water optimization coastal gujarat power...

19
Water Optimization Coastal Gujarat Power Ltd.

Upload: others

Post on 18-Mar-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

Water Optimization Coastal Gujarat Power Ltd.

Page 2: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

Private and Confidential | 01

Plant Design Parameter

Technology : Super-Critical, Pulverised Imported Coal-fired Seawater based power plant (Steam conditions atSteam Turbine inlet to be 242 bar (g), 565 °Csuperheat / 593 °C reheat).

Nos. of Units : Five (830 MW x 5)

Nos. of Stacks : Two 275 m high multi-flue stacks

Type of Fuels : Imported Coal

Cooling System : Once-through system

Page 3: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

Water Source and Utilization at CGPL

Water RequirementPlant Water Usage Water Requirement

(m3/hr)Type of Water

For CW System 567625 Sea WaterMakeup for Boilers 148 DM Water

Makeup to HVAC System 300 Service WaterPotable Water 1.5 Produced from Sea Water

Makeup to Ash handling system

79 Sea water

Service Water System 778 Produced from Sea WaterCHP-Dust Suppression

system217 Service water

Water Source – All the water requirement are fulfilled from Sea Water

Page 4: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

Private and Confidential | 01

Water Consumption & Savings

Water Optimization( Effluent collection-Treatment- Recycle-Reuse)CPU regeneration ,DM regeneration coal runoff pit water treated through ETP and supplied

to green belt and reused as gardening water. Approx.398 hector green belt area has beendeveloped through ETP water )

Measures carried for saving of different types of water:All plant storm water drain has been connected to rain water harvesting system.From rain water harvesting system water being used at Coal handling plant sprinkler system for dust suppression.

Page 5: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

Fire water Hydrant Pressure Monitoring Unit at CGPL:

Fire water Hydrant Pressure Monitoring Unit at CGPL:Online Pressure transmitter installed at fire water line furthest and highest point. Pressure transmitter value has been provided in PI system so that we can monitor pressure & in case of leakage in fire hydrant system same has been rectified promptly.

Earlier firewater lines were underground so it was difficult to identify underground leakages, The monitoring help us in early identification of line leakage instantly .

Instead of manual RC valve auto pressure control valve installed in system to maintain desired pressure as well as helping in monitoring of consumption

Page 6: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

Fire water Hydrant Pressure Monitoring Unit at CGPL:

Page 7: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

Private and Confidential | 03

Use of steam pegged deaerated water for boiler filling and cleaning to achieve minimum time and corrosion: (O&M Best Practice)

\\172.16.117.3\MU 30 DEA LEVEL\\172.16.117.3\MU 30 DEAERATOR TEMP145.89DEG C

DEAERATOR TEMP15-Jul-17 1:57:19 AM14-Jul-17 4:02:14 PM 9.92 hours

Plot-0

70

80

90

100

110

120

130

140

150

DM Water filled to boiler is maintained at proper pH and also de

aerated by steam pegging i.e.

maintained 105 deg C + for reduction of dissolved oxygen

Page 8: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

Private and Confidential | 06

SWRO Permeate water remineralization:

PARAMETERSRain feed

River Water

Ground Water

SWRO Water

Conductivity(µs/Cm) 140 3200 900

pH 7.2 8.0 7.0

Ca(PPM) 40 240 6

Mg(PPM) 25 60 14

Alkalinity(PPM) 55 320 12

Cl (PPM) 12 820 260

Comparison of different types of water:

Though SWRO water brings down the TDS level to fresh water level but availability of different ions in that water does not match with normal river water on which we have all the experience, so the problem came when we used MS line for fire and service water.

Kutch in Gujarat having no fresh water source other than ground water. CGPL-Mundra makes all water from sea water and SWRO technology.

Page 9: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

Optimization of DM water consumption

0.72%

0.67%

0.55%0.58%

0.37%

0.30%

0.00%

0.10%

0.20%

0.30%

0.40%

0.50%

0.60%

0.70%

0.80%

FY 13 FY 14 FY 15 FY 16 FY 17 FY 18

Station Make-up %

Reduction in DM water consumption by 0.25% saves 1.8 Kcal/kwh in heat rate. Net

saving of 4.43 Cr/annum. (from FY 15 to FY 18)

Continual reduction in DM water consumption from FY 13 to FY 18

•Optimisation in soot blowing operation.

•Reduction in HTPRDS Pressure set point.

•Early identification and rectification of DM water and steam losses points.

•Reduction in clean up and start up time.

Action taken

Page 10: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

Effluent Treatment Plant

Guard Pond, Effluent Treatment Plant

Capacity: 1500 M3 (750 M3 Each)

Source of Water: Different Process Drains

Usage: Treated Water is used for Gardening

Page 11: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

Clean Up cycle- Time Reduction & Process Optimization

Unit#1019/04/20

16

Unit#4006/07/20

16

Unit#2017/07/20

16

Unit#3021/07/20

16

Unit#5001/01/20

17

Unit#3018/01/20

17

unit#1006/06/20

17

unit#3014/07/20

17

Unit#1016/09/20

17

unit#1026/10/20

17

Unit#3026/06/20

18

Unit#2013/07/20

18

Unit#3030/07/20

18

unit#1006/08/20

18

Time 69.79 57.6 56.47 26.05 32 19.6 19.8 22.5 19 20 16 14 15 15.4

69.79

57.6 56.47

26.0532

19.6 19.8 22.519 20

16 14 15 15.4

0

10

20

30

40

50

60

70

80

Hou

rs

Time Required for Cleanup (Target 16hours)

Problem Statement

• Cold Start-up time Reduction

Target• Reduction of

clean-up cycle time from 58 hrs. to 28 hrs.

