wire reinforcement institute design of … the design requirements set forth in brab report #33.many...

36
942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974] TECH FACTS www.wirereinforcementinstitute.org Excellence Set in Concrete WIRE REINFORCEMENT INSTITUTE ® TF 700-R-03 DESIGN OF SLAB-ON-GROUND FOUNDATIONS A Design, Construction & Inspection Aid For Consulting Engineers © Wire Reinforcement Institute, Inc. 2003 August 1981 Prepared for: Copyright, Wire Reinforcement Institute Wire Reinforcement Institute 942 Main Street Hartford, CT 06103 Phone (800) 522-4WRI [4974] Fax (860) 808-3009 Authored By: Walter L. Snowden, P.E. Austin, TX 512-338-0431 or 512-338-1804 This procedure was developed by Walter L.Snowden, P.E., Consulting Engineer, of Austin, Texas, over a period of some 15 years. It is empirically derived by observing slab performance and writing or modifying equations to give results which approximate the foundations which had been found to give satisfactory results. In addition, Mr. Snowden, has served on the Pre-Stress Concrete Institute Ad Hoc Committee for the development of “ Tentative Recommendations for Pre-Stressed Slabs-on-Ground” and as a Consultant to the Building Research Advisory Board Committee on Residential Slabs-On-Ground. Designs done by this method should be economical yet give quite satisfactory results with a minimum of deflection and resulting superstructure distress. While this publication deals only with foundations reinforced with reinforcing bars and/or welded wire reinforcement, the procedure has been developed to be independent of the type of reinforcing used.

Upload: dangcong

Post on 16-Apr-2018

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in Concrete

WIRE REINFORCEMENT INSTITUTE®

TF 700-R-03

DESIGN OF SLAB-ON-GROUND FOUNDATIONS

A Design, Construction & Inspection AidFor Consulting Engineers

© Wire Reinforcement Institute, Inc. 2003

August 1981

Prepared for:

Copyright, Wire Reinforcement Institute

Wire Reinforcement Institute

942 Main Street

Hartford, CT 06103

Phone (800) 522-4WRI [4974]

Fax (860) 808-3009

Authored By:

Walter L. Snowden, P.E.

Austin, TX

512-338-0431 or 512-338-1804

This procedure was developed by Walter L. Snowden, P. E., Consulting Engineer, of Austin, Texas, over a period ofsome 15 years. It is empirically derived by observing slab performance and writing or modifying equations to giveresults which approximate the foundations which had been found to give satisfactory results.

In addition, Mr. Snowden, has served on the Pre-Stress Concrete Institute Ad Hoc Committee for the developmentof “ Tentative Recommendations for Pre-Stressed Slabs-on-Ground” and as a Consultant to the Building ResearchAdvisory Board Committee on Residential Slabs-On-Ground.

Designs done by this method should be economical yet give quite satisfactory results with a minimum of deflectionand resulting superstructure distress.

While this publication deals only with foundations reinforced with reinforcing bars and/or welded wire reinforcement,the procedure has been developed to be independent of the type of reinforcing used.

Page 2: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

Table of Contents

INTRODUCTION 1

EARLY DEVELOPMENTS 1

SOILS INVESTIGATIONS 2

LABORATORY TESTING 3

DETERMINING THE EFFECTIVE P.I. 5

OTHER PARAMETERS 5

WARNING 6

LOADING CONSIDERATIONS 7

SUPPORT CONSIDERATIONS 7

THE SLAB DESIGN 10

BEAM SPACING AND LOCATION 12

SLAB REINFORCING 13

BEAM REINFORCING 13

SITE PREPARATION 14

SLAB FORMING 15

STEEL PLACEMENT 16

SPECIAL CONDITIONS 19

CONCRETE PLACING 20

INSPECTION 22

SHRINKAGE CRACKS 23

APPENDIX A NOTATION

APPENDIX B DESIGN EXAMPLES

APPENDIX C REFERENCES

TF 700-R-03

Page 3: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

INTRODUCTIONWithin the last several years there has beena lot of interest in a design procedure for thedesign of light foundations, particularly foruse under single family residences. Reportsand recommendations have been undertak-en and prepared by several study groups forthe purposes of developing design criteria orextending the Criteria for Selection andDesign of Residential Slabs-on-Ground,BRAB Report #33. The recommendationsderived from these and other studies varyfrom extremely light to extremely heavy.

It was actually the widespread use of the"post-tensioned" slab-on-ground whichinduced this interest in design procedure andin many studies of reported slab failures.Such reports have; perhaps, created an over-cautious climate concerning any moves tolighten the design requirements set forth inBRAB Report #33. Many theoretical analysesshow that no lessening of the requirements ispossible, while other studies and actual fieldinstallation indicate that considerable vari-ances are permissible in many areas.

In the design procedure to be presentedherein, adjustments are made to the BRABprocedure which allow the use of this simpleprocedure with larger slabs and further sim-plify the design engineer's problem of design-ing an adequate foundation at a reasonablecost, both in terms of the engineer's time,and cost of the installation itself.

The intent of this handbook is to provide adesign procedure which could be used in anyConsulting engineer's office to give adequatedesigns for economical construction withoutthe use of large computers, or the necessityfor site investigations so extensive as tomake the use of engineered foundations eco-nomically prohibitive. The following proce-

dure, with modifications, has been used forthe last 15 years in designing foundations inthe southwest with excellent results.

EARLY DEVELOPMENTSIn the early 1950's the use of the monolithicreinforced slab foundation become wide-spread in the south central portion of theUnited States. For the most part there wereno consistent standards, and many differentversions of this foundation were to be foundthroughout the area. Each office of theFederal Housing Administration had a differ-ent version being used in its area, and the dif-ferences in cross-section and reinforcingwere great. Engineers did not have a gener-ally accepted procedure to analyze the slab,and, therefore, the problem was mostlyignored.

In 1955 the Federal Housing Administrationtogether with the National Academy ofScience organized a group of nationally emi-nent authorities and began a several yearresearch project to develop guidelines fordesign of slab-on-ground foundations.

The final report, Building Research AdvisoryBoard (BRAB) Report #33 en-titled Criteriafor Selection and Design of Residential slab-on-ground, was issued in 1968 and waswidely discussed by builders. First designs tofollow the BRAB Report required foundationsheavier even than the San Antonio FHAoffice standard LAS-22 ( Fig. 1). LAS-22 wasthought to be the heaviest design ever need-ed, but a local study showed it was inade-quate perhaps 30% of the time. There wasnaturally, great resistance to the added costsof design and construction required by theBRAB Report.

TF 700-R-03 • Page 1

Page 4: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

The next important contribution also oc-curred in 1968 when a full scale post-ten-sioned slab was built and tested to destruc-tion. A subsequent report established the fea-sibility of using post-tensioning in slab-on-ground construction and verified many of theBRAB assumptions.

In 1965 the writer developed a complete,overall design system, later modified to con-form, in format, to BRAB Report #33 and fur-ther influenced by the work done by H. PlattThompson, P.E. This system gained wide usein both Austin and San Antonio because ofthe lower cost which the post-tensioned slab

enjoyed compared to the heavier F.H.A. SanAntonio "Standard Slab".

Variations from the BRAB Report #33 weredeveloped to maintain a reasonable ratiobetween cost of the slab-on-ground and thevalue of the house it supported. The varia-tions presented later in this paper have beenderived empirically.

SOIL INVESTIGATIONSIt is considered imperative that a soils inves-tigation be made on any site on which adesign is to prepared.

TF 700-R-03 • Page 2

RESIDENTIAL SLAB-ON-GROUND CONSTRUCTIONFEDERAL HOUSING ADMINISTRATION SAN ANTONIO~ TEXAS INSURING OFFICE

EXTERIOR EXTERIOR INTERIOR ATTACHED GARAGE,BEAM BEAM BEAM CARPORT, PORCH BEAMS

(MASONRY) (FRAME)

ALL RESIDENTIAL SLAB-ON-GROUND CONSTRUCTIONSHALL COMPLY WITH THESEMINIMUMS. VARIATIONS AREACCEPTABLE WHERE SOILINVESTIGATION OF THE BUILD-ING SITE, CLIMATIC RATINGS,AND ENGINEERING ANALYSISINDICATE A SLAB OF LIGHTEROR HEAVIER DESIGN IS SUIT-ABLE.

