Merancas Classroom Building
Weekly Update May 31, 2019
Merancas Campus
Meetings & Milestones
• This Week:
• Placed Area A and B Slab on Grade• Completed Underground Electrical• Completed Underground Plumbing• Strip Area A and B Forms• Place Area C Forms• Place Stone in Area C• Installed Area C Vapor Barrier • Placed Area C Rebar Mesh• Subcontractor Meeting
• 05/28/19 at 10:00AM
• OACG Meeting• 05/28/19 at 1:30PM
• Balance of Work Re-Bid• 05/29/19 at 2:00PM
Meetings & Milestones
• Next Week:
• Complete Area C Slab on Grade Prep
• Pour Area C Slab on Grade 06/04
• Strip Area C Slab on Grade Forms
• Begin Steel Erection
• Subcontractor Meeting
• 06/04/19 at 10:00AM
• State Construction Meeting
• 06/04/19 at 1:30PM
Progress Photos
Place Area A Slab
on Grade
Progress Photos
Place Area A Slab on
Grade
Progress Photos
Place Area B Slab
on Grade
Progress Photos
Wet Cure Area A
and B
Progress Photos
Area C Slab on
Grade Form Work
Progress Photos
Placed Area C
Stone
Progress Photos
Placed Area C
Vapor Barrier
Progress Photos
Placed Area C
Rebar Mesh
Progress Photos
Area C
Underground
Electrical Conduit
Conclusion of Weekly Update 05/31/2019