• 24 hrs. to 20 hrs. subsequently in 2 years from FY17

Oil Gun Trial • LDO Test trial

during Boiler Cold flushing

• 1 hr. gain in LP Clean up Time

Installation of double dosing system• Parallel Clean up

of Condensate and Feed water cycle

• 4 hrs gain in LP Clean up time

Automation of Startup tool

• Real time gap identification with bench mark and

• Trigger alarm to take proactive action & preparation

Page 12: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

Clean Up cycle- Time Reduction & Process Optimization

• Maintain Deaerator temperature over 110o C during filling of boiler to ensure least % of O2 present in boiler water. As O2 is less there is less chance of corrosion and less cleanup time required. Even in case of hydro test feed water temperature is kept at higher side & later ID fan started to cool down boiler.

• Vacuum pulling activity started after starting CEP. Due to low pressure in Hotwell, deaeration or O2 removal starts early. Earlier we used to start the vacuum pulling activity just before light up.

• A dump line to atmosphere installed at CEP discharge , Incase hot well water turbidity increases over 10NTU then dump condensate to atmosphere and take fresh water. Earlier in case of water contamination it was drain through deaerator and thus loosing heat and time.

• Steam blowing through HP-LP bypass started to remove exfoliated material inside superheater and reheater tubes, if turbidity increases Dump line is opened.

• Temporary pump is installed to assist conduit filling trough adjacent filled seal well to speed up CW pump startup.

• A check sheet developed for Oil guns, after implementation of the same oil gun availability increased.

BRP(boiler recirculation pump) online NRV checking operation procedure developed ,thus unnecessary unit tripping and delay averted during wet to dry mode conversion .

Mill to be taken into service after achieving 40kg boiler pressure, it will prevent sudden metal temperature rise in superheater and reheater and prevent exfoliation.

Page 13: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

Clean Up cycle- Time Reduction & Process Optimization

• QC NRV’S mandatory operation checking incorporated in every startup.

• Mills HAD and CAD mandatory operation checking incorporated in every startup.

• CW discharge hydraulic valve logic changed and now fast closing modification implemented to prevent conduit drain.

• Turbine TSI parameters are captured in the gap analysis ,which gives a ready reference for next startup and ensure healthiness of our major equipment.

• BFP lube oil level switch replaced to online lube oil transmitter. We can preplan oil top-up activity thus reduce time delay.

• During shutdown to ensure gradual cooling of pressure parts in boiler to minimize exfoliation, we have adopted hot box up procedure. Boiler should be hot boxed up for 8 hours after normal shutdown.

• Double dosing system incorporated for simultaneous clean up of condensate and feedwater cycle.

• Start-up checklist for turbine and boiler area prepared.

Page 14: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

Service Water Consumption

CW CT Basin Makeup

BA Pump House

Boiler Header

TG Header

ICHS & ECHS

Aashiyana Township

Labor Colony

Unit 10 – 50 MOC Line

Cooling Towers makeup water

Fire Water System

ICHS

Main Plant

Service Water System

CW CT Basin Makeup

BA Pump House

Boiler Header

TG Header (C Row)

ICHS & ECHS

Aashiyana Township

Labor Colony

Unit 10 – 50 MOC Line (A Row)

Cooling Towers makeup water

Page 15: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

SERVICE WATER CONSUMPTION 2018 – 2019 till 21/02/19

1222511514 11853 11948

12321 12130 1234711523 11865

10957

9828

9597

8000

9000

10000

11000

12000

13000

14000

15000

Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19

SERVICE WATER CONSUMPTION TREND (M3) 2018 - 2019

Service Water Reduction after replacement of SW & FW Line: 11800 M3/day to 9800 M3/day Per Day Saving: 2000M3/Day Cost of Generation: 38/M3

Per day Saving: 2000x38= 76000/-Day Annual Saving: 2.77 Crores

Page 16: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

Full Fire System Outage

18

7

43

0

4

8

12

16

20

FY 16 FY 17 FY 18 FY 19

Page 17: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

Measures undertaken for Water conservation

Measures Short term Measures Medium Term Measures Long-termWater metering ( measuring)

Development of MIS- online system for Water consumption monitoring

Reducing leaks and over flows Revisit design criteria modify and improveBring all underground water pipe lines to surface

Rain Water collection & Utilization

)

Enhance Waste Water Reutilization (Quantify)-ETP & STP

Page 18: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

Private and Confidential | 01

COI Water Management Platform at Tata Power

• We have a community of interest ( COI) platform across our Tata Power level for water management.

• Through COI platform we are sharing our best practices, ideas & resolve issues with other divisions.

• KPIs are being given to all divisions and being tracked & shared to COI in each month.

Page 19: Water Optimization Coastal Gujarat Power Ltd.environment.missionenergy.org/presentations/CGPL.pdfWater Source and Utilization at CGPL Water Requirement Plant Water Usage Water Requirement

Thank You!Website: www.tatapower.com

Email Id: [email protected]

[email protected]

Disclaimer: The contents of this presentation are private & confidential. Please do not duplicate, circulate or distribute without prior permission.

Private and Confidential |