2 Research Option 2: Funding commitments and risk posed by entering into a PFI

contract

By October 2007 the total capital value of PFI contracts signed throughout the UK was £68bn

committing the British taxpayer to future spending of £215bn (Timmins 2009) over the life of

the contracts. The global financial crisis which began in 2007 presents PFI with difficulties

because many sources of private capital have dried up (Monbiot 2009), making it more

difficult to finance such large scale projects as the £1billion East Sussex County Council and

Brighton & Hove City council contract. The PFI was deemed to be ―Best Value‖ at time of

signature as economies of scale were achieved through the councils working together to fund

facilities they may not have been able to on their own.

However, further research is required to understand whether the methods for meeting the

targets as proposed and modelled by the MBM and LMBM are a sustainable financial option

for the future or whether alternative methods are required that focus on much smaller

contracts. The implication may be that smaller facilities may be required that that are easier to

finance.

7.2.3 Research option 3: Waste as a Resource

Legislative drivers in relation to household waste collection are currently focused on ensuring

at least two recyclables are collected separately from the household by 2010; the type and

range of recyclables targeted and manner in which they are collected and pre-processed

varies significantly. Choices being made are not necessarily market based decisions, or

necessarily borne from consideration of the carbon content or resource potential of the waste

material; rather the decisions are based on the most cost effective collection system to deliver

the greatest tonnage of recyclate to ensure that tonnage based performance targets are met.

Operating a weight based approach such as this does favour collection of the heavier

materials, rather than making decisions based on the value of the material for reprocessing

and its value in terms of potential use. From a resource conservation point of view this does

not necessarily make sense, with lightweighting or ‗rightweighting‘ of products and

packaging playing a big part in the manufacturing process, more material (or heavier

material) will have to be collected to ensure the weight based recycling targets are met.

Page 158: Waste management model

158

The European revised waste framework directive is currently being implemented into

national legislation and includes a requirement by 2015 for Member States to set up separate

waste collection schemes for at least paper, metal, plastic and glass. The UK response to this

is to encourage the separate collection of waste where this is technically, environmentally and

economically practical while still allowing for co-mingled collection of materials for

subsequent separate collection in a MRF to continue after 2015 where this is the most

effective means of increasing recycling rates in local circumstances. In addition the Directive

also sets targets for recycling or preparing for re-use at least 50% by weight of these

materials. The UK is also interpreting the requirement to recycle 50% of specified materials

to apply to the totality of household waste, not for each individual material. This has the

potential to further encourage the collection of heavier materials instead of those with higher

economic and environmental recycling value.

Further research is required to help local authorities model the management of wastes as a

resource, rather than as a way of disposing of a problem.

7.2.4 Research opportunity summary

Local authorities and the private sector need to focus on materials not waste within the

broader context of resource management and carbon reduction/savings as a medium to long

term strategy. Within the South East recycling performance for household waste is on target

and reliance on landfill is reducing, therefore the region needs to reach a point whereby

decisions made regarding collection and recovery are done so outside of the restricted

framework of statutory targets which currently drive waste management. Instead materials

across all waste streams should be considered in terms of their resource potential and carbon

impact. Placing the management of waste within a broader resource framework will allow

alignment of energy priorities and targets and ensure the contribution of resource

management to the carbon agenda is fully realised. To understand the impact of this approach

requires further research, it is necessary for the academic community to embrace this

changing approach and support the policy and management sector with evidence for the

future approach.

Page 159: Waste management model

159

Local authorities and the private sector need to focus on materials not waste within the

broader context of resource management and carbon reduction/savings as a medium to long

term strategy. Within the South East recycling performance for household waste, is on target

and reliance on landfill is reducing. Therefore the region needs to reach a point whereby

decisions made regarding collection and recovery are done outside of the restricted

framework of statutory targets which currently drive waste management. Instead materials

across all waste streams should be considered in terms of their resource potential and carbon

impact. Placing the management of waste within a broader resource framework will allow

alignment of energy priorities and targets and ensure the contribution of resource

management to the carbon agenda is fully realised. To understand the impact of this approach

requires further research, it is necessary for the academic community to embrace this

changing approach and support the policy and management sector with evidence for the

future approach.

7.3 Conclusion

The research has presented the geographical, political and waste background to the area of

Brighton and Hove and East Sussex. It has identified the pressures and drivers for change and

it has identified most of the technological options available to a local authority. The author

has sought to alleviate the pressures on local government by constructing two mass flow

models; one that assesses mass flow through specific facilities, the latter performing the same

function, but additionally modelling the impact of the Landfill Allowance Trading scheme.

The two models were rigorously tested and critically used by two councils as the modelling

tool for their £1billion waste technologies procurement. As demonstrated by this thesis,

wastes management is not a static industry, indeed in 1999, commentators of the day were

suggesting that reaching the landfill targets in the UK for diversion were unachievable. Fast

forward ten years and the consensus is that zero waste places are achievable.

How has the mindset changed so much in a decade? There are many factors; statutory

government targets for recycling, the landfill tax escalator, the Landfill Allowance Trading

Scheme (LATS), Waste Strategy 2000 and 2007 and most importantly councils. There has

been move from a pick and tip system to a separate, sort, process, compost, recycle, recover

and finally dispose to landfill through a very complex logistical methodology. All in all a

major shift from single dimension service to a multi faceted industry. The systematic change

Page 160: Waste management model

160

has produced impressive results; recycling increasing from under 10% to 37.5% in a decade,

a near fourfold change, less than 50% of MSW now goes to landfill, a near fivefold decrease,

unconceivable ten years ago. I wonder whether we have had the dynamic stimulus for the

next decade already, perhaps Hilary Benn and John Denham, DEFRA and CLG respectively,

have already set the target; Zero Waste to landfill.

The direction of travel for the industry points to an ever increasing need to construct

technology to deal with the waste our society produces; the MBM and LMBM help the

decision makers have the right information to improve the way waste is managed.

Page 161: Waste management model

161

REFERENCES

ACR+ 2005, European campaign for waste reduction, 100 kg less waste per inhabitant,

Association of Cities and Regions for Recycling and sustainable Resource management,

http://www.acrplus.org/-kg

Adams K. T., Phillips P. S. & Morris J.R, 2000, A radical new development for sustainable

waste management in the UK: the introduction of local authority Best Value legislation.

Resources, Conservation and Recycling, Volume 30, Issue 3, 1 September 2000, Pages 221-

244

Al Seadi, T., 2002, Quality management of AD residues from biogas production. IEA

Bioenergy, Task 24 – Energy from Biological Conversion of Organic Waste, January 2002.

Allen G., 2001, Research paper 01/117 - The Private Finance Initiative (PFI) House of

Commons Library. ISSN 1368-8456 18th December 2001

Alter H., 1989,. The origins of municipal solid waste: The relations between residues from

packaging materials and food Waste Management & Research, Volume 7, Issue 2, June 1989,

Pages 103-114

Aumonier 2001 – interview with Simon Aumonier, Partner in ERM consulting – The role of

Planning in Integrated Waste management

Barr S. and Gilg A. W., 2005, Conceptualising and analysing household attitudes and actions

to a growing environmental problem: Development and application of a framework to guide

local waste policy Applied Geography, Volume 25, Issue 3, July 2005, Pages 226-247

Bastin L., and Longden D. M., 2009, Comparing transport emissions and impacts for energy

recovery from domestic waste (EfW): Centralised and distributed disposal options for two

UK Counties. Computers, Environment and Urban Systems, Volume 33, Issue 6, November

2009, Pages 492-503

Braber K, 1995, Anaerobic digestion of municipal solid waste: A modern waste disposal

option on the verge of breakthrough Biomass and Bioenergy, Volume 9, Issues 1-5, 1995,

Pages 365-376

Braekman-Danheux C, D'haeyere A., Fontana A. and Laurent P. 1998, Upgrading of waste

derived solid fuel by steam gasification Fuel, Volume 77, Issues 1-2, January 1998, Pages 55-

59

Breakspere R.J., Heath P.J. and Morgan R.J. 1978, Waste glass — re-use or throw away?

Conservation & Recycling, Volume 2, Issue 1, 1978, Pages 49-58

Brunner P.H, and Ernst W. R. 1986, Alternative methods for the analysis of municipal solid

waste, Waste Management & Research, Volume 4, Issue 2, June 1986, Pages 147-160.

Burnley S, 2001,The impact of the European landfill directive on waste management in the

United Kingdom, Resources, Conservation and Recycling 32 (2001) 349–358

Page 162: Waste management model

162

Burnley S.J., Ellis J.C., Flowerdew R., Poll A.J. and Prosser H. 2007, Assessing the

composition of municipal solid waste in Wales, Resources, Conservation and Recycling 49

(2007) 264–283

Burnley S. J., 2007,. A review of municipal solid waste composition in the United Kingdom

Waste Management, Volume 27, Issue 10, Pages 1274-1285

Carlsson K., 1986, Heavy metals from ―energy from waste‖ plants—comparison of gas

cleaning systems, Waste Management & Research, Volume 4, Issue 1, March 1986, Pages

15-20

Carter 2001– interview with Tracy Carter, Project Director, ESCC and BHC PFI Contract –

the pressures of meeting contract deadlines

Cecchi F., Traverso P.G. and Cescon P., 1986, Anaerobic digestion of organic fraction of

municipal solid wastes — digester performance Science of The Total Environment, Volume

56, 15 November 1986, Pages 183-197

Cecchi F., Pavan P, Alvarez J. M., Bassettit A. and Cozzolinot C., 1991, Anaerobic digestion

of Municipal waste: thermophilic vs Mesophillic performance at High Solids, Waste

Management & Research (1991) 9, 305-315

Clift R., Doig A. and Finnveden G., 2000, The Application of Life Cycle Assessment to

Integrated Solid Waste Management: Part 1—Methodology, Process Safety and

Environmental Protection, Volume 78, Issue 4, July 2000, Pages 279-287

Coggins 2002, Civic Amenity Sites –Cinderella at last being invited to the Ball ? Chairman‘s

Paper given to ‗Making Better Use of Civic Amenity Sites‘ M-E-L Research Workshop

Seminar, Birmingham, 7th March 2002

Consonni S., Giugliano M., & Grosso M. Alternative strategies for energy recovery from

municipal solid waste: Part A: Mass and energy balances Waste Management, Volume 25,

Issue 2, 2005, Pages 123-135

Corker P and Davies J, 1999. Who's afraid of the Landfill Directive? The Waste Manager,

August 1999, pps 22-23

Dacombe P., Krivtsov V., Banks C. & Heaven S. 2004, An energy and materials flow model

for evaluation of alternatives for processing domestic and commercial wastes – a case study

of Southampton, University of Southampton

Department of Environment, 1990, Environmental Protection Act (1990) - UK Parts I and II,

Crown copyright, London, UK: HMSO, 16 July 1999

Department of the Environment, 1994, This common inheritance: the third year report:

Britain's environmental strategy, London: HMSO, 1994

Department of the Environment, Transport and the Regions, Less Waste - More Value

Consultation Paper on the Waste Strategy for England and Wales, June 1998 Crown

copyright, London, UK: HMSO

Page 163: Waste management model

163

Department of the Environment, Transport and the Regions (DETR), 1999. Limiting Landfill:

A Consultation paper on limiting landfill to meet the EC Landfill Directive's targets for the

landfill of biodegradable municipal waste, Crown copyright, London, UK: HMSO

DETR, 2000, Waste Strategy 2000 for England and Wales. Part 1. Crown copyright, London,

UK: HMSO 2000.

DETR, 2000b, Guidance on Municipal Waste Management Strategies. Crown copyright,

London, UK: HMSO 2001.

DETR 2001, Department of the Environment, Transport and the Regions (DETR),

Environment in your pocket. HMSO, UK.

DECC 2009, Department of Energy and Climate change, Digest of United Kingdom energy

statistics (DUKES), Inland Consumption of Primary Fuels and Equivalent Energy Use,

http://www.decc.gov.uk/en/content/cms/statistics/publications/dukes/dukes.aspx

DECC 2009, Department of Energy and Climate change, Digest of United Kingdom energy

statistics (DUKES), Aggregate Energy balance 2007 Figures Table 7.1.1,

http://www.decc.gov.uk/en/content/cms/statistics/publications/dukes/dukes.aspx

Department for Environment, Food and Rural Affairs (DEFRA), 2003, Government response

to Strategy Unit report ‗Waste not, Want not‘, Crown copyright, London, UK: HMSO 2003

DEFRA, 2004, Municipal waste, commercial waste and the Landfill Allowances Trading

Scheme, Crown copyright, London, UK: HMSO August 2004

DEFRA, 2005, Landfill Allowances and Trading Scheme (England) (Amendment)

Regulations 2005, Crown copyright, London, UK: HMSO, 2005

DEFRA, 2006, Guidance on the Landfill Allowance Schemes: Municipal Waste revised June

2006 Crown copyright, London, UK: HMSO June 2006

DEFRA, 2006, Operational Waste Facilities in England and Wales at the end of June 2006,

Crown copyright, London, UK: HMSO 2006

DEFRA, 2007, Prepared by Enviros Consulting Limited on behalf of Defra as part of the

New Technologies Supporter Programme. Introductory Guide to Options for the Diversion of

Biodegradable Municipal Waste from Landfill, Crown copyright, London, UK: HMSO 2007

Dent C. G. & Krol A. A., 1990, Municipal Solid Waste Conversion to Energy, Biomass 22

(1990) 307-327

Dolk H., Vrijheid M., Armstrong B., Abramsky L., Bianchi F., Garne E., Nelen V., Robert

E., Scott J.E.S., Stone D., Tenconi R., 1998, Risk of congenital anomalies near hazardous-

waste landfill sites in Europe; the EUROHAZCON study. The Lancet, Vol 352, August 8,

1998

Page 164: Waste management model

164

Environment, Transport and Regional Affairs (EFRA) Committee, 1999. Thirteenth Report:

The Operation of the Landfill Tax - Volume 1: Report and Proceeding of the Committee.

HMSO, London.

Eriksson O., Frostell B., Björklund A., Assefa G., Sundqvist J. -O., Granath J., Carlsson M.,

Baky A., Thyselius L.ORWARE—a simulation tool for waste management

Resources, Conservation and Recycling, Volume 36, Issue 4, November 2002, Pages 287-307

Edelmann W. Moser C. & Engeli H., 1997 More than 12 years of experience with

commercial anaerobic digestion of the organic fraction of municipal solid wastes in

Switzerland. Biomass & wood energy Programme 910018 - Biomasse (Übrige Biomasse,

Abfälle, Klärschlamm, ohne Holz), Department of the Environment, Transport, Energy and

Communications, Swiss Federal Office of Energy (SFOE), 01.11.1997

Emery A., Davies A., Griffiths A. & Williams K., 2007, Environmental and economic

modelling: A case study of municipal solid waste management scenarios in Wales

Resources, Conservation and Recycling, Volume 49, Issue 3, January 2007, Pages 244-263

Energy Technology Support Unit (ETSU), 1998, An Introduction to Household Waste

Management: Energy-from-waste incineration, ETSU, Harwell, Oxfordshire, 1998.

Environment Agency 2001, ‗Large Scale Composting – a practical manual for the UK‘

Crown copyright, London, UK: HMSO, May 2001.

European Council, 1975 European Council, Council Directive 75/442/EEC of 15 July 1975

on waste, as amended by Council Directive 91/156/EEC, Official Journal of the European

Communities L 194 (1975), pp. 039–041.

European Council, 1991a European Council, Council Directive 91/689/EEC of 12 December

1991 on hazardous waste, Official Journal of the European Communities L 377 (1991), pp.

020–027 (Amended by Council Directive 94/31/EC. Official Journal of the European

Communities, L 168, p. 028.).

European Council, 1991b European Council, Council Directive 91/414/EEC of 15 July 1991

concerning the placing of plant protection products on the market, Official Journal of the

European Communities L 230 (1991), pp. 001–032.

European Council, 1994 European Council, Council Decision 94/904/EC of 22 December

1994 establishing a list of hazardous waste pursuant to Article 1(4) of Council Directive

91/689/EEC on hazardous waste, Official Journal of the European Communities L 356

(1994), pp. 014–022.

European Council, 1999 European Council, Council Directive 99/31/EC of 6 April 1999 on

the landfill of waste, Official Journal of the European Communities L 182 (1999), pp. 001–

019.

European Council, 2001 European Council, Council Decision 2001/573/EC of 23 July 2001

amending Commission Decision 2000/532/EC as regards the list of wastes, Official Journal

of the European Communities L 203 (2001), pp. 018–019.

Page 165: Waste management model

165

European Council, 2003 European Council, Council Decision 2003/33/EC of 19 December

2002 establishing criteria and procedures for the acceptance of waste at landfills pursuant to

Article 16 of and Annex II to Directive 1999/31/EC, Official Journal of the European

Communities L 11 (2003), pp. 027–049.

European Commission, 2008, Green Paper - On the management of bio-waste in the

European Union {SEC(2008) 2936}, Brussels, 3.12.2008, COM(2008) 811 final ENV 1036

AGRI 471

European Environment Agency (EEA) 2006, EEA Technical report No 5/2006 Paper and

cardboard — recovery or disposal? Review of life cycle assessment and cost-benefit analysis

on the recovery and disposal of paper and cardboard, European Environment Agency,

Copenhagen, Denmark ISBN 92-9167-783-3

Fenton R. 1978, Current trends in municipal solid waste disposal in New York City

Resource Recovery and Conservation, Volume 1, Issue 2, October 1975, Pages 167-176

Flyvbjerg B., Mette K. Holm S., and Buhl S. L., 2002, Underestimating Costs in Public

Works Projects: Error or Lie?, Journal of the American Planning Association, vol. 68, no. 3,

Summer 2002, pp. 279-295

Fricke K., Santen H., Wallmann R., Hüttner A. & Dichtl N., 2007Operating problems in

anaerobic digestion plants resulting from nitrogen in MSW, Waste Management, Volume 27,

Issue 1, 2007, Pages 30-43

Fruteau de Laclos H., Desbois S. and Saint-Joly C., Anaerobic digestion of municipal solid

organic waste: Valorga full-scale plant in tilburg, Water Science and Technology Volume 36,

Issues 6-7, 1997 , Pages 457-462

Garg A., Smith R., Hill D., Longhurst P.J., Pollard S.J.T. & Simms N.J.An integrated

appraisal of energy recovery options in the United Kingdom using solid recovered fuel

derived from municipal solid waste, Waste Management, Volume 29, Issue 8, August 2009,

Pages 2289-2297

Gray KR, Biddlestone AJ, 1980, Agricultural use of composted town refuse. Inorganic

Pollution and Agriculture. Ministry of Agriculture, Fisheries and Food, Reference Book 326,

London, UK, 1980. pp. 279–305.

Gim B., Deuermeyer B. L. & Curry G. L.Optimal scheduling of a single anaerobic digester

with multiple feedstocks, Computers & Industrial Engineering, Volume 41, Issue 1, October

2001, Pages 1-15

Gray J.M., 2002, Landraising of waste in England, 1990–2000: a survey of the

geomorphological issues raised by planning applications, Applied Geography 22 (2002) 209–

234

Hegberg A. B., Hallenbeck W. H., Brenniman G. R. and Wadden R. A. 1991. Municipal solid

waste incineration with energy recovery in the U.S.A.—Technologies, facilities and vendors

for less than 550 tons per day. Waste Management & Research (1991) 9, 127-152

Page 166: Waste management model

166

Hopkowicz M., Hultman B., Kurbiel J., Plaza E. (Editors), TRITA-AMI REPORT 3088,

ISSN 1400-1306, ISRN KTH/AMI/REPORT 3088-SE, ISBN 91-7283-190-1. 2001

IESE 2009, presentation to NAWDO, MBT Local Authority Support Project, September

2009

Iyengar S. R. & Bhave P. P., 2006, In-vessel composting of household wastes, Waste

Management, Volume 26, Issue 10, 2006, Pages 1070-1080

Kiely G., Tayfur G., Dolan C. & K. Tanji, 1997, Physical and mathematical modelling of

anaerobic digestion of organic wastes, Water Research, Volume 31, Issue 3, March 1997,

Pages 534-540

Kirkeby J. T., Birgisdottir H., B. G. Singh, Hauschild M., &. Christensen T.H Modelling of

environmental impacts of solid waste landfilling within the life-cycle analysis program

EASEWASTE Waste Management, Volume 27, Issue 7, 2007, Pages 961-970

Kuhlman L.R., 1990, Windrow composting of agricultural and municipal wastes, Resources,

Conservation and Recycling, Volume 4, Issues 1-2, August 1990, Pages 151-160

Lewis, M. F.; Haug, T R.; Poosti, A; Redd, K.R., 2007, Proceedings of the Water

Environment Federation, Residuals and Biosolids Management 2007, pp. 338-348(11)

Lee P., D. Fitzsimons and D. Parker, 2005, Quantification of the Potential Energy from

Residues (EfR) in the UK, ICE, RPA, London (2005).

Lee S., 2002, presentation to the IWM conference, Torquay 2002

Lu Y., Wu X, Guo J., 2009, Characteristics of municipal solid waste and sewage sludge co-

composting, Waste Management, Volume 29, Issue 3, March 2009, Pages 1152-1157

Lyas J. K., Shaw P. J. & Mark van Vugt, 2005, Kerbside recycling in the London Borough of

Havering: progress and priorities, Resources, Conservation and Recycling, Volume 45, Issue

1, September 2005, Pages 1-17

Marchettini N., Ridolfi R. & Rustici M., 2007. An environmental analysis for comparing

waste management options and strategies Waste Management, Volume 27, Issue 4, 2007,

Pages 562-571

Mattsson C.H., Berg P.E.O. & Clarkson P.A.The development of systems for property close

collection of recyclables: experiences from Sweden and England, Resources, Conservation

and Recycling, Volume 38, Issue 1, April 2003, Pages 39-57

Maycox, A., 2003. The Village Initiative Project: achieving household waste minimisation in

the rural locale. CIWM Sci. Tech. Rev. 4 3, pp. 10–17

Mazzanti M. & Zoboli R., 2008, Waste generation, waste disposal and policy effectiveness,

Evidence on decoupling from the European Union, Resources, Conservation and Recycling

52 (2008) 1221–1234

Page 167: Waste management model

167

McOmish D., 1996, East Chisenbury: ritual and rubbish at the British Bronze Age-Iron Age

transition, Antiquity, March, 1996

Mercia Waste website, Mercia Energy from Waste Facility, http://www.envirecover.co.uk

Miranda M.L. & Hale B., 1997, Waste not, want not: the private and social costs of waste-to-

energy production, Energy Policy, Volume 25, Issue 6, May 1997, Pages 587-600

Morrissey A. J. & Browne J., 2004, Waste management models and their application to

sustainable waste management, Waste Management, Volume 24, Issue 3, 2004, Pages 297-

308

Mühle S., Balsam I., and Cheeseman C.R., 2010, Comparison of carbon emissions associated

with municipal solid waste management in Germany and the UK

Resources, Conservation and Recycling, In Press, Corrected Proof, Available online 8

February 2010,

Newton J. W., 1983, Planning, design and on-going control of environmental protection

practices for landfill sites in the U.K. Waste Management & Research, Volume 1, Issue 4,

1983, Pages 337-346

Nguyen P.H.L., Kuruparan P., & Visvanathan C., 2007, Anaerobic digestion of municipal

solid waste as a treatment prior to landfill, Bioresource Technology, Volume 98, Issue 2,

January 2007, Pages 380-387

Nie Y., Li T., Yan G., Wang Y. & Ma X., An Optimal Model and Its Application for the

Management of Municipal Solid Waste from Regional Small Cities in China, ISSN 1047-

3289 Journal of Air & Waste Management Association. 54: Feb 2004, pages 191–199,

Office of Government Commerce (OGC), 2006, Kelly Report to the Financial Secretary to

the Treasury - Improving competition and capacity planning in the municipal waste market.

Crown copyright, London, UK: HMSO 2006

Organisation for Economic Co-operation and Development (OECD), Environment policy

committee, 2004,Working Group on Waste Prevention and Recycling, Working Group on

Environmental Information and Outlooks- Towards Waste Prevention Performance

indicators, ENV/EPOC/WGWPR/SE(2004)1/FINAL, 30-Sep-2004

Ostrem K., 2004, Greening Waste: Anaerobic digestion for treating the organic fraction of

municipal waste, Submitted in partial fulfilment of requirements for M.S. thesis in Earth

Resources Engineering Department of Earth and Environmental Engineering Fu Foundation

of School of Engineering and Applied Science, Columbia University, May 2004

OWS 2000, Organic Waste Systems (OWS) Fact-file on DRANCO AD facility,

http://www.ows.be/pages/index.php?choose_lang=EN&menu=85

Papageorgiou A., Barton J.R. & A. Karagiannidis Assessment of the greenhouse effect

impact of technologies used for energy recovery from municipal waste: A case for England,

Journal of Environmental Management, Volume 90, Issue 10, July 2009, Pages 2999-3012

Page 168: Waste management model

168

PE Europe 2003, PE Europe GMBH, Business Briefing: CPI Technology 2003

Peacock 2000 – interview with Amelia Peacock, Manager of the Community Health and

Environment team, Brighton & Hove City Council – the pressures of Waste Management

Petts J., 1992, Incineration risk perceptions and public concern: Experience in the U.K.

improving risk communication Waste Management & Research, Volume 10, Issue 2, April

1992, Pages 169-182

Petts J., 1994, Effective Waste Management: Understanding and Dealing With Public

Concerns, Waste Management & Research, Vol. 12, No. 3, (1994) 207-222

Phillips P.S., Gronow B. & Read A. D., 1998, A regional perspective on waste minimisation:

a case study of the East Midlands of England, Resources, Conservation and Recycling,

Volume 23, Issue 3, August 1998, Pages 127-161

Price J. L., 2001, The landfill directive and the challenge ahead: demands and pressures on

the UK householder, Resources, Conservation and Recycling 32 (2001) 333–348

Porteous A., 2005, Why energy from waste incineration is an essential component of

environmentally responsible waste management Waste Management, Volume 25, Issue 4,

2005, Pages 451-459

Qin W., Egolfopoulos F. N., Tsotsis T. T., 2000, Fundamental and environmental aspects of

landfill gas utilization for power generation. Chemical Engineering Journal, Volume 82,

Issues 1-3, 15 March 2001, Pages 157-172

Qviström M., 2008, A waste of time? On spatial planning and ‗wastelands‘ at the city edge of

Malmö (Sweden), Urban Forestry & Urban Greening, Volume 7, Issue 3, 1 August 2008,

Pages 157-169

Rasapoor M., Nasrabadi T., Kamali M., & Hoveidi H., 2009, The effects of aeration rate on

generated compost quality, using aerated static pile method, Waste Management, Volume 29,

Issue 2, February 2009, Pages 570-573

Read A. D., Phillips P.S. & Murphy A., 1997, English county councils and their agenda for

waste minimisation, Resources, Conservation and Recycling 20 (1997) 277-294

Read A. D. 1999a ‗‗A weekly doorstep recycling collection, I had no idea we could!‘‘

Overcoming the local barriers to participation, Resources, Conservation and Recycling 26

(1999) 217–249

Read A. D. 1999b , Making waste work: making UK national solid waste strategy work at the

local scale, Resources, Conservation and Recycling 26 (1999) 259–285

Reichenbach J., 2008, Status and prospects of pay-as-you-throw in Europe – A review of

pilot research and implementation studies, Waste Management, Volume 28, Issue 12,

December 2008, Pages 2809-2814

Page 169: Waste management model

169

Renkow M. & Rubin A. R., 1998, Does municipal solid waste composting make economic

sense?, Journal of Environmental Management (1998) 53, 339–347

Resource Futures 2009, WR0121 – Understanding Waste Growth at Local Authority Level,

Final Report to Defra, RF project no: 506, 3rd October 2009

Riley 2001 – interview with Keith Riley, Managing Director of Hampshire Waste Services –

How the Private sector manages a PFI contract

Rodríguez-Iglesias J., Marañón E., Castrillón L., Riestra P. & Sastre H., 2003, Life cycle

analysis of municipal solid waste management possibilities in Asturias, Spain, Waste

Management & Research, Vol. 21, No. 6, 535-548 (2003)

Rushbrook P. E . & Finnecy E . E ., 1988, Planning for future waste management operations

in developing countries, Waste Management & Research (1988) 6, 1-21

Schevon G. R. & Damas G., 1986, Using double liners in landfill design and operation,

Waste Management & Research, Volume 4, Issue 2, June 1986, Pages 161-176

Six W. and De Baere, L. Dry Anaerobic Conversion: The Dranco Process Organic Waste

Systems N.V., Gent, Belgium (DoE 1990)

Slater R., Frederickson J., Thomas C., Wield D. & Potter S., 2007, A critical evaluation of

partnerships in municipal waste management in England, Resources, Conservation and

Recycling, Volume 51, Issue 3, September 2007, Pages 643-664

South East Regional Plan (SERP) 160: Revised Waste Planning Advice A Sustainable Waste

Planning Strategy For The South East 1996-2010 (March 1997).

Strategy Unit, 2002 'Analysis of household waste composition and factors driving waste

increases', (2002) Analysis for 'Waste Not, Want Not' Prime Ministers Strategy Unit, 2002,

Crown copyright, London, UK: HMSO

Stypka T., 2007, Integrated solid waste management model as a tool of sustainable

development, Proceedings of Polish-Swedish seminars, Stockholm June 6-8, 2004 Integration

and optimisation of urban sanitation systems. E. Plaza, E. Levlin, (Editors) TRITA-

LWR.REPORT 3017, ISSN 1650-8610, ISRN KTH/LWR/REPORT 3017-SE, ISBN 978-91-

7178-825-2. 2007

Stypka T. Proceedings of a Polish-Swedish seminar, Nowy Targ - Zakopane, October 24-26,

2001. Wastewater, Sludge and Solid Waste Management, Oct 2001

Taseli B. K, 2007, The impact of the European Landfill Directive on waste management

strategy and current legislation in Turkey‘s Specially Protected Areas, Resources,

Conservation and Recycling 52 (2007) 119–135

Thomas, 2001 C. Thomas, Public understanding and its effect on recycling performance in

Hampshire and Milton Keynes, Resources, Conservation and Recycling 32 (2001), pp. 259–

274

Page 170: Waste management model

170

Tonglet M., Phillips P.S., Bates M. P. Determining the drivers for householder pro-

environmental behaviour: waste minimisation compared to recycling, Resources,

Conservation and Recycling 42 (2004) 27–48

Tyson K. S., Rymes M., Hammond E., 1996, Future potential for MSW energy development,

Biomass and Bioenergy, Volume 10, Issues 2-3, 1996, Pages 111-124

Tucker P. & Smith D., (1999), Simulating Household Waste Management Behaviour, Journal

of Artificial Societies and Social Simulation vol. 2, no. 3, 30-Jun-1999

Veolia Environment 2009, - Financial and Strategic Analysis Review from Global Markets

Direct - Company Reports 23 page report published Aug 20, 2009

Waste & Resources Action Programme (WRAP) 2007, Composting Wood or Cardboard

Waste with Green Garden or Household Kitchen Waste, ISBN: 1-84405-299-0 Research

date: August 2005 – December 2006, Published May 2007, Banbury, UK

Waste & Resources Action Programme (WRAP) 2009, Choosing the right recycling

collection system Published 2009, Banbury, UK

Waste watch 2004, History of waste and recycling information sheet, updated October 2004

http://www.wasteonline.org.uk/resources/InformationSheets/HistoryofWaste.pdf

Woodard R. Bench M., Harder M. K. & Stantzos N., 2004, The optimisation of household

waste recycling centres for increased recycling—a case study in Sussex, UK, Resources,

Conservation and Recycling, Volume 43, Issue 1, December 2004, Pages 75-93

Wright 2000– interview with Mitchell Wright, Site manager of Beddingham landfill site,

Lewes, operated by Viridor

Zhang R., El-Mashad H.M., Hartman K., Wang F, Liu G., Choate C. & Gamble P., 2007,

Characterization of food waste as feedstock for anaerobic digestion, Bioresource Technology,

Volume 98, Issue 4, March 2007, Pages 929-935

Zhiqiang K.Z.L., Solutions for Urban Residential Garbage Treatment; Urban Manage.

Technol. 2001, 3, 8-12.

Page 171: Waste management model

171

Appendix 1 Local Authority Officer Questionnaire

Key factors for optimal model for usage by Local Authorities Questionnaire

I am conducting research to understand the parameters that local authority

officers would require to enable them to model the future size of facilities to

meet European and UK recycling and recovery targets.

Could you please score the following factors on priority for ease of usage out of

5, with 1 being highest priority and 5 being the lowest?

Thank you for your time, I will feed back to you the results.

