    Materials, Handling, PreparationMaterials, Handling, Preparation

    SafetySafety

    Cement, when mixed with water, releasesCement, when mixed with water, releases

    alkali; take precautions to avoid dry cementalkali; take precautions to avoid dry cement

    entering the eyes, mouth and nose when mixingentering the eyes, mouth and nose when mixingconcreteconcrete

    Prevent skin contact with wet cement orPrevent skin contact with wet cement or

    concrete by wearing suitable protective clothingconcrete by wearing suitable protective clothing

    If cement or concrete enters the eyes,If cement or concrete enters the eyes,

    immediately wash it out thoroughly with cleanimmediately wash it out thoroughly with clean

    water, seek medical treatmentwater, seek medical treatment

  • 8/6/2019 Workmanship on Building Sites

    3/28

    ReadyReady--Mix Concrete DeliveryMix Concrete Delivery

    Check Delivery TicketCheck Delivery TicketSerial number and date, truck numberSerial number and date, truck number

    Name of the Purchaser, Location of the SiteName of the Purchaser, Location of the Site

    Grade of Concrete orMix proportion, SpecifiedGrade of Concrete orMix proportion, Specifiedworkability, Min Cement Content, Cement Typeworkability, Min Cement Content, Cement Type

    Nominal max size of AggregateNominal max size of Aggregate

    Proportion of FlyProportion of Fly--Ash / GGBS in the MixAsh / GGBS in the MixMax Free w/c Ratio, Type of Admixture, dosageMax Free w/c Ratio, Type of Admixture, dosage

    Quantity of Concrete, Time of loadingQuantity of Concrete, Time of loading

    Any other items specifiedAny other items specified

  • 8/6/2019 Workmanship on Building Sites

    4/28

    Handling and Site StorageHandling and Site Storage

    ReinforcementR

    einforcementKeep clean; store reinforcement of ground;Keep clean; store reinforcement of ground;cover with polythene sheet to prevent corrosioncover with polythene sheet to prevent corrosion

    Do not permit rusting; if necessary cover theDo not permit rusting; if necessary cover the

    steel to exclude rain, but allow good circulationsteel to exclude rain, but allow good circulation

    of air all around the steelof air all around the steel

    Store different sizes separately from each otherStore different sizes separately from each other

    and ensure that they are clearlyand ensure that they are clearly labelledlabelled

    Dirt / grease prevents proper bond with theDirt / grease prevents proper bond with the

    concreteconcrete

  • 8/6/2019 Workmanship on Building Sites

    5/28

    Storing AccessoriesStoring Accessories

    Binding wire, joints sealants, water bars, coverBinding wire, joints sealants, water bars, cover

    blocks, spaces, admixtures, release agents etcblocks, spaces, admixtures, release agents etc

    in conditions and temperatures such that theyin conditions and temperatures such that they

    do not deteriorate, becomes damaged, soiled ordo not deteriorate, becomes damaged, soiled orcontaminatedcontaminated

  • 8/6/2019 Workmanship on Building Sites

    6/28

    InIn--Situ ConcreteSitu Concrete

    Weather ConditionsWeather ConditionsHot weather: Take precautions to ensure thatHot weather: Take precautions to ensure thatthe temperature of concrete is not higher thanthe temperature of concrete is not higher than

    3030oo C at the time of placingC at the time of placing

    Cold weather: The temperature of concreteCold weather: The temperature of concreteshould not fall below 5should not fall below 5oo C at any time duringC at any time during

    placing and compacting; place the concreteplacing and compacting; place the concrete

    quickly; do not place concrete against frozen orquickly; do not place concrete against frozen orice and snow covered surfacesice and snow covered surfaces

    Ensure that the concrete temperature is at leastEnsure that the concrete temperature is at least

    1010oo C, insulate the concrete surfaceC, insulate the concrete surface

  • 8/6/2019 Workmanship on Building Sites

    7/28

    InIn--Situ ConcreteSitu Concrete

    Preparation for ConcretingPreparation for ConcretingClean all rubbish, debris, free water from allClean all rubbish, debris, free water from all

    surfaces on to which the concrete is to besurfaces on to which the concrete is to be

    poured; remove wire nails, screws etc in thepoured; remove wire nails, screws etc in thecase of formworkcase of formwork

    General inspection: Check availability ofGeneral inspection: Check availability of

    Materials including RMC, Labor, Plant andMaterials including RMC, Labor, Plant and

    Equipment, Power and Water Supply, StandbyEquipment, Power and Water Supply, StandbyEquipment and SparesEquipment and Spares

    Confirm setting out checkingConfirm setting out checking

  • 8/6/2019 Workmanship on Building Sites

    8/28

    InIn--Situ ConcreteSitu Concrete

    Preparation for ConcretingPreparation for ConcretingConfirm inspection earlier permanent workConfirm inspection earlier permanent work

