water licence application for construction of inuvik ... · figure 3-1 is a map of the inuvik to...

94
Water Inuvik SubmJune 2 Prepare Govern Departm Yellowk Prepare Kavik-S Inuvik, Project r Licence A k - Tuktoya ission to the 013 ed for: nment of the ment of Tran knife, Northwe ed by: Stantec Inc. Northwest Te Number: 123 Application aktuk Highe Northwes Northwest T nsportation est Territories erritories and 3511113 n for Consway st Territorie Territories s Calgary, Albe truction of s Water Bo erta f oard

Upload: others

Post on 21-Mar-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

WaterInuvik

Submi

June 2

PrepareGovern

Departm

Yellowk

PrepareKavik-S

Inuvik, N

Project

r Licence Ak - Tuktoya

ission to the

013

ed for: nment of the

ment of Tran

knife, Northwe

ed by: Stantec Inc.

Northwest Te

Number: 123

Applicationaktuk Highw

e Northwes

Northwest T

nsportation

est Territories

erritories and

3511113

n for Constway

st Territorie

Territories

s

Calgary, Albe

truction of

s Water Bo

erta

f

oard

Page 2: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk
Page 3: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Table of Contents

June 2013

iii

Table of Contents

1 PROJECT NAME..........................................................................................................................1-1

2 APPLICANT AND CONTRACTOR CONTACT INFORMATION.................................................2-1

2.1 APPLICANT INFORMATION........................................................................................................2-1

2.2 CONTRACTOR AND SUB-CONTRACTORS INVOLVED IN THE PROJECT ............................2-1

3 LOCATION OF UNDERTAKING..................................................................................................3-1

4 DESCRIPTION OF UNDERTAKING............................................................................................4-1

4.1 PROJECT DETAILS .....................................................................................................................4-44.1.1 Embankment Construction ...........................................................................................4-44.1.2 Watercourse Crossings Construction ...........................................................................4-4

4.1.2.1 Bridge Crossings .....................................................................................4-134.1.2.2 Culverts ...................................................................................................4-13

4.1.3 Borrow Pit Development .............................................................................................4-144.1.3.1 Additional Studies Required for Borrow Sources....................................4-17

4.1.4 Winter Road Construction...........................................................................................4-184.1.5 Camps and Other Supporting Infrastructure...............................................................4-18

4.2 ABANDONMENT PLAN..............................................................................................................4-19

4.3 PROPOSED TIME SCHEDULE .................................................................................................4-20

5 TYPE OF UNDERTAKING ...........................................................................................................5-1

6 STUDIES UNDERTAKEN TO DATE ...........................................................................................6-1

7 WATER USE.................................................................................................................................7-1

7.1 OBTAINING WATER ....................................................................................................................7-1

7.2 CROSSING WATERCOURSES ...................................................................................................7-1

7.3 MODIFYING THE BED OR BANK OF A WATERCOURSE.........................................................7-1

8 QUANTITY OF WATER INVOLVED ............................................................................................8-1

8.1 WINTER ACCESS ROAD CONSTRUCTION...............................................................................8-6

8.2 CAMP WATER USE .....................................................................................................................8-8

8.3 WATER SOURCES ......................................................................................................................8-8

9 WASTE DEPOSITED ...................................................................................................................9-1

9.1 WASTE MATERIALS GENERATED ............................................................................................9-19.1.1 Greywater and Sewage ................................................................................................9-19.1.2 Solid Waste...................................................................................................................9-29.1.3 Recyclables and Hazardous Waste..............................................................................9-2

9.2 SURFACE WATER RUNOFF.......................................................................................................9-3

9.3 STORAGE OF FUEL ....................................................................................................................9-39.3.1 Fuel and Lubricants ......................................................................................................9-39.3.2 Explosives.....................................................................................................................9-4

10 OTHER PERSONS OR PROPERTIES AFFECTED BY THIS UNDERTAKING.......................10-1

Page 4: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water LicSubmissTable of CJune 2013

iv

11  C11.1  S

11.2  S

12  E12.1  T12.2  H

12.3  F

13  P

M13.1  O

13.2  S13.3  V

13.4  P

13.5  IM

13.6  R1313131313131313

13.7  A

13.8  E13.9  P

13.10  C

14  E

15  R

List of

Table 2-1Table 4-1Table 4-2

Table 4-3Table 4-4Table 4-5Table 4-6

Table 4-7Table 4-8

cence Applicion to the No

Contents

COMMUNITY UMMARY OF

UMMARY OF

NVIRONMENERRAIN, SO

HYDROLOGY

ISH AND FIS

REDICTED E

MITIGATION .OVERVIEW ...

PATIAL AND

VALUED COM

ROJECT INT

MPACT ASSE

RESIDUAL EF3.6.1  Asse3.6.2  Terr3.6.3  Wate3.6.4  Wate3.6.5  Fish3.6.6  Mus3.6.7  Wate3.6.8  Harv

ASSESSMENT

FFECTS OF ROPOSED M

CUMULATIVE

NVIRONMEN

REFERENCES

f Tables

ApplicScopeBorrowDeveloWatercBorrowPrimarOptionSourceConstrWater

cation for Coorthwest Ter

CONSULTATF PUBLIC INV

F ISSUES AN

NTAL OVERVILS AND PER

Y AND WATER

SH HABITAT .

ENVIRONME..........................................

D TEMPORAL

MPONENTS ..

TERACTIONS

ESSMENT AN

FFECTS OF Tessment of Rain, Soils ander Quantity (Ser Quality ..... and Fish Hakrat and Beaverbirds and Wvesting and T

T OF RESIDU

ACCIDENTS

MONITORING

E EFFECTS...

NTAL MANAG

S ...................

ant Contact Ine of Developmw Sources anopment as Recourse Crossw Sources Pory Constructional (Preferredes .................ruction ActivitLicence App

onstruction oritories Wate

TION ............VOLVEMENT

ND CONCERN

VIEW ............RMAFROST .

R QUALITY ..

.....................

NTAL IMPAC

.....................

.....................

L SCOPE ......

.....................

S WITH THE

ND MITIGATI

THE PROJECesidual Envird Permafrost .Surface Wate.....................bitat ..............ver ................

Waterfowl ......Traditional Lan

UAL ENVIRO

S AND MALFU

G PROGRAM

.....................

GEMENT PL

.....................

nformation ....ment as Revie

d Material Reeviewed by Esing Type andotentially to beon Plan includ) Constructio.....................ty Timing (Winlication Pre-C

of Inuvik - Tuer Board

......................T ....................

NS ................

......................

......................

......................

......................

CTS OF UND

......................

......................

......................

......................

ENVIRONME

ON ...............

CT ON THE Eonmental Effe......................r) ..........................................................................................................nd Use ..........

ONMENTAL E

UNCTIONS ...

MS ..................

......................

ANS .............

......................

......................ewed by EIRBequirements CIRB ...............

d Locations ....e Used Duringding Use of Sn Plan Includ......................nter/ Summer

Construction P

ktoyaktuk H

.....................

.....................

.....................

.....................

.....................

.....................

.....................

DERTAKING A

.....................

.....................

.....................

.....................

ENT ..............

.....................

ENVIRONMENects .................................................................................................................................................................

EFFECTS ................................................

.....................

.....................

.....................

.....................B ....................Considered in..........................................g Project Con

Six Borrow Soing Use of Fo.....................r) ..................Program Sche

ighway

.....................

.....................

.....................

.....................

.....................

.....................

.....................

AND PROPO

.....................

.....................

.....................

.....................

.....................

.....................

NT ........................................................................................................................................................................................

.....................

.....................

.....................

.....................

.....................

.....................

.....................

.....................n the Scope o..........................................

nstruction ......urces ............ourteen Borro..........................................edule and Sta

......................

.....................

.....................

......................

.....................

.....................

.....................

OSED

......................

.....................

.....................

.....................

.....................

.....................

.....................

.....................

.....................

.....................

.....................

.....................

.....................

.....................

.....................

.....................

.....................

.....................

.....................

......................

......................

.....................

.....................of the ....................................................................................ow ..........................................atus ..............

.. 11-1 

.. 11-1 

.. 11-1 

.. 12-1 

.. 12-1 

.. 12-2 

.. 12-7 

.. 13-1 

.. 13-1 

.. 13-2 

.. 13-2 

.. 13-3 

.. 13-4 

13-11 13-11 13-11 13-12 13-12 13-12 13-13 13-14 13-14 

13-15 

13-16 

13-18 

13-18 

.. 14-1 

.. 15-1 

.... 2-1 

.... 4-1 

.... 4-3 

.... 4-5 

.. 4-15 

.. 4-16 

.. 4-17 

.. 4-20 

.. 4-20 

Page 5: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Table of Contents

June 2013

v

Table 8-1 Annual Project Water Use – Southern Spread ................................................................8-1Table 8-2 Annual Project Water Use – Northern Spread.................................................................8-1Table 8-3 Proposed Water Sources (Year 1)...................................................................................8-2Table 8-4 Proposed Water Sources (Year 2)...................................................................................8-4Table 8-5 Proposed Water Sources (Year 3)...................................................................................8-5Table 8-6 Daily and Annual Water Use Requirements per Construction Period .............................8-7Table 8-7 Length of Access Trails and Winter Roads Over Land and Water ..................................8-7Table 12-1 List of Common Freshwater Fish found in the Project Area (modified from

Rescan 1999).................................................................................................................12-7Table 13-1 Candidate and Selected Valued Components in the Project Area and Rationale

for Selection ...................................................................................................................13-3Table 13-2 Project Activity Interaction Matrix...................................................................................13-4Table 13-3 Potential Environmental Effects and Mitigations............................................................13-5Table 13-4 Synopsis of Recommended EIRB Mitigations Additional to Developer

Commitments ...............................................................................................................13-15

List of Figures

Figure 3-1 ITH Project Overview .......................................................................................................3-3Figure 3-2 Watercourse Crossings along the ITH Alignment............................................................3-5Figure 4-1 Culvert Type Section........................................................................................................4-7Figure 4-2 Large Diameter Bridge Culvert Type Section ..................................................................4-9Figure 4-3 Major Crossing - Bridge Type Section ...........................................................................4-11Figure 12-1 ITH Project Drainage Basins..........................................................................................12-3Figure 12-2 ITH Project Watersheds.................................................................................................12-5

Appendices

APPENDIX A Schedule III FormAPPENDIX B Construction Plan Overview AtlasAPPENDIX C Watercourse Crossing Overview AtlasAPPENDIX D Studies Undertaken to DateAPPENDIX E Environmental Management PlansAPPENDIX F Hunter and Trapper Committee PresentationAPPENDIX G EIRB’s Final Report of the Panel for the Substituted Environmental Impact

Review Proposal to Construct the Inuvik to Tuktoyaktuk HighwayAPPENDIX H Government of Canada Response to the Panel Report on the Proposal to

Construct the Inuvik to Tuktoyaktuk HighwayAPPENDIX I Developer/ Applicant Commitments

Page 6: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardTable of Contents

June 2013

vi

Page 7: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 1: Project Name

June 2013

1-1

1 PROJECT NAME

Construction of the Inuvik to Tuktoyaktuk Highway

Page 8: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 1: Project Name

June 2013

1-2

Page 9: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 2: Applicant and Contractor Contact Information

June 2013

2-1

2 APPLICANT AND CONTRACTOR CONTACT INFORMATION

Applicant and contractor contact information are provided in the following subsections. A signed Schedule

III form is included in Appendix A.

2.1 Applicant Information

The contact information for the Applicant, and their Primary and Field contact persons are provided in

Table 2-1.

Table 2-1 Applicant Contact Information

Applicant

Name Government of the Northwest Territories – Department of Transportation

(GNWT-DOT)

Mailing Address Lahm Ridge Tower, 2nd Floor

4501 50 Avenue

P.O. Box 1320

Yellowknife, NT X1A 2L9

Phone 867-920-6247

Fax 867-920-2565

Primary Contact Field Contact

Name Jim Stevens

Title Director Mackenzie Valley Highway

Phone 867-920-6247

Alternate Phone 867-445-3151

Fax 867-920-2565

2.2 Contractor and Sub-contractors Involved in the Project

A contractor will be confirmed in September 2013.

Page 10: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 2: Applicant and Contractor Contact Information

June 2013

2-2

Page 11: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 3: Location of Undertaking

June 2013

3-1

3 LOCATION OF UNDERTAKING

Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between

Inuvik and Tuktoyaktuk in the Inuvialuit Settlement Region (ISR). The ITH project traverses Tuktoyaktuk

7(1)(a) and 7(1)(b) lands, as identified in the Inuvialuit Final Agreement, and Crown lands. Proposed

borrow sources, watercourses, water sources, camps, and access trails are shown in the Construction

Atlas (Appendix B) and watercourse crossings are shown in Figure 3-2 and the Watercourse Crossings

Atlas (Appendix C). No wastes are proposed for deposit in the ITH project area.

The UTM coordinates (UTM Zone 8, NAD 83) of the Project are as follows:

KP 0 (at the end of Navy Road) - Easting: 550347.89, Northing: 75910194.07

KP 119 (at the junction of the Tuktoyaktuk to Source 177 Access Road) –

Easting: 579470.03, Northing: 7690056.87

Page 12: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 3: Location of Undertaking

June 2013

3-2

Page 13: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

NUNWTYT

INUVIK TO TUKTOYAKTUK CONSTRUCTION PROGRAM

ITH Project OverviewFIGURE NO. 3-1

ProjectLocation

Acknowledgements: Original Drawing by Jacques Whitford - AXYS Ltd.

Last

Modif

ied: J

une 1

1, 20

13 B

y: jpe

tho

PW13

170

309

173/305

314/325

Navy Pit

I401AI401A

PW11 (2.46)

PW10 (2.46)

GSC4

GSC3

PW17

PW18

PW19

312 West

174

177

27A

Inuvik

Tuktoyaktuk

SitidgiLake

NoelLake

HuskyLakes

ParsonsLake

HuskyLakes

Old ManLake

Macken

zie Ri

ver

Holmes Creek

Middle Channel

East Channel

8

43

31

18

35a

30a

23a

PREPARED FOR

123510689-175

0 5 10 15

KilometresMetres - 1:375,000

Major Bridge Crossing

Potential Borrow Source

Highway Alignment

Tuktoyaktuk to Source 177 Access Road

Navy Road

Inuvik, 7(1)a Private Lands

Inuvik, 7(1)b Private Lands

Tuktoyaktuk, 7(1)a Private Lands

Tuktoyaktuk, 7(1)b Private Lands

Provincial Park/Reserve

PREPARED BY

Page 14: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk
Page 15: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

NUNWTYT

INUVIK TO TUKTOYAKTUK HIGHWAY OVERVIEW

Watercourse Crossings along the ITH AlignmentFIGURE NO. 3-2

ProjectLocation

Acknowledgements: Original Drawing by Jacques Whitford - AXYS Ltd.

Last

Modif

ied: J

une 1

1, 20

13 B

y: jpe

tho

PW13

170

309

173/305

314/325

I401AI401A

PW11 (2.46)

PW10 (2.46)

GSC4

GSC3

PW17

PW18

PW19

312 West

174

177

27A

Inuvik

Tuktoyaktuk

SitidgiLake

NoelLake

HuskyLakes

ParsonsLake

HuskyLakes

Old ManLake

Macken

zie Ri

ver

Holmes Creek

Middle Channel

East Channel

Pingo CanadianLandmark

9 87 6

543

1

A2

A3

A8

A9

31

2625

21

20

1817

15

14

13

1210

39d39c

39b

39a

A2a

A10A11

A1335a

34e34c

34b

34a33b

30a29a

28a

27c27b

24a23a

22b

22a

21a

13a

2

19

16

11

5a

A12

33a

27a

24b

20a

18a

17a

12b12a

34a2

27b2

PREPARED FOR

123510689-169

0 5 10 15

KilometresMetres - 1:375,000

Major Bridge Crossing

Large Diameter Bridge Culvert

Culvert

Potential Borrow Source

Highway Alignment

Tuktoyaktuk to Source 177 Access Road

Navy Road

Provincial Park/Reserve

PREPARED BY

Page 16: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk
Page 17: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 4: Description of Undertaking

June 2013

4-1

4 DESCRIPTION OF UNDERTAKING

GWNT-DOT is submitting a Water Licence Application to the Northwest Territories Water Board

(NWTWB), to authorize certain activities associated with construction of the Inuvik to Tuktoyaktuk

Highway pursuant to requirements of the Northwest Territories Waters Act and the Northwest Territories

Waters Regulations.

The ITH project is a proposed 140 km all-season highway between the Town of Inuvik and the Hamlet of

Tuktoyaktuk in the ISR. The ITH project has undergone substituted panel review by the Environmental

Impact Review Board (EIRB) pursuant to the Inuvialuit Final Agreement and the Canadian Environmental

Assessment Act. The EIRB concluded in its decision report of January 25, 2013 that the ITH project will

result in significant impacts to the environment, but that these impacts can be mitigated through the

implementation of 51 recommended measures (Appendix G, EIRB 2013). The Governments of Canada

and Northwest Territories have responded to the EIRB’s report by accepting, accepting the intent or

rejecting each of the EIRB’s recommendations (Appendix H, Government of Canada 2013).

The EIRB’s recommendations were based on the scope of the development as shown in Table 4-1.

