welcome to amar groupamargroup.com.au/pdf/amar_capabilities_statement-jan_2014.pdf · amar groups...

13

Upload: others

Post on 22-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Welcome to AMAR Groupamargroup.com.au/pdf/AMAR_Capabilities_Statement-Jan_2014.pdf · AMAR Groups task was to manage the disconnection and refurbishment of the electrical infrastructure
Page 2: Welcome to AMAR Groupamargroup.com.au/pdf/AMAR_Capabilities_Statement-Jan_2014.pdf · AMAR Groups task was to manage the disconnection and refurbishment of the electrical infrastructure

Welcome to AMAR Group

AMAR Group offers expertise in all facets of Electrical Design, Consultation,

Installation, Construction, Project Management, Commissioning and

Operations. Together these skills compliment our ability to provide the Energy,

Resource and Industrial sectors, along with our local Commercial and Domestic

clients, with Efficient Solutions to meet their Electrical requirements.

Since its beginning, AMAR Group has been based in the Barossa Valley, and

has grown to be a reputable company providing Electrical Services throughout

Australia and within our Local Community for over 10 years.

Anthony Mitchell and Andrew Reimann lead AMAR Group with specific

expertise, bought together with experience across numerous electrical

industries.

AMAR Group provides Professional Services and Quality workmanship for all

work completed, from Domestic Installations and repair jobs, through to the

most complex Industrial projects. AMAR Group is backed by an experienced

network of professional personnel who are capable of providing TURNKEY

Project Solutions including Design, Installation, Commissioning, Maintenance

and Operations.

Page 3: Welcome to AMAR Groupamargroup.com.au/pdf/AMAR_Capabilities_Statement-Jan_2014.pdf · AMAR Groups task was to manage the disconnection and refurbishment of the electrical infrastructure

Solutions

AMAR Group provides services Australia wide for Total Project Solutions.

Electrical Installations

Domestic, Commercial and Industrial

Residential Subdivision Services

High Voltage Jointing, Switching and Commissioning

Construction Temporary Power

Earth Grids and Lightning Protection

Water Treatment plants

Winery Transfer Systems

Public Lighting

Power Generation

Power Station Construction

Grid Connections – Generators and Substations

Standby Generators

Cogeneration

Commissioning

Operations and Maintenance

AEMO Compliance

Electrical Testing

Earth Systems and Grid Testing

High Voltage Cable Testing

AS3017 and AS3000 Electrical Installation Testing

Test and Tag Equipment Compliance Testing

Consultancy Services

Power generation design concepts

Design Review

Assistance with grid connections

3rd Party Assessment

Project & Site Management Services

Page 4: Welcome to AMAR Groupamargroup.com.au/pdf/AMAR_Capabilities_Statement-Jan_2014.pdf · AMAR Groups task was to manage the disconnection and refurbishment of the electrical infrastructure

Occupational health & Safety

AMAR Group maintains the highest regards for the safety of our workers, clients

and all personnel involved.

All AMAR Group personnel are dedicated to providing services to our clients

which meet all expectations, delivering projects on time, within budget, and

meeting all Occupational Health and Safety requirements.

AMAR Group has built its OH&S system to meet and exceed the requirements

of the AS/NZS 4801:2001 work, health & safety management systems.

AMAR Group will so far as reasonably practical comply with the relevant Work

Health and Safety Act and Regulations.

The most important reasons to be safe aren’t at work

…..They’re at home

Page 5: Welcome to AMAR Groupamargroup.com.au/pdf/AMAR_Capabilities_Statement-Jan_2014.pdf · AMAR Groups task was to manage the disconnection and refurbishment of the electrical infrastructure

Our Commitment

VISION

AMAR Group strives to provide services which continually surpass our clients’

expectations whilst providing the efficient outcomes expected.

VALUES

AMAR Group values honest, open relationships with all stake holders including

our suppliers, clients and the communities in which we operate. We operate a

transparent and enjoyable environment for all personnel we have contact with.

ENVIRONMENT

AMAR Group value the environments around us, the communities in which we

live and work, and ensure our actions will have minimal impact during and after

our projects are completed.

COMMUNITY

AMAR Group provides project solutions in many locations throughout Australia,

therefore having a large number of communities and causes in which we

support.

AMAR Group support local communities by employing quality local personnel

and suppliers for our projects, allowing us to provide cost effective solutions

whilst providing opportunities for local communities.

