who wants to build high towers, has to spend time on a...
TRANSCRIPT
Klaus Hudelmaier · Ingenieurbüro für GrundbauBVV Spezialtiefbautechnik Vertriebs GmbHBleibtreustrasse 9, D-81479 Munich/GermanyTel.: +49-(0)89-6 65 19 30Fax: +49-(0)89-6 13 17 [email protected] ko
m D
ESIG
N ·
1 Gm
bH, M
unic
h ·
05.
2004
· #
420
03 ·
NL
0.5
OFFER
The specialist: more than 30 years of activity in special deep foundation.
His success is based on experience and reliability.
Turn his experience to your advantage! From planning
and specialist advice to applications technology com
bined with a variety of high quality specialist machi
nery, everything can be obtained from one source.
Fundamentally safe!
Klaus Hudelmaier has been active in special deep foun-
dation work for more than 30 years as contractor and
expert in the development of projects and applications
technology.
Below please find a range of outstanding projects:
2 3
Who wants to build high towers, has to spend time on a solid base.
Anton Bruckner
One of Munich’s deepest excavations! Since the possi
bility of building to great heights was limited, the
foundations had to be laid at a depth of 30 m.
OFFICE BLOCK FOR "MÜNCHNER RÜCK” REINSSURANCE, MUNICH LEOPOLDSTRASSE
The execution.
The excavation with dimensions of 80 m x 55 m, has
a depth of 31.0 m below ground level.
For securing the excavation a combination of sheet pile
walls and augered piles of 1.200 mm diameter is installed.
After an excavation depth of six metres the excavated
soil is deposited at the
south west side of the
excavation by a 4 m3
wheel loader. From there,
the excavated soil is
transported vertically
upwards by a crawler
The task.
To create the excavation for the new administration
building for "Münchner Rück” reinssurance with seven
storeys underground.
The challenge
* Buildings directly adjoining the excavation site.
* Connecting the excavation to one of Munich’s main
arterial roads.
* Regulations on environmental protection and noise
prevention require water recycling and reduction of
emissions.
* Quaternary groundwater level may not be lowered.
* Tertiary groundwater has to be unconfined.
The soil conditions.
* Two metres of concrete foundations of the previous
building.
* Underneath: gravel, tertiary sands and clay with depo-
sits of limestone.
Seven storeys down to a depth of 31 m.
Contractor for special deep foundation projects
crane with 3 m3 grab (monitored by closed-circuit tele-
vision) and loaded onto lorries. Before the lorries are
allow ed onto the road again, their tyres are cleaned in a
specially developed tyre-wash. Within 9 months 8,300
m2 of sheet pile walls and augered piles, which are
secured by 4 rows of soil anchors, are installed and
130,000 m3 of excavated soil is transported from the
jobsite.
In a 3-path filter system 100 m3 per hour of groundwater,
processing water and jetting water is turned into drinking
water again and re-circulated to groundwater via a
640 m long pipeline and 12 dry wells.
4 5
Always a great challenge: excavations for buildings
that are supposed to rise high up to the sky.
The execution.
The excavation walls for the Deutsche Bank are installed
as a combination of an interpile sheeting in the quater-
nary gravel and a slurry wall in the clay, sand and lime-
stone formations. Because of the 4.5 m thick base plate
and the underground storeys, slurry wall sections with an
installation depth of 22 m are used. The slurry wall is
secured by a total of over 10,000 m of pressure grouted
soil anchors.
The task.
To create the excavation for a building with 40 storeys
above ground level and 3 storeys underground.
The challenge.
* Directly adjacent buildings.
* Extremely difficult soil and groundwater conditions.
The soil conditions.
* Quaternary gravel with groundwater.
* Sands and clay with confined groundwater and
deposits of limestone.
Multi-storey building on good ground.
A total of 2,200 m2 of slurry wall and 1,000 m2 of inter-
pile sheeting are installed in order to create the excava-
tion for one of Germany’s architectural symbols.
During construction much attention is paid to the settle-
ment of the 4.5 m thick base plate. It is monitored by an
extensive measuring programme and – if necessary –
balanced by ballasts fixed to the base plate.
6 7
DEUTSCHE BANK (BANK OF GERMANY), FRANKFURT
Contractor for special deep foundation projects
Behind the excavation the timehonoured law court,
to the right a through road with heavy goods traffic,
to the left a department store. And below two adja
cent roads the tunnels of the "SBahn” (suburban
railway) and the "UBahn” (underground railway).
The execution.
Since the client wants the excavation to be completed in
the shortest possible period of time, a vibrated sheet pile
wall is chosen. In order to check the effect of the vibra-
tions on the vicinity – the law court as well as the
"S-Bahn” and "U-Bahn” – the vibrations are measured. The
measurements reveal that there is no risk of damage to
the law court due to the vibrations. The vibrations
measured in the "S-Bahn” and "U-Bahn” tunnels are below
the limits allowed for these constructions. On the basis
of these results a sheet pile wall is installed down to 16.0
m below ground level and from 11.5 m below ground level
a pile wall is built to support the bottom of the sheet pile
wall and to found the outer walls of the building.
