world bank documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · mis...

87
Document of The World Bank Report No: ICR00002228 IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-46790 IDA-49490 TF-11094) ON CREDIT IDA-46790 IN THE AMOUNT OF SDR 120 MILLION (US$190 MILLION EQUIVALENT) CREDIT IDA 49490 IN THE AMOUNT OF SDR 47.4 MILLION (US$75 MILLION EQUIVALENT) AND GRANT TF-11094 IN THE AMOUNT OF £6.05 MILLION (US$ 8.0 MILLION EQUIVALENT) TO THE GOVERNMENT OF THE REPUBLIC OF UGANDA FOR A TRANSPORT SECTOR DEVELOPMENT PROJECT June 5, 2017 Transport and ICT Global Practice Africa Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 13-Mar-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

Document of

The World Bank

Report No: ICR00002228

IMPLEMENTATION COMPLETION AND RESULTS REPORT

(IDA-46790 IDA-49490 TF-11094)

ON

CREDIT IDA-46790

IN THE AMOUNT OF SDR 120 MILLION

(US$190 MILLION EQUIVALENT)

CREDIT IDA 49490

IN THE AMOUNT OF SDR 47.4 MILLION

(US$75 MILLION EQUIVALENT)

AND

GRANT TF-11094

IN THE AMOUNT OF £6.05 MILLION

(US$ 8.0 MILLION EQUIVALENT)

TO THE

GOVERNMENT OF THE REPUBLIC OF UGANDA

FOR A

TRANSPORT SECTOR DEVELOPMENT PROJECT

June 5, 2017

Transport and ICT Global Practice

Africa Region

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

CURRENCY EQUIVALENTS

(Exchange Effective Rate December 2015)

Currency Unit = Uganda Schilling (UGX)

US$ 1.00 = UGX 3335

UK£ 1.00 = US$ 1.48

US$ 1.00 = SDR 0.6307

FISCAL YEAR

July 1 – June 30

ABBREVIATIONS AND ACRONYMS

AF Additional Financing

AfDB African Development Bank

APL Adaptable Program Loan

BRT Bus Rapid Transit

CAS Country Assistance Strategy

DANIDA Danish International Development Agency

DBST Double Bituminous Surface Treatment

DFID U.K. Department for International Development

DRC Democratic Republic of Congo

DRS Department of Road Safety

DP Development Partner

DUCAR District, Urban, and Community Access Roads

EAC East African Community

EC European Commission

EIA Environmental Impact Assessment

EIRR Economic Internal Rate of Return

ESIA Environmental and Social Impact Assessment

ESMP Environmental and Social Management Plan

GDP Gross Domestic Product

GIS Geographic Information System

GKMA Greater Kampala Metropolitan Area

GoU Government of Uganda

GRC Grievance Redress Committee

HDM-4 Highway Development and Management Model, version 4

ICR Implementation Completion and Results Report

IDA International Development Association

ISR Implementation Status and Results Report

JICA Japan International Cooperation Agency

KCCA Kampala Capital City Authority

Page 3: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

M&E Monitoring and Evaluation

MATA Metropolitan Area Transport Authority

MIS Management Information System

MoFPED Ministry of Finance, Planning, and Economic Development

MoWT Ministry of Works and Transport

MTR Midterm Review

MTRA Multi-sector Transport Regulatory Authority

NEMA National Environmental Management Authority

NERAMP North Eastern Road Corridor Asset Management Project

NGO Nongovernmental Organization

NPV Net Present Value

NRSC National Road Safety Council

NRSA National Road Safety Authority

NTPS National Transport Policy and Strategy

OPRC Output-and Performance-based Road Contract

PAD Project Appraisal Document

PAP Project-Affected Person

PDO Project Development Objective

PDU Procurement and Disposal Unit (UNRA)

PIU Project Implementation Unit

PPIAF Public-private Infrastructure Advisory Facility Trust Fund

RAP Resettlement Action Plan

RCDS Road Crash Database

RMS Road Management System

RSDP Road Sector Development Program

SIL Specific Investment Loan

TMT Top Management Team

TSDP Transport Sector Development Project

TSDMS Transport Sector Data Management System

UNRA Uganda National Roads Authority

URF Uganda Road Fund

URURA Urban and Rural Roads Authority

Senior Global Practice Director: Jose Luis Irigoyen

Practice Manager: Aurelio Menendez

Project Team Leader: Negede Lewi

ICR Team Leader: Richard Martin Humphreys/Stephen Muzira

ICR Author: Peter Freeman

Page 4: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

UGANDA

Transport Sector Development Project

CONTENTS

Data Sheet A. Basic Information .................................................................................................................. i

B. Key Dates ............................................................................................................................... i C. Ratings Summary ................................................................................................................... i D. Sector and Theme Codes ...................................................................................................... ii E. Bank Staff ............................................................................................................................ iii

F. Results Framework Analysis ................................................................................................ iii G. Ratings of Project Performance in ISRs ............................................................................ viii

H. Restructuring (if any) ........................................................................................................... ix 1. Project Context, Development Objectives and Design ......................................................... 1 2. Key Factors Affecting Implementation and Outcomes ......................................................... 7

3. Assessment of Outcomes ..................................................................................................... 16 5. Assessment of Bank and Borrower Performance ................................................................ 24

7. Comments on Issues Raised by Borrow/Implementing Agencies/Partners ........................ 33 Annex 1. Project Costs and Financing .................................................................................... 34 Annex 2a. TSDP Outputs by Component ................................................................................ 35 Annex 2b. Operational Risk Assessment Framework ............................................................. 41 Annex 3. Economic and Financial Analysis ............................................................................ 47 Annex 4. Bank Lending and Implementation Support/Supervision Processes ....................... 53

Annex 5. Summary of Borrower's ICR and/or Comments on Draft ICR ................................ 55

Annex 6. List of Supporting Documents ................................................................................. 71 MAP ........................................................................................................................................ 73

Page 5: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

i

A. Basic Information

Country: Uganda Project Name:

UGANDA

TRANSPORT

SECTOR

DEVELOPMENT

PROJECT

Project ID: P092837 L/C/TF Number(s): IDA-46790, IDA-

49490, TF-11094

ICR Date: 6/5/2017 ICR Type: Core ICR

Lending Instrument: Specific Investment

Loan Borrower:

GOVERNMENT OF

UGANDA

Original Total

Commitment: XDR 120.00 million Disbursed Amount: XDR 106.96 million

Revised Amount: XDR 106.96 million

Environmental Category: B

Implementing Agencies:

Uganda National Roads Authority (UNRA)

Co-financiers and Other External Partners: United Kingdom Department for International Development; Japanese International

Cooperation Agency

B. Key Dates

Process Date Process Original Date Revised / Actual

Date(s)

Concept Review: 02/05/2008 Effectiveness: 08/05/2010 07/15/2010

Appraisal: 09/30/2009 Restructuring(s): 06/16/2011

05/31/2013

Approval: 12/10/2009 Midterm Review: 06/10/2012 05/10/2013

Closing: 06/30/2014 01/31/2016

C. Ratings Summary

C.1 Performance Rating by ICR

Outcomes: Unsatisfactory

Risk to Development Outcome: Substantial

Bank Performance: Unsatisfactory

Borrower Performance: Unsatisfactory

Page 6: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

ii

C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)

Bank Ratings Borrower Ratings

Quality at Entry: Unsatisfactory Government: Unsatisfactory

Quality of Supervision: Unsatisfactory Implementing

Agency/Agencies: Unsatisfactory

Overall Bank

Performance: Unsatisfactory

Overall Borrower

Performance: Unsatisfactory

C.3 Quality at Entry and Implementation Performance Indicators

Implementation

Performance Indicators

QAG Assessments

(if any) Rating

Potential Problem

Project at any time

(Yes/No):

No Quality at Entry

(QEA): None

Problem Project at any

time (Yes/No): Yes

Quality of

Supervision (QSA): None

DO rating before

Closing/Inactive status: Unsatisfactory

D. Sector and Theme Codes

Original Actual

Major Sector/Sector

Public Administration

Public administration - Transportation 11 11

Transportation

Roads and highways 89 89

Major Theme/Theme/Sub Theme

Economic Policy

Trade 4 4

Trade Facilitation 4 4

Private Sector Development

ICT 14 14

ICT Solutions 14 14

Urban and Rural Development

Rural Development 45 45

Rural Infrastructure and service delivery 45 45

Urban Development 37 37

Urban Infrastructure and Service Delivery 37 37

Page 7: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

iii

E. Bank Staff

Positions At ICR At Approval

Vice President: Makhtar Diop Obiageli Katryn Ezekwesili

Country Director: Diarietou Gaye John McIntire

Practice

Manager/Manager: Aurelio Menendez C. Sanjivi Rajasingham

Project Team Leader: Negede Lewi Dieter E. Schelling

ICR Team Leader: Richard Martin

Humphreys/Stephen Muzira

ICR Primary Author: Peter Nigel Freeman

F. Results Framework Analysis

Project Development Objectives (from Project Appraisal Document) The project development objective is to improve the connectivity and efficiency of the transport

sector through: (i) improved condition of national road network; (ii) improved capacity for road

safety management; and (iii) improved transport sector and national road management.

Revised Project Development Objectives (as approved by original approving authority) Not applicable.

(a) PDO Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target

Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1:

Average vehicle operating costs (US$ per vehicle-km) reduced on the Gulu-

Atiak and Vurra-Oraba roads.

Value

quantitative or

qualitative)

US$0.352

US$0.224

US$0.224

Date achieved 07/15/2010 06/30/2014 01/31/2016

Comments

(including %

achievement)

Fully achieved by 2014. Data based on Highway Development and Management

Model, version 4 manual (HDM-4). Note: Kamwenge-Fort Portal added at AF.

Indicator 2:

Travel time on Gulu-Atiak and Vurra-Oraba roads reduced from 2 hours (2009)

to 1 hour (2014).

Value

quantitative or

qualitative)

2 hours

1 hour

1 hour

Page 8: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

iv

Date achieved 07/15/2010 06/30/2014 01/31/2016

Comments

(including %

achievement)

Fully achieved by 2014. Data based on survey by UNRA Directorate of

Planning

Indicator 3: National roads in poor condition reduced from 36% to 15%

Value

quantitative or

qualitative)

36%

15%

22%

Date achieved 07/15/2010 06/30/2014 01/31/2016

Comments

(including %

achievement)

Not achieved; target of 15% not reached. Indicator was reworded at AF

“Roads in good and fair condition as a share of total classified roads (percent)”

Indicator 4:

Access of rural population to all season roads in the target areas increased from

64% to 90%

Value

quantitative or

qualitative)

64%

90%

84%

Date achieved 07/15/2010 12/31/2014 01/31/2016

Comments

(including %

achievement)

Partially achieved. Some 4.95 million people to be provided with access to an

all-season access road. The final beneficiary estimate was 4.17 million. This

indicator was reworded at AF to “Share of rural population with access to an all-

season road (percent)”

Indicator 5:

Annual rate of growth of road accident fatalities declines after the National Road

Safety Agency (NRSA) becomes operational

Value

quantitative or

qualitative)

7%

Less than 7%

4%

-3.2%

Date achieved 07/15/2010 12/31/2014 05/14/2011 01/31/2016

Comments

including %

achievement

Though technically achieved, this was not due to the project. The NRSA was

turned down by the Cabinet. Road safety campaigns by the police were likely

responsible for the decline in road fatalities. Indicator was changed at AF to

“Annual rate of road accident fatalities (7 percent)”

Page 9: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

v

(b) Intermediate Outcome Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target

Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1: Km of road rehabilitated/upgraded

Value

quantitative or

qualitative)

0 km

159 km

225 km

166 km

Date achieved 07/15/2010 12/31/2014 05/14/2011 01/31/2016

Comments

(including %

achievement)

Not achieved at closure. Original target of 159 km exceeded with additional 7

km of road through Arua town. However, works on the 66 km Kamwenge to

Fort Portal road only 49% complete when the Credit was cancelled. Since then

the road has been completed and the target met, using Government of Uganda

funding.

Indicator 2: National Road Safety Authority (NRSA) created and operational

Value

quantitative or

qualitative)

Road Safety managed by

Government Department

NRSA established

and operational

NRSA creation

turned down by

Cabinet

Date achieved 07/15/2010 12/31/2014 01/31/2016

Comments

(including %

achievement)

Not achieved. Although the road safety policy statement was agreed, Cabinet

turned down the creation of NRSA in November 2014 due to insufficient

information.

Indicator 3: Crash database established and operational

Value

quantitative or

qualitative)

Crash database not yet

established

Database

established and

fully operational

Database

established

Date achieved 07/15/2010 12/31/2014 01/31/2016

Comments

(including %

achievement)

Achieved. Database established, made functional and tested in the pilot regions.

Data collected from other regions still to be put in system manually

Indicator 4:

Detailed design and bidding documents for phase 1 bus rapid transit system

prepared

Value

quantitative or

qualitative)

Design and bidding

documents not prepared

Documents

completed and

approved

Documents

completed and

approved

Page 10: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

vi

Date achieved 07/15/2010 12/31/2014 01/31/2016

Comments

(including %

achievement)

Achieved. Designs and reports approved by a technical committee and by

stakeholders at a workshop.

Indicator 5: Framework for Metropolitan Area Transport Authority (MATA) prepared

Value

quantitative or

qualitative)

No framework in place

Framework

drafted and

approved

Framework drafted,

but not yet

approved

Date achieved 07/15/2010 12/31/2014 01/31/2016

Comments

(including %

achievement)

Partially achieved. Framework drafted and received financial clearance, but yet

to be approved by Cabinet.

Indicator 6: Transport Policy Updated

Value

quantitative or

qualitative)

Policy not updated

Policy updated

and approved

Policy drafted, but

not yet approved

Date achieved 07/15/2010 12/31/2014 01/31/2016

Comments

(including %

achievement)

Partially achieved. Revised policy drafted and amended, but financial clearance

requested before presentation to the Cabinet.

Indicator 7: Traffic and Road Safety Act Legal framework updated

Value

quantitative or

qualitative)

Legal framework not

updated

Legal framework

amendment agreed

by management

Legal framework

drafted, but yet to

be legislated

Date achieved 07/15/2010 12/31/2014 01/31/2016

Comments

(including %

achievement)

Partially achieved. Work done by consultant deemed unsatisfactory and

amendment drafted in-house.

Indicator 8: Transport Sector Data Management System (TSDMS) established

Value

quantitative or

qualitative)

No TSDMS

TDMS established

TDMS established

and operational

Date achieved 07/15/2010 12/31/2014 01/31/2016

Page 11: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

vii

Comments

(including %

achievement)

Achieved. System is operational and Ministry now produces an Annual Sector

Performance Review

Indicator 9:

Multisector Transport Regulatory Authority (MTRA) established

Value

quantitative or

qualitative)

No MTRA

MTRA established

and functioning

Cabinet did not

approve

Date achieved 07/15/2010 12/31/2014 01/31/2016

Comments

(including %

achievement)

Not achieved. The draft Bill was not approved. The Cabinet was reluctant to

create new institutions and MoWT determined it would only prioritize the

establishment of NRSA and MATA

Indicator 10: District, Urban and Community Access Roads (DUCAR) agency established

Value

quantitative or

qualitative)

No DUCAR agency

DUCAR agency

established and

operational

DUCAR not

established

Date achieved 07/15/2010 12/31/2014 01/31/2016

Comments

(including %

achievement)

Not achieved. Despite agreement from stakeholders in districts, municipalities

and town councils, the request to clear the financial implications of the agency

has not been responded to and it has not been submitted to Cabinet.

Indicator 11: UNRA share of administrative costs as part of overall budget is less than 5%

Value

quantitative or

qualitative)

Not available

less than 5%

Less than 5 percent

Date achieved 07/15/2010 12/31/2014 01/31/2016

Comments

(including %

achievement)

Achieved. After the restructuring of UNRA by the Board, Ministry of Finance,

Planning and Economic Development accepted an increase in the wage

bill starting July 2015

Indicator 12:

UNRA Management Information System (MIS) established including red flag

system

Value

quantitative or

qualitative)

No system

System in place

System in place

Date achieved 07/15/2010 12/31/2014 01/31/2016

Page 12: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

viii

Comments

(including %

achievement)

Partially achieved. A Contract Management System is in place, but not yet fully

functional. A review to improve functionality is ongoing.

Indicator 13: Average time deviation from procurement plan

Value

quantitative or

qualitative)

Not done

Less than 10%

Not available

Date achieved 07/15/2010 12/31/2014 01/31/2016

Comments

(including %

achievement)

Not achieved. UNRA could not provide this information, due to the

restructuring of the institution.

Indicator 14: Annual Customer Satisfaction Survey to be instituted

Value

quantitative or

qualitative)

Not done

Done

Done

Date achieved 07/15/2010 12/31/2014 01/31/2016

Comments

(including %

achievement)

Achieved. Carried out by the Uganda Road Fund

Indicator 15: Capacity (number of staff) of Internal Audit Unit of UNRA increased to carry

out technical audits

Value

quantitative or

qualitative)

6

14

7

Date achieved 07/15/2010 12/31/2014 01/31/2016

Comments

(including %

achievement)

This indicator was added when the AF was approved. It was not achieved during

the life of the project.

G. Ratings of Project Performance in ISRs

No. Date ISR

Archived DO IP

Actual

Disbursements

(US$, millions)

1 04/30/2010 Satisfactory Satisfactory 0.00

2 12/12/2010 Satisfactory Satisfactory 0.00

3 07/27/2011 Satisfactory Moderately Satisfactory 4.00

4 02/05/2012 Satisfactory Moderately Satisfactory 10.09

5 07/07/2012 Satisfactory Moderately Satisfactory 31.93

6 01/03/2013 Satisfactory Moderately Satisfactory 31.93

Page 13: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

ix

7 07/21/2013 Moderately Satisfactory Moderately

Unsatisfactory 67.53

8 01/28/2014 Moderately Satisfactory Moderately

Unsatisfactory 100.57

9 08/04/2014 Moderately

Unsatisfactory Unsatisfactory 113.09

10 02/24/2015 Moderately Satisfactory Moderately

Unsatisfactory 123.25

11 08/17/2015 Moderately Satisfactory Moderately

Unsatisfactory 175.92

12 02/18/2016 Unsatisfactory Unsatisfactory 175.92

H. Restructuring (if any)

Restructuring

Date(s)

Board

Approved

PDO Change

ISR Ratings at

Restructuring

Amount

Disbursed at

Restructuring

in US$,

millions

Reason for Restructuring &

Key Changes Made DO IP

06/16/2011 S MS 4.00

Additional Financing: Inclusion

of Kamwenge - Fort Portal

Road, strengthening of UNRA

Internal Audit Unit and

extension of closing date by one

year to 01/31/2016.

05/31/2013 S MS 44.27 Reallocation of amounts

I. Disbursement Profile

Page 14: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

x

Page 15: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

1

This Implementation Completion and Results Report (ICR) for the Uganda Transport Sector

Development Project has a unique significance in that it highlights issues where an overly

complex project was designed in a manner that was incompatible with the available capacity in

Government. The project was restructured, and additional finance provided, to add a road

section that was not initially identified as challenging from a safeguards point of view, despite

the fact that it presaged a considerable influx of labor to a poor rural area, where there were

also some systemic social issues, without any attempt to appropriately manage the adverse

impacts on the affected communities. This resulted in a complaint to the Inspection Panel and

acknowledgement by World Bank management that there were serious weaknesses in the

preparation, implementation and supervision of the project. The contractor failed to rectify

shortcomings on a range of issues that impacted the communities, and the World Bank first

suspended disbursements and then took the exceptional step of cancelling the Credits. Following

these events, the World Bank carefully reviewed its entire portfolio of similar projects, the way it

considers environmental and social issues in project design and implementation, and its

Standard Bidding Documents to improve environmental and social provisions in contracts for

both civil contractors and supervising engineers. It also issued guidelines for staff on managing

the risks of adverse impacts on communities from a temporary project-induced influx of labor.

Particular attention has been given in this ICR to the lessons learned from these events.

1. Project Context, Development Objectives and Design

1.1 Country Context

1. Uganda is a landlocked country in East Africa bordered by the Democratic Republic of

Congo (DRC), Kenya, Rwanda, South Sudan, and Tanzania. It has a rapidly growing population

of 34.6 million people, with 55 percent under 18 years of age.1 Uganda is classified as a low-

income country and in 2015 had a gross domestic product (GDP) per capita of US$670.2

However, the country has substantial natural resources, including fertile soils, regular rainfall

and sizeable mineral deposits of copper and cobalt. More recently, reserves of both crude oil and

natural gas have been discovered. Coffee is an important export commodity, but over 80 percent

of the population live in rural areas and are reliant on subsistence agriculture.

2. Following independence from Britain in 1962, Uganda sporadically experienced unrest

and conflict. Corruption and human rights issues have also caused concern among development

partners (DPs), and this has hampered the investment climate. On the other hand, the United

Nations Refugee Agency reported that in 2015 Uganda was hosting over half a million refugees

mostly from South Sudan, Burundi and the DRC. It recognized that Uganda has a progressive

policy toward such people, providing land, protection and the right to be employed or run a

business.3

3. Beginning around 2009, exogenous shocks, including the global economic crisis and

surges in international commodity prices, negatively affected the country’s growth rate. Other

1 Uganda Bureau of Statistics, 2016, Census 2014 Final Results.

2 World Bank data

3 United Nations Refugee Agency, 2005, Uganda Hosts Record 500,000 Refugees and Asylum Seekers. (Accessed

September 7, 2016), www.unhcr.org

Page 16: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

2

issues reinforced this situation—primarily a lower export performance, adverse weather

conditions, declining development aid, as well as high inflation. A subsequent tightening of

monetary policy reduced GDP growth to 3.4 percent in 2012, down from the 7 to 8 percent range

in 2008 and the earlier years in the decade.4 Nevertheless, Uganda was able to surpass the 2015

Millennium Development Goal of halving the poverty rate.5 The share of the population living

below the poverty line declined from 35 percent in 2001 to 22 percent by 2013. This trend has

been attributed in part to a diversification of economic activity away from an over-reliance on

farm activities in favor of nonfarm household enterprises.6

1.2 Sector Context

4. In Uganda, road transport is the dominant mode and plays a pivotal role in supporting the

economic and social development of the country. Road transport carries over 90 percent of the

country’s passenger and freight traffic and provides the only means of access for much of the

rural population. The road infrastructure also serves the primary mode on the key transit corridor

linking Uganda and the neighboring land-locked countries, to the Indian Ocean port of Mombasa

in Kenya. The classified road network length is about 66,000 km and consists of 21,000 km of

national, 32,000 km of district and 13,000 km of urban roads, while the community access road

network is estimated to be in the order of 85,000 km. Other modes of transport are a railway

system with a network of 1,260 km of track, (of which only 320 km are functioning), water

transport—mainly wagon and stage ferries on Lake Victoria and the Nile River - and air

transport facilities, including an international airport at Entebbe, and 13 domestic air fields.7

5. National roads, of which 3,490 km are paved, connect districts and cities with one

another and with neighboring countries. These roads account for only 30 percent of the network,

but carry 80 percent of the total road traffic. The Uganda National Roads Authority (UNRA)

created in 2008 is responsible for managing the national road network. District roads provide

access from rural areas to markets, health centers, educational institutions, administrative centers

and other services and are managed by district governments, while local governments manage

urban roads and sub-county local governments manage community roads. An Act of Parliament

established the Uganda Road Fund (URF) in 2008 with the objective of financing routine and

periodic maintenance of public roads in Uganda mainly from road user charges. The URF

became operational in 2010. It was intended to have been a second-generation road fund, but still

receives its funds from the Ministry of Finance, Planning and Economic Development

(MoFPED) and is subject to budgetary fluctuations and political priorities.4

1.3 National Transport Policy and Strategy

6. The National Transport Policy and Strategy (NTPS), adopted in 2002, promotes less

4 Uganda Economic Update: Bridges Across Borders – Unleashing Uganda’s regional trade Potential, February

2013 – First Edition, World Bank 5 The Millennium Development Goals (MDGs) were the world’s time bound and quantified targets for addressing

extreme poverty in its many dimensions 6 Poverty head count ratio at national poverty line (% of population). Source: Uganda Bureau of Statistics. Estimates

are consistent with the World Bank’s Global Poverty Working Group data. 7 Ministry of Works and Transport.2015, Annual Sector Performance Report Financial Year 2014/15

4 A second-generation road fund is financed by fuel levies and other user charges and is managed by a board

representing the interests of the road users.

