water treatment plant 2016 summary report · perth water treatment plant summary report 2016 page 8...

20
Water Treatment Plant 2016 Summary Report

Upload: others

Post on 09-Mar-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Water Treatment Plant

2016 Summary Report

Page 2: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Table of Contents Overview .................................................................................................................................... 4

SECTION 1 – FAILURE TO MEET REQUIREMENTS ................................................................ 6

1.1 Adverse Water Quality Incident reports (Drinking Water System) ...................................... 6

1.2 Ministry Orders ............................................................................................................................ 7

1.2.1. Drinking Water System ............................................................................................... 7

1.2.2. Water Treatment Subsystem ..................................................................................... 7

1.2.3. Water Distribution Subsystem ................................................................................... 7

1.3 Additional Known Failures to Meet Requirements ................................................................. 7

1.3.1. Drinking Water System ............................................................................................... 8

1.3.2. Water Treatment Subsystem ..................................................................................... 8

1.3.3 Water Distribution Subsystem ................................................................................... 8

1.4 Additional concerns regarding meeting requirements ........................................................... 8

1.4.1. Drinking Water System ............................................................................................... 8

1.4.2. Water Treatment Subsystem ..................................................................................... 9

1.4.3. Water Distribution Subsystem ................................................................................... 9

SECTION 2 – SUMMARY OF PLANT FLOWS ........................................................................ 10

2.1 Raw Water (Source water) ...................................................................................................... 10

2.1.2 Maximum Raw Water Flow: ..................................................................................... 10

2.2 Service Water (Treated Discharged Water) ......................................................................... 10

2.2.1 Average Daily Service Water Flow: ........................................................................ 10

2.2.3 Service Water Discharge: ........................................................................................ 10

2.3 Plant process water .................................................................................................................. 10

2.3.1 Backwash water to Waste: ....................................................................................... 11

SECTION 3 – SUMMARY OF DRINKING WATER SYSTEM ABILITIES ................................. 12

3.1. Water Treatment Ability ........................................................................................................... 12

3.1.1. Disinfection ability ...................................................................................................... 12

3.1.2. Chlorine Dioxide use ................................................................................................. 12

3.1.3. pH adjustment (use of lime) ..................................................................................... 13

3.1.4. Coagulation abilities .................................................................................................. 13

3.1.5. Pumping capacity ...................................................................................................... 13

3.1.6. Computer System ...................................................................................................... 13

Page 3: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

3.2. Water Taking Ability .................................................................................................................. 14

3.3. Water Storage Ability ................................................................................................................ 14

3.4. Water Treatment and Distribution Personnel ....................................................................... 14

Table 1 – Summary of Flows January 1, 2016 to December 31, 2016 ....................................... 16

Table 2 – Historical Average Daily Service Water Flow (m3) ....................................................... 17

Table 3 - 2016 Raw Water Taking Perth Water Treatment Plant ................................................. 18

Page 4: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Perth Water Treatment Plant Summary Report 2016 Page 4

2016 Summary Report

Overview

The Town of Perth Drinking Water System (DWS), categorized as a large municipal residential system, is comprised of two components:

1. Class III Water Treatment Subsystem, 2. Class I Water Distribution Subsystem.

This report is prepared in accordance to the Drinking Water Systems Regulation 170/03, Schedule 22 of the Safe Drinking Water Act, (SDWA), 2002.

It will cover a period for the preceding calendar year, January 01 to December 31, 2016.

A Ministry of Environment inspection of both facilities was conducted between December 14 and 22, 2016 for the 2016 reporting year. The report is not available to date.

The completion and presentation of this report will also fulfill the requirement for a compliance report to be produced in accordance applicable regulations.

Supplemental information sources would include, but not limited to, The Town of Perth Water Treatment Plant’s year end documentation.

