dreamfoundationon.weebly.com€¦ · web viewdistribution system serve as the link from the...
TRANSCRIPT
1
CHAPTER ONE
INTRODUCTION
2
1.1 Introduction
Electric power distribution only became necessary in the 1880 when electricity started being
generated at power stations. Before that electricity was usually generated where it was used. The
first power distribution systems installed in European and US cites were used to supply
lighting: arc lighting running on very high voltage (usually higher than 3000 volt) alternating
current (AC) or direct current (DC), and incandescent lighting running on low voltage (100 volt)
direct current. Both were supplanting gas lighting systems, with arc lighting taking over large
area/street lighting, and incandescent lighting replacing gas for business and residential lighting.
Electric power distribution is the final stage in the delivery of electric power; it carries electricity
from the transmission system to individual consumers. Distribution substations connect to the
transmission system and lower the transmission voltage to medium voltage ranging between
2 kV and 35 kV with the use of transformers. Primary distribution lines carry this medium
voltage power to distribution transformers located near the customer's premises. Distribution
transformers again lower the voltage to the utilization voltage of household appliances and
typically feed several customers through secondary distribution lines at this voltage. Commercial
and residential customers are connected to the secondary distribution lines through service drops.
Customers demanding a much larger amount of power may be connected directly to the primary
distribution level or the subtransmission level.
1.2 Bangladesh Power Sector at a Glance
Bangladesh's energy infrastructure is quite small, insufficient and poorly managed. The
per capita energy consumption in Bangladesh is one of the lowest (321 kWh) in the world.
Noncommercial energy sources, such as wood fuel, animal waste, and crop residues, are
estimated to account for over half of the country's energy consumption. Bangladesh has small
reserves of oil and coal, but very large natural gas resources. Commercial energy consumption is
mostly natural gas (around 66%), followed by oil, hydropower and coal.
Electricity is the major source of power for most of the country's economic activities.
Bangladesh's installed electric generation capacity was 10289 MW in January, 2014; only three-
3
fourth of which is considered to be ‘available’. Only 62% of the population has access to
electricity with a per capita availability of 321 kWh per annum. Problems in the Bangladesh's
electric power sector include corruption in administration, high system losses, and delays in
completion of new plants, low plant efficiency, erratic power supply, electricity theft, blackouts,
and shortages of funds for power plant maintenance. Overall, the country's generation plants
have been unable to meet system demand over the past decade.
Power Sector at a glance-2016
Electricity Growth: 12 %
Generation Capacity (including captive): 14,077 MW (Sep. 2016)
Total Consumers: 19.8 Million (Sep. 2016)
Transmission Line: 9,695 Ckt. km
Distribution Line: 3,41,000 km
Distribution Loss: 11.36%
Per Capita Generation: 371 kWh
Access to Electricity: 74%
Parameters 2015 (At present) 2021 2030
Consumers (Mill.) 17.8 24.2 36.3
Line Constr (Thou KM) 341 481 641
Sub-Station (MVA) 24,720 35,700 66,500
Peak Demand (MW) 8,177 18,800 33,700
Distribution System Loss 11.36% 9.50% 8.70%
Table 1.1-Power Distribution: Future Plan
1.2.1 Generation Expansion Plan Up to 2021
Based on the primary fuel supply ability and Government`s limited ability to finance power
generation projects, an aggressive midterm generation expansion plan and a long term generation
plan was prepared to meet the growing demand of electricity to cope with accelerated economic
4
growth under the present govt. Revised generation plan prepared in 2015 targeting about 17,300
MW generation additions from 2015 to 2021 which is proved in the table below:
Year 2015
MW
2016
MW
2017
MW
2018
MW
2019
MW
2020
MW
2021
MW
Total
Public 848 885 202 1397 1611 1000 1900 9661
Private 1110 328 130 630 1152 1811 612 5773
Power
Import
100 500 1300 1900
Total 1958 1313 2027 2027 2763 2811 3812 17334
Table 1.2-Year wise generation projects to be completed (From 2015 to 2021)
1.2.2 Annual Development Program for BPDB’s Own Distribution Projects
A total of 9 distribution projects were undertaken in the Revised Annual Development Program
(RADP) in the FY14-FY15. Original Allocation, Revised Allocation and Expenditure incurred in
the FY14-15 are shown in the flowing table
Sub-sector Original ADP
FY14-15
RADP
FY14-15
Expenditure Incurred
FY14-15
Local Foreig
n
Total Local Foreig
n
Total Local Foreig
n
Total
Distributio
n
34,04
1
27,410 61,45
1
27,59
2
17,535 45,12
7
27,37
7
17,599 44,97
6
Table 1.3- FY14-15of ADP, RADP and EI
1.2.3 Future Distribution Project Up to 2018
From the view point of continuous improvement in retail sales performance and
consumer’s service and satisfaction, BPDB has under taken the following projects
that are at the various stages of approval and procurement process:
5
Sl.
no
Name of the Project
Project costs Year of
Complit
ion
Cumu
Progres
s (%)Local
(lakh tk)
Foreign
(lakh tk)
Total
(lakh tk)
1
10-Town power system dev.
Project (Rajshahai, Pabna,
Dinajpur, Bogora, Joypurhat,
Gaibandha, Nilfamari,
Shirajgonj, Thakurgoan &
Rangpur)
23,788 26,901 50,689 June`20
16
97.22
2
Emergency rehabilitation &
expansion of urban areas
power dist. system under
Chittagong zone
17,862 17,862 Dec
2015
96.60
3
Emergency rehabilitation &
expansion of urban areas
power dist. system under
Rajshahi zone
11,001 11,001 Dec
2014
99.50
4
Prepayment metering project
for dist. southern zone, Ctg
(Phase-1)
13,736 13,736 Dec
2016
1.07
5
Greater Chittagong power
Distribution project, SCADA
rehabilitation
1,817 8,589 10,405
Dec
2015 87.00
6
Central zone power
distribution project,
Mymensing
43,113 1,00,831 1,43,943
June
2015 90.38
7
Chittagong hill-tracts power
distribution project,
Rangamati
18,079 18,079
Dec
2015 89.66
Solar Street-Lighting
programmed in city
Dec
6
8 corporation 8,002 23,659 31,661 2015 27.17
9
Pre-payment metering project
for distribution Comilla and
Mymensing zone
2,844 10,405 13,249
Dec
2015 0.74
10
Chittagong zone power
distribution system
development project,
Chittagong
1,09,970 1,09,970
June
2018 6.65
Table 1.4 Future project up to 2018
1.3 Distribution System
Distribution system serve as the link from the distribution substation to the customer. This
system provides the safe and reliable transfer of electric energy to various customers throughout
the service territory. Typical distribution system being as the medium-voltage three-phase
circuit, typically about 33-66 KV, and terminate at a lower secondary three or single-phase
voltage typically below 1 KV at the overhead and underground circuits in a mix of branching
laterals from the station to the various customers. The circuit is design around various condition
such as terrain, visual regulations, or customer requirements. These various branching lateral can
be operated in a radial configuration or as a looped configuration, where two or more parts of the
feeder are connected tougher usually through a normally open distribution switch. High- density
urban areas often connected in a complex distribution to customer to customer. Most three-phase
systems are for larger loads as commercial or industrial customer. The three-phase system are
often drawn as one line in the following distribution circuit drawing (Fig. 1.1)
7
Fig. 1.1 Power Distribution System
1.4 Transmission and Distribution Losses
We have seen the static of Bangladesh Power system as standard distribution losses are 11.96%
(2014-2015) and 12.03% (2013-2014). And 7.919% (2015) power system losses of WZPDCL.
