wind handbook wind energy project giz pecc3 eng

31

Click here to load reader

Upload: ai-viet

Post on 08-Oct-2014

82 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: Wind Handbook Wind Energy Project GIZ PECC3 ENG

15.06.2011 Seite 1Page 115.06.2011 Seite 1

GUIDELINE ON WIND POWER PLANNING IN VIET NAM

Presenter: Nguyen Hoang Dung

Hanoi, June 03rd, 2011GIZ/MoIT Wind Energy Project

Page 2: Wind Handbook Wind Energy Project GIZ PECC3 ENG

AGENDA

● Introduction

● Steps and procedures of wind power planning on provincial level

● Methodology for identifying sites for wind power development

● Content of the wind power planning on provincial level

15.06.2011 Seite 2Page 2

● Monitoring and evaluation

● Lessons learnt from the study on wind power planning in Binh Thuan province

15.06.2011

Page 3: Wind Handbook Wind Energy Project GIZ PECC3 ENG

NECESSITY OF WIND POWER DEVELOPMENT IN VIET NAM (1)

● Using renewable energy helps to reduce independence onconventional fuel resources and environmental pollutionWind power is paid attention because of:

● Low production cost

● Save land resources

● High potential

● Short time of construction

15.06.2011 Seite 3Page 3

● Short time of construction

● Technologies have been developed to the provenlevel

15.06.2011

Page 4: Wind Handbook Wind Energy Project GIZ PECC3 ENG

● Global installed capacity by end of 2010 is 196,6 GW.

● Only in 2010 the additional installed capacity is 37,6MW(increase of 23,6% compared with 2009)

● VN: by end of 2010, 20 turbines with total capacity of 30MWhave been installed

● According to the Strategy and Master Plan on RE Developmentfor Viet Nam up to 2015, with an extension up to 2025, RE

NECESSITY OF WIND POWER DEVELOPMENT IN VIET NAM (2)

15.06.2011 Seite 4Page 4

for Viet Nam up to 2015, with an extension up to 2025, REaccounts for 4,8%

● 8/2010, WS on ‘Regulation on management of constructioninvestment of WPP in Viet Nam” by MOIT

15.06.2011

Page 5: Wind Handbook Wind Energy Project GIZ PECC3 ENG

NECESSITY OF PREPARING PROVINCIAL WIND POWER PLANNING

● Investors identify themselves potential sites

● Issues of land use

● Development in coherence with local and national power development plan

15.06.2011 Seite 5Page 5

power development plan

15.06.2011

Page 6: Wind Handbook Wind Energy Project GIZ PECC3 ENG

RATIONAL AND OBJECTIVES OF THIS MANUAL

● Within the project ‘Establishment of legal framework andtechnical assistance for grid connected wind power in VietNam’, technical assistance in wind power planning onprovincial level

● Strong need to develop this guideline after the cooperation withBinh Thuan province on wind power planning. The guidelinecould facilitate other provinces in dealing with issues whileconducting wind power planning

15.06.2011 Seite 6Page 6

conducting wind power planning

● Focus on methodology and on identification of suitable sites forwind power development

15.06.2011

Page 7: Wind Handbook Wind Energy Project GIZ PECC3 ENG

TARGET GROUP OF THE MANUAL

● Authorities in provinces, decision makers on different levels

● Consultants agencies

15.06.2011 Seite 7Page 7

● Investors, producers and interested

15.06.2011

Page 8: Wind Handbook Wind Energy Project GIZ PECC3 ENG

PROCEDURES OF WIND POWER PLANNING ON PROVINCIAL LEVEL

Quy hoạch phát triển

22Consultant conducts planning

33

11 Selection of planning consultant

Planning is approved by Provincial

15.06.2011 Seite 8Page 8

triển điện lực

33

44Planning is approved by MOIT

55Planning published by Provincial PC

Planning is approved by Provincial People’s Committee

Page 9: Wind Handbook Wind Energy Project GIZ PECC3 ENG

FUNDAMENTAL OF WIND POWER PLANNING

● Wind power is kind of energy source, thus planning must complywith technical regulations of the power sector, be compatible withdevelopment planning of other power systems and of other sectors.

● Planning of WP shall meet the following requirements:

● Consistency with local socioeconomic development plans andother related plans

● Selection of optimal sites, the effective use of the country’s

15.06.2011 Seite 9Page 9

● Selection of optimal sites, the effective use of the country’senergy resources

● Consistency with the national power development plan, theprovincial power development plan

15.06.2011

Page 10: Wind Handbook Wind Energy Project GIZ PECC3 ENG

ROLES AND RESPONSIBILITIES OF RELATED ORGANIZATION

Submitted to MOIT for approval

Approval decisionMinistry of Industry and

Trade (MOIT)

Provincial People’s

Committee (PPC)Department of Planning and

Investment (DPI)

