![Page 1: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/1.jpg)
Procurement Plan-Goods Country/Organisation: RWANDA
Project/Programme: Electricity Access Scale-Up and Sector Wide Approach Development Project (EASSDP)
Loan #: Credit IDA 51930
Description*Package
Number
Lot
Number
Procurement
Method
Pre-or Post
Qualification
Prior or Post
Review
If Prequalification
add 7-13 wks
List of Contracts
40/G/2012-EASSDP 4 ICB Post Qualification Prior Review
41/G/2012-EASSDP 3 ICB Post Qualification Prior Review
42/G/2012-EASSDP 2 ICB Post Qualification Prior Review
43/G/2012-EASSDP 1 ICB Post Qualification Prior Review
45/G/2012-EASSDP 1 ICB Post Qualification Prior Review
Tender to supply of various IT equipment for
EARP 67/G/2013-EASSDP 1 NCB Post Qualification Post Review
Tender for supply of hotel services for various
EARP meetings for the year 2014 68/G/2013-EASSDP 1 NCB Post Qualification Post Review
47/G/2012-EASSDP 1 ICB Post Qualification Prior Review
Tender to supply office stationaries 49/G/2013-EASSDP 1 NCB Post Qualification Post Review
BASIC DATA
Norm Duration of Proc Steps
Tender to supply wooden poles, concrete poles
and steels and accessories
Tender to supply Overhead ACSR Conductor,
Overhead ABC Twisted Cables, MV Insulators
and MV & LV accessories
Tender to Supply of distribution Transformers
and MV Overhead Switchgear
Tender to supply and installation of solar water
heaters for hospitals and schools
Tender for supply of service connection meters
Tender for supply of Tools and equipment for
linesman
838940PROP0P110Box0382116B00PUBLIC0.xls 1 of 28 01/09/2014 3:10 AM
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
![Page 2: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/2.jpg)
Procurement Plan-Goods
Total Cost
838940PROP0P110Box0382116B00PUBLIC0.xls 2 of 28 01/09/2014 3:10 AM
![Page 3: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/3.jpg)
Procurement Plan-Goods Country/Organisation: RWANDA
Project/Programme: Electricity Access Scale-Up and Sector Wide Approach Development Project (EASSDP)
Loan #: Credit IDA 51930
Description*
List of Contracts
Tender to supply of various IT equipment for
EARP
Tender for supply of hotel services for various
EARP meetings for the year 2014
Tender to supply office stationaries
Norm Duration of Proc Steps
Tender to supply wooden poles, concrete poles
and steels and accessories
Tender to supply Overhead ACSR Conductor,
Overhead ABC Twisted Cables, MV Insulators
and MV & LV accessories
Tender to Supply of distribution Transformers
and MV Overhead Switchgear
Tender to supply and installation of solar water
heaters for hospitals and schools
Tender for supply of service connection meters
Tender for supply of Tools and equipment for
linesman
If Post-Review, No-objection Dates are not needed
Spec Proc Notice
Advert
Plan
vs.
