water efficiency in the automotive sector...volvo group north america, llc water efficiency in the...

24
Volvo Group North America, LLC Water Efficiency in the Automotive Sector Steve Pierett, C.E.M., CP EnMS , C.R.M. Environmental Manager

Upload: others

Post on 04-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

  • Volvo Group North America, LLC

    Water Efficiency in the Automotive Sector

    Steve Pierett, C.E.M., CP EnMS, C.R.M. Environmental Manager

  • Volvo NRV Plant – Dublin, Virginia

    Area’s Largest Manufacturing FacilityLargest Mfg. Facility in Volvo Family

    New River Valley Plant, Dublin, VA

  • Volvo NRV Plant – Dublin, Virginia

    OVERVIEW

    •Examine a decade plus of water savings benefits

    •Review two projects•Review water savings versus energy savings

  • Volvo NRV Plant – Dublin, Virginia

    (80.000)

    (60.000)

    (40.000)

    (20.000)

    -

    20.000

    40.000

    60.000

    80.000

    2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015

    x M

    illio

    n ga

    ls O

    r Per

    cent

    Red

    uctio

    n

    By Year

    Plantwide Total Water Use 2003 - 2015 est.

    Overall, water use efficiency improved 41% since the baseline year of 2003.

    Overall, water use efficiency improved 41% since the baseline year of 2003.

    Overall, water use efficiency improved 41% since the baseline year of 2003.

    Overall, water use efficiency improved 41% since the baseline year of 2003.

    Chart1

    20042004

    20052005

    20062006

    20072007

    20082008

    20092009

    20102010

    20112011

    20122012

    20132013

    20142014

    20152015

    Overall, water use efficiency improved 41% since the baseline year of 2003.

    Overall, water use efficiency improved 41% since the baseline year of 2003.

    Overall, water use efficiency improved 41% since the baseline year of 2003.

    Overall, water use efficiency improved 41% since the baseline year of 2003.

    By Year

    x Million gals Or Percent Reduction

    Plantwide Total Water Use 2003 - 2015 est.

    58.97039

    -5.2332787862

    48.5354

    -22.0025385486

    50.16224

    -19.3881706812

    41.65244

    -33.0636075265

    34.915635

    -43.8898021863

    26.7686363636

    -56.9822092147

    27.24304

    -56.2198320768

    42.12001

    -32.3122121934

    26.36419

    -57.6321634678

    34.931

    -43.8651102915

    39.7

    -36.2012217964

    36.71

    -41.0062179382

    WaterUsage2003-2013

    20042004

    20052005

    20062006

    20072007

    20082008

    20092009

    20102010

    20112011

    20122012

    20132013

    58.97039

    -5.2332787862

    48.5354

    -22.0025385486

    50.16224

    -19.3881706812

    41.65244

    -33.0636075265

    34.915635

    -43.8898021863

    26.7686363636

    -56.9822092147

    27.24304

    -56.2198320768

    42.12001

    -32.3122121934

    26.36419

    -57.6321634678

    34.931

    -43.8651102915

    TotalAnnualWaterUse2003-2015est

    20042004

    20052005

    20062006

    20072007

    20082008

    20092009

    20102010

    20112011

    20122012

    20132013

    20142014

    20152015

    Overall, water use efficiency improved 41% since the baseline year of 2003.

    From the updated baseline of 2008, water use has increased 5.1%.

    By Year

    x 10 Million gals Or Percent Reduction

    Plantwide Total Water Use 2003 - 2015 est.

    58.97039

    -5.2332787862

    48.5354

    -22.0025385486

    50.16224

    -19.3881706812

    41.65244

    -33.0636075265

    34.915635

    -43.8898021863

    26.7686363636

    -56.9822092147

    27.24304

    -56.2198320768

    42.12001

    -32.3122121934

    26.36419

    -57.6321634678

    34.931

    -43.8651102915

    39.7

    -36.2012217964

    36.71

    -41.0062179382

    AnnualWaterUsage

    YearWater Purchased - 10 Million galsOverall Percent ReductionOverall Percent Reduction from 2008Reduction in Water use - galPlant Cost Avoidance for water and sewerRegional Energy to Produce Clean WaterCost to Process WaterPlant Energy to Operate WW Reuse System

