work
DESCRIPTION
Brian Doherty Spring 2013 PortfolioTRANSCRIPT
-
WORKBRIAN PATRICK DOHERTY
M.Arch University of Texas at Austin
-
BRIAN PATRICK DOHERTY
5715 Joe Sayers AvenueAustin, Texas 78756 [email protected] 860.304.2448
-
ACADEMIC WORK01. East Havana Kindergarten 6-1102. The Ganzfoort School of Classical Piano 12-1903. Town Lake Viewing Platform 20-2304. The Airport of the Future: Mumbai 24-2905. Neighbor Oriented Development 30-3506. Texas Impact Design 36-4307. West Campus Housing 44-49
EXPLORATIONS01. Bodies of Light 52-5302. Facade Analysis 54-5503. Architectural Drawing 56-57
PROFESSIONAL WORK01. Meadow Lane Residence 60-6502. Model Making 66-6703. The Maufrais Urban Farm Projects 68-71
RESUME 74-75
WORK
-
ACADEMICWORK
-
ACADEMICWORK
-
6
BELOW, LEFT Looking back towards Central Havana from the North end of the site. The steep slope collapses the visual experience to one of foreground and background, reducing the immediacy of East Havana to one of reference.
BELOW, RIGHT An existing site wall marks this visual boundary as well as a dramatic change in the character of landscape.
01. EAST HAVANA KINDERGARTENSemester Spring 2012 Critic Cisco Gomes Location Havana, CubaIn collaboration with Karl Gleason
A kindergarten for East Havana requires consideration not only for the importance of early childhood learning but also the development of the entire barrio, an historically neglected and isolated neighborhood near the heart of Cubas capitol city. The proposal seeks to restore the importance that East Havana once had for both the vitality and identity of the centuries-old city, while at the same time becoming a catalyst for future growth near the school.
At the top of the site, topography falls away steeply and abruptly to the sea below. From this vantage point one experiences an unusual view; middle ground falls away, collapsing foreground and distant views and obscuring important land and sea markers that connect, both physically and psychologically, Old Havana with East Havana.
The East Havana Kindergarten reclaims this middle ground. At its low end, the school engages an historical edge of the citys Entrance Canal, overlooking a small inlet created during the construction of the underground tunnel that connects Central and East Havana. At the schools high end, it affords a physical and symbolic connection with a prospective edge - an optimistic face presented towards the growing and developing neighborhood.
-
East Havana Kindergarten 7
ABOVE Main Level Plan
BELOW, LEFT Site Plan showing the relationship of the school to Central Havana across the Canal de Entrada
BELOW Final Model
-
8
The building organizes program sectionally to address site conditions and negotiate the conceptual grain of the project. Shared program creates a threshold condition between the public and the school. An educational research foundation is accessed from the top of the site, while the school is accessed within the middle ground of the project. The building takes advantage of the slope, providing a service entry further down the hill and beneath the main entry.
Individual classrooms are located across a play yard from this administrative wing of the building. Each classroom occupies its own elevation and connects visually to the specific and lush landscape beyond. While individually unique, each is visually connected to adjacent classrooms through clerestory glazing and a spine of beams and skylights.
Circulation between shared programs and individual classrooms creates a pattern of movement always bracketed by timeunderstanding of a past, promise of a future. A peeling away of layers of construction along the traversed paths of the School heightens awareness and celebrates the rich contexts of East Havana that gave the city life. More importantly, it reveals an intrinsic value held by East Havana through learning and early childhood development, a beginning for generations of growth and pride in one of Havanas most storied neighborhoods.
FOUNDATION
ENTRY
SCHOOL
ENTRY
SERVICE ENTRY
CONCEPTUAL ORGANIZATION OF SITE
PROGRAM ORGANIZATION
SECTIONAL ENTRY, SPATIAL LAYERING, AND CIRCULATION
CONCEPTUAL GRAIN
ARCH
ITECTU
RAL G
RAIN
FoundationAdmin/SupportCommunal SpacesIndividual Spaces
-
East Havana Kindergarten 9
ABOVE Series of Longitudinal sections
BELOW View across courtyard towards classrooms
-
10
Scale:Date:
EAST HAVANA KINDERGARTENHavana, Cuba
Karl Gleason. Brian Doherty. A601Perspectives05.10.12
A5018
A5017
A5019
A5016
----
EXPANDED ALUMINUM MESH SCREEN
STAINLESS STEEL CLIPS
1/4" INTEGRALLY COLORED CEMENT COMPOSITE PANEL
HAT CHANNELS
PLYWOOD SHEATHING
6" STEEL STUDS
BATT INSULATION
5/8" GYP. BOARD, PAINTED
INVERTED ROOF PANELS
ROOF MEMBRANE
1" RIGID BOARD INSULATION
1 1/2" STEEL DECK
SUSPENDED 5/8" GYP. BOARD CEILING
3/4" TONGUE AND GROOVE HARDWOOD FLOORING
3/4" TONGUE AND GROOVE PLYWOOD SUBFLOOR
1X3 TREATED WD. SLEEPERS @ 16" O.C.
STEEL DECK WITH CONCRETE TOPPING
BATT INSULATION
3 1/4" STEEL STUD
1/2" PLYWOOD SHEATHING
OAK SOFFIT ON FURRING STRIPS
1/4" INTEGRALLY COLORED CEMENT COMPOSITE PANEL
HAT CHANNELS
1/2" PLYWOOD SHEATHING
3 1/4" STEEL STUDS @ 16" O.C.
BATT INSULATION
5/8" GYP BOARD, PAINTED
AIR BARRIER
AIR BARRIER
2 - Upper Level A14' - 6"
Main Level-0' - 2"
A50112
A50111
A50113
A50110
CAST IN PLACE CONCRETE STRIP FOOTING
PERFORATED DRAIN PIPE
CRUSHED GRAVEL
FILTER FABRIC
DRAINAGE MAT
2" RIGID INSULATION BOARD
WATERPROOF MEMBRANE
WATERPROOF MEMBRANE
8" STRUCTURAL CMU
2" RIGID BOARD INSULATION
2" CAVITY
4" CMU VENEER BLOCK
12" CMU BOND BEAM
ALUMINUM WINDOW
1/2" PLYWOOD SHEATHING
6" STEEL STUDS @ 16" O.C.
HAT CHANNELS
5/8" INTEGRALLY COLORED CEMENT COMPOSITE PANEL
C 8 X 13.75
STAINLESS STEEL CLIP
EXPANDED ALUMINUM MESH SCREEN
BATT INSULATION
5/8" GYP. BOARD, PAINTED
STEEL PLATE CLIP
HSS 8 X 4 X 3/8" BEAM
STEEL ROOF DECK
INVERTED ROOF PANELS
3 5/8" STEEL STUD
5/8" INTEGRALLY COLORED CEMENT COMPOSITE PANEL
METAL COPING
SUSPENDED 5/8" GYP. BOARD CEILING
AIR BARRIER
-
East Havana Kindergarten 11
A5012
A5011
Scale:Date:
EAST HAVANA KINDERGARTENHavana, Cuba
Karl Gleason. Brian Doherty. 3/4" = 1'-0" A304Wall Section05.10.12
1/4" STEEL PLATE MULLION REINFORCING
INVERTED WINDOW MULLION
LOW IRON INSULATED GLAZING
3/8" STEEL MULLION REINFORCING
METAL GUTTER
STEEL DECKING
CAST-IN-PLACE CONCRETE BEAM
PAINTED GYPSUM BOARD
PULL-DOWN BLIND
CONCRETE PAVER
1/4" STEEL PLATE MULLION REINFORCING
CAST-IN-PLACE CONCRETE FOOTING
INVERTED WINDOW MULLION
LOW IRON INSULATED GLAZING
1 X 4 TONGUE AND GROOVE WOOD FLOORING
INVERTED ROOF PANEL
2" CRUSHED GRAVEL
2" SAND
A5015
A5014
A5013
INVERTED ROOF PANEL
SINGLE PLY ROOF MEMBRANE
1" RIGID BOARD INSULATION
2" STEEL DECK
SUSPENDED 5/8" GYP. BOARD CEILING
CAST-IN-PLACE CONCRETE BEAM
ROLLER SHADE
CONCRETE BEAM BEYOND
CLEAR CHANNEL GLASS
CONCRETE PAVER
2" SAND
4" AGGREGATE
1 X 4 TONGUE AND GROOVE WOOD FLOORING
PLYWOOD SUBFLOOR
1X3 TREATED SLEEPERS
4" CONCRETE SLAB ON GRADE
4" GRAVEL
SUSPENDED OAK SOFFIT ON FURRING STRIPS
SLIDING DOOR TRACK
HSS 8 X 4 X 3/8
CLEAR CHANNEL GLASS SLIDING DOOR FRAME
TRENCH DRAIN
W 4X13 DOOR FRAME
OPPOSITE The building is approached between two ridges in the landscape. The building extends a sense of threshold through its expressed layering.
The classrooms can be seen beyond, pulling one through the project and the site.
ABOVE Classrooms open to intimately scaled outdoor areas, extending the space of the school
into the natural landscape beyond.
-
12
The Ganzfoort School of Classical Piano was the culmination of a semester studying the works and ideas of Louis Kahn. The studio began with Kahns idea of the plan as a society of rooms - a polar contrast to the modern conception of the free plan and flowing space. Ideas of Order and Institution were paramount.
The design creates an alignment of structure and space, using a long spanning folded plate to set the spatial and structural order of the building. A rhythm of servant and served spaces organizes the plan, providing mechanical services, programmatic support, and reflected light to the central spaces.
The building is approached parallel to its long face beneath the shade of a row of trees. A small pathway leads breaks through the rhythm of the facade into an entry court, created by truncating one of the structural bays. This places the remainder of this truncated bay - the grand living room - as the primary element of the otherwise non-hierarchical arrangement.
The residence is contained within the two bays to the north, and the school is contained in the bays to the south. Accommodating the change in grade creates a large open room for the school - an area to wait and meet between lessons, to hold receptions, or to perform concerts.
02. THE GANZFOORT SCHOOL OF CLASSICAL PIANOSemester Spring 2011 Critic Michael Benedikt Location Austin, Texas
-
Ganzfoort School of Piano 13
ABOVE Site PlanBELOW Site photographs
-
ABOVE The building is approached between the rhythm of the facade and a row of trees.
BELOW The entry courtyard
-
BELOW, MIDDLE The dining room is lit from above and looks out to the entry court
BELOW The master living room
-
16
0 4 8 32 ft
Overlapping Zones of Program Modular Organization Structural Bay
-
Ganzfoort School of Piano 17
FOLDED PLATESTRUCTURAL BAY
Concrete Shear Wall acts as a diaphragm for the folded plate, allowing the system to resist transverse splaying and lateral loading
Concrete folded plate spans 64 feet between end shear walls. Top edge is turned up and outer edges are turned down and thickened to move more material away from the neutral axis, as well as to provide more edge support.
FOLDED PLATE ROOFFolded plate roof structure spans the width of the building between shear wall diaphragms, enclosing served spaces beneath. Each bay is structurally independent.
PARTITION WALLS
SERVICE SPACESStructurally independent from the room structure,each core contains environmental services as well as complimentary, service program spaces.
