world bank document · ppp public private partnership ppra public procurement regulatory authority...
TRANSCRIPT
Document of
The World Bank
Report No: ICR00004220
IMPLEMENTATION COMPLETION AND RESULTS REPORT
(IDA-52150 AND IDA-53970)
ON A
SERIES OF TWO CREDITS
IN THE TOTAL AMOUNT OF SDR 130.1 MILLION
(US$200 MILLION EQUIVALENT)
TO THE
UNITED REPUBLIC OF TANZANIA
FOR THE
FIRST AND SECOND POWER AND GAS SECTOR DPO
December 21, 2017
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
ii
CURRENCY EQUIVALENTS
(Exchange Rate Effective as of December 21, 2017)
Currency Unit = Tanzania Shilling (T Sh)
T Sh 2,240.00 = US$1.00
US$1.00 = SDR 0.706255
GOVERNMENT FISCAL YEAR
July 1 – June 30
TANESCO FINANCIAL YEAR
Since July 1, 2015: July 1 – June 30
Transition year: January 1, 2014 – June 30, 2015
Until December 31, 2013: January 1 – December 31
ABBREVIATIONS AND ACRONYMS
AfDB African Development Bank
CAS Country Assistance Strategy
DP Development Partner
DPO Development Policy Operation
EPP Emergency Power Producer
ESCBP Energy Sector Capacity Building Project
EWURA Energy and Water Utilities Regulatory Authority
FYDP Five Year Development Plan
GDP Gross Domestic Product
GHG Greenhouse Gas
IMF International Monetary Fund
IPP Independent Power Producer
IPTL Independent Power Tanzania Ltd.
ISR Implementation Status and Results Report
KPI Key Performance Indicator
LNG Liquefied Natural Gas
MEM Ministry of Energy and Minerals
MOF Ministry of Finance and Planning
M&E Monitoring and Evaluation
NAO National Audit Office
NDC Nationally Determined Contribution
NGUMP National Gas Utilization Master Plan
NNGIP National Natural Gas Infrastructure Project
PDO Program Development Objective
PPP Public Private Partnership
PPRA Public Procurement Regulatory Authority
PSMP Power System Master Plan
REA Rural Energy Agency
SCF Standby Credit Facility
TANESCO Tanzania Electric Supply Company
TPDC Tanzania Petroleum Development Corporation
USAID U.S. Agency for International Development
iii
Senior Global Practice Director: Carlos Felipe Jaramillo
Country Director: Bella Bird
Practice Director: Paloma Anos Casero
Task Team Leaders: Jacques Morisset, Yutaka Yoshino
ICR Task Team Leader: Joern Huenteler
ICR Primary Author: Nestor Ntungwanayo
iv
CONTENTS
Data Sheet
A. Basic Information ................................................................................................................... v
B. Key Dates ............................................................................................................................... v
C. Ratings Summary .................................................................................................................. vi
D. Sector and Theme Codes ...................................................................................................... vii
E. Bank Staff ............................................................................................................................ viii
F. Results Framework Analysis .................................................................................................. x
G. Ratings of Program Performance in ISRs ........................................................................... xiii
H. Restructuring (if any) .......................................................................................................... xiii
1. Program Context, Development Objectives, and Design ........................................................... 1
2. Key Factors Affecting Implementation and Outcomes .............................................................. 8
3. Assessment of Outcomes .......................................................................................................... 18
4. Assessment of Risk to Development Outcome ......................................................................... 34
5. Assessment of Bank and Borrower Performance ..................................................................... 36
6. Lessons Learned........................................................................................................................ 39
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners........................... 40
Annex 1. Bank Lending and Implementation Support/Supervision Processes ............................. 41
Annex 2. Beneficiary Survey Results ........................................................................................... 43
Annex 3. Stakeholder Workshop Report and Results ................................................................... 44
Annex 4. Summary of Borrower's ICR and/or Comments on Draft ICR ..................................... 45
Annex 5. Comments of Cofinanciers and Other Partners/Stakeholders ....................................... 46
Annex 6. Supporting Data............................................................................................................. 47
Annex 7. List of Supporting Documents ...................................................................................... 49
Annex 8. Map................................................................................................................................ 50
v
A. Basic Information
Program 1
Country Tanzania Program Name TZ First Power and Gas
Sector DPO
Program ID P143645 L/C/TF Number(s) IDA-52150
ICR Date December 21, 2017 ICR Type Core ICR
Lending Instrument Development Policy
Lending Borrower
Ministry of Finance and
Planning
Original Total
Commitment SDR 64.90 million Disbursed Amount SDR 64.90 million
Implementing Agency: Ministry of Finance and Planning
Cofinanciers and Other External Partners: n.a.
Program 2
Country Tanzania Program Name TZ Second Power and
Gas Sector DPO
Program ID P145254 L/C/TF Number(s) IDA-53970
ICR Date December 21, 2017 ICR Type Core ICR
Lending Instrument DPL Borrower Ministry of Finance and
Planning
Original Total
Commitment SDR 65.20 million Disbursed Amount SDR 65.20 million
Implementing Agency: Ministry of Finance and Planning
Cofinanciers and Other External Partners: n.a.
B. Key Dates
TZ First Power and Gas Sector DPO - P143645
Process Date Process Original Date Revised/Actual
Date(s)
Concept Review: 01/17/2013 Effectiveness: - 06/12/2013
Appraisal: 02/06/2013 Restructuring(s): - -
Approval: 03/26/2013 Mid-term Review: 11/07/2013 11/07/2013
Closing: 06/30/2014 06/30/2014
vi
TZ Second Power and Gas Sector DPO - P145254
Process Date Process Original Date Revised/Actual
Date(s)
Concept Review: 11/07/2013 Effectiveness: - 06/09/2014
Appraisal: 02/03/2014 Restructuring(s): n.a. n.a.
Approval: 03/21/2014 Mid-term Review: 11/07/2013 11/07/2013
Closing: 06/30/2015 06/30/2015
C. Ratings Summary
C.1 Performance Rating by ICR
Overall Program Rating
Outcome Moderately Unsatisfactory
Risk to Development Outcome High
Bank Performance Moderately Satisfactory
Borrower Performance Moderately Unsatisfactory
C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)
Overall Program Rating
Bank Ratings Borrower Ratings
Quality at Entry Moderately Satisfactory Government: n.a.
Quality of
Supervision: Moderately Satisfactory
Implementing
Agency/Agencies: n.a.
Overall Bank
Performance Moderately Satisfactory
Overall Borrower
Performance Moderately Unsatisfactory
C.3 Quality at Entry and Implementation Performance Indicators
TZ First Power and Gas Sector DPO - P143645
Implementation
Performance Indicators
QAG Assessments
(if any) Rating:
Potential Problem Program
at any time (Yes/No): No Quality at Entry (QEA) None
Problem Program at any
time (Yes/No): No
Quality of Supervision
(QSA) None
DO rating before
Closing/Inactive status
Moderately
Satisfactory
vii
TZ Second Power and Gas Sector DPO - P145254
Implementation
Performance Indicators
QAG Assessments
(if any) Rating:
Potential Problem Program
at any time (Yes/No): No Quality at Entry (QEA) None
Problem Program at any
time (Yes/No): No
Quality of Supervision
(QSA) None
DO rating before
Closing/Inactive status
Moderately
Satisfactory
D. Sector and Theme Codes
TZ First Power and Gas Sector DPO - P143645
Original Actual
Major Sector
Energy and Extractives
Other Energy and Extractives 57 57
Oil and Gas 43 43
Major Theme/Theme/Sub Theme
Private Sector Development
Business Enabling Environment 28 28
Investment and Business Climate 28 28
Jobs 14 14
Job Creation 14 14
Public Sector Management
Public Administration 15 15
Transparency, Accountability and Good Governance 15 15
Public Finance Management 15 15
Public Expenditure Management 15 15
Urban and Rural Development
Rural Development 14 14
Rural Infrastructure and Service Delivery 14 14
Urban Development 14 14
Urban Infrastructure and Service Delivery 14 14
viii
TZ Second Power and Gas Sector DPO - P145254
Original Actual
Major Sector
Energy and Extractives
Other Energy and Extractives 44 44
Energy Transmission and Distribution 11 11
Oil and Gas 45 45
Major Theme/Theme/Sub Theme
Private Sector Development
Jobs 14 14
Job Creation 14 14
Public Private Partnerships 10 10
Public Sector Management
Public Administration 15 15
Transparency, Accountability and Good Governance 15 15
Public Finance Management 15 15
Public Expenditure Management 15 15
Urban and Rural Development
Rural Development 14 14
Rural Infrastructure and service delivery 14 14
Urban Development 14 14
Urban Infrastructure and Service Delivery 14 14
E. Bank Staff
TZ First Power and Gas Sector DPO - P143645
Positions At ICR At Approval
Vice President: Makhtar Diop Makhtar Diop
Country Director: Bella Bird Philippe Dongier
Practice Manager/Manager: Abebe Adugna Dadi Albert Zeufack
Task Team Leader: Jacques Morisset Jacques Morisset
ICR Team Leader: Joern Huenteler
ICR Primary Author: Nestor Ntungwanayo
TZ Second Power and Gas Sector DPO - P145254
Positions At ICR At Approval
Vice President: Makhtar Diop Makhtar Diop
Country Director: Bella Bird Philippe Dongier
ix
TZ Second Power and Gas Sector DPO - P145254
Positions At ICR At Approval
Practice Manager/Manager: Abebe Adugna Dadi Albert Zeufack
Task Team Leader: Yutaka Yoshino Yutaka Yoshino
ICR Team Leader: Joern Huenteler
ICR Primary Author: Nestor Ntungwanayo
x
F. Results Framework Analysis
Program Development Objective (from Program Document Loan and Program Summaries)
The PDO of the program was to (a) strengthen the country’s ability to bridge the financial gap in its
power sector, (b) reduce the cost of power supply and promote private sector participation in the power
sector, and (c) strengthen the policy and institutional framework for the management of the country’s
natural gas resources.
Revised Program Development Objectives
The PDO was not revised during the period of implementation of the two operations (DPO-1 and DPO-2).
PDO Indicator(s)
TZ First and Second Power and Gas Sector DPOs (P143645 and P145254).
Indicator Baseline Value
Original Target
Values (from
approval
documents)1
Actual Value
Achieved when the
DPO program
elapsed
Actual Value
Achieved at the
time of the ICR
Pillar 1 Strengthening the country’s ability to bridge the financial gap in its power
sector
Indicator 1: TANESCO operating deficit (US$ million)
Value (quantitative
or qualitative)
240 50 92a (80)
b
(profit)
Date achieved Year to
December 31,
2013
2016 Year to June 30,
2016
Year to June 30,
2017
Comments (including
% achievement)
Overachieved, albeit with delay. Improvements in the operating deficit of the
Tanzania Electric Supply Company (TANESCO) were a result of (a) tariff
reforms, (b) significant cost reductions (Indicator 5), and (c) significant
reductions in technical and non-technical losses (Indicator 3). Results were
achieved despite a major depreciation of the Tanzanian Shilling during FY2015
(8 percent) and FY2016 (24 percent), affecting TANESCO’s fuel cost.
Indicator 2: TANESCO accounts (trade and other) payable (T Sh billion)
Value (quantitative
or qualitative)
707 300 1,187a 1,331
b
Date achieved 2012 2016 June 30, 2016 June 30, 2017
Comments (including
% achievement)
Not achieved, because of (a) pressure on TANESCO’s cash flow as external
financing is insufficient for TANESCO’s investment program, including for new
connections; (b) insufficient surplus cash generated from operations; and (c) a
major depreciation of the T Sh (see Indicator 1) (TANESCO’s arrears are mostly
denominated in U.S. dollars but indicator is in Tanzania Shilling).
Indicator 3: TANESCO technical and non-technical losses in transmission and
1 Indicators and their targets were partially revised during the preparation and approval of the second DPO in
February 2014. The DPO series assesses the Program against the revised indicators.
xi
TZ First and Second Power and Gas Sector DPOs (P143645 and P145254).
Indicator Baseline Value
Original Target
Values (from
approval
documents)1
Actual Value
Achieved when the
DPO program
elapsed
Actual Value
Achieved at the
time of the ICR
distribution (%)
Value (quantitative
or qualitative)
21 18 18.29c 16.44
c
Date achieved 2012 2016 Year to June 30,
2016
Year to June 30,
2017
Comments (including
% achievement)
Achieved and subsequently exceeded, as a result of measures to enhance
transparency in—and accountability for—TANESCO’s operational performance,
as well as investments in grid strengthening.
Pillar 2: Reducing the cost of power supply and promoting private sector
participation in the power sector
Indicator 4: Amount of gas-fired power generation capacity commissioned after 2011
(MW)
Value (quantitative
or qualitative)
105 400 255d 255
d
Date achieved 2012 2016 March 20, 2016 June 30, 2017
Comments (including
% achievement)
Not achieved. The Kinyerezi I gas power plant (150 MW) was fully
commissioned in 2016 and the first unit of Kinyerezi II is expected to be
commissioned by the end of 2017. However, while construction of both power
plants was delayed, the pressure to commission new capacity was less than
anticipated as demand grew much slower than expected (actual sales in 2016
were 17% lower than projected in the Program Document of the first
Development Policy Operation [DPO-1]) and hydrology conditions have been
relatively favorable. However, TANESCO will need to secure additional capacity
soon to be able to withstand another major drought.
Indicator 5: Average unit cost of power sales (US$/kWh)
Value (quantitative
or qualitative)
0.18f 0.15 0.12
a 0.09
b
Date achieved 2012 2016 Year to June 30,
2016
Year to June 30,
2017
Comments (including
% achievement)
Achieved and significantly exceeded, as a result of (a) the phaseout of
emergency power plants, made possible by relatively good hydrological years in
2015 and 2017, new gas-fired generation capacity, and relatively slow demand
growth; (b) a shift from oil products to natural gas in the generation mix; and (c)
significant reductions in technical and non-technical losses (Indicator 3).
Indicator 6: Number of bids for gas IPP power plants launched on a competitive basis
(count)
Value (quantitative
or qualitative)
0 1 0 0
Date achieved 2012 2016 March 20, 2016 June 30, 2017
Comments (including
% achievement)
Not achieved. The pressure to secure new capacity has not been as high as
anticipated (see Indicator 4). In addition, a series of major sector governance
controversies relating to independent power producers (IPPs) and emergency
power producers (EPPs) slowed down plans for procurement of privately-owned
xii
TZ First and Second Power and Gas Sector DPOs (P143645 and P145254).
Indicator Baseline Value
Original Target
Values (from
approval
documents)1
Actual Value
Achieved when the
DPO program
elapsed
Actual Value
Achieved at the
time of the ICR
generation capacity during the Program period.
Indicator 7: Ministry of Energy and Minerals (MEM)2 documents on sector reforms
published for public knowledge (count)
Value (quantitative
or qualitative)
0 2 2 2
Date achieved 2012 2016 March 20, 2016 June 30, 2017
Comments (including
% achievement)
Achieved. The two major sector reform documents approved by MEM since
2012 are (a) the Electricity Supply Industry Reform Strategy and Roadmap 2014–
2025 (2014) and (b) the National Energy Policy (2015).
Pillar 3 Strengthening the policy and institutional framework for the management of
the country’s natural gas resources
Indicator 8: Volume of gas produced (mmscfd)
Value (quantitative
or qualitative)
78 250 102e 132
e
Date achieved 2012 2016 Year to December
31, 2015
Year to December
31, 2016
Comments (including
% achievement)
Not achieved. Growth in gas production has been much slower than anticipated
at approval of the DPOs, largely due to (a) slow domestic demand growth (see
Indicator 4); (b) the decline in global energy prices; and (c) slow reform progress
in the upstream regulatory and policy framework.
Indicator 9: Amount of onshore proven natural gas reserves (Tcf)
Value (quantitative
or qualitative)
1.0 3.5 1.369e 1.187
e
Date achieved 2012 2016 April 1, 2015c December 31,
2016
Comments (including
% achievement)
Not achieved. Probable reserves are now estimated at 57 Tcf. However,
investment exploration and production (which would probable reserves into
‘proven reserves’) has been subdued, largely due to (a) slow domestic demand
growth (see Indicator 4); (b) the decline in global energy prices; and (c) slow
reform progress in the upstream regulatory and policy framework.
Indicator 10: Annual monitoring under the Natural Resource Charter initiative
Value (quantitative
or qualitative)
No Yes No No
Date achieved 2012 2016 March 20, 2016 June 30, 2017
Comments (including
% achievement)
Not achieved. Reform progress in the upstream regulatory and policy framework
has been much slower than anticipated, as a result of a series of sector
governance controversies in the energy and minerals sectors (details in the main
text) in combination with a change in Government and policy priorities and the
decline in global energy prices which made the development of Tanzania’s
2 The ICR was prepared before the Ministry of Energy and Minerals was renamed the Ministry of Energy in late
2017.
xiii
TZ First and Second Power and Gas Sector DPOs (P143645 and P145254).