    If appropriate, obtain weather forecastIf appropriate, obtain weather forecast

    Check adequacies of access to points ofCheck adequacies of access to points ofdischarge and access platformsdischarge and access platforms

    Check readiness of the batching plantCheck readiness of the batching plant

    Check the communication systemCheck the communication systemConfirm arrangements for transporting, placing,Confirm arrangements for transporting, placing,

    compacting, finishing, curing and testingcompacting, finishing, curing and testing

  • 8/6/2019 Workmanship on Building Sites

    9/28

    InIn--Situ ConcreteSitu Concrete

    Preparation for ConcretingPreparation for Concreting--Earth FacesEarth Faces

    When concreting against earth surfaces, check:When concreting against earth surfaces, check:

    Stability of earth slopesStability of earth slopes

    Safety of earth faces when construction plantSafety of earth faces when construction plantis in operationis in operation

    Arrangements for removal of waterArrangements for removal of water

  • 8/6/2019 Workmanship on Building Sites

    10/28

  • 8/6/2019 Workmanship on Building Sites

    11/28

    InIn--Situ ConcreteSitu ConcretePreparation for ConcretingPreparation for Concreting--Joints etcJoints etc -- CheckCheck

    Construction of joints, dowels, water bars etcConstruction of joints, dowels, water bars etc

    Inserts and boxInserts and box--outs for accuracy and securityouts for accuracy and security

    Fixing of stop endsFixing of stop endsArrangement for forming kickersArrangement for forming kickers

    Preparation of hardened surfacesPreparation of hardened surfaces

  • 8/6/2019 Workmanship on Building Sites

    12/28

    InIn--Situ ConcreteSitu Concrete

    Reinforcement CheckR

    einforcement CheckSize, type, markings, location and cover areSize, type, markings, location and cover are

    correctcorrect

    Anchorages and laps are correctAnchorages and laps are correctThat it is rigidly securedThat it is rigidly secured

    Surface conditionSurface condition

    Use of spacers including type and sizeUse of spacers including type and sizeThe aim of preThe aim of pre--concreting check is to ensureconcreting check is to ensure

    that concreting proceeds without delay / defectsthat concreting proceeds without delay / defects

  • 8/6/2019 Workmanship on Building Sites

    13/28

    InIn--Situ ConcreteSitu Concrete

    Sampling and TestingSampling and TestingFollow appropriate procedures, usingFollow appropriate procedures, using

    equipment in good working orderequipment in good working order

    Complete certificates of sampling, cube making,Complete certificates of sampling, cube making,curing and testing to confirm compliance withcuring and testing to confirm compliance with

    SpecificationsSpecifications

    Transport concrete cubes to the lab ensuringTransport concrete cubes to the lab ensuring

    that they are kept moist, are not damaged andthat they are kept moist, are not damaged and

    spend the minimum time in transitspend the minimum time in transit

  • 8/6/2019 Workmanship on Building Sites

    14/28

    InIn--Situ ConcreteSitu Concrete

    Sampling and TestingSampling and TestingThe procedures for sampling, specimenThe procedures for sampling, specimen

    making, curing and testing given in IS:516 &making, curing and testing given in IS:516 &

    IS:1199 are very detailed and involve the use ofIS:1199 are very detailed and involve the use of

    well maintained standard equipment confirmedwell maintained standard equipment confirmed

    at regular intervals to comply with theat regular intervals to comply with the

    appropriate Standardsappropriate Standards

    Cubes should be stored and tested at anCubes should be stored and tested at anaccredited laboratory; store specimens underaccredited laboratory; store specimens under

    controlled temperature (27controlled temperature (27oo C inC in 33oo C)C)

  • 8/6/2019 Workmanship on Building Sites

    15/28

    InIn--Situ ConcreteSitu Concrete

    Sampling and TestingSampling and TestingDeviations from standard requirements canDeviations from standard requirements can

    affect results significantly and may lead toaffect results significantly and may lead to

    errors in judgment concerning the quality of theerrors in judgment concerning the quality of the

    concreteconcrete

    Supervision of personnel trained in theSupervision of personnel trained in the

    procedures is essentialprocedures is essential

    The use of a laboratory accredited for siteThe use of a laboratory accredited for site

    sampling and specimen making issampling and specimen making is

    recommendedrecommended

  • 8/6/2019 Workmanship on Building Sites

    16/28

    InIn--Situ ConcreteSitu Concrete

    Placing ConcretePlacing ConcretePlace concrete in one continuous operationPlace concrete in one continuous operation

    between and up to the construction joints orbetween and up to the construction joints or

    other limiting featuresother limiting features

    Discharge concrete through the reinforcementDischarge concrete through the reinforcement

    or other obstructions with care; avoid dispersal,or other obstructions with care; avoid dispersal,

    segregation or loss of ingredientssegregation or loss of ingredients

    Where reinforcement is congested use chutesWhere reinforcement is congested use chutes

    or trunking to direct the concrete into positionor trunking to direct the concrete into position