-
18
-
Ganzfoort School of Piano 19
-
20
Located at a curve along the Town Lake running trail, the viewing platform intervenes to stitch together three disjointed areas while providing places for sitting along the water and viewing the lake from above. Situated at a moment where the trail bends up and away from the waters edge to a higher wooded bank, the platform creates a porous threshold, marking a moment of transition along the trail.
Where the trail splits and moves up the hill, a pathway of varied seating continues along the waterfront, piercing the wall of the platform to create a terraced seating area that engages the lake. A path from the baseball fields above the trail merges with the viewing platform above, visually connecting the users of the fields to the adjacent but visually distant trail and lake while providing people watching and sweeping views of downtown.
The platform celebrates the variety of this overlooked moment along the trail, engaging what is peculiar and special about each elevation while weaving them together into one cohesisive form.
LEFT A gentle curve in the town lake trail offers a moment of architectural opportunity
03. TOWN LAKE VIEWING PLATFORMSpring 2010 Critic Joyce Rosner Location Austin, Texas
-
Town Lake Viewing Platform 21
ABOVE Site Plan
BELOW A progression of models investigating threshold conditions and sectional relationships
between each elevation
-
22
VIEWPOINTThe viewing platform has two main viewing areas - one held up above the water at the edge of the treeline, affording views of downtown. The other is at the waters edge, with a more focused, immediate view of the lake.
UPPER PATHWAYAn elevated pathway connects the baseball field, currently separated from the lake by thick trees, to the waterfront. The pathway turns at the trail, to create an implied axis and a place for watching the motion below.
LOWER PATHWAYA lower pathway splits with the hike and bike trail, retaining earth to create spots for sitting along the waters edge. The pathway moves through the threshold of the structural frame to arrive at the lower viewing area.
Circulation Pathways Implied Axes View Points
-
Town Lake Viewing Platform 23
-
24
The worlds population is rapidly urbanizing, with a projected 60% of the worlds citizens living in cities by 2025. The scale of these urban centers city is increasingly global, needing connective transit systems on a worldwide scale.
This creates a spatial conundrum an increased demand for air travel, yet the growing demand upon urban land pushes the airport further and further afield from the population it serves. Airports become metropolises of their own, cast into suburban areas or beyond as unwelcome neighbors.
The resulting scenario is one of dead-end development, where a significant infrastructural investment is made beyond the city itself, rather than within its boundaries. Passengers are made to travel significant lengths to begin their journey, arriving to a tired procession of lines, frustrations, and anxious waiting. Arriving passengers are given the implication of arrival, yet face the reality of a long, slow drive to the final destination shown on their ticket.
This project uses Mumbai as a setting to explore the possibilities in this problem. Mumbai is set to be the second largest in the world by 2025. It sits along the western coast of India on a small peninsula of reclaimed land, and due to the breakneck pace of population growth it is rapidly running out of land. The lands at its edges are national forests and marshlands, which are desparately needed for dealing with the intense rains of the monsoon season.
In response to these physical limitations a problem shared by many cities around the globe planners have attempted to channel growth to the city of Navi Mumbai (New Mumbai) across the bay to the east. However, the bottleneck of only one east west connection between the two cities has dramatically limited the growth of Navi Mumbai, with population numbers significantly below projections.
The proposed airport is located between these two urban centers, and is accessed only through public transit. This limitation enables a broad rethinking of the spatial sequencing of the airport that overlaps the multiple steps of waiting involved in the airport experience.
04. THE AIRPORT OF THE FUTUREFall 2011 Critic Vincent Snyder Location Mumbai, IndiaIn Collaboration with Greg Montgomery
-
Airport of the Future 25
Metro
Suburban Rail SystemMonorail
Mountains
Marshland
Urbanization
Open SpaceSeaports and Airports
0 3 6 15 30 45 km
REGIONAL ANALYSIS
TAXIWAYRUNWAY TRAIN
TERMINALAPRON AND TAXIWAYMAINTENENCE APRON AND TAXIWAY MAINTENENCE
-
26
Passengers are checked through security on the train itself with each train car becoming a secured space between its departure from land and its arrival at the airport. Bags are checked on the train, scanned, and pre-sorted. The traditional procession of a long trip to the airport, check-in, baggage check, and security is overlapped into the integral spatial move of the building and the one step that all passengers must take a train ride to the airport.
Once passengers arrive, they progress up towards light, from a tall skylight space up to the main concourse level, lit from the side. A datum of the ground plane is constantly present, emphasized by the presence of airplanes at the windows above, not below. Passengers are served by quick services in kiosks that peel up from the ground plane, or by slower amenities like restaurants, located in carved out spaces that act as eddies within the flow of the concourse. Gates are located above grade, and the procession across that datum is up into the light. Passengers ascend escalators within a skylight service core, and then onto a system of catwalks, where they are connected to the endless horizontality of the ocean and the horizon beyond.
Proposed Airport Experience
Current Airport ExperienceSPATIAL SEQUENCING
-
Airport of the Future 27
-
28
-
Airport of the Future 29
ABOVE Shops in the main concourse emerge up from the ground plane. Gates are accessed
through skylit cores. Planes hover above to the left and right.
BELOW Gates hover above the datum of the ground plane, connecting travelers to the horizon
line of the ocean surrounding the airport.
-
30
This two week urban design competition aimed at reconnecting three of Seattles most diverse neighborhoods through principles of transit oriented development and sustainable water management. Light rail, bus, and bike transit networks are used to link together adjacent neighborhoods with new open space and sustainable community anchors. The design also creates an urban pedestrian front along the main thoroughfare of the site, connecting by pedestrian pathways to a town green, centered around a rainwater filtration pond.
This connection between urban form, transit systems, and natural water cycles offers a vibrant and livable model for urban development.
My contribution to this team project included programming, master planning, site design, and producing final diagrams and renderings. This project was selected from 8 projects by a University sponsored jury to receive the Cogburn Family Foundation Architecture and Urbanism Prize.
05. NEIGHBOR ORIENTED DEVELOPMENTSpring 2011 Critic Simon Atkinson Location Seattle, WashingtonIn Collaboration with Greg Montgomery, Jenna Dezinski, Sarah Sha, and Ryan NorthropAwarded First Prize in UTSoA Urban Design Competition
BELOW A public market, bus depot, and bike rental greet pedestrians as they arrive by light rail.
-
Mount Baker Redevelopment 31
1 23
4
5 6
78
91011
12
13
1415
16
1718
1920
1. Parking and Car Share Depot2. Art Gallery3. Light Rail Station4. Artist Housing5. Bus Depot6. Bike Depot and Plaza7. Hotel8. City Market and Plaza9. Seattle Community College Green Jobs Center
10. Grocery Store11. Parking Depot12. Lowes13. Retail and Residential 14. Residential15. Community Garden16. Water Retention and Filtration Pond17. Car and Bike Parking18. Community Center19. Retail and Residential20. Residential
-
32
ten foot intervals
Q.F.C
.
Lowes
Retail
Apartm
ent
Apartm
ent
Mount B
aker C
omm
unity
Green R
oof
Bicycle P
ath
Playg
round
Green W
all
Storm
Water P
ool
P-P
atch C
omm
unity G
arden
Beacon H
illC
omm
unity Green B
elt
Education
Center
Wind P
ower
System
Parking
Loading
Coffee S
hop
Outdoor
Restaurant
Multi-Family Housing
Transit Hub as Anchor
High Density Mixed-Use StreetCommunity AnchorsWater Collection as Hinge Point of SiteGreen Corridor ConnectionMajor Pedestrian Urban StreetsSlowed Traffic ZoneCommunity Connection
Transit Hub as AnchorMulti-Family HousingHigh Density Mixed-UseCommunity Anchors
Multi-Family Housing
Transit Hub as Anchor
High Density Mixed-Use StreetCommunity AnchorsWater Collection as Hinge Point of SiteGreen Corridor ConnectionMajor Pedestrian Urban StreetsSlowed Traffic ZoneCommunity Connection
Multi-Family Housing
Transit Hub as Anchor
High Density Mixed-Use StreetCommunity AnchorsWater Collection as Hinge Point of SiteGreen Corridor ConnectionMajor Pedestrian Urban StreetsSlowed Traffic ZoneCommunity Connection
Water Collection as HingeGreen Corridor ConnectionMajor Pedestrian StreetCommunity Connection
Multi-Family Housing
Transit Hub as Anchor
High Density Mixed-Use StreetCommunity AnchorsWater Collection as Hinge Point of SiteGreen Corridor ConnectionMajor Pedestrian Urban StreetsSlowed Traffic ZoneCommunity Connection
Multi-Family Housing
Transit Hub as Anchor
High Density Mixed-Use StreetCommunity AnchorsWater Collection as Hinge Point of SiteGreen Corridor ConnectionMajor Pedestrian Urban StreetsSlowed Traffic ZoneCommunity Connection
Land Use Diagram
-
Mount Baker Redevelopment 33
ten foot intervals
Q.F.C
.
Lowes
Retail
Apartm
ent
Apartm
ent
Mount B
aker C
omm
unity
Green R
oof
Bicycle P
ath
Playg
round
Green W
all
Storm
Water P
ool
P-P
atch C
omm
unity G
arden
Beacon H
illC
omm
unity Green B
elt
Education
Center
Wind P
ower
System
Parking
Loading
Coffee S
hop
Outdoor
Restaurant
Open Space
Existing Open Space
Green Roof
Green Paths
Open Space
Existing Open Space
Green Roof
Green Paths
Existing Open Space
Open Space
Green Roof
Green Pathways
-
34 36
11
2
34
2
3
4
5
Hi, my name is Amy. I am in town for a conference. I love the proximity here to both the airport and downtown Seattle. I enjoy staying here because it has a great neighborhood atmosphere, and they have the best market right outside my hotel. If I am lucky, there will be a great event in the park.
Hi, Im Nancy, this is my husband Louis andour children, Carlos and Maria. After we drop our kids at the Day Care, Louis goes to the English as a Second Language class at the Library. Afterward, Carlos goes to the park to play soccer with his friends while we garden nearby. We will go to La Cocina de Consuelo for dinner tonight.
I study at the Rainier branch of Seattle Community College here. I ride my bike to Pro Bikes every morning where I lock up my bike, take a shower at their facilities, and get a drink from Felicias Cafe.
My name is Li. I sell Vietnamese specialtygoods at the Rainier St. Market.I commute to work each morning from Columbia City on the city bus. On my way home, I stop at the grocery store, but if I am lucky, Francis sends me home with fresh tomatoes from her garden. When I am not working, I enjoy sitting in the park feeding the ducks.
1
2
3
1
2
3
4
Hi, my name is Veronica and I live in a studio apartment above my favorite Sushi Restaurant. I start every morning at the gym and treat myself to a fresh croissant at the Southeast Bakery afterwards. My friend George is coming over tonight with our favorite bread and pasta from the market to help me finish painting my apartment. It is so nice being this close to Lowes.
I am an artist and I live in the new artist housing next to the light rail station. There is a great arts culture here with the gallery. Sometimes I paint at the water front, and I sell my paintings here at the market.
12
3
4
5
1
2
3
Hi, I am a professor UWCenter for Water here. I enjoy teaching my classesoutside by the water spiral and I love to do my work in the park. I also enjoy ending my day with my colleagues at the local pub on Rainier.