Indicator Baseline Value
Original Target
Values (from
approval
documents)1
Actual Value
Achieved when the
DPO program
elapsed
Actual Value
Achieved at the
time of the ICR
natural gas resources less lucrative.
a. Source: Audited financial statements of TANESCO. b. Source: Draft unaudited financial statements of
TANESCO. c. Source: TANESCO. d Source: TANESCO.
e. Source: National Bureau of Statistics; Tanzania Petroleum Development Corporation.
Note: f. Updated data suggest that the 2012 baseline was 0.16; the value in 2013 was 0.18.
G. Ratings of Program Performance in ISRs
TZ First Power and Gas Sector DPO - P143645
No. Date ISR
Archived DO IP
Actual Disbursements
(US$, millions)
1 04/16/2014 Moderately Satisfactory Moderately Satisfactory 98.22
TZ Second Power and Gas Sector DPO - P145254
No. Date ISR
Archived DO IP
Actual Disbursements
(US$, millions)
1 08/13/2015 Moderately Satisfactory Moderately Unsatisfactory 100.43
H. Restructuring (if any)
There were no program restructurings during the period of implementation of the two operations (DPO-1
and DPO-2). However, results indicators and triggers were revised during the appraisal of DPO-2.
1
1. Program Context, Development Objectives, and Design
1. This Implementation Completion and Results Report (ICR) assesses the results of the
programmatic series of two Development Policy Operations (DPOs) to the United Republic of
Tanzania. The DPO series aimed to (a) strengthen the country’s ability to bridge the financial gap in its
power sector, (b) reduce the cost of power supply and promote private sector participation in the power
sector, and (c) strengthen the policy and institutional framework for the management of the country’s
natural gas resources. The first operation (DPO-1) of SDR 64.90 million was approved by the World
Bank’s Board of Directors on March 26, 2013. The second operation (DPO-2) of SDR 65.20 million was
approved on March 21, 2014.
2. The series was originally set up to consist of three programmatic DPOs. However, because of
a delay in implementing the prior actions for DPO-3, on March 20, 2016 the programmatic series was
considered to have lapsed because no subsequent operation was presented to the Board within 24 months
after the Board approval of the previous operation in the series. A concept review meeting for a follow-up
series of two operations was held in July 2016, but preparation of the follow-up DPO series was cancelled
at the time of this ICR.
1.1 Context at Appraisal
3. When the DPO reform program was initiated in 2013, only 16 percent of Tanzanians had
access to electricity and the lack of access to affordable and reliable energy was viewed as a major
constraint to Tanzania’s economic growth and diversification. Based on the latest Household Budget
Survey 2011/12 data, only 16 percent of the population had access to electricity. Tanzania had access
rates that were higher than Malawi and Uganda (9 percent) but lower than Kenya and Zambia (over 20
percent) and far lower than developing countries of East Asia (more than 90 percent coverage) and South
Asia (62 percent). Access to the national grid was particularly limited in rural areas and for the poor. Only
1.1 percent of the lowest income quintile in rural areas had access to electricity.3 U.S. Agency for
International Development (USAID) and World Bank studies4 found that poor infrastructure, especially
power and transport, was a key constraint to economic growth and diversification in Tanzania. Managers
of firms and most Tanzanian enterprises considered routine load shedding and power outages to be the
most serious constraint to doing business. The lack of access to cheap and reliable energy was costing
local firms as much as 5 percent of sales and as much as 18 percent for manufacturing firms. This scale
was consistent with other reports in Africa, which suggest that power outages result in significant losses
equivalent to 6–16 percent of turnover. To promote electricity access, in early 2013, the Government
reduced connection fees by 30 percent to 90 percent, and instructed the Tanzania Electric Supply
Company (TANESCO) to increase its customers base to 1,500,000 by 2015 and target 250,000 new
connections per year.
4. Reforms to modernize Tanzania’s power sector had begun in the early 2000s but a
significant sector reorganization, stipulated by the Electricity Act of 2008, still had to be
implemented. TANESCO, the vertically integrated utility, was corporatized in 2002 under the Public
Corporations Act, but is still fully government-owned. The company was under a private management
contract between May 2002 and December 2006, which focused on financial and technical performance
improvements. A Rural Electrification Agency was established through the Rural Energy Act of 2005,
with the mission to promote and facilitate availability and access to modern energy services in rural
3 National Panel Survey, 2010–2011.
4 USAID. 2011. “Tanzania Growth Diagnostics, Partnership for Growth.” and World Bank. 2009. “Investment
Climate Assessment.”
2
mainland Tanzania. An independent Energy and Water Utilities Regulatory Authority (EWURA) became
operational in 2006. This was followed by the adoption of an Electricity Act in 2008, which established a
stronger separation between ownership, policy, and regulatory functions and created a clearer framework
for sector governance, licensing, and tariff regulation. The Act included a mandate for the Ministry of
Energy and Minerals (MEM) to prepare and publish a policy for the reorganization of the electricity
market. The Act also stipulated the strengthening of the governance of TANESCO, reforming its top
management structure and creating a Board of Directors with public and private sector stakeholder
representations. However, implementation of the Electricity Act of 2008 had yet to make significant
progress by the time of the appraisal of DPO-1, and the Government retained strong influence over all
decision-making in the sector.
5. Tanzania was facing a power supply crisis during the appraisal of DPO-1 and DPO-2,
which threatened to derail the country’s industrialization agenda, put severe financial strain on
TANESCO and the Government, and endangered its electricity access targets. In the years leading
up to the DPO series, Tanzania was experiencing declining reserve capacity, triggered by growing
demand and years of underinvestment in new and diversified generation capacity. Out of total of 1,092
MW of installed capacity in 2010, hydropower represented 52 percent, natural gas 33 percent, oil
products 13 percent and imports 1 percent. In FY2010/11, as a result of poor rainfall that reduced
hydropower production, Tanzania started experiencing a series of supply deficit. At the peak of the crisis,
in mid-2011, some parts of the country experienced daily load shedding of up to 12 hours. TANESCO
entered into expensive, short-term contracts with private emergency power producers (EPPs) to provide a
total of 317 MW of generation capacity. These steps eased supply shortages but significantly increased
the cost of supply: In 2012, the share of electricity generation of the EPPs was 11 percent, but their share
of costs was 43 percent, doubling the average unit cost of sales (from US$0.08 per kWh in 2010 to
US$0.165 per kWh in 2012). This turned the power supply crisis into a financial crisis when the regulator
did not pass through the additional costs to consumers. In mid-2012, TANESCO’s financial shortfall was
running at more than US$40 million per month, as the hydrological condition continued to be below
average, while electricity demand kept increasing, requiring continued engagement of the expensive
EPPs. TANESCO accumulated arrears to the EPPs, independent power producers (IPPs), and fuel and
other suppliers, as tariffs and Government transfers to the sector did not keep up with the rising cost of
supply. By the end of 2014, the total cumulative financial gap of the energy sector was expected to be
between US$760 million and US$1 billion (or between 2.9 percent and 3.8 percent of gross domestic
product [GDP]). The reform program prepared by the Government in response to this power supply crisis
(the ‘Program’) was supported by the DPO series (envisioned as programmatic DPO series with three
operations). The Program was also supported by the IMF and the AfDB.
6. To respond to the power sector crisis, the Government had prepared a Program of reforms
that included (a) crisis-response measures to address the short-term fiscal risks; and (b) medium- to
long-term reform measures to prevent a similar crisis from repeating in the future. The Program had
support at the highest levels of the Government and had been developed in close collaboration with
development partners (DPs). It consisted of prior actions under three, interlinked pillars. The short term,
crisis-response elements of the Porgram included measures to close the financial gap in the power sector
through a combination of tariff reforms, transparent Government transfers to TANESCO, and
Government-guaranteed commercial borrowing by TANESCO (Pillar 1). The medium to long-term
reform measures (crisis-prevention) aimed at ensuring that the power and the gas sectors are developed
5 At the time of appraisal, the estimate of the cost of supply in 2012 was US$0.18, which is reflected in the baseline
of Results Indicator 5. However, more recent statistics indicate that the average cost of supply was US$0.16 in
FY2012 and US$0.18 in FY2013.
3
and operated in a more efficient, transparent, and financially sustainable manner. To reduce the cost of
supply and mitigate the risk of supply shocks (such as droughts or oil price increases), the authorities
intended to shift the energy mix away from the expensive emergency supply to more efficient, gas-fired
generation, developed through the private sector (Pillar 2). To ensure sufficient gas supply to the power
sector (and the economy overall), the authorities aimed to develop a framework to attract investment in
upstream natural gas exploration and production (Pillar 3).
7. Increasing gas production in a relatively short period and at relatively low cost required an
adequate investment framework that had the capacity to incentivize investment in gas production.
During 2013–16, the Government’s strategy was to use existing nearshore gas reserves to supply new gas
power plants through the construction of a new pipeline. In the longer term, the authorities planned to
invest in renewable resources and possibly coal and hydroenergy. The development of offshore massive
gas reserves was at the top of the Government’s agenda, but the expected impact on economic growth and
poverty was expected to occur only when production starts in about 7–10 years. The objective of the
strategy was not only to increase power capacity but also to significantly reduce production costs by
lowering the reliance of the energy network on expensive fuel power plants. It could also help diversify
the risks associated with climatic shocks and variations in fuel prices on international markets. The DPO
series was to support this medium-term vision.
8. The proposed series was to complement a larger World Bank portfolio supporting the
energy sector of Tanzania directly or indirectly. Ongoing and planned complementary World Bank
interventions cited in the Program documents included the following: (a) investment lending that intended
to promote access to energy, strengthen the transmission and distribution network, and expand use of
renewable energy6; (b) the Energy Sector Capacity Building Project (ESCBP, P126875)
7; (c) nonlending
analytical work and technical assistance on the multisector gas agenda; (d) a potential policy-based
guarantee operation to increase the capacity of TANESCO to borrow commercially at attractive terms;
and (e) ongoing and future general budget support aimed at improving effectiveness and transparency in
public finance areas including revenue mobilization and public investment management.
9. The country’s macroeconomic performance during the period covered by the DPO
program was broadly positive (Table 1). The real GDP annual growth for Tanzania remained high
during FY2013–17, averaging about 7.0 percent, driven by construction and services. In FY2016/17, the
growth rate is projected to reach 6.6 percent. The inflation rate remained low and stable. The external
balance improved, with the current account deficit falling from14.3 percent in FY2012/13 to an estimated
2.8 percent in FY2016/17. The fiscal deficit improved sharply after FY2012/13 from 6.8 percent of GDP
to around 3 percent of GDP, and remained stable throughout the Program period. However, a looser
monetary policy has yet to translate into a reduced cost of borrowing for the private sector or into
increased private investment, partly because of the continued uncertainty. Going forward, fiscal and
monetary policy challenges remain, with persistently high domestic payment arrears (at around 6 percent
of GDP at the end of FY2016/17) and the low execution rate of the development budget (62 percent in
FY2016/17) threatening the credibility of the budget. The growth outlook is favorable in the short- to
medium-term, with key risks being both mostly domestic and under the Government’s control. In the
medium term, the main risks relate to a further deterioration in business sentiment as a result of increased
policy uncertainty and to a decline in the execution rate of the development budget. The most significant
6 At the time of appraisal, the World Bank was supporting the Government’s access agenda and renewable energy
objectives (Tanzania Energy Development and Access Project [TEDAP], 2008; US$167 million) as well as
investment in transmission grid expansion (Backbone Transmission Project 2010; US$150 million). 7 The ESCBP (2015; US$35 million) provides capacity building to the Government and its institutions.
4
external risks relate to potential rebounds in oil prices, volatile global financial conditions, and a decline
in demand from Tanzania’s main export partners.
Table 1. Key Economic Indicators: FY2012/13–FY2016/17
(in percent unless otherwise indicated)
Government Fiscal Years (July 1–June 30)
2013/14 2014/15 2015/16 2016/17e 2017/18
f 2018/19
f
Real GDP growth, at constant market prices 7.0 7.0 7.0 6.6 6.8 6.9
Private Consumption 4.5 2.3 4.5 4.0 4.0 4.0
Government Consumption -0.5 -4.0 -7.4 2.6 6.3 6.2
Gross Fixed Capital Investment 12.8 11.5 8.0 5.3 10.0 9.7
Exports, Goods and Services 17.7 23.0 -23.2 3.9 2.8 4.7
Imports, Goods and Services 2.9 -2.1 -26.8 -5.3 2.9 3.6
Real GDP growth, at constant factor prices 6.9 8.6 5.7 6.5 6.8 6.9
Agriculture 3.4 2.3 2.1 2.5 2.5 2.7
Industry 10.3 11.3 10.7 10.2 10.7 10.6
Services 7.1 10.3 5.0 6.4 6.6 6.6
CPI 6.0 6.3 5.0 6.4 6.6 6.6
Current Account Balance (% of GDP) -10.3 -8.6 -4.4 -2.8 -3.3 -3.6
Financial and Capital Account (% of GDP) 11.1 9.1 4.5 2.9 3.4 3.7
Net Foreign Direct Investment (% of GDP) 5.1 3.9 2.9 2.9 5.8 9.5
M3 growth (in FY) 15.6 18.8 12.7 6.1 .. ..
Private sector credit growth (in FY) 16.5 18.2 18.5 1.3 .. ..
Revenue (% of GDP) 14.8 17.2 16.7 17.6 18.0 18.3
Expenditure (% of GDP) 17.8 20.6 20.0 20.7 21.6 21.9
Fiscal Balance (% of GDP) -3.0 -3.4 -3.3 -3.1 -3.6 -3.6
Arrears (% of GDP, in FY) 4.3 6.5 6.4 6.3 .. ..
Debt (% of GDP) 33.6 34.5 37.4 37.6 38.2 39.2
Notes: e = estimate, f = forecast.
Source: International Monetary Fund (IMF) Report, World Bank Staff.
Note: a. Net of treasury bills issued for liquidity management.
b. Excludes interest payments due on external debt under negotiation for relief and domestic unpaid claims.
1.2 Original Program Development Objectives (PDO) and Key Indicators (as approved)
10. The PDO of the Program supported by DPO-1 and DPO-2 was to (a) strengthen the country’s
ability to bridge the financial gap in its power sector, (b) reduce the cost of power supply and promote
private sector participation in the power sector, and (c) strengthen the policy and institutional framework
for the management of the country’s natural gas resources.”
5
11. The Program’s results indicators are shown in Table 2.
1.3 Revised PDO and Key Indicators, and Reasons/Justification
12. No changes were made to the PDO between DPO-1 and DPO-2.
13. DPO-2 made some changes to selected indicators with the aim to better align with the
interpretation of the original objectives and capture progress toward them. It also added three new results
indicators and revised the target year of all indicators from 2015 to 2016. Table 2 presents the two sets of
indicators indicating the concordance between them. When referring to results indicators of the DPO
series, this ICR refers to the numbering shown in Table 2 (for example, ‘Results Indicator 1’ is
TANESCO’s operating deficit).
14. The revised indicators are used in this ICR to evaluate the DPO series. When assessing the DPO
series’ achievement of its PDOs, this ICR takes into account that the results indicators were designed for a
series of three operations but only two out of three planned DPOs were approved.
Table 2. Original and Adjusted Results Indicators of the Program
# Indicator as Approved under
DPO-1
Indicator as Approved under
DPO-2
Baselinea
(2012) Target
a (2016)
Pillar 1: Strengthening the country’s ability to bridge the financial gap in its power sector
1 TANESCO operating deficit
(US$, millions)
TANESCO operating deficit
(US$, millions)
240
(DPO-1: 244)
50
2 Amount of accumulated arrears
to suppliers by TANESCO (US$,
millions)
TANESCO accounts (trade and
other) payable (T Sh, billions)
T Sh 707
billion
(DPO-1:
US$276
million)
T Sh 300
billion
(DPO-1:
US$50
million)
Pillar 2: Reducing the cost of power supply and promoting private sector participation in the power
sector
3 TANESCO technical and non-
technical losses in transmission
and distribution (%)
21 18
4 New generation capacity added
to the system, cumulative (MW)
Amount of gas-fired power
generation capacity
commissioned after 2011 (MW)
105 400
(DPO-1: >600)
5 Average unit cost of power sales
(US$/kWh)
Average unit cost of power sales
(US$/kWh)
0.18b
(DPO-1: 0.20)
0.15
(DPO-1: 0.13)
6 Number of bids for gas IPP
power plants launched on a
competitive basis
Number of bids for gas IPP
power plants launched on a
competitive basis
0 1
7 MEM documents on sector
reforms published for public
knowledge
0 2
Pillar 3: Strengthening the policy and institutional framework for the management of the country’s
natural gas resources
8 Volume of gas produced
(mmscfd)
Volume of gas produced
(mmscfd)
78 250
(DPO-1: >290)
6
# Indicator as Approved under
DPO-1
Indicator as Approved under
DPO-2
Baselinea
(2012) Target
a (2016)
9 Amount of onshore proven
natural gas reserves (Tcf)
Amount of onshore proven
natural gas reserves (Tcf)
1.0 3.5
10 Annual monitoring under the
Natural Resource Charter
initiative
No Yes
Note: MEM = Ministry of Energy and Mining; mmscfd = Million Standard Cubic Feet per Day; Tcf = Trillion
Cubic Feet.
a. Values in brackets are from DPO-1. b. Updated statistics indicate that the baseline cost was 0.16 in 2012 and 0.18
in 2013.