CONCRETE: 2500 PSI MIN. COMPRESSIVE STRENGTH. LAPSOR SPLICES: MINIMUM 30 DIAMETERS.

SLAB: 4” MINIMUM THICKNESS WITH W OR D9 WIRE 10” O.C.BOTH WAYS. MAXIMUM CLEAR PANEL BETWEEN BEAMS IS15 FEET.BEAMS: 10” WIDE BY 30” DEEP. (24” DEEP FORATTACHED GARAGE. CARPORT, OR PORCH BEAMS) REIN-FORCE WITH TWO #6 BARS TOP AND TWO #6 BARS BOT-TOM, CONTINUOUS. SPACE ALL STIRRUPS 22” O.C. ALLBEAMS SHALL PENETRATE MINIMUM 6” INTO UNDIS-TURBED SOIL.

CORNER BARS: PROVIDE #6 CORNER BARS IN ALL CORNERSOF THE PERIMETER OR EXTERIOR BEAMS. INSTALL ONEAT TOP, OUTSIDE. AND ONE AT BOTTOM, OUTSIDE.

FIGURE 1

Page 5: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

For a small site with one structure, the mini-mum is obviously one test boring, whichshould be made where the worst soil condi-tion is anticipated; ie, where fill is located, orwhere the worst clay is suspected. If it is notobvious, then more than one test hole is indi-cated. In no case should a design be attempt-ed without an adequate soils investigation ofthe site.

For large sites with large structures or morethan one structure, several test holes mustbe used. In planning the investigation, planfor the worst. It is always possible to omit bor-ings in the field, based on data as it develops.

For a subdivision, there can be no fixed min-imum number of borings. The work doneshould be that which is required to get theanswer. In general, locating holes about oneto every four or Five lots, if the subdivision isreasonably uniform, will be adequate. Shoulddifferent materials be encountered, addition-al borings must be placed to provide morecomplete information of the underlying soils.In some cases it is necessary to drill each lot.When a contact between a high P.I. soil andlimestone is discovered, for instance, each lotwhich the contact crosses must be designedas though the entire lot were the worst soilcondition.

As drilling progresses, samples should betaken at 2’ intervals and at each different soilstrata encountered, to a depth of at least 15’If it is likely that some soil will be cut from thelot, borings should be deepened appropriate-ly. Perhaps all borings should be 20 feet deepto allow for any cut, but at present, 15’ bor-ings are considered sufficient. Undisturbedsamples should be taken, where possible, toallow evaluation of unconfined finedstrengths of the various strata. As unconfinedstrength of 1 ton is usually sufficient for sin-

gle story frame houses such as those underconsideration. For commercial and multi-story, 2 tons is usually adequate to insureagainst bearing capacity failure.

During field investigation it is important tomake notes of existing fill, trees, thickets, oldfence lines, roads, slope of each lot, topogra-phy, seeps, sinks, rock outcrops, and anyarea which may require fill to bring it up tograde before construction. Grading anddrainage plans, when available, may be help-ful in identifying some of these significantfeatures. Note these fill lots or even suspect-ed fill lots in the report so that proper caremay be exercised by the insuring agency, cityofficials, design engineers, et. al.Uncompacted fill under the beams of anengineered slab will almost certainly createproblems. Specify that all fill be acceptablematerial, properly compacted. H.U.D. proj-ects and subdivisions are supposed torequire that fill be placed in accordance with“Data Sheet 79-G”. 15

LABORATORY TESTINGAfter the proper field investigations havebeen made, it is necessary to run laboratorytests on samples from the various stratataken in the field. It is important that all stratabe correctly identified and tested.Identification should be in accordance withthe unified soil classifications chart shown inFig. 2. Such terms as “caliche,” “fat clays,”“loam” and other colloquialisms should beavoided or used only as extra comment.Plotting liquid limits and plasticity indices onthe classification chart will confirm field eval-uations. If proper testing and Identificationare done, some degree of uniformity can beapplied to Slab-on-Ground designs.

TF 700-R-03 • Page 3

Page 6: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

TF 700-R-03 • Page 4

MAJOR DIVISIONSGROUP

SYMBOLSTYPICALNAMES

CO

AR

SE

GR

AIN

ED

SO

ILS

Mor

e th

an 5

0% r

etai

ned

on N

o.20

0 si

eve*

GRAVELS

50% or more ofcoarse fraction

retained on No. 4sieve

CLEANGRAVELS

GWWell-graded gravels and

gravel-sand mixtures,little or no fines

GPPoorly graded gravelsand gravel-sand mix-tures, little or no fines

GRAVELSWITHFINES

GM Silty gravels, gravel-sand-silt mixtures

GC Clayey gravels, gravel-sand-clay mixtures

SANDS

More than 50% ofcoarse

fraction passesNo.4 sieve

CLEANSANDS

SWWell-graded sands and

gravelly sands,little or no fines

SPPoorly graded sandsand gravel-sand mix-tures, little or no fines

SANDSWITHFINES

SM Silty sands, and-siltmixtures

SC Clayey sands, sand-siltmixtures

FIN

EG

RA

INE

DS

OIL

S50

% m

ore

pass

es N

o.20

0 si

eve*

SILTS AND CLAYS

Liquid limit 50%or Less

MLInorganic silts, very finesands, rock flour, silty or

clayey fine sands

CL

Inorganic clays of low tomedium plasticity, gravel-ly clays, sandy clays, siltyclays, lean clays

OLOrganic silts and

organic silty clays oflow plasticity

SILTS AND CLAYS

Liquid limit greaterthan 50%

MH

Inorganic silts,micaceous or diatoma-

ceous, fine sands orsilts, elastic silts

CH Inorganic clays of highplasticity, fat clays

OH Organic clays of mediumto high plasticity

Highly Organic Soils PT Peat, muck and otherhighly organic soils

Figure 2

* Based on the material passing the 3 -in. (75-mm) sieve.

Page 7: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

DETERMINING THE “EFFECTIVE P.I.”The BRAB report bases its design procedureon the soil plasticity index (P.I.). This designprocedure also uses the P.I. because it is arelatively simple-pIe test which is routinelyperformed in all testing laboratories.

Since the soil is not always constant withdepth, it is necessary to find the “effective P.I.”of the underlying 15 Feet. BRAB Report #33suggests a weighing system (Fig.3).

This seems as valid as any weightingmethod, as McDowell's16,17 procedure forcalculating potential vertical rise also indi-cates that the upper few feet is the mostactive. The activity then decreases with depthdue to confining pressure and protectionfrom seasonal moisture change, etc. Anysystem that gives more attention to the sur-face soils is probably satisfactory. One placewhere this system might give erroneousresults would be in formations which containsand stringers or are overlaid by porous sandwhich would provide quick, easy routes forwater to reach underlying or interbedded CHclays.

Another case would be high P.I. clays over-laying rock. Using a zero (0) P.I. for these rocklayers can reduce the “effective P.I.” exces-sively making it appear to be a very innocu-ous site, It is probably best never to use zerofor a P.I. Since BRAB recognizes 15 as abreaking point for Type Ill slabs, some mini-mum value such as 15 should always beused for those layers with little or no P.I.BRAB recognized the problem by utilizing theP.l. immediately below the slab if it was high-er than the P.I. of the lower layers. This veryconservative approach will always yeld good,

safe designs, considerablyoverdesigned.

OTHER PARAMETERSOnce the “effective P.I.'s” foreach boring are calculated,they need to be modified bysome other parameters. Theslope of the lot should beused to increase the “effectiveP.I.” Figure 4 can be used todetermine coefficients basedon slope.

The degree of over-consolidation of the natu-ral material can be estimated from the uncon-fined compressive strengths. By using Fig. 5a coefficient for over-consolidation can bedetermined.