David Greenfield

Parameter Score

Understanding of processes to be used

Behaviour of Processes is evidenced

Evidence and processes included in the

collection service

Ease of data entry aligned to current

reporting

Ease of analysis

High quality data history

Format of model

Page 172: Waste management model

Results of individual questionnaires and scoring of the Mode average

Key factors for

optimal model for

usage by Local

Authorities

(1 being

highest, 5

lowest)

Understanding

of processes to

be used

Behaviour of

Processes is

evidenced

Evidence and

processes

included in

the collection

service

Ease of data

entry aligned

to current

reporting

Ease of

analysis

High quality

data history

Format of

model

Priority for ease of

usage 1.55 2 1.95 1.25 1 2.1 4.2

Officer 1 2 1 1 1 1 2 5

Officer 2 2 3 2 1 1 2 5

Officer 3 2 2 2 1 1 2 4

Officer 4 1 3 1 1 1 2 4

Officer 5 1 2 2 1 1 1 4

Officer 6 2 1 3 2 1 3 5

Officer 7 1 4 1 2 1 3 4

Officer 8 1 2 3 1 1 2 4

Officer 9 1 1 1 1 1 2 4

Officer 10 2 2 2 1 1 2 4

Officer 11 3 2 2 1 1 2 3

Officer 12 2 3 2 2 1 3 4

Officer 13 1 2 2 1 1 2 5

Officer 14 1 2 2 1 1 1 4

Officer 15 2 1 2 2 1 2 4

Officer 16 1 2 2 1 1 3 3

Officer 17 3 2 2 1 1 2 5

Officer 18 1 1 3 1 1 2 5

Officer 19 1 2 2 2 1 3 4

Officer 20 1 2 2 1 1 1 4

Page 173: Waste management model

173

Appendix 2: RS1

The following sheets show the three parts of the RS1 Mass balance Model, as used by East Sussex

County Council and Brighton & Hove City Council for the PFI Integrated Waste Management

Services Contract (IWMSC)

Page 174: Waste management model

174

RS1 Input Sheet

Financial

Year

Contract

YearMRF1 MRF2 MRF3 MRF4

On-farm

Composting

Anaerobic

Digestor

Composter 1

throughput from

AD plant when

operational

Composter 2

throughput

from AD plant

when

operational

Composter 1

throughput IF

NO AD plant

Composter 2

throughput IF

NO AD plant

Third Party

wasteRDF Plant

Household

Waste diverted

by use of bring

banks

HWS Bring

banks

Throughput of

EfW 1

Throughput

of EfW 2 EfW 1 EfW 2 Perecnetage

growth Per year

for Municipal

Waste

Perecnetage

growth Per year

for Household

Waste

85% 85% 0% 0% 100% 50% 100% 100% N/A 35% 100% 100% 69% 69% Base Ash 28% 28% (Percentage) (Percentage)

15% 15% 0% 0% N/A 50% 0% 0% N/A N/A 65% N/A N/A 31% 31%Base ash to

landfill50% 50%

50% 50% 0% 0% N/A 50% 0% 0% N/A N/A 50% 100% N/A N/A 50% 50%

50% 50% 0% 0% N/A 50% 0% 0% N/A N/A 50% 0% N/A N/A 50% 50%

0% 0% 0% 0% N/A 0% 0% 0% N/A N/A 0% 0% N/A N/A 0% 0%

2002/3 1 - - - - 5,000.00 - - - - 19,114.00 75,000.00 15,044.48 - - - 0.00% 0.00%

2003/4 2 40,000.00 - - - 15,000.00 - - - - 19,496.00 75,000.00 3,836.34 6,905.42 - - 2.00% 2.00%

2004/5 3 40,000.00 - - - 15,000.00 - - - - 19,886.00 75,000.00 3,913.07 7,043.52 - - 2.00% 2.00%

2005/6 4 40,000.00 16,000.00 - - 5,000.00 60,000.00 30,000.00 - - 20,284.00 75,000.00 3,991.33 7,184.40 - - 2.00% 2.00%

2006/7 5 40,000.00 16,000.00 - - 5,000.00 60,000.00 30,000.00 - - 20,690.00 75,000.00 4,071.16 7,328.08 - - 2.00% 2.00%

2007/8 6 40,000.00 16,000.00 - - 5,000.00 60,000.00 30,000.00 - - 20,897.00 18,750.00 4,111.87 7,401.36 - - 1.00% 1.00%

2008/9 7 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 21,105.00 - 2,076.49 7,475.38 150,000.00 - 1.00% 1.00%

2009/10 8 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 21,317.00 - 2,097.26 7,550.13 150,000.00 - 1.00% 1.00%

2010/11 9 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 21,530.00 - 2,118.23 7,625.63 150,000.00 - 1.00% 1.00%

2011/12 10 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 21,745.00 - 2,139.41 10,269.19 150,000.00 - 1.00% 1.00%

2012/13 11 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 21,854.00 - 2,150.11 10,320.53 150,000.00 - 0.50% 0.50%

2013/14 12 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 21,963.00 - 2,160.86 10,372.13 150,000.00 - 0.50% 0.50%

2014/15 13 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 22,073.00 - 2,171.67 10,423.99 150,000.00 - 0.50% 0.50%

2015/16 14 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 22,183.00 - 2,182.52 13,095.14 180,000.00 - 0.50% 0.50%

2016/17 15 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 22,294.00 - 2,193.44 13,160.62 180,000.00 - 0.50% 0.50%

2017/18 16 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 22,406.00 - 2,204.40 13,226.42 180,000.00 - 0.50% 0.50%

2018/19 17 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 22,518.00 - 2,215.43 13,292.55 180,000.00 - 0.50% 0.50%

2019/20 18 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 22,630.00 - 2,226.50 13,359.02 180,000.00 - 0.50% 0.50%

2020/21 19 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 22,743.00 - 2,237.64 13,425.81 180,000.00 - 0.50% 0.50%

2021/22 20 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 22,857.00 - 2,248.82 13,492.94 180,000.00 - 0.50% 0.50%

2022/23 21 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 22,971.00 - 2,260.07 13,560.41 180,000.00 - 0.50% 0.50%

2023/24 22 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 23,086.00 - 2,271.37 13,628.21 180,000.00 - 0.50% 0.50%

2024/25 23 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 23,202.00 - 2,282.72 13,696.35 180,000.00 - 0.50% 0.50%

2025/26 24 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 23,318.00 - 2,294.14 13,764.83 180,000.00 - 0.50% 0.50%

2026/27 25 40,000.00 62,000.00 - - 5,000.00 60,000.00 30,000.00 - - 23,434.00 - 2,305.61 13,833.65 180,000.00 - 0.50% 0.50%

Total residues

residues to landfill

residues to efw

residues to benefical

use

-

-

-

-

HW growth

EFW ResiduesThroughputs and efficiencies

Efficiency of plant

0%

Base figure HW 376,112

Input column for MW &

HW growth0.0%

Base figure MW 393,271

Waste Growth

Fly ash 3% 3%

Residue to

Beneficial

Use

50% 50%

Page 175: Waste management model

175

The RS1 Calculation sheet:

The following nine pages are screen shots of the single spreadsheet that is used to calculate the mass flow of waste between facilities;

each sheet is shown for the full twenty five years. The yellow cells show the data that has been imported from the input sheet. The

aquamarine rows refer to the target years set in Waste Strategy 2000. It should be noted that there are three waste columns; MSW

which has been then been split into Contract Household waste and Contract waste other Household waste, this division was required for

the PFI contract.

Page 176: Waste management model

176

MRF Calculation Sheet

Total MRF

throughput

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63

Financial

Year

Contract

Year

Total

Municipal

Waste

throughput

Contract

Household

Waste

Contract Waste

other than

Household Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

throughput

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

throughput

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

throughput

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

2002/3 1 - - - - - - - - - - - - - - - - - - - - - - - - -

2003/4 2 40,000 37,717 2,283 34,000 32,059 1,941 - - - - - - - - - - - - - - - - - - 40,000

2004/5 3 40,000 37,728 2,272 34,000 32,069 1,931 - - - - - - - - - - - - - - - - - - 40,000

2005/6 4 40,000 37,738 2,262 34,000 32,078 1,922 16,000 15,095 905 13,600 12,831 769 - - - - - - - - - - - - 56,000

2006/7 5 40,000 37,749 2,251 34,000 32,086 1,914 16,000 15,099 901 13,600 12,835 765 - - - - - - - - - - - - 56,000

2007/8 6 40,000 38,077 1,923 34,000 32,366 1,634 16,000 15,231 769 13,600 12,946 654 - - - - - - - - - - - - 56,000

2008/9 7 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

2009/10 8 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

2010/11 9 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

2011/12 10 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

2012/13 11 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

2013/14 12 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

2014/15 13 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

2015/16 14 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

2016/17 15 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

2017/18 16 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

2018/19 17 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

2019/20 18 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

2020/21 19 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

2021/22 20 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

2022/23 21 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

2023/24 22 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

2024/25 23 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

2025/26 24 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

2026/27 25 40,000 38,166 1,834 34,000 32,441 1,559 62,000 59,157 2,843 52,700 50,283 2,417 - - - - - - - - - - - - 102,000

MRF 2 Diversion of Household Waste

stream MRF3 throughput

MRF 3 Diversion of Household Waste

stream MRF4 throughput

MRF 4 Diversion of Household Waste

stream

Type of Year

MRF 1 throughputMRF 1 Diversion of Household Waste

stream MRF 2 throughput

Page 177: Waste management model

177

MRF Diversion & Composting section

Diversion of

Household

Waste to

facilities i.e.

throughput of

MRFs

Diversion of

dry recyclables

from landfill

through MRF's

Percentage of

Household Waste

diverted by

composting

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (Percentage) (Percentage) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (Percentage)

64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

Total Municipal

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total Municipal

Waste

- - - - - - 0.0% 0.0% - - - - - - 5,000 4,713 287 5,000 4,713 287 1.3%

34,000 32,059 1,941 - - - 10.4% 8.9% - - - - - - 15,000 14,144 856 15,000 14,144 856 3.9%

34,000 32,069 1,931 - - - 10.2% 8.7% - - - - - - 15,000 14,148 852 15,000 14,148 852 3.8%

47,600 44,909 2,691 - - - 14.0% 11.9% 30,000 28,304 1,696 - - - 5,000 4,717 283 35,000 33,021 1,979 8.8%

47,600 44,921 2,679 - - - 13.8% 11.7% 30,000 28,312 1,688 - - - 5,000 4,719 281 35,000 33,030 1,970 8.6%

47,600 45,312 2,288 - - - 13.6% 11.6% 30,000 28,558 1,442 - - - 5,000 4,760 240 35,000 33,318 1,682 8.5%

86,700 82,724 3,976 15,300 13,889 668 24.6% 20.9% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 8.4%

86,700 82,724 3,976 15,300 13,889 668 24.3% 20.7% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 8.3%

86,700 82,724 3,976 15,300 13,889 668 24.1% 20.5% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 8.3%

86,700 82,724 3,976 15,300 13,889 668 23.8% 20.3% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 8.2%

86,700 82,724 3,976 15,300 13,889 668 23.7% 20.2% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 8.1%

86,700 82,724 3,976 15,300 13,889 668 23.6% 20.1% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 8.1%

86,700 82,724 3,976 15,300 13,889 668 23.5% 20.0% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 8.1%

86,700 82,724 3,976 15,300 13,889 668 23.4% 19.9% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 8.0%

86,700 82,724 3,976 15,300 13,889 668 23.3% 19.8% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 8.0%

86,700 82,724 3,976 15,300 13,889 668 23.1% 19.7% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 7.9%

86,700 82,724 3,976 15,300 13,889 668 23.0% 19.6% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 7.9%

86,700 82,724 3,976 15,300 13,889 668 22.9% 19.5% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 7.9%

86,700 82,724 3,976 15,300 13,889 668 22.8% 19.4% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 7.8%

86,700 82,724 3,976 15,300 13,889 668 22.7% 19.3% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 7.8%

86,700 82,724 3,976 15,300 13,889 668 22.6% 19.2% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 7.7%

86,700 82,724 3,976 15,300 13,889 668 22.5% 19.1% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 7.7%

86,700 82,724 3,976 15,300 13,889 668 22.3% 19.0% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 7.7%

86,700 82,724 3,976 15,300 13,889 668 22.2% 18.9% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 7.6%

86,700 82,724 3,976 15,300 13,889 668 22.1% 18.8% 30,000 28,624 1,376 - - - 5,000 4,771 229 35,000 33,395 1,605 7.6%

On-farm Total diversion of Household Waste from

landfill through composters

Total diversion of Household Waste

from landfill via MRF'sTotal residues to EFW from MRF's

Composter 1 throughput from AD plant

when operational

Composter 2 throughput from AD plant

when operational

Page 178: Waste management model

178

Bring Bank and Recycling Rate Calculations

Household Waste

diverted by use of bring

banks

HWS Bring banks

Percentage of Household

Waste stream that is diverted

by Bring banks

Third party recycling outside

of contract

Percentage of Household

Waste stream that is diverted

by Third Party

Household Waste stream

recycled

(tonnes) (tonnes) (Percentage) (tonnes) (Percentage) (tonnes) (Percentage)

85 86 87 88 89 90 91 92 93 94

Total Municipal Waste Total Municipal Waste Total Municipal Waste Third Party Waste Total Municipal Waste Total Municipal Waste

Contract

Household

Waste

Contract Waste

other than

Household Waste

Third Party Waste Total Municipal Waste

15,044 - 4.00% 19,114 5.08% 39,158 19,758 287 19,114 10.4%

3,836 6,905 2.80% 19,496 5.08% 79,238 56,945 2,797 19,496 20.7%

3,913 7,044 2.80% 19,886 5.08% 79,843 57,173 2,783 19,886 20.4%

3,991 7,184 2.80% 20,284 5.08% 114,060 89,105 4,670 20,284 28.6%

4,071 7,328 2.80% 20,690 5.08% 114,689 89,350 4,649 20,690 28.2%

4,112 7,401 2.80% 20,897 5.08% 115,010 90,143 3,970 20,897 28.0%

2,076 7,475 2.30% 21,105 5.08% 152,357 125,671 5,581 21,105 36.7%

2,097 7,550 2.30% 21,317 5.08% 152,664 125,766 5,581 21,317 36.4%

2,118 7,626 2.30% 21,530 5.08% 152,974 125,863 5,581 21,530 36.1%

2,139 10,269 2.90% 21,745 5.08% 155,854 128,527 5,581 21,745 36.4%

2,150 10,321 2.90% 21,854 5.08% 156,025 128,589 5,581 21,854 36.3%

2,161 10,372 2.90% 21,963 5.08% 156,196 128,652 5,581 21,963 36.1%

2,172 10,424 2.90% 22,073 5.08% 156,369 128,714 5,581 22,073 36.0%

2,183 13,095 3.50% 22,183 5.08% 159,161 131,396 5,581 22,183 36.5%

2,193 13,161 3.50% 22,294 5.08% 159,348 131,473 5,581 22,294 36.3%

2,204 13,226 3.50% 22,406 5.08% 159,537 131,550 5,581 22,406 36.2%

2,215 13,293 3.50% 22,518 5.08% 159,726 131,627 5,581 22,518 36.0%

2,227 13,359 3.50% 22,630 5.08% 159,916 131,704 5,581 22,630 35.9%

2,238 13,426 3.50% 22,743 5.08% 160,106 131,782 5,581 22,743 35.8%

2,249 13,493 3.50% 22,857 5.08% 160,299 131,861 5,581 22,857 35.6%

2,260 13,560 3.50% 22,971 5.08% 160,491 131,939 5,581 22,971 35.5%

2,271 13,628 3.50% 23,086 5.08% 160,686 132,018 5,581 23,086 35.4%

2,283 13,696 3.50% 23,202 5.08% 160,881 132,098 5,581 23,202 35.2%

Household Waste Recycling RateRecycling

Bring banks Recycling rate

Diversion of Waste from landfill via recycling

Page 179: Waste management model

179

RDF & Anaerobic Digestion

Capacity of plant

Diversion of

Municipal

Waste from

landfill via

RDF

Percentage

of Municipal

Waste

recovery by

RDF

Percentage of

Municipal Waste

recovery by AD

(tonnes) (tonnes) (Percentage) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (Percentage)

95 96 97 98 99 100 101 102 103 104 105 106 107

Total Municipal

Waste

Total

Municipal

Waste

Total

Municipal

Waste

Total Municipal Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total Municipal

Waste

75,000 26,250 6.67% - - - - - - - - - 0.0%

75,000 26,250 6.54% - - - - - - - - - 0.0%

75,000 26,250 6.42% - - - - - - - - - 0.0%

75,000 26,250 6.29% 60,000.00 56,608 3,392 30,000.00 28,304 1,696 30,000 28,304 1,696 7.2%

75,000 26,250 6.17% 60,000.00 56,623 3,377 30,000.00 28,312 1,688 30,000 28,312 1,688 7.0%

18,750 6,563 1.53% 60,000.00 57,116 2,884 30,000.00 28,558 1,442 30,000 28,558 1,442 7.0%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.9%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.8%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.8%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.7%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.7%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.6%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.6%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.6%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.5%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.5%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.5%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.4%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.4%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.4%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.3%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.3%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.3%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.3%

- - - 60,000.00 57,248 2,752 30,000.00 28,624 1,376 30,000 28,624 1,376 6.2%

RDF Anaerobic digestion

Diversion of Municipal Waste from landfill via

ADResidue to compostingCapacity of plant

Page 180: Waste management model

180

Energy from Waste Part 1

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

108 109 110 111 112 113 114 115 116 117 118 119

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

- - - - - - - - - - - -

- - - - - - - - - - - -

- - - - - - - - - - - -

- - - - - - - - - - - -

- - - - - - - - - - - -

- - - - - - - - - - - -

150,000 143,121 6,879 103,500 98,753 4,747 - - - - - -

150,000 143,121 6,879 103,500 98,753 4,747 - - - - - -

150,000 143,121 6,879 103,500 98,753 4,747 - - - - - -

150,000 143,121 6,879 103,500 98,753 4,747 - - - - - -

150,000 143,121 6,879 103,500 98,753 4,747 - - - - - -

150,000 143,121 6,879 103,500 98,753 4,747 - - - - - -

150,000 143,121 6,879 103,500 98,753 4,747 - - - - - -

180,000 171,745 8,255 124,200 118,504 5,696 - - - - - -

180,000 171,745 8,255 124,200 118,504 5,696 - - - - - -

180,000 171,745 8,255 124,200 118,504 5,696 - - - - - -

180,000 171,745 8,255 124,200 118,504 5,696 - - - - - -

180,000 171,745 8,255 124,200 118,504 5,696 - - - - - -

180,000 171,745 8,255 124,200 118,504 5,696 - - - - - -

180,000 171,745 8,255 124,200 118,504 5,696 - - - - - -

180,000 171,745 8,255 124,200 118,504 5,696 - - - - - -

180,000 171,745 8,255 124,200 118,504 5,696 - - - - - -

180,000 171,745 8,255 124,200 118,504 5,696 - - - - - -

180,000 171,745 8,255 124,200 118,504 5,696 - - - - - -

180,000 171,745 8,255 124,200 118,504 5,696 - - - - - -

EFW

Throughput of EfW 1Diversion of Municipal Waste from

landfill via EfW 1Throughput of EfW 2

Diversion of Municipal Waste from

landfill via EfW 2

Page 181: Waste management model

181

Energy from Waste Part 2

Base ash To

landfill

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 141 138 139 140

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

Total Municipal

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Waste other

than

Household

Waste

- - - - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - - - -

42,000 40,074 1,926 21,000 20,037 963 21,000 20,037 963 - - - - - - - - 21,000 21,000 20,037 963.07

42,000 40,074 1,926 21,000 20,037 963 21,000 20,037 963 - - - - - - - - - 21,000 21,000 20,037 963.07

42,000 40,074 1,926 21,000 20,037 963 21,000 20,037 963 - - - - - - - - - 21,000 21,000 20,037 963.07

42,000 40,074 1,926 21,000 20,037 963 21,000 20,037 963 - - - - - - - - - 21,000 21,000 20,037 963.07

42,000 40,074 1,926 21,000 20,037 963 21,000 20,037 963 - - - - - - - - - 21,000 21,000 20,037 963.07

42,000 40,074 1,926 21,000 20,037 963 21,000 20,037 963 - - - - - - - - - 21,000 21,000 20,037 963.07

42,000 40,074 1,926 21,000 20,037 963 21,000 20,037 963 - - - - - - - - - 21,000 21,000 20,037 963.07

50,400 48,089 2,311 25,200 24,044 1,156 25,200 24,044 1,156 - - - - - - - - - 25,200 25,200 24,044 1,155.68

50,400 48,089 2,311 25,200 24,044 1,156 25,200 24,044 1,156 - - - - - - - - - 25,200 25,200 24,044 1,155.68

50,400 48,089 2,311 25,200 24,044 1,156 25,200 24,044 1,156 - - - - - - - - - 25,200 25,200 24,044 1,155.68

50,400 48,089 2,311 25,200 24,044 1,156 25,200 24,044 1,156 - - - - - - - - - 25,200 25,200 24,044 1,155.68

50,400 48,089 2,311 25,200 24,044 1,156 25,200 24,044 1,156 - - - - - - - - - 25,200 25,200 24,044 1,155.68

50,400 48,089 2,311 25,200 24,044 1,156 25,200 24,044 1,156 - - - - - - - - - 25,200 25,200 24,044 1,155.68

50,400 48,089 2,311 25,200 24,044 1,156 25,200 24,044 1,156 - - - - - - - - - 25,200 25,200 24,044 1,155.68

50,400 48,089 2,311 25,200 24,044 1,156 25,200 24,044 1,156 - - - - - - - - - 25,200 25,200 24,044 1,155.68

50,400 48,089 2,311 25,200 24,044 1,156 25,200 24,044 1,156 - - - - - - - - - 25,200 25,200 24,044 1,155.68

50,400 48,089 2,311 25,200 24,044 1,156 25,200 24,044 1,156 - - - - - - - - - 25,200 25,200 24,044 1,155.68

50,400 48,089 2,311 25,200 24,044 1,156 25,200 24,044 1,156 - - - - - - - - - 25,200 25,200 24,044 1,155.68

50,400 48,089 2,311 25,200 24,044 1,156 25,200 24,044 1,156 - - - - - - - - - 25,200 25,200 24,044 1,155.68

EFW 1 Base ash to Beneficial

UseEFW 2 Base ash arising

EFW 2 Base ash to landfill

(INACTIVE WASTE)

EFW 2 Base ash to Beneficial

Use Process waste residues put to

beneficial useEFW 1 Base ash arising

EFW 1 Base ash to landfill

(INACTIVE WASTE)

BASE ASH from EFW

Page 182: Waste management model

182

Energy from Waste Part 3

Third party

Waste arising

outside of

contract

Third party

Recovered

outside of

contract

Percentage of

Municipal

Waste stream

that is diverted

by Third Party

Percentage of

Municipal (Contract)

Waste stream

recovered by Energy

Recovery

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (Percentage)

142 143 144 145 146 147 148 149 150 151 152

Total Municipal

Waste

Total Municipal

Waste

Total Municipal

Waste

Total Municipal

Waste

Total Municipal

Waste

Total Municipal

Waste

Contract

Household

Waste

Contract Waste

other than

Household

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract Waste

other than

Household

Waste

Total Municipal

Waste

- - 94,114 45,364 11.5% - - - - - - 0.00%

- - 94,496 45,746 11.4% - - - - - - 0.00%

- - 94,886 46,136 11.3% - - - - - - 0.00%

- - 95,284 46,534 11.2% 60,000 56,608 3,392 30,000 28,304 1,696 7.19%

- - 95,690 46,940 11.0% 60,000 56,623 3,377 30,000 28,312 1,688 7.05%

- - 39,647 27,460 6.4% 60,000 57,116 2,884 30,000 28,558 1,442 6.98%

4,500 - 21,105 21,105 4.9% 210,000 200,369 9,631 133,500 127,378 6,122 30.74%

4,500 - 21,317 21,317 4.9% 210,000 200,369 9,631 133,500 127,378 6,122 30.44%

4,500 - 21,530 21,530 4.9% 210,000 200,369 9,631 133,500 127,378 6,122 30.14%

4,500 - 21,745 21,745 4.9% 210,000 200,369 9,631 133,500 127,378 6,122 29.84%

4,500 - 21,854 21,854 4.9% 210,000 200,369 9,631 133,500 127,378 6,122 29.69%

4,500 - 21,963 21,963 4.9% 210,000 200,369 9,631 133,500 127,378 6,122 29.54%

4,500 - 22,073 22,073 4.9% 210,000 200,369 9,631 133,500 127,378 6,122 29.40%

5,400 - 22,183 22,183 4.9% 240,000 228,994 11,006 154,200 147,128 7,072 35.33%

5,400 - 22,294 22,294 4.9% 240,000 228,993 11,007 154,200 147,128 7,072 35.15%

5,400 - 22,406 22,406 4.9% 240,000 228,993 11,007 154,200 147,128 7,072 34.98%

5,400 - 22,518 22,518 4.9% 240,000 228,993 11,007 154,200 147,128 7,072 34.80%

5,400 - 22,630 22,630 4.9% 240,000 228,994 11,006 154,200 147,128 7,072 34.63%

5,400 - 22,743 22,743 4.9% 240,000 228,994 11,006 154,200 147,128 7,072 34.46%

5,400 - 22,857 22,857 4.9% 240,000 228,993 11,007 154,200 147,128 7,072 34.28%

5,400 - 22,971 22,971 4.9% 240,000 228,994 11,006 154,200 147,128 7,072 34.11%

5,400 - 23,086 23,086 4.9% 240,000 228,994 11,006 154,200 147,128 7,072 33.94%

5,400 - 23,202 23,202 4.9% 240,000 228,993 11,007 154,200 147,128 7,072 33.78%

5,400 - 23,318 23,318 4.9% 240,000 228,993 11,007 154,200 147,128 7,072 33.61%

5,400 - 23,434 23,434 4.9% 240,000 228,994 11,006 154,200 147,128 7,072 33.44%

Fly ash

Fly ash to landfill

(tonnes)

Total throughput of Municipal (Contract) Waste

through Energy Recovery facilities

Diversion of Municipal (Contract) Waste from

landfill via Energy Recovery facilities

Third Party waste

Page 183: Waste management model

183

Recovery Rate and Landfill Calculations Diversion of

Municipal Waste

from landfill Waste to Landfill

Total percentage

of Municipal

(Contract) Waste

stream

recovered

Diversion of

Municipal Waste

from landfill

Total amount

of Waste going

to landfill out of

county (Horton)

Total

percentage of

Waste being

landfilled out

of county

(tonnes) (tonnes) (tonnes) (tonnes) (Percentage) (tonnes) (tonnes) (Percentage) (tonnes) (Percentage) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

153 154 155 156 157 158 159 159 160 161 162 163 164 165 166 167 168 169 170

Total

Municipal

Waste

Contract

Household

Waste

Contract Waste

other than

Household

Waste

Third Party

Waste

Total Municipal

Waste

Total Municipal

Waste

Total Municipal

Waste

Total

Municipal

Waste

Total

Municipal

Waste

Total

Municipal

Waste

Total

Municipal

Waste

Contract

Household

Waste

Contract

Household

Waste Active

waste

Contract

Household In

active Waste

Contract

Waste other

than

Household

Waste

Contract Waste

other than

Household Waste

Active waste

Contract Waste

other than

Household Waste

Inacative waste

Total

Municipal

Waste Active

waste

Total

Municipal

Waste

Inacative

waste

39,158 19,758 287 45,364 9.96% 39,158 46,000 12% 48,750 12% 305,363 287,848 287,848 - 17,515 17,515 - 305,363 -

79,238 56,945 2,797 45,746 19.75% 79,238 46,000 11% 48,750 12% 273,149 257,558 257,558 - 15,591 15,591 - 273,149 -

79,843 57,173 2,783 46,136 19.51% 79,843 46,000 11% 48,750 12% 280,567 264,629 264,629 - 15,938 15,938 - 280,567 -

144,060 117,409 6,366 46,534 34.52% 144,060 - - 48,750 12% 224,533 211,837 211,837 - 12,695 12,695 - 224,533 -

144,689 117,662 6,338 46,940 33.99% 144,689 - - 48,750 11% 232,250 219,178 219,178 - 13,072 13,072 - 232,250 -

145,010 118,701 5,412 27,460 33.73% 145,010 - - 12,188 3% 272,748 259,639 259,639 - 13,109 13,109 - 272,748 -

285,857 253,048 11,704 21,105 65.83% 306,857 - - - - 127,389 121,547 101,510 20,037 5,842 4,879 963 106,389 21,000

286,164 253,144 11,704 21,317 65.25% 307,164 - - - - 131,424 125,396 105,360 20,037 6,027 5,064 963 110,424 21,000

286,474 253,240 11,704 21,530 64.67% 307,474 - - - - 135,500 129,286 109,249 20,037 6,214 5,251 963 114,500 21,000

289,354 255,905 11,704 21,745 64.67% 310,354 - - - - 137,050 130,765 110,728 20,037 6,285 5,322 963 116,050 21,000

289,525 255,967 11,704 21,854 64.39% 310,525 - - - - 139,116 132,736 112,699 20,037 6,380 5,417 963 118,116 21,000

289,696 256,029 11,704 21,963 64.11% 310,696 - - - - 141,193 134,718 114,681 20,037 6,475 5,512 963 120,193 21,000

289,869 256,092 11,704 22,073 63.83% 310,869 - - - - 143,280 136,709 116,672 20,037 6,571 5,608 963 122,280 21,000

313,361 278,525 12,653 22,183 71.79% 338,561 - - - - 117,858 112,453 88,409 24,044 5,405 4,249 1,156 92,658 25,200

313,548 278,601 12,653 22,294 71.47% 338,748 - - - - 119,953 114,452 90,408 24,044 5,501 4,345 1,156 94,753 25,200

313,737 278,678 12,653 22,406 71.16% 338,937 - - - - 122,058 116,460 92,416 24,044 5,598 4,442 1,156 96,858 25,200

313,926 278,755 12,653 22,518 70.85% 339,126 - - - - 124,174 118,479 94,435 24,044 5,695 4,539 1,156 98,974 25,200

314,116 278,833 12,653 22,630 70.54% 339,316 - - - - 126,301 120,508 96,464 24,044 5,792 4,637 1,156 101,101 25,200

314,306 278,911 12,653 22,743 70.23% 339,506 - - - - 128,438 122,548 98,503 24,044 5,890 4,735 1,156 103,238 25,200

314,499 278,989 12,653 22,857 69.93% 339,699 - - - - 130,585 124,596 100,552 24,044 5,989 4,833 1,156 105,385 25,200

314,691 279,068 12,653 22,971 69.62% 339,891 - - - - 132,744 126,656 102,612 24,044 6,088 4,932 1,156 107,544 25,200

314,886 279,147 12,653 23,086 69.32% 340,086 - - - - 134,913 128,726 104,681 24,044 6,187 5,031 1,156 109,713 25,200

315,081 279,226 12,653 23,202 69.01% 340,281 - - - - 137,092 130,805 106,761 24,044 6,287 5,131 1,156 111,892 25,200

315,277 279,306 12,653 23,318 68.71% 340,477 - - - - 139,283 132,896 108,851 24,044 6,388 5,232 1,156 114,083 25,200

315,473 279,386 12,653 23,434 68.41% 340,673 - - - - 141,486 134,997 110,953 24,044 6,488.60 5,333 1,156 116,286 25,200

Total amount of Contract Waste going to landfill

Total Recovery rate

Total Municipal (Contract) recovered Third Party Waste to Landfill

Page 184: Waste management model

184

Void Space Calculations

Percentage of Waste Landfilled

Total void space needed per

annum (m3) to include necessary

inert for engineering

Cumulative total void space needed

(Percentage) (tonnes) (tonnes) (tonnes)

171 172 173 174 175

Total Municipal Waste Total Municipal Waste

Active wasteTotal Municipal Waste Inacative waste Total Municipal Waste Total Municipal Waste

77.6% 367,907 - 404,697.32 404,697

68.1% 329,095 - 362,004.25 766,702

68.6% 338,032 - 371,835.19 1,138,537

53.8% 270,521 - 297,573.33 1,436,110

54.6% 279,819 - 307,801.12 1,743,911

63.4% 328,612 - 361,473.70 2,105,385

29.3% 128,179 14,000 156,397.02 2,261,782

30.0% 133,040 14,000 161,744.52 2,423,526

30.6% 137,952 14,000 167,146.99 2,590,673

30.6% 139,819 14,000 169,201.21 2,759,875

30.9% 142,308 14,000 171,939.25 2,931,814

31.2% 144,811 14,000 174,691.70 3,106,506

31.5% 147,325 14,000 177,457.31 3,283,963

25.8% 111,637 16,800 141,280.21 3,425,243

26.2% 114,160 16,800 144,056.33 3,569,299

26.5% 116,696 16,800 146,845.74 3,716,145

26.8% 119,245 16,800 149,649.84 3,865,795

27.1% 121,808 16,800 152,468.70 4,018,264

27.4% 124,383 16,800 155,301.07 4,173,565

27.8% 126,970 16,800 158,147.03 4,331,712

28.1% 129,571 16,800 161,007.97 4,492,720

28.4% 132,184 16,800 163,882.64 4,656,602

28.7% 134,810 16,800 166,771.13 4,823,374

29.0% 137,450 16,800 169,674.83 4,993,048

29.3% 140,103 16,800 172,593.81 5,165,642

void space required (m3) per annum

Void Space

Page 185: Waste management model

185

Appendix 3: The MBM test mass flow diagrams:

The following flow diagrams depict the results from the testing of the MBM for eight different configurations. The explanation is

contained with Section 5.7.2 as well as the Option 1 mass flow diagram.

Page 186: Waste management model

186

Page 187: Waste management model

187

Page 188: Waste management model

188

Page 189: Waste management model

189

Page 190: Waste management model

190

Page 191: Waste management model

191

Page 192: Waste management model

192

Page 193: Waste management model

193

Appendix 4: The MBM USER MANUAL

Page 194: Waste management model

194

THE DETAILED CONSTRUCTION, CALCULATIONS AND ASSUMPTIONS USED IN

DEVELOPING THE NEW MASS BALANCE MODEL (MBM)

It is the aim to construct a walk through manual for anybody that wishes to use this model. The

manual will take each of the six sections and present an overview of that section and then describe

all of the calculations within that section and links to any other section.

For each section description there will be an extract from the model shown as a table that contains

the cells within the excel model for that section, there will be a top row that is made up of letters, this

is the column identification letter. The letter relates to the column label in the excel spreadsheet. In

the left hand column is a series of number, these in a similar way, relate to the identification numbers

of each row, again these are related to the number in the excel spreadsheet.

An example of the first three columns of the model is given below as a guide to explanation;

The example shows the reader that D6 would be the identification code for the cell “year 2001/2”,

when looking at the spreadsheet on the computer; the code would be the same as the table here.

The reader will also notice the use of shading, C-D4 and C-D5 are descriptions that are used within

the model and are shaded to visually separate them from all the other rows; ease of reading. C-D8 is

also shaded, this is a row that is a target year and similarly this is used to visually highlight this row,

there are three such rows in the table, which will be explained later in the chapter.

From this point forward all reference to columns and rows will be by row 4 “Column number” and

column 2 “Row Number”, therefore C4 would actually be read as “Column 1, row 5” or C1 R5. The

reason for this is that when printed the model does not show the lettered columns or the row

numbers, and as such a way of identifying each cell is required for the model once printed, and also

for use in identifying the summary of each equation in each column (where appropriate). The

following will now describe each of the six sections of the model in the order that they are viewed

when opening the model:

Model timescales

A B C D

1 Row Number

2 1 Column heading Financial Year

3 2 Units Years

4 3 Column Number 1

5 4 Summary of equation in column

6 5 Base Year 2001/2

7 6 2002/3

8 7 2003/4

9 8 2004/5

Page 195: Waste management model

195

Columns 1 and 1a consists entirely of input cells, these cells will be used to identify the year, and the

model currently expresses a financial year and a contract year. These can be quite easily changed to

suit the needs of the user, but each year, whether the base year is 2001/2 or 2022/23 will have to be

manually typed.

The reason for both is really quite simple, by showing the financial year it tells you in real time the

year you will be in, but by showing the contract year it makes identification of that year easier. For

ease of use in the model, the first 6 columns have been frozen, i.e. are permanently on display, so

that when scrolling along the model the user is always aware of what year and what MW and HW

tonnages they are looking reading information from.

Waste and Waste Growth.

The second section of the model looks at the relationship between waste arising and waste growth,

the base year figures for column 2, Household Waste and column 3, Municipal waste is actual data

and is therefore an input cell. The rest of the column is made up of simple equations see paragraph

4.5.4.

Row Number

1 Column heading Financial Year Contract Year

2 Units Years Years

3 Column Number 1 1a

4 Summary of equation in column

5 Base Year 2001/2 0

6 2002/3 1

7 2003/4 2

Row Number

1 Column heading Financial Year Contract Year Waste growth per

year Household

Waste Municipal Waste

2 Units Years Years (Percentage) (tonnes) (tonnes)

3 Column Number 1 1a 1b 2 3

4 Summary of equation

361,507 378,000

5 Base Year 2001/2 0 2.0% 368,737 385,560

6 2002/3 1 2.0% 376,112 393,271

7 2003/4 2 2.0% 383,634 401,137

8 2004/5 3 2.0% 391,307 409,159

Page 196: Waste management model

196

There is a need to distinguish between HW and MW because in calculating Recycling rates only HW is

used. Essentially Household Waste comprises 90% of the Municipal Waste, but in certain areas, for

example East Sussex and Brighton & Hove this rises to nearer 95%.

A waste growth model is used within the model to calculate the number of tonnes arising of Municipal

and Household waste. The waste for the base year is inputted to cells C2R5 and D2R5 the waste

growth model is cut into column 3 (paste special as a figure) and the equations then calculate the

waste for each year for columns 2 & 3. This calculated in this model and as such would not need to

be modelled elsewhere.