The task.
To create a square excavation with 90 m long sides for
the "Elisenhof”, an office block and commercial centre
well situated in the centre of Munich.
The challenge.
* Immediate vicinity to the old law court.
* Main arterial road with heavy goods vehicle traffic
directly alongside the excavation.
* Two sides of the excavation border on the "S-Bahn”
and "U-Bahn” tunnels.
* Excavation depth: 14 m for four underground levels.
The soil conditions.
* Replenishments down to approx. four metres.
* Gravel down to approx. eight metres; beneath: silty,
fine sand down to a depth of 14 m.
* Below: cohesive tertiary.
* Several groundwater levels.
* First level horizon of groundwater approx. 4.0 m deep.
Gently rocking the foundations of the Law.
Three sides of the sheet pile wall are anchored by pres-
sure grouted soil anchors. On the fourth side such ancho-
rage is not possible due to the "S-Bahn” tunnel.
The solution: a steep slope remains in the excavation and
is secured by a lining. As soon as the construction reaches
the slope the lining wall between sheet pile wall and the
partly finished building is supported by struts and simul-
taneously, the slope is removed from top to bottom.
When the bottom of the foundation is reached, the rest
of the building is finished.
8 9
OFFICE BLOCK AND COMMERCIAL CENTRE "ELISENHOF”, MUNICH
Contractor for special deep foundation projects
Listed buildings in the direct neighbourhood. Building
foundation immersed four metres in groundwater.
A narrow jobsite in the inner city area.
The execution.
For the executing contractor a special proposal is drawn
up: surrounding the excavation by a steel sheet pile wall
secured by rearward anchorage. The sheet piles pene-
trate the deep clay stratum, so a impermeable trough is
created.
The task.
In a heavily built-up area a building is to be built with its
foundation 4 metres below groundwater level. Greatest
demands are made on the construction method for the
building requirements. Due to the buildings directly
adjoining the excavation, which are partly listed, a
method low in vibration but nevertheless economical
has to be used.
0The challenge.
* Seven metres deep excavation, groundwater level
approx. three metres below ground level.
* Lowering the groundwater level is not permissible.
* Creating the excavation as an impermeable trough.
* Precise monitoring of the vibration emissions on
adjacent buildings and observing low limits.
The soil conditions.
* Artificial replenishment down to a depth of four to
five metres.
* Underneath: an up to three metres thick stratum of
peat and silty sands.
* Down to a depth of 14 to 15 metres gravel and sands
which are followed by a very thick clay stratum.
* The groundwater level (about three metres deep)
requires an excavation created as dense trough.
For difficult building conditions there are three remedies: experience, experience, experience.
The adjacent building is listed.
Consequently, the vibration emission
may not exceed 2.0 mm/sec. As instal-
lation aid for the 16.5 m long sheet
piles in pairs low pressure jetting is
chosen. During installation emission
limits are observed. The excavation
with 4,350 m2 of sheet pile wall with
non-polluting lock sealing compound
and 2,050 m of pressure grouted soil
anchors is completed within the
period stipulated.
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
170 100 200 300 400 0 10 20 30 40 0 5 10
Depth [m]
Pressure [Bar] Frequency [Hz] Time
Depth [m] Depth [m]
8.00
11.70
14.20
15.30
17.30100.43
5.50
5.00
3.40
1.70
A
BGS - 7.25 110.70
112.25
102.40
117.73
7.05 GW
1.70 Silt(very sandy, soft) >4<
1.60 Silt(very sandy, soft) >4<
0.50 Peat(sandy, soft) >2<
2.50 Sand
3.70 Sand
2.50 Sand
1.10 Gravel(very sandy) >3<
2.00 Clay(sandy, silty, semisolid) >4-5<
1.70 Filling (bricks, stones, silt, gravel, sand)
starting time 18:07:50ending time 18:13:35date 24.02.1997Max. depth [m] 16,95job site 961072pile no. 15
PDE®
B IV
Cut-off wall with sheet piles
Production methods
Bored piles Sheet pile wall Deep sealing sole ashigh pressure grout injection or plastic gel injection
OK Surface = 117,70
BoEx = 110,70
Clay ~ 102
Sand, Gravel
b
Clay ~ 102
Sand, Gravel
10 11
WEIHERHOF CENTRE, KARLSRUHE
Contractor for special deep foundation projects
Jetting – assisted vibrating
Flushing pipes
Jetting platform
Gravel
Clay
Gravel
Clay
RIEM ARCADEN, MUNICHRIEM
The execution.