Page 17: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

3

costly, efficient, and reliable transport services. To carry out this strategy, the Government of

Uganda (GoU) has received substantial support from its DPs. The first 10-year Road Sector

Development Program (RSDP) Phase 1 covered the period from FY 1996/97 to 2005/06. In April

2002, the RSDP was updated and rolled over for a further 10 years as RSDP Phase 2 (FY2001/02

to FY2010/11) at an estimated cost of US$2.3 billion. District roads were included for the first

time. Based on the lessons learned from implementation of the first two phases, the GoU then

developed RSDP Phase 3, including some urban roads. To adequately respond to the growing

transport demand, provide support for national economic development, and expand competitive

regional trade, RSDP Phase 3 prioritized the rehabilitation and maintenance of the major road

corridors. The volume of trade with neighboring states was and still is rapidly increasing,

especially trade with South Sudan. This strategy was also intended to address infrastructure

bottlenecks and non-physical trade barriers (such as border controls) that hampered the smooth

flow of traffic for both people and goods. The planned investment requirement for RSDP Phase 3

was US$10.36 billion over the 10-year period from FY 2009/10 to 2018/19.5

7. The Bank has supported transport projects such as RSDP Phase 1 in Uganda since the

early nineties. RSDP Phase 2 was still active when the Transport Sector Development Project

(TSDP) was appraised. Adaptable Program Loans (APLs) had been implemented under the

previous road projects as part of RSDP Phases 1 and 2. However, the World Bank proposed a

Specific Investment Loan (SIL) rather than an APL for the TSDP. This was mainly because of

difficulties in predicting the timetable and costs of APLs over a long investment period. By using

a SIL with a short-term focus, results were expected to be better defined and achievable within a

shorter time period.

8. At appraisal of the TSDP, Uganda was receiving finance for all sectors from more than

40 bilateral and multilateral organizations, which made it difficult for the Government to engage

with all of them effectively. The project approval occurred during a time when several financiers

were seeking ways to improve donor harmonization, based on a sector wide approach. The

Transport Sector Framework was the result of a joint institutional support initiative prepared

inter alia between the GoU, the European Commission (EC), the United Kingdom Department

for International Development (DFID), the Danish International Development Agency

(DANIDA) and the World Bank (see Annex 2, Table 2.1). The GoU through an annual Joint

Transport Sector Review coordinated the mostly parallel funding from the DPs. This was based

on a Uganda Joint Assistance Strategy encompassing issues such as better economic

management, removal of infrastructure bottlenecks, and improved governance and human

resource development.

9. According to a stakeholder survey of the effectiveness of this sector approach, the

greatest benefits were perceived as sound economic advice and delivery of financial resources.

However, some responders criticized the approach for theoretical solutions that disregarded

political realities. In addition, a review funded by DFID found that although the strategy was

well intended, in retrospect it was neither a necessary nor sufficient condition for more effective

aid and concluded that transaction costs were not reduced because lenders and donors had

5 UNRA. 2012. Preparation of Third Phase of Road Sector Development Program, Kagga and Mott Macdonald.

Page 18: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

4

different agendas and rules.6 Consequently, though endorsing continued efforts to harmonize,

IDA returned to its earlier model of the Country Assistance Strategy (CAS) and prepared a CAS

for 2011-2015 covering all World Bank support, which had as a strategic objective “enhancing

public infrastructure.” For the road sector, this included strengthening the impact of the roads

budget. A public expenditure review made detailed recommendations in relation to national

roads with respect to land issues as well as procurement; monitoring and evaluation (M&E); and

absorption capacity. Whilst these factors were taken into account in preparing the TSDP, some of

the mitigation measures proved inadequate.

1.4 Project Development Objectives (PDO) and Key Indicators

10. The PDO in both the original Financing Agreement and the Project Appraisal Document

(PAD) was to improve the connectivity and efficiency of the transport sector through (i)

improved condition of the national road network; (ii) improved capacity for road safety

management; and (iii) improved transport sector and national road management.

11. The original PDO indicators included the following:

Average vehicle operating costs on the Gulu-Atiak and Vurra-Oraba roads to reduce

from US$0.352 per vehicle-km in 2009 to US$0.224 per vehicle-km in 2014;

Travel time on the Gulu-Atiak and Vurra-Oraba roads to reduce from two hours

2009) to one hour (2014);

National roads in poor condition to reduce from 36 percent in FY2009/10 to 15

percent in FY2013/14;

Access of the rural population to all-season roads in the target area to increase from

64 percent to 90 percent; and

Annual rate of growth of road accident fatalities to decline after the National Road

Safety Authority (NRSA) becomes operational.

1.5 Revised PDO and Key Indicators, and reasons/justification

12. The PDO remained unchanged throughout the life of the Project, but the Results

Framework was modified as follows:

The Kamwenge-Fort Portal road was added to the indicators of reductions in vehicle

operating costs and travel time with the same target values; and

A new indicator was added in respect of the capacity of the Internal Audit Unit in

UNRA to enable it to carry out technical audits. The staffing target was 14 persons

against a baseline of 6 persons.

1.6 Main Beneficiaries

13. The entire population of Uganda was expected to benefit indirectly from the project—

especially the policy, institutional and safety aspects—but national road users and communities

6 DFID. 2009. Review of the Uganda Joint Assistance Strategy - Current and Future Prospects by the Overseas

Development Institute, London and the Centre for Performance Management, Kampala.

Page 19: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

5

living near the roads selected for improvement were the direct beneficiaries. More specifically,

both local and long distance users would have improved access to markets and services and

transport would be facilitated to and from neighboring states to the north and west of Uganda.

Policy and institutional reforms were intended to lead to better integration and efficiency for a

number of Government departments and authorities especially UNRA, the Ministry of Works

and Transport (MoWT) including the Department of Road Safety, and affected local authorities,

including the Kampala Capital City Authority (KCCA).7

1.7 Original Components

14. The five original components were financed by means of an International Development

Association (IDA) Credit (4679-UG) of US$190 million equivalent, and DFID-recipient

executed Trust Fund grant (TF11094) of UK£ 6.05 million, US$8.0 million equivalent, that

contributed to some of the road safety and institutional subcomponents.

Component A: Road Investments: Upgrading and Rehabilitation of National Roads (IDA

financing US$162. 1 million)

15. This component was to be executed by UNRA. The component was to finance the paving

of the Gulu to Atiak and Vurra-Arua-Oraba roads (approximately 160 km), linking northern

Uganda with southern Sudan (now South Sudan) and northeastern DRC. Component A also

included the preparation of design and bidding documents for the reconstruction of the Tororo to

Soroti road (151 km) and the Lira-Kamdini-Gulu roads (148 km), in preparation for future

financing. This would help ensure that the entire northern corridor from Kenya to the South

Sudan and DRC borders would eventually be paved and in good condition.

Component B: Enhanced Road Safety: (IDA financing US$3.5 million, DFID US$1.0

million)

16. This component was to provide funding for the establishment and start-up funding of the

National Road Safety Authority (NRSA). MoWT was to execute this component, and a special

Stakeholder Committee was to be put in place to oversee its implementation. The project design

envisaged a consultant financed by the Global Road Safety Facility being employed from

October 2009 to January 2010 to prepare a draft road safety policy and strategy and a draft law

for the creation of the NRSA in consultation with stakeholders. It had been agreed with the GoU

that the creation of the NRSA was a priority and Government would endeavor to make it

operational at the beginning of FY20l1/12. NRSA was to be funded by the Road Fund (about

US$2 million per annum was envisaged). The component was also to provide financing for

making a police crash database operational.

Component C: Urban Transport Planning: Preparation of a Kampala Urban Transport

Project (IDA financing US$4.5 million)

17. MoWT was to implement this component, and a specific stakeholder committee was to

be put in place to oversee its implementation. The Public-Private Infrastructure Advisory Facility

7 KCCA came into force on the March 1, 2011, by the Kampala Capital City Act 2010. It is supervised by the

Central Government.

Page 20: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

6

Trust Fund, administered by the World Bank, had approved an allocation of US$267,000 to

finance a pre-feasibility study for the establishment of a Bus Rapid Transit (BRT) system in the

Greater Kampala Metropolitan Area (GKMA). The study was to commence in November 2009

and was scheduled for completion in March 2010. The pre-feasibility study was intended to

prepare design and bidding documents for the BRT infrastructure in the selected corridor in

GKMA, as well as draft bidding documents for the bus operators, fare collectors, fund managers,

system financial models, the central business district traffic management and parking studies, a

bicycle path master plan, and draft legislation and support for a Metropolitan Area Transport

Authority (MATA).

Component D: Institutional Support (Government): Support to Ministry of Works and

Transport (IDA financing US$7.9 million, DFID US$3.0 million)

18. This component was to assist MoWT to focus on its core functions namely policy setting,

strategic planning, sector oversight and monitoring, and to spin off some of its responsibilities to

the newly created entities under its umbrella. There were four sub-components: (i) strengthening

of the policy and planning division through updating of the sector policy, review of the sector

legal framework and introduction of a Transport Sector Data Management System (TSDMS); (ii)

assistance to create the proposed Multi-sector Transport Regulatory Authority (MTRA); (iii)

assistance for the transformation of the management of district, urban and community access

roads (DUCAR) into an Agency; and (iv) other support through, technical assistance, equipment,

training and financing operating costs.

Component E: Institutional Support (UNRA): Support to Uganda National Roads

Authority (IDA financing US$12.0 million, DFID US$4.0 million)

19. This component included: (i) the improvements/refurbishment of regional offices of

UNRA; (ii) provision of additional technical assistance to the one provided under EC financing;

(iii) financing of various studies needed by UNRA to enhance its performance; (iv) provision of

training; (v) provision of office equipment and supervision vehicles; and (vi) financing of

incidental operating costs because of UNRA acting as the Project Implementation Unit of TSDP.

1.9 Revised Components

20. Additional financing. On June 16, 2011, less than a year after the effectiveness of the

original Credit and with an appropriate waiver from Bank management8 dated November 19,

2010, the Board approved a further IDA Credit (4949–UG) in the equivalent amount of US$75

million.9 This Additional Financing (AF) was primarily to cover the upgrading of the Kamwenge

to Fort Portal road (66 km) from gravel to bituminous standard. This would extend the length of

road improved under the project to 225 km. The request from the GoU to include the road in the

TSDP was received too late to allow the road to be included in the original appraisal because

there was insufficient time to undertake the necessary due diligence of its technical design and

safeguards related work. Additional provision was made in the Additional Financing to

strengthen the internal audit functions of UNRA to undertake technical audits of road projects,

8 A waiver was required from the Regional Vice President to proceed with the Additional Financing under

Operational Policy 13.20, as the TSDP had been under implementation for less than 12 months. 9 The Credit was denominated in SDR for an amount of 47.4 million.

Page 21: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

7

and the closing date for the project was extended by one year to January 31, 2016 (see Table 1

below).

Project Component Original Cost Revised Cost at AF

IDA DFID TOTAL IDA DFID TOTAL

A: Road Investments 162.1 0.0 162.1 235.1 0.0 235.1

B: Road Safety 3.5 1.0 4.5 3.5 1.0 4.5

C: Urban Transport Planning 4.5 0.0 4.5 4.5 0.0 4.5

D: Institutional Support – Government 7.9 3.0 10.9 7.9 3.0 10.9

E: Institutional Support- UNRA 12.0 4.0 16.0 14.0 4.0 18.0

TOTAL 190.0 8.0 198.0 265.0 8.0 273.0

Note: The African Development Bank (AfDB) had earlier separately funded the preparation of Environmental and

Social Assessments, Resettlement Action Plans (RAPs) for the Kamwenge to Fort Portal road. The road designs for

the Gulu-Atiak and Vurra-Oraba roads were financed under an earlier Bank financed operation (RDPP3). It was also

involved through parallel financing in another section of the Ibanda-Fort Portal road. During implementation, the

Japan International Cooperation Agency (JICA) financed a condition survey of district and community access roads.

The World Bank diverted funds in 2015 to complete this initiative under component D when the amount made

available to the GoU by JICA was found to be insufficient.

1.10 Other significant changes

21. The project had a second restructuring on May 31, 2013, to reallocate amounts between

the Credit and Grant Agreements (see further details in paragraph 25).

22. On October 22, 2015, the Bank suspended disbursements under the Project due to the

Borrower’s non-compliance with its obligation to implement the Project in conformity with

environmental and social standards and practices, and on December 21, 2015, the Bank cancelled

the Project. See paragraphs 31–37 for more details.

2. Key Factors Affecting Implementation and Outcomes

2.1 Project Preparation and Risk Assessment

23. Project preparation was largely based on previous projects and although concern was

expressed about the capacity of UNRA, the Bank team was confident that new staff would be

recruited to tackle the rapidly increasing workload. No cap on recruitment by the GoU was

foreseen. The PAD remarked on the weaknesses of technical assistance in the past and how there

had been some waste of resources due to a lack of capacity in Government. It is therefore

surprising that this project was designed with four new authorities to be established.10

The PAD

also indicated that there had been problems previously with reforms taking more time than had

been anticipated, but there was no plan to mitigate this. Project design was overly complex with

too many sub-components. The level of commitment to such major reform was relatively

untested. The capacity to ensure environmental and social safeguard compliance was not even

10

These included the Multi-Sectoral Transport Regulatory Agency (MTRA), the Metropolitan Area Transport

Authority (MATA), the National Road Safety Agency (NRSA), and the District, Urban and Community Road

Agency (DUCAR.

Page 22: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

8

discussed. The resources provided to prepare the project were unreflective of the systemic risks.

24. The original risk assessment for the TSDP is summarized in Table 2. Among the lessons

learned from the implementation experience of earlier road projects in Uganda was the need to

have measurable outputs in a specified time period. This related to both technical assistances for

building local capacity and benchmarks for effecting policy and institutional reforms.11

In

general, capacity constraints were inadequately assessed and the overall rating of moderate was

an understatement.

Table 2. Risks and Mitigations Measures at Appraisal: Transport Sector Development Project

Risks Risk Mitigation Measures Risk Rating

with

Mitigation To Project Development Objectives

The URF does not provide a

consistent flow of finance for

road maintenance

Substantial technical assistance has been put in place for URF

under joint institutional support framework. The GoU Policy

Letter states that transfers will be made in accordance with the

law.

Low

UNRA has constrained

implementing capacity

UNRA is recruiting additional staff. Gaps have been identified

and a substantial technical assistance program will lessen the risk Moderate

To Component Results

Slow progress in phasing out

force account execution of works

Current force account constitutes only 10 percent of UNRA’s

overall maintenance expenditures and UNRA plans to reduce this

further to 5 percent by 2013–14

Low

Governance risks due to

corruption in the road sector

A Governance and Accountability Action Plan has been agreed

supported by a ‘red flag’ system Moderate

Financial management risks UNRA had substantial experience and a good record in this

regard Moderate

Procurement risks

Management oversight improved and hands-on coaching to be

provided by a consultant. Vacant positions to be filled and an

acceptable record keeping and tracking system to be kept.

Substantial

Overall Risk Assessment: Moderate.

11

Transport Sector Development Project, 2009, PAD, page 6, Report No 50977-UG.

Page 23: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

9

2.2 Implementation Issues

Reduced value of Trust Fund Grant and IDA Credits

25. Although the Trust Fund Administrative Grant Agreement was approved on April 6,

2010, it was not signed until May 27, 2012, some 23 months later. DFID planned contribution of

US$8.0 million to the two institutional strengthening components had during this period reduced

to US$6.14 million due to negative fluctuations in the exchange rate. This resulted in changed

allocations for Component D, ‘Support to MoWT,’ (down from US$3.0 million to US$2.0

million) and Component E, ‘Support to UNRA,’ (down from US$4.0 million to US$3.1

million).12

The impact of the reduction in value of DFID contribution slightly weakened the

institutional support rendered and the delays introduced unnecessary complexity into the

administrative arrangements because funds were ‘loaned’ from the IDA Credit so that work

could begin.

Design of Institutional Support and Reforms

26. A design issue was the complexity of the reform and institutional support program that

had the challenge of creating a number of new authorities, updates of legislation, office

upgrading, training, and the introduction of new hardware and software. This “Christmas tree”

approach was comprehensive, but unrealistic given the capacity constraints evident in

Government.

Midterm Review

27. The Midterm Review (MTR) mission for the TSDP took place between April 22 and May

10, 2013. The mission expressed concern because both the construction and the institutional

development and reform activities were proceeding more slowly than anticipated. The Vurra-

Oraba road was reported to be behind schedule with 30.9 percent of the works completed in 52.7

percent of the contract period. The main reason was attributed to frequent equipment breakdowns

at one of the two crushing plants. A plan was devised accordingly to accelerate the progress on

the works. The Gulu-Atiak road was also delayed with 28.3 percent of the works completed in

47.0 percent of the contract period. Delays at this site were, amongst other reasons, due to design

problems, including a need to increase the thickness of the pavement structure and a haphazard

approach by the contractor. The discovery of a land mine also made it necessary to have the road

section checked for unexploded ordnance.

28. Progress with components B, C and D were also found to be well behind schedule.

MoWT had only recently prepared the policy for drafting the NRSA bill and received clearance

from the Ministry of Public Service to establish the authority. The preparatory studies to inform

the preparation of the Kampala Urban Transport Project started late. Nevertheless, the World

Bank, with support from the Public-Private Infrastructure Advisory Facility (PPIAF), provided

technical support for the BRT study as well as a feasibility study for the proposed establishment

of MATA – a pivotal step in the process. Regarding support to MoWT, delays were affecting

12

Final Report on DFID Trust Fund Utilization in the Transport Sector Development Project, July 2015.

Page 24: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

10

implementation and the MTR team considered progress to be unsatisfactory. Progress with

Component E, (support to UNRA), was deemed satisfactory. As a result of the findings from the

MTR, various proposals were made by the World Bank team to speed up construction progress

in general. However, the status of safeguard arrangements was not scrutinized to the same degree

as that for the civil works construction and social issues were not mentioned.

Additional Financing Risk Assessment

29. When Additional Financing was approved to scale up the project, the project results

framework was amended slightly to incorporate the Kamwenge-Fort Portal road and the

strengthening of the UNRA Internal Audit Unit to enable it to carry out technical audits. The

former was to be measured through reduced vehicle operating costs and time, while the latter

was specified as an output based on staff employed in the unit. The AF effectiveness took almost

16 months (October 22, 2012) because the GoU informed IDA that parliamentary approval

would be necessary first. A revised risk assessment framework was detailed in the Project Paper

requesting the Additional Credit.13

This is shown in full in Annex 2, table 2.3, but the main

points were:

An action plan was developed to enhance stakeholder awareness about land

compensation and to ensure that there were adequate resources to enable timely

compensation;

Although UNRA’s Board had given approval for 46 vacant positions to be filled (in

planning, project management, maintenance, internal audit, finance, and

administration, and legal), only 14 could be filled because of a wage cap imposed by

Government. A plan to lift the cap was to be pursued; and

The UNRA Procurement and Disposal Unit (PDU) was to report directly to the

Executive Director to increase management oversight.

Commission of Inquiry into Uganda National Roads Authority

30. Complaints from the public concerning the award of contracts, mismanagement, abuse of

office and corruption in UNRA led to the appointment of a new Executive Director, on April 27,

2015. On June 8, 2015, the President of Uganda appointed a Commission of Enquiry to look into

the affairs of UNRA. In September, nearly 900 employees were dismissed and a process was

launched to screen former employees who reapplied for their jobs and to recruit additional

personnel. Some former employees were not reappointed and some were recommended for

prosecution. This major disruption in UNRA constrained its operational capacity in the short to

medium term, which was reflected in its oversight of the Kamwenge-Fort Portal Road.

Inspection Panel

31. On December 19, 2014, the Inspection Panel14

(referred hereafter as the Panel) received a

Request for Inspection from community members of the Bigodi town in Uganda raising concerns

13

Transport Sector Development Project, 2011, Project Paper for Proposed Additional Credit, Report No. 59825. 14 The Inspection Panel is a three-member body created in 1993 by the World Bank’s Board of Executive Directors.

It provides an independent forum for project-affected persons (PAPs) who believe that they or their interests have

been or could be directly harmed by a project financed by the World Bank.

Page 25: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

11

about the Uganda Transport Sector Development Project - Additional Financing (“the Project”).

The request raised a number of issues including lack of community participation, sexual violence

against children by road workers, increased child labor and school dropouts, increased number of

accidents on the road and as a result of the stone quarry, a rise in crime in the community, poor

compensation practices and unclear redress mechanism, among others.