The table below shows firstly in bold, in C2R4, the summary of the equation as shown in the model;

this is then shown as a description related to the column and row numbers for the first year. Row 6

shows what the numerical equation would actually be. Whereas row 7 shows the equation as it

actually is on the model. In the model the rows following 7 use exactly the same equation as in row 7

but with the numbering moving down with each row, e.g. row 8 would use F12 & E13 and row 9

would use F13 & E14. This is achieved in the model by dragging the equation in row 6 (in the model

this is an actual equation) down to the bottom of the table by doing this Excel automatically changes

the numbers.

The user also has the option of manually inputting the data by just typing in each year’s figures. This

is far more time consuming and doesn’t allow for an easy comparison of different waste growth

scenarios.

Row Number

1 Column heading

Contract Year

Waste growth per year

Household Waste Municipal Waste

2 Units Years (Percentage) (tonnes) (tonnes)

3 Column Number

1a 1b 2 3

4 Summary of

equation

= 2+(2*1b)) which for year one =C2R5+(C2R5*C1bR6)

= 3+(3*1b)) which for year one =C3R5+(C3R5*C1bR6)

5 Base Year 0 2.0% 368,737 385,560

6 1 2.0% = 368,737 + (368,737*2.0%) = 385,560+ (385,560*2.0%)

7 2 2.0% =F11+(F11*E12) =G12+(G12*E13)

Page 197: Waste management model

197

Targets

This section is perhaps one of the most important as it relates to directly what the user wants to

obtain from the model, the targets that are to be set in terms of recycling and recovery. There are

ten columns in this section that all relate to either the targets set by the user or the modelled targets

attained by the assumptions in sizing the facilities and/or the assumptions upon which the facilities

efficiencies are based.

Columns 4,5,7,8,9 and 10 are the results that are calculated in the model; these are therefore

calculated cells and should not be altered. They are directly linked to the summary cells at each of

the three following sections.

Columns 6 and 11 are input columns, these are for the user to set the performance targets that they

wish to achieve and then use columns 5 and 10 to see if the targets set have been met.

There are also two more columns in this section they are; Columns 11a and 11b and they are

calculated in order to summarise and show the total facilities capacity and the actual amount of waste

that is not treated by all the waste management facilities. This latter column 11b, when added to

column 11a might (especially after the implementation of an EfW) be greater than the total MW

arising (column 3). The reason being that each facility has an efficiency rating and for example, MRF’s

are normally 80-85% efficient (Project Integra), meaning there will therefore be a residue; if this

residue is transported to an EfW and burnt it will be used as part of the capacity of that plant and

therefore treated twice. This is not a true reflection on the total amount of waste being treated by all

the facilities, because less waste is actually going through the facilities, as some is double counted.

Row Number

1 Column heading

Household Waste,

Recycling

Household Waste,

Recycling

Household Waste,

Recycling Targets in Contract

Municipal Waste, Energy

Recovery (EFW)

Municipal Waste, Energy

Recovery (EFW)

Municipal Waste, Total

Recovery

Municipal Waste, Total

Recovery

Municipal Waste,

Recovery Targets in Contract

2 Units (tonnes) (Percentage

) (Percentage) (tonnes)

(Percentage)

(tonnes) (Percentage) (Percentage

)

3 Column Number

4 5 6 7 8 9 10 11

4 Summar

y of equation

(=34) (=4/2) (=47) (=7/3) (=4+7) (=9/3)

5 Base Year

6 1 39,158 10.4% 26,250 6.7% 65,408 16.6%

7 2 76,936 20.1% 20% 26,250 6.5% 103,186 25.7%

8 3 79,843 20.4% 20% 26,250 6.7% 106,093 27.1%

9 4 110,210 27.6% 25% 59,250 14.8% 169,460 42.5% 40%

Page 198: Waste management model

198

Recycling and composting

The fourth stage of the model is used to calculate the recycling rate needed to be achieved, by using

different recycling methods. As a result this section has been split into four parts:

Material Recycling Facilities (MRFs);

Composting facilities.

Bring Banks;

Household Waste Recycling Sites (HWRS) and;

Each type of recycling has its own characteristics, which have been described on a facility-by-facility

basis in the previous chapter; the following will explain how the waste flows through each of the

facilities.

Material Recycling Facilities (MRFs)

The section consists of 13 columns, eight of which relate to individual facilities, the last five acting as

summary columns. In the table below, an example of a 40,000 tonne per annum (tpa) MRF is given

in column 12, normally a high-tech MRF will enable 85% of the waste delivered to that facility to be

recycled (Juniper 2000, Project Integra). As such the efficiency for a MRF has been set at 85% as

shown in columns 13,15,17& 19. The columns 12, 14, 16 & 18 comprise of input cells and the

throughput capacity of a MRF can be entered into one cell, dragged down to simulate that tonnage

over each year. By looking to the future and predicting that that 40,000 tpa MRF would need to be

increased in capacity in later years is not a problem as the increased capacity can be entered into one

of the lower cells for the specific year.

Row Number

1 Column heading

MRF 1 through put

MRF 1 Diversion of Household Waste stream - 15% residue goes to incinerator

MRF 2 throughput

MRF 2 Diversion of Household Waste stream - 15% residue goes to incinerator

Total MRF throughput

Total diversion of Household Waste from landfill via MRF's

Total residues to EFW from MRF's

Diversion of Household Waste to facilities i.e. throughput of MRFs

Diversion of dry recyclables from landfill through MRF's

2 Units (tonnes) (tonnes) (tonnes)

(tonnes) (tonnes) (tonnes) (tonnes) (Percentage) (Percentage)

3 Column Number

12 13 14 15 20 21 22 23 24

4 Summary of equation (efficiency

85% 85% (=12+14+ 16+18)

(=13+15+ 17+19)

(=20-21) (=20/2) (=21/2)

5 Base Year

6 1 - - - - - - - 0.0%

7 2 40,000 34,000 - - 40,000 34,000 - 10.4% 8.9%

8 3 40,000 34,000 - - 40,000 34,000 - 10.2% 8.7%

9 4 40,000 34,000 15,000 12,750 55,000 46,750 - 13.8% 11.7%

Page 199: Waste management model

199

Columns 13,15, 17 & 19 (17& 19 are not shown above) as described earlier used an 85%

assumption, this 85% is an input cell that relates to all the cells below and the preceding column,

thus, in the example given, cell C12R7 indicates a MRF with a capacity of 40,000tpa, the cell C13R7

then uses the calculation:

C12R7*$C13$R4 (note the $ in equation mean fixed column id and row id),

i.e., 40,000 * 85% = 34,000tpa.

In the model the actual equation for C13R7 is =V10*$W$7

In the model there are a maximum of four possible MRFs, each has the ability to have a different

efficiency, or to not be used at all. The author has chosen to use four small sized MRFs for this

model, two of which are not shown in the above table for ease of reading.

Columns 20 indicates the total capacity of the MRFs, this is a simple calculation that adds the total

capacity for each MRF (columns 12+14+16+18). This resultant number indicates the total throughput

of the MRFs. Column 21 indicates the total amount of recycling undertaken by the total capacity of

the MRFs by, again a simple equation, adding the columns 13+15+17+19 together.

Column 22 shows whether any the residues from the MRFs are delivered to the EFW. An assumption

has been made that when an EFW is operational, all residue from the MRFs will be delivered to the

EFW. In the model this is undertaken by using a complex “IF” equation;

=IF ($BP10+$BR10=0,0,AF10-AG10) where:

BP10 has the column title: Throughput of EfW 1;

BR10 has the column title: Throughput of EfW 2;

AF10 has the column title: Total MRF throughput; and

AG10 has the column title: Total diversion of Household Waste from landfill via MRF's

There is therefore a possibility of two different answers, one of zero, if there is no operational EFW,

or two, the sum of the residues from the MRFs. There could be a case to add in another variable, for

example, if the EFW capacity were smaller than the total of the residues from the MRFs. If this were

the case, the following equation could replace the current equation (it is the authors view that this

scenario would be very rare and as such will use the equation in Para 4.7.2.9):

=IF($BP10+$BR10=0,0,IF($BP10+$BR10=>(AF10-AG10),(AF10-AG10)),IF($BP10+$BR10<(AF10-

AG10), ($BP10+$BR10)) where:

Page 200: Waste management model

200

BP10 has the column title: Throughput of EfW 1;

BR10 has the column title: Throughput of EfW 2;

AF10 has the column title: Total MRF throughput; and

AG10 has the column title: Total diversion of Household Waste from landfill via MRF's

The new equation effectively asks three questions and give three possible answers,

part one, sees if the EFW is operational, if it isn’t then a zero will be placed in the cell,

part two sees if the capacity of the EFW is equal to or greater than the sum of the residues from the

MRF, if the answer is yes, the sum of the residues from the MRF is inputted into the cell, and

part three sees if the capacity of the EFW is less than the sum of the residues from the MRF, if this

were the case, the total capacity of the EFWs would be inputted into the cell.

Column 23 consists of calculation cells that indicate the percentage of the HW that is delivered to the

MRFs, a simple equation, the sum of column 20 divided by column 2 (total HW arising). Column 24

consists again of calculation cells, this column show the contribution towards the recycling rate made

by the MRFs, the equation is the sum of column 21 divided by column 2 (total HW arising).

Composting facilities

Composting has been identified in chapter 3 of being of various technologies, enclosed, open and on

farm. In the model the author has chosen to use the example of both an enclosed compost facility

and an on-farm facility. This reflects current legislation; in that green waste collected form

households should be composted in an enclosed facility, whereas green waste from HWRS can be

composted in open-air facilities. The composting section of the model is made up of 4 columns; the

first two columns are for the facilities, column 27 for the enclosed composter and 28 for the on-farm

facilities.

Row Number

1 Column heading Enclosed Composter On-farm

Total diversion of Household Waste from landfill through composters

Percentage of Household Waste diverted by composting

2 Units (tonnes) (Percentage) (tonnes) (Percentage)

3 Column Number 27 28 29 30

4 Summary of equation (efficiency)

95% (=27+28) (=29/2)

5 Base Year

6 1 5,000 5,000 1.3%

7 2 15,000 15,000 3.9%

8 3 25,650 5,000 30,650 7.8%

9 4 25,650 5,000 30,650 7.7%

Page 201: Waste management model

201

The Enclosed Composter is 95% efficient, as such there needs to be an equation to calculate this,

column 27 uses the efficiency rate that should be hard typed by the user into cell C27R4. This

efficiency rate is then used in the calculation of cell C27R8;

=(27000*$AL$7) which equals 25,650 as shown in C27R8

The above equation has two variables, the first being the size of the composter, in the case of this

example this has been set as 27,000tpa, if the user wishes to change this then it is simple to just

change the number in cell C27R8 and then drag to the bottom of the column. The second variable is

the efficiency, as described in paragraph 4.7.3.3 this can be changed in cell C27R4 (in the equation

$AL$7 relates to C27R4 in the model.

Column 28 is a simple hard type column where the user inputs the size of on-farm capacity to be

used, in the above example the capacity varies between 5,000tpa and 15,000tpa, this is to take

account for a greater need of composting in year 3 when recycling targets are higher and before the

enclosed composter is built.

The purpose of column 29 is to show the combined capacity of the composting facilities, the equation

is just a simple addition of columns 27 & 28. Column 29 then, in a similar manner to the MRF, works

out the contribution made by the combined capacity of the composters to the recycling rate. This is

achieved by dividing column 29 by column 2. The above example shows that with a composting

production of 30,650tpa in year 4, the contribution to achieving the 30% recycling rate is 7.7%

Bring Banks

There are two types of bring banks currently in operation within the area, these are banks operated

by the WCAs at dedicated sites around their individual areas, and banks placed in Household waste

recycling sites (HWRS's) by the WDA.

Column 31 shows the banks provided by the WCAs; in the example above the tonnage collected in

the base year is the actual collected, while year one is the tonnage expected after a growth of 4%,

Row Number

1 Column heading Household Waste diverted by use of bring banks

HWRS Bring banks Percentage of Household Waste stream that is diverted by Bring banks

2 Units (tonnes) (tonnes) (Percentage)

3 Column Number 31 31a 32

4 Summary of equation (efficiency)

(=31/2)

5 Base Year 14,749 3,798 5.03%

6 1 15,044 3,874 5.03%

7 2 15,044 4,604 5.12%

8 3 3,913 4,696 2.20%

9 4 3,991 7,184 2.80%

Page 202: Waste management model

202

this is higher than the actual growth rate of waste for the reason that WCAs would have to increase

recycling activities at a greater rate than waste growth to achieve higher recycling targets. It is the

author’s opinion that a 4% increase may look like a small increase, but the physical aspects of

actually setting up new bring sites would be prohibitive in increasing this to a higher increase.

Years 2 onwards shows a much lower figure for bring recycling than for either the base year or year

1, mainly because a substantial amount of bring bank collected waste would be delivered to the MRF

instead of directly to market (as is currently the case). It is the authors view that a small percentage

of bring bank material will still go direct to market and the prudent view is made in the calculation of

cell C31R7 that 1% of the total HW arising will be bring banks delivered material direct to market.

This is shown by equation extracted from the model below;

` =F11*0.01, where F11 is the total HW arising.

As can be seen from the above paragraph, an assumption has been made by the author about the

recycling activities under taken by the WCAs in utilising bring banks to achieve recycling targets, in

the same way, the performance levels of the bring bank recycling have been estimated.

Aside from this model, the author has used a complex model to determine the recycling levels that

would be required at the HWRSs to achieve the recycling rates for the whole area, once the WCAs

have achieved their individual recycling targets. This model need not be in this report, suffice to say

that its results have been used to calculate the percentage required for bring bank recycling.

There have been four different percentages used to calculate the recycling undertaken by WDA bring

banks, these are;

Years 2 & 3 2% of the 20% HWRS recycling rate per annum

Years 4 – 6 2% of the 30% HWRS recycling rate per annum

Years 7 – 13 2% of the 40% HWRS recycling rate per annum

Years 14 onwards 2% of the 50% HWRS recycling rate per annum

Table XX Bring banks assumptions

The table shows that the percentage rate of the recycling level for the bring banks stays the same,

but that the total recycling rate increases, as the recycling rate as a whole for the HWRS increases,

the tonnage of recycled material collected by the bring banks also increases. This can be seen in

column 31a.

The equation that is used in column C31aR7 is the following;

= (123,356 *0.2)*0.2

Page 203: Waste management model

203

Whereas the equation in C31aR9 is;

= (125,835 *0.3)*0.2

This reflects paragraph 4.7.4.8 with the overall recycling rate increasing from 0.2 to 0.3.

The amount of material collected by the bring banks will also increase due to the increase in waste

arising at the HWRS, this may be a high level assumption that as waste grows, the amount of

recycling achieved by one particular method increases proportionally.

The summary column (column 32) for this section is, again, a simple addition equation, adding the

sum of columns 31 & 31a, the difference between previous summary columns is that total capacity

tonnage is not shown and the equation perform a two part role, firstly adding the totals and then

dividing by the total amount of HW to get the contribution made by bring banks to the overall

recycling rate. This is done for cell C32R7 by the following equation:]

= (AQ11+AR11)/F11 where:

AQ11 is column 31 (Household Waste recycled by WCA bring banks),

AR11 is column 31a (HWRS Bring banks), and

F11 is column 2 (total HW arising)

The equation is replicated in the rest of the column

Third party recycling

The concept of third party recycling is not an unusual one in the arena of councils, normally the

recycling is undertaken by charities, for example OXFAM, the Salvation Army and the Scout

Association, but there is another concept of third party recycling that can occur. For example, in

Brighton the community recycling group MAGPIE collect recyclables, for the each tonne they collect

and recycle, they receive a recycling credit, as described in chapters 1 & 2.

The assumption made is that all third party recycling is waste that has been recycled by some body

other than the WDA, which the WDA authorises and then pays recycling credits to.

In the case of this model, the author has added another variable, the case of the WCA delivering

waste direct to market under their own scheme and as such that waste not becoming part of the

contract waste. For example, if within the ESCC area, Wealden WCA decided to take all the recycling

that was collected by them by way of kerbside and bring bank schemes and delivered direct to

market, they would then receive a recycling credit for that tonnage.

Page 204: Waste management model

204

The author has used the above example as the contribution to the third party waste, therefore by

using Wealden DC’s target of 33% recycling there is a substantial amount of third party waste arising

that is recycled.

The section on third party waste only contains 2 columns, with column 32a being the total third party

recycling, the use could add further columns to break down the total into constituent parts, the

author is only using the Wealden data and as such, for this example, will only use one column, adding

other will also complicate the column numbering system.

Row Number

1 Column heading Third party recycling Percentage of Household Waste stream that is diverted by Third Party

2 Units (tonnes) (Percentage)

3 Column Number 32a 32b

4 Summary of equation (efficiency)

(=32a/2)

5 Base Year

6 1 19,114 5.08%

7 2 19,496 5.08%

8 3 19,886 5.08%

9 4 20,284 5.08%

The above table shows that Wealden DC diverting its recyclable material away from the facilities

within the model means that a recycling rate of just over 5% is achieved. If this were to occur in an

operational situation would be classed as non-contract waste.

The equation for C32aR6 is a based upon a separate model that calculates the predicted waste

arisings for Wealden DC in that particular year, this model uses the same waste growth figures as

given in paragraph 4.5.6.2, it is assumed that waste growth will be even overall of the area. In reality

this probably will not be the case and as such it will vary according to numerous different reasons

including House building, economics and waste minimisation activities.

Recycling rate

The recycling rate section is the culmination of all of the previous sections within the Recycling and

Composting section. The purpose is to summarise the total amount of recycling achieved and then

calculate the recycling rate.

This achieved by using two columns; one which is an addition cell, adding all of the summary totals

from the previous section and, two, the calculated recycling rate.

Page 205: Waste management model

205

Row Number

1 Column heading Diversion of Waste from

landfill via recycling Household Waste stream

recycled

2 Units (tonnes) (Percentage)

3 Column Number 33 34

4 Summary of equation

(efficiency) (=21+29+31+31a+32a) (=33/2)

5 Base Year

6 1 43,032 11.4%

7 2 88,144 23.0%

8 3 93,145 23.8%

9 4 108,860 27.3%

The equation in C33R4 shows there are six variables contributing to the total recycling rate, where;

Column 21 is the Total diversion of Household Waste from landfill via MRF's,

Column 29 is the Total diversion of Household Waste from landfill through composters,

Column 31 is the Household Waste recycled by WCA bring banks,

Column 31a is the HWRS Bring banks,

Column 32a is the Third party recycling, and

Column 36a is the Recycling undertaken at the RDF plant (see section 4.8)

The total of these six columns gives the predicted recycling achieved with the B & HCC and ESCC

area for that particular year.

This total recycled tonnage is then divided by the total household waste arising; in column 2, and the

subsequent percentage is the predicted recycling rate for that year. The model takes this percentage

and automatically replicates it in column 5; it can then be compared by the user to column 6 to see if

the recycling target for that year has been achieved.

If the recycling rate in column 5 is not what is required, the user should look at ways of increasing,

or decreasing the capacities and or deemed assumptions to gain the desired levels.

The author has taken the view in the model that each facility should have a fixed capacity from the

outset that can only be increased, therefore if a recycling rate of 33% is required in year 25, the

facility should be large enough to recycle that tonnage from the date of the move up to that target, in

the case of this example that would be year 14 when the target went from 30% to 33%. This means

that in the years preceding year 25 the recycling rate will be higher than 33% (unless there is a

decrease in waste arsing).

It is also acknowledged that a simple yes/no column could be developed to indicate in what years the

targets are achieved. This can be for the future.

Page 206: Waste management model

206

Section 5 Energy Recovery

The section in the model relating to energy recovery is probably one of the most contentious issues in

the model, not in terms of the way the model works, but in terms of public perception, this has been

discussed in chapter 4 and as such need not be elaborated further here.

There are three commercially proven types of Energy Recovery (excluding landfill gas reclamation,

which does not contribute towards Recovery Targets [Guidance on municipal waste management

strategies]) Refuse Derived Fuel production, Anaerobic Digestion, and Energy from Waste

(Incineration). The latter being the most controversial.

Refuse Derived Fuel production (RDF)

ESCC currently has an operational RDF plant in the east of the county, if the user were looking at

another county or area, this may not be one of the favoured technologies, as it is seen in some

quarters as being outdated, and too inefficient to be useful in achieving recovery targets.

The section of the model dedicated to RDF is four columns, RDF is a relatively simple process in that

waste is shredded post delivery & metals are extracted by an eddy current and overband separator.

The plant currently recycles approximately 2,000 tpa of metals. The remaining waste is then

processed through the RDF plant to produce pellets; in this part of process there is vapour loss and

the production of a small amount of electricity.

Row Number

1 Column heading Capacity of plant Energy recovery by

RDF Metal recycling by

RDF Percentage of Municipal Waste

Energy Recovery by RDF

2 Units (tonnes) (tonnes) (tonnes) (Percentage)

3 Column Number 35 36 36a 37

4 Summary of equation

(efficiency) 32.05% 1.997% (=36/3)

5 Base Year 75,000 26,250 6.94%

6 1 75,000 24,039 1,498 6.11%

7 2 75,000 24,039 1,498 5.99%

8 3 75,000 24,039 1,498 5.88%

9 4 75,000 24,039 1,498 5.76%

In the model, column 35 is the input column where the user hard types the capacity of the plant. In

this example, the author has used to capacity off the current ESCC RDF plant.

Column 36 is the calculation column for the energy recovery; cell C36R4 is the efficiency of the plant.

This again, is from the current performance of the plant and is used in column 36 in the equation:

=BG10*BH$7 where:

BG10 is column 35; and

BH$7 is efficiency of the plant (32.05%)

Page 207: Waste management model

207

The calculation of the metals recycled by the plant is made in column 36a, in the same way as for

column 36. The main difference is the efficiency, or to be accurate, the calculation of the tonnes

recycled, in the case of the metals it is 1.997% as indicated in C36aR4. The equation is the same as

for column 36

The final column of the section is the percentage, by the RDF process, towards the Energy recovery

target. This is slightly different to the calculation of the Recycling Target because up to 2015/16 the

Recovery target is measured against the Municipal waste a\risings, after that time it is measured

against the Household waste arisings [A way with Waste 1998]. In the case of RDF the facility is due

to close in 2007/8 [ESCC], and as such will not be affected by the change to HW later in the time

frame, but the recovery that it does contribute has to be calculated against the MW arisings.

In calculating the recovery rate the following calculation is used:

=BH10/G10 where:

BH10 is the total of column 36; and

G10 is the total MW arising.

The recovery rate that the RDF plant contributes is between 6.11% and 1.4%

Anaerobic Digestion (AD)

The AD plant is one that can vary a great deal in its efficiency; it is entirely dependant on the input to

the facility. If a good quality feed stock is used the production of recyclable material and energy will

be high, if a mixed MSW fraction is used the resultant biodegraded product will be sufficient only for

landfill cover and non-compost uses [composting association]

In the case of this model, the author has chosen to use a mixed MSW fraction for the input, reflecting

the current situation that hardly any of the area has separate green garden, wood or food collection.

The size of the plant to make it economically viable is such that there would not be enough

biodegradable waste separated from the household stream using current projections (see chapter 5)

The extract from the model above shows that there are 3 efficiencies that need to be looked at, these

have been explained in chapter 3, but for the model they use exactly the same equation:

=BL13*BM$7 where

BL13 is the capacity of the plant (C37a); and

BM$7 is the efficiency, in the case of the above equation this relates to C37b (this part of the

equation will also relate to C37c & C37d.)

Page 208: Waste management model

208

Once these different fractions of the waste have been calculated a further calculation is required to

show what is going directly to landfill, this is shown in C37e. The equation is a simplistic (=C37a-

(C37b +C37c+C37d)). The total of this equation can be used to calculate the total diversion from

landfill, column C37f (C37e/C37a), this is required because by looking at C37g the user will see that

the calculated energy recovery is very low. Whereas the facility is good at diverting waste from

landfill, which is the one of the main pressures facing councils.

Energy from Waste (EFW)

The EFW section of the model is very similar to that of the AD, the main difference being the

efficiencies. In the case of the EFW, the recovery of energy is very high at 67%, where recycling is

possible this normally accounts for 2% of the inputs, the remainder is base ash 28% (which can

reused or put to beneficial use) and fly ash (3%), which has to be disposed of in special waste landfill

sites. The exert from the model below shows the cells required for one EFW, in the model this section

is repeated so that two EFWs’ can be used if required.

The exert uses very similar equations to those in the AD section, in this example the author has used

an EFW of the size 100,000tpa, this enable all of the columns preceding it to be understandable in

relation to the efficiencies. Once the calculations have been made for each of the EFWs’ there is a

summary section, this is replicated below and shows that some of the base ash is used for beneficial

use and some is sent direct to landfill. The percentage split on this would be dependent upon market

conditions at the time of operation. The author has used a 60:40 split to show the difference in

tonnages.

Row Number

Column heading Throughput of

EfW 1

Diversion of Municipal Waste from landfill via

EfW 1

Metal put to beneficial use

Total Base ash arising

Fly ash arising

1 Units (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

2 Column Number 38 39 39a 39b 39c

3 Summary of equation

(efficiency) 69% 2% 26% 3%

12 7 100,000 69,000 2,000 26,000 3,000

13 8 100,000 69,000 2,000 26,000 3,000

14 9 100,000 69,000 2,000 26,000 3,000

15 10 100,000 69,000 2,000 26,000 3,000

Row Number

1 Column heading

Total Throughput

of EFWs

Total diversion of Waste from

landfill via EFWs

Total Metal put to

beneficial use

Total Base ash arising

Base ash put to Beneficial

use

Base ash sent to landfill

Fly ash arising

Energy Recovery by

EFW

2 Units (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (Percentage)

3 Column Number

42 42a 42 43 43a 43b 43c 44

4 Summary of

equation (efficiency)

(=38 + 40) (=39 + 41) (=39a + 41a) (=39b +

41b) 60% 40%

(=39c + 41c)

(=42/3)

17 12 100,000 69,000 2,000 28,000 16,800 11,200 3,000 15.27%

18 13 100,000 69,000 2,000 28,000 16,800 11,200 3,000 15.19%

19 14 165,000 113,200 3,300 46,200 27,720 18,480 4,950 24.80%

20 15 165,000 113,200 3,300 46,200 27,720 18,480 4,950 24.68%

Page 209: Waste management model

209

The above extract shows the years 12 –15, with year 14 being a target year. The author has used the

model to show what might happen if two facilities were to be provided at different times, this would

be a scenario that might occur to enable a council to move from the 45% target to the 67% target.

The user can see that as a result of the second facility, the energy recovery by the EFW jumps from

15% to 25%, a very significant increase.

Summary of Energy Recovery

The three previous sections have shown how the energy recovery is achieved under this particular

solution, the model has three columns that firstly calculate the total capacity of all the energy

recovery facilities, and secondly the total energy recovery achieved by all of the facilities.

The energy recovery facilities, over the twenty five year period, contribute between 6.11% recovery

at its lowest in 2002/3 and 35.98% at its highest in 2015/16. When these figures are combined with

the performance figures from the recycling section, a total Recovery rate can be calculated.

Calculation of the Recovery Rate

The recovery rate is calculated by adding the total recycled materials (column 33) and the total

energy recovered (column 43) and dividing by either the total Household waste arising (column 3) or

the Total Municipal waste arising (Column 4) (The principal in terms of which to calculate against is

the same as that for energy recovery).

Row Number

1 Column heading Total Municipal (Contract) recovered Total percentage of Municipal

(Contract) Waste stream recovered

2 Units (tonnes) (Percentage)

3 Column Number 48 49

4 Summary of equation

(efficiency) (=33+46) (=48/3 or 4)

5 Base Year

6 1 68,569 17.44%

7 2 113,681 28.34%

8 3 118,682 29.01%

9 4 150,547 36.07%

The results of this column are transferred to column 10, where a comparison of the estimated

Recovery Rate and the Target Recovery Rate can be made.

If the Recovery Rate in column 10 is not what is required, the user should look at ways of increasing,

or decreasing the capacities and or deemed assumptions to gain the desired levels.

Section 6 Beneficial Use and diversion from landfill

Page 210: Waste management model

210

The beneficial use and diversion from landfill section is a small section (columns 50-52) that

calculates the total amount of waste diverted away from landfill. This is calculated by adding the total

number of tonnes Recovered to the amount of waste put to beneficial use from the AD and EFW

facilities.

The total beneficial use is calculated in column 51, where amount of waste put to beneficial use from

the AD and EFW facilities is added together

The equation in column 51 then adds that tonnage to that as a result of column 48 to give a cell

value that is a useful guide to the total impact of the solution in that year; i.e. the total diversion from

landfill.

There are no targets for diverting waste from landfill, but the more that is achieved the less reliant

councils need be on an ever diminishing disposal route.

Section 7 Landfill

The section on landfill is really a summary of all that is left within the waste stream; it is also a check

to make sure all the number add up. There are seven columns starting with C53, which is a

calculation of the total number of tonnes of waste requiring landfill (including special waste from the

EFW). This is a very simple calculation, total MW minus C51 (total diversion from landfill).

The total percentage of the MW arising requiring landfill is an indication of the progress made in

diverting away from landfill. This is the reverse equation of C52, and again, is useful for visual aid

more than anything else.

Row Number

1 Column heading

Total Landfill capacity required

Percentage of Waste Landfilled

Void space required (m3) per annum

Total void space needed per

annum (m3) to include necessary

inert for engineering

Cumulative total void

space needed

Void identified within area and

subsequently used also showing shortfall

of void within area

Safety Check

2 Units (tonnes) (Percentage) (tonnes) (tonnes) (tonnes)

3 Column Number

53 54 55 56 57 58 59

4 Summary

of equation (efficiency)

(=53/3) (=53/0.83) (=55*1.1) (=56+55) (58-57)

5 Base Year 1,900,000

6 1 324,702 82.6% 391,207 430,328 430,328 1,469,672 OK

7 2 287,455 71.7% 346,332 380,965 811,292 1,088,708 OK

8 3 290,477 71.0% 349,973 384,970 1,196,262 703,738 OK

9 4 181,346 43.5% 218,489 240,338 1,436,600 463,400 OK

Page 211: Waste management model

211

Once the total number of tonnes requiring landfill has been identified, the total landfill void required

for the waste needs to be calculated. This is done by two different calculations, firstly by calculating

the density off MW and secondly, calculating the void required for engineering works, to then give an

overall void capacity for the waste.