Actual
Prep &
Submission
by Ex Agency
No-objection
Date
On-line UNDB
Gateway
Nat Press
Bid Invitation
Date
Bid Closing-
Opening
Submission
Bid Eval Rpt
No-objection
Date
Plan 4 - 7 wks 1 - 1.5 wks 1.5 - 2 wks 6 to 12 wks 1.5 - 3 wks 1 - 1.5 wks
Actual
Plan 10-Apr-13 20-Apr-13 4-May-13 4-May-13 3-Jul-13 24-Jul-13 3-Aug-13
Actual
Plan 20-Jun-13 30-Jun-13 14-Jul-13 14-Jul-13 12-Sep-13 3-Oct-13 13-Oct-13
Actual
Plan 30-Dec-13 9-Jan-14 23-Jan-14 23-Jan-14 24-Mar-14 14-Apr-14 24-Apr-14
Actual
Plan 15-Jan-14 25-Jan-14 8-Feb-14 8-Feb-14 9-Apr-14 30-Apr-14 10-May-14
Actual
Plan 10-Dec-13 20-Dec-13 3-Jan-14 3-Jan-14 17-Feb-14 10-Mar-14 20-Mar-14
Actual
Plan 05-Jan-14 NA 5-Jan-14 5-Jan-14 9-Feb-14 2-Mar-14 NA
Actual
Plan 05-Jan-14 NA 5-Jan-14 5-Jan-14 9-Feb-14 2-Mar-14 NA
Actual
Plan 30-Oct-13 9-Nov-13 23-Nov-13 23-Nov-13 7-Jan-14 28-Jan-14 7-Feb-14
Actual
Plan 05-Jan-14 NA 5-Jan-14 5-Jan-14 9-Feb-14 2-Mar-14 NA
Actual
Bid EvaluationBidding Period
Draft Bid Documents, including
specs and quantities, draft SPN
838940PROP0P110Box0382116B00PUBLIC0.xls 3 of 28 01/09/2014 3:10 AM
![Page 4: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/4.jpg)
Procurement Plan-Goods
Total Cost Plan
Actual
838940PROP0P110Box0382116B00PUBLIC0.xls 4 of 28 01/09/2014 3:10 AM
![Page 5: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/5.jpg)
Procurement Plan-Goods Country/Organisation: RWANDA
Project/Programme: Electricity Access Scale-Up and Sector Wide Approach Development Project (EASSDP)
Loan #: Credit IDA 51930
Description*
List of Contracts
Tender to supply of various IT equipment for
EARP
Tender for supply of hotel services for various
EARP meetings for the year 2014
Tender to supply office stationaries
Norm Duration of Proc Steps
Tender to supply wooden poles, concrete poles
and steels and accessories
Tender to supply Overhead ACSR Conductor,
Overhead ABC Twisted Cables, MV Insulators
and MV & LV accessories
Tender to Supply of distribution Transformers
and MV Overhead Switchgear
Tender to supply and installation of solar water
heaters for hospitals and schools
Tender for supply of service connection meters
Tender for supply of Tools and equipment for
linesman
Contract Implementation
Plan
vs.
Actual
Contract Amount
in US$'000
Date
Contract
Award
Date
Contract
Signature
Opening
of
Let of Credit
Arrival
of
Goods
Inspection
Final
Acceptance
Plan 1 wk 1.5-3 wks 4-9 wks
Actual
Plan 10-Aug-13 31-Aug-13 30-Oct-13 28-May-14 11-Jun-14
Actualdate
Plan 20-Oct-13 10-Nov-13 9-Jan-14 8-Jun-14 22-Jun-14
Actual
Plan 1-May-14 22-May-14 21-Jul-14 18-Dec-14 1-Jan-15
Actual
Plan 17-May-14 7-Jun-14 6-Aug-14 4-Dec-14 18-Dec-14
Actual
Plan 27-Mar-14 17-Apr-14 16-Jun-14 14-Oct-14 28-Oct-14
Actual
Plan 2-Mar-14 16-Mar-14 NA 14-Jun-14 21-Jun-14
Actual
Plan 2-Mar-14 16-Mar-14 NA 14-Jun-14 21-Jun-14
Actual
Plan 14-Feb-14 7-Mar-14 6-May-14 30-Jul-15 13-Aug-15
Actual
Plan 2-Mar-14 16-Mar-14 NA 14-Jun-14 21-Jun-14
Actual
Contract Finalization
838940PROP0P110Box0382116B00PUBLIC0.xls 5 of 28 01/09/2014 3:10 AM
![Page 6: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/6.jpg)
Procurement Plan-Goods
Total Cost Plan #REF!
Actual #REF!