Section 1 contains, any known failure to meet, or any priority concerns that might lead to failures

to meet, the requirements of: the SDWA itself, the SDWA regulations and associated MOE publications, the system’s Certificate of Approval, any orders duration of the failure, and measures taken to correct the failure

Section 2 contains, A summary of quantities and flow rates of water taken from the Tay River, in

addition to water production and process wastewater generation.

Page 5: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Perth Water Treatment Plant Summary Report 2016 Page 5

Section 3 contains, an overview summary of the DWS water treatment abilities a summary of the DWS water taking ability a summary of the DWS water storage ability a summary of the DWS operating personnel

Page 6: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Perth Water Treatment Plant Summary Report 2016 Page 6

SECTION 1 – FAILURE TO MEET REQUIREMENTS

1.1 Adverse Water Quality Incident reports (Drinking Water System)

On Apr 29, 2016 an AWQI was generated when a Distribution Water Sample test

result exceeded the allowable concentration. The test was conducted through a

voluntary program that the municipality participates in with the MOECC. The

parameter is regulated through Sched 24 of OReg 169 and therefore was still

considered adverse in spite of being part of a voluntary program. The proper steps

for reporting and Adverse were followed, together with consultation with local

MOECC Inspector. Re-sampling and testing was completed, and subsequent test

results were within allowable limits. It was determined that the exceedance may

have resulted from the specific sampling site (washroom tap) and the location for

future samples was changed to prevent a re-occurrence. Typically a Sched 24

exceedance, would then require the municipality to increase its sampling frequency,

however, discussion with MOECC Inspector resulted in that requirement being

waived. Notice of Issue Resolution was submitted on May 5 2016

On Oct 3 2016, during a valve replacement initiative by staff and contractor, a

portion of the storage reservoir was contaminated with hydraulic oil. The small

chamber where the spill occurred was isolated and extensively cleaned by staff and

spill professionals. Again, proper AWQI notification was made as well as

consultation with MOECC and MOH, due to the nature of the incident. Extensive

follow up sampling of various parameters – mainly hydrocarbons) was completed

and all results were satisfactory. Notice of Issue Resolution was submitted on Oct

5 2016.

Page 7: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Perth Water Treatment Plant Summary Report 2016 Page 7

Incident

Date Parameter Result

Regulatory

Limit

Corrective

Action

Corrective

Action Date

Apr 29

2016

1,4

Dichlorobe

nzene

6.1

ug/L

5.0

ug/L

Re-sample

and test

(upstream,

downstream) May 5 2016

Oct 3

2016

Treated

Water

Storage

contaminati

on

Various

levels of

hydrocar

bons n/a

Isolated,

cleaned, re-

sampled Oct 5 2016

1.2 Ministry Orders

1.2.1. Drinking Water System No MOE orders issued.

1.2.2. Water Treatment Subsystem No MOE orders issued.

1.2.3. Water Distribution Subsystem No MOE orders issued.

1.3 Additional Known Failures to Meet Requirements

Page 8: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Perth Water Treatment Plant Summary Report 2016 Page 8

At the time of compilation of this summary report the MOE’s inspection report for

this period had not yet been received. There were zero non- compliance items in

the 2015 Inspection Report, resulting in a 100% Inspection Rating for the

municipality. A summary of Inspection recommendations and best practices is

included in Appendix 1.

1.3.1. Drinking Water System No known failures to meet requirements.

1.3.2. Water Treatment Subsystem

Requirement

failure

Requirement

location

Duration

of

failure

Any corrective

action taken

none

1.3.3 Water Distribution Subsystem

Requirement

failure

Requirement

location

Duration

of failure

Any

corrective

action taken

none

1.4 Additional concerns regarding meeting requirements

1.4.1. Drinking Water System

Issue Any corrective action

taken

none

Page 9: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Perth Water Treatment Plant Summary Report 2016 Page 9

1.4.2. Water Treatment Subsystem

Issue Any corrective action taken or

being proposed

Process Waste /

Residue Management

In 2015 the, Phase 1, of the process

waste treatment system was

completed and implemented through

the Geotube System. This included

treatment of the settled solids from

the former siphon discharge.