TF 700-R-03 • Page 5

Slope of natural ground vs. Slope Correction CoefficientFigure 4

Figure 3

Page 8: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

Other factors are known to require consider-ation; moisture condition at time of construc-tion, geologic formation, percentage of soilpassing #40 sieve, percentage passing #200 sieve, all of these affect the potential volumechange of the underlying soil. The correctvalue of “effective P.I.” is that from the equa-tion:Eff. P.I. ( ) = Effective PI x Cs x Co x Cy x Cz • • • • • Cn

Much work needs to done in this area.

The ultimate performance of a slab reflectshow well the soil analysis was done. Slabdesign is only as good as the soil data onwhich it is based. Some engineers say theydo not need soil data to do a design.They areeither deceiving themselves or are over-designing their slabs in which case theydelude their clients and ultimately, the pur-chaser of the structure. There are few cir-cumstances where the engineer is justified inover-designing and wasting the client’smoney. There are no circumstances wherethe engineer is justified in under-designing--even at the client’s request.

WARNINGIt should be recognized that there are certainconditions which neither this procedure norany other will be able to anticipate. Examplesof such problems which might cause difficul-ty, even to a well designed slab, would be thelocation of an old fence row beneath thefoundations, a broken water pipe, improperdrainage away from the foundation, a slablocated on top of of previously existing tree orthicket, massive erosion or loss of supportdue to lack of compliance with proper sitepreparation standards, poor maintenance, orimproper installation. There are numerousdocumented cases where slabs have exhibit-ed less than the desired results due to one ormore of these causes. Most of the causesmentioned above can be mitigated by properconstruction and inspection.The others, suchas old fence lines, trees, or thickets are gen-erally unknown to the Soils Engineer and theDesign Engineer, and, in many cases, cannotbe anticipated at all. It is felt that the presentstate of the art make these conditions fallbeyond those for which the designer canproperly be considered responsible. Theproblem with this line of reasoning is that bythe time it becomes apparent there is a prob-lem with the slab, it is not possible in mostcases to determine that the problem is one ofthose which could not be anticipated. Theowner is having difficulty, and he is seekingrelief, and quite often, revenge and restitu-tion. These cases usually end up beingdecided by a jury. This is one very good rea-son for not trying to reduce the design stan-dards too far and for trying to get a goodstandard adopted so it will be clearly definedwhen the engineer has done all that he canbe reasonably expected to do.

TF 700-R-03 • Page 6

Unconfined Compressive Strength (qu) TSF

Figure 5

Page 9: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

LOADING CONSIDERATIONS First look at a small slab for a single storyhouse, trussed roof construction, masonryveneer, fire place and one car garage. Whatdo the loads look like? (see Fig. 6 )1. Roof LL & DL, stud wall, brick veneer and

ceiling loads2. Brick chimney load3. Stud wall and brick veneer4. Wheel loads5. Floor live loads (including non bearing

partition allowances)6. Concentrated loads from beam spanning

garage doors

Loads in Fig.6 are only the loads applied tothe top of the slab. To these must be addedthe weight of the slab, edge beams, and inte-rior stiffening beams. (see Fig.7).

To the soil underneath, these loads are notnearly so clearly defined. For the small slabs

generally used under houses and small com-mercial buildings the loads can be assumedto be uniform. When the unconfined strengthof the soil is less than 1 ton/sq. ft., settlementor bearing can be a problem and should beconsidered, but on stiff expansive clays anydistress in the slab and superstructure will becaused by the volumetric movement of thesoil due to moisture change. If the soil did notchange, the weight of the house or smallbuilding would be transmitted directly throughthe slab and into the under-lying soil whichwith the exception mentioned above, caneasily carry the weight since it is usually lessthan 500 lbs. per sq.ft.

Since the loads are small, it seems justifiedto use the simplifying assumption of a uni-form load. This has given good results on sin-gle story residences.

SUPPORT CONDITIONSPrior to the time the BRAB report was issued,the writer had been working on the problemsome years and had developed a workingdesign procedure.

The procedure involved an area of loss ofsupport, (Fig. 8 ) the diameter of which was afunction of the soil (P.I., degree of com-paction, etc.) and which was allowed to moveto any position under the building. The mostcritical locations, of course, were under loadbearing walls and columns. The equation hadbeen adjusted to give both positive and neg-ative movements.

TF 700-R-03 • Page 7

Superstructure LoadsFigure 6

Slab ConfigurationFigure 7

Area of Support LossFigure 8

Page 10: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

This procedure was developed entirely fromlooking at slabs that seemed to work andthose which did not and writing an equationwhich would produce sections equal to thosewhich had been performing satisfactorily.Formulas had been developed which tookinto account loss in the center as shownabove, loss at edges and corners. Also, therewere provisions for inclusion of concentratedloads.

This procedure designed only one or twobeams at a time. The BRAB report showedsupport conditions (see Fig.9) which allowedall beams in a given direction to be consid-ered at one time. This simplified the designprocedure, and, when the two design proce-dures were compared, they were found togive similar results. The BRAB procedureproduced heavier-designs, but, with minormodifications, they could be adjusted

The moment equations developed by BRABgive a maximum moment, both positive andnegative at midspan (Fig. 10). This is not asimple cantilever moment. For short slabs itis a reasonable analysis. For longer slabs itquickly becomes excessive.

To eliminate the problem, several alternativeshave been discussed:

a. Design all slabs, longer than a certain

length, for a maximum moment based onthat length and all slabs less than that, fortheir exact length (Fig. 11a)

b. Use an effective length in the originalBRAB equations. (Fig. 11b)

c. Design all slabs for both positive and neg-ative bending based on some cantileverlength. (Fig. 12)

Note that with Figure 11a there is no increasein design moment beyond the assumed max-imum length. Obviously, as the slabs getlonger, more reinforcing needs to be addedto compensate for friction losses, drag, etc.P.C.I. goes into great detail to calculate theselosses. By using an effective value for “L” asshown in Figure 11b, these losses are auto-matically covered. While this was a complete-

TF 700-R-03 • Page 8

Assumed Support ConditionsFigure 9

Location of Maximum MomentFigure 10

Length Modification AssumptionsFigure 11

← Non-supported

← Supported

← Non-supported

a. Cantilever

b. Simple Span Beam

Page 11: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

ly empirical approach, it was easy to use andgave good results.

It has been noted during previous researchconcerning slab-on-ground construction thatthe large slabs tend to reach an equilibrium inthe center portion and fluctuate only withseasonal moisture change.

Some routine testing during the time of thesoils investigations can reasonably define thedepth of the zone of seasonal moisturechange which, many say, is roughly equal tothe horizontal distance moisture may pene-trate under a slab and cause differentialmovement or pressure. While this doesindeed give a cantilever action such as waspreviously described, the point of maximummoment is not located at a distance from theedge equal to the depth of the seasonalmoisture change and nato distance of Much work has been done trying todefine this cantilever distance. This designprocedure has developed an empirical curvewhich, when used with the equations set outlater, gives good results. Again, it makes nodifference whether the cantilever theory isused or the BRAB equations are used, solong as the proper input is supplied for eithercriteria.

The BRAB equations utilizing an effectivelength, as opposed to the total length, wereused for years and gave good results. Sincethe P.C.I. and P.T.I. have advocated a can-tilever approach, this procedure has beenmodified to use a cantilever (see Fig. 12)which gives the same results as the modifiedBRAB equations. Note that in cases bothpositive and negative reinforcing are sup-plied.

There is, at this time, a great deal of discus-sion concerning the relative equality of the

positive and negative moments used indesign. It seems that a large number of engi-neers feel that the positive moment is not assignificant a design parameter as is the neg-ative moment. Numerous proposals havebeen offered for the reduction of the positivemoment. A look at the loading conditions onmost slabs will offer support to this reductiontheory, and some experimental work hasbeen undertaken by this firm to evaluate thisproposal. The results observed indicate thatsome reductions are justified and allowable.To date, no findings have been brought forth,backed by any performance data, to indicatewhat magnitude of reduction should be con-sidered.