Table 4-1 Scope of Development as Reviewed by EIRB

Project Component Included in Scope of Development Not Included in Scope of Development

All-weather highwayfrom Inuvik toTuktoyaktuk

Primary Alignment as amended byAlternatives 1 and 3

Alternative 2 (Upland Route), and thoseportions of the Primary alignment amendedby Alternatives 1 and 3

Watercourse crossingstructures

84 stream crossing structures,consisting of 52 culverts, 9 bridges, 23culverts or short bridges

Summer works – limited to out-of-streambed activities, such as bridgegirder and deck construction andassociated works

Winter works – all instream activitiesand associated works

Any additional stream crossingstructures not included in this inventory

Summer works – no instream work orassociated activities

Page 18: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 4: Description of Undertaking

June 2013

4-2

Table 4-1 Scope of Development as Reviewed by EIRB (cont’d)

Project Component Included in Scope of Development Not Included in Scope of Development

Aggregate Sources(borrow and quarryareas to supportconstruction,operations andmaintenancerequirements)

The aggregate sources and volumes to beextracted in the indicated timeframes, asidentified in Table 1

Any additional aggregate sources notidentified in Table 1

1

Any additional volumes not identified inTable 1

Any additional volume of aggregaterequired from any of the identifiedsources during any of the operationaltime periods (i.e., construction, years 1-20, 21-40, 41-50) indicated in Table 1

Construction stagingareas

Construction staging areas to be usedduring construction of the ITH

None

Maintenance areas Winter and summer season maintenanceareas associated with the temporaryconstruction camp locations

Any other maintenance area required duringconstruction but not identified

Temporaryconstruction campfacilities (includingwater use,wastewater disposal,resupply, powersupply, and domesticwaste disposal)

Temporary construction camp facilitieslocated at the borrow source closer to theconstruction activities

Any other temporary construction campfacilities not located at the closest borrowsource

Temporaryconstruction accessroads

Temporary winter access road that isparallel to the permanent alignmentduring construction

Temporary winter access roads to theborrow sources during construction

None

Ongoing operationsof the all-weatherhighway

All equipment and associated activities foroperations phase will be staged locallyfrom Inuvik and Tuktoyaktuk

Maintenance or staging areas that maybe required for operations that will belocated at any point along the Inuvik toTuktoyaktuk Highway

Temporary or permanent access roadsto water sources to be used for dustsuppression during operations phase

Stockpile areas along the permanentroad alignment used to store granularmaterial for summer maintenance andre-habilitation during the operationsphase

1Note that this should refer to “Table 2” in the EIRB report (EIRB 2013) titled “Estimated Material Requirements for

the 50-year Period”. For reference, these include Sources 325/314, 309, 174, 170, 177, 173/305 and 307.

Page 19: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Table 2 of

Table 4-2

The ITH p

Const

Winte

Winte

Winte

Const

Summ

Winte

Trans

Storag

Construct

f the EIRB’s R

2 BorroDevel

project compr

truction and o

er developmen

er and summe

er construction

truction of per

mer embankm

er and summe

sportation of fu

ge of fuel

tion activities

Water Lice

Report of EIR

ow Sourceslopment as

ises:

operation of w

nt and operati

er operation of

n of new emb

rmanent wate

ment compacti

er operation of

uel, waste, eq

are planned t

nce Applicat

R is reproduce

and MateriReviewed b

winter roads an

ion of borrow

f temporary c

ankment

ercourse cross

ion, surfacing

f temporary m

quipment and

to begin winte

tion for ConsSubmission

ed here for ref

ial Requiremby EIRB

nd access tra

sources

camps

sing and drain

and grading

maintenance a

personnel

er 2013 and w

struction of In to the North

Secti

ference, as T

ments Cons

ails

nage structure

and storage a

will be comple

Inuvik - Tukthwest Territoon 4: Descrip

Table 4-2.

sidered in th

es

areas

eted summer

toyaktuk Higories Water Bption of Undert

June

he Scope o

2017.

ghwayBoardtaking e 2013

4-3

f the

Page 20: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 4: Description of Undertaking

June 2013

4-4

4.1 Project Details

Throughout this discussion, construction activities are described as being undertaken in either “winter” or

“summer”. For the purpose of this application, “winter” is defined as the period between approximately

November 15 and April 30, and “summer” is considered to be the period between May 1 and

November 14. These periods may change annually based on snow and ground conditions.

4.1.1 Embankment Construction

Approximately 40 km of new alignment will be constructed each winter, along separate spreads, each

approximately 20 km in length. Construction spreads will progress from North to South (beginning at

Source 177 Access Road), and South to North (generally beginning at the end of Navy Road, within the

ISR). Progressive spreads constructed each winter will begin at the end of the embankment constructed

the previous winter. Construction of the embankment for the ITH project will occur during the winter

months to protect the ice-rich terrain along the alignment and to establish a frozen core embankment for

the highway.

Embankment material will be sourced from borrow pits authorized for use on the project. Material will be

hauled directly from borrow pits to the end of constructed embankment, where it will be “end-dumped”

over geotextile fabric, and leveled. Successive “lifts” (thicknesses) of material will be placed until the

specified thickness is achieved.

Surfacing and grading of constructed embankment will be conducted in summer, once the constructed

embankment is able to support heavy equipment: during mid-July to late September. During this time,

compaction of the embankment and installation of insulation in certain areas may also be completed.

Material suitable for surfacing will be sourced from approved sources and will have been stockpiled along

the embankment in winter.

4.1.2 Watercourse Crossings Construction

The ITH from Kilometer Post (KP) 0 to KP 119 crosses 65 watercourses. In summer 2012, a

hydrotechnical field assessment of the stream crossings was completed to obtain site specific information

for the design of each watercourse crossing (KAVIK-STANTEC 2012e). Specific information collected on

each watercourse crossing including geographic coordinates (UTM based), channel descriptions,

topographical information including channel cross sections, elevation, water velocity measurements, and

photographs. A desktop hydrologic analysis was completed to estimate the 2-year, 10-year, 20-year,

50-year and 100-year return flow for each watershed along the proposed highway. A copy of this study is

included in Appendix B of KAVIK-STANTEC’s (2012e) Hydrotechnical Assessment of Stream Crossings

(provided in Appendix D.3). This information was used to complete an advanced design of the size and

type of the crossings for each of the 65 watercourses. A final design is expected in August 2013.

Fish and fish habitat related assessments have also been undertaken at select watercourse crossings

with potential fish habitat (Appendix D.4, D.5, D.6).

Page 21: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 4: Description of Undertaking

June 2013

4-5

The construction of the watercourse crossings will be concurrent with the construction of the new highway

embankment. Crossing structures will comprise culverts, large diameter bridge culverts, and bridges.

Final crossing designs will be submitted to support applications for fisheries authorizations.

Three crossing categories are proposed for the ITH project. The crossing locations, categorized by type,

are shown in Figure 3-2 and the Watercourse Crossing Atlas (Appendix C). The crossing types include:

Culvert crossings – crosses watercourses that are small in width, with peak 100-year flows of up to 3.0

metres/second (m3/s). Culvert structures of minimum 1,200 mm diameter will be used. A type section

drawing of a culvert is shown in Figure 4-1.

Large diameter bridge culvert crossings – will be used to cross watercourses with larger wetted widths

than culvert crossings and with peak 100-year flows of between 3.0 m3/s and 4.0 m

3/s. A type section

drawing of a large diameter bridge culvert is shown in Figure 4-2.

Major bridge crossings – typically crosses watercourses larger in width than watercourses crossed by

large diameter bridge culvert crossings, and with peak 100-year flows greater than 4.0 m3/s. A type

section drawing of a major bridge crossing is shown in Figure 4-3.

Final crossing designs will be available in August 2013.

The crossings types and geographic coordinates are listed in Table 4-3 and shown on Figure 3-2.

Table 4-3 Watercourse Crossing Type and Locations

Crossing Type Crossing # Northing Easting Crossing # Northing Easting

Culvert Crossing 1 7591582.3 550663.1 25 7629147.3 559101.8

2 7591899.5 550677.3 26 7630498.2 558692.7

5 7594078.0 550770.7 27a 7632088.7 559103.4

5a 7594199.8 550776.2 27b 7633290.0 558943.2

6 7596008.5 550877.7 27b2 7634125.3 558597.0

7 7596782.8 550489.2 27c 7634927.0 558119.7

9 7598256.7 550524.8 28a 7638033.9 558406.2

10 7598920.1 550436.2 29a 7639756.6 558215.9

11 7599279.2 550485.0 33a 7656657.9 567410.9

12 7600900.1 550243.5 33b 7656660.9 567653.9

12a 7601903.5 550447.4 34a 7657858.4 569591.3

12b 7602926.7 550398.4 34a2 7660124.8 571503.8

13 7602970.6 550405.2 34b 7660497.8 572206.4

13a 7606561.1 551297.6 34c 7661864.8 573369.7

14 7608123.4 552137.6 34e 7662853.5 573754.7

Page 22: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 4: Description of Undertaking

June 2013

4-6

Table 4-3 Watercourse Crossing Type and Locations (cont’d)

Crossing Type Crossing # Northing Easting Crossing # Northing Easting

Culvert Crossing(cont’d)

16 7611749.0 553248.2 A13 7664637.7 575960.8

17 7612085.1 553395.0 A11 7667973.0 576384.9

18a 7614160.4 555251.5 A10 7668519.5 576566.3

19 7614235.2 555440.8 A9 7669715.5 577775.8

20 7614393.5 556120.3 A8 7671465.9 577944.0

20a 7614578.6 556336.0 A2 7676338.5 578994.3

21a 7616111.9 557674.4 A2a 7678011.7 582169.6

22a 7618194.1 558218.8 39a 7680357.8 583457.9

22b 7622664.6 558812.1 39b 7683024.2 582861.7

24a 7628182.3 558907.9 39c 7683711.4 582984.8

24b 7628460.1 558988.5 39d 7685257.4 582320.0

Large DiameterBridge CulvertCrossing

15 7610783.2 553217.9

17a 7612979.5 554011.6

21 7614766.9 556660.1

A12 7667634.6 576340.0

A3 7674365.3 577908.5

Major BridgeCrossing

3 7592392.6 550644.5

4 7593258.0 550710.9

8 7597730.2 550570.8

18 7613971.9 554813.2

23a 7626147.9 559229.3

30a 7640372.3 558731.5

31 7648594.3 563401.5

35a 7664134.8 575596.5

Page 23: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk
Page 24: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk
Page 25: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk
Page 26: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk
Page 27: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk
Page 28: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk
Page 29: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 4: Description of Undertaking

June 2013

4-13

There are nine watercourse crossings greater than 5 m wide at the ordinary high water mark, as

assessed by KAVIK-STANTEC in Hydrotechnical Assessment of Stream Crossings (2012e,

Appendix D.3). These crossings include 3, 4, 13A, 18, 21, 30A, 31, 35, A2a; their locations are shown on

the Watercourse Crossing Atlas (Appendix C).

The in-stream activities for closed bottom culvert installations will be confined to winter months, when all

locations are anticipated to be frozen to the bottom. In-stream activities are described in the following

subsections.

4.1.2.1 Bridge Crossings

Bridges and bridge foundations will be constructed at up to eight watercourse crossing locations

(Table 4-3). Bridge foundations will be constructed concurrent with embankment construction - within

spreads to be constructed each winter.

The construction of the foundations at most bridge crossings consists of:

installation of pilings (January - February) - these piles will be located outside of the stream channel in

all cases. No piles will be installed within the normal flow channel. The ad-freeze piles will be bored

into the stream bank, the cutting material hauled away for disposal, the piles installed in the boring,

and a sand slurry mix poured into the hole to bond the pile to boring wall.

installation of foundations/abutments and wing walls (February - March) - these abutments and wing

walls are installed on top of the piles, out of the stream bed itself. As such there is no work in the

stream itself on these items.

launching girders (May)

placement of erosion control (April - May) - erosion control may consist of placement of large diameter

clean rock, hand placed from the edge of the stream bed covering the embankment and protecting the

piles, abutments, and wing walls from erosion. Erosion control will be conducted in a manner

consistent with the Sediment and Erosion Control Plan (Appendix E.1).

While bridge foundations are being constructed, a winter ice bridge or snow fill detour will be constructed

adjacent to the works to allow movement of equipment around the construction site. Decking will be

placed in winter, but final manual installation of railings will be completed in summer.

4.1.2.2 Culverts

The embankment construction will include the placement of small and large diameter culverts for

watercourse crossings and to prevent ponding along the edges of the embankment (equalization

culverts). These crossing locations are distributed along the length of the highway. Culvert installation will

be concurrent with embankment construction along that section.

Page 30: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 4: Description of Undertaking

June 2013

4-14

The placement of large diameter culverts will occur after the stream to be crossed has frozen to the

bottom, and will involve the following steps:

excavation of ice out of the streambed to the installation elevation

sub-excavation, if required (at the present time, sub-excavation is not anticipated for any crossing)

placement of suitable granular material as the foundation bedding

compaction, installation of the culvert and backfilling

placement of erosion control as required

All culvert crossings are anticipated to be frozen to the bottom during installation. However, if it is found

that installation will be required in a stream that does not freeze to the bottom, an isolated crossing

construction will be applied with appropriate approval from DFO.

The final design of culverts, including consideration of diameter, material, and closed- versus open-

bottom culverts will be determined as a part of final design. Final design will also specify the type of

culvert to be constructed at each crossing location.

While culverts are being constructed, a temporary winter ice bridge or snow fill detour will be constructed

adjacent to the works to allow movement of equipment around the construction site.

4.1.3 Borrow Pit Development

Borrow pits will be developed to provide material for embankment construction. Up to fourteen borrow pits

may be developed during the three to four year construction period. A number of these borrow sources

may be used for more than one year of winter construction. The development and use of material from six

of these borrow sources was included within the scope of the EIRB’s review. Eight additional sources are

being considered for development and use during the construction period, as identified in Table 4-4. All

borrow sources potentially to be used for project construction will require authorizations from Aboriginal

Affairs and Northern Development Canada or the Inuvialuit Land Administration. Use of Source 177 is

already authorized. Applications for land use permits, quarry licences and quarry permits will be

submitted in August 2013.

Page 31: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 4: Description of Undertaking

June 2013

4-15

Table 4-4 Borrow Sources Potentially to be Used During Project Construction

Borrow Source Land Owner

Status

GeotechnicalInvestigations Reviewed by EIRB

Source 177 Inuvialuit permitted

Source 170 Inuvialuit √ √

Source 173/305orSource 174*

Inuvialuit √ √

Inuvialuit/Crown planned √

Source 309 Crown planned √

Source 312W Crown planned -

Source PW19A Inuvialuit planned -

Source 314/325 Inuvialuit/Crown √ √

Source PW18 Crown planned -

Source PW17 Crown planned -

Source PW13 Crown planned -

Source GSC 3-4 Crown √ -

Source PW 10-11 Crown √ -

Source I401A Inuvialuit √ -

PRIMARY CONSTRUCTION PLAN – SIX BORROW SOURCES

A project construction plan has been developed around use of the six sources previously included within

the EIRB’s review (the “primary construction plan”), summarized in Table 4-5 and shown in Appendix B.

Borrow pit development will consist of:

construction of winter roads for hauling material

removal and stockpiling of overburden

blasting or ripping of material

temporary stockpiling of material

material hauling

erosion control and meltwater management

progressive (annual) reclamation of areas of the pit

Page 32: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 4: Description of Undertaking

June 2013

4-16

Table 4-5 Primary Construction Plan including Use of Six Borrow Sources

Borrow Source Land Owner

Alignment Segment / Timing Status

Year 1(N or S)

Year 2(N or S)

Year 3(N or S)

GeotechnicalInvestigations

Reviewedby EIRB

Source 177 Inuvialuit N - - permitted

Source 170 Inuvialuit N N - √ √

Source 173/305 Inuvialuit N N √ √

Source 174 Inuvialuit/Crown N N planned √

Source 309 Crown N planned √

Source 314/325 Inuvialuit/Crown S S √ √

Pits will be developed in accordance with the associated Pit Development Plan, to be approved by

Aboriginal Affairs and Northern Development Canada or Inuvialuit Land Administration, as part of

authorizations issued for individual pit development.

Borrow pits will be developed and operated in winter. During late summer (August – September), some

local grading and stockpiling may be undertaken at the source using equipment stored there during

summer. Winter camps and equipment will be stored during the summer at borrow sources, on a pad of

adequate thickness to protect permafrost. No summer road access to borrow pits will be required.

The methods for developing and operating these six borrow sources will apply to all sources proposed for

construction and will be detailed in pit development plans.

OPTIONAL CONSTRUCTION PLAN – FOURTEEN BORROW SOURCES

Use of other borrow sources identified in Table 4-6 is at this time optional, although preferred, and

described as the “optional construction plan”. The integration of optional sources into the construction

plan is being considered because it will reduce environmental effects, reduce project costs and improve

construction efficiency. Use of optional borrow sources during construction will:

Reduce the length of winter roads to be constructed

Limit operation of borrow sources to 1-2 construction seasons

Minimize need to construct winter roads to borrow sources over multiple seasons

Allow camps located at borrow sources to be closer to the alignment

Reduce project costs by reducing haul distance

The “optional” (yet preferred) integration of additional borrow sources is summarized in Table 4-6 and

illustrated in Appendix B.