838940PROP0P110Box0382116B00PUBLIC0.xls 6 of 28 01/09/2014 3:10 AM
![Page 7: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/7.jpg)
Procurement Plan-Works Country/Organisation: RWANDA
Project/Programme: Electricity Access Scale-Up and Sector Wide Approach Development Project (EASSDP)
Loan #: Credit IDA 51930
Description*Package
Number
Lot
Number
Lumpsum or
Bill of
Quantities
Procurement
Method
Pre-or Post
Qualification
Prior or Post
Review
If Prequalification
add 7-13 wks
List of Contracts
49/W/2012-EASSDP 4 Bill of Quantities ICB Post QualificationPrior or Post Review
50/W/2012-EASSDP 4 Bill of Quantities ICB Post QualificationPrior Review
33/EPC/2012-EASSDP 2 Lump sum ICB Post QualificationPrior Review
51/EPC/2012-EASSDP 1 Lump sum ICB Post QualificationPrior Review
60/EPC/2013-EASSDP 2 Lump sum ICB Post QualificationPrior Review
61/EPC/2013-EASSDP 1 Lump sum ICB Post QualificationPrior Review
Engineering, procurement and
construction contract for green field
areas (Southern Zone)
Basic Data
Engineering, procurement and
construction contract for green field
areas (Northern Zone)
Construction of 110kV line Bugarama-
Ntendezi (23km) and Construction of
110/30kV Ntendezi substation
Construction of 110/30/6.6kV Bugarama
substation EWSA scope
Norm Duration of Proc Steps
Construction of MV and LV lines with
EWSA supplied Materials (Southern
Zone)
Construction of MV and LV lines with
EWSA supplied Materials (Northern
Zone)
838940PROP0P110Box0382116B00PUBLIC0.xls 7 of 28 01/09/2014 3:10 AM
![Page 8: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/8.jpg)
Procurement Plan-Works Total Cost
838940PROP0P110Box0382116B00PUBLIC0.xls 8 of 28 01/09/2014 3:10 AM
![Page 9: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/9.jpg)
Procurement Plan-Works Country/Organisation: RWANDA
Project/Programme: Electricity Access Scale-Up and Sector Wide Approach Development Project (EASSDP)
Loan #: Credit IDA 51930
Description*
List of Contracts
Engineering, procurement and
construction contract for green field
areas (Southern Zone)
Engineering, procurement and
construction contract for green field
areas (Northern Zone)
Construction of 110kV line Bugarama-
Ntendezi (23km) and Construction of
110/30kV Ntendezi substation
Construction of 110/30/6.6kV Bugarama
substation EWSA scope
Norm Duration of Proc Steps
Construction of MV and LV lines with
EWSA supplied Materials (Southern
Zone)
Construction of MV and LV lines with
EWSA supplied Materials (Northern
Zone)
If Post-Review, No-objection Dates are not needed
Spec Proc Notice
Advert
Plan
vs.
Actual
Prep &
Submission
by Ex Agency
No-objection
Date
On-line UNDB
Gateway
Nat Press
Bid Invitation
Date
Bid Closing-
Opening
Submission
Bid Eval Rpt
No-objection
Date
Plan 4 - 7 wks 1 - 1.5 wks 1.5 - 2 wks 1.5 - 2 wks 6 -12 wks 2 - 6wks 1 - 1.5 wks
Actual
Plan 01-Dec-13 11-Dec-13 25-Dec-13 25-Dec-13 23-Feb-14 4-Apr-14 14-Apr-14
Actual
Plan 15-Jan-14 25-Jan-14 8-Feb-14 8-Feb-14 9-Apr-14 19-May-14 29-May-14
Actual
Plan 05-Jun-13 14-Jun-13 24-Jun-13 24-Jun-13 17-Oct-13 26-Nov-13 6-Dec-13
Actual
Plan 08-Jul-13 19-Sep-13 24-Oct-13 24-Oct-13 22-Jan-14 19-Feb-14 1-Mar-14
Actual
Plan 15-Dec-13 27-Dec-13 10-Jan-14 10-Jan-14 14-Mar-14 11-Apr-14 21-Apr-14
Actual
Plan 15-Dec-13 27-Dec-13 10-Jan-14 10-Jan-14 14-Mar-14 11-Apr-14 21-Apr-14
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Bid EvaluationBidding Period
Draft Bid Documents, including specs
and quantities, draft SPN
838940PROP0P110Box0382116B00PUBLIC0.xls 9 of 28 01/09/2014 3:10 AM
![Page 10: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/10.jpg)
Procurement Plan-Works Total Cost Plan
Actual
838940PROP0P110Box0382116B00PUBLIC0.xls 10 of 28 01/09/2014 3:10 AM
![Page 11: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/11.jpg)
Procurement Plan-Works Country/Organisation: RWANDA
Project/Programme: Electricity Access Scale-Up and Sector Wide Approach Development Project (EASSDP)
Loan #: Credit IDA 51930
Description*
List of Contracts
Engineering, procurement and
construction contract for green field
areas (Southern Zone)
Engineering, procurement and
construction contract for green field
areas (Northern Zone)
Construction of 110kV line Bugarama-
Ntendezi (23km) and Construction of
110/30kV Ntendezi substation
Construction of 110/30/6.6kV Bugarama
substation EWSA scope
Norm Duration of Proc Steps
Construction of MV and LV lines with
EWSA supplied Materials (Southern
Zone)
Construction of MV and LV lines with
EWSA supplied Materials (Northern
Zone)
Plan
vs.