Phase 2 development is continuing

and includes treatment of all other

sources of water to the waste

channel.

1.4.3. Water Distribution Subsystem

Issue Any corrective action taken or

being proposed

none

Page 10: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Perth Water Treatment Plant Summary Report 2016 Page 10

SECTION 2 – SUMMARY OF PLANT FLOWS

2.1 Raw Water (Source water) When reviewing the 2016 raw water flows (from source), and the allowable water

taking ability in accordance with the current Permit to Take Water (PTTW), of 9,090

m3: See Table 1 at end of document. Table 3 at end of document shows a

complete listing of Daily Raw Water Taking in 2016.

2.1.1. Average Daily Raw Water Flow:

The daily average raw water flow was 2,817 m³ in 2016, or approximately 31% of the PTTW, The daily average in 2015 was 3,214 m³ showing continued consistent water demand over recent years.

2.1.2 Maximum Raw Water Flow: The maximum raw water flow in any given day in 2016 was 5,396 m³ which is 59.4% of the PTTW maximum.

2.2 Service Water (Treated Discharged Water) Below are salient points regarding 2016 service water flows (treated water to the

distribution system)

2.2.1 Average Daily Service Water Flow: The daily average service water flow was 2,656 m³ in 2016. This represents a significant decrease of 401 cubic metres or 13% from 2015 (3,057 m³ was the average in 2015).

2.2.3 Service Water Discharge: In 2016, a total of 972,383 m3 service water was discharged to the Town. Decreased from 2015 (1,115,473 m³)

2.3 Plant process water The 2016 year continued to see a significant change to the management of process waste water at the facility. The plant was built to direct all sources of process waste (settled sludge, backwash water) to a sub-grade channel that conveyed waste back to the source, at a deposit point downstream of the intake. This issue had been identified on previous MOECC reports and after working with the Ministry and various consultants a system was installed to further treat this process waste in 2015. This system receives wasted sludge to a mixing tank where a polymer is added to form ‘floc’ and is then pumped to a ‘Geobag’ which allows for dewatering and containment of the sludge. A network of bags allows for rotational use and disposal of dried sludge at the Town’s landfill site. The project was broken into two phases. Phase 1 (settled sludge from coagulation/settling process), was completed and implemented in March of 2015. The Drinking Water License was amended to regulate the maximum

Page 11: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Perth Water Treatment Plant Summary Report 2016 Page 11

allowable concentration of Total Suspended Solids from the system. The second phase of implementation will address all other sources of waste with the backwash water being the largest volume. Completion had been mandated for Dec 31 2016, however this was extended to July 2017. The rationale behind the extension was to allow the municipality to upgrade the filters and associated backwashing methods, with a positive displacement air scour system, which in turn, has greatly reduced backwash waste volumes, but still maintained backwash effectiveness.

2.3.1 Waste Volumes In the 2016 calendar year, a total volume of 12,267 m3 has been directed to the residue treatment system and thereby lessening the amount of solids deposited back to the river.

Page 12: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Perth Water Treatment Plant Summary Report 2016 Page 12

SECTION 3 – SUMMARY OF DRINKING WATER SYSTEM ABILITIES

3.1. Water Treatment Ability The Perth water treatment plant continues to maintain a strong position in

supporting its ability to provide a reliable supply of safe, clean drinking water to its

community. Funding reserves are maintained in case of an operational emergency

or unexpected major breakdown.

3.1.1. Disinfection ability Disinfection of the drinking water is ultimately achieved through two points of

application – primary disinfection – dosed as water enters the clear well and

secondary disinfection – dosed at the treated water discharge point. Both of

these critical treatment processes have redundancy in the pumps as well as

the dosage lines. It should be noted that many other factors contribute to the

overall disinfection process, including pre-treatment, coagulation and pH

control. Varying raw water conditions require operators to adjust and control

chemical dosages to meet regulations in a cost effective manner. Of most

importance is the daily CT calculation. The CT value is the product of the

concentration of a disinfectant and the contact time with the water being

disinfected.