32. A Non-Government Organization (NGO), ‘Joy for Children, Uganda’ represented the

communities. Because these concerns had not been raised previously with World Bank

management, the Panel following normal procedures gave management the opportunity to

address the problems. Several missions involving Bank management, specialists and the task

team reviewed the shortcomings in implementation and discussions were held with UNRA and

Government officials. On September 11, 2015, a second request from the same entities was

received restating earlier concerns and noting that management actions to address these problems

were in their view unsatisfactory−progress remained slow and many mitigation measures had not

been implemented. The Panel registered the Request on September 28, 2015, and requested Bank

management to respond to the registration. On October 13, 2015, a Notice to Correct was issued

to the Contractor, on behalf of the Employer, requiring the Contractor to undertake 36 remedial

actions to address non-compliance with the contract.15

33. Eventually, on October 21, 2015, the World Bank suspended disbursements under the

project due to the Borrower’s non-compliance with its obligation to implement the project in

conformity with the World Bank’s environmental and social standards and practices.

34. Over the period November 19-24, 2015, a high-level mission comprising, the World

Bank’s Country Manager, the Transport Practice Director, the Practice Manager and Task Team

Leader met with key officials in the GoU including the Minister of MoWT, and the Permanent

Secretaries of the MoFPED and the Ministry of Gender, Labor, and Social Development to

discuss the situation, clarify outstanding obligations, and identify follow up actions. This

informed the preparation of the Bank’s Management Response16

to the registration of the

request, issued on December 17, 2015.

35. On December 21, 2015, the World Bank cancelled the Project due to the Contractor’s

repeated failure to remedy the instances of non-compliance, and the lack of demonstrated

willingness from UNRA to address the identified social risks. The World Bank also suspended

disbursements for civil works on two other World Bank financed projects implemented by

UNRA pending a review of that organization’s capacity and the need for UNRA to build its

capacity to engage and communicate with affected communities. These were the Albertine

Region Sustainable Development Project and the North Eastern Road Corridor Asset

Management Project (NERAMP).

36. The Panel commenced the investigation stage in January 2016, and carried out field

visits, interviews and focus group discussions with the requestors and community members and

confirmed many of the claims of harm in the request in the Investigation Report, issued on

15

The Notice to Correct specified a deadline for each remedial action to be implemented, reflecting the seriousness

of the issue, and/or the ease of corrective actions. 16

World Bank (2015) Management Response to the Request for Inspection Panel Review of the Uganda Transport

Sector Development Project - Additional Financing, Washington D.C.

Page 26: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

12

August 4, 2016. In their formal response17

, World Bank management agreed with the Panel’s

findings that there were serious weaknesses in the preparation, implementation and supervision

of the project. It acknowledged that the World Bank failed to identify and mitigate risks

associated with a full range of social impacts that a project of this size and scope could have in a

poor, rural area with many pre-existing vulnerabilities. World Bank Management also issued a

report detailing the lessons learned from this project, together with an agenda for action, which

looked beyond project-level compliance and focused more broadly on the institutional level to

identify systemic changes to strengthen oversight of projects in high-risk environments.18

37. One year after it was issued, the number of remedial actions in the Notice to Correct that

were considered to be compliant had increased to 32, but the Contractor remained out of

compliance in respect of four: work permits for foreign personnel, blasting operations at the

quarry, workplace accidents, compensation and grievance redress. All the actions were

eventually complied with by end of April 2017.

2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization

38. The design of the project’s Results Framework had some notable shortcomings. Although

the PDO and indicators largely reflected the project’s direct outcomes, there was a lack of

outcome indicators for the project objective of improved sector management. Causal linkages

between the PDO and the performance indicators for the physical infrastructure improvements

were fairly well aligned in that they measured the condition of the national road network and

reductions in travel time and operating costs for users of the upgraded roads under the project.

However, other key indicators, notably changes in the annual rate of road accidents and the

access of the rural population to all-season roads, posed problems of attribution to the project.

Progress with reform measures and capacity building, were only measured in terms of outputs.

39. At approval of the AF, some indicators covering the road section from Kamwenge to Fort

Portal were added as well as a new intermediate indicator in respect of an additional activity to

increase the capacity of UNRA’s Internal Audit Unit to be able to carry out technical audits. The

Database Section of MoWT was given overall responsibility for monitoring and reporting on the

performance of the transport sector. During implementation the capacity-building outputs

concerning UNRA were recorded as completed, but some of the benefits of this initiative may

have been reduced because of the disruptive re-organization within the authority.

40. An enduring aspect of the project was the strengthening of MoWT database and the

capacity to utilize it. A performance review of all transport sector modes is now produced

annually, which contains a wealth of useful information that is being used to assist decision-

making. This review has been regularly updated and is of high quality.

17

World Bank (2016a) Management Report and Recommendations in response to the Inspection Panel Investigation

Report of the Uganda: TSDP AF (P121097), Washington D.C. 18

World Bank (2016b) Uganda: TSDP AF: Lessons Learned and Agenda for Action, Washington D.C.

Page 27: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

13

2.4 Safeguards and Fiduciary Compliance

Safeguards Compliance: Gulu-Atiak and Vurra-Oraba roads

41. The TSDP was identified in the PAD as an environmental category B project requiring

partial assessment. Safeguards triggered at appraisal were Environmental Assessment (OP/BP

4.01), Physical Cultural Resources (OP/BP 4.11), and Involuntary Resettlement (OP/BP 4.12).

Although compliance weaknesses were identified, the potential social impacts were not of the

magnitude experienced on the Kamwenge-Fort Portal Road.

Environmental and Social Impacts

42. Environmental and Social Impact Assessments (ESIAs) for both the Gulu-Atiak and

Vurra-Oraba roads were prepared and disclosed both in country and at the InfoShop. Compliance

weaknesses during implementation led to closer oversight by the supervision consultants and the

World Bank team. The original ESIA and RAP documents needed substantive revision and

updating in respect of the functioning and updating of records of PAPs; and the already

identified capacity constraints within UNRA had not been resolved. Continuing budget

constraints limited the number of vacant positions in UNRA that could be filled. The contractors

applied mitigation measures to ensure compliance with road safety measures and the health and

safety of workers including supply of protective equipment and provision of lunch, drinking

water and sanitary facilities for the workers. Regular sensitization of the workers about work

safety and HIV/AIDS also took place. Monitoring of the safeguard instruments was undertaken

by UNRA, and progress made available in quarterly reports to the World Bank.

Decommissioning and restoration plans were prepared and accepted by the National

Environmental Management Authority (NEMA). Borrow pits and quarries were restored except

in isolated cases where the quarries were needed for other projects. In these instances, formal

handover documentation was completed. Roundabouts were improved and the pavement

strengthened at busy intersections.

Physical and Cultural Resources

43. Several physical cultural resources were identified: the Vurra military graves, an old East

African community (EAC) border post building, former colonial buildings in Arua town, an iron

smelting site in Nyoro village, and a sacred area in the Koboko District, where the Buranga

community performed rituals. In all cases, except the last one, the project did not affect the sites.

For the Buranga community the road was realigned, and compensation was paid as well because

the site could not be completely avoided due to the proximity of the adjacent border with DRC.

Historic buildings in Atiak and a fort in Pabo were preserved.

Involuntary Resettlement

44. RAPs for both the Gulu-Atiak and Vurra-Oraba roads were prepared and disclosed. The

World Bank team reviewed these documents, but found them in need of improvement to comply

with the World Bank’s safeguard policies and standards. UNRA submitted revised documents,

which were further reviewed and considered satisfactory by the safeguards team. The number of

persons affected and compensated was as follows: (i) Gulu-Atiak: 1,884 out of 2,027 PAPs were

Page 28: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

14

compensated (93 percent);19 (ii) Vurra-Oraba: 3,276 out of 3,935 PAPs compensated (83

percent).20 The reason for the shortfall in this case was that whilst additional PAPs were

identified, but there were no funds allocated for land acquisition in the financial year because

compensation was supposed to have been concluded. Special arrangements have been made by

GoU so that this backlog can be cleared as soon as new funds are available.

Safeguards Compliance: Kamwenge-Fort Portal Road

45. In addition to the safeguards triggered at appraisal, i.e. Environmental Assessment

(OP/BP 4.01), Physical Cultural Resources (OP/BP 4.11), and Involuntary Resettlement (OP/BP

4.12), in the AF Paper two further safeguards were added: Natural Habitats (OP/BP 4.04) and

Forests (OP/BP 4.36). The 2011 ESIA for the Kamwenge-Fort Portal road proposed that it be a

category ‘A’ project (potentially significant adverse impacts), but during the preparation for

Additional Financing this was downgraded to category “B”. Given the complex and systemic

social issues which emerged during implementation (which were identified in the original ESIA,

but insufficiently considered and reflected in the ESMP) as well as the fact that the road ran

through a National Park, this change in the safeguard category was an error of judgment.

Forests and Natural Habitats

46. A 13.3 km section of the Kamwenge-Fort Portal Road traverses the Kibale National Park.

This park protects a large area of forest previously managed as a logged Forest Reserve; it

adjoins Queen Elizabeth National Park and is an important eco-tourism destination popular for

its population of chimpanzees and other primates. While the upgraded road generally has a 30m

reserve, the section through the park was originally proposed not to be widened to eliminate

impacts associated with land take and destruction of trees and their canopies. Non-destruction of

tree canopies was also expected to substantially reduce the frequency of road kills resulting from

primates crossing at road level. Further, to avoid undesired tree damage occasioned by the need

for turning space for heavy equipment, a gravel quarry was identified at either end of the park so

that haulage trucks did not have to turn. Moreover, the road designs provided for properly signed

speed humps at 200-500m intervals with the aim of reducing noise and road kill levels in the

park. However, on December 22, 2014 the Uganda Wildlife Authority approved the wider cross

section of the road through Kibale National Park, despite this alternative being rejected in the

ESIA, on condition that only a limited number compensation of trees would be removed during

the road upgrading, and that some additional speed reduction devices (speed humps) were

installed, as it was eventually complied with.

Physical and Cultural Resources

47. During the site inspection of the Kamangwe-Fort Portal road (June 2014) the World Bank

team identified a cultural site, the Lugard Camp site established in the late 19th century by

Captain Frederick Lugard as an administrative center in the Kabarole District and protected

under the Historical Monuments Act. The Museum authorities inspected the site, but it was

determined that it would be unaffected by the project.

19

Of the pending payments, 10 are court cases and the remaining are due for re-assessment 20

There were over 200 complaints of non-payment due to bounced payments and missing documentation. These

complaints are being resolved on a case-by-case basis.

Page 29: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

15

Involuntary Resettlement and social issues

48. The number of persons affected and compensated was 2,246 out of 2,844 identified (79

percent). Originally, the number of expected beneficiaries was 2,430, but a further sweep by a

team of surveyors and valuation experts added another 414 PAPs eligible for compensation. This

was necessary because the original estimate was based on sampling and not a full census. The

World Bank and UNRA have continued to follow up on the completion of compensation even

after project cancellation. As of March 27, 2017, 94 percent of PAPs had received

compensation.21

49. However, the significant social concerns raised by the communities including sexual

violence against children by road workers, increased child labor and school dropouts, increased

number of accidents on the road and as a result of the stone quarry, a rise in crime in the

community, poor compensation practices and unclear redress mechanism, were not responded to

adequately in a timely manner. In addition to the action plan to mitigate these infractions, and

given the sensitivity of the gender-related matters, the World Bank undertook a diagnostic study

of gender-based violence in Uganda. The purpose was to make recommendations for how the

World Bank can in future better identify and address the potential impacts of gender-based

violence.22

Fiduciary Compliance

Financial Management

50. Pastel Accounting software was used to account for project funds. An assessment of

financial management practices carried out in December 2014 rated them only moderately

satisfactory because project accounts and World Bank reconciliations were not up-to-date,

withholding taxes deducted from contractors lacked receipts, and supporting documentation for

overseas trips was insufficient. These deficiencies were corrected and afterwards the financial

management aspects were rated as satisfactory with adequate financial systems in place,

qualified accountants deployed with knowledge of World Bank systems, and no ineligible

payments were recorded. UNRA and MoWT liaised with the Auditor General to have the

financial records reviewed in a single audit exercise. No irregularities were reported.

Procurement

51. Procurement commenced late in several cases such as purchase of equipment for pilot

phase of DUCAR and the review of engineering designs for future projects. At AF, three

measures were agreed to improve procurement capacity: the UNRA PDU was to report directly

to the Executive Director to increase management oversight; an outsourced independent

procurement evaluation was to be introduced to benchmark and validate UNRA’s procurement

actions and its management information system for procurement tracking, while the capacity of

UNRA’s Internal Audit Unit was to be strengthened to enable it to carry out technical audits. It

21

World Bank, 2017 First Progress Report of the Implementation of Management’s Action Plan in Response to the

Inspection Panel Report. 22

McLean, L and P. Bukuluki. 2016. Uganda Gender-based Violence Diagnostic. Washington, DC: World Bank.

Page 30: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

16

took 26 months from Board presentation in June 2011 until the selected contractor was mobilized

in August 2013. During this time, two procurement specialists were employed (financed by the

World Bank) and ten staff put in place by the GoU (against a target of 14). During the UNRA

restructuring, however, some apparently competent procurement staffs were let go for reasons

not disclosed to the World Bank and at project closure only seven staff members were in place.

The new organizational structure has to implement a proposed program amounting to between

US$700 million to US$2 billion over a period of four years.

2.5 Post-completion Operation/Next Phase

52. Although, for reasons explained elsewhere in this report, the Credit to finance the

Kamwenge - Fort Portal road was cancelled with the works 49 percent completed, the contractor

continued with the project using the GoU’s own funds. At the time of cancellation of TSDP, the

World Bank also suspended funding of the civil works components under UNRA of the

Albertine Region Sustainable Development Project, 100 km, and the NERAMP, 340 km,

because of concerns about the capacity of UNRA to implement safeguards management and

community engagement in accordance with World Bank guidelines. UNRA proposes to utilize

its own resources to fund the recurrent maintenance costs of the road, from the resources

provided by the Road Fund. The World Bank's support for the NERAMP project is designed to

pilot output and performance-based road contracts (OPRC),23

which could be extended to the

remainder of the network, if the results are promising. The NERAMP project is also providing

additional support to ensure for the sustainability of reforms within UNRA, as well as

improvements in staffing and training. At the same the Bank will continue to advocate for

adequate levels and use of funds to ensure the sustainability of the road network at all levels

from the Road Fund.

3. Assessment of Outcomes

3.1 Relevance of Objectives, Design and Implementation

Relevance of Objective(s)

Rating: High

53. The TSDP supported a slice of the RSDP, based on priorities guided by the country’s

Poverty Eradication Action Plan and linked to the Government’s Medium Term Expenditure

Framework. Inadequate infrastructure especially roads and transport, was identified as a binding

constraint for growth and economic transformation. The transport sector operates within various

frameworks, the over-arching one being the Uganda Vision 2040 (launched in April 2013). In

2009, the Letter of Development Policy for the Transport Sector laid out the principles for the

environment in which TSDP would operate. The National Development Plan (2010/2011-

2014/2015) detailed the country’s development challenges and opportunities. Transport,

especially roads, was among the sectors given priority because of the strong link with rural

agricultural production and hence poverty reduction. These strategic objectives continue to remain key

priorities of the Government of Uganda.

23

Under OPRC contractors are not paid directly for “inputs” or physical works, but for maintaining specified

Service Levels (Road Conditions).

Page 31: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

17

54. In addition, the Government’s NTPS hinged on the promotion of less costly, efficient and

reliable transport services as the means of providing effective support to increased agricultural

and industrial production, trade, tourism, social and administrative services. This was supported

through the Uganda Joint Assistance Strategy, 2001-2007, and also in the immediate years

afterwards, until the CAS for 2011-2015. The CAS had a strategic objective of “enhancing

public infrastructure,” that for road sector included strengthening the impact of the roads budget,

strengthening accountability, and improving governance arrangements. The intention was to

facilitate trade with neighboring countries, increase the percentage of national roads in good

condition and increase the access of the rural population to all-season roads. The relevance of

these objectives were confirmed in the CAS Progress Report issued in July, 2013.24

IDA co-

financed the TSDP together with DFID in support of key priorities in the Uganda National

Transport Master plan by improving connectivity and efficiency The objectives were and remain

highly relevant.

Relevance of Design

Rating: Modest

55. The project’s objectives and its design were reasonably well aligned, but overly complex.

The sector-wide approach to comprehensively reform the sector had too many subcomponents

and was beyond the capacity of the GoU to implement. Although the weak organizational

structure of UNRA and serious understaffing were identified as risks both in the PAD and in the

Project Paper for AF, the implications of these risks were underestimated. In particular, the

failure to properly assess UNRA’s capacity to comply with World Bank’s safeguard

requirements. Strengthening measures were built into the project that included studies, training,

equipment and office refurbishment, but many posts in UNRA remained unfilled and, as

unfolding events made it clear, there was insufficient environmental and social specialist

capacity. The scope of institutional development, capacity-building and planning activities in the

project’s design proved far too ambitious, and eventually posed significant implementation

challenges.

3.2 Achievement of Project Development Objectives

PDO: To improve the connectivity and efficiency of the transport sector through improved

condition of the National road network. Rating: Modest

Outcomes

56. The average vehicle operating cost per vehicle-km was reduced by a third from US$0.352

to 0.224 on the Gulu-Atiak and Vurra-Oraba roads by 2014. The target was fully achieved.

57. Travel time on the same roads reduced by half from two hours to one hour - also meeting

the target.

58. However, because the Kamwenge-Fort Portal road was not complete at project closing,

savings in either vehicle operating costs or time were not meaningfully calculable, although the

24

IDA/IFC and MIGA (2013) CAS Progress Report for the Republic of Uganda for the period FY11-FY15.

Page 32: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

18

expected benefits were being realized on already completed sections.

59. Access of the rural population to all-season roads in the target areas improved from 64

percent of the population to 77 percent by June 2014 (the target was 90 percent).25

Under the AF

this indicator was slightly reworded as the share of the rural population with access to an all-

season road, with the same target of 90 percent. It was envisaged that 4,950,000 rural people

would achieve access under the project. The target was not met. In the final Implementation

Status Results report (ISR), actual beneficiaries were estimated at 4,172,614 and the ISR

indicates that the original target may have been over-estimated.

60. A further indicator in the original project was that National roads in poor condition be

reduced from 36 percent to 15 percent. This was changed at AF, to “roads in good and fair

condition” as a percentage of all classified roads, with a baseline value of 64 percent and a target

of 90 percent. Using the original definition, 22 percent of roads were in in poor condition at

closure; using the revised definition 64 percent of all classified roads in good/fair condition –

(the urban roads were generally in a poorer condition than the national roads). Neither target was

met.

Outputs

61. Road length constructed. The original target of 159 km of road was exceeded by seven

km due to the upgrading of the road through the town of Arua. At AF, the target was revised to

225 km. However, works on the 66 km of road from Kamwenge to Fort Portal were only 49

percent complete when the World Bank Credit was cancelled. According to the final ISR 166 km

in total had been completed under the project. The works in the meantime have continued funded

utilizing GoU own funds.

62. Engineering consultancy services. In preparation for four future road upgrades in the

RSDP, the project funded the consultancy services for feasibility studies, environmental and

social assessments and detailed engineering designs. The actual road sections were expanded as

circumstances changed. The final list of roads included was Tororo-Mbale-Soroti (340 km),

Kamdini-Nebbi-Goli-and Ayer-Bobi (230 km), Kafu-Karuma-Kamdini (104 km), and Zirobwe-

Wobulenzi (23 km). In the case of the Tororo road, the consultant prepared a long-term OPRC

contract as an input to the Northeastern Corridor Road Asset Management Project.

Rating: Negligible

Outcomes

63. The rate of growth of road accident fatalities in Uganda was seven percent per annum at

appraisal—a statistic of great concern. The original target was that with the establishment of the

25

Accessibility in the target areas is according to the Implementation Status and Results Report (ISR), sequence 10,

February 2015.

Page 33: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

19

NRSA this rate of growth would decline, but no specific numerical target was set. At AF

approval, the indicator target was revised to a rate of growth not exceeding four percent growth

in fatalities when compared to the previous year—a very modest target. Actual figures were

much better than this with traffic fatalities peaking in 2012 at 3,343, then falling to 3,124 in

2013, 2,937 in 2014 and 2,845 in 2015, (see annex 2, table 2.2). However, these achievements

were not attributable to the project. The decline may have been due to the traffic police

introducing dedicated enforcement teams targeting major causes of accidents such as speeding,

drunk driving and incompetent drivers.26

Increased traffic congestion in the cities of Kampala

and Entebbe may also have reduced the severity of accidents due to lower speeds.

64. Expressed another way, in 2013 the death rate per 10,000 vehicles was 45 and this

declined to 26 by project closure despite the increasing vehicle population. The death rate per

100,000 people was 30, which is close to the World Health Organization estimate of 27.8.27

Notwithstanding, this remains one of the highest rates in Africa, even though rates in some

neighboring states are worse (Kenya 29.1, Rwanda 32.1 and Tanzania 32.9). The TSDP was

instrumental in supporting the formulation of the new road safety policy and created awareness

of good practice with the Uganda Police. However, since both the crash data base and the

establishment of the NRSA are still pending there is no convincing evidence that the reduction in

fatalities was attributable to the project’s interventions.

Outputs

65. NRSA created and operational. Although it approved the Road Safety Policy28

in

November 2014, Cabinet was reluctant to create new institutions and did not approve the

establishment of the NRSA. The objective in establishing the NRSA was to strengthen

institutional capacity in achieving national road safety objectives. The NRSA was envisioned to

be a central government authority that would coordinate all efforts of all stakeholders with

differing road safety activities and initiatives. It would be an autonomous, self-accounting

institution. MoWT made a strategic decision in 2015 to re-submit a request to Cabinet for the

establishment of the NRSA with stronger justification based on empirical evidence. In the

interim, road safety matters remain in the Ministry with support from underfunded advisory

National Road Safety Council (NRSC).29

66. Establishment of Road Crash Database. The overall objective of the database was to

enable the establishment of a well-functioning reliable road crash data system. This was

structured in three phases: Phase 1 was dedicated to a needs assessment; Phase 2 was for

ensuring the system was functional and piloting the project in specific districts; and Phase 3 (an

additional activity) was for the roll out. The Implementation Completion and Results Report

(ICR) mission confirmed that the system was functional and that data collected from non-pilot

regions can be put in the system manually. Equipment was procured and delivered to the

Ministry in December 2015.

67. Consultancy to update the Traffic and Road Safety Act of 1998. A consultant was hired to

26

Uganda Police. 2013. Annual Crime and Traffic Road Safety Report. Kampala. 27

World Health Organization.,2015. Road Safety Report. Geneva: World Health Organization. 28

A strategy to deal with ‘bodaboda’ motorbikes was added by MoWT 29

Ministry of Works and Transport, 2015. Annual Sector Performance Report Financial Year 2014/15.