    2003 Base62.2276.2232003NAkWhr7.5 cents/kWhr

    200458.970-5.25.89720043,256,507$ 30,286594.45

    200548.535-22.04.854200513,691,497$ 127,33124918.69

    200650.162-19.45.016200612,064,657$ 112,20122016.47

    200741.652-33.14.165200720,574,457$ 191,34237428.08

    200834.916-43.93.492200827,311,262$ 253,99549737.28

    200926.769-57.023.3%2.677200935,458,261$ 329,76264548.40

    201027.243-56.222.0%2.724201034,983,857$ 325,35063747.75

    201142.120-32.3-20.6%est.4.212201120,106,887$ 186,99436627.45

    201226.364-57.624.5%2.636201235,862,707$ 333,52365348.95

    201334.931-43.9-0.0%3.493201327,295,897$ 253,85249737.26

    201439.700-36.2-13.7%3.970201422,526,897$ 209,50041030.75

    201536.710-41.0-5.1%est.thru June3.671201525,516,897$ 237,30746434.83

    2015-200325.523.901Average23,220,815$ 215,954

    Usage25.5 M gallons2004 to 2015301,870,598$ 2,807,397

    Decrease1.82 kWhr/1000 gal

    from 2003

    NRVWaterUsage

    Month/ YearWater UsageNRV Plant GallonsTrucks

    gal/truck

    Jan-042,2935,057,7302206

    Feb-042,4795,599,8902259

    Mar-042,0775,369,8302586

    Apr-042,0305,321,5302622

    May-042,1234,783,9202253

    Jun-041,7115,999,7703506

    Jul-042,0945,315,9902539

    Aug-041,5363,986,0402595

    Sep-041,1184,233,4003786

    Oct-041,1534,507,6503911

    Nov-041,3384,606,3603444

    Dec-041,2163,963,2803259

    Jan-051,1394,544,3503989

    Feb-051,1674,323,1503705

    Mar-051,1833,942,4303333

    Apr-051,1024,376,2603971

    May-051,0404,193,6204033

    Jun-058833,561,6604032

    Jul-051,1183,284,0502937

    Aug-051,1253,876,3403447

    Sep-058863,842,6404336

    Oct-051,0044,338,0004320

    Nov-051,1164,220,4403783

    Dec-051,2123,752,4603095

    Jan-061,2944,428,1603422

    Feb-061,1574,354,2003763

    Mar-069614,400,0004,578

    Apr-061,0304,098,3103,979

    May-068984,356,0404,852

    Jun-067223,480,7404,823

    Jul-068993,819,8404,247

    Aug-061,1723,702,7403158

    Sep-068874,075,0504593

    Oct-068974,505,6205,022

    Nov-061,0544,347,8704,124

    Dec-061,2364,376,2603,5411,017Average 2006 gal/truck

    Jan-071,7626,185,3903,511

    Feb-072,6073,195,8301,226

    Mar-072,2102,908,8701,316

    Apr-073,1282,853,100912

    May-073,9202,951,820753

    Jun-072,0152,806,9001,393

    Jul-071,5223,324,7002,184

    Aug-072,3373,202,2501,370

    Sep-071,6203,289,1302,030

    Oct-071,4073,765,4502,677

    Nov-071,4203,592,3002,530

    Dec-071,3203,474,7002,633

    Jan-081,5854,619,6502,914

    Feb-0801,524,30096

    Mar-082,3431,958,740836

    Apr-081,3754,292,5603,122

    May-081,1362,570,7902,264

    Jun-081,4002,357,2301,684

    Jul-082,0882,357,2301,129

    Aug-082,0722,600,1201,255

    Sep-081,6803,236,9201,927

    Oct-081,5323,094,0002,019

    Nov-082,4593,386,0901,377

    Dec-081,8092,905,6651,606

    216 VHD's3209 VN's1153 Mack's

    NRVMonthlyWaterUsage

    37987

    38018

    38047

    38078

    38108

    38139

    38169

    38200

    38231

    38261

    38292

    38322

    38353

    38384

    38412

    38443

    38473

    38504

    38534

    38565

    38596

    38626

    38657

    38687

    38718

    38749

    38777

    38808

    38838

    38869

    38899

    38930

    38961

    38991

    39022

    39052

    39083

    39114

    39142

    39173

    39203

    39234

    39264

    39295

    39326

    39356

    39387

    39417

    39448

    39479

    39508

    39539

    39569

    39600

    39630

    39661

    39692

    39722

    39753

    39783

    NRV Plant Water Usage 2004 - 2008 (gal/truck)