The building contractor had planned a single-phase slurry
wall with integrated sheet pile wall of 31 m depth, in
order to penetrate the impermeable clay strata. According
to the special proposal projected and worked out by
Klaus Hudelmaier the single-phase slurry wall with inte-
grated sheet pile wall is replaced by a vibrated sheet pile
wall. The sheet pile wall penetrates the impermeable
tertiary sand at 22 m below ground level.
In order to minimize water ingress below the bottom of
the sheet pile wall and to close the jetting gap which is
necessary for installing the sheet piles, the jetting water
Project development
is replaced by bento-
nite suspension on the
last few metres. Thus,
the sheet pile wall is
tightly joined with the surrounding soil.
The impermeability of the sheet pile wall trough with the
immense dimensions of 330 m x 180 m is further
im proved by the fact that the locks of the sheet pile wall
are sealed with a sealing compound.
The pre-calculated amount of 160 l/sec remaining water
is reduced by 25%.
In his function as technical advisor Klaus Hudelmaier
is as much admired as he is wellknown as executing
contractor. He willingly offers others his vast experi
ence in special deep foundation. This often makes
building projects easier and thus cheaper.
The task.
To enclose the excavation as an impermeable trough.
Installation of a single-phase slurry wall, complete with
sheet piles, secured by two rows of soil anchors.
The challenge.
* Dimensions of the excavation 330 m x 180 m.
* Installation of lining walls in very densely compacted
gravel and sands.
* Short deadline for completion.
The soil conditions.
* Replenishments to a depth of four metres.
* Gravel to a depth of approx. eight metres.
* Underneath: silty, fine sand to a depth of 14 metres.
* Below these strata: clay and fine sands in alternating
strata.
Well-advised thanks to vast experience.
12 13
The execution.
The original plan projected costly soil exchange drillings
in order to install the sheet piles. Upon Klaus Hudelmaier’s
proposal jetting assisted vibrating with a strong vibrator
and a basic machine with rope crowd system is used for
installing 5,100 m2 of sheet piles. At some points the
tertiary clay-silt has to be penetrated down to a depth of
Project development
three metres! A situation which makes the highest demands
on material and machinery.
Thanks to Klaus Hudelmaier’s many years of experience,
especially concerning the selection of the machines to be
used, all sheet piles can be installed in time and the building
project is completed at a much lower cost.
Soft wood flood planeHard wood flood plane
Wieland-Kanal 14m3/s
Power plant
Städtlegraben
90m3 /s
Städtlegr.
(vertie
ft)
UIAG-Kanal
ILLER
Restructuring Distance
AU
DIETENHEIMSeepage water drain pipe
Gießen - Extension
Gießen
70-180l/s
Special building projects require special consultation.
For restoring a section of the River Iller at Illertissen
a soil formation causes great difficulties.
The task.
In the course of the restoration of an Iller section for-
ming the natural border between Bavaria and Baden-
Württemberg, drop structures have to be installed into
the river on a distance of 6 kilometres (3.7 miles).
The challenge.
* Sheet pile wall penetrating clay down to a depth of
three metres.
* Selecting the appropriate vibrator and fitting sheet
pile profiles.
The soil conditions.
Beneath a two to four metres thick stratum of gravel
tertiary formations are situated. They consist of hard,
almost impenetrable clay-silt.
5.100 m2 of sheet piles – and all is in a state of flux
14 15
DROP STRUCTURE IN THE RIVER ILLER AT ILLERTISSEN
In close cooperation with the equipment producing
company LIEBHERRWerk Nenzing GmbH and Dieseko’s
Piling + Vibro Equipment, Klaus Hudelmaier offers his
customers extensive and competent advice as well as
complete support in applications technology.
A combination offering a competent link between
applications technology and equipment technology.
EQUIPMENT TECHNOLOGY
Consultation.
* On special technical solutions
* On applications technology
* On the selection of equipment
* On job scheduling
That is the way to carry out building projects
perfectly.
Phone: +49(0)896 65 19 30
Email: k.hudelmaier@bvvspezialtiefbau.de
Everything from one source. Consultation – selection of applications technology – selection of equipment.
Salesrental
16 17
Since 1 April 1995, Klaus Hudelmaier is managing partner of
the BVV Spezialtiefbautechnik Vertriebs GmbH in Munich,
which he also founded.
Born in 1942, he first learned bricklaying after leaving
school.
After finishing studies to be a civil engineer at the colleges
of Stuttgart and Munich he held various professional posi-
tions in special deep foundation companies, among others
as construction manager and assessor in the foundation
laboratory of the Sager & Woerner company, as managing
director of the TerraGrundbau GmbH and as partner and
managing director of the Techno Grundbau GmbH in
Munich.
Personal data.
VITA KLAUS HUDELMAIER
18
In 1988 he opened his own engineering company for foun-
dation and soil mechanics.
Since many years a close cooperation in the field of equip-
ment development and application systems in special deep
foundation exists between Liebherr-Werk Nenzing GmbH,
Dieseko Verhuur B.V. in Sliedrecht, his engineering company
and BVV.