1
Wind Energy Hamburg 2018
Practical Engineering to Mitigate
Subsea Power Cable RisksSubsea UK 26.09.2018
![Page 3: Wind Energy Hamburg 2018 - Subsea UK](https://reader030.vdocument.in/reader030/viewer/2022012717/61af46805f7ca47dae017797/html5/thumbnails/3.jpg)
3
BPP-Cables Overview
BPP-TECH (Parent)
Specialist Engineering company working in the offshore energy, & insurance industries
▪ Vessel and subsea equipment
▪ Power cables, risers, umbilicals, flexibles and hoses
▪ Delivery Management & QA/QC
▪ Engineering design analysis
▪ Risk & reliability
▪ Mooring assessments
▪ Instrumentation & monitoring
BPP-Cables
Established in 2009 (owned by BPP-TECH and Keppel Offshore & Marine)
London - Houston – Jakarta - Aberdeen – Newcastle
Complementary skill sets brings variety for engineers
![Page 4: Wind Energy Hamburg 2018 - Subsea UK](https://reader030.vdocument.in/reader030/viewer/2022012717/61af46805f7ca47dae017797/html5/thumbnails/4.jpg)
4
Our specialist areas:
Our specialist areas include:
▪ Reducing project risks & costs
▪ Optimised cable designs & fitness for purpose reviews
▪ Engineering analysis and advice regarding installation / protection / repair
▪ In-depth knowledge of marine & subsea equipment
▪ Engineering and management support services
▪ Whole or part project delivery management
▪ Highly skilled on-site / on-board engineers
▪ Insured risk & forensic failure analysis
Independent perspective
![Page 5: Wind Energy Hamburg 2018 - Subsea UK](https://reader030.vdocument.in/reader030/viewer/2022012717/61af46805f7ca47dae017797/html5/thumbnails/5.jpg)
5
Offshore Energy Experience since 1980’s
Engineering principles apply across the subsea spectrum…
![Page 6: Wind Energy Hamburg 2018 - Subsea UK](https://reader030.vdocument.in/reader030/viewer/2022012717/61af46805f7ca47dae017797/html5/thumbnails/6.jpg)
6
Subsea Cable RiskWe can input at any stage of the process
▪ Risks exist throughout the power cable lifecycle
▪ Wide variety of risks and ways in which they can be addressed
▪ Risks are present during
Design of Cables &
Infrastructure
Manufacture & Factory
Acceptance Testing
Packing, transportation
& storage
Installation & burial
ServiceRecovery &
Repair
![Page 7: Wind Energy Hamburg 2018 - Subsea UK](https://reader030.vdocument.in/reader030/viewer/2022012717/61af46805f7ca47dae017797/html5/thumbnails/7.jpg)
7
Subsea Cable Risk
Planning is key
![Page 8: Wind Energy Hamburg 2018 - Subsea UK](https://reader030.vdocument.in/reader030/viewer/2022012717/61af46805f7ca47dae017797/html5/thumbnails/8.jpg)
8
Cable Engineering – Tools for the JobBPP-Cables evaluate and optimise cable designs
▪ Constructional reviews
▪ Finite Element for design verification, parametric models, local fatigue and stresses
▪ Global & local including laying, hauling, bending, crushing and side wall pressure calculations
▪ Dynamic, including clashing and extreme loading
▪ Thermal analysis and cable rating calculations
▪ Fatigue and service life assessments
▪ Environmental Impact
▪ Installation methodologies
▪ Mechanical, electrical and environmental testing
Quality toolbox contains selection of tools
Abaqus Ansys BPP-Softcore ETAP OrcaFlex SolidWorks
![Page 9: Wind Energy Hamburg 2018 - Subsea UK](https://reader030.vdocument.in/reader030/viewer/2022012717/61af46805f7ca47dae017797/html5/thumbnails/9.jpg)
9
Design Tools
Software tools allow cable design engineers to:
▪ Rapidly understand the effect of design changes
▪ Optimise power cable and umbilical designs to:
▪ Extend fatigue life
▪ Expand operational envelopes
▪ Verify feasibility of designs for given conditions
Engineering-led projects for:
cable vibration analysis,
roller impact assessment,
H.V. dynamic cable development…
![Page 10: Wind Energy Hamburg 2018 - Subsea UK](https://reader030.vdocument.in/reader030/viewer/2022012717/61af46805f7ca47dae017797/html5/thumbnails/10.jpg)
10
Cable Components & Protections SystemsCable Components
▪ Optimise conductors