As mentioned in previous reports the proximity and position of the sodium

hypochlorite and coagulant tanks is a potential safety hazard. Accidental

contact between the two chemicals produces a highly exothermic reaction

releasing chlorine gas. The building analysis of 2011 reviewed chemical

storage at the plant and determined that long-term safe chemical handling

should be addressed. Tender No. PS-13-10 was circulated in November

2013 and listed the safety concerns that need to be addressed in the

chemical room. Some ventilation issues were addressed, however,

separated chemical storage was not. Spill containment was installed in the

acid room in 2013. This item has been noted on the annual MOE Inspection

reports for many years and continues to be an area of concern, especially as

‘unmanned’ automated operations are on the horizon.

3.1.2. Chlorine Dioxide use Chlorine dioxide continues to be generated seasonally on site and plays an important role in achieving disinfection while mitigating the formation of chlorine disinfection by-products such as THM’s and HAA’s (see 3.1.1 above). These disinfection by-products are suspected carcinogens and are commonly formed when high doses of chlorine gas or sodium hypochlorite react with raw water heavily laden with organic matter. Chlorine dioxide use is uncommon among water treatment facilities due to chemical cost however the advantage of a “cleaner” disinfection process with less by-product formation is worth the extra cost during extreme seasonal water quality

Page 13: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Perth Water Treatment Plant Summary Report 2016 Page 13

challenges seen in Perth. As well, the renewal of the municipal Drinking Water License saw the additional sampling requirement of Chlorates and Chlorites added as a quarterly sampling requirement.

3.1.3. pH adjustment (use of lime) Following the coagulation and disinfection processes, where the pH of the water is lowered through the addition of chemicals, hydrated lime needs to be mixed in the clearwell to return the pH to a range of 7.1 to 7.3. This range is desired in an effort to ensure the water within the distribution system is close to neutral and thereby not aggressive in the deterioration of the distribution network as well as homeowner plumbing and fixtures. The Town of Perth qualified for relief from the legislated lead sampling program in 2011 as a result of few exceedances of the lead maximum allowable concentration.

3.1.4. Coagulation abilities The water treatment plant employs a high-end coagulant called PAX XL-6 to

aid in the flocculation and sedimentation of suspended solids in water prior

to filtration. Although more expensive than conventional coagulants such as

aluminum sulphate, product usage is reduced and outperforms other less

expensive chemicals at certain critical temperature ranges. Winter months

and the associated cold water temperature and density present the most

difficult conditions for the coagulant to settle the solids. Our new licence

allows for pH enhancement (use of HCl) in situations of high pH or alkalinity

raw water conditions that make floc formation difficult.

3.1.5. Pumping capacity The total volume of treated water pumped from the WTP in 2016 was

972,383 m³. This total has decreased from 2015, but generally represents

the average from the past 5 years. Continued reconstruction, maintenance,

leak repairs, decreased industry usage, and public awareness of water

conservation are all attributed to considerably less water demand. (2005

treated water pumped – 1,583,302 m³)

3.1.6. Computer System A new SCADA (Supervisory Control and Data Acquisition) system was

completed in 2014; however some modifications and additions to the

programming are still required. With the objective of low lift automation,

numerous pieces of equipment, chemical pumps and analyzers are still

being added to the infrastructure and controls for these items must then be

programmed into the SCADA system. The existing hydro service (and

electrical capability within the plant) is very near its maximum capability and

should be addressed in the 2016 year to continue to allow for large

Page 14: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Perth Water Treatment Plant Summary Report 2016 Page 14

consumption items such as filter blower and Residue management phase 2

equipment.