Page 33: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 4: Description of Undertaking

June 2013

4-17

Table 4-6 Optional (Preferred) Construction Plan Including Use of Fourteen BorrowSources

Borrow Source Land Owner

Alignment Segment / Timing Status

Year 1(N or S)

Year 2(N or S)

Year 3(N or S)

GeotechnicalInvestigations

Reviewed byEIRB

Source 177 Inuvialuit N - - permitted

Source 170 Inuvialuit N N - √ √

Source 27A Inuvialuit - N X -

Source 173/305orSource 174*

Inuvialuit N √ √

Inuvialuit/Crown N planned √

Source 309 Crown N planned √

Source 312W Crown S planned -

Source PW19A Inuvialuit S planned -

Source 314/325 Inuvialuit/Crown S √ √

Source PW18 Crown S planned -

Source PW17 Crown - - - planned -

Source PW13 Crown planned -

Source GSC 3-4 Crown S S √ -

Source PW 10-11 Crown S √ -

Source I401A Inuvialuit S S S √ -

The GNWT-DOT made several commitments to mitigate effects from borrow pit development and

operation during the EIRB review process (Appendix I), and the EIRB made a number of

recommendations necessary to mitigate effects from borrow pit operations (Appendix G). GNWT-DOT

expects that these mitigations would apply to all fourteen borrow sources proposed for construction.

4.1.3.1 Additional Studies Required for Borrow Sources

Geotechnical investigations of all potential borrow sources to be used for construction have been ongoing

in 2012 and 2013, and additional investigations are planned for 2014. These investigations confirm the

volume, quality and extent of material, and will support applications for regulatory authorizations. All

geotechnical investigations of these fourteen proposed borrow sources were completed with the

appropriate permits and consultation with Inuvialuit organizations (KAVIK-STANTEC 2012a, 2012f).

During these consultations, GNWT-DOT communicated that the purpose of these investigations was to

identify additional potential borrow sources for use during project construction.

Page 34: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water LicSubmissSection 4:June 2013

4-18

Evaluation

develop a

Additiona

be subjec

4.1.4

Winter roa

camp sup

Winter roa

support he

roads will

a minimum

snow off e

thickness

alignment

roads will

Construct

Novembe

each seas

Water to c

are shown

Access tra

and to mo

will consis

4.1.5

During wi

include:

const

fuel st

waste

equip

Construct

operated

preferably

can be ad

cence Applicion to the No Description o

n of results of

a final constru

l borrow sour

ct to the Inuvia

Winter

ads and acce

pplies during w

ads comprise

eavy equipme

be constructe

m 20 cm of ic

established ic

of ice sufficie

t, and will max

be constructe

tion of the win

er of each yea

son.

construct acc

n in Appendix

ails will be co

obilize equipm

st of 20 cm of

Camps

nter and sum

ruction camps

torage facilitie

e storage, tran

ment and ma

tion camps wi

per spread (N

y be located a

ddressed by m

cation for Coorthwest Terof Undertaking

f geotechnica

ction plan, wh

ces not previo

aluit Final Agr

Road Cons

ss trails will b

winter constru

overland roa

ent operation

ed by sprayin

ce cover over

ce surface on

ent for the equ

ximize use of

ed immediate

nter and ice a

ar. Access roa

ess roads wil

x B and furthe

onstructed to c

ment to summ

f compacted s

and Other

mer construc

s

es

nsportation, tr

terials staging

ill be operated

North and Sou

at operational

moving borrow

onstruction oritories Wateg

al investigation

hich will acco

ously include

reement’s scr

struction

be constructed

uction.

ads and ice ro

s such as gra

ng water over

frozen groun

the lake and

uipment loads

f overwater po

ely adjacent to

ccess roads w

ads must be c

l be sourced

er details are p

conduct clear

mer storage loc

snow, and wil

Supporting

ction activities

reatment and

g areas

d in winter an

uth), for a tota

borrow sourc

w sources clo

of Inuvik - Tuer Board

ns of borrow s

ompany applic

d in the EIRB

reening proce

d to facilitate

oads. Winter r

avel hauling, f

a packed sno

d. Ice roads (

then, as requ

s. Winter road

ortions (ice ro

o the alignme

will begin as e

completed prio

from approve

provided in S

ring where req

cations, at the

l not require t

g Infrastruct

s, supporting f

disposal facil

nd summer. Tw

al of four cam

ces. Where lo

oser to the alig

ktoyaktuk H

sources is un

cations of use

B review, but p

ess.

movement of

roads will be c

fuel re-supply

ow trail, to cre

(over water) w

uired, flooding

ds will be loca

oads) where p

ent.

early as poss

or to commen

ed water sour

Section 8.

quired, to sup

e end of each

the applicatio

ture

facilities will b

ities

Two camps, of

mps during eac

ocal concerns

gnment, optio

ighway

nderway and w

e of individual

proposed for

f material, pe

constructed e

y and waste tr

eate a layer o

will be constru

g the ice surfa

ated in proxim

practical. In ot

sible in the win

ncing embank

rces. Potentia

pport winter ro

h winter seaso

on of any wate

be required. S

f 60 person c

ch winter. Wi

s, or environm

onal camp loc

will be used t

l borrow sourc

construction,

rsonnel, fuel,

each year to

ransfer. Winte

of ice, to estab

ucted by clea

ace to build u

mity to the

ther areas, w

nter, possibly

kment constru

al water sourc

oad construct

on. Access tr

er.

Supporting fac

capacity will b

nter camps w

mental impact

cations have b

o

ces.

may

and

er

blish

ring

p a

winter

y mid-

uction

ces

tion

ails

cilities

e

will

ts

been

Page 35: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 4: Description of Undertaking

June 2013

4-19

identified (Appendix B). Winter camps and borrow pit equipment will be stored during the summer at

borrow sources, on a pad of adequate thickness to protect permafrost.

Four camps will be operated in summer. Summer camps will have a capacity of 20 people, and will be

located on previously constructed embankment. Summer camps will support activities to be conducted

along the embankment, including compaction, grading and installation of railings.

Fuel storage areas will be needed at each camp location or at equipment and materials staging areas.

Diesel and gasoline will be required to support construction and camp operations. Fuel will be supplied

from Tuktoyaktuk and Inuvik, and refueling of vehicles will be undertaken either at the fuel storage

location, or at designated locations along the construction spread. Fuel will remain stored at camp

locations to be operated the following winter.

Five anticipated waste streams will be generated during the construction operations:

camp greywater

camp sewage

camp solid waste

recyclables

hazardous waste

The construction camps will utilize waste management facilities (greywater, sewage, solid waste and

recyclable waste) in both Inuvik and Tuktoyaktuk for the treatment and disposal of the waste generated at

the camps. Negotiations for this waste management service have been initiated with both communities.

Hazardous waste will be managed independently using the appropriate contracted resources for

collection, transport and ultimate disposal.

During construction, equipment maintenance will be required, and materials such as culverts and bridge

decks may need to be temporarily stored until emplacement. Designated areas will be constructed during

winter to allow for equipment and materials storage and maintenance. These storage and maintenance

areas will be located on or adjacent to borrow sources or constructed embankments.

4.2 Abandonment Plan

Reclamation plans will be included in each Pit Development Plan to be approved by the appropriate

regulator in accordance with the requirements of the Inuvialuit Settlement Region Granular Resources

Management Plan (ILA and INAC nd). A table of contents for a Pit Development Plan is provided in

Appendix E.4. GNWT-DOT is in discussion with Aboriginal Affairs and Northern Development Canada

and the Inuvialuit Land Administration regarding the content and details of such plans. The highway itself

is a permanent public infrastructure and as such, will not be abandoned.

Page 36: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 4: Description of Undertaking

June 2013

4-20

4.3 Proposed Time Schedule

Construction activities are planned to begin December 2013 and will be completed in September 2017.

The primary embankment construction activities shown in Table 4-7 ends in Summer 2016; however, it is

anticipated that some additional grading activities may carry over during Winter 2016-17 and Summer

2017. The program will experience periods of shutdown from approximately May 1 to July 15 each year.

Table 4-7 summarizes generally, the timing of construction activities in winter and summer.

A fourth winter of construction (2016-17) may be required to complete embankment construction,

including placement of surfacing material.

Certain additional pre-construction studies are planned. These are summarized in Table 4-8.

Table 4-7 Construction Activity Timing (Winter/ Summer)

Winter2013-14

Summer2014

Winter2014-15

Summer2015

Winter2015-16

Summer2016

Embankment and CrossingsConstruction

Year 1-N

Year 1-S

Year 2-N

Year 2-S

Year 3-N

Year 3-S

Borrow Pit Development 4 to 51

4 to 6 4 to 5

Access Road Construction Year 1-N

Year 1-S

Year 2-N

Year 2-S

Year 3-N

Year 3-S

Camps and SupportingInfrastructure

42

2 4 2 4 2

Surfacing/Grading/Railings Year 1-N

Year 1-S

Year 2-N

Year 2-S

Year 3-N

Year 3-S

NOTES:1

Indicates number of borrow sources to be developed2

Indicates number of camps to be operated

Table 4-8 Water Licence Application Pre-Construction Program Schedule and Status

Program Activity Proposed Timing Status

Fisheries/ Hydrology

Fish habitat assessments at locations notpreviously surveyed

Field Survey July 2013 Planned

Final Report August 2013 -

Bathymetric studies (of 38 lakes not previouslysurveyed)

Field Survey July 2013 Planned

Final Report August 2013 -

Page 37: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 4: Description of Undertaking

June 2013

4-21

Table 4-8 Water Licence Application Pre-Construction Program Schedule and Status(cont’d)

Program Activity Proposed Timing Status

Borrow Sources:

2013 geotechnical investigations of borrow sources Drilling NA Completed

Final Report June 2013 Working

2014 geotechnical investigations of borrow sources Drilling January –February 2014

Planned

Final Report June 2014 -

Consultation

Water Sources, Camp Locations, Navigable Waters(Tuktoyaktuk)

Consultation June 2013 Completed

Water Sources, Camp Locations, Navigable Waters

(Inuvik)

Consultation June 2013 Planned

Fish Habitat Assessments – DFO Authorization Consultation July 2013 Planned

Permitting

DFO Authorizations Submit July 2013 Working

DFO Compensation Plan Draft Options Plan September 2013 Working

Municipal Waste Transfer Agreements Agreement August 2013 In Discussion

ILA / AANDC Land Use Permit Applications Submit August 2013 Working

Quarry Permit / Licence Applications Application August 2013 Working

EISC Pre-Screening To Be Determined June 2013 In Discussion

Navigable Waters Application Application June 2013 Working

Update Final BridgeLocations

August 2013 Working

Environmental Management Plans

Emergency Response Plan Draft NA Completed

Final for Approval August 2013 Working

Spill Response Procedure NA NA Completed

Spill Contingency Plan Draft July 2013 Working

Final for Approval August 2013 -

Safe Work Procedure – Fueling Equipment NA NA Completed

Safe Work Procedure – Handling Petroleum NA NA Completed

Page 38: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 4: Description of Undertaking

June 2013

4-22

Table 4-8 Water Licence Application Pre-Construction Program Schedule and Status(cont’d)

Program Activity Proposed Timing Status

Environmental Management Plans (cont’d)

Waste Management Plan Draft July 2013 Working

Final for Approval August 2013 -

Pit Development Plans Draft July 2013 Working

Final for Approval August 2013 -

Sediment and Erosion Control Plan Draft NA Completed

Final for Approval July 2013 Working

Explosives Management Plan Draft July 2013 Working

Final for Approval August 2013 -

Fish and Fish Habitat Protection Plan Draft July 2013 Working

Final for Approval August 2013 -

Page 39: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 5: Type of Undertaking

June 2013

5-1

5 TYPE OF UNDERTAKING

The ITH construction project is considered an Industrial Undertaking as it comprises the construction of

an all-weather highway to provide access between the two communities of Inuvik and Tuktoyaktuk.

Page 40: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 5: Type of Undertaking

June 2013

5-2

Page 41: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 6: Studies Undertaken to Date

June 2013

6-1

6 STUDIES UNDERTAKEN TO DATE

Several studies have been undertaken to date in support of the environmental assessment and the water

licence. A copy of these studies is included in Appendix D.

Studies undertaken related to watercourse crossings and potential water sources include:

Inuvik to Tuktoyaktuk Highway 2013 Bathymetric Survey (Kiggiak-EBA 2013, Appendix D.1)

Lake Bathymetry Survey for the Inuvik to Tuktoyaktuk Highway (IMG-Golder 2012b, Appendix D.2)

Inuvik – Tuktoyaktuk Highway Hydrotechnical Assessment of Stream Crossings (KAVIK-STANTEC

2012e, Appendix D.3)

Other studies undertaken related to watercourse crossings include:

Fish Habitat Assessment at Select Watercourse Crossings along the Inuvik to Tuktoyaktuk Highway

(IMG-Golder 2012a, Appendix D.4)

Spring 2010 Aquatic Field Program Results for the Inuvik to Tuktoyaktuk Highway, Northwest

Territories (Kiggiak-EBA 2010, Appendix D.5)

Assessment of Fisheries Potential of the Tuktoyaktuk to Source 177 All-Weather Road Impact Area

(IMG-Golder 2009, Appendix D.6)

Page 42: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 6: Studies Undertaken to Date

June 2013

6-2

Page 43: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 7: Water Use

June 2013

7-1

7 WATER USE

The proposed water uses associated with the ITH project are:

To obtain water

To cross a watercourse

To modify the bed or bank of a watercourse (installation of culverts)

7.1 Obtaining Water

Water will be obtained for the purpose of daily camp operations and winter road construction. The use of

water will range from 32 m3/day, to 1,524 m

3/day during a short period of approximately 6 weeks. Water

use varies significantly throughout a construction year, depending on the construction period. Details are

provided in Section 8.

7.2 Crossing Watercourses

As discussed in Section 4.1.2, nine watercourses greater than 5 m wide at the ordinary high water mark

will be crossed.

7.3 Modifying the Bed or Bank of a Watercourse

The ITH project involves modifying the bed or bank of watercourses with continuous water flow and of

watercourses greater than 5 m wide at the ordinary high water mark (see Section 4.1.2).

Construction of all watercourse crossings, as described in the previous section, will require modification of

the bed or bank of the watercourse. The construction of bridges will require the excavation and

modification of “bed and banks” for the installation of pilings, the installation of foundations and

embankments and the placement of erosion control. All of these works will be undertaken during the

winter months when the bed and banks are in a frozen condition. The construction of culverts will also

require modification of “bed and banks”. The placement of large diameter culverts will occur after the

stream to be crossed has frozen to the bottom, and will involve the excavation of ice out of the streambed

to the installation elevation, sub-excavation (if required), placement of suitable granular material as the

foundation bedding and compaction, installation of the culvert and backfilling.

Page 44: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 7: Water Use

June 2013

7-2

Page 45: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 8: Quantity of Water Involved

June 2013

8-1

8 QUANTITY OF WATER INVOLVED

Water will be used for domestic camp use, winter and ice road construction and maintenance, and

summer embankment construction and surfacing. The annual project water use volumes per spread are

described in Tables 8-1 and 8-2.

Table 8-1 Annual Project Water Use – Southern Spread

Water UseNov 15 – Dec 31

(Total m3)

Jan 1 – May 15(Total m

3)

May 16 – Nov 14(Total m

3)

Total Water Useper Year (m

3)

Domestic camp use1

564 1,620 1,098 3,282

Winter road construction 37,600 12,150 - 52,930

Winter road maintenance - 1,350 -

Summer embankmentconstruction and surfacing

- - 1,830

Ice roads* Not Applicable

ANNUAL TOTAL 56,212

NOTE:1

Bottled drinking water will be supplied from the Town of Inuvik

Table 8-2 Annual Project Water Use – Northern Spread

Water UseNov 15 – Dec 31

(Total m3)

Jan 1 – May 15(Total m

3)

May 16 – Nov 14(Total m

3)

Total Water Useper Year (m

3)

Domestic camp use1

564 1,620 1,098 3,282

Winter road construction 32,900 12,150 - 48,230

Winter road maintenance - 1,350 -

Summer embankmentconstruction and surfacing

- - 1,830

Ice roads Not Applicable

ANNUAL TOTAL 51,512

NOTE:1

Bottled drinking water will be supplied from the Hamlet of Tuktoyaktuk

Page 46: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 8: Quantity of Water Involved

June 2013

8-2

The proposed water sources and proposed volume of water withdrawal for each year of construction will

be in accordance with the DFO’s (2010) Protocol for Water Withdrawal from Ice-covered Waterbodies in

the Northwest Territories and Nunavut. Proposed volumes to be withdrawn are identified in Tables 8-3

(Year 1), 8-4 (Year 2), and 8-5 (Year 3). GNWT-DOT is applying to use 10% of the available volume,

although actual water use will be significantly less. The locations of the water sources are shown in

Appendix B. Note that at the time of application, not all lake volumes are known. Lake volumes for lakes

to be used during first year construction (2013-14) are indicated in Table 8-3. Lakes for which volumes

will be reported through planned bathymetric studies in 2013, are indicated in Table 8-3 as “not available”.