1.4 Original Policy Areas Supported by the Program
15. The DPO series supported three main policy areas, which also formed the elements of the
PDO: (a) strengthening the country’s ability to bridge the financial gap in the power sector, (b) reducing
the cost of power supply and promoting private sector participation in the power sector, and (c)
strengthening the policy and institutional framework for the management of the country’s natural gas
resources. Below is a description of the expected outcome, the prior actions completed under the two first
operations, and the triggers that were to set the stage for the third operation.
Pillar 1: Strengthening the country’s ability to bridge the financial gap in its power sector
16. Expected outcomes. Pillar 1 aimed to restore the financial sustainability of the sector by (a)
raising TANESCO’s collected revenues close to a cost-reflective8 level and (b) arresting and eventually
reversing the buildup of arrears. These outcomes, measured by the size of TANESCO’s operating deficit
and the level of its arrears, were expected to be affected by measures under Pillar 1 (which focused on the
revenue side of TANESCO’s income statement) as well as Pillars 2 and 3 (which tackled the cost of
electricity supply).
17. Prior actions and triggers. Under DPO-1 and DPO-2, the Government implemented measures to
(a) increase tariffs and improve bill collection, including from Government consumers and (b) ensure
fiscal transfers to TANESCO are determined based on TANESCO’s needs as well as transparent and
consistent with an adequate macroeconomic policy framework. Triggers for DPO-3 (as approved under
DPO-2) were a comprehensive national subsidy policy with principles for subsidizing the energy sector
and a commitment to reduce the level of transfers to TANESCO in FY2014/15 to the level of not more
than 2 percent of controlled total public expenditure.9
Pillar 2: Reducing the cost of power supply and promoting private sector participation in the power
sector
18. Expected outcomes. Pillar 2 aimed to reduce the cost and risks related to power supply by (a)
reducing system losses; (b) promoting private investment to overcome the supply shortage and ending the
dependence on EPPs; (c) replacing costly and polluting oil-fired power generation with natural gas-based
8 ‘Cost-reflective’ revenues are understood for this ICR as revenues that are sufficient to cover TANESCO’s cost.
The cost incurred by the Government of servicing debt on behalf of TANESCO is not included in this definition.
9 Controlled total expenditure = total expenditure − consolidated funds service − wage − foreign development
expenditure.
7
generation in Tanzania’s power mix; and (d) enhancing sector governance and performance through
closer monitoring, enhanced access to information for all stakeholders, and the adoption of a participative
and consultative approach to problem solving and policy formulation. These outcomes were to be
measured by newly installed generation capacity, loss reduction, unit cost of power sales; launched
tenders for private sector-owned generation capacity; and sector reform documents published by the
MEM. Expected outcomes of Pillar 2 were interlinked with those of Pillars 1 and 3, in two main ways:
First, as mentioned earlier, prior actions under this pillar were also expected to contribute to the outcomes
of Pillar 1. Second, the additional upstream gas investments required for additional gas-fired power plants
(Results Indicator 2) were to be enabled through measures under Pillar 3.
19. Prior actions and triggers. Under DPO-1 and DPO-2, the Government adopted, and took
measures to implement, a new strategic power sector policy. Implementation measures included (a) a
performance contract between TANESCO and the MEM; (b) period publication of performance reports,
financial audits, and procurement audits; and (c) launching a capacity-building program. The Government
also prepared a road map for structural reforms, which was to be approved under DPO-3. Triggers for
DPO-3 (as approved under DPO-2) were for (a) TANESCO to continue improving and reporting publicly
on collection performance and on operational losses, (b) the Government to phase out 150 MW of EPPs,
(c) TANESCO to implement the 2013 policy to promote private sector participation in power generation
by launching at least one competitive bidding process for new gas-based generation capacity to diversify
power generation sources in the country toward lower cost structure of the power sector, and (d) the
Government to approve the road map for structural reforms of the energy sector (including the power and
gas subsectors).
Pillar 3: Strengthening the policy and institutional framework for the management of the country’s
natural gas resources
20. Expected outcomes. Pillar 3 aimed to expand gas supply to the sector by strengthening the policy
and institutional framework of the upstream gas sector. This expected outcome was likely to contribute to
the objectives of the other two pillars, as secure gas supply for its planned gas-fired generation capacity
was critical to reduce costs (Pillar 2) and restore the balance of revenues and costs in the sector (Pillar 1).
21. Prior actions and triggers. Under DPO-1 and DPO-2, the Government has put in place the first
building blocks of the policy and institutional framework. The Government (a) adopted a Natural Gas
Policy, based on a consultative process; (b) launched a program to adopt a Tanzania Natural Resource
Charter; (c) elevated the natural gas agenda by including natural gas development in the mandate of the
Cabinet committee on economic affairs and creating an interministerial senior task force; (d) cleared
arrears with gas developers; (e) verified the amount of natural gas reserves in the United Republic of
Tanzania’s territory; and (f) mandated the Tanzania Petroleum Development Company (TPDC) to publish
its audited financial statements; its latest procurement audit reports, and its key performance indicators
(KPIs). Triggers for DPO-3 (as approved under DPO-2) foresaw the completion of the major building
blocks of the policy and institutional framework by (a) adopting a National Gas Utilization Master Plan,
(b) preparing new natural gas legislation, and (c) and adopting a Petroleum Policy.
Distinction between crisis response elements and medium- to long-term reform elements of the
Policy and Results Matrix in this ICR
22. In the narrative and assessment, this ICR distinguishes crisis-response elements of the
Policy and Results Matrix on the one side and medium- to long-term reform elements on the other.
The three pillars group prior actions of the DPO series according to the objectives. However, for the
purpose of the assessment carried out in this ICR it was considered useful to distinguish between short-
term (crisis response) measures that yielded immediate results and reforms to the energy sector structure,
8
sector policy framework, and sector institutions that could be expected to translate into tangible outcomes
only in the medium to long term. The former includes measures on tariffs, arrears clearance, and fiscal
transfers under Pillar 1 and also measures relating to performance contracts and performance audits under
Pillar 2 and arrears clearance under Pillar 3. The latter includes most reform measures under both Pillar 2
and Pillar 3. This distinction was made because as laid out in sections 2–6 of this ICR, the assessment of
adequacy of design and objectives of the DPO series was found to differ significantly between these two
elements of the Policy and Results Matrix.
1.5 Revised Policy Areas
23. The policy areas for the PDO program were not revised. The Policy and Results Matrix
approved with DPO-2 included only relatively small changes to the prior actions of DPO-2 compared to
the triggers approved with DPO-1, as summarized in Table 5 in section 2.1.
1.6 Other Significant Changes
24. The Government and IDA did not proceed with the proposed third operation in the series
because of delays in the implementation of the Program. On March 20, 2016, the programmatic series
was considered lapsed because no subsequent operation was presented to the Board within 24 months
after the Board approval of the previous operation in the series (in this case, DPO-2). A concept review
meeting for a follow-up series of two operations (DPO-3 and DPO-4) was held in July 2016, but
preparation of the follow-up DPO series was cancelled at the time of the ICR. Details on the reasons for
the delays and the status of triggers for DPO-3 are provided in section 2.
2. Key Factors Affecting Implementation and Outcomes
2.1 Program Performance
25. The programmatic series consisted of two single-tranche DPOs, disbursed in full upon
effectiveness, in the total amount of SDR 130.1 million. Key dates of the two operations are provided
in Table 3.
Table 3. Key Dates of the DPO Series
Operation Disbursed Amount Approval Effectiveness
Date Closing
DPO-1 SDR 64.9 million March 26, 2013 June 12, 2013 June 30, 2014
DPO-2 SDR 65.2 million March 21, 2014 June 9, 2014 June 30, 2015
26. All prior actions were completed by the Government before the Board presentation of
DPO-1 and DPO-2. Table 4 shows the key objectives pursued and all prior actions completed ahead of
the approval of each operation. None of the prior actions was reversed after Board approval. However,
progress on some reform areas tackled by the prior actions either slowed down or was partially reversed
in subsequent years (see section 3.2 for details).
Table 4. Policy Matrix and Status of Prior Actions
Prior Action Status
Pillar 1: Strengthening the country’s ability to bridge the financial gap in its power sector
Prior action #1.1: TANESCO has increased its collection of revenues by 30% between Completed
9
Prior Action Status
CY2011 and CY2012, through tariff increase and improved collections of bills. ahead of
DPO-1 Prior action #1.2: To improve the financial conditions of TANESCO in FY2013, (a)
EWURA reviewed the current electricity tariffs; (b) the Government has identified the
amount of subsidies to be transferred from the Government budget to TANESCO based on,
among others, the abovementioned tariff review; and (c) the Government has paid T Sh 67
billion by June 2012 to clear its arrears to TANESCO for electricity consumed by
governmental entities.
Prior action #2.1: TANESCO has implemented new tariffs, approved by EWURA in
December 2013 in order to increase its revenue.
Completed
ahead of
DPO-2 Prior action #2.2: The Government had created in its approved FY2013/14 budget a
specific code with funds for transfers to TANESCO to improve fiscal transparency.
Prior action #2.3: The Government has taken actions to reduce the level of transfers to
TANESCO from the level of FY2012/13 and has committed that the level will not exceed
2.5 percent of controlled total expenditure in FY2013/14.
Pillar 2: Reducing the cost of power supply and promoting private sector participation in the power
sector
Prior action #1.3: The Government adopted a policy aiming to reduce the cost of power
supply, improve the operational efficiency of the power sector, and promote the
participation of the private sector in power generation through a competitive and
transparent bidding process that respects the national laws and the best practices of
international environmental and social standards.
Completed
ahead of
DPO-1
Prior action #1.4: TANESCO and the Ministry of Energy and Mining signed a
performance contract, which includes measurable key performance indicators for
TANESCO to enhance its efficiency in CY2013.
Prior action #1.5: TANESCO published (a) periodic performance reports prepared by
TANESCO against the key performance indicators set out in the abovementioned
performance contract between TANESCO and MEM; (b) its latest annual audit report
issued by NAO; and (c) its latest annual performance report issued by PPRA.
Prior action #2.4: The Government and TANESCO have implemented the initial phase of
the 2013 Policy for Private Sector Participation in Power Generation through Competitive
Processes by launching PPP capacity-building programs for (a) screening and conducting
due diligence; (b) financial structuring; (c) structuring processes for selecting developers
and implementing transactions; (d) preparing legal and regulatory documents; and (e)
managing government and public corporation fiscal risks.
Completed
ahead of
DPO-2
Prior action #2.5: The Government has adopted the recommendations of the Presidential
Big Results Now (BRN) Initiative to develop a road map for structural reforms of the
energy sector and has established a Ministry Delivery Unit within MEM to oversee the
implementation of the recommendations.
Pillar 3: Strengthening the policy and institutional framework for the management of the country’s
natural gas resources
Prior action #1.6: The Government completed a nationwide public consultation process
for adopting its Natural Gas Policy.
Completed
ahead of
DPO-1 Prior action #1.7: The Government adopted measures, including clearing arrears with gas
developers by paying them US$106.9 million by December 2012 and verifying the amount
of natural gas reserves in the United Republic of Tanzania’s territory, which will enable
higher production of natural gas and its use in power generation after CY2014.
Prior action #2.6: The Government has adopted the Natural Gas Policy. Completed
10
Prior Action Status
Prior action #2.7: The Government has launched a program to adopt a Tanzania Natural
Resource Charter and has established an expert panel to oversee the program.
ahead of
DPO-2
Prior action #2.8: The Government has established a top-level institutional mechanism to
enhance interministerial coordination by mandating the Cabinet committee on economic
affairs to handle the natural gas agenda and creating an interministerial senior task force on
natural gas.
Prior action #2.9: TPDC has published on its website its latest audited financial statement,
latest procurement audit report, and key performance indicators.
Note: EWURA = Energy and Water Utilities Regulatory Authority; NAO = National Audit Office; PPP = Public-
Private Partnership; PPRA = Public Procurement Regulatory Authority.
27. Minor adjustments were made to the DPO series’ Policy and Results Matrix during
preparation and appraisal of DPO-2. The Government had made progress on all results indicators
approved with DPO-1 (listed in Table 2), and showed continued resolve to address the crisis in the power
sector. Reflecting the continuity of the implementation of the Program, the Policy and Results Matrix
approved with DPO-2 included only relatively small changes to the prior actions of DPO-2 compared to
the triggers approved with DPO-1, as summarized in Table 5 below. Changes to the results indicators
were summarized in Table 2 above.
Table 5. Prior Actions for DPO-2 Compared to Triggers for DPO-2 as Approved under DPO-1
# Trigger for DPO-2, as
Approved under DPO-1 Prior Action for DPO-2 Comment
Pillar 1: Strengthening the country’s ability to bridge the financial gap in its power sector
2.1 TANESCO to increase revenues
through a combination of better
bills collection, reduction in
losses, and, if necessary,
requesting EWURA to adjust
tariffs.
TANESCO has implemented
new tariffs, approved by
EWURA in December 2013
in order to increase its
revenue.
Trigger modified to capture
the stronger action taken by
the Government (approved
tariff increase) and edited for
clarity.
2.2 To improve fiscal transparency,
the Government has provisioned
in the FY2014 budget
contingency funds that can be
used to address the financing gap
in TANESCO.
The Government had created
in its approved FY2013/14
budget a specific code with
funds for transfers to
TANESCO to improve fiscal
transparency.
Substance strengthened
(specific budget line instead
of contingency fund) and
trigger language edited for
clarity.
2.3 In FY2014, Government shall use
a combination of tariff increases,
commercial borrowing, and
government subsidies to cover the
financing gap in TANESCO.
Government subsidies shall not
exceed 2.5 percent of total
expenditures (excluding
consolidated funds services,
wages, and development foreign).
The Government has taken
actions to reduce the level of
transfers to TANESCO from
the level of FY2012/13 and
has committed that the level
will not exceed 2.5 percent
of controlled total
expenditure in FY2013/14.
Substance maintained, but
trigger language edited for
clarity.
Pillar 2: Reducing the cost of power supply and promoting private sector participation in the
power sector
11
# Trigger for DPO-2, as
Approved under DPO-1 Prior Action for DPO-2 Comment
2.4 The Government, and TANESCO
as appropriate, have adopted
concrete measures (including
training, hiring transaction
advisers if necessary, and
completing necessary studies) to
improve its technical and
commercial capacity to develop
PPP projects in the energy sector
through transparent and
competitive process, as well as to
evaluate unsolicited proposals
(where they have merits),
including subjecting them to a
competitive process.
The Government and
TANESCO have
implemented the initial phase
of the 2013 Policy for
Private Sector Participation
in Power Generation through
Competitive Processes by
launching PPP capacity-
building programs for (a)
screening and conducting
due diligence; (b) financial
structuring; (c) structuring
processes for selecting
developers and
implementing transactions;
(d) preparing legal and
regulatory documents; and
(e) managing government
and public corporation fiscal
risks.
Substance maintained, but
trigger language edited for
clarity.
2.5 The Government has completed
an Energy Sector Review whose
objective is to recommend
structural reforms aimed at
improving power sector
performance (including efficiency
and accountability), to comply
with the Electricity Act (2008,
including part viii), and has
approved its recommendations.
The Government has adopted
the recommendations of the
Presidential Big Results
Now (BRN) Initiative to
develop a road map for
structural reforms of the
energy sector and has
established a Ministry
Delivery Unit within MEM
to oversee the
implementation of the
recommendations.
Substance maintained and
strengthened (establishment
of delivery unit) and trigger
language edited for clarity.
Pillar 3: Strengthening the policy and institutional framework for the management of the
country’s natural gas resources
2.6 The Government approves the
Natural Gas Policy.
The Government has adopted
the Natural Gas Policy.
Trigger language edited for
clarity.
2.7 Gas Act to be submitted to
Parliament after participative
public consultations, including (a)
transparent and participative
regulatory practices and (b)
access to information and
participative monitoring by
stakeholders.
The Government has
launched a program to adopt
a Tanzania Natural Resource
Charter and has established
an expert panel to oversee
the program.
Trigger was replaced. The
Gas Act was moved to DPO-
3 because by the time of
DPO-2 it had not been
submitted to the Parliament
as an extended period was
required to conduct public
consultations. At the same
time, the Government
implemented an equally
significant action in
strengthening the policy and
institutional framework for
the management of the
natural gas resources by
12
# Trigger for DPO-2, as
Approved under DPO-1 Prior Action for DPO-2 Comment
launching the Natural
Resource Charter initiative.
