windsor solar project - samsung renewable energy€¦ · windsor official plan (see appendix a1)....
TRANSCRIPT
WATER ASSESSMENT REPORT Windsor Solar Project
February 2015
Windsor Solar Project Water Assessment Report
P a g e | i
Table of Contents
Page
1. Introduction ..................................................................................................................................... 1
2. The Proponent ................................................................................................................................. 3
3. Project Location ............................................................................................................................... 4
4. Records Review Purpose .................................................................................................................. 6
5. Records Review Results ................................................................................................................. 10
5.1 Water Bodies .................................................................................................................... 10
5.1.1 Average Annual High Water Mark Determination .............................................. 10
5.1.2 Lakes .................................................................................................................... 10
5.1.3 Lake Trout Lakes .................................................................................................. 10
5.1.4 Permanent and/or Intermittent Streams ............................................................ 11
5.1.5 Seepage Areas ...................................................................................................... 11
5.2 Aquatic Species at Risk ...................................................................................................... 11
5.3 Provincial Plan Areas ......................................................................................................... 12
5.4 Regulated Areas ................................................................................................................ 12
6. Summary of Records Review ......................................................................................................... 13
7. Site Investigation Purpose ............................................................................................................. 14
8. Site Investigation Methodology ..................................................................................................... 15
8.1 Names and Qualifications of Site Investigators ................................................................ 15
8.2 Site Investigation Dates, Times, Duration, and Weather Conditions ............................... 15
8.3 Access to Adjacent Lands .................................................................................................. 16
9. Site Investigation Results ............................................................................................................... 18
9.1 Lakes ................................................................................................................................. 18
9.2 Lake Trout Lakes ............................................................................................................... 18
9.3 Permanent and/or Intermittent Streams ......................................................................... 18
9.3.1 Lappan Drain ........................................................................................................ 18
9.3.2 McGill Drain ......................................................................................................... 20
9.3.3 Rivard Drain ......................................................................................................... 21
Windsor Solar Project Water Assessment Report
P a g e | ii
9.3.4 Rusette Drain ....................................................................................................... 22
9.4 Seepage Areas ................................................................................................................... 22
10. Summary of Amendments to the Records Review ........................................................................ 24
10.1 Rivard Drain ...................................................................................................................... 24
11. Conclusions .................................................................................................................................... 25
12. References ..................................................................................................................................... 27
List of Figures
Figure 1: General Location of Windsor Solar Project in Ontario .................................................................. 2
Figure 2: Project Location, Natural Features and Setbacks .......................................................................... 5
Figure 3: Records Review Mapping ............................................................................................................... 9
Figure 4: Accessible Lands........................................................................................................................... 17
Figure 5: Water Assessment Site Investigation Results .............................................................................. 23
List of Tables
Table 1: Checklist for Requirements under O.Reg. 359/09 - Water Assessment - Records Review ............ 1
Table 2: Records and Resources Searched and Analyzed During Records Review ....................................... 7
Table 3: Summary of Provincial Plan Areas and Applicability to the Project Location ............................... 12
Table 4: Summary of the Water Assessment Records Review ................................................................... 13
Table 5: Names and Qualifications of Site Investigators ............................................................................ 15
Table 6: Site Investigation Dates, Times, Duration and Weather Conditions ............................................. 16
Table 7: Summary of the Water Assessment Site Investigation Report ..................................................... 26
List of Appendices
Appendix A: Supplementary Information
Appendix B: GIS Data Layer Information
Appendix C: Field Notes
Appendix D: Site Photos
Windsor Solar Project Water Assessment Report
P a g e | 1
P a g e | 1
1. INTRODUCTION
Windsor Solar LP proposes to develop a solar facility with a maximum name plate capacity of
50 megawatts alternating current (MWac), located on the Windsor International Airport property in the
City of Windsor, Ontario (Figure 1). The Windsor International Airport is owned by the City of Windsor
and operated by Your Quick Gateway (Windsor) Inc. (YQG). The renewable energy facility will be known
as the Windsor Solar Project (the “Project”).
Windsor Solar LP has initiated the Project with the Independent Electricity System Operator (IESO)1 and
will require approval under Ontario Regulation 359/09 – Renewable Energy Approval (REA) under Part
V.0.1 of the Ontario Environmental Protection Act. Ontario Regulation 359/09 requires that all
renewable energy projects conduct a records review and site investigation for all water bodies that fall
within the Project Location or the prescribed setback area (REA Section 29). This Water Assessment
Report was completed in partial fulfillment of the regulatory requirements for the REA process as
detailed in Table 1. Additional details regarding the potential impacts and mitigation measures required
to protect these features will be provided in a separate Water Body Report, as required. These reports
will be submitted to the Ministry of Environment and Climate Change (MOECC) for review and
comment, as required in Ontario Regulation 359/09, and will provide for the protection of water bodies
within and adjacent to the Project Location.
Table 1: Checklist for Requirements under O.Reg. 359/09 - Water Assessment - Records Review
Required Documentation Location in Report
Search for and analysis of the records set out in Column 1 of the Table to
section 30 of O. Reg. 359/09 was conducted in respect of the Project Location
for the purpose of making the determinations set out opposite the records in
Column 2 of the Table.
Water Assessment Report Section
5, Records Review Results
Report was prepared setting out a summary of the records searched and the
results of the analysis conducted above.
Water Assessment Report Section
6, Summary of Records Review
1 The IESO and Ontario Power Authority were merged as of January 1, 2015.
_̂Project Location
U.S.A.
