weekly update may 31, 2019 - home | central piedmont 05... · 2019-06-06 · weekly update may 31,...

13
Merancas Classroom Building Weekly Update May 31, 2019 Merancas Campus

Upload: others

Post on 28-Jun-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Weekly Update May 31, 2019 - Home | Central Piedmont 05... · 2019-06-06 · Weekly Update May 31, 2019 Merancas Campus. Meetings & Milestones ... • 05/28/19 at 1:30PM •Balance

Merancas Classroom Building

Weekly Update May 31, 2019

Merancas Campus

Page 2: Weekly Update May 31, 2019 - Home | Central Piedmont 05... · 2019-06-06 · Weekly Update May 31, 2019 Merancas Campus. Meetings & Milestones ... • 05/28/19 at 1:30PM •Balance

Meetings & Milestones

• This Week:

• Placed Area A and B Slab on Grade• Completed Underground Electrical• Completed Underground Plumbing• Strip Area A and B Forms• Place Area C Forms• Place Stone in Area C• Installed Area C Vapor Barrier • Placed Area C Rebar Mesh• Subcontractor Meeting

• 05/28/19 at 10:00AM

• OACG Meeting• 05/28/19 at 1:30PM

• Balance of Work Re-Bid• 05/29/19 at 2:00PM

Page 3: Weekly Update May 31, 2019 - Home | Central Piedmont 05... · 2019-06-06 · Weekly Update May 31, 2019 Merancas Campus. Meetings & Milestones ... • 05/28/19 at 1:30PM •Balance

Meetings & Milestones

• Next Week:

• Complete Area C Slab on Grade Prep

• Pour Area C Slab on Grade 06/04

• Strip Area C Slab on Grade Forms

• Begin Steel Erection

• Subcontractor Meeting

• 06/04/19 at 10:00AM

• State Construction Meeting

• 06/04/19 at 1:30PM

Page 4: Weekly Update May 31, 2019 - Home | Central Piedmont 05... · 2019-06-06 · Weekly Update May 31, 2019 Merancas Campus. Meetings & Milestones ... • 05/28/19 at 1:30PM •Balance

Progress Photos

Place Area A Slab

on Grade

Page 5: Weekly Update May 31, 2019 - Home | Central Piedmont 05... · 2019-06-06 · Weekly Update May 31, 2019 Merancas Campus. Meetings & Milestones ... • 05/28/19 at 1:30PM •Balance

Progress Photos

Place Area A Slab on

Grade

Page 6: Weekly Update May 31, 2019 - Home | Central Piedmont 05... · 2019-06-06 · Weekly Update May 31, 2019 Merancas Campus. Meetings & Milestones ... • 05/28/19 at 1:30PM •Balance

Progress Photos

Place Area B Slab

on Grade

Page 7: Weekly Update May 31, 2019 - Home | Central Piedmont 05... · 2019-06-06 · Weekly Update May 31, 2019 Merancas Campus. Meetings & Milestones ... • 05/28/19 at 1:30PM •Balance

Progress Photos

Wet Cure Area A

and B

Page 8: Weekly Update May 31, 2019 - Home | Central Piedmont 05... · 2019-06-06 · Weekly Update May 31, 2019 Merancas Campus. Meetings & Milestones ... • 05/28/19 at 1:30PM •Balance

Progress Photos

Area C Slab on

Grade Form Work

Page 9: Weekly Update May 31, 2019 - Home | Central Piedmont 05... · 2019-06-06 · Weekly Update May 31, 2019 Merancas Campus. Meetings & Milestones ... • 05/28/19 at 1:30PM •Balance

Progress Photos

Placed Area C

Stone

Page 10: Weekly Update May 31, 2019 - Home | Central Piedmont 05... · 2019-06-06 · Weekly Update May 31, 2019 Merancas Campus. Meetings & Milestones ... • 05/28/19 at 1:30PM •Balance

Progress Photos

Placed Area C

Vapor Barrier

Page 11: Weekly Update May 31, 2019 - Home | Central Piedmont 05... · 2019-06-06 · Weekly Update May 31, 2019 Merancas Campus. Meetings & Milestones ... • 05/28/19 at 1:30PM •Balance

Progress Photos

Placed Area C

Rebar Mesh

Page 12: Weekly Update May 31, 2019 - Home | Central Piedmont 05... · 2019-06-06 · Weekly Update May 31, 2019 Merancas Campus. Meetings & Milestones ... • 05/28/19 at 1:30PM •Balance

Progress Photos

Area C

Underground

Electrical Conduit

Page 13: Weekly Update May 31, 2019 - Home | Central Piedmont 05... · 2019-06-06 · Weekly Update May 31, 2019 Merancas Campus. Meetings & Milestones ... • 05/28/19 at 1:30PM •Balance

Conclusion of Weekly Update 05/31/2019