This replacement was to
accommodate those latest
developments while
maintaining the strength of
the overall program under
DPO-2.
2.8 The Government establishes a
top-level institutional mechanism
to enhance intersectoral
cooperation on the gas policy
agenda.
The Government has
established a top-level
institutional mechanism to
enhance interministerial
coordination by mandating
the Cabinet committee on
economic affairs to handle
the natural gas agenda and
creating an interministerial
senior task force on natural
gas.
Trigger edited for clarity.
2.9 TPDC publishes (on its website
and in print) its internal periodic
performance reports, latest audit
annual report of the NAO and
latest annual performance report
of the PPRA.
TPDC has published on its
website its latest audited
financial statement, latest
procurement audit report,
and key performance
indicators.
Trigger edited for clarity.
28. Progress toward implementing triggers for DPO-3 was delayed during 2014–2016 and fell
short of the expectations in some areas, causing the series to lapse in early 2016. Completion of all
triggers and Board approval of DPO-3 was originally envisioned by early 2015. However, only one
trigger (#3.2) was met by then. Several others were met during 2015 and 2016, as summarized in Table 6,
while four triggers were not met by the time of the ICR. Consequently, the series lapsed 24 months after
Board approval of DPO-2, on March 24, 2016.
Table 6. Status of Triggers of DPO-3 (as approved with DPO-2) at the time of the ICR
Trigger for DPO-3 Status
Trigger #3.1: The Government adopts
a comprehensive national subsidy
policy, which defines principles for
providing subsidies in the energy
sector.
Not met. No national subsidy policy has been adopted. Meanwhile,
the Government has eliminated subsidies for capacity charges, fuels,
and other operating expenses but continues to fund TANESCO’s
capital expenses.
Trigger #3.2: The Government has
committed to reduce the level of
transfers to TANESCO in FY2014/15
to the level not more than 2 percent of
controlled total public expenditure.
Met, without delay. In FY2014/15 the Government provided transfers
of US$33 million (net of taxes) to TANESCO, which is equivalent to
around 1 percent of controlled total public expenditures. Net transfers
in FY2015/16 and FY2016/17 were US$7 and US$3 million,
respectively.
Trigger #3.3: TANESCO continues to
improve and report publicly on
collection performance and on
Met, albeit with delay. Bill collection increased from 90% in
FY2014/15 to 101% in FY2015/16 and 96% in FY2016/17.
Technical and non-technical losses in the distribution grid fell from
13
Trigger for DPO-3 Status
operational losses and develops a plan
to meet the targets set by the EWURA
order in December 2013.
19% in 2012 to 12.3% in FY2015/16 and 10.4% in FY2016/17,
meeting the 2013 EWURA order target of 15.1%.
Trigger #3.4: The Government phases
out Emergency Power Projects by 150
MW without lowering the reliability of
power supply delivery.
Met, albeit with delay. EPP capacity in use declined from 317 MW in
2012 and 2013 to 162 in FY2015/16 and 0 in FY2016/17. This has
been achieved without lowering the reliability of power supply
delivery but the sector remains highly exposed to supply shortages in
the case of technical failures or a major drought.
Trigger #3.5: TANESCO implements
the 2013 policy to promote private
sector participation in power
generation by launching at least one
competitive bidding process for new
gas-based power project(s) to diversify
power generation sources in the
country toward lower cost structure of
the power sector.
Not met. The Government chose to implement Kinyerezi I (including
extension) and Kinyerezi II as public projects. The Government’s
policy toward private sector participation in future generation
projects is unclear.
Trigger #3.6: The Government
approves the road map for structural
reforms of the energy sector (including
the power and gas subsectors), which
includes specific structural measures
aimed at improving its governance and
overall efficiency and time-bound
implementation schedule, and initiates
its implementation.
Partially met. The MEM adopted and published on its website the
Electricity Supply Industry Reform Strategy and Roadmap in June
2014, which is consistent with recommendations of the energy lab of
Big Results Now. However, it excludes the natural gas subsector and
implementation of the road map has not proceeded as per the
envisioned implementation schedule. The Government’s policy
toward implementation of the road map is unclear.
Trigger #3.7: The Government adopts
a National Gas Utilization Master Plan
(NGUMP).
Not met. The Government has prepared the draft NGUMP that has
not been shared widely by energy sector stakeholders.
Trigger #3.8: The Government
prepares a Gas Bill to the Parliament.
Met, albeit with delay. The Oil and Gas Revenue Management Act
2015 and the Petroleum Act were passed by the Parliament in June
2015 following the adoption of the Natural Gas Revenue
Management Policy adopted by the Cabinet in May 2015.
Trigger #3.9: The Government
prepares and adopts a Petroleum
Policy.
Met, albeit with delay. The Petroleum Policy was adopted by the
Cabinet in 2014. Following the adoption of the Petroleum Policy, the
Petroleum Act 2015 was passed by the Parliament in June 2015,
signed by the President in October 2015, and gazetted thereafter. The
substance of the act still needs to be supplemented with the
establishment of an effective sector institutional framework and the
gradual introduction of an internationally benchmarked, prioritized
body of regulations to implement the act. The act was amended in
July 2017 following the parliamentary inquiry into mining contracts.
2.2 Major Factors Affecting Implementation
Design Factors Affecting Program Implementation and Outcomes
29. The Government was highly committed to resolve the 2011–2013 electricity supply crisis
and associated financial difficulties of TANESCO, leading to strong implementation performance
up to Board approval of DPO-2. The objectives, prior actions, and results indicators were very closely
14
aligned with the Government’s response to the electricity supply crisis. Major tariff hikes, which raised
per-unit revenues of TANESCO by 35 percent in 2012 and 30 percent in 201410
, underscored the
Government’s commitment to implement difficult reforms.
30. The World Bank’s DPO series was part of a concerted donor effort to support the
Government’s response to the fiscal and macroeconomic implications of the electricity supply crisis,
reducing the risk of reform slippage, especially during 2012–2014. The Government’s reform
response was developed in close consultation with stakeholders including the energy sector donor
consultation group. A Standby Credit Facility (SCF) arrangement of the IMF (2012–2014; SDR 149
million) included structural benchmarks on TANESCO’s financial recovery—complementary to the DPO
series—and closely monitored fiscal transfers and domestic borrowing for the electricity sector. While
overall program performance was ‘mixed’, the third and final SCF review noted that “[s]ignificant
progress was achieved in addressing financial difficulties of the energy sector” (p. 9). The Government’s
power sector reform program also received support from the African Development Bank (AfDB) in the
form of a three-phase budget support operation (2015–2017; SDR 100 million in total).
31. The crisis-response elements of the Policy and Results Matrix was informed by recent
analytical work and global experience and had a clear line of sight between prior actions and
results indicators. The short-term reform elements supported by the DPO series, which included tariff
reforms, fiscal transfers, and performance agreements between the MEM and TANESCO, were informed
by extensive, up-to-date analysis, and lessons learned from the World Bank’s reform and crisis-response
experience in the power sector. Relevant analytical work included (a) the Power System Master Plan
(PSMP 2012), (b) a short-term financial assessment (2012–2015) of TANESCO, (c) the Big Results Now
Energy Lab Report (2013), and (d) the Government of Tanzania-Energy Development Partner Group—
Joint Energy Sector Review (2013). Prior actions and objectives were clearly aligned and there was a
clear line of sight between prior actions and results indicators.
32. In contrast, the medium- to long-term reform elements of the Policy and Results Matrix
carried high implementation risks because they were backloaded, heavy on commitments and light
on implementation, and missed a clear line of sight between prior actions and results indicators. Prior actions and triggers under Pillars 2 and 3 called for fundamental reforms to the power and gas
sectors but envisioned that the analytical foundations and buy-in of stakeholders would be established, to
a large extent, during implementation. The program also envisioned that Government commitments—in
the form of policies, plans, and road maps—would be followed by reform implementation measures
above and beyond the measures laid out in the DPO Policy and Results Matrix. As outlined in more detail
in section 3, Program progress stalled on several fronts after the immediate pressure of the crisis eased in
2015.
33. The World Bank took an informed risk by engaging with the Government on natural gas
reforms (supported by Pillar 3) without significant prior sector dialogue, because of the strategic
importance of a strong upstream natural gas policy framework for the development of Tanzania’s
energy sector. Unlike in the power sector pillars, Pillar 3 of the DPO series could not build on solid
analytical foundations and an established sector dialogue. Only after initiation of the preparation of the
DPO series did the World Bank engage in deeper sector dialogue through a natural gas ‘scoping mission’,
10 EWURA’s tariff orders refer to increases of 39.19 percent and 40.29 percent in 2012 and 2014, respectively.
Relative changes in per-unit revenues differ from relative changes in tariffs because of changes in the composition
of consumption and parallel changes in fixed charges for consumers. Data on per-unit revenues was taken from
TANESCO’s financial statements.
15
co-led by the World Bank and including six other DPs, which developed the policy and institutional
actions to be undertaken by the authorities. However, the World Bank’s senior management assessed the
risk of not engaging on such an important sector as higher than the Program’s risks.
34. The technical risk assessment was adequate but important governance risks were missed;
the political economy of power sector reform in particular was poorly reflected in the design of the
medium- to long-term reform measures in the Program. The most important technical risks that
materialized had been correctly identified, including hydrology, global energy prices, and exchange rate
volatility, and the appraisal documents rightly noted that these risks could not be fully mitigated within
the Program. However, risks relating to the governance of the Program and the political economy of
power sector reform could have been better reflected in the length, scope and ambition of the DPO series.
Specifically, these risks included (a) the Government’s reform commitment beyond the immediate crisis,
(b) insufficient stakeholder consensus on structural sector reforms (the exact nature of which was to be
determined under the Program), and (c) the risks associated with designing a reform program that spans
election cycles.
External Factors Affecting Program Implementation and Outcomes
35. During implementation, progress toward the envisioned outcomes was affected by a
number of external factors, including major macroeconomic and governance risks that
materialized. The main external factors of the Program that affected implementation are summarized in
Table 7, grouped by (a) sector developments outside of the Program, (b) governance factors, and (c)
macroeconomic factors.
Table 7. Major External Factors of the Program Affecting Implementation
Factors Impact on Program Implementation
Sector developments outside of the Program
Access agenda becoming priority: To promote
access, in early 2013, the Government reduced
connection fees by 30% to 90%, and instructed
TANESCO to increase its customers base to
1,500,000 by 2015 and target 250,000 new
connections per year.
Investments in new connections and related
distribution grid strengthening were
financed mainly from TANESCO’s internal
cash funds, limiting the company’s ability
to pay off arrears (thus affecting Results
Indicator 2)
Electricity demand growth slowdown: Slower than
expected, demand growth in FY2012–17 averaged
7.6%, below the 10% growth per year estimated
during appraisal of DPO-1.
Improved balance between demand and
supply and lessened pressure to commission
new gas power plants (Results Indicator 4)
Hydrology improvements. Hydrology improved
after drought in FY2011–13 and was above average in
FY2015 and FY2017. FY2016 hydrology was at
similar level as FY2011–13.
Decrease in TANESCO’s generation cost
during FY2015 and FY2017 (Results
Indicator 5)
Improved balance between demand and
supply and lessened pressure to commission
new gas power plants (Results Indicator 4)
Global energy price decline. Global oil and liquefied
natural gas (LNG) prices declined after mid-2014,
subsequently remained subdued through the end of
2017.
Slowdown in investor interest in natural gas
exploration and production, especially
offshore (Results Indicator 8)
Impact on TANESCO’s generation cost was
favorable but more than cancelled out by
exchange rate depreciation from FY2015
onwards (Results Indicators 1 and 5)
16
Factors Impact on Program Implementation
Gas pipeline delay. Completion of the National
Natural Gas Infrastructure Project (NNGIP), a core
element of the Government strategy to increase
natural gas-fired power generation, was delayed by
one year (completed October 2015)
Delay in the availability of gas for new
power plants (especially Kinyerezi I) and
fuel switching of existing power plants
(Results Indicator 4)
Governance factors
Legal controversies. The inquiry into the sale of the
Independent Power Tanzania Ltd (IPTL) plant in
2014, controversies surrounding the structure of
payments to IPPs and EPPs, and the mining sector
inquiry in 2017 both led to removal or suspension of
prolonged periods of time of MEM officials including
key leadership positions.
Delay in implementation of sector reform
program under Pillar 2 (especially Results
Indicators 6 and 7) as well as difficulties in
maintaining the strategic policy dialogue for
DPO-3 in the absence of the MEM
leadership team
2015 election. Parliamentary and presidential
elections held in October 2015 led to change in the
Government.
Reorientation of priorities for sector reform
program under Pillar 2 (especially Results
Indicators 6 and 7)
Macroeconomic factors
Growth and inflation: GDP growth remained
favorable at around 7 percent throughout the
implementation period. Inflation declined after
FY2012 and remained around 5–6 percent in
FY2013–FY2016/17.
Improvements in households’ available
income, cushioning the impact of tariff
increases (indirectly affecting Results
Indicator 1)
Exchange rate depreciation: Major exchange rate
depreciation during FY2015 (8 percent) and FY2016
(24 percent). Relatively stable before and after.
Increase in value of TANESCO’s arrears to
suppliers (which are mostly denominated in
U.S. dollars) by around 30 percent (Results
Indicator 2)
Impact on TANESCO’s generation cost was
unfavorable and only partially cancelled out
by decline in global energy prices from
FY2015 onwards (Results Indicators 1 and
5)
Fiscal consolidation: The Central Government’s
overall fiscal consolidation, as a result of lower-than-
expected domestic revenue collection, diminishing aid
disbursements, and higher investment in infrastructure
projects, posed a challenge for the energy sector in
receiving sufficient public funds to scale up necessary
investments. Arrears to contractors, suppliers and
pension funds by the Government reached over 6
percent of GDP at the end of FY2015/16.
The Central Government’s fiscal
consolidation slowed down investment
financing from the Ministry of Finance and
Planning (MOF) for TANESCO’s capital
investment program
Phaseout of direct budget transfers to
TANESCO even though TANESCO’s net
income remained negative.
2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization
36. M&E design:
Results Framework. The Program’s results indicators and target values, identified at
appraisal of DPO-1 and revised at DPO-2, were adequately linked to the PDO. The Results
Framework included more outcome indicators (for example, Results Indicators 1–5 and 8–9)
than output indicators (Results Indicators 6, 7, and 10). The focus on outcomes was
adequate for the crisis-response elements of the Program (for example, tariff reforms and
17
phase-out of EPPs) but less appropriate for the medium- to long-term elements of the
Program. In the case of the latter, the emphasis on outcomes blurred the line of sight
between prior actions and results indicators (for example, the link between the natural gas
policy framework and the volumes of proven gas reserves and gas produced). Output
indicators would have been more adequate for these prior actions. Results indicators were
appropriately defined,11
measurable, and did not require data collection efforts beyond the
financial and performance reporting of the MEM and TANESCO, ensuring that (a)
monitoring of the indicators relied on and further built capacity of country systems (b) it
could continue beyond the Program period, and (c) this ICR had access to reliable
information on all results indicators.
Roles and responsibilities. The MOF was notionally responsible for overseeing the M&E
of the Program, but was to draw on the assistance of the MEM, TANESCO, and the energy
sector regulator, EWURA. This setup was adequate in view of the selected results
indicators. Key Program results indicators were also included in (a) the budget support
framework used by the Government and DPs over the past decade in Tanzania, (b) the IMF
program, and (c) the World Bank-led annual Public Expenditure Review process. This close
integration of M&E efforts across the World Bank’s and other DPs’ engagement benefited
M&E implementation.
37. M&E implementation:
Results monitoring. The Government and the World Bank continuously monitored
progress against the main financial and performance indicators of the power sector, which
included the results indicators of the DPO series, although information on reform progress is
not always reflected on time. Financial monitoring of TANESCO in particular still needs to
become more timely. On the World Bank side, two Implementation Status and Results
Reports (ISRs) were filed, in April 2014 and August 2015, but they did not give a thorough
account of the reasons for delays and postponement of the DPO-3, in part reflecting the fact
that the M&E framework’s choice of outcome indicators over output indicators was
inadequate for monitoring the progress of medium- to long-term reforms (see above).
However, overall, monitoring of the Results Framework was implemented adequately and at
the time of ICR, data on all indicators were readily available.
Change in financial year affecting M&E implementation. The M&E framework was set
up to measure progress in TANESCO’s financial years, which were equal to calendar years
at the time of appraisal. However, TANESCO soon switched to a new financial year from
July 1 to June 30 to align with the Government’s fiscal year, starting in FY2015/16. The
transition year FY2014/15 was an 18-month period. This ICR adopts TANESCO’s financial
years for the measurement of the results indicators.