Table 8-3 Proposed Water Sources (Year 1)

Water SourceName

AvailableVolume

(m3)

10% of AvailableWater Volume(Application

volume)(m

3)

ProposedVolume to be

Withdrawn(m

3) Bathymetric Data

SOUTHERN SPREAD

Lake at KP1 NA Will submit October 20131

Lake at KP4 NA Will submit October 20131

Lake at KP5 NA Will submit October 20131

Lake at KP6 NA Will submit October 20131

Lake at KP7 NA Will submit October 20131

Lake at KP11 NA Will submit October 20131

Inuvik 4 (KP14) 1,154,0002

115,400 26,000 Completed (Kiggiak-EBA 2013)

Inuvik 5 (KP15 Frozen toground –max. depth1.7 m

Completed (Kiggiak-EBA 2013)

Inuvik 6 (KP17) Frozen toground –max. depth2.0 m

NA Completed (Kiggiak-EBA 2013)

Lake 6 (KP18) 42,5002

4,250 Completed (Kiggiak-EBA 2013)

Inuvik 7 (KP23) 29,5002

2,950 Completed (Kiggiak-EBA 2013)

Lake at KP24 NA Will submit October 20131

Lake at KP25 NA Will submit October 20131

38 (Jimmy Lakes)(KP28)

NA Will submit October 20131

37 (KP29) NA Will submit October 20131

Lake at KP29A NA Will submit October 20131

Page 47: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 8: Quantity of Water Involved

June 2013

8-3

Table 8-3 Proposed Water Sources (Year 1) (cont’d)

Water SourceName

AvailableVolume

(m3)

10% of AvailableWater Volume(Application

volume)(m

3)

ProposedVolume to be

Withdrawn(m

3) Bathymetric Data

SOUTHERN SPREAD (cont’d)

Lake at KP29B NA Will submit October 20131

Lake at KP33 NA Will submit October 20131

35 (KP33) NA Will submit October 20131

Mackenzie River unlimited unlimited 25,300 Completed (Kiggiak-EBA 2013)

TOTAL 56,300

NORTHERN SPREAD

Tuk 4 (KP102) 169,0002

16,900 16,000 Completed (Kiggiak-EBA 2013)

Tuk 3/ Lake 105(KP105)

528,0002,3

52,800 16,600 Completed (Kiggiak-EBA 2013;IMG-Golder 2012)

KP110 NA Will submit October 20131

KP111 NA Will submit October 20131

Tuk 2/ Lake 106(KP113)

32,5002,3

3,250 3,000 Completed (Kiggiak-EBA 2013;IMG-Golder 2012)

Tuk 1 (KP 115) 46,0002

4,600 4,000 Completed (Kiggiak-EBA 2013)

Lake 119 (KP119) 721,7242

72,172 12,000 Completed (IMG-Golder 2012)

Lake 120 (KP120) 4,231,0942

423,109 Completed (IMG-Golder 2012)

TOTAL 51,600

NOTES:1

Additional bathymetric surveys of proposed lakes are planned for August 2013; results will be submitted tothe NWT Water Board August 2013

2Available under ice volume

3Values used are from Kiggiak-EBA 2013

NA – not available

Page 48: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 8: Quantity of Water Involved

June 2013

8-4

Table 8-4 Proposed Water Sources (Year 2)

Water SourceName

AvailableVolume

(m3)

10% of AvailableWater Volume(Application

volume)(m

3)

ProposedVolume to be

Withdrawn(m

3) Bathymetric Data

SOUTHERN SPREAD

Lake at KP1 NA Will submit October 20131

Lake at KP4 NA Will submit October 20131

Lake at KP5 NA Will submit October 20131

Lake at KP6 NA Will submit October 20131

Lake at KP7 NA Will submit October 20131

Lake at KP11 NA Will submit October 20131

Inuvik 4 (KP14) 1,154,0002

115,400 26,000 Completed (Kiggiak-EBA 2013)

Inuvik 5 (KP15 Frozen toground –max. depth1.7 m

Completed (Kiggiak-EBA 2013)

Inuvik 6 (KP17) Frozen toground –max. depth2.0 m

NA Completed (Kiggiak-EBA 2013)

Lake 6 (KP18) 42,5002

4,250 Completed (Kiggiak-EBA 2013)

Inuvik 7 (KP23) 29,5002

2,950 Completed (Kiggiak-EBA 2013)

Lake at KP24 NA Will submit October 20131

Lake at KP25 NA Will submit October 20131

38 (Jimmy Lakes)(KP28)

NA Will submit October 20131

37 (KP29) NA Will submit October 20131

Lake at KP29A NA Will submit October 20131

Lake at KP29B NA Will submit October 20131

Lake at KP33 NA Will submit October 20131

35 (KP33) NA Will submit October 20131

Mackenzie River unlimited unlimited 25,300 Completed (Kiggiak-EBA 2013)

TOTAL 56,300

Page 49: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 8: Quantity of Water Involved

June 2013

8-5

Table 8-4 Proposed Water Sources (Year 2) (cont’d)

Water SourceName

AvailableVolume

(m3)

10% of AvailableWater Volume(Application

volume)(m

3)

ProposedVolume to be

Withdrawn(m

3) Bathymetric Data

NORTHERN SPREAD

Lake at KP82A NA Will submit October 20131

Lake at KP82B NA Will submit October 20131

Lake at KP85 NA Will submit October 20131

Lake at KP86 NA Will submit October 20131

Lake at KP91 NA Will submit October 20131

Lake at KP100 NA Will submit October 20131

Lake at KP101 NA Will submit October 20131

TOTAL 51,600

NOTES:1

Additional bathymetric surveys of proposed lakes are planned for August 2013; results will be submitted tothe NWT Water Board August 2013

2Available under ice volume

NA – not available

Table 8-5 Proposed Water Sources (Year 3)

Water SourceName

AvailableVolume

(m3)

10% of AvailableWater Volume(Application

volume)(m

3)

ProposedVolume to be

Withdrawn(m

3) Bathymetric Data

Lake at KP40 NA Will submit October 20131

Lake at KP41 NA Will submit October 20131

Lake at KP42 NA Will submit October 20131

Lake at KP45 NA Will submit October 20131

Lake at KP47 NA Will submit October 20131

Lake at KP50A NA Will submit October 20131

Lake at KP50B NA Will submit October 20131

Lake at KP52 NA Will submit October 20131

Lake at KP54 NA Will submit October 20131

Lake at KP55 NA Will submit October 20131

Page 50: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 8: Quantity of Water Involved

June 2013

8-6

Table 8-5 Proposed Water Sources (Year 3) (cont’d)

Water SourceName

AvailableVolume

(m3)

10% of AvailableWater Volume(Application

volume)(m

3)

ProposedVolume to be

Withdrawn(m

3) Bathymetric Data

Lake at KP61 NA Will submit October 20131

Lake at KP70 NA Will submit October 20131

11BC (KP71) NA Will submit October 20131

Lake at KP77 NA Will submit October 20131

Lake at KP78 NA Will submit October 20131

TOTAL 107,900

NOTES:1

Additional bathymetric surveys of proposed lakes are planned for August 2013; results will be submitted tothe NWT Water Board August 2013

NA – not available

8.1 Winter Access Road Construction

Water will be used for the construction and maintenance of winter and ice roads.

During construction, there are four distinct water use periods per construction year (November 15 to

November 14). From approximately November 15 to December 31, the maximum quantity of water used

per day may be up to 1,500 m3

(1,500,000 litres) to construct winter roads; this would be 700 m3

per day

at the northern construction spread, and 800 m3

per day at the southern construction spread. After the

roads are constructed, the water withdrawal rates decline significantly, to approximately 200 m3

(200,000

litres) per day (total of both spreads), from January 1 to May 15 for continued winter road construction

and maintenance, then 20 m3

(20,000 litres) per day (total of both spreads) from May 16 to November 14

for compaction of the embankment material and the final granular surfacing.

Table 8-6 identifies the per day cubic metre water use in each construction spread within each annual

construction period and the annual domestic water use.

The total annual water quantity required for the ITH project is approximately 107,724 m3; approximately

48,230 m3at the northern construction spread, approximately 52,930 m

3at the southern construction

spread, and approximately 6,564 m3

for domestic camp use. Water use will peak for a period of

approximately six weeks during the annual construction period.

The water used for the construction of winter roads will not be returned to source, except where it exists

as an overwater ice road. Melt water is expected to slowly infiltrate into the active layer.

Page 51: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 8: Quantity of Water Involved

June 2013

8-7

Table 8-6 Daily and Annual Water Use Requirements per Construction Period

ConstructionPeriod

Number ofDays

Daily Water Use(m

3)

Total PerConstruction

Period(m

3)Southern Spread Northern Spread

Nov 15 –Dec 31 47 800 700 70,500

Jan 1 - May 15 135 100 100 27,000

May 16 - Sept 30 138 10 10 2,760

Oct 1 - Nov 14 45 10 10 900

Annual Construction Water Use 101,160

Annual Domestic Water Use 6,564

ANNUAL TOTAL 107,724

Water withdrawal will be in accordance with the DFO’s (2010) Protocol for Water Withdrawal from Ice-

covered Waterbodies in the Northwest Territories and Nunavut, whereby no more than 10% of available

water will be withdrawn from any waterbody (Tables 8-3, 8-4, 8-5).

The operating capacity of the submersible pump will be 45 litres per second (600 gallons per minute) and

the size of the intake screen will be 0.70 m2

and will conform to DFO’s (1995) Freshwater Intake End-of-

Pipe Fish Screen Guideline and (2011) Fish Screen Design Criteria for Flood and Water Truck Pumps.

The length of access trails and winter roads over land and over water are shown in Table 8-7 below.

Table 8-7 Length of Access Trails and Winter Roads Over Land and Water

ConstructionYear Construction Spread

Access Trail Winter Road

Total(km)

Over Land(km)

Over Water(km)

Over Land(km)

Over Water(km)

Year 1 South (Optional/Preferred) 9.4 1.7 35.3 3.6 50.0

South (Primary) 42.9 0.0 29.4 1.0 73.3

North 2.4 15.5 4.9 12.1 34.9

Year 2 South (Optional/Preferred) 11.2 0.0 32.7 13.0 56.9

South (Primary) 11.2 0.0 29.5 4.9 45.6

North 5.9 17.8 5.5 29.7 58.9

Year 3 South (Optional/Preferred) 0.0 0.0 0.3 0.0 0.3

South (Primary) 0.0 0.0 21.8 0.0 21.8

North 0.0 0.0 28.1 12.6 40.7

Total (Optional/ Preferred) 28.9 35.0 106.8 71.0 241.7

Total (Primary) 62.4 33.3 119.2 60.3 275.2

Page 52: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 8: Quantity of Water Involved

June 2013

8-8

8.2 Camp Water Use

Domestic water use will include cooking, bathing, toilet, and laundry related activities. Bathing, toilets and

laundry are the largest consumers of water; therefore, low or no-flow toilets and low water use showers

and laundry facilities will be used at the camps. A maximum of approximately 6 m3

(6,000 litres) per day

will be required during peak construction periods, for a 60 person camp. It is estimated that each person

will use up to 100 litres of water per day. This is approximately 24 m3

(24,000 litres) of water required per

day over the four camps operating in the northern and southern spreads during peak construction

periods.

Bottled drinking water for camp use will be supplied from the Hamlet of Tuktoyaktuk and the Town of

Inuvik.

8.3 Water Sources

Tables 8-3 to 8-5 lists the approximately 50 potential water sources identified over the length of the all-

weather highway to provide water for the winter and ice road construction. The locations of these water

sources are shown on the Construction Atlas (Appendix B). The bathymetric investigation of many of

these water sources has been completed (Appendix D), and the remainder of the bathymetric

investigations will be completed in 2013 (as identified in Table 4-8). The bathymetric investigations will

form the basis of the final selection of the water sources to be used in the road construction in compliance

with DFO’s (2010) Protocol for Water Withdrawal from Ice-covered Waterbodies in the Northwest

Territories.

Bathymetric surveys for the identification of the appropriate water source have been undertaken using

two different methodologies. Winter bathymetric surveys were completed over ice using Ground

Penetrating Radar (GPR) to measure the depth of the water along several cross sections of a given lake

(Kiggiak-EBA 2013). Summer bathymetric surveys were completed from a boat using sonar depth

recording and Global Position System (GPS) position recording (IMG-Golder 2012b).

DFO will require that fish be protected from entrainment or impingement where water is extracted from

fish-bearing waters, including any water withdrawals made using water trucks. DFO has a Freshwater

Intake End-of-Pipe Fish Screen Guideline and Fish Screen Design Criteria for Flood and Water Truck

Pumps to assist proponents in the design and installation of fish screens.

Page 53: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 9: Waste Deposited

June 2013

9-1

9 WASTE DEPOSITED

During the construction activities for the Inuvik to Tuktoyaktuk Highway various waste materials will be

generated, and various hazardous materials will be utilized. Methodologies have been developed for the

collection, transportation, treatment and disposal of the waste materials generated during the construction

activities with no anticipated deposition of the waste as part of project operations. In addition,

methodologies have been developed for the transportation, storage, containment, and utilization of the

various hazardous materials utilized during the construction activities with no anticipated deposition of

the hazardous materials as part of project operations.

Contingency plans for managing accidental discharges of waste materials or hazardous materials have

been developed to manage unanticipated events.

9.1 Waste Materials Generated

Five types of waste will be generated during construction operations, none of which will be discharged to

land or in or near any waterbodies. The waste types include:

camp greywater

camp sewage

camp solid waste

recyclables

hazardous waste

9.1.1 Greywater and Sewage

Management of greywater and sewage will include the storage of wastewater generated at the

construction camps (if required) and the periodic transport and disposal of sewage waste. Sewage from

no-flow (Pacto) or low flow toilets will be stored in sealed watertight containers and transported to

approved sewage lagoon facilities at either Tuktoyaktuk or Inuvik.

Greywater will be stored using approved holding tanks and will not receive any treatment while stored. All

camp greywater will be stored in 14,000 litre skid-mounted tanks. Full tanks will be transported to

approved wastewater facilities in Tuktoyaktuk or Inuvik.

The largest camps associated with the construction will have capacity for up to 60 people, depending on

the construction season. The wastewater generation associated with the maximum number of people (60

people) will be approximately 6 m3

(6,000 litres) per day per camp during the winter construction season

(November to May), or up to 24 m3

(24,000 litres) per day including all camps at both the northern and

southern spreads. Less wastewater will be generated during summer construction activities.

Page 54: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 9: Waste Deposited

June 2013

9-2

Each camp location will typically have a three day supply of water and wastewater storage available,

approximately 18-20 m3

(18,000-20,000 litre) each, with an additional 45 m3

(45,000 litre) insulated skid

mounted tank at each winter camp as additional storage in the event of a blizzard or other unforeseen

event.

The Town of Inuvik operates under a water licence with the Gwichin Land and Water Board, and the

Hamlet of Tuktoyaktuk operates under a water licence with the NWTWB. Waste transfer agreements will

be negotiated with municipalities prior to construction.

There are no alternative methods for sewage and greywater treatment/disposal proposed, as package

treatments plants with subsequent discharge to land may be ineffective and unreliable for this type of

sensitive environment and cold climate.

9.1.2 Solid Waste

The management of solid waste from the camps and construction activities may include incineration or

the storage of the solid waste and the periodic collection of the wastes in a covered container vehicle.

The vehicle will haul the waste to the waste disposal facilities at either Tuktoyaktuk or Inuvik for disposal

within each of these facilities.

The camps associated with the construction program will have 20 to 60 people in residence at any one

time. The solid waste generated during maximum occupancy (60 people) will be approximately 1 m3

per

day. There are four camps proposed, two in the northern spread, and two in the southern spread, for an

approximate total of 4 m3

of waste generated per day during peak construction periods.

The solid waste disposal facility at the Town of Inuvik operates under a water licence with the Gwichin

Land and Water Board, and the solid waste disposal facility at the Hamlet of Tuktoyaktuk operates under

a water licence with the NWTWB. The Applicant is currently negotiating an agreement with the

municipalities to receive this waste.

9.1.3 Recyclables and Hazardous Waste

The solid waste generated at the construction camps and equipment maintenance areas will include

minor amounts of hazardous wastes. Hazardous waste types will typically include fuel, lubricants, and

residuals from explosives.

Hazardous waste will be separated from solid waste and stored in ventilated enclosures, in closed-bottom

containers, in accordance with the Waste Management Plan. It will then be packaged, and hauled to

Inuvik for the appropriate treatment and ultimate disposal. The hazardous waste will be either treated and

disposed through a working arrangement with the Town of Inuvik, or transported for disposal via a

licensed carrier and an appropriate manifest to an approved disposal facility outside the NWT.

Recyclable waste will be disposed of through the recycling depot in Inuvik (if the facility is operational).

Page 55: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 9: Waste Deposited

June 2013

9-3

9.2 Surface Water Runoff

Sediment dislodged during project activities, such as borrow pit operation or watercourse crossing

construction, has the potential to enter adjacent watercourses or waterbodies.

The operation of the borrow pits for the supply of material for the road construction, as well as the

construction of watercourse crossings has the potential to generate seasonal surface runoff that may

contain sediment. Any runoff containing sediment will be managed in accordance with the project specific

Sediment and Erosion Control Plan (SECP, Appendix E.1).

9.3 Storage of Fuel

Two types of hazardous materials will be used during construction operations:

Fuel and Lubricants

Explosives

Storage and transport of explosives will be authorized under the NWT Explosives Act and any other

applicable legislation. The blasting contractor will be responsible for obtaining and operating in

accordance with applicable legislation.

9.3.1 Fuel and Lubricants

The management of the fuel and lubricants will include the winter and summer transportation of fuel and

lubricants to storage facilities at the borrow sites and strategic sites along the all-weather highway. The

fuel and lubricants will be transported along the winter roads, ice roads and constructed embankment by

fuel transport vehicles operated by qualified drivers. The fuel will be stored in approved storage tanks,

with appropriate secondary containment. The lubricants will be stored in sheltered facilities with

secondary containment. Lubricants that are waste material from oil changes and related activities will be

managed as hazardous wastes.