Page 212: Waste management model

212

Appendix 5: RS1 Calculations sheet formulas

The following 21 sheets are a screen shot of the equations written to enable the MBM to work

Page 213: Waste management model

213

RS1 formulas for Calculation sheet

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

='Summary sheet'!AX8+1 =C7+1 =D7+1 =E7+1 =F7+1 =G7+1

Financial

Year

Cont

ract

Year

Total Municipal Waste

throughputContract Household Waste Contract Waste other than Household Waste Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste

2002/3 1 ='Input sheet'!D11 =C11*('Summary sheet'!$M10/'Summary sheet'!$F10) =C11*('Summary sheet'!$N10/'Summary sheet'!$L10) =C11*$F$10 =F11*('Summary sheet'!$M10/'Summary sheet'!$F10) =F11*('Summary sheet'!$N10/'Summary sheet'!$L10)

2003/4 2 ='Input sheet'!D12 =C12*('Summary sheet'!$M11/'Summary sheet'!$L11) =C12*('Summary sheet'!$N11/'Summary sheet'!$L11) =C12*$F$10 =F12*('Summary sheet'!$M11/'Summary sheet'!$L11) =F12*('Summary sheet'!$N11/'Summary sheet'!$L11)

2004/5 3 ='Input sheet'!D13 =C13*('Summary sheet'!$M12/'Summary sheet'!$L12) =C13*('Summary sheet'!$N12/'Summary sheet'!$L12) =C13*$F$10 =F13*('Summary sheet'!$M12/'Summary sheet'!$L12) =F13*('Summary sheet'!$N12/'Summary sheet'!$L12)

2005/6 4 ='Input sheet'!D14 =C14*('Summary sheet'!$M13/'Summary sheet'!$L13) =C14*('Summary sheet'!$N13/'Summary sheet'!$L13) =C14*$F$10 =F14*('Summary sheet'!$M13/'Summary sheet'!$L13) =F14*('Summary sheet'!$N13/'Summary sheet'!$L13)

2006/7 5 ='Input sheet'!D15 =C15*('Summary sheet'!$M14/'Summary sheet'!$L14) =C15*('Summary sheet'!$N14/'Summary sheet'!$L14) =C15*$F$10 =F15*('Summary sheet'!$M14/'Summary sheet'!$L14) =F15*('Summary sheet'!$N14/'Summary sheet'!$L14)

2007/8 6 ='Input sheet'!D16 =C16*('Summary sheet'!$M15/'Summary sheet'!$L15) =C16*('Summary sheet'!$N15/'Summary sheet'!$L15) =C16*$F$10 =F16*('Summary sheet'!$M15/'Summary sheet'!$L15) =F16*('Summary sheet'!$N15/'Summary sheet'!$L15)

2008/9 7 ='Input sheet'!D17 =C17*('Summary sheet'!$M16/'Summary sheet'!$L16) =C17*('Summary sheet'!$N16/'Summary sheet'!$L16) =C17*$F$10 =F17*('Summary sheet'!$M16/'Summary sheet'!$L16) =F17*('Summary sheet'!$N16/'Summary sheet'!$L16)

2009/10 8 ='Input sheet'!D18 =C18*('Summary sheet'!$M17/'Summary sheet'!$L17) =C18*('Summary sheet'!$N17/'Summary sheet'!$L17) =C18*$F$10 =F18*('Summary sheet'!$M17/'Summary sheet'!$L17) =F18*('Summary sheet'!$N17/'Summary sheet'!$L17)

2010/11 9 ='Input sheet'!D19 =C19*('Summary sheet'!$M18/'Summary sheet'!$L18) =C19*('Summary sheet'!$N18/'Summary sheet'!$L18) =C19*$F$10 =F19*('Summary sheet'!$M18/'Summary sheet'!$L18) =F19*('Summary sheet'!$N18/'Summary sheet'!$L18)

2011/12 10 ='Input sheet'!D20 =C20*('Summary sheet'!$M19/'Summary sheet'!$L19) =C20*('Summary sheet'!$N19/'Summary sheet'!$L19) =C20*$F$10 =F20*('Summary sheet'!$M19/'Summary sheet'!$L19) =F20*('Summary sheet'!$N19/'Summary sheet'!$L19)

2012/13 11 ='Input sheet'!D21 =C21*('Summary sheet'!$M20/'Summary sheet'!$L20) =C21*('Summary sheet'!$N20/'Summary sheet'!$L20) =C21*$F$10 =F21*('Summary sheet'!$M20/'Summary sheet'!$L20) =F21*('Summary sheet'!$N20/'Summary sheet'!$L20)

2013/14 12 ='Input sheet'!D22 =C22*('Summary sheet'!$M21/'Summary sheet'!$L21) =C22*('Summary sheet'!$N21/'Summary sheet'!$L21) =C22*$F$10 =F22*('Summary sheet'!$M21/'Summary sheet'!$L21) =F22*('Summary sheet'!$N21/'Summary sheet'!$L21)

2014/15 13 ='Input sheet'!D23 =C23*('Summary sheet'!$M22/'Summary sheet'!$L22) =C23*('Summary sheet'!$N22/'Summary sheet'!$L22) =C23*$F$10 =F23*('Summary sheet'!$M22/'Summary sheet'!$L22) =F23*('Summary sheet'!$N22/'Summary sheet'!$L22)

2015/16 14 ='Input sheet'!D24 =C24*('Summary sheet'!$M23/'Summary sheet'!$L23) =C24*('Summary sheet'!$N23/'Summary sheet'!$L23) =C24*$F$10 =F24*('Summary sheet'!$M23/'Summary sheet'!$L23) =F24*('Summary sheet'!$N23/'Summary sheet'!$L23)

2016/17 15 ='Input sheet'!D25 =C25*('Summary sheet'!$M24/'Summary sheet'!$L24) =C25*('Summary sheet'!$N24/'Summary sheet'!$L24) =C25*$F$10 =F25*('Summary sheet'!$M24/'Summary sheet'!$L24) =F25*('Summary sheet'!$N24/'Summary sheet'!$L24)

2017/18 16 ='Input sheet'!D26 =C26*('Summary sheet'!$M25/'Summary sheet'!$L25) =C26*('Summary sheet'!$N25/'Summary sheet'!$L25) =C26*$F$10 =F26*('Summary sheet'!$M25/'Summary sheet'!$L25) =F26*('Summary sheet'!$N25/'Summary sheet'!$L25)

2018/19 17 ='Input sheet'!D27 =C27*('Summary sheet'!$M26/'Summary sheet'!$L26) =C27*('Summary sheet'!$N26/'Summary sheet'!$L26) =C27*$F$10 =F27*('Summary sheet'!$M26/'Summary sheet'!$L26) =F27*('Summary sheet'!$N26/'Summary sheet'!$L26)

2019/20 18 ='Input sheet'!D28 =C28*('Summary sheet'!$M27/'Summary sheet'!$L27) =C28*('Summary sheet'!$N27/'Summary sheet'!$L27) =C28*$F$10 =F28*('Summary sheet'!$M27/'Summary sheet'!$L27) =F28*('Summary sheet'!$N27/'Summary sheet'!$L27)

2020/21 19 ='Input sheet'!D29 =C29*('Summary sheet'!$M28/'Summary sheet'!$L28) =C29*('Summary sheet'!$N28/'Summary sheet'!$L28) =C29*$F$10 =F29*('Summary sheet'!$M28/'Summary sheet'!$L28) =F29*('Summary sheet'!$N28/'Summary sheet'!$L28)

2021/22 20 ='Input sheet'!D30 =C30*('Summary sheet'!$M29/'Summary sheet'!$L29) =C30*('Summary sheet'!$N29/'Summary sheet'!$L29) =C30*$F$10 =F30*('Summary sheet'!$M29/'Summary sheet'!$L29) =F30*('Summary sheet'!$N29/'Summary sheet'!$L29)

2022/23 21 ='Input sheet'!D31 =C31*('Summary sheet'!$M30/'Summary sheet'!$L30) =C31*('Summary sheet'!$N30/'Summary sheet'!$L30) =C31*$F$10 =F31*('Summary sheet'!$M30/'Summary sheet'!$L30) =F31*('Summary sheet'!$N30/'Summary sheet'!$L30)

2023/24 22 ='Input sheet'!D32 =C32*('Summary sheet'!$M31/'Summary sheet'!$L31) =C32*('Summary sheet'!$N31/'Summary sheet'!$L31) =C32*$F$10 =F32*('Summary sheet'!$M31/'Summary sheet'!$L31) =F32*('Summary sheet'!$N31/'Summary sheet'!$L31)

2024/25 23 ='Input sheet'!D33 =C33*('Summary sheet'!$M32/'Summary sheet'!$L32) =C33*('Summary sheet'!$N32/'Summary sheet'!$L32) =C33*$F$10 =F33*('Summary sheet'!$M32/'Summary sheet'!$L32) =F33*('Summary sheet'!$N32/'Summary sheet'!$L32)

2025/26 24 ='Input sheet'!D34 =C34*('Summary sheet'!$M33/'Summary sheet'!$L33) =C34*('Summary sheet'!$N33/'Summary sheet'!$L33) =C34*$F$10 =F34*('Summary sheet'!$M33/'Summary sheet'!$L33) =F34*('Summary sheet'!$N33/'Summary sheet'!$L33)

2026/27 25 ='Input sheet'!D35 =C35*('Summary sheet'!$M34/'Summary sheet'!$L34) =C35*('Summary sheet'!$N34/'Summary sheet'!$L34) =C35*$F$10 =F35*('Summary sheet'!$M34/'Summary sheet'!$L34) =F35*('Summary sheet'!$N34/'Summary sheet'!$L34)

Type of Year

MRF 1 throughput MRF 1 Diversion of Household Waste stream

Page 214: Waste management model

214

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

=H7+1 =I7+1 =J7+1 =K7+1 =L7+1 =M7+1

Total Municipal Waste throughput Contract Household Waste Contract Waste other than Household Waste Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste

='Input sheet'!E11 =I11*('Summary sheet'!$M10/'Summary sheet'!$F10) =I11*('Summary sheet'!$N10/'Summary sheet'!$L10) =I11*$L$10 =L11*('Summary sheet'!$M10/'Summary sheet'!$F10) =L11*('Summary sheet'!$N10/'Summary sheet'!$L10)

='Input sheet'!E12 =I12*('Summary sheet'!$M11/'Summary sheet'!$L11) =I12*('Summary sheet'!$N11/'Summary sheet'!$L11) =I12*$L$10 =L12*('Summary sheet'!$M11/'Summary sheet'!$L11) =L12*('Summary sheet'!$N11/'Summary sheet'!$L11)

='Input sheet'!E13 =I13*('Summary sheet'!$M12/'Summary sheet'!$L12) =I13*('Summary sheet'!$N12/'Summary sheet'!$L12) =I13*$L$10 =L13*('Summary sheet'!$M12/'Summary sheet'!$L12) =L13*('Summary sheet'!$N12/'Summary sheet'!$L12)

='Input sheet'!E14 =I14*('Summary sheet'!$M13/'Summary sheet'!$L13) =I14*('Summary sheet'!$N13/'Summary sheet'!$L13) =I14*$L$10 =L14*('Summary sheet'!$M13/'Summary sheet'!$L13) =L14*('Summary sheet'!$N13/'Summary sheet'!$L13)

='Input sheet'!E15 =I15*('Summary sheet'!$M14/'Summary sheet'!$L14) =I15*('Summary sheet'!$N14/'Summary sheet'!$L14) =I15*$L$10 =L15*('Summary sheet'!$M14/'Summary sheet'!$L14) =L15*('Summary sheet'!$N14/'Summary sheet'!$L14)

='Input sheet'!E16 =I16*('Summary sheet'!$M15/'Summary sheet'!$L15) =I16*('Summary sheet'!$N15/'Summary sheet'!$L15) =I16*$L$10 =L16*('Summary sheet'!$M15/'Summary sheet'!$L15) =L16*('Summary sheet'!$N15/'Summary sheet'!$L15)

='Input sheet'!E17 =I17*('Summary sheet'!$M16/'Summary sheet'!$L16) =I17*('Summary sheet'!$N16/'Summary sheet'!$L16) =I17*$L$10 =L17*('Summary sheet'!$M16/'Summary sheet'!$L16) =L17*('Summary sheet'!$N16/'Summary sheet'!$L16)

='Input sheet'!E18 =I18*('Summary sheet'!$M17/'Summary sheet'!$L17) =I18*('Summary sheet'!$N17/'Summary sheet'!$L17) =I18*$L$10 =L18*('Summary sheet'!$M17/'Summary sheet'!$L17) =L18*('Summary sheet'!$N17/'Summary sheet'!$L17)

='Input sheet'!E19 =I19*('Summary sheet'!$M18/'Summary sheet'!$L18) =I19*('Summary sheet'!$N18/'Summary sheet'!$L18) =I19*$L$10 =L19*('Summary sheet'!$M18/'Summary sheet'!$L18) =L19*('Summary sheet'!$N18/'Summary sheet'!$L18)

='Input sheet'!E20 =I20*('Summary sheet'!$M19/'Summary sheet'!$L19) =I20*('Summary sheet'!$N19/'Summary sheet'!$L19) =I20*$L$10 =L20*('Summary sheet'!$M19/'Summary sheet'!$L19) =L20*('Summary sheet'!$N19/'Summary sheet'!$L19)

='Input sheet'!E21 =I21*('Summary sheet'!$M20/'Summary sheet'!$L20) =I21*('Summary sheet'!$N20/'Summary sheet'!$L20) =I21*$L$10 =L21*('Summary sheet'!$M20/'Summary sheet'!$L20) =L21*('Summary sheet'!$N20/'Summary sheet'!$L20)

='Input sheet'!E22 =I22*('Summary sheet'!$M21/'Summary sheet'!$L21) =I22*('Summary sheet'!$N21/'Summary sheet'!$L21) =I22*$L$10 =L22*('Summary sheet'!$M21/'Summary sheet'!$L21) =L22*('Summary sheet'!$N21/'Summary sheet'!$L21)

='Input sheet'!E23 =I23*('Summary sheet'!$M22/'Summary sheet'!$L22) =I23*('Summary sheet'!$N22/'Summary sheet'!$L22) =I23*$L$10 =L23*('Summary sheet'!$M22/'Summary sheet'!$L22) =L23*('Summary sheet'!$N22/'Summary sheet'!$L22)

='Input sheet'!E24 =I24*('Summary sheet'!$M23/'Summary sheet'!$L23) =I24*('Summary sheet'!$N23/'Summary sheet'!$L23) =I24*$L$10 =L24*('Summary sheet'!$M23/'Summary sheet'!$L23) =L24*('Summary sheet'!$N23/'Summary sheet'!$L23)

='Input sheet'!E25 =I25*('Summary sheet'!$M24/'Summary sheet'!$L24) =I25*('Summary sheet'!$N24/'Summary sheet'!$L24) =I25*$L$10 =L25*('Summary sheet'!$M24/'Summary sheet'!$L24) =L25*('Summary sheet'!$N24/'Summary sheet'!$L24)

='Input sheet'!E26 =I26*('Summary sheet'!$M25/'Summary sheet'!$L25) =I26*('Summary sheet'!$N25/'Summary sheet'!$L25) =I26*$L$10 =L26*('Summary sheet'!$M25/'Summary sheet'!$L25) =L26*('Summary sheet'!$N25/'Summary sheet'!$L25)

='Input sheet'!E27 =I27*('Summary sheet'!$M26/'Summary sheet'!$L26) =I27*('Summary sheet'!$N26/'Summary sheet'!$L26) =I27*$L$10 =L27*('Summary sheet'!$M26/'Summary sheet'!$L26) =L27*('Summary sheet'!$N26/'Summary sheet'!$L26)

='Input sheet'!E28 =I28*('Summary sheet'!$M27/'Summary sheet'!$L27) =I28*('Summary sheet'!$N27/'Summary sheet'!$L27) =I28*$L$10 =L28*('Summary sheet'!$M27/'Summary sheet'!$L27) =L28*('Summary sheet'!$N27/'Summary sheet'!$L27)

='Input sheet'!E29 =I29*('Summary sheet'!$M28/'Summary sheet'!$L28) =I29*('Summary sheet'!$N28/'Summary sheet'!$L28) =I29*$L$10 =L29*('Summary sheet'!$M28/'Summary sheet'!$L28) =L29*('Summary sheet'!$N28/'Summary sheet'!$L28)

='Input sheet'!E30 =I30*('Summary sheet'!$M29/'Summary sheet'!$L29) =I30*('Summary sheet'!$N29/'Summary sheet'!$L29) =I30*$L$10 =L30*('Summary sheet'!$M29/'Summary sheet'!$L29) =L30*('Summary sheet'!$N29/'Summary sheet'!$L29)

='Input sheet'!E31 =I31*('Summary sheet'!$M30/'Summary sheet'!$L30) =I31*('Summary sheet'!$N30/'Summary sheet'!$L30) =I31*$L$10 =L31*('Summary sheet'!$M30/'Summary sheet'!$L30) =L31*('Summary sheet'!$N30/'Summary sheet'!$L30)

='Input sheet'!E32 =I32*('Summary sheet'!$M31/'Summary sheet'!$L31) =I32*('Summary sheet'!$N31/'Summary sheet'!$L31) =I32*$L$10 =L32*('Summary sheet'!$M31/'Summary sheet'!$L31) =L32*('Summary sheet'!$N31/'Summary sheet'!$L31)

='Input sheet'!E33 =I33*('Summary sheet'!$M32/'Summary sheet'!$L32) =I33*('Summary sheet'!$N32/'Summary sheet'!$L32) =I33*$L$10 =L33*('Summary sheet'!$M32/'Summary sheet'!$L32) =L33*('Summary sheet'!$N32/'Summary sheet'!$L32)

='Input sheet'!E34 =I34*('Summary sheet'!$M33/'Summary sheet'!$L33) =I34*('Summary sheet'!$N33/'Summary sheet'!$L33) =I34*$L$10 =L34*('Summary sheet'!$M33/'Summary sheet'!$L33) =L34*('Summary sheet'!$N33/'Summary sheet'!$L33)

='Input sheet'!E35 =I35*('Summary sheet'!$M34/'Summary sheet'!$L34) =I35*('Summary sheet'!$N34/'Summary sheet'!$L34) =I35*$L$10 =L35*('Summary sheet'!$M34/'Summary sheet'!$L34) =L35*('Summary sheet'!$N34/'Summary sheet'!$L34)

MRF 2 throughput MRF 2 Diversion of Household Waste stream

Page 215: Waste management model

215

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

=N7+1 =O7+1 =P7+1 =Q7+1 =R7+1 =S7+1

Total Municipal Waste throughput Contract Household Waste Contract Waste other than Household Waste Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste

='Input sheet'!F11 =O11*('Summary sheet'!$M10/'Summary sheet'!$F10) =O11*('Summary sheet'!$N10/'Summary sheet'!$L10) =O11*$R$10 =R11*('Summary sheet'!$M10/'Summary sheet'!$F10) =R11*('Summary sheet'!$N10/'Summary sheet'!$L10)

='Input sheet'!F12 =O12*('Summary sheet'!$M11/'Summary sheet'!$L11) =O12*('Summary sheet'!$N11/'Summary sheet'!$L11) =O12*$R$10 =R12*('Summary sheet'!$M11/'Summary sheet'!$L11) =R12*('Summary sheet'!$N11/'Summary sheet'!$L11)

='Input sheet'!F13 =O13*('Summary sheet'!$M12/'Summary sheet'!$L12) =O13*('Summary sheet'!$N12/'Summary sheet'!$L12) =O13*$R$10 =R13*('Summary sheet'!$M12/'Summary sheet'!$L12) =R13*('Summary sheet'!$N12/'Summary sheet'!$L12)

='Input sheet'!F14 =O14*('Summary sheet'!$M13/'Summary sheet'!$L13) =O14*('Summary sheet'!$N13/'Summary sheet'!$L13) =O14*$R$10 =R14*('Summary sheet'!$M13/'Summary sheet'!$L13) =R14*('Summary sheet'!$N13/'Summary sheet'!$L13)

='Input sheet'!F15 =O15*('Summary sheet'!$M14/'Summary sheet'!$L14) =O15*('Summary sheet'!$N14/'Summary sheet'!$L14) =O15*$R$10 =R15*('Summary sheet'!$M14/'Summary sheet'!$L14) =R15*('Summary sheet'!$N14/'Summary sheet'!$L14)

='Input sheet'!F16 =O16*('Summary sheet'!$M15/'Summary sheet'!$L15) =O16*('Summary sheet'!$N15/'Summary sheet'!$L15) =O16*$R$10 =R16*('Summary sheet'!$M15/'Summary sheet'!$L15) =R16*('Summary sheet'!$N15/'Summary sheet'!$L15)

='Input sheet'!F17 =O17*('Summary sheet'!$M16/'Summary sheet'!$L16) =O17*('Summary sheet'!$N16/'Summary sheet'!$L16) =O17*$R$10 =R17*('Summary sheet'!$M16/'Summary sheet'!$L16) =R17*('Summary sheet'!$N16/'Summary sheet'!$L16)

='Input sheet'!F18 =O18*('Summary sheet'!$M17/'Summary sheet'!$L17) =O18*('Summary sheet'!$N17/'Summary sheet'!$L17) =O18*$R$10 =R18*('Summary sheet'!$M17/'Summary sheet'!$L17) =R18*('Summary sheet'!$N17/'Summary sheet'!$L17)

='Input sheet'!F19 =O19*('Summary sheet'!$M18/'Summary sheet'!$L18) =O19*('Summary sheet'!$N18/'Summary sheet'!$L18) =O19*$R$10 =R19*('Summary sheet'!$M18/'Summary sheet'!$L18) =R19*('Summary sheet'!$N18/'Summary sheet'!$L18)

='Input sheet'!F20 =O20*('Summary sheet'!$M19/'Summary sheet'!$L19) =O20*('Summary sheet'!$N19/'Summary sheet'!$L19) =O20*$R$10 =R20*('Summary sheet'!$M19/'Summary sheet'!$L19) =R20*('Summary sheet'!$N19/'Summary sheet'!$L19)

='Input sheet'!F21 =O21*('Summary sheet'!$M20/'Summary sheet'!$L20) =O21*('Summary sheet'!$N20/'Summary sheet'!$L20) =O21*$R$10 =R21*('Summary sheet'!$M20/'Summary sheet'!$L20) =R21*('Summary sheet'!$N20/'Summary sheet'!$L20)

='Input sheet'!F22 =O22*('Summary sheet'!$M21/'Summary sheet'!$L21) =O22*('Summary sheet'!$N21/'Summary sheet'!$L21) =O22*$R$10 =R22*('Summary sheet'!$M21/'Summary sheet'!$L21) =R22*('Summary sheet'!$N21/'Summary sheet'!$L21)

='Input sheet'!F23 =O23*('Summary sheet'!$M22/'Summary sheet'!$L22) =O23*('Summary sheet'!$N22/'Summary sheet'!$L22) =O23*$R$10 =R23*('Summary sheet'!$M22/'Summary sheet'!$L22) =R23*('Summary sheet'!$N22/'Summary sheet'!$L22)

='Input sheet'!F24 =O24*('Summary sheet'!$M23/'Summary sheet'!$L23) =O24*('Summary sheet'!$N23/'Summary sheet'!$L23) =O24*$R$10 =R24*('Summary sheet'!$M23/'Summary sheet'!$L23) =R24*('Summary sheet'!$N23/'Summary sheet'!$L23)

='Input sheet'!F25 =O25*('Summary sheet'!$M24/'Summary sheet'!$L24) =O25*('Summary sheet'!$N24/'Summary sheet'!$L24) =O25*$R$10 =R25*('Summary sheet'!$M24/'Summary sheet'!$L24) =R25*('Summary sheet'!$N24/'Summary sheet'!$L24)

='Input sheet'!F26 =O26*('Summary sheet'!$M25/'Summary sheet'!$L25) =O26*('Summary sheet'!$N25/'Summary sheet'!$L25) =O26*$R$10 =R26*('Summary sheet'!$M25/'Summary sheet'!$L25) =R26*('Summary sheet'!$N25/'Summary sheet'!$L25)

='Input sheet'!F27 =O27*('Summary sheet'!$M26/'Summary sheet'!$L26) =O27*('Summary sheet'!$N26/'Summary sheet'!$L26) =O27*$R$10 =R27*('Summary sheet'!$M26/'Summary sheet'!$L26) =R27*('Summary sheet'!$N26/'Summary sheet'!$L26)

='Input sheet'!F28 =O28*('Summary sheet'!$M27/'Summary sheet'!$L27) =O28*('Summary sheet'!$N27/'Summary sheet'!$L27) =O28*$R$10 =R28*('Summary sheet'!$M27/'Summary sheet'!$L27) =R28*('Summary sheet'!$N27/'Summary sheet'!$L27)

='Input sheet'!F29 =O29*('Summary sheet'!$M28/'Summary sheet'!$L28) =O29*('Summary sheet'!$N28/'Summary sheet'!$L28) =O29*$R$10 =R29*('Summary sheet'!$M28/'Summary sheet'!$L28) =R29*('Summary sheet'!$N28/'Summary sheet'!$L28)

='Input sheet'!F30 =O30*('Summary sheet'!$M29/'Summary sheet'!$L29) =O30*('Summary sheet'!$N29/'Summary sheet'!$L29) =O30*$R$10 =R30*('Summary sheet'!$M29/'Summary sheet'!$L29) =R30*('Summary sheet'!$N29/'Summary sheet'!$L29)

='Input sheet'!F31 =O31*('Summary sheet'!$M30/'Summary sheet'!$L30) =O31*('Summary sheet'!$N30/'Summary sheet'!$L30) =O31*$R$10 =R31*('Summary sheet'!$M30/'Summary sheet'!$L30) =R31*('Summary sheet'!$N30/'Summary sheet'!$L30)

='Input sheet'!F32 =O32*('Summary sheet'!$M31/'Summary sheet'!$L31) =O32*('Summary sheet'!$N31/'Summary sheet'!$L31) =O32*$R$10 =R32*('Summary sheet'!$M31/'Summary sheet'!$L31) =R32*('Summary sheet'!$N31/'Summary sheet'!$L31)

='Input sheet'!F33 =O33*('Summary sheet'!$M32/'Summary sheet'!$L32) =O33*('Summary sheet'!$N32/'Summary sheet'!$L32) =O33*$R$10 =R33*('Summary sheet'!$M32/'Summary sheet'!$L32) =R33*('Summary sheet'!$N32/'Summary sheet'!$L32)

='Input sheet'!F34 =O34*('Summary sheet'!$M33/'Summary sheet'!$L33) =O34*('Summary sheet'!$N33/'Summary sheet'!$L33) =O34*$R$10 =R34*('Summary sheet'!$M33/'Summary sheet'!$L33) =R34*('Summary sheet'!$N33/'Summary sheet'!$L33)

='Input sheet'!F35 =O35*('Summary sheet'!$M34/'Summary sheet'!$L34) =O35*('Summary sheet'!$N34/'Summary sheet'!$L34) =O35*$R$10 =R35*('Summary sheet'!$M34/'Summary sheet'!$L34) =R35*('Summary sheet'!$N34/'Summary sheet'!$L34)

MRF 3 Diversion of Household Waste stream MRF3 throughput

Page 216: Waste management model

216

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

=T7+1 =U7+1 =V7+1 =W7+1 =X7+1 =Y7+1

Total Municipal Waste throughput Contract Household Waste Contract Waste other than Household Waste Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste

='Input sheet'!G11 =U11*('Summary sheet'!$M10/'Summary sheet'!$F10) =U11*('Summary sheet'!$N10/'Summary sheet'!$L10) =U11*$X$10 =X11*('Summary sheet'!$M10/'Summary sheet'!$F10) =X11*('Summary sheet'!$N10/'Summary sheet'!$L10)

='Input sheet'!G12 =U12*('Summary sheet'!$M11/'Summary sheet'!$L11) =U12*('Summary sheet'!$N11/'Summary sheet'!$L11) =U12*$X$10 =X12*('Summary sheet'!$M11/'Summary sheet'!$L11) =X12*('Summary sheet'!$N11/'Summary sheet'!$L11)

='Input sheet'!G13 =U13*('Summary sheet'!$M12/'Summary sheet'!$L12) =U13*('Summary sheet'!$N12/'Summary sheet'!$L12) =U13*$X$10 =X13*('Summary sheet'!$M12/'Summary sheet'!$L12) =X13*('Summary sheet'!$N12/'Summary sheet'!$L12)

='Input sheet'!G14 =U14*('Summary sheet'!$M13/'Summary sheet'!$L13) =U14*('Summary sheet'!$N13/'Summary sheet'!$L13) =U14*$X$10 =X14*('Summary sheet'!$M13/'Summary sheet'!$L13) =X14*('Summary sheet'!$N13/'Summary sheet'!$L13)

='Input sheet'!G15 =U15*('Summary sheet'!$M14/'Summary sheet'!$L14) =U15*('Summary sheet'!$N14/'Summary sheet'!$L14) =U15*$X$10 =X15*('Summary sheet'!$M14/'Summary sheet'!$L14) =X15*('Summary sheet'!$N14/'Summary sheet'!$L14)

='Input sheet'!G16 =U16*('Summary sheet'!$M15/'Summary sheet'!$L15) =U16*('Summary sheet'!$N15/'Summary sheet'!$L15) =U16*$X$10 =X16*('Summary sheet'!$M15/'Summary sheet'!$L15) =X16*('Summary sheet'!$N15/'Summary sheet'!$L15)

='Input sheet'!G17 =U17*('Summary sheet'!$M16/'Summary sheet'!$L16) =U17*('Summary sheet'!$N16/'Summary sheet'!$L16) =U17*$X$10 =X17*('Summary sheet'!$M16/'Summary sheet'!$L16) =X17*('Summary sheet'!$N16/'Summary sheet'!$L16)

='Input sheet'!G18 =U18*('Summary sheet'!$M17/'Summary sheet'!$L17) =U18*('Summary sheet'!$N17/'Summary sheet'!$L17) =U18*$X$10 =X18*('Summary sheet'!$M17/'Summary sheet'!$L17) =X18*('Summary sheet'!$N17/'Summary sheet'!$L17)

='Input sheet'!G19 =U19*('Summary sheet'!$M18/'Summary sheet'!$L18) =U19*('Summary sheet'!$N18/'Summary sheet'!$L18) =U19*$X$10 =X19*('Summary sheet'!$M18/'Summary sheet'!$L18) =X19*('Summary sheet'!$N18/'Summary sheet'!$L18)

='Input sheet'!G20 =U20*('Summary sheet'!$M19/'Summary sheet'!$L19) =U20*('Summary sheet'!$N19/'Summary sheet'!$L19) =U20*$X$10 =X20*('Summary sheet'!$M19/'Summary sheet'!$L19) =X20*('Summary sheet'!$N19/'Summary sheet'!$L19)

='Input sheet'!G21 =U21*('Summary sheet'!$M20/'Summary sheet'!$L20) =U21*('Summary sheet'!$N20/'Summary sheet'!$L20) =U21*$X$10 =X21*('Summary sheet'!$M20/'Summary sheet'!$L20) =X21*('Summary sheet'!$N20/'Summary sheet'!$L20)

='Input sheet'!G22 =U22*('Summary sheet'!$M21/'Summary sheet'!$L21) =U22*('Summary sheet'!$N21/'Summary sheet'!$L21) =U22*$X$10 =X22*('Summary sheet'!$M21/'Summary sheet'!$L21) =X22*('Summary sheet'!$N21/'Summary sheet'!$L21)

='Input sheet'!G23 =U23*('Summary sheet'!$M22/'Summary sheet'!$L22) =U23*('Summary sheet'!$N22/'Summary sheet'!$L22) =U23*$X$10 =X23*('Summary sheet'!$M22/'Summary sheet'!$L22) =X23*('Summary sheet'!$N22/'Summary sheet'!$L22)

='Input sheet'!G24 =U24*('Summary sheet'!$M23/'Summary sheet'!$L23) =U24*('Summary sheet'!$N23/'Summary sheet'!$L23) =U24*$X$10 =X24*('Summary sheet'!$M23/'Summary sheet'!$L23) =X24*('Summary sheet'!$N23/'Summary sheet'!$L23)

='Input sheet'!G25 =U25*('Summary sheet'!$M24/'Summary sheet'!$L24) =U25*('Summary sheet'!$N24/'Summary sheet'!$L24) =U25*$X$10 =X25*('Summary sheet'!$M24/'Summary sheet'!$L24) =X25*('Summary sheet'!$N24/'Summary sheet'!$L24)

='Input sheet'!G26 =U26*('Summary sheet'!$M25/'Summary sheet'!$L25) =U26*('Summary sheet'!$N25/'Summary sheet'!$L25) =U26*$X$10 =X26*('Summary sheet'!$M25/'Summary sheet'!$L25) =X26*('Summary sheet'!$N25/'Summary sheet'!$L25)

='Input sheet'!G27 =U27*('Summary sheet'!$M26/'Summary sheet'!$L26) =U27*('Summary sheet'!$N26/'Summary sheet'!$L26) =U27*$X$10 =X27*('Summary sheet'!$M26/'Summary sheet'!$L26) =X27*('Summary sheet'!$N26/'Summary sheet'!$L26)

='Input sheet'!G28 =U28*('Summary sheet'!$M27/'Summary sheet'!$L27) =U28*('Summary sheet'!$N27/'Summary sheet'!$L27) =U28*$X$10 =X28*('Summary sheet'!$M27/'Summary sheet'!$L27) =X28*('Summary sheet'!$N27/'Summary sheet'!$L27)

='Input sheet'!G29 =U29*('Summary sheet'!$M28/'Summary sheet'!$L28) =U29*('Summary sheet'!$N28/'Summary sheet'!$L28) =U29*$X$10 =X29*('Summary sheet'!$M28/'Summary sheet'!$L28) =X29*('Summary sheet'!$N28/'Summary sheet'!$L28)

='Input sheet'!G30 =U30*('Summary sheet'!$M29/'Summary sheet'!$L29) =U30*('Summary sheet'!$N29/'Summary sheet'!$L29) =U30*$X$10 =X30*('Summary sheet'!$M29/'Summary sheet'!$L29) =X30*('Summary sheet'!$N29/'Summary sheet'!$L29)

='Input sheet'!G31 =U31*('Summary sheet'!$M30/'Summary sheet'!$L30) =U31*('Summary sheet'!$N30/'Summary sheet'!$L30) =U31*$X$10 =X31*('Summary sheet'!$M30/'Summary sheet'!$L30) =X31*('Summary sheet'!$N30/'Summary sheet'!$L30)

='Input sheet'!G32 =U32*('Summary sheet'!$M31/'Summary sheet'!$L31) =U32*('Summary sheet'!$N31/'Summary sheet'!$L31) =U32*$X$10 =X32*('Summary sheet'!$M31/'Summary sheet'!$L31) =X32*('Summary sheet'!$N31/'Summary sheet'!$L31)

='Input sheet'!G33 =U33*('Summary sheet'!$M32/'Summary sheet'!$L32) =U33*('Summary sheet'!$N32/'Summary sheet'!$L32) =U33*$X$10 =X33*('Summary sheet'!$M32/'Summary sheet'!$L32) =X33*('Summary sheet'!$N32/'Summary sheet'!$L32)

='Input sheet'!G34 =U34*('Summary sheet'!$M33/'Summary sheet'!$L33) =U34*('Summary sheet'!$N33/'Summary sheet'!$L33) =U34*$X$10 =X34*('Summary sheet'!$M33/'Summary sheet'!$L33) =X34*('Summary sheet'!$N33/'Summary sheet'!$L33)

='Input sheet'!G35 =U35*('Summary sheet'!$M34/'Summary sheet'!$L34) =U35*('Summary sheet'!$N34/'Summary sheet'!$L34) =U35*$X$10 =X35*('Summary sheet'!$M34/'Summary sheet'!$L34) =X35*('Summary sheet'!$N34/'Summary sheet'!$L34)

MRF4 throughput MRF 4 Diversion of Household Waste stream

Page 217: Waste management model

217

Total MRF throughput

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

=Z7+1 =AA7+1 =AB7+1 =AC7+1 =AD7+1 =AE7+1 =AF7+1

Total Municipal Waste Total Municipal Waste Contract Household Waste Contract Waste other

than Household Waste Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste

=C11+I11+O11+U11 =F11+L11+R11+X11 =G11+M11+S11+Y11 =H11+N11+T11+Z11 =IF($CA11=0,0,AA11-AB11) =AE11*('Summary sheet'!$M10/'Summary sheet'!$F10) =AE11*('Summary sheet'!$N10/'Summary sheet'!$F10)

=C12+I12+O12+U12 =F12+L12+R12+X12 =G12+M12+S12+Y12 =H12+N12+T12+Z12 =IF($CA12=0,0,AA12-AB12) =AE12*('Summary sheet'!$M11/'Summary sheet'!$F11) =AE12*('Summary sheet'!$N11/'Summary sheet'!$F11)

=C13+I13+O13+U13 =F13+L13+R13+X13 =G13+M13+S13+Y13 =H13+N13+T13+Z13 =IF($CA13=0,0,AA13-AB13) =AE13*('Summary sheet'!$M12/'Summary sheet'!$F12) =AE13*('Summary sheet'!$N12/'Summary sheet'!$F12)

=C14+I14+O14+U14 =F14+L14+R14+X14 =G14+M14+S14+Y14 =H14+N14+T14+Z14 =IF($CA14=0,0,AA14-AB14) =AE14*('Summary sheet'!$M13/'Summary sheet'!$F13) =AE14*('Summary sheet'!$N13/'Summary sheet'!$F13)

=C15+I15+O15+U15 =F15+L15+R15+X15 =G15+M15+S15+Y15 =H15+N15+T15+Z15 =IF($CA15=0,0,AA15-AB15) =AE15*('Summary sheet'!$M14/'Summary sheet'!$F14) =AE15*('Summary sheet'!$N14/'Summary sheet'!$F14)

=C16+I16+O16+U16 =F16+L16+R16+X16 =G16+M16+S16+Y16 =H16+N16+T16+Z16 =IF($CA16=0,0,AA16-AB16) =AE16*('Summary sheet'!$M15/'Summary sheet'!$F15) =AE16*('Summary sheet'!$N15/'Summary sheet'!$F15)

=C17+I17+O17+U17 =F17+L17+R17+X17 =G17+M17+S17+Y17 =H17+N17+T17+Z17 =IF($CA17+CG17=0,0,AA17-AB17) =AE17*('Summary sheet'!$M16/'Summary sheet'!$F16) =AE17*('Summary sheet'!$N16/'Summary sheet'!$F16)

=C18+I18+O18+U18 =F18+L18+R18+X18 =G18+M18+S18+Y18 =H18+N18+T18+Z18 =IF($CA18+CG18=0,0,AA18-AB18) =AE18*('Summary sheet'!$M17/'Summary sheet'!$F17) =AE18*('Summary sheet'!$N17/'Summary sheet'!$F17)

=C19+I19+O19+U19 =F19+L19+R19+X19 =G19+M19+S19+Y19 =H19+N19+T19+Z19 =IF($CA19+CG19=0,0,AA19-AB19) =AE19*('Summary sheet'!$M18/'Summary sheet'!$F18) =AE19*('Summary sheet'!$N18/'Summary sheet'!$F18)

=C20+I20+O20+U20 =F20+L20+R20+X20 =G20+M20+S20+Y20 =H20+N20+T20+Z20 =IF($CA20+CG20=0,0,AA20-AB20) =AE20*('Summary sheet'!$M19/'Summary sheet'!$F19) =AE20*('Summary sheet'!$N19/'Summary sheet'!$F19)

=C21+I21+O21+U21 =F21+L21+R21+X21 =G21+M21+S21+Y21 =H21+N21+T21+Z21 =IF($CA21+CG21=0,0,AA21-AB21) =AE21*('Summary sheet'!$M20/'Summary sheet'!$F20) =AE21*('Summary sheet'!$N20/'Summary sheet'!$F20)