38. M&E utilization. The M&E framework was used in the implementation of the Program and
decisions on the World Bank’s DPO series in an adequate manner. On the Government side, financial
indicators informed Government decisions, including tariff reforms. On the World Bank side, a midterm
review in June 2015 came to the conclusion that—at that time—only three out of the nine triggers were
11 The results indicators included two minor errors—the unit of Results Indicator 5 should have been listed as
US¢/kWh and Results Indicator 6 should have referred to ‘tenders’, rather than ‘bids’—but these were
inconsequential for the quality of the M&E framework.
18
met (#3.2, #3.8 and #3.9), leading to the decision of not proceeding with DPO-3 until after the general
elections in October 2015.
2.4 Expected Next Phase/Follow-up Operation
39. For IDA18 (FY2018–20), the Government and the World Bank are in dialogue on a follow-
up operation to continue support in specific policy areas of the Program, in particular TANESCO’s
financial recovery, complemented by lending in other areas of the Government’s energy sector
development program. As of November 2017, a particular emphasis of the operation will be on
resolving the problem of the legacy payment arrears. Other ongoing and pipeline operations of IDA in the
sector include financing for access, transmission (including interconnections with neighboring countries),
and capacity building.
3. Assessment of Outcomes
3.1 Relevance of Objectives, Design and Implementation
Overall Rating: Substantial
(a) Relevance of Objectives: Substantial
40. The objectives of the crisis-response elements of the Policy and Results Matrix—to restore
TANESCO’s financial viability and reduce fiscal risks—were core to the Government’s and the
World Bank’s strategy in the energy sector. From initial approval through to closing of the series, the
objectives of improving the financial situation of the power sector and phasing out EPPs to reduce the
cost of energy supply (that is, Pillar 1 and parts of Pillar 2) were closely aligned with (a) Tanzania’s
National Strategy for Growth and Poverty Reduction 2025 (Mkakati wa Kukuza Uchumi na Kupunguza
Umaskini Tanzania [MKUKUTA] II), (b) Tanzania’s five-year development plans (FYDP I 2011/12–
2015/16 and FYDP II 2015/16–2020/21), (c) the World Bank’s Country Assistance Strategy (CAS) for
FY2012–FY2015,12
and (d) the World Bank’s energy sector strategy.13
41. Initially, the objectives of the medium- to long-term reform elements of the Policy and
Results Matrix reflected shared priorities between the Government and the World Bank, but their
relevance to the Government was less clear at the time of the ICR. At the time of appraisal, there was
strong Government commitment to the objectives of promoting private sector participation in power
generation (Pillar 2) and strengthening the policy and institutional framework for natural gas utilization
(Pillar 3). These objectives were translated into concrete policy commitments and action plans with the
Electricity Supply Industry Reform Strategy and Roadmap 2014–2025 of 2014 and the National Energy
Policy of 2015. However, reform implementation toward these two objectives slowed down after 2014—
in part due to the IPTL inquiry, skepticism within the Government about the structure of payments to
IPPs and EPPs14
, and preparations for the election of 2015—and has not picked up since then. FYDP II,
prepared by the new Government, strongly emphasizes energy infrastructure development and includes
certain elements of the Electricity Supply Industry Reform Strategy and Roadmap 2014–2025, but puts
12 The objectives are also aligned with the draft CPF for FY2017–FY2022, which is currently under preparation.
13 As captured in the World Bank. 2013. “Toward a Sustainable Energy Future for All: Directions for the World
Bank Group’s Energy Sector.” Washington, DC.
14 Specifically, there is skepticism within the Government about the adequacy of capacity payments to IPPs and
EPPs (fixed annual payments to cover capital costs).
19
less emphasis on the objectives of private sector participation and strengthening the policy and
institutional framework for natural gas. At the time of the ICR, new controversies surrounding the IPTL
power plant and contracts in the mining industry have introduced additional uncertainty about the ways in
which the Government handles contracts with private investors on large investments, including in the
power and natural gas sectors, thus potentially affecting the relevance of the DPO series’ objectives
relating to the private sector.
42. The DPO series’ objectives were aligned with Tanzania’s Nationally Determined
Contribution (NDC) to the Paris Agreement. Tanzania’s NDC, submitted in 2015, builds on the reform
directions of the Program, including in the following two priority mitigation measures specified in the
NDC: (a) investing in energy diversification to ensure overall energy security for economic development
through enhanced availability, affordability, and reliability while contributing toward energy emissions
intensity reduction over time and (b) expanding the use of natural gas for power production, cooking,
transport, and thermal services through improvement of natural gas supply systems throughout the
country.
43. Acceleration of TANESCO’s electrification program became a core objective for the
Government in the power sector from 2013 onwards and would have to be part of any
comprehensive energy sector reform program initiated at the time of the ICR, but was not reflected
in the objectives and design of the evaluated DPO series. To promote electricity access, in early 2013,
the Government reduced connection fees by 30 percent to 90 percent, and instructed TANESCO to
increase its customers base to 1,500,000 by 2015 and target 250,000 new connections per year. While the
Rural Energy Agency (REA) was to finance rural and peri-urban connections; a substantial share of new
connections was to be financed from TANESCO’s own funds. This put pressure on TANESCO’s cash
flow and limited the company’s ability to pay back arrears. However, this scale-up in access investment
was not sufficiently considered in the design of the DPO, especially its measures and targets relating to
arrears.
(b) Relevance of Design: Substantial
44. The choice of a programmatic DPO series and the selection of prior actions were adequate
for the crisis-response elements of the Program. The electricity supply crisis required the Government
to take difficult decisions in a short time and follow up and avoid reversal over a period of several years.
The programmatic DPO was the right instrument to support such reforms.
45. Through careful design of the prior actions, the DPO series enabled the Government to
internalize difficult policy trade-offs. Enough flexibility was built into the design of the Policy and
Results Matrix to allow the Government’s deliberation on important but difficult policy decisions to
follow due course. This was achieved by agreeing with the Government on the objective and desired
outcomes of the prior actions and triggers, while leaving the resolution of policy trade-offs to the
Government. For instance, the Triggers for DPO-2 under Pillar 1 specified the fiscal reform objective (a
cap on transfers to TANESCO), which but left the exact nature of policy actions. During preparation of
DPO-2 the language of Prior Action 2.1 was then adjusted to account for the outcomes of the
Government’s deliberation.
46. However, the DPO series’ approach to bringing arrears under control would be inadequate
at the time of the ICR. The design of the DPO series was based on a careful analysis of TANESCO’s
profitability (net income) under different scenarios. Beyond immediate measures (for example, clearance
of Government arrears to TANESCO), less attention was paid in the analysis and the design of the Policy
and Results Matrix to TANESCO’s cash flow and potential impacts on arrears from reduced Government
transfers, the changes in Government subsidies for connections and connection targets (see above), or
20
policy slippage in the shift toward private sector-owned generation. While there was consistent logic
behind the Program’s strategy to reduce arrears, the DPO series would have benefited from separate
analysis and risk mitigation measures in this regard. More careful analysis of TANESCO’s cash flow
under different scenarios would be needed to inform renewed support by DPs to resolve TANESCO’s
arrears.
47. The medium- to long-term reform elements of the Program would have benefited from less
backloading and a clearer line of sight between prior actions and results indicators. As outlined in
more detail in section 3, Program progress stalled on several fronts after the immediate pressure of the
crisis eased in 2015. This hindered achievement of the Program’s results indicators even where outputs of
the prior actions were achieved.
48. The design of the DPO series could have been more resilient to changes in the Government
priorities if the PDO of the series had solely focused on ends (for example, security of supply or
financial sustainability), rather than means (for example, private sector participation). Reference in
the PDO to private sector participation in particular limited the World Bank’s ability to adjust to changes
in the Government’s priorities after the completion of the second DPO.
(c) Relevance of Implementation: High
49. Implementation arrangements were highly relevant in that they emphasized ongoing
dialogue and the mobilization of technical support, which were critical in view of the complexity of
attempted power sector and natural gas upstream reforms. The ongoing technical assistance
engagement, including several activities for which the World Bank team raised trust fund resources,
helped maintain the technical dialogue despite a transition in Government and several changes in sector
leadership during the implementation of the DPO series.
50. The decision not to proceed with the third operation in the series within the two years after
Board approval of DPO-2 was adequate. The decision reflected an adequate adjustment to changing
context and Government priorities.
51. Close alignment of the DPO series with DPs’ programs was critical for the success achieved
during implementation and parallel technical assistance by the World Bank provided much-needed
capacity-building support to implement the Program. The close alignment with the parallel IMF
program (2012–2014) and the World Bank’s ESCBP were essential for achieving the results of the
Program.
3.2 Achievement of Program Development Objectives
Rating: Modest
52. Achievement of the PDO is assessed as Moderately Unsatisfactory on the basis of the
progress on key indicators. The PDO of the program was to (a) strengthen the country’s ability to bridge
the financial gap in its power sector, (b) reduce the cost of power supply and promote private sector
participation in the power sector, and (c) strengthen the policy and institutional framework for the
management of the country’s natural gas resources. As laid out below in detail and summarized in Table
8, the DPO series performed well on Results Indicators 1, 3, and 5, which relate to TANESCO’s
operating deficit, technical losses, and cost of supply. The DPO series also achieved Results Indicator 7
(documents published on sector reforms). However, the series only made partial progress toward
Indicators 4, 8, and 9, and did not make any progress (or even reversed progress) on Results indicators 2,
6, and 10.
21
22
Table 8. Performance of Program against DPO Target Indicators
# Indicator 2012
(Baseline)
Target
set in
2013
Target
set in
2014
Actual
FY2015/16
Actual
FY2016/17
1 TANESCO operating
deficit/(profit) (US$ million)
240 50 50 92 (82)a
2 TANESCO accounts (trade
and other) payable (T Sh
billion)
707 — 300 1,187 1,331a
3 TANESCO technical and
non-technical losses in
transmission and distribution
21 — 18 18.3 16.4
4 Amount (in MW) of gas-
fired power generation
capacity commissioned
105 >600 400 255 255
5 Average unit cost of power
sales (US$/MWh)
0.18 0.13 0.15 0.12 0.09a
6 Number of bids for gas IPP
power plants launched on a
competitive basis
0 1 1 0 0
7 MEM documents on sector
reforms published for public
knowledge
0 — 2 2 2
8 Volume of gas produced
(mmscfd)
78 >290 250 102b 132
c
9 Amount of onshore proven
natural gas reserves (Tcf)
1.0 3.5 3.5 1.4d 1.2
e
10 Annual monitoring under the
Natural Resource Charter
initiative
No — Yes No No
Note: In 2014, TANESCO’s financial year was changed from January–December (until FY2013) to June–
June. (starting FY2016). The transition fiscal year had 18 months (January 2014 to June 2015). a Based on
unaudited draft financial statements of TANESCO. b year to December 31, 2015;
d year to December 31,
2016; d as of April 2015;
e as of December 31, 2016.
53. An ex post analysis of the results chain of the Program is presented in Table 9. The table
presents, for each pillar, a summary of the implemented prior actions and their immediate outputs; other
factors affecting the results indicators; and the Program’s performance toward the results indicators. The
results chain for each pillar is discussed below in details.
23
Table 9: Efficacy and Causal Chain of the Series Reform Program
Prior Actions and Outputs
(DPO-1 and DPO-2)
Other Factors Affecting Results
Indicators
Performance toward Results
Indicators
Objective 1: Strengthening the country’s ability to bridge the financial gap in its power sector
(Efficacy Rating: Modest)
Two tariff increases in
January 2012 and January
2014
Improvements in bill
collection from
conventional meters and
increased use of prepaid
meters
Reduction of Government
arrears to TANESCO
Improved transparency
and reduction of
Government transfers to
TANESCO
During the Program period, the
Government pursued fiscal
consolidation amid lower-than-
expected domestic revenues and slow
aid disbursements, reducing the fiscal
resources available to support
TANESCO’s investment program
Major exchange rate depreciation
during FY2015 (8 percent) and
FY2016 (24 percent) increased the
value of TANESCO’s arrears to
suppliers (which are mostly
denominated in U.S. dollars) and its
fuel cost
Hydrology improved after the drought
in FY2011–FY2013 and was above
average in FY2015 and FY2017
(FY2016 hydrology was poor again),
leading to decrease in TANESCO’s
generation cost
Access agenda became priority after
2013 for the Government, which
reduced connection fees and instructed
TANESCO to increase its customers
base to 1,500,000 by 2015 and target
250,000 new connections per year, to
be financed mainly from TANESCO’s
internal cash funds, limiting the
company’s ability to pay off arrears
TANESCO turned around
its operating results,
improving its operating
margin from −21% in
FY2012 and −41% in
FY2013 to 13% in FY2015,
−14% in FY2016, and 12%
in FY2017
Arrears continued to
increase: trade and other
payables surged from a total
of T Sh 472 billion (US$298
million at that time) at the
end of FY2011 to T Sh 980
billion (US$565 million) in
FY2015, T Sh 1,187 billion
(US$538 million) in
FY2016, and T Sh 1,331
billion (US$605 million) at
the end of FY2017
Objective 2: Reducing the cost of power supply and promoting private sector participation in the
power sector
(Efficacy Rating: Modest)
New strategic power
sector policy
Road map for structural
reforms
Capacity-building
program
Performance contract
between TANESCO and
the MEM
Regular publication of
performance reports
(including bill collection
and technical/non-
technical losses), financial
audits, and procurement
audits
Parliamentary and presidential
elections held in October 2015 led to
change in Government, reorientation
of priorities and delay in
implementation of sector reform
program under Pillar 2
The inquiry into the sale of IPTL
private power plant in 2014 and the
mining sector inquiry in 2017 both led
to removal or suspension of prolonged
periods of time of MEM officials
including key leadership positions,
causing delays in implementation of
sector reform program under Pillars 2
and 3
Completion of the NNGIP pipeline, a
Technical and non-technical
losses in transmission and
distribution fell from
22.4%in FY2011 and 24.7%
in FY2013 to 16.4% in
FY2017
Installed gas-fired
generation capacity
increased by 150 MW in
2016 and another 425 MW
are under construction, out
of which 30MW are
expected to be
commissioned by the end of
2017
Average cost of supply has
24
Prior Actions and Outputs
(DPO-1 and DPO-2)
Other Factors Affecting Results
Indicators
Performance toward Results
Indicators
core element of the Government
strategy to increase natural gas-fired
power generation, was delayed by
about one year, which delayed the
availability of gas for new power
plants (especially Kinyerezi I) and fuel
switching of existing power plants
Good hydrology in FY2015 and
FY2017 as well as slower-than-
expected demand growth (7.6%
compared to estimated 10% per year])
improved balance between demand
and supply and lessened pressure to
commission new gas power plants
fallen back at pre-crisis
level (US¢9.2 per kWh in
FY2017 compared to
US¢8.4 per kWh in FY2010
and US¢18.4 per kWh in
FY2013)
No new tenders for private
sector-owned generation
capacity were issued
Objective 3: Strengthening the policy and institutional framework for the management of the
country’s natural gas resources
(Efficacy Rating: Modest)
Adoption of Natural Gas
Policy
Launch of a program to
adopt a Tanzania Natural
Resource Charter
Inclusion of natural gas in
the mandate of the
Cabinet committee on
economic affairs and
creation of an
interministerial senior task
force
Clearing of arrears with
gas developers
Verification of the amount
of natural gas reserves
Publication of TPDC’s
audited financial
statements, its latest
procurement audit reports,
and its key performance
indicators
New natural gas
legislation
New Petroleum Policy
and legislation
Global oil and LNG prices declined
after mid-2014, subsequently
remained subdued through the end of
2017, leading to a slowdown in
investor interest in natural gas
exploration and production, especially
offshore
The inquiry into the sale of IPTL
private power plant in 2014 and the
mining sector inquiry in 2017 both led
to removal or suspension of prolonged
periods of time of MEM officials
including key leadership positions,
causing delays in implementation of
sector reform program under Pillars 2
and 3
Volume of gas produced
increased from 78 mmscfd
in 2012 to 102 mmscfd in
2015 and 132 mmscfd in
2016
Amount of onshore proven
natural gas reserves
increased from 1.0 Tcf in
2012 to 1.4 Tcf in 2015 and
1.2 Tcf in 2016
Annual monitoring under
the Natural Resource
Charter initiative was not
implemented
Source: Data from TANESCO, TPDC, and MEM; analysis by World Bank staff.
Objective 1: Strengthen the country’s ability to bridge the financial gap in its power sector
Rating: Modest
54. TANESCO’s profitability recovered from the 2011–2013 crisis, buoyed by tariff increases,
improved hydrology, and the phase-out of EPPs. As a result of the measures taken under the DPO
25
series, average tariff per unit sold increased from T Sh 136 per kWh in FY2011 to T Sh 249 per kWh in
FY2016 and T Sh 238 per kWh in FY2017. GDP growth remained favorable during the same period, at
around 7 percent and inflation declined after to around 5–6 percent in FY2013–FY2016/17, cushioning
the impact of tariff increases and avoiding erosion of tariffs in real terms. In parallel, changes in the fuel
mix (discussed under Pillar 2 below) and the phase-out of 317 MW of expensive EPPs reduced the cost of
power generation.