L A K E E R I E
L A K E S T . C L A I R
'Ð
'Ð
']
'±
'z
WINDSOR
CHATHAM
SARNIA
LONDON
LEAMINGTON
COUNTY ROAD 42
WINDSOR SOLAR PROJECT
FIGURE 1GENERAL PROJECT LOCATION
0 10 205 km ²MAP DRAWING INFORMATION:DATA PROVIDED BY MNRMAP CREATED BY: GMMAP CHECKED BY: MBMAP PROJECTION: NAD 1983 UTM Zone 17N
FILE LOCATION: I:\GIS\149152 - Samsung Windsor\mxd\PDR
PROJECT: 149152STATUS: DRAFTDATE: 9/22/2014
1:500,000
%±%Ð
%Ð
%z
%z
%Ò%Ð
%̂
%]
Windsor Solar Project Water Assessment Report
P a g e | 3
P a g e | 3
2. THE PROPONENT
Windsor Solar LP is coordinating and managing the approvals process for the Project. Windsor Solar LP is
located at 2050 Derry Road West 2nd Floor, Mississauga, ON, L5N 0B9 (1-866-236-5040). Dillon
Consulting Limited (Dillon) has been retained by Windsor Solar LP to prepare the REA application for the
Project. The contact at Dillon is:
Full Name of Company: Dillon Consulting Limited
Prime Contact: Michael Enright, Project Manager
Address: 1155 North Service Road West, Unit 14, Oakville, Ontario, L6M 3E3
Telephone: (905) 901-2912 ext. 3401
Fax: (905) 901-2918
Email: [email protected]
Windsor Solar Project Water Assessment Report
P a g e | 4
P a g e | 4
3. PROJECT LOCATION
The proposed Class 3 Solar Facility is to be located within the YQG, Windsor International Airport
property, in the City of Windsor. The overall optioned lands available for development consist of
approximately 175 hectares (432 acres) and the proposed Project Location is generally bounded by
Rhodes Drive to the north, Division Road to the south, Lauzon Parkway to the east, and Walker Road to
the west. Of the optioned lands, approximately 128.3 hectares (317 acres) will be occupied by
components to make up the Project. The geographic coordinates of the centroid of the proposed Project
Location are as follows:
Latitude: 42° 16’ 40.84” N
Longitude: 82° 56’ 22.87” W
Figure 1 shows the general location of the Project in southwestern Ontario. The Project Location is
defined in Ontario Regulation 359/09 to be “a part of land and all or part of any building or structure in,
on or over which a person is engaging in or proposes to engage in the project”. The Project Location as
shown on Figure 2 identifies the maximum buildable area for the Project. Figure 2 also includes the 50
m setbacks. The 50 m setbacks are development prohibitions for solar facilities that are outlined in Part
V, Sections 37 and 38 of Ontario Regulation 359/09. Project components, including solar modules and
electrical facilities such as inverters, transformers, substations and electrical lines, will be located on the
Windsor International Airport lands owned by the City of Windsor and operated by YQG. The planned
solar facility will occur on lands designated as “Airport”, and “Future Employment Area” by the City of
Windsor Official Plan (see Appendix A1).
&,
#*
")
")
")
")
")
")
")")
")
")
")
")
")")
Windsor Airport Swamps (ER 23)
JEFFERSON
RD.
PILETTE RD
.
SHO
OTIN
G R
AN
GE RD
.
E C ROW EXPRESSWAY
E C ROW EXPRESSWAY
COUNTY ROAD 42
LAU
ZON
PARKW
AY
RHODES DRIVE
NORTH SERVICE ROAD EAST
CO
NC
ESS
ION
RO
AD
9
JEFFERSON
BO
ULEVA
RD
Source: Esri, DigitalGlobe, GeoEye, i-cubed, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AEX, Getmapping,Aerogrid, IGN, IGP, swisstopo, and the GIS User Community
WINDSOR SOLAR PROJECT
FIGURE 2PROJECT LOCATION -NATURAL FEATURES AND SETBACKS
0 100 200 30050 m ²MAP DRAWING INFORMATION:DATA PROVIDED BY MNR, ERCAMAP CREATED BY: GMMAP CHECKED BY: JPMAP PROJECTION: NAD 1983 UTM Zone 17N
FILE LOCATION: I:\GIS\149152 - Samsung Windsor\mxd\Water Assessment\
PROJECT: 149152STATUS: DRAFTDATE: 11/13/2014
1:10,000
_̂ Project Location
U.S.A.
LAKE ERIE
LAKE ST. CLAIR
WINDSORCHATHAM
SARNIA
LONDON
%] %±
%Ð
%z
%Ò
%Ð
%̂
%Ð
") Gate
#* Communication Tower
&, Point of Common Coupling
Fence
Operations & Maintenance Building
MV Station
Substation Transformer
Substation Yard
Temporary Laydown Area
Railway
Permanent / Intermittent Stream
Ephemeral Drain
Project Location
Project Location 50 m Setback
Project Location 120 m Setback
Project Location 300 m Setback
Parcel Boundary
Provincially Significant Wetland
Woodland
Access Road
Solar Panel Row
Windsor Solar Project Water Assessment Report
P a g e | 6
P a g e | 6
4. RECORDS REVIEW PURPOSE
A records review was completed, consistent with Section 30 of Ontario Regulation 359/09, for the
Project Location (Figure 2) using secondary source information.
Section 30 of Ontario Regulation 359/09 states a water assessment for a renewable energy facility
includes a records review to search for and determine whether the Project Location is:
1. In a water body.
2. Within 120 m of the average annual high water mark of a lake, other than a Lake Trout
lake that is at or above development capacity.
3. Within 300 m of the average annual high water mark of a Lake Trout lake that is at or
above development capacity.
4. Within 120 m of the average annual high water mark of a permanent or intermittent
stream.
5. Within 120 m of a seepage area.
Under Ontario Regulation 359/09, the definition of a water body includes lakes, permanent and
intermittent streams and seepage areas, but does not include:
a) Grassed waterways.
b) Temporary channels for surface drainage, such as furrows or shallow channels that
can be tilled and driven through.
c) Rock chutes and spillways.
d) Roadside ditches that do not contain a permanent or intermittent stream.
e) Temporary ponded areas that are normally farmed.
f) Dugout ponds.
g) Artificial bodies of water intended for the storage, treatment or recirculation of runoff
from farm animal yards, manure storage facilities and site and outdoor confinement
areas.
Table 2 outlines the secondary sources of information used to conduct the water assessment records
review.
Windsor Solar Project Water Assessment Report
P a g e | 7
P a g e | 7
Table 2: Records and Resources Searched and Analyzed During Records Review
Record Source Records Requested and/or Reviewed
Ministry of Natural Resources and Forestry (MNRF) District Office: Aylmer Main Contact: Catherine Jong, Management Biologist
Records requested directly from MNRF Aylmer District relating to natural heritage features
Date of Request: May 26, 2014
Date of Data Receipt: June 19, 2014
Manuals/Guidelines Natural Heritage Reference Manual for Natural Heritage Policies of the Provincial Policy Statement, Second Edition, (OMNR, 2010)
Natural Heritage Assessment Guide for Renewable Energy Projects, Second Edition, November 2012
Significant Wildlife Habitat Technical Guide (OMNR, 2000), Appendices and Decision Support Tool
Significant Wildlife Habitat Eco-regional Criteria Schedules, (OMNR, March 2012)
Land Information Ontario (LIO), data requested/accessed April 2014
Interactive Online Mapping Tool Agricultural Information Atlas (municipal drains) Warehouse Data (see Appendix B for data layers obtained)
Ontario Crown Land Use Policy Atlas, online data accessed April 2014
Crown Land areas
Federal Government Canadian Wildlife Service/ Environment Canada
Contact: Denise Fell, Environmental Assessment Officer, via email Records relating to natural features and wildlife species
Date of Request: May 28, 2014
Date of Data Receipt: No records received
Fisheries and Oceans Canada online mapping (Fisheries and Oceans Canada, May 2014)
Distribution of Fish Species at Risk mapping for Essex Region Conservation Authority (valid May 2014- May 2015)
Conservation Authority Essex Region Conservation Authority Contact: Tim Byrne, Watershed Management Services
Meeting with ERCA to discuss records relating to natural features and municipal drains.
