WORK SCHEDULE FOR INSTALLATION OF WORKING PILES FOR FOUNDATION PROPOSED MIXED USE DEVELOPMENT ON PLOT No.300, (VICTORIA VIEW) NEW BAGAMOYO ROAD, KINONDONI DAR ES SALAAM Activity Duration Year 2015 Weeks 28-Sep 5-Oct-15 12-Oct-15 19-Oct-15 26-Oct-15 2-Nov-15 Days M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M Task Series A: Overall Project Management Task A1: Preparation of reinforcement cages Task A2:Installation of vertical borehole for bored cast insitu pile Task A3: Removal of all excavated materials materials from boreholes Total Days: 38 Key: Full-Time

Upload: nuru-j-haule

Post on 10-Feb-2016

215 views

Category:

Documents


1 download

DESCRIPTION

2

TRANSCRIPT

Page 1: Work Schedule Rev

WORK SCHEDULE FOR INSTALLATION OF WORKING PILES FOR FOUNDATION

PROPOSED MIXED USE DEVELOPMENT ON PLOT No.300, (VICTORIA VIEW) NEW BAGAMOYO ROAD, KINONDONI DAR ES SALAAM

Activity

Duration

Year 2015

Weeks 28-Sep 5-Oct-15 12-Oct-15 19-Oct-15 26-Oct-15 2-Nov-15 9-Nov-15

Days M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S

Task Series A: Overall Project Management

Task A1: Preparation of reinforcement cages

Task A2:Installation of vertical borehole for bored cast insitu piles foundation

Task A3: Removal of all excavated materials materials from boreholes

Total Days: 38Key: Full-Time