TF 700-R-03 • Page 9

L (1-C).2

(1-C) vs. Cantilever Length (lc)Figure 12

L or L’ vs kFigure 13

Page 12: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

THE SLAB DESIGNThe proper procedures for soils investiga-tions and reporting have been mentioned inthis report, and, assuming that the properinformation is available, an actual foundationdesign can be begun. The design procedurebegins by determining a unit weight of thebuilding including its foundation. Assume thatsuch weight is distributed uniformly over theentire foundation area. Those conditionswhere concentrated loads are felt to be ofsuch magnitude that they must be consid-ered, are not covered in this paper.

As previously stated, the weight of the struc-ture is not so significant as the support con-ditions of the underlying soil material, howev-er, the weight calculated in these proceduresis generally indicative of the amount of differ-ential movement which can be tolerated bythe superstructure. The heavier the unitweight, the more brittle and sensitive tomovement is the superstructure material ingeneral. Also, heavier loads generated bymulti-story buildings indicates that additional

stiffness must be supplied to the foundationbecause of the sensitivity of multi-story build-ings to differential movement. A very lightwood frame structure with wood siding andno masonry would be far less susceptible tostructural and cosmetic damage than wouldbe a heavy all-masonry or brick veneer typebuilding. Use of these increased unit weightsautomatically generates additional momentand deflection criteria to satisfy the need foradditional stiffness and strength.

These criteria, incidentally, apply to residen-tial and small commercial construction andnot to the more monumental type structuressuch as banks, churches, and highrise build-ing. These same design procedures could beused for these types of buildings, reducingthe allowable deflections and stresses, andincluding allowances for high concentratedloads to produce the more rigid foundationsnecessary for this type construction.

In any event, assume that for this criteria thecalculated weight of the house, including the

foundation for one storybrick veneer type con-struction, is "w" lbs. persq. ft. (The value 200 canbe used for almost anysingle story woodframe,brick veneer type con-struction and not be toofar from the actual weightof the house).

With the weight of thehouse known, refer toFig. 14 which is extracteddirectly from BRABreport to select the cli-matic rating for the city inwhich the house is tobuilt. The values for Texas

TF 700-R-03 • Page 10

Climatic Rating (Cw) ChartFigure 14

Page 13: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

range from 15 in west Texas to as high as 30in east Texas. This chart reflects the stabilityof the moisture content which may be expect-ed in the soil due to the climatic conditionswhich may vary from year to year. A very lownumber indicates an arid climate which willbe very low humidity and low ground mois-ture except for a few weeks or months of theyear when a heavy rainfall will occur and theground will take on a considerable amount ofmoisture creating apotential for a large vol-umetric change in ashort period of time. Thelarger numbers, such asthose in east Texas,indicate in general amore humid climatewhere the moisture con-tent of the soil tends toremain more uniformthe year round. Refer tothe BRAB report for amore complete de-scription of this chart.

The P.I. and the climateconditions now beingknown, it is possible toselect from Fig. 15 thesoil-climate support index, indicated as (1-C).

The following formulas will be used to calcu-late the moment, shear and deflection, usingthe equivalent lengths shown in Fig. 14 aspreviously discussed.

These calculations are performed for boththe “Long” and “Short” directions. The actualvalue of L and L’ are used when they refer tothe width of the slab. The most critical ofthese is deflection. A slab which deflects toomuch will cause serious problems for thesuperstructure, even though the slab doesnot actually break. In general then, it is bestto solve first for “I required”.

The cross. section of slab is not known, butthe value of 200 lbs ./sq.ft. is almost alwaysadequate to include the slab weight.

TF 700-R-03 • Page 11

PI vs. (1-C)Figure 15

Where: M = Moment, positive or negative∆ = Deflection in inchesV = Total shearw = Unit weightL’ = Width of slab consideredLc = Cantilever length (lck)Ec= Creep modulus of Elasticity of concreteI = Moment of Inertia of section

M = w L ‘ (Lc)2

2

∆ = w (Lc)4 L’4 Ec I

V = w L’ Lc

Page 14: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

BEAM SPACING AND LOCATIONAlmost all houses, if not a basic rectangle,can be divided into two or more rectangles. Ifthe building under consideration is a combi-nation of two or more rectangles, a set of cal-culations must be done for each rectangle.The rectangles are then overlaid and theheavier design governs the common areasas shown in Fig. 16. Obviously there will betimes when good engineering judgement isrequired, as all houses are not nice neatmodules.

On some occasions the geometry of thehouse will dictate where the beams are to beplaced. When this is the case, the beams canbe located, and the calculations carried outfor width and depth based on the knownnumber of beams in each rectangle.

If the design seems excessively heavy byusing the maximum spacing's, it is possibleto recalculate beam depths and reinforcingbased on supplying additional beams.

Once the spacing and location are known,the size of the beams can be determined bytrial and error. BRAB specifies that the maxi-mum face to face distance between beamsshould be 15’. P.C.I. states the maximum

should be 20’. Experience has shown thatthese are very conservative values. They areto apply to any slab on soil with P.I. of 15 orabove. This is a very rigid requirement.Perhaps a more rational approach is onesuch as is shown in Fig. 17.

The designer can then use a chart such asthe one shown, or the various maximums tomake the first run.The number of beams thenwill be:No. = L + 1 Where S = Spacing from the chart

S

With the number of beams known, a width foreach can be selected, and a calculationmade for the moment of inertia. If desired, avery good first approximation can be madeby using the following formulas.

The difference in the two equations takes intoaccount the cracked section moment of iner-tia vs. the gross section allowed in the pre-stressed slab. Anyone not wishing to use thegross section moment of inertia can use thereinforcing steel for both type slabs. Theseequations are good only with beam spacingsno greater than those shown in Fig. 17.

TF 700-R-03 • Page 12

Slab Segments and CombinedFigure 16

1-C vs. Maximum beam spacingFigure 17

Page 15: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

These solutions will give you “N” no. of beams“b” inches wide and “d” inches deep whichwill give you an “I” in the order of magnituderequired to limit deflection to 1/480*. It ispointless to argue about the relative merits of1/360 vs. 1/480. In most cases depths basedon 1/360 will not be economical when itcomes to selecting reinforcing.

This design moment has been used to selecta cross section which will resist deflection. Itis now necessary to provide the reinforcing.Referring back to the BRAB (also PCI) it isnecessary to provide both positive and nega-tive reinforcing.

* ACI 318-77, Table 9.5 (b) page 12 recommends 1/480 for roof orfloor construction supporting or attached to non-structural elementslikely to be damaged by large deflections.

SLAB REINFORCING

BRAB states again an arbitrary maximumspacing; the only choices are #3 bars at 12”(Asfy = 4400 lbs./ft. with Grade 40, or 6600Ibs./ ft. with Grade 60 bars), or in a 5” slab, or#3 bars at 10” (Asfy = 5200 lbs./ft. with Grade40, 7920 lbs./ ft. with Grade 60 bars) O.C. ina 4” slab when the beam spacing exceeds 12feet. Both are excessive in most cases. Aslong as the beam spacing does not exceed

that shown in Fig. 17, it is possible to use lessslab reinforcing.

ACI would limit the minimum reinforcing toAsfy = 3840 for Grade 40 and Asfy = 5184 forGrade 60 in a 4” slab. That is not realistic.Slabs-on-ground are not as sensitive to tem-perature change as suspended slabs, andneed much less reinforcement. Many slabshave been done with Asfy less than 2600with no ill effects. These are on low P.I.designs, of course. On high P.I. sites, therequirements of Asfy = 5200 as recommend-ed in BRAB is reasonable. (Fig. 18)

*ACI 318-77 allows As/LF - 0.0018 x 60,000 which will further fy

reduce the 0.0020 or 0. 0018 requirements when reinforcement withyield strengths exceeding 60,000 PSI measured at a yield strain of0.35 percent are specified.

BEAM REINFORCINGSolve for top beam steel based on negativemoment, include slab steel falling within thecooperating slab area. (see Fig. 20).