GIS & Interactive Online Mapping, for mapping of municipal drains
Date: May 22, 2014
Municipality Single-Tier Municipality: City of Windsor (2013)
Official Plan and mapping Schedules reviewed Review of any applicable studies done to date in the area of the
Project Location
City of Windsor Update to the CNHS Inventory (dated June 2008)
Reviewed for information relevant to the Candidate Natural Heritage Site #39 located within 300 m of the Project Location
Planning Authorities and Local Boards Municipal Planning Authority See Above
Local Planning Board Not applicable in Project Location
Local Roads Board Not applicable in Project Location
Local Services Board Not applicable in Project Location
Windsor Solar Project Water Assessment Report
P a g e | 8
P a g e | 8
Record Source Records Requested and/or Reviewed
Other Resources Great Lakes Conservation Blueprint for Aquatic Biodiversity. Volume 2: Ecodistrict Summaries; Cedar Creek Tertiary Watershed 2GH (Phair et al., 2005)
Produced by the Nature Conservancy of Canada. A summary of statistics and land use relating to water bodies in the tertiary watershed.
Windsor International Airport Master Plan. YQG (Windsor) Inc. (2010)
Reviewed for information related to natural environment features located on Windsor International Airport lands.
Lauzon Parkway Improvements Class EA Study (McCormick Rankin Corporation, August 2013)
Review of Appendix F Part A (Natural Environment – Existing Conditions). Field studies occurred in 2011/2012 and a portion of the study area overlapped the Project Location.
Windsor Annexed Lands Master Planning Study – Background Reports Summary (Stantec Consulting Ltd., November 2006)
A summary report prepared by Stantec Consulting Ltd. in association with Pryde, Schropp and McComb that includes discussion on natural features within the airport lands.
Google Earth Pro Aerial Imagery
Provincial Plan Area Records Niagara Escarpment Plan, 2014. (Niagara Escarpment Commission, June 2014)
Project location does not fall within the Niagara Escarpment Plan Area
Oak Ridges Moraine Conservation Plan, 2001. (Ontario Ministry of Municipal Affairs and Housing, 2001)
Project location does not fall within the Oak Ridges Moraine Conservation Plan Area
Greenbelt Plan, 2005. (Ontario Ministry of Municipal Affairs and Housing, 2005)
Project location does not fall within the Greenbelt Plan Area
Lake Simcoe Protection Plan, 2009. (Ontario Ministry of the Environment , July 2009)
Project location does not fall within the Lake Simcoe Protection Plan Area
Rivard Drain
Windsor Airport Swamps (ER 23)
Windsor Airport Swamps (ER 23)
Lit t
le R
iver
Rivard Drain
McGill Drain
Rusette Drain
Lappan Drain
Branch of Rusette Drain
McGill Drain
JEFFERSON
RD.
PILETTE RD
.
SHO
OTIN
G R
AN
GE RD
.
E C ROW EXPRESSWAY
E C ROW EXPRESSWAY
COUNTY ROAD 42
LAU
ZON
PARKW
AY
RHODES DRIVE
NORTH SERVICE ROAD EAST
CO
NC
ESS
ION
RO
AD
9
WINDSOR SOLAR PROJECT
FIGURE 3RECORDS REVIEW MAPPING
0 100 200 30050 m ²MAP DRAWING INFORMATION:DATA PROVIDED BY MNR, ERCAMAP CREATED BY: GMMAP CHECKED BY: JPMAP PROJECTION: NAD 1983 UTM Zone 17N
FILE LOCATION: I:\GIS\149152 - Samsung Windsor\mxd\Water Assessment\
PROJECT: 149152STATUS: DRAFTDATE: 9/2/2014
1:10,000
Railway
Watercourse
Project Location
Project Location 120 m Setback
Project Location 300 m Setback
Parcel Boundary
Provincially Significant Wetland
Woodland (Airport Woodlands Environmentally Significant Area #39)
Pond
_̂ Project Location
U.S.A.
LAKE ERIE
LAKE ST. CLAIR
WINDSORCHATHAM
SARNIA
LONDON
%] %±
%Ð
%z
%Ò
%Ð
%̂
%ÐJefferson Woodlot
Shooting Range Woodlot
East Perimeter Woods
St. Louis Woods
Windsor Solar Project Water Assessment Report
P a g e | 10
P a g e | 10
5. RECORDS REVIEW RESULTS
The Project is located at the YQG, Windsor International Airport and is designated in part as either
“Airport” or “Future Employment Area” by the City of Windsor Official Plan (see Appendix A1). The
Project Location is within the Cedar Creek Tertiary Watershed (2GH) and was summarized in the Great
Lakes Conservation Blueprint for Aquatic Biodiversity (Phair et al., 2005). The watershed drains into
Lake Erie and there are 163,000 ha of stream systems. Sparse and dense deciduous forest are scattered
throughout the watershed. Agriculture is the dominant land-use throughout the watershed. The Project
Location is within the Little River subwatershed, nested within the Detroit River watershed. Little River is
located east of the Project Location (approximately 655 m) and flows northward into the Detroit River.
5.1 Water Bodies
Based on review and analysis of the records and resources outlined in Table 2, and in
accordance with Ontario Regulation 359/09, determinations were made whether the Project
Location is in a water body or within 120 m of the average annual high water mark of a water
body (Figure 3). All mapping used for the records review is based on agency data (see Appendix
B) and is not necessarily reflective of site conditions. In consideration of potential Lake Trout
lakes and to meet the requirements of the Construction Plan Report, water bodies within 300 m
are also noted. The Construction Plan Report is included as part of the REA Application.