    2292.7153218495

    2478.9243027888

    2076.5003866976

    2029.5690312738

    2123.3555259654

    1711.2863662293

    2093.7337534462

    1536.0462427746

    1118.1722134179

    1152.5568908208

    1337.5029036005

    1216.1030991102

    1139.2203559789

    1166.8421052632

    1182.8472847285

    1102.0548980106

    1039.8264319365

    883.3482142857

    1118.1647940075

    1124.5546852335

    886.2177121771

    1004.1666666667

    1115.6330954269

    1212.4264943457

    1294.0268848626

    1157.1086898751

    961.1183923111

    1029.9849208344

    897.7823577906

    721.6960398092

    899.4207676007

    1172.4952501583

    887.230568256

    897.1764237356

    1054.2846750727

    1235.8825190624

    1761.7174594133

    2606.7128874388

    2210.3875379939

    3128.399122807

    3920.0796812749

    2015.0035893755

    1522.2985347985

    2337.4087591241

    1620.2610837438

    1406.5932013448

    1419.8814229249

    1319.6733763768

    1585.3294440631

    0

    2342.990430622

    1374.9391415759

    1135.50795053

    1399.7802850356

    2087.8919397697

    2071.8087649402

    1679.7716658018

    1532.4418028727

    2459.0341321714

    1809.2559153176

  • Volvo NRV Plant – Dublin, Virginia

    Cab Leak Test Water Recycling• Baseline water use for cab leak testing -

    1100 gallons per truck• System installed to clean and recycle the

    water used for cab leak testing. • Investment was $520,000• The benefit of recycling this water for reuse

    – Water use savings of 700 gallons per truck

    • This represented a plant-wide reduction for water use of 22%

  • Volvo NRV Plant – Dublin, Virginia

    Process Wastewater Treatment MethodThe reuse system consists of the following components:

    To PlantProcesses

    Cartridge Filter

    UV LightUF FeedStorage

    Ultra-Filtration

    High Pressure Reverse Osmosis

    ReuseWater

    StorageUV Light

    WWT

    WasteWater

    Storage

    HPRO Feed

    Storage

    UntreatedWastewater

    UV Light

  • Volvo NRV Plant – Dublin, Virginia

    Process Wastewater Reuse Drivers

    • Surfactant issues at the regional authority / foaming• Molybdenum contamination of land-applied sludge • Volvo was proactive to identify its contribution to a

    potential issue

    Environmental Issues

    Volvo Environmental Requirements• Wanted Position: To install water recycling processes

    with low water usage and preferably with chemical recycling in closed loop processes

  • Volvo NRV Plant – Dublin, Virginia

    Process Wastewater Reuse Incentives

    • Average incoming water from processes = 12M gal• Average reuse water to processes = 7.4M gal• Average annual reuse rate is 62% for process water

    Environmental Sustainability

    Environmental Liability / Risk Mgmt. Capital funds invested for recycling water instead of

    meeting increasingly stringent environmental regulations. $1.5 MUSD vs 1.1 MUSD

  • Volvo NRV Plant – Dublin, Virginia

    Process WWTP Specifications

    1. Average daily flow from WWTP

    36,307 gallons per day

    2. Maximum treated flow (WWT) = 500 gpm

    3. Storage capacity of untreated wastewater

    274,000 Gallons

    4. Conventional precipitation system. Treats Nickel and Zinc (0.099 mg/L limit for Ni and 0.6 mg/l limit for Zn)

  • Volvo NRV Plant – Dublin, Virginia

    Usage Points With a Focus on Process Opportunities E-coat high-purity water (HPW) system required replacement Ran 3-4 months of water testing to baseline system to verify

    performance before incorporating process needs Advantage:

    Avoid additional capital expense and incorporated e-coat into reuse system instead

    Disadvantages: Drives reuse water requirement to lower conductivity More frequent discharge events due to more stringent

    water quality requirements

  • Volvo NRV Plant – Dublin, Virginia

    PROCESS

    E-coat System: 15,000 to 20,000 gpd

    NON-PROCESS

    Humidification: 500 to 1,000 gpd

    Parts Wash: 12,000 gpd

    Cooling Tower: 4,000 to 6,000 gpd

    Usage Points

  • Volvo NRV Plant – Dublin, Virginia

    System Upgrade in 2015• UltraFilter and High Pressure Reverse Osmosis replaced NF/RO

    – When NF permeate conductivity > 2000 µohms/cm, the RO permeate conductivity will exceed 30 µohms for processes.• Resulting in a discharge event

    – Install UF and HPRO operating at 800 – 1000 psi allowing treatment of conductivities of 45,000 µohms/cm

    • Upstream of WWTP, reduce solids content of wastewater to minimize impact and loading on UF and HPRO– Install filter system to remove E-coat solids and other solids

    • Improve Water Balance between production and non-production periods– Added two 17,000 gallon tanks to store clean water for reuse