15.06.2011 Seite 10Page 1015.06.2011

Coordinating with

Submitted to PPC for endorsement

Department of Industry and Trade (DoIT)

Consulting Unit

Investment (DPI)

Department of Natural Resources and Environment

(DoNRE)

Local Power Companies

District People’s Committee

Other related organisations

Page 11: Wind Handbook Wind Energy Project GIZ PECC3 ENG

● Step 1: Preliminary identification of potential areas

● Step 2: Identifying concrete sites suitable for wind power development

METHODOLOGY FOR IDENTIFYING SITES FOR WIND POWER DEVELOPMENT

Potential areas

(step 1)

Provincial administration border

15.06.2011 Seite 11Page 1115.06.2011

● Step 3: Selecting suitable sites for integration into the wind power development plan by means of grading these sites according to ranking criteria.

Suitable areas

(step 2)

(step 2)

Selection of

sites for the

plan (step 3)

Page 12: Wind Handbook Wind Energy Project GIZ PECC3 ENG

APPROACH METHODOLOGY TO WAsP (Wind Atlas Analysis and Application Program)

MODEL FOR ROUGHNESS OF TERRAINInput data: Terrain classification

MODEL FOR MOUNTAINEOUS TERRAIN Input data: Height contour lines

GENERALISED WIND CLIMATE

15.06.2011 Seite 12Page 1215.06.2011

INPUT DATAWind and wind direction

MODEL FOR SHELTERING OBSTACLESInput data: Position and dimensions of objects

Input data: Terrain classification

RESULTSWind regime at concrete area

Page 13: Wind Handbook Wind Energy Project GIZ PECC3 ENG

EXCLUSION AND BUFFER ZONES

● Paddy fields

● Residential or office land

● Land reserved for national security and defence

● Land for industry and production enterprises

● Land for traffic, transport routes, railways, land roads and other traffic structures

● Rivers, streams, ponds, lakes and irrigation reservoirs

15.06.2011 Seite 13Page 1315.06.2011 Seite 13

● Rivers, streams, ponds, lakes and irrigation reservoirs

● Land for cemeteries and burial grounds

● Nature reserves

● Tourist areas

● Religious or worship areas

● Protected, natural or ecological forests

These areas plus their surrounding vicinities (called ‘buffer zones’) shall be excluded to mitigate the impacts of the operation of wind turbines/wind farms on them

15.06.2011

Page 14: Wind Handbook Wind Energy Project GIZ PECC3 ENG

INFRASTRUCTURE REQUIREMENTS

● Topography

● Land type

● Access to national power grid

● Access and transportation

● Environmental issues (erosion, humidity, floods).

15.06.2011 Seite 14Page 1415.06.2011 Seite 14

floods).

● Site scale

15.06.2011

Page 15: Wind Handbook Wind Energy Project GIZ PECC3 ENG

APLICATION OF GIS IN PLANNING

● A geographical information system (GIS) tool issuitable planning mentioned above becauseactivities such as defining exclusion areas and bufferzones, and identifying distances and suitable areasare easy to perform using GIS. Furthermore, GIS isalso suitable for managing, upgrading and reporting

15.06.2011 Seite 15Page 15

also suitable for managing, upgrading and reportingon planned areas.

● Application of MapInfo GIS.

� Examples of GIS application for wind powerdevelopment planning in Binh Thuan

15.06.2011

Page 16: Wind Handbook Wind Energy Project GIZ PECC3 ENG

Based on WB wind atlas, potential wind areas are preliminarily identified (dark and light pink areas)

15.06.2011 Seite 16Page 1615.06.2011

areas)

Page 17: Wind Handbook Wind Energy Project GIZ PECC3 ENG

3 wind measurement towers are installed in potential areas for 12 months to map wind potential of those areas,

15.06.2011 Seite 17Page 1715.06.2011

those areas, such as in TuyPhong, Bac Binhand Tien Thanh

Page 18: Wind Handbook Wind Energy Project GIZ PECC3 ENG

The three maps are then combined into one map of wind potential.

15.06.2011 Seite 18Page 1815.06.2011

Page 19: Wind Handbook Wind Energy Project GIZ PECC3 ENG

Higher potential areas are then selected (coloured areas).

15.06.2011 Seite 19Page 1915.06.2011

Page 20: Wind Handbook Wind Energy Project GIZ PECC3 ENG

Based on the topographical maps, steep areas not suitable for wind power development under the present

15.06.2011 Seite 20Page 2015.06.2011

present conditions are marked (red coloured areas)

Page 21: Wind Handbook Wind Energy Project GIZ PECC3 ENG

Maps of unsuitable areas (with high slope) are arranged on map of potential areas

15.06.2011 Seite 21Page 2115.06.2011

Page 22: Wind Handbook Wind Energy Project GIZ PECC3 ENG

Excluded areas are arranged …

15.06.2011 Seite 22Page 22

arranged …

Page 23: Wind Handbook Wind Energy Project GIZ PECC3 ENG

… as well as

15.06.2011 Seite 23Page 23

… as well as buffer areas

Page 24: Wind Handbook Wind Energy Project GIZ PECC3 ENG

The remaining coloured areas are suitable areas for wind power development planning

