wellington estate dlf 5 · 2020. 5. 1. · epc company •march 2014 – first techno-commercial...

20
Wellington Estate DLF 5 Solar PV Plant Phase 1 (200 kWp) commissioned on 10 th October 2017

Upload: others

Post on 12-Sep-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

Wellington Estate DLF 5

Solar PV Plant Phase 1 (200 kWp) commissioned on 10th October 2017

Page 2: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

Start of our Solar (Learning) Process…

• January 2014 - First Contact with any SolarEPC Company

• March 2014 – First techno-commercialproposal received for a 116 kWp plant,@Rs.95,000/kWp

• Plan deferred / dropped for following reasons:• New Concept

• Project cost range found prohibitively high andfinancially unviable at that time.

Page 3: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

Our Solar (learning) Process…

Size Price Status

November 2016

Notsubmitted

Not submittedOffer not submitted

January 2017 350kWp 65,000/kWpDesign

submitted

February 2017 150 kWp 59,500/kWpDesign not submitted

February 2017 100 kWp 71,000/kWpDesign not submitted

March 2017 130 kWp 72,000/kWpDesign not

found suitable

May 2017 56.70 kWpRate not

submittedDesign not

found suitable

June 2017 260kWp 55,000/kWpDesign

submitted

Page 4: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

Final Selection in June 2017…

▪ Actively engaged with WECA since Jan 2017.

▪ Shared full details of design data, including shadow simulation and production analysis.

▪ Ready to work on component basis.▪ Offered a choice of component

vendors.▪ Offered same SolarEdge technology, as

was being offered by Havells.▪ Ready to meet WECA target price of

Rs. 50,000 per kWp + tax

▪ Contacted WECA (in June 2017) during finalization with Greenroots.

▪ Not willing to submit full details of design data.

▪ Was outsourcing installation and commissioning; Greenroots being one of their INC vendors.

▪ Not offering a choice of components.▪ Not being very open with technical

information being asked.▪ Introduced WECA to SolarEdge

optimizer technology.

Page 5: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

Project Implementation Process…

▪ For subsidy eligibility, only Indian panels could be selected.

▪ One of the top solar Solar Panel makers in India with a 10-year business success history.

▪ Prompt & quick delivery.

▪ Best in class technology.▪ Enhanced safety features.▪ Longest warranty period.▪ Offering remote online real time

monitoring for life.

Solar Panels Invertors & Optimizers

Selection of main Technology Vendors

Page 6: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

▪Unloading and safe storage ofincoming material on ground level.

▪Carrying all material from ground levelto roof top (via Lift/Stairs).

▪Storage of material on roof top.▪Disturbance to residents from

installation work.

Project Implementation Process…

Logistical Challenges

Page 7: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

Remote Web Monitoring

Page 8: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

Remote Web Monitoring

https://monitoringpublic.solaredge.com/solaredge-web/p/site/public?name=DLF5%20Wellington%20Solar#/dashboard

Page 9: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

Wellington Estate DLF 5

Solar PV Plant Phase 2 (150 kWp) planning started in April 2018

Page 10: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

Wellington Estate DLF 5

Solar PV Plant Phase 2 commissioned on 10th February 2019

Page 11: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

Contribution of Solar Power inCommon Area Electricity

Phase 1 = 200 kWp[~40%]

After Phase 2 = 350 kWp[~70%]

GRID POWERSOLAR POWER

Page 12: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

Annual Financial Savings

AchievedWith 200 kWp

Rs. 20 lac

ExpectedWith 350 kWp

Rs. 33 lac

Page 13: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

Annual Environmental Savings

Current~300 tons After Expansion~500 tons

~1000 trees ~1600 trees

Page 14: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

Wellington Solar Plant Aerial View

Page 15: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

Wellington Solar Plant Aerial View

Page 16: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

Wellington Solar Plant Press Coverage

Page 17: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

Wellington Solar Plant Press Coverage

Page 18: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

▪ Maximum capacity should be installed in oneshot and not in phases.

▪ Best available technology in terms of modules& invertors should be given priority over cost.

▪ Post-installation preventive maintenanceshould be given high priority to derivemaximum plant efficiency.

▪ For plants above 50 kWp, an independentprofessional design consultant should bepreferred.

Learnings from the Experience

Page 19: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for
Page 20: Wellington Estate DLF 5 · 2020. 5. 1. · EPC Company •March 2014 – First techno-commercial proposal received for a 116 kWp plant, @Rs.95,000/kWp •Plan deferred / dropped for

Wellington Estate DLF 5