PROJECT TITLE: BTMP-B Fire & Gas Integrity Restoration Project. WORK ORDER NO: TBA DATE OF VISIT: 27 th December 2012 PARTICIPANTS: Eugene Joseph – Jr. Engineer (SES) Vincent Bising – E&I Supervisor (SES) PLATFORM INVOLVED: BTMP-B OBJECTIVE: To verify and identify the remaining scope of works from previous campaign. To identify hotwork location for next campaign if any and also to highlight any findings or concerns which were encountered during this site visit. No FINDINGS & RECOMMENDATIONS Acti on Drilling Deck 1 Remaining scope is to carry out like to like replacement of Infra Red Gas Detector QZA0321A/B/C/D/E (4 nos). No more hotwork. To check against scope of work on cable replacements scope whether to use existing cables or new cables. This was highlighted by E&I Supv, Vincent. INFO INFO Production Deck 1 Found out during visit, there are not enough spare MCTs for trunk cables from field JB to enter Control Room. SSB to look into this matter since it might require new MCT to be installed. All trunk cables had been laid from outside of Control Room to its dedicated JBs but pending penetration to Control Room and glanding & termination at field JB sides. SSB PE INFO 1 | Page This spare MCT might be insufficient to accommodate all the Trunk cables coiled near field JB. Pending glanding &

Upload: victor-biacolo

Post on 26-Jan-2016

234 views

Category:

Documents


2 download

DESCRIPTION

Workscoping report

TRANSCRIPT

Page 1: Workscoping Report BARTON FGS

PROJECT TITLE: BTMP-B Fire & Gas Integrity Restoration Project.WORK ORDER NO: TBADATE OF VISIT: 27th December 2012PARTICIPANTS: Eugene Joseph – Jr. Engineer (SES)

Vincent Bising – E&I Supervisor (SES)

PLATFORM INVOLVED: BTMP-B

OBJECTIVE:

To verify and identify the remaining scope of works from previous campaign. To identify hotwork location for next campaign if any and also to highlight any findings or concerns which were encountered during this site visit.

No FINDINGS & RECOMMENDATIONS Action

Drilling Deck1 Remaining scope is to carry out like to like replacement of Infra Red Gas Detector

QZA0321A/B/C/D/E (4 nos). No more hotwork. To check against scope of work on cable replacements scope whether to use existing cables or

new cables. This was highlighted by E&I Supv, Vincent.

INFO

INFO

Production Deck1 Found out during visit, there are not enough spare MCTs for trunk cables from field JB to enter

Control Room. SSB to look into this matter since it might require new MCT to be installed. All trunk cables had been laid from outside of Control Room to its dedicated JBs but pending

penetration to Control Room and glanding & termination at field JB sides.

SSB PE

INFO

1 | P a g e

This spare MCT might be insufficient to accommodate all the new F&G trunk cables.

Trunk cables coiled near field JB. Pending glanding & termination.

Page 2: Workscoping Report BARTON FGS

No FINDINGS & RECOMMENDATIONS Action

Production Deck2 Below are F&G which still pending mounting pole installation & mounting support installation.

Hotwork & welding habitat required:i. QZA3035(T) – Located at Safe Zone

Below are F&G which still pending mounting pole installation but doesn’t require hotwork because the mounting supports were welded during previous campaign:

i. QZA3004ii. QZA3034 – No support required for this detector as the mounting plate will be

mounted directly to an existing pipe support.

INFO

INFO

3 F&G which requires hotwork & welding habitat for cable saddle installation:i. QZA3031 (R) – Located at safe zone

INFO

2 | P a g e

QZA3034 will be mounted on this pipe support.

Mounting pole to be welded on existing I-beam at this location.

Page 3: Workscoping Report BARTON FGS

ii. XZA3003 – Located at safe zoneiii. XZA3008 – Located at safe zoneiv. XZA3017 – Located at zone 2v. XZA3015 – Located at zone 2.

No FINDINGS & RECOMMENDATIONS Action

4 All cables from field JBs to F&G devices are not yet install, lay & pull. All F&G Field JBs were installed during previous campaign. Some existing cable trays/ladder already full. Consider some additional cable tray/ladder

during next campaign.

INFOINFOSSB PE

3 | P a g e

Cable saddle to be welded at this location for XZA3003.

Cable saddle to be welded at this location for XZA3015.

Mounting pole for XZA3015 already welded during previous campaign.

Cable saddle to be welded at this location for XZA3017.

Mounting pole for XZA3017 already welded during previous campaign.

Page 4: Workscoping Report BARTON FGS

No FINDINGS & RECOMMENDATIONS ActionCELLAR DECK

1 Below are F&G Detectors which are still pending mounting pole installation & mounting support installation. Hotwork & welding habitat required:

i. XZA2009 – Safe Zone ii. XZA2010 – Safe Zone

iii. QZA2008 – Safe Zoneiv. QZA2040 – Safe Zone (Also outstanding hotwork for coaming (deck penetration for

cable))v. XZA2015 – Safe Zone

vi. QZA2002 – Safe Zonevii. QZA2001 – Safe Zone

viii. XZA2001 – Safe Zoneix. QZA2003 – Zone 2x. QZA2007 – Zone 2

xi. XZA2002 – Zone 2xii. QZA2006 – Zone 2

xiii. XZA2006 – Zone 2 Below are F&G Detectors which are still pending mounting pole installation but doesn’t

require hotwork because the mounting supports had been welded during previous campaign:i. QZA2032(T)

ii. XZA2004 Layout below show cable trays which are still pending installation (Require both hotwork &

non hotwork). Blue colour show cold work tray installation, red colour shows hotwork tray installation.

For the non hotwork, the cable tray mounting supports had been installed during previous campaign.

INFO

4 | P a g e

Jacket Leg B1

Existing cable tray full.

Page 5: Workscoping Report BARTON FGS

5 | P a g e

END OF REPORT

Tray supports had been installed. Outstanding cable tray installation. Require cold work only.

Outstanding both cable trays & cable tray supports installation. Hotwork required.