Fuel and lubricant transportation, storage, and application activities will be executed with the application

of the appropriate regulations, including approved procedures for packaging and handling during

transportation, approved containers (tanks and secondary containment for storage), and approved

application procedures.

Fuel storage areas will need to be constructed at each camp location or at equipment and materials

staging areas. Diesel and gasoline will be required to support construction operations. Exact fuel amounts

and types are not yet known, but it is estimated that each fuel storage locations may require capacity to

store up to 150 m3

(150,000 litres) of diesel and 5 m3

(5,000 litres) of gasoline.

Plans for the handling petroleum products, fuelling equipment, and responding to spills have been

developed or are currently being developed (Appendix E).

Page 56: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 9: Waste Deposited

June 2013

9-4

9.3.2 Explosives

The operation of the borrow pits will require the use of explosives as part of the extraction process. ANFO

(or AN/FO, for ammonium nitrate/fuel oil) explosives will be used during borrow pit operations. Explosives

will be managed in accordance with the Guidelines for the Use of Explosives In or Near Canadian

Fisheries Waters (DFO 1998). The storage and transport of ANFO will be permitted pursuant to

applicable legislation.

Blasting will be done at times when the ground is frozen, but in the event that water is encountered,

plastic blast hole liners will be used.

Page 57: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

10

The Haml

discussion

OTHER PUNDERT

let of Tuktoya

n with these l

Water Lice

PERSONTAKING

aktuk and Tow

icencees rega

nce Applicat

Section 10

S OR PR

wn of Inuvik h

arding the rec

tion for ConsSubmission: Other Perso

ROPERTIE

ave licenced

ceipt of solid w

struction of In to the Northons or Propert

ES AFFEC

waste manag

waste and wa

Inuvik - Tukthwest Territoies Affected b

CTED BY

gement facilit

astewater.

toyaktuk Higories Water Bby This Undert

June

Y THIS

ties. The DOT

ghwayBoardtaking e 2013

10-1

T is in

Page 58: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 10: Other Persons or Properties Affected by This Undertaking

June 2013

10-2

Page 59: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 11: Community Consultation

June 2013

11-1

11 COMMUNITY CONSULTATION

11.1 Summary of Public Involvement

The ITH project recently completed an environmental review by a substituted panel review process

pursuant to the Inuvialuit Final Agreement and the Canadian Environmental Assessment Act. This

process was open to the public, and several interested parties engaged in the process during the

information request, technical hearings, and public hearing stages of the process.

Consultation was held with co-management agencies (e.g., Wildlife Management Advisory Council,

Fisheries Joint Management Committee, Inuvialuit Games Council, Tuktoyaktuk-Inuvik Work Group),

municipal councils, community corporations, hunter and trapper committees, and/or with the public on

several aspects of the ITH project, including traditional knowledge and traditional land use (February

2012), wildlife and fish protection (September, October and November 2012), and watercourse crossings

(September 2012).

Consultation regarding geotechnical investigations of the borrow sources listed in Table 4-4, was

undertaken as part of the Environmental Impact Screening Committee’s review of Inuvik – Tuktoyaktuk

2013-2014 Geotechnical Investigations Program (EISC File No. 12/12-01). During this consultation, the

GNWT-DOT made it clear that the objective for investigating these borrow sources were for further

consideration for use during construction of the ITH project.

Water licence-related consultation was also conducted with the Tuktoyaktuk Hunter and Trapper

Committee in June 2013 to discuss camp site and water withdrawal locations. A copy of this presentation

is provided in Appendix F. Additional consultation with the Inuvik Hunter and Trapper Committee is

scheduled for June 17, 2013. Consultation records for these meetings will be provided by June 20, 2013.

Project plans will be adjusted as required to respond to concerns raised about locations of camps, use of

specific water sources or other aspects of construction.

11.2 Summary of Issues and Concerns

On January 25, 2013 the Environmental Impact Review Board (EIRB) released its Final Report for the

Environmental Impact Review of the ITH project (EIRB 2013) – the “Report of EIR”. The Report of EIR

made 51 recommendations it deemed necessary to mitigate the adverse environmental and socio-

economic effects of the project (Appendix G).

On April 5, 2013 the Government of Canada responded to the EIRB’s report, as required by the Canadian

Environmental Assessment Act. The Government of Canada “accepted”, “accepted the intent” of, or

“rejected” each of the 51 recommendations (Government of Canada 2013, Appendix H).

Page 60: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 11: Community Consultation

June 2013

11-2

During the EIRB’s review of the ITH project, the Applicant made a number of commitments related to

environmental management and protection, benefits and collaboration, project construction and

operation, project design and ongoing monitoring. A complete list of Applicant commitments is provided in

Appendix I.

Page 61: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 12: Environmental Overview

June 2013

12-1

12 ENVIRONMENTAL OVERVIEW

12.1 Terrain, Soils and Permafrost

The ITH project area spans two distinct Ecoregions: the Mackenzie Delta and the Tuktoyaktuk Coastal

Plain (Ecosystem Classification Group 2007). The Mackenzie Delta Ecoregion is part of the Taiga Plain

Ecozone and consists of the southern two-thirds portion of the Mackenzie River Delta. Typical terrain

along the Delta consists of low-lying fluvial and marine deltaic deposits characterized by a complex

network of small lakes and interconnected fluvial channels. North and east of the Mackenzie Delta is the

Tuktoyaktuk Coastal Plain. Part of the Southern Arctic Ecozone, the Tuktoyaktuk Coastal Plain includes

active portion of the Mackenzie River delta as well as uplands areas characterized by older glacial and

marine deltaic sediments.

More specifically, the terrain along the ITH project area consist of rolling to gently undulating landscape

characterized by glacial and post glacial deposits. Undulating till, hummocky outwash deposits and

extensive lacustrine plains modified by thermokarst and other periglacial processes are the most common

types of deposit. Alluvial and colluvial deposits are found overlying glacial deposits in several areas.

These materials are deposited by streams and gravity related processes and are found along

watercourses and moderate to steep slopes. Very poorly-drained peat-covered areas are extensive in

topographic lows and at proximity to small water bodies. Detailed terrain and surficial material

characterization and mapping in the project area was undertaken by KAVIK-STANTEC in 2012 (KAVIK-

STANTEC 2012b, 2012c, 2012d).The region is underlain by continuous permafrost with sediments often

containing excess ice in the form of ice veins, lenses, wedges, and massive ice (Rampton 1988).

Permafrost related landforms are present throughout the area as represented by extensive polygonal

networks and unique landforms such as pingos. The depth of the active layer (i.e. the portion of soil that

thaws seasonally) varies greatly in relation with the type of material and local site conditions (i.e.,

drainage, water content, micro-topography, etc.). Work from Tarnocai et al. (2004) in the Inuvik –

Tuktoyaktuk area indicates that active layer range anywhere from 30 cm to over 150 cm.

Organic and Turbic Cryosols developed on level to rolling organic, morainal, alluvial, glaciofluvial, and

marine deposits are the dominant soils of the Ecoregion. Areas where permafrost is found within one

metre of the surface, Brunisolic, Regosolic or Gleysolic Static Cryosols have developed. Wetlands are

typically composed of moderately decomposed fen peat, and polygonal peat bogs.

Page 62: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 12: Environmental Overview

June 2013

12-2

12.2 Hydrology and Water Quality

The study area includes three separate drainage areas (Figure 12-1) within two watersheds (Figure 12-2).

Most of the study area drains into Husky Lakes (Figure 12-1). Less than 10% of the study area drains into

the Mackenzie River primarily in the vicinity of Inuvik. The most northerly portion of the study area drains

into Kugmallit Bay and Tuktoyaktuk Harbour. Surface hydrology in the study area is influenced by long

cold winters, short cool summers and relatively low precipitation (IOL et al. 2004). Low terrain also

influences the hydrology causing the formation of diffuse drainage patterns. There are many shallow

lakes and ponds throughout the study area, as well as deeper larger lakes such as Husky Lakes,

Parsons, Noell and Jimmy lakes. Lakes are generally connected to other lakes or large drainage systems

by small creeks.

Permafrost in the study area restricts the amount of subsurface drainage. As a result, most spring runoff

drains to nearby wetland and lake complexes. However, in areas of predominantly peat and inter-

hummock channels, subsurface runoff into streams can also be important (Quinton and Marsh 1999).

Most of the smaller shallow lakes, ponds, and streams freeze to, or near to the bottom during the winter

period. Larger streams such as Zed Creek and Hans Creek may not freeze to the bottom and maintain

running water throughout the year (IMG-Golder 2012a).

Salts originating from the Beaufort Sea and transported by the air result in chlorine and sodium ions being

the dominant ions found in lakes on the Tuktoyaktuk Peninsula. Lakes have low levels of inorganic

nitrogen and inorganic phosphorus. Generally, there is a decline of nutrients in lakes located north of the

treeline compared to those in the tree line transition zone, except where local thaw-related failures have

directly impacted tundra lakes (Kokelj et al. 2009). Organically bound nutrients are closely associated with

vegetational and climatic zones (Pienitz et al. 1997). Total metal concentrations in the Lower Mackenzie

sub-basin, in which the study area is within, are typically lower than guideline levels for aquatic health and

drinking water but seasonally high levels can occur with increased discharge and suspended sediment

loads as occurs during spring run-off (Kiggiak-EBA 2011).

Page 63: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

NUNWTYT

INUVIK TO TUKTOYAKTUK HIGHWAY OVERVIEW

ITH Project Drainage BasinsFIGURE NO.12-1

ProjectLocation

Base Data: Government of Canada; Drainage Basins: Rescan & Stantec Ltd.

Last

Modif

ied: J

une 1

1, 20

13 B

y: jpe

tho

Inuvik

Tuktoyaktuk

SitidgiLake

NoelLake

HuskyLakes

ParsonsLake

HuskyLakes

Old ManLake

Macken

zie Ri

ver

Holmes Creek

Middle Channel

East Channel

Husky LakesDrainage Basin

Kugmallit BayDrainage Basin

Mackenzie Delta

DrainageBasin

314/325

GSC3GSC4

309

PW13

I401A

170

174

PW17

177

173/305

PW19A

PW18

312 West

PW11 (2.46)

PW10 (2.46)

27A

8

43

31

18

35a

30a

23a

PREPARED FOR

123510689-174

0 5 10 15

KilometresMetres - 1:375,000

Drainage Basin

Major Bridge Crossing

Potential Borrow Source

Highway Alignment

Tuktoyaktuk to Source 177 Access Road

Navy Road

Provincial Park/Reserve

PREPARED BY

Page 64: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk
Page 65: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

NUNWTYT

INUVIK TO TUKTOYAKTUK HIGHWAY OVERVIEW

ITH Project WatershedsFIGURE NO.12-2

ProjectLocation

Base Data: Government of Canada; Watersheds: Government of Canada.

Last

Modif

ied: J

une 7

, 201

3 By:

jpetho

Inuvik

Tuktoyaktuk

SitidgiLake

NoelLake

HuskyLakes

ParsonsLake

HuskyLakes

Old ManLake

Macken

zie Ri

ver

Holmes Creek

Middle Channel

East Channel

Eastern Mackenzie Delta

Southern Beaufort Sea - Eskimo Lakes

Lower Peel andWestern Mackenzie Delta

Mackenzie River Delta (Main Channel)

43

A3

31

2118

15

A12

35a

30a

23a

17a

PREPARED FOR

123510689-148

0 5 10 15

KilometresMetres - 1:375,000

Single Span Bridge

Major Stream Crossing

Watersheds

Potential Borrow Source

Highway Alignment

Tuktoyaktuk to Source 177 Access Road

Navy Road

Provincial Park/Reserve

PREPARED BY

Page 66: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk
Page 67: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 12: Environmental Overview

June 2013

12-7

12.3 Fish and Fish Habitat

The fish fauna for the study area is represented by eight freshwater families of which the Salmonidae

family, including whitefish, is the most diverse and abundant. Families and species common to the area

are listed in Table 12-1. Some marine or estuarine species will move up streams short distances and can

be found at the mouths of creeks especially those draining into Kugmallit Bay or Husky Lakes during the

open water season. These species include fourhorn sculpin, rainbow smelt, starry flounder and arctic

flounder (Rescan 1999).

Table 12-1 List of Common Freshwater Fish found in the Project Area (modified fromRescan 1999)

Family Species Common Name

Esocidae Esox Lucius Northern pike

Osmeridae Hypomesus olidus Pond smelt

Salmonidae Coregonus autumnalis Arctic cisco (herring)

C. sardinella Least cisco (big-eye herring)

C. clupeaformis Lake whitefish (humpack)

C. nasus Broad whitefish (whitefish)

Prosopium cylindraceum Round whitefish

Salvelinus namaycush Lake trout

Stenodus leucichthys Inconnu (coney)

Thymallus arcticus Arctic grayling

Cyprinidae unidentified Unidentified minnows

Catostomidae Catostomus catostomus Longnose sucker

Gadidae Lota lota Burbot (loche)

Gasterosteidae Pungitius pungitius Ninespine stickleback

Cottidae Cottus cognatus Slimy sculpin

Important lakes for fisheries in the ITH project area include Noell Lake, Jimmy Lake, Parsons Lake and

Husky Lakes. Noell Lake supports Arctic grayling and lake trout populations (Rescan 1999), as well as

lake and broad whitefish (ICC et al. 2006). Jimmy Lake receives the outflow of Noell Lake and drains into

Husky Lakes via Stanley Creek. Jimmy Lake supports at least seven species of fish including Arctic

grayling, lake trout and northern pike. Broad whitefish are also present in Jimmy Lake and it has been

speculated that these whitefish utilize the lake as a nursery and have migrated to Jimmy Lake via the

creek system from Husky Lakes (Rescan 1999).

Page 68: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 12: Environmental Overview

June 2013

12-8

Parsons Lake supports at least 10 species of fish (Rescan 1999). Harvested species include Arctic

grayling, northern pike, lake trout, broad and lake whitefish and Arctic cisco. Zed Creek connects Parsons

Lake with Husky Lakes and allows fish passage between both lake systems. Husky Lakes consists of a

series of five interconnected basins which eventually drain into Liverpool Bay. During fish surveys in 2002

(Harwood 2003), 12 species of fish were captured including both freshwater and marine species (species

tolerant of brackish water). Fish species include lake trout, broad and lake whitefish, Arctic and least

ciscoes, inconnu, Arctic grayling, northern pike, starry and Arctic flounders, Pacific herring, saffron cod.

Fourhorn sculpin are also present in Husky Lakes.

Creeks such as Hans Creek, Zed Creek and Jimmy Creek provide habitat and migratory corridors for a

variety of species including lake whitefish, round whitefish, lake trout, Arctic grayling, ninespine

stickleback and slimy sculpin (Rescan 1999). Northern pike and burbot may also occur in these creeks

(IOL et al. 2004). There is suitable spawning habitat for Arctic grayling in both Hans and Zed Creek (IMG-

Golder 2011).

Most creeks in the study area will freeze to or near the bottom preventing the use of these systems by

fish during the winter period however community harvesters have reported that now some creeks no

longer freeze to the bottom, such as a creek into Noell Lake and some creeks in the Parsons Lake area

(ICC et al. 2006). There is sufficient water depth and flow in Hans Creek and Zed Creek to suggest the

potential for these creeks to provide overwintering fish habitat (IMG-Golder 2011).

For creeks and lakes (e.g., Keneksek and Canyanek systems) which drain into Kugmallit Bay the

shallower lakes may be used by different fish species for rearing and feeding. Deeper lakes may also be

used for overwintering. The streams connecting these lakes are mainly used for migrating between the

lakes and the ocean. Large upstream and downstream runs of broad and lake whitefish, and least cisco

can occur in these streams as fish either try to move up to the lakes to feed, rear, overwinter or move

down to return back to the ocean or Mackenzie River system (Chang-Kue and Jessop 1992; Bond and

Erickson 1987).

Page 69: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 13: Predicted Environmental Impacts of Undertaking and Proposed Mitigation

June 2013

13-1

13 PREDICTED ENVIRONMENTAL IMPACTS OF UNDERTAKINGAND PROPOSED MITIGATION

13.1 Overview

This section describes the potential effects of ITH project activities on Valued Components (VCs),

identifies mitigation measures to reduce, control or eliminate the effects, and presents the implications of

residual effects.

The ITH project, as an Industrial Undertaking defined in the Northwest Territories Waters Regulations, will

require a water license for the following activities:

Construction of a structure across a watercourse 5 or more metres wide at ordinary high water mark at

point of construction

Watercourse training (culverts)

Use of 300 or more cubic metres per day of water

In addition, there may be an indirect deposit of waste to surface water in conjunction with quarrying above

ordinary high water mark.

Project activities related to water licence requirements include:

Watercourse crossings

Water withdrawal for winter road construction and camp use

Waste management

Storage and handling of petroleum products

Potential environmental effects associated with these activities were identified through community

consultation, a review of the previous environmental assessment and screenings conducted for the ITH

project, and a review of scientific literature, maps, the Inuvialuit CCPs (ICCP 2008, TCCP 2008) and the

Inuvialuit Harvest Study (Joint Secretariat 2003).

The scope of development related to this water licence application that was included in the Panel’s review

(EIRB 2013) is as follows:

Temporary construction camp facilities located at the borrow source closer to the construction activities

Temporary winter access road that is parallel to the permanent alignment during construction

Temporary winter access roads to the borrow sources during construction

Watercourse crossing structures

Page 70: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 13: Predicted Environmental Impacts of Undertaking and Proposed Mitigation

June 2013

13-2

The ITH project has undergone an environmental review by a substituted panel review process pursuant

to the Inuvialuit Final Agreement and the Canadian Environmental Assessment Act.