3
4
2
1
cy
ont
Gallery
Hi, Ceeenjj
Bus stop BikeStation Parking
Day Care Education Library Class
Restaurant
PharmacyGrocery Lowes Market
Hair Cut
Shower
Coffee Bar
Taekwondo
Soccer
Jogging
Tennis Garden Water Front
Gym Squash
Gallery
11
2
34
2
3
4
5
Hi, my name is Amy. I am in town for a conference. I love the proximity here to both the airport and downtown Seattle. I enjoy staying here because it has a great neighborhood atmosphere, and they have the best market right outside my hotel. If I am lucky, there will be a great event in the park.
Hi, Im Nancy, this is my husband Louis andour children, Carlos and Maria. After we drop our kids at the Day Care, Louis goes to the English as a Second Language class at the Library. Afterward, Carlos goes to the park to play soccer with his friends while we garden nearby. We will go to La Cocina de Consuelo for dinner tonight.
I study at the Rainier branch of Seattle Community College here. I ride my bike to Pro Bikes every morning where I lock up my bike, take a shower at their facilities, and get a drink from Felicias Cafe.
My name is Li. I sell Vietnamese specialtygoods at the Rainier St. Market.I commute to work each morning from Columbia City on the city bus. On my way home, I stop at the grocery store, but if I am lucky, Francis sends me home with fresh tomatoes from her garden. When I am not working, I enjoy sitting in the park feeding the ducks.
1
2
3
1
2
3
4
Hi, my name is Veronica and I live in a studio apartment above my favorite Sushi Restaurant. I start every morning at the gym and treat myself to a fresh croissant at the Southeast Bakery afterwards. My friend George is coming over tonight with our favorite bread and pasta from the market to help me finish painting my apartment. It is so nice being this close to Lowes.
I am an artist and I live in the new artist housing next to the light rail station. There is a great arts culture here with the gallery. Sometimes I paint at the water front, and I sell my paintings here at the market.
12
3
4
5
1
2
3
Hi, I am a professor UWCenter for Water here. I enjoy teaching my classesoutside by the water spiral and I love to do my work in the park. I also enjoy ending my day with my colleagues at the local pub on Rainier.
3
4
2
1
Bus stop BikeBikeBikeBikeBikeStation Parking
Day Care Education Library Class
Restaurant
PharmacyGrocery Lowes Market
Hair Cut
Shower
Coffee Bar
Taekwondo
Soccer
Jogging
Tennis Garden Water Front
Gym Squash
Gallery
-
Mount Baker Redevelopment 35
ABOVE A bioretention water system connectcs housing and a pedestrian mall
of shopping to the natural water cycles of the neighborhood at the heart of the
development
OPPOSITE The programming and site planning afford a variety of uses and experiences, and encourages social
interaction between the areas diverse population.
-
36
My work with Texas Impact Design explores the intersections of design, architecture, and public service. The project - a primary school in Tororo, Uganda - combines sustainable agriculture, aquaculture, education, and passive sustainable design to act as an agent for social transformation.
In the Spring of 2012, the UT School of Architecture was approached with the opportunity to design a primary school for a village in the Busia District of Uganda. Answering this challenge, I worked with six other students to propose a new idea for a primary school - one that nurtures the whole student, engages a larger community, and promotes sustainability in education and practice.
In the Summer of 2012, our team traveled to Uganda to present our ideas at the Sustainable Futures Conference in Kampala, to meet with our client for the project, and to research first hand the context we will be working in.While there, we identified a client for the school - a small orphanage in the eastern region of Uganda that desires to grow into a primary school.
I have continued to work as a leading member on this project since its inception in 2012. My responsibilities have included research, design, master planning, and fundraising. Currently, we are revising our long term master plan for the school and developing new classroom prototypes. We are also in the process of founding a non-profit organization to help fund and manage the construction of the school.
Construction is anticipated to begin in the summer of 2014.
06. TEXAS IMPACT DESIGNSpring 2012-Present Critic Michael Garrison Location Tororo, UgandaIn Collaboration with Texas Impact Design (student group)
TORORO DISTRICT
LAKE VICTORIA
KARAMOJA
UGANDApopulation: 32,710,000size: 241,550 km^2capital: Kampalalife expectancy: 53 years
-
Texas Impact Design 37
ABOVE Children at Smile Africa playing on the newly constructed playground equipment
LEFT The Texas Impact Design team with the staff and volunteers of Smile Africa. We are currently developing a master plan for
the organization that will allow it to grow from an orphanage into a progressive,
sustainable primary school.
-
38
The nation of Uganda faces many issues, including poverty and unemployment, inadequate infrastructure, inadequate financial services, gender issues, and poor social services. Lack of quality education is at the root of these issues. Today, teacher-to-student ratios are at a grim level of 1:100. While the gender gap in enrollment between boys and girls is only 1.1% in first grade; by seventh grade the gap reaches 16%. Out of 100 students who begin primary school, less than 30 finish, and only 12 continue to secondary school.
Our proposal is aimed at improving some of these statistics. The school is designed to foster self-sufficiency, critical thinking, and practical skills. Classrooms and the curriculum are designed around a shared garden, where students learn about innovative agricultural methods and balanced nutrition while contributing to their own healthy diets. Classrooms are organized around gathering spaces of various scales, maximizing flexibility and creating safe spaces for learning, play, and community events.
The schools architecture responds directly to its site, using natural ventilation and daylighting to make classrooms that facilitate active learning in a sustainable way. Building assemblies employ local materials and are designed for inexpensive construction and upkeep. Stabilized soil block will be used as the major construction material. These building blocks are made by compressing a mixture of soil and cement in a small, hand-operated press. This technology offers low construction costs, dramatically reduces the impact of construction on the environment, and is easy to teach and replicate.
BELOW Students sit in a shaded outdoor classroom learning adjacent to the learning
garden
OPPOSITE Classrooms are organized in pairs around a central teachers office, which also
functions as a ventilation stack. Classrooms cluster around a learning garden, integrating
sustainable agriculture into the daily curriculum of the school
-
Texas Impact Design 39
-
40
A system of aquaponics, slow drip irrigation, and permaculture farming is at the core of the educational and architectural life of the school. Children in Uganda often lack proper diet, making good nutrition a primary issue in the health and growth of primary school aged children. The school proposes to integrate sustainable agricultural practices into the curriculum and classroom design. This will enable the school to provide food for all of the students in addition to teaching valuable skills, responsibilities, and healthy living. The proposed production methods will become a closed-loop system that will allow for sustained production and agricultural support.
-
Texas Impact Design 41
EFFLUENT
SEAFOOD
PRODUCE
COMPOST
CLEAN WATER
AQUACULTURE
AGRICULTURE
KITCHEN
CLASSROOM OUTDOOR CLASSROOM
SHADED STEPS
PERMACULTURE BEDS
AQUAPONICS
-
42
In the Summer of 2012, our student group traveled to Uganda to begin the work of making this project a reality. In addition to sharing our work at an international architecture conference, we spent several days discussing our ideas for a sustainable school with the leaders of Smile Africa, as well as with city officials and local building professionals.
When we werent working on revising our designs to meet the conditions of the site, we spent our time renovating and building an addition to the childrens playground. This small contribution to the school captured the excitement and optimism of this project, and has become a cherished part of the daily life of the school.
-
Texas Impact Design 43
-
44
The architectural response to the programmatic and contextual issues of this project is a simple separation of the programmatic areas of each housing unit into two separate L-shaped buildings. The social spaces are moved to the interior of the site, separating the interior of the site from the street to create an absolutely and collectively owned space, isolated from the surrounding world.
This communal relationship between the sites inhabitants and a shared garden space provides a platform for interaction and active living where each resident, from the property owner to tenants, is together and equal. Personal and private spaces are contained in a second L-Shaped building, held separate from the communally owned spaces. They are oriented toward the world beyond, juxtaposing the quiet life of users with the larger community beyond. This separation is emphasized by a tall gulf of space which is pierced by thin corridors bridging between the two pieces of each unit. Along San Gabriel this block of bedrooms hovers above a long, deep front porch, which provides a slow movement from the front door to the street, as well as owned space to engage the passing world.
University of Texas
project site
07. WEST CAMPUS HOUSINGFall 2009 Critic Francisco Gomes Location Austin, TexasNominated for UTSoA Design Excellence Award
-
West Campus Housing 45
ABOVE The deep porch creates a welcoming, shaded transition from the street
LEFT A progression of study models exploring ideas of urban presence
BELOW Final Models
-
46
Owners Apartment
Co-op
Rental Apartment #1
Rental Apartment #2
GARDENSPORCH
LIVING AREAS
PARKIN
G
BEDROOMS
BEDROO
MS
LIVING AREAS
-
West Campus Housing 47
COMMUNAL/PRIVATE
COMMUNAL/PUBLIC
INDIVIDUAL/PUBLIC
ABOVE The deep porch creates a welcoming, shaded transition from the street
BELOW Section Diagram
-
48
-
West Campus Housing 49
ABOVE Final Model
OPPOSITE, TOP North South Section showing the relationship of the Owners Apartment to the
communal garden area
OPPOSITE, MIDDLE East Elevation
OPPOSITE, BOTTOM North Elevation
-
EXPLORATIONS
-
EXPLORATIONS
-
52
This project was designed and executed by reBILD - a small student organization founded by myself and four friends at the University of Texas School of Architecture.
The project is an exploration of expectation, light, and space. The installation was set in Battle Hall, UTs historic Architecture library. The series of seven low-tech sculptures, made of saran wrap and packing tape, were set throughout the main reading room. Their presence was both dramatic and subtle, slowly changing throughout the day with the varying intensity and direction of light.
My role in this project included design and planning, production, and placement of the sculptures.
01. BODIES OF LIGHTFall 2009In collaboration with reBILD
-
Explorations 53
-
54
This project analyzed the envelope assembly of Peter Zumthors Kunsthaus Bregenz. Emphasis was placed on the relationship of aesthetic and function concerns, such as weatherproofing, ventilation, day lighting, insulation, and shading, as well as the relationship of the building envelope to the larger concepts of the building. The final product of this analysis was a set of detailed drawings and a 1/2=10 scale model of the building envelope assembly.
02. FACADE ANALYSISFall 2010 Critic Uli Dangel In Collaboration with Parker Doelling
-
Explorations 55
-
56
Fall 2009 Critic John BloodThese selected drawings investigate lineweight, page composition, and varying techniques for creating architectural space within a two dimensional drawing.
Life Drawing Study Charcoal on Newsprint
Paraline StudyGraphite on Stonehenge. 22x30
03. ARCHITECTURAL DRAWING
-
Explorations 57
Conic SectionsGraphite on Stonehenge; 22x30
Freehand Perspective Geometry InvestigationGraphite on Stonehenge; 22x30
-
PROFESSIONAL WORK
-
PROFESSIONAL WORK
-
60
01. MEADOW LANE RESIDENCETod Williams Billie Tsien ArchitectsAugust 2012-January 2013
The house is sited on a long narrow lot overlooking the Atlantic Ocean to the South and Shinnecock Bay to the North. The primary material for the building is cast-in-place concrete, which is used as an expressed structural frame, the exterior cladding, and the interior floors and ceilings. A complex construction sequencing was developed to ensure that a continuous thermal and waterproofing barrier could be installed and verified while maintaining the desired expression and constructability of concrete on the interior and exterior.
