westside subbasin’s draft groundwater sustainability plan · estimated annual gsp management,...

19
Westside Subbasin’s Draft Groundwater Sustainability Plan Westlands Water District Board of Directors Serving as the Groundwater Sustainability Agency of the Westside Subbasin October 15, 2019 DRAFT 1

Upload: others

Post on 28-May-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

Westside Subbasin’s Draft Groundwater Sustainability Plan 

Westlands Water District Board of Directors Serving as the Groundwater Sustainability Agency

of the Westside Subbasin October 15, 2019

DRAFT 1

Page 2: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

Outline

Groundwater Sustainability Agency

Basin Setting Monitoring Network Projects and Management Actions

(PMAs) Implementation Costs Governance Questions

PRELIMINARY 2

Page 3: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

 

Groundwater Sustainability Agency (GSA) Chapter 1

Sustainable GroundwaterManagement Actrequirements

Westlands Water District andFresno County are the GSAs

Required to submit andadopt GroundwaterSustainability Plan (GSP) byJanuary 31, 2020 to addressundesirable results

PRELIMINARY 3

Page 4: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

Notice and Communication Chapter 2

Hosted 15 Public Outreach Events Provided 43 Board Updates

PRELIMINARY 4

Page 5: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

 

  

Plan Area

• Western Area of theSan JoaquinGroundwater Basin

• Adjacent Subbasins:• Delta‐Mendota,• Kings,• Tulare Lake and• Pleasant Valley

• GroundwaterConditions

• Land Use• Water Supplies• Water Quaility

Chapter 2

Page 6: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

66

Basin Setting (Subsidence) Chapter 2

Land Surface

Clay and silt (aquitard)

Sand and gravel

Pre-Development Post-Development PRELIMINARY

Radar Subsidence Measurements July 2013 to March 2015

Page 7: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

Basin Setting (Subsidence) Chapter 2

Check 20

Check 19

Check 18

Check 17

Check 16

Check 15

PRELIMINARY 7

Page 8: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

PRELIMINARY

Monitoring Network (Considerations)

Sustainability Criteria

Groundwater Levels Undesirable Results Minimum Threshold Measurable Objective

Chapter 3

Groundwater Quality

Page 9: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

9

Monitoring Network (Groundwater Levels)

Monitoring Sites

Chapter 3

Land Surface Subsidence & Compaction Monitoring Sites DRAFT

Page 10: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

PMA No. 1 – Surface Water Deliveries Chapter 4 Total Delivered Water (taf)

PRELIMINARY 10

Page 11: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

 

 

PMA No. 2 ‐ Groundwater Extraction Allocation

Chapter 4

Extraction amount basedon estimated SustainableYield: Previous estimates Numerical model

Distribution on per‐ grossacre

Provisional amount: 0.45AF/acre

Provisional Aquifer‐specificallocation: 0.60 AF/acre

Carryover/bankingpermitted

Augmented through GWCredit Program

Designed to PromoteConjunctive Use

Page 12: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

12

Feasibility demonstrated in2017 pilot study

Retrofitting existing wells Report of Waste Discharge

Permit complete CEQA Review complete

PMA No. 3 – Aquifer Storage and Recovery Chapter 4

DRAFT

Page 13: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

PMA No. 4 – Targeted Pumping Reduction Chapter 4

Incentives to reduce pumping in sensitive areas/period Determined at start of

water contract year Subsidence areas

Alternative sources of water Pumping from unaffected

areas (Upper Aquifer) In‐lieu surface water

provided by District PMA No. 2 may be sufficient

PRELIMINARY 13

Page 14: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

 

   

PMA No. 5 – Recharge Basins Chapter 4

Currently in exploratoryand planning phase

Located on Districtowned land in westernportion of Subbasin

Recharge rate up to 18acre‐ft/day

Contingent ondemonstratingfeasibility

PRELIMINARY 14

Page 15: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

 

Estimated Annual GSP Monitoring Costs Chapter 5

No. Description Estimated Annual 

Cost

1 Groundwater Level Monitoring $10,000

2 Water Quality Monitoring $20,000

3 Land Subsidence Monitoring $14,000

4 Administrative Personnel $170,000

5 Annual Comprehensive DWR Reporting $50,000

Total $264,000

PRELIMINARY 15

Page 16: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

 

 

Estimated Annual GSP Management, Administration and Other Costs

Chapter 5

No. Description Estimated Annual 

Cost

1 Groundwater Metering $15,000

2 Operation and Maintenance $45,000

3 Project Management and Coordination  $100,000

4 Administrative Personnel  $70,000

5 Engineering & Consulting Services $20,000

6 Legal Expenses $50,000

7 Public Outreach $15,000

Total $315,000

PRELIMINARY 16

Page 17: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

 

Governance  Chapter 6

Powers of the GSA Rules and Regulations Specific Powers• Replenishment• Groundwater Storage• Transfers (water, credits, allocations, stored water)• Accounting• Committee formation– Advisory Committee– Technical Advisory Committee

Variances

PRELIMINARY 17

Page 18: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

Next Steps

Host a workshop on October 18th at 1:30P.M.

Host a Special Board Meeting on October30th at 3:00 P.M. to receive publiccomments

Review and respond to public comments Consider adopting the GSP on December17, 2019

PRELIMINARY 18

Page 19: Westside Subbasin’s Draft Groundwater Sustainability Plan · Estimated Annual GSP Management, Administration and Other Costs Chapter 5 No. Description Estimated Annual Cost 1 Groundwater

Questions

Kiti Campbell 559‐241‐6226 [email protected]

PRELIMINARY 19