5.1.1 Average Annual High Water Mark Determination
For the purposes of this REA reporting, the average annual high water mark for streams is
defined as the usual or average level to which a body of water rises at its highest point and
remains for sufficient time so as to change the characteristics of the land. In flowing waters, this
refers to the “active channel/bankfull level” which is often the one-to two-year flood flow return
level (MOECC, 2013).
5.1.2 Lakes
A search and analysis of the records and resources outlined in Table 2 did not identify any
named lakes, as defined by Ontario Regulation 359/09, in the Project Location or within the
surrounding 300 m.
5.1.3 Lake Trout Lakes
A search and analysis of the records and resources outlined in Table 2 did not identify any Lake
Trout lakes under management by the MNRF, in the Project Location or within the surrounding
300 m setback area.
Windsor Solar Project Water Assessment Report
P a g e | 11
P a g e | 11
5.1.4 Permanent and/or Intermittent Streams
A search and analysis of records and resources outlined in Table 2 identified three potential
streams within the Project Location, and one potential stream in the surrounding 120 m setback
(Figure 3). These four potential streams are identified as named municipal drains on ERCA
mapping, and as watercourses on MNRF mapping, as follows:
The Lappan Drain is shown to originate west of the Project Location and outside the 300 m
setback. It flows generally eastward, enters and flows through the Project Location, turns
southward, exits the Project Location, and discharges into the McGill Drain at a confluence
located within the 120 m setback area for the Project.
The McGill Drain is shown to originate within the Project Location, near its southwest boundary.
It generally flows in an easterly direction within both the Project Location and the 120 m
setback. This drain discharges into Little River approximately 655 m to the northeast of the
Project.
The Rivard Drain is shown to originate within the Project Location, near its southern boundary.
It flows generally eastward, exits the Project Location near its southeast boundary, and
discharges into the Little River approximately 1.6 km to the east.
The Rusette Drain is shown to originate north of the Project Location and outside the 300 m
setback. It flows generally eastward, enters the 120 m setback area near its northern boundary,
turns northward, and discharges into another tributary of the Rusette Drain. This system then
discharges into the Little River.
5.1.5 Seepage Areas
A search and analysis of the records and resources outlined in Table 2 did not identify any
seepage areas in the Project Location or within the surrounding 300 m.
5.2 Aquatic Species at Risk
Species at Risk listed under the federal Species at Risk Act and provincial Endangered Species
Act, 2007, with the potential to interact with the Project Location and/or adjacent lands, are
being considered in consultation with the appropriate agency. Reporting related to the
protection of Species at Risk will be provided to the appropriate agency under separate cover as
required. This reporting format meets the requirements as set out in Ontario Regulation 359/09,
and is consistent with the direction provided by the MNRF and the MOECC.
Windsor Solar Project Water Assessment Report
P a g e | 12
P a g e | 12
5.3 Provincial Plan Areas
Under Ontario Regulation 359/09, if any part of the Project Location falls within a provincial plan
area, the Project may be subject to different criteria to evaluate the applicable water bodies. In
addition, should development occur within the prescribed setback area of a water body, it may
be subject to a different set of prohibitions under Ontario Regulation 359/09. Table 3 outlines
the provincial plan areas that should be considered when planning a renewable energy project,
and identifies which, if any, are applicable to the Project Location.
Table 3: Summary of Provincial Plan Areas and Applicability to the Project Location
Provincial Plan Area Applicability to Project
Oak Ridges Moraine Conservation Plan Area None
Niagara Escarpment Plan Area None
Greenbelt - Natural Heritage System None
Greenbelt – Protected Countryside None
Lake Simcoe Protection Plan None
5.4 Regulated Areas
Portions of the lands within the Project Location are regulated by ERCA under Ontario
Regulation 158/06, Essex Region Conservation Authority: Regulation of Development,
Interference with Wetlands and Alterations to Shorelines and Watercourses (see Appendix A).
Where required, ongoing consultation with ERCA will occur to obtain relevant permits and/or
approvals for the Project.
Windsor Solar Project Water Assessment Report
P a g e | 13
P a g e | 13
6. SUMMARY OF RECORDS REVIEW
This report is intended to fulfill the requirements for the water assessment records review under
Ontario Regulation 359/09. Table 4 summarizes the determinations made during this records review. All
previously mapped water bodies within the Project Location and surrounding 300 m are outlined on
Figure 3.
Table 4: Summary of the Water Assessment Records Review
Water Body ID Source of Information*
Distance Relative to Project Location
Lakes
No known features identified within the Project Location or adjacent lands within 300 m
Lake Trout Lakes
No known features identified within the Project Location or adjacent lands within 300 m
Permanent and/or Intermittent Streams
Lappan Drain MNRF LIO and ERCA Mapping
Within Project Location
McGill Drain MNRF LIO and ERCA Mapping
Within Project Location
Rivard Drain MNRF LIO and ERCA Mapping
Within Project Location
Rusette Drain MNRF LIO and ERCA Mapping
Within 120 m setback
Seepage Areas
No known features identified within the Project Location or adjacent lands within 300 m
Provincial Plan Areas
None applicable within the Project Location or adjacent lands within 300 m
Regulated Areas
ERCA Regulation Limit ERCA Mapping Within Project Location
* See Table 2 and Appendix B
Windsor Solar Project Water Assessment Report
P a g e | 14
P a g e | 14
7. SITE INVESTIGATION PURPOSE
This site investigation report was completed to analyze the accuracy of the determinations made in the
records review. It is consistent with Section 31 of Ontario Regulation 359/09, which states that a person
who proposes to engage in a renewable energy project shall ensure that a physical investigation of the
land and water within 120 m of the Project Location is conducted for the purpose of determining:
Whether the results of the analysis summarized in the records review report are correct or
require correction, and identifying any required corrections.
Whether any additional water bodies exist, other than those identified in the records review.
The boundaries, located within 120 m of the Project Location, of any water body that was
identified in the records review or the site investigation.
The distance from the Project Location to the boundaries of the water body.
Windsor Solar Project Water Assessment Report
P a g e | 15
P a g e | 15
8. SITE INVESTIGATION METHODOLOGY
Based on the determinations made during the records review, all water bodies that were mapped within
the Project Location and surrounding 120 m were the subject of a site investigation. The Project
Location was assessed by site investigators in order to document the presence of applicable water
bodies within the Project Location. Documentation of applicable and accessible water bodies included a
record of qualitative and quantitative observations including type and location of water body, average
annual high water mark, habitat types, surrounding riparian composition and taking of representative
photographs. Efforts were co-ordinated with the site investigator conducting the natural heritage
assessment of the Project Location to locate any potential water bodies not identified during the records
review and streams were marked using GPS devises in the field to verify locations on mapping.