Actual
Contract Amount
in US$ '000
Date
Contract
Award
Date
Contract
Signature
Mobilization
Advance
Payment
Substantial
Completion
Final
Acceptance
Plan 1 wk 1.5-3 wks
Actual
Plan 21-Apr-14 12-May-14 26-Jun-14 21-Jun-15 15-Jun-16
Actual
Plan 5-Jun-14 26-Jun-14 10-Aug-14 5-Aug-15 30-Jul-16
Actual
Plan 13-Dec-13 3-Jan-14 17-Feb-14 11-Aug-15 5-Aug-16
Actual
Plan 8-Mar-14 29-Mar-14 13-May-14 4-Nov-15 29-Oct-16
Actual
Plan 28-Apr-14 19-May-14 3-Jul-14 25-Dec-15 19-Dec-16
Actual
Plan 28-Apr-14 19-May-14 3-Jul-14 25-Dec-15 19-Dec-16
Actual
Plan
Actual
Plan
Actual
Plan
Actual
Contract Finalization Contract Implementation
838940PROP0P110Box0382116B00PUBLIC0.xls 11 of 28 01/09/2014 3:10 AM
![Page 12: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/12.jpg)
Procurement Plan-Works Total Cost Plan 0.00
Actual 0.00
838940PROP0P110Box0382116B00PUBLIC0.xls 12 of 28 01/09/2014 3:10 AM
![Page 13: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/13.jpg)
Procurement Plan-Works Country/Organisation: RWANDA
Project/Programme: Electricity Access Scale-Up and Sector Wide Approach Development Project (EASSDP)
Loan #: Credit IDA 51930
Description*
List of Contracts
Engineering, procurement and
construction contract for green field
areas (Southern Zone)
Engineering, procurement and
construction contract for green field
areas (Northern Zone)
Construction of 110kV line Bugarama-
Ntendezi (23km) and Construction of
110/30kV Ntendezi substation
Construction of 110/30/6.6kV Bugarama
substation EWSA scope
Norm Duration of Proc Steps
Construction of MV and LV lines with
EWSA supplied Materials (Southern
Zone)
Construction of MV and LV lines with
EWSA supplied Materials (Northern
Zone)
Final
Cost
Contract Implementation
838940PROP0P110Box0382116B00PUBLIC0.xls 13 of 28 01/09/2014 3:10 AM
![Page 14: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/14.jpg)
Procurement Plan-Works Total Cost 0.00
0.00
838940PROP0P110Box0382116B00PUBLIC0.xls 14 of 28 01/09/2014 3:10 AM
![Page 15: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/15.jpg)
Procurement Plan-Works Country/Organisation: RWANDA
Project/Programme: Electricity Access Scale-Up and Sector Wide Approach Development Project (EASSDP)
Loan #: Credit IDA 51930
Description*
List of Contracts
Engineering, procurement and
construction contract for green field
areas (Southern Zone)
Engineering, procurement and
construction contract for green field
areas (Northern Zone)
Construction of 110kV line Bugarama-
Ntendezi (23km) and Construction of
110/30kV Ntendezi substation
Construction of 110/30/6.6kV Bugarama
substation EWSA scope
Norm Duration of Proc Steps
Construction of MV and LV lines with
EWSA supplied Materials (Southern
Zone)
Construction of MV and LV lines with
EWSA supplied Materials (Northern
Zone)
Comments
Tender under evaluation
Tender published
838940PROP0P110Box0382116B00PUBLIC0.xls 15 of 28 01/09/2014 3:10 AM