8
Energy losses occur in the process of supplying electricity to consumers due to technical and
commercial losses. The technical losses are due to energy dissipated in the conductors and
equipment used for transmission, transformation, sub-transmission and distribution of power.
These technical losses are inherent in a system and can be reduced to an optimum level. The
losses can be further sub grouped depending upon the stage of power transformation &
transmission system as transmission losses (400KV/220KV/132KV/66KV) as Sub-transmission
losses (33KV/11KV) and Distribution losses (11KV/0.4KV). The commercial losses are caused
by pilferage, defective meters and errors in meter reading and in estimating unmetered supply of
energy.
1.5 Objective
The objective of this thesis are:
The Brief description distribution system.
Losses of distribution system.
System losses degeneration in innovative ways.
Preparing signal line diagram.
Estimation and implementation of 1 MW grid connected solar system
1.6 Research Methodology
We have been done our field work by visiting Sub-Station of West Zone Power Distribution
Company Limited and advised by executive Engineers of WZPDCL.
9
CHAPTER TWO
VOLTAGE LEVEL WISE POWER
SYSTEM LOSS OF WZPDCL,
SATKHIRA
10
2.1 Introduction
We have been that the static of Bangladesh Power system, the standard distribution losses are
11.41% (2014-2015) and 12.03% (2013-2014) and 7.91% (2015) power system losses of
WZPDCL.
2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-160
2
4
6
8
10
12
14
1614.3
12.311.66
12.311.38
11.9511.41
12.45
system loss 2008-2016
Fig. 2.1 Standard Distribution Loss
2.2 11KV Voltage Level Loss Calculation
2.2.1 Commercial Operation Statics
Sl.
No
Name
of
Feeder
Jul-2014 Syste
m
Loss
(%)
Aug-2014 Sep-2014
Energy (KWH) Energy (KWH)
Syste
m
Loss
(%)
Energy (KWH)
Syste
m
Loss
(%)
Import Sale Import Sale Import Sale
1 TOWN 1806907 1591291 11.93 1836153 1605207 12.58 1733708 1535548 11.43
11
2 KATIA 1245590 1039474 16.55 1260836 1062337 15.74 1221160 1011481 17.17
3 OLD
SATKHI
RA
1048489 799981.5 23.70 1057988 857357 18.96 951772 845974 11.12
4 TEXTILE 280516 276099 1.57 283949 277986 2.10 332860 326280 1.98
5 SULTANPU
R1194145 977106.5 18.18 1178385 1043688 11.43 1082900 966867 10.72
6 LABSHA 566022 510885 9.74 575851 519522 9.78 540362 492942 8.78
7 HOSPITA
L58083 56424 2.86 51933 49840 4.03 57545 56400 1.99
8Total
6199752 5251261 15.30 6245095 5415937 13.28 592030
7
523549
2
11.57
Sl.
No
Name
of
Feeder
Oct-2014 Syste
m
Loss
(%)
Nov-2014 Dec-2014
Energy (KWH) Energy (KWH)
Syste
m
Loss
(%)
Energy (KWH)
Syste
m
Loss
(%)
Import Sale Import Sale Import Sale
1 TOWN 1614471 1432131 11.29 1210503 1172577 3.13 1141555 1052867 7.77
2 KATIA 1140222 930083 18.43 816009 753697 7.64 779748 683202 12.38
3 OLD
SATKHI
RA
893738 734218.5 17.85 653344 591955 9.40 610006 522929 14.27
4 TEXTILE 284950 281093 1.35 323048 318862 1.30 294580 290102 1.52
5 SULTANPU
R1022804 904135.5 11.60 768612 703311 8.50 799153 720121 9.89
6 LABSHA 486910 459945 5.54 385517 369754 4.09 370323 353675 4.50
7 HOSPITA
L46384 45696 1.48 33717 33279 1.30 28858 28419 1.52
8 Total 5489480 4787302 12.79 4190750 3943435 5.90 402422 365131 9.27
12
3 5
Sl.
No
Name
of
Feeder
Jan-2015 Syste
m
Loss
(%)
Feb-2015 Mar-2015
Energy (KWH) Energy (KWH)
Syste
m
Loss
(%)
Energy (KWH)
Syste
m
Loss
(%)
Import Sale Import Sale Import Sale
1 TOWN 1211214 1127737 6.89 1176449 1139691 3.12 1773841 1546430 12.82
2 KATIA 820531 724822 11.66 810942 741846 8.52 1031823 863649 16.30
3 OLD
SATKHI
RA
672819 581199 13.62 680939 599309.5 11.99 887063.9 763757 13.90
4 TEXTILE 280498 272448 2.87 257602 249616 3.10 356298.7 348104 2.30
5 SULTANPU
R850021 762449.5 10.30 807217 741615.5 8.13 1055998 875620 17.08
6 LABSHA 392231 373949 4.66 394228 374534 5.00 529914.1 498861 5.86
7 HOSPITA
L29640 28789 2.87 30587 29639 3.10 41509 40554 2.30
8Total
4256954 3871393 9.06 4157964 3876251 6.78 567644
8
493697
5
13.03
Sl.
No
Name
of
Feeder
Apr-2015 Syste
m
Loss
(%)
May-2015 Jun-2015
Energy (KWH) Energy (KWH) Syste
m
Loss
(%)
Energy (KWH) Syste
m
Loss
(%)
Import Sale Import Sale Import Sale
1 TOWN 1715663.9 1556520 15.55 2365484 2041161 13.71 2163502 1868808 13.62
2 KATIA 1120229 946053 18.24 1462871 1121347 23.35 1386066. 1181977 14.72
13
3
3 OLD
SATKHI
RA
928484.94 759142.5 1.05 1183134 971628.5 17.881110449.
2986842 11.13
4TEXTILE 321400.5 318032 14.70 312394.4 308896 1.12
304481.1
5301071 1.12
5 SULTANPU
R1062062.3 905916.5 3.91 1398735 1144782 18.16
1273507.