8.1 Names and Qualifications of Site Investigators
The names and qualifications of site investigators are outlined in Table 5 below. The site
investigators listed below have been involved with the Project since it began and are involved in
other renewable energy projects that are currently seeking approval under Ontario Regulation
359/09.
Table 5: Names and Qualifications of Site Investigators
Name
Degrees and
Professional
Designations
Years of
Experience Project Role Certifications
Ben Gottfried Adv. Dip (Fish and
Wildlife Technician)
6 Water Bodies
Assessment
Incidental
Wildlife
Certified Inspector of
Sediment and
Erosion Control
Ontario Ministry of
Natural Resources
Class 1 Electrofishing
Trevor Goulet B.Sc. (Env.), Natural
Resources
Management
3 Water Bodies
Assessment
Incidental
Wildlife
Environmental
Professional in-
Training (EPt)
8.2 Site Investigation Dates, Times, Duration, and Weather Conditions
As outlined in Table 6, a single site investigation was conducted on May 14, 2014. The details
of the site investigation completed in accordance with REA Section 31(3) are provided in Table
6 and should be read concurrently with Table 5. Field notes that are part of the Natural
Windsor Solar Project Water Assessment Report
P a g e | 16
P a g e | 16
Heritage Assessment (i.e., ELC) are included in the Natural Heritage Assessment Site
Investigation Report.
Table 6: Site Investigation Dates, Times, Duration and Weather Conditions
Date
(2014)
Survey
Type
Site
Inve
stig
ato
r(s)
Star
t Ti
me
Du
rati
on
(h
ou
rs)
Weather Conditions
(Field Observations)
Weather Conditions
(EC* Station)
Air
Te
mp
. (oC
)
Win
d (
Be
aufo
rt
Scal
e)
Clo
ud
Co
ver
(%)
Ave
rage
Air
Te
mp
.
(oC
)
Win
d
(Sp
ee
d/D
ire
ctio
n)
Pre
cip
itat
ion
(m
m)
May 14 Water Body
and
Watercourse
Assessment
BG,
TG
10:00 5.0 17 3 100 13.3 17
km/h
NNE
7.6
Total Duration of Field Work: 5.0 hours
*Nearest Environment Canada (EC) Weather Station at Windsor, Ontario (42°16’32.00” N, 82°57’20.00”W).
8.3 Access to Adjacent Lands
As outlined in Ontario Regulation 359/09, all lands within 120 m of a project component are
required to be assessed for water bodies. In the case of the Project, access was not available
to some lands within 120 m of the Project Location. Some areas of lands to the north of the
Project Location were not accessible because they were within an industrial facility without
available access, and lands to the northwest of the Project Location were not accessible
because they were near the airport’s runway and taxiway, where access was not permitted by
YQG for health and safety reasons (Figure 4). Water bodies located on adjacent lands where
access was not available were assessed from property lines and road rights-of-way, where
applicable. This alternative site investigation was conducted in accordance with Ontario
Regulation 359/09 (see Figure 4).
Rivard Drain
Windsor Airport Swamps (ER 23)
Windsor Airport Swamps (ER 23)
Lit t
leR
iver
Rivard Drain
McGill Drain
Rusette Drain
Lappan Drain
Branch of Rusette Drain
McGill Drain
JEFFERSON
RD.
PILETTE RD
.
SHO
OTIN
G R
AN
GE RD
.
E C ROW EXPRESSWAY
E C ROW EXPRESSWAY
COUNTY ROAD 42
LAU
ZON
PARKW
AY
RHODES DRIVE
NORTH SERVICE ROAD EAST
CO
NC
ESS
ION
RO
AD
9
WINDSOR SOLAR PROJECT
FIGURE 4ACCESSIBLE LANDS
0 100 200 30050 m ²MAP DRAWING INFORMATION:DATA PROVIDED BY MNR, ERCAMAP CREATED BY: GMMAP CHECKED BY: JPMAP PROJECTION: NAD 1983 UTM Zone 17N
FILE LOCATION: I:\GIS\149152 - Samsung Windsor\mxd\Water Assessment\
PROJECT: 149152STATUS: DRAFTDATE: 9/8/2014
1:10,000
Railway
Watercourse
Project Location
Project Location 50 m Setback
Project Location 120 m Setback
Project Location 300 m Setback
Area of Alternative Site Investigation
Parcel Boundary
Provincially Significant Wetland
Woodland (Airport Woodlands Environmentally Significant Area #39)
Pond
_̂ Project Location
U.S.A.
LAKE ERIE
LAKE ST. CLAIR
WINDSORCHATHAM
SARNIA
LONDON
%] %±
%Ð
%z
%Ò
%Ð
%̂
%ÐJefferson Woodlot
Shooting Range Woodlot
East Perimeter Woods
St. Louis Woods
Windsor Solar Project Water Assessment Report
P a g e | 18
P a g e | 18
9. SITE INVESTIGATION RESULTS
Based on the site investigation, the occurrence of water bodies within the Project Location or its
surrounding 120 m is documented below. In addition to assessing if the results of the records review
were correct or required corrections and/or amendments, information relating to each water body, if
any, within the Project Location and surrounding 120 m was collected. This included the type of water
body, plant and animal composition and the ecosystem of the land and water under investigation. In
consideration of potential Lake Trout lakes and to meet the requirements of the Construction Plan
Report, water bodies within 300 m were also noted. The Construction Plan Report is included as part of
the REA Application.
9.1 Lakes
As outlined in Table 4, a search and analysis of the records and resources did not identify any
lakes in the Project Location or within the surrounding 300 m. The results of the site
investigation confirmed this determination for lands within 300 m of the Project Location.
9.2 Lake Trout Lakes
As outlined in Table 2, a search and analysis of the records and resources did not identify any
lakes that had potential to support a managed population of Lake Trout in the Project Location
or within the surrounding 120 m. The results of the site investigation confirmed this
determination for lands within 300 m of the Project Location.
9.3 Permanent and/or Intermittent Streams
As outlined in Table2, a search and analysis of the records and resources identified four streams
mapped within the Project Location (Figure 3), and within the 120 m surrounding area. Results
of the site investigation found that three of these streams are permanent and/or intermittent
streams, while one was found to be seasonal surface drainage swale (Figure 5). Each is discussed
in the following sections. All site investigation notes are available in Appendix C. Appendix D
contains representative site photographs.