The design for this project is by Tod Williams and Billie Tsien. My role on this project was in the production of drawings from 50% Design Development through 100% Construction documents.
I comprised one third of the three person project team, working directly with the project architect and under the supervision of the firms partners. This small project team allowed me to be heavily involved in all facets of the project, including drafting, producing design studies, developing details, and participating in client and consultant meetings. I also worked directly with the projects structural and mechanical engineers on the coordination of our drawings to achieve a highly coordinated drawing set prior to construction.
The project was drawn in Revit only the second project the office has used BIM for. My knowledge of the program allowed me to take a primary role in the 3D modeling and the production of drawings. Within our team, I was responsible for drafting and updating the plans, elevations, RCPs, power plans, interior elevations, site details, interior details, and schedules. The project architect on the project was responsible for producing the exterior envelope drawings and details.
-
Meadow Lane Residence 61
0($'2:/$1(6287+$037211
-
62
DN
3
3 4
D D
C C
1.2 2.1 3.9 4.8
203A205A
4A6.00
3A6.00
2A6.00
1A6.01
238 SFGUEST BEDROOM
201
98 SFGUEST BATH
202
214 SFGUEST BEDROOM
203
103 SFGUEST BATH
204
203 SFGUEST BEDROOM
205
106 SFGUEST BATH
206
288 SFMASTER BEDROOM
209
164 SFMASTER BATH
210
152 SFMASTER CLOSET
211
249 SFSUN ROOM
208
548 SFHALL207
B B
42' - 4" 15' - 7" 8' - 3" 18' - 7"
209A
A A
A6.121
SIM
OVERHANG OVERHANG
3' - 6" 3' - 6"
1A6.00
A7.083
A7.03
11
A3.01 8
1.4 3.6 4.6
4A6.01
3A6.01
C.2 C.2
C.7 C.7
A7.126
109' - 6"
9' - 9" 22' - 6" 22' - 6" 22' - 6" 22' - 6" 9' - 9"
5' -
1"
7' -
5"3'
- 4
1/2"
9' -
10 1
/2"
6' -
9"
S ID
E YA R
D S
ETBA
CK
P ER
VA R
IAN
CE
S ID
E YA R
D S
ETBA
CK
P ER
VA R
IAN
CE
2' - 4 5/8"
2' - 3"
08.01
05.10
3
3
3
06.01
06.0306.04
00.04
06.03
03.0203.02
08.1203.23
05.1005.01
05.01
05.10
01.01
3
9
1
1
03.1803.18
11.01
06.03 06.03
06.05
06.03
03.0203.02
00.04
3
1
1 3
11.01
06.03
00.04
08.17
08.04
06.0306.03
06.05
06.03
03.23
00.04
06.0306.05
06.03
11.01
06.03
08.04
OTB
03.0203.02 03.0203.02
03.0203.02A7.03 1618
A7.03 45
6
A3.041
E E
5
5
1
1 2.42
10
A7.03 1
2
3
2A6.01
5A6.01
3' - 3"
A7.153
A7.155
A7.154
A3.031
7A7.14
2A6.15
A7.03
17
A7.031920
A3.046
210A
A7.0315 A7.03
14
A7.03
12
A7.03 13A7.03 79
8
201A
204A206A
1A4.01
2A4.01
1A4.02
1A4.00
2A4.02
08.12
4' -
3 7/
8"
5' -
7 3/
4"
3' - 7 1/4"
10' - 7 3/4"
2' - 3 3/8"3' - 4 3/4" 2' - 3"
3' - 6 1/2" 2' - 3"
2' -
9 1/
2"
15' - 11 1/4"
11' - 3 1/4"
13' - 7"5' - 0"
5' -
3 7/
8"
4' -
1 3/
4"
6' - 3" 1' - 9" 18' - 0" 1' - 9" 7' - 8" 14' - 1" 1' - 9" 7' - 0 7/8" 9' - 0 7/8" 1' - 9" 5' - 11 3/8" 9' - 11 5/8" 1' - 9" 7' - 8 1/2" 1' - 9" 6' - 3"
A6.132
A6.132
5' - 5"
1' - 10"
8' - 7"
1 5/8"
5' - 0"
10.02
10.02
----
-- -
-
- -
A7.143
WAL
E NTA
SR E
SID E
N CE
1240
MEA
DO
WLA
NE
VILL
AGE
OF
SOU
T HAM
PTO
N,N
Y11
968
SCALE
DWN BY TWBTA
DRAWING ISSUE
PRELIMINARY DESIGNPHASE FINAL
DRAFT SUBMISSION TOSOUTHAMPTON B.D.
07.17.2012
05.11.2012
50% DESIGNDEVELOPMENT
07.30.2012
222
CEN
TRAL
PAR
KSO
UTH
NEW
YOR
K,N
Y1 0
019
TO
DW
ILL
IAM
S
AR
CH
ITE
CT
S,L
LP
BIL
LIE
TS
IEN
T F E
212.
582.
2385
212.
245.
1984
mai
l@tw
bta .
com
100% DESIGNDEVELOPMENT 09.14.2012
50% CONSTRUCTIONDOCUMENTS
NOT
FOR
CONS
TRUC
TIO
N
50% CONSTRUCTIONDOCUMENTS 11.16.2012
1/4" = 1'-0"
A1.04
SECO
NDFL
OO
RPL
A N
08.04 IN-SWING OPERABLE WINDOW WITH FIXED INSECTSCREEN
08.12 CUSTOM WOOD PIVOT DOOR W/ CUSTOM METALPULL
08.17 SLIDING POCKET DOOR ASSEMBLY10.02 WOOD-BURNING FIREPLACE11.01 WALL MOUNTED TELEVISION
00.04 SEE RCP01.01 OPENING ABOVE03.02 CONCRETE TOPPING WITH RADIANT PIPING03.18 C.I.P. CONCRETE SUNSHADE03.23 COORDINATE DOOR HARDWARE WITH C.I.P. CONC05.01 TEMPERED GLASS GUARDRAIL05.10 FIXED MILK GLASS PANEL06.01 CUSTOM WOOD BENCH06.03 CUSTOM WOOD CABINETRY06.04 CUSTOM WOOD SHELVING06.05 CUSTOM WOOD DESK08.01 S.S. WINDOW SYSTEM
DN
DN
DN
UP
102' - 6"
3
3 4
D D
C C
1.2 2.1 3.9 4.8
103A
101A102A
4A6.00
3A6.00
2A6.00
1A6.01
46 SFGUEST BATH
104
132 SFGUEST BEDROOM
103
41 SFPOWDER
102
310 SFSTUDY
105
54 SFENTRY HALL
101
621 SFLIVING
106391 SFDINING
107433 SFKITCHEN
108
122 SFSTORAGE HALL
109
72 SFLAUNDRY
110
B B
A A
FLOOD ZONE VE(EL 17)
FLOOD ZONE X(OUTSIDE 0.2% ANNUAL CHANCE
FLOOD)
COASTAL EROSION HAZARD LINE
SUNSET
SUMMERSOLSTICE
100'-0"TOP OF DUNE SETBACK
DEC
K &
POO
L S E
T BA C
KP E
R V
A RIA
NC
E
S ID
E YA R
D S
ETBA
CK
P ER
VA R
IAN
CE
S ID
E YA R
D S
ETBA
CK
P ER
VA R
IAN
CE
A6.121
POOL
23' - 6"
23' - 5"
ENTRY PORCH
5' -
1"
DECK
DN
1A6.00
A7.082
A7.02
27 A3.015
A7.02 25
A7.02
16
REVISED COASTAL EROSION HAZARD LINE 8.15.2012
1.4 3.6 4.6
4A6.01
3A6.01
C.2 C.2
C.7 C.7
A7.125
2
1A4.01
2A4.01
03.0703.07
03.04
03.08
3A
3 1
08.02
08.13
00.01
05.01
06.03
03.0210.01
03.1808.01
01.03
08.0408.02
09.05
06.03
06.04
06.0303.01
03.02
00.01
08.02
03.09
03.09
03.0703.07
06.05
06.04
08.02
11.01
09.07
11.0100.04
06.03
7
9A
5
9A
3
03.0703.07
7
1
08.06
05.04
12.04
12.04
OTA
03.26
03.26
03.26
12.06
1A4.02
23.05
03.14
26.04
03.26 03.26
10.02
03.0203.02
77
12.04
03.02
E E
5
5
1
1 2.4
2.42
2
A7.02
17 A7.02 19
A7.02
23
24 22
18
21
20
A3.026
A3.0211
2A6.01
5A6.01
A6.132
2A6.12
--
13A7.14
14A7.14
12A7.14
11A7.14
A7.0226
34 SFDECK STORAGE
E102
354 SFOUTDOOR DINING
E101
103B
1A4.00
A4.022
26.04
W108
W106
EXTENT OF SUNSHADE ABOVE
23.05
103C
03.38
03.37
13.07
03.38
13.08
13.09
05.17
03.3803.07
26.03
26.03
03.19
05.02
26.04
26.04
26.03
"4 - '51"2 - '7"5 - '1"1 - '12"8/7 5 - '4 22' - 6" "8/7 5 - '4"6 - '22
4' -
6 1/
2"2'
- 10
1/2
"3'
- 4
1/2"
9' -
10 1
/2"
6' -
9"2'
- 6
7/8"
7' - 10" 1' - 1" "5 - '3"0 - '02 7' - 10"
1' - 0" 7' - 10"
49' - 0"
40' - 0" 3' - 6"
5' - 0"
5' -
7 3/
4"
6' -
6 1/
4"
4' -
6 1/
4"
2' - 3 5/8"
4' -
1 3/
4"
4' -
6 1/
4"
4' - 0" 5' - 1 1/4"
12' - 3"
11' -
1 5
/8"
5' - 0 1/2"
5' -
5 1/
4" 7' - 1 3/4"
3' -
1 3/
4"
2' - 9 1/2"8"
1' - 6 1/2"
8' -
0"
5' - 6"
05.16
05.16
2A6.04
4A6.04
3A6.04
1A6.04
'41"8 - '7"9 - '1"0 - '51"0 - '3"9 - '1"3 - '6 "3 - '6"9 - '1"5 - '91"9 - '1"1 - '22"9 - '1"1 -
2' -
8 3/
4"
2' -
8 3/
4"
2' -
1"
7' - 2" 1' - 10 3/4"
3A6.12
4A6.06
3A6.05
A6.054
2' - 5"
25' - 6 7/8" 23' - 11" 23' - 10" 25' - 7 7/8"
1A6.13
----
QEQEQE
QEQE
QEQE
QEQE
A6.071
13A6.22
1A6.15
A6.07
A6.07
3
A6.07 4
6
----
5A7.14
WAL
E NTA
SR E
SID E
N CE
1240
MEA
DO
WLA
NE
VILL
AGE
OF
SOU
T HAM
PTO
N,N
Y11
968
SCALE
DWN BY TWBTA
DRAWING ISSUE
PRELIMINARY DESIGNPHASE FINAL
DRAFT SUBMISSION TOSOUTHAMPTON B.D.