81051100 17.46
6LABSHA 525642.93 505087 1.05 679322.3 646288 4.86
630217.7
7593391 5.84
7 HOSPITA
L44140 43678 15.55 56371 55740 1.12 53649 53048 1.12
8Total
5717624 5034429 11.95 745831 6289842 15.67 692187
2
603623
7
12.79
Sl.
No
Name
of
Feeder
Jul-2015 Syste
m
Loss
(%)
Aug-2015 Sep-2015
Energy (KWH) Energy (KWH)
Syste
m
Loss
(%)
Energy (KWH)
Syste
m
Loss
(%)
Import Sale Import Sale Import Sale
1 TOWN 1764507 1532964 13.12 1924266 1590592 17.34 1841861 1649214 10.46
2 KATIA 1276149 1057870 17.10 1362030 1080658 20.66 1329172 1078628 18.85
3 OLD
SATKHI
RA
1022486 871827 14.73 1120442 907440.5 19.01 1065478 926154 13.08
4 TEXTILE 285616 282418 1.12 350064 346178 1.11 313160 309402 1.20
5 SULTANPU
R1128083 914848 18.90 1203636 961780.5 20.09 1194286 1004693 15.88
6 LABSHA 563500 530217 5.91 605568 563806 6.90 585717 553069 5.57
7 HOSPITA
L45899 45386 1.12 54424 53820 1.11 50558 49951 1.20
8 Total 6086240 5235530 13.98 6620430 5504275 16.86 638023 557111 12.68
14
2 1
Sl.
No
Name
of
Feeder
Oct-2015 Syste
m
Loss
(%)
Nov-2015 Dec-2015
Energy (KWH) Energy (KWH)
Syste
m
Loss
(%)
Energy (KWH)
Syste
m
Loss
(%)
Import Sale Import Sale Import Sale
1 TOWN 1796839 1593617 11.31 1320254 1273008 3.58 1294772 1205206 6.92
2 KATIA 1266535 1052555 16.89 898377 823498 8.33 890066 786475 11.64
3 OLD
SATKHI
RA
1033110 892498 13.61 753783 684035 9.25 713447 623845 12.56
4 TEXTILE 333674 330437 0.97 306714 298402 2.71 259722 255826 1.50
5 SULTANPU
R1164807 990290 14.98 882676 765315 13.30 875262 767900 12.27
6 LABSHA 561671 530135 5.61 408032 389489 4.54 433132 414268 4.36
7 HOSPITA
L50504 50014 0.97 34945 33998 2.71 29476 29034 1.50
8Total
6207140 5439546 12.37 4604781 4267745 7.32 449587
6
408255
4
9.19
Sl.
No
Name
of
Feeder
Jan-2016 Syste
m
Loss
(%)
Feb-2016 Mar-2016
Energy (KWH) Energy (KWH)
Syste
m
Loss
(%)
Energy (KWH)
Syste
m
Loss
(%)
Import Sale Import Sale Import Sale
1 TOWN 1350543 1260055 6.70 1436151 1370561 4.57 1479562 1329551 10.14
15
5 3
2KATIA 909329 807059 11.25 989738 801458 19.02
1015642
68519288 16.12
3 OLD
SATKHI
RA
738159 648997 12.08 784998 656881 16.32 8268607 7093134 14.22
4 TEXTILE 254136 251188 1.16 260148 255283 1.87 2711504 2672494 1.44
5 SULTANPU
R914917 820616 10.31 952078 834151 12.39 9497260 8048521 15.25
6 LABSHA 430264 410979 4.48 452991 432855 4.45 4605859 4359929 5.34
7 HOSPITA
L26844 26533 1.16 29470 28919 1.87 366728 361634 1.39
8Total
4624191 4225427 8.62 4905574 4380108 10.71 504020
10
443505
13
12.01
Sl.
No
Name
of
Feeder
Apr-2016 Syste
m
Loss
(%)
May-2016 Jun-2016
Energy (KWH) Energy (KWH)
Syste
m
Loss
(%)
Energy (KWH)
Syste
m
Loss
(%)
Import Sale Import Sale Import Sale
1 TOWN 2066432 1820296 11.91 2213720 1969296 11.04 2457273 2165617 11.87
2 KATIA 1235030 1031087 16.51 1486075 1169791 21.28 1495432 1226964 17.95
3 OLD
SATKHI
RA
1036705 881457 14.98 1171501 1000980 14.56 1235907 1064997 13.83
4 TEXTILE 348270 343360 1.41 312162 307917 1.36 289713 285947 1.30
5 SULTANPU
R1181516 988927 16.30 1365547 1147334 15.98 1312294 1078005 17.85
6 LABSHA 564984 535111 5.29 660637 633433 4.12 670988 640661 4.52
7 HOSPITA 44608 43979 1.41 55782 55023 1.36 58018 57264 1.30
16
L
8Total
6477545 5644217 12.86 7265424 6283774 13.51 751962
5
651945
5
13.30
Table 2.1- Total Energy (watt) and System Loss
2.3 Improving the Existing Condition Of 11KV and .4KV Voltage
Level in innovative way
2.3.1 Line loss
Loss in conductors where lower size conductors are used. This causes temperature rise in
conductors which further aggravate the loss.
Loss in higher loaded phase wires due to unbalanced loading.
Losses due to current in neutral for cases of unbalanced where neutral wire of lower size
used (like 3/2 core cables, and neutral wires of size lower than phase wires).
Lessening of strands in multi-strand conductors like ASCR, AAC, AAA).
2.3.1.(a) Losses In Mid-Span Joints (Or Any Joint) At Terminations
Contacts of joints due to improper installation and looseness.
Contacts of joints due to inadequate surface area of contact.
2.3.2 Losses in Transformers (Typically DT)
Loose connection at brushing.
Bend in jumpers at connectors where the strands are not tightly held.
High no-load loss depending on type of core used.
High no-load loss in repair transformers, where the core has not been properly tighten.
No-load loss in case a large number of lightly loaded DTs.
17
High copper loss for transformers operating at sub-optimal loading which is not
commensurate with designed optimal loading.
2.3.3 Losses In Service Cables And Connections
Under sized service cables.
Loss in joints of service cables at the poles or junction boxes.
Use of inappropriate fasteners without spring washer at the crimped joints.
2.3.4 Loss Due To High Impedance Faults
Tree touching, creepers, bird nesting.
Insulator breakages and tracking on the surface of the insulator.
2.3.5 Losses in Re-Wired Fuses/Jumpers
Loose connection.
Inadequate size of fuse wire-open a source of hot spots.
2.3.6 Loss at Consumer end Meter
Poor accuracy of meters.
Large error in capital CTs/PTs.
Voltage drop in PT cables in huge distance.
Loose connection in PT wire termination.
Over headed line.
2.3.7 Tampering/ Bypass of Meters
Where meter without tamper-proof-temper-deterrent/tamper-evident meters are used.
18
Poor quality sealing of meters.