Page 34: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

20

review the Act and prepare revised legislation, however, the final report produced was deemed

unsatisfactory by the Ministry technical team. Nevertheless, in view of the approved road safety

policy and emerging need for tighter Axle Load Control, the Ministry decided to finalize

amendments to the Traffic and Road Safety Act in-house. The principles for drafting the

amendment have been finalized, but the legislation has yet to be enacted.

Rating: Modest

Outputs

Ministry of Works and Transport

68. Preparation of Kampala Urban Transport Project. This subcomponent comprised

support to introduce a BRT system in the GKMA and the establishment of a Metropolitan Area

Transport Authority (MATA). The final draft design, procurement strategy, operating conditions

and taxi transformation strategy have been discussed with stakeholders and technical committee

members. The duration of the contract was also extended to cater for a BRT route extension from

20 km to 25 km. Regarding the establishment of MATA, a study was carried out to advise

Government on establishing such an authority. This was completed in April 2014. The MoFPED

has issued a Certificate of Financial Clearance and Cabinet approved the principles for a Bill to

establish MATA. The First Parliamentary Council, however, is still drafting the detailed Bill and

an action plan for implementation remains under discussion.

69. Establishment of Multi-Sectoral Transport Regulatory Authority (MTRA). Cabinet did not

approve the establishment of a MTRA and MoWT have not pushed this proposal any further to

date.

70. Establishment of the District, Urban, Community Road Agency (DUCAR) agency. In

1998 policy matters related to district and urban roads were transferred from the Ministry of

Local Government to MoWT, which established a division for DUCAR. It had proved very

difficult to build and maintain sufficient capacity at district level. In 2004 a ten-year investment

plan was developed covering the maintenance and upgrading of 16,372 km of roads. MoWT

decided to enhance the status and performance of DUCAR by establishing an agency under its

oversight. To this end TSDP funds were allocated to assist with the drafting of an appropriate

Bill and consultation with local communities. MoWT opted to prepare the draft Bill in-house and

held consultations with 111 districts, 12 municipalities and 198 town councils. It obtained their

consent to create an authority to manage the roads, with the exception of community access

roads. At a stakeholder’s workshop it was formally agreed that the agency should be established,

but re-named the Urban and Rural Roads Authority (URURA). However, MoWT decided that

the NRSA and MATA were the priority new authorities and URURA may only be supported at a

later date.

71. Support for the development of software for TSDMS. After a needs assessment,

diagnostics and specifications report, the work proceeded with equipment procured under TSDP.

Page 35: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

21

The system was launched at the transport sector review workshop in 2014. As a result of this

work, the Ministry now produces an annual sector performance review. This report contains

considerable useful information including key indicators to track performance.

72. Updating of NTPS. The policy has been updated and reviewed by the Sector Working

Group. It provides for the establishment of the NRSA and MATA, but has yet to be cleared by

the MoFPED pending greater clarity on the financial implications. Further consultation is taking

place before resubmitting the draft for financial clearance.

73. Consultancy Services for the preparation of a strategic implementation plan for the

National Transport Master Plan. The Strategic Implementation Plan for the National Transport

Master Plan including a Master Plan for the GKMA was completed during FY 2014/15.

74. Consultancy Services for Updating Inland Water Transport Legislation. A study was

commissioned in 2014 to review inland water transport laws, harmonize legislation within the

region and update them to international standards. A Cabinet Memorandum seeking approval of

the principles is being finalized, but as yet parliamentary approval has not yet been given.

75. Condition Survey for District and Urban Roads. This item was partly funded by JICA

support to MoWT. The task was to prepare a condition survey for the URURA network,

comprising 30,000 km of district roads and 85,000 km of community access roads. JICA had

covered about half of this network. A request was made for the balance to be funded from TSDP.

This has been done and the database has been completed and is in use. Information technology

equipment has been procured and delivered.

76. Transport Sector Capacity Development. Six staff members completed Masters degrees

in Transport Economics and Planning at the University of Leeds in the United Kingdom. Other

staff received training in professional management skills in Israel and South Africa.

Uganda National Roads Authority

77. Upgrading of UNRA regional offices. Five regional offices were to be upgraded. The

designs have been completed, but the cancellation of the Credit affected the procurement of the

works contract and also the construction.

78. UNRA: Road Inventory and Mapping. Some 10,000 km of district roads were reclassified

to become part of the national road network and transferred to UNRA’s management. The data

collection (including mapping, an inventory of road assets, condition assessment and traffic

census have been completed. Quality assurance and uploading of the data in the Road

Management System (RMS) was completed in May 2012. The project was successfully

completed with the commissioning of the RMS in June 2012.

79. Development of a Geographic Information System (GIS) based Rights-of-Way

Management Information System. The system was to support RAP preparation, land acquisition,

registration and land administration. In addition, it would respond to queries and complaints as

well as M&E. System development was completed and the system was installed on the UNRA

server. GIS officers were given training to provide technical and helpdesk support.

Page 36: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

22

80. Procurement of equipment for UNRA. This included the procurement of heavy-duty

scanners, and 15 double cabin pickup vehicles.

81. Technical assistance: communications. The outputs under this support were a perception

survey, communications strategy, monthly media analysis reports, designing communication

materials, website management, social media, operational templates, social intermediation,

community relations and training.

82. Technical assistance: procurement. A procurement consultant with skills in roads and

contract management joined the PDU in August 2010

83. Ferry Services Advisor for UNRA. At the close of Financial Year 2014/15, UNRA had

eight operational ferries linking national roads. A ninth Ferry at Bukakata/Luuku was provided

and operated by Kalangala Infrastructure Services contracted by the GoU to provide

infrastructure services in Kalangala under a Public Private Partnership (PPP) arrangement. An

advisor was appointed for 12 months to review the current system and make recommendations

for future operation.

84. Axle Load Control Advisor. The draft policy was completed in 2010, but the process was

dragged out by harmonization efforts at the EAC level, which resulted in the enactment of the

EAC Vehicle Load Control Bill by the East African Legislative Assembly. However, due to

delays in assent to the Bill by some Heads of State within EAC, the policy is now going to be

reviewed and forwarded to Cabinet for final approval.

85. Internal Audit Unit. A consultant commenced services in September 2013 for a period of

two years. In addition, consultancy services were procured for establishing and developing a

Technical Audit Unit in the Directorate of Internal Audit. It was intended that 14 staff would be

employed in this unit, but at project closure there were only seven staffs.

86. General capacity building (UNRA). A consulting firm provided this service from June

2014 to December 30, 2015, when it was terminated due to the restructuring of the organization.

87. Asset Management Support (UNRA). This service was to ensure that asset management

practices in the newly established asset management systems were fully mainstreamed in

UNRA’s business. The service will expire in February 2017.

3.3 Efficiency

Rating: Modest

88. Economic analyses for the upgrading of the Gulu-Atiak and the Vurra-Oraba roads were

undertaken at appraisal using the Highway Development and Management Model (HDM-4).

The analyses in Table 3 were based on economic costs, excluding taxes and duties.

Table 3: Economic Analysis Results

Road Section Appraisal Completion

NPV@12% EIRR % NPV@12% EIRR %

Page 37: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

23

discount rate discount rate

Gulu-Atiak $25.68m 18.1 $65.09m 28.3

Vurra-Oraba $53.96m 21.2 $22.51m 18.0

Kamwenge-Fort Portal $19.00m 18.0 Not completed Not completed

89. The Gulu-Atiak road gave a better return at completion due to higher than anticipated

traffic. The Kamwenge-Fort Portal road, representing a third of the road investment cost, had an

NPV of US$19 million and an EIRR of 16.8 percent at appraisal. Because the Credit was

cancelled and the road was unfinished at closure no further economic evaluation was undertaken.

90. Operational and administrative efficiency: The project has been characterized by

delays. The MTR reported most components were behind schedule and the completion date was

extended by 18 months. The Trust Fund Administrative Agreement (largely due to delays on the

Bank’s side) took 23 months before approval, by which time the value of DFID grant had shrunk

by 30 percent due to exchange rate fluctuations. At the time of approval of the AF steps were

taken to improve procurement capacity, but still by closure most of the reforms in the transport

sector had not been completed. There were savings due to exchange rate fluctuations that could

have been used had the project closing date been extended; the Kamwenge-Fort Portal road

construction continued after closure using GOU funding. The overall rating for efficiency was

downgraded to modest because prior to closure the Kamwenge-Fort Portal Road was unfinished

and because of the long delays during implementation.

3.4 Justification of Overall Outcome Rating

91. The overall project outcome rating is unsatisfactory.30

The project’s objectives remain

highly relevant to the Ugandan economy, reducing poverty, and the World Bank’s program in

Uganda. However, the relevance of design was modest. Establishing four new agencies was

ambitious and Government had misgivings about worsening the situation given the governance

issues in UNRA and elsewhere. The achievement of two project objectives (connectivity and

efficiency; transport sector and road management) is rated modest, and the achievement of the

secondary level objectives (road safety and transport sector road management) are rated

negligible and modest respectively. The AF Credit for the Kamwenge-Fort Portal road was

cancelled when only 49 percent of the construction was complete, although construction

continued using GoU funds. Efficiency was modest, given the delays that had occurred.

4. Assessment of Risk to Development Outcome

Rating: Significant

92. Although the overall project outcome is unsatisfactory, several components of the project

did achieve some useful results, and the risks to their sustainability are worth considering. One is

the sustained maintenance of the completed Gulu-Atiak and Vurra-Oraba road sections. The

URF remains underfunded and this matter requires urgent attention to avoid worsening the

30

This conforms with the standards of Appendix J, Table 1, of the ICR Guidelines.

Page 38: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

24

maintenance backlog. This road will also add to the maintenance needs and not all PAPs had yet

been compensated by the time the ICR was being prepared. In regard to road safety, the project

supported the preparation and adoption of the National Road Safety Policy, but it remains

uncertain whether the Government will follow this up with appropriate legal, regulatory and

institutional measures, which were not taken up during the life of the project. Finally, there are

numerous pending risks to the sustainability of the project’s contributions to improved sector

management, including the preparation of the Kampala Urban Transport Project, the

establishment of MATA and the NRSA, the updating of NTPS and the finalizing of the Inland

Water Transport Bill.

5. Assessment of Bank and Borrower Performance

5.1 Bank Performance

(a) Bank Performance

Quality at Entry: Unsatisfactory 93. The TSDP appropriately supported a portion of the RSDP, based on priorities guided by

the country’s NTPS, Poverty Eradication Action Plan and the CAS of 2011/15. The project at

appraisal was classified as environmental category ‘B’ because the two road projects were more

or less on the same alignments and no significant adverse effects were anticipated. An

appropriate team was mobilized. Identified risks at appraisal related to the absorption of

technical assistance for building local capacity and benchmarks for effecting policy and

institutional reforms. Although the risks for financial management and procurement were rated

moderate and substantial, all other risks were questionably appraised as being low or moderate,

with an overall risk rating of moderate. It was assumed that because the World Bank and its DPs

had rendered considerable technical assistance to the sector over several years, the risk of

insufficient capacity was only moderate, but there were serious shortcomings in MoWT when it

came to the reform program, and in UNRA in ensuring there was sufficient capacity to review

the quality of documents submitted by the design consultants as well as to ensure safeguards

compliance. This was clearly exacerbated when UNRA was given another 10,000 km to manage

without a commensurate increase in staff.

94. The World Bank team was diligent in securing funding through DFID for road safety and

institutional support, while the AfDB had already funded the preparation of ESIAs, RAPs and

road designs. A Governance and Accountability Action Plan was drawn up to address

governance, but there were no specific risk measures associated with road safety. The

establishment of the four proposed new authorities supported by TSDP, was extremely

unrealistic, given the project complexity, staffing, budgetary and political implications of

establishing these new entities. The Cabinet clearly had misgivings about these proposals and in

the end MoWT decided to only press for consideration the two highest priority authorities,

namely, the NRSA and MATA—neither of which had materialized by preparation of this ICR.

Overall, the project design addressed many sector needs with numerous subcomponents covering

construction, road safety, urban transport and transport sector reform, posing a challenge for the

Government given its stretched operational capacity.

Page 39: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

25

(b) Quality of Supervision Rating: Unsatisfactory 95. Implementation support to the Gulu-Atiak and Vurra-Oraba roads, the implementation of

which were relatively straightforward, had a satisfactory outcome, despite some early

construction delays prior to the MTR. Supervision of the reform program was intensive with a

full-time Bank staff hired in the country office and working with the Ministry on a daily basis in

addition to support provided by DFID. Delays by the Borrower were a recurring feature,

however, characterized by late starts, a general lack of urgency, and the failure to succeed in

establishing any of the proposed authorities. By the time the Administrative Grant Agreement

with DFID was signed the planned contribution of US$8.0 million had reduced to US$6.14

million due to exchange rate fluctuations in the two years that had elapsed. The Bank team could

have pushed this trust fund contribution with more vigor. The time to gain support from

stakeholders, navigate the procedures to prepare a Bill to set up a new authority, and obtain a

Certificate of Financial Clearance from the MoFPED was generally underestimated by the World

Bank and impacted headway. Nevertheless, some progress was made in respect of formulating

road safety policy; setting up a pilot crash database, design of a BRT system in Kampala and in

establishing a TSDMS. It is difficult to evaluate the World Bank’s performance in respect of the

capacity-building subcomponents because no outcomes were specified or measured.

96. Turning to the supervision performance after approval of the AF, the findings of the

Inspection Panel (accepted by Management) are highly pertinent. Many have to do with

inadequate preparation of the AF proposal. In the updated draft 2011 ESIA for the Kamwenge-

Fort Portal road the project was proposed as a category “A” (potentially significant adverse

impacts), but in preparation for the AF this was downgraded to category “B”, as detailed under

section 2.4. As environmental category “B” the project was precluded from the benefits of

increased internal scrutiny and resources. The final ESIA made only brief references to the

systemic social impacts and risks. The Bank team made regular visits, but initially did not

include persons with a background in social safeguards, or the particular areas of concern.

97. Given the high prevalence of child abuse and child pregnancy in rural Uganda, these

matters deserved much more than cursory attention and the composition of the implementation

team should have reflected this. A major shortcoming was that the ESIA did not identify in

sufficient detail the key risks arising from the influx of a large number of construction workers

and therefore the potential impacts on the affected poor rural communities and subsequent

mitigation measures applied were inadequate and not properly addressed in the Environmental

and Social Management Plan (ESMP). The Panel observed that an adequate assessment of

UNRA’s environmental and social capacity had not been conducted; as a consequence, the

project’s technical assistance and capacity enhancement components tended to focus more on

procurement.

98. The site specific ESMP prepared by the contractor lacked information on how to mitigate

identified risks and was not shared in its revised form with the World Bank by the Employer

until at least two years into the civil works implementation. The World Bank was remiss in not

pursuing this and also assuring that activities and costs associated with social safeguards

Page 40: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

26

mitigation were adequately reflected in the bidding documents or in the contract.31

The World

Bank also relied on figures for affected persons that were out-of-date; the 2,200 people identified

in the first RAP grew to 2,844 during supervision. Moreover, the focus in terms of social

safeguards was primarily on involuntary resettlement as opposed to social and environmental

issues for the re-aligned sections. The Bank should have been more stringent in ensuring

compliance on environmental and social issues and should have taken stronger action such as

proposing suspension of disbursements at an earlier stage. Implementation supervision ratings

tended to mask the true nature of the problems.

99. The Inspection Panel found that Management did not ensure the design or

implementation of appropriate mitigation measures to protect the community and workers

against construction impacts, thus seriously jeopardizing human health, safety, and livelihoods in

non-compliance with OP/BP 4.01 on Environmental Assessment. Further, it found that early and

ongoing consultations with community members would have raised sufficient warning signals to

address the problems raised in the Request. Project implementation continued despite the serious

compliance failures and harm repeatedly identified in supervision reports, and in the absence of

decisive action by Management. Consequently, the Panel found Management in non-compliance

with OP/BP 10.00 on Investment Project Financing.

100. There was over-reliance on verification sampling rather than a full census to identify

PAPs, despite the recognized weakness of the original census under the RAP commissioned by

the AfDB. The World Bank should have insisted on a new census given the uncertainty of the

figures. In addition, there was an interval of more than two years between the original census and

the updated RAP. The Panel also found that the updated RAP contained an inadequate

vulnerability assessment and did not properly identify necessary assistance programs targeting

vulnerable groups. Consequently, the Panel found that Management did not ensure the

preparation and implementation of an updated RAP compliant with OP/BP 4.12 on Involuntary

Resettlement. Moreover, road construction commenced and continued before most PAPs were

compensated, which is contrary to Bank policy. Such compensation amounts were frequently

insufficient due to failure to assess the full impact of the road on land-take, and there was

insufficient livelihoods restoration assistance as set out in the 2011 RAP.

101. The World Bank failed to ensure the Borrower complied with its obligation to report

monthly on RAP implementation. Early detection of problems by the World Bank would have

permitted interventions to address known concerns and prevented compensation problems from

escalating. World Bank Policy OP 4.12 on Involuntary Resettlement requires institutionalized

mechanisms for the continued participation of affected persons and redress of their grievances.

The RAP set out a procedure for establishing a grievance redress mechanism that included

employing a RAP Implementation Consultant with field presence along the road in collaboration

with a local NGO-funded to monitor RAP effectiveness. This was not done.

102. The 2011 ESIA and appraisal documents for the Additional Finance lacked a required

analysis of risks to women and children caused by labor influx, in particular those risks related to

sex with minors, teenage pregnancies, sexual harassment, child labor, and school dropouts.

31

However, there were provisions for Occupational Health Safety, an HIV/AIDS service provider, and a lump sum

for the environmental action plan.

Page 41: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

27

Mitigation measures mainly focused on HIV/AIDS prevention and were inadequate to respond to

the multidimensional problem of gender-based violence and child protection. Management’s

initial response to the complaints failed to meet the standards of systematic or holistic assessment

of risks, which aimed, among other objectives, to identify adequate risk management measures

for affected communities.

103. Finally, despite the Bank undertaking several implementation support missions, the

composition of these teams lacked the requisite expertise to address issues related to gender-

based violence and child protection. Effective implementation support (including adequate

understanding of the community) could have resulted in earlier detection of some problems caused

by the project. The Panel found Management’s overall supervision of the Project, including its

actions in response to the Request received in December 2014, in non-compliance with the

World Bank Policy on Investment Project Financing OP/BP 10.00.

(c) Justification of Rating for Overall Bank Performance

Rating: Unsatisfactory

104. The World Bank overestimated the willingness and capacity of the Borrower’s achieving

the transport reform and the road safety outcomes of the original project design, which proved

far too ambitious. The Kamwenge - Fort Portal road under the AF added another dimension of

complexity and risk as discussed above. The Panel’s Investigation Report revealed many

shortcomings on the part of the World Bank in relation to the AF, which led, in tandem with the

Borrower’s non-compliance with its obligations, to the cancellation of the financing.

5.2 Borrower Performance

(a) Government Performance

Rating: Unsatisfactory

105. In its Letter of Development Policy for the Transport Sector, the GoU placed emphasis

on the provision of technically sound, economically justified, financially and environmentally

sustainable infrastructure as well as the active participation of the private sector. The

Government restructured MoWT to focus on formulating policies, setting standards, strategic

planning, sector oversight and monitoring. At the same time, the Government began delegating

executive functions, including implementation and regulatory functions, to specialized entities,

which had been or are being created. Accordingly, UNRA was established to manage National

roads and the URF was set up, albeit with a smaller budget than needed to provide for adequate

maintenance. Despite this progress, during the life of TSDP there has been a reluctance to move

further forward with new authorities including the NRSA, which was turned down by the

Cabinet. This slowed the reform process and shown a wavering in commitment. Although the

reform component started late, there were pockets of success – for instance, progress was made

in completing the design for the BRT, and a road safety policy was approved. The reform

process within MoWT proceeded overall very slowly and at project closure no new agencies had

been established. There was a disconnect between what had been articulated in the policy and

commitment to implement the steps necessary to achieve the policy goals.

106. The Government also supported the implementation of a Governance and Accountability

Page 42: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

28

Action Plan aimed at developing a system and culture for promoting transparency and

accountability in the road sector. This was an important move, but governance is still a major

issue emphasized by the appointment in 2015 of a Commission of Enquiry into UNRA. While

the World Bank welcomed this development, which followed complaints from the public, the

subsequent dismissal and re-appointment of selected staff (after a thorough screening) inevitably

caused a major disruption to the operational capacity of UNRA and its ability to respond to the

supervision issues on the Kamwenge-Fort Portal road. Similarly, the addition of 10,000 km of

district roads re-designated as National roads doubled the responsibility of UNRA, but there was

a failure to provide a commensurate improvement in staff numbers. A cap on recruitment meant

that despite the project’s best efforts to build capacity, the authority continued to be constrained

by weak capacity. The weak governance environment had an adverse effect on implementation.

(b) Implementing Agency or Agencies Performance

Rating: Unsatisfactory

Ministry of Works and Transport

107. The MTR mission expressed concern because the reform activities were proceeding more

slowly than anticipated. A sense of urgency was lacking and this did not appreciably improve

during the life of the project. The indicators in the results framework were recorded, but this did

not translate into action when results were falling short of target. There were delays in

procurement and in recruiting additional staff. The MTR states that there was a lack of follow up

and a lack of accountability for the delays in procurement processing. All reform activities were

constrained by the failure to achieve Cabinet approval for any of the four proposed new agencies.

It would be unfair to say that no progress was made with the reform agenda, but the results were

patchy and varied by department. The design of the proposed Kampala BRT was completed, but

there was some dissension as to whether this was the right solution as a light rail proposal was

also suggested. In any case, the planning could not proceed in the absence of approval of MATA.

On the other hand, the timely completion of the URURA condition survey, the establishment of

the crash database, and the annual transport sector performance review were positive steps

forward.

Uganda National Road Agency

108. UNRA suffered from a significant staffing shortage throughout project implementation.

Continuing budget constraints and a cap on hiring limited the number of staff that could be

recruited and even when new staff came on board it was unrealistic to think they could operate at

full capacity until they had received at least some orientation and training. Although there were

not major problems on the Gulu-Atiak and Vurra-Oraba roads, the performance of the contractor

appointed for the Kamwenge-Fort Portal road was poor and UNRA did not supervise the project

adequately. Although there were social concerns expressed by the communities affected by the

project, as early as June 2014 and the World Bank’s Aide Memoire at the time expressed

“concern in regard to the violation of basic social, environmental, health and safety requirements

by the contractor,” UNRA took little action. The supervising engineer’s instructions also appear

to have been largely ignored by the contractor and UNRA did not take appropriate actions. It is

clear that the contractor did not give a priority to safeguards as demonstrated by the fact that

safeguard staffing was only hired on a part time basis.