07.17.2012
05.11.2012
50% DESIGNDEVELOPMENT
07.30.2012
222
CEN
TRAL
PAR
KSO
UTH
NEW
YOR
K,N
Y1 0
019
TO
DW
ILL
IAM
S
AR
CH
ITE
CT
S,L
LP
BIL
LIE
TS
IEN
T F E
212.
582.
2385
212.
245.
1984
mai
l@tw
bta .
com
100% DESIGNDEVELOPMENT 09.14.2012
50% CONSTRUCTIONDOCUMENTS
NOT
FOR
CONS
TRUC
TIO
N
50% CONSTRUCTIONDOCUMENTS 11.16.2012
1/4" = 1'-0"
A1.03
FIRS
TFL
OO
RP L
AN
06.05 CUSTOM WOOD DESK08.01 S.S. WINDOW SYSTEM08.02 LIFT AND LOCK GLAZED S.S.
DOORS08.04 IN-SWING OPERABLE WINDOW
WITH FIXED INSECT SCREEN08.06 SOLID WOOD DOOR08.13 OUT-SWING S.S. SCREEN
DOOR09.05 CUSTOM RUG09.07 WALL POCKET FOR
FLATSCREEN MONITOR10.01 TELEPHONE10.02 WOOD-BURNING FIREPLACE11.01 WALL MOUNTED TELEVISION12.04 S.S. FOOT GRILLE12.06 FLOOR LAMP13.07 OVERFLOW PERIMETER DRAIN13.08 INFINITY EDGE DRAIN13.09 TROUGH23.05 CUSTOM S.S. DUCT, SEE MECH
DRAWINGS26.03 DUPLEX FLOOR OUTLET W/
CUSTOM S.S. ENCLOSURE26.04 PLUG CONCEALING DUPLEX
FLOOR OUTLET
00.01 SEE STRUCTURAL DRAWINGS00.04 SEE RCP01.03 SUNSHADE ABOVE03.01 C.I.P. CONCRETE03.02 CONCRETE TOPPING WITH
RADIANT PIPING03.04 CONCRETE GUARDRAIL03.07 PRECAST CONC PAVERS ON
PEDESTALS03.08 C.I.P. CONCRETE SITE WALL03.09 C.I.P. CONCRETE SITE WALL
ON PILES03.14 C.I.P. CONCRETE STAIR W/
TOPPING03.18 C.I.P. CONCRETE SUNSHADE03.19 C.I.P. CONCRETE SITE STAIR03.26 PROVIDE OPENING IN CONC03.37 PRECAST CONCRETE
POOL/SPA COPING03.38 T.O. CONCRETE WALL05.01 TEMPERED GLASS GUARDRAIL05.02 S.S. HANDRAIL05.04 CUSTOM S.S. DOOR PULL05.16 SELF-CLOSING S.S. GATE05.17 ACID ETCHED GLASS PRIVACY
PANEL06.03 CUSTOM WOOD CABINETRY06.04 CUSTOM WOOD SHELVING
DN
UP
3
3
4
4
D D
C C
1.2 2.1 3.9 4.8
4A6.00
002A
3A6.00
2A6.00
1A6.01
003A
B B
E.3E.3
E.7E.7
2.6
2.6
1.6
1.6
UP
144 SFBUILDING ENTRY
002
1610 SFSTORAGE
001
514 SFPARKING
003
ENTRY PORCH ABOVE
A A
COASTAL EROSION HAZARD LINE
FLOOD ZONE VE(EL 17)
FLOOD ZONE X(OUTSIDE 0.2% ANNUAL CHANCE FLOOD)
293 SFSTORAGE
007
S ID
E YA R
DS E
T BA C
KP E
RVA
RIA
NC
E
285 SFMECH ROOM
005
175 SFPOOL EQ ROOM
006
31 SFTRASHE003
DRIVE ABOVE
13' - 5"
1A6.00
A7.081
3' -
1 1/
2"
A7.02 6
1.4
1.4
3.6
3.6
4.6
4.6
4A6.01
3A6.01
C.2 C.2
C.7 C.7
A7.124
DEC
K&
POO
LS E
T BA C
KP E
RVA
RIA
NC
E
S ID
E YA R
DS E
T BA C
KP E
RVA
RIA
NC
E
"7 - '81"3 - '8"7 - '51
27' -
6"
4' -
6 1/
2"2'
- 10
1/2
"3'
- 4
1/2"
9' -
10 1
/2"
6' -
9"
1' -
4 1/
2"
"7 - '2"7 - '81"4 - '1"11 - '6"7 - '51"8/5 2 - '01"2/1 3 - '21"11 - '21"11 - '6"8 - '2
E.1E.1
2.3
2.3
10' -
0 1
/2"
11' -
11
7/8"
10' -
4 7
/8"
1
03.14
03.01
03.09
03.0900.01
10.00
10.00
1A
03.01
07.02
09.09
22.18 22.18
1A4.02
09.09
03.02
08.18
E E
5
5
1
1
2.4
2.42
2
22 SFSTORAGE
003A
8 SFSTORAGE
002A
7
5
A7.0215
A6.093
2A6.01
002B
5A6.01
A6.143
A6.092
A6.094A6.09
5
A6.098
A6.091
A6.096
A6.097
414 SFTUNNEL
011
12' - 6"
A6.099A6.09
9
003B
002C
4A6.02
02.03
DN
002D
22.18
22.18
00.02
00.0107.09
07.08
1A
7
005A
006A
007A
22.18
03.09
1A4.01
2A4.01
1A4.02
1A4.00
A4.022
03.19
09.0909.09
09.0909.09
09.0909.09
09.0909.09
09.0909.09
09.0909.09
4A6.04
3A6.04
4A6.06
1A6.05
2A6.05
----
208I
----
1A6.15
4A6.15
1' -
9"1'
- 9"
WAL
E NTA
SR E
SID E
N CE
1240
MEA
DO
WLA
NE
VILL
AGE
OF
SOU
T HAM
PTO
N,N
Y11
968
SCALE
DWN BY TWBTA
DRAWING ISSUE
PRELIMINARY DESIGNPHASE FINAL
DRAFT SUBMISSION TOSOUTHAMPTON B.D.
07.17.2012
05.11.2012
50% DESIGNDEVELOPMENT
07.30.2012
222
CEN
TRAL
PAR
KSO
UTH
NEW
YOR
K,N
Y1 0
019
TO
DW
ILL
IAM
S
AR
CH
ITE
CT
S,L
LP
BIL
LIE
TS
IEN
T F E
212.
582.
2385
212.
245.
1984
mai
l@tw
bta .
com
100% DESIGNDEVELOPMENT 09.14.2012
50% CONSTRUCTIONDOCUMENTS
NOT
FOR
CONS
TRUC
TIO
N
50% CONSTRUCTIONDOCUMENTS 11.16.2012
1/4" = 1'-0"
A1.01
LOW
ERLE
V EL
P LAN
1/A2.3 1/A2.3
07.02 E.I.F.S.07.08 BUILDING JOINT07.09 BUILDING JOINT COVER08.18 RATED ASSEMBLY REQUIRED09.09 EPOXY PAINT10.00 UNREINFORCED CMU BREAKAWAY WALL22.18 AREA DRAIN
00.01 SEE STRUCTURAL DRAWINGS00.02 SEE MEP DRAWINGS02.03 TRENCH DRAIN03.01 C.I.P. CONCRETE03.02 CONCRETE TOPPING WITH RADIANT PIPING03.09 C.I.P. CONCRETE SITE WALL ON PILES03.14 C.I.P. CONCRETE STAIR W/ TOPPING03.19 C.I.P. CONCRETE SITE STAIR
-
Meadow Lane Residence 63
FLOOR 123' - 6"
FLOOR 234' - 3"
3 4
T.O. ROOF44' - 9"
T.O. PARAPET46' - 0"
BREAKAWAY/GRADE19' - 0"
LOWER LEVEL13' - 6"
TENNIS PAVILION7' - 6"
4A6.00
3A6.00
2A6.00
1A6.01
4.7
1A5.00
2.61.6
T.O. CHIMNEY53' - 0"
285 SFMECH ROOM
005
1A6.00
2A5.00
1.4 3.6 4.6
4A6.01
3A6.01
2.3
FLOOD ZONE VE17' - 0"
03.22
01.08 03.11 03.10
05.03 13.01
07.10 03.10
08.04
08.06
03.07
01.08
01.07
01.07
03.11 03.1003.11
51 2.42
2A6.12
A6.024
SIM
03.11
48.0148.01 48.01
00.02
03.01
03.20
03.11
00.02 00.02
03.0501.07
W106
10.00
03.11
03.22
A6.064
03.1103.11
03.11
----
T.O. CONCRETE45' - 9 1/2"
1' - 9"
6' - 10"
WAL
E NTA
SR E
SID E
N CE
1240
MEA
DO
WLA
NE
VILL
AGE
OF
SOU
T HAM
PTO
N,N
Y11
968
SCALE
DWN BY TWBTA
DRAWING ISSUE
PRELIMINARY DESIGNPHASE FINAL
DRAFT SUBMISSION TOSOUTHAMPTON B.D.
07.17.2012
05.11.2012
50% DESIGNDEVELOPMENT
07.30.2012
222
CEN
TRAL
PAR
KSO
UTH
NEW
YOR
K,N
Y1 0
019
TO
DW
ILL
IAM
S
AR
CH
ITE
CT
S,L
LP
BIL
LIE
TS
IEN
T F E
212.
582.
2385
212.
245.
1984
mai
l@tw
bta .
com
100% DESIGNDEVELOPMENT 09.14.2012
50% CONSTRUCTIONDOCUMENTS
NOT
FOR
CONS
TRUC
TIO
N
50% CONSTRUCTIONDOCUMENTS 11.16.2012
1/4" = 1'-0"
A4.00
NORT
HEL
E VAT
ION
13.01 MANUALLY OPERATED, TCC CLAD SLIDING ROOFHATCH/GEAR
48.01 PHOTOVOLTAIC ARRAY
03.20 ARCHITECTURAL CONCRETE03.22 EXTENT OF C.I.P. FACADE POUR05.03 CUSTOM S.S. COPING07.10 CHIMNEY08.04 IN-SWING OPERABLE WINDOW WITH FIXED INSECT
SCREEN08.06 SOLID WOOD DOOR10.00 UNREINFORCED CMU BREAKAWAY WALL
00.02 SEE MEP DRAWINGS01.07 WALL REMOVED FOR CLARITY01.08 SUNSHADE BEYOND03.01 C.I.P. CONCRETE03.05 CONCRETE RETAINING WALL03.07 PRECAST CONC PAVERS ON PEDESTALS03.10 CONCRETE CONSTRUCTION JOINT03.11 CRACK CONTROL JOINT
FLOOR 123' - 6"
FLOOR 234' - 3"
3
T.O. PARAPET46' - 0"
BREAKAWAY/GRADE19' - 0"
1.22.13.94.8
3A6.00
4.7
1A5.00
2.6 1.6
9' -
8 1/
4"1'
- 0"
8' -
10 3
/4"
1' -
0"
T.O. CHIMNEY53' - 0"
2A5.00
1.43.64.6
4A6.01
3A6.01
2.3
FLOOD ZONE VE17' - 0"
T.O. ROOF SLAB43' - 9"
3' - 6" 3' - 6"
03.07
03.18
5 12.4 2
00.0248.01
06.08
MIN
.
