world bank document - documents & reports - all...
TRANSCRIPT
Document of
The World Bank
Report No: ICR00003027
IMPLEMENTATION COMPLETION AND RESULTS REPORT
(IBRD-76220)
ON A
LOAN
IN THE AMOUNT OF US$4.4 MILLION
TO THE
UNITED MEXICAN STATES
FOR A
RESULTS-BASED MANAGEMENT AND BUDGETING PROJECT
June 30, 2014
Poverty Reduction and Economic Management
Colombia and Mexico Country Management Unit
Latin America and the Caribbean Region
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
CURRENCY EQUIVALENTS (Exchange Rate Effective April 10, 2014)
Currency Unit=Mexican Pesos
US$ 1.00 = MXP $13.05
MXP $1 = US$ 0.076
FISCAL YEAR January 1 – December 31
ABBREVIATIONS AND ACRONYMS
CONEVAL National Council for the Evaluation of Social Development Policy (Consejo
Nacional de Evaluación de la Política de Desarrollo Social)
GoM Government of Mexico
IADB Inter-American Development Bank
IEG Independent Evaluation Group
IFAI Federal Institute for Access to Public Information and Data Protection (Instituto
Federal de Acceso a la Información y Protección de Datos)
IT Information Technology
M&E Monitoring and Evaluation
NAFIN Development Banking Institution (Financial Agent: Nacional Financiera, S.N.C.)
NDP/PND National Development Plan (Plan Nacional de Desarollo)
OECD
PBR
Organization for Economic Co-operation and Development
Results Based-Budgeting (Presupuesto Basado en Resultados)
PFM
PGCM
Public Financial Management
Close and Modern Government Program (Programa de Gobierno Cercano y
Moderno)
PI
PMG
Performance Information
Management Improvement Program (Programa de Mejora de la Gestión)
PSBR Public Sector Borrowing Requirements
RBB Results-based budgeting
SE Undersecretary of Expenditures (Subsecretaría de Egresos)
SED Performance Evaluation System (Sistema de Evaluacion del Desempeno)
SFP Ministry of Public Administration (Secretaría de la Función Pública)
SHCP Ministry of Finance and Public Credit (Secretaría de Hacienda y Crédito
Público)
SIDAFF
SIGAIF
Integrated Federal Financial Management System (Sistema Integral de
Administración Financiera Federal)
Harmonized Governmental Financial Information System (Sistema
Gubernamental Armonizado de Información Financiera)
SISED Performance Evaluation Program Information System (Sistema de Información
para el Sistema de Evaluación del Desempeño)
Vice President: Jorge Familiar
Country Director: Gloria M. Grandolini
Sector Manager: Arturo Herrera Gutierrez
Project Team Leader: Pedro Arizti
ICR Team Leader: Pedro Arizti
MEXICO
Results-based Management and Budgeting Project
CONTENTS
Data Sheet
A. Basic Information
B. Key Dates
C. Ratings Summary
D. Sector and Theme Codes
E. Bank Staff
F. Results Framework Analysis
G. Ratings of Project Performance in ISRs
H. Restructuring
I. Disbursement Graph
1. Project Context, Development Objectives and Design ............................................... 1
2. Key Factors Affecting Implementation and Outcomes .............................................. 6
3. Assessment of Outcomes .......................................................................................... 11
4. Assessment of Risk to Development Outcome ......................................................... 15
5. Assessment of Bank and Borrower Performance ..................................................... 15
6. Lessons Learned ....................................................................................................... 18
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners .......... 19
Annex 1. Project Costs and Financing .......................................................................... 22
Annex 2. Outputs by Component ................................................................................. 23
Annex 3. Economic and Financial Analysis ................................................................. 26
Annex 4. Bank Lending and Implementation Support/Supervision Processes ............ 28
Annex 5. Beneficiary Survey Results ........................................................................... 30
Annex 6. Stakeholder Workshop Report and Results ................................................... 31
Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR ..................... 32
Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders ....................... 33
Annex 9. List of Supporting Documents ...................................................................... 34
MAP
A. Basic Information
Country: Mexico Project Name:
MX Results-based
Management and
Budgeting
Project ID: P106528 L/C/TF Number(s): IBRD-76220
ICR Date: 06/30/2014 ICR Type: Core ICR
Lending Instrument: TAL Borrower: GOVERNMENT OF
MEXICO
Original Total
Commitment: US$ 17.2M Disbursed Amount: US$ 0.37M
Revised Amount: US$ 4.4M
Environmental Category: C
Implementing Agencies:
Secretaría de Hacienda y Crédito Publico (SHCP)
Cofinanciers and Other External Partners:
B. Key Dates
Process Date Process Original Date Revised / Actual
Date(s)
Concept Review: 09/20/2007 Effectiveness: 03/19/2010 03/19/2010
Appraisal: 10/02/2008 Restructuring(s): 11/15/2012
Approval: 12/11/2008 Mid-term Review: 02/06/2012
Closing: 12/31/2013 12/31/2013
C. Ratings Summary
C.1 Performance Rating by ICR
Outcomes: Moderately Unsatisfactory
Risk to Development Outcome: Moderate
Bank Performance: Moderately Unsatisfactory
Borrower Performance: Moderately Unsatisfactory
C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)
Bank Ratings Borrower Ratings
Quality at Entry: Moderately
Unsatisfactory Government:
Moderately
Unsatisfactory
Quality of Supervision: Moderately
Unsatisfactory
Implementing
Agency/Agencies:
Moderately
Unsatisfactory
Overall Bank
Performance:
Moderately
Unsatisfactory Overall Borrower
Performance:
Moderately
Unsatisfactory
C.3 Quality at Entry and Implementation Performance Indicators
Implementation
Performance Indicators
QAG Assessments
(if any) Rating
Potential Problem Project
at any time (Yes/No): No
Quality at Entry
(QEA): None
Problem Project at any
time (Yes/No): Yes
Quality of
Supervision (QSA): None
DO rating before
Closing/Inactive status:
Moderately
Unsatisfactory
D. Sector and Theme Codes
Original Actual
Sector Code (as % of total Bank financing)
Central government administration 100 100
Theme Code (as % of total Bank financing)
Managing for development results 50 50
Public expenditure, financial management and
procurement 50 50
E. Bank Staff
Positions At ICR At Approval
Vice President: Jorge Familiar Pamela Cox
Country Director: Gloria M. Grandolini Axel van Trotsenburg
Sector Manager: Arturo Herrera Gutierrez Nicholas Paul Manning
Project Team Leader: Pedro Arizti Roberto Adrian Senderowitsch
ICR Team Leader: Pedro Arizti
ICR Primary Author: Azul Del Villar
F. Results Framework Analysis
Project Development Objectives (from Project Appraisal Document) The development objective of the project is to establish that federal departments and agencies in
Mexico provide decision makers and the public with rigorous, timely, user-friendly information
on the efficiency and effectiveness of government organizations and program expenditures.
Revised Project Development Objectives (as approved by original approving authority) The objective of the project is to strengthen the Ministry of Finance’s (Secretaría de Hacienda y
Crédito Público, SHCP) capacity to (i) allow the use of standardized performance information of
priority public programs during budget preparation; (ii) generate harmonized subnational fiscal
information; and (iii) disseminate budget performance information to the Borrower's citizens on a
regular basis.
(a) PDO Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target
Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1 : Performance information using a performance framework is generated and used
during budget request discussions between line secretariats and SHCP.
Value
(quantitative or
qualitative)
Performance is not widely
used by line secretariats
in their budget requests.
Budget preparation
discussions are mainly
focused on inputs and are
not based on standardized
performance information
that allow to measure
relevance, efficiency of
programs.
Performance
information
(PI) is used by
SHCP during
budget
preparation in
conversation
with line
ministries.
SHCP
uses
standardized
performance
information
that allow to
measure
relevance,
efficiency of
effectiveness
of programs.
Performance
information (PI)
presented in a
timely fashion to
Congress in a
format that allows
interpretation and
meets their needs.
Content includes
outcome and output
measures. Line
ministries send
budget requests to
SHCP with PI.
Date achieved 10/03/2012 12/31/2013 12/31/2013
Comments
(incl. %
achievement)
Achieved
Indicator 2 : An active network and a portal to inform civil society at large on a regular basis
about budget performance increasing transparency and accountability to citizens.
Value
quantitative or
Qualitative)
Budget performance
information is readily
available to civil society
via the new portal but has
not been expanded to all
levels of Government.
There is a
portal
containing
financial and
non-financial
performance
information
about the
budget and its
process
available for
citizens, and
the
Portal containing PI
on budget
performance is
available to citizens
+ Citizen’s Budget
+ Citizen’s Public
Accounts (Cuenta
Pública)
information
has been
expanded to
all the levels
of
Government.