Page 43: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

29

109. UNRA’s management capacity was inadequate to deal with this complex project. Over

the last few years, there have been delays in payments to contractors and consultants under

Government-funded projects primarily due to over-commitment in the road sector. Such issues

likely stretched the contract management capacity of UNRA as it has to deal, in parallel with

TSDP, with many contractual claims due to variations, extensions of time, and delayed

payments.32

110. Overall, UNRA lacked the capacity to ensure that projects followed the World Bank

guidelines, did not carry out appropriate supervision and was particularly weak in the areas of

compliance with environmental and social safeguards and community engagement. Subsequent

to the closing of the project, UNRA capacity has steadily improved. This has led to the

contractor complying with 32 of the 36 actions in the Notice to Correct over a 12-month period.

(c) Justification of Rating for Overall Borrower Performance

Rating: Unsatisfactory

111. The Government increased the road development program in Uganda over and above the

available capacity to implement the program effectively. This has meant that reforms were not

followed through and on the Kamwenge-Fort Portal road there was a failure to meet the World

Bank’s safeguard requirements. These problems also jeopardized other approved projects, which

had to be suspended pending urgent measures to improve UNRA’s capacity.

Lessons Learned

112. Following the Panel’s investigation, the World Bank conducted a thorough review to

document lessons from the Uganda experience so as to avoid similar problems in other projects

and to improve guidance, procedures and standards to staff involved in project preparation,

design and supervision of projects in countries that had weak capacity. The main lessons and

some follow up actions are given below:

Institutional Reforms

113. New transport agencies should only be established when there is clear acceptance of

their value by the Borrower at all levels and there is a sound understanding of the

financial, legal and political implications of such initiatives. There needs to be sufficient

capacity in place to ensure the necessary stakeholder buy-in, financial clearance from the

appropriate financial ministry, and the preparation of suitable legislation. The establishment of

four new agencies in Uganda covering road safety, metropolitan transport, multi-sector transport

regulation, and district urban and community access roads was unrealistic during the life of one

project, given the extent of the capacity of MoWT to absorb and implement such initiatives.

Cabinet turned down both the MTRA and the NRSA proposals when they were presented.

MoWT has since decided to focus on the MATA and NRSA agencies, the latter now based on a

stronger submission. However, at project closure no new agencies had been established.

114. Reform initiatives and capacity building in the transport sector should not be

32

World Bank. 2014. Northeastern Road Corridor Asset Management Project, Project Appraisal Document, Report

PAD 707. Washington DC: World Bank.

Page 44: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

30

subordinate to progress with the physical investment components. There is a natural

tendency in infrastructure projects for attention to be focused on physical construction progress

once contracts have been awarded. In TSDP, there should have been a parallel focus from the

outset on the softer components if the targets set were to be achieved prior to project closure.

There is a tendency for such components to be rolled over to a follow-on project if not completed

on time and this is a concern requiring both the World Bank and its Client’s attention. In this

case, because the loan was cancelled and follow-on projects suspended, continuity was impacted

severely.

Institutional Capacity

115. Where capacity is thin, fewer, but more focused activities should be the norm. In

TSDP there were simply too many activities. Had there been less there may have been a different

outcome.

116. Donor crowding without proper consideration of the client’s capacity to manage its

full aid program can affect the capacity to deliver appropriately. In Uganda, at the time of

appraisal there was a concerted effort by several development partners to operate jointly.

However, it was concluded that this did not necessarily reduce transaction costs because of the

differing agendas and rules of the partners.

117. Capacity building and training indicators need to be given more thought during

preparation. It is not always useful to say that a person attended a course or that a new staff

appointment was made in a critical position. The bottom line is whether the organization can

operate more effectively because of these inputs and this needs to be measured over time. New

staff members are not necessarily immediately effective.

118. In complex projects a thorough assessment of all aspects relating to the

implementing agency’s capacity including safeguards is essential, with credible measures to

address any weaknesses identified. In all large infrastructure projects, the World Bank needs to

ensure that sufficient contract capacity is in place before implementation commences and that

qualified social and environmental staffs are assigned to the project, or if this is not likely,

alternative arrangements are made for greater implementation oversight, which reflects the

capacity constraints. Where applicable the guidance provided in managing the risks of adverse

impacts on communities from temporary project-induced labor influx should be followed.

119. Failure to put in place robust community engagement processes weakens the World

Bank’s ability to anticipate potential social impacts and respond appropriately when

problems arise. There was no grievance redress mechanism in place or partnerships with NGOs

in the Uganda TSDP that could assist in understanding and resolving sensitive local issues.

120. When AF substantially increases the project scope a thorough review of the

safeguard implications of the new component(s) should take place. In some cases, the revised

project should not necessarily be given the same environmental classification as the parent

project. In the case of the TSDP, the circumstances associated with the added road were much

more complex than the ones in the original project and an environmental category “A,”

recognizing potentially significant adverse impacts, should have been designated.

Page 45: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

31

121. The World Bank staff skills and capacity need to match the risk and complexity of

the anticipated operations. There was an over reliance by the World Bank on newly hired

safeguard staff who had received limited support from others in the region and from

headquarters. Until well after the Inspection Panel complaint was received, there was no

deployment of staff with the right skills to address systemic social risks or to engage the

communities. Implementation supervision report ratings were misleadingly positive.

Procurement and contract management

122. Based on the lessons learned from the TSDP, the World Bank has taken a series of

actions to enhance the procurement and contractual provisions for both civil contractors and

supervising engineers. While the engineering aspects of works contracts were normally well

covered, the expectations in respect of environmental and social safeguards were not spelt out.

The Bank Standard Procurement Documents have been revised to incorporate changes reflecting

enhanced environmental or social, health and safety safeguards as of January 2017. This

includes:

Bidders are required to declare any civil works contracts that have been suspended or

terminated by the employer for reasons related to environmental or social safeguard

compliance (including health and safety issues in the past five years). This information is

used to inform additional due diligence that may be required prior to contract signing.

Contractors are required to post an environmental and social performance bond that the

contracting entity could cash should a contractor fail to remedy cases of environmental

and social non-compliance. The bond is for a reasonable amount, which, in combination

with the current performance bond, would normally not exceed 10 percent of the contract

amount. The bond would be cashable based on failure to comply with the engineer’s

notice to correct the said defects.

A provisional sum could be included in civil works contracts to be used as agreed

between the contracting entity and the contractor in cases where contractors have fully

met all environmental and social obligations under the contract and propose to further

enhance environmental and social outcomes. The parties’ agreement on the use of this

provisional sum would be subject to the World Bank’s ‘no-objection.’

Civil works contractors and supervising engineers would be required to include dedicated

staff with appropriate qualifications and experience to manage specific social and

environmental impacts.

A guidance note has been produced for managing the risks of adverse impacts on

communities from temporary project induced labor influx.33

The importance of assessing

impacts and designing mitigating factors increases with the social fragility of the road

corridor. While many of these potential impacts should be carefully identified and

evaluated in a project’s ESIA, they may only become fully known once a contractor is

appointed and decides on sourcing the required labor force. This means that not all

33 World Bank, 2017, Managing the Risks of Adverse Impacts on Communities from Temporary Project-induced Labor Influx,

Operations Policy and Country Services, and Environmental and Social Safeguards Advisory Team, Washington DC

Page 46: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

32

specific risks and impacts can be fully assessed prior to project implementation, and

others may emerge as the project progresses. Site specific measures may have to be

developed before the contractor starts work, and they may have to be updated as the

project is implemented.

Land acquisition, resettlement, and compensation processes need to be aligned with

procurement in a manner that those processes are appropriately completed along specific

segments of the road project ahead of the start of civil works on those segments.

123. For the purpose of addressing the actions listed above, the Bank is launching a

procurement pilot in the East Africa Region with the purpose of engaging with a broad set

of stakeholders and devising strategies and actions to enhance procurement and contract

management approaches. This engagement will form the basis for i) introducing the enhanced

Standard Procurement Documents to the Road Agencies and other stakeholders in the sub-region

to get their commitments to its implementation, and ii) exchanging ideas on strengthening

bidding documents to set out clear expectations with respect to environmental or social

safeguards. UNRA is expected to use this platform to play a leading role in peer regional efforts.

124. Road agencies, as UNRA is doing, can also take steps to strengthen clauses and

requirements in bidding and contractual documents for all road projects that relate to

social, environmental, health and safety, and labor issues. This includes the revision of

bidding documents to include penalties for contractors that do not comply with such

requirements, as well as the development of a Contract Management Manual that should

contribute to overall successful contract performance and value for money throughout the

procurement and contract management process. For the ongoing NERAMP procurement process,

UNRA is including clauses in the contract document to incorporate the new environmental,

social, health and safety requirements.

125. In addressing the issues related to the TSDP, UNRA has also learned some lessons

and taken actions that are applicable to other road agencies, such as: (i) revamping its

environmental and social management systems, staffing and training, and embrace general

attitudinal changes with a recognition of the need to deliver road infrastructure projects in a way

that enhances social impacts for the local communities; (ii) improving community engagement

(with client care officers, dedicated resident project engineers and on-the-ground land

compensation teams, as well as training and the rolling out of Grievance Redress Committees);

and (iii) enhancing the collaboration with, and empowerment of supervision engineers.

126. The TSDP has also shown the large and pivotal value of introducing the services of

NGOs to work closely with the road agency, Supervision Engineers, and contractors in

“Enhancing Social Impact” under (Bank financed) road contracts. The aim is to help: (i)

prevent issues related to sexual and gender-based violence; (ii) promote the empowerment and

improved livelihoods for young girls; and (iii) monitor implementation of various measures to

address social risk and enhance the positive social impacts associated with the road works,

including addressing issues associated with the implementation of resettlement action plans.

Page 47: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

33

7. Comments on Issues Raised by Borrow/Implementing Agencies/Partners

(a) Borrower/implementing agencies

127. See Borrower’s ICR in Annex 5.

128. There is a disconnect between the Bank and Client perceptions of project ratings. The

Client refers primarily to the extent of the road upgrading completed under the project, which it

says met most of the PDO outcome indicators. (It met two out of five of the original indicators,

but the impact on these indicators was reduced by the Kamwenge-Fort Portal road that was

unfinished when the Credit was cancelled). Regarding intermediate indicators, some were

achieved, but none of the four new authorities proposed under the project were established.

Efforts to strengthen capacity also produced mixed results. The contractual non-compliance with

agreed social and environmental standards compounded by unsatisfactory progress with the

handling of compensation claims by PAPs contributed to the cancellation of the Credits, such

impacts are not factored in to the ratings given in the Borrower ICR.

(b) Co-financiers

129. The draft report was sent to DFID for comment but comments have not been received to

date.

(c) Other partners and stakeholders

130. There were no other comments received.

Page 48: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

34

Annex 1. Project Costs and Financing

(a) Project Cost by Component (in US$, millions equivalent)

Components

Appraisal

Estimate

(US$,

millions)

AF Estimate

(US$,

millions)

Actual/Latest

Estimate

(US$,

millions)

Latest %

of

Appraisal

Latest %

of Revised

Estimate

A. Road Investments 162.1 235.1 140.7 86.8 59.8

B. Enhanced Road Safety 4.5 4.5 2.1 46.7 46.7

C. Urban Transport Planning 4.5 4.5 4.1 91.1 91.1

D. Institutional Support (Government) 10.9 10.9 5.8 53.2 53.2

E. Institutional Support (UNRA) 16.0 18.0 12.5 78.1 69.4

Total Project Costs* 198.0 273.0 165.2 83.4 60.5

Total Financing Required 198.0 273.0 — — —

Note: *Including physical and price contingencies.

(b) Financing

Source of Funds

Appraisal

Estimate

(US$,

millions)

Revised

Estimate at

AF (US$,

millions)

Actual/Latest

Estimate (US$,

millions)

Latest % of

Appraisal

Latest % of

Revised

Estimate

IDA 190.0 265.0 159.1 83.7 60.0

DFID 8.0 8.0 6.1 76.2 76.2

Page 49: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

35

Annex 2a. TSDP Outputs by Component

Original Components at Appraisal

Component A: Road Investments

Project Surfacing Contract Progress Land and Property

Compensation

Gulu-Atiak (74

km)

Surface

dressing

Works contract:

UGX 89.669 billion

Supervision contract:

€928,027

RAP contract:

UGX 317.486 million

Commenced in February

2012. The project is nearly

completed. Major works on

the Gulu Municipal road to

the airport and cathedral have

also been completed; the

contractor is finalizing

drainage works and

correction of defects within

Gulu town.

The project was completed on

January 30, 2015; the

performance certificate was

issued on May 20, 2016.

Approved value:

UGX 10.262 billion;

Amount paid

UGX 10.140 billion;

Valued PAPs 2,027;

paid PAPs 1,884;

percentage: 92.94

Vurra-Arua-

Oraba (92 km)

Surface

dressing

Works contract:

UGX 138.861 billion

Supervision contract:

US$2.108 million,

revised to US$2.362

million

RAP contract:

UGX 396.599 million

Approved value:

UGX 18.396 billion;

Amount paid

UGX 16.827 billion.

Valued PAPs 3,935;

paid PAPs 3,276;

percentage 83.20

1. The Gulu-Atiak road, which lies entirely in the Acholi region of Uganda, is part of the

northern corridor route that links South Sudan to the port of Mombasa. It is a strategic road as it

is the main gateway for trade between Uganda and Southern Sudan to bolster regional

integration. The road also provides links to Moyo and Adjumani districts in northern Uganda.

Physical works progress of major works is 100 percent complete. The Vurra-Arua-Oraba road is

part of the national road network linking northeastern Democratic Republic of Congo and

southwestern Sudan to the port of Mombasa. It is situated in the northwestern part of Uganda

stretching northward parallel to the Uganda-Democratic Republic of Congo border and connects

with South Sudan close to where the borders of Uganda, South Sudan, and Democratic Republic

of Congo converge.

Preparation of Road Design and Bidding Documents

2. Component A also financed consultancy services for feasibility study, the ESIAs, and

detailed engineering design for the reconstruction and upgrading of the following roads:

(a) Tororo-Mbale-Soroti-Lira-Kamdini road (340 km): The contract was signed in

May 3, 2013. The contract was amended on October 3, 2013, to allow the consultant

to assess the corridor and prepare a long-term OPRC for the Tororo-Mbale-Soroti-

Lira-Kamdini road. The consultant has submitted all the reports, which were the

basis for the preparation of the NERAMP.

Page 50: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

36

(b) Kafu-Karuma-Kamdini road (104 km): The contract was signed on April 23,

2013, and the consultant submitted the final detailed engineering design on

September 29, 2014.

(c) Zirobwe-Wobulenzi road (23 km): The contract was signed on September 25,

2013, and was amended to cater for an extended scope of services. The consultant

submitted the final documents for the detailed engineering design, bidding

documents, ESIAs, and RAP.

(d) Kamdini-Nebbi-Goli and Ayer-Bobi road (230 km): The contract was signed on

May 3, 2013, for the Lira-Kamdini-Gulu road (148 km) road. However, because of

the proposed plan to have Tororo-Kamdini corridor as an asset management

contract, the scope of service for this contract was amended to enable the consultant

to prepare design and bidding documents for the rehabilitation of the Kamdini-

Karuma-Olwiyo-Pakwach-Nebbi road (161 km) and for upgrading of Nebbi-Goli

(15 km) and Ayer-Bobi (54 km) road to paved bitumen standard. The consultant has

submitted the final documents for the detailed engineering design, bidding

documents, ESIAs, and RAP.

Revised Component at AF

Project Funder Surfacing Contract Progress Land and Property

Compensation

Kamwenge-

Fort Portal

road (66 km)

World

Bank/

GoU

Surface

dressing

Works contract:

UGX 117.942

billion

Supervision

contract:

€1.929 million

(UGX 1.142

billion)

RAP contract:

UGX 961.150

million

Civil works commenced in

August 2013, originally

scheduled for completion in

January 2016.

Cumulative progress as of

October 2016 was 83.9

percent against a plan of

100 percent. Time elapsed

was 130 percent.

The project encountered

challenges regarding

adherence to environmental

and social safeguard

standards, resulting in

cancellation of funding by

the World Bank in

December 2015.

Approved value:

UGX 9.121 billion

Amount paid:

UGX 8.228 billion

Valued PAPs: 2,844

Paid PAPs 2,246

Supplementary valuation

report 3 approved

number added in the

total above.

Verification and

disclosure is completed;

preparations of payment

are batches ongoing.

3. The additional IDA credit in the amount of US$75 million was approved in May 2011 to

scale up the project to include the paving of the Kamwenge-Fort Portal road (66 km). This road

connects Western Uganda to the Northern Corridor and the Trans-Africa Highway.

Page 51: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

37

Distribution of Funds by Components

Components Works

Total Contract

Amount, US$ (at

Contract Rate)

Total Cumulative

Amount, US$ (Paid

up to May 31, 2016)

Component A: Road Investments: Upgrading and Rehabilitation of National Roads

A1.1 Construction of gravel to bitumen of Gulu-Atiak

road (74 km) 55,188,698.00 49,477,370.00

A1.2 Construction supervision of Gulu-Atiak road 1,991,613.71 1,537,580.72

A1.3 Construction of Vurra-Arua-Oraba road works

(85 km) 58,331,426.00 56,616,495.00

A1.4 Construction supervision of Vurra-Arua-Oraba

road works 2,669,480.00 2,666,226.00

A1.5 Construction of Kamwenge-Fort Portal road

works (66 km) 47,310,635.00 21,857,069.00

A1.6 Construction supervision of Kamwenge-Fort

Portal road 2,891,169.00 2,285,465.00

A1.7

Assessment and preparation of an asset

management contract for Tororo-Mbale-Soroti-

Kamdini road (340 km)

2,193,253.00 2,029,914.00

A1.8

Design and bidding documents for full

reconstruction of Kamdini-Pakwachi-Nebbi-

Arua road

2,384,279.00 1,077,994.00

A1.9 Consultancy services design update of Zirobwe-

Wobulenzi road (23 km) 498,215.00 409,560.00

A1.10

Consultancy services for feasibility study and

detailed engineering design for Kafu-Karuma-

Kamdini road (104 km)

1,211,079.00 1,101,028.00

Component B: Enhanced Road Safety

B.1 Support to putting in place the NRSA and road

safety enhancing measures 466,808.00 419,465.38

B.2 Preparation of draft bill for the NRSA 39,126.71 1,914.35

B.3 Making the crash database operational 2,068,595.06 1,504,518.51

Component C: Urban Transport Planning: Preparation of Kampala Urban Transport Project

C.1 Preparation of Phase 1 of the Kampala BRT

studies 4,215,293.76 3,691,928.45

C.2 Support to start up MATA 408,305.73 408,305.73

Component D: Institutional Support to Ministry of Works and Transport

D.1 Support to policy and planning division/NTPS 682,676.30 682,676.30

D.2 Support to the Ministry for Software

Development for the TSDMS 60,138.35 46,473.92

D.3 Inland Water Transport Legislation 486,810.00 486,810.00

D.4 Support to start up MTRA Nil Nil

D.5 Assistance to DUCAR agency 3,319,200.00 2,821,477.76

D.6

Support to other core MoWT functions -

preparation of detailed strategic implementation

plan for the NTMP/GKMA

632,047.08 632,047.08

D.7 Support to other core MoWT functions - training 127,443.72 127,443.72

D.8 Support to MoWT supply of information

technology equipment 1,298,932.06 958,548.44

Component E: Institutional Support to UNRA

E.1

Consultancy services (design and construction

supervision) for the renovation and upgrading of

five UNRA station offices to regional offices

443,336.00 85,343.00

Page 52: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

38

Components Works

Total Contract

Amount, US$ (at

Contract Rate)

Total Cumulative

Amount, US$ (Paid

up to May 31, 2016)

design completed, but works not tendered.

Supervision will extend into 2016.

E.2 Technical assistance to UNRA

E.2.1 Technical assistance for capacity-building

support to UNRA 3,490,595.00 2,442,027.00

E.2.2 Asset management support to UNRA (2 years) 1,689,811.04 992,681.29

E.2.3 Technical assistance to UNRA - Axle Load

Control Advisor 836,513.00 836,513.00

E.2.4 Technical assistance to UNRA - Procurement

Consultant 522,812.00 522,812.00

E.2.5 Technical assistance to UNRA - Procurement

Specialists 297,000.00 188,765.00

E.2.6 Technical assistance to UNRA - ferry services 120,000.00 100,000.00

E.2.7 Technical assistance to UNRA -

Communications Specialist 118,800.00 118,800.00

E.2.8

Consultancy services for establishing and

developing a Technical Audit Unit in the

Directorate of Internal Audit, UNRA

1,661,172.00 1,538,166.00

E.2.9 Preparation of ICR 25,600.00 25,600.00

E.2.10 Preparation of road investment priority list by

individual consultant 6,400.00 6,400.00

E.2.11 Recruitment of six consultants to fill technical

skills gap in three Directorates (two in each) 147,762.00 147,223.00

E.3 Studies

E.3.1 National Roads Data Collection Study

(Implementation of RMS and Addendum No. 1) 3,831,725.13 2,085,883.00

E.3.2 GIS-based Rights-of-Way Management

Information System 1,295,595.46 1,252,118.53

E.3.3 Development of UNRA's Communication

Strategy 150,000.00 43,566.00

E.4 Training

E.4.1 Training in accordance with the approved

UNRA Training Plan 1,407,425.00 1,407,425.00

E.4.2 Asset management/OPRC Best Practice Study

visits 179,122.00 179,122.00

E.5 Equipment

E.5.1 Three heavy-duty scanners 94,500.00 94,500.00

E.5.6 Equipment for GIS-based ROW MIS 190,000.00

E.5.7 Vehicles 448,155.00 448,155.00

E.6 Operating costs

E.6.1 Incremental Operational Costs because of

UNRA’s function as implementing agency 1,000,000 124,799.00

Total of all components 206,431,548.11 163,480,210.18

Page 53: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

39

Institution Key Issues to be

Addressed World Bank EC DFID DANIDA Total

MoWT

Sector policy setting

Strategic planning

Sector oversight

Transport regulation

Sector monitoring

Road safety capacity

Adjustment of legal

framework

US$0.4 million

under RSDP-3

for TA

US$7.9 million

support to

MoWT under

the TSDP

US$3.5 million

for road safety

under the TSDP

— US$4.0 million support to

World Bank TSDP —

US$15.8

million

DUCAR

Strategy for district

road management

Planning, budgeting,

and expenditure

management

Technical oversight

Monitoring

Support to DUCAR

included in the

above

— Support to DUCAR

included in the above

Long-term

advisor to

DUCAR

division in

MoWT

(US$2.0

million)

US$2.0

million

Road Fund

(Ministry of

Finance)

Establishment of Road

Fund Secretariat

Regulations

Operating procedures

Financial management

systems

Monitoring systems

US$2.6 million for TA to

work in coordination with

DFID support

— — US$2.6

million

Page 54: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

40

Institution Key Issues to be

Addressed World Bank EC DFID DANIDA Total

UNRA

UNRA management

Road network

management

Procurement, MIS

Contract/bridge

management

Ferry operations

Axle load control

US$2.6 for TA;

US$ 12m for

regional offices

US$6.2 million for TA (to

work in coordination with

DFID and World Bank

support)

US$4.0 million support to

World Bank TSDP

US$24.8

million

National Road

Construction

Industry

Strengthening of

contractors and

consultant associations

Business development

Technical skills

Contract management

Code of conduct

US$4.3 million for TA to

work in coordination with

DFID support

US$15.8 million for project

to promote markets for

northern corridor

integration to work in

coordination with EC

support

US$20.1

million

Total

Total planned

expenditure

US$26.4 million,

of which US$3.0

million for RSDP-3 US$13.l million US$23.8 million

US$2.0

million

US$65.3

million

Source: PAD TSDP, page 26.