3' -
9 1/
2"
05.1613.08
----
FLOOR 123' - 6"
FLOOR 234' - 3"
34
T.O. ROOF44' - 9"
T.O. PARAPET46' - 0"
BREAKAWAY/GRADE19' - 0"
LOWER LEVEL13' - 6"
1.22.13.94.8
4A6.00
3A6.00
2A6.00
1A6.01
4.7
1A5.00
2.6 1.6T.O. CHIMNEY53' - 0"
1A6.00
2A5.00
1.43.64.6
4A6.01
3A6.01
2.3
FLOOD ZONE VE17' - 0"
03.11 03.0103.20
03.10 03.11 03.1005.03 07.10
13.01
08.04 08.1308.03
10.00
03.11
08.01
08.04
08.02
5 12.4 2
07.0207.02
00.02 48.0148.01
03.10
-
T.O. CONCRETE45' - 9 1/2"
WAL
E NTA
SR E
SID E
N CE
1240
MEA
DO
WLA
NE
VILL
AGE
OF
SOU
T HAM
PTO
N,N
Y11
968
SCALE
DWN BY TWBTA
DRAWING ISSUE
PRELIMINARY DESIGNPHASE FINAL
DRAFT SUBMISSION TOSOUTHAMPTON B.D.
07.17.2012
05.11.2012
50% DESIGNDEVELOPMENT
07.30.2012
222
CEN
TRAL
PAR
KSO
UTH
NEW
YOR
K,N
Y1 0
019
TO
DW
ILL
IAM
S
AR
CH
ITE
CT
S,L
LP
BIL
LIE
TS
IEN
T F E
212.
582.
2385
212.
245.
1984
mai
l@tw
bta .
com
100% DESIGNDEVELOPMENT 09.14.2012
50% CONSTRUCTIONDOCUMENTS
NOT
FOR
CONS
TRUC
TIO
N
50% CONSTRUCTIONDOCUMENTS 11.16.2012
1/4" = 1'-0"
A4.01
SOUT
HEL
E VAT
ION
SCALE : 1/4" = 1'-0"1 SOUTH ELEVATION
SCALE : 1/4" = 1'-0"2 SOUTH ELEVATION (SCREEN REMOVED)
ABOVE, TOP Site Sections
ABOVE, BOTTOM Wall Sections
OPPOSITE Lower Level, First Floor, and Second Floor Plans
-
64
FLOOR 123' - 6"
FLOOR 234' - 3"
T.O. PARAPET46' - 0"
BREAKAWAY/GRADE19' - 0"
LOWER LEVEL13' - 6"
TENNIS PAVILION7' - 6"
RESIDENCE
DECK
POOL
FLOOD ZONE X FLOOD ZONE VE
CO
ASTA
L ER
OSI
ON
HAZ
ARD
LIN
ER
EAR
SET
BAC
K
84'-9
5/8
" DEC
K SE
TBAC
KPE
R V
ARIA
NC
E
FLOOD ZONE AE
TENNIS COURT7' - 0"
STORAGEBLDG
ACCESS
T.O. CHIMNEY53' - 0"
T.O. T.P. PARAPET18' - 8"
FLOOD ZONE VE17' - 0"
382 SFTENNIS PAVILION
008
293 SFSTORAGE
007
175 SFPOOL EQ ROOM
006
285 SFMECH ROOM
005
23.05 23.0505.09
05.09
03.0803.15
03.18
DRIVE
48.01
07.08
POOL AND SPA DESIGN ANDCONSTRUCTION TO BE CONFIRMED
CANOPY T.B.D.
T.O. CONCRETE45' - 9 1/2"
FLOOR 123' - 6"
FLOOR 234' - 3"
T.O. PARAPET46' - 0"
BREAKAWAY/GRADE19' - 0"
LOWER LEVEL13' - 6"
T.O. T.P. PARAPET18' - 8"FLOOD ZONE VE17' - 0"
T.O. ROOF SLAB43' - 9"
103 SFGUEST BATH
204
621 SFLIVING
106
548 SFHALL207
1610 SFSTORAGE
001
DRIVEDECK DECK
POOL
48.01
13.01
03.18
POOL AND SPA DESIGN ANDCONSTRUCTION TO BE CONFIRMED
CANOPY T.B.D.
06.08
FLOOD ZONE X FLOOD ZONE VE
CO
ASTA
L ER
OSI
ON
HAZ
ARD
LIN
ER
EAR
SET
BAC
K
84'-9
5/8
" DEC
K SE
TBAC
KPE
R V
ARIA
NC
E
FLOOD ZONE AE
T.O. CONCRETE45' - 9 1/2"
WAL
E NTA
SR E
SID E
N CE
1240
MEA
DO
WLA
NE
VILL
AGE
OF
SOU
T HAM
PTO
N,N
Y11
968
SCALE
DWN BY TWBTA
DRAWING ISSUE
PRELIMINARY DESIGNPHASE FINAL
DRAFT SUBMISSION TOSOUTHAMPTON B.D.
07.17.2012
05.11.2012
50% DESIGNDEVELOPMENT
07.30.2012
222
CEN
TRAL
PAR
KSO
UTH
NEW
YOR
K,N
Y1 0
019
TO
DW
ILL
IAM
S
AR
CH
ITE
CT
S,L
LP
BIL
LIE
TS
IEN
T F E
212.
582.
2385
212.
245.
1984
mai
l@tw
bta .
com
100% DESIGNDEVELOPMENT 09.14.2012
50% CONSTRUCTIONDOCUMENTS
NOT
FOR
CONS
TRUC
TIO
N
50% CONSTRUCTIONDOCUMENTS 11.16.2012
1/8" = 1'-0"
A5.00
SITE
SECT
I ONS
SCALE : 1/8" = 1'-0"1 LONGITUDINAL SITE SECTION
03.08 C.I.P. CONCRETE SITE WALL03.15 C.I.P. CONCRETE SITE STAIR ON GRADE03.18 C.I.P. CONCRETE SUNSHADE05.09 S.S. FRAME AND WIRE MESH FENCE ASSEMBLY06.08 WOOD WALKWAY TO REPLACE EXISTING07.08 BUILDING JOINT13.01 MANUALLY OPERATED, TCC CLAD SLIDING ROOF HATCH/GEAR23.05 CUSTOM S.S. DUCT, SEE MECH DRAWINGS48.01 PHOTOVOLTAIC ARRAY
SCALE : 1/8" = 1'-0"2 SITE SECTION @ ENTRY
002A 002C002B003A 003B
TOSTUDIO
MILLWORKT.B.D.; TV
HERE?
009A 009B
102A 101A
103A103C103B
MILLWORKT.B.D.
OPENTO
LIVING
MILLWORKT.B.D.
OPEN TOSTUDY
OPEN TOENTRY HALLMILLWORKT.B.D.
OPEN TOLAUNDRY
OPENTO
KITCHEN
OPEN TOKITCHEN
OPEN TOSTORAGE
ROOM
E1 E2
OPEN TOKITCHEN
OPEN TOSTORAGE HALL
MILLWORKT.B.D.
GENERAL NOTES:
1. INTERIOR ELEVATIONS IN PROGRESS, USE FOR ORIENTATION AND VISUALIZATION ONLY2 INTERIOR FINISHES, ORNAMENTAL METALS AND DETAILING T.B.D, PENDING CLIENT AND ARCHITECTREVIEW3. MECHANICAL SUPPLY AND RETURN SHOWN FOR LOCATIONS ONLY, SEE MECH DRAWINGS; FINALEXTENTS AND DETAILING PENDING SELECTION OF INTERIOR FINISHES4. SEE POWER PLANS AND RCPS FOR ALL OUTLETS, SWITCHES, SCONES, ETC.5. PLUMBING FIXTURES, BATHROOM ACCESSORIES AND NICHE LOCATIONS T.B.D.
NORTH ELEVATION3 BUILDING ENTRY - RM 002 SOUTH ELEVATION1 BUILDING ENTRY - RM 002WEST ELEVATION2 BUILDING ENTRY - RM 002NORTH ELEVATION7 PARKING - RM 003 SOUTH ELEVATION5 PARKING - RM 003WEST ELEVATION6PARKING - RM 003
EAST ELEVATION11 TENNIS PAVILION - RM 008 NORTH ELEVATION10 TENNIS PAVILION - RM 008 SOUTH ELEVATION8 TENNIS PAVILION - RM 008WEST ELEVATION9 TENNIS PAVILION - RM 008
EAST ELEVATION14 STUDIO - RM 009
SOUTH ELEVATION12 STUDIO - RM 009WEST ELEVATION13 STUDIO - RM 009
EAST ELEVATION4 BUILDING ENTRY - RM 002
TOTENNIS
PAVILION
SCALE : 1/4" = 1'-0"16 ENTRY HALL - RM 101
NORTH ELEVATION17 BUILDING ENTRY/STORAGE HALL - RMS 101/108
EAST ELEVATION21 GUEST BEDROOM - RM 103
SOUTH ELEVATION18 GUEST BEDROOM - RM 103WEST ELEVATION19 GUEST BEDROOM - RM 103
NORTH ELEVATION20 GUEST BEDROOM - RM 103WEST ELEVATION22STUDY - RM 105
NORTH ELEVATION23 STUDY - RM 105EAST ELEVATION24 STUDY - RM 105EAST ELEVATION25 LIVING - RM 106
SOUTH ELEVATION27 STORAGE HALL - RM 109WEST ELEVATION28 LAUNDRY - RM 110EAST ELEVATION29 LAUNDRY - RM 110 EAST ELEVATION26 RM 107 - EAST ELEV
SCALE : 1/4" = 1'-0"15 RM 011 - EAST ELEV
-
Meadow Lane Residence 65
FLOOR 123' - 6"
FLOOR 234' - 3"
T.O. ROOF44' - 9"
LOWER LEVEL13' - 6"
T.O. CHIMNEY53' - 0"
2A7.12 C.2C.7
13" X 18" CHIMNEY FLUEWITH CLAY LINER; WRAP W/CERAMIC FIBER PAPER
ASH PIT
FIREBRICK; USEREFRACTORY MORTARW/ 1/4" FLUSH JOINTS
PREFABRICATED CLAYSMOKE CHAMBER; WRAP W/CERAMIC FIBER PAPER
ONE-PIECE PREFABRICATEDCLAY THROAT; WRAP W/CERAMIC FIBER PAPER
METAL PLATE SURROUND
CAST IRON CLEANOUTDOOR
ASH CHUTE; PROVIDEDROP AT HEARTHFLOOR
PROVIDE METALBASE FLASHINGAND REGLET
C.I.P CONCRETECHIMNEY
TOP SURFACE SLOPEDTO DRAIN
PRECAST CONC CAP ONMETAL PLATE W/ METALROD COLUMNS
30.00
T.O. ROOF SLAB43' - 9"
WOOD STORAGE
5A7.17
FLOOR 123' - 6"