Lack of seal issue, seal monitoring and management system.
Shabby installation of meters and metering systems.
Exposed CTs/PTs where such devices are not properly securitized.
2.4 Improve Existing System Losses in Innovative Way
2.4.1 Network Reconfiguration
It gives an option to handle the increased demand and increases system reliability. It is effective
when voltage drops between the nodes to be linked is rich and the distance between the nodes is
short. Within a feeder it is effective only when the zigzag factor is high.
2.4.2 Network Reconductoring
The size of conductor/ cable determines the current density and the resistance of the line. A
lower conductor size can cause high 12R losses and high voltage drop which causes a loss of
revenue as consumer’s consumption and hence revenue is reduced. The recommended practice is
to find out whether the conductor is able to deliver the peak demand of the consumers at the
correct voltages that is the voltage drop must remain within the allowed limits.
2.4.3 Automatic Voltage Booster
It is similar to that of the series capacitor as on-load tap changer it boosts the voltage at its point
of location in discrete steps. This in turn improves the voltage profile and reduces the losses in
the section beyond its point of location towards the receiving end. It has a total voltage boosts of
10% in four equal steps and the loss reduction is directly proportional to voltage boosts.
2.4.4 Facts Devices
Flexible ac transmission system, or EACTS is a family of power electrons devices provides a
verity of benefits for increasing transmission efficiency. Perhaps the most immediate is their
ability to allow existing AC lines to be loaded more heavily without increasing the risk of
disturbance on the system. Actual results vary with the characteristics of each installation, but
19
industry experience has shown FACTS devices to enhance transmission capacity by 20-40%.
FACTS devices stabilize voltage, and in so doing remove some of the operation safety
constraints that prevent operation from loading a given line more heavily. In addition to the
efficiency gains, these devices also deliver a clear reliability benefit.
2.4.5 Energy Management System (EMS)
An energy management system (EMS) is a system of computer-aided tools used by operators of
electric utility grids to monitor, control and optimize the performance of the distribution system.
The EMS monitoring and control functions are referred to as the supervisory control and data
acquisition (SCADA). This intelligent of the system, increase reliability, and predict electricity
system performance as well as optimize energy usage to reduce costs.
2.4.6 Power Factor Correction
Certain customer inductive loads, distribution line, and transformers require reactive power to be
supplied the electric grid. Addition of reactive power (VAR) increases the total line current,
which contributes to additional losses in the system.
2.4.7 Load Balancing and Load Management
If the loads on each of the three phase of a distribution lines or among feeders are redistributed,
the losses will be reduced, the best method to identify load balance is to construct current
duration curves for all three phase. In the scenario of overload distribution system, load
management plays a very important role for reduction of technical losses. Distribution
automation along with CADA is important tool for load management which should be
introduced.
2.4.8 Capacitor Installation
The use of capacitor to correct for poor power factor is a well-established and cost effective
means of reducing distribution system losses and maximizing the revenue. In most LT
distribution circuits, it is found that the power factor (PF) ranges from 0.65 to 0.75. for low PF
the amount of current drawn increases to meet the same KW demands of load. Overall
improvement in the operating condition can be brought about by reducing the system reactance.
20
This can be done by the application of shunt capacitor in the following ways-across individual
customers, advantage points on LT and 11 KV feeders, at distribution transformers and 33/11
KV sub stations.
Figure 2.2- Capacitor with Insulation
2.4.9 Increase in HT/LT Ratio
It is well known that for high HT/LT ratio, the losses will be low. The losses for a given quantum
of power supplied by a line are inversely proportional to the square of its operating voltage.
Higher the operating voltage, lower will be line losses. Therefore, by increasing the HT lines the
losses will be reduced.
2.4.10 Additional Feeders
Adding an additional feeder can reduce loading losses in two ways. First, the current in the
existing feeder could effectively be cut in half, resulting in a reducing in a reduction in 12*R
losses, net of the losses in the new feeder. There could be a net loss reduction in the substation
transformers if the new feeder is fed from another substation transformer and the transformer
losses serving the new feeder do not increase more than the loss reduction in the original
transformer. It is important to calculate total system losses for the existing configuration and for
the new feeder configuration. In general, adding feeder cannot be cost-justified by loss
reductions alone. Many factors need to be considered when adding transmission and distribution
feeders, including cost analysis, reliability issues, growth estimates and load diversity.
21
2.4.11 Gas-Insulated Substation
Gas-insulated substations are a possible solution to help reduce losses. Typical substations
occupy large tracts of land and are located outside of dense load areas. As a result, lower-voltage
lines from substations can go quite a distance before reaching load centers, which increases
losses. Gas insulated substations are encapsulated, with all equipment inside a metal housing,
and can be contained in a basement or building close to the load center, which would help in the
reduction of losses.
Figure 2.3- Gas- Insulated Substations
22
CHAPTER THREE
Ways of Power Loss Degeneration
23
3.1 Introduction
Using ultra-modem equipment such as underground cable, maintenance free XER, prepaid
meter, overhead cover cable etc., and synthesizing causes with expenses we can reduce power
system losses in Bangladesh from 12% to 6% and we get more benefit. Manually we can reduce
the power system losses in distribution side by doing 11KV distribution line will be longer,
0.4KV distribution line will be smaller, under sizing cable, disconnecting illegal connection.
To save the Energy we can use some innovative ideas such as:
Underground cable in distribution system.
Maintenance free XER.
Prepaid meter.
Automation in distribution.
GIS in distribution side.
Some other innovative way in distribution side.
3.2 Underground Cable
A cable so prepared that it can withstand pressure and can be installed below the ground level
and normally two or more conductors are placed in an underground cable with separate
insulation on each conductor.
24
Figure 3.1-Underground Cable
3.2.1 Parts of an Underground Cable
3.2.1.(a) Conductor Or Cor
Conductor is the main part of the underground cable. It is a conducting material generally made
up of copper, aluminum or ACSR depending on many factors like voltage rating, power to be
handled, distance between service and load point.
3.2.1(b) Insulation
Each core is provided with individual insulation and the purpose of this insulation is to separate
the conductor from the part or other conductors.
3.2.1(c) Armor
Armor is a galvanized steel layer for providing mechanical strength to the cable.
3.2.1.(d) Serving
Serving is an insulating layer protects the cable from corrosion and other chemical reaction with
soil. It prevents moisture being entered in the cable.
25
3.2.2. (a) Advantages of UG Cables Power Grid Security
Not affected by ice, snow, rain, wind, dust, smoke or fog.
Not affected by Ice stoms, Tornadoes, Hurricanes.
Nothing to be stolen.
3.2.2. (b) Advantages of UG Cables Economy
Low maintenance costs.
Land use minimized.
Value of land and building unaffected.
Low manpower cost.
High reliability and availability.
Few faults, bumps on power system.
Low shock hazard.