=C22+I22+O22+U22 =F22+L22+R22+X22 =G22+M22+S22+Y22 =H22+N22+T22+Z22 =IF($CA22+CG22=0,0,AA22-AB22) =AE22*('Summary sheet'!$M21/'Summary sheet'!$F21) =AE22*('Summary sheet'!$N21/'Summary sheet'!$F21)

=C23+I23+O23+U23 =F23+L23+R23+X23 =G23+M23+S23+Y23 =H23+N23+T23+Z23 =IF($CA23+CG23=0,0,AA23-AB23) =AE23*('Summary sheet'!$M22/'Summary sheet'!$F22) =AE23*('Summary sheet'!$N22/'Summary sheet'!$F22)

=C24+I24+O24+U24 =F24+L24+R24+X24 =G24+M24+S24+Y24 =H24+N24+T24+Z24 =IF($CA24+CG24=0,0,AA24-AB24) =AE24*('Summary sheet'!$M23/'Summary sheet'!$F23) =AE24*('Summary sheet'!$N23/'Summary sheet'!$F23)

=C25+I25+O25+U25 =F25+L25+R25+X25 =G25+M25+S25+Y25 =H25+N25+T25+Z25 =IF($CA25+CG25=0,0,AA25-AB25) =AE25*('Summary sheet'!$M24/'Summary sheet'!$F24) =AE25*('Summary sheet'!$N24/'Summary sheet'!$F24)

=C26+I26+O26+U26 =F26+L26+R26+X26 =G26+M26+S26+Y26 =H26+N26+T26+Z26 =IF($CA26+CG26=0,0,AA26-AB26) =AE26*('Summary sheet'!$M25/'Summary sheet'!$F25) =AE26*('Summary sheet'!$N25/'Summary sheet'!$F25)

=C27+I27+O27+U27 =F27+L27+R27+X27 =G27+M27+S27+Y27 =H27+N27+T27+Z27 =IF($CA27+CG27=0,0,AA27-AB27) =AE27*('Summary sheet'!$M26/'Summary sheet'!$F26) =AE27*('Summary sheet'!$N26/'Summary sheet'!$F26)

=C28+I28+O28+U28 =F28+L28+R28+X28 =G28+M28+S28+Y28 =H28+N28+T28+Z28 =IF($CA28+CG28=0,0,AA28-AB28) =AE28*('Summary sheet'!$M27/'Summary sheet'!$F27) =AE28*('Summary sheet'!$N27/'Summary sheet'!$F27)

=C29+I29+O29+U29 =F29+L29+R29+X29 =G29+M29+S29+Y29 =H29+N29+T29+Z29 =IF($CA29+CG29=0,0,AA29-AB29) =AE29*('Summary sheet'!$M28/'Summary sheet'!$F28) =AE29*('Summary sheet'!$N28/'Summary sheet'!$F28)

=C30+I30+O30+U30 =F30+L30+R30+X30 =G30+M30+S30+Y30 =H30+N30+T30+Z30 =IF($CA30+CG30=0,0,AA30-AB30) =AE30*('Summary sheet'!$M29/'Summary sheet'!$F29) =AE30*('Summary sheet'!$N29/'Summary sheet'!$F29)

=C31+I31+O31+U31 =F31+L31+R31+X31 =G31+M31+S31+Y31 =H31+N31+T31+Z31 =IF($CA31+CG31=0,0,AA31-AB31) =AE31*('Summary sheet'!$M30/'Summary sheet'!$F30) =AE31*('Summary sheet'!$N30/'Summary sheet'!$F30)

=C32+I32+O32+U32 =F32+L32+R32+X32 =G32+M32+S32+Y32 =H32+N32+T32+Z32 =IF($CA32+CG32=0,0,AA32-AB32) =AE32*('Summary sheet'!$M31/'Summary sheet'!$F31) =AE32*('Summary sheet'!$N31/'Summary sheet'!$F31)

=C33+I33+O33+U33 =F33+L33+R33+X33 =G33+M33+S33+Y33 =H33+N33+T33+Z33 =IF($CA33+CG33=0,0,AA33-AB33) =AE33*('Summary sheet'!$M32/'Summary sheet'!$F32) =AE33*('Summary sheet'!$N32/'Summary sheet'!$F32)

=C34+I34+O34+U34 =F34+L34+R34+X34 =G34+M34+S34+Y34 =H34+N34+T34+Z34 =IF($CA34+CG34=0,0,AA34-AB34) =AE34*('Summary sheet'!$M33/'Summary sheet'!$F33) =AE34*('Summary sheet'!$N33/'Summary sheet'!$F33)

=C35+I35+O35+U35 =F35+L35+R35+X35 =G35+M35+S35+Y35 =H35+N35+T35+Z35 =IF($CA35+CG35=0,0,AA35-AB35) =AE35*('Summary sheet'!$M34/'Summary sheet'!$F34) =AE35*('Summary sheet'!$N34/'Summary sheet'!$F34)

Total diversion of Household Waste from landfill via MRF's Total residues to EFW from MRF's

Page 218: Waste management model

218

Composters

Diversion of Household

Waste to facilities i.e.

throughput of MRFs

Diversion of dry recyclables

from landfill through MRF's

(Percentage) (Percentage) (tonnes) (tonnes) (tonnes)

=AG7+1 =AH7+1 =AI7+1 =AK7+1 =AL7+1

Total Municipal Waste Total Municipal Waste Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste

=AA11/'Summary sheet'!H10 =AB11/'Summary sheet'!H10 =(IF('Input sheet'!J11=0,'Input sheet'!L11,IF('Input sheet'!J11>0,'Input sheet'!J11)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK11*('Summary sheet'!$M10/'Summary sheet'!$L10) =AK11*('Summary sheet'!$N10/'Summary sheet'!$L10)

=AA12/'Summary sheet'!H11 =AB12/'Summary sheet'!H11 =(IF('Input sheet'!J12=0,'Input sheet'!L12,IF('Input sheet'!J12>0,'Input sheet'!J12)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK12*('Summary sheet'!$M11/'Summary sheet'!$L11) =AK12*('Summary sheet'!$N11/'Summary sheet'!$L11)

=AA13/'Summary sheet'!H12 =AB13/'Summary sheet'!H12 =(IF('Input sheet'!J13=0,'Input sheet'!L13,IF('Input sheet'!J13>0,'Input sheet'!J13)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK13*('Summary sheet'!$M12/'Summary sheet'!$L12) =AK13*('Summary sheet'!$N12/'Summary sheet'!$L12)

=AA14/'Summary sheet'!H13 =AB14/'Summary sheet'!H13 =(IF('Input sheet'!J14=0,'Input sheet'!L14,IF('Input sheet'!J14>0,'Input sheet'!J14)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK14*('Summary sheet'!$M13/'Summary sheet'!$L13) =AK14*('Summary sheet'!$N13/'Summary sheet'!$L13)

=AA15/'Summary sheet'!H14 =AB15/'Summary sheet'!H14 =(IF('Input sheet'!J15=0,'Input sheet'!L15,IF('Input sheet'!J15>0,'Input sheet'!J15)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK15*('Summary sheet'!$M14/'Summary sheet'!$L14) =AK15*('Summary sheet'!$N14/'Summary sheet'!$L14)

=AA16/'Summary sheet'!H15 =AB16/'Summary sheet'!H15 =(IF('Input sheet'!J16=0,'Input sheet'!L16,IF('Input sheet'!J16>0,'Input sheet'!J16)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK16*('Summary sheet'!$M15/'Summary sheet'!$L15) =AK16*('Summary sheet'!$N15/'Summary sheet'!$L15)

=AA17/'Summary sheet'!H16 =AB17/'Summary sheet'!H16 =(IF('Input sheet'!J17=0,'Input sheet'!L17,IF('Input sheet'!J17>0,'Input sheet'!J17)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK17*('Summary sheet'!$M16/'Summary sheet'!$L16) =AK17*('Summary sheet'!$N16/'Summary sheet'!$L16)

=AA18/'Summary sheet'!H17 =AB18/'Summary sheet'!H17 =(IF('Input sheet'!J18=0,'Input sheet'!L18,IF('Input sheet'!J18>0,'Input sheet'!J18)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK18*('Summary sheet'!$M17/'Summary sheet'!$L17) =AK18*('Summary sheet'!$N17/'Summary sheet'!$L17)

=AA19/'Summary sheet'!H18 =AB19/'Summary sheet'!H18 =(IF('Input sheet'!J19=0,'Input sheet'!L19,IF('Input sheet'!J19>0,'Input sheet'!J19)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK19*('Summary sheet'!$M18/'Summary sheet'!$L18) =AK19*('Summary sheet'!$N18/'Summary sheet'!$L18)

=AA20/'Summary sheet'!H19 =AB20/'Summary sheet'!H19 =(IF('Input sheet'!J20=0,'Input sheet'!L20,IF('Input sheet'!J20>0,'Input sheet'!J20)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK20*('Summary sheet'!$M19/'Summary sheet'!$L19) =AK20*('Summary sheet'!$N19/'Summary sheet'!$L19)

=AA21/'Summary sheet'!H20 =AB21/'Summary sheet'!H20 =(IF('Input sheet'!J21=0,'Input sheet'!L21,IF('Input sheet'!J21>0,'Input sheet'!J21)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK21*('Summary sheet'!$M20/'Summary sheet'!$L20) =AK21*('Summary sheet'!$N20/'Summary sheet'!$L20)

=AA22/'Summary sheet'!H21 =AB22/'Summary sheet'!H21 =(IF('Input sheet'!J22=0,'Input sheet'!L22,IF('Input sheet'!J22>0,'Input sheet'!J22)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK22*('Summary sheet'!$M21/'Summary sheet'!$L21) =AK22*('Summary sheet'!$N21/'Summary sheet'!$L21)

=AA23/'Summary sheet'!H22 =AB23/'Summary sheet'!H22 =(IF('Input sheet'!J23=0,'Input sheet'!L23,IF('Input sheet'!J23>0,'Input sheet'!J23)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK23*('Summary sheet'!$M22/'Summary sheet'!$L22) =AK23*('Summary sheet'!$N22/'Summary sheet'!$L22)

=AA24/'Summary sheet'!H23 =AB24/'Summary sheet'!H23 =(IF('Input sheet'!J24=0,'Input sheet'!L24,IF('Input sheet'!J24>0,'Input sheet'!J24)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK24*('Summary sheet'!$M23/'Summary sheet'!$L23) =AK24*('Summary sheet'!$N23/'Summary sheet'!$L23)

=AA25/'Summary sheet'!H24 =AB25/'Summary sheet'!H24 =(IF('Input sheet'!J25=0,'Input sheet'!L25,IF('Input sheet'!J25>0,'Input sheet'!J25)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK25*('Summary sheet'!$M24/'Summary sheet'!$L24) =AK25*('Summary sheet'!$N24/'Summary sheet'!$L24)

=AA26/'Summary sheet'!H25 =AB26/'Summary sheet'!H25 =(IF('Input sheet'!J26=0,'Input sheet'!L26,IF('Input sheet'!J26>0,'Input sheet'!J26)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK26*('Summary sheet'!$M25/'Summary sheet'!$L25) =AK26*('Summary sheet'!$N25/'Summary sheet'!$L25)

=AA27/'Summary sheet'!H26 =AB27/'Summary sheet'!H26 =(IF('Input sheet'!J27=0,'Input sheet'!L27,IF('Input sheet'!J27>0,'Input sheet'!J27)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK27*('Summary sheet'!$M26/'Summary sheet'!$L26) =AK27*('Summary sheet'!$N26/'Summary sheet'!$L26)

=AA28/'Summary sheet'!H27 =AB28/'Summary sheet'!H27 =(IF('Input sheet'!J28=0,'Input sheet'!L28,IF('Input sheet'!J28>0,'Input sheet'!J28)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK28*('Summary sheet'!$M27/'Summary sheet'!$L27) =AK28*('Summary sheet'!$N27/'Summary sheet'!$L27)

=AA29/'Summary sheet'!H28 =AB29/'Summary sheet'!H28 =(IF('Input sheet'!J29=0,'Input sheet'!L29,IF('Input sheet'!J29>0,'Input sheet'!J29)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK29*('Summary sheet'!$M28/'Summary sheet'!$L28) =AK29*('Summary sheet'!$N28/'Summary sheet'!$L28)

=AA30/'Summary sheet'!H29 =AB30/'Summary sheet'!H29 =(IF('Input sheet'!J30=0,'Input sheet'!L30,IF('Input sheet'!J30>0,'Input sheet'!J30)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK30*('Summary sheet'!$M29/'Summary sheet'!$L29) =AK30*('Summary sheet'!$N29/'Summary sheet'!$L29)

=AA31/'Summary sheet'!H30 =AB31/'Summary sheet'!H30 =(IF('Input sheet'!J31=0,'Input sheet'!L31,IF('Input sheet'!J31>0,'Input sheet'!J31)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK31*('Summary sheet'!$M30/'Summary sheet'!$L30) =AK31*('Summary sheet'!$N30/'Summary sheet'!$L30)

=AA32/'Summary sheet'!H31 =AB32/'Summary sheet'!H31 =(IF('Input sheet'!J32=0,'Input sheet'!L32,IF('Input sheet'!J32>0,'Input sheet'!J32)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK32*('Summary sheet'!$M31/'Summary sheet'!$L31) =AK32*('Summary sheet'!$N31/'Summary sheet'!$L31)

=AA33/'Summary sheet'!H32 =AB33/'Summary sheet'!H32 =(IF('Input sheet'!J33=0,'Input sheet'!L33,IF('Input sheet'!J33>0,'Input sheet'!J33)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK33*('Summary sheet'!$M32/'Summary sheet'!$L32) =AK33*('Summary sheet'!$N32/'Summary sheet'!$L32)

=AA34/'Summary sheet'!H33 =AB34/'Summary sheet'!H33 =(IF('Input sheet'!J34=0,'Input sheet'!L34,IF('Input sheet'!J34>0,'Input sheet'!J34)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK34*('Summary sheet'!$M33/'Summary sheet'!$L33) =AK34*('Summary sheet'!$N33/'Summary sheet'!$L33)

=AA35/'Summary sheet'!H34 =AB35/'Summary sheet'!H34 =(IF('Input sheet'!J35=0,'Input sheet'!L35,IF('Input sheet'!J35>0,'Input sheet'!J35)))*(IF('Input sheet'!$J$5=0,'Input sheet'!L$5,IF('Input sheet'!$J$5>0,'Input sheet'!$J$5))) =AK35*('Summary sheet'!$M34/'Summary sheet'!$L34) =AK35*('Summary sheet'!$N34/'Summary sheet'!$L34)

Composter 1 throughput from AD plant when operational

Page 219: Waste management model

219

(tonnes) (tonnes) (tonnes)

=AM7+1 =AN7+1 =AO7+1

Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste

=(IF('Input sheet'!K11=0,'Input sheet'!M11,IF('Input sheet'!K11>0,'Input sheet'!K11)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN11*('Summary sheet'!$M10/'Summary sheet'!$L10) =AN11*('Summary sheet'!$N10/'Summary sheet'!$L10)

=(IF('Input sheet'!K12=0,'Input sheet'!M12,IF('Input sheet'!K12>0,'Input sheet'!K12)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN12*('Summary sheet'!$M11/'Summary sheet'!$L11) =AN12*('Summary sheet'!$N11/'Summary sheet'!$L11)

=(IF('Input sheet'!K13=0,'Input sheet'!M13,IF('Input sheet'!K13>0,'Input sheet'!K13)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN13*('Summary sheet'!$M12/'Summary sheet'!$L12) =AN13*('Summary sheet'!$N12/'Summary sheet'!$L12)

=(IF('Input sheet'!K14=0,'Input sheet'!M14,IF('Input sheet'!K14>0,'Input sheet'!K14)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN14*('Summary sheet'!$M13/'Summary sheet'!$L13) =AN14*('Summary sheet'!$N13/'Summary sheet'!$L13)

=(IF('Input sheet'!K15=0,'Input sheet'!M15,IF('Input sheet'!K15>0,'Input sheet'!K15)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN15*('Summary sheet'!$M14/'Summary sheet'!$L14) =AN15*('Summary sheet'!$N14/'Summary sheet'!$L14)

=(IF('Input sheet'!K16=0,'Input sheet'!M16,IF('Input sheet'!K16>0,'Input sheet'!K16)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN16*('Summary sheet'!$M15/'Summary sheet'!$L15) =AN16*('Summary sheet'!$N15/'Summary sheet'!$L15)

=(IF('Input sheet'!K17=0,'Input sheet'!M17,IF('Input sheet'!K17>0,'Input sheet'!K17)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN17*('Summary sheet'!$M16/'Summary sheet'!$L16) =AN17*('Summary sheet'!$N16/'Summary sheet'!$L16)

=(IF('Input sheet'!K18=0,'Input sheet'!M18,IF('Input sheet'!K18>0,'Input sheet'!K18)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN18*('Summary sheet'!$M17/'Summary sheet'!$L17) =AN18*('Summary sheet'!$N17/'Summary sheet'!$L17)

=(IF('Input sheet'!K19=0,'Input sheet'!M19,IF('Input sheet'!K19>0,'Input sheet'!K19)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN19*('Summary sheet'!$M18/'Summary sheet'!$L18) =AN19*('Summary sheet'!$N18/'Summary sheet'!$L18)

=(IF('Input sheet'!K20=0,'Input sheet'!M20,IF('Input sheet'!K20>0,'Input sheet'!K20)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN20*('Summary sheet'!$M19/'Summary sheet'!$L19) =AN20*('Summary sheet'!$N19/'Summary sheet'!$L19)

=(IF('Input sheet'!K21=0,'Input sheet'!M21,IF('Input sheet'!K21>0,'Input sheet'!K21)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN21*('Summary sheet'!$M20/'Summary sheet'!$L20) =AN21*('Summary sheet'!$N20/'Summary sheet'!$L20)

=(IF('Input sheet'!K22=0,'Input sheet'!M22,IF('Input sheet'!K22>0,'Input sheet'!K22)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN22*('Summary sheet'!$M21/'Summary sheet'!$L21) =AN22*('Summary sheet'!$N21/'Summary sheet'!$L21)

=(IF('Input sheet'!K23=0,'Input sheet'!M23,IF('Input sheet'!K23>0,'Input sheet'!K23)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN23*('Summary sheet'!$M22/'Summary sheet'!$L22) =AN23*('Summary sheet'!$N22/'Summary sheet'!$L22)

=(IF('Input sheet'!K24=0,'Input sheet'!M24,IF('Input sheet'!K24>0,'Input sheet'!K24)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN24*('Summary sheet'!$M23/'Summary sheet'!$L23) =AN24*('Summary sheet'!$N23/'Summary sheet'!$L23)

=(IF('Input sheet'!K25=0,'Input sheet'!M25,IF('Input sheet'!K25>0,'Input sheet'!K25)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN25*('Summary sheet'!$M24/'Summary sheet'!$L24) =AN25*('Summary sheet'!$N24/'Summary sheet'!$L24)

=(IF('Input sheet'!K26=0,'Input sheet'!M26,IF('Input sheet'!K26>0,'Input sheet'!K26)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN26*('Summary sheet'!$M25/'Summary sheet'!$L25) =AN26*('Summary sheet'!$N25/'Summary sheet'!$L25)

=(IF('Input sheet'!K27=0,'Input sheet'!M27,IF('Input sheet'!K27>0,'Input sheet'!K27)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN27*('Summary sheet'!$M26/'Summary sheet'!$L26) =AN27*('Summary sheet'!$N26/'Summary sheet'!$L26)

=(IF('Input sheet'!K28=0,'Input sheet'!M28,IF('Input sheet'!K28>0,'Input sheet'!K28)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN28*('Summary sheet'!$M27/'Summary sheet'!$L27) =AN28*('Summary sheet'!$N27/'Summary sheet'!$L27)

=(IF('Input sheet'!K29=0,'Input sheet'!M29,IF('Input sheet'!K29>0,'Input sheet'!K29)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN29*('Summary sheet'!$M28/'Summary sheet'!$L28) =AN29*('Summary sheet'!$N28/'Summary sheet'!$L28)

=(IF('Input sheet'!K30=0,'Input sheet'!M30,IF('Input sheet'!K30>0,'Input sheet'!K30)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN30*('Summary sheet'!$M29/'Summary sheet'!$L29) =AN30*('Summary sheet'!$N29/'Summary sheet'!$L29)

=(IF('Input sheet'!K31=0,'Input sheet'!M31,IF('Input sheet'!K31>0,'Input sheet'!K31)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN31*('Summary sheet'!$M30/'Summary sheet'!$L30) =AN31*('Summary sheet'!$N30/'Summary sheet'!$L30)

=(IF('Input sheet'!K32=0,'Input sheet'!M32,IF('Input sheet'!K32>0,'Input sheet'!K32)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN32*('Summary sheet'!$M31/'Summary sheet'!$L31) =AN32*('Summary sheet'!$N31/'Summary sheet'!$L31)

=(IF('Input sheet'!K33=0,'Input sheet'!M33,IF('Input sheet'!K33>0,'Input sheet'!K33)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN33*('Summary sheet'!$M32/'Summary sheet'!$L32) =AN33*('Summary sheet'!$N32/'Summary sheet'!$L32)

=(IF('Input sheet'!K34=0,'Input sheet'!M34,IF('Input sheet'!K34>0,'Input sheet'!K34)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN34*('Summary sheet'!$M33/'Summary sheet'!$L33) =AN34*('Summary sheet'!$N33/'Summary sheet'!$L33)

=(IF('Input sheet'!K35=0,'Input sheet'!M35,IF('Input sheet'!K35>0,'Input sheet'!K35)))*(IF('Input sheet'!$K$5=0,'Input sheet'!M$5,IF('Input sheet'!$K$5>0,'Input sheet'!$K$5))) =AN35*('Summary sheet'!$M34/'Summary sheet'!$L34) =AN35*('Summary sheet'!$N34/'Summary sheet'!$L34)

Composter 2 throughput from AD plant when operational

Page 220: Waste management model

220

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

=AP7+1 =AQ7+1 =AR7+1 =AS7+1 =AT7+1 =AU7+1

Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste Total Municipal Waste Contract Household Waste Contract Waste other than

Household Waste

='Input sheet'!H11*'Reference model Formulas'!$AQ$10 =AQ11*('Summary sheet'!$M10/'Summary sheet'!$L10) =AQ11*('Summary sheet'!$N10/'Summary sheet'!$L10) =AK11+AN11+AQ11 =AL11+AO11+AR11 =AM11+AP11+AS11

='Input sheet'!H12*'Reference model Formulas'!$AQ$10 =AQ12*('Summary sheet'!$M11/'Summary sheet'!$L11) =AQ12*('Summary sheet'!$N11/'Summary sheet'!$L11) =AK12+AN12+AQ12 =AL12+AO12+AR12 =AM12+AP12+AS12

='Input sheet'!H13*'Reference model Formulas'!$AQ$10 =AQ13*('Summary sheet'!$M12/'Summary sheet'!$L12) =AQ13*('Summary sheet'!$N12/'Summary sheet'!$L12) =AK13+AN13+AQ13 =AL13+AO13+AR13 =AM13+AP13+AS13

='Input sheet'!H14*'Reference model Formulas'!$AQ$10 =AQ14*('Summary sheet'!$M13/'Summary sheet'!$L13) =AQ14*('Summary sheet'!$N13/'Summary sheet'!$L13) =AK14+AN14+AQ14 =AL14+AO14+AR14 =AM14+AP14+AS14

='Input sheet'!H15*'Reference model Formulas'!$AQ$10 =AQ15*('Summary sheet'!$M14/'Summary sheet'!$L14) =AQ15*('Summary sheet'!$N14/'Summary sheet'!$L14) =AK15+AN15+AQ15 =AL15+AO15+AR15 =AM15+AP15+AS15

='Input sheet'!H16*'Reference model Formulas'!$AQ$10 =AQ16*('Summary sheet'!$M15/'Summary sheet'!$L15) =AQ16*('Summary sheet'!$N15/'Summary sheet'!$L15) =AK16+AN16+AQ16 =AL16+AO16+AR16 =AM16+AP16+AS16

='Input sheet'!H17*'Reference model Formulas'!$AQ$10 =AQ17*('Summary sheet'!$M16/'Summary sheet'!$L16) =AQ17*('Summary sheet'!$N16/'Summary sheet'!$L16) =AK17+AN17+AQ17 =AL17+AO17+AR17 =AM17+AP17+AS17

='Input sheet'!H18*'Reference model Formulas'!$AQ$10 =AQ18*('Summary sheet'!$M17/'Summary sheet'!$L17) =AQ18*('Summary sheet'!$N17/'Summary sheet'!$L17) =AK18+AN18+AQ18 =AL18+AO18+AR18 =AM18+AP18+AS18

='Input sheet'!H19*'Reference model Formulas'!$AQ$10 =AQ19*('Summary sheet'!$M18/'Summary sheet'!$L18) =AQ19*('Summary sheet'!$N18/'Summary sheet'!$L18) =AK19+AN19+AQ19 =AL19+AO19+AR19 =AM19+AP19+AS19

='Input sheet'!H20*'Reference model Formulas'!$AQ$10 =AQ20*('Summary sheet'!$M19/'Summary sheet'!$L19) =AQ20*('Summary sheet'!$N19/'Summary sheet'!$L19) =AK20+AN20+AQ20 =AL20+AO20+AR20 =AM20+AP20+AS20

='Input sheet'!H21*'Reference model Formulas'!$AQ$10 =AQ21*('Summary sheet'!$M20/'Summary sheet'!$L20) =AQ21*('Summary sheet'!$N20/'Summary sheet'!$L20) =AK21+AN21+AQ21 =AL21+AO21+AR21 =AM21+AP21+AS21

='Input sheet'!H22*'Reference model Formulas'!$AQ$10 =AQ22*('Summary sheet'!$M21/'Summary sheet'!$L21) =AQ22*('Summary sheet'!$N21/'Summary sheet'!$L21) =AK22+AN22+AQ22 =AL22+AO22+AR22 =AM22+AP22+AS22

='Input sheet'!H23*'Reference model Formulas'!$AQ$10 =AQ23*('Summary sheet'!$M22/'Summary sheet'!$L22) =AQ23*('Summary sheet'!$N22/'Summary sheet'!$L22) =AK23+AN23+AQ23 =AL23+AO23+AR23 =AM23+AP23+AS23

='Input sheet'!H24*'Reference model Formulas'!$AQ$10 =AQ24*('Summary sheet'!$M23/'Summary sheet'!$L23) =AQ24*('Summary sheet'!$N23/'Summary sheet'!$L23) =AK24+AN24+AQ24 =AL24+AO24+AR24 =AM24+AP24+AS24

='Input sheet'!H25*'Reference model Formulas'!$AQ$10 =AQ25*('Summary sheet'!$M24/'Summary sheet'!$L24) =AQ25*('Summary sheet'!$N24/'Summary sheet'!$L24) =AK25+AN25+AQ25 =AL25+AO25+AR25 =AM25+AP25+AS25

='Input sheet'!H26*'Reference model Formulas'!$AQ$10 =AQ26*('Summary sheet'!$M25/'Summary sheet'!$L25) =AQ26*('Summary sheet'!$N25/'Summary sheet'!$L25) =AK26+AN26+AQ26 =AL26+AO26+AR26 =AM26+AP26+AS26

='Input sheet'!H27*'Reference model Formulas'!$AQ$10 =AQ27*('Summary sheet'!$M26/'Summary sheet'!$L26) =AQ27*('Summary sheet'!$N26/'Summary sheet'!$L26) =AK27+AN27+AQ27 =AL27+AO27+AR27 =AM27+AP27+AS27

='Input sheet'!H28*'Reference model Formulas'!$AQ$10 =AQ28*('Summary sheet'!$M27/'Summary sheet'!$L27) =AQ28*('Summary sheet'!$N27/'Summary sheet'!$L27) =AK28+AN28+AQ28 =AL28+AO28+AR28 =AM28+AP28+AS28

='Input sheet'!H29*'Reference model Formulas'!$AQ$10 =AQ29*('Summary sheet'!$M28/'Summary sheet'!$L28) =AQ29*('Summary sheet'!$N28/'Summary sheet'!$L28) =AK29+AN29+AQ29 =AL29+AO29+AR29 =AM29+AP29+AS29

='Input sheet'!H30*'Reference model Formulas'!$AQ$10 =AQ30*('Summary sheet'!$M29/'Summary sheet'!$L29) =AQ30*('Summary sheet'!$N29/'Summary sheet'!$L29) =AK30+AN30+AQ30 =AL30+AO30+AR30 =AM30+AP30+AS30

='Input sheet'!H31*'Reference model Formulas'!$AQ$10 =AQ31*('Summary sheet'!$M30/'Summary sheet'!$L30) =AQ31*('Summary sheet'!$N30/'Summary sheet'!$L30) =AK31+AN31+AQ31 =AL31+AO31+AR31 =AM31+AP31+AS31

='Input sheet'!H32*'Reference model Formulas'!$AQ$10 =AQ32*('Summary sheet'!$M31/'Summary sheet'!$L31) =AQ32*('Summary sheet'!$N31/'Summary sheet'!$L31) =AK32+AN32+AQ32 =AL32+AO32+AR32 =AM32+AP32+AS32

='Input sheet'!H33*'Reference model Formulas'!$AQ$10 =AQ33*('Summary sheet'!$M32/'Summary sheet'!$L32) =AQ33*('Summary sheet'!$N32/'Summary sheet'!$L32) =AK33+AN33+AQ33 =AL33+AO33+AR33 =AM33+AP33+AS33

='Input sheet'!H34*'Reference model Formulas'!$AQ$10 =AQ34*('Summary sheet'!$M33/'Summary sheet'!$L33) =AQ34*('Summary sheet'!$N33/'Summary sheet'!$L33) =AK34+AN34+AQ34 =AL34+AO34+AR34 =AM34+AP34+AS34

='Input sheet'!H35*'Reference model Formulas'!$AQ$10 =AQ35*('Summary sheet'!$M34/'Summary sheet'!$L34) =AQ35*('Summary sheet'!$N34/'Summary sheet'!$L34) =AK35+AN35+AQ35 =AL35+AO35+AR35 =AM35+AP35+AS35

On-farm Total diversion of Household Waste from landfill through composters

Page 221: Waste management model

221

Percentage of Household Waste

diverted by composting

Household Waste

diverted by use of bring

banks

HWS Bring banksPercentage of Household Waste

stream that is diverted by Bring banks

Third party recycling outside

of contract

Percentage of Household Waste

stream that is diverted by Third Party

(Percentage) (tonnes) (tonnes) (Percentage) (tonnes) (Percentage) (tonnes)

=AV7+1 =AW7+1 =AY7+1 =AZ7+1 =BA7+1 =BC7+1 =BD7+1 =BF7+1 =BG7+1 =BH7+1

Total Municipal Waste Total Municipal Waste Total Municipal Waste Total Municipal Waste Third Party Waste Total Municipal Waste Total Municipal Waste Contract Household Waste Contract Waste other than

Household Waste Third Party Waste

=AT11/'Summary sheet'!H10 ='Input sheet'!P11 ='Input sheet'!Q11 =(AY11+AZ11)/'Summary sheet'!H10 ='Input sheet'!N11 =BC11/'Summary sheet'!H10 =BI11+BH11+BG11 =AU11+AC11+AY11+AZ11 =AV11+AD11 =BC11

=AT12/'Summary sheet'!H11 ='Input sheet'!P12 ='Input sheet'!Q12 =(AY12+AZ12)/'Summary sheet'!H11 ='Input sheet'!N12 =BC12/'Summary sheet'!H11 =BI12+BH12+BG12 =AU12+AC12+AY12+AZ12 =AV12+AD12 =BC12

=AT13/'Summary sheet'!H12 ='Input sheet'!P13 ='Input sheet'!Q13 =(AY13+AZ13)/'Summary sheet'!H12 ='Input sheet'!N13 =BC13/'Summary sheet'!H12 =BI13+BH13+BG13 =AU13+AC13+AY13+AZ13 =AV13+AD13 =BC13

=AT14/'Summary sheet'!H13 ='Input sheet'!P14 ='Input sheet'!Q14 =(AY14+AZ14)/'Summary sheet'!H13 ='Input sheet'!N14 =BC14/'Summary sheet'!H13 =BI14+BH14+BG14 =AU14+AC14+AY14+AZ14 =AV14+AD14 =BC14

=AT15/'Summary sheet'!H14 ='Input sheet'!P15 ='Input sheet'!Q15 =(AY15+AZ15)/'Summary sheet'!H14 ='Input sheet'!N15 =BC15/'Summary sheet'!H14 =BI15+BH15+BG15 =AU15+AC15+AY15+AZ15 =AV15+AD15 =BC15

=AT16/'Summary sheet'!H15 ='Input sheet'!P16 ='Input sheet'!Q16 =(AY16+AZ16)/'Summary sheet'!H15 ='Input sheet'!N16 =BC16/'Summary sheet'!H15 =BI16+BH16+BG16 =AU16+AC16+AY16+AZ16 =AV16+AD16 =BC16

=AT17/'Summary sheet'!H16 ='Input sheet'!P17 ='Input sheet'!Q17 =(AY17+AZ17)/'Summary sheet'!H16 ='Input sheet'!N17 =BC17/'Summary sheet'!H16 =BI17+BH17+BG17 =AU17+AC17+AY17+AZ17 =AV17+AD17 =BC17

=AT18/'Summary sheet'!H17 ='Input sheet'!P18 ='Input sheet'!Q18 =(AY18+AZ18)/'Summary sheet'!H17 ='Input sheet'!N18 =BC18/'Summary sheet'!H17 =BI18+BH18+BG18 =AU18+AC18+AY18+AZ18 =AV18+AD18 =BC18

=AT19/'Summary sheet'!H18 ='Input sheet'!P19 ='Input sheet'!Q19 =(AY19+AZ19)/'Summary sheet'!H18 ='Input sheet'!N19 =BC19/'Summary sheet'!H18 =BI19+BH19+BG19 =AU19+AC19+AY19+AZ19 =AV19+AD19 =BC19

=AT20/'Summary sheet'!H19 ='Input sheet'!P20 ='Input sheet'!Q20 =(AY20+AZ20)/'Summary sheet'!H19 ='Input sheet'!N20 =BC20/'Summary sheet'!H19 =BI20+BH20+BG20 =AU20+AC20+AY20+AZ20 =AV20+AD20 =BC20

=AT21/'Summary sheet'!H20 ='Input sheet'!P21 ='Input sheet'!Q21 =(AY21+AZ21)/'Summary sheet'!H20 ='Input sheet'!N21 =BC21/'Summary sheet'!H20 =BI21+BH21+BG21 =AU21+AC21+AY21+AZ21 =AV21+AD21 =BC21

=AT22/'Summary sheet'!H21 ='Input sheet'!P22 ='Input sheet'!Q22 =(AY22+AZ22)/'Summary sheet'!H21 ='Input sheet'!N22 =BC22/'Summary sheet'!H21 =BI22+BH22+BG22 =AU22+AC22+AY22+AZ22 =AV22+AD22 =BC22

=AT23/'Summary sheet'!H22 ='Input sheet'!P23 ='Input sheet'!Q23 =(AY23+AZ23)/'Summary sheet'!H22 ='Input sheet'!N23 =BC23/'Summary sheet'!H22 =BI23+BH23+BG23 =AU23+AC23+AY23+AZ23 =AV23+AD23 =BC23