TF 700-R-03 • Page 13

1-C vs. AsfyFigure 18

(1-C) vs. As/LF

Figure 19

Effective Width of “T” BeamsFigure 20

Page 16: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

Solve for the bottom steel based on calculat-ed (reduced if feasible) positive moment. Putthe same size bars in a beam if 2 or more arerequired. It is usually best not to use morethan 3 bottom bars in each beam. If thatmuch steel is required, deepen the beams toincrease the lever arms or add more beamsor both.

SITE PREPARATIONOften the most overlooked part of the entireoperation is the site preparation. The propersequence should include the following:

1. Site clearing2. Excavation (if any)3. Fill selection and placement

Inadequate attention to any of these phasescan cause foundation problems even yearsafter the slab is built.

It is very important that the site be cleared ofall grass, weeds, old decaying or decayedorganics, roots and trash. This material whenleft under the slab can and will continue todecay and cause settlement at later dates. Itis surprising how little settlement is requiredto cause superstructure distress. Theremoval of approximately six inches of topsoil is usually adequate to removegrass,weeds, etc. and their roots. Trees andlarge bushes generally require grubbing togreater depths to insure adequate removal.This site clearing should be done prior tobeginning any required excavation.

Excavation of on-site material can begin afterthe clearing and grubbing is completed. Thisallows any acceptable on-site fill materialuncovered to be placed or stockpiled withoutcontamination. This is desirable when practi-cal because it is cost effective to handle thematerial only once. When a continuous,

simultaneous cut and fill operation can bearranged, it will save the owner-developerquite a bit in site preparation costs.

When, for some reason, this operation can-not be arranged, it is necessary to stockpileor waste the excavated material. Stockpilesshould be made on prepared sites. Theyshould be cleared the same as a buildingsite. Wasting should be in an area which willnot be utilized later for building and which willnot be subject to erosion or create drainageblockage.

All on-site material which is not suitable forstructural fill should be wasted or removedfrom the site.

Fill selection is usually governed by theexpansive qualities of the natural soil. Fillshould always be as good or better than theon-site material on which it is placed.Sometimes more than one type of fill may beused.

In general, lot preparation in subdivisions ispoorly done. Side slope lots requiring cut andfill on each lot are usually done without anyeffort to select the best material or supply anycompaction to the fill.

TF 700-R-03 • Page 14

Side Slope LotsFigure 21

Page 17: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

SLAB FORMING1. Foundation forms are to be built to con-

form to the size and shape of the founda-tion, and should be tight enough to preventleaking of mortar. The bracing must bedesigned so that the concrete may bevibrated without displacement or distortionof forms.

2. Beams should be formed by one of twomethods:

a. Single family slabs have been tradi-tionally done by placing loose fillinside the forms and forming thebeams with paper sacks filled withsand or fill material. For small, lightlyloaded slabs this seems adequate.

b. Large slabs such as apartments,warehouse, shopping centers, etc.,are often beamed by placing com-pacted fill to underslab grade andthen trenching the beams with apower trencher. This method addssupport to the slab and, helps it resistdeflection by effectively reducing thepotential expansion of underlying soil.

Unless specified on the plans or spec-ifications for single family foundations,it is assumed that the methoddescribed in "a" above will be used.Method "b" may be used if desired,but it is not required. For multi-familyfoundations or commercial work,method “b” should be required.

3. After the beams are Formed, a waterproofmembrane should be placed.** Either 6 milpoly or hot-mopped asphalt impregnated

felt may be used. The waterproofingshould be lapped adequately to provide acontinuous sheet under the entire slab.When poly is used, care must be taken tosee that it does not become entangled inthe reinforcing. Nailing the beam sides tothe fill just before placing helps. At theexterior beam, the poly should be cut off atthe bottom inside face of the beam andnailed as shown (Fig. 22), carried up ontothe exterior form and nailed (Fig. 23), orlapped with felt and nailed (Fig. 24).

TF 700-R-03 • Page 15

* Not universally accepted, even by all HUD/VA offices, but currently used in San Antonio-Central Texas area.**There is much discussion over the membrane requirement, but it currently is a HUD/VA requirement.

Edge Beam Forming and StakingFigure 22

Edge Beam Forming Figure 24

Edge Beam Forming Figure 23

Typical Steel Placement Figure 25

Page 18: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

STEEL PLACEMENT1. For the most part, steel placement in the beams will be two bars in the top and two in the

bottom (Fig. 25). The bars will be held in position by stirrups at appropriate spacing. Thespacing should be that which will assure the proper positioning of the steel. The bottombars should be set on concrete bricks or blocks to keep them raised above the bottom ofthe beams. Corner bars equal in size to the larger size (maximum size - #6 bars) of anybars meeting at an exterior corner (Fig. 26) should be provided both top and bottom.Where interior beams dead end into exterior beams, corner bars should be supplied forbottom reinforcing only and should be the same size as the bottom bars in the interiorbeam or #6 bar maximum. (Fig. 27)

TF 700-R-03 • Page 16

Steel Placement at CornersFigure 26

Steel Placement Interior to Exterior BeamFigure 27

Page 19: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

2. After the beam steel is in place, the slab steel is placed. If it is necessary to lop slab steel,the laps in adjacent bars should be staggered at least 5’ - 0” (Fig. 28)

The slab steel is run continuously from side form to side form (lapping 24 diameters mm.where splices are required), allowing 1-1/2” cover over the ends of the bars. On the edgeswhere the bars run parallel to the form, the first bar should be placed a maximum of 12”from the outside form. All slab steel should be securely tied and blocked up by chairs orconcrete briquettes. (Figures 29 & 30 )

3. To insure the lowest possible foundation cost the use of welded wire reinforcement forslab reinforcement should be investigated. Different styles of WWR can furnish the samesteel area and the following are suggested for design example:

TF 700-R-03 • Page 17

Stagger Laps in Slab SteelFigure 28

Blocking Steel Interior BeamFigure 30

Blocking Steel Exterior BeamFigure 29

Page 20: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

TF 700-R-03 • Page 18

Welded Plain Welded WireReinforcementASTM Specification A 185, fy = 65 KSI

As req’d = .098 x 40/65 = .060 in2/ft.

Est. wt. = 42#/CSF WWR 4 x 4 - W2 x W2

6 x 6 - W3 x W312 x 12 - W6 x W6 12 x 12 - W6 x W6 with 2-W3 outside edge wires @ 4” c/c each side.

Welded Deformed Welded WireReinforcementASTM Specification A497, fy = 80 KSI

As req’d = .098 x 40/70 = .056 in2/ft. est.

wt. 36#/CSF

WWR 16 x 16 - D6.5 x D6.5 with oneD3.8 outside edge wire each side.

The two welded wire reinforcement styleswith 12” spacing for smooth wire and 16”spacing for deformed wire have been recent-ly developed to further improve the efficien-cy of welded wire reinforcement. The largerwire spacings make it possible to install thewelded wire reinforcement at the desiredlocation in the slab because it permits theworkmen to stand in the openings and raisethe welded wire reinforcement to place thesupports.

All welded wire reinforcement sheets mustbe spliced at both sides and ends to developthe full design fy. For smooth welded wirereinforcement ACI 318-77 requires that thetwo outside cross wires of each sheet beoverlapped a minimum of 2 inches and thesplice length equals one spacing plus 2 inch-es with a minimum length of 6 inches or 1.5Id whichever is greater. For slabs on ground

the one space + 2 inches or 6” minimum willprevail. This means that for a 12” wire spac-ing the minimum side lap splice would be 14”but by spacing the 2 edge wires at 4” the lapis reduced to the minimum of 6”. In additionthe lapping of 2 wires in the splice length willprovide twice the required steel area. Byreducing the area of the 2 edge wires by50%, the required As is provided uniformlythroughout the width of the slab. This reduc-tion in wire size does not reduce the capaci-ty of the splice because ASTM SpecificationA-185 provides that the weld strength shallbe not less than 35,000 times the area of thelarger wire. These tonnage saving featuresapply only to side laps but many welded wirereinforcement manufacturers can providesheets with variable transverse wire spac-ings and the length of end laps can bereduced even though wire sizes cannot.