Note: DANIDA = Danish International Development Agency; TA = Technical Assistance.

Page 55: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

41

Annex 2b. Operational Risk Assessment Framework

No. Description

(MoWT Transport Sector Performance Report 2014–15) June 2011 June 2012

Actual

June 2013

Actual

June 2014

Target

June 2015

Actual

June 2015

Roads

1 Road network in fair to good condition (%)

National roads (paved) - fair to good 74 77.6 77.0 80.0 78 80.0

National roads (unpaved) - fair to good 64 66.6 66.0 68.0 68 70.0

District roads (unpaved) - fair to good 55 65.0 65.3 50.5 55 57.8

Urban roads (paved) - fair to good 50 61.0 73.7 58.2 — 58.0

Urban roads (unpaved) - fair to good 55 44.0 44.7 48.5 — 47.0

KCCA roads (paved) - fair to good 11 — 35.0 48.0 50 49.0

KCCA roads (unpaved) - fair to good 48 — 60.0 60.0 62 61.0

2 Paved road network (km)

National roads 3,264 3,317 3,489 3,795 4,000 3,981.0

Urban roads 684 824.0 745.0 745.0 — 745.0

KCCA 416 422.0 463.0 483.5 495 498.0

3 Road safety

Total fatalities (road deaths) 2,954 3,343 3,124 2,937 — 2,845.0a

Fatalities per 10,000 vehicles 46 45.0 36.0 30.0 — 26.0

Total registered vehicles 635,656 739,036.0 865,823.0 974,714.0 — 1,102,021.0

4 Road service level - travel time (minutes/km)

On national roads n.a. 1.18 1.15 1.01 — 1.15

Note: a. All data on road fatalities is for the previous calendar years as opposed to the financial year from Uganda Police.

Page 56: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

42

Table 2.3. Additional Financing of the Transport Sector Development Project

Project Development Objective:

The PDO is to improve the connectivity and efficiency of the transport sector through (i) improved condition of national road network; (ii) improved capacity for

road safety management; and (iii) improved transport sector and national road management.

PDO-level Results Indicators:

1. Average vehicle operating costs on targeted roads (US$ per vehicle km)

2. Travel time on targeted routes (hours)

3. Roads in good and fair condition as a share of total classified roads (percentage) - core indicator

4. Share of rural population with access to an all-season road (percentage) - core indicator

5. Annual rate of road accident fatalities (percentage)

6. Direct project beneficiaries (number), of which female (percentage)

7. Roads rehabilitated, non-rural - core indicator

Risk Category Risk

Rating Risk Description Proposed Mitigation Measures

1. Project

stakeholder risks M-I

Experiences have shown that compensation for land and

properties did not move ahead as planned, thus delaying

some road projects.

An action plan was developed with UNRA before appraisal,

which included the following actions: (a) UNRA to appoint

consultants before appraisal who will implement the RAP; (b)

UNRA to ensure the consultants enhance stakeholder

awareness; (c) UNRA to ensure there are adequate resources to

meet the involuntary RAP costs and be able to timely

compensate the local people for loss of land/property and/or

income.

2. Implementing

agency risks

Page 57: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

43

Risk Category Risk

Rating Risk Description Proposed Mitigation Measures

Capacity M-L

The increased annual budget for the transport sector

(US$318 million in FY2007/08, US$542 million in

FY2008/09, and US$546 million in FY2009/10, 85 percent

of which is managed by UNRA) requires a substantial

increase in UNRA’s implementation capacity. Thus, the

need to address the following: (a) weak organizational

structure; (b) inadequate experience in procurement

management; (c) inadequate record keeping; (d) inadequate

staff numbers; and (e) delays in implementation of the

approved Procurement Plan for the main TSDP.

UNRA’s board has given approval to fill 46 vacant positions in

its various directorates. Currently, only 14 of the proposed

positions can be filled as a result of the wage cap. An action

plan to lift the cap on recurrent expenditure has been discussed

with the GoU. UNRA will also pursue the transfer of all

operational expenses related to road maintenance to a special

account to be financed by the URF, as stipulated in the Road

Fund Act.

Other actions include the following:

(a) The PDU to report directly to the Executive Director to

increase management oversight and monitoring of procurement

functions; (b) unbundle the concentration of activities in the

PDU and delegating and reassigning activities as appropriate to

functionally designated units;

(c) recruitment of a Procurement Consultant to provide hands-

on coaching and mentoring to the PDU staff; (d) introduce an

outsourced independent procurement evaluation to benchmark

and validate UNRA’s procurement actions; (e) strengthen the

internal audit functions of UNRA to provide real-time technical

audits of road projects/program implementation; (f) strengthen

the PPDA’s oversight function through the World Bank

Integrity Vice Presidency’s capacity-building initiatives; (g)

enhance mechanisms for stakeholder and external monitoring

of road projects; and (h) establish acceptable MIS for

procurement tracking.

Fraud and corruption M-I

Petty and high-level corruption are prevalent and affect

every institution in the country and are rifest in

procurement, privatization, administration of revenues and

public expenditures, and public service delivery.

Despite the Government’s purported zero tolerance policy

on corruption, few, if any, high-level officials involved in

major corruption scandals have been tried, hindering

attempts to raise the bar and address lower-level corruption.

The World Bank is working with the GoU to reinvigorate

institutions and accountability systems, rethinking

decentralization policies, and relaunching stalled public service

reform processes. The Governance and Anticorruption is a

cross-cutting pillar in the CAS 2011–15 and plans are being

built into new operations and the value for money agenda is

supported across the portfolio, including in Analytical and

Advisory Activities/Economic Sector Work, particularly the

Page 58: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

44

Risk Category Risk

Rating Risk Description Proposed Mitigation Measures

Performance Evaluation Reviews. The recently developed data

tracking mechanism provides the Government with a self-

assessment tool for corruption and governance and identifies

areas where key reforms to address governance have failed.

This will help provide pointers for better governance

arrangements in investment projects.

3. Project risks

Design M-L Capacity of UNRA to review the quality of documents

submitted by design consultants is highly constrained.

A substantial technical assistance program to strengthen the

capacity of UNRA has been built in the TSDP to address this.

Social and

environmental M-I

Relevant environmental regulations and policies are largely

in place but not adequately implemented. Capacity of the

implementing agency for environmental management,

including supervision of implementation of planned

environmental mitigation measures is lacking.

Project road crosses Kibale National Park with critically

endangered primate species including chimpanzees.

The Roads Authority retains consultants for the

implementation of RAPs and their reporting is weak and

irregular in spite of guidance provided by IDA.

Implementing agency will continue receiving capacity

strengthening assistance from the European Union. The ESIA

and RAP for the Kamwenge-Fort Portal road will guide the

road works undertaken in the AF. Implementation of the

environmental management plans and RAPs will be undertaken

by the contractor and UNRA with support of short-term

consultants respectively. Environmental mitigation measures,

as outlined in the ESIA, will be implemented, including (a) a

special, low impact regimen for road upgrade design and

activities in Kibale National Park; (b) intensive IDA

supervision; and (c) advisory monitoring of project activities in

Kibale National Park by a major conservation, NGO, or

academic entity.

Capacity building in UNRA with one additional sociologist and

all to be trained in monitoring and reporting for RAPs

implementation.

Program and donor M-I

Framework for program and donor coordination is not

strong, and proposed subcommittees of the Transport Sector

Working Group do not meet regularly.

Meetings of the Transport Sector Working Group to be held on

a monthly basis and the subcommittees to sit more frequently,

as and when needed. Progress of the previous year and program

of the following year to be discussed annually.

Delivery Quality M-I Capacity of UNRA to supervise major civil works contracts

is highly constrained.

A substantial number of technical assistants under a technical

assistance program to strengthen the capacity of UNRA has

been built in the TSDP to address this.

Overall Risk Rating at

Preparation

Overall Risk Rating During Implementation Comments

M-I M-I

Page 59: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

45

No. Issue Actions

1 Compensation

(a) Provide the World Bank with a comprehensive report including strip maps on the

compensation status of the PAPs on the Kamwenge-Fort Portal road, including

number of PAPS in original, first supplementary, second supplementary, and third

supplementary; location of PAPs by chainage; and type of compensation impact,

cost, and progress in payments; and

(b) 100 percent compensation of PAPs by December 31, 2015.

2 Road safety

(a) All safety signage and speed humps along the road installed as per the engineer’s

instructions;

(b) PAPs living in houses in precarious conditions compensated, relocated, and

houses demolished in km 193+535, km 150+750, km 156;

(c) Proper safety barriers erected in areas with heavy excavations on the road or at

high embankment locations and not the single run tape provisions currently in place;

(d) Prepare and implement a robust Traffic Management Plan; and

(e) Undertake road safety campaigns.

3 Child protection

(a) Sign contract on expanded Terms of Reference with the HIV service provider to

undertake child protection work, including collaborations as necessary with other

competent persons and institutions to deliver this priority task;

(b) Implement the child protection activities specified in the contract, including but

not limited to sensitization, awareness campaigns, liaising with schools, health

centers, sensitization of contractor’s workers, liaising with local communities,

MoGLSD, parents, crime preventers, linking to legal services, liaising with police

on prevention and prosecution, and preparation and display of zero tolerance

materials toward child protection.

4

Employment

contracts,

workman’s

compensation,

identity cards

(a) Prepare and sign contracts with workers that are compliant with the national

labor laws,

(b) Document all payments paid to accident victims (both workers and members of

the public) in accordance with the national laws and the contract,

(c) Maintain the accident log and status on follow-up of claims, and

(d) Provide all workers with identity cards.

5 Sexual harassment

(a) Provide a copy of the sexual harassment policy,

(b) Implement the zero tolerance toward sexual harassment policy including

sensitization of all contractor’s workers, and

(c) Provide gender-separated facilities.

6 General health and

safety

(a) Register workplace with the MoGLSD;

(b) Prepare and implement an Occupational Health and Safety Plan, eecruit a

competent Occupational Health and Safety Officer;

(c) Provide Occupational Health and Safety training to all workers;

(d) Provide drinking water, bath, changing, and sanitation facilities (including

gender separated facilities) to workers; and

(e) Provide appropriate and adequate Personal Protective Equipment to all workers

and ensure its use by all the workers.

7

Grievance Redress

Committees

(GRCs)

(a) Ensure adequate facilitation (stationery) and working of the GRCs; and

(b) Prepare monthly progress report on their functionality, complaints received, and

status of resolution.

8

Communication

and Community

Engagement Plan

(a) Prepare and implement a Communication and Community Engagement Plan that

ensures that communities are informed of road activities, receive feedback on the

status of their compensation, and can also air other concerns related to the project

road that the GRCs cannot handle or resolve at the community level; and

(b) Ensure non-retaliation of community members, workers, or other parties who

have raised complaints.

9 HIV/AIDS

sensitization

(a) Ensure implementation of HIV/AIDS service provider work according to the

contract with timely payment of the service provider and review the work

Page 60: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

46

No. Issue Actions

awareness and

education

undertaken to ensure compliance with national standards.

10

General ESMP and

associated social

and environmental

requirements

(a) Undertake actions included in the ESIA, 2011 ESMP, and the contractor’s 2014

ESMP: (i) take reasonable precautions to prevent unlawful conduct on by its

employees; (ii) provide accommodation for workers in a camp; (iii) prepare and

implement a Gender Action Plan which includes gender sensitization for

communication and conduct toward women; (iv) retain an environmental and social

specialist on site; (v) provide separate bath and toilet facilities for men/women; (vi)

allocate certain jobs to women; (vii) implement an HIV prevention and awareness

program; (viii) prohibit child labor; (ix) institute and enforce a policy to prevent

sexual harassment; and (x) establish a community liaison; and

(b) Comply fully with NEMA conditions of approval for operation of quarries and

other work sites, including not blasting before compensating people living within a

500 m safety radius; wet crushing, proper waste material disposal, proper licensing,

operation and restoration of borrow pits, quarries, dump sites, and other work sites;

and

(c) Comply with the project environmental requirements and the Uganda Wildlife

Authority approvals for work undertaken in Kibale National Park.

11 Drainage and

access

(a) Address drainage and access provision issues as per engineer’s instructions and

community requests.

12 Work resource

mobilization

(a) Mobilize adequate, good working equipment and competent personnel as per

contract requirements and engineer’s instructions.

Page 61: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

47

Annex 3. Economic and Financial Analysis

Project Efficiency

1. Appraisal: Economic Evaluation of the Upgrading of the Gulu-Atiak road (74 km)

1.1 Project Costs

1. Economic analyses for the upgrading of the Gulu-Atiak road at appraisal were undertaken

using the Highway Development and Management Model (HDM-4). The analyses were based

on economic costs, excluding taxes and duties. The economic costs were assumed to amount to

91.9 percent of financial costs and the discount rate used was 12 percent. The appraisal period

was 25 years. No shadow pricing of unskilled labor was undertaken.

2. Before the improvement, the road had a gravel surface in poor condition. The subprojects

comprised the construction of a new sub-base, base, and a bituminous surfacing for the main

carriageway and its shoulders; upgrading the road furniture; and the installation of drainage

structures. Two alternative design standards were defined for the road: Alternative A - DBST on

200 mm crushed stone-base course, 150 mm mechanically stabilized sub-base, and 150 mm

natural gravel subgrade and Alternative B - 50 mm asphalt concrete on 200 mm crushed stone-

base course, 150 mm mechanically stabilized sub-base, and 150 mm natural gravel subgrade.

Alternative A was found to be the less costly option. The financial costs for the upgrading of this

road project are summarized in table 3.1.

Table 3.1. Financial Costs of Upgrading Gulu-Atiak Road Project at Appraisal

Description Length

(km)

Total Cost (US$, millions) Cost/km (US$)

Alternative A Alternative B Alternative A Alternative B

Gulu-Lacor

Lacor-Atiak

11

63

9.0

51.6

11.0

63.0

818,919

818,919

1,000,000

1,000,000

Total 74 60.6 74.0 818,919 1,000,000

3. The maintenance regimen adopted for each alternative was a scheduled routine and

standard periodic maintenance. Total maintenance costs were approximately the same for

alternatives A and B. Traffic growth from 2010 to 2023 was assumed as 6 percent a year and

3 percent thereafter for all vehicle types. The road project road was split into two sections for

economic analysis, with a separate assessment of traffic for each link The HDM-4 analysis was

based on economic factors alone to calculate the viability of the proposed works. The results

were predominantly influenced by road roughness, which was greatly improved because of the

pavement upgrading.

1.2 Results of the Economic Analysis at Appraisal

4. The results of the economic analysis are set out in table 3.2. The analysis indicated that

for both Alternatives A and B, road upgrading for the two road sections was economically

Page 62: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

48

feasible with an EIRR well in excess of the 12 percent economic feasibility threshold. The

combined result for Alternatives A and B on all the sections gave NPVs (at a 12 percent

discount rate) of US$25.68 million and U$16.91 million, respectively. The approximate overall

EIRR for the combined projects under Alternative A was 18.l percent, while that for Alternative

B was 15.5 percent.

Page 63: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

49

Location Alternative

Surface Type

Length

(km)

Pavement

Width Initial

Roughness

(IRI m/km)

Base

Year

2007

ADDT

Range

Revised Financial Costs Revised Economic

Analysis

Existing Appraised Existing New

Total Cost

(US$,

millions)

Cost per km

(US$)

NPV at 12%

(US$,

millions)

NPV/Cost

Ratio

Gulu-

Lacor

A

B

Gravel

Gravel

DBST/CSB

AC/CSB

11

11

5.0

5.0

9.5

9.5

14.0

14.0

779

779

9.008

11.000

818,919

1,000,000

13.94

12.56

1.548

1.142

Lacor-

Atiak

A

B

Gravel

Gravel

DBST/CSB

AC/CSB

63

63

5.0

5.0

9.5

9.5

17.0

17.0

330

330

51.592

63.000

818,919

1,000,000

11.74

4.36

0.228

0.069

Note: AC = Asphalt Concrete; ADDT = ; CSB = Crushed Stone-Base; IRI = International Roughness Index; Economic costs in the economic analysis were

calculated to be 91.9 percent of financial costs. The combined project EIRRs are derived from the HDM-4 output tables.

Page 64: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

50

1.3 Sensitivity Analysis

5. The sensitivity analyses undertaken examined the impact on the economic feasibility of

assuming 20 percent lower traffic, 30 percent higher investment costs, and a worst-case scenario

combining 20 percent lower traffic and 20 percent higher investment costs. The analyses

indicated that all sections using Alternative A would remain economically feasible, even with 20

percent higher investment costs and 20 percent lower traffic. However, the more expensive

Alternative B was uniformly more uneconomical because of its higher overall investment costs.

Alternative A was selected as a more robust investment.

2. Appraisal: Economic Evaluation of Upgrading of Vurra-Eruba, Arua-Oraba road (85

km)

2.1 Project Costs

6. Economic analyses for the upgrading of the Vurra-Eruba-Arua-Oraba road at appraisal

were undertaken using HDM-4 on the same basis as for the Gulu-Atiak road. The existing road

in this case was a gravel road in fair condition. Base year (2009) traffic estimates and subsequent

traffic growth assumptions are used for the economic analysis, as shown in tables 3.3 and 3.4.

Road Section Vurra-Eruba Arua-Manibe Manibe-Koboko Koboko-Oraba

Motorized 422 1,584 694 1,685

Bicycles 1,140 2,735 422 1,567

Pedestrians 536 1,430 1,021 2,122

Analysis Period Vurra-Arua Eruba-Arua-Manibe Manibe-Koboko Koboko-Oraba

Existing Surface Type Unpaved Paved Unpaved Unpaved

Growth Rate Passenger Freight Passenger Freight Passenger Freight Passenger Freight

>

2012–16 7.6 7.3 7.4 5.3 7.6 5.3 7.6 8.1

2017–26 7.0 6.0 6.0 5.0 7.0 6.0 7.0 6.0

2027 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0

7. The project road was split into six links for the economic analysis, with separate

assessments of traffic for each link. The HDM-4 analysis is based on economic factors alone to

calculate the viability of the proposed works.

Results of Economic and Sensitivity Analysis at Appraisal

8. The results of the revised economic analysis by alternative are set out in Table 3.5. The

analysis undertaken using HDM-4 indicates that each upgrading alternative for the two road

sections is economically feasible, with EIRRs well in excess of the 12 percent economic

feasibility threshold. A combined result for all the road sections is given in table 3.5. Alternative

A, which has the highest NPV of US$53.96 million and an EIRR of 21.2 percent, made it the

selected option for the detailed design. The analysis by section revealed that the Vurra­Eruba

section failed with an NPV of −US$2.11 million and EIRRs below the 12 percent discount rate

of 5.5 percent. All other sections had positive NPVs and EIRR above 12 percent. The sensitivity

Page 65: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

51

analyses indicated that all sections using Alternative A would remain economically feasible,

even with 20 percent higher investment costs and 20 percent lower traffic.

Table 3.5. Summary of Economic Analysis by Alternative

Alternatives NPV (US$, millions) EIRR (%)

Alternative

Carriageway

A – DBST with 6.5 m wide 53.96 21.2

Alternative B - AC with 6.5 m wide carriageway 47.36 19.4

Note: AC = Asphalt Concrete.

3. Additional Financing: Economic Analysis for the Kamwenge-Fort Portal Upgrading (66

km)

9. The economic analysis of the additional works for upgrading the Kamwenge-Fort Portal

road was also carried out using HDM-4 and was based on the estimated costs from the design

stage and the projected traffic volume. Financial costs were determined for each section and

converted to economic costs by applying a conversion factor of 83 percent based on UNRA’s

procedural guidelines. The period of analysis was 20 years, with cost and benefits discounted at a

rate of 12 percent using benefit categories of savings in vehicle operating costs, timesaving, and

induced agricultural production. Traffic volumes were 1,569 motorized vehicles per day and 788

nonmotorized vehicles per day (mainly bicycles). A sensitivity analysis was also conducted by

varying investment costs and traffic growth. In the worst-case scenario (combining −20 percent

traffic and +20 percent costs), overall project NPVs/EIRRs for the Kamwenge-Fort Portal road

were US$-5.7 million and 13.2 percent, respectively.

10. On the other hand, an EIRR of 13.4 percent and NPV of US$20.5 million were obtained

when a corridor-wide (that is, Nyakahita-Kazo-Kamwenge-Fort Portal) sensitivity analysis is

done. The sensitivity analysis results indicate that even in the worst-case scenario of lower

traffic growth rate of 20 percent and higher investment cost of 20 percent, upgrading the

Kamwenge-Fort Portal road to bitumen standard offers robust results—that is, with an EIRR of

13.2 percent, which is higher than the economic viability threshold of 12 percent. The economic

analysis results indicate that the project is economically viable. The economic analysis (base

case) showed the preferred option to be DBST, on crushed stone aggregate base and natural

gravel sub-base, with an EIRR return of 16.8 percent and NPV of US$19.9 million. For the

corridor, the EIRR was 19.6 percent and the NPV was US$117.4 million, as summarized in table

3.6.