3.2. Water Taking Ability The WTP is operating well within the PTTW limits. The Permit To Take Water

(#5464-6MHL84) authorizes the municipality to take water with maximum volumes

regulated for both litres/min as well as litres per day. This Permit was renewed in

the 2016 year and wil expire again in 2026. Raw Water pump capacities

determine these figures (6,360 l/min and 9,092,000 l/day). In 2016, the maximum

day total was 5,396,000 litres, which occurred during a four day stretch of vigorous

spring flushing of the distribution network. More typical day averages are around

2,800,000 litres per day. This represents about 2/3 of the water plants rated

capacity. Staff routinely inspects the inlet at the golf course for debris, blockages or

structural damage. The 24” inlet isolation valve, located at the rear of the plant was

replaced in 2015. This valve had been a necessary repair for a few years. It was

installed by ODS Marine and equipped with a floor level actuator that will allow

operators to close and protect the plant, in case of a contaminated raw water

supply.

3.3. Water Storage Ability The clear well and reservoir were cleaned and inspected in 2015. While on site, the

contracted dive crew also pressure washed and inspected the underwater valve

network to establish more information and potential pricing for replacing these

valves. Initial work was started to replace one of these valves, however, following

an accidental contamination of the reservoir, the project has been delayed to allow

for further process evaluation. The elevated tank had an inspection completed in

October of 2016, with proposals being given for tank level monitoring upgrades.

Regular maintenance and emergency repairs occurred within the distribution

system including mains, services and hydrants.

3.4. Water Treatment and Distribution Personnel The WTP is a Class III facility and is staffed 16 hours a day, from Monday to Friday,

and Saturday/Sunday shifts are 12 hrs. Shifts and duties are rotated amongst three

full time operators and a Lead Hand, who covers shifts during times of vacation,

illness or absenteeism. The Lead Hand has WTP Level II license, one shift operator

has a level II licence and two operators have a level III licence.

The Distribution system is a Class 1 facility and is maintained by a Lead Hand and

four operators, who rotate through other departments within the organization. The

Lead Hand possesses a level III license in distribution and supply. All four

operators have level II licenses.

Page 15: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Perth Water Treatment Plant Summary Report 2016 Page 15

18 January 2016

Graham Patterson Lead Hand – WT and WWT

Page 16: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Perth Water Treatment Plant Summary Report 2016 Page 16

Table 1 – Summary of Flows January 1, 2016 to December 31, 2016 Perth Water Treatment Plant

PTTW maximum allowable flow rate: 9,090 m3/ day

Raw water (m3)

Discharge (Service)

Water (m3)

Month Monthly Daily

Average Flow

Monthly

Total

Flow

Monthly

Daily

Average

Flow

Monthly

Total

Flow

January 2,655 82,296 2,502 77,560

February 2,729 79,137 2,571 74,545

March 2,853 88,438 2,455 76,091

April 2,849 85,467 2,471 74,132

May 3,044 94,369 2,931 90,871

June 3,093 92,781 2,996 89,874

July 2,988 92,640 2,954 91,585

August 3,086 95,651 3,024 93,752

September 2,757 82,717 2,694 80,829

October 2,729 84,595 2,603 80,697

November 2,553 76,598 2,372 71,141

December 2,473 76,677 2,300 71,306

Year Average 2,817 85,947 2,656 81,032

Year Total 1,031,366 972,383

Page 17: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Perth Water Treatment Plant Summary Report 2016 Page 17

Table 2 – Historical Average Daily Service Water Flow (m³)

