work schedule

1
Project : 2-Storey Office Building Contract Duration : 90 calendar days Location : Tagbilaran City, Bohol 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 I General Requirements 753,480.00 9.44 II Health & Safety Requirements 235,872.00 2.96 III Furnish & Installed Billboard 26,208.00 0.33 IV Site Works 147,201.16 1.85 V Structural Works 2,823,461.73 35.39 VI Architectural Works 3,615,959.05 45.32 VII Waterline & Sanitary Works 205,107.89 2.57 VIII Electrical Works 170,780.59 2.14 Total Contract 7,978,070.43 100.00 Planned Monthly Accomplishment (%) Planned Cumulative Monthly Accomplishment (%) Planned Monthly Accomplishment (Amount) Planned Cumulative Monthly Accomplishment (Amount) Actual Monthly Accomplishment (%) Actual Cumulative Monthly Accomplishment (%) Slippage (%) WORK SCHEDULE NUMBER OF DAYS Item No. Item of Work Contract Amount Weighted Percentage 8.17% 21.97% 27.76% 21.60% 13.41% 7.09% 30.14% 57.90% 79.50% 92.91% 100.00% 651,808.35 1,752,782.07 2,214,712.35 1,723,263.21 1,069,859.24 565,645.19 2,404,590.43 4,619,302.78 6,342,565.99 7,412,425.23 7,978,070.43

Upload: rhejo-orioque

Post on 03-Dec-2015

1 views

Category:

Documents


0 download

DESCRIPTION

seminarnotes

TRANSCRIPT

Page 1: Work Schedule

Project : 2-Storey Office Building Contract Duration : 90 calendar daysLocation : Tagbilaran City, Bohol

5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90

I General Requirements 753,480.00 9.44 II Health & Safety Requirements 235,872.00 2.96 III Furnish & Installed Billboard 26,208.00 0.33 IV Site Works 147,201.16 1.85 V Structural Works 2,823,461.73 35.39 VI Architectural Works 3,615,959.05 45.32 VII Waterline & Sanitary Works 205,107.89 2.57 VIII Electrical Works 170,780.59 2.14

Total Contract 7,978,070.43 100.00

Planned Monthly Accomplishment (%)

Planned Cumulative Monthly Accomplishment (%)

Planned Monthly Accomplishment (Amount)

Planned Cumulative Monthly Accomplishment (Amount)Actual Monthly Accomplishment (%)Actual Cumulative Monthly Accomplishment (%)Slippage (%)

WORK SCHEDULE

NUMBER OF DAYSItem

No.Item of Work

Contract

Amount

Weighted

Percentage

8.17% 21.97% 27.76% 21.60% 13.41% 7.09%

30.14% 57.90% 79.50% 92.91% 100.00%

651,808.35 1,752,782.07 2,214,712.35 1,723,263.21 1,069,859.24 565,645.19

2,404,590.43 4,619,302.78 6,342,565.99 7,412,425.23 7,978,070.43