![Page 16: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/16.jpg)
Procurement Plan-Works Total Cost
838940PROP0P110Box0382116B00PUBLIC0.xls 16 of 28 01/09/2014 3:10 AM
![Page 17: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/17.jpg)
Procurement Plan-Consultants Country/Organisation: RWANDA For Contracts under projects approved after the May 2002 Guidelines
Project/Programme: Electricity Access Scale-Up and Sector Wide Approach Development Project (EASSDP)If Post-Review, No-objection Dates are not needed
Loan #: Credit IDA 51930Contract
Type
Description*Selection
Method
Lumpsum
or
Time-Based
Prior/Post
Review
Plan
vs.
Actual
Prep &
Submission
by Ex Ag
No-objection
Date
On-line UNDB
Gateway
Nat Press
Submission of
Expression of
interest
Lead-time
before
shortlist
Plan 3 - 6 wks 1 - 2 wks 1 - 1.5 wks 2 wks 2 wks
Actual
List of Contracts
CQS
Lumpsum
Post Review Plan 15-Jul-13 29-Jul-13 8-Aug-13 22-Aug-13 5-Sep-13
Actual
CQS
Lumpsum
Post Review Plan 25-Aug-14 8-Sep-14 18-Sep-14 2-Oct-14 16-Oct-14
Actual
QBS Lumpsum Prior Review Plan 20-Dec-13 3-Jan-14 13-Jan-14 27-Jan-14 10-Feb-14
Actual
IC Lumpsum Post Review Plan 15-Oct-13 29-Oct-13 8-Nov-13 22-Nov-13 6-Dec-13
Actual
CQS Time Based Post Review Plan 25-Dec-13 8-Jan-14 18-Jan-14 1-Feb-14 15-Feb-14
Actual
IC Lumpsum Post Review Plan 21-Nov-13 21-Nov-13 9-Dec-13 24-Dec-13 3-Jan-14
Actual
IC Lumpsum Post Review Plan 5-Dec-13 12-Dec-13 19-Dec-13 3-Jan-14 13-Jan-14
Actual
IC Lumpsum Post Review Plan 5-Dec-13 12-Dec-13 19-Dec-13 3-Jan-14 13-Jan-14
Consultancy services for
recruitment of independent pre-
shipment inspection agency
Request for EOI
(where required)Preparation
Terms of Reference
Norm Duration of Proc Steps
Consultancy Services for impact
evaluation phase 1
consultant to supervise contracts as
a Project Manager to mitigate the
issue of partiality during contract
management
Consultancy Services for impact
evaluation phase 2
Consultancy services for
eleboration of technical
specification of SWH
Study to establish and advise on
legal framework for new companies
to replace EWSA
Study to undertake the Energy
Sector Functional and
Organizational restructuring of
EWSA
Study to undertake scoping for
Management Information System
(MIS)838940PROP0P110Box0382116B00PUBLIC0.xls 17 of 28 01/09/2014 3:10 AM
![Page 18: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/18.jpg)
Procurement Plan-Consultants Actual
CQS Lumpsum Post Review Plan 5-Dec-13 12-Dec-13 19-Dec-13 2-Jan-14 16-Jan-14
Actual
CQS Lumpsum Post Review Plan 21-Nov-13 21-Nov-13 9-Dec-13 23-Dec-13 6-Jan-14
Actual
SSS Lumpsum Post Review Plan 22-Nov-13 22-Nov-13 Not Applicable 25-Nov-13 5-Dec-13
Actual
Total Cost Plan
Actual
Audit study to undertake separation
of assets
Development of Least cost Power
Development Plan
Short-term Consultant to Review
Proposed Strengthening Projects