FLOOR 234' - 3"
T.O. ROOF44' - 9"
LOWER LEVEL13' - 6"
T.O. CHIMNEY53' - 0"
2A7.12
C.2 C.7
5A7.12
7A7.12
4A7.12
T.O. ROOF SLAB43' - 9"
13" X 18" CHIMNEY FLUEWITH CLAY LINER; WRAP W/CERAMIC FIBER PAPER
ASH PIT
FIREBRICK; USEREFRACTORY MORTARW/ 1/4" FLUSH JOINTS
PREFABRICATED CLAYSMOKE CHAMBER; WRAP W/CERAMIC FIBER PAPER
ONE-PIECE PREFABRICATEDCLAY THROAT; WRAP W/CERAMIC FIBER PAPER
METAL PLATE SURROUND
ASH CHUTE; PROVIDEDROP AT HEARTHFLOOR
GASFIREPLACE
METAL PLATESURROUND
FLOOR 123' - 6"
FLOOR 234' - 3"
3
T.O. ROOF44' - 9"
LOWER LEVEL13' - 6"
T.O. CHIMNEY53' - 0"
CHIMNEY FLUE WITH CLAYLINER; WRAP W/ CERAMICFIBER PAPER
AIR INTAKE FOR CHIMNEY
ASH PIT
CAST IRON ASH DUMP
FIREBRICK; USEREFRACTORY MORTARW/ 1/4" FLUSH JOINTS
PREFABRICATED CLAY SMOKECHAMBER; WRAP W/ CERAMICFIBER PAPER
ONE-PIECE PREFABRICATEDCLAY THROAT; WRAP W/CERAMIC FIBER PAPER
CAST IRON DAMPER
ROLLING FIRESCREEN;SECURE TO STEELANGLE
CAST IN-WALL LUMINAIRE
T.O. ROOF SLAB43' - 9"
4" CMU BACKUP; WRAP W/CERAMIC FIBER PAPER
3
2A7.12
C.2
C.7CAST IRON ASH DUMP
METAL PLATE
FIREBRICK AT HEARTHW/ SOAPSTONEPANELS ON MUDSET
CHASE FOR PIPING
LOCATION OF FLUEOVERHEAD
5'-0
1/2"
3'-4
"2'
-1"
1'-4
"6"
7"
7'-5
1/2"
STEE
LO
PEN
ING
3'-4
"1'
-6"
6"
CHASE FOR PIPING
METAL PLATE
3A7.07
1A7.07
4" CMU BACKUP; WRAPW/ CERAMIC FIBERPAPER
P.LAM. BOX FORWOOD STORAGE ST
EEL
OPE
NIN
GST
EEL
OPE
NIN
G
A7.138
3
C
2A7.12
C.2
C.7
EXTENT OFCHIMNEY BELOW
PIPE CHASE
IN-WALLLUMINAIRE
IN-WALLLUMINAIRE
PIPE CHASE
3A7.07
1A7.07
5A7.17
3
2A7.12
C.2
C.7
12"X12" CAST IRONCLEANOUT DOOR
ASH PIT
CHASE EXTENDSTO LOWER LEVELCEILING
CHASE EXTENDSTO LOWER LEVELCEILING
ASH DUMP ABOVE
ASH DUMP ABOVE
1' - 3"
3A7.07
1A7.07
3
C
2A7.12
C.2
C.7
METAL RODCOLUMNS
STONE CHIMNEYCAP ABOVE
CHIMNEY FLUE
EXTENT OFCHIMNEY BELOW
3A7.07
1A7.07
CHIMNEY FLUE
GAS FIREPLACEBELOW
WAL
E NTA
SR E
SID E
N CE
1240
MEA
DO
WLA
NE
VILL
AGE
OF
SOU
T HAM
PTO
N,N
Y11
968
SCALE
DWN BY TWBTA
DRAWING ISSUE
PRELIMINARY DESIGNPHASE FINAL
DRAFT SUBMISSION TOSOUTHAMPTON B.D.
07.17.2012
05.11.2012
50% DESIGNDEVELOPMENT
07.30.2012
222
CEN
TRAL
PAR
KSO
UTH
NEW
YOR
K,N
Y1 0
019
TO
DW
ILL
IAM
S
AR
CH
ITE
CT
S,L
LP
BIL
LIE
TS
IEN
T F E
212.
582.
2385
212.
245.
1984
mai
l@tw
bta .
com
100% DESIGNDEVELOPMENT 09.14.2012
50% CONSTRUCTIONDOCUMENTS
NOT
FOR
CONS
TRUC
TIO
N
50% CONSTRUCTIONDOCUMENTS 11.16.2012
1/2" = 1'-0"
A7.12
CHIM
NEY
P LAN
SAN
DEL
EV
SCALE : 1/2" = 1'-0"3 CHIMNEY ELEVATION LOOKING WEST SCALE : 1/2" = 1'-0"1CHIMNEY ELEVATION LOOKING EAST
SCALE : 1/2" = 1'-0"2 SECTION THROUGH CHIMNEYSCALE : 1/2" = 1'-0"5 CHIMNEY PLAN LEVEL ONE
SCALE : 1/2" = 1'-0"6 CHIMNEY PLAN LEVEL TWO
SCALE : 1/2" = 1'-0"4 CHIMNEY PLAN LOWER LEVEL
SCALE : 1/2" = 1'-0"7 CHIMNEY PLAN ROOF LEVEL
ABOVE, TOP Site Sections
ABOVE, BOTTOM Wall Sections
OPPOSITE Lower Level, First Floor, and Second Floor Plans
FLOOR 123' - 6"
FLOOR 234' - 3"
T.O. PARAPET46' - 0"
LOWER LEVEL13' - 6"
TENNIS PAVILION7' - 6"
"FIRST POUR"; CONCRETEBUILDING STRUCTURE
"SECOND POUR";ARCHITECTURAL CONCRETEFACADE
1.5" GROOVED FACERIGID INSULATION
AIR/WATER BARRIER
TUNNEL ROOFINSULATION
TUNNEL ROOFWATERPROOFING
UNDERSLABWATERPROOFING
UNDERSLABINSULATION
FLOOD ZONE VE17' - 0"
INTERIOR
INTERIOR
INTERIOR
INTERIOR
EXTERIOR
T.O. ROOF SLAB43' - 9"
E
A6.103
A6.112
TOPPING SLAB,SLOPED TO DRAIN
3.5" CLOSED-CELLPOLYURETHANE SPRAYFOAM INSULATION
FOUNDATION WALLWATERPROOFING
T.O. CONCRETE45' - 9 1/2"
FLOOR 123' - 6"
FLOOR 234' - 3"
T.O. PARAPET46' - 0"
BREAKAWAY/GRADE19' - 0"
LOWER LEVEL13' - 6"
HALFEN HIT - INSULATEDCONNECTION, SEESTRUCTURAL DRAWINGS
"SECOND POUR";ARCHITECTURALCONCRETE FACADE
1.5" GROOVED FACERIGID INSULATION
AIR/WATER BARRIER
"FIRST POUR"; CONCRETEBUILDING STRUCTURE
"FIRST POUR"; CONCRETEBUILDING STRUCTURE
"FIRST POUR"; CONCRETEBUILDING STRUCTURE
FOUNDATION WALLINSULATION
"FIRST POUR";CONCRETE BUILDINGSTRUCTURE
SEE STRUCTURALDRAWINGS
FILTER FABRIC
HALFEN HIT INSULATEDCONNECTION; SEESTRUCTURAL DRAWINGS
PRECAST PAVERS ONPEDESTALS
WATERPROOFING
CONCRETE SLABON PILES, SEESTRUCTURAL
FLOOD ZONE VE17' - 0"
INTERIOR
INTERIOR
INTERIOR
EXTERIOR
FOUNDATION WALLWATERPROOFING
T.O. ROOF SLAB43' - 9"
E
A6.111
A6.104
A6.105
1.5" SQUARE EDGERIGID INSULATION
STAINLESS STEEL COPING
A6.123
T.O. CONCRETE45' - 9 1/2"
FLOOR 123' - 6"
FLOOR 234' - 3"
D
T.O. PARAPET46' - 0"
BREAKAWAY/GRADE19' - 0"
LOWER LEVEL13' - 6"
"SECOND POUR";ARCHITECTURALCONCRETE FACADE
1.5" GROOVED FACERIGID INSULATION
3.5" CLOSED CELLPOLYURETHANE FOAMINSULATION
"FIRST POUR";CONCRETE BUILDINGSTRUCTURE
CONCRETETOPPING WITHRADIANT PIPING
"FIRST POUR";CONCRETE BUILDINGSTRUCTURE
CONCRETETOPPING WITHRADIANT PIPING
METAL PLATE EDGE
FILTER FABRIC
RIGID INSULATION
UNDERSLAB INSULATION
UNDERSLABWATERPROOFING
FOUNDATIONWATERPROOFING
FLOOD ZONE VE17' - 0"
INTERIOR
INTERIOR
INTERIOR
T.O. ROOF SLAB43' - 9"
E
A6.112
A6.102
A6.101
A6.113
PILE CAP BEYOND
CMU BREAKAWAY WALL
EXTERIOR
T.O. CONCRETE45' - 9 1/2"
FLOOR 123' - 6"
FLOOR 234' - 3"
T.O. ROOF44' - 9"
T.O. PARAPET46' - 0"
LOWER LEVEL13' - 6"
TENNIS PAVILION7' - 6"
548 SFHALL207
T.O. ROOF SLAB43' - 9"
E
A6.124
A6.126
A6.107
A6.108
STAINLESS STEELWINDOW SYSTEM
FOUNDATION WALLINSULATION
FOUNDATION WALLWATERPROOFING
TUNNEL ROOFINSULATION
TUNNEL ROOFWATERPROOFING
A6.032
Sim
8" SELF-BALLASTINGRIGID INSULATION
ROOF WATERPROOFING
CONCRETE TOPPINGSLAB, SLOPED TO DRAIN
CONCRETE TOPPING,SLOPED TO DRAIN
TUNNEL ROOF SLAB,SEE STRUCTURALDRAWINGS
EXPANSION JOINT, SEESTRUCTURAL DRAWINGS
"SECOND POUR";ARCHITECTURALCONCRETE FACADE
"FIRST POUR";CONCRETE BUILDINGSTRUCTURE
9' -
9"
T.O. CONCRETE45' - 9 1/2"
WAL
E NTA
SR E
SID E
N CE
1240
MEA
DO
WLA
NE
VILL
AGE
OF
SOU
T HAM
PTO
N,N
Y11
968
SCALE
DWN BY TWBTA
DRAWING ISSUE
PRELIMINARY DESIGNPHASE FINAL
DRAFT SUBMISSION TOSOUTHAMPTON B.D.
07.17.2012
05.11.2012
50% DESIGNDEVELOPMENT
07.30.2012
222
CEN
TRAL
PAR
KSO
UTH
NEW
YOR
K,N
Y1 0
019
TO
DW
ILL
IAM
S
AR
CH
ITE
CT
S,L
LP
BIL
LIE
TS
IEN
T F E
212.
582.
2385
212.
245.