3.2.3 Disadvantages of UG Cables
Initial cost is high, outage time, locate fault and repair (OH one day, UG 7-10 days).
Fault location instantaneous, can have longer repair time.
Continuous teach required (sensitive areas, directional boring).
Soil thermal conditions modified.
Not possible to installed in mountain areas.
Considering insulation most of the cable are designed for 33 KV
3.2.4 Power Grid Security Continued
Quebec ice storms in the winter of 1998.
Hydro-Quebec hundreds of kilometers of EHV and HV lines collapsed.
Thousands of towers.
Blackout initiated by OH line at First Hydro in Ohio.
3.2.5 Classification of Cables
26
Cables for underground service may be classified in two ways according to:
The type of insulating material used in their manufacture.
The voltage for which they are manufactured.
However, the latter method of classification is generally preferred, according to which
cables can be divided into the following groups:
Low-tension (L.T.) cables- up to 1000V.
High-tension (H.T.) cables- up to 11,000V.
Super-tension (S.T.) cables- from 22 KV to 33 KV.
Extra high-tension (E.H.T) cables- from 33 KV to 66KV.
Extra super voltage cables- beyond 132KV.
3.2.6 Low voltage single phase cable
Single phase underground cable two types
Single core PVC cable.
Single core oil filled cables.
3.3 Prepayment Energy
Prepayment energy meters are a type of domestic energy meter that requires users to pay for
energy before using it. This is done via a smartcard, token or key that can be “topped up” at a
corner shop or via a smart phone app.
3.3.1 Different Types of Prepayment Meters
There are two main types of prepayment meters:
Key meters: A key meter uses a special electronic key with our tariff information on it.
Smart Card Meters: A smart card meanwhile sends our latest information through to our
supplier when topped up.
27
Figure 3.2 Prepayment Energy Meter
3.3.2 Advantage of Prepayment Meters
3.3.2(a) Customers Benefit Are:
Customers like the new system.
Easy and transparent.
They can control their own consumption.
They can control their budget.
No hassles with bill payment, disconnection or reconnection.
There is no minimum charge.
Require no deposit.
No more disputed bills.
Warning for low credit.
Negative credit during friendly hours/ holidays.
28
Emergency credit.
Abnormal voltage protection.
Automated record keeping.
3.3.2 (b) The Power Company’s Benefits Are
Upfront payment.
Improved cash flow.
Decreased non-technical losses.
Lower overheads expenses (no meter reading or billing).
Increased revenue.
No outstanding
Tamper protection.
Non-allowance of cover sanctioned load.
Better load management.
Better customer services.
Automated record keeping.
Create power saving attitude to the consumers.
3.3.3 Disadvantages of Prepayment Meters
Above average costs for our gas and electricity.
The best energy deals on the market aren’t available to prepayment meter customers.
We can be inconvenient because we have to go out to ‘tor up’ keys and smartcards.
If we can’t reach a shop to top up our meter energy can be switched off.
Older meters need to have their prices updated manually after price rises or falls, which
can take months. This means we could be left paying old rates and owing a lump sum or
paying too much.
3.3.4 Scheme Works of a Pre-Payment Meter
29
The basic principle of prepayment is to buy Energy in advance and inform the meter in some
ways. The credit stored is deducted as per energy usages and the meter will cut the output line as
the credit reaches zero. If the consumers buy more credit and recharges, he can enjoy energy
usage without discontinuity. Vending stations are used to sell credit to the consumers. A number
of vending stations are connected to a System Master Station (SMS). The SMS is used to process
the data centrally.
3.4 Dry-Type Transformers
To minimize environmental contamination and fire hazard, customer are specifying dry-type
transformers more frequently. These transformers meet strict parameters with respect to
electricity system demands and functioning in areas with extreme climatic conditions. ABB’s dry
and cast transformers are virtually maintenance free and are manufactured in accordance with
industry and international standards including ISO 9001. ABB offers a full range of dry-type
transformer with primary voltages through 72.5 KV built according to all major standards
including IEC and ANSI.
3.4.1 Advantages
Dry type transformer accommodates less place than any other.
This XER do not catches a fire.
Installation at any place is convenient.
Eco-friendly looks & use.
Internal inspection is possible.
No corrosion.
Side clearance is less.
Maintenance.
3.4.2 Disadvantages
Cannot be used for more than 2000 KVA.
3.5 Automation in Distribution Side
30
Grid and distribution lines experience fault by extracted trees or pole at the time of any natural
disaster as flood heavy rain fall, cyclone, birds interacting with the cables or over voltage caused
for thunder attack. It causes suffering to consumer CB Trip and interrupt causeless power supply.
To provide consumer cause less power supply, distribution automation could be used at
distribution side that detects the fault very shortly and re-establishes uninterrupted power supply.
3.5.1 Automatic Circuit Re-Closers
These are the devices similar in function to circuit breakers, except they also have the
ability to reduce after opening again, and reclose again, repeating this cycle a
predetermined number.
The faults on cables are generally not temporary.
If the temporary fault has vanished during the dead time, the auto re-closer remains
closed. If fault persists after first/second re-closer one en-closer one enclosing is
attempted. If fault persists after third/final re-closer, the auto re-closer is opened and
locked.
3.5.2 Line Sectionalizer
A sectionalized is a protective device, used in conjunction with a re-closer, or breaker and
re-closer relay, which isolates faulted sections of lines. The sectionalizer does not
interrupt fault current.
Instead, it counts the number of operations of the interrupting device upstream and opens
while the interrupting device is open.
Reclosing relays and automatic sectionalizing equipment are used together to isolate a
faulted portion of a distribution circuit. After the downstream line sectionalizer has
operated, the reclosing relay at the substation should have one auto re-closing cycle left
to re-energize the undaunted section of the circuit.
31
3.6 Electricity Distribution and GIS
The use of GIS in power system has greatly enhanced the efficiency in energy sector. Proximity
to the furthest customer and high cost to invest capital, are the reasons that make the distribution
system as an important part of electrical utility, which endeavor to improve the reliability of
general power system. Analyses such as selection of suitable areas, optimum path finding, the
profile analyses, the engineering design of wires and towers, and the cost estimation can all be
done using GIS.
Electric utilities are realizing the benefits of GIS technology in the management of facilities for
engineering, construction operation, and maintenance and services purposes. Problems of
planning in distribution system can be solved by using new methods and specific techniques.
Complexity of electrical distribution system and necessity of accurate up-to-date information of
the network assets is a reasonable intention for introducing new method of information
technology.
Figure 3.3-Operation of GIS
32
3.6.1 Aims and Objectives
The aim of the project is to generate a geospatial model for electricity consumers and facilities to
provide a better understanding towards effective distribution and conservation of electricity. The
objectives of the study are to:
Carry out an appraisal of the existing electrical distribution network in the study area.
Map the existing electricity distribution facilities in the study area.