The proposed activities are consistent with those reviewed by the EIRB. All borrow sources will be

operated consistent with the Developer’s Commitments (Appendix I) and in response to the EIRB’s

relevant recommendations (Appendix G). Winter roads will be constructed in the same direction as, and

within 1 km of, (parallel to) the alignment to be constructed. Camp facilities will be located at borrow

sources.

13.2 Spatial and Temporal Scope

The spatial scope of the ITH project is evaluated at the following three scales: Project Footprint, Project

Area and Regional Area. The Project Footprint includes the highway embankment, winter and ice roads,

borrow sources, water sources, and camp areas. The Project Area includes a 1 km buffer extending from

Project Footprint boundaries. The Regional Area includes a 15 km buffer extending from Project Footprint

boundaries, and the seasonal range of each VC has been included in the assessment.

The temporal scope of the ITH project is limited to December 2013 (Year 1) to September 2017 (Year 4),

as discussed in Section 4.3: Proposed Time Schedule.

13.3 Valued Components

A Valued Component (VC) is defined as an environmental, social, economic or cultural component that is

considered important by the proponent, local communities, technical specialists and/or government. The

assessment of ITH project effects on VCs provides an indication of ITH project effects on broader

environmental and social conditions. Similarly, mitigation measures for ITH project effects on VCs provide

protection for the broader environmental and social systems they represent.

Candidate VCs in relation to the ITH project were selected based on:

Sensitivity to project effects

Importance to local communities and resource users

Territorial, national or international importance (including status under the SARA)

Value as an indicator of effects on related resources and broader systems

Candidate VCs were identified for the ITH project based on the environmental overview and community

consultation. Candidate VCs were screened to select final VCs based on their potential to be affected by

ITH project activities. In this study, candidate VCs were excluded if they did not overlap temporally or

spatially with the ITH project, or if there is no, or negligible, potential for the ITH project to affect them.

Selected VCs and the rationale for selection are provided in Table 13-1. The selected VCs are the subject

of further assessment and mitigation planning in Section 13.5.

Page 71: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 13: Predicted Environmental Impacts of Undertaking and Proposed Mitigation

June 2013

13-3

Table 13-1 Candidate and Selected Valued Components in the Project Area andRationale for Selection

Candidate VC Selection Rationale

Terrain, Soil and Permafrost Potential for ground disturbance during construction activities

Soil will be disturbed during borrow source activities

Water Quantity (Hydrology) Drainage patterns may be affected by the use of snow fills at creek crossings

Water withdrawal may affect lake water levels

Water Quality Water quality may be affected by accidental degradation of lake and creek banksand improper fill materials at lake and creek crossing locations

Water quality may be affected in the case of an accidental spill or discharge

Fish and Fish Habitat Fish and fish habitat may be affected through water withdrawal reducing or alteringviable fish habitat

Fish may be entrained or impinged by the water intake

Fish migration may be delayed or blocked due to snowfills used in watercourses

Improper fill materials at creek and lake crossings or cutting of banks may lead tosedimentation of watercourses or waterbodies potentially affecting fish habitat andfish health

Accidental fuel spills could have health effects or cause tainting of fish

Muskrat and Beaver Potential for push ups and dens to be disturbed by winter road construction andoperation

Waterbirds and Waterfowl Potential for changes to water quality from project activities

Harvesting and TraditionalLand Use

The winter and ice roads will provide access to subsistence fishing and harvestingareas

Lakes are an important subsistence fish harvest source

Larger watercourses may be used for transportation

13.4 Project Interactions with the Environment

A summary of potential ITH project interactions with environmental components is presented in

Table 13-2.

Page 72: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 13: Predicted Environmental Impacts of Undertaking and Proposed Mitigation

June 2013

13-4

Table 13-2 Project Activity Interaction Matrix

Te

rrain

,S

oil

an

dP

erm

afro

st

Wa

ter

Qu

an

tity(H

yd

rolo

gy

)

Wa

ter

Qu

ality

Fis

ha

nd

Fis

hH

ab

itat

Mu

sk

rat

an

dB

ea

ve

r

Wa

terb

irds

an

dW

ate

rfow

l

Ha

rve

stin

ga

nd

Tra

ditio

nal

La

nd

Us

e

Clearing of Right-of-Way and Access Roads √ √ √ √ √

Ice Road Construction and Use √ √ √ √ √

Overland Winter Road Construction and Use √ √ √ √ √ √ √

Winter Access Trail Construction and Use √ √ √ √ √ √

Winter Highway Embankment Construction √ √ √ √ √

Summer Highway Embankment Construction √ √ √ √

Watercourse Crossing Construction √ √ √ √ √

Camp & Equipment Mobilization andDemobilization

√ √

Camp Operation √ √ √ √ √ √

Camp Waste Management √ √

Borrow Source Development and Operation √ √ √ √ √

Equipment Maintenance and Storage √ √ √ √

Fuel Transfer and Storage √ √ √ √

Equipment Refueling √ √ √ √

13.5 Impact Assessment and Mitigation

The Applicant has developed many mitigation measures and commitments during the environmental

review process. This has resulted in the Substituted Panel determining that “it will cause impacts on the

environment”, but that “the potential adverse effects of the ITH project can be mitigated and properly

managed if the Panel’s recommendations and the Developer’s commitments are implemented” (EIRB

2013, p. iii). The Government of Canada (2013, p. 5) stated that “taking into consideration the Panel

Report and the implementation of mitigation measures that are considered appropriate, the Government

of Canada has determined that the ITH project is not likely to cause significant adverse environmental

effects.” The Applicant/Developer Commitments are included in Appendix I.

Potential environmental effects and corresponding mitigation measures are identified in Table 13-3. The

mitigation measures will be implemented for the duration of ITH project construction activities.

Page 73: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Table 13

Potentia

Terrain, S

Disturbancof permafrof-way and

Potential dterrain andconstructioroads, acccamps

Disturbancresult of nconstructio

Potential dcamp anddemobiliza

Disturbancof permafrdevelopme

3-3 Poten

al Environmen

Soil and Perma

ce of soil and drost from clearid access trails

disturbance of d permafrost duon and operatiocess trails and

ce of sensitive ew embankmeon

disturbance to equipment moation

ce of soil and drost during borrent and operat

Water Lice

Section 13: P

ntial Environ

tal Effects

afrost

degradation ing of right-

sensitive uring on of winter temporary

terrain as a ent

soil from obilization /

degradation row source tion

nce Applicat

Predicted Envi

nmental Eff

Clearing w

Clearing w

Equipment

Constructioroads, acce

Winter roadcrossings a

A minimumon the wintperiods)

Access trai

Constructioconditions

Engineeredterrain (e.g

Constructioroads, acce

Constructioroads, acce

A minimumon winter ro

Access trai

Mobilizatioconducted

Pit developDevelopme

Pit DevelopGranular R

Pit developGuidelines

Pit operatio

Borrow pitsreclaimed iPlan

Overburdereclamation

tion for ConsSubmissionronmental Im

fects and M

ill only be cond

ill be done by h

t used for clear

on vehicles will ess trails or con

ds and access as much as pra

m depth of 20 cmter road and at

ils will be const

on of new emba

d mitigation willg., polygonal ter

on vehicles will ess trails or con

on vehicles will ess trails or con

m depth of 20 cmoads and acce

ils will be const

n of camps andalong construc

pment and operent Plan

pment Plans wResources Man

pment will followVolume 7: Pits

on will primarily

s will be closedin a progressive

n, including orgn

struction of In to the North

pacts of Unde

Mitigations

Mitigation

ducted during fr

hand, where pr

ing will be equi

only be operatnstructed emba

trails will be roactical

m of packed sncamp locations

tructed to trans

ankment will oc

l be applied onrrain, ice-rich g

only be operatnstructed emba

only be operatnstructed emba

m of packed sness trails during

tructed to trans

d equipment ducted embankme

ration will be co

ill conform to thagement Plan

w guidance in Is and Quarries

y be during wint

d as soon as thee manner, as d

ganic material w

Inuvik - Tukthwest Territoertaking and P

n

rozen ground c

ractical

ipped with mus

ted on designaankment

outed so as to m

now or ice coves (during winte

sport heavy equ

ccur primarily d

slopes and areground)

ted on designaankment

ted on designaankment

now or ice coveg winter operatio

sport heavy equ

uring summer went

onducted accor

he Inuvialuit Se(ILA and INAC

NAC’s (2010) N

ter

ey are no longedescribed in the

will be stockpile

toyaktuk Higories Water BProposed Mitig

June

conditions

shroom shoes

ated winter road

minimize overla

er will be maintaer construction

uipment as req

during winter (fr

eas of sensitive

ated winter road

ated winter road

er will be maintaons

uipment as req

will only be

rding to the Pit

ettlement RegioC nd)

Northern Land

er required ande Pit Developm

ed for use durin

ghwayBoardgation e 2013

13-5

ds, ice

and

ained

uired

rozen)

e

ds, ice

ds, ice

ained

uired

on

Use

d ment

ng

Page 74: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water LicSubmissSection 13June 2013

13-6

Table 13

Potentia

Terrain, S

Potential lyear winte

Degradatiosummer sequipmen

Degradatiosummer oequipmen

EIRB R36Water Boasame roadto access year in ordand terrainrepeated u

EIRB R37develop a respect tothat includsurface pewinter roaaggregatereports shappropriatAANDC, oless that eparticular impacts ofterrain chamonitoringshall be incumulativemanagemestablishe

cence Applicion to the No3: Predicted E

3-3 Poten

al Environmen

Soil and Perma

ong term effecer roads on soil

on of permafrotorage of campt

on of permafrooperation of camt

6: AANDC and tard shall ensurd alignments araggregate sou

der to avoid then damage caususe.

7: The Developemonitoring pro vegetation and

des active layerermafrost impad construction

e sources. Monould be filed wte regulators, inon a regular baevery two yearsemphasis on cf the roads on taracteristics. Tg program and ntegrated into the effects and aent programs t

ed by the IEMO

cation for Coorthwest Ternvironmental

ntial Environ

tal Effects

afrost (cont’d)

cts of multi-l

ost due to ps and

ost from mps and

the NWT e that the re not used

urces every e vegetation sed by

er shall ogram with d terrain r and near-cts from to the itoring

with the ncluding sis and not s, with cumulative these his its results

he daptive to be

OC.

onstruction oritories WateImpacts of Un

nmental Eff

)

Winter roadwhere poss

Additional bmulti-year o

Camps andadequate t

Camps andconstructed

Winter roadwhere poss

Additional bmulti-year o

Monitoring

of Inuvik - Tuer Board ndertaking an

fects and M

ds will be desigsible

borrow sourcesoperations

d equipment wihickness to pro

d equipment opd embankment

ds will be desigsible

borrow sourcesoperations

programs will b

ktoyaktuk H

nd Proposed M

Mitigations (

Mitigation

gned to minimiz

s have been pr

ill be stored at otect permafros

perated during t only

gned to minimiz

s have been pr

be developed i

ighway

Mitigation

cont’d)

n

ze length of ove

roposed to mini

borrow sourcesst

summer will op

ze length of ove

roposed to mini

in discussion w

erland portions

imize the need

s, on a pad of

perate on

erland portions

imize the need

with regulators

s,

for

s,

for

Page 75: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 13: Predicted Environmental Impacts of Undertaking and Proposed Mitigation

June 2013

13-7

Table 13-3 Potential Environmental Effects and Mitigations (cont’d)

Potential Environmental Effects Mitigation

Water Quantity (Hydrology)

Changes to water volume or flowdue to water withdrawal duringconstruction and operation of winterroads, access trails, watercoursecrossings, and temporary camps

Water withdrawal will not exceed 10% of the available volume of anywaterbody, as per the DFO (2010) Protocol for Winter Water Withdrawalfrom Ice-covered Waterbodies in the Northwest Territories and Nunavut

Changes to water volume or flowdue to watercourse crossingconstruction

Construction of watercourse crossings will be conducted primarily in winter

Temporary watercourse crossings will be constructed in winter only, as icebridges or snow fills, in accordance with the DFO (2007b) OperationalStatement for Ice Bridges and Snow Fills

Snow fills will be removed or v-notched at Program closure as per DFO’s(2007b) Operational Statement for Ice Bridges and Snow Fills

EIRB R34: The 10 per cent waterwithdrawal limit contained in theDFO Protocol for Winter WaterWithdrawal from Ice-coveredWaterbodies in the NorthwestTerritories and Nunavut (2010) shallbe applied to every lake and waterbody used as a water source overthe lifetime of the Project.

Water withdrawal will not exceed 10% of the available volume of anywaterbody, as per the DFO (2010) Protocol for Winter Water Withdrawalfrom Ice-covered Waterbodies in the Northwest Territories and Nunavut

EIRB R35: Monitoring of the effectsof long term water use for theconstruction of these roads shall beincluded in the regulatory approvalsgranted by DFO, AANDC and theNWT Water Board, as appropriate,and the results of this monitoringshall be integrated into thecumulative effects and adaptivemanagement programs to beestablished by the IEMOC.

DOT will develop a monitoring program for monitoring the long term effectsof water use in discussion with the appropriate regulators

Water Quality

Sedimentation due to erosion andrunoff from clearing activities,borrow source operation, andconstruction of watercoursecrossings, winter roads, ice roads,access trails, and new embankment

All project activities will follow measures to prevent or minimizesedimentation and erosion as described in the Sedimentation and ErosionControl Plan (Appendix E.1)

Page 76: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 13: Predicted Environmental Impacts of Undertaking and Proposed Mitigation

June 2013

13-8

Table 13-3 Potential Environmental Effects and Mitigations (cont’d)

Potential Environmental Effects Mitigation

Water Quality (cont’d)

Contamination of waterbody fromaccidental release of greywater,sewage or solid waste

All camp waste will be handled, stored and disposed of in accordance withthe Waste Management Plan (AppendixE.2)

Tanks used for transporting greywater will:

be watertight and designed to reduce surge during transport

be regularly and properly maintained by the operator to ensuredependable performance

All sewage will be contained and sealed in watertight containers

All solid waste will be stored in sealed, bear-proof containers

No wastewater will be discharged to land

Contamination of waterbody fromaccidental release of deleteriousmaterials from borrow sourcedevelopment and operation

All project activities will follow measures to prevent or minimizesedimentation and erosion as described in the Sediment and ErosionControl Plan (Appendix E.1)

All project activities will follow measures to prevent accidental release ofdeleterious materials as described in the Explosives Management Plan(Appendix E.3)

Borrow pit development will be conducted in accordance with the PitDevelopment Plan (Appendix E.4)

Contamination of waterbody fromaccidental release of fuel orhazardous materials duringequipment maintenance or storage,or fuel transport, transfer or storage

The Spill Response Procedure and Spill Contingency Plan (AppendicesE.5 and E.6) will be implemented if a spill occurs

All refueling and fuel transfer will be conducted in accordance with the SafeWork Practices for Fueling Equipment and Handling Petroleum

All hazardous waste will be handled, stored and disposed of in accordancewith the Waste Management Plan (Appendix E.2)

Refueling and servicing of machinery and storage of fuel and othermaterials for the machinery will occur a minimum of 100 m away from anywaterbody

Drip pans and drip trays will be placed under all equipment while not in use

All equipment will be inspected regularly to ensure it is free of leaks

All fuel storage containers will have integrated 110% secondarycontainment

Potential water quality effects wereidentified by the EIRB in relation tofish and fish habitat. As such, thoserecommendations are provided inthe Fish and Fish Habitat section ofthis table.

Page 77: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 13: Predicted Environmental Impacts of Undertaking and Proposed Mitigation

June 2013

13-9

Table 13-3 Potential Environmental Effects and Mitigations (cont’d)

Potential Environmental Effects Mitigation

Fish and Fish Habitat

Potential alteration of fish habitatassociated with clearing activities,borrow source operation, andconstruction of watercoursecrossings, winter roads, accesstrails, and new embankment

All project activities will follow measures to prevent or minimizesedimentation and erosion as described in the Sediment and ErosionControl Plan (Appendix E.1)

Alteration of fish habitat will be authorized by DFO

Potential alteration of fish habitatfrom water withdrawal

Water withdrawal will follow DFO’s (2010) Protocol for Winter WaterWithdrawal from Ice-covered Waterbodies in the Northwest Territories andNunavut

Potential fish entrapment andmortality from water intake

Water intakes will contain a fish screen as per DFO’s (1995) FreshwaterIntake end-of-Pipe Fish Screen Guidelines and/or DFO’s (2011) FishScreen Design Criteria for Flood and Water Truck Pumps

EIRB R30: The Developer shall,prior to construction, developmanagement plans for theprotection of fish and fish habitat inany areas affected by constructionin collaboration with DFO, and theTuktoyaktuk and Inuvik HTCs andFJMC.

Developer Commitment (Appendix I):

The Developer will develop and implement a fish and fish habitat protectionplan in cooperation with DFO, FJMC and the Tuktoyaktuk-Inuvik WorkingGroup that will include mitigation measures and adherence to OperationalStatements or other direction by DFO.

EIRB R31: The Developer shalldevelop a long-term maintenanceplan for the Hans and Zed Creekcrossings to protect fish habitat.