OCCUPATIONAL HEALTH and SAFTEY

AMAR Group is committed to ensuring the welfare of its employees, contractors

and the public at all times. We strive to be leaders in all areas of Occupational

Health and Safety, by using best practice and procedures.

Page 6: Welcome to AMAR Groupamargroup.com.au/pdf/AMAR_Capabilities_Statement-Jan_2014.pdf · AMAR Groups task was to manage the disconnection and refurbishment of the electrical infrastructure

The AMAR Group Team

At AMAR Group, our people are our most valuable assets; they represent the

company and our values. We actively seek out individuals who stand out in their

field to offer a high level of quality and efficiency. Together we work closely with

our customers to ensure compliance with all procedures.

AMAR Group Directors

Anthony Mitchell has worked within the Power Generation industry for over

twenty years and his knowledge and expertise is highly regarded throughout

Australia. Anthony has broad knowledge of the Mining, Resource and Heavy

Industrial fields along with AEMO Compliance requirements.

Andrew Reimann has worked throughout Australia in the Industrial,

Commercial and Power Generation sectors for almost fifteen years and has

received industry recognition for his projects. Andrew has wide experience in

Construction Management, Operations and compliance to Australian Standards.

Together our directors have experience in Design, Installation, Project

Management and commissioning of over 200MW of power generation, and all

facets of Diesel and Gas fuelled power generation installations. Installation and

Commissioning of High voltage switchgear, switchyards, transformers,

underground reticulation systems and more recently commissioning of the

Adelaide Desalination Plant Electrical Reticulation Systems are among the

latest projects AMAR Group are involved in.

Page 7: Welcome to AMAR Groupamargroup.com.au/pdf/AMAR_Capabilities_Statement-Jan_2014.pdf · AMAR Groups task was to manage the disconnection and refurbishment of the electrical infrastructure

Recent Projects

Lonsdale 20MW Diesel Peaking Power Station Relocation (2010–2011)

AMAR Group responsibilities for this project included; design input, electrical

supervision, AEMO requirements, technical support and liaising with ETSA

Utilities for the grid connection, validation testing and protection system

commissioning.

This project, located in Lonsdale South Australia, required the de-

commissioning of eighteen containerised generator sets, diesel fuel storage

tanks, four 11kV Ring Main Units, two 11kV Fault Current Limiting Reactors

along with the control and protection systems.

The existing equipment, along with a new concrete pre-cast control room and

switch room, complete with 11kV High Voltage switchboard was instated on the

new site. New auxiliary distribution boards, control panels, control systems and

auxiliary services were installed and commissioned. Two 11kV high voltage

circuits were installed from the new switchroom to the nearby ETSA substation

to enable the exporting of 20MW into the electricity network.

AMAR group were contracted by Cummins Power Generation, Energy Solutions

Business to assist in providing their client, Infratil Energy Australia, the

relocated Peaking Power Station Solution. This was to make way for a new

65MW Peaking Power Station to be built on the site of the existing plant.

Page 8: Welcome to AMAR Groupamargroup.com.au/pdf/AMAR_Capabilities_Statement-Jan_2014.pdf · AMAR Groups task was to manage the disconnection and refurbishment of the electrical infrastructure

Pt Stanvac 65MW Diesel Peaking Power Station (2010 – 2011)

AMAR Group worked closely with the Cummins Power Generation, Energy

Solutions Business construction and engineering team to assist in providing

their client, Infratil Energy Australia a high performance 65MW Diesel Peaking

Power Station.

AMAR Group responsibilities for this project included; initial engineering design

input, installation and commissioning of the 66kV substation, construction

temporary power, supervision of electrical installation, technical support and

liaison with ETSA Utilities for the grid connection, AEMO requirements,

validation testing and full commissioning.

This project consisted of thirty-six diesel generators capable of providing nearly

60MW of electricity into the national electricity grid. These generators are

installed within six acoustically designed buildings, all containing auxiliary power

and lighting systems, control systems and mechanical services. The 11kV

alternators are connected to 11kV switchboards, which in turn are connected to

11kV/66kV power transformers connected to a 66kV switchyard and remotely

Page 9: Welcome to AMAR Groupamargroup.com.au/pdf/AMAR_Capabilities_Statement-Jan_2014.pdf · AMAR Groups task was to manage the disconnection and refurbishment of the electrical infrastructure

controlled switching equipment. One 66kV circuit run underground to the nearby

ETSA Utilities sub-station where the Power Station is connected to the 66kV

electricity network.