=AT24/'Summary sheet'!H23 ='Input sheet'!P24 ='Input sheet'!Q24 =(AY24+AZ24)/'Summary sheet'!H23 ='Input sheet'!N24 =BC24/'Summary sheet'!H23 =AT24+AB24+AY24+AZ24+BC24=AU24+AC24+AY24+AZ24 =AV24+AD24 =BC24

=AT25/'Summary sheet'!H24 ='Input sheet'!P25 ='Input sheet'!Q25 =(AY25+AZ25)/'Summary sheet'!H24 ='Input sheet'!N25 =BC25/'Summary sheet'!H24 =AT25+AB25+AY25+AZ25+BC25=AU25+AC25+AY25+AZ25 =AV25+AD25 =BC25

=AT26/'Summary sheet'!H25 ='Input sheet'!P26 ='Input sheet'!Q26 =(AY26+AZ26)/'Summary sheet'!H25 ='Input sheet'!N26 =BC26/'Summary sheet'!H25 =AT26+AB26+AY26+AZ26+BC26=AU26+AC26+AY26+AZ26 =AV26+AD26 =BC26

=AT27/'Summary sheet'!H26 ='Input sheet'!P27 ='Input sheet'!Q27 =(AY27+AZ27)/'Summary sheet'!H26 ='Input sheet'!N27 =BC27/'Summary sheet'!H26 =AT27+AB27+AY27+AZ27+BC27=AU27+AC27+AY27+AZ27 =AV27+AD27 =BC27

=AT28/'Summary sheet'!H27 ='Input sheet'!P28 ='Input sheet'!Q28 =(AY28+AZ28)/'Summary sheet'!H27 ='Input sheet'!N28 =BC28/'Summary sheet'!H27 =AT28+AB28+AY28+AZ28+BC28=AU28+AC28+AY28+AZ28 =AV28+AD28 =BC28

=AT29/'Summary sheet'!H28 ='Input sheet'!P29 ='Input sheet'!Q29 =(AY29+AZ29)/'Summary sheet'!H28 ='Input sheet'!N29 =BC29/'Summary sheet'!H28 =AT29+AB29+AY29+AZ29+BC29=AU29+AC29+AY29+AZ29 =AV29+AD29 =BC29

=AT30/'Summary sheet'!H29 ='Input sheet'!P30 ='Input sheet'!Q30 =(AY30+AZ30)/'Summary sheet'!H29 ='Input sheet'!N30 =BC30/'Summary sheet'!H29 =AT30+AB30+AY30+AZ30+BC30=AU30+AC30+AY30+AZ30 =AV30+AD30 =BC30

=AT31/'Summary sheet'!H30 ='Input sheet'!P31 ='Input sheet'!Q31 =(AY31+AZ31)/'Summary sheet'!H30 ='Input sheet'!N31 =BC31/'Summary sheet'!H30 =AT31+AB31+AY31+AZ31+BC31=AU31+AC31+AY31+AZ31 =AV31+AD31 =BC31

=AT32/'Summary sheet'!H31 ='Input sheet'!P32 ='Input sheet'!Q32 =(AY32+AZ32)/'Summary sheet'!H31 ='Input sheet'!N32 =BC32/'Summary sheet'!H31 =AT32+AB32+AY32+AZ32+BC32=AU32+AC32+AY32+AZ32 =AV32+AD32 =BC32

=AT33/'Summary sheet'!H32 ='Input sheet'!P33 ='Input sheet'!Q33 =(AY33+AZ33)/'Summary sheet'!H32 ='Input sheet'!N33 =BC33/'Summary sheet'!H32 =AT33+AB33+AY33+AZ33+BC33=AU33+AC33+AY33+AZ33 =AV33+AD33 =BC33

=AT34/'Summary sheet'!H33 ='Input sheet'!P34 ='Input sheet'!Q34 =(AY34+AZ34)/'Summary sheet'!H33 ='Input sheet'!N34 =BC34/'Summary sheet'!H33 =AT34+AB34+AY34+AZ34+BC34=AU34+AC34+AY34+AZ34 =AV34+AD34 =BC34

=AT35/'Summary sheet'!H34 ='Input sheet'!P35 ='Input sheet'!Q35 =(AY35+AZ35)/'Summary sheet'!H34 ='Input sheet'!N35 =BC35/'Summary sheet'!H34 =AT35+AB35+AY35+AZ35+BC35=AU35+AC35+AY35+AZ35 =AV35+AD35 =BC35

Diversion of Waste from landfill via recycling

Page 222: Waste management model

222

RDF Anaerobic digestion

Household Waste stream recycled Capacity of plantDiversion of Municipal

Waste from landfill via RDF

Percentage of Municipal

Waste recovery by RDF

(Percentage) (tonnes) (tonnes) (Percentage) (tonnes) (tonnes) (tonnes)

=BI7+1 =BJ7+1 =BL7+1 =BM7+1 =BN7+1 =BP7+1 =BQ7+1

Total Municipal Waste Total Municipal Waste Total Municipal Waste Total Municipal Waste Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste

=BF11/'Summary sheet'!H10 ='Input sheet'!O11 =BL11*'Input sheet'!$O$5 =BM11/'Summary sheet'!F10 ='Input sheet'!I11 =BP11*('Summary sheet'!$M10/'Summary sheet'!$F10) =BP11*('Summary sheet'!$N10/'Summary sheet'!$L10)

=BF12/'Summary sheet'!H11 ='Input sheet'!O12 =BL12*'Input sheet'!$O$5 =BM12/'Summary sheet'!F11 ='Input sheet'!I12 =BP12*('Summary sheet'!$M11/'Summary sheet'!$L11) =BP12*('Summary sheet'!$N11/'Summary sheet'!$L11)

=BF13/'Summary sheet'!H12 ='Input sheet'!O13 =BL13*'Input sheet'!$O$5 =BM13/'Summary sheet'!F12 ='Input sheet'!I13 =BP13*('Summary sheet'!$M12/'Summary sheet'!$L12) =BP13*('Summary sheet'!$N12/'Summary sheet'!$L12)

=BF14/'Summary sheet'!H13 ='Input sheet'!O14 =BL14*'Input sheet'!$O$5 =BM14/'Summary sheet'!F13 ='Input sheet'!I14 =BP14*('Summary sheet'!$M13/'Summary sheet'!$L13) =BP14*('Summary sheet'!$N13/'Summary sheet'!$L13)

=BF15/'Summary sheet'!H14 ='Input sheet'!O15 =BL15*'Input sheet'!$O$5 =BM15/'Summary sheet'!F14 ='Input sheet'!I15 =BP15*('Summary sheet'!$M14/'Summary sheet'!$L14) =BP15*('Summary sheet'!$N14/'Summary sheet'!$L14)

=BF16/'Summary sheet'!H15 ='Input sheet'!O16 =BL16*'Input sheet'!$O$5 =BM16/'Summary sheet'!F15 ='Input sheet'!I16 =BP16*('Summary sheet'!$M15/'Summary sheet'!$L15) =BP16*('Summary sheet'!$N15/'Summary sheet'!$L15)

=BF17/'Summary sheet'!H16 ='Input sheet'!O17 0 0 ='Input sheet'!I17 =BP17*('Summary sheet'!$M16/'Summary sheet'!$L16) =BP17*('Summary sheet'!$N16/'Summary sheet'!$L16)

=BF18/'Summary sheet'!H17 ='Input sheet'!O18 0 0 ='Input sheet'!I18 =BP18*('Summary sheet'!$M17/'Summary sheet'!$L17) =BP18*('Summary sheet'!$N17/'Summary sheet'!$L17)

=BF19/'Summary sheet'!H18 ='Input sheet'!O19 0 0 ='Input sheet'!I19 =BP19*('Summary sheet'!$M18/'Summary sheet'!$L18) =BP19*('Summary sheet'!$N18/'Summary sheet'!$L18)

=BF20/'Summary sheet'!H19 ='Input sheet'!O20 0 0 ='Input sheet'!I20 =BP20*('Summary sheet'!$M19/'Summary sheet'!$L19) =BP20*('Summary sheet'!$N19/'Summary sheet'!$L19)

=BF21/'Summary sheet'!H20 ='Input sheet'!O21 0 0 ='Input sheet'!I21 =BP21*('Summary sheet'!$M20/'Summary sheet'!$L20) =BP21*('Summary sheet'!$N20/'Summary sheet'!$L20)

=BF22/'Summary sheet'!H21 ='Input sheet'!O22 0 0 ='Input sheet'!I22 =BP22*('Summary sheet'!$M21/'Summary sheet'!$L21) =BP22*('Summary sheet'!$N21/'Summary sheet'!$L21)

=BF23/'Summary sheet'!H22 ='Input sheet'!O23 0 0 ='Input sheet'!I23 =BP23*('Summary sheet'!$M22/'Summary sheet'!$L22) =BP23*('Summary sheet'!$N22/'Summary sheet'!$L22)

=BF24/'Summary sheet'!H23 ='Input sheet'!O24 0 0 ='Input sheet'!I24 =BP24*('Summary sheet'!$M23/'Summary sheet'!$L23) =BP24*('Summary sheet'!$N23/'Summary sheet'!$L23)

=BF25/'Summary sheet'!H24 ='Input sheet'!O25 0 0 ='Input sheet'!I25 =BP25*('Summary sheet'!$M24/'Summary sheet'!$L24) =BP25*('Summary sheet'!$N24/'Summary sheet'!$L24)

=BF26/'Summary sheet'!H25 ='Input sheet'!O26 0 0 ='Input sheet'!I26 =BP26*('Summary sheet'!$M25/'Summary sheet'!$L25) =BP26*('Summary sheet'!$N25/'Summary sheet'!$L25)

=BF27/'Summary sheet'!H26 ='Input sheet'!O27 0 0 ='Input sheet'!I27 =BP27*('Summary sheet'!$M26/'Summary sheet'!$L26) =BP27*('Summary sheet'!$N26/'Summary sheet'!$L26)

=BF28/'Summary sheet'!H27 ='Input sheet'!O28 0 0 ='Input sheet'!I28 =BP28*('Summary sheet'!$M27/'Summary sheet'!$L27) =BP28*('Summary sheet'!$N27/'Summary sheet'!$L27)

=BF29/'Summary sheet'!H28 ='Input sheet'!O29 0 0 ='Input sheet'!I29 =BP29*('Summary sheet'!$M28/'Summary sheet'!$L28) =BP29*('Summary sheet'!$N28/'Summary sheet'!$L28)

=BF30/'Summary sheet'!H29 ='Input sheet'!O30 0 0 ='Input sheet'!I30 =BP30*('Summary sheet'!$M29/'Summary sheet'!$L29) =BP30*('Summary sheet'!$N29/'Summary sheet'!$L29)

=BF31/'Summary sheet'!H30 ='Input sheet'!O31 0 0 ='Input sheet'!I31 =BP31*('Summary sheet'!$M30/'Summary sheet'!$L30) =BP31*('Summary sheet'!$N30/'Summary sheet'!$L30)

=BF32/'Summary sheet'!H31 ='Input sheet'!O32 0 0 ='Input sheet'!I32 =BP32*('Summary sheet'!$M31/'Summary sheet'!$L31) =BP32*('Summary sheet'!$N31/'Summary sheet'!$L31)

=BF33/'Summary sheet'!H32 ='Input sheet'!O33 0 0 ='Input sheet'!I33 =BP33*('Summary sheet'!$M32/'Summary sheet'!$L32) =BP33*('Summary sheet'!$N32/'Summary sheet'!$L32)

=BF34/'Summary sheet'!H33 ='Input sheet'!O34 0 0 ='Input sheet'!I34 =BP34*('Summary sheet'!$M33/'Summary sheet'!$L33) =BP34*('Summary sheet'!$N33/'Summary sheet'!$L33)

=BF35/'Summary sheet'!H34 ='Input sheet'!O35 0 0 ='Input sheet'!I35 =BP35*('Summary sheet'!$M34/'Summary sheet'!$L34) =BP35*('Summary sheet'!$N34/'Summary sheet'!$L34)

Capacity of plant

Page 223: Waste management model

223

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

=BR7+1 =BS7+1 =BT7+1 =BU7+1 =BV7+1 =BW7+1

Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste

=BP11*$BS$10 =BS11*('Summary sheet'!$M10/'Summary sheet'!$F10) =BS11*('Summary sheet'!$N10/'Summary sheet'!$L10) =BP11-BS11 =BV11*('Summary sheet'!$M10/'Summary sheet'!$F10) =BV11*('Summary sheet'!$N10/'Summary sheet'!$L10)

=BP12*$BS$10 =BS12*('Summary sheet'!$M11/'Summary sheet'!$L11) =BS12*('Summary sheet'!$N11/'Summary sheet'!$L11) =BP12-BS12 =BV12*('Summary sheet'!$M11/'Summary sheet'!$L11) =BV12*('Summary sheet'!$N11/'Summary sheet'!$L11)

=BP13*$BS$10 =BS13*('Summary sheet'!$M12/'Summary sheet'!$L12) =BS13*('Summary sheet'!$N12/'Summary sheet'!$L12) =BP13-BS13 =BV13*('Summary sheet'!$M12/'Summary sheet'!$L12) =BV13*('Summary sheet'!$N12/'Summary sheet'!$L12)

=BP14*$BS$10 =BS14*('Summary sheet'!$M13/'Summary sheet'!$L13) =BS14*('Summary sheet'!$N13/'Summary sheet'!$L13) =BP14-BS14 =BV14*('Summary sheet'!$M13/'Summary sheet'!$L13) =BV14*('Summary sheet'!$N13/'Summary sheet'!$L13)

=BP15*$BS$10 =BS15*('Summary sheet'!$M14/'Summary sheet'!$L14) =BS15*('Summary sheet'!$N14/'Summary sheet'!$L14) =BP15-BS15 =BV15*('Summary sheet'!$M14/'Summary sheet'!$L14) =BV15*('Summary sheet'!$N14/'Summary sheet'!$L14)

=BP16*$BS$10 =BS16*('Summary sheet'!$M15/'Summary sheet'!$L15) =BS16*('Summary sheet'!$N15/'Summary sheet'!$L15) =BP16-BS16 =BV16*('Summary sheet'!$M15/'Summary sheet'!$L15) =BV16*('Summary sheet'!$N15/'Summary sheet'!$L15)

=BP17*$BS$10 =BS17*('Summary sheet'!$M16/'Summary sheet'!$L16) =BS17*('Summary sheet'!$N16/'Summary sheet'!$L16) =BP17-BS17 =BV17*('Summary sheet'!$M16/'Summary sheet'!$L16) =BV17*('Summary sheet'!$N16/'Summary sheet'!$L16)

=BP18*$BS$10 =BS18*('Summary sheet'!$M17/'Summary sheet'!$L17) =BS18*('Summary sheet'!$N17/'Summary sheet'!$L17) =BP18-BS18 =BV18*('Summary sheet'!$M17/'Summary sheet'!$L17) =BV18*('Summary sheet'!$N17/'Summary sheet'!$L17)

=BP19*$BS$10 =BS19*('Summary sheet'!$M18/'Summary sheet'!$L18) =BS19*('Summary sheet'!$N18/'Summary sheet'!$L18) =BP19-BS19 =BV19*('Summary sheet'!$M18/'Summary sheet'!$L18) =BV19*('Summary sheet'!$N18/'Summary sheet'!$L18)

=BP20*$BS$10 =BS20*('Summary sheet'!$M19/'Summary sheet'!$L19) =BS20*('Summary sheet'!$N19/'Summary sheet'!$L19) =BP20-BS20 =BV20*('Summary sheet'!$M19/'Summary sheet'!$L19) =BV20*('Summary sheet'!$N19/'Summary sheet'!$L19)

=BP21*$BS$10 =BS21*('Summary sheet'!$M20/'Summary sheet'!$L20) =BS21*('Summary sheet'!$N20/'Summary sheet'!$L20) =BP21-BS21 =BV21*('Summary sheet'!$M20/'Summary sheet'!$L20) =BV21*('Summary sheet'!$N20/'Summary sheet'!$L20)

=BP22*$BS$10 =BS22*('Summary sheet'!$M21/'Summary sheet'!$L21) =BS22*('Summary sheet'!$N21/'Summary sheet'!$L21) =BP22-BS22 =BV22*('Summary sheet'!$M21/'Summary sheet'!$L21) =BV22*('Summary sheet'!$N21/'Summary sheet'!$L21)

=BP23*$BS$10 =BS23*('Summary sheet'!$M22/'Summary sheet'!$L22) =BS23*('Summary sheet'!$N22/'Summary sheet'!$L22) =BP23-BS23 =BV23*('Summary sheet'!$M22/'Summary sheet'!$L22) =BV23*('Summary sheet'!$N22/'Summary sheet'!$L22)

=BP24*$BS$10 =BS24*('Summary sheet'!$M23/'Summary sheet'!$L23) =BS24*('Summary sheet'!$N23/'Summary sheet'!$L23) =BP24-BS24 =BV24*('Summary sheet'!$M23/'Summary sheet'!$L23) =BV24*('Summary sheet'!$N23/'Summary sheet'!$L23)

=BP25*$BS$10 =BS25*('Summary sheet'!$M24/'Summary sheet'!$L24) =BS25*('Summary sheet'!$N24/'Summary sheet'!$L24) =BP25-BS25 =BV25*('Summary sheet'!$M24/'Summary sheet'!$L24) =BV25*('Summary sheet'!$N24/'Summary sheet'!$L24)

=BP26*$BS$10 =BS26*('Summary sheet'!$M25/'Summary sheet'!$L25) =BS26*('Summary sheet'!$N25/'Summary sheet'!$L25) =BP26-BS26 =BV26*('Summary sheet'!$M25/'Summary sheet'!$L25) =BV26*('Summary sheet'!$N25/'Summary sheet'!$L25)

=BP27*$BS$10 =BS27*('Summary sheet'!$M26/'Summary sheet'!$L26) =BS27*('Summary sheet'!$N26/'Summary sheet'!$L26) =BP27-BS27 =BV27*('Summary sheet'!$M26/'Summary sheet'!$L26) =BV27*('Summary sheet'!$N26/'Summary sheet'!$L26)

=BP28*$BS$10 =BS28*('Summary sheet'!$M27/'Summary sheet'!$L27) =BS28*('Summary sheet'!$N27/'Summary sheet'!$L27) =BP28-BS28 =BV28*('Summary sheet'!$M27/'Summary sheet'!$L27) =BV28*('Summary sheet'!$N27/'Summary sheet'!$L27)

=BP29*$BS$10 =BS29*('Summary sheet'!$M28/'Summary sheet'!$L28) =BS29*('Summary sheet'!$N28/'Summary sheet'!$L28) =BP29-BS29 =BV29*('Summary sheet'!$M28/'Summary sheet'!$L28) =BV29*('Summary sheet'!$N28/'Summary sheet'!$L28)

=BP30*$BS$10 =BS30*('Summary sheet'!$M29/'Summary sheet'!$L29) =BS30*('Summary sheet'!$N29/'Summary sheet'!$L29) =BP30-BS30 =BV30*('Summary sheet'!$M29/'Summary sheet'!$L29) =BV30*('Summary sheet'!$N29/'Summary sheet'!$L29)

=BP31*$BS$10 =BS31*('Summary sheet'!$M30/'Summary sheet'!$L30) =BS31*('Summary sheet'!$N30/'Summary sheet'!$L30) =BP31-BS31 =BV31*('Summary sheet'!$M30/'Summary sheet'!$L30) =BV31*('Summary sheet'!$N30/'Summary sheet'!$L30)

=BP32*$BS$10 =BS32*('Summary sheet'!$M31/'Summary sheet'!$L31) =BS32*('Summary sheet'!$N31/'Summary sheet'!$L31) =BP32-BS32 =BV32*('Summary sheet'!$M31/'Summary sheet'!$L31) =BV32*('Summary sheet'!$N31/'Summary sheet'!$L31)

=BP33*$BS$10 =BS33*('Summary sheet'!$M32/'Summary sheet'!$L32) =BS33*('Summary sheet'!$N32/'Summary sheet'!$L32) =BP33-BS33 =BV33*('Summary sheet'!$M32/'Summary sheet'!$L32) =BV33*('Summary sheet'!$N32/'Summary sheet'!$L32)

=BP34*$BS$10 =BS34*('Summary sheet'!$M33/'Summary sheet'!$L33) =BS34*('Summary sheet'!$N33/'Summary sheet'!$L33) =BP34-BS34 =BV34*('Summary sheet'!$M33/'Summary sheet'!$L33) =BV34*('Summary sheet'!$N33/'Summary sheet'!$L33)

=BP35*$BS$10 =BS35*('Summary sheet'!$M34/'Summary sheet'!$L34) =BS35*('Summary sheet'!$N34/'Summary sheet'!$L34) =BP35-BS35 =BV35*('Summary sheet'!$M34/'Summary sheet'!$L34) =BV35*('Summary sheet'!$N34/'Summary sheet'!$L34)

Residue to compostingDiversion of Municipal Waste from landfill via AD

Page 224: Waste management model

224

Percentage of Municipal

Waste recovery by AD

(Percentage) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

=BX7+1 =BY7+1 =CA7+1 =CB7+1 =CC7+1 =CD7+1 =CE7+1

Total Municipal Waste Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste

=BS11/'Summary sheet'!F10 ='Input sheet'!R11 =CA11*('Summary sheet'!$M10/'Summary sheet'!$F10) =CA11*('Summary sheet'!$N10/'Summary sheet'!$L10) =CA11*$CD$10 =CD11*('Summary sheet'!$M10/'Summary sheet'!$F10) =CD11*('Summary sheet'!$N10/'Summary sheet'!$L10)

=BS12/'Summary sheet'!F11 ='Input sheet'!R12 =CA12*('Summary sheet'!$M11/'Summary sheet'!$L11) =CA12*('Summary sheet'!$N11/'Summary sheet'!$L11) =CA12*$CD$10 =CD12*('Summary sheet'!$M11/'Summary sheet'!$L11) =CD12*('Summary sheet'!$N11/'Summary sheet'!$L11)

=BS13/'Summary sheet'!F12 ='Input sheet'!R13 =CA13*('Summary sheet'!$M12/'Summary sheet'!$L12) =CA13*('Summary sheet'!$N12/'Summary sheet'!$L12) =CA13*$CD$10 =CD13*('Summary sheet'!$M12/'Summary sheet'!$L12) =CD13*('Summary sheet'!$N12/'Summary sheet'!$L12)

=BS14/'Summary sheet'!F13 ='Input sheet'!R14 =CA14*('Summary sheet'!$M13/'Summary sheet'!$L13) =CA14*('Summary sheet'!$N13/'Summary sheet'!$L13) =CA14*$CD$10 =CD14*('Summary sheet'!$M13/'Summary sheet'!$L13) =CD14*('Summary sheet'!$N13/'Summary sheet'!$L13)

=BS15/'Summary sheet'!F14 ='Input sheet'!R15 =CA15*('Summary sheet'!$M14/'Summary sheet'!$L14) =CA15*('Summary sheet'!$N14/'Summary sheet'!$L14) =CA15*$CD$10 =CD15*('Summary sheet'!$M14/'Summary sheet'!$L14) =CD15*('Summary sheet'!$N14/'Summary sheet'!$L14)

=BS16/'Summary sheet'!F15 ='Input sheet'!R16 =CA16*('Summary sheet'!$M15/'Summary sheet'!$L15) =CA16*('Summary sheet'!$N15/'Summary sheet'!$L15) =CA16*$CD$10 =CD16*('Summary sheet'!$M15/'Summary sheet'!$L15) =CD16*('Summary sheet'!$N15/'Summary sheet'!$L15)

=BS17/'Summary sheet'!F16 ='Input sheet'!R17 =CA17*('Summary sheet'!$M16/'Summary sheet'!$L16) =CA17*('Summary sheet'!$N16/'Summary sheet'!$L16) =CA17*$CD$10 =CD17*('Summary sheet'!$M16/'Summary sheet'!$L16) =CD17*('Summary sheet'!$N16/'Summary sheet'!$L16)

=BS18/'Summary sheet'!F17 ='Input sheet'!R18 =CA18*('Summary sheet'!$M17/'Summary sheet'!$L17) =CA18*('Summary sheet'!$N17/'Summary sheet'!$L17) =CA18*$CD$10 =CD18*('Summary sheet'!$M17/'Summary sheet'!$L17) =CD18*('Summary sheet'!$N17/'Summary sheet'!$L17)

=BS19/'Summary sheet'!F18 ='Input sheet'!R19 =CA19*('Summary sheet'!$M18/'Summary sheet'!$L18) =CA19*('Summary sheet'!$N18/'Summary sheet'!$L18) =CA19*$CD$10 =CD19*('Summary sheet'!$M18/'Summary sheet'!$L18) =CD19*('Summary sheet'!$N18/'Summary sheet'!$L18)

=BS20/'Summary sheet'!F19 ='Input sheet'!R20 =CA20*('Summary sheet'!$M19/'Summary sheet'!$L19) =CA20*('Summary sheet'!$N19/'Summary sheet'!$L19) =CA20*$CD$10 =CD20*('Summary sheet'!$M19/'Summary sheet'!$L19) =CD20*('Summary sheet'!$N19/'Summary sheet'!$L19)

=BS21/'Summary sheet'!F20 ='Input sheet'!R21 =CA21*('Summary sheet'!$M20/'Summary sheet'!$L20) =CA21*('Summary sheet'!$N20/'Summary sheet'!$L20) =CA21*$CD$10 =CD21*('Summary sheet'!$M20/'Summary sheet'!$L20) =CD21*('Summary sheet'!$N20/'Summary sheet'!$L20)

=BS22/'Summary sheet'!F21 ='Input sheet'!R22 =CA22*('Summary sheet'!$M21/'Summary sheet'!$L21) =CA22*('Summary sheet'!$N21/'Summary sheet'!$L21) =CA22*$CD$10 =CD22*('Summary sheet'!$M21/'Summary sheet'!$L21) =CD22*('Summary sheet'!$N21/'Summary sheet'!$L21)

=BS23/'Summary sheet'!F22 ='Input sheet'!R23 =CA23*('Summary sheet'!$M22/'Summary sheet'!$L22) =CA23*('Summary sheet'!$N22/'Summary sheet'!$L22) =CA23*$CD$10 =CD23*('Summary sheet'!$M22/'Summary sheet'!$L22) =CD23*('Summary sheet'!$N22/'Summary sheet'!$L22)

=BS24/'Summary sheet'!F23 ='Input sheet'!R24 =CA24*('Summary sheet'!$M23/'Summary sheet'!$L23) =CA24*('Summary sheet'!$N23/'Summary sheet'!$L23) =CA24*$CD$10 =CD24*('Summary sheet'!$M23/'Summary sheet'!$L23) =CD24*('Summary sheet'!$N23/'Summary sheet'!$L23)

=BS25/'Summary sheet'!F24 ='Input sheet'!R25 =CA25*('Summary sheet'!$M24/'Summary sheet'!$L24) =CA25*('Summary sheet'!$N24/'Summary sheet'!$L24) =CA25*$CD$10 =CD25*('Summary sheet'!$M24/'Summary sheet'!$L24) =CD25*('Summary sheet'!$N24/'Summary sheet'!$L24)

=BS26/'Summary sheet'!F25 ='Input sheet'!R26 =CA26*('Summary sheet'!$M25/'Summary sheet'!$L25) =CA26*('Summary sheet'!$N25/'Summary sheet'!$L25) =CA26*$CD$10 =CD26*('Summary sheet'!$M25/'Summary sheet'!$L25) =CD26*('Summary sheet'!$N25/'Summary sheet'!$L25)

=BS27/'Summary sheet'!F26 ='Input sheet'!R27 =CA27*('Summary sheet'!$M26/'Summary sheet'!$L26) =CA27*('Summary sheet'!$N26/'Summary sheet'!$L26) =CA27*$CD$10 =CD27*('Summary sheet'!$M26/'Summary sheet'!$L26) =CD27*('Summary sheet'!$N26/'Summary sheet'!$L26)

=BS28/'Summary sheet'!F27 ='Input sheet'!R28 =CA28*('Summary sheet'!$M27/'Summary sheet'!$L27) =CA28*('Summary sheet'!$N27/'Summary sheet'!$L27) =CA28*$CD$10 =CD28*('Summary sheet'!$M27/'Summary sheet'!$L27) =CD28*('Summary sheet'!$N27/'Summary sheet'!$L27)

=BS29/'Summary sheet'!F28 ='Input sheet'!R29 =CA29*('Summary sheet'!$M28/'Summary sheet'!$L28) =CA29*('Summary sheet'!$N28/'Summary sheet'!$L28) =CA29*$CD$10 =CD29*('Summary sheet'!$M28/'Summary sheet'!$L28) =CD29*('Summary sheet'!$N28/'Summary sheet'!$L28)

=BS30/'Summary sheet'!F29 ='Input sheet'!R30 =CA30*('Summary sheet'!$M29/'Summary sheet'!$L29) =CA30*('Summary sheet'!$N29/'Summary sheet'!$L29) =CA30*$CD$10 =CD30*('Summary sheet'!$M29/'Summary sheet'!$L29) =CD30*('Summary sheet'!$N29/'Summary sheet'!$L29)

=BS31/'Summary sheet'!F30 ='Input sheet'!R31 =CA31*('Summary sheet'!$M30/'Summary sheet'!$L30) =CA31*('Summary sheet'!$N30/'Summary sheet'!$L30) =CA31*$CD$10 =CD31*('Summary sheet'!$M30/'Summary sheet'!$L30) =CD31*('Summary sheet'!$N30/'Summary sheet'!$L30)

=BS32/'Summary sheet'!F31 ='Input sheet'!R32 =CA32*('Summary sheet'!$M31/'Summary sheet'!$L31) =CA32*('Summary sheet'!$N31/'Summary sheet'!$L31) =CA32*$CD$10 =CD32*('Summary sheet'!$M31/'Summary sheet'!$L31) =CD32*('Summary sheet'!$N31/'Summary sheet'!$L31)

=BS33/'Summary sheet'!F32 ='Input sheet'!R33 =CA33*('Summary sheet'!$M32/'Summary sheet'!$L32) =CA33*('Summary sheet'!$N32/'Summary sheet'!$L32) =CA33*$CD$10 =CD33*('Summary sheet'!$M32/'Summary sheet'!$L32) =CD33*('Summary sheet'!$N32/'Summary sheet'!$L32)

=BS34/'Summary sheet'!F33 ='Input sheet'!R34 =CA34*('Summary sheet'!$M33/'Summary sheet'!$L33) =CA34*('Summary sheet'!$N33/'Summary sheet'!$L33) =CA34*$CD$10 =CD34*('Summary sheet'!$M33/'Summary sheet'!$L33) =CD34*('Summary sheet'!$N33/'Summary sheet'!$L33)

=BS35/'Summary sheet'!F34 ='Input sheet'!R35 =CA35*('Summary sheet'!$M34/'Summary sheet'!$L34) =CA35*('Summary sheet'!$N34/'Summary sheet'!$L34) =CA35*$CD$10 =CD35*('Summary sheet'!$M34/'Summary sheet'!$L34) =CD35*('Summary sheet'!$N34/'Summary sheet'!$L34)

Throughput of EfW 1 Diversion of Municipal Waste from landfill via EfW 1

Page 225: Waste management model

225

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

=CF7+1 =CG7+1 =CH7+1 =CI7+1 =CJ7+1 =CK7+1

Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste

='Input sheet'!S11 =CG11*('Summary sheet'!$M10/'Summary sheet'!$F10) =CG11*('Summary sheet'!$N10/'Summary sheet'!$L10) =CG11*$CJ$10 =CJ11*('Summary sheet'!$M10/'Summary sheet'!$F10) =CJ11*('Summary sheet'!$N10/'Summary sheet'!$L10)

='Input sheet'!S12 =CG12*('Summary sheet'!$M11/'Summary sheet'!$L11) =CG12*('Summary sheet'!$N11/'Summary sheet'!$L11) =CG12*$CJ$10 =CJ12*('Summary sheet'!$M11/'Summary sheet'!$L11) =CJ12*('Summary sheet'!$N11/'Summary sheet'!$L11)

='Input sheet'!S13 =CG13*('Summary sheet'!$M12/'Summary sheet'!$L12) =CG13*('Summary sheet'!$N12/'Summary sheet'!$L12) =CG13*$CJ$10 =CJ13*('Summary sheet'!$M12/'Summary sheet'!$L12) =CJ13*('Summary sheet'!$N12/'Summary sheet'!$L12)

='Input sheet'!S14 =CG14*('Summary sheet'!$M13/'Summary sheet'!$L13) =CG14*('Summary sheet'!$N13/'Summary sheet'!$L13) =CG14*$CJ$10 =CJ14*('Summary sheet'!$M13/'Summary sheet'!$L13) =CJ14*('Summary sheet'!$N13/'Summary sheet'!$L13)

='Input sheet'!S15 =CG15*('Summary sheet'!$M14/'Summary sheet'!$L14) =CG15*('Summary sheet'!$N14/'Summary sheet'!$L14) =CG15*$CJ$10 =CJ15*('Summary sheet'!$M14/'Summary sheet'!$L14) =CJ15*('Summary sheet'!$N14/'Summary sheet'!$L14)

='Input sheet'!S16 =CG16*('Summary sheet'!$M15/'Summary sheet'!$L15) =CG16*('Summary sheet'!$N15/'Summary sheet'!$L15) =CG16*$CJ$10 =CJ16*('Summary sheet'!$M15/'Summary sheet'!$L15) =CJ16*('Summary sheet'!$N15/'Summary sheet'!$L15)

='Input sheet'!S17 =CG17*('Summary sheet'!$M16/'Summary sheet'!$L16) =CG17*('Summary sheet'!$N16/'Summary sheet'!$L16) =CG17*$CJ$10 =CJ17*('Summary sheet'!$M16/'Summary sheet'!$L16) =CJ17*('Summary sheet'!$N16/'Summary sheet'!$L16)

='Input sheet'!S18 =CG18*('Summary sheet'!$M17/'Summary sheet'!$L17) =CG18*('Summary sheet'!$N17/'Summary sheet'!$L17) =CG18*$CJ$10 =CJ18*('Summary sheet'!$M17/'Summary sheet'!$L17) =CJ18*('Summary sheet'!$N17/'Summary sheet'!$L17)

='Input sheet'!S19 =CG19*('Summary sheet'!$M18/'Summary sheet'!$L18) =CG19*('Summary sheet'!$N18/'Summary sheet'!$L18) =CG19*$CJ$10 =CJ19*('Summary sheet'!$M18/'Summary sheet'!$L18) =CJ19*('Summary sheet'!$N18/'Summary sheet'!$L18)

='Input sheet'!S20 =CG20*('Summary sheet'!$M19/'Summary sheet'!$L19) =CG20*('Summary sheet'!$N19/'Summary sheet'!$L19) =CG20*$CJ$10 =CJ20*('Summary sheet'!$M19/'Summary sheet'!$L19) =CJ20*('Summary sheet'!$N19/'Summary sheet'!$L19)

='Input sheet'!S21 =CG21*('Summary sheet'!$M20/'Summary sheet'!$L20) =CG21*('Summary sheet'!$N20/'Summary sheet'!$L20) =CG21*$CJ$10 =CJ21*('Summary sheet'!$M20/'Summary sheet'!$L20) =CJ21*('Summary sheet'!$N20/'Summary sheet'!$L20)