for the EWSA HV and MV
Networks
Study to undertake scoping for
Management Information System
(MIS)
838940PROP0P110Box0382116B00PUBLIC0.xls 18 of 28 01/09/2014 3:10 AM
![Page 19: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/19.jpg)
Procurement Plan-Consultants Country/Organisation: RWANDA
Project/Programme: Electricity Access Scale-Up and Sector Wide Approach Development Project (EASSDP)
Loan #: Credit IDA 51930
Description*
List of Contracts
Consultancy services for
recruitment of independent pre-
shipment inspection agency
Norm Duration of Proc Steps
Consultancy Services for impact
evaluation phase 1
consultant to supervise contracts as
a Project Manager to mitigate the
issue of partiality during contract
management
Consultancy Services for impact
evaluation phase 2
Consultancy services for
eleboration of technical
specification of SWH
Study to establish and advise on
legal framework for new companies
to replace EWSA
Study to undertake the Energy
Sector Functional and
Organizational restructuring of
EWSA
Study to undertake scoping for
Management Information System
(MIS)
Submission
Date
No-objection
Date
1 - 2 wks
5-Sep-13 Not Applicable
16-Oct-14 Not Applicable
11-Feb-14 25-Feb-14
6-Dec-13 Not Applicable
16-Feb-14 2-Mar-14
3-Jan-14 Not Applicable
13-Jan-14 Not Applicable
13-Jan-14 Not Applicable
Request for Proposals
838940PROP0P110Box0382116B00PUBLIC0.xls 19 of 28 01/09/2014 3:10 AM
![Page 20: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/20.jpg)
Procurement Plan-Consultants
Total Cost
Audit study to undertake separation
of assets
Development of Least cost Power
Development Plan
Short-term Consultant to Review
Proposed Strengthening Projects
for the EWSA HV and MV
Networks
Study to undertake scoping for
Management Information System
(MIS)
16-Jan-14 Not Applicable
6-Jan-14 Not Applicable
5-Dec-13 Not Applicable
838940PROP0P110Box0382116B00PUBLIC0.xls 20 of 28 01/09/2014 3:10 AM
![Page 21: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/21.jpg)
Procurement Plan-Consultants Country/Organisation: RWANDA
Project/Programme: Electricity Access Scale-Up and Sector Wide Approach Development Project (EASSDP)
Loan #: Credit IDA 51930
Description*
List of Contracts
Consultancy services for
recruitment of independent pre-
shipment inspection agency
Norm Duration of Proc Steps
Consultancy Services for impact
evaluation phase 1
consultant to supervise contracts as
a Project Manager to mitigate the
issue of partiality during contract
management
Consultancy Services for impact
evaluation phase 2
Consultancy services for
eleboration of technical
specification of SWH
Study to establish and advise on
legal framework for new companies
to replace EWSA
Study to undertake the Energy
Sector Functional and
Organizational restructuring of
EWSA
Study to undertake scoping for
Management Information System
(MIS)
Plan
vs.
