welcome
TRANSCRIPT
WELCOME
CIVIL CONSTRUCTION OF
A HOUSE
(TIME TAKEN)
COST ESTIMATEDesign/Approval of plan NILMake foundation/build super structure
6,00,000
Select &order Electrical & other accessories
1,00,000
Wiring of the building 20,000Carpentry works 1,50,000Laying of Roof 5,00,000Wall plastering/laying floors/Painting
70,000
Fixing of fittings(Sanitary, electrical etc)
20,000
Giving power and water connections for the site
30,000
Final polishing ,testing & handing over
10,000
UNIT - 2Establishing the
Project
Feasibility ReportPART 1: 1.Technical configuration is defined2.Performance requirements for various SYSTEMS,SUB-
SYSTEMS & KEY EQUIPMENTS are specified3.Cost estimate for the project is FROZEN4.Techno-Economic viability is EXAMINED,APPRAISED &
APPROVED5.An over all implementation schedule is DRAWN. Part 2 :6.Financial arrangements made to implement the project7.A project Manager has been appointed8.Pre- project Activities completed & “A ZERO DATE IS
FIXED”
Feasibility Report 1.Raw Materials(RM) Survey2.Demand Survey3.Technical Study of Product pattern, Process
selection, Plant Size and Raw Materials (RM) Requirements
4.Location Study5.Project capital cost estimates & Sources of
Finance6.Profitability & Cash Flow analysis &7.Cost-Benefit Analysis
Technical aspectsProduct PatternProcess selectionplant sizeRaw materials requirementsLocation Study
Financial aspects TYPES OF FINANCING
FINANCIAL INSTITUTIONS
FOREIGN INSTITUTIONS
NATIONAL INSTITUTIONS
TYPES OF COST ESTIMATESOrder of Magnitude Estimate: ( +/_60
%Accuracy)Study Estimate: ( +/_ 30 % Accuracy)Preliminary Estimate : ( +/_ 20 %
Accuracy)Definitive Estimate: ( +/_ 10 %
Accuracy)Detailed Estimate: ( +/_ 05 %
Accuracy)
Finalization of Project Implementation Schedule
TIME STUDY APPROACH PREVIOUS PROJECT DATAGUESTIMATING APPROACHRANGE ESTIMATESTIME TAKEN Vs TIME REQUIREDESTIMATES FROM VENDORS & CONTRACTORSALLOCATED & COMMITTED TIME
Evaluation of Project Profitability
PAY BACK PERIOD ( PBP )RETURN ON INVESTMENT ( ROI ) NET PRESENT VALUE ( NPV )INTERNAL RATE OF RETURN ( IRR )BENEFIT COST RATIO ( BCR )SOCIAL PROFITABILITY
THANKYOU