='Input sheet'!S22 =CG22*('Summary sheet'!$M21/'Summary sheet'!$L21) =CG22*('Summary sheet'!$N21/'Summary sheet'!$L21) =CG22*$CJ$10 =CJ22*('Summary sheet'!$M21/'Summary sheet'!$L21) =CJ22*('Summary sheet'!$N21/'Summary sheet'!$L21)

='Input sheet'!S23 =CG23*('Summary sheet'!$M22/'Summary sheet'!$L22) =CG23*('Summary sheet'!$N22/'Summary sheet'!$L22) =CG23*$CJ$10 =CJ23*('Summary sheet'!$M22/'Summary sheet'!$L22) =CJ23*('Summary sheet'!$N22/'Summary sheet'!$L22)

='Input sheet'!S24 =CG24*('Summary sheet'!$M23/'Summary sheet'!$L23) =CG24*('Summary sheet'!$N23/'Summary sheet'!$L23) =CG24*$CJ$10 =CJ24*('Summary sheet'!$M23/'Summary sheet'!$L23) =CJ24*('Summary sheet'!$N23/'Summary sheet'!$L23)

='Input sheet'!S25 =CG25*('Summary sheet'!$M24/'Summary sheet'!$L24) =CG25*('Summary sheet'!$N24/'Summary sheet'!$L24) =CG25*$CJ$10 =CJ25*('Summary sheet'!$M24/'Summary sheet'!$L24) =CJ25*('Summary sheet'!$N24/'Summary sheet'!$L24)

='Input sheet'!S26 =CG26*('Summary sheet'!$M25/'Summary sheet'!$L25) =CG26*('Summary sheet'!$N25/'Summary sheet'!$L25) =CG26*$CJ$10 =CJ26*('Summary sheet'!$M25/'Summary sheet'!$L25) =CJ26*('Summary sheet'!$N25/'Summary sheet'!$L25)

='Input sheet'!S27 =CG27*('Summary sheet'!$M26/'Summary sheet'!$L26) =CG27*('Summary sheet'!$N26/'Summary sheet'!$L26) =CG27*$CJ$10 =CJ27*('Summary sheet'!$M26/'Summary sheet'!$L26) =CJ27*('Summary sheet'!$N26/'Summary sheet'!$L26)

='Input sheet'!S28 =CG28*('Summary sheet'!$M27/'Summary sheet'!$L27) =CG28*('Summary sheet'!$N27/'Summary sheet'!$L27) =CG28*$CJ$10 =CJ28*('Summary sheet'!$M27/'Summary sheet'!$L27) =CJ28*('Summary sheet'!$N27/'Summary sheet'!$L27)

='Input sheet'!S29 =CG29*('Summary sheet'!$M28/'Summary sheet'!$L28) =CG29*('Summary sheet'!$N28/'Summary sheet'!$L28) =CG29*$CJ$10 =CJ29*('Summary sheet'!$M28/'Summary sheet'!$L28) =CJ29*('Summary sheet'!$N28/'Summary sheet'!$L28)

='Input sheet'!S30 =CG30*('Summary sheet'!$M29/'Summary sheet'!$L29) =CG30*('Summary sheet'!$N29/'Summary sheet'!$L29) =CG30*$CJ$10 =CJ30*('Summary sheet'!$M29/'Summary sheet'!$L29) =CJ30*('Summary sheet'!$N29/'Summary sheet'!$L29)

='Input sheet'!S31 =CG31*('Summary sheet'!$M30/'Summary sheet'!$L30) =CG31*('Summary sheet'!$N30/'Summary sheet'!$L30) =CG31*$CJ$10 =CJ31*('Summary sheet'!$M30/'Summary sheet'!$L30) =CJ31*('Summary sheet'!$N30/'Summary sheet'!$L30)

='Input sheet'!S32 =CG32*('Summary sheet'!$M31/'Summary sheet'!$L31) =CG32*('Summary sheet'!$N31/'Summary sheet'!$L31) =CG32*$CJ$10 =CJ32*('Summary sheet'!$M31/'Summary sheet'!$L31) =CJ32*('Summary sheet'!$N31/'Summary sheet'!$L31)

='Input sheet'!S33 =CG33*('Summary sheet'!$M32/'Summary sheet'!$L32) =CG33*('Summary sheet'!$N32/'Summary sheet'!$L32) =CG33*$CJ$10 =CJ33*('Summary sheet'!$M32/'Summary sheet'!$L32) =CJ33*('Summary sheet'!$N32/'Summary sheet'!$L32)

='Input sheet'!S34 =CG34*('Summary sheet'!$M33/'Summary sheet'!$L33) =CG34*('Summary sheet'!$N33/'Summary sheet'!$L33) =CG34*$CJ$10 =CJ34*('Summary sheet'!$M33/'Summary sheet'!$L33) =CJ34*('Summary sheet'!$N33/'Summary sheet'!$L33)

='Input sheet'!S35 =CG35*('Summary sheet'!$M34/'Summary sheet'!$L34) =CG35*('Summary sheet'!$N34/'Summary sheet'!$L34) =CG35*$CJ$10 =CJ35*('Summary sheet'!$M34/'Summary sheet'!$L34) =CJ35*('Summary sheet'!$N34/'Summary sheet'!$L34)

Throughput of EfW 2 Diversion of Municipal Waste from landfill via EfW 2

Page 226: Waste management model

226

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

=CL7+1 =CM7+1 =CN7+1 =CO7+1 =CP7+1 =CQ7+1

Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste

=CA11*$CM$10 =CM11*('Summary sheet'!$M10/'Summary sheet'!$F10) =CM11*('Summary sheet'!$N10/'Summary sheet'!$L10) =CM11*$CP$10 =CP11*('Summary sheet'!$M10/'Summary sheet'!$F10) =CP11*('Summary sheet'!$N10/'Summary sheet'!$L10)

=CA12*$CM$10 =CM12*('Summary sheet'!$M11/'Summary sheet'!$L11) =CM12*('Summary sheet'!$N11/'Summary sheet'!$L11) =CM12*$CP$10 =CP12*('Summary sheet'!$M11/'Summary sheet'!$L11) =CP12*('Summary sheet'!$N11/'Summary sheet'!$L11)

=CA13*$CM$10 =CM13*('Summary sheet'!$M12/'Summary sheet'!$L12) =CM13*('Summary sheet'!$N12/'Summary sheet'!$L12) =CM13*$CP$10 =CP13*('Summary sheet'!$M12/'Summary sheet'!$L12) =CP13*('Summary sheet'!$N12/'Summary sheet'!$L12)

=CA14*$CM$10 =CM14*('Summary sheet'!$M13/'Summary sheet'!$L13) =CM14*('Summary sheet'!$N13/'Summary sheet'!$L13) =CM14*$CP$10 =CP14*('Summary sheet'!$M13/'Summary sheet'!$L13) =CP14*('Summary sheet'!$N13/'Summary sheet'!$L13)

=CA15*$CM$10 =CM15*('Summary sheet'!$M14/'Summary sheet'!$L14) =CM15*('Summary sheet'!$N14/'Summary sheet'!$L14) =CM15*$CP$10 =CP15*('Summary sheet'!$M14/'Summary sheet'!$L14) =CP15*('Summary sheet'!$N14/'Summary sheet'!$L14)

=CA16*$CM$10 =CM16*('Summary sheet'!$M15/'Summary sheet'!$L15) =CM16*('Summary sheet'!$N15/'Summary sheet'!$L15) =CM16*$CP$10 =CP16*('Summary sheet'!$M15/'Summary sheet'!$L15) =CP16*('Summary sheet'!$N15/'Summary sheet'!$L15)

=CA17*$CM$10 =CM17*('Summary sheet'!$M16/'Summary sheet'!$L16) =CM17*('Summary sheet'!$N16/'Summary sheet'!$L16) =CM17*$CP$10 =CP17*('Summary sheet'!$M16/'Summary sheet'!$L16) =CP17*('Summary sheet'!$N16/'Summary sheet'!$L16)

=CA18*$CM$10 =CM18*('Summary sheet'!$M17/'Summary sheet'!$L17) =CM18*('Summary sheet'!$N17/'Summary sheet'!$L17) =CM18*$CP$10 =CP18*('Summary sheet'!$M17/'Summary sheet'!$L17) =CP18*('Summary sheet'!$N17/'Summary sheet'!$L17)

=CA19*$CM$10 =CM19*('Summary sheet'!$M18/'Summary sheet'!$L18) =CM19*('Summary sheet'!$N18/'Summary sheet'!$L18) =CM19*$CP$10 =CP19*('Summary sheet'!$M18/'Summary sheet'!$L18) =CP19*('Summary sheet'!$N18/'Summary sheet'!$L18)

=CA20*$CM$10 =CM20*('Summary sheet'!$M19/'Summary sheet'!$L19) =CM20*('Summary sheet'!$N19/'Summary sheet'!$L19) =CM20*$CP$10 =CP20*('Summary sheet'!$M19/'Summary sheet'!$L19) =CP20*('Summary sheet'!$N19/'Summary sheet'!$L19)

=CA21*$CM$10 =CM21*('Summary sheet'!$M20/'Summary sheet'!$L20) =CM21*('Summary sheet'!$N20/'Summary sheet'!$L20) =CM21*$CP$10 =CP21*('Summary sheet'!$M20/'Summary sheet'!$L20) =CP21*('Summary sheet'!$N20/'Summary sheet'!$L20)

=CA22*$CM$10 =CM22*('Summary sheet'!$M21/'Summary sheet'!$L21) =CM22*('Summary sheet'!$N21/'Summary sheet'!$L21) =CM22*$CP$10 =CP22*('Summary sheet'!$M21/'Summary sheet'!$L21) =CP22*('Summary sheet'!$N21/'Summary sheet'!$L21)

=CA23*$CM$10 =CM23*('Summary sheet'!$M22/'Summary sheet'!$L22) =CM23*('Summary sheet'!$N22/'Summary sheet'!$L22) =CM23*$CP$10 =CP23*('Summary sheet'!$M22/'Summary sheet'!$L22) =CP23*('Summary sheet'!$N22/'Summary sheet'!$L22)

=CA24*$CM$10 =CM24*('Summary sheet'!$M23/'Summary sheet'!$L23) =CM24*('Summary sheet'!$N23/'Summary sheet'!$L23) =CM24*$CP$10 =CP24*('Summary sheet'!$M23/'Summary sheet'!$L23) =CP24*('Summary sheet'!$N23/'Summary sheet'!$L23)

=CA25*$CM$10 =CM25*('Summary sheet'!$M24/'Summary sheet'!$L24) =CM25*('Summary sheet'!$N24/'Summary sheet'!$L24) =CM25*$CP$10 =CP25*('Summary sheet'!$M24/'Summary sheet'!$L24) =CP25*('Summary sheet'!$N24/'Summary sheet'!$L24)

=CA26*$CM$10 =CM26*('Summary sheet'!$M25/'Summary sheet'!$L25) =CM26*('Summary sheet'!$N25/'Summary sheet'!$L25) =CM26*$CP$10 =CP26*('Summary sheet'!$M25/'Summary sheet'!$L25) =CP26*('Summary sheet'!$N25/'Summary sheet'!$L25)

=CA27*$CM$10 =CM27*('Summary sheet'!$M26/'Summary sheet'!$L26) =CM27*('Summary sheet'!$N26/'Summary sheet'!$L26) =CM27*$CP$10 =CP27*('Summary sheet'!$M26/'Summary sheet'!$L26) =CP27*('Summary sheet'!$N26/'Summary sheet'!$L26)

=CA28*$CM$10 =CM28*('Summary sheet'!$M27/'Summary sheet'!$L27) =CM28*('Summary sheet'!$N27/'Summary sheet'!$L27) =CM28*$CP$10 =CP28*('Summary sheet'!$M27/'Summary sheet'!$L27) =CP28*('Summary sheet'!$N27/'Summary sheet'!$L27)

=CA29*$CM$10 =CM29*('Summary sheet'!$M28/'Summary sheet'!$L28) =CM29*('Summary sheet'!$N28/'Summary sheet'!$L28) =CM29*$CP$10 =CP29*('Summary sheet'!$M28/'Summary sheet'!$L28) =CP29*('Summary sheet'!$N28/'Summary sheet'!$L28)

=CA30*$CM$10 =CM30*('Summary sheet'!$M29/'Summary sheet'!$L29) =CM30*('Summary sheet'!$N29/'Summary sheet'!$L29) =CM30*$CP$10 =CP30*('Summary sheet'!$M29/'Summary sheet'!$L29) =CP30*('Summary sheet'!$N29/'Summary sheet'!$L29)

=CA31*$CM$10 =CM31*('Summary sheet'!$M30/'Summary sheet'!$L30) =CM31*('Summary sheet'!$N30/'Summary sheet'!$L30) =CM31*$CP$10 =CP31*('Summary sheet'!$M30/'Summary sheet'!$L30) =CP31*('Summary sheet'!$N30/'Summary sheet'!$L30)

=CA32*$CM$10 =CM32*('Summary sheet'!$M31/'Summary sheet'!$L31) =CM32*('Summary sheet'!$N31/'Summary sheet'!$L31) =CM32*$CP$10 =CP32*('Summary sheet'!$M31/'Summary sheet'!$L31) =CP32*('Summary sheet'!$N31/'Summary sheet'!$L31)

=CA33*$CM$10 =CM33*('Summary sheet'!$M32/'Summary sheet'!$L32) =CM33*('Summary sheet'!$N32/'Summary sheet'!$L32) =CM33*$CP$10 =CP33*('Summary sheet'!$M32/'Summary sheet'!$L32) =CP33*('Summary sheet'!$N32/'Summary sheet'!$L32)

=CA34*$CM$10 =CM34*('Summary sheet'!$M33/'Summary sheet'!$L33) =CM34*('Summary sheet'!$N33/'Summary sheet'!$L33) =CM34*$CP$10 =CP34*('Summary sheet'!$M33/'Summary sheet'!$L33) =CP34*('Summary sheet'!$N33/'Summary sheet'!$L33)

=CA35*$CM$10 =CM35*('Summary sheet'!$M34/'Summary sheet'!$L34) =CM35*('Summary sheet'!$N34/'Summary sheet'!$L34) =CM35*$CP$10 =CP35*('Summary sheet'!$M34/'Summary sheet'!$L34) =CP35*('Summary sheet'!$N34/'Summary sheet'!$L34)

EFW 1 Base ash to landfill (INACTIVE WASTE)EFW 1 Base ash arising

Page 227: Waste management model

227

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

=CR7+1 =CS7+1 =CT7+1 =CU7+1 =CV7+1 =CW7+1

Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste

=CM11*$CS$10 =CS11*('Summary sheet'!$M10/'Summary sheet'!$F10) =CS11*('Summary sheet'!$N10/'Summary sheet'!$L10) =CG11*$CV$10 =CV11*('Summary sheet'!$M10/'Summary sheet'!$F10) =CV11*('Summary sheet'!$N10/'Summary sheet'!$F10)

=CM12*$CS$10 =CS12*('Summary sheet'!$M11/'Summary sheet'!$L11) =CS12*('Summary sheet'!$N11/'Summary sheet'!$L11) =CG12*$CV$10 =CV12*('Summary sheet'!$M11/'Summary sheet'!$L11) =CV12*('Summary sheet'!$N11/'Summary sheet'!$F11)

=CM13*$CS$10 =CS13*('Summary sheet'!$M12/'Summary sheet'!$L12) =CS13*('Summary sheet'!$N12/'Summary sheet'!$L12) =CG13*$CV$10 =CV13*('Summary sheet'!$M12/'Summary sheet'!$L12) =CV13*('Summary sheet'!$N12/'Summary sheet'!$F12)

=CM14*$CS$10 =CS14*('Summary sheet'!$M13/'Summary sheet'!$L13) =CS14*('Summary sheet'!$N13/'Summary sheet'!$L13) =CG14*$CV$10 =CV14*('Summary sheet'!$M13/'Summary sheet'!$L13) =CV14*('Summary sheet'!$N13/'Summary sheet'!$F13)

=CM15*$CS$10 =CS15*('Summary sheet'!$M14/'Summary sheet'!$L14) =CS15*('Summary sheet'!$N14/'Summary sheet'!$L14) =CG15*$CV$10 =CV15*('Summary sheet'!$M14/'Summary sheet'!$L14) =CV15*('Summary sheet'!$N14/'Summary sheet'!$F14)

=CM16*$CS$10 =CS16*('Summary sheet'!$M15/'Summary sheet'!$L15) =CS16*('Summary sheet'!$N15/'Summary sheet'!$L15) =CG16*$CV$10 =CV16*('Summary sheet'!$M15/'Summary sheet'!$L15) =CV16*('Summary sheet'!$N15/'Summary sheet'!$F15)

=CM17*$CS$10 =CS17*('Summary sheet'!$M16/'Summary sheet'!$L16) =CS17*('Summary sheet'!$N16/'Summary sheet'!$L16) =CV17*('Summary sheet'!$M16/'Summary sheet'!$L16) =CV17*('Summary sheet'!$N16/'Summary sheet'!$F16)

=CM18*$CS$10 =CS18*('Summary sheet'!$M17/'Summary sheet'!$L17) =CS18*('Summary sheet'!$N17/'Summary sheet'!$L17) =CG18*$CV$10 =CV18*('Summary sheet'!$M17/'Summary sheet'!$L17) =CV18*('Summary sheet'!$N17/'Summary sheet'!$F17)

=CM19*$CS$10 =CS19*('Summary sheet'!$M18/'Summary sheet'!$L18) =CS19*('Summary sheet'!$N18/'Summary sheet'!$L18) =CG19*$CV$10 =CV19*('Summary sheet'!$M18/'Summary sheet'!$L18) =CV19*('Summary sheet'!$N18/'Summary sheet'!$F18)

=CM20*$CS$10 =CS20*('Summary sheet'!$M19/'Summary sheet'!$L19) =CS20*('Summary sheet'!$N19/'Summary sheet'!$L19) =CG20*$CV$10 =CV20*('Summary sheet'!$M19/'Summary sheet'!$L19) =CV20*('Summary sheet'!$N19/'Summary sheet'!$F19)

=CM21*$CS$10 =CS21*('Summary sheet'!$M20/'Summary sheet'!$L20) =CS21*('Summary sheet'!$N20/'Summary sheet'!$L20) =CG21*$CV$10 =CV21*('Summary sheet'!$M20/'Summary sheet'!$L20) =CV21*('Summary sheet'!$N20/'Summary sheet'!$F20)

=CM22*$CS$10 =CS22*('Summary sheet'!$M21/'Summary sheet'!$L21) =CS22*('Summary sheet'!$N21/'Summary sheet'!$L21) =CG22*$CV$10 =CV22*('Summary sheet'!$M21/'Summary sheet'!$L21) =CV22*('Summary sheet'!$N21/'Summary sheet'!$F21)

=CM23*$CS$10 =CS23*('Summary sheet'!$M22/'Summary sheet'!$L22) =CS23*('Summary sheet'!$N22/'Summary sheet'!$L22) =CG23*$CV$10 =CV23*('Summary sheet'!$M22/'Summary sheet'!$L22) =CV23*('Summary sheet'!$N22/'Summary sheet'!$F22)

=CM24*$CS$10 =CS24*('Summary sheet'!$M23/'Summary sheet'!$L23) =CS24*('Summary sheet'!$N23/'Summary sheet'!$L23) =CG24*$CV$10 =CV24*('Summary sheet'!$M23/'Summary sheet'!$L23) =CV24*('Summary sheet'!$N23/'Summary sheet'!$F23)

=CM25*$CS$10 =CS25*('Summary sheet'!$M24/'Summary sheet'!$L24) =CS25*('Summary sheet'!$N24/'Summary sheet'!$L24) =CG25*$CV$10 =CV25*('Summary sheet'!$M24/'Summary sheet'!$L24) =CV25*('Summary sheet'!$N24/'Summary sheet'!$F24)

=CM26*$CS$10 =CS26*('Summary sheet'!$M25/'Summary sheet'!$L25) =CS26*('Summary sheet'!$N25/'Summary sheet'!$L25) =CG26*$CV$10 =CV26*('Summary sheet'!$M25/'Summary sheet'!$L25) =CV26*('Summary sheet'!$N25/'Summary sheet'!$F25)

=CM27*$CS$10 =CS27*('Summary sheet'!$M26/'Summary sheet'!$L26) =CS27*('Summary sheet'!$N26/'Summary sheet'!$L26) =CG27*$CV$10 =CV27*('Summary sheet'!$M26/'Summary sheet'!$L26) =CV27*('Summary sheet'!$N26/'Summary sheet'!$F26)

=CM28*$CS$10 =CS28*('Summary sheet'!$M27/'Summary sheet'!$L27) =CS28*('Summary sheet'!$N27/'Summary sheet'!$L27) =CG28*$CV$10 =CV28*('Summary sheet'!$M27/'Summary sheet'!$L27) =CV28*('Summary sheet'!$N27/'Summary sheet'!$F27)

=CM29*$CS$10 =CS29*('Summary sheet'!$M28/'Summary sheet'!$L28) =CS29*('Summary sheet'!$N28/'Summary sheet'!$L28) =CG29*$CV$10 =CV29*('Summary sheet'!$M28/'Summary sheet'!$L28) =CV29*('Summary sheet'!$N28/'Summary sheet'!$F28)

=CM30*$CS$10 =CS30*('Summary sheet'!$M29/'Summary sheet'!$L29) =CS30*('Summary sheet'!$N29/'Summary sheet'!$L29) =CG30*$CV$10 =CV30*('Summary sheet'!$M29/'Summary sheet'!$L29) =CV30*('Summary sheet'!$N29/'Summary sheet'!$F29)

=CM31*$CS$10 =CS31*('Summary sheet'!$M30/'Summary sheet'!$L30) =CS31*('Summary sheet'!$N30/'Summary sheet'!$L30) =CG31*$CV$10 =CV31*('Summary sheet'!$M30/'Summary sheet'!$L30) =CV31*('Summary sheet'!$N30/'Summary sheet'!$F30)

=CM32*$CS$10 =CS32*('Summary sheet'!$M31/'Summary sheet'!$L31) =CS32*('Summary sheet'!$N31/'Summary sheet'!$L31) =CG32*$CV$10 =CV32*('Summary sheet'!$M31/'Summary sheet'!$L31) =CV32*('Summary sheet'!$N31/'Summary sheet'!$F31)

=CM33*$CS$10 =CS33*('Summary sheet'!$M32/'Summary sheet'!$L32) =CS33*('Summary sheet'!$N32/'Summary sheet'!$L32) =CG33*$CV$10 =CV33*('Summary sheet'!$M32/'Summary sheet'!$L32) =CV33*('Summary sheet'!$N32/'Summary sheet'!$F32)

=CM34*$CS$10 =CS34*('Summary sheet'!$M33/'Summary sheet'!$L33) =CS34*('Summary sheet'!$N33/'Summary sheet'!$L33) =CG34*$CV$10 =CV34*('Summary sheet'!$M33/'Summary sheet'!$L33) =CV34*('Summary sheet'!$N33/'Summary sheet'!$F33)

=CM35*$CS$10 =CS35*('Summary sheet'!$M34/'Summary sheet'!$L34) =CS35*('Summary sheet'!$N34/'Summary sheet'!$L34) =CG35*$CV$10 =CV35*('Summary sheet'!$M34/'Summary sheet'!$L34) =CV35*('Summary sheet'!$N34/'Summary sheet'!$F34)

EFW 1 Base ash to Beneficial Use EFW 2 Base ash arising

Page 228: Waste management model

228

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

=CX7+1 =CY7+1 =CZ7+1 =DA7+1 =DB7+1 =DC7+1

Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste Total Municipal Waste Contract Household Waste Contract Waste other than Household Waste

=CV11*$CY$10 =CY11*('Summary sheet'!$M10/'Summary sheet'!$F10) =CY11*('Summary sheet'!$N10/'Summary sheet'!$F10) =CV11*$DB$10 =DB11*('Summary sheet'!$M10/'Summary sheet'!$F10) =DB11*('Summary sheet'!$N10/'Summary sheet'!$F10)

=CV12*$CY$10 =CY12*('Summary sheet'!$M11/'Summary sheet'!$L11) =CY12*('Summary sheet'!$N11/'Summary sheet'!$F11) =CV12*$DB$10 =DB12*('Summary sheet'!$M11/'Summary sheet'!$L11) =DB12*('Summary sheet'!$N11/'Summary sheet'!$F11)

=CV13*$CY$10 =CY13*('Summary sheet'!$M12/'Summary sheet'!$L12) =CY13*('Summary sheet'!$N12/'Summary sheet'!$F12) =CV13*$DB$10 =DB13*('Summary sheet'!$M12/'Summary sheet'!$L12) =DB13*('Summary sheet'!$N12/'Summary sheet'!$F12)

=CV14*$CY$10 =CY14*('Summary sheet'!$M13/'Summary sheet'!$L13) =CY14*('Summary sheet'!$N13/'Summary sheet'!$F13) =CV14*$DB$10 =DB14*('Summary sheet'!$M13/'Summary sheet'!$L13) =DB14*('Summary sheet'!$N13/'Summary sheet'!$F13)

=CV15*$CY$10 =CY15*('Summary sheet'!$M14/'Summary sheet'!$L14) =CY15*('Summary sheet'!$N14/'Summary sheet'!$F14) =CV15*$DB$10 =DB15*('Summary sheet'!$M14/'Summary sheet'!$L14) =DB15*('Summary sheet'!$N14/'Summary sheet'!$F14)

=CV16*$CY$10 =CY16*('Summary sheet'!$M15/'Summary sheet'!$L15) =CY16*('Summary sheet'!$N15/'Summary sheet'!$F15) =CV16*$DB$10 =DB16*('Summary sheet'!$M15/'Summary sheet'!$L15) =DB16*('Summary sheet'!$N15/'Summary sheet'!$F15)

=CV17*$CY$10 =CY17*('Summary sheet'!$M16/'Summary sheet'!$L16) =CY17*('Summary sheet'!$N16/'Summary sheet'!$F16) =CV17*$DB$10 =DB17*('Summary sheet'!$M16/'Summary sheet'!$L16) =DB17*('Summary sheet'!$N16/'Summary sheet'!$F16)

=CV18*$CY$10 =CY18*('Summary sheet'!$M17/'Summary sheet'!$L17) =CY18*('Summary sheet'!$N17/'Summary sheet'!$F17) =CV18*$DB$10 =DB18*('Summary sheet'!$M17/'Summary sheet'!$L17) =DB18*('Summary sheet'!$N17/'Summary sheet'!$F17)

=CV19*$CY$10 =CY19*('Summary sheet'!$M18/'Summary sheet'!$L18) =CY19*('Summary sheet'!$N18/'Summary sheet'!$F18) =CV19*$DB$10 =DB19*('Summary sheet'!$M18/'Summary sheet'!$L18) =DB19*('Summary sheet'!$N18/'Summary sheet'!$F18)

=CV20*$CY$10 =CY20*('Summary sheet'!$M19/'Summary sheet'!$L19) =CY20*('Summary sheet'!$N19/'Summary sheet'!$F19) =CV20*$DB$10 =DB20*('Summary sheet'!$M19/'Summary sheet'!$L19) =DB20*('Summary sheet'!$N19/'Summary sheet'!$F19)

=CV21*$CY$10 =CY21*('Summary sheet'!$M20/'Summary sheet'!$L20) =CY21*('Summary sheet'!$N20/'Summary sheet'!$F20) =CV21*$DB$10 =DB21*('Summary sheet'!$M20/'Summary sheet'!$L20) =DB21*('Summary sheet'!$N20/'Summary sheet'!$F20)

=CV22*$CY$10 =CY22*('Summary sheet'!$M21/'Summary sheet'!$L21) =CY22*('Summary sheet'!$N21/'Summary sheet'!$F21) =CV22*$DB$10 =DB22*('Summary sheet'!$M21/'Summary sheet'!$L21) =DB22*('Summary sheet'!$N21/'Summary sheet'!$F21)

=CV23*$CY$10 =CY23*('Summary sheet'!$M22/'Summary sheet'!$L22) =CY23*('Summary sheet'!$N22/'Summary sheet'!$F22) =CV23*$DB$10 =DB23*('Summary sheet'!$M22/'Summary sheet'!$L22) =DB23*('Summary sheet'!$N22/'Summary sheet'!$F22)

=CV24*$CY$10 =CY24*('Summary sheet'!$M23/'Summary sheet'!$L23) =CY24*('Summary sheet'!$N23/'Summary sheet'!$F23) =CV24*$DB$10 =DB24*('Summary sheet'!$M23/'Summary sheet'!$L23) =DB24*('Summary sheet'!$N23/'Summary sheet'!$F23)

=CV25*$CY$10 =CY25*('Summary sheet'!$M24/'Summary sheet'!$L24) =CY25*('Summary sheet'!$N24/'Summary sheet'!$F24) =CV25*$DB$10 =DB25*('Summary sheet'!$M24/'Summary sheet'!$L24) =DB25*('Summary sheet'!$N24/'Summary sheet'!$F24)

=CV26*$CY$10 =CY26*('Summary sheet'!$M25/'Summary sheet'!$L25) =CY26*('Summary sheet'!$N25/'Summary sheet'!$F25) =CV26*$DB$10 =DB26*('Summary sheet'!$M25/'Summary sheet'!$L25) =DB26*('Summary sheet'!$N25/'Summary sheet'!$F25)

=CV27*$CY$10 =CY27*('Summary sheet'!$M26/'Summary sheet'!$L26) =CY27*('Summary sheet'!$N26/'Summary sheet'!$F26) =CV27*$DB$10 =DB27*('Summary sheet'!$M26/'Summary sheet'!$L26) =DB27*('Summary sheet'!$N26/'Summary sheet'!$F26)

=CV28*$CY$10 =CY28*('Summary sheet'!$M27/'Summary sheet'!$L27) =CY28*('Summary sheet'!$N27/'Summary sheet'!$F27) =CV28*$DB$10 =DB28*('Summary sheet'!$M27/'Summary sheet'!$L27) =DB28*('Summary sheet'!$N27/'Summary sheet'!$F27)

=CV29*$CY$10 =CY29*('Summary sheet'!$M28/'Summary sheet'!$L28) =CY29*('Summary sheet'!$N28/'Summary sheet'!$F28) =CV29*$DB$10 =DB29*('Summary sheet'!$M28/'Summary sheet'!$L28) =DB29*('Summary sheet'!$N28/'Summary sheet'!$F28)

=CV30*$CY$10 =CY30*('Summary sheet'!$M29/'Summary sheet'!$L29) =CY30*('Summary sheet'!$N29/'Summary sheet'!$F29) =CV30*$DB$10 =DB30*('Summary sheet'!$M29/'Summary sheet'!$L29) =DB30*('Summary sheet'!$N29/'Summary sheet'!$F29)

=CV31*$CY$10 =CY31*('Summary sheet'!$M30/'Summary sheet'!$L30) =CY31*('Summary sheet'!$N30/'Summary sheet'!$F30) =CV31*$DB$10 =DB31*('Summary sheet'!$M30/'Summary sheet'!$L30) =DB31*('Summary sheet'!$N30/'Summary sheet'!$F30)

=CV32*$CY$10 =CY32*('Summary sheet'!$M31/'Summary sheet'!$L31) =CY32*('Summary sheet'!$N31/'Summary sheet'!$F31) =CV32*$DB$10 =DB32*('Summary sheet'!$M31/'Summary sheet'!$L31) =DB32*('Summary sheet'!$N31/'Summary sheet'!$F31)

=CV33*$CY$10 =CY33*('Summary sheet'!$M32/'Summary sheet'!$L32) =CY33*('Summary sheet'!$N32/'Summary sheet'!$F32) =CV33*$DB$10 =DB33*('Summary sheet'!$M32/'Summary sheet'!$L32) =DB33*('Summary sheet'!$N32/'Summary sheet'!$F32)

=CV34*$CY$10 =CY34*('Summary sheet'!$M33/'Summary sheet'!$L33) =CY34*('Summary sheet'!$N33/'Summary sheet'!$F33) =CV34*$DB$10 =DB34*('Summary sheet'!$M33/'Summary sheet'!$L33) =DB34*('Summary sheet'!$N33/'Summary sheet'!$F33)

=CV35*$CY$10 =CY35*('Summary sheet'!$M34/'Summary sheet'!$L34) =CY35*('Summary sheet'!$N34/'Summary sheet'!$F34) =CV35*$DB$10 =DB35*('Summary sheet'!$M34/'Summary sheet'!$L34) =DB35*('Summary sheet'!$N34/'Summary sheet'!$F34)

EFW 2 Base ash to landfill (INACTIVE WASTE) EFW 2 Base ash to Beneficial Use

Page 229: Waste management model

229

Base ash To landfillThird party Waste arising

outside of contract

Third party Recovered

outside of contract

Percentage of Municipal

Waste stream that is diverted

by Third Party

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

=DH7+1 =DD7+1 =DF7+1 =DG7+1 =DE7+1 =DI7+1 =DJ7+1 =DL7+1 =DN7+1 =DO7+1 =DP7+1

Total Municipal Waste Total Municipal Waste Contract Household

Waste

Contract Waste other

than Household Waste Total Municipal Waste Total Municipal Waste Total Municipal Waste Total Municipal Waste Total Municipal Waste Total Municipal Waste Contract Household Waste

Contract Waste other than

Household Waste

=CP11+CY11 =CS11+DB11 =CT11+DC11 =CU11+DD11 =CA11*$DI$10 =CG11*$DJ$10 =BC11+BL11 =BC11+BM11 =DM11/'Summary sheet'!F10 =CA11+CG11+BP11 =CB11+CH11+BQ11 =CC11+CI11+BR11

=CP12+CY12 =CS12+DB12 =CT12+DC12 =CU12+DD12 =CA12*$DI$10 =CG12*$DJ$10 =BC12+BL12 =BC12+BM12 =DM12/'Summary sheet'!F11 =CA12+CG12+BP12 =CB12+CH12+BQ12 =CC12+CI12+BR12

=CP13+CY13 =CS13+DB13 =CT13+DC13 =CU13+DD13 =CA13*$DI$10 =CG13*$DJ$10 =BC13+BL13 =BC13+BM13 =DM13/'Summary sheet'!F12 =CA13+CG13+BP13 =CB13+CH13+BQ13 =CC13+CI13+BR13

=CP14+CY14 =CS14+DB14 =CT14+DC14 =CU14+DD14 =CA14*$DI$10 =CG14*$DJ$10 =BC14+BL14 =BC14+BM14 =DM14/'Summary sheet'!F13 =CA14+CG14+BP14 =CB14+CH14+BQ14 =CC14+CI14+BR14

=CP15+CY15 =CS15+DB15 =CT15+DC15 =CU15+DD15 =CA15*$DI$10 =CG15*$DJ$10 =BC15+BL15 =BC15+BM15 =DM15/'Summary sheet'!F14 =CA15+CG15+BP15 =CB15+CH15+BQ15 =CC15+CI15+BR15

=CP16+CY16 =CS16+DB16 =CT16+DC16 =CU16+DD16 =CA16*$DI$10 =CG16*$DJ$10 =BC16+BL16 =BC16+BM16 =DM16/'Summary sheet'!F15 =CA16+CG16+BP16 =CB16+CH16+BQ16 =CC16+CI16+BR16