9.3.1 Lappan Drain
The site investigation found that the Lappan Drain occurred as mapped on the MNRF and ERCA
mapping reviewed in the records review (Figure 3). The Lappan Drain originates approximately
610 m west of the Project Location (UTM Zone 17T 338765 E, 4681947 N; Figure 5; Photo 1 in
Appendix D). Near its origin, the Lappan Drain is fed by a sub-surface corrugated steel pipe (CSP)
culvert (diameter of approximately 1.0 m), conveying flow from the west (Photo 2 in Appendix
D). Near the culvert, the drain is also fed by a swale conveying water from the north. This swale
was observed to be dry at the time of the site investigation and likely conveys water seasonally
during spring freshet and times of greater precipitation. It therefore does not meet the
definition of a water body under Ontario Regulation 359/09 and was not mapped on Figure 5.
Windsor Solar Project Water Assessment Report
P a g e | 19
P a g e | 19
From the CSP culvert, the Lappan Drain flows generally eastward, enters the 120 m setback
area, then crosses under Pilette Road through a concrete box culvert approximately 2.0 m wide
and 1.0 m high (Photo 3 in Appendix D). The drain then enters the Project Location, flows
eastward, and crosses under Jefferson Road via a concrete box culvert approximately 2.0 m
wide and 1.0 m high (Photo 4 and Photo 5 in Appendix D). Two small utility sheds are located
near the box culvert on the west side of Jefferson Road. One is a general storage shed. The other
is an equipment shed containing a water level monitoring system, which is operated by YQG
operations staff. The monitoring system equipment includes a plastic pipe plumbed from the
drain into the shed, and an electrical conduit wired into the shed (Photo 4 in Appendix D). The
drain then turns southward, exits the Project Location, and empties into the McGill Drain within
the 120 m setback area. The Lappan Drain is fed by various temporary/seasonal surface
drainage channels throughout the Project Location (Photo 6 in Appendix D).These
temporary/seasonal surface drainage channels do not meet the definition of a water body.
Lappan Drain was observed to be a channelized permanent stream. At the time of site
investigation, water was flowing heavily into the drain from the sub-surface CSP culvert near its
origin. Along the length of the drain within the Project Location, the habitat type was primarily
flat, with occasional runs. Substrates were primarily silt and detritus. The mean wetted width
ranged from 1.8 to 2.0 m. The mean wetted depth ranged from 0.1 to 0.4 m. The mean bankfull
width was 4.0 m, while the mean bankfull depth was 1.2 (widths and depths are approximate).
Banks were stable, with minimally erodible soil and material. In-water and shore cover for the
stream included: overhanging and in-stream woody debris (5-10%); organic debris (30%);
overhanging vascular macrophytes (15%); in-stream vascular macrophytes (50%). Shore cover
provided coverage to approximately 1 – 30% of the stream surface area. Vegetation was mostly
emergent, and included various pondweed species, common reeds (Phragmites spp.), cattails
(Typha spp.) and willows (Salix spp.). No submergent or floating vegetation species were
observed. Four individuals of Cyprinidae were observed in the drain, approximately 200 m west
of Jefferson Road.
Surrounding riparian lands included occasional scrubland in the adjacent 10 m, and cultivated
agricultural lands. Riparian scrubland was sparsely treed in the portions west of Jefferson Road
(Photo 7 in Appendix D), and was more heavily treed in the portions east of Jefferson Road
(Photo 5 in Appendix D). Some surrounding agricultural areas were recently row planted with
Winter wheat (Triticum aestivum) while other areas were last row planted with Corn (Zea mays),
and contained stubble and stover from the most recent harvest; likely in autumn of 2013.
Windsor Solar Project Water Assessment Report
P a g e | 20
P a g e | 20
9.3.2 McGill Drain
The site investigation found that McGill Drain occurs as mapped on the MNRF and ERCA
mapping reviewed in the records review. It originates within the Project Location, near its
southwest boundary, east of Pilette Road (339576 E, 4681754 N; Figure 5; Photo 8 in Appendix
D). From here, it flows generally eastward through the Project Location. It exits the Project
Location at its southeast boundary, continues eastward, then turns northward near the
perimeter of a swamp identified as Provincially Significant Wetland (PSW) Windsor Airport
Swamp ER 23 (Figure 5; Photo 9 and Photo 10 in Appendix D). The drain re-enters the Project
Location, turns eastward, flows for approximately 250 m within the Project Location, then exits
the Project Location at its eastern boundary, approximately 5 m west of Jefferson Road. Within
the 120 m setback area, the drain crosses Jefferson Road via a concrete box culvert,
approximately 2.0 m wide and 2.0 m high (Photo 11 in Appendix D). From here, the drain flows
eastward within the 120 m setback, is fed by the Lappan Drain, then crosses Shooting Range
Road via a CSP culvert, approximately 60 cm in diameter (Photo 12 in Appendix D). The McGill
Drain then flows north-eastward, exits the 120 m setback area, and empties into the Little River.
The reach of the McGill Drain between its origin and its confluence with the Lappan Drain was
observed to be a channelized intermittent stream. Although water was actively flowing in the
drain at the time of site investigation, observed characteristics, including extensive cover of
terrestrial grasses, indicated that periods of stream dry-up likely occur during the summer in this
reach. The reach of the McGill Drain downstream of the confluence was observed to be a
channelized permanent stream. Observed characteristics, including cover by aquatic plant
species, indicated that active water flow is consistent throughout the year from water inputs
from the Lappan Drain.
Along the length of the drain within the Project Location, the habitat type was primarily flat,
with occasional runs. Substrates were a mix of primarily silt and detritus. The mean wetted
width ranged from 1.6 to 1.8 m. The mean wetted depth ranged from 0.1 m in western areas to
0.5 m in eastern areas. The mean bankfull width ranged from 2.5 to 3.0 m, while the mean
bankfull depth ranged from 0.8 to 1.0 m (widths and depths are approximate). Banks were
primarily stable, with minimally erodible soil and material. An area of bank erosion and
instability was observed east of Shooting Range Road along the drain’s southeast bank (Photo
13 in Appendix D). At this location, the opposite bank was protected from erosion by rip-rap
material (Photo 14 in Appendix D). In-water and shore cover for the stream included:
overhanging and in-stream woody debris (5%); organic debris (70%); overhanging vascular
macrophytes (5%); in-stream vascular macrophytes (30%). Shore cover provided coverage to
approximately 1 – 30% of the stream surface area. Vegetation was predominantly emergent,
and included various pondweed species, common reeds (phragmites spp.), cattails (typha spp.)
and various terrestrial grasses. Sparse patches of a pondweed species (Elodea spp.), were
observed in areas near the drain origin. No floating vegetation was observed. Fish were
observed within the drain approximately 100 m east of the drain origin (Photo 15 in Appendix
D).