▪ Electrical insulation
▪ Shielding materials
▪ Water, oil and gas blocking layers
▪ Mechanical protection
▪ Armouring
Protection Systems
The interface of the cable to the
host structure requires protection:
▪ Bend restrictors
▪ Bend limiters
▪ Bend stiffeners
▪ Articulated armour
Added complexities
![Page 11: Wind Energy Hamburg 2018 - Subsea UK](https://reader030.vdocument.in/reader030/viewer/2022012717/61af46805f7ca47dae017797/html5/thumbnails/11.jpg)
11
Consultancy to aid Decision-making
• Understanding risks
• Minimising those risks
• Improving performance
• Potentially extending operating asset life
Impartial, engineering and experience-based opinions
![Page 12: Wind Energy Hamburg 2018 - Subsea UK](https://reader030.vdocument.in/reader030/viewer/2022012717/61af46805f7ca47dae017797/html5/thumbnails/12.jpg)
12
During Installation▪ Excessive tension, torque and/or bending
▪ Crushing/crimping
▪ Poor tension control
▪ Looping and kinking during laying
▪ Fatigue during lay suspension
▪ Impact during burial
Prevention is best
![Page 13: Wind Energy Hamburg 2018 - Subsea UK](https://reader030.vdocument.in/reader030/viewer/2022012717/61af46805f7ca47dae017797/html5/thumbnails/13.jpg)
13
During ServiceIn-service subsea cable failures can be caused by sub-optimal design, installation and/or third party
damage. Typical problems include one or more of the following:
▪ Mechanical damage including wear and fatigue
▪ Overheating
▪ Sub-standard materials/material degradation
▪ Layer separation and instability
▪ Thermo-mechanical movement
▪ Overbending
▪ Crushing
▪ Corrosion
▪ Gassing
▪ Problems with joints, connectors and terminations
▪ Dropped objects / dragged anchors / fishing / trawling
▪ Scour & shifting sandbanks
▪ Extreme weather
▪ Marine life damage
▪ Contact at cable / pipeline crossing locations
▪ Exposure to adverse agents, temperatures and pressure
Some of the above apply to onshore cables
![Page 14: Wind Energy Hamburg 2018 - Subsea UK](https://reader030.vdocument.in/reader030/viewer/2022012717/61af46805f7ca47dae017797/html5/thumbnails/14.jpg)
14
When it hasn’t gone to plan…
We see things you don’t want to see!
![Page 15: Wind Energy Hamburg 2018 - Subsea UK](https://reader030.vdocument.in/reader030/viewer/2022012717/61af46805f7ca47dae017797/html5/thumbnails/15.jpg)
15
…and investigate possible causes…
Dissection, Testing and Client Confidentiality
![Page 16: Wind Energy Hamburg 2018 - Subsea UK](https://reader030.vdocument.in/reader030/viewer/2022012717/61af46805f7ca47dae017797/html5/thumbnails/16.jpg)
16
…and go back a few spaces and we try to find
solutionsIdeally, engage BPP at an early stage of the process
▪ Risks exist throughout the power cable lifecycle
▪ Wide variety of risks and ways in which they can be addressed
▪ Risks are present during
Design of Cables &
Infrastructure
Manufacture & Factory
Acceptance Testing
Packing, transportation
& storage
Installation & burial
ServiceRecovery &
Repair
![Page 17: Wind Energy Hamburg 2018 - Subsea UK](https://reader030.vdocument.in/reader030/viewer/2022012717/61af46805f7ca47dae017797/html5/thumbnails/17.jpg)
17
Summary
BPP Cable Lifecycle Knowledge
Design and Manufacture – Array and Export
Installation
Protection
Performance
Incidents, Failures and Remedial Actions
Well-placed to support floating offshore wind developments too…
![Page 18: Wind Energy Hamburg 2018 - Subsea UK](https://reader030.vdocument.in/reader030/viewer/2022012717/61af46805f7ca47dae017797/html5/thumbnails/18.jpg)
18
JIP Launching
O & M focus should include Cables – Array and Export - as key infrastructure elements (alongside Topsides)
Let’s evaluate collected data cleverly and use it to:
Improve Performance & Reduce Downtime
Predict Lifespan & Transfer Knowledge to other Assets
Let’s work together
![Page 19: Wind Energy Hamburg 2018 - Subsea UK](https://reader030.vdocument.in/reader030/viewer/2022012717/61af46805f7ca47dae017797/html5/thumbnails/19.jpg)
19
Questions?