Perth Water Treatment Plant

2016 2015 2014 2013 2012

JAN. 2,502 2,872 3,211 2,795 2,521,

FEB. 2,571 3,290 2,980 3,504 2,708

MARCH 2,455 3,298 3,053 3,664 2,741

APRIL 2,471 3,157 3,247 3,565 2,698

MAY 2,931 3,392 3,003 3,187 3,098

JUNE 2,996 3,002 3,285 2,845 3,109

JULY 2,954 3,048 3,292 3,034 3,441

AUG. 3,024 3,015 3,099 3,076 3,137

SEPT. 2,694 2,979 2,992 2,839 2,962

OCT. 2,603 2,998 2,901 2,894 2,839

NOV. 2,372 2,852 2,693 2,916 2,658

DEC. 2,300 2,784 2,642 3,134 2,578

MAXIMUM 3,024 3,392 3,292 3,644 2,917

MINIMUM 2,300 2,784 2,642 2,795 2,155

AVERAGE 2,656 3,057 3,033 3,119 2,892

Page 18: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Perth Water Treatment Plant Summary Report 2016 Page 18

Table 3 - 2016 Raw Water Taking Perth Water Treatment Plant - Appendix 1

2016Day January February March April May June July August September October November December

1 2,149,000 3,074,000 2,757,000 2,531,000 2,512,000 3,471,000 2,432,000 3,157,000 3,040,000 2,251,000 2,496,000 2,650,000

2 2,179,000 2,741,000 2,695,000 2,011,000 4,683,000 2,816,000 2,182,000 3,180,000 2,899,000 2,450,000 3,289,000 2,596,000

3 2,101,000 2,929,000 3,168,000 2,839,000 5,396,000 3,279,000 2,308,000 3,684,000 2,389,000 2,776,000 2,297,000 2,342,000

4 2,785,000 2,764,000 2,416,000 3,237,000 4,222,000 2,781,000 3,404,000 3,868,000 2,584,000 2,655,000 2,736,000 2,284,000

5 2,501,000 3,260,000 2,839,000 2,436,000 3,298,000 2,102,000 3,024,000 3,432,000 3,009,000 2,603,000 2,284,000 2,805,000

6 2,543,000 2,700,000 3,284,000 2,496,000 2,858,000 3,056,000 3,642,000 2,395,000 2,881,000 2,535,000 2,297,000 2,552,000

7 2,624,000 2,653,000 2,983,000 2,720,000 2,178,000 3,078,000 2,911,000 2,536,000 3,083,000 2,498,000 2,831,000 2,531,000

8 3,158,000 2,798,000 3,455,000 2,716,000 2,162,000 2,656,000 4,061,000 3,624,000 2,579,000 2,248,000 2,722,000 2,598,000

9 2,074,000 2,746,000 3,034,000 2,112,000 2,817,000 2,702,000 2,587,000 3,696,000 3,258,000 2,243,000 2,787,000 2,469,000

10 2,303,000 2,950,000 3,294,000 2,480,000 2,547,000 3,032,000 2,461,000 3,429,000 2,501,000 2,666,000 2,054,000 2,216,000

11 2,626,000 2,765,000 3,519,000 2,584,000 2,821,000 2,177,000 3,241,000 3,578,000 2,559,000 4,184,000 2,586,000 2,263,000

12 2,919,000 3,047,000 5,231,000 3,074,000 2,662,000 2,197,000 3,542,000 3,473,000 3,111,000 4,155,000 2,248,000 3,650,000

13 2,580,000 2,530,000 2,813,000 3,590,000 2,793,000 2,962,000 3,560,000 2,348,000 2,734,000 4,201,000 2,373,000 2,320,000

14 2,758,000 2,542,000 3,265,000 2,947,000 1,878,000 2,900,000 3,083,000 2,352,000 2,681,000 3,581,000 3,063,000 2,818,000

15 2,939,000 2,768,000 3,012,000 2,556,000 2,416,000 3,187,000 3,118,000 3,460,000 2,654,000 2,395,000 2,300,000 2,415,000

16 2,726,000 2,311,000 2,573,000 2,554,000 2,173,000 3,932,000 2,532,000 3,286,000 2,829,000 2,400,000 2,633,000 2,675,000

17 2,401,000 2,592,000 2,782,000 2,623,000 2,949,000 3,444,000 2,569,000 3,360,000 2,509,000 2,373,000 2,841,000 2,375,000