Date achieved 10/03/2012 12/31/2013 12/31/2013
Comments
(incl. %
achievement)
Achieved, the portal site address is: www.transparenciapresupuestaria.gob.mx
Indicator 3 : Percent of public programs with improved strategic design and reporting
Value
quantitative or
Qualitative)
In 2008 the percentage of
public programs using
performance information
was 28%.
For the 2013
budget
preparation the
percentage of
programs
using
performance
information is
set to be over
75%.
The majority of the
programs have a
more robust design
across key
dimensions
(objectives,
indicators,
baselines, links to
strategies) enabling
better reporting and
evaluation. (832
programs out of
984)
Date achieved 10/03/2012 12/31/2013 12/31/2013
Comments
(incl. %
achievement)
Achieved at 84.5%
Indicator 4 : Percent of municipalities that have a simplified financial management system
installed and working.
Value
quantitative or
Qualitative)
0
Around 80%
of
approximately
1,200 small
municipalities
(of total
approximately
2,500
municipalities)
The Accounting
Unit changed
priorities to focus
on developing the
Government
Accounting System
(SCG) first.
Date achieved 10/03/2012 12/31/2013 12/31/2013
Comments
(incl. %
achievement)
Not achieved
(b) Intermediate Outcome Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1 : Number of municipalities that have been trained in the use of the new municipal
simplified FMIS.
Value
(quantitative
or Qualitative)
Around 80%
of
approximately
1,200 small
municipalities
Pilot of
Harmonized
Governmental
Financial
Information System
(SIGAIF) installed
in some
municipalities, not
operational though.
The Accounting
Unit changed
priorities to focus
on developing the
Government
Accounting System
(SCG) first.
Date achieved 10/03/2012 12/31/2013 12/31/2013
Comments
(incl. %
achievement)
Not achieved
Indicator 2 : Functional design developed for the amplified FMIS that will cover the
decentralized institutions in the Government.
Value
(quantitative
or Qualitative)
Non existent
SIDAFF has a
module
designed for
decentralized
institutions.
The Accounting
Unit changed
priorities to focus
on developing the
Government
Accounting System
first.
Date achieved 10/03/2012 12/31/2013 12/31/2013
Comments
(incl. %
achievement)
Not achieved
Indicator 3 : Design of a conceptual model for integration of financial information in
municipalities, states and federation.
Value
(quantitative
or Qualitative)
Non existent
SIDAFF has a
module
designed for
integrating all
three levels of
Government.
The Accounting
Unit changed
priorities to focus
on developing the
Government
Accounting System
first.
Date achieved 10/03/2012 12/31/2013 12/31/2013
Comments
(incl. %
achievement)
Not achieved
Indicator 4 : Design and dissemination of a number of strategic evaluations (e.g. security
policy, water policy, education).
Value
(quantitative
or Qualitative)
Non existent
Strategic
social and
non-social
evaluations
carried out and
disseminated
through the
portal.
Three strategic
evaluations were
published in the
Budget
Transparency Portal
in April 2014.
Date achieved 10/03/2012 12/31/2013 04/30/2014
Comments
(incl. %
achievement)
Partially achieved.
Indicator 5 : Design of terms of reference for non-social program evaluations.
Value
(quantitative
or Qualitative)
Non existent
Terms of
Reference
(ToR) for non-
social program
evaluations
available.
SHCP has advised
on adapting ToR to
conduct program
evaluations other
than social, and on
revising the ToR of
the Consistency and
Results evaluations
as well as the Cost
Effectiveness for
non social programs
Date achieved 10/03/2012 12/31/2013 12/31/2013
Comments
(incl. %
achievement)
Not achieved
Indicator 6 : Development of a methodology and guidelines for better social program
focalization.
Value
(quantitative
or Qualitative)
Non existent
Methodology
and guidelines
for better
social program
focalization
available.
Not achieved
Date achieved 10/03/2012 12/31/2013 12/31/2013
Comments
(incl. %
achievement)
Not achieved
Indicator 7 : Public programs portfolio review to identify program delays and development of
methodology for ex ante screening.
Value
(quantitative
or Qualitative)
Non existent
Public
programs
portfolio
review carried
out and
methodology
for ex ante
screening
available.
Not achieved
Date achieved 10/03/2012 12/31/2013 12/31/2013
Comments
(incl. %
achievement)
Not achieved
Indicator 8 : Design and dissemination of an evaluation for the SED
Value
(quantitative
or Qualitative)
Non existent
SED
evaluation
carried out and
disseminated
through the
portal.
Important changes
will take place
fostered by the
PND, regarding the
SED’s scope (i.e.
PGCM)
Date achieved 10/03/2012 12/31/2013 12/31/2013
Comments
(incl. %
achievement)
Not achieved
G. Ratings of Project Performance in ISRs
No. Date ISR
Archived DO IP
Actual
Disbursements
(US$ millions)
1 01/27/2009 Satisfactory Satisfactory 0.00
2 09/18/2009 Moderately Satisfactory Moderately
Unsatisfactory 0.00
3 06/11/2010 Moderately Satisfactory Moderately
Unsatisfactory 0.00
4 12/14/2010 Moderately Satisfactory Moderately
Unsatisfactory 0.00
5 04/26/2011 Moderately Satisfactory Moderately
Unsatisfactory 0.00
6 11/02/2011 Moderately Satisfactory Moderately
Unsatisfactory 0.00
7 05/16/2012 Moderately Satisfactory Moderately
Unsatisfactory 0.00
8 01/07/2013 Moderately Satisfactory Moderately
Unsatisfactory 0.02
9 04/01/2013 Moderately Satisfactory Moderately
Unsatisfactory 0.02
10 12/07/2013 Moderately Unsatisfactory 0.21
Unsatisfactory
H. Restructuring (if any)
Restructuring
Date(s)
Board
Approved
PDO Change
ISR Ratings at
Restructuring
Amount
Disbursed at
Restructuring
in
US$ millions
Reason for Restructuring &
Key Changes Made DO IP
11/15/2012 Y MS MU 0.00
The restructuring aligned the
PDO to a reduced Project scope
and partial loan cancellation.
If PDO and/or Key Outcome Targets were formally revised (approved by the original approving
body) enter ratings below:
Outcome Ratings
Against Original PDO/Targets Moderately Unsatisfactory
Against Formally Revised PDO/Targets Moderately Unsatisfactory
Overall (weighted) rating Moderately Unsatisfactory
I. Disbursement Profile
1
1. Project Context, Development Objectives and Design
1.1 Context at Appraisal
1. During the 2004-2007 period, the Mexican economy experienced a balanced and
broad-based economic expansion with an average annual gross domestic product (GDP)
growth rate of 3.8 percent. A vigorous global economic expansion contributed to the
enhanced growth performance, as the value of exports increased at a double-digit annual
average rate. Price stability also contributed to a healthy growth of domestic demand,
with improved purchasing power of wages and salaries, and an expansion of domestic
credit and consumer lending.
2. In this context, the fiscal reform approved in September 2007 marked a crucial
step in strengthening the country’s fiscal accounts. This fiscal reform enabled the
Government of Mexico (GoM) to raise tax collection rates, strengthen fiscal federalism,
and decrease tax evasion. Building on the improved macroeconomic and fiscal
framework, the GoM focused on enhancing the quality of public expenditures throughout
the budget cycle, from planning to execution and evaluation. As a result, the Government
established a results-based budgeting initiative, the Performance Evaluation System
(Sistema de Evaluación del Desempeño, SED), for which it sought Bank support.
3. Furthermore, the 2008-2013 Country Partnership Strategy (CPS) for Mexico
called for strengthening institutions to improve their functioning and enhancing citizen
perceptions of the public sector through a set of initiatives that included a move towards
results-based budgeting. The higher-level objective of the Project—improving the
quality of public expenditures in Mexico—was therefore fully consistent with the FY08-
13 CPS. The Project was also aligned with two of the primary objectives of the 2007-
2012 National Development Plan (NDP), which aimed to “improve regulation,
management, the processes and results of Federal Public Administration to satisfy citizen
needs in relation to the provision of public goods and services;” and “promote and
guarantee transparency, accountability, access to information, and the protection of
personal information in all spheres of government.”1
1.2 Original Project Development Objectives (PDO) and Key Indicators
4. The original objective of the Project was to strengthen the Borrower’s capacity
(through its federal departments and agencies) to provide decision makers and the public
with rigorous, timely, user-friendly information on the efficiency and effectiveness of
government organizations and their program expenditures.2
1 Mexico Country Partnership Strategy FY 2008-2013, March 4, 2008, Report No. 42846-MX.
2There is a slight difference between the Original PDO in the PAD and the Loan Agreement (LA). The one used in the
ICR is that of the LA.
2
5. The original PDO indicators were: (i) Performance information presented in
budget requests from line ministries to SHCP and in budget submitted to Congress; (ii)
Satisfaction of Congress and civil society organizations with the performance information
made available via government websites (as measured through user surveys); (iii) Percent
of programs with improved strategic design and reporting3
; (iv) Progression of
organizations through the steps (levels) established for each Management Improvement
Program (Programa de Mejora de la Gestión, PMG), marking increased levels of
administrative capacity and efficiency.
1.3 Revised PDO (as approved by original approving authority) and Key Indicators,
and reasons/justification
6. The Project had to be restructured (level 1) in November 2012 as a result of
changes in national priorities and most importantly, due to the fact that some activities
had been financed and implemented using local funds, in light of the loan’s start up
delays and lengthy process towards effectiveness. Therefore, the Government and the
Bank agreed on reducing the Project scope, partially cancelling the loan and redesigning
activities to better align them with Government priorities.
7. In order to align them with a reduced Project scope and partial loan cancellation,
the PDO and its key indicators and the results framework were revised. The revised PDO
is to strengthen SHCP’s capacity to: (i) allow the use of standardized performance
information of priority public programs during budget preparation; (ii) generate
harmonized sub-national fiscal information; and (iii) disseminate budget performance
information to the Borrower’s citizens on a regular basis. The table below illustrates the
change in key indicators.
Table 1. Changes in PDO indicators
Original PDO-Level Indicator
(PAD 2008)
Revised PDO-Level Indicator (restructuring
2012)
1. Performance information presented in budget
requests from line ministries to SHCP and in
budget submitted to Congress.
(Revised) Performance information using a
performance framework is generated and used
during budget request discussions between line
secretariats and SHCP.
2. Satisfaction of Congress and civil society
organizations with the performance
information made available via government
websites (as measured through user surveys).
(Revised) An active network and a portal to
inform society at large on a regular basis about
budget performance, increasing transparency
and accountability to citizens.
3. Percent of programs with improved strategic
design and reporting.
(Revised) Percent of public programs for which
there is performance information using a
standardized performance framework.
3There is evidence from previous analytic work supported by the Bank (Technical assistance to the SHCP on October
2007, corroborated by subsequent CONEVAL analysis) that the quality of strategic design of public programs is weak
along several different dimensions (objectives, indicators, link to strategies). Using equivalent dimensions, the UED
unit was supposed to be able to measure overall quality over time, using that previous work as a baseline.
3
4. Progression of organizations through the
steps (levels) established for each PMG
system, marking increased levels of
administrative capacity and efficiency.
(Dropped original and replaced with new)
Percent of municipalities that have a simplified
financial management system installed and
working.
Source: Proposed Project Restructuring of Results-based Management and Budgeting Loan 68464-MX, 2012.
1.4 Main Beneficiaries
8. The primary target groups of the Project were the users of performance
information, including line ministries, Congress and the general public. These main
beneficiaries did not change when the Project was restructured.
1.5 Original Components (as approved)4
Component 1.Management Improvement Program.
9. Provision of technical assistance and training for the design and implementation
of selected management improvement and austerity systems, including, inter alia:
(a) assistance in the design of the institutional module of the Borrower’s Programa
Especial de la Mejora de la Gestión en la Administración Pública Federal 2008-2012;
(b) assistance for technical groups established and to be established with respect to each
of said management improvement and austerity systems; and
(c) capacity building for actors responsible for the implementation of said management
improvement and austerity systems.
Component 2. Results-Based Management and Budgeting Integrated Information Systems
10. Provision of technical assistance and training to support the development of an
integrated information system, including, inter alia, the development of the necessary
institutional arrangements, procedures, and an associated electronic database to:
(a) receive budget and other expenditure information from different sources;
(b) organize and analyze said information; and
(c) produce abridged, user-friendly reports with key messages to inform various
stakeholders and improve transparency of budget execution.
Component 3.Financial Management Strengthening for Results-Based Budgeting
11. Provision of technical assistance and training to strengthen the quality and
integrity of financial data, including, inter alia:
(a) modernization of the Borrower’s public accounts (Cuenta Pública) and the underlying
government accounting systems to strengthen the usefulness, integrity and transparency
4 The components are presented as per the Loan Agreement. For a more detailed description of the original
components see the Project Appraisal Document Report No: 46271-MX.
4
of public accounting records and related accounting management systems for
management decision making and public accountability; and
(b) strengthening of the quality and timeliness of the Borrower’s budget execution
reporting.
Component 4. Results-Based Management and Evaluation System Consolidation
12. Provision of technical assistance and training to:
(a) address government’s capacity limitations to carry out, contract and use evaluations of
government programs; and
(b) consolidate a system to evaluate the effectiveness of federal policies and programs
through, inter alia:
(i) (A) creation and consolidation of a Sistema de Evaluación del Desempeño in the
Borrower’s government; and
(B) strengthening of the alignment of the Borrower’s National System for
Democratic Planning components, including, Vision 2030, National Development
Plan, sector strategies and budgetary programs and the strengthening of a selected
set of strategic indicators based on sharper program design, and ownership
building of these indicators among the Borrower’s line secretariats;
(ii) strengthening the generation of performance data for the analysis of the
Programas Federales; and
(iii) implementation of results-based management approaches at the state level.
Component 5. Monitoring and Evaluation
13. Provision of technical assistance and training to SFP and SHCP to develop the
necessary organizational and evaluation capacity to monitor the progress and to evaluate
the implementation of the Borrower’s Sistema de Evaluación del Desempeño and related
institutional reforms.
1.6 Revised Components
14. The November 2012 restructuring (level 1) introduced the following changes to
the components:
(i) Components 1 (Management Improvement Program) and 2 (Results-Based
Management and Budgeting Integrated Information Systems) were cancelled as a
result of changes in Government priorities and use of own resources;
(ii) Component 3 (Financial Management Strengthening for Results-Based
Budgeting) continued as originally designed with some changes in activities that
focused on modernizing Government accounting and public accounts, as well as
harmonizing and integrating budget execution reporting;
(iii) Component 4 (Results-Based Management and Evaluation System Consolidation)
was revised to update Project activities with respect to consolidating the
5
Government evaluation system and to include a fourth sub-component according
to the following description5:
“the provision of support to the Borrower’s fiscal transparency initiatives
including: (a) the participatory design and implementation of an integrated fiscal
transparency web portal, and (b) the design of guidelines and regulations to foster
fiscal transparency in the Borrower’s federal, state and municipal levels of
government”;
(iv) Component 5 (Monitoring and Evaluation) would continue with some changes in
activities including cancellation of activities to be originally implemented by SFP.
The revised description6 is as follows:
“Provision of technical assistance and training to SHCP to develop the necessary
organizational and evaluation capacity to monitor the progress and to evaluate the
implementation of the Borrower's Sistema de Evaluación del Desempeño and
related institutional reforms.”
1.7 Other significant changes
15. The November 2012 restructuring (level 1) introduced these additional changes:
(i) the restructured Project was to be implemented solely by the SHCP through its
Subscretaría de Egresos (SE) eliminating the participation of the Public
Administration Ministry or Secretaría de la Función Pública, SFP;
(ii) the Project financing reflected the cancellation of US$12.756 million of the
loan amount (from US$17.2 million to US$4.4 million) and revisions to the
costs by component, financing plan and expenditure categories;
(iii) the procurement arrangements were changed to apply the Consultant and
Procurement Guidelines of May 2004 as revised October 1, 2006 and May 1,
2010 to the restructured Project; this was to enable application of the Bank
Guidelines that are harmonized with the then currently authorized policies and
procedures for externally funded projects in the country; and
(iv) the procurement plan and implementation schedule was revised as a result of
the reduction in Project scope and partial loan cancellation.
16. With respect to Project financing changes, the total Project cost was reduced from
US$31.9 million to US$6.7 million (excluding front-end fee)7. In terms of the Project’s
financing plan, the reduction in total Project cost reduced both the counterpart fund
contribution as well as the required IBRD loan amount (from US$17.2 million to US$4.4
million including the front-end fee). See Table 2 for details.
5 Amendment to the Loan Agreement dated November 29, 2012. 6 Ibid. 7 See Annex 1 for more details.
6
Table 2: Summary of Project Total Costs and Estimated Financing Plan (US$ million)
As approved (PAD) After restructuring
Components/Activities Local IBRD Total Local IBRD Total
1. Management
improvement program
(PMG)
0 7.600 7.600 0 0 0
2. Development of an
Integrated Information
System for Results-Based
Budgeting and
Management (SISED)
2.100 1.900 4.000 0 0 0
3. Strengthening Financial
Information for the
implementation of Results
Based Budgeting
2.075 1.925 4.000 1.850 2.925 4.775
4. Consolidation of the
Performance Evaluation
System and Results Based
Budgeting
6.050 4.000 10.050 0.440 1.131 1.571
5. Institutional
Strengthening and
Program Monitoring and
Evaluation
4.500 1.775 6.275 0 0.3875 .3875
TOTAL 14.725 17.200 31.925 2.29 4.4435 6.7335
Source: Proposed Project Restructuring of Results-based Management and Budgeting Loan 68464-MX, 2012.
2. Key Factors Affecting Implementation and Outcomes
2.1 Project Preparation, Design and Quality at Entry
17. The quality at entry is viewed to have been moderately unsatisfactory. During
preparation, the Project benefitted from synergies that emerged from activities organized
by the Bank, such as the Performance Budgeting workshop that took place in Mexico in
June 2008, which presented international experiences on the topic and became an
important input for the initial design of the reforms. In addition, the two original
counterparts, SFP and SHCP, also benefited from the economies of scale derived from
implementing the results-oriented agenda towards a comprehensive reform–including
both management and budget. However, the design of the Project was complex; the
potential lack of coordination between the two main counterparts (SFP and SHCP),
identified as substantial risk at appraisal, materialized during the Project’s initial stages
and implementation. Moreover, it should be noted that moving from monitoring budget
execution to results monitoring, and from compliance to results in public sector
management via a more comprehensive program, such as the PMG, implied a big reform.
Most countries in Latin America and in Asia—as highlighted by one of the peer
reviewers—have struggled with this type of changes. As such, even though counterparts
coordinated their efforts and defined their roles for the results-based management and
budgeting reform during the Project’s preparation, the significant delay in loan
effectiveness and subsequent delay in implementation suggests that the coordination
mechanisms needed for the Project were underestimated.
7
18. The PAD indicated that the Project met the criteria for readiness for
implementation.8
However, there were delays between the signing of the Loan
Agreement and the declaration of effectiveness. The Project was approved by the Board
on December 11, 2008. The Project’s legal agreement was signed on April 21, 2009, and
became effective on March 19, 2010 due to an unanticipated delay in internal GoM
administrative processes – specifically, the execution of the administrative agreements
(Contrato de Mandato)9 between the Borrower’s Representative (Public Credit Unit in
SHCP), the Financial Agent (Nacional Financiera, NAFIN), and the implementing
agencies - SFP and SHCP.
19. Overall, the long time elapsed since the loan’s approval and effectiveness (16
months), along with a challenging procurement environment involving multiple parties
(i.e., in Mexico it typically involves participation of three to four parties - the
implementing entity/ies, the financial agent and the Bank) and weak procurement
capacities in the implementing agencies, made it impossible for the Government to start
utilizing the loan proceeds until one and a half years after Board approval.
2.2 Implementation
20. The implementation of the Project is viewed to have been moderately
unsatisfactory primarily due to the lack of physical progress under the Project.
21. Start-up delays, a complex project design that included a governance framework
involving two implementing agencies, limited implementation capacity, as well as
changes in Government counterparts10
, severely hampered Project execution. Moreover,
within SHCP the reform and Project activities were not fully internalized or appropriated
in particular by the operational teams. SHCP areas (Budget Direction, Evaluation
Direction, and International Affairs) were not fully aligned conceptually regarding
Performance Based Budgeting and its priorities and targets. These resulted in the
Government requesting a partial cancellation of the Project (US$12.7 million equivalent
to 74% of Loan amount) as early as August 2011. As of Project restructuring in
November 2012, only the front-end fee for the IBRD loan of US$43,108 had been
disbursed under the loan. Moreover, lengthy procurement processes, in some cases
caused by changes in Project Government leaders and operational teams, not only
affected Project implementation but also posed a risk to its continuity, triggering internal
8 Readiness for implementation means that the Project ideally should become effective within four months from Board
approval and is able to evidence physical implementation including initial disbursement for project activities (not just front-end fee) within the first six months following effectiveness.
9There were two specific effectiveness conditions for this operation:(a) the duly executed Contrato de Mandato by the
respective parties; and (b) related legal opinions from the respective parties of the Contrato de Mandato.
10 In the SFP, there were 5 subsecretarios between 2008 and 2012.
8
Bank discussions on a possible loan closing during the process of restructuring in
2011/2012.
22. Despite this lack of progress, the Government remained committed to the overall
objective of the Project that supports a critical public sector reform, namely the
introduction of results-based management and budgeting in the context of a continued
effort to modernize and harmonize public financial management (PFM) rules and
procedures in all levels of government in Mexico. This is evidenced by some activities
being advanced and financed with local resources and which was the basis for the
continued positive assessment of the achievement of the PDO11
.
23. Using its own resources, significant progress was made by the Government in
pursuing the indicated PFM reform agenda particularly in the areas of results-based
budgeting, performance evaluation, accounting harmonization, fiscal transparency and
public procurement management. The most important achievements in these areas are
presented below: 24. Results-Based budgeting and performance evaluation: The PBR-SED
12 reform
led by the SE has successfully advanced the design and introduction of specific
guidelines and instruments to gradually adopt a results and performance orientation in the
Federal Government’s budgeting process. By developing a conceptual model, the new
system articulated two instruments aiming at incorporating the results and performance
dimensions into the resource allocation procedures, i.e., the adoption of performance
indicators for public sector programs and the implementation of systematic evaluation
activities over public sector policies and programs.
25. Accounting harmonization: As part of the overall strategy to modernize public
sector financial management practices in the country, the Government started an
ambitious program towards the harmonization of public accounts and accounting
practices across Federal and sub-national governments. Introducing results-informed
management capabilities require adequate accounting, reporting and consolidation of
information mechanisms as a sine qua non condition for success. Thus, based on
timelines clearly established in legislation passed at the request of the Administration,
efforts were deployed to modernize and harmonize accounting systems.
26. Fiscal transparency: The SE also achieved significant progress in the fiscal
transparency agenda. After a broad consultation and participatory process involving
specialized Non Government Organizations (NGOs) and experts, and in collaboration
with the Access to Information regulatory entity – IFAI, the SE launched a fiscal
transparency Portal13
that provides access to detailed information on the allocation and use
of federal government’s resources. The portal is now fully operational and has also
included a citizens’ friendly application–Presupuesto Ciudadano–that not only facilitates
11 ISR DO rating was Moderately Satisfactory from late 2009 – early 2013. 12
PBR-SED stands for Presupuesto Basado en Resultados y Sistema de Evaluación del Desempeño. 13
For more details visit http://www.transparenciapresupuestaria.gob.mx
9
access to budget information, but also describes the budgetary process in a very
accessible way for citizens.
27. The SFP had also been advancing the public sector management modernization
agenda complementing efforts in areas related to the improvement of public sector
management practices, streamlining internal regulatory frameworks, and modernizing the
Federal Government’s public procurement system and procedures.
28. Progress achieved by both the SE and SFP using own resources was in line with
the PDO and had received Bank’s feedback and guidance. In the case of the PBR-SED
effort, the Bank sustained technical dialogue during Project implementation support
missions for those activities that should be carried out through the Bank loan. On the
other hand, the PFM harmonization work was supported through both Bank
implementation support activities and a parallel advisory services activity.
29. With these advances using local funds, a Government request for a partial
cancellation was received on August 8, 2011. This was followed by a request in late
2011 to reduce the Project scope to reflect the advances and redesign of activities to
better align them with current priorities. In this regard, the processing of the cancellation
by the Bank was delayed pending validation of the final set of activities that would need
to be dropped and those that needed to be incorporated under the restructured Project to
ensure viability after restructuring. Moreover, the November 2012 restructuring was
finalized after a careful re-assessment by Government counterparts and the Bank that
took into account the potential impact of the political transition following the Presidential
elections in July 2012. Specifically, the SFP indicated its preference to cancel its
activities in the Project.
30. Moreover, soon after the Project restructuring, the new Administration took place
in 2013. Among the first impact on the Project was the change in the executing unit from
the Budget Office of the SE to the Performance Evaluation Unit (Unidad de Evaluación
del Desempeño, UED)14
. This facilitated a better alignment of presidential priorities with
sectorial plans and programs’ objectives/ targets. However, the political transition also
resulted into a set-back in Project execution since the activities needed to be revalidated
with the new counterparts. Actual Project activities implemented were minimal with
total disbursements of less than US$400K. Furthermore, priority shifts in some critical
results areas of the Project led to some results indicators not being achieved at all. This
was particularly true for the roll-out of simplified financial management systems to small
municipalities that could not be achieved because of a priority shift towards the
development of the Government Accounting System first.
14 This evaluation unit reported to the Budget Office Director (UPCP). In October 2012, the internal Regulations of the
SHCP were amended through a Decree; these reforms included the creation of the Performance Evaluation Unit with
attributions to coordinate performance evaluations established in article 111 of the Budget and Fiscal Responsibility
Federal Law (LFPRH).
10
31. Another factor affecting implementation was the existence of a similar operation
supported by IADB. The IADB supported Performance Based Budgeting through a loan,
but there was a lack of effective coordination between the two institutions. In this
context, both Banks were almost competing and not aligned in technical aspects.
2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization
32. M&E design. The results framework presented in the PAD provided for
performance indicators for the PDO and intermediate results for each component.
However, these were largely qualitative in nature and with only the desired target value at
end of Project identified. No target values were identified for the time period between
beginning and ending which made monitoring a challenge and perhaps more susceptible
to optimistic assessments as evidenced by the Moderately Satisfactory ratings for PDO
achievement throughout the life of the Project except for the last ISR. Progress towards
achieving the PDO could have been more meaningfully and objectively assessed if target
values were identified for the implementation period and not just at exit. Moreover, with
mid-course target values, mid-course corrections could have been introduced earlier.
33. M&E implementation. During the second and third years of implementation, the
Bank scheduled periodic high level meetings with and between Deputy Ministers to
discuss the progress of the Project, but these meetings did not occur as planned and when
they did, they could not provide guidance to the Project at the political or technical level
needed. The PDO and intermediate indicators were adjusted during Project restructuring
(level one) in 2012 to establish a better link with Project activities. While the target
values were also identified only for Project exit, the indicators have improved to allow
for a more objective if not quantitative assessment during implementation post-
restructuring. The Bank regularly monitored progress under the Project through periodic
implementation support missions and were also included in the implementing agencies
progress reports.
34. M&E utilization. The PDO and intermediate results indicators, particularly with
respect to the target measures or percentages, were closely monitored by the Bank team
and reported in ISRs. The counterparts provided updates to the Bank on the results
indicators usually at the conclusion of every implementation support missions. Post-
restructuring, the Government also used the transparency portal to monitor most of the
results indicators. However, more in situ monitoring effort is done in each ministry
through their planning units instead of the UED at SHCP.
2.4 Safeguard and Fiduciary Compliance
35. No safeguard policies were triggered by the Project at design, an appropriate
decision, as no such issues arose during implementation.
36. The key issues and risks concerning procurement for Project implementation were
identified since Project appraisal; these included the lack of experience of the two
implementing agencies in applying Bank procurement guidelines. The corrective
11
measures were agreed with the executing agencies and were mainly related to keeping
enough trained personnel on Bank guidelines in the implementing agencies’ procurement
units. However, limited procurement capacity continued to be an issue during
implementation before and after restructuring which posed a substantial risk to the
Project’s success.
37. Risk for Project financial management was assessed as low and was considered to
be satisfactory throughout Project implementation. Financial monitoring reports were
submitted on time and were acceptable to the Bank. All minor inconsistencies found
during supervision were properly addressed by the client and did not impact the controls
of the Project. Annual audit reports for the Project were submitted accordingly and
reviewed by the Bank, with auditors issuing their unqualified opinions.
2.5 Post-completion Operation/Next Phase
38. Continuing commitment to the development objective beyond the scope of the
loan has been demonstrated through the decisions of actors including the UED to engage
in related activities with their own funding. There are also positive signals that future
Bank engagement with SHCP would include a focus on strengthening the UED as well as
the M&E capacities of line ministries and sub-national governments. To this end, the
lessons from this Project are expected to inform future engagements and could therefore
help to consolidate and sustain the Close and Modern Government Program (Programa
de Gobierno Cercano y Moderno, PGCM),15
as well as the reform process of SHCP in
the area of performance information, integrated financial management, use of this
information for improving commitments that result from evaluations and for management
and budget decision making.
3. Assessment of Outcomes
3.1 Relevance of Objectives, Design and Implementation
39. To achieve faster growth, reduce extreme poverty and promote shared prosperity,
Mexico needed to improve public service delivery. Mexico’s public service delivery is
still hindered by expenditure inefficiencies at all levels of government: federal, state, and
municipal. In this context, sound and informed budget decision making were critical to
ensure that services were delivered efficiently, as well as in a transparent and accountable
manner.
40. The GoM recognized this challenge in the 2013-18 NDP, which lays out a cross-
cutting program for a “Close and Modern Government”. The PGCM aims at establishing
a results-based, efficient government, as well as developing monitoring and evaluation
15 See section 3.1 for more details on this cross cutting program included in the National Development Plan 2013-2018.
12
mechanisms for improving performance and service delivery. Additionally, the program
seeks to simplify procedures and regulations, allow for greater transparency and
accountability, ensure an optimal use of public resources, and seize the potential of
information and communication technologies. By focusing on enhancing the information
on performance available for government entities and citizens, the Project’s original
design and implementation are fully aligned with the GoM’s current strategy and
continue to be highly relevant for Mexico.
41. As mentioned in the Project Appraisal Document (PAD), the Project was aligned
with the CPS FY08-1316
that called for strengthening institutions to improve their
functioning and to enhance citizen perception of the public sector through a set of
initiatives including results based-budgeting. The Project was also consistent with the
World Bank thematic engagement set forth in the new CPS FY14-19, specifically with
the third theme, “Strengthening Public Finances and Government Efficiency”. 17
The
Bank strategy underscores the need for Mexico to improve public sector performance,
including expenditure quality and equity, and aims at supporting better service delivery.
Through this Project, the Bank has contributed to extending the monitoring and
evaluation techniques of key public policies, strengthening the supervision of indicator
achievements, and generalizing the follow up of intermediate results, establishing the
foundations for a more efficient and transparent public administration.
42. As mentioned earlier, design of the Project was complex but it was key to enable
the changes that needed to happen in order to pursue a results-oriented reform in budget
and public sector management and effectiveness. With respect to implementation, albeit
unsatisfactory in the end, it was relevant as it allowed for a continuing engagement and
dialogue between the Government and the Bank on the critical public sector reform areas
beyond the Project.
3.2 Achievement of Project Development Objectives
43. The overall rating for PDO achievement is Moderately Unsatisfactory.
44. Prior to the November 2012 restructuring, the achievement of outcomes is
assessed in this ICR to be moderately unsatisfactory. While credit is due to the SHCP
and SFP for their achievements using own resources, these did not enable the Project to
sufficiently progress towards achieving its desired outcomes. Nevertheless, as discussed
in Section 2, their achievements in advancing results based budgeting and performance
evaluation, accounting harmonization and fiscal transparency, albeit without any loan
disbursement except for the front-end-fee, were aligned with the PDO.
45. Post-restructuring, the achievement of outcomes with disbursement of
approximately US$400K are assessed to be likewise moderately unsatisfactory for failure
16 Report No. 42846-MX
17 Report No. 83496-MX
13
to achieve several results indicators including the PDO indicator and related intermediate
outcome indicators with respect to the roll-out of a simplified financial management
system to small municipalities and the evaluation of public programs. Nevertheless, the
following achievements after the restructuring are worth noting:
(i) Performance information (PI) is now presented in a timely manner to
Congress in a format that allows interpretation and meets their needs. The
content includes outcome and output measures.
(ii) The majority of the public programs (84.5%) have a robust design across key
dimensions (objectives, indicators, baselines, links to strategies) enabling
better reporting and evaluation.
(iii) The Portal containing the PI on budget performance is available to citizens. In
2013, the UED developed more citizen friendly applications such as Cuenta
Pública Ciudadana 2012 and 2013, as well as their English versions. These
initiatives were mostly financed by component 4 of the loan. An improved
version of the budget transparency portal is to be launched in June 2014,
including new platform, features, etc. See figure below and Annex 2 for more
details on outputs that contributed to achieve PDOs.
46. Overall, the Project supported the introduction of better management practices,
processes and tools in the Mexican public administration, including better and timely
performance information, enhanced reporting and evaluation of public programs, and
transparent and available budget information. The adoption of the Budget Transparency
Portal, which was largely funded by loan funds, resulted into tangible outcomes in terms
of generating information and enabled the country to maintain its Open Budget Index
standing.18
At the same time, the Project financed the training of officials through a
18 In 2012, Mexico has been one of the countries that provide “significant budget information” per the Open Budget
Index.
Outputs. 1. Budget Transparency Portal
2. Established methodology and manuals that set the minimum technical requirements and guidelines for budget transparency and provide orientation for performance indicators
3. Developed Training Programs based on the challenges identified and on demands (i.e. logical framework matrix)
Component 4. Consolidation of the performance evaluation system’s (Sistema de Evaluación del Desempeño – SED) institutional architecture and strengthening the system for evaluating policy and program effectiveness (Presupuesto Basado en Resultados – PBR)
Project Development Objective 2. An active network and a portal to inform society at large on a regular basis about budget performance, increasing transparency and accountability to citizens
14
series of activities including online courses, workshops and the development of a series
of manuals and methodologies to collect, monitor and evaluate budget information. This
now appear to have good results as evidenced by the work being continued and
specifically evidenced with SHCP’s presentation of the “Guidelines to register, revise,
update, schedule and monitor the Budget Programs Results Indicators Matrix (MIR)” in
the first semester of 2014.
3.3 Efficiency
47. Project efficiency is low. The reduction in scope and the limited results achieved
despite the restructuring and extension suggest that overall efficiency is much lower than
expectations at design and at restructuring. The long time elapsed between preparation
and the Project closing with minimal physical accomplishments and limited results vis-à-
vis the overall desired outcomes suggest there were opportunities missed which were
partly alluded to in the Borrower’s comments on the relevance of Project activities
(particularly those of SFP) having been reduced given the delays. In monetary terms,
from the beginning, a cost-benefit analysis was not considered to assess the impact of
these institutional reforms, as problems in the quantification of intangibles and issues of
attribution make it difficult to express their impacts. Moreover, given loan amount
disbursed (US$373,684) vis-à-vis the time-overrun in implementation and the resources
mobilized in the Bank for preparation and provision of implementation support
(US$967,977) which are more than double the loan disbursement, it could be considered
that the Project failed to be efficient. Nevertheless, the operation managed to achieve
significant results in terms of increased transparency, good governance and
accountability, as measured by greater availability and access to budget data and
performance information (see Annex for more details). Further potential efficiency gains
and cost savings are expected from these types of reforms when fully implemented.
3.4 Justification of Overall Outcome Rating
Rating: Moderately Unsatisfactory
48. As discussed above, while the relevance of the objective remains high with the
public financial management and results-based agenda at the federal and subnational
levels remaining a priority, the achievement of the PDO could only be rated moderately
unsatisfactory given the inefficient Project implementation and the non-achievement of
significant outcomes.
3.5 Overarching Themes, Other Outcomes and Impacts
(a) Poverty Impacts, Gender Aspects, and Social Development
49. No direct poverty, gender or measurable impact on the population is attributable
to the Project. However, the Project’s impact on public sector management areas has
potential indirect impact on reducing poverty through the effect of better resource
15
allocation and improved service delivery conditions, as well as by channeling generated
savings more efficiently to national priorities.
(b) Institutional Change/Strengthening
50. The M&E capacity of the UED was significantly strengthened in the latter part of
the Project. From Project start to November 2012, the Project was executed by the
Budget Office of the SE. Beginning December 2012 (when the current administration
took office) the UED19
took over Project execution. This facilitated a better alignment of
presidential priorities with sectorial plans and programs’ objectives and targets. Technical
assistance during implementation support missions by the Bank contributed to this, as
well as feedback to the reform decisions provided by TTLs and experts members of the
World Bank team.
(c) Other Unintended Outcomes and Impacts (positive or negative)
51. No significant unintended outcomes or impacts were identified.
3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops
52. No beneficiary survey or stakeholder workshops were conducted specifically for
reviewing Project performance.
4. Assessment of Risk to Development Outcome
Rating: Moderate
53. The general direction of the reforms supported by the Project is aligned with those
of the Government’s PGCM. As such, risks to the outcomes that have been achieved to
date are considered to be moderate. While in the medium to long term, further advances
in effectiveness building off Project activities will likely require additional investments in
technology and process redesign, all of these are considered in the PGCM.
5. Assessment of Bank and Borrower Performance
5.1 Bank Performance
(a) Bank Performance in Ensuring Quality at Entry
Rating: Moderately Unsatisfactory
19 This evaluation unit reported to the Budget Office Director (or UPCP). In October 2012 through a Decree the
internal Regulations of the SHCP were amended; these reforms included the creation of the Performance Evaluation
Unit (UED) with attributions to coordinate performance evaluations established in article 111 of the Budget and Fiscal Responsibility Federal Law (LFPRH).
16
54. The Project was intended to achieve challenging reforms in public management
and results-based budgeting, building from efforts supported by the Bank during the
beginning of the 2006-2012 administration and Project preparation. The Project was
prepared taking into account lessons learned from international experiences and taking
advantage of the synergies between SFP and SHCP who were then working together
towards a results oriented agenda. The Project was consistent with the federal
government’s objectives and the Bank strategy in Mexico. However, several
shortcomings in Project design posed significant challenges to implementation. In
particular, the failure to identify the challenges involved in coordinating amongst and
with several federal government entities, and the overestimation of the counterpart’s
capacity to carry out complex procurement processes (both in SFP and SHCP) caused
significant risks to the successful completion of the Project. As noted by the Borrower in
their comments, Project implementation could have benefited from having a focal point
for coordination as well from providing a venue to collaborate among all the stakeholders
during Project preparation. The delay in declaring the loan effective (16 months from
Board approval) suggests a significant under-estimation of the Project’s readiness to be
implemented.
(b) Quality of Supervision
Rating: Moderately Unsatisfactory
55. The initial implementation support phase of the Project could be characterized as
overly optimistic and highly focused on technical aspects, with inadequate attention paid
to operational constraints. On the positive side, in a context where the Government was
moving fast with their reform agenda and the demands were changing, the Bank was able
to sustain technical dialogue specifically on the PBR-SED and PFM harmonization
efforts which were financed by local funds. On the negative side, the Bank failed to take
advantage of the synergies in place between SFP and SHCP in the early stages of
implementation. On top of that, the SFP faced high-level public officials’ turnover and
the World Bank team failed to recognize these implementation risk flags or adjust to
these changes in the context accurately. The Bank’s implementation support team also
suffered from lack of leadership at the beginning of implementation when the TTLs were
changed20
. Hence, realistic assessments of Project implementation constraints early on
could have facilitated a Project turnaround by addressing the changing dynamics in the
reform. There were also indications that communications between the Bank team,
fiduciary teams, financial agent and implementing agencies could have been better to
improve Project implementation support and administrative processes.
56. By 2011, it became clear that the Project scope had to be reduced and Project
activities redesigned to better align them with the incoming Government’s priorities as
20 The Project had a total of three TTLs throughout the five years of implementation,
17
was detailed in the Government requests. However, the processing of the partial
cancellation by the Bank was postponed to allow for a thorough assessment of viability
and commitment from the newly elected administration (at the end of 2012). During this
time, the Bank flagged potential issues and took action to solve them effectively
throughout the last year of implementation. The new government had just taken office
and continued to align its priorities; and as noted above, even though the Bank team
engaged in intensive implementation support, procurement processes lingered for
extensive periods given procurement capacity constraints within the implementing
agency and as such only a few contracts were executed with less than 10% of the total
restructured loan funds disbursed. Nevertheless, post-restructuring, a closer collaboration
between the Bank team and the counterparts were established that not only help move the
Project forward as well as contributed to the institutional strengthening of the UED.
(c) Justification of Rating for Overall Bank Performance
Rating: Moderately Unsatisfactory
57. Based on the Bank performance in ensuring quality at entry, and the quality of
implementation support, the overall Bank performance is rated as Moderately
Unsatisfactory. A number of challenges that led to delays in Project start-up and
execution were not fully identified at design, and communication between the Bank and
the client could have been better during the initial part of implementation. However, this
ICR recognizes the Bank implementation support team’s significant efforts during the
latter part of implementation to better address the procurement issues and to try to
achieve the new Government’s goals.
5.2 Borrower Performance
(a) Government Performance
Rating: Moderately Unsatisfactory
58. Despite the fact that Project implementation suffered delays, the areas supported
under this Project were part of the Government of Mexico’s priority agenda with respect
to improving results based management and budgeting as evidenced by the reform
advances that took place using their own resources. However, the political commitment
to the Project was weakened by the weak (if not lack of) coordination between SFP and
SHCP and compounded by the turnover of government officials (5 subsecretarios held
office in the SFP as the main counterparts for Components 1 and 2). Moreover, the
Project was not fully internalized or appropriated in particular by the SHCP’s operational
teams. SHCP areas (Budget Direction, Evaluation Direction, and International Affairs)
were not fully aligned conceptually regarding Performance Based Budgeting and its
priorities and targets. SFP and SHCP’s high-level commitment could have translated into
proactive measures by ensuring that the Project operational units were progressing with
Project implementation satisfactorily.
18
(b) Implementing Agency or Agencies Performance
Rating: Moderately Unsatisfactory
59. The Project Implementation Units both at the SFP and SHCP were committed to
the Project but had a low capacity in fiduciary aspects, especially procurement as
identified in the risks at appraisal. During the last year of implementation, SHCP’s
implementing unit (within the UED) was very organized and engaged but lacked
familiarity with the Bank’s procurement guidelines that did not allow them to disburse
most of the resources. Nevertheless, despite their capacity constraint, they were able to
focus on limited activities that had significant contribution to the desired Project
outcomes. With their limited implementation capacity, they were able to advance on the
Budget Transparency Portal that enabled the Project to deliver on its objective of
disseminating budget performance information to the Borrower’s citizens on a regular
basis.
(c) Justification of Rating for Overall Borrower Performance
Rating: Moderately Unsatisfactory
60. Considering the above arguments, the overall Borrower performance is deemed
moderately unsatisfactory.
6. Lessons Learned
61. The instrument was not the best alternative for what was needed for these reforms.
The mitigation measures in place did not lower the risks identified at appraisal. This
Project benefitted the most from the technical assistance and feedback received both
during preparation and the last years of implementation. In retrospect, it would have
been better to have supported the Government’s agenda with a Non-Lending Technical
Assistance (NLTA) program or a Reimbursable Advisory Services (RAS) to support
more effectively the type of reforms the Government was pursuing. The chosen
instrument allowed the Bank to promote the technical dialogue with the authorities and
amongst stakeholders, and also ensured agreements and commitments at the highest
levels. However, these were not fully internalized or appropriated in particular by the
SHCP’s operational teams as discussed above.
62. Assessment of Risks - Coordination mechanisms were not enough. Although there
were mitigation measures in place for this risk, the fact that there were two implementing
agencies and a financial agent was more complex than initially assessed. Moreover,
within each of the implementing agencies, coordination was not enforced thus affecting
project implementation and disbursement performance. The designation of a focal point
for coordination could have helped as noted by the Borrower.
63. Demand not well read in the case of SHCP. While Components 1 and 2 were very
much in line with the Government’s (SFP) agenda, both conceptual and technical; the
19
Components related to results-based budgeting (SE of SHCP) which included the Budget
Office (UPCP) in the first stages and the UED in the last years were not aligned. This is
largely reflected in the lack of disbursements throughout the Project.
64. Additional implementation support should be considered for projects that involve
more than one implementing unit that are not familiar with large and complex
procurement processes, such as some investments within this Project. For this Project, the
need for additional support should have been anticipated at the beginning of Project
implementation. While capacities at the Ministries were strengthened, this was not
enough. Moreover, improved harmonization of procurement procedures between the
Bank and GoM is a necessity as noted by the Borrower’s comments.
65. Ensure alignment between Government processing and Bank required action. As
reflected in the Borrower’s comments below, timely action from the Bank with respect to
issuing Bank feedback especially “no objection” is also a critical element for timely
implementation.
66. Meaningful and objective results indicators are critical for monitoring complex
reform initiatives. While reform initiatives do not always allow for quantifiable
measures of success, this Project could have benefited from a results framework that
provided for mid-course target values that could have informed counterparts and the
Bank that mid-course corrections were warranted earlier.
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners
(a) Borrower/implementing agencies
67. The Borrower provided very informative and pertinent comments and these have
been taken into consideration in the assessment of overall performance of the Project, the
Borrower and the Bank as well as in the lessons learned section. These comments are as
follows:
a) The initial objective of the GoM’s “Results based Management and
Budgeting” Project aimed at having the departments and federal organizations
of the country provide decision makers and citizens in general with rigorous,
timely and easy to access information regarding the efficiency and
effectiveness of public expenditure programs.
b) The GoM sought Bank support for the financing of the Project through an
IBRD loan, with the objective of reaching the goals proposed under the five
components that integrated the Project. Given the legal attributions conferred
by the Federal Public Administration Organic Law, the Government mandated
the two main ministries involved in the PBR-SED initiative (SHCP and SFP)
with the implementation of the Project.
20
c) Having two implementing agencies was an obstacle to the successful
execution of the Project, basically due to the complexity of coordinating the
work of the two ministries and the lack of clarity in the Project objectives, as
well as its scope. This was accentuated by the absence of a coordination focal
point and the limited cooperation amongst both ministries, the Financial
Agent and the Bank. Also, the pace of the execution of the Project did not
satisfy Government expectations in terms of results.
d) In addition, the delay between the signing of the Legal Agreement (April 21,
2009) and effectiveness (March 19, 2010) had also a negative influence in the
implementation of the Project. During the first stages of Project execution, it
was not possible to hire any consultancy and advisory services due to delays
in the execution of Bank administrative processes—such as “no objections”—
through the Financial Agent. As a result, the first consultancy services were
only provided in 2011.
e) Under these circumstances, one of the executing agencies, SFP, decided not to
continue with the implementation of the Project, cancelling the total amount
of resources allocated to its components. As the entity responsible for the
PMG, SFP was counting on the Project to help advance that agenda, including
the design of documents, tools and methodologies. The initial delays reduced
the relevance of the components included in the Project from the perspective
of SFP.
f) Consequently, the Project was restructured in order to have only one
executing agency, the SHCP. The SHCP used the loan resources to: hire, inter
alia, the consultancy services to analyze and evaluate the strategic indicators
of the budget programs; conduct training sessions with regards to PBR-SED;
and implement the mechanisms to report the federal resources transferred to
state entities and municipalities. These activities had a positive impact in the
PBR-SED implementation.
g) Under the restructured Project, the Financial Agent acted in a timely manner,
which was key for the review of the documents needed to register processes
and for obtaining “no objections” from the Bank with respect to the hiring of
consultancy services, as well as disbursements. This also helped produce
Project-required financial and progress reports on time.
h) In the view of SHCP, Bank procurement and hiring processes, especially
those requiring “no objections”, could be improved. The long time elapsed
between Bank approval/rejection caused delays in the processing of contracts,
which greatly affected the proper implementation of Project activities and as a
result had a negative impact on its overall implementation.
i) In terms of areas of opportunity, greater harmonization between GoM and
Bank procurement procedures could be sought, even though there are already
21
documents streamlining Federal Government and World Bank processes. It
would be also advisable to establish work programs on time and in accordance
to reality, including clear hiring procedures that expedite processes so the
products delivered can be used to influence the final results. Finally, it would
be convenient to improve project preparation by working jointly and with
better coordination and communication among involved stakeholders.
68. The Borrower also provided additional editorial comments in other sections of the
ICR. These have been addressed in finalizing the document.
(b) Cofinanciers
Not applicable
(c) Other partners and stakeholders
69. IADB supported Performance Based Budgeting through a loan, but did not work
in coordination with the World Bank. Based on the interviews of stakeholders of the
reforms, the Banks were seen as almost competing and not aligned technically.
22
Annex 1. Project Costs and Financing
(a) Project Cost by Component (in US$ Million equivalent)
Components Appraisal Estimate
(US$ millions)
Actual/Latest
Estimate
(US$ millions)
Percentage of
Appraisal
Component 1 7.6 0 0.00
Component 2 4 0 0.00
Component 3 4 0 0.00
Component 4 10.050
0.875*
8.70
Component 5 6.275 0 0.00
Total Baseline Cost 31.495 0.875 2.80
Physical Contingencies
0.00
0.00
0.00
Price Contingencies
0.00
0.00
0.00
Total Project Costs 0.00 0.00
Front-end fee PPF 0.00 0.00 0.00
Front-end fee IBRD 0.43 0.43 0.00
Total Financing Required 31.925 0.918** 2.90
Source: Informe de avance segundo semestre de 2013, UED - SHCP
*Sum of Loan Disbursement of US$330,576.52 and Counterpart Fund Contributions of US$543,391.
**May not equal due to rounding off.
(b) Financing
Source of Funds Type of
Cofinancing
Appraisal
Estimate (US$ millions)
Actual/Latest
Estimate (US$ millions)
Percentage of
Appraisal
Borrower 14.725 0.543 3.70
International Bank for Reconstruction
and Development 17.200 0.331 1.90
23
Annex 2. Outputs by Component
As discussed in the main section of the ICR, the executed Project activities relate to
Component 4. Below presents the outputs under said Component.
Component 4 - Results-Based Management and Evaluation System Consolidation
1. The key outputs delivered by Component 4 of the Project are described below:
a) Budget Transparency Portal (BTP): Since 2011, SHCP has had in place a Budget
Transparency Portal (www.transparenciapresupuestaria.gob.mx) on which
performance information of the budget programs can be found, as well as public
financial information. The main objectives and contents of this portal are describe in
the table below:
Table 2.1. Objectives and contents of the BTP
Objectives Content
More transparency in Public
Resources Management Public Finance Statistics
Transferred resources to the local
governments
Budget Information
Quarterly Reports in Open Data formats
Cuenta de la Hacienda Pública Federal
Budget transparency towards citizens
(friendly language)
Transparency by Thematic areas,
focused on citizens interests
Citizen Budget
Cuenta Pública Ciudadana or Public
Accounts for Citizens
Frequently Asked Questions
Glossary
Investment Projects
Performance Information (indicators and
goals)
External/Independent Evaluations
Aid and support for Natural Disasters
Reconstruction
Source: Final Report and Results Framework Matrix, UED, SHCP. April 21, 2014.
The main strength of the portal compared to other countries is the fact that all the
performance information is public, including external evaluations (more than a
thousand) and MIRs (results indicators matrix) with indicators (757). There is also
access to public investment information including those funded under special funds
such as FONDEN (or Natural Disaster Fund). The UED has also reached out to
NGOs and civil society to ensure that the information is useful for their purposes and
24
understandable for everyone. For instance, the information included in the citizen
budget for 2014 explains in a friendly manner the following topics:
Growth
Total Budget
Sources of revenue and debt
Deficit
Functional Classification of Expenditures (why the Government spends?)
Administrative Classification of Expenditures (who spends?)
Economic Classification of Expenditures (on what the Government spends?)
Investment Projects
Measures taken to reduce expenditures
SED information such as percentage of expenditures with performance indicators
Links to more detailed information
b) Methodology and Manuals were developed, including:
- “Methodology to develop and implement budget transparency portals at the
federal and local levels (technical and functional)”
- “Guide to establish and monitor goals for federal entities and agencies of the
Government”
- “Training Manual to monitor Budget Program’s objectives based on strategic
indicators”
- “Improved guide to design strategic and management indicators”
c) Various Training Programs have been and will continue to be conducted:
- Online Training
- Training for Trainers
- Training based on identified challenges on MIRs (theory, practical, continued
technical assistance, ad hoc workshops)
- Training to improve the Single Format System or Sistema de Formato Único
(SFU), i.e. information collection and registration as well as quality of
information.
2. A full account of the outputs completed by the Project under component 4 is
presented in the table below. These outputs were mostly financed by counterpart funds
and contributed towards achieving the intermediate result indicator “Consolidation of the
performance evaluation system’s (SED) institutional architecture and strengthening the
system for evaluating policy and program effectiveness” by supporting the targets
specified below as well.
Table 2.2. Completed Project outputs by source of financing
Output Original
Budget
Executed
Budget Target supported
Outputs financed with loan resources 346,000 325,884
Consultancy to prepare and facilitate the 31,000 24,259 Evaluation unit operational in SFP,
25
Project’s selection and hiring processes (1) including an institutional
performance evaluation system
Methodological guide for the technical and
functional implementation of the transparency
web portal at the federal and subnational
levels
40,000 40,000
Evaluation unit operational in SFP,
including an institutional
performance evaluation system
Development of minimum criteria and
transparency guidelines for the federal and
subnational governments
32,000 32,000
Evaluation unit operational in SFP,
including an institutional
performance evaluation system
Collection of feedback on PBR program and
the SED 52,000 52,000
The SED unit manages the
evaluation of non-social programs
successfully
Training of trainers course 33,000 33,000
Set of strategic indicators has
improved after support and training
provided to Government officials in
charge of programs
Consultancy for the analysis of budget
strategic indicators for the 2013 budget cycle 18,000 18,000
Evaluation unit operational in SFP,
including an institutional
performance evaluation system
Consultancy for the maintenance of the
Budget transparency portal 18,000 18,000
Evaluation unit operational in SFP,
including an institutional
performance evaluation system
Consultancy for the implementation of the
SFU 18,000 18,000
Set of strategic indicators has
improved after support and training
provided to Government officials in
charge of programs
Consultancy for the conceptualization and
analysis of the information produced by the
SFU
25,000 25,000
Set of strategic indicators has
improved after support and training
provided to Government officials in
charge of programs
Consultancy to prepare and facilitate the
Project’s selection and hiring processes (2) 52,000 37,500
Evaluation unit operational in SFP,
including an institutional
performance evaluation system
Consultancy for the establishment of a
monitoring and evaluation system for the
Project’s selection and hiring processes
27,000 28,125
Evaluation unit operational in SFP,
including an institutional
performance evaluation system
Outputs financed with local resources 574,093 574,093
TOR for the carrying out of the activities to be
conducted under components iii, iv and v of
the Project
102,241 102,241 -
External audit for loan 7622-MX 2,852 2,852 -
Results-based budgeting online course
(auditing and results-oriented indicators
modules).
469,000 469,000
Set of strategic indicators has
improved after support and training
provided to Government officials in
charge of programs
26
Annex 3. Economic and Financial Analysis
1. The overarching goals of the reforms supported by the Project aimed at increasing
transparency and strengthening good governance and accountability in the Sistema de
Evaluación al Desempeño (SED), which are difficult to measure. Therefore, the
economic and financial analysis for this operation needs to go beyond quantitative
estimations and rely on qualitative data. The assumption is that the support to the GoM’s
institution building efforts provided by the Project, notably in terms of results-based
management and budgeting, has contributed to a more transparent and accountable
governance framework. However, the outputs of the reforms carried out by the GoM,
including the Programa de Mejora de la Gestión (PMG) and Presupuesto Basado en
Resultados (PBR), as well as the SED and the sectorial strategies and specific programs,
are not fully attributable to the Project or a single reform initiative, and their impact may
not be apparent in the short-term.
2. Overall, the Project supported the introduction of better management practices,
processes and tools in the Mexican public administration, including better and timely
performance information, enhanced reporting and evaluation of public programs, and
transparent and available budget information. The most important instrument in this
regard is the Budget Transparency Portal, which was mostly financed with the loan
resources. The adoption of this portal resulted into tangible outcomes in terms of
generating information, since according to the Open Budget Index (OBI), Mexico has
been one of the countries that provides “significant budget information” in their portal
since 2012. Today most budget information is presented in Open Data format, which
allows the private sector, NGOs and civil society in general to access what is relevant for
them. In fact, online visits increased to 28.5% in 2013 compared to 2012, and as of the
first quarter of 2014, there was an increase of almost 50% compared to the same period
of 2013 and more than doubled compared to the first quarter of 2012.
3. At the same time, the Project financed the training of officials through a series of
activities, including online courses, workshops and the development of a series of
manuals and methodologies. These initiatives were aimed at increasing the capacity of
public officials to collect, monitor and evaluate budget information, and now appear to
have achieved good results. At the end of 2013, out of the 981 budget programs included
in the programmable budget (the total is 1,005), 854 programs have performance
information, which is equivalent to 87% of the programmable budget. The work has
continued in the first semester of 2014, when the SHCP presented the “Guidelines to
register, revise, update, schedule and monitor the Budget Programs Results Indicators
Matrix (MIR)”.
4. The upward trend in the use of information by the public, along with the training
received by officials, also suggests a positive impact of the Project in terms of creating an
institutional context more conducive to efficiency. Although it cannot be quantified, it
seems likely that the combined effect of greater accountability and increased capacity
27
will produce financial savings eventually, ultimately boosting the quality of public
expenditures in Mexico.
28
Annex 4. Bank Lending and Implementation Support/Supervision Processes
(a) Task Team members
Names Title Unit Responsibility/
Specialists
Lending
Pedro Arizti Senior Public Sector Specialist LCSPS TTL
Rosa Maria Hernandez-
Fernandez Senior Executive Assistant LCC1C Assistant
Mariano Lafuente Public Sector Mgmt. Spec. LCSPS Management and HR
Improvement
Karla Soledad Lopez Flores Operations Assistant CTGBD Assistant
Felix Prieto Arbelaez Senior Procurement Specialist LCSPT
Jeffrey James Rinne Consultant PRMPS HR Management
Fernando Rojas Consultant LCSPS Public Sector
Maria Guadalupe Toscano
Nicolas Public Sector Mgmt. Spec. LCSPS
Manuel Antonio Vargas
Madrigal Lead Financial Management Spec MNAFM
Supervision/ICR
Juan Carlos Alvarez Senior Counsel LEGES
Pedro Arizti Senior Public Sector Specialist LCSPS TTL
Dmitri Gourfinkel Financial Management Specialist LCSFM Financial
Management
Alberto Leyton Senior Public Sector Specialist ECSP4 TTL
Xiomara A. Morel Senior Financial Management
Specialist LCSFM
Victor Manuel Ordonez Conde Senior Finance Officer CTRLN
Jeffrey James Rinne Consultant PRMPS HR Management
Tomas Socias Senior Procurement Specialist LCSPT
Maria Guadalupe Toscano
Nicolas Public Sector Mgmt. Spec. LCSPS
Manuel Antonio Vargas
Madrigal Lead Financial Management Spec MNAFM
May Olalia Senior Operations Officer LSCPS
Azul del Villar Baston Consultant LCSPS ICR
Eguiar Lizundia Gonzalez Consultant LCSPS ICR
(b) Staff Time and Cost
Stage of Project Cycle
Staff Time and Cost (Bank Budget Only)
No. of staff weeks US$ Thousands (including
travel and consultant costs)
Lending
FY07 2.81 18.963
FY08 52.03 301.141
FY09 27.55 131.268
Total: 82.39 451.373
29
Supervision/ICR
FY09 11.19 41.890
FY10 25.14 89.238
FY11 19.33 82.145
FY12 21.75 108.016
FY13 25.39 99.577
FY14 17.20 95.645
Total: 120.00 516.604
34
Annex 9. List of Supporting Documents
Project Appraisal Document on a Results-based Management and Budgeting Loan
(Report No: 46271-MX), 2008
Mexico Country Partnership Strategy FY14-19
Mexico Country Partnership Strategy 2008-2012
Proposed Project Restructuring of Results-based Management and Budgeting Loan
(Report Number 68464-MX), 2012.
Proyecto de Apoyo a la Gestión y Presupuesto para Resultados Préstamo 7622-
MXBanco Internacional de Reconstrucción y Fomento. Informe de Progreso en la
Ejecucion del Proyecto, Segundo Semestre 2013. SHCP, abril 21, 2014.