    If interrupted, form additional construction jointIf interrupted, form additional construction joint

  • 8/6/2019 Workmanship on Building Sites

    17/28

    InIn--Situ ConcreteSitu Concrete

    Displacement while placing ConcreteDisplacement while placing ConcreteWhile placing, ensure no displacement orWhile placing, ensure no displacement or

    damage occurs todamage occurs to

    damp proof membranesdamp proof membranesreinforcementreinforcement

    formwork orformwork or

    embedded fittingsembedded fittingsIf displacement occurs, take corrective actionIf displacement occurs, take corrective action

    immediately; necessary labor to be availableimmediately; necessary labor to be available

  • 8/6/2019 Workmanship on Building Sites

    18/28

    InIn--Situ ConcreteSitu Concrete

    Compacting ConcreteCompacting ConcreteCompact the concrete ensuring thatCompact the concrete ensuring that

    a) it forms a solid uniform mass free of voidsa) it forms a solid uniform mass free of voids

    b) it is packed tight around the reinforcementb) it is packed tight around the reinforcementc) it fills all parts of formwork or excavationc) it fills all parts of formwork or excavation

    d) there is no segregation of ingredientsd) there is no segregation of ingredients

    e) it is amalgamated with previous batchese) it is amalgamated with previous batchesf) there is no damage to adjacent concretef) there is no damage to adjacent concrete

    g) the required finish will be obtainedg) the required finish will be obtained

    h) vibrators are operated by trained personnelh) vibrators are operated by trained personnel

  • 8/6/2019 Workmanship on Building Sites

    19/28

    InIn--Situ ConcreteSitu ConcreteDeep Sections, Walls, Columns, BeamsDeep Sections, Walls, Columns, Beams

    Place and compact concrete in layers; eachPlace and compact concrete in layers; each

    layer should extend over the length and width oflayer should extend over the length and width of

    the section; place succeeding layers withoutthe section; place succeeding layers without

    delay and merge them, by compaction, with thedelay and merge them, by compaction, with the

    layer belowlayer below

    Check for plastic settlement cracking and reCheck for plastic settlement cracking and re--

    vibrate as necessaryvibrate as necessary

  • 8/6/2019 Workmanship on Building Sites

    20/28

    InIn--Situ ConcreteSitu Concrete

    Surface FinishSurface FinishFill formwork at a steady rate to allow sufficientFill formwork at a steady rate to allow sufficient

    time for compaction, but avoid cold jointstime for compaction, but avoid cold joints

    between succeeding layersbetween succeeding layers

    Do not permit the vibrator to touch any faces ofDo not permit the vibrator to touch any faces of

    the formworkthe formwork

    Vibrate thoroughlyVibrate thoroughly

    Provide uniformed finish as specifiedProvide uniformed finish as specified

    Avoid contact between the formwork face andAvoid contact between the formwork face and

    the vibratorthe vibrator

  • 8/6/2019 Workmanship on Building Sites

    21/28

    InIn--Situ ConcreteSitu Concrete

    CuringCuringCuring period: 7 days for concrete surfacesCuring period: 7 days for concrete surfaces

    subject to direct wear or abrasionsubject to direct wear or abrasion

    10 days; cure and insulate10 days; cure and insulatesections 300 mm or less in thickness when thesections 300 mm or less in thickness when the

    average air temperature is 7average air temperature is 7oo C or lessC or less

    Curing compound: A oneCuring compound: A one--time application oftime application of

    curing compound at the earliest is deemed tocuring compound at the earliest is deemed to

    satisfy the requirements of this clausesatisfy the requirements of this clause

  • 8/6/2019 Workmanship on Building Sites

    22/28

    FormworkFormwork

    Fix all props and struts vertically and whereFix all props and struts vertically and where

    necessary brace them; provide sole plates andnecessary brace them; provide sole plates and

    seat them firmly throughout their lengthseat them firmly throughout their length

    Seat all supports adequately and securely onSeat all supports adequately and securely on

    their bearingstheir bearings

    Fix stop ends securelyFix stop ends securely

    Align forms correctly and ensure their levelAlign forms correctly and ensure their level