18 2,623,000 2,741,000 2,525,000 2,949,000 3,189,000 2,940,000 3,066,000 2,681,000 2,414,000 2,198,000 2,630,000 2,271,000

19 2,953,000 3,292,000 2,306,000 3,751,000 2,775,000 3,020,000 3,258,000 3,022,000 2,949,000 2,837,000 2,121,000 2,692,000

20 2,632,000 2,534,000 2,252,000 3,675,000 3,464,000 3,844,000 3,044,000 2,788,000 2,891,000 3,143,000 2,227,000 2,648,000

21 2,862,000 2,167,000 2,475,000 3,595,000 2,443,000 3,435,000 3,200,000 2,500,000 2,891,000 2,761,000 2,588,000 2,383,000

22 3,171,000 2,776,000 3,234,000 3,363,000 2,603,000 3,882,000 3,262,000 3,059,000 3,090,000 2,272,000 2,558,000 2,466,000

23 2,562,000 2,778,000 2,452,000 2,697,000 2,959,000 3,418,000 2,825,000 3,031,000 2,675,000 2,551,000 2,536,000 2,313,000

24 2,430,000 2,412,000 2,651,000 2,905,000 3,597,000 3,510,000 2,893,000 2,890,000 2,440,000 2,882,000 2,630,000 2,690,000

25 3,040,000 2,479,000 2,236,000 3,285,000 3,525,000 3,241,000 2,853,000 3,136,000 2,230,000 2,678,000 3,026,000 1,930,000

26 2,835,000 2,966,000 2,160,000 3,119,000 3,082,000 3,056,000 3,124,000 3,211,000 2,689,000 2,570,000 2,119,000 2,285,000

27 2,719,000 2,622,000 2,196,000 2,709,000 3,128,000 2,943,000 3,011,000 2,753,000 2,841,000 2,444,000 2,341,000 2,299,000

28 2,849,000 2,392,000 2,753,000 3,024,000 3,494,000 3,369,000 2,957,000 2,527,000 3,062,000 2,447,000 2,863,000 2,316,000

29 3,183,000 2,808,000 2,476,000 2,620,000 2,942,000 2,979,000 3,049,000 3,274,000 2,569,000 2,391,000 2,481,000 2,234,000

30 2,487,000 2,971,000 2,269,000 3,519,000 3,372,000 2,755,000 3,100,000 2,676,000 2,305,000 2,641,000 2,359,000

31 2,584,000 2,631,000 3,284,000 2,686,000 2,821,000 2,902,000 2,232,000

Minimum 2,074,000 2,167,000 2,160,000 2,011,000 1,878,000 2,102,000 2,182,000 2,348,000 2,230,000 2,198,000 2,054,000 1,930,000

Maximum 3,183,000 3,292,000 5,231,000 3,751,000 5,396,000 3,932,000 4,061,000 3,868,000 3,258,000 4,201,000 3,289,000 3,650,000

Average 2,654,710 2,728,862 2,852,839 2,848,900 3,044,161 3,092,700 2,988,387 3,085,516 2,757,233 2,728,871 2,553,267 2,473,452

Monthly

total 82,296,000 79,137,000 88,438,000 85,467,000 94,369,000 92,781,000 92,640,000 95,651,000 82,717,000 84,595,000 76,598,000 76,677,000

Running

Year total 82,296,000 161,433,000 249,871,000 335,338,000 429,707,000 522,488,000 615,128,000 710,779,000 793,496,000 878,091,000 954,689,000 1,031,366,000

Page 19: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Perth Water Treatment Plant Summary Report 2016 Page 19

Page 20: Water Treatment Plant 2016 Summary Report · Perth Water Treatment Plant Summary Report 2016 Page 8 At the time of compilation of this summary report the MOE’s inspection report

Perth Water Treatment Plant Summary Report 2016 Page 20