All project activities will follow measures to prevent or minimizesedimentation and erosion as described in the Sediment and ErosionControl Plan (Appendix E.1)

All Program activities will be conducted in accordance with the Fish andFish Habitat Protection Plan to be developed in consultation with theappropriate agencies

Wildlife and Wildlife Habitat

Disturbance or destruction ofmuskrat push-ups or nests from iceroad construction or winter waterwithdrawal

Muskrat surveys will be conducted prior to water withdrawal or winter roadconstruction

Disturbance or destruction of nestsof migratory birds due to summerconstruction activities

Bird nest sweeps will be conducted prior to summer construction activities

EIRB R32: The IEMOC shalldetermine appropriate setbackdistances for… critical habitat ofSAR, waterfowl and tundra-nestingbird species.

All Program activities will be conducted in accordance with the Wildlife andWildlife Habitat Protection Plan to be developed in consultation with theappropriate agencies

Page 78: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 13: Predicted Environmental Impacts of Undertaking and Proposed Mitigation

June 2013

13-10

Table 13-3 Potential Environmental Effects and Mitigations (cont’d)

Potential Environmental Effects Mitigation

Harvesting and Traditional Land Use

Potential disruption of access toharvesting and traditional land useareas during winter construction

No construction activities will take place within 1,000 m of Husky Lakes

HTCs will be notified of construction schedule and location of activities

Temporary site-specific signage will be posted, as necessary, ifconstruction activities occur near traditional trails

Potential disruption of access toharvesting and traditional land useareas during summer construction

No construction activities will take place within 1,000 m of Husky Lakes

HTCs will be notified of construction schedule and location of activities

Summer construction activities will be limited to the constructedembankment

Potential disruption of fish harvestactivities due to watercoursecrossing construction or waterwithdrawal activities

No construction activities will take place within 1,000 m of Husky Lakes

HTCs will be notified of construction schedule and location of activities

EIRB R20: The Developer shallwork with the Parties (DFO, EC,ENR) and comanagement bodies(FJMC, WMAC) and HTCs toensure that the Developer’smitigation, monitoring andmanagement commitments relatedto wildlife, fish and harvesting aremet and reported on annuallythrough IEMOC or through thespecific comanagement bodiesresponsible for resourcemanagement in the ISR.

Developer Commitment (Appendix I):

An annual construction monitoring report will be provided to applicableregulators and interested parties that will include:

Encounters and mortalities;

Notifications provided to workers regarding wildlife presence;

Waste management practices;

Measures used to reduce disturbance to any nesting birds;

Dust control effectiveness;

Conformance with the Wildlife Management Plan, EnvironmentalManagement Plan, Erosion and Sediment Control Plan, and otherplans;

Adaptive management measures that were implemented, if any.

An Environmental Management Plan (EMP) will be prepared prior toconstruction, and will be submitted for regulatory approval prior to use. TheEMP will clearly define expectations for compliance monitoring,responsibilities, requirements for training, and reporting.

Page 79: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 13: Predicted Environmental Impacts of Undertaking and Proposed Mitigation

June 2013

13-11

13.6 Residual Effects of the Project on the Environment

13.6.1 Assessment of Residual Environmental Effects

As discussed in Section 13.5, the Substituted Panel reviewed the ITH project’s environmental effects and

determined that “it will cause impacts on the environment”, but that “the potential adverse effects of the

ITH project can be mitigated and properly managed if the Panel’s recommendations and the Developer’s

commitments are implemented” (EIRB 2013, p. iii). The Government of Canada (2013, p. 5) stated that

“taking into consideration the Panel Report and the implementation of mitigation measures that are

considered appropriate, the Government of Canada has determined that the ITH project is not likely to

cause significant adverse environmental effects.” The Government of Canada responded to the EIRB’s

recommendations by “accepting”, “accepting the intent of” or “rejecting” each of the recommendations.

Residual environmental effects are those effects to environmental components which remain after the

application of mitigation. The mitigation to be applied has been summarized in Table 13-3.

13.6.2 Terrain, Soils and Permafrost

To mitigate residual effects to terrain, soil and permafrost, the EIRB (2013) recommended that:

R36: AANDC and the NWT Water Board shall ensure that the same road alignments are not used to

access aggregate sources every year in order to avoid the vegetation and terrain damage caused by

repeated use.

R37: The Developer shall develop a monitoring program with respect to vegetation and terrain that

includes active layer and near-surface permafrost impacts from winter road construction to the

aggregate sources. Monitoring reports should be filed with the appropriate regulators, including

AANDC, on a regular basis and not less that every two years, with particular emphasis on cumulative

impacts of the roads on these terrain characteristics. This monitoring program and its results shall be

integrated into the cumulative effects and adaptive management programs to be established by the

IEMOC.

The Government of Canada’s responses to the EIRB’s recommendations are as follows:

R36: The Government of Canada accepts the intent of this recommendation and notes that it is

directed at AANDC and the Northwest Territories Water Board. The Government of Canada

understands the intent of this recommendation is to reduce the damage to vegetation and terrain from

repeated use of winter access roads. AANDC, as a regulator of land-use activities, has the ability to

manage this activity on a case-by-case basis, and will work with the Northwest Territories Water Board

and the Developer to ensure the appropriate management of winter road alignment.

R37: The Government of Canada notes that this recommendation is directed at the Developer and

accepts its intent. The Government of Canada agrees with the need for monitoring reports to be

provided to the regulators, consistent with legislative and regulatory requirements, and will work with

the Developer to determine the appropriate scope of a monitoring program with respect to vegetation

and terrain.

Page 80: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 13: Predicted Environmental Impacts of Undertaking and Proposed Mitigation

June 2013

13-12

13.6.3 Water Quantity (Surface Water)

To mitigate residual effects to water quantity, the EIRB (2013) recommended that:

R34: The 10 per cent water withdrawal limit contained in the DFO Protocol for Winter Water

Withdrawal from Ice-covered Waterbodies in the Northwest Territories and Nunavut (2010) shall be

applied to every lake and water body used as a water source over the lifetime of the Project.

R35: Monitoring of the effects of long term water use for the construction of these roads shall be

included in the regulatory approvals granted by DFO, AANDC and the NWT Water Board, as

appropriate, and the results of this monitoring shall be integrated into the cumulative effects and

adaptive management programs to be established by the IEMOC.

The Government of Canada’s responses to the EIRB’s recommendations are as follows:

R34: The Government of Canada accepts this recommendation. The Developer has committed to

using DFO’s “Protocol for Winter Water Withdrawal from Ice-Covered Waterbodies in the Northwest

Territories” and other relevant guidelines. The Government of Canada notes that detailed information

is not required for all waterbodies according to the protocol; however, location and quantities being

withdrawn would still be required for each water source to determine compliance. This information

requirement will be addressed through the Northwest Territories Water Board process.

R35: The Government of Canada accepts the intent of this recommendation. Currently, there is no

program in place for the monitoring of long term water use; however, DFO will work with other parties

as appropriate, including AANDC and the Northwest Territories Water Board, to ensure that impacts

from water use are avoided and by providing expert advice in the development of monitoring plans,

coordinating monitoring efforts and sharing of information.

13.6.4 Water Quality

Potential water quality effects were identified by the EIRB in relation to fish and fish habitat. As such,

those recommendations are provided in Section 13.6.5.

13.6.5 Fish and Fish Habitat

To mitigate residual effects to fish and fish habitat, the EIRB (2013) recommended that:

R29: The Developer shall consult with both DFO and AANDC to determine appropriate mitigation

measures before using a chemical dust suppressant technique on the ITH.

R30: The Developer shall, prior to construction, develop management plans for the protection of fish

and fish habitat in any areas affected by construction in collaboration with DFO, and the Tuktoyaktuk

and Inuvik HTCs and FJMC.

R31: The Developer shall develop a long-term maintenance plan for the Hans and Zed Creek

crossings to protect fish habitat.

Page 81: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 13: Predicted Environmental Impacts of Undertaking and Proposed Mitigation

June 2013

13-13

The Government of Canada’s responses to the EIRB’s recommendations are as follows:

R29: The Government of Canada accepts the intent of this recommendation and notes that it is

directed at the Developer. The Government of Canada supports the need to manage the use of

chemical dust suppressants and would like to note that EC, TC, DFO, AANDC and the Northwest

Territories Water Board have overlapping jurisdiction with respect to the management of this matter.

The Developer shall consult with these departments to determine appropriate mitigation measures

before using a chemical dust suppressant techniques on the Project. The Government of Canada will

work with the Developer and other appropriate parties to promote compliance with relevant legislation

and to provide advice on proposed mitigation measures related to chemical dust suppressant

techniques.

R30: The Government of Canada notes that this recommendation is directed at the Developer and

accepts its intent. As a participant in the co-management structure set out in the Inuvialuit Final

Agreement, DFO will continue to work with the Fisheries Joint Management Council and Hunters and

Trappers Committees on the management of fisheries resources in the Inuvialuit Settlement Region.

DFO will ensure that the mitigation measures as well as monitoring and management plans required

under any potential Fisheries Act authorizations are met through standard compliance monitoring and

enforcement.

R31: The Government of Canada notes that this recommendation is directed at the Developer and

accepts its intent. DFO will work with the Developer with respect to crossing design details, fish habitat

compensation, mitigation measures and monitoring to address the information requirements necessary

to make a regulatory decision and issue potential authorizations under paragraph 35(2)(b) of the

Fisheries Act. If the crossings are properly designed, long-term maintenance to protect fish and fish

habitat may not be required.

13.6.6 Muskrat and Beaver

To mitigate residual effects to muskrat, the EIRB (2013) recommended that:

R25: The Developer shall complete pre-construction surveys for muskrat push-ups on lakes where

winter snow removal and/or winter water withdrawal will take place.

R26: The Developer shall follow mitigation measures set out in permits issued under the Wildlife Act

and monitor mitigation success, if muskrats are present.

The Government of Canada’s responses to the EIRB’s recommendations are as follows:

R25: The Government of Canada notes that this recommendation is directed at the Developer. The

Government of Canada accepts the intent of the recommendation and will work with the Developer

and appropriate parties, as required, to ensure its implementation.

R26: The Government of Canada notes that this recommendation is directed at the Developer. The

Government of Canada accepts the intent of the recommendation and will work with the Developer

and appropriate parties, as required, to ensure its implementation.

Page 82: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 13: Predicted Environmental Impacts of Undertaking and Proposed Mitigation

June 2013

13-14

No recommendations were made by the EIRB related to beavers.

13.6.7 Waterbirds and Waterfowl

Potential water quality effects were identified by the EIRB in relation to species at risk. To mitigate

residual effects to waterbirds and waterfowl, the EIRB (2013) recommended that:

R32: The IEMOC shall determine appropriate setback distances for… critical habitat of SAR, waterfowl

and tundra-nesting bird species.

The Government of Canada’s responses to the EIRB’s recommendations (relevant to bird species) are as

follows:

R32: The Government of Canada accepts the intent of this recommendation. The Government of

Canada expects the Developer to work with parties to determine appropriate setback distances for …

nests of bird species at risk, waterfowl and other tundra-nesting bird species under the umbrella of the

follow-up program and through the development of the WEMP. The Government of Canada notes that

regulatory authorities may have the ultimate discretion to determine setbacks where they may be

included as conditions in permits or authorizations issued for the Project. The Government of Canada

would also like to clarify that critical habitat as defined in the federal Species at Risk Act has not been

identified for any of the species at risk that may occur in the area proposed for development of the

Project…The Government of Canada will work with the appropriate parties to meet the intent of this

recommendation, as required.

13.6.8 Harvesting and Traditional Land Use

To mitigate residual effects to harvesting and traditional land use, the EIRB (2013) recommended that:

R20: The Developer shall work with the Parties (DFO, EC, ENR) and comanagement bodies (FJMC,

WMAC) and HTCs to ensure that the Developer’s mitigation, monitoring and management

commitments related to wildlife, fish and harvesting are met and reported on annually through IEMOC

or through the specific comanagement bodies responsible for resource management in the ISR.

R50: The Inuvialuit Land Administration shall work with the Developer, HTCs, FJMC and WMAC

(NWT) to ensure proper signage and guidelines are established to monitor access to the Husky Lakes

area.

R51: Developer shall consult with the communities, HTC's and ISR comanagement boards on the

development and content of the Project's environmental management plans in relation to Category E

lands.

Page 83: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 13: Predicted Environmental Impacts of Undertaking and Proposed Mitigation

June 2013

13-15

The Government of Canada’s responses to the EIRB’s recommendations are as follows:

R20: The Government of Canada notes that this recommendation is directed at the Developer. The

Government of Canada accepts the intent of the recommendation and modifies it such that the results

of monitoring would be met and reported on through a combination of regulatory instruments, the

follow-up program and specific co-management bodies responsible for resource management in the

Inuvialuit Settlement Region. DFO will continue to work closely with co-management bodies such as

the Fisheries Joint Management Committee and the Tuktoyaktuk to Inuvik working group to manage

fisheries resources in the Inuvialuit Settlement Region. DFO will ensure that the mitigation measures

as well as monitoring and management plans required under any potential Fisheries Act authorizations

are met through standard compliance monitoring and enforcement. Environment Canada will continue

to work closely with co-management bodies such as the Wildlife Management Advisory Council to

manage wildlife resources within their departmental mandate. The Government of Canada will work

with other appropriate parties, as required, to monitor implementation of the Developer’s commitments

related to mitigation, monitoring and management for wildlife, fish and harvesting.

R50: The Government of Canada notes that this recommendation is directed at the Inuvialuit Land

Administration.

R51: The Government of Canada notes that this recommendation is directed at the Developer and

accepts its intent.

13.7 Assessment of Residual Environmental Effects

With the application of the mitigation measures (Table 13-3), the Developer Commitments (Appendix I),

the EIRB’s recommendations (Appendix G), and the Government of Canada’s recommendations

(Appendix H) residual effects to the VCs will be prevented or mitigated.

Additional monitoring and consultation requirements not included in Developer Commitments and not

otherwise required as part of regulatory approvals are summarized in Table 13-4:

Table 13-4 Synopsis of Recommended EIRB Mitigations Additional to DeveloperCommitments

EIRB Mitigation GNWT-DOT Action Anticipated Timing

Wildlife EffectsManagement Plan(WEMP)

The GNWT-DOT will need to ensure that the relevant co-management agencies are given the opportunity to provide input onthe inclusion of specific items to be addressed in the WEMP, priorto its finalization (e.g. R21, R24, R33).

Prior to construction

Mitigation andMonitoring forMuskrat

The GNWT-DOT will need to discuss the requirements for muskratmitigation with ENR.

The GNWT-DOT will need to determine, in discussion with ENR,the specific objectives and methods for monitoring the effects ofproject activities to muskrat.

Prior to construction

Page 84: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 13: Predicted Environmental Impacts of Undertaking and Proposed Mitigation

June 2013

13-16

Table 13-4 Synopsis of Recommended EIRB Mitigations Additional to DeveloperCommitments (cont’d)

EIRB Mitigation GNWT-DOT Action Anticipated Timing

Monitoring of effectsto water resources,vegetation, terrainand permafrost

The GNWT-DOT will need to determine, in discussion with DFOand the NWTWB, the specific objectives and methods formonitoring the effects of long-term water use on water resources.

The GNWT-DOT will need to determine, in discussion with AANDCand the NWTWB, the specific objectives and methods formonitoring the effects of project access roads on terrain, vegetationand near-surface permafrost.

Prior to construction

Evidence ofpermafroststabilization inborrow pits

The GNWT-DOT will need to develop a methodology for adequatelyproving to regulators that permafrost has been re-established in pitfloors and walls following pit reclamation.

By end of secondyear operation

13.8 Effects of Accidents and Malfunctions

The following section states the findings of the EIRB (2013, p. 145-147).

The potential exists for accidents or malfunctions to occur in association with any human activity,

including those proposed for the construction of the ITH. Environmental consequences of potential

accidents or malfunctions related to the ITH project and associated aggregate borrow and construction

camp activities would be primarily limited to those related to vehicle crashes and fuel storage,

transportation and handling system failures.

The Developer has proposed to employ a number of preventative and mitigation measures to minimize

environmental effects of malfunctions or accidents that may occur in connection with the project. Their

key strategy will be to prevent accidents and malfunctions through education, monitoring, follow-up and

enforcement. With the application and implementation of preventative and mitigation measures, the

Developer anticipates no significant fuel, chemical or other product spills are expected to occur.

These measures include:

implementation of best management and industry practices to prevent or minimize the occurrence of

accidents or malfunctions;

ensuring that all on-site contractors have industry-compliant and satisfactory Health, Safety and

Environmental (HSE) policies, programs and manuals and that they are successfully implemented

throughout the project;

ensuring that the Developer and its contractors have an environmental management plan and spill

contingency plan that will address potential accidents and malfunctions for the life of the project. In

particular, the Developer will ensure that a spill contingency plan is in place that conforms to INAC’s

(2007) Guidelines for Spill Contingency Planning. In particular, the plan will include:

descriptions of the type and amount of contaminants stored at the project location;

site map of the location;

Page 85: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 13: Predicted Environmental Impacts of Undertaking and Proposed Mitigation

June 2013

13-17

steps to be taken to report, contain, clean-up and dispose of contaminants in the case of a spill;

a description of the training provided to employees to respond to a spill; and

an inventory of and the location of response and clean-up equipment available to implement the

spill contingency plan.

compliance with the terms and conditions of the necessary Inuvialuit Land Administration and

AANDC’s land use and quarry permits and authorizations that will be issued for the construction

project;

conformance with existing applicable GNWT and Workers Compensation Board standards;

fuel and other hydrocarbons will be stored in accordance with Canadian Council of Ministers of the

Environment (CCME’s) (2003) Environmental Code of Practice for Aboveground and Underground

Storage Tank Systems Containing Petroleum and Allied Petroleum Products, INAC’s (2011b) Northern

Land Use Guidelines: Camp and Support Facilities, and to the extent applicable, and the Canadian

Environmental Protection Act (CEPA) Storage Tank System for Petroleum Products and Allied

Petroleum Products Regulations.

all vehicles and equipment will be re-fuelled at least 100 m from water bodies following INAC’s (2011b)

Northern Land Use Guidelines: Camp and Support Facilities; and,

spills will be reported to the 24-hour Spill Report Line.