Actual
Invitation
Date
Submission/
Opening
Date
Submission
Evaluation
Report (T)
No-objection
Evaluation
Report (T)
Opening
Financial
Proposals
Preparation
Eval Report
(T) (F)
Negotiations (N)
Plan 4 to 12 wks 2 - 3 wks 0.5 - 2 wks 2 wks 1 - 2 wks 2 wks
Actual
Plan 5-Sep-13 3-Oct-13 17-Oct-13 Not Applicable 3-Oct-13 17-Oct-13 31-Oct-13
Actual
Plan 16-Oct-14 13-Nov-14 27-Nov-14 Not Applicable 13-Nov-14 27-Nov-14 11-Dec-14
Actual
Plan 28-Feb-14 19-Apr-14 10-May-14 24-May-14 7-Jun-14 14-Jun-14 28-Jun-14
Actual
Plan 6-Dec-13 13-Dec-13 20-Dec-13 Not Applicable 13-Dec-13 20-Dec-13 27-Dec-13
Actual
Plan 5-Mar-14 24-Apr-14 15-May-14 29-May-14 12-Jun-14 19-Jun-14 3-Jul-14
Actual
Plan 3-Jan-14 10-Jan-14 17-Jan-14 Not Applicable 10-Jan-14 17-Jan-14 19-Jan-14
Actual
Plan 13-Jan-14 20-Jan-14 27-Jan-14 Not Applicable 20-Jan-14 27-Jan-14 29-Jan-14
Actual
Plan 13-Jan-14 20-Jan-14 27-Jan-14 Not Applicable 20-Jan-14 27-Jan-14 29-Jan-14
Proposal Evaluation and Negotiation for Projects after May 2002
Technical (T) & Financial (F) and Negotions (N)
Consultant
Proposals
838940PROP0P110Box0382116B00PUBLIC0.xls 21 of 28 01/09/2014 3:10 AM
![Page 22: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/22.jpg)
Procurement Plan-Consultants
Total Cost
Audit study to undertake separation
of assets
Development of Least cost Power
Development Plan
Short-term Consultant to Review
Proposed Strengthening Projects
for the EWSA HV and MV
Networks
Study to undertake scoping for
Management Information System
(MIS) Actual
Plan 16-Jan-14 23-Jan-14 30-Jan-14 Not Applicable 23-Jan-14 30-Jan-14 6-Feb-14
Actual
Plan 6-Jan-14 13-Jan-14 20-Jan-14 Not Applicable 13-Jan-14 20-Jan-14 27-Jan-14
Actual
Plan 5-Dec-13 12-Dec-13 19-Dec-13 Not Applicable 12-Dec-13 19-Dec-13 21-Dec-13
Actual
Plan
Actual
838940PROP0P110Box0382116B00PUBLIC0.xls 22 of 28 01/09/2014 3:10 AM
![Page 23: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/23.jpg)
Procurement Plan-Consultants Country/Organisation: RWANDA
Project/Programme: Electricity Access Scale-Up and Sector Wide Approach Development Project (EASSDP)
Loan #: Credit IDA 51930
Description*
List of Contracts
Consultancy services for
recruitment of independent pre-
shipment inspection agency
Norm Duration of Proc Steps
Consultancy Services for impact
evaluation phase 1
consultant to supervise contracts as
a Project Manager to mitigate the
issue of partiality during contract
management
Consultancy Services for impact
evaluation phase 2
Consultancy services for
eleboration of technical
specification of SWH
Study to establish and advise on
legal framework for new companies
to replace EWSA
Study to undertake the Energy
Sector Functional and
Organizational restructuring of
EWSA
Study to undertake scoping for
Management Information System
(MIS)
Plan
vs.
