webinar slides - road project - co2 capture plant feed study
DESCRIPTION
Elvira Huizeling, responsible for Special Projects in the Capture team of the ROAD project, lead a Global CCS Institute webinar on the ROAD CO2 Capture Plant FEED Study report. ROAD stands for ‘Rotterdam Opslag en Afvang Demonstratieproject’ (Rotterdam Capture and Storage Demonstration Project) and is one of the largest integrated demonstration projects in the world for the capture and storage of CO2. ROAD had just completed the front-end engineering design (FEED) study for the capture plant as performed by Fluor. The main results from the FEED study were presented in this webinar, including topics such as technology selection, process flow diagrams, heat and mass balances, layout designs, cooling studies, capital and O&M cost estimates and project schedules. A recording of the webinar can be seen at http://www.globalccsinstitute.com/community/events/2011/10/27/webinar-road-project-co2-capture-plant-feed-studyTRANSCRIPT
![Page 1: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/1.jpg)
GCCSI WebinarROAD project- CO2 Capture plant FEED study
Elvira Huizeling
November 22, 2011
![Page 2: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/2.jpg)
Page 2
Agenda
1. Introduction
2. FEED study scope and boundaries
3. Capture Plant Process & Design
4. HSE
5. CO2 stream, compression
6. Financials and planning
![Page 3: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/3.jpg)
Page 3
1. Introduction
![Page 4: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/4.jpg)
Page 4
ROAD means...
Rotterdam
Opslag
Afvang
Demonstratieproject(Rotterdam Storage and Capture Demonstration)
![Page 5: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/5.jpg)
Page 5
Co-operating Partners ROAD
• Maasvlakte CCS Project C.V. is a joint venture of:• E.ON Benelux
• Electrabel Nederland (GDF SUEZ Group)
• In co-operation with intended partners:• TAQA Energy
• GDF SUEZ E&P
• With financial support of:• European Commission (EU)
• Government of the Netherlands
• Global CCS Institute
![Page 6: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/6.jpg)
Page 6
Objectives ROAD
• Demonstrate feasibility (technical, economic) of large-scale, integrated CCS chain
• Capture and storage of ca. 1.1 Mton CO2 per year in (nearly) depleted gas reservoirs in period of 2015 – 2020
• Acquire knowledge and experience with deployment of large-scale, integrated CCS chain:• Technical• Legal• Economic• Organizational• Social
![Page 7: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/7.jpg)
Page 7
20 meters
Power plant(Maasvlakte)
CO2capture
compression
pipeline 20 km over seabed (North Sea)
pipeline5 km onshore(Maasvlakte)
3,5 km
PlatformP-18A
Not on scale
ROAD CO2 Capture, Transport and Storage Chain
CO2 storage in depleted gasreservoirs
![Page 8: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/8.jpg)
Page 8
MPP3 location Capture Location: Maasvlakte Power Plant 3
![Page 9: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/9.jpg)
Page 9
CO2 Capture Unit
• Technology: post-combustion
• Size: 250 MW equivalent
• Capture rate: 90%
• CO2 capture:
1.1 mln tonne/yr
• Operational: 2015
![Page 10: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/10.jpg)
Page 10
CO2 Transport: 5 km onshore, 20 km offshore
![Page 11: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/11.jpg)
Page 11
CO2 Storage Location
• Depleted gas reservoir P18
• Operator: TAQA
• Depth: 3,500 m
• Capacity: 35 mln tonne
• Available: 2014
• Alternatives / future expansion options
are being investigated (EOR)
![Page 12: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/12.jpg)
Page 12
Other GCCSI reports (soon to be) available
– Capture technology selection methodology
– Permitting process
– Mitigating project risk & handling business risk
– Stakeholder management
– Execution strategy
![Page 13: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/13.jpg)
Page 13
2. FEED study scope and boundaries
![Page 14: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/14.jpg)
Page 14
Boundary of this work
• In this report you can find a short inventarisation on all topics relevant for taking a Final Investment Decision, based on GCCSI know-how
• Work reported here is about Capture Front End Engineering and Design (FEED), not about complete project
• Integration with power plant is included
![Page 15: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/15.jpg)
Page 15
CCS Project Development Framework
![Page 16: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/16.jpg)
Page 16
Base installation
• E.ON Maasvlakte Power Plant 3 (Rotterdam, The Netherlands)
• Output : 1.070 MWe
• Efficiency : 46% (LHV)
• Operational : End 2012
• Capture ready (conform TÜV NORD requirements)
![Page 17: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/17.jpg)
Page 17
17
CCS@MPP3 – Overview Interfaces
Carbon Capture
MPP3
Solvent
Caustic Soda
Flue gas
Instrument air
Flue gas condensate
LP-steam
(steam) condensate
CW supply
Electric power
CW to outletpond
Treated Flue gas
Demin water
Heated condensate
Cold Condensate
Nitrogen
CO2 to storage
Reclaimer waste
![Page 18: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/18.jpg)
Page 18
3. Capture plant process and design