The project construction team will work closely with the ILA environmental and wildlife monitors when the

proposed ITH is being constructed.

The Developer and its contractors are expected to generate hazardous wastes. DOT is currently a

registered generator of hazardous waste and is directly responsible for the hazardous waste generated

from their operations. Further, DOT is indirectly responsible for the hazardous waste generated from

private contractors on the project. The Developer is aware that hazardous waste must be disposed of at

an approved facility, and that it is not appropriate to dispose of hazardous waste in NWT community solid

waste facilities.

To mitigate potential adverse environmental effects associated with improper hazardous waste disposal

and to further demonstrate that proper hazardous waste management planning is in place, the Developer

has committed to the development of a hazardous waste management plan (HWMP) that will encompass

all pre-construction and construction phases of the project and will apply to the Developer and all

contractors involved in receiving, transferring, and transporting hazardous waste for the Developer’s

activities on land, water, and air.

The HWMP will include, but not be limited to:

identifying hazardous waste sources, types, and approximate quantities to be produced, including

liquid, solid, dangerous goods and non-dangerous goods;

describing waste segregation methods;

Page 86: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 13: Predicted Environmental Impacts of Undertaking and Proposed Mitigation

June 2013

13-18

describing all on-site treatment and disposal methods; and,

describing hazardous wastes that will be transported to approved receiving facilities.

Safety measures to prevent vehicle accidents on the proposed ITH have been and will continue to be

incorporated into the ITH design by the Developer. Measures to avoid or minimize accidents will include

posted speed limits and adequate signage alerting drivers to highway curves and upcoming bridges.

Bridge design will incorporate guardrails to prevent a vehicle from going off the bridge and into a

watercourse in the event of an accident.

With respect to environmental effects, a worst case would involve environmental damage to the Husky

Lakes and effects to traditional activities and harvesting as a result of a fuel supply truck crash or rollover

on the ITH, in a location nearest the Husky Lakes (e.g., km 80) and which causes a fuel spill of greater

than 10,000 L into an open watercourse that is a direct tributary to the Husky Lakes. This scenario is

discussed under section 13 of this report.

The Panel accepts the Developer’s evidence on accidents and malfunctions.

13.9 Proposed Monitoring Programs

Monitoring plans that will be implemented during the ITH project to verify the effectiveness of mitigation

measures are as follows:

Wildlife Effects Monitoring Plan (Developer Commitment, Appendix I)

Aquatic Effects Monitoring Plan (EIRB R35)

Terrain, Vegetation and Permafrost Monitoring Plan (if needed) (EIRB R37)

Compliance Monitoring Plan (Developer Commitment, Appendix I)

13.10 Cumulative Effects

No new projects have been proposed in the region since the Substituted Panel’s review. The Panel’s

analysis of the cumulative effects resulted in recommendations for ongoing monitoring. EIRB (2013,

p. 137-141) recommendations are as follows:

R46: The Developer, in collaboration with GNWT-ENR, EC and wildlife comanagement organizations,

working through the IEMOC [Independent Environmental Monitoring and Oversight Committee], shall

further develop and implement the proposed WEMP to ensure that it addresses both direct and

cumulative effects from highway construction and operations on wildlife distribution and abundance

within the regional cumulative effects study area.

R47: The results of WEMP monitoring of cumulative effects on wildlife, vegetation and land use shall

be integrated into the IEMOC’s adaptive management framework, and, to the extent possible, into any

government regional cumulative effects monitoring programs.

Page 87: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 13: Predicted Environmental Impacts of Undertaking and Proposed Mitigation

June 2013

13-19

The Government of Canada’s responses to the EIRB’s recommendations are as follows:

R46: The Government of Canada notes that this recommendation is directed at the Developer and

accepts its intent. The recommendation requires the Developer to collaborate with Government of

Northwest Territories Department of Environment and Natural Resources, Environment Canada and

wildlife co-management organizations. The Government of Canada believes that the WEMP can be

developed and implemented as part of the follow-up program in such a way that it addresses direct

effects from construction and operations on wildlife distribution and abundance and can contribute

towards broader cumulative effects monitoring within the regional cumulative effects study area. The

Government of Canada will work with the appropriate parties, as required, to ensure that the

development and implementation of the WEMP meets the intent of this recommendation.

R47: The Government of Canada accepts the intent of this recommendation. However, the

Government of Canada believes that the results of the WEMP monitoring of project-specific effects on

wildlife, vegetation and land use could be integrated into an adaptive management framework formed

under the umbrella of the follow-up program. The Government of Canada will work with the appropriate

parties, as required, to ensure the results of the project-specific WEMP are integrated into any

government regional cumulative effects monitoring programs to the extent possible.

Page 88: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 13: Predicted Environmental Impacts of Undertaking and Proposed Mitigation

June 2013

13-20

Page 89: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 14: Environmental Management Plans

June 2013

14-1

14 ENVIRONMENTAL MANAGEMENT PLANS

Several environmental management plans have been prepared or are being developed for the ITH

project. These plans describe management actions, mitigation measures, and equipment available to

prevent, manage, mitigate, or respond to potential issues. These plans are provided in Appendix E, and

include:

Sediment and Erosion Control Plan (Appendix E.1)

Waste Management Plan (Appendix E.2)

Explosives Management Plan (Appendix E.3)

Pit Development Plan (Appendix E.4)

Spill Response Procedure (Appendix E.5)

Spill Contingency Plan (Appendix E.6)

Safe Work Procedure – Fueling Equipment (Appendix E.7)

Safe Work Procedure – Handling Petroleum (Appendix E.8)

Emergency Response Plan (Appendix E.9)

Each plan’s current stage of development and schedule for completion is shown in Table 4-8.

Page 90: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 14: Environmental Management Plans

June 2013

14-2

Page 91: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 15: References

June 2013

15-1

15 REFERENCES

Bond, W.A., and R.N. Erikson. 1987. Fishery data from Phillips Bay, Yukon, 1985. Can. Data Rep. Fish.

Aquat. Sci. 635: v + 39 p.

Canadian Council of Ministers of the Environment (CCME). 2003. Environmental Code of Practice for

Aboveground and Underground Storage Tank Systems Containing Petroleum and Allied

Petroleum Products. Accessed from: http://www.ccme.ca/assets/pdf/pn_1326_eng.pdf

Chang-Kue, K.T.J., and Jessop, E.F. 1992. Coregonid migration studies at Kukjuktuk Creek, a coastal

drainage on the Tuktoyaktuk Peninsula, Northwest Territories. Canadian Technical Report of

Fisheries and Aquatic Sciences 1811. Winnipeg: Central and Arctic Region, Dept. of Fisheries

and Oceans.

Community of Inuvik, the Wildlife Management Advisory Council (NWT) and the Joint Secretariat (ICCP).

2008. Inuvik Inuvialuit Community Conservation Plan: A Plan to Provide Guidance Regarding the

Conservation and Management of Renewable Resources and Lands within the Inuvialuit

Settlement Region in the Vicinity of Inuvik, Northwest Territories. Inuvik, Northwest Territories.

Community of Tuktoyaktuk, the Wildlife Management Advisory Council (NWT) and the Joint Secretariat

(TCCP). 2008. Tuktoyaktuk Community Conservation Plan: A Plan for the Conservation and

Management of Natural Resources and Lands within the Inuvialuit Settlement Region in the

Vicinity of Tuktoyaktuk, Northwest Territories. Tuktoyaktuk, Northwest Territories.

Craighead, L., D. Paetkau, H.V. Reynolds, E.R. Vyse, and C. Strobeck. 1995. Microsatellite analysis of

paternity and reproduction in arctic grizzly bears. Journal of Heredity 86:255-261.

Department of Fisheries and Oceans/ Fisheries and Oceans Canada (DFO). 1995. Freshwater Intake

End-of-Pipe Fish Screen Guideline. Accessed from: http://www.dfo-

mpo.gc.ca/habitat/role/141/1415/14155/pipe/index-eng.asp

Department of Fisheries and Oceans/ Fisheries and Oceans Canada (DFO). 1998. Guidelines for the Use

of Explosives In or Near Canadian Fisheries Waters. Prepared by D.G. Wright and G.E. Hopky.

Accessed from: http://www.dfo-mpo.gc.ca/Library/232046.pdf

Department of Fisheries and Oceans/ Fisheries and Oceans Canada (DFO). 2007a. Clear Span Bridges.

. Northwest Territories Operational Statement. Version 3.0. Accessed from: http://www.dfo-

mpo.gc.ca/regions/central/habitat/os-eo/provinces-territories-territoires/nt/os-eo05-eng.htm

Department of Fisheries and Oceans/ Fisheries and Oceans Canada (DFO). 2007b. Ice Bridges and

Snow Fills: Northwest Territories Operational Statement Version 3.0. Accessed from:

http://www.dfo-mpo.gc.ca/regions/central/habitat/os-eo/provinces-territories-territoires/nt/pdf/os-

eo10_e.pdf

Page 92: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 15: References

June 2013

15-2

Department of Fisheries and Oceans/ Fisheries and Oceans Canada (DFO). 2010. DFO Protocol for

Winter Water Withdrawal from Ice-covered Waterbodies in the Northwest Territories and

Nunavut. Accessed from:

http://mvlwb.ca/Boards/WLWB/Registry/2010/W2010C0005/W2010C0005%20-

%20Land%20Use%20Permit%20Application%20-

%20DFO%20Water%20Withdrawal%20Protocol%20-%20Aug%2025_10.pdf

Department of Fisheries and Oceans/ Fisheries and Oceans Canada (DFO). 2011. Fish Screen Design

Criteria for Flood and Water Truck Pumps.

Environmental Impact Review Board (EIRB). January 25, 2013. Final Report of the Panel for the

Substituted Environmental Impact Review of the Hamlet of Tuktoyaktuk, Town of Inuvik and

GNWT - Proposal to Construct the Inuvik to Tuktoyaktuk Highway.

Government of Canada. April 5, 2013. Government of Canada Response to the Panel Report on the

Proposal to Construct the Inuvik to Tuktoyaktuk Highway.

Harwood, L. 2003. Husky Lakes Ecological Assessment Progress Report (2002). Unpublished report

prepared for the Fisheries Joint Management Committee, PERD, Devon Canada Corporation and

the Tuktoyaktuk and Inuvik Hunter and Trapper Committees. 7 p.

IMG-Golder Corporation. 2009. Assessment of Fisheries Potential of the Tuktoyaktuk to Source 177 All-

Weather Road Impact Area. Prepared for GNWT Department of Transportation.

IMG-Golder Corporation. January 2012a. Fish Habitat Assessment at Select Watercourse Crossings

along the Inuvik to Tuktoyaktuk Highway. Prepared for Government of the Northwest Territories –

Department of Transportation. Project Number: 11-1320-0001.

IMG-Golder Corporation. September 28, 2012b. Lake Bathymetry Survey for the Inuvik to Tuktoyaktuk

Highway. Prepared for Government of the Northwest Territories – Department of Transportation.

Project Number: 11-1320-0001-12.

Imperial Oil Resources Ventures Limited Partnership, ConocoPhillips Canada (North) Limited,

ExxonMobil Canada Properties, Shell Canada Limited and Mackenzie Valley Aboriginal Pipeline

Limited (IOL et al.). 2004. Environmental Impact Statement for the Mackenzie Gas Project.

Submitted to the National Energy Board.

Inuvialuit Land Administration and Indian and Northern Affairs Canada (ILA and INAC). No Date (nd).

Inuvialuit Settlement Region Granular Resources Management Plan. Accessed from:

http://www.inuvialuitland.com/resources/ISR_GRMP.pdf

Indian and Northern Affairs Canada (INAC). 2003. Northern Land Use Guidelines – Access: Roads and

Trails. Accessed from: http://www.aadnc-aandc.gc.ca/eng/1100100023568

Indian and Northern Affairs Canada (INAC). April 2007. Guidelines for Spill Contingency Planning.

Prepared by Water Resources Division, Indian and Northern Affairs Canada. Yellowknife NT.

Accessed from: http://www.nwtwb.com/Downloads/Spill_Contingency_Planning_2007.pdf

Page 93: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water Board

Section 15: References

June 2013

15-3

Indian and Northern Affairs Canada (INAC). 2010. Northern Land Use Guidelines: Pits and Quarries.

Volume 7

Indian and Northern Affairs Canada (INAC). 2011. Northern Land Use Guidelines: Camp and Support

Facilities. Accessed from: http://www.aadnc-aandc.gc.ca/DAM/DAM-INTER-

NWT/STAGING/texte-text/nlug6_1313789162200_eng.pdf

Joint Secretariat. March 2003. Inuvialuit Harvest Study: Data and Methods Report 1988-1997. Inuvik,

NWT. Accessed from: http://www.jointsecretariat.ca/pdf/js/IHS10yrDataMethodsReport.pdf.

Accessed December 22, 2011.

KAVIK-STANTEC. January 2012a. Inuvik – Tuktoyaktuk Highway Potential Borrow Source Geotechnical

Investigations Program – Project Description Report. Submitted to the Environmental Impact

Screening Committee. Prepared for Government of the Northwest Territories – Department of

Transportation. Project Number: 123510744.

KAVIK-STANTEC. March 12, 2012b. Inuvik – Tuktoyaktuk Highway Baseline Data Acquisition Program

Terrain Evaluation. Prepared for Government of the Northwest Territories – Department of

Transportation. Project Number: 123510689.

KAVIK-STANTEC. August 30, 2012c. Inuvik to Tuktoyaktuk Highway – Surficial Geology and Terrain

Constraints (Mapbook). Prepared for Government of the Northwest Territories – Department of

Transportation. Project Number: 123510689.

KAVIK-STANTEC. August 31, 2012d. Inuvik to Tuktoyaktuk Highway – Terrain and Permafrost Field

Verification Program. Prepared for Government of the Northwest Territories – Department of

Transportation. Project Number: 123510689.

KAVIK-STANTEC. September 30, 2012e. Inuvik – Tuktoyaktuk Highway Hydrotechnical Assessment of

Stream Crossings. Prepared for Government of the Northwest Territories – Department of

Transportation c/o E. Gruben’s Transport Ltd. Project Number: 1144901635.

KAVIK-STANTEC. December 10, 2012f. Inuvik – Tuktoyaktuk Highway 2013-2014 Geotechnical

Investigations Program – Project Description Report. Submitted to the Environmental Impact

Screening Committee. Prepared for Government of the Northwest Territories – Department of

Transportation. Project Number: 1235110025.

Kokelj, S.V., B. Zajdlik, and M.S. Thompson. 2009. The Impacts of Thawing Permafrost on the Chemistry

of Lakes across the Subarctic Boreal-Tundra Transition, Mackenzie Delta Region, Canada.

Permafrost and Periglacial Processes. 20:185-199.

Kiggiak-EBA Consulting Ltd. October 2010. Spring 2010 Aquatic Field Program Results for the Inuvik to

Tuktoyaktuk Highway, Northwest Territories. Prepared for Hamlet of Tuktoyaktuk, Town of Inuvik

and the Government of the Northwest Territories. Project Number V23201098.1300.

Kiggiak-EBA. 2011. Environmental Impact Statement for Construction of the Inuvik to Tuktoyaktuk

Highway, NWT. Inuvik, NT. May 2011.

Page 94: Water Licence Application for Construction of Inuvik ... · Figure 3-1 is a map of the Inuvik to Tuktoyaktuk (ITH) project (the ITH project) area, situated between Inuvik and Tuktoyaktuk

Water Licence Application for Construction of Inuvik - Tuktoyaktuk HighwaySubmission to the Northwest Territories Water BoardSection 15: References

June 2013

15-4

Kiggiak-EBA Consulting Ltd. June 2013. Inuvik to Tuktoyaktuk Highway 2013 Bathymetric Survey –

Rev.1. Prepared for EGT Northwind Ltd. Project Number. KE1057 (E11103030-01).

Pienitz, R., Smol, J.P., and Lean, D.R.S. 1997. Physical and chemical limnology of 59 lakes located

between the southern Yukon and the Tuktoyaktuk Peninsula, Northwest Territories (Canada).

Can. J. Fish. Aquat. Sci. 54: 330–346.

Quinton, W.L. and Marsh, P. (1999). A conceptual framework for runoff generation in a permafrost

environment. Hydrol. Process., 13, 2563–2581.

Rampton, V.N. 1988. Surficial Geology of Tuktoyaktuk, District of Mackenzie. Geological Survey of

Canada Surficial Geology Map 1647a 1:500,000 Scale.

Rescan Environmental Services Ltd. (Rescan). 1999. Proposed Inuvik to Tuktoyaktuk Road:

Environmental/ Socioeconomic Baseline Report. Prepared for GNWT Department of

Transportation. Yellowknife, NWT.