Road Link and intervention NPV@12%

(US$, millions) EIRR (%)

Kamwenge-Fort Portal road (DBST) 19.9 16.8

Project corridor 117.4 19.6

4. Results at Completion

Gulu-Atiak Project Analysis Results

Page 66: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

52

11. The economic evaluation results of the DBST base case cost-benefit analysis, considering

the final completion economic cost of construction of US$563,182 per km and the central 2014

Annual Average Daily Traffic for the entire road, indicated an EIRR of 28.3 percent. The NPV

was US$65.09 million. The EIRR is above the cutoff rate of return of 12 percent opportunity cost

of capital in Uganda and thus, confirms the viability of the intervention in the project.

Vura-Arua-Oraba Project Analysis Results

12. The economic evaluation results of the DBST base case cost-benefit analysis, considering

the final completion economic cost of construction of US$612,100 per km and the central 2014

AADT traffic for the entire road, indicated an EIRR of 18 percent. The NPV was US$22.507

million. The EIRR is above the cutoff rate of return of 12 percent opportunity cost of capital in

Uganda and thus, confirms the viability of the intervention in the project.

Kamwenge-Fort Portal Project Analysis Results

13. The economic evaluation results of the DBST base case cost-benefit analysis, considering

the final completion economic cost of construction of 737,955 per km and the central 2014

AADT traffic for the entire road, indicated an EIRR of 9.7 percent. The NPV was US$ −6.196

million. The EIRR is below the cutoff rate of return of 12 percent opportunity cost of capital in

Uganda. However, this result may be disregarded because the project was not actually completed

at closure.

Table 3.7. Summary of Base Case Economic Evaluation Results at Completion

Road Section Investment Cost

(US$, millions)

Economic Cost

Per Km

NPV

(US$,

millions)

EIRR

(%)

Gulu-Ataik (74 km) road 49.03 563,182 65.089 28.3

Vurra-Arua-Oraba road (85km) 61.21 612,100 22.507 18.0

Kamwenge-Fort Portal (66 km) road 57.30 737,955 −6.196 9.7

Source: UNRA 2016 HDM4 Project Completion Results.

Operational and Administrative Efficiency

14. The project has been characterized by delays. The MTR reported that most components

were behind schedule; the Trust Fund Administrative Agreement took 23 months before

approval, by which time the value of DFID Grant had shrunk by 30 percent because of exchange

rate fluctuations. At the AF, steps were taken to improve procurement capacity; however, by

closure, most of the reforms in the transport sector had still not been completed. The Kamwenge-

Fort Portal road could only have been completed using IDA finance if a further extension of the

closing date had been approved, but this did not happen as the Credit was cancelled.

Page 67: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

53

Annex 4. Bank Lending and Implementation Support/Supervision Processes

(a) Task Team members

Names Title Unit Responsibility/

Specialty

Lending

Nina Chee Regional Safeguards Adviser OPSPF

Martin Fodor Sr. Environmental Specialist

Grace Nakuya Musoke

Munanura Senior Procurement Specialist GGO01

Faith-Lucy Matumbo Program Assistant AFCE1

Richard Olowo Lead Procurement Specialist GCFKE

Nina M. Jones Program Assistant AFTTR -

HIS

Agnes Kaye Program Assistant AFMUG

Labite Victorio Ocaya Sr Highway Engineer AFTU1 -

HIS

Dieter E. Schelling Consultant GSURR

Paul Kato Kamuchwezi Sr. Financial Management Specialist GGO31

Zemedkun Girma Tessema Sr. transport Specialist GTI07

Constance Nekessa-Ouma Social development Specialist GSU07

Subhash C. Seth Consultant GTI06

Supervision/ICR

Richard Martin Humphreys Lead Transport Economist GTI01

Negede Lewi Sr Highway Engineer GTI01

Peter Nigel Freeman Consultant GTI01

Stephen Muzira Sr. Transport Specialist GTI01

Paul Kato Kamuchwezi Sr Financial Management Specia GGO31

Agnes Kaye Program Assistant AFMUG

Grace Nakuya Musoke

Munanura Senior Procurement Specialist GGO01

Labite Victorio Ocaya Sr Highway Engineer AFTU1 -

HIS

Subhash C. Seth Consultant GTI06

Celi Marie Dean Temporary GTI01

Barbara Nalugo Program Assistant AFMUG

Constance Nekessa-Ouma Social Development Specialist GSU07

Franklin Mutahakana Sr. Operations Officer AFMUG

Herbert Oule Sr. Environment Specialist GEN01

Shamiela Saeki Mir Communications Officer ECRIM

Sheila Byiringiro AFREC

Zemedkun Girma Tessema Sr. Transport Specialist GTI07

Page 68: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

54

(b) Staff Time and Cost

Stage of Project Cycle

Staff Time and Cost (Bank Budget Only)

No. of staff weeks USD Thousands (including

travel and consultant costs)

Lending

FY05 0.18 3.30

FY06 0.0 4.26

FY07 0.0 0.0

FY08 8.56 48.76

FY09 25.19 130.1

FY10 30.78 171.8

Total: 64.71 358.22

Supervision/ICR

FY10 5.72 27.3

FY11 21.18 71.4

FY12 30.47 70.9

FY13 31.75 112.3

FY14 20.89 83.4

FY15 19.98 101.3

FY16 43.96 272.4

FY17 12.5 146.2

Total: 186.45 885.2

Page 69: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

55

Annex 5. Summary of Borrower's ICR34

and/or Comments on Draft ICR

1.1. Introduction

1. This document is the contribution of the GoU ICR of the TSDP, which was co-financed

by IDA and DFID through Credits and a Grant, respectively. The GoU and the DPs attached

great importance toward the achievement of the PDOs. The ICR provides an evaluation of the

TSDP implementation and operation against the costs and benefits that have been derived from

the project finances. The ICR also provides an assessment of lessons learned, the financiers’

performance in relation to their respective obligations under the financing agreements, and the

extent to which the purpose of the finances were achieved. It is intended that the project

performance data provided in this ICR will assist the World Bank in the preparation of its final

ICR.

1.2. Context at Appraisal

2. In 1996, the GoU, with the assistance of DPs, formulated the first 10-year (1996/97–

2005/06) RSDP Phase 1. In April 2002, RSDP Phase 1 was updated and rolled over to the

second 10-year RSDP Phase 2 (2001/02–2010/11) and its total estimated cost was increased

from the original US$1.5 million to US$2.3 billion. An MTR of RSDP Phase 2 was carried out

in 2007/08 to assess the pace of implementation. The findings and lessons drawn from RSDP

Phase 2 were to be used in the preparation of RSDP Phase 3 (2009/10–2018/19). It had been

planned to continue with a fourth phase (RSDP Phase 4) that would have financed those RSDP

Phase 3 projects that could not be financed because of cost increases. During a bilateral meeting

between MoWT and IDA on October 7, 2008, it was decided that the GoU could finance most of

these items through an increased road sector allocation.

3. The road component of the proposed TSDP was intended to support a three-year period

(2010/11–2012/13) of the Five-Year National Roads Development and Maintenance Plan

prepared by UNRA as an interim investment plan. The TSDP was aimed at improving the sector

performance through contributing jointly with other DPs in a sector wide approach. The TSDP

was intended to be the first in a series of proposed transport sector projects that would

individually support three-year rolling plans of the overall road transport investment and reform

program. Total financing of the TSDP was US$198 million, with IDA supporting the project

with Credits of US$190 million and a Grant of US$8 million from DFID.

1.3. Project Development Objective and Key Indicators

4. An SIL-financed the TSDP. This instrument was selected as the most appropriate to

support sector reforms and capacity building, complemented by targeted infrastructure

investment, all to be accomplished within a defined period.

5. The key development objective of the TSDP was to improve the performance of the

transport sector in Uganda to enhance economic growth and reduce poverty through (a)

reduction of transport costs and travel times on major corridors, (b) improvement of road safety,

34

To avoid duplication, details on outputs and funds per component and economic and financial analysis are to be

found in annex 2A and 3.

Page 70: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

56

and (c) enhancement of sector management capacity.

6. The project outcome indicators included the following:

(i) The reduction of transport costs and travel times on major road corridors and

enhancing regional connectivity

(ii) Share of national roads in poor condition decreased

(iii) Percentage of rural population with access to an all season road in the target area

increased

(iv) Decline in annual rate of growth of accident fatalities

1.4. Key Project Data

Project ID Type Credit/Grant

No.

Approval

Date

Financing

Agreement

Signing

Effectiveness

Date

Closing

Date

Amount

(US$,

millions)

P092837

Credit IDA-49790 December

10, 2009

February 3,

2010 July 15, 2010

January

31, 2016 190.00

Grant TF-11094 April 6,

2010

March 27,

2012 March 27, 2012

June 30,

2014 6.15

AF Credit IDA-46790 June 16,

2011 June 5, 2012

October 22,

2012

January

31, 2016 75.00

Total

Amount 271.15

1.5. Risk Assessment and Mitigation at Appraisal

7. The following are the critical project risks and proposed mitigation strategies:

Description of Risk Why is it Important? Risk

Rating Mitigation Measures

Residu

al Risk

The URF is not

operational as per the

law. One of the

requirements of the

Road Fund Law is

that user charges are

being transferred

directly from the

source to the URF on

a monthly basis.

The URF is essential for

the sustainability of the

road network. The URF is

expected to provide a

consistent flow of finance

for maintenance. This will

help develop the local

construction industry.

M

The URF, with the MoFPED

approval, will cover the funding for

that maintenance of the project. The

MoFPED has already committed to

secure the budget allocation for the

project while UNRA will prioritize

the project among other maintenance

requirements.

L

Page 71: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

57

Description of Risk Why is it Important? Risk

Rating Mitigation Measures

Residu

al Risk

UNRA’s constrained

implementing

capacity

The increased annual

budget allocation for the

national roads subsector

(from an average for

US$100 million from

2001/02 to 2007/08 to

about US$500 million

from 2008/09 to 2014/15)

requires a substantial

increase in UNRA’s

implementing capacity.

S

To mitigate this risk, UNRA will

establish a Contract Management

Team responsible for managing the

project on behalf of the UNRA.

M

Financial

management risks

Substantial country risks

persist S

UNRA, which takes on the key

financial management responsibility

for the project, has substantial

experience and a good financial

management record (from its

predecessor RAFU)

M

Procurement risks

UNRA procures works for

over US$500 million

annually.

H Regular monitoring and follow-up of

procurement timelines. S

Overall risk rating: Moderate

Note: Rating of risks is on a four-point scale: H = High; S = Substantial; M = Moderate; and L = Low.

1.6. Implementation Arrangements

8. MoWT and UNRA implemented the project. UNRA is the legal entity responsible for the

development, maintenance, and management of the national road network under the supervision

of MoWT. The proceeds of the credit were availed by the MoFPED to UNRA as a Grant. The

Permanent Secretary of MoWT and the Executive Director of UNRA were the Accounting

Officers for the project. MoWT implemented Components B, C, and D, while UNRA

implemented Components A and E. The Permanent Secretary of MoWT and the Executive

Director of UNRA delegated the function of the day-to-day management of the project to the

TSDP Project Coordinators within MoWT and UNRA. MoWT and UNRA implemented the

project fully mainstreamed in the existing institutional systems. Project Managers were

appointed by UNRA for day-to-day management of the project. UNRA was responsible for the

overall financial management of the project and the timely presentation of consolidated progress

reports and consolidated unaudited interim financial reports to IDA.

1.7. Partnership Arrangements

9. The TSDP was co-financed by IDA (US$190 million equivalent) and DFID (US$8

million equivalent). It was supported jointly by parallel funding from other DPs for a three-year

period (2010/11–2012/13) of the implementation of the GoU’s National Transport Master Plan

(NTMP) in a sector wide framework. The GoU led the coordination through annual Joint

Transport Sector Review meetings and quarterly performance reviews, where progress against

the targets set were reviewed and discussed with sector stakeholders. Furthermore, to monitor

and coordinate the reform process in general and the implementation of the RSDP in particular, a

Steering Committee was set up within the MoFPED, consisting of its Permanent

Secretary/Secretary to the Treasury as Chairperson and Officials from the Ministry of Public

Page 72: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

58

Service and MoWT as well as representatives of the DPs.

1.8. Sustainability

10. MoWT was to enhance its policy setting, strategic planning, oversight, and monitoring

capacity and assist the various executing agencies to perform their duties that were crucial for the

sustainability of the transport sector program. Improvement of maintenance performance was

key for the sustainability of the road sector program. This required timely and stable availability

of maintenance funding and capacity of the private sector. In the past, when maintenance of the

national roads was under MoWT, the quality of maintenance was mixed, as the maintenance

budgets were unpredictable and fluctuating, and as a consequence, planning was difficult and the

local construction industry did not develop adequately. It was expected that with the

establishment of the URF on July 1, 2010, the situation would improve.

2.1. Project Components

11. The project was structured into five components intended to achieve the PDOs to

improve the connectivity and efficiency of the transport sector through (i) improved condition of

the national road network; (ii) improved capacity for road safety management; and (iii) improved

transport sector and national road management.

Component A: Road Investments: Upgrading and Rehabilitation of National Roads

12. This component comprised the following subcomponents.

Subcomponent 1: Upgrading of Gulu-Atiak Road (74 km) to Bitumen Standard

13. The works are completed. The road is constructed to a width of 6.5 m, with 1.5 m

shoulders either side (increased to 3.25 m in urban areas to allow for parking). The works

executed include (a) geometric improvements to the existing road’s vertical and horizontal

alignment carried out to conform with UNRA’s requirements as provided for in MoWT Road

Design Manual and in the standard and special specifications for the civil works; (b) site

clearance and removal of topsoil; (c) earthworks for new alignment inclusive of the formation of

all drains, side ditches, junctions, and minor link roads in urban and rural locations and in

climbing lanes; (d) construction of embankments over swamps; (e) construction of pavement

layers consisting of a mechanically modified sub-base and crushed stone-base and double

bituminous surface dressing as a wearing course; (f) construction of rigid pavement at two

roundabouts and five major junctions; and (g) installation of streetlights at the two roundabouts,

road marking, guardrails, road signs, bus-bays, speed humps, rumble strips, and other items of

road furniture.

Subcomponent 2: Upgrading of Vurra-Arua-Oraba Road (85 km) to Bitumen Standard

14. The works are completed. The road is constructed to a width of 6.5 m, with 1.5 m

shoulders either side (increased to 3.25 m in urban areas to allow for parking). The works carried

out under this subcomponent include the upgrading of the existing gravel road to a class II

bituminous standard road. The pavement structure comprised 200 mm mechanically stabilized

gravel sub- base, 200 mm crushed stone-base, and DBST wearing course—900 mm and 1,200

Page 73: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

59

mm main culverts and 600 mm access culverts were constructed. Longitudinal drains comprised

earth and lined (stone pitch and concrete) drains. Ancillary works included metal guardrails and

vertical road signs to improve safety. HIV/AIDS awareness information was satisfactorily

carried out, including education and communication services. Utilities within the road prism

were successfully relocated.

Subcomponent 3: Upgrading of Kamwenge-Fort Portal Road (66 km) to Bitumen Standard

15. The road is constructed to a width of 6.5 m, with 1.5 m shoulders either side (increased to

3.25 m in urban areas to allow for parking). The works executed include (a) geometric

improvements to the existing road’s vertical and horizontal alignment carried out to conform

with UNRA’s requirements as provided for in MoWT Road Design Manual and in the standard

and special specifications for the civil works; (b) site clearance and removal of topsoil; (c)

earthworks for new alignment inclusive of the formation of all drains, side ditches, junctions, and

minor link roads in urban and rural locations and in climbing lanes; (d) construction of

embankments over swamps; (e) construction of pavement layers consisting of a mechanically

modified sub-base and crushed stone-base and double bituminous surface dressing as a wearing

course.

Subcomponent 4: Preparation of Road Design and Bidding Documents

16. Component A also financed consultancy services for feasibility studies, ESIAs, and

detailed engineering designs for the reconstruction and upgrading of the following roads:

Tororo-Mbale-Soroti-Lira-Kamdini road (340 km): The contract was amended on

October 3, 2013, to allow the consultant to assess the corridor and prepare a long-

term OPRC.

Kafu-Karuma-Kamdini road (104 km).

Zirobwe-Wobulenzi road (23 km): The contract was amended to cater for the

extended scope of services.

Kamdini-Nebbi-Goli and Ayer-Bobi road (230 km).

Component B: Enhanced Road Safety

17. Under this component, the GoU committed to prepare and develop the National Road

Safety Policy and establish and operationalize an NRSA by FY2011/12. The policy was

developed and approved on November 26, 2014. However, the Policy Statement for the

establishment of the NRSA was not approved. The top management team (TMT) of MoWT

recommended the ministry to rather strengthen the capacity of the department implementing road

safety issues. The review of the Traffic and Road Safety Act has, nevertheless recommended the

establishment of a strong road safety lead agency to replace the NRSC.

18. This component also provided funding for the establishment of an RCDS. Phase I, (needs

assessment system design, review of crash form) and Phase II (database software development,

training and piloting of the new crash form, and testing the database) were completed.

Page 74: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

60

Implementation of Phase III (rollout phase), however, was delayed because of the lack of

equipment, which was under procurement. The equipment was eventually delivered to the

ministry at the beginning of December 2015.

19. The following pending activities are yet to be implemented to ensure successful

completion of the subcomponent:

Securing funds for pending training programs to enable rollout of the RCDS

Roll out of the RCDS country wide

Internet connectivity for the police stations

20. Because of these pending activities, a request for contract extension was granted from

December 25, 2015, to December 24, 2016, to successfully roll out the RCDS. This extension

approved by the Contracts Committee was subsequently affected by the cancellation of the

credits. Cancellation of the credits affected the program in the following ways:

The implementation of the RCDS had reached a critical stage where most of key

inputs required for its establishment had been achieved, leaving only training and

rollout.

The establishment of the RCDS was left in suspense despite the effort that had been

made toward the implementation and commitment from both the ministry and other

key stakeholders such as the Uganda Police and UNRA.

Failure to secure funds could waste the expenditure made so far toward the RCDS

establishment.

21. The road safety enhancement included an update of the transport sector legal framework

by MoWT by July 1, 2013. The drafting principles for the amendment of the Traffic and Road

Safety Act were prepared and approved by the ministry’s TMT. The Drafting Principles were

reviewed and harmonized with the Roads Bill, which is being drafted by the First Parliamentary

Council.

22. Improved roads and increased private car and motorcycle ownership, coupled with the

absence of public transport facilities, have led to an alarming deterioration of road safety. In

FY2015/16, there was an increase in fatalities by 13 percent over the previous year. The total

estimated financial loss as a result of road crashes in Uganda was US$1.32 billion in 2015. The

economic cost of dealing with the consequences of road trauma already runs into hundreds of

billions of dollars each year and the social cost is equally high. The TSDP’s outcome indicator

was to reduce the accident fatality rate and enhance safety. The TSDP cancellation based on the

failure of one activity (that is, Kamwenge-Fort Portal road) should not have affected other

important Government priorities such as the rollout of the RCDS, customization, technical

support, and training.

Component C: Urban Transport Planning: Preparation of Kampala Urban Transport

Project

Page 75: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

61

23. MoWT implemented this component. The main purpose was to finance the feasibility

study, detailed engineering designs, and contract preparation for the pilot BRT project for the

GKMA and fund preparation for the legislation for the establishment of a MATA.

24. The BRT feasibility study and system engineering designs were prepared and completed,

ready to be implemented by the Government. Drafting Principles for the establishment of the

MATA Bill were prepared and approved by the Cabinet (January 2016). The approved Drafting

Principles have been forwarded to the First Parliamentary Council for Drafting of the bill. The

GoU affirms that the establishment of MATA is a priority institutional reform strategy to

mitigate the challenges of congestion within the GKMA, which is faced with high urbanization

resulting into increased motorization. Commitment to actualize plans is yet to be concretized by

concerned Ministries, Departments, and Agencies.

Component D: Institutional Support to the Ministry of Works and Transport

25. The GoU Sector Policy required MoWT to carry out institutional reform actions to

devolve power to the new institutions accountable to it. This required redefinition of the role of

the ministry to focus on policy formulation, sector oversight, strategic planning, setting

standards, and M&E. To that effect, MoWT launched a number of studies and service contracts

under this component. The main activities undertaken are summarized below.

Strengthening of the Policy and Planning Division

26. Under this component, the ministry was able to procure hardware office equipment and

design DEVINFO for the establishment of the TSDMS. The TSDMS was launched and

commissioned in 2014 at a joint Transport Sector Review Workshop. The system has been tested

and is currently being used. A number of studies related to transport policy and planning were

carried out by the ministry, namely the development and update of an NTPS, the Inland Water

Transport Legislation, whose drafting principles have been approved and forwarded to First

Parliamentary Council for drafting of the bill. The detailed Strategic Implementation Plan for the

National Transport Master Plan including the Plan for GKMA was prepared and successfully

developed. Preparation of a condition survey for the DUCAR network and creation of a database

were completed. The final draft of the NTPS was presented to the TMT and discussed.

However, it did not obtain financial clearance approvals from the MoFPED to enable submission

of the Cabinet Memorandum to the Cabinet Secretariat. The NTPS supported the establishment

of the NRSA and MATA but experienced serious financial setbacks after the TSDP Credit

cancellation. Further, consultation is being made with relevant stakeholders to clarify and

respond to issues raised by the MoFPED before resubmitting the draft for financial clearance

and, thereafter, to proceed with submission to the Cabinet Secretariat for approval.

Technical Assistance toward Establishment of MTRA

27. Technical officers of the ministry undertook in-depth consultations about the

establishment of the MTRA. They collaborated with all transport sector stakeholders. The

concept of establishing a new MTRA was mooted to take over the functions of the Directorate of

Transport. The stakeholders objected to this concept and advised through the TMT to

alternatively strengthen the capacity of the Transport Directorates to enable them to perform this

Page 76: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

62

task.

Other Support to MoWT through TA, Studies, Equipment, and Training

28. This component was focused on assistance to transform the DUCAR divisions to an

agency through technical assistance, purchase of equipment, training, and finance operating

costs. The ministry was able to procure information technology equipment for a DUCAR data

center and for the local governments to improve the condition of the local roads. The ministry

increased the capacity and skills in transport planning by training a number of several officers in

Transport Planning and Economics to master’s level at Leeds University. It is important to

evaluate and take into account the knowledge, skills, talents, and competencies achieved as a

result of the TSDP activities in Uganda.

Component E: Institutional Support to UNRA

29. The main activities undertaken under this component are summarized in the following

paragraphs.

30. Upgrading of regional offices. This involved the detailed design, construction, and

supervision for the upgrading of five UNRA regional offices. The design and supervision

contract commenced on April 18, 2013. The design is completed, but the supervision phase

depended on the procurement of the works contract, which was subsequently affected by the

cancellation of the credits.