55. Results Indicator 1 was achieved and TANESCO reached operating cost recovery despite
the phase-out of operating subsidies from the Government and a major depreciation in FY2015/16. As a result, TANESCO’s profitability improved significantly, as shown in Figure 1, turning its operating
deficit of US$239 million in FY2013 into an operating surplus of US$149 million in FY2014/15 and
US$80 million in FY2016/17 (FY2015/16 showed an operating deficit of US$92 million because of poor
hydrology conditions). This was achieved amid a period of fiscal consolidation and reduction of budget
transfers to TANESCO as well as major exchange rate depreciation during FY2015 (8 percent) and
FY2016 (24 percent), which translated into higher fuel cost.
Figure 1. Gross Profit Margin (before Government subsidies and other cost and revenues) and Operating
Profit Margina of TANESCO during FY2008–FY2016/17
Note:
a The operating profit margin is defined here as income before financing cost and taxes; * 18-
month period; ** based on TANESCO’s unaudited draft financial statements.
Source: TANESCO.
56. Government subsidies to cover TANESCO’s operating expenses were phased out as
profitability improved. TANESCO had since the mid-2000s benefited from Government subsidies to
cover its operating expenses. These subsidies escalated during the crisis of 2011–2013, reaching US$139
million in FY2013. As a result of the measures taken under the DPO series, Government transfers (net of
taxes) to cover operating costs of TANESCO became more transparent and decreased from US$117
million in FY2012 and US$139 million in FY2013 to US$3 million in FY2016 and 0 in FY2017. The
Government continues to contribute to financing investment projects in the sector (capital expenses),
consistent with the subsidy policies adopted in the National Energy Policy 2015.
-60.00%
-50.00%
-40.00%
-30.00%
-20.00%
-10.00%
0.00%
10.00%
20.00%
2008 2009 2010 2011 2012 2013 2014/15* 2015/16 2016/17**
TANESCO profitability
Gross profit margin % Operating profit margin (EBIT) %
26
Figure 2. Development of TANESCO’s Trade and Other Payables
Source: World Bank staff estimates based on TANESCO data; 2017 data based on unaudited draft
financial statements.
57. Cash collected per year by TANESCO more than doubled between FY2011 and FY2015/16
as a result of measures taken under the DPO series. Between FY2011 and FY2015/16, revenues per
kWh increased by 82 percent. Average bill collection increased from 82 percent in FY2012 to 101 percent
in FY2016 and 96 percent in FY2017.
Figure 3: Impact of acceleration of electrification program on TANESCO’s cash needs for investment
Source: World Bank staff estimates based on TANESCO data.
58. Arrears continued to climb, however, as measures taken under the DPO series were
insufficient to counterbalance other factors that put pressure on TANESCO’s arrears balance.
These factors included in particular the acceleration of the electrification program, insufficient
Government transfers for investment, and the exchange rate depreciation:
The sharp depreciation of the local currency between 2015 and 2016 raised the nominal
value of TANESCO arrears to suppliers by almost 30 percent in local currency.
-
50
100
150
200
250
300
350
400
450
500
-
200,000
400,000
600,000
800,000
1,000,000
1,200,000
1,400,000
2009 2010 2011 2012 2013 2015 2016 2017
Da
ys o
f co
st o
f sa
les
TzSh
bil
lio
n
TANESCO trade & other payables (FY2015 adjusted for longer period)
Trade and other payables TSh million Creditor days
-
50,000
100,000
150,000
200,000
250,000
300,000
350,000
-
100,000
200,000
300,000
400,000
500,000
600,000
2008 2009 2010 2011 2012 2013 2014/15* 2015/16 TAN
ESCO
's s
elf-
finan
ced
inve
stm
ents
(fin
ance
d
fro
m c
as
h f
low
an
d b
orr
ow
ing
) in
T S
h m
illio
n
No
. of a
nn
ua
l co
nn
ect
ion
s
* 18-month period
TANESCO's self-financed investments compared to growth in new connections
27
Government support for TANESCO’s investment program fell short of cash needs as the
Government underwent a period of expenditure consolidation in 2014/15 and 2015/16 to
maintain its fiscal deficit target.
Except for two small commercial loans in the total amount of around T Sh 60 billion,
TANESCO’s access to commercial borrowing to repay arrears was restricted by the
Government after FY2014/15.
After the 2015 election, the new Government put a strong emphasis on a rigorous
verification process before clearing outstanding payments/arrears to the private sector,
which slowed down payment of outstanding arrears across the public sector.
At the same time, TANESCO’s cash used for investment increased sharply after the
Government in January 2013 reduced the cost of new connections by 29 percent to 75
percent and instructed TANESCO to increase its customers base to 1,500,000 by 2015 and
target 250,000 new connections per year (see Figure 3).
59. Results indicator 2 (trade and other payables) was therefore missed by a wide margin,
despite the significant increase in cash collected. As shown in Figure 2, trade and other payables surged
from a total of T Sh 472 billion (US$298 million) at the end of FY2011 to T Sh 980 billion (US$565
million) in FY2015, T Sh 1,187 billion (US$538 million) in FY2016, and T Sh 1,331 billion (US$605
million) at the end of FY2017. If measured in creditor days, trade and other payables fell in FY2012 and
FY2013 but increased thereafter. That is, while operational performance of TANESCO significantly
improved, the burden of the historical payment arrears has gotten worse. Most of these payables are due
to the electricity and fuel suppliers and some are interest carrying. Resolving them is of critical
importance for TANESCO’s financial sustainability, supply security, and investment environment.
Objective 2: Reduce the cost of power supply and promote private sector participation in the power
sector
Rating: Modest
60. Measures to improve transparency and accountability on TANESCO's operational
performance contributed to reducing system losses and improving bill collection. Technical and non-
technical losses in transmission and distribution fell from 22.4 percent in FY2011 and 24.7 percent in
FY2013 to 16.4 percent in FY2017 (compared to a target of 18 percent under Results Indicator 3, see
Figure 4). Average bill collection increased from 82 percent in FY2012 to 101 percent15
in FY2016 and
96 percent in FY2017. Prior actions under the DPO series contributed to this improvement, including the
performance contract between TANESCO and the MEM and the publication of performance reports,
financial audits, and procurement audits, which enhanced transparency and accountability at TANESCO.
15 The collection rate exceeded 100 percent because the Government made two large, one-off payments to
TANESCO to pay off outstanding arrears, and as a result the total cash collected during the year exceeded the total
amount billed.
28
Figure 4. Decline in Technical and Non-Technical Losses during FY2009–FY2016/17
Note: * 18-month period; ** based on TANESCO’s management accounts.
Source: TANESCO.
61. Newly commissioned gas-fired generation capacity improved supply security and helped
phase out oil-fired generation and EPPs. The target of Results Indicator 4, the commissioning of 400
MW of new gas-fired generation capacity, was not met but significant progress has been made as of the
time of the ICR. The Kinyerezi I gas power plant (150 MW) was fully commissioned in 2016 and the first
unit of Kinyerezi II is expected to be commissioned by the end of 2017. As a result, the share of liquid
fuels (diesel and heavy fuel oil) in the generation mix fell from 18 percent in FY2013 to 4 percent in
FY2017 (see Figure 5), leading to lower costs and lower per unit emissions. Together with improved
hydrology and lower-than-expected demand growth (see below) allowed TANESCO to phase-out 317
MW of oil-fired EPPs.
Figure 5. Tanzania’s Power Generation Mix
Source: TANESCO.
62. Delays in the commissioning of gas-fired generation capacity (Results Indicator 4) can be
explained by infrastructure bottlenecks as well as a lower-than-anticipated need for additional
capacity. Completion of the NNGIP pipeline, a core element of the Government strategy to increase
natural gas-fired power generation, was delayed by about one year, which delayed the availability of gas
for new power plants (especially Kinyerezi I) and fuel switching of existing power plants. At the same
time, good hydrology in FY2015 and FY2017 as well as slower-than-expected demand growth (7.6
0%
5%
10%
15%
20%
25%
30%
2009 2010 2011 2012 2013 2014/15* 2015/16 2016/17**
Total transmission & distribution losses (%)
2,502 2,635 2,626 2,687 1,977 2,040 1,948
2,587
1,321 2,025 2,428
1,402 1,572 1,982
2,356
2,568 2,802 3,172 2,723
1,273
3,664
4,178
-
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
Jan-Dec Jan-Dec Jan-Dec Jan-Dec Jan-Dec Jan-Dec Jan-Dec Jan-Dec Jan-Jun Jul-Jun Jul-Jun
2007 2008 2009 2010 2011 2012 2013 2014 2015* 2015/16 2016/17
GW
h
Power generation by source (2009-2017)
Hydro Gas Diesel HFO Biomass Imports
29
percent compared to an estimated 10 percent per year) improved balance between demand and supply and
lessened pressure to commission new gas power plants.
Figure 6. Revenues and Cost of Supply of TANESCO FY2009–FY2016/17
Note: * 18-month period; ** based on TANESCO’s unaudited draft financial statements.
Source: World Bank staff estimates based on TANESCO data.
63. The switch from oil to gas-fired generation and the phaseout of EPPs contributed to a sharp
reduction in the cost of supply, leading to overachievement on Results Indicator 5. The average cost
of supply (Results Indicator 5; see Figure 6) fell by half and returned to pre-crisis levels (US¢9.2 per kWh
in FY2017, which compares to US¢8.4 per kWh in FY2010 and US¢18.4 per kWh in FY2013). The main
factors were better hydrology (about one-third of the reduction) and the replacement of oil-fired
generation and EPPs with natural gas (two-thirds of the reduction).
64. Implementation of the reform policy and road map developed under the Program stalled
soon after they were published, and the private sector participation agenda did not advance under
the DPO series. Results Indicator 7 was met when the MEM published a road map for structural reforms
and a new strategic power sector policy.16
Both documents strongly emphasized the need to attract private
sector investment into the sector. To facilitate implementation, the Government initiated a capacity-
building program. However, the inquiry into the sale of the IPTL private power plant in 2014 led to
removal or suspension for prolonged periods of MEM officials including key leadership positions, putting
reform implementation on hold. The preparation for the parliamentary and presidential elections held in
October 2015 further stalled implementation and under the new Government the reform agenda laid out in
2014–2015 did not pick up significant momentum again, despite the issuance in October 2016 of “The
Electricity (Market Re-organization and Promotion of Competition) Regulations, 2016” 2016, pursuant to
the Electricity Act of 2008. The regulations stipulated that the power sector would be unbundled along the
functional lines (generation, transmission, distribution), market liberalized, and procurement of generation
projects competitively done. The regulations also established an Electricity Infrastructure Procurement
Committee. The FYDP-II, too, calls for a more significant role for the private sector in generation and
emphasizes the need for independence in decision-making in determining power purchasing tariffs,
management of the power master plan, and power transmission. However, the October 2016 regulations
are yet to be implemented, the Government however retains strong influence over decision-making in the
sector, and its medium- to long-term vision for sector reforms remains to be articulated. Results
16 These documents are the (a) the Electricity Supply Industry Reform Strategy and Roadmap 2014–2025 (2014) and
(b) the National Energy Policy (2015).
-
0.05
0.10
0.15
0.20
2009 2010 2011 2012 2013 2014/15* 2015/16 2016/17**
US$
/kW
h
Revenues and cost of supply (per kWh)
Own generation US$/kWh Transmission US$/kWhPurchased electricity US$/kWh Distribution expenses US$/kWhDepreciation US$/kWh Revenues from electricity sales US$/kWh
30
Indicator 6, which aimed to capture the first competitive auction for private sector-owned generation
capacity, was not met as the Government is yet to proceed with such a tender.
Objective 3: Strengthen the policy and institutional framework for the management of the
country’s natural gas resources
Rating: Modest
65. Under Pillar 3 of the Program, the Government established a policy framework for the
upstream natural gas sector and laid the groundwork for subsequent legislative reforms. Under
DPO-1 and DPO-2, the Government (a) approved a Natural Gas Policy and a Petroleum Policy in 2014;
(b) cleared arrears with developers; (c) initiated an independent verification of Tanzania’s natural gas
reserves; (d) took measures to make TPDC more transparent and improve accountability, and (e)
established a top-level institutional mechanism to enhance policy coordination by mandating the Cabinet
committee on economic affairs to handle the natural gas agenda and creating an interministerial senior
task force on natural gas. These measures—in particular the two policies and the coordination
mechanism—laid the foundations for subsequent legislative reforms (see below). The Government also
initiated a benchmarking exercise of the natural gas sector in close partnership with the Natural Resource
Charter.
66. The Government maintained the reform momentum in the natural gas sector after approval
of DPO-2 and implemented legislation that reformed sector governance. The Parliament passed the
Petroleum Act of 2015, the Oil & Gas Revenue Management Act of 2015, and the Tanzania Extractive
Industries Transparency Initiative Act of 2015. Taken together, these measures established a unified legal
framework for investment in upstream natural gas in Tanzania, by (a) tasking two agencies to regulate the
upstream and midstream,/downstream segments (the Petroleum Upstream Regulatory Agency and the
Energy and Water Utilities Regulatory Agency); (b) mandating the regulatory agencies to establish and
maintain a transparent licensing and contracting framework; (c) tasking the Government to establish a
transparent fiscal regime; and (d) mandating the establishment of an Oil and Gas Fund for maintaining
fiscal and macroeconomic stability, enhancing social and economic development, and safeguarding
resources for future generations. However, the legal framework suffered from a series of conceptual
contradictions—on the one hand introducing a regulatory structure and regulatory procedures favoring
free market principles, transparency and competition, while on the other opening space for Government
interference in due process—and introduced elements in its institutional framework that may discourage
prospective investors. Further, follow-up on the legislative reforms has been slower than anticipated, in
part due to a slump in global energy prices and the resulting downturn in global capital investment in the
oil and gas industry. The Natural Resource Charter initiative has not yet been implemented (Results
Indicator 10).
67. Investments in gas production by established private sector partners increased but fell short
of expected levels. The gas-to-power investment program is a core in the FYDP II and in the Electricity
Supply Industry Reform Strategy and Roadmap, which establish ambitious targets for the expansion of
power generation capacity. During the Program period, the volume of gas produced increased from 78
mmscfd in 2012 to 102 mmscfd in 2015 and 132 mmscfd in 2016 (Results Indicator 8). Information
provided by the private sector suggests that these numbers underestimate investment as additional
production capacity is ready for ramp-up (possibly up to 200 mmscfd). However, even when accounting
for these uncounted investments, private sector interest fell short of expected levels, and may lead to
shortages in gas supply if gas-fired generation capacity is scaled up rapidly (current Government plans
calling for the trebling of gas-based generation capacity by FY2020/21 will require an equally ambitious
expansion of natural gas production to over 300 mmscfd).
31
68. Investments in new exploration also fell short of expectations, at least partially because of
the decline in global energy prices. Global oil and LNG prices declined after mid-2014 and
subsequently remained subdued through the end of 2017, leading to a slowdown in investor interest in
natural gas exploration. As a result, the amount of onshore proven natural gas reserves increased only
slightly, from 1.0 Tcf in 2012 to 1.4 Tcf in 2015 and 1.2 Tcf in 2016 (Results Indicator 9).17
In
consequence, the development of Tanzania’s offshore resources is also unlikely to proceed in the short to
medium term.
3.3 Justification of Overall Outcome Rating
Rating: Moderately Unsatisfactory
69. The DPO series is rated Moderately Unsatisfactory because, despite significant
achievements in the crisis-response elements of the Policy and Results Matrix, the Program did not
make sufficient progress towards its objectives (efficacy). The relevance of objectives was Substantial
but efficacy was Modest (4 out of 10 results indicators were achieved). The outcome rating compares to a
rating of Moderately Satisfactory in the latest ISR for ‘Progress toward achievement of PDO’. The
rating’s justification is that measures taken under the DPO series:
Enabled the Program to achieve 4 out of 10 indicators (and overachieve on two of them),
even though the results indicators were designed for a series of three operations but only
two out of three planned DPOs were approved;
Led to major rebalancing of cost and revenues in the power sector, bringing TANESCO’s
profitability back to pre-crisis levels (Results Indicators 1 and 5);
Contributed to significant improvements in TANESCO’s operational performance,
including a one-fourth reduction in technical and non-technical losses and achievement of
good practice benchmark levels of bill collection;
Scaled up the power-to-gas supply chain in Tanzania and established a legislative
framework for upstream natural gas development, but did not achieve the envisioned
medium-term supply security of natural gas and gas-fired power;
Laid the conceptual groundwork for a power sector reform policy and road map, but could
not facilitate significant progress toward reform implementation.
