WIND FARMS: FROM DEVELOPMENT TO OPERATIONS Orla Nagle UCC, October 22 nd 2012 IEI Young Engineers Society

Upload: others

Post on 25-Apr-2020

11 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: WIND FARMS: FROM DEVELOPMENT TO OPERATIONS Wind Farm... · WIND FARMS: FROM DEVELOPMENT TO OPERATIONS OrlaNagle UCC, October 22 nd 2012 ... • Prelim Grid Connection Assessment

WIND FARMS:

FROM DEVELOPMENT

TO OPERATIONS

Orla Nagle

UCC, October 22nd 2012

IEI Young Engineers Society

Page 2: WIND FARMS: FROM DEVELOPMENT TO OPERATIONS Wind Farm... · WIND FARMS: FROM DEVELOPMENT TO OPERATIONS OrlaNagle UCC, October 22 nd 2012 ... • Prelim Grid Connection Assessment

Wind Energy Development Stages

Bord Gáís Energy 2

Page 3: WIND FARMS: FROM DEVELOPMENT TO OPERATIONS Wind Farm... · WIND FARMS: FROM DEVELOPMENT TO OPERATIONS OrlaNagle UCC, October 22 nd 2012 ... • Prelim Grid Connection Assessment

Feasibility Assessment :

• Planning Policies – Site Zoning • Ground conditions, Land cover

1. Feasibility

Bord Gáís Energy 3

• Planning Policies – Site Zoning

• Environmental Designation(s)

• Wind Resource

• Site ownership

• Planning History - Site & Area

• Prelim Landscape & Visual Assessment

• Site Drainage & Hydrology

• Ground conditions, Land cover

• Proximity to neighbouring

development

• Archaeological

• Prelim Grid Connection Assessment

• Access & Transportation

• Cumulative Impacts

• Assessment of Alternatives

Page 4: WIND FARMS: FROM DEVELOPMENT TO OPERATIONS Wind Farm... · WIND FARMS: FROM DEVELOPMENT TO OPERATIONS OrlaNagle UCC, October 22 nd 2012 ... • Prelim Grid Connection Assessment

1. Feasibility - cont’d

• Preliminary turbine layout

� Constraints identified

� Viable development areas established

� Site Capacity - no. of turbines

• A feasibility study can prove very effective in

Bord Gáís Energy 4

• A feasibility study can prove very effective in

identifying areas for further investigation and

allows an early focus on relevant issues

• Pre-planning discussions

• Feasibility Stage Consultation

Page 5: WIND FARMS: FROM DEVELOPMENT TO OPERATIONS Wind Farm... · WIND FARMS: FROM DEVELOPMENT TO OPERATIONS OrlaNagle UCC, October 22 nd 2012 ... • Prelim Grid Connection Assessment

• Development Team

• Environmental Assessment:

� Environmental Impact Assessment (EIA)

� Environmental Report

• An EIA is a multi-disciplinary, iterative process

2. Assessment

Bord Gáís Energy 5

• An EIA is a multi-disciplinary, iterative process

designed to identify, characterise and quantify

the likely effects of a proposed development on

the environment

• The approach to an EIA should be informed by:

� Statutory requirements (EIA Directive and EIA Regs)

� Consultation with statutory and non-statutory consultees

� Current guidance and best practice

Page 6: WIND FARMS: FROM DEVELOPMENT TO OPERATIONS Wind Farm... · WIND FARMS: FROM DEVELOPMENT TO OPERATIONS OrlaNagle UCC, October 22 nd 2012 ... • Prelim Grid Connection Assessment

2. Environmental Assessment

& Planning Application - cont’d

Bord Gáís Energy 6

Page 7: WIND FARMS: FROM DEVELOPMENT TO OPERATIONS Wind Farm... · WIND FARMS: FROM DEVELOPMENT TO OPERATIONS OrlaNagle UCC, October 22 nd 2012 ... • Prelim Grid Connection Assessment

• Typical Planning Process

2. Assessment – cont’d

Bord Gáís Energy 7

• Other possible consents & contracts:

� CER - License to Construct, Authorisation to Generate

� Felling License – Forestry Services

� Grid Connection Agreement - Eirgrid

� Land Lease Agreement

Page 8: WIND FARMS: FROM DEVELOPMENT TO OPERATIONS Wind Farm... · WIND FARMS: FROM DEVELOPMENT TO OPERATIONS OrlaNagle UCC, October 22 nd 2012 ... • Prelim Grid Connection Assessment

3. Construction Stage

• Development & implementation of a

Construction & Environmental

Management Plan (CEMP), which defines

� work practices

� construction management procedures

� environmental responsibilities

Bord Gáís Energy 8

� environmental responsibilities

Ensuring environmental protection and

planning compliance during development

construction

• Contractual requirement for Civil

Contractor, Turbine Contractor, Electrical

Contractor etc.

Page 9: WIND FARMS: FROM DEVELOPMENT TO OPERATIONS Wind Farm... · WIND FARMS: FROM DEVELOPMENT TO OPERATIONS OrlaNagle UCC, October 22 nd 2012 ... • Prelim Grid Connection Assessment

3. Construction Stage – cont’d

• Surface Water Management Plan:

� Site Hydrology

� Drainage Infrastructure

� Erosion & Sediment Control – buffer

zones, silt traps, silt fencing etc.

� Watercourse Crossings – bridges, culverts

Bord Gáís Energy 9

� Watercourse Crossings – bridges, culverts

� Materials Storage – fuels, oils etc.

� Consultation – IFI, OPW etc.

Page 10: WIND FARMS: FROM DEVELOPMENT TO OPERATIONS Wind Farm... · WIND FARMS: FROM DEVELOPMENT TO OPERATIONS OrlaNagle UCC, October 22 nd 2012 ... • Prelim Grid Connection Assessment

Benefits of a CEMP & Good Environmental Practice on Site:

3. Construction Stage – cont’d

Bord Gáís Energy 10

Page 11: WIND FARMS: FROM DEVELOPMENT TO OPERATIONS Wind Farm... · WIND FARMS: FROM DEVELOPMENT TO OPERATIONS OrlaNagle UCC, October 22 nd 2012 ... • Prelim Grid Connection Assessment

Questions?