15.06.2011 Seite 24Page 2415.06.2011

Page 25: Wind Handbook Wind Energy Project GIZ PECC3 ENG

CONTENT OF WIND POWER PLANNING ON PROVINCIAL LEVEL

● Summary of findings● Introduction● Natural conditions and socioeconomic features● Methodology● Evaluation results● Options for connection to the national power grid● Anticipated investment need and financial indicators of

the project

15.06.2011 Seite 25Page 2515.06.2011 Seite 25

the project● Environmental impact assessment● Conclusions and recommendations

15.06.2011

Page 26: Wind Handbook Wind Energy Project GIZ PECC3 ENG

INSPECTION AND SUPERVISION (1)

Supervision of technical implementation

The technique of overlapping layers by GeographicalInformation System (GIS) is new in Viet Nam. This is amodern technique, which is precise, scientific, easilymanageable, updatable and adjustable. However, it requiresthe following conditions:

● Available and suitable input data: This is an important

15.06.2011 Seite 26Page 26

● Available and suitable input data: This is an importantcondition, which decides the quality of planning.

● Planning consultant unit shall have sufficient trained staffand equipment

● Planning management unit shall have well trained,qualified staff and knowledge

15.06.2011

Page 27: Wind Handbook Wind Energy Project GIZ PECC3 ENG

INSPECTION AND SUPERVISION (2)

Monitoring on environmental impacts

● The information from land use maps is not usually updated,leading to differences between what’s on the map and the actualsituation. Therefore, there is a need to compare planned ideaswith the reality on site.

● Monitoring may be easily done by comparing coordinatesobtained from portable GPS equipment with coordinates shownin the map made by software and GIS.

15.06.2011 Seite 27Page 27

in the map made by software and GIS.

● The planning management unit shall also use the sametechnique during site survey to identify possible environmentalimpacts from concrete projects of an investor. The planningmanagement unit may also provide correct advice to theProvincial People’s Committee.

15.06.2011

Page 28: Wind Handbook Wind Energy Project GIZ PECC3 ENG

LESSONS LEARNT FROM BINH THUAN PROVINCE’S CASE

Difficulties and challenges

● Lack of state regulations on contents and procedures for wind power planning

● Low awareness of wind power, its technologies as the wind power industry in Viet Nam

● Difficulty on land use planning

15.06.2011 Seite 28Page 28

Page 29: Wind Handbook Wind Energy Project GIZ PECC3 ENG

LESSONS LEARNT FROM BINH THUAN PROVINCE’S CASE (2)

Questions raised during planning

● WPP is new, therefore, a methodology needs to be developed. During theplanning process, the planning consultant cooperated and shared experienceswith a German consultant (Bosch &Partner). The mapping technique, usingmap to process software and the MapInfo Program 10.0, was introduced asan advanced technique for planning in developed countries. However,because Vietnamese conditions are different to those in Germany in terms ofthe qualification and availability of databases, the planning approachaccording to the methodology presented by the German consultant is not

15.06.2011 Seite 29Page 29

according to the methodology presented by the German consultant is notvery feasible in Viet Nam.

● Criteria for exclusion and buffer areas as a basis for identifying suitable windpower development areas are not available.

● The digital maps of the current status of local land use and plans are createdby an other software, with layers which are not suitable for the MapInfosoftware; therefore, they must be converted.

● Most of the staff are not trained to use GPS software and tools.

15.06.2011

Page 30: Wind Handbook Wind Energy Project GIZ PECC3 ENG

LESSONS LEARNT FROM BINH THUAN PROVINCE’S CASE (3)

Problem solving measures

● After discussions and exchanges of ideas, the planning consultant andGerman consultants reached a consensus. National consultant developed asuitable methodology for planning which is feasible for Vietnameseconditions. This methodology was successfully used in the case Binh Thuan.

● During planning, DoIT Binh Thuan, as advisor to the Provincial People’sCommittee, prepared a temporary regulation on excluded areas and bufferzones. This regulation is temporary and effective in Binh Thuan province

15.06.2011 Seite 30Page 30

only, while waiting for MOIT to promulgate the regulation nationwide.

● The GIZ Wind Energy Project has been highly appreciated for havingproviding with specialists to revise the maps of the current status and landuse plan of Binh Thuan province, and with training and transferringinformation on MapInfo software to related staff. These maps have beenupdated and revised properly and provide important input for planning.

15.06.2011

Page 31: Wind Handbook Wind Energy Project GIZ PECC3 ENG

Thank you very much for your attention!

On behalf of consultant team:1. Nguyễn Hoàng Dũng2. Nguyễn Quốc Khánh

15.06.2011 Seite 31Page 3115.06.2011