Woodland District 50: Operations and Facilities Report
Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time Cleaning Services Health Life Safety (HLS) Update Other updates Questions
1
![Page 2: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/2.jpg)
Energy Update – Electric This year we are collecting hourly usage data
2
![Page 3: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/3.jpg)
Energy Update – Electric SavingsSeven Month Comparison
3
![Page 4: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/4.jpg)
Energy Update – Gas SavingsSeven Month Comparison
4
![Page 5: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/5.jpg)
5
Energy Update – Gas SavingsSeven Month Comparison
![Page 6: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/6.jpg)
Energy Update – Primary School-LEED (LEADERSHIP IN ENERGY AND ENVIRONMENTAL DESIGN)
Primary currently is at an Energy Star score of 69, which qualifies for LEED certification.
We are pursuing an Energy Star score of 80 to begin the evaluation process for LEED certification late summer/early fall, 2012.
In order to pursue LEED certification we will: Continue to send Electric/Gas/Water usage data to Transwestern Sustainability and Siemens for analysis. Continually adjust the heating, ventilation and air conditioning (HVAC) system-through the energy management system and manually, to improve conditions and efficiency. Keep working with principals and staff on energy conservation awareness and reduce “Vampire Load”. 6
![Page 7: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/7.jpg)
Primary School 2012 Summer Work
7
![Page 8: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/8.jpg)
Elementary East School 2012 Summer Work
8
![Page 9: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/9.jpg)
Elementary West School Summer Work
9
![Page 10: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/10.jpg)
Intermediate School Summer Work
10
![Page 11: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/11.jpg)
Middle School Summer Work
11
![Page 12: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/12.jpg)
Five-Year Facility Plan Why
Long range planning Budgeting purposes Ties in Capital requests presented annually to the Board Helpful for grant applications
Includes Supplies Purchased Services Capital expenditures Health Life Safety inspections Equipment/furnishing replacement schedule
Does not include Salaries, Benefits and Utilities 12
![Page 13: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/13.jpg)
Five-Year Facility Plan…
13
![Page 14: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/14.jpg)
14
Five-Year Facility Plan…
![Page 15: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/15.jpg)
Five-Year Facility Plan…
15
![Page 16: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/16.jpg)
Current Five-year agreement started July 2007, $162,000/yr, ends this June, cost is $198,000/yr.
Agreement maintains: Building automation system Mechanical systems Fire device systems Security cameras
Proposed renewal cost: $237,445, with a 3%/year escalation rate. Includes 60 cameras added in 2009, not in original agreement
Administrative/Siemens negotiations Five year agreement Include in the 176 security camera maintenance, 10 cameras/year to
replace or upgrade, + $25,000
16
Siemens Maintenance Agreement…
![Page 17: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/17.jpg)
Reductions Remove pump maintenance from agreement - $12,600.
District Maintenance Techs to accomplish pump maintenance. Remove fire device inspection/testing, - $29,000.
Fire device specialist companies have provided proposals to inspect/test for approximately $20,000/year.
Results Initial proposal, $237,445 subtract $12,600 for pump maintenance,
subtract $29,000 for fire device inspection/testing, add $25,000 security camera maintenance = $220,845.
Contract with fire device specialist company to inspect/test devices approximately $20,000
Siemens proposal - $188,000/year for Five years and NO escalation rate.
Bring to the Board for action, April 24, 2012 – Effective 7/1/12. 17
Siemens Maintenance Agreement
![Page 18: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/18.jpg)
Original contract commenced July 2006 - $905,000/yr. Reduced cleaning frequency July 2010 - $705,000/yr. Clean classrooms, offices, LRCs one time/week. Common areas, restrooms, health office, staff lounge cleaned
daily. Quality Control
[email protected] - tool used to address daily cleaning issues.
80 discrepancies since school started, over 15,000 rooms cleaned total.
O&F leadership team conducted a site inspection of South Campus during winter break, in conjunction with semi-annual asbestos inspection. Teachers/staff are doing a very good job in keeping the rooms as clean as possible.
Custodians are available and provide assistance with cleaning issues during the day
Conduct Cleaning Contract Survey… 18
Citywide Cleaning Services…
![Page 19: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/19.jpg)
Bring to the Board for action, April 24, 2012. Current pricing - $705,280.68 for three (3) to five (5) years no
price increase If the Board wishes to add an additional day of cleaning at
the five schools, the cost increase would be $100,000
19
Citywide Cleaning Services
![Page 22: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/22.jpg)
HEALTH LIFE SAFETY (HLS) UPDATE
OWP/P Architects: June 2012 - conduct first decennial HLS inspection at Intermediate. Nov-Dec 2012- receive authorization to proceed with repairs. Jan-Feb 2013 – bid out Intermediate HLS projects. Feb-Mar 2013 – Board award successful bidders. June 2013 – commence HLS projects.
Summer 2015 – conduct decennial HLS inspections for South Campus and Middle School.
22
![Page 23: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/23.jpg)
Other Updates…
Public Service program has realized over 3,500 hours of work for the District from July 2011 to Feb 2012.
Snow removal Deep cleaning Specialized work – painting, bodywork, etc. Outdoor work-grass cutting and landscaping
23
![Page 24: Woodland District 50: Operations and Facilities Report Energy Update 2012 Summer Work Five-Year Facility Plan Service Maintenance Agreement Night Time](https://reader036.vdocument.in/reader036/viewer/2022062314/56649e045503460f94af0e32/html5/thumbnails/24.jpg)
O&F and Technology departments are conducting an internal trial operations of a web based facility scheduling program. Training will be conducted for outside community users and bringing on-line for FY13.
Building Information Book (BIB) – O&F’s standard operating procedures manual, is a work in-progress.
24
Other Updates