![Page 19: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/19.jpg)
Page 19
19
CCS-MPP3: Process Scheme CC-Plant
Electric
Power
Controls
Drinking water
Fire water
Storm water
Sewage
![Page 20: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/20.jpg)
Page 20
![Page 21: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/21.jpg)
Page 21
Impact of the capture plant on the power plant process, Efficiency in (LHV)
Parameter Unitwithout
Carbon Capture with
Carbon Capture
Electrical Output (Gross) MW 1,117 1,086
Electrical Output (Net) MW 1,069 1,012
Electrical Efficiency (Net) % 46.3 43.9
Specific CO2 emission g/kWh 755 641
Cooling demand Power Plant MW 1,090 985
Cooling demand Carbon CapturePlant
MW 0 161
Overall Cooling demand MW 1,090 1,146
![Page 22: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/22.jpg)
Page 22
22
CCS@MPP3 - Layout
![Page 23: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/23.jpg)
Page 23
Plot plan
STACK
Direct
Contact
Cooler
Blower
Absorber
Stripper
CO2 compressor
![Page 24: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/24.jpg)
Page 24
4. HSE
![Page 25: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/25.jpg)
Page 25
Requested permit values
Component Yearly value
(6% O2)
[mg/Nm3]
Mass flow
[tonnes per
year]
Yearly value
(6% O2)
[mg/Nm3]
Mass flow
[tonnes per
year]
MEA 11 6.2 2.0 6.2
NH31 5.0 2.8 1.0 3.1
NOx as NO2 77.6 44.0 70.0 215.0
SO2 0 0 31 95.0
HCl 3.7 2.1 2.9 9.0
HF 0.5 0.3 0.4 1.3
CxHy 23 13 10 31
Fly ash 2 1.1 3.3 10
CO2 - 18,000 - 687,000
Operational situation:
100% flue gas through CC-Plant
Operational situation:
ca. ¼ flue gas through CC-Plant
EIA: Tabel 3.5: Emission in stack (MPP3 and CC-Plant)
1) NO2
based on
5% of NOx
![Page 26: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/26.jpg)
Page 26
Other streams to consider for permit
• Water• Process water• Cooling water• Demineralized water
• Waste• Other chemicals
• Sodium hydroxide• Solvent • Hydrogen• Nitrogen• Activated Coal
• Noise
![Page 27: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/27.jpg)
Page 27
HAZID
• Hazid was performed in June 2010 and three actions still remained for EPC phase
• First item is already picked up in discussions with authorities
No: Description: By: Due: Response: By: Date:
7
Discussions with authorities need to be opened
to discuss impact of capture plant on operating
permit, with respect to emissions. JV Project EPC
10
Capture plant and MPP3 operators to be trained
regarding emergency response planning. JV operations EPC
20
Ensure all power lines are identified prior to any
excavation or piling work. Construction EPC
![Page 28: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/28.jpg)
Page 28
5. CO2 Stream and compressor
![Page 29: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/29.jpg)
Page 29
CO2 stream specification
• The boundaries of the CO2 specification have been defined
• Purity of CO2 99.9%
• From all elements produced in post combustion capture plant only H2O and O2 are of any relevance.
• Details like the trip values still have to be determined (at which amount of for example H2O and O2 the plant must be stopped?)
• Most important is the temperature and pressure of the stream to determine the phase of the stream
![Page 30: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/30.jpg)
Page 30
Compressor will operate in supercritical areaAssumed operating conditions
for ROAD:
Pressure max 129 bar (a)
T between 40 and 80 °C
![Page 31: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/31.jpg)
Page 31
6. Financials and planning
![Page 32: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/32.jpg)
Page 32
CAPEX for Capture plant of 250 MWe excl. integration
The capital cost estimate breakdown for the capture plant is as follows:
• Equipment: 60 – 70 MM Euro
• Materials and Labor: 65 – 75 MM Euro
• Engineering: 15 – 20 MM Euro
• Indirect Field Costs: 5 – 10 MM Euro
• Owner’s costs (Operator training & first fills): 1 – 2 MM Euro
• Financial and other costs: 25 – 35 MM Euro
• Total: 170 – 210 MM Euro
![Page 33: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/33.jpg)
Page 33
Operating costs capture plant, including steam (Million of Euro, 2010 Euros)
2015 2016 2017 2018 2019
Staff costs 2,1 1,9 1,9 2,0 2,0
Variable costs 18,5 21,1 23,9 24,1 24,3
Maintenance 2,7 2,7 2,7 2,8 2,8
Other costs 1,5 1,5 1,5 1,5 1,5
Total operating costs 24,7 27,2 29,9 30,3 30,7
Power price assumed:
55 €/MWh
![Page 34: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/34.jpg)
Page 34
Construction Schedule
![Page 35: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/35.jpg)
Page 35
Time Path and Milestones
14 July 2009 : EU project proposal submission
September 2009 : Project selection by EU
May 2010 : Grant decision by Government of the Netherlands
September 2010 : Publication starting note Environmental Impact Assessment
Q4 2011 : EIA and permit procedures
2013 : Power plant (MPP3) operational
2015 : Integrated CCS chain operational
2015-2020 : Demonstration phase CCS chain
![Page 36: Webinar Slides - ROAD Project - CO2 Capture Plant FEED Study](https://reader034.vdocument.in/reader034/viewer/2022052523/55644316d8b42ace308b5876/html5/thumbnails/36.jpg)
Page 36
Maasvlakte CCS Project C.V.
Parallelweg 1
3112 NA Schiedam
www.road2020.nl