3.4 Overarching Themes, Other Outcomes and Impacts
(a) Poverty Impacts, Gender Aspects, and Social Development
70. Poverty impacts of the electricity tariff reforms under the Program were mitigated through
cross-subsidies between consumer groups. As shown in the tariff schedule in annex 6, electricity tariffs
in Tanzania are differentiated by consumer groups. Small household consumers (category D1; defined as
average consumption below 75 kWh per month) have been and continue to be subsidized. As of FY2017,
the tariff applied to this consumer group is T Sh 100 per kWh, compared to a general use tariff of T Sh
17 The Government statistic of 57 Tcf of natural gas reserves corresponds to a gross approximation of ‘gas in place’,
which has not been independently assessed and does not correspond to the internationally recognized meaning of
‘reserves’.
32
292 per kWh (category T1). In relative terms, tariffs for D1 increased by 67 percent between FY2012–
2017 (28 percent in real terms), the highest value among the five categories, but in absolute terms the
increase of D1 tariffs (T Sh 40 per kWh) was the second lowest among the categories (see annex 6). Thus,
cross-subsidies mitigated the poverty impact of the reforms under the DPO series.
71. Growth in real household income from strong GDP growth and contained inflation also
mitigated the poverty impacts of the tariff reforms under the DPO series. GDP growth remained
favorable at around 7 percent throughout the implementation period. Inflation declined after FY2012 and
remained around 5–6 percent in FY2013–FY2016/17.
72. A review of household spending on electricity tariffs in over 20 Sub-Saharan African
countries found that, after the tariff reforms, the share of household spending on electricity in
Tanzania was still not above average in the region (1.9–5.8 percent among the poor and 3.0–3.3
percent among all households).18
This is in line with the finding that the tariff reforms under the Program
did not have significant negative impacts on poverty in Tanzania.
73. The tariff increases enabled TANESCO to significantly expand its electrification program
from 2013 onward, with the associated positive social and gender impacts. Providing households,
social institutions, and enterprises with new energy access and improved energy services has the potential
to promote gender equality, create employment and business opportunities, and contribute to a broad
range of human development outcomes. As shown in Figure 7, TANESCO and REA accelerated the
implementation of Tanzania’s electrification program. Between them, the two institutions more than
tripled the number of new connections completed per year between FY2012 and FY2015/16.
TANESCO’s contribution to this expansion was largely financed from its own resources and thus
benefited significantly from increased revenues due to the tariff reforms under the Program.
Figure 7. New Electricity Connections Completed by TANESCO and REA in FY2004–FY2016/17
Source: TANESCO.
74. Reduced budget transfers to the power sector contributed to fiscal consolidation and
provided fiscal space for spending on other priorities, including spending on social development.
18 Kojima, M., X. Zhou, J. J. Han, J. de Wit, R. Bacon, and C. Trimble. 2016. “Who Uses Electricity in Sub-Saharan
Africa?” World Bank Policy Research Working Paper 7889. World Bank, Washington, DC.
http://documents.worldbank.org/curated/en/967821470756082684/pdf/WPS7789.pdf.
-
50,000
100,000
150,000
200,000
250,000
300,000
350,000
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2015* 2016 2017
New connections per year (incl. REA)
33
During the Program period, fiscal consolidation remained a major challenge for the Government due to
lower-than-expected domestic revenue collection, diminishing aid disbursements, and higher investment
in infrastructure projects. As a result of the Program, Government transfers to the power sector (net of
taxes) decreased from US$117 million in FY2012 and US$139 million in FY2013 to US$3 million in
FY2016 and 0 in FY2017. This provided fiscal space and reduced the pressure on fiscal consolidation in
other sectors.
(b) Institutional Change/Strengthening
75. TANESCO and the MEM took several measures under the Program to strengthen
TANESCO’s governance and operational capacity, but the long-term impact of these measures has
been marginal. The key institutional change brought in by the DPO program was the signing of a
performance contract for FY2013 between TANESCO and the MEM, which included measurable KPIs
for TANESCO. However, follow-up on areas of underperformance has been limited. TANESCO’s
institutional independence and its accountability for performance have not changed significantly since the
beginning of the Program. Other governance measures included the publication of financial reports and
performance audits, but publication of these documents has since been irregular and the scope of
reporting could be improved.
76. The Government has put in place a comprehensive reform road map for institutional
restructuring and strengthening in the power sector, but implementation of the road map has been
limited. Under the Program, the Government adopted the recommendations of the Presidential Big
Results Now Initiative to develop a road map for structural reforms of the energy sector, developed the
Electricity Supply Industry Reform Strategy and Roadmap 2014–2025 in 2014, and established a
Ministry Delivery Unit within the MEM to oversee the implementation of the road map. However,
implementation of the roadmap has been limited19
.
77. Significant institutional reforms in the natural gas sector were initiated with the adoption of
new gas sector legislation in 2015. The legislative reforms under the Program established the basic
elements of its legal and institutional framework for the proper development of its natural gas sector.
(c) Other Unintended Outcomes and Impacts (positive or negative)
78. Implementation of the Program halted the increase in specific greenhouse gas (GHG)
emissions of Tanzania’s power sector. Per unit GHG emissions in the sector increased by 78 percent,
from 228 gCO2/kWh to 408 gCO2/kWh, between 2008 and 2013. This trend was due to increased reliance
on oil-fired generation while hydropower output remained stable and was expected to continue in the
absence of larger utilization of natural gas. By promoting hydropower and natural gas over oil-fired
generation, the Program reversed this trend and specific emissions fell to an average of 361 gCO2/kWh
during FY2014–FY2016/2017.
19 Reforms envisioned in the roadmap to be completed by the end of FY2017/18 included the unbundling of
generation from transmission and distribution; direct trading between generators and bulk off-takers; the creation of
a designated independent market operator; and a mechanism and rules for the operation of a retail market for
electricity by the regulator. None of these reforms were under way at the time of the ICR, and whether or not they
will be implemented in the future was uncertain.
34
Figure 8. Impact of the Program on GHG Emissions in the Sector
Source: World Bank staff estimates based on TANESCO data.
79. The ICR identified no other unintended outcomes or impacts.
3.5 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops
80. No beneficiary survey or stakeholder workshop was held.
4. Assessment of Risk to Development Outcome
Overall Rating: High
81. The risk to the development outcome is assessed as High, for six main reasons: (a) the tight
balance between supply and demand in the power sector; (b) continued pressure on TANESCO’s cash
flow; (c) changes in the priorities and reform direction of the new Government in the power sector; (d)
recent reforms in the upstream natural gas policy framework and potential impacts on the investment
climate; (e) there is a risk that the Government is learning the wrong lessons from private sector
investments in the power sector; and (f) macroeconomic risks, including exchange rate risks, constraints
on fiscal space limiting the Government’s ability to contribute to TANESCO’s investment program and
arrears repayment, and global energy price volatility.
82. First, the supply-demand balance in Tanzania’s power sector is still precarious and
TANESCO may fall back into financial difficulties—e.g., in case of a drought or power plant failure
before additional gas-fired generation capacity comes online and the interconnection to Ethiopia is
commissioned. Tanzania has experienced periodic financial crises in the power sector (last in 2011–
2013), largely due to a lack of sufficient supply capacity to withstand droughts. As of end-2017, the
supply-demand balance remains tight, even at the current level of connectivity, as evidenced by the major
10-hour power outage in late October 2017. Two major gas power plant investments (Kinyerezi I
Extension and Kinyerezi II) are expected to be completed in 2018/19, adding 425 MW in total20
. In
addition, a new grid interconnection with Kenya/Ethiopia is expected to be completed in phases starting
in 2019, eventually allowing up to 400 MW of imports. However, utilizing the new gas plants will require
20 Kinyerezi II (240 MW) will be gradually commissioned by August 2018. The Kinyerezi I Extension (185 MW) is
expected to be fully operational by the beginning of 2019.
-
100
200
300
400
500
Jan-Dec Jan-Dec Jan-Dec Jan-Dec Jan-Dec Jan-Dec Jan-Dec Jan-Jun Jul-Jun Jul-Jun
2008 2009 2010 2011 2012 2013 2014 2015 2015/16 2016/17
gCO
2/k
Wh
Specific GHG emissions of the power sector in Tanzania FY2008-FY2016/2017
35
securing gas supplies, which are at risk of falling short of quantities needed for the new gas-fired
generation plants; and until the investments are completed, the system remains vulnerable to outages in
case of failures of individual power plants. Improved system expansion planning and execution, including
supply diversification by utilizing Tanzania’s solar and wind resources, will be important to further
reduce vulnerability to droughts and other supply side risks.
83. Second, plans for major public investment in the power sector will continue to put pressure
on cash flow, limiting TANESCO’s ability to repay its arrears. The 2016 PSMP update implies major
public investment in generation and transmission. The same is true for the Government’s access targets
(connecting 50 percent of the population by 2020 and over 75 percent by 2030, up from 33 percent in
2016), which imply a major scale-up of investment in new connections. World Bank estimates suggest
that achieving the targets would require 600,000–800,000 new household connections per year, up from
around 250,000 per year in recent years. TANESCO is already at the limits of its financing capacity and
access to commercial borrowing is restricted. Pressure on TANESCO’s liquidity is therefore expected to
continue.
84. Third, the Government has at least partially shifted direction in the reform program in the
power sector, potentially reversing or stalling some of the outputs and outcomes under the
Program. The new Government has charted out a new course of action with regard to key economic
policy directions, but its priorities in the energy sector are still being worked out. An ongoing consulting
assignment on the financial situation of TANESCO is an illustration of the Government’s intent to
understand the prevailing situation before embarking on a new reform program. Whether or not the
Government intends to continue implementation of the reform program laid out under Pillar 2—including
the reform road map laid out in the documents that contributed to Results Indicator 7—is currently
unclear. Nonetheless, it is clear that the current Government is putting less emphasis on private sector-
funded infrastructure development in the energy sector than the Program laid out under this DPO series,
meaning that some of the outputs and outcomes of the Program may be reversed or stalled in the future.
The Government also retains strong direct influence over decision-making in the sector and has weakened
EWURA’s ability to make independent regulatory decisions.21
85. Fourth, there is a risk that the Government is learning the wrong lessons from past private
sector investments in the power sector. While the Government and TANESCO implemented the initial
phase of the 2013 Policy for Private Sector Participation in Power Generation through Competitive
Processes by launching PPP capacity-building programs, the DPO series was not able to demonstrate the
benefits of well-executed private sector investments in the power sector. Therefore, a small number of
controversial and poorly executed contracts continue to cast a shadow on the outlook for privately-owned
generation in Tanzania in general. In the absence of a clearly articulated rationale and shared vision
among sector stakeholders, the Government’s policy toward private sector participation in future
generation projects is unclear. The risk to the development outcome is that the Government concludes
from these poorly executed investments that private sector investments are not worth pursuing at all,
rather than that private sector investments have to be done right.
86. Fifth, recent amendments to the Petroleum Act in mid-2017, passed in response to the
outcomes of a parliamentary inquiry into mining contracts with the private sector, may affect the
natural gas investment framework. Shortly before the ICR was prepared, in July 2017, the Government
amended the Petroleum Act of 2015. Potential impacts of the reforms include (a) negatively affecting the
21 In December 2016, the Minister of Energy and Minerals suspended EWURA tariff order. In June 2017, the Prime
Minister suspended the Director General of EWURA after EWURA initiated the license renewal process for IPTL.
EWURA then declined to renew the operating license for IPTL in August 2017.
36
stability of existing Production Sharing Agreements; and (b) clouding the prospects for future private
investment in the sector. Therefore, although the impact of the amendments on the attractiveness of
investment in natural gas exploration and production was not fully clear at the time of the ICR, the
amendments increased the risks to the development outcome.
87. Sixth, while the macroeconomic outlook is relatively stable, macroeconomic risks to the
development outcome include TANESCO’s exposure to exchange rate risks; constrained fiscal
space limiting the Government’s ability to adequately fund TANESCO’s investment program or
contribute to repayment of arrears; and global energy price volatility. Tanzania’s economy remains
one of the highest performers in the region, exceeded in 2016 only by Côte D’Ivoire and Ethiopia. Real
GDP expanded at a slower rate of 6.8 percent in the first half of 2017 compared to 7.7 percent over the
same period in 2016. The inflation rate has remained low and stable and reserves are at a healthy level.
The outlook remains favorable with the main downside risks of a domestic nature and largely under
Government control. However, TANESCO’s arrears remain exposed to exchange rate risks as much of it
is denominated in US$. Furthermore, in view of continued fiscal constraints for the Central Government,
such as persistently high arrears22
and underexecution of the development budget, it is unclear to what
extent the Government can contribute to funding TANESCO’s investment program or the repayment of
arrears. Lastly, macroeconomic risks to the sustainability to the development outcome also include global
energy price volatility, especially the potential negative impact of sustained low energy prices on
investments in the development of Tanzania’s natural gas resources.
5. Assessment of Bank and Borrower Performance
5.1 Bank Performance
(a) Bank Performance in Ensuring Quality at Entry
Rating: Moderately Satisfactory
88. World Bank performance in ensuring quality at entry is rated Moderately Satisfactory for the
following reasons:
The World Bank ensured that the DPO series was part of a concerted donor effort to support
the Government’s response to the fiscal and macroeconomic implications of the electricity
supply crisis during 2012–2014.
The objectives of the crisis-response elements of the Policy and Results Matrix—to restore
TANESCO’s financial viability and reduce fiscal risks—were core to the Government’s and
the World Bank’s strategy in the energy sector.
The crisis-response elements of the Policy and Results Matrix was informed by recent
analytical work and global experience and had a clear line of sight between prior actions and
results indicators.
Enough flexibility was built into the design of the Policy and Results Matrix to allow the
Government’s deliberation on important but difficult policy decisions to follow due course.
For instance, the Triggers for DPO-2 under Pillar 1 specified the fiscal reform objective (a
22 Arrears to contractors, suppliers, and pension funds by the Government reached over 6 percent of GDP at the end
of FY2015/16.
37
cap on transfers to TANESCO), but left the exact nature of policy actions open. During
preparation of DPO-2 the language of Prior Action 2.1 was then adjusted to account for the
outcomes of the Government’s deliberation.
The medium- to long-term reform elements of the Policy and Results Matrix were risky
because they were backloaded; heavy on commitments and light on implementation; and
missed a clear line of sight between prior actions and results indicators. Some of these risks
were informed risks and thus do not represent shortcomings in the performance of the World
Bank, but important governance risks were missed; the political economy of power sector
reform in particular was poorly reflected in the design of the medium- to long-term reform
measures in the Program.
(b) Quality of Supervision
Rating: Moderately Satisfactory
89. World Bank performance in ensuring quality at supervision is rated Moderately Satisfactory for
the following reasons.
Continued close alignment of the DPO series with DPs’ programs was critical for the
success achieved during implementation.
Throughout the implementation of the Program, the World Bank provided close
implementation support by an experienced core team as part of regular supervision missions
and additional support missions as needed.
The parallel technical assistance under the World Bank’s ESCBP provided much-needed
capacity-building support to implement the Program.
The World Bank continuously monitored progress against the main financial and
performance indicators of the power sector and the M&E framework was used in the
implementation of the Program and decisions on the World Bank’s DPO series in an
adequate manner.
The decision not to proceed with the third operation in the series within the two years after
Board approval of DPO-2 reflected an adequate adjustment to changing context and
Government priorities and was based on in-depth dialogue with the Government during
three missions in September and then in November and December 2016.
However, the World Bank’s implementation support is considered to have had moderate
shortcomings, because it did not reflect a complete understanding of the political economy
of power sector reform in Tanzania and the World Bank team was not always able to
respond to implementation challenges on time. For instance:
i. The major change in the Government’s policy for connection charges in early
2013 and its impact on TANESCO’s finances were not recognized in the
preparation of DPO-2 and thus not reflected in the design of the operation.
ii. The fact that arrears continued to mount in FY2014/15 despite positive income
could have led the Bank team to adjust course in the reform dialogue.
38
iii. In hindsight, more could have been done to disseminate global best practices in
structuring and executing private-sector participation in the power sector, and the
potential benefits for Tanzania’s development.
iv. The DPO series’ results framework was not adjusted when it became clear that
the third DPO would not be not approved within 24 months.
(c) Justification of Rating for Overall Bank Performance
Rating: Moderately Satisfactory
90. This rating combines the ratings for Quality at Entry and Quality of Supervision.
5.2 Borrower Performance
Rating: Moderately Unsatisfactory
91. While the MOF was the official implementing agency of DPO series, the ICR considers the MOF
and the MEM as the key implementers of the program, as both represented the Government in the
implementation of the Program. Government performance is rated Moderately Unsatisfactory because of
significant shortcomings despite strong performance in some areas of the Policy and Results Matrix:
Government commitment to and leadership in the crisis-response elements of the Policy and
Results Matrix was strong and the Government successfully managed the fiscal impacts of
the power sector crisis in 2011–2013. Service and performance improvements facilitated
under the leadership of the MEM contributed to the social acceptability of tariff reforms.