31. Road inventory and mapping. About 10,000 km of roads that were formally district

roads and reclassified as national roads were transferred to UNRA for management. The data

collection, which included mapping of this new network, inventory of the road assets, condition

assessments, and traffic census information, were substantially completed in December 2011.

Quality assurance and uploading of the data in the RMS was successfully completed on May 4,

2012. The contract was completed with the commissioning of the RMS in June 2012.

32. Development of a GIS Right-of-Way Management Information System. The aim of

developing this system was to support the RAP preparation, land acquisition, registration and

land administration, query, complaints management, and M&E. A computerized database of the

Right-of-Way information was created to increase efficiency and effectiveness of service

delivery at UNRA.

33. System development was completed and the system was installed on the UNRA server

and end-user computers. Capacity building and training of end users was conducted. A core team

of GIS officers was trained to give technical and helpdesk support. The system is being used on

new projects and data generated from previous projects will be uploaded. Training and capacity

building will be continued, especially to cater for new staff joining the organization. The

designer, because of intellectual property rights, can only implement future system upgrades and

modifications. There is need to put in place a service maintenance contract to cater for upgrades

and any changes requested by end users. Furthermore, the system was developed based on

ArcGIS software, licensed software from ESRI. There is, however, favorable development in

free GIS software. The cost of maintenance would have been lower where the system is to be

designed based on free GIS software.

Page 77: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

63

34. Equipment. Fifteen double cabin pickup vehicles and heavy-duty scanners were

procured.

Technical Assistance: Specialist Assistance (UNRA)

35. Communication Specialist. The consultant commenced work on May 4, 2012. The

contract was for a period of two years with the original expiry date of April 24, 2014, but was

extended to October 23, 2014.

36. Procurement. The consultant commenced work in August 2010. The consultant doubled

as the Acting Director for the PDU. The consultant offered his services up to June 31, 2014,

when he handed over the work to a new substantive Director, who was appointed by UNRA. In

addition, a Procurement Specialist was recruited, who commenced service on July 21, 2011, up

to October 22, 2015.

37. Ferry Services Advisor. The contract with the Ferry Services Advisor was for a period

of six months and commenced on July 10, 2012.

38. Axle Load Control Advisor. The consultant commenced the services on September 30,

2013, and concluded on January 31, 2015.

39. Internal Audit Unit. The consultant commenced the services on September 30, 2013, for

a period of two years.

40. General capacity building. The two-year contract for these services commenced in June

2014. The contract was terminated on December 30, 2015, because of the restructuring exercise

the organization was undergoing.

41. Asset management support. This was a two-year support service intended to help

UNRA fully functionalize its RMS and to mainstream asset management practice in its business.

The services commenced in February 2015 and will expire in February 2017.

2.2. Fiduciary Issues

Procurement

42. The procurement for the project was carried out in accordance with the World Bank’s

‘Guidelines: Procurement under IBRD Loans and IDA Credits’, dated May 2004 and revised

October 2006; ‘Guidelines: Selection and Employment of Consultants by World Bank

Recipients’, dated May 2004 and revised October 2006; and the provisions stipulated in the

Financing Agreement. The national legislation on public procurement, as laid out in the Public

Procurement and Disposal of Public Assets Act, is generally in line with the World Bank’s

guidelines.

Financial Management

43. The financial management for the project was generally reliable and adequate systems

were in place. Pastel accounting software was used to account for project funds. The project

Page 78: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

64

finances were released and utilized in accordance with the agreed financial schedule. The

supervision missions reviewed the project financial management arrangements with regard to

correct recording of all transactions and balances, to ensure proper use of World Bank’s funds in

an economic and effective way for the purpose intended. In this way, the funds disbursement by

donor, component, and category were scrutinized.

2.3. Environment and Safeguard Compliance

Gulu-Atiak and Vurra-Oraba Roads

44. The project obtained approvals for ESIAs from NEMA. Auxiliary components of the

projects undertook stand-alone environmental assessments and obtained approvals from NEMA.

Comprehensive environmental audits for the road projects were undertaken and approvals were

also obtained from NEMA.

45. The contractor’s ESMPs were prepared for the two completed projects to guide

implementation of environmental and social management and monitoring activities on a

continuous basis throughout project implementation. The ESMPs were based on the

Environmental Impact Statements and NEMA approval conditions in the licenses and

certificates.

46. RAPs were prepared and approved by the Chief Government Valuer to guide mitigation

of social impacts and implementation of compensation for PAPs. Both projects procured

HIV/AIDS service providers to mitigate social impacts resulting from interaction of workers and

the local communities.

Physical Cultural Resources

47. Physical Cultural Resource Assessments were undertaken alongside ESIAs to guide

Physical Cultural Resource Assessments’ preservations for both roads. The monument and

graves and customs house in Vurra, historical buildings in Arua town, and ritual trees in Aroi

sub-county and Koboko were preserved. Historical buildings in Atiak and a historical fort in

Pabo were preserved.

Quarries and Borrow Pits

48. The quarry operations for both projects were preceded by stand-alone ESIAs, which were

approved by NEMA. A total of 300 borrow pits were opened on the Vurra-Oraba road and

almost all have been restored. Forty borrow areas were opened on the Gulu-Atiak road and all

have been restored. The few borrow areas that are still operational have been formally

transferred to other projects and NEMA informed.

Decommissioning Plans

49. Both projects prepared decommissioning plans for major components, including

contractor’s camps, quarries, borrow areas, and spoil disposal areas, which were submitted to

NEMA for review and approval. NEMA was informed of the project’s completion and transfer

of quarries for purposes of providing materials to other projects.

Page 79: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

65

Final Environmental Mitigation Reports

50. Final Environmental and Social Mitigation Reports for the completed projects have been

prepared and submitted for review and approval in line with the General Specifications for Road

and Bridge Works 2005. The reports will be submitted to NEMA for concurrence before the

retention money can be released.

Lessons Learned in Environmental and Social Management

51. The ESMPs should always be undertaken and approvals obtained in line with national

systems and World Bank safeguard policies. Conditions of approval and environmental and

social contract clauses should always be implemented on a day-to-day basis to avoid

noncompliance with environmental and social safeguards. While acquiring quarry facilities,

abbreviated RAPs should always be prepared and approved to ensure fair compensation of PAPs.

For a discussion of environmental and social issues on the Kamwenge-Fort Portal road, see

section 6.

52. For the Kamwenge-Fort Portal road see Section 6.2.

3. Assessment of Outcomes

53. At cancelation of the Credit, the project had achieved 84 percent of the planned km of

road to be upgraded (189 km of tarmac against the planned 225 km). The Gulu-Atiak road (74

km) and Vura-Arua-Oraba road (85 km) were completed. About 30 km of the Fort Portal road

was complete against the planned 66.2 km. The project, on the whole, met most of the outcome

indicators as detailed in the TSDP Results Framework.

3.1. Relevance of Objectives, Design and Implementation

54. The TSDP was highly relevant to the country’s development objectives as stated in the

Vision 2040 and the National Development Plan II strategy to achieve middle-income status by

2020. The TSDP strategy was based on achieving the goals of the TSDP of 2008 and the

National Transport Master Plan that included the Plan for GKMA and the 2002 draft NTPS. It

was consistent with the Government’s poverty reduction and economic growth strategy by

improving the rural and urban populations’ access to basic services, markets, and employment

opportunities. Through civil works and bridges in remote and isolated areas, it has facilitated

connectivity between and within regions as well as employment generation and marketing

opportunities. It has complemented other Government efforts with a rich HIV/AIDS agenda in

the project areas.

3.2. Justification of Overall Outcome Rating

55. The TSDP is rated Satisfactory because of its contribution to improve the performance of

the transport sector in Uganda to enhance economic growth and reduce poverty through (a)

reduction of transport costs and travel times on the major corridors, (b) improvement of road

safety, and (c) enhancement of sector management capacity.

56. Policy and institutional reforms in the transport sector were aimed at supporting MoWT

Page 80: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

66

in reviewing its portfolio mandate and rationalizing its service deliveries. However, the targeted

authorities had not been established, namely MATA, the NRSA, MTRA, and DUCAR agency.

The project ended while the processes toward the establishment of agencies such as MATA and

the NRSA were still under way, while the establishment of MTRA and DUCAR has been

suspended.

57. The TSDP financed important studies, which comprised an update of the NTPS, Strategic

Implementation Plan for the National Transport Master Plan including a Plan for GKMA, Inland

Water Policy and Legislation, National Road Safety Policy, and a review of the Traffic and Road

Safety Act. Capacity building was also addressed in the subsectors based on information from

the studies’ reports. The recommendations from the studies led to skills upgrading training as

well as professional enrichment for various categories of staff in all road agencies. In MoWT

Department of Policy and Planning, for instance, transport planners and economists received a

master’s degree in Transport Planning and Economics from the University of Leeds. A number

of staff in the Directorate of Transport and Engineering received short-term training in transport

project management and appraisal from the Transportation Institute in Israel. The retooling skills

obtained are being put to good use within the ministry.

4. Performance of the Government and the Bank

4.1. Assessment of the Government Performance

58. The performance of the GoU can be assessed as follows:

Positive

The PDOs were consistent and in conformity with Uganda’s Vision 2040, the

National Transport Master Plan, and the National Development Plan. It was,

therefore, consistent with the Government planning and legal frameworks.

The Government demonstrated its commitment by establishing an acceptable

procurement tracking and record keeping system within 12 months of effectiveness.

Reliable and adequate systems for financial management were put in place.

Negative

Contractual noncompliance—the Government did not adequately enforce

compliance to road safety issues, labor issues, health and safety issues, and social

and environmental safeguards on the Kamwenge-Fort Portal road upgrading works.

Compensation—unsatisfactory progress with respect to the speed in handling the

claims and a number of pending compensation claims.

4.2. Assessment of IDA Performance

59. The performance of IDA in the project can be assessed as follows:

Page 81: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

67

Positive

The project was consistent with the CAS.

The World Bank played a leadership role among donors in supporting road sector

reforms and capacity building.

Regular supervision missions provided the necessary support in project

implementation, were constructive, and were strong in enforcing fiduciary measures

and safeguards.

Negative

Delays in providing ‘no-objections’

5. Disbursements

Disbursements – by Loan

Pro

ject

Lo

an

/Gra

nt

Sta

tus

Cu

rren

cy

Ori

gin

al

Rev

ised

Ca

nce

lled

Dis

bu

rse

d

Un

dis

bu

rse

d

Dis

bu

rse

d (

%)

P092837 IDA-46790 Closed US$ 190.00 190.00 30.92 159.08 0.00 83.73

P092837 IDA-49490 Closed US$ 75.00 75.00 75.00 0.00 0.00 0.00

P092837 TF-11094 Closed US$ 6.15 6.15 0.00 6.15 0.00 100.00

Total 271.15 271.15 105.92 165.23 0.00 60.94

TSDP - Loss in Loan Value (US$40.76 million)

60. The present depreciated value of the two TSDP Credits is US$40.76 million. This

represents the movement between the SDR (the Credits’ currency) and the U.S. dollar (the

disbursing currency) over the Credit term.

6. Project Closure

61. The project closure was a result of the project not being carried out in accordance with

appropriate and agreed social and environmental standards. The genesis of the closure of the

project stemmed from the social and environmental social safeguard issues on the Kamwenge-

Fort Portal road, which were not adequately managed. This first led to the suspension of the

project’s credit disbursements, which culminated in the cancellation of the funding to the TSDP.

6.1. Suspension of the Project Credits Disbursements

62. After road works commenced under the project on August 1, 2013, World Bank

supervision missions repeatedly found instances of noncompliance with a number of

environmental and social requirements, particularly concerning land acquisition and various

physical impacts of construction, and alerted the implementing agency, UNRA, that they

Page 82: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

68

required remediation. After multiple reviews, there was a lack of progress with corrective actions

and concerns about allegations of sexual misconduct by contracted road workers. The World

Bank’s Regional Vice President for Africa sent a letter dated October 21, 2015, to the GoU

informing the suspension of disbursements under the project (Credits: IDA-46790 and IDA-

49490), effective October 22, 2015. Under the conditions of suspension, no funds already

withdrawn and in the project Designated Accounts were to be applied for any payments for civil

works on the Kawenge-Fort Portal road. The reasons underlying the suspension were threefold:

(i) Contractual noncompliance. The contractor failed to comply with general

contractual requirements including, but not limited to, road safety issues, labor

issues, working with the community issues, health and safety issues (including

incidences of deaths reported), and environmental issues, among others.

(ii) Compensation. Unsatisfactory progress with respect to the speed in handling the

claims and a number of pending compensation claims,

(iii) Social safeguards. There were complaints from the community citing workers of

the contractor involved in sexual abuse and sexual harassment of female employees.

Certain actions on child protection that were agreed to be necessary had not been

fully undertaken.

6.2. Cancellation of the Project

63. Concerns related to sexual misconduct of contracted road workers under the project were

first brought to the World Bank’s attention in a letter of complaint from some communities in

December 2014. Subsequent World Bank missions to the project site to review the issues raised,

working closely with the Government agencies concerned, specialized social development

consultants, and a local civil society organization, provided more insight into the complaints. The

World Bank concluded that there was credible evidence of project road workers engaging in

sexual misconduct with minors. The World Bank alerted the Government and UNRA, urging the

involvement of law enforcement and child protection agencies. On September 28, 2015, the

Inspection Panel—the independent accountability mechanism for people and communities who

believe that they have been, or are likely to be, adversely affected by a World Bank-funded

project—registered a request for inspection regarding the TSDP. The request concerned

complaints from the Bigodi and Nyabubale-Nkingo communities, located along the Kamwenge

to Fort Portal road. The World Bank Management reviewed the request and concluded that the

World Bank and the GoU failed to take sufficient measures to mitigate the identified risks and to

take action in a timely manner after serious issues were brought to their attention. After further

review and after the GoU and the Government contractor failed to take corrective steps, the

World Bank management informed the World Bank Board that it was cancelling the project,

effective December 21, 2015. The World Bank Group President Jim Yong Kim announced the

cancellation of funding to the Uganda TSDP because the project was not being carried out in

accordance with appropriate and agreed social and environmental standards.

64. At the time of cancellation of funding, substantial progress had been achieved for the

planned road upgrading works and capacity-building activities planned for UNRA. The Gulu-

Atiak road and Vura-Arua-Oraba road were substantially completed. For the Kamwenge-Fort

Page 83: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

69

Portal road, only 30 km of the planned 66 km had been paved with tarmac. The GoU continued

with the financing of the Kamwenge-Fort Portal road.

65. The obligation left to the GoU upon cancellation of the funding was enormous, whereby,

some of the subcomponents could no longer be completed because of budgetary constraints. The

shock of cancellation of funding highly risks the effort the project had made in supporting the

sector’s policy and strategy.

7. Challenges, Lessons Learned, and Conclusion

7.1. Challenges

The implementation of the RCDS had reached a critical stage where most of key

inputs required for its establishment had been achieved with only training and

rollout remaining.

The cancellation of the Credits on account of an unrelated component left the

establishment of the RCDS in suspense at a critical stage. A lot of effort had been

made toward implementation by both the ministry and all key stakeholders who

were left frustrated by the cancellation.

Failure to find alternative funding for completion of the program means that all the

prior expenditures could result in sunk costs.

Getting a champion for the BRT project was necessary for the completion and

implementation of the BRT system.

Reviewing BRT feasibility and design documents was challenging because of

insufficient skills regarding BRT designs at the ministry.

There are different opinions from different stakeholders on choice of mass rapid

transport that would reduce congestion in the GKMA (BRT versus light rail).

Preparatory activities such as the transformation of the taxi industry, land

acquisition, and sensitization before implementation of BRT are a hindrance to the

BRT’s success.

Government processes and approvals to establish MATA have been lengthy and

affected the implementation of the BRT system in Kampala.

A long procurement process basing on the PPDA and World Bank procedures

delayed progress.

Delays in approving requests for reallocating funds from nonperforming components

to reprioritized activities affected completion of vital objectives.

7.2. Lessons Learned

Page 84: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

70

Project Appraisals should gather adequate information from previous programs in order to arrive

at a realistic, achievable timeline for implementation of major institutional reforms; and

Cancellation of an entire Credit with a multitude of components because of problems with a

single subcomponent is unfair. Only the funds for the problematic one should be withdrawn.

There is need for continued capacity building in the field of Public Transport and Planning in the

Ministry.

Political support and Top Management support is critical to the success of major public

infrastructure projects.

Involvement of stakeholders enriches the outputs and outcomes of infrastructure projects.

MoFPED has to be heavily and actively involved at each and every stage of an infrastructure

project, especially at conceptualization, to have agreement and guarantee counterpart funding.

Contracts ought to be drafted carefully to pay attention to such details as taxes in order to

minimize conflicts during contract implementation.

Establishing of a fully funded BRT Implementation Unit within the Ministry in the initial stages

is key for the success of BRT before actualization of MATA

Additional resources are required to fast track the reforms

Environmental and social plans should always be undertaken and approvals obtained in line with

national systems and World Bank Safeguard Policies. Conditions of approval and environmental

and social contract clauses should always be implemented on a day-to-day basis to avoid non-

compliance with environmental and social safeguards. While acquiring quarry facilities,

Abbreviated Resettlement Action Plans should always be prepared and approved to ensure fair

compensation of Project Affected Persons.

7.3. Conclusion

66. The Government’s sector policy and medium-term strategy hinge on the promotion of

sustainable, efficient, safe, and reliable transport services as the means for providing effective

support to increase agriculture and industrial production, trade, tourism, social, and

administrative services. This is in line with the Government’s National Development Plan, which

is to improve the stock and quality of roads infrastructure, transport, and traffic management.

The TSDP provided the framework for fulfilling the Government’s objective. The project was

critical in supporting the GoU to roll out the sector reforms into implementation.

Page 85: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

71

Annex 6. List of Supporting Documents

Aide Memoires, Project Progress Reports, Implementation Status and Results Reports,

Environmental and Social Impact Assessments and Environmental and Social

Management Plans

Country Assistance Strategy for the Republic of Uganda for the Period 2011-2015, April

27, 2010, Report 54187-UG.

DFID (U.K. Department for International Development), 2015, Final Report on DFID

Trust Fund Utilization in the Transport Sector Development Project

DFID (U.K. Department for International Development). 2009. Review of the Uganda

Joint Assistance Strategy - Current and Future Prospects by Alison Evans of the

Overseas Development Institute, London and Peter Sentongo of the Centre for

Performance Management, Kampala.

Employment (Employment of Children) Regulations, Government of Uganda, April 20,

2012.

Fact Sheet, Uganda Economic Update 6. 2015 (September).

First Progress Report on the Implementation of Management’s Action Plan in Response

to the Inspection Panel Investigation Report (INSP/106710-UG) on the Republic of

Uganda Transport Sector Development Project- Additional Financing (P121097), March

30, 2017

Financing Agreement for Credit 4679-UG conformed, February 3, 2010.

Guidelines for Reviewing World Bank Implementation Completion and Results Reports, a

Manual for Evaluators, last updated August 1, 2014.

Implementation Completion Report Guidelines, OPCS, August 2006, last updated July

22, 2014.

Inspection Panel Investigation Report: Transport Sector Development Project -

Additional Financing, August 4, 2016; and Management Response.

Inspection Panel Process Guidance Note, October 2014.

Inspection Panel: Request for Inspection - Notice of Registration, September 28, 2015.

Letter of Development Policy for the Transport Sector (Uganda), October 8, 2009.

Management Response to Request for Inspection Panel Review of the Uganda Transport

Development Project - Additional Financing, December 17, 2015.

Managing the Risks of Adverse Impacts on Communities from Temporary Project

Induced Labor Influx, 2016, Environmental and Social Safeguards Advisory Team,

Operations Policy and Country Services, Washington DC

Mclean, L, and P. Bukuluki. 2016. Uganda Gender-Based Violence Diagnostic.

Washington, DC: World Bank.

Mid-term Review, Mission Report, April 22–May 10, 2013.

Ministry of Works and Transport. 2015. Annual Sector Performance Report Financial

Year 2014/15, Government of Uganda

Progress Report on Country Assistance Strategy.

Resettlement Action Plan, January 2011, AWE Engineers, Kampala, Uganda.

The Independent. 2016. How Uganda Ranks in Drink Driving, Fatal Accidents and

Helmet Use. All Africa Global Media (March).

Transport Case Study, Republic of Uganda, April 2012, Independent Evaluation Group.

Page 86: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

72

Transport Paper TP-21, Monitoring Road Works Contracts and Unit Costs for Enhanced

Governance in Sub-Saharan Africa, Alexeeva V. et al, September 2008.

Uganda Bureau of Statistics. 2016. Census 2014 Final Results.

Uganda National Road Agency. 2012. Preparation of Third Phase of Road Sector

Development Program. Kagga and Mott Macdonald.

Uganda Police. 2013. Annual Crime and Traffic Road Safety Report, Kampala.

Uganda Road Fund. Road Maintenance Monitoring Report, Q1 FY2015/16, November

2015.

Uganda Sexual and Gender-based Violence Diagnostic. 2016. Washington, DC: World

Bank.

Uganda Transport Sector Development Project, Environmental Assessment, E1879, July

2009.

Uganda Transport Sector Development Project, Resettlement Action Plan, RP665, July

2009.

United Nations Refugee Agency. 2005. Uganda Hosts Record 500,000 Refugees and

Asylum Seekers. (accessed September 7, 2016), www.unhcr.org.

World Bank. 2010. Rural Road Investment Efficiency: Lessons from Burkina Faso,

Cameroon and Uganda, Report 53646.

World Bank Bridges Across Borders--Unleashing Uganda’s Regional Trade Potential.

Uganda Economic Update 1. 2013 (February).

World Bank Northeastern Road Corridor Asset Management Project, Project Appraisal

Document, Report PAD 707, Washington, DC: World Bank. 2014

World Bank Uganda Overview, Country at a Glance (accessed October 14, 2016).

http://www.worldbank.org/en/country/uganda.

World Bank, 2016, Lessons learned and Agenda for Action from the Uganda TSDP

World Bank, 2011, Transport Sector Development Project, Project Paper on a Proposed

Additional Credit, Report 59825, Washington DC

World Bank, 2009, Transport Sector Development Project, Project Appraisal Document,

Report 50977-UG, Washington DC

World Health Organization. 2015. Road Safety Report, Geneva.

Page 87: World Bank Documentdocuments.worldbank.org/curated/en/284931506968826934/... · 2017-10-03 · MIS Management Information System MoFPED Ministry of Finance, Planning, and Economic

73

MAP