1984
mai
l@tw
bta .
com
100% DESIGNDEVELOPMENT 09.14.2012
50% CONSTRUCTIONDOCUMENTS
NOT
FOR
CONS
TRUC
TIO
N
50% CONSTRUCTIONDOCUMENTS 11.16.2012
1/2" = 1'-0"
A6.00
WAL
LSE
CTIO
N S
SCALE : 1/2" = 1'-0"4 WALL SECTIONSCALE : 1/2" = 1'-0"2 WALL SECTION @ COLUMN SCALE : 1/2" = 1'-0"1
TYPICAL WALL SECTION
SCALE : 1/2" = 1'-0"3 WALL SECTION @ TUNNEL ENTRY
FLOOR 123' - 6"
FLOOR 234' - 3"
C
T.O. PARAPET46' - 0"
BREAKAWAY/GRADE19' - 0"
LOWER LEVEL13' - 6"
BA
FLOOD ZONE VE17' - 0"
PRECAST PAVERSON PEDESTALS
SLOPED CONCRETESLAB;SEE STRUCTURALDWGS
WATERPROOFING
FOUNDATIONWATERPROOFING
FOUNDATIONWALL INSULATION
INTERIOR
INTERIOREXTERIOR
T.O. ROOF SLAB43' - 9"
S.S. WINDOWSYSTEM
C.I.P CONCSUNSHADE; ARCHCONC FINISH
DUPLEX FLOOR OUTLET,CUSTOM S.S.
ENCLOSURE, SEEPLANS FOR LOCATIONS
MOTORIZEDWINDOW SHADE
E.I.F.S.
A6.153
A6.137
A6.134
A6.136
----
FLOOR 123' - 6"
FLOOR 234' - 3"
T.O. PARAPET46' - 0"
BREAKAWAY/GRADE19' - 0"
LOWER LEVEL13' - 6"
BA
FLOOD ZONE VE17' - 0"
PRECAST PAVERSON PEDESTALS
WATERPROOFING
INTERIOREXTERIOR
INTERIOR
S.S. WINDOW SYSTEM
C.I.P CONC SUNSHADE;ARCH CONC FINISH
LINEAR FLOOR DIFFUSER,SEE PLANS FOR LOCATIONS
T.O. ROOF SLAB43' - 9"
SLOPED CONCRETESLAB;SEE STRUCTURAL DWGS
AIR SUPPLY SLOT;SEE MECH AND
ARCH PLANS
UNREINFORCED C.M.U.BREAKAWAY WALL
MOTORIZEDWINDOW SHADE
E.I.F.S.
4"
A6.139
A6.1310
A6.1311
FLOOR 123' - 6"
FLOOR 234' - 3"
T.O. PARAPET46' - 0"
BREAKAWAY/GRADE19' - 0"
LOWER LEVEL13' - 6"
"FIRST POUR"; CONCRETEBUILDING STRUCTURE
"SECOND POUR";ARCHITECTURAL CONCRETEFACADE
WALL INSULATION
AIR/WATERBARRIER
HALFEN HIT -INSULATED BALCONYCONNECTION; SEESTRUCTURALDRAWINGS
HALFEN HIT -INSULATED BALCONYCONNECTION;SEE STRUCTURALDRAWINGS
FOUNDATIONWATERPROOFING
RIGID INSULATION
UNDERSLABWATERPROOFING
UNDERSLABINSULATION
DRAINAGE MAT
316 STAINLESS STEELCOPING
FLOOD ZONE VE17' - 0"
"FIRST POUR"; CONCRETEBUILDING STRUCTURE
INTERIOR
INTERIOR
INTERIOR
EXTERIOR
T.O. ROOF SLAB43' - 9"
HALFEN HIT INSULATEDPARAPET CONNECTION;SEE STRUCTURALDRAWINGS
E
A6.106
T.O. CONCRETE45' - 9 1/2"
FLOOR 123' - 6"
FLOOR 234' - 3"
T.O. PARAPET46' - 0"
BREAKAWAY/GRADE19' - 0"
LOWER LEVEL13' - 6"
B.O. FLOOR 122' - 6"
FLOOD ZONE VE17' - 0"
T.O. ROOF SLAB43' - 9"
1
A6.144
A6.145
----
A6.111
PILE CAP; SEESTRUCTURALDRAWINGS
STAINLESS STEELCORNER GUARD
"SECOND POUR";ARCHITECTURALCONCRETE FACADE
"FIRST POUR";CONCRETE BUILDINGSTRUCTURE
PAINTED ALUMINUMINSULATED GARAGEDOOR
7' -
3"
FLOOR 123' - 6"
FLOOR 234' - 3"
T.O. PARAPET46' - 0"
LOWER LEVEL13' - 6"
B.O. 2ND FLR SLAB33' - 3"
B.O. FLOOR 122' - 6"
T.O. ROOF SLAB43' - 9"
STAIR LANDING 228' - 7 1/8"
5
----
"SECOND POUR";ARCHITECTURALCONCRETE FACADE
FILTER FABRIC
FOUNDATIONWALL INSULATION
FOUNDATION WALLWATERPROOFING
"FIRST POUR";CONCRETE BUILDINGSTRUCTURE
"FIRST POUR";CONCRETE BUILDINGSTRUCTURE
1.5" GROOVED FACERIGID INSULATION
3.5" CLOSED-CELLPOLYURETHANE SPRAYFOAM INSULATION
WAL
E NTA
SR E
SID E
N CE
1240
MEA
DO
WLA
NE
VILL
AGE
OF
SOU
T HAM
PTO
N,N
Y11
968
SCALE
DWN BY TWBTA
DRAWING ISSUE
PRELIMINARY DESIGNPHASE FINAL
DRAFT SUBMISSION TOSOUTHAMPTON B.D.
07.17.2012
05.11.2012
50% DESIGNDEVELOPMENT
07.30.2012
222
CEN
TRAL
PAR
KSO
UTH
NEW
YOR
K,N
Y1 0
019
TO
DW
ILL
IAM
S
AR
CH
ITE
CT
S,L
LP
BIL
LIE
TS
IEN
T F E
212.
582.
2385
212.
245.
1984
mai
l@tw
bta .
com
100% DESIGNDEVELOPMENT 09.14.2012
50% CONSTRUCTIONDOCUMENTS
NOT
FOR
CONS
TRUC
TIO
N
50% CONSTRUCTIONDOCUMENTS 11.16.2012
1/2" = 1'-0"
A6.01W
ALL
SECT
ION S
SCALE : 1/2" = 1'-0"4 WALL SECTION @ SOUTH COLUMN SCALE : 1/2" = 1'-0"3WALL SECTION @ SOUTH WALL
SCALE : 1/2" = 1'-0"1 WALL SECTION @ FULL HEIGHT WALLSCALE : 1/2" = 1'-0"2WALL SECTION @ GARAGE
SCALE : 1/2" = 1'-0"5 WALL SECTION @ WEST WALL
-
66
02. MODEL MAKINGAlterstudio Architecture LLPFebruary-March 2013
I was commissioned by Alterstudio Architecture, a small residential firm in Austin, to build multiple presentation models. This included a model for a building that was currently in design for a client presentation (not shown), and a recently completed house. The model shown here - a recently completed renovation and addition to an existing bungalow - is currently on display at an exhibition of the firms work at Bennington, College in Vermont.
-
Model Making 67
-
68
The Maufrais Urban Farm Projects were a set of small design build projects conducted during the Spring 2012 semester as a lab component for the course Construction 2: Architectures of Building Performance. Working in three teams of 25, students worked together to design and construct small projects supporting the educational mission of a local urban farm. Each project was developed within the constraints of a $3,500 dollar budget and eight days of construction.
I worked as a Teaching Assistant for this course. In addition to typical responsibilities of managing coursework, I was responsible for managing the design and construction of one of these small projects - a retaining wall and shaded seating area connecting the parking area to the educational display.
During the first half of the semester, students worked through an iterative design process in small groups, developing components of the design. I was responsible for teaching students about the related materials and assemblies, and how to balance costs, scheduling, and design intent. In addition, I led several class wide design charrettes to make final design decisions for the project.
On the construction site, I was responsible for teaching basic techniques of construction, project management, and how to consider construction and design simultaneously.
In addition, I co-authored a paper analyzing this project as a means of integrating design-build into architecture curriculums through the construction course sequence. The paper was presented at the BTES session of the 2013 ACSA conference, and will be published this summer.
03. THE MAUFRAIS URBAN FARM PROJECTSUniversity of Texas School of ArchitectureSpring 2012
-
Maufrais Urban Farm Projects 69
ABOVE Leading a classwide design charrette to make final design decisions.
LEFT Advising students on construction details and means of assembly
BELOW Students installing steel plate retaining wall and shade canopy
-
70
-
Maufrais Urban Farm Projects 71
-
RESUME
-
RESUME
-
BRIAN PATRICK DOHERTY
5715 Joe Sayers AvenueAustin, Texas 78756 [email protected] 860.304.2448
-
PROFESSIONAL EXPERIENCE Tod Williams Billie Tsien Architects New York, New York August 2012-January 2013Worked as member of three person project team for Meadow Lane Residence from 50% Design Development through 100% Construction Documents. Coordinated complex architectural concrete drawings with structural and mechanical engineers. Produced design studies, permitting documents, construction drawings, and assisted in managing project Revit model.
Humphries Poli Architects Denver, Colorado May August 2011Produced As-Built drawings for Denvers North High School Renovation. Produced study models, construction documents, and permitting submittals for Altura Elementary School Renovation and Addition. Produced presentation materials for several library and school projects.
Alterstudio Austin, Texas January-April 2013Produced presentation models for client presentations and a traveling exhibition of the firms work.
University of Texas at Austin, School of Architecture Austin, TexasTeaching Assistant, Fall 2010, Spring 2011, Spring 2012Led undergraduate discussion sections, organized coursework, and managed a design-build project for Construction I and II courses.
Federation of American Scientists Washington, D.C.Research Assistant, June 2007 August 2009Researched, Authored, and Published policy papers about energy efficiency, advanced building technologies, building codes, manufactured housing, and emergency relief housing. Presented research at the ASCE Architectural Engineering Institute Conference (Denver, 2008) and the U.S. China Green Energy Conference. (Beijing, November 2008). Managed program website, wrote grant applications, and handled progams administrative, budget, and office needs.
EDUCATION The University of Texas Austin School of Architecture Austin, TexasMaster of Architecture, September 2009 May 2013Current GPA: 3.94
Haverford College Haverford, PennsylvaniaBachelor of Arts, September 2003 May 2007Major: Growth and Structure of Cities at Bryn Mawr CollegeSemester Abroad: Danish Institute for Study Abroad, Copenhagen, Denmark (Spring 2006)Thesis: Student Space at Haverford College - An Architectural Analysis
SKILLSRevit, AutoCAD, Adobe Photoshop, Adobe Illustrator, Adobe InDesign, Sketchup, Kerkythea, Rhino, VRay, Cnc Routing, Laser Cutting, woodworking
HONORS AND AWARDS Tau Sigma Delta Honors Society University of Texas, Spring 2013J. M. West Texas Corporation Fellowship in Architecture University of Texas, Fall 2012Goldwin Goldsmith Memorial Scholarship in Architecture Texas Society of Architects, Fall 2012Jorge Luis Divino Centennial Scholarship in Architecture University of Texas, Fall 2011Goldwin Goldsmith Memorial Scholarship in Architecture Texas Society of Architects, Fall 2011Cogburn Family Foundation Architecture and Urbanism Prize University of Texas, Spring 2010John S. Chase Endowed Presidential Scholarship University of Texas, Fall 2009Design Excellence Award Nominee University of Texas, Fall 2009Haverford College Varsity Soccer Team Captain Spring 2005 to Fall 2006