Estimate the trend in electricity consumption pattern in the study area.
Conduct gap analysis of electricity requirement in the study area.
3.6.1 (a) The Following Recommendations Are Advanced For Efficient Electricity
Distribution Networks
More efforts must be made to bring in refined and scientific approaches such as GIS into
the management of electricity distribution network.
Training programs should be organized for technical online staff of electricity
distribution on the integration of GIS in the management of electricity distribution.
The user requirement and survey analysis conducted before implementation of electricity
projects should include spatial information system from the onset so as to forestall drop
in voltage within the distribution network.
3.6.2 Distribution System Software Key Features
Balanced and unbalanced load flow and voltage drop analysis.
Protective device coordination including extensive re-closer modeling and sequencing.
Optimal capacitor placement and sizing to minimize losses and improve voltage profile.
Comprehensive load modeling.
Advanced reliability assessment and distribution reliability analysis.
Switching sequence management for load transfer simulations.
GIS map interface.
Advanced monitoring, simulation & control.
33
Predict system response to operator actions.
Fast, optimal & intelligent load shedding and restoration.
System optimization and automation.
Demand-side management.
Intelligent one-line diagrams.
Intelligent one-line diagrams.
Multi-dimensional database.
Time domain event event playback with simulation capability.
Integrated alarm, warning and acknowledgement.
Client-server configuration.
Built-in redundancy and automatic fail over.
3.6.3 Operators
Advanced alarm management.
Flexible graphical monitoring.
Multiple access levels.
Multi-console monitoring.
Built-in redundancy and automatic fail over.
Substation automation.
Train and assist operators.
Reduce downtime.
Improve operator usability and confidence.
Avoid time-of-use penalties.
3.6.4 Managers
i. Reliable and accurate plant data.
ii. Single platform reduced maintenance and support.
iii. Optimize operation and increase reliability.
34
iv. Minimize operating costs.
v. Evaluate cost allocation.
vi. Provide data accessibility.
vii. Improve energy conservation.
3.6.5 Engineers
i. Cause and effect investigation.
ii. Minimize system losses.
iii. Extended equipment lifetime.
iv. Expand capabilities as site requirements change.
v. Inherent handling of large scale systems.
3.7 Some Innovative Way in Distribution Side
Sl.
no.
Problem Proposal
1
11 KV voltage level tapping between
WZPDCL and PBS (feeder):
Transformer and bus bar losses of 11 KV
tapping between WAZPDCL and PBS are
distributed proportionally which is actually
illogical in truth, loss increases inversely in
case of cover extended load.
In case of 11 KV voltage level tapping an
act could be enforced asserting that,
tapping issuing institute could prepare bill
in F tariff tapping issuing institute could
bear total bus bar and XER loss.
2
Establish power factor improvement
instruments for C tariff consumer:
The most benefit able way for declining
line loss and voltage drop is power factor
improvement at consumer side. Though
according to power consumption rate and
For C tariff power factor rectifying yardage
could be enacted in proper rate like F & E
tariff, besides disconnecting by notice law.
35
regulation 7.3.1 and 7.3.2 C tariff consumer
could be disconnected, failing to sustain
power factor within approved limit
consumer apathy causes much troubles in
field level. Such as:
i. Establish capacitor bank and
internationally undo the
connection.
ii. Not replace damaged capacitor
bank.
iii. Establish low quality capacitor
bank that fails to do essential
power factor development
moreover they oppugn to add extra
PFI unit etc.
iv. In this consumer incentive should
be ensured in establishing power
factor improvement instruments...
3
Pacifying the penalty collection for illegal
consumer is necessary.
Decisions could be made by forming
committee in every circle consisting
corresponding dept. head and executive
engineer to ascertain penal rate according
to power consumption and regulation act
17.00
4
Average bill of damaged meter:
In case of average bill for damaged meter it
has been noticed that, of even after many
months of average bill feeder in-charge
feeder supervisor are bot informed timely.
Proper measure should be taken as for the
meter reader supervisor could be informed
According to electricity act 1910 clause 26
sub clause 3 should any average bill
certainly committee as described below
a. 3-phase 11KV:
a. Corresponding administrative
engineer.
b. Corresponding meter reader
36
immediately before preparing average bill
and be able to take decision and initiative
according to it.
(executive engineer)
b. 3-phase 400V:
a. Corresponding executive engineer.
b. Corresponding meter reader (feeder
supervisor).
c. 1-phase 230V:
a. Corresponding feeder supervisor.
b. Corresponding feeder in-charge.
c. Corresponding feeder meter reader.
5
If some acts could be drawn to simplify
undue collection from disconnected
consumers undue collection could be
pacified.
Beside notice and case ministry of power
energy and mineral resource of people
republic of Bangladesh needs to add
following acts:
i. If disconnected defaulter consumer
uses connections against several
accounts within one premise those
should be disconnected by 10 days’
notice.
ii. If any consumer unwilling to repay
the undue, facilities himself by
using his or other consumers
construction as well as connection
in that case his or the other
consumer connection should be
under cut off by 10 days’ notice
law.
iii. If any consumers dies leaving his
undue repaid, in that case the
appropriator, resident occupier or
the buyer of his property consuming
his own or any of other
37
establishment, his or the other
providing connection should be
under cut off by 10 days’ notice
law.
Table 3.1-Some Innovative Way in Distribution Side
CHAPTER FOUR
SYSTEM PROTECTION
38
4.1 Introduction
Power system is subjected to faults and transient. These will result in over currents and over
voltages that can cause damage to conductors as well insulation. That result in equipment loss
and system failure. In distribution system the main devices for over current or fault current
protection are fuses and circuit breakers. In addition to these over voltage protection devices and
relays are also employed. The modern power system is complex and even though protection
equipment from 4 to 5% of the total cost involved in the system, they pay a very important role
in the system design for good quality and reliability.
4.2 Objectives of Distribution System Protection
Minimize the fault duration
Minimize the number of consumer effected by the fault
Eliminates the safety hazards as fast as possible
Minimize the service failure to the smallest possible branch in the distribution system
To discriminate between over loading, short circuit and very temporary fault.
4.3 Over Current Protection Devices
These include
Fuses
Relay controlled circuit breakers
Automatic circuit re-closers
39
Automatic line sectionalizes
4.3.1 Fuse
A fuse is a type of low resistance resistor that acts as a sacrificial device to provide over
current protection, of either the load or source circuit.
Its essential component is a metal wire or strip that melts when too much current flows
through it, interrupting the circuit that it connects.
The fuse element is generally made of materials having low melting point, high
conductivity and least detritions due to oxidation e.g. silver, copper etc.
Figure 4.1-Electrical Fuse
4.3.1(a) Advantages
Cheapest form of protection available.