Windsor Solar Project Water Assessment Report
P a g e | 21
P a g e | 21
In reaches of the drain near the adjacent Windsor Airport Swamps ER 23 PSW, the surrounding
riparian lands contained sparse areas of shrub vegetation, including Bigtooth aspen (Populus
grandidentata) and willows. Riparian areas further from the PSW were cultivated agricultural
lands throughout; primarily winter wheat to the south and clover mixed with various weeds to
the north.
9.3.3 Rivard Drain
The site investigation found that the portion of the Rivard Drain occurring within the Project
Location and its surrounding 300 m setback is not a permanent or intermittent watercourse.
Rather, it is a seasonal swale that conveys surface water. It has both been tilled and driven
through. Therefore, it does not meet the definition of a water body under Ontario Regulation
359/09, and is not mapped as such on Figure 5. The characteristics of the drain observed during
the site investigation are described below to provide further evidence that this is not an
applicable water body.
The site investigation found that the Rivard Drain occurs only partially as mapped on the MNRF
and ERCA mapping reviewed in the records review (Figure 3). The drain originates within the
Project Location, near its south boundary (339988 E, 4681705 N; Figure 5). From here, it flows
generally eastward through the southern area of the Project Location (Photos 16 and 17 in
Appendix D), as mapped (Figure 3). The drain then exits the Project Location at its southeast
boundary, and continues eastward within the 120 m and 300 m setback areas, also as mapped
(Figure 3). The drain then diverts approximately 5.0 m south of, and entirely outside of, the
Windsor Airport Swamp ER 23 PSW, flowing entirely within an agricultural field (Photos 18 and
19 in Appendix D). The observation that the drain is outside of the PSW differs from what is
shown on MNRF and ERCA mapping, which instead shows the drain flowing within the PSW. This
discrepancy and its required amendment to the records review mapping is discussed in Section
10.1 of this report.
East of the PSW, the Rivard Drain exits the 300 m setback area, enters a roadside ditch along the
west side of Jefferson Road (Photo 20 in Appendix D), crosses Jefferson Road via a concrete box
culvert, and flows eastward toward the Little River (Photo 21 in Appendix D).
In the portion of the Rivard Drain mapped within the PSW swamp area (Figure 3), a long area of
standing water was observed. However, this was found to be a depression area within the PSW
and not part of Rivard Drain (Photos 22 and 23 in Appendix D).
At the time of site investigation, there was minor water flow throughout the portion of the drain
within the Project Location. The habitat type was entirely flat. Substrates were primarily silt and
detritus. The mean wetted width ranged from 0.3 m in western areas to 1.5 m in eastern areas.
The mean wetted depth ranged from 0.02 m in western areas to 0.08 m in eastern areas (all
widths and depths are approximate). The mean bankfull width and depth could not be
determined as the drain had no distinct banks. No in-stream cover or shore cover were
observed along the portion of the drain in the agricultural field.
Windsor Solar Project Water Assessment Report
P a g e | 22
P a g e | 22
9.3.4 Rusette Drain
During the site investigation, the portion of the Rusette Drain occurring within the Project
Location 120 m setback area could not be observed due to unavailable access to an enclosed
industrial facility. Instead, a portion of the drain located approximately 200 m to the west,
outside of the 300 m setback, was accessed and observed (340674 E, 4683581 N; Figure 5;
Photo 24 in Appendix D). From the access point, the drain flowed eastward, and entered twin
CSP culverts (Photo 25 in Appendix D). Each culvert had a diameter of approximately 1.0 m, and
each was partially covered with a metal screen cage with a width and height of approximately
0.5 m.
The site investigation found that the Rusette Drain was a channelized permanent stream. At the
time of investigation the drain was actively flowing. Surface habitat type was a run with
occasional flat areas. Substrates were primarily silt and detritus. Mean wetted width was
approximately 1.5 m and mean wetted depth was approximately 0.3 m. Banks were stable, with
minimally erodible soil and material. In-water and shore cover for the stream included:
overhanging and in-stream woody debris (5-10%); organic debris (25%); overhanging and in-
stream vascular macrophytes (10%). Shore cover provided coverage to approximately 1 – 30% of
the stream surface area. Vegetation was predominantly emergent common reeds. Surrounding
riparian communities were grassed meadows within the surrounding 10 m, and cultivated
agricultural land beyond the surrounding 10 m to the south.
9.4 Seepage Areas
As indicated in Table 2, a search and analysis of applicable records and resources of the Project
Location did not identify any seepage areas, as defined by Ontario Regulation 359/09, in the
Project Location or within the surrounding 300 m. The results of this site investigation verified
this determination.
Windsor Airport Swamps (ER 23)
Windsor Airport Swamps (ER 23)
JEFFERSON
RD.
PILETTE RD
.
SHO
OTIN
G R
AN
GE RD
.
Rivard Drain
Litt
leRiv
er
McGill Drain
Rusette Drain
Lappan Drain
Branch of Rusette Drain
Lappan Drain
McGill Drain
Rusette Drain
M
cGillDrain
Rivard Drain
E C ROW EXPRESSWAY
E C ROW EXPRESSWAY
COUNTY ROAD 42
LAU
ZON
PARKW
AY
RHODES DRIVE
NORTH SERVICE ROAD EAST
CO
NC
ESS
ION
RO
AD
9
WINDSOR SOLAR PROJECT
FIGURE 5WATER ASSESSMENTSITE INVESTIGATION MAP
0 100 200 30050 m ²MAP DRAWING INFORMATION:DATA PROVIDED BY MNR, ERCAMAP CREATED BY: GMMAP CHECKED BY: JPMAP PROJECTION: NAD 1983 UTM Zone 17N
FILE LOCATION: I:\GIS\149152 - Samsung Windsor\mxd\Water Assessment\
PROJECT: 149152STATUS: DRAFTDATE: 9/17/2014
1:10,000
Railway
Permanent / Intermittent Stream
Ephemeral Drain
Project Location
Project Location 50 m Setback
Project Location 120 m Setback
Project Location 300 m Setback
Parcel Boundary
Airport
Provincially Significant Wetland
Woodland (Airport Woodlands Environmentally Significant Area #39)
_̂ Project Location
U.S.A.