The length of splice for deformed weldedwire reinforcement is determined by the sizeand spacing of the spliced wires, and onlythe outside cross wire is lapped. While thelap length cannot be changed, the size of theoutside cross wire can be reduced withoutchanging the strength of the lap. ASTMSpecification A497 stipulates that the weldshear strength shall not be less than 35,000times the area of the larger wire. These engi-neered welded wire reinforcement styles arenot generally available for small foundationslabs, but, when numerous small buildingsor large slabs are being considered, it is pru-dent to check with welded wire reinforce-ment suppliers because substantial savingsin cost can often be accomplished. As withrebar reinforcing, welded wire reinforcementmust be chaired or supported on brick orblocks to insure proper placement in theslab.

Page 21: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

SPECIAL CONDITIONS

1. Special conditions from time to time willarise which will require modifications tobeam depths, forms, etc. Many of theseare covered by typical details which illus-trate what modifications are allowed with-out approval from the Engineer. If a spe-cial condition occurs, such as a deep

beam, the Contractor needs instruc-tions in the typical details tellinghow to handle the situation. In thecase of the deep beam, deepen thebeam by the required amount andrelocate steel (Fig. 32).Refer to“Note A” to see if additional steel isrequired. Obviously, if the beamexceeds 72”, the engineer must becontacted for additional information.

2. When an exterior beam is deepened,some slight changes must be made to theinterior beams which intersect the deep-ened beam (Fig. 33). The bottom of theinterior beam should slope down at leastas deep as the mid-depth of the deep-ened exterior beam. If the interior beamdepth is already deeper than the mid-depth of the deepened exterior beam, nochanges are required to the interiorbeam.

3. Extended beams to carry wing wallsshould be handled as shown in the typicaldetail (Fig. 34). It is very important that

TF 700-R-03 • Page 19

NOTE “A”1. WHEN OVERALL DEPTH EXCEEDS 36”

ADD 1 - #3 HORIZONTAL IN EXTERIORFACE OF BEAM FOR EACH 18”. STARTSPACING 6” FROM THE TOP.

2. FOR BEAMS 36” TO 54” DEEP USE #3 STIR-RUPS AT MAXIMUM 24” O.C.

3. FOR BEAMS 54” TO 72” DEEP USE #3 STIR-RUPS AT MAXIMUM I8” O.C.

4. FOR BEAMS OVER 72” DEEP CONTACTENGINEER FOR SPECIFIC DETAILS.

Engineered Welded Wire Reinforcement Sheet with Special Side LapsWelded Smooth Welded Wire Reinforcement

Figure 31

Deepened BeamFigure 32

Interior to Exterior BeamFigure 33

Extended Concrete BeamFigure 34

Page 22: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

the additional top reinforcing be added asshown; otherwise the beam may be bro-ken off.

4. Beams that continue throughdrops must be deepened by theamount of the drop, and the tran-sition sloped (Fig. 35). If the dropis framed as a sharp corner onthe bottom of the beam, stressconcentrations can occur whichmay cause difficulties.

5. Other special conditions may arise fromtime to time but they are too numerous tobe covered here.

TF 700-R-03 • Page 20

Side View of Typical Beam at DropFigure 35

Side View of Typical Beam at DropFigure 36

Drop under Sleeve through Beam

CONCRETE PLACINGOver the years the word “pouring” has cometo be used almost exclusively to describe thefunction of placing concrete. Unfortunatelythat term is all too descriptive of the practicewhich has become common throughout theindustry. When placing concrete for an engi-neered foundation, it is imperative that theconcrete actually be placed, not “poured”.

Residential floors need to have adequatestrength, surfaces that are hard and free ofdusting, and the cracking should be held to aminimum. The hardness and finish of the sur-face will depend on how densely the surfacematerials are compacted during finishing,and the adequacy of the cement paste.

Cracking however is mainly a function of thedrying shrinkage which takes place immedi-ately after placing and is generally more con-trolled by atmospheric conditions than by theconsistency of the concrete itself. This is agross generalization, however, as high watercement ratios will increase the shrinkageproblem. Good concrete for slabs-on-groundshould be made from a mix in which thewater cement ratio is kept low and shouldcontain as much coarse aggregate as pos-sible at the surface. Compressive strengthsfor concrete slab-on-ground foundations aregenerally specified as a minimum of 2500PSI at 28 days. It is important to note theword minimum. The 2500 PSI should be theminimum strength, not the average strength.

Page 23: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

This 2500 PSI is a generally accepted figurein the industry, since it has become anaccepted figure for HUD/VA construction.

In keeping the water cement ratio low, addmixtures can be of particular benefit. This isparticularly true with respect to air entrain-ment, retardants and accelerators.

Calcium chloride is a common cold weatheradditive to accelerate settling and hardening.It should properly only be added to the mix inthe mixing water. It is important to emphasizethat calcium chloride is not to be used in afoundation which is pre-stressed. The use ofcalcium chloride in foundations with rebarreinforcing or welded wire reinforcing must belimited to a minimum of 2% by weight ofcement.

Several operations need to completed beforebeginning the placing of concrete. Screedsshould be set inside the form area to estab-lish finished slab grade prior to beginningconcrete placing.This will improve the level ofthe finished slab and eliminate much of theunevenness of the slabs currently found.Keys for joints may, on certain occasions, beused as screeds, since they need to beplaced at proper intervals in large slabs toeliminate or control the shrinkage cracking.

When the concrete is delivered it should beplaced as close as possible to its final posi-tion in the foundation. It should be spreadwith shorthandle, square ended shovels andnot by the use of rakes. Internal vibration atthe time of placing should be mandatory, asthis allows a stiffer mix to be used and facili-tates placing.

Screeding, tamping, and bull floating will beof course finished prior to the time the bleedwater has accumulated on the surface. After

the bull floating, the final finishing should notbegin until bleed water has risen and evapo-rated, and the water sheen has disappearedfrom the surface. At the time the concreteshall be stiff enough to sustain a man's footpressure without indentation.

With regard to final finishing operations, theaccumulation and evaporation of bleed waterwill vary considerably with weather condi-tions and types of mixes. When bleed water istoo slow to evaporate, it may be pulled offwith a hose, or blotted with burlap. The sur-face of a foundation should never be driedwith what is commonly called dusting. This isa method whereby dry cement and, some-times, dry cement and sand is placed on theslab to blot the bleed water. This will cause aweak surface and, possibly, subsequentdeterioration of the surface.

Immediately after the foundation has beenfinished, a curing compound should beplaced to inhibit further evaporation of waterfrom the concrete mix. This will tend toreduce the amount of shrinkage crackingwhich will occur in the foundation.

When using a liquid curing membrane, it isimportant to select a com-pound that will notinterfere with future bonding of floor finishes.There are several such compounds on themarket.

Forms should remain on the finished con-crete slab for a minimum of 24 hours.Removal prior to that time can cause damageto the concrete. After 24 hours the forms canbe carefully removed without damaging theconcrete.

TF 700-R-03 • Page 21

Page 24: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

INSPECTIONThe most general problem encountered waslack of suitable field inspection and control. Ifthe foundations are not constructed in accordwith the design drawings and specifications,then benefits to be derived from improve-ments in codes or the state of the art will bediminished.” 20

Before placing, the contractor should call foran inspection by some inspection agency. ForFHA-VA single family construction, this ishandled by the FHA or VA. For non FHA/VAhouses it is, or should be, handled by the city,but most cities, especially small ones, do nothave enough staff.

Cities should require adequate inspection,,either by their own forces, or by the designengineer who should, after all, be most famil-iar with his own design.

When the Engineer is not permitted to checkthe construction, one of the other inspectorsshould furnish a certificate to the Engineerthat the slab is properly installed in accor-dance with the Engineer s plan. The followingis a partial list of points which should be ver-ified by the inspector.