=CP17+CY17 =CS17+DB17 =CT17+DC17 =CU17+DD17 =CA17*$DI$10 =CG17*$DJ$10 =BC17+BL17 =BC17+BM17 =DM17/'Summary sheet'!F16 =CA17+CG17+BP17 =CB17+CH17+BQ17 =CC17+CI17+BR17

=CP18+CY18 =CS18+DB18 =CT18+DC18 =CU18+DD18 =CA18*$DI$10 =CG18*$DJ$10 =BC18+BL18 =BC18+BM18 =DM18/'Summary sheet'!F17 =CA18+CG18+BP18 =CB18+CH18+BQ18 =CC18+CI18+BR18

=CP19+CY19 =CS19+DB19 =CT19+DC19 =CU19+DD19 =CA19*$DI$10 =CG19*$DJ$10 =BC19+BL19 =BC19+BM19 =DM19/'Summary sheet'!F18 =CA19+CG19+BP19 =CB19+CH19+BQ19 =CC19+CI19+BR19

=CP20+CY20 =CS20+DB20 =CT20+DC20 =CU20+DD20 =CA20*$DI$10 =CG20*$DJ$10 =BC20+BL20 =BC20+BM20 =DM20/'Summary sheet'!F19 =CA20+CG20+BP20 =CB20+CH20+BQ20 =CC20+CI20+BR20

=CP21+CY21 =CS21+DB21 =CT21+DC21 =CU21+DD21 =CA21*$DI$10 =CG21*$DJ$10 =BC21+BL21 =BC21+BM21 =DM21/'Summary sheet'!F20 =CA21+CG21+BP21 =CB21+CH21+BQ21 =CC21+CI21+BR21

=CP22+CY22 =CS22+DB22 =CT22+DC22 =CU22+DD22 =CA22*$DI$10 =CG22*$DJ$10 =BC22+BL22 =BC22+BM22 =DM22/'Summary sheet'!F21 =CA22+CG22+BP22 =CB22+CH22+BQ22 =CC22+CI22+BR22

=CP23+CY23 =CS23+DB23 =CT23+DC23 =CU23+DD23 =CA23*$DI$10 =CG23*$DJ$10 =BC23+BL23 =BC23+BM23 =DM23/'Summary sheet'!F22 =CA23+CG23+BP23 =CB23+CH23+BQ23 =CC23+CI23+BR23

=CP24+CY24 =CS24+DB24 =CT24+DC24 =CU24+DD24 =CA24*$DI$10 =CG24*$DJ$10 =BC24+BL24 =BC24+BM24 =DM24/'Summary sheet'!F23 =CA24+CG24+BP24 =CB24+CH24+BQ24 =CC24+CI24+BR24

=CP25+CY25 =CS25+DB25 =CT25+DC25 =CU25+DD25 =CA25*$DI$10 =CG25*$DJ$10 =BC25+BL25 =BC25+BM25 =DM25/'Summary sheet'!F24 =CA25+CG25+BP25 =CB25+CH25+BQ25 =CC25+CI25+BR25

=CP26+CY26 =CS26+DB26 =CT26+DC26 =CU26+DD26 =CA26*$DI$10 =CG26*$DJ$10 =BC26+BL26 =BC26+BM26 =DM26/'Summary sheet'!F25 =CA26+CG26+BP26 =CB26+CH26+BQ26 =CC26+CI26+BR26

=CP27+CY27 =CS27+DB27 =CT27+DC27 =CU27+DD27 =CA27*$DI$10 =CG27*$DJ$10 =BC27+BL27 =BC27+BM27 =DM27/'Summary sheet'!F26 =CA27+CG27+BP27 =CB27+CH27+BQ27 =CC27+CI27+BR27

=CP28+CY28 =CS28+DB28 =CT28+DC28 =CU28+DD28 =CA28*$DI$10 =CG28*$DJ$10 =BC28+BL28 =BC28+BM28 =DM28/'Summary sheet'!F27 =CA28+CG28+BP28 =CB28+CH28+BQ28 =CC28+CI28+BR28

=CP29+CY29 =CS29+DB29 =CT29+DC29 =CU29+DD29 =CA29*$DI$10 =CG29*$DJ$10 =BC29+BL29 =BC29+BM29 =DM29/'Summary sheet'!F28 =CA29+CG29+BP29 =CB29+CH29+BQ29 =CC29+CI29+BR29

=CP30+CY30 =CS30+DB30 =CT30+DC30 =CU30+DD30 =CA30*$DI$10 =CG30*$DJ$10 =BC30+BL30 =BC30+BM30 =DM30/'Summary sheet'!F29 =CA30+CG30+BP30 =CB30+CH30+BQ30 =CC30+CI30+BR30

=CP31+CY31 =CS31+DB31 =CT31+DC31 =CU31+DD31 =CA31*$DI$10 =CG31*$DJ$10 =BC31+BL31 =BC31+BM31 =DM31/'Summary sheet'!F30 =CA31+CG31+BP31 =CB31+CH31+BQ31 =CC31+CI31+BR31

=CP32+CY32 =CS32+DB32 =CT32+DC32 =CU32+DD32 =CA32*$DI$10 =CG32*$DJ$10 =BC32+BL32 =BC32+BM32 =DM32/'Summary sheet'!F31 =CA32+CG32+BP32 =CB32+CH32+BQ32 =CC32+CI32+BR32

=CP33+CY33 =CS33+DB33 =CT33+DC33 =CU33+DD33 =CA33*$DI$10 =CG33*$DJ$10 =BC33+BL33 =BC33+BM33 =DM33/'Summary sheet'!F32 =CA33+CG33+BP33 =CB33+CH33+BQ33 =CC33+CI33+BR33

=CP34+CY34 =CS34+DB34 =CT34+DC34 =CU34+DD34 =CA34*$DI$10 =CG34*$DJ$10 =BC34+BL34 =BC34+BM34 =DM34/'Summary sheet'!F33 =CA34+CG34+BP34 =CB34+CH34+BQ34 =CC34+CI34+BR34

=CP35+CY35 =CS35+DB35 =CT35+DC35 =CU35+DD35 =CA35*$DI$10 =CG35*$DJ$10 =BC35+BL35 =BC35+BM35 =DM35/'Summary sheet'!F34 =CA35+CG35+BP35 =CB35+CH35+BQ35 =CC35+CI35+BR35

(tonnes)

Fly ash to landfill Total throughput of Municipal (Contract) Waste through Energy Recovery facilitiesProcess waste residues put to beneficial use

Page 230: Waste management model

230

Percentage of Municipal (Contract)

Waste stream recovered by Energy

Recovery

(tonnes) (tonnes) (tonnes) (Percentage) (tonnes) (tonnes) (tonnes) (tonnes)

=DQ7+1 =DR7+1 =DS7+1 =DT7+1 =DU7+1 =DW7+1 =DX7+1 =DY7+1

Total Municipal Waste Contract Household Waste Contract Waste other than

Household Waste Total Municipal Waste Total Municipal Waste Contract Household Waste

Contract Waste other than

Household Waste Third Party Waste

=CD11+CJ11+BS11 =BT11+CE11+CK11 =BU11+CF11+CL11 =DR11/'Summary sheet'!F10 =BF11+DR11 =BG11+DS11 =BH11+DT11 =DM11

=CD12+CJ12+BS12 =BT12+CE12+CK12 =BU12+CF12+CL12 =DR12/'Summary sheet'!F11 =BF12+DR12 =BG12+DS12 =BH12+DT12 =DM12

=CD13+CJ13+BS13 =BT13+CE13+CK13 =BU13+CF13+CL13 =DR13/'Summary sheet'!F12 =BF13+DR13 =BG13+DS13 =BH13+DT13 =DM13

=CD14+CJ14+BS14 =BT14+CE14+CK14 =BU14+CF14+CL14 =DR14/'Summary sheet'!F13 =BF14+DR14 =BG14+DS14 =BH14+DT14 =DM14

=CD15+CJ15+BS15 =BT15+CE15+CK15 =BU15+CF15+CL15 =DR15/'Summary sheet'!F14 =BF15+DR15 =BG15+DS15 =BH15+DT15 =DM15

=CD16+CJ16+BS16 =BT16+CE16+CK16 =BU16+CF16+CL16 =DR16/'Summary sheet'!F15 =BF16+DR16 =BG16+DS16 =BH16+DT16 =DM16

=CD17+CJ17+BS17 =BT17+CE17+CK17 =BU17+CF17+CL17 =DR17/'Summary sheet'!F16 =BF17+DR17 =BG17+DS17 =BH17+DT17 =DM17

=CD18+CJ18+BS18 =BT18+CE18+CK18 =BU18+CF18+CL18 =DR18/'Summary sheet'!F17 =BF18+DR18 =BG18+DS18 =BH18+DT18 =DM18

=CD19+CJ19+BS19 =BT19+CE19+CK19 =BU19+CF19+CL19 =DR19/'Summary sheet'!F18 =BF19+DR19 =BG19+DS19 =BH19+DT19 =DM19

=CD20+CJ20+BS20 =BT20+CE20+CK20 =BU20+CF20+CL20 =DR20/'Summary sheet'!F19 =BF20+DR20 =BG20+DS20 =BH20+DT20 =DM20

=CD21+CJ21+BS21 =BT21+CE21+CK21 =BU21+CF21+CL21 =DR21/'Summary sheet'!F20 =BF21+DR21 =BG21+DS21 =BH21+DT21 =DM21

=CD22+CJ22+BS22 =BT22+CE22+CK22 =BU22+CF22+CL22 =DR22/'Summary sheet'!F21 =BF22+DR22 =BG22+DS22 =BH22+DT22 =DM22

=CD23+CJ23+BS23 =BT23+CE23+CK23 =BU23+CF23+CL23 =DR23/'Summary sheet'!F22 =BF23+DR23 =BG23+DS23 =BH23+DT23 =DM23

=CD24+CJ24+BS24 =BT24+CE24+CK24 =BU24+CF24+CL24 =DR24/'Summary sheet'!H23 =BF24+DR24 =BG24+DS24 =BH24+DT24 =DM24

=CD25+CJ25+BS25 =BT25+CE25+CK25 =BU25+CF25+CL25 =DR25/'Summary sheet'!H24 =BF25+DR25 =BG25+DS25 =BH25+DT25 =DM25

=CD26+CJ26+BS26 =BT26+CE26+CK26 =BU26+CF26+CL26 =DR26/'Summary sheet'!H25 =BF26+DR26 =BG26+DS26 =BH26+DT26 =DM26

=CD27+CJ27+BS27 =BT27+CE27+CK27 =BU27+CF27+CL27 =DR27/'Summary sheet'!H26 =BF27+DR27 =BG27+DS27 =BH27+DT27 =DM27

=CD28+CJ28+BS28 =BT28+CE28+CK28 =BU28+CF28+CL28 =DR28/'Summary sheet'!H27 =BF28+DR28 =BG28+DS28 =BH28+DT28 =DM28

=CD29+CJ29+BS29 =BT29+CE29+CK29 =BU29+CF29+CL29 =DR29/'Summary sheet'!H28 =BF29+DR29 =BG29+DS29 =BH29+DT29 =DM29

=CD30+CJ30+BS30 =BT30+CE30+CK30 =BU30+CF30+CL30 =DR30/'Summary sheet'!H29 =BF30+DR30 =BG30+DS30 =BH30+DT30 =DM30

=CD31+CJ31+BS31 =BT31+CE31+CK31 =BU31+CF31+CL31 =DR31/'Summary sheet'!H30 =BF31+DR31 =BG31+DS31 =BH31+DT31 =DM31

=CD32+CJ32+BS32 =BT32+CE32+CK32 =BU32+CF32+CL32 =DR32/'Summary sheet'!H31 =BF32+DR32 =BG32+DS32 =BH32+DT32 =DM32

=CD33+CJ33+BS33 =BT33+CE33+CK33 =BU33+CF33+CL33 =DR33/'Summary sheet'!H32 =BF33+DR33 =BG33+DS33 =BH33+DT33 =DM33

=CD34+CJ34+BS34 =BT34+CE34+CK34 =BU34+CF34+CL34 =DR34/'Summary sheet'!H33 =BF34+DR34 =BG34+DS34 =BH34+DT34 =DM34

=CD35+CJ35+BS35 =BT35+CE35+CK35 =BU35+CF35+CL35 =DR35/'Summary sheet'!H34 =BF35+DR35 =BG35+DS35 =BH35+DT35 =DM35

Diversion of Municipal (Contract) Waste from landfill via Energy Recovery facilities Total Municipal (Contract) recovered

Page 231: Waste management model

231

Total percentage of Municipal

(Contract) Waste stream

recovered

Diversion of Municipal Waste from

landfill

Total amount of Waste going

to landfill out of county

(Horton)

Total percentage of Waste

being landfilled out of

county

(Percentage) (tonnes) (tonnes) (Percentage) (tonnes) (Percentage)

=DZ7+1 =EA7+1 =EC7+1 =EC7+1 =ED7+1 =EF7+1

Total Municipal Waste Total Municipal Waste Total Municipal Waste Total Municipal Waste Total Municipal Waste Total Municipal Waste

=DW11/'Summary sheet'!F10 =DF11+DW11 =344000-298000 =ED11/'Summary sheet'!F10=DL11-DM11 =EF11/'Summary sheet'!F10

=DW12/'Summary sheet'!F11 =DF12+DW12 =344000-298000 =ED12/'Summary sheet'!F11=DL12-DM12 =EF12/'Summary sheet'!F11

=DW13/'Summary sheet'!F12 =DF13+DW13 =344000-298000 =ED13/'Summary sheet'!F12=DL13-DM13 =EF13/'Summary sheet'!F12

=DW14/'Summary sheet'!F13 =DF14+DW14 0 0 =DL14-DM14 =EF14/'Summary sheet'!F13

=DW15/'Summary sheet'!F14 =DF15+DW15 0 0 =DL15-DM15 =EF15/'Summary sheet'!F14

=DW16/'Summary sheet'!F15 =DF16+DW16 0 0 =DL16-DM16 =EF16/'Summary sheet'!F15

=DW17/'Summary sheet'!F16 =DF17+DW17 0 0 =DL17-DM17 =EF17/'Summary sheet'!F16

=DW18/'Summary sheet'!F17 =DF18+DW18 0 0 =DL18-DM18 =EF18/'Summary sheet'!F17

=DW19/'Summary sheet'!F18 =DF19+DW19 0 0 =DL19-DM19 =EF19/'Summary sheet'!F18

=DW20/'Summary sheet'!F19 =DF20+DW20 0 0 =DL20-DM20 =EF20/'Summary sheet'!F19

=DW21/'Summary sheet'!F20 =DF21+DW21 0 0 =DL21-DM21 =EF21/'Summary sheet'!F20

=DW22/'Summary sheet'!F21 =DF22+DW22 0 0 =DL22-DM22 =EF22/'Summary sheet'!F21

=DW23/'Summary sheet'!F22 =DF23+DW23 0 0 =DL23-DM23 =EF23/'Summary sheet'!F22

=DW24/'Summary sheet'!H23 =DF24+DW24 0 0 =DL24-DM24 =EF24/'Summary sheet'!F23

=DW25/'Summary sheet'!H24 =DF25+DW25 0 0 =DL25-DM25 =EF25/'Summary sheet'!F24

=DW26/'Summary sheet'!H25 =DF26+DW26 0 0 =DL26-DM26 =EF26/'Summary sheet'!F25

=DW27/'Summary sheet'!H26 =DF27+DW27 0 0 =DL27-DM27 =EF27/'Summary sheet'!F26

=DW28/'Summary sheet'!H27 =DF28+DW28 0 0 =DL28-DM28 =EF28/'Summary sheet'!F27

=DW29/'Summary sheet'!H28 =DF29+DW29 0 0 =DL29-DM29 =EF29/'Summary sheet'!F28

=DW30/'Summary sheet'!H29 =DF30+DW30 0 0 =DL30-DM30 =EF30/'Summary sheet'!F29

=DW31/'Summary sheet'!H30 =DF31+DW31 0 0 =DL31-DM31 =EF31/'Summary sheet'!F30

=DW32/'Summary sheet'!H31 =DF32+DW32 0 0 =DL32-DM32 =EF32/'Summary sheet'!F31

=DW33/'Summary sheet'!H32 =DF33+DW33 0 0 =DL33-DM33 =EF33/'Summary sheet'!F32

=DW34/'Summary sheet'!H33 =DF34+DW34 0 0 =DL34-DM34 =EF34/'Summary sheet'!F33

=DW35/'Summary sheet'!H34 =DF35+DW35 0 0 =DL35-DM35 =EF35/'Summary sheet'!F34

Third Party Waste to Landfill

Page 232: Waste management model

232

(tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes) (tonnes)

=EG7+1 =EH7+1 =EI7+1 =EJ7+1 =EK7+1 =EL7+1 =EM7+1 =EN7+1 =EO7+1

Total Municipal Waste Contract Household Waste Contract Household Waste

Active waste

Contract Household In active

Waste Contract Waste other than Household Waste

Contract Waste other than

Household Waste Active waste

Contract Waste other than

Household Waste Inacative waste

Total Municipal Waste

Active waste

Total Municipal Waste

Inacative waste

='Summary sheet'!F10-(EC11+EF11) =EH11*('Summary sheet'!$M10/'Summary sheet'!$L10) =EI11-(CQ11+CZ11) =(CQ11+CZ11) =EH11*('Summary sheet'!$N10/'Summary sheet'!$L10) =EL11-(CR11+DA11) =CR11+DA11 =EJ11+EM11 =EK11+EN11

='Summary sheet'!F11-(EC12+EF12) =EH12*('Summary sheet'!$M11/'Summary sheet'!$L11) =EI12-(CQ12+CZ12) =(CQ12+CZ12) =EH12*('Summary sheet'!$N11/'Summary sheet'!$L11) =EL12-(CR12+DA12) =CR12+DA12 =EJ12+EM12 =EK12+EN12

='Summary sheet'!F12-(EC13+EF13) =EH13*('Summary sheet'!$M12/'Summary sheet'!$L12) =EI13-(CQ13+CZ13) =(CQ13+CZ13) =EH13*('Summary sheet'!$N12/'Summary sheet'!$L12) =EL13-(CR13+DA13) =CR13+DA13 =EJ13+EM13 =EK13+EN13

='Summary sheet'!F13-(EC14+EF14) =EH14*('Summary sheet'!$M13/'Summary sheet'!$L13) =EI14-(CQ14+CZ14) =(CQ14+CZ14) =EH14*('Summary sheet'!$N13/'Summary sheet'!$L13) =EL14-(CR14+DA14) =CR14+DA14 =EJ14+EM14 =EK14+EN14

='Summary sheet'!F14-(EC15+EF15) =EH15*('Summary sheet'!$M14/'Summary sheet'!$L14) =EI15-(CQ15+CZ15) =(CQ15+CZ15) =EH15*('Summary sheet'!$N14/'Summary sheet'!$L14) =EL15-(CR15+DA15) =CR15+DA15 =EJ15+EM15 =EK15+EN15

='Summary sheet'!F15-(EC16+EF16) =EH16*('Summary sheet'!$M15/'Summary sheet'!$L15) =EI16-(CQ16+CZ16) =(CQ16+CZ16) =EH16*('Summary sheet'!$N15/'Summary sheet'!$L15) =EL16-(CR16+DA16) =CR16+DA16 =EJ16+EM16 =EK16+EN16

='Summary sheet'!F16-(EC17+EF17) =EH17*('Summary sheet'!$M16/'Summary sheet'!$L16) =EI17-(CQ17+CZ17) =(CQ17+CZ17) =EH17*('Summary sheet'!$N16/'Summary sheet'!$L16) =EL17-(CR17+DA17) =CR17+DA17 =EJ17+EM17 =EK17+EN17

='Summary sheet'!F17-(EC18+EF18) =EH18*('Summary sheet'!$M17/'Summary sheet'!$L17) =EI18-(CQ18+CZ18) =(CQ18+CZ18) =EH18*('Summary sheet'!$N17/'Summary sheet'!$L17) =EL18-(CR18+DA18) =CR18+DA18 =EJ18+EM18 =EK18+EN18

='Summary sheet'!F18-(EC19+EF19) =EH19*('Summary sheet'!$M18/'Summary sheet'!$L18) =EI19-(CQ19+CZ19) =(CQ19+CZ19) =EH19*('Summary sheet'!$N18/'Summary sheet'!$L18) =EL19-(CR19+DA19) =CR19+DA19 =EJ19+EM19 =EK19+EN19

='Summary sheet'!F19-(EC20+EF20) =EH20*('Summary sheet'!$M19/'Summary sheet'!$L19) =EI20-(CQ20+CZ20) =(CQ20+CZ20) =EH20*('Summary sheet'!$N19/'Summary sheet'!$L19) =EL20-(CR20+DA20) =CR20+DA20 =EJ20+EM20 =EK20+EN20

='Summary sheet'!F20-(EC21+EF21) =EH21*('Summary sheet'!$M20/'Summary sheet'!$L20) =EI21-(CQ21+CZ21) =(CQ21+CZ21) =EH21*('Summary sheet'!$N20/'Summary sheet'!$L20) =EL21-(CR21+DA21) =CR21+DA21 =EJ21+EM21 =EK21+EN21

='Summary sheet'!F21-(EC22+EF22) =EH22*('Summary sheet'!$M21/'Summary sheet'!$L21) =EI22-(CQ22+CZ22) =(CQ22+CZ22) =EH22*('Summary sheet'!$N21/'Summary sheet'!$L21) =EL22-(CR22+DA22) =CR22+DA22 =EJ22+EM22 =EK22+EN22

='Summary sheet'!F22-(EC23+EF23) =EH23*('Summary sheet'!$M22/'Summary sheet'!$L22) =EI23-(CQ23+CZ23) =(CQ23+CZ23) =EH23*('Summary sheet'!$N22/'Summary sheet'!$L22) =EL23-(CR23+DA23) =CR23+DA23 =EJ23+EM23 =EK23+EN23

='Summary sheet'!F23-(EC24+EF24) =EH24*('Summary sheet'!$M23/'Summary sheet'!$L23) =EI24-(CQ24+CZ24) =(CQ24+CZ24) =EH24*('Summary sheet'!$N23/'Summary sheet'!$L23) =EL24-(CR24+DA24) =CR24+DA24 =EJ24+EM24 =EK24+EN24

='Summary sheet'!F24-(EC25+EF25) =EH25*('Summary sheet'!$M24/'Summary sheet'!$L24) =EI25-(CQ25+CZ25) =(CQ25+CZ25) =EH25*('Summary sheet'!$N24/'Summary sheet'!$L24) =EL25-(CR25+DA25) =CR25+DA25 =EJ25+EM25 =EK25+EN25

='Summary sheet'!F25-(EC26+EF26) =EH26*('Summary sheet'!$M25/'Summary sheet'!$L25) =EI26-(CQ26+CZ26) =(CQ26+CZ26) =EH26*('Summary sheet'!$N25/'Summary sheet'!$L25) =EL26-(CR26+DA26) =CR26+DA26 =EJ26+EM26 =EK26+EN26

='Summary sheet'!F26-(EC27+EF27) =EH27*('Summary sheet'!$M26/'Summary sheet'!$L26) =EI27-(CQ27+CZ27) =(CQ27+CZ27) =EH27*('Summary sheet'!$N26/'Summary sheet'!$L26) =EL27-(CR27+DA27) =CR27+DA27 =EJ27+EM27 =EK27+EN27

='Summary sheet'!F27-(EC28+EF28) =EH28*('Summary sheet'!$M27/'Summary sheet'!$L27) =EI28-(CQ28+CZ28) =(CQ28+CZ28) =EH28*('Summary sheet'!$N27/'Summary sheet'!$L27) =EL28-(CR28+DA28) =CR28+DA28 =EJ28+EM28 =EK28+EN28

='Summary sheet'!F28-(EC29+EF29) =EH29*('Summary sheet'!$M28/'Summary sheet'!$L28) =EI29-(CQ29+CZ29) =(CQ29+CZ29) =EH29*('Summary sheet'!$N28/'Summary sheet'!$L28) =EL29-(CR29+DA29) =CR29+DA29 =EJ29+EM29 =EK29+EN29

='Summary sheet'!F29-(EC30+EF30) =EH30*('Summary sheet'!$M29/'Summary sheet'!$L29) =EI30-(CQ30+CZ30) =(CQ30+CZ30) =EH30*('Summary sheet'!$N29/'Summary sheet'!$L29) =EL30-(CR30+DA30) =CR30+DA30 =EJ30+EM30 =EK30+EN30

='Summary sheet'!F30-(EC31+EF31) =EH31*('Summary sheet'!$M30/'Summary sheet'!$L30) =EI31-(CQ31+CZ31) =(CQ31+CZ31) =EH31*('Summary sheet'!$N30/'Summary sheet'!$L30) =EL31-(CR31+DA31) =CR31+DA31 =EJ31+EM31 =EK31+EN31

='Summary sheet'!F31-(EC32+EF32) =EH32*('Summary sheet'!$M31/'Summary sheet'!$L31) =EI32-(CQ32+CZ32) =(CQ32+CZ32) =EH32*('Summary sheet'!$N31/'Summary sheet'!$L31) =EL32-(CR32+DA32) =CR32+DA32 =EJ32+EM32 =EK32+EN32

='Summary sheet'!F32-(EC33+EF33) =EH33*('Summary sheet'!$M32/'Summary sheet'!$L32) =EI33-(CQ33+CZ33) =(CQ33+CZ33) =EH33*('Summary sheet'!$N32/'Summary sheet'!$L32) =EL33-(CR33+DA33) =CR33+DA33 =EJ33+EM33 =EK33+EN33

='Summary sheet'!F33-(EC34+EF34) =EH34*('Summary sheet'!$M33/'Summary sheet'!$L33) =EI34-(CQ34+CZ34) =(CQ34+CZ34) =EH34*('Summary sheet'!$N33/'Summary sheet'!$L33) =EL34-(CR34+DA34) =CR34+DA34 =EJ34+EM34 =EK34+EN34

='Summary sheet'!F34-(EC35+EF35) =EH35*('Summary sheet'!$M34/'Summary sheet'!$L34) =EI35-(CQ35+CZ35) =(CQ35+CZ35) =EH35*('Summary sheet'!$N34/'Summary sheet'!$L34) =EL35-(CR35+DA35) =CR35+DA35 =EJ35+EM35 =EK35+EN35

Total amount of Contract Waste going to landfill

Page 233: Waste management model

233

Percentage of Waste Landfilled

Total void space needed per

annum (m3) to include

necessary inert for

engineering

Cumulative total void

space needed

(Percentage) (tonnes) (tonnes) (tonnes)

=EP7+1 =EQ7+1 =ER7+1 =ES7+1 =ET7+1

Total Municipal Waste

Total Municipal

Waste Active

waste

Total Municipal

Waste

Inacative waste

Total Municipal Waste Total Municipal

Waste

=EH11/'Summary sheet'!F10 =EO11/0.83 =EP11/1.5 =(ER11+ES11)*1.1 =ET11

=EH12/'Summary sheet'!F11 =EO12/0.83 =EP12/1.5 =(ER12+ES12)*1.1 =EU11+ET12

=EH13/'Summary sheet'!F12 =EO13/0.83 =EP13/1.5 =(ER13+ES13)*1.1 =EU12+ET13

=EH14/'Summary sheet'!F13 =EO14/0.83 =EP14/1.5 =(ER14+ES14)*1.1 =EU13+ET14

=EH15/'Summary sheet'!F14 =EO15/0.83 =EP15/1.5 =(ER15+ES15)*1.1 =EU14+ET15

=EH16/'Summary sheet'!F15 =EO16/0.83 =EP16/1.5 =(ER16+ES16)*1.1 =EU15+ET16

=EH17/'Summary sheet'!F16 =EO17/0.83 =EP17/1.5 =(ER17+ES17)*1.1 =EU16+ET17

=EH18/'Summary sheet'!F17 =EO18/0.83 =EP18/1.5 =(ER18+ES18)*1.1 =EU17+ET18

=EH19/'Summary sheet'!F18 =EO19/0.83 =EP19/1.5 =(ER19+ES19)*1.1 =EU18+ET19

=EH20/'Summary sheet'!F19 =EO20/0.83 =EP20/1.5 =(ER20+ES20)*1.1 =EU19+ET20

=EH21/'Summary sheet'!F20 =EO21/0.83 =EP21/1.5 =(ER21+ES21)*1.1 =EU20+ET21

=EH22/'Summary sheet'!F21 =EO22/0.83 =EP22/1.5 =(ER22+ES22)*1.1 =EU21+ET22

=EH23/'Summary sheet'!F22 =EO23/0.83 =EP23/1.5 =(ER23+ES23)*1.1 =EU22+ET23

=EH24/'Summary sheet'!F23 =EO24/0.83 =EP24/1.5 =(ER24+ES24)*1.1 =EU23+ET24

=EH25/'Summary sheet'!F24 =EO25/0.83 =EP25/1.5 =(ER25+ES25)*1.1 =EU24+ET25

=EH26/'Summary sheet'!F25 =EO26/0.83 =EP26/1.5 =(ER26+ES26)*1.1 =EU25+ET26

=EH27/'Summary sheet'!F26 =EO27/0.83 =EP27/1.5 =(ER27+ES27)*1.1 =EU26+ET27

=EH28/'Summary sheet'!F27 =EO28/0.83 =EP28/1.5 =(ER28+ES28)*1.1 =EU27+ET28

=EH29/'Summary sheet'!F28 =EO29/0.83 =EP29/1.5 =(ER29+ES29)*1.1 =EU28+ET29

=EH30/'Summary sheet'!F29 =EO30/0.83 =EP30/1.5 =(ER30+ES30)*1.1 =EU29+ET30

=EH31/'Summary sheet'!F30 =EO31/0.83 =EP31/1.5 =(ER31+ES31)*1.1 =EU30+ET31

=EH32/'Summary sheet'!F31 =EO32/0.83 =EP32/1.5 =(ER32+ES32)*1.1 =EU31+ET32

=EH33/'Summary sheet'!F32 =EO33/0.83 =EP33/1.5 =(ER33+ES33)*1.1 =EU32+ET33

=EH34/'Summary sheet'!F33 =EO34/0.83 =EP34/1.5 =(ER34+ES34)*1.1 =EU33+ET34

=EH35/'Summary sheet'!F34 =EO35/0.83 =EP35/1.5 =(ER35+ES35)*1.1 =EU34+ET35

void space required (m3) per

annum

Page 234: Waste management model

234

Appendix 6: National LATS Survey

The following sheets are an extract of the questionnaire sent to every WDA in England; there are two sheets, a best case scenario and a

contingency scenario. Both screen shots show a small number of authorities

Page 235: Waste management model

235

Base

Year

2002/3

MSW

Recovery

rate

2005/6

Recovery

rate

2009/10

Recovery

rate

2015/16

Recovery

rate

20020/21

jpporder Region

LA

Type Local Authority Tonnes Tonnes % age % age % age % age 2003/4 2004/5 2005/6 2006/7 2007/8 2008/9 2009/10

1 North East U Stockton-on-Tees Borough Council

2 North East U Redcar and Cleveland Borough Council

3 North East U Middlesbrough Borough Council

4 North East U Hartlepool Borough Council

5 North East U Darlington Borough Council

13 North East D Durham County Council

20 North East D Northumberland County Council

21 North East U Sunderland City Council

22 North East U South Tyneside MBC

23 North East U North Tyneside Council

24 North East U Newcastle-upon-Tyne City Council MBC

25 North East U Gateshead MBC

26 North West U Warrington Borough Council

29 North West U Halton Borough Council

34 North West D Cheshire County Council

41 North West D Cumbria County Council

42 North West U Wigan MBC

52 North West D Greater Manchester WDA (MBC)

65 North West U Blackpool Borough Council

66 North West U Blackburn with Darwen Borough Council

67 North West D Lancashire County Council

73 North West D Merseyside WDA (MBC)

74 Yorkshire/HumberU East Riding of Yorkshire Council

75 Yorkshire/HumberU Kingston-upon-Hull City Council

76 Yorkshire/HumberU North East Lincolnshire Council

77 Yorkshire/HumberU North Lincolnshire Council

78 Yorkshire/HumberU York City Council

86 Yorkshire/HumberD North Yorkshire County Council

87 Yorkshire/HumberU Sheffield City Council

88 Yorkshire/HumberU Rotherham MBC

89 Yorkshire/HumberU Doncaster MBC

90 Yorkshire/HumberU Barnsley MBC

91 Yorkshire/HumberU Leeds City Council MBC

92 Yorkshire/HumberU Kirklees MBC

93 Yorkshire/HumberU Wakefield City MDC

94 Yorkshire/HumberU Bradford City MDC (MBC)

95 Yorkshire/HumberU Calderdale MBC

96 E Midlands U Derby City Council

For each year, please estimate the tonnes of Biodegradable Municipal Waste likely to be

sent to landfill. If not possible to estimate to 2020, please aim to estimate to 2013/14 if at

all possible. The figure should take into account waste growth.

"BEST CASE SCENARIO". On this sheet, you should

enter the figures you plan to achieve. Please see the

next spreadsheet for 'contingency case scenario'

figures.

Page 236: Waste management model

236

jpporder Region

LA

Type Local Authority 2003/4 2004/5 2005/6 2006/7 2007/8 2008/9 2009/10 2010/11 2011/12 2012/13

1 North East U Stockton-on-Tees Borough Council

2 North East U Redcar and Cleveland Borough Council

3 North East U Middlesbrough Borough Council

4 North East U Hartlepool Borough Council

5 North East U Darlington Borough Council

13 North East D Durham County Council

20 North East D Northumberland County Council

21 North East U Sunderland City Council

22 North East U South Tyneside MBC

23 North East U North Tyneside Council

24 North East U Newcastle-upon-Tyne City Council MBC

25 North East U Gateshead MBC

26 North West U Warrington Borough Council

29 North West U Halton Borough Council

34 North West D Cheshire County Council

41 North West D Cumbria County Council

42 North West U Wigan MBC

52 North West D Greater Manchester WDA (MBC)

65 North West U Blackpool Borough Council

66 North West U Blackburn with Darwen Borough Council

67 North West D Lancashire County Council

73 North West D Merseyside WDA (MBC)

74 Yorkshire/HumberU East Riding of Yorkshire Council

75 Yorkshire/HumberU Kingston-upon-Hull City Council

76 Yorkshire/HumberU North East Lincolnshire Council

77 Yorkshire/HumberU North Lincolnshire Council

78 Yorkshire/HumberU York City Council

86 Yorkshire/HumberD North Yorkshire County Council

87 Yorkshire/HumberU Sheffield City Council

88 Yorkshire/HumberU Rotherham MBC

89 Yorkshire/HumberU Doncaster MBC

90 Yorkshire/HumberU Barnsley MBC

91 Yorkshire/HumberU Leeds City Council MBC

92 Yorkshire/HumberU Kirklees MBC

93 Yorkshire/HumberU Wakefield City MDC

"CONTINGENCY CASE SCENARIO". On this sheet,

you should enter the figures which, if you were

scenario planning for some delays or problems, you

would work with."

For each year, please estimate the tonnes of Biodegradable Municipal Waste likely to be

sent to landfill. If not possible to estimate to 2020, please aim to estimate to 2013/14 if at

all possible. The figure should take into account waste growth.

Page 237: Waste management model