This plant is capable of being fully online within five minutes and supplying

nearly 60MW into the national electricity grid to help meet short-term peak load

demand on the distribution network.

Royal North Shore Hospital Co-Generation Plant (2011 – 2012)

AMAR Group was engaged by Cummins Power Generation, Energy Solutions

Business to provide technical support, complete the electrical and control

system installation, and provide testing and commissioning services for the

new, NSW Health, Royal North Shore Hospital located in St Leonards, 10km

from Sydney.

The project consisted of two 2MWe gas engines to provide 4MWe of

cogeneration base load power, and two 2MWe diesel standby engines. The

11kV Generators are connected to the Hospital High Voltage distribution

system, Capable of being synchronised with the local electricity network and

able to meet the total electricity load of the hospital services if required.

The cogeneration plant provides waste heat recovery via the exhaust gas heat

exchangers while mechanical ventilation ensure the plant room and engines are

supplied with fresh air for its safe and efficient operation. Gas supply and

control systems, Diesel fuel storage and supply systems, along with Cummins

Page 10: Welcome to AMAR Groupamargroup.com.au/pdf/AMAR_Capabilities_Statement-Jan_2014.pdf · AMAR Groups task was to manage the disconnection and refurbishment of the electrical infrastructure

own Generator set control system, are part of the fully integrated & automatic

solution provided to the project head contractor, Thiess Pty Ltd.

AMAR Group were able to deliver our works on time, within budget and

provided Cummins Power Generation with a high quality installation receiving

accolades from all stake holders involved with this Project.

SA Water - Adelaide Desalination Plant (2011 – 2013)

AMAR Group were Contracted by Abigroup Contractors Pty Ltd and McConnell

Dowell Constructors (AUST) Pty Ltd to provide Electrical Commissioning

Services.

AMAR Group responsibilities for this project include lead electrical

commissioning engineer, electrical supervision, technical support and liaison

with ETSA utilities for the grid connection, validation testing and commissioning

of the 11kV distribution network, electrical infrastructure and the plant &

equipment.

Page 11: Welcome to AMAR Groupamargroup.com.au/pdf/AMAR_Capabilities_Statement-Jan_2014.pdf · AMAR Groups task was to manage the disconnection and refurbishment of the electrical infrastructure

The Adelaide Desalination Plant, located at Lonsdale, South Australia will

provide the city of Adelaide with up to 100Gl of water per year, making it

capable of providing up to 50% of Adelaide's domestic water supply.

AGL Moranbah Coal Seam Methane Power Station (2013)

The AGL Moranbah power station consisted of 8 x 1.57MW Cummins

reciprocating coal seam gas lean burn generators that had been in operation for

10 years, these generators were replaced with Cummins 1.75MW.

AMAR Groups task was to manage the disconnection and refurbishment of the

electrical infrastructure and control systems upgrade, reconnect the new

generators and complete the re-energisation and commissioning tasks whilst

the existing station maintained the required output.

Page 12: Welcome to AMAR Groupamargroup.com.au/pdf/AMAR_Capabilities_Statement-Jan_2014.pdf · AMAR Groups task was to manage the disconnection and refurbishment of the electrical infrastructure

AMAR Group Networks

AMAR Group values our clients, the input we have into the success of their

businesses, and strive to provide them with efficient cost effective project

outcomes.

AMAR Group Networks

our clients, the input we have into the success of their

businesses, and strive to provide them with efficient cost effective project

our clients, the input we have into the success of their

businesses, and strive to provide them with efficient cost effective project

Page 13: Welcome to AMAR Groupamargroup.com.au/pdf/AMAR_Capabilities_Statement-Jan_2014.pdf · AMAR Groups task was to manage the disconnection and refurbishment of the electrical infrastructure

Contact AMAR Group

AMAR Group looks forward to discussing your queries and how we can provide

you with solutions to meet your requirements.

Contact AMAR Group Australia wide by calling

1300 554 513

Web: www.amargroup.com.au

Enquiries: [email protected]

Head Office

NURIOOTPA - Barossa Valley

PO Box 1045

Nuriootpa

South Australia 5355

ANTHONY MITCHELL ANDREW REIMANN

TECHNICAL DIRECTOR PROJECT MANAGER

[email protected] [email protected]

0435 880 323 0411 044 209