world bank document€¦ · (world bank partial credit guarantee) public disclosure authorized ......
TRANSCRIPT
D2
E-235 VOL. 22
TNB Stage II Inter Connection and
Transmission System Expansion Project No. 9
J2 VII Viil H Uiiiii~i-UI l&ll i Xi -it-lJtirn
Construction and
Maintenance of Transmission Lines
EGAT - INVESTMENT PROGRAM SUPPORT PROJECT
(WORLD BANK PARTIAL CREDIT GUARANTEE)
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
TNB Stage II Inter Connection and
Transmission System Expansion Project No. 9
Environmentai Guiueiines for irianni-ug,
Construction and
Maintenance of Transmission Lines
Contents
TRANSMISSION SYSTEM EXPANSION PROJECT NO. 9 andEGAT-TNB STAGE II INTER CONNECTION
ENVIRONMENTAL GUIDELINES FOR PLANNING, CONSTRUCTION ANDMAINTENANCE OF TRANSMISSION LINES
pageExecutive Summary i
1 Introduction 1
2 Project Description 3
3 Legal and Administrative 72
4 Route Selection Criteria and Mitigation Strategies 78
5 Environmental Issues 90
6 Mitigation Measures 92
8. Monitoring 93
Executive Summary
TNB Stage 11 Inter Connection and
Transmission System Expansion Project No. 9
Environmental Guidelines for Planning, Construction and
Maintenance of Transmission Lines
Introduction
1. The Electricity Generating Authority of Thailand (EGAT) is a state enterprise
under direct supervision of the Office of the Prime Minister. EGAT was established
on May V 11969 to nationalize nd consolidate thA>e fuLnctions and responsibili-es of
three independent state enterprises: the Yanhee Electricity Authority (YEA), the
Lignite Authority (LA) and the North-East Electricity Authority (NEEA). EGAT is
now in the process of privatization. EGAT has the responsibility to provide electricity
for the entire Kingdom of Thailand by generating, transmitting and selling bulk
energy to two distributing entities, namely the Metropolitan Electricity Authority
(MEA) and the Provincial Electricity Authority (PEA).
2. The current EGAT long term Power Development Plan (PDP 95-01) includes
about