Requires no maintains
Break heavy short circuit current without noise and smoke
The minimum time of operation that can be made much shorter than of the circuit
breaker
4.3.1(b) Disadvantages
40
Considerable time is required in removing and replacing a fuse after operation.
The current time characteristics of a fuse can`t be correlated that of protected apparatus.
4.4 Circuit Breakers
a. There are the devices that can carry and interrupt normal load current, like switches; in
addition, they interrupt short-circuit (fault) current.
b. Circuit breaker are always paired with a relay which senses short-circuit condition using
potential transformers (PTs) and current transformers (CTs).
c. A circuit breaker is essentially consist of fixed and moving contacts called electrodes.
d. Under normal operating conditions, these contacts remain in closed and will not open
automatically until and unless the system become faulted.
e. Circuit breaker are rated for low voltages (<1000 V), medium voltages (over 1000 V but
less than 7200 V) and high voltages (>7200 V).
41
Figure 4.2-Circuit Breaker
4.4.1 The Circuit Breakers Used In the Distribution System
Air circuit breaker
Oil circuit breaker
Minimum oil circuit breaker
Vacuum circuit breaker
4.5 Automatic Circuit Re-closers
There the devices similar in function to circuit breakers, except they also have the ability
to reclose after opening, open again, repeating this cycle a predetermined number of
times until they lockout .
The fault on cables are generally not temporary.
42
If the temporary fault has vanished during the dead time, the auto re-closer remains
closed. If fault persists after first/second re-closer one enclosing is attempted. If fault
persists after third/final re-closer, the auto reclose is opened and locked.
Figure 4.3-Re-Closer
4.6 Automatic Line Sectionalizer
A sectionalize is a protective device, used in conjunction with a re-closer, or breaker and
reclosing relay, which isolates faulted of lines. The sectionalizer does not interrupt fault
current.
Instead, it counts the number of operations of the interrupting device upstream and opens
while the interrupting device is open.
Reclosing relays and automatic sectionalizing equipment are used together to isolate a
faulted portion of a distribution circuit. After the downstream line sectionalize has
operated, the reclosing relay at the substation should have one auto reclosing cycle left to
re-energize the unfaulted section of the circuit.
4.6.1 Advantages
43
1. Automatic sectionalizes are cheaper than auto re-closers.
2. They may be employed for interrupting or switching loads within their rating.
4.7 Co-Ordination of Protective Devices
i. Protective device coordination is the process of determining the “best fit” timing of
current interruption when abnormal electrical conditions occur.
ii. The goal is to minimize an outage to the greatest extent possible.
iii. Historically, protective device coordination was done on translucent log-log paper.
Modern methods normally include detailed computer based analysis and reporting.
iv. Protective coordination is also handled through dividing the power system into protective
zones.
v. If a fault were to occur in a given zone, necessary actions will be executed to isolate that
zone from the entire system.
vi. Overlapped regions are created by two sets of instrument transformers and relays for each
circuit breaker. They are designed for redundancy to eliminate unprotected areas.
4.7.1 Objectives of Co-ordination
i. Minimize the extent of fault in order to reduce the number customers affected.
ii. Minimize the service interruption due to faults.
iii. Minimize the duration of service outages to identify the location of the fault.
iv. Types of co-ordination
a.Fuse to Fuse
b. Auto re-closers to Fuse
c.Circuit breaker to Fuse
d. Circuit breaker to Auto Re-closers
4.7.1(a) Fuse to Fuse Coordination
Fuse A is called protected fuse.
Fuse B is called protecting fuse.
44
For perfect coordination fuse B mist melt and clear the fault before fuse A is damaged.
4.7.1(b) Auto Re-closers to Fuse
If the fault F beyond the fuse B is temporary, the auto re-closer AR should clear it
without blowing of fuse B.
Figure 4.4-Recloser to Fuse Coordination
4.7.1(c) Circuit Breaker to Fuse
When fuse A is used as a main protection and circuit breaker as a backup, the operating
time is selected as 150% of total operating time of the fuse of over current relays for
phase to phase fault.
Therefore the fuse A operates first and the circuit breaker operates next only if fuse fails
to operate.
If the circuit breaker provides main protection and fuse A as a backup, the relays should
operate instantaneously and circuit breaker should isolate the before blowing the fuse.
The minimum melting time of fuse should be about 135% more than total fault clearing
time of the circuit breaker relay combination for phase to phase faults.
4.7.1(d) Circuit Breaker to Auto Re-closers
45
The circuit breaker provides a backup protection.
The auto re-closer provides main protection.
CHAPTER FIVE
Tariff, Revenue, Protocol and46
Consumer’s Participation with
WZPDCL Programs
5.1 Introduction
Electricity prices vary between countries and can even vary within a single region or distribution
network of the same country. In standard regulation monopoly markets, electricity rates typically
vary for residential, commercial, and industrial customers. Prices for any single class of
electricity customer can also very by time –of-day or by the capacity or nature of the supply
circuit (e.g. 5kw, 12kw, 18kw, 24kw, are typical in some of the large developed countries); for
industrial customers, single-phase vs. 3-phase, etc. If a specific market allows real-time dynamic
pricing, a more recent option in limited markets to date typically following the introduction of
electronic metering, prices can even vary between times of low and high electricity network
demand.
5.2 Tariff
47
A tariff is the pricing structure a retailer charges a customer for energy consumption. It’s divided
into two parts: the ‘fixed charge’ for supply of energy to your premises. The ‘variable charge’ for
the amount of energy you use.
5.2.1 Global Electricity Prices by Select Countries in 2015
(in U.S. dollar cents Per kilowatt hour)
48
Figure 5.1-Global Electricity Prices (in U.S. dollar cents per kilowatt hour)
5.2.2 New Electricity Bill Tariff in Bangladesh (PDB)
49
Table 5.1-New Electricity Bill Tariff in Bangladesh (PDB)
5.2.3 Tariff Rates in Bangladesh and Its Neighbors Country
50
Country/Region 0-100 Unit Residential (Bdt/kwh) Agriculture (Bdt/kwh)
Bangladesh 3.68 (Up to 75 Unit: 3.33) 2.51
West Bengal, India3.88 (rural),
3.90 (urban)
Off peak: 2.34,
Peak: 9.06
KESC (Karachi) 5.90 Flat: 11.00
Nepal 6.79
.50 unit: 8.00
Srilanka3.88
.90 unit: 13.25
Source: BPDP (2012) Table 5.2 Tariff Rates in Bangladesh and Its Neighbors
5.3 Revenue
In Bangladesh 2014-15 Budget subsidies for “Power and Energy Saving” was 18 Thousands and
540 core take.