Actual
Submission DateNo-objection
Date
Contract Amount
in
US$ '000
Contract Award Contract
Signature
Plan 1 - 2 wks 1 - 2 wks 1 wk 1 - 3 wks
Actual
Plan 31-Oct-13 Not Applicable 7-Nov-13 21-Nov-13
Actual
Plan 11-Dec-14 Not Applicable 18-Dec-14 1-Jan-15
Actual
Plan 5-Jul-14 12-Jul-14 19-Jul-14 2-Aug-14
Actual
Plan 27-Dec-13 Not Applicable 3-Jan-14 17-Jan-14
Actual
Plan 10-Jul-14 17-Jul-14 24-Jul-14 7-Aug-14
Actual
Plan 19-Jan-14 Not Applicable 21-Jan-14 28-Jan-14
Actual
Plan 29-Jan-14 Not Applicable 31-Jan-14 7-Feb-14
Actual
Plan 29-Jan-14 Not Applicable 31-Jan-14 7-Feb-14
Draft Contract Contract Finalization
838940PROP0P110Box0382116B00PUBLIC0.xls 23 of 28 01/09/2014 3:10 AM
![Page 24: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/24.jpg)
Procurement Plan-Consultants
Total Cost
Audit study to undertake separation
of assets
Development of Least cost Power
Development Plan
Short-term Consultant to Review
Proposed Strengthening Projects
for the EWSA HV and MV
Networks
Study to undertake scoping for
Management Information System
(MIS) Actual
Plan 6-Feb-14 Not Applicable 13-Feb-14 27-Feb-14
Actual
Plan 27-Jan-14 Not Applicable 3-Feb-14 17-Feb-14
Actual
Plan 21-Dec-13 Not Applicable 23-Dec-13 30-Dec-13
Actual
Plan 0.00
Actual 0.00
838940PROP0P110Box0382116B00PUBLIC0.xls 24 of 28 01/09/2014 3:10 AM
![Page 25: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/25.jpg)
Procurement Plan-Consultants Country/Organisation: RWANDA
Project/Programme: Electricity Access Scale-Up and Sector Wide Approach Development Project (EASSDP)
Loan #: Credit IDA 51930
Description*
List of Contracts
Consultancy services for
recruitment of independent pre-
shipment inspection agency
Norm Duration of Proc Steps
Consultancy Services for impact
evaluation phase 1
consultant to supervise contracts as
a Project Manager to mitigate the
issue of partiality during contract
management
Consultancy Services for impact
evaluation phase 2
Consultancy services for
eleboration of technical
specification of SWH
Study to establish and advise on
legal framework for new companies
to replace EWSA
Study to undertake the Energy
Sector Functional and
Organizational restructuring of
EWSA
Study to undertake scoping for
Management Information System
(MIS)
Plan
vs.
Actual
Mobilization
Advance
Payment
Draft
Report
Final
Report
Final
Cost
Plan
Actual
Plan 21-Dec-13 20-Jan-14 19-Feb-14
Actual
Plan 31-Jan-15 2-Mar-15 1-Apr-15
Actual
Plan 16-Aug-14 11-Aug-15
Actual
Plan 24-Jan-14 23-Feb-14
Actual
Plan 21-Aug-14 10-Aug-16
Actual
Plan 4-Feb-14 21-Mar-14 5-Apr-14
Actual
Plan 14-Feb-14 31-Mar-14 15-Apr-14
Actual
Plan 14-Feb-14 31-Mar-14 15-Apr-14
Contract Implementation
838940PROP0P110Box0382116B00PUBLIC0.xls 25 of 28 01/09/2014 3:10 AM
![Page 26: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/26.jpg)
Procurement Plan-Consultants
Total Cost
Audit study to undertake separation
of assets
Development of Least cost Power
Development Plan
Short-term Consultant to Review
Proposed Strengthening Projects
for the EWSA HV and MV
Networks
Study to undertake scoping for
Management Information System
(MIS) Actual
Plan 6-Mar-14 4-Jun-14
Actual
Plan 24-Feb-14 25-May-14
Actual
Plan 6-Jan-14 20-Feb-14 7-Mar-14
Actual
Plan 0.00
Actual 0.00
838940PROP0P110Box0382116B00PUBLIC0.xls 26 of 28 01/09/2014 3:10 AM
![Page 27: World Bank Documentdocuments.worldbank.org/curated/en/206871468305666424/pdf/838… · areas (Southern Zone) Basic Data Engineering, procurement and construction contract for green](https://reader033.vdocument.in/reader033/viewer/2022060218/5f06a29c7e708231d418f95a/html5/thumbnails/27.jpg)
SUMMARY
I Goods&Works Allocated Amounts Funds Available
1 Goods #REF!
2 Works #REF!
S/TOTAL #REF! 50,000,000.00
II Consultancy (TA)&Operating Cost
1 *Consultancy (TA) and operating costs 10,000,000.00
S/TOTAL 10,000,000.00 10,000,000.00
GENERAL TOTAL #REF! 60,000,000.00