LAKE ERIE
LAKE ST. CLAIR
WINDSORCHATHAM
SARNIA
LONDON
%] %±
%Ð
%z
%Ò
%Ð
%̂
%ÐJefferson Woodlot
Shooting Range Woodlot
East Perimeter Woods
St. Louis Woods
Windsor Solar Project Water Assessment Report
P a g e | 24
P a g e | 24
10. SUMMARY OF AMENDMENTS TO THE RECORDS REVIEW
Based on the results of the site investigations, no previously unidentified water bodies were
identified within the Project Location or surrounding 120 m. Results of the site investigation of the
streams mapped within the Project Location determined that amendments are required to be made to
the records reviewed (Figure 3) for one water body, as follows.
10.1 Rivard Drain
Two amendments are required for the Rivard Drain. First, the portion of the drain within the
Project Location and its 300 m setback was observed to be ephemeral in nature and therefore
not an applicable water body under Ontario Regulation 359/09.
Second, the Rivard Drain is shown on ERCA mapping to enter and flow within the southern area
of the Windsor Airport Swamp ER 23 PSW. However, it was observed during the site
investigation to not flow within the PSW. Rather, it diverts approximately 5 m south of the
southern boundary of the PSW. Figure 5 shows the revised location of the ephemeral drain.
Windsor Solar Project Water Assessment Report
P a g e | 25
P a g e | 25
11. CONCLUSIONS
This report is intended to fulfill the requirements for the Water Assessment Report under Ontario
Regulation 359/09. Based on the results of the site investigations, there are two applicable water
bodies (Lappan Drain and McGill Drain) within the Project Location, both of which also extend into the
surrounding 120 m setback. One applicable water body (Russet Drain) occurs strictly within the 120 m
setback. Based on this, an Environmental Impact Study (i.e., a Water Body Report) on three water
bodies (Lappan Drain, McGill Drain and Rusette Drain) as outlined in Sections 39 and 40 of Ontario
Regulation 359/09 is required for this project.
Table 7 summarizes the results of the site investigation in the context of the proposed Project.
Windsor Solar Project Water Assessment Report
P a g e | 26
P a g e | 26
Table 7: Summary of the Water Assessment Site Investigation Report
Water Body ID
Does the Project
Location overlap
this water body?
Is the Project Location
within 120 m of this water
body?
Distance to nearest project
components
Project Components within 120 m of the
water body*
EIS
Req
uir
ed?
Lakes
None identified within the Project Location or adjacent lands within 300 m
Lake Trout Lakes
None identified within the Project Location or adjacent lands within 300 m
Permanent and/or Intermittent Streams
Lappan Drain Yes Yes 32 m to fencing Fencing*
Inverters
Access Roads
Panels
Yes
McGill Drain Yes Yes 32 m to fencing Fencing*
Inverters
Access Roads
Panels
Yes
Rusette Drain No Yes 91 m to fencing Substation
Fencing*
Yes
Seepage Areas
None identified within the Project Location or adjacent lands within 300 m
*Project component closest to each water body
Windsor Solar Project Water Assessment Report
P a g e | 27
P a g e | 27
12. REFERENCES
City of Windsor. 2013 Official Plan and Schedules. 2013. City of Windsor. June 2008. Update to the Candidate Natural Heritage System (CNHS) Inventory. 235 pp. Essex Region Conservation Authority. GIS & Interactive Mapping.
http://gisweb.countyofessex.on.ca/svlerca/Viewer.html?Viewer=Public. Accessed June 2014. Fisheries and Oceans Canada. May 2014. Distribution of Fish and Mussel Species at Risk. Essex Region
Conservation Authority. Valid May 2014 to May 2015. McCormick Rankin Corporation. August 2013. Lauzon Parkway Improvements Class EA Study. Appendix F
Part A- Natural Environment- Existing Conditions. 44 pp. Niagara Escarpment Commission. June 2014. Niagara Escarpment Plan, 2014. Toronto: Queen’s Printer
for Ontario. 145 pp. Ontario Ministry of the Environment. June 2009. Lake Simcoe Protection Plan. Toronto: Queen’s Printer
for Ontario. 93 pp. Ontario Ministry of the Environment. 2013. Technical Guide to Renewable Energy Approvals. Toronto:
Queen’s Printer for Ontario. 267 pp. Ontario Ministry of Municipal Affairs and Housing. 2001. Oak Ridges Moraine Conservation Plan, 2001.
Toronto: Queen’s Printer for Ontario. 72 pp. Ontario Ministry of Municipal Affairs and Housing. 2005. Greenbelt Plan, 2005. Toronto: Queen’s Printer
for Ontario. 57 pp. Ontario Ministry of Natural Resources. Crown Land Use Policy Atlas.
http://crownlanduseatlas.mnr.gov.on.ca/clupa.html. Accessed April 2014. Ontario Ministry of Natural Resources. Land Information Ontario.
http://www.giscoeapp.lrc.gov.on.ca/web/MNRF/NHLUPS/NaturalHeritage/Viewer/Viewer.html. Accessed April 2014.
Ontario Ministry of Natural Resources. March 2010. Natural Heritage Reference Manual for Natural
Heritage Policies of the Provincial Policy Statement, 2005. Second Edition. Toronto: Queen’s Printer for Ontario. 248pp.
Ontario Ministry of Natural Resources. March, 2012. Significant Wildlife Habitat Eco-regional Criteria
Schedules. http://www.ebr.gov.on.ca/ERS-WEB-
External/displaynoticecontent.do?noticeId=MTE1ODc5&statusId=MTczNDgy. Accessed April
2014.
Windsor Solar Project Water Assessment Report
P a g e | 28
P a g e | 28
Ontario Ministry of Natural Resources. 2000. Significant Wildlife Habitat Technical Guide. 151pp. Ontario Ministry of Natural Resources. 2012. Natural Heritage Assessment Guide for Renewable Energy
Projects. Second Edition. 109pp. Phair, C., Henson, B.L., Brodribb, K.E. 2005. Great Lakes Conservation Blueprint for Aquatic Biodiversity:
Volume 2: Tertiary Watershed Summaries. Nature Conservancy of Canada. 454 pp. Stantec Consulting Ltd. November 2006. Windsor Annexed Lands Master Planning Study- Background
Reports Summary. 134 pp. Your Quick Gateway (Windsor) Inc. 2010. Windsor International Airport Master Plan. 195 pp.