2 0 0 8 - 2 0 0 9 2 0 0 9 - 2 0 1 0 2 0 1 0 - 2 0 1 1 2 0 1 1 - 2 0 1 2 2 0 1 2 - 2 0 1 3 2 0 1 3 - 2 0 1 4
2677
2637
5968
.42 71
85.8
8795
.43
7928
2213
1030
5912
.81
5912
.81
8851
.77
7916
Total Budget (Core Taka) Achievement (Core Taka)
Figure 5.2-ADP Growth at Electricity Sector
2010 2015 2020 2025 2030 2035 2041
GDP (million 93,236 126,630 181,282 258,598 351,109 453,642 587,665
51
USD)
GDP (billion
BDT)6,071 8,245 11,804 16,838 22,862 29,538 38,265
Exchange rate
(BDT/USD)65.1
Growth rate
(p.a.)6.1% 6.3% 7.4% 7.4% 6.3% 5.3% 4.4%
[13] Table-5.3-Real GDP Revenue
5.4 Protocol
A protocol is the special set of rules that end points in a telecommunication connection use when
they communicate. Protocols specify interactions between the communicating entities.
5.4.1 Electricity Protocol
When any VIP guest like a Prime minister, minister meeting or any large function like fair,
cultural program or any kind of religions program (Milady Mikhail) is organized by consumer
then there needs to supply uncut electricity that is called electricity protocol.
In our country sometimes many programs are held by general people. When this program are
held then our electricity distribution company have to take necessary steps to hold this program
comfortably so that they should supply uncut electricity. For this program they are facing many
problems because this extra load demand is unexpected. As a result for fulfill this electricity
demand some other feeder in distribution side have to shut down for program. Shut down
feeder’s consumer have to suffer very badly. So for this program or any other VIP purpose they
have to arrange a standby generator for supporting electricity demand. On the other hand if occur
any fault in distribution line then they have to use the generator. And obviously generator should
keep in running condition. Without this generator they can also use solar power or DC supply.
52
So in any program or official work they should not only depend on power grid or distribution
line.
5.5 Consumer Help to WZPDCL
i. Un-sanctioned/Non-permitted Air conditioners, heater, Microwave, Induction heater
should be avoided.
ii. Consumer should not use illegal connection.
iii. Consumer should use smart home security system so that they can control their electricity
from any place.
iv. In electricity protocol, fair, any cultural program or religions program or VIP guest
meeting consumer have to use a standby generator.
v. Every consumer must have it use smart meter (prepaid meter) because it’s calculation
helpful for consumer and any distribution company.
vi. Consumer have to use a good wiring system.
vii. In case of post payment metering consumers should pay their electricity bill within fixed
date.
5.6 WZPDCL Helpful to Consumer
i. WZPDCL have to sure uncut electricity for consumer and they have to use good quality
electricity equipment for consumer safety.
ii. Safety purpose should be increase their concern.
iii. Need a good relation with consumer.
iv. WZPDCL have to ensure that consumer have to pay electricity bill comfortably also it
will be online system.
v. WZPDCL should be concern about prepaid meter and encourage for using it for
consumer.
53
5.7 Consumer Survey
The Question as followed bellow has been asked to Apx.500 Consumers. The Answers picked up
from the most common ones:
You any load shedding in your area? (If have) how it’s Have longer?
Ans: Yes. Almost one hour daily (two or three times).
Have you get sufficient electrical energy as your need?
Ans: Yes
Have you faced any riddle when you connected your new connection?
Ans: No.
Are you satisfy with your electricity safety?
Ans: Yes. But little bit reflected upon on ours.
How does behave a meter reader when they collect your meter reading?
Ans: Good
Have you any puzzle meter reading or electricity bill?
Ans: Yes. Sometimes we are getting confused.
Have you paid off your electricity bill timely?
Ans: Yes. Try our best.
Have you taken any steps to stop power wastage?
Ans: Yes. Like when a light isn’t need it will be shut off.
Are you satisfied with supplying electricity from WZPDCL?
Ans: Yes.
Are you satisfied with WZPDCL’s Tariff rate?
Ans: Yes. But it should be less.
54
Have you faced any equipment break down (like meter break down)? They what do you
do?
Ans: Yes. Then then we contact with officers of WZPDCL.
Did you find power management efficient during or natural danger?
Ans: No. it’s most displeasing.
What are you do when your voltage low down?
Ans: I’m try to shut down my main switch.
When you go to WZPDCL’s office, how are they behave with you?
Ans: Good. They co-operate with us.
55
CHAPTER SIX
CONCLUSION AND
RECOMMENDATIONS
56
6.1 Conclusion
Bangladesh is an energy hungry country. Power infrastructure of Bangladesh insufficient but the
demand is rapidly increasing. Our Govt. want to provide electricity to all. So first of all we
should be focused on distribution system with some new technology. Some innovative ideas we
described in this thesis that’s might be helpful to reduce system losses in distribution side and
more efficient to provide electricity in industrial area or residential area. Now Govt. want to get
10% of total consumption from renewable energy technology.
6.2 Limitations of the Work
If we want to accomplish above innovative way then it will bear more initial cost. But it is so
important to implement the above way which are innovative because it will be more convenient.
6.3 Future Scopes of the Work
There is no termination of innovative way when yoke is developed then new exploration will be
exposed and added to power system in this way power system will be reduced. Power system
will be improved with the addition of new technique.
57
References[1]. https://en.wikipedia.org/wiki/Electricity_sector_in_Bangladesh
[2]. https://en.wikipedia.org/wiki/Electric_power_distribution
[3]. https://www.desco.org.bd/?page=tarrif-rate-2, retired on 03.6.2016
[4]. https://dpdc.org.bd/bn/?lng=bn, retired on 5.6.2016
[5]. https://www.bpdb.gov.bd/bpdb/,retried on 5.5.1016
[6]. https://www.wzpdcl.org.bd/,retired on 13.5.2106
[7]. www.powermin.nic.in/jsp_servlets/internal.jsp retired on 13.5.2016
[8]. D. W. A. Willen et al., Test results of full-scale I-ITS cable models and plans for a 36 kV, 2 k Arms utility
demonstration, submitted for publication, Applied Superconductivity Conference, 2000.
[9]. R. L. Hughey, Development of a high temperature superconductivity power delivery system, Jicable, pp. 92-
96, 1999
[10]. M. Nassi, Latest development of HTS cable systems in Europe and the USA", Proceedings of the ISS 1999,
Tokyo, Japan, pp. 821-826, October 1999.
[11]. M. Leghissa, J. Rieger, H.-W. Neumuller, Development of HTS power transmission cables, IEEE Trans. on
Appl. Supercond., vol. 9, pp. 406- 411,1999.
[12]. T. Shibata et al., Development of high temperature superconducting power cable prototype system, IEEE
Trans. on Power Delivery, vol. 14,no. 1,pp. 182-187, 1999.
[13]http://powerdivision.portal.gov.bd/sites/default/files/files/powerdivision.portal.gov.bd/page/4f81bf4d_1180_4c5
3_b27c_8fa0eb11e2c1/1%20%281%29.pdf
58