    Reference:Reference: Formwork: Guide to Good PracticeFormwork: Guide to Good Practice

    issued by The Concrete Society, UKissued by The Concrete Society, UK

  • 8/6/2019 Workmanship on Building Sites

    23/28

    FormworkFormwork

    ConstructionConstruction

    Construct formwork to soffits with any preConstruct formwork to soffits with any pre--

    camber necessary to allow for deflection of thecamber necessary to allow for deflection of the

    formwork; any specified preformwork; any specified pre--camber is forcamber is for

    concrete itself. Any preconcrete itself. Any pre--camber to allow forcamber to allow for

    deflections of formwork is in addition to thisdeflections of formwork is in addition to this

    Construct joints in formwork and betweenConstruct joints in formwork and between

    formwork and completed work to prevent loss offormwork and completed work to prevent loss ofgrout. Use foam plastics strip seals, if requiredgrout. Use foam plastics strip seals, if required

    Do not overstress the tie boltsDo not overstress the tie bolts

  • 8/6/2019 Workmanship on Building Sites

    24/28

    FormworkFormwork

    Cleaning and TreatmentCleaning and Treatment

    Before each use of formwork:Before each use of formwork:

    a) clean the contact surfaces and dry thema) clean the contact surfaces and dry them

    before applying a release agentbefore applying a release agentb) ensure the release agent is appropriateb) ensure the release agent is appropriate

    to the surface to be coatedto the surface to be coated

    c) coat formwork surfaces evenly and thinlyc) coat formwork surfaces evenly and thinlywith release agent; treat vertical surfaceswith release agent; treat vertical surfaces

    before horizontal surfaces and wipe off thebefore horizontal surfaces and wipe off the

    excessexcess

  • 8/6/2019 Workmanship on Building Sites

    25/28

    FormworkFormwork Striking TimeStriking Time

    Remove the formwork only when the concreteR

    emove the formwork only when the concretehas developed sufficient strength; the surface ofhas developed sufficient strength; the surface of

    the concrete should not be damaged; thethe concrete should not be damaged; the

    structure itself is not overloaded in relation tostructure itself is not overloaded in relation to

    the strength reached and there is no excessivethe strength reached and there is no excessivedeflection in structural membersdeflection in structural members

    Prop as necessary after striking the formworkProp as necessary after striking the formwork

    The concrete strength is assessed by testingThe concrete strength is assessed by testingcubes prepared for the purpose or by referencecubes prepared for the purpose or by reference

    to Tables ofMinimum Striking Timesto Tables ofMinimum Striking Times

  • 8/6/2019 Workmanship on Building Sites

    26/28

    FormworkFormwork -- Striking TimesStriking TimesType ofType of

    FormworkFormwork

    Minimum PeriodMinimum Period

    Surface Temp ofSurface Temp ofConc above 16Conc above 16oo CC

    before Strikingbefore Striking

    Surface Temp ofSurface Temp ofConc 7Conc 7oo CC

    Vertical formworkVertical formwork

    Columns, Walls,Columns, Walls,BeamsBeams

    12 hours12 hours 24 hours24 hours

    Soffit formwork toSoffit formwork to

    slabsslabs

    4 days4 days 6 days6 days

    Props to slabsProps to slabs 10 days10 days 15 days15 days

    Beams soffitBeams soffit 10 days10 days 15 days15 days

    Props to beamsProps to beams 14 days14 days 21 days21 days

  • 8/6/2019 Workmanship on Building Sites

    27/28

    FormworkFormwork

    Making good after StrikingMaking good after Striking

    Remove fins etc from the surfaceRemove fins etc from the surface

    Fill in tie holes with 1:3 semiFill in tie holes with 1:3 semi--dry mortar welldry mortar well

    rammed in and finished flush with the face oframmed in and finished flush with the face ofthe concrete; fill blow holes exceeding 5 mmthe concrete; fill blow holes exceeding 5 mm

    across with 1:1.5 mortar rubbed inacross with 1:1.5 mortar rubbed in

    Take care on permanently exposed concreteTake care on permanently exposed concrete

    surfaces; if strength and durability cannot besurfaces; if strength and durability cannot be

    assured, agree procedures for repair orassured, agree procedures for repair or

    replacementreplacement

  • 8/6/2019 Workmanship on Building Sites

    28/28

    ReinforcementReinforcement

    While fixing reinforcement, check the type ofWhile fixing reinforcement, check the type of

    steel (Fe 415 / Fe 500) is correct for its locationsteel (Fe 415 / Fe 500) is correct for its location

    Steel properties vary, use of lower qualitySteel properties vary, use of lower quality

    reinforcement could result in structural failurereinforcement could result in structural failure

    Bend reinforcement cold on proper bending m/cBend reinforcement cold on proper bending m/c

    Cut and bend bars in accordance with the ISCut and bend bars in accordance with the IS

    Do not straighten or reDo not straighten or re--bend bars withoutbend bars without

    instructions; if reinforcement temperature isinstructions; if reinforcement temperature isbelow 5below 5oo C obtain instructions before bendingC obtain instructions before bending