  • Volvo NRV Plant – Dublin, Virginia

    Process Wastewater Treatment MethodThe reuse system consists of the following components:

    To PlantProcesses

    Cartridge Filter

    UV LightUF FeedStorage

    Ultra-Filtration

    High Pressure Reverse Osmosis

    ReuseWater

    StorageUV Light

    WWT

    WasteWater

    Storage

    HPRO Feed

    Storage

    UntreatedWastewater

    UV Light

  • Volvo NRV Plant – Dublin, Virginia

    Design Specifications and Installation

    Ultraviolet Light (254nm) Cartridge Filtration

  • Volvo NRV Plant – Dublin, Virginia

    Design Specifications and Installation

    Ultra-Filtration High Pressure RO

  • Volvo NRV Plant – Dublin, Virginia

    Process Improvement - 2015• Installed solids removal equipment for E-coat discharge to

    reduce impact of process on conductivity/TDS & TSS.

  • Volvo NRV Plant – Dublin, Virginia

    Process Improvement - 2015

    • Expand the storage capacity for reuse water to address losses associated with shutdown periods by addition of two 17,000 gallon pure water storage tanks.

  • Volvo NRV Plant – Dublin, Virginia

    Process Improvement - 2015• High pressure RO system will address lower conductivity

    requirement for E-coat, but allow improved system reuse (provide up to 93% recovery of process water)– Operating at membrane pressures from 800 to 1,000 psi will

    allow for treatment of waters with conductivities approaching 45,000 μohms/cm.

  • Volvo NRV Plant – Dublin, Virginia

    Reference: EPRI- 2013 - Electricity Use and Management in the Municipal Water Supply and Wastewater Industries• Public Water Supply Average w/o CEC data = 1,903 kWh/MG

    – Community Surface Source = 1,600 kWh/MG– Community Groundwater Source = 2,100 kWh/MG

    • Municipal Wastewater/Secondary Treatment = 2,080 kWh/MG– Greater than Secondary Treatment = 2,690 kWh/MG

    • For this analysis:1903 + 2080 = 3983 kWh/MG or 3.983 kWh/1000 gallons

  • Volvo NRV Plant – Dublin, Virginia

    Impact of Reduction in Water Use

    • Plant-wide Baseline Water Use is 62M gal• Water Use Average from 2004 to Present is 39M gal• Average Annual Reduction in Water Use is 23M gal• Plant-wide Average Cost Savings is $216,230 per yr-------------------------------------------------------------------------• WWTP reuse system savings in 2015 is ~$69,000• Increased Energy Use for WWTP reuse system is

    136,320 KWH on average or $18,135/year • WWTP reuse system net cost savings is ~$51,000 in

    2015

  • Volvo NRV Plant – Dublin, Virginia

    Nominal Benefit to the County

    • County Energy Savings Based on plant water savings• 926 KWH per Year average

    • At 7.5 cents/KWH, Average County Cost Avoidance• $69.46 per year

    • Overall, nominal energy savings or cost benefit for the County

  • Volvo NRV Plant – Dublin, Virginia

    Overall Benefits for Wastewater Recycling and Reuse

    • Additional energy cost to operate reuse systems is outweighed ~ 4:1 by the savings from reduced water use at county rates

    • Improved feed water quality and water balance for processes

    • Reduced chemical usage for non-process requirements

    • Partial Fulfillment of the Volvo Environmental Goal

    • Reduced environmental liability and risk with fewer discharges to POTW

  • Volvo NRV Plant – Dublin, Virginia

    Thank You

  • Steve Pierett, C.E.M., CP EnMS, C.R.M.

    Environmental Manager

    Volvo Group North America, LLC 540-674-7730

    [email protected]

    Brian Kidd, Principal

    ProChem, Inc.

    540-268-9884

    [email protected]

    mailto:[email protected]:[email protected]

    Slide Number 1New River Valley Plant, Dublin, VAOVERVIEWSlide Number 4Cab Leak Test Water Recycling�Process Wastewater Treatment MethodProcess Wastewater Reuse DriversProcess Wastewater Reuse IncentivesProcess WWTP SpecificationsUsage Points With a Focus on Process OpportunitiesUsage Points �System Upgrade in 2015Process Wastewater Treatment MethodDesign Specifications and InstallationDesign Specifications and InstallationProcess Improvement - 2015Process Improvement - 2015Process Improvement - 2015Reference: EPRI- 2013 - Electricity Use and Management in the Municipal Water Supply and Wastewater IndustriesImpact of Reduction in Water UseNominal Benefit to the CountyOverall Benefits for Wastewater Recycling and ReuseThank You Slide Number 24