Web Server Migration April 30 th , 2004 Presented by Geoff Strom Information Technology Services

Upload: rhonda-gates

Post on 31-Dec-2015

59 views

Category:

Documents


6 download

DESCRIPTION

Web Server Migration. April 30 th , 2004 Presented by Geoff Strom Information Technology Services. Topics. Reasons for Migration User and Web Site Changes Impact on Services Hosting Structure Directory Layout System Administration Schedule. Reasons for Migration. Concerns. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Web Server Migration

Web Server Migration

April 30th, 2004Presented by Geoff Strom

Information Technology Services

Page 2: Web Server Migration

Topics

• Reasons for Migration

• User and Web Site Changes

• Impact on Services

• Hosting Structure

• Directory Layout

• System Administration

• Schedule

Page 3: Web Server Migration

Reasons for Migration

Page 4: Web Server Migration

Concerns

• WXA is unsupported at both the hardware and software level

• Administration is minimal and done manually

• Reliability and security are concerns

Page 5: Web Server Migration

Solutions

• Future growth in web service offerings depends on an upgraded, secure, and manageable platform

• Supported hardware is available (FXWEB1)

Page 6: Web Server Migration

User Changes

Page 7: Web Server Migration

Accounts

• Will be named

• Username same as SLU email

• Initial quota will be 50MB

• Will be verified nightly with system information

• Accounts no longer in the system will be disabled immediately, pending removal

Page 8: Web Server Migration

Access

• SFTP

• SSH on request

• No more insecure Telnet or FTP

• Software upgrades will be necessary

• Web based "control panel" containing account information and tools

Page 9: Web Server Migration

Web Site Changes

Page 10: Web Server Migration

Owner

• Single defined owner

• Will be able to assign group members

• Web based "control panel" containing site information and tools

• MySQL database server on request

• PHP on request

Page 11: Web Server Migration

Groups

• Named after the web site

• Members have full read/write permissions

• Only members will have access

• Initial quota will be 100MB

Page 12: Web Server Migration

Impact on Services

Page 13: Web Server Migration

Services that will be migrated

• All current web sites

• phpMyAdmin (slumyadmin)

• phpEasySurvey (EasySurvey)

• Homefree (pages.slu.edu)

Page 14: Web Server Migration

Services that will not be migrated

• ServletExec

• TestPilot

• UltimateBB

Page 15: Web Server Migration

By The Numbers

• Approximately 300 user accounts will be migrated

• Approximately 400 web sites will be migrated

Page 16: Web Server Migration

Hosting Structure Changes

Page 17: Web Server Migration

Current Hosting Structure

• Three kinds of web sites– Domains

• http://www.slucare.edu/

– Virtual Hosts• http://medschool.slu.edu/

– Everybody else• http://www.slu.edu/colleges/AS/

• http://www.slu.edu/centers/heartland/

Page 18: Web Server Migration

New Hosting Structure

• Two kinds of web sites– Domains

• http://www.slucare.edu/

– Virtual Hosts• http://medschool.slu.edu/

• All existing sites that are not already Domains or Virtual Hosts will be converted to Virtual Hosts

Page 19: Web Server Migration

Domains

• Available via traditional addresses:– http://www.slucare.edu/

Page 20: Web Server Migration

Virtual Hosts

• Available via traditional addresses:– http://medschool.slu.edu/

• Two alternative addresses will also be available:– http://www.medschool.slu.edu/– http://www.slu.edu/medschool/

Page 21: Web Server Migration

Aliases

• Redirects from the original address

• http://www.slu.edu/colleges/medschool/ would redirect to http://medschool.slu.edu/

• Make transition easier but should expire

• All converted web sites will be granted a temporary Alias to ease the transition

Page 22: Web Server Migration

Directory Layout

Page 23: Web Server Migration

Current Directory Layout

Page 24: Web Server Migration

New Directory Layout

Page 25: Web Server Migration

New Directory Layout

• Home directories will have two sub directories:– files– public_html

• Unable to modify home directory content

• Access to web sites via symbolic links

Page 26: Web Server Migration

System Administration

Page 27: Web Server Migration

Current System Administration

• Done manually

• Small number of people with the skill and access to make changes

Page 28: Web Server Migration

New System Administration

• Stored in a database

• Easy to use front end

• Increased number of administrators

• Configuration files rebuilt automatically

Page 29: Web Server Migration

Schedule

Page 30: Web Server Migration

Schedule

March – May Develop server, tools, and policies

May 10th Announce migration plan and new policies

May 25th Migrate WXA user accountsNew user accounts will be on new system

June 1st Start of web site migrationNew web sites will be on new system

June – August Rolling web site migration(12 weeks for 400 sites = 34 sites per week)

August 23rd End of migration

Page 31: Web Server Migration

Questions?