TF 700-R-03 • Page 22

1. Check number of beams

2. Measure beam width

3. Measure beam depth

4. Check beam spacing

5. Check tightness and alignment of forms

6. Check blocking under beam reinforcement

7. Check compliance with fill penetration or have fill certification

8. Check beams for proper number and size of reinforcing bars

9. Check the slab reinforcing for proper size and spacing.

10. Check to see that all slab reinforcing is adequately blocked to insureproper placement in concrete.

11. Test concrete for maximum 6” slump

12. Make cylinders for strength certification

13. See that concrete is vibrated or rodded

14. Insure adequate curing

15. Check for cracking or honeycombing

Page 25: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

SHRINKAGE CRACKSAll concrete has cracks! There is not yet inthe industry the ability to produce crack-freeconcrete. What can best be done is to limit orreduce the amount and kinds of cracks.

Those cracks that occur prior to the harden-ing of the concrete are generally formed bythe movement of the formwork, settlement ofthe concrete during setting, or plastic shrink-age cracks which occur while the concrete isstill plastic. Other cracks which can occurafter the setting of concrete are shrinkagecracks due to drying of the concrete, thermalcracks due to changes in internal heat ofhydration or due to external temperature vari-ations, cracks due to stress concentrations,or cracks due to structural overloads.

The most common cracks which are seen infoundations are plastic shrinkage crackswhich occur early after the concrete is placedand are due to the rapid drying of the freshconcrete. Even if plastic cracking does notoccur, similar type cracks can form during theearly stages of hardening even days after thefinal finishing has taken place. While curingmembranes will not eliminate the plasticshrinkage cracks that occur prior to setting,they can be very beneficial in reducing oreliminating the shrinkage cracks which willoccur after finishing.

The effects of temperature, relative humidity,and wind velocity are, in general, beyond thecontrol of the engineer or the contractor andmust be accepted as risks when the slab isplaced.

It is, therefore, wise to specify the minimumsacks of concrete which will be expected togive the recommended compressivestrength, utilize the minimum water contentnecessary for workability, and not permit

over-wetting of concrete on the job. It cannotbe said too often that the use of internalvibration will facilitate placing of concrete andhelp eliminate internal settlement. The use ofa surface curing membrane, placed as soonas possible after final finishing, will help elim-inate shrinkage cracks which are caused bydrying of the hardened concrete.

It is common practice in commercial work touse control joints to reduce shrinkage crackproblems. These are good procedures, butnot commonly used in single family construc-tion.

Again, it is important to recognize that allshrinkage cracks cannot be eliminated, giventhe present state of the art.

TF 700-R-03 • Page 23

Page 26: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

NOTATIONAc = Gross Area of Concrete Cross-Section

Ass = Area of Steel Reinforcing in Slab

Asbb = Area of Steel Reinforcing in Bottom of Beam

Astb = Area of Steel Reinforcing in Top of Beam

a = Depth of Stress Block ( ult. strength)

bb = Width of Beam Portion of Cross-Section

bs = Width of Slab Portion of Cross-Section

B = Total Width of all Beams of Cross-Section

Cw = Climatic Rating

db = Depth of Beam Portion of Cross-Section

ds = Depth of Slab Portion of Cross-Section

E = Modulus of Elasticity of Concrete

Ec = Creep Modulus of Elasticity of Concrete

f’c = 28 Day Compressive Strength of Concrete

fy = Yield Strength of Reinforcing

Ig = Gross Moment of Inertia of Cross-Section

Io = Moment of Inertia of Segments of Slab Cross-Section

kI = Length Modification Factor-Long Direction

ks = Length Modification Factor-Short Direction

L = Total Length of Slab in Prime Direction

L’ = Total Length of Slab (width) Perpendicular to L

Lc = Design Cantilever Length (Ick)

Ic = Cantilever Length as Soil Function

MI = Design Moment in Long Direction in kft

Ms = Design Moment in Short Direction in kft

NI = Number of Beams in Long Direction

Ns = Number of Beams in Short Direction

PI = Plasticity Index

S = Maximum Spacing of Beams

V = Design Shear Force (Total)

v = Design Shear Stress (Unit)

vc = Permissible Concrete Shear Stress

w = Weight per sq. ft. of House and Slab

q allow = Allowable Soil Bearing

qu = Unconfined Compressive Strength of Soil

i-c = Soil/Climatic Rating Factor∆ allow = Allowable Deflection of Slab, in.

TF 700-R-03 • Appendix A-1

Page 27: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

TF 700-R-03 • Appendix A-2

L’

L

Minimum number, width and depth of beams

Page 28: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

DESIGN EXAMPLES

For comparison to BRAB Report #33, assume for a design example the same single storyresidence located in San Antonio, Texas, which was used in BRAB Report #33.

Assume:

Effective P.1. = 37 3 x 5 x 41 = 615Climatic rating C = 17 2 x 5 x 41 = 410Slope = 0% 5 x15 = 75

EPF P.1. = 1100/300 = 36.67Unconfined compression qu = 2800 >1 TSF.Unit weight = 200 lbs./sq. ft.

First divide slab into two overlapping rectangles.

TF 700-R-03 • Appendix B-1

Page 29: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

For purposes of example, solve the 24’ - 0” x 42’ - 0 rectangle

From Fig. 15, 1-C = .23From Fig. 17, S = 16From Fig. 12, Ic = 7From Fig. 13, KI = .95 KIIc = .95 x 7.0 = 6.65

Ks = .80 KsIc = .80 x 7.0 = 5.60

Number of beams in long direction NI = + 1 = 2.5 = 3

Number of beams in short direction Ns = + 1 = 3.6 = 4

Assume beam widths = 9” each beam

BL = 3 x 9 = 27”

Bs = 4 x 9 = 36” Geometry of house causes 5 beams Bs = 45

Solve for long and short moments:

ML = = 106 kf

Ms = = 132 kf

Solve for beam depths:

dL = = 25.9” = 26”

ds = = 22.2” = “say 22”

TF 700-R-03 • Appendix B-2

200 (6.65) 2x 242000

200 (5.60) 2x 422000

664 x 106 x 6.6527

664 x 132 x 5.6045

3

3

24.016.0

42.016.0

Page 30: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

Solve for steel in bottom of beams : Long direction

Using fy = 60,000

Assume: 6 - #5 bars As = 1.86 sq.in.

a = = = 0.378

Assume: lever arm for positive reinforcing = d-3”

Mu = 1.86 x60 (26-3) / 12 = 213.9

M = 213.9 / 1.6 = 133.7 vs. 106

or using fy = 40,000

Assume:6 - #6 bars As = 2.64 sq.in.

a = = =0.358

Assume: lever arm for positive reinforcing = d-3”

Mu = 2.64 x 40 (26-3) / 12 = 202.4

M = 202.4 / 1.6- 126.5 vs. 106

Asfy for all three of these combinations = 3.85 k/lf

Assume lever arm for negative reinforcing = d - 4”

TF 700-R-03 • Appendix B-3

Asfy0.85f’cb

1.86 x 60,0000.85 x 2500 x 139

Asfy0.85f’cb

1.86 x 60,0000.85 x 2500 x 139

a

9” 9” 9”24” 24”32” 32”

26”

1/2”

2”

2”

9” 9” 9”24” 24”32” 32”

Page 31: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

- Mu from slab steel - steel in flanges only

112” / 12 x 3.85 x ( 26-4) / 12 = 65.9 kf/1.6 - 41.2-M - 41.2 kf = Moment to be reinforced for 106 - 41 = 65kf

For fy = 60,000

Assume: 6 - #4 bars As = 1.20

Mu = l.20 x 60 x (26’- 4”) / 12 = 132

M = 132 / 12 = 82.5 > 64

For fy = 40,000

Assume: 6 - #5 bars As = 1.86

Asfy = 1.86 x 40 = 74.4k

Mu = 74.4 x (26-4) / 12 = 126.4kf

M = 136.4 / 1.6 = 85.2 > 64

A cross section taken across the slab would then show:

TF 700-R-03 • Appendix B-4

6 x 6 W2.9 x W2.912 x 12 W2.5 x W2.5 (80kft) or6 x 6 W2.9 x W2.9 (65kft)

2# 4 BARS or2# 5 BARSTOP EACH BEAM

2# 5 BARS or2# 6 BARSBOTTOM EACHBEAM

# stirrups orWW stirrups

8” 8” 8”

4”

26”

Page 32: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

Solve for steel in bottom of beams : Short direction

For fy = 60,000

Assume: 10 - #4 bars As = 2.00

a = = 0.235”

Assume: lever arm for negative moment = d-3

Mu = 2.00 x 60 (22-3) / 12 = 190.0

M = 190 / 1.6 119 vs. 132

Try increasing two exterior and center beams to 26”

Mu (ext .beams) = 1.80 x 60 (26-3) / 12 = 138kft

Mu (int. beams) = 0.80 x 60 (22-3) / 12 = 76kft

Total Mu = 138 + 76 = 214kft

Total M = 214 / 1.6 = 134 vs. 132

For fy = 40,000

Assume: 10 - #5 As = 3.l0 sq.in.

a= = 0.243”

TF 700-R-03 • Appendix B-5

2.00 x 600.85 x 2.5 x 240

3.10 x 400.85 x 2.5 x 240

Page 33: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

Assume: lever arm for negative moment = d-3

Mu = 3.10 x 40(22-3) / 12 = 196kftM = 196/1.6 = l22 vs. 132kft

Try increasing two exterior beams to 26”

Mu (ext. beams) = 1.24 x 40 ( 26’ 3’)/ 12 = 95kft

Mu (mt. beams) = l.86 x 40(22’ 3”)/ 12 118

Total Mu = 95 + 118 = 213kft

Total M =213/1.6 = 133 vs. 132

Solve for steel in top of beams: Short direction slab steel same as long direction

-M slab steel - steel in flanges only

M sIab steel 240/ 12 x 3.85 (22’ 4”)/ 12 = 111.6/ 1.6-73.5kft

-M -73.5 = 132 -73.5 = 58.5kft moment to be reinforced for.

(This is slightly conservative since beams are deepened)

For fy = 60,000

Assume: top steel to be 10 - #3 bars or W or D9 @ 10” ea. way-Mu = 0.66 x 60 (26-4) / 12 = 72.6

0.44x 60 (22-4) / 12 = 39.6

Total -Mu = 72.6 + 39.6 = 112.2

-Mu = 112.2 / 1.6 = 70.1 > 58.5

TF 700-R-03 • Appendix B-6

Page 34: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

For fy = 40,000

Assume: top steel to be #3 bars or W or D9 @ 10” ea. way

-Mu = 0.80 x 40 (22-4) / 12 = 58.7

1.20 x 40 (22-4) / 12 = 72.0

Total -Mu = 130

-M = 130.7 / 1.6 = 81.7 > 58.5kft

SUMMARY:

Long Direction Beams

3-9” x 26” beams, reinforced with 2 #4 or 2 #5 bars top, 2 # 5 or

2 #6 bars bottom each beam

Short Direction Beams

2-9” x 26” exterior and center interior beams, reinforced with

2 #3 or 2 #4 bars top, 2 #4 or 2 #5 bars bottom.

2-9” x 22” interior beams, reinforced with 2 #3 or 2 #4 bars top,

2 #4 or 2 #5 bars bottom.

Slab reinforcing to be:

fy = 80,000 - 12 x 12 - W4.5 x W4.5

fy = 65,000 - 6 x 6 - W2.9 x W2.9

TF 700-R-03 • Appendix B-7

Page 35: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

REFERENCES

1. Tentative Recommendations forPrestressed Slab-On-Ground, Ad HocCommittee of the P.C.l. Post-TensioningCommittee Committee Chicago.

2. Interim Criteria for Slab-On-GroundConcrete Foundations for ResidentialConstruction", Construction ResearchCenter, University of Texas at Arlington.Dr. E.L. Buckley, P.E., PhD

3. Criteria for Selection and Design ofResidential Slab-On-Ground, Report#33to the Federal Housing Administration,Publication 1571, National Academy ofSciences, Washington, D.C., 1968.

4. Home Builders Protest New Slab DesignCriteria, Engineering News Record, Vol.176, No.1 Jan.6, 1966,

5. Lytton, R.L., "Stiffened Mat DesignConsidering Viscoelasticity, Geometryand Site Conditions", Proceedings, 3rdInternational Conference on ExpansiveClays, Vol.11, Haifa, Israel.

6. Snowden, Walter L., Personal notes andinspection reports, memos and corre-spondence with others, unpublished,1967 to present.

7. Dawson, Raymond F., "Movement ofSmall Houses on an Expansive ClaySoil", Proceedings. 3rd. InternationalConference on Soil Mechanics andFoundation Engineering, Zurich, Vol.1,1953

8. Snowden, Walter L. and Meyer, Kirby T.,"Comparison of Performance of Slab-On-Ground Foundations on Expansive andon Non-Expansive Soils", paper present-ed to Texas Section American Society ofCivil Engineers, Soil Mechanics Division,San Antonio, Texas. 1967.

9. Anderson, R.B. and Thompson, H.Platt,"Analysis of a Prestressed Post-Tensioned Foundation Using the KellySystem", H.Platt Thompson EngineeringCompany, Inc., Houston, Texas January31, 1968.

10.Meyer, Kirby T., and Lytton, R.L.,Foundation Design in Swelling Clays",Texas Section American Society of CivilEngineers, Soil Mechanics Division,Austin, Texas, 1966.

11.Matlock, Hudson and Haliburton, T.A.,"BMCOL 29, a program for FiniteElement Solution of Beam Columns onNon-Linear Supports", 1335 BonhamTerrace, Austin, Texas June 15, 1964.

TF 700-R-03 • C-1

Page 36: WIRE REINFORCEMENT INSTITUTE DESIGN OF … the design requirements set forth in BRAB Report #33.Many theoretical analyses show that no lessening of the requirements is possible, while

942 Main Street • Suite 300 • Hartford, CT 06103 (800) 552-4WRI [4974]

TECH FACTS

www.wirereinforcementinstitute.org

Excellence Set in ConcreteWIRE REINFORCEMENT INSTITUTE®

12.Matlock, Hudson, "GRDBM 23, RandomDirection Beam System ComputerProgram", unpublished class notes, TheUniversity of Texas, Austin, Texas, 1965.

13.Lytton, R.L., "Analysis for Design ofFoundations on Expansive Clays",Geomechanics Journal, Institute ofBusiness Australia, 1970.

14.Lytton, R.L. and Meyer, Kirby T.,"Stiffened Mats on Expansive Clays",Journal, Soil Mechanics and FoundationDivision, ASCE Vo. 97, No. SM7, July1971.

15."Land Development with ControlledEarthwork", Data Sheet 79-G, HUDHandbook 4140.3 Land Planning DataSheet Handbook, U.S. Department ofHousing and Urban Development,Washington, D.C. June 19, 1973.

16.McDowell, Chester, “Interrelationship ofLoad, Volume Change, and LayerThickness of Soils to the Behavior ofEngineering Structures”, Vol. 35,Highway Research Board Proceedings.

17.McDowell, Chester, "RemedialProcedures used in the Reduction ofDetrimental Effects of Swelling Soils",TPI-65E, Texas Highway Department.

18.” Structural Failures: Modes, Causes,Responsibilities", A Compilation ofPapers Presented at the "ASCE NationalMeeting on Structural Engineering",Cleveland, Ohio, April 1972.

19.Thornwaite, C.W., 1948, "An ApproachToward a Rational Classification ofClimate", Geographical Review, V.38

20.Olson, Ray E., "A Study of FoundationFailures & Distress", Report for NationalBureau of Standards, Gaithersberg,Maryland, July, 1973.

21.ACI Committee 318,"Building CodeRequirements for Reinforced Concrete(ACI 318), American Concrete Institute,Farmington Hills, MI.

TF 700-R-03 • C-2