The MOF, in coordination with the MEM, TANESCO, and EWURA took ownership in
selecting and implementing the prior actions and the borrower’ commitment was reflected in
the timely approval of DPO-1 and DPO-2.
The Government established a policy framework for upstream natural gas development,
maintained momentum after approval of DPO-2 and adopted legislation that reformed
natural gas sector governance.
Government commitment to the medium- to long-term power sector reforms—including
private sector participation, structural reforms of the power sector, good governance and
financial sustainability of TANESCO and an independent regulatory function—in the Policy
and Results Matrix was less clear from the start.
The Government’s reform efforts in the energy sector and engagement with the World Bank
lost momentum when the IPTL controversy led to removal or suspension of prolonged
periods of time of MEM officials including key leadership positions. Despite progress in
some areas, reform efforts are yet to regain momentum, causing major delays in
implementation of the Program. DPO-3 was cancelled as a result.
Insufficient Government funding for TANESCO’s investment program after approval of
DPO-2 led to a cash shortfall at TANESCO and contributed to the buildup of arrears. Under
DPO-2, the Government and TANESCO committed to finance any remaining financing gap
in the power sector (after tariff reforms) from Government subsidies and commercial
39
borrowing. However, actual Government measures fell short of this commitment, especially
with regard to cash needs for investment.
6. Lessons Learned
Rating: Moderately Unsatisfactory
92. A sectoral DPO series can be an effective crisis response when it is closely aligned with an
IMF program, complements fiscal consolidation with service improvements, and has a clear line of
sight between prior actions and expected outcomes. The Power and Gas Sector DPO series was
successful in the first two years and in (most of) the crisis-response elements relating to financial
sustainability and fiscal risks of the power sector, for three main reasons. First, close coordination and
parallel support by several DPs, especially the IMF, was critical for sustained implementation of these
difficult reforms. Second, the major tariff reforms between FY2011 and FY2014/15 which, cumulatively,
more than doubled tariffs for some categories, were acceptable to consumers only because they were
accompanied by significant reductions in outages and improvements in quality of service. This further
underpins recent global experience, which suggests that consumers are willing to pay more if they in turn
receive better service. Third, the crisis-response elements of the Policy and Results Matrix—especially
measures relating to TANESCO’s revenues and costs such as tariff reforms and the phase-out of EPPs—
had a clear line of sight between prior actions and expected outcomes.
93. Improving liquidity and profitability of utilities are related objectives but require separate
analyses and risk mitigation measures. The DPO series implicitly assumed that achieving profitability
and reducing arrears—the two subobjectives under Pillar 1—could be achieved largely through the same
measures (the term ‘financing gap’ in the PDO was meant to capture both cash needs and net income).
However, trends in profitability and arrears diverged widely during the Program period because
TANESCO’s investment program was inadequately funded, underscoring the need for separate analyses
and risk mitigation measures in the design of operations targeting both.
94. Engaging in the natural gas agenda was a risk worth taking, even if outcomes as measured
by the results indicators were only Modest. The Bank used this DPO series as an opportunity to
establish an engagement with the Government in the natural gas sector, which was and remains critical
for the development of Tanzania’s energy sector. This decision enabled the DPO series to support a
comprehensive reform program that tackled the whole energy supply chain. While the reform momentum
in the natural gas sector slowed down when global energy prices declined in 2015, significant progress
was made towards a modern upstream natural gas policy framework that would not have been possible
without the DPO series. Thus, despite weak performance on indicators under Pillar 3, engagement in the
gas sector reform proved to be risk worth taking.
95. World Bank-supported power sector reform programs in Sub-Saharan Africa need to take
into account the full breadth of utility investment obligations—including investments to deliver on
the electricity access agenda—and their impacts on sector fundamentals. The Government’s efforts
to expand electricity access were recognized in the design of the Program, but not fully integrated into the
financial modeling that underpinned the Program’s Results Framework. The impact of the access agenda
on sector financials was therefore not anticipated, even in DPO-2, which was approved after the
Government significantly expanded financial obligations for TANESCO in financing new connections
(because of the delays in TANESCO’s financial reporting, the full impact of these reforms was not yet
visible in the performance indicators by the time of appraisal of DPO-2). As a result, TANESCO’s arrears
continued to rise despite significant improvement and, in fact, overachievement, on TANESCO’s income
statement (see section 3.2 for more details). In view of the prominence of the access agenda in the
Sustainable Development Goals and the sector development programs of Sub-Saharan African
40
governments, the lesson from this DPO series is that future energy DPOs in Sub-Saharan Africa—
including in Tanzania—need to take access investments and related policy frameworks more explicitly
into account into the design of the operation.
96. Where the promotion of private sector participation is part of a World Bank-supported
reform program, program design needs to be informed by a political economy analysis and global
best-practices as well as associated benefits need to be clearly articulated. The series was
underpinned by comprehensive economic and financial analysis and informed by the World Bank’s
global experience with energy sector reform. However, no systematic stakeholder mapping and political
economy analysis were undertaken. Therefore, the political economy risks of power sector reform in
Tanzania were insufficiently reflected in the design and implementation of the program, which
contributed to the underperformance of the DPO series (see sections 2 and 3 for details). For instance, in
hindsight, the DPO series’ expectations about the pace and momentum of reforms (beyond immediate
crisis-response measures) appear overambitious, and the results framework should have been adjusted
once it became clear that DPO-3 would not be approved. Further, more could have been done to articulate
and share with the Government global best practices in structuring and executing private-sector
participation in the power sector (e.g., best practice in risk sharing in PPP models), and the potential
benefits for Tanzania’s development. In the absence of a clearly articulated rationale and shared vision
among sector stakeholders, a small number of controversial and poorly executed contracts cast a shadow
on the outlook for PPPs in Tanzania’s power sector in general. This lesson learned is in line with
emerging findings from a currently ongoing review of the global power sector reform agenda by the
World Bank’s Energy and Extractives Global Practice (‘Rethinking Power Sector Reform’; P157376),
which will lay out an agenda for more closely integrating political economy considerations into power
sector reform programs.
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners
(a) Borrower/Implementing agencies
97. Not applicable.
(b) Cofinanciers
98. Not applicable.
(c) Other partners and stakeholders (for example, NGOs/private sector/civil society)
99. Not applicable.
41
Annex 1. Bank Lending and Implementation Support/Supervision Processes
(a) Task Team Members
P143645 – TZ First Power and Gas Sector DPO
Names Title Unit Responsibility/
Specialty
Lending
Jacques Morisset Program Leader AFCF2 Task Team Leader
Vladislav Vucetic Lead Energy Specialist GEE01 Team Member
Nazaneen Ismail Ali Senior Procurement Specialist GGO05 Procurement
Mona El-Chami Senior Financial Management
Specialist GGO23 Financial Management
Mustafa Zakir Hussain Operations Adviser: OPSPQ Team Member
Robert Schlotterer Lead Infrastructure Finance Specialist GEEFS Team Member
Yutaka Yoshino Program Leader AFCE1 Team Member
Emmanuel Mungunasi Senior Economist GMF07 Team Member
Sanjeev Ahluwalia n.a. n.a. Team Member
Zhengjia Meng Young Professional GEEFS Team Member
Alexander Huurdeman Senior Gas Specialist GEEX1 Team Member
Goodluck Mosha n.a. n.a. Team Member
Waly Wane Senior Economist GED07 Team Member
Chiara Bronchi Practice Manager GGO13 Team Member
Katherine Bain Consultant GGODR Team Member
Victoria Cunningham n.a. n.a. Team Member
Agnes Mganga Program Assistant AFCE1 Team Member
Leah Mukuta n.a. n.a. Team Member
Mercy Sabai Sr Financial Management Specialist GGO31 Team Member
Donald Mneney Consultant GGO01 Team Member
Ann Jeannette Glauber Lead Environmental Specialist GEN2A Team Member
Charles Feinstein n.a. n.a. Peer reviewer
Francisco Carneiro Program Leader LCC3C Peer reviewer
P145254 - TZ Second Power and Gas Sector DPO
Names Title Unit Responsibility/
Specialty
Lending
Yutaka Yoshino Program Leader AFCE1 Task Team leader
Vladislav Vucetic Lead Energy Specialist GEE01 Team Member
Natalyia Kulichenko Senior Energy Specialist GEE07 Team Member
Mustafa Zakir Hussain Operations Adviser: OPSPQ Team Member
Jacques Morisset Program Leader AFCF2 Team Member
Emmanuel Mungunasi Senior Economist GMF07 Team Member
Victoria Cunningham n.a. n.a. Team Member
Nicola Woodroffe n.a. n.a. Team Member
Lydie Ahodehou Program Assistant GMF07 Team Member
Zhengjia Meng Young Professional GEEFS Team Member
Alexander Huurdeman Senior Gas Specialist GEEX1 Team Member
Justina Kajange Operations Analyst GTI11 Team Member
Zoe Kolovou Lead Counsel LEGAM Team Member
42
P145254 - TZ Second Power and Gas Sector DPO
Names Title Unit Responsibility/
Specialty
Luis Schwarz Senior Finance Specialist WFALN Team Member
Roy Sudharshan Canagarajah Manager ECADE Team Member
Hilda Emeruwa Operations Analyst GMFDR Team Member
Oliver Braedt Program Leader LCC6C Team Member
Ann Jeannette Glauber Lead Environmental Specialist GEN2A Team Member
Amy Faust Consultant GSU13 Team Member
Helen Shahriari Senior Social Scientist GSU05 Team Member
Alexandra C. Bezeredi Lead Social Development Specialist GSU01 Team Member
Hanneke Van Tilburg Senior Social Development Specialist OPSPF Team Member
Leah Mukuta n.a. n.a. Team Member
Isis Gaddis Senior Economist GCGDR Team Member
Nadia Belhaj Hassine Senior Economist GPV01 Team Member
Mercy Sabai Senior Financial Management
Specialist GGO31 Financial Management
Donald Mneney Consultant GGO01 Team Member
Milan Brahmbhatt n.a. n.a. Peer reviewer
Charles Feinstein n.a. n.a. Peer reviewer
Havard Halland Senior Economist GGOPS Peer reviewer
(b) Staff Time and Cost
P143645 – Tanzania First Power and Gas Sector DPO
Stage
Staff Time and Cost (Bank Budget Only)
No. of Staff Weeks US$, thousands (including travel and
consultant costs)
Lending and Supervision
FY13 35.40 170,101.33
TOTAL 35.40 170,101.33
P145254 – Tanzania Second Power and Gas Sector DPO
Stage
Staff Time and Cost (Bank Budget Only)
No. of Staff Weeks US$, thousands (including travel and
consultant costs)
Lending and Supervision
FY14 43.62 175,965.66
TOTAL 43.62 175,965.66
43
Annex 2. Beneficiary Survey Results
Not applicable.
44
Annex 3. Stakeholder Workshop Report and Results
Not applicable.
45
Annex 4. Summary of Borrower's ICR and/or Comments on Draft ICR
No comments from the Borrower were received by the time of the submission of this ICR.
46
Annex 5. Comments of Cofinanciers and Other Partners/Stakeholders
Not applicable.
47
Annex 6. Supporting Data
Table 6.1. Results Indicators
No. Pillar 1 Unit 2008 2009 2010 2011 2012 2013 2015 2016 2017
1 TANESCO operating deficit US$
million (3) (20) (3) 22 109 239 (149) 92 (80)
2 TANESCO accounts (trade and other)
payable
T Sh
million 202,236 321,883
428,9
61
472,21
3 707,012
824,0
33
979,9
18
1,187,
238
1,330,
931
3 TANESCO technical and non-technical
losses in transmission and distribution (%) % 25.18 24.98 22.81 22.42 21.87 24.70 17.81 18.29 16.44
Pillar 2 Unit 2008 2009 2010 2011 2012 2013 2015 2016 2017
4 Amount of gas-fired power generation
capacity commissioned after 2011 (MW) MW n.a. n.a. n.a. n.a. 105 105 105 255 285
5 Average unit cost of power sales
(US$/MWh) US¢/kWh 9.28 9.21 8.35 11.89 16.50 18.36 12.90 12.21 9.19
6 Number of bids for gas IPP power plants
launched on a competitive basis (count) n.a. n.a. n.a. n.a. n.a. n.a. 0 0 0 0
7 MEM documents on sector reforms
published for public knowledge (count) n.a. n.a. n.a. n.a. n.a. n.a. 0 2 2 2
Pillar 3 Unit 2008 2009 2010 2011 2012 2013 2015 2016 2017
8 Volume of gas produced (mmscfd) mmscfd n.a. n.a. n.a. n.a. 78 n.a. 102 132 n.a.
9 Amount of onshore proven natural gas
reserves (Tcf) Tcf n.a. n.a. n.a. n.a. 1.000 n.a. 1.369 1.187 n.a.
10 Annual monitoring under the Natural
Resource Charter initiative n.a. No No No No No No No No No
48
Table 6.2. Electricity Tariffs by Category FY2008–FY2017
Electricity Tariffs Category Unit FY2008 FY2009 FY2010 FY2011 FY2012 FY2013 FY2015 FY2016 FY2017
Change
FY2012–
FY2017
D1
Consumers
who consume
on average
below 75 kWh
Service charge T Sh/Month — — — — — — — — — —
Energy charge
(0–75 kWh) T Sh/kWh 49 49 49 60 60 60 100 100 100 67%
Energy charge
(>75 kWh) T Sh/kWh 156 156 156 195 273 273 350 350 350 28%
T1 General usage
tariff
Service charge T Sh/Month 2,303 2,303 2,303 2,738 3,841 3,841 5,520 0 0 −100%
Energy charge T Sh/kWh 129 129 129 157 221 221 298 292 292 32%
Maximum
demand charge T Sh/kVA/Month — — — — — — — — — —
T2
Consumers at
400 V and
above and
>7,500
kWh/month
Service charge T Sh/Month 8,534 8,534 8,534 10,146 14,233 14,233 14,233 14,233 14,233 0%
Energy charge T Sh/kWh 85 85 85 94 132 132 200 195 195 48%
Maximum
demand charge T Sh/kVA/Month 9,347 9,347 9,347 12,078 16,944 16,944 15,004 15,004 15,004 −11%
T3 Medium
voltage
Service charge T Sh/Month 8,534 8,534 8,534 10,146 14,233 13,233 16,769 16,769 16,769 18%
Energy charge T Sh/kWh 79 79 79 84 118 118 159 157 157 33%
Maximum
demand charge T Sh/kVA/Month
8,669 10,350 14,520 13,200 13,200 13,200 28%
T5 High voltage
Service charge T Sh/Month 8,534 8,534 8,534 10,146 14,233 15,233 0 0 0 −100%
Energy charge T Sh/kWh 75 75 75 83 106 106 156 152 152 43%
Maximum
demand charge T Sh/kVA/Month 4,775 4,775 4,775 8,610 12,079 12,079 16,550 16,550 16,550 37%
49
Annex 7. List of Supporting Documents
Title Date Reference Number
2016 Power System Master Plan Update December 2016 n.a.
AfDB Power Sector Reforms and Governance
Support Program (PSRGSP) Phases I–III
2015, 2016 n.a.
Aide Memoires for the Project’s Supervision Missions Multiple Multiple
Development of Electricity Tariff-Setting
Methodology and Carrying Out Cost of Service Study
(Mercados Study)
August 2012 n.a.
DPO Program Documents February 2013,
February 2014
74994-TZ, 84028 -TZ
Electricity Supply Industry Reform Strategy and
Roadmap 2014–2025
June 2014 n.a.
IMF Staff Reports on Article IV Consultations and
Reviews under the Standby Credit Facility
Arrangement
2012–2014 Multiple
Program Implementation Status and Results Reports
(ISRs)
Multiple Multiple
TANESCO Audited Financial Statements and
Management Accounts
2008–2016 n.a.
TANESCO Short-term Financial Assessment 2012–
2015
June, 2012 n.a.
TANESCO Tariff Applications 2012–2016 n.a.
TANESCO Turnaround Study (MCC) 2016 n.a.
Tanzania Development Vision 2025 1999 n.a.
Tanzania Economic Update 10: Managing Water
Wisely
November 2017 n.a.
Tanzania National Energy Policy December, 2015 n.a.
Tanzania Rural Electrification Expansion Program—
Program for Results
May, 2016 103827-TZ
Tanzania: Intended Nationally Determined
Contribution (INDC) under the UNFCCC
September 2015 n.a.
The Tanzania Five-Year Development Plan 2011/12–
2015/16
June 2011 n.a.
The Tanzania Five-Year Development Plan 2016/17–
2020/21
June 2016 n.a.
World Bank Tanzania CAS for FY2012/15 May, 2011 60269-TZ
Note: MCC = Millennium Challenge Corporation; UNFCCC = United Nations Framework Convention on
Climate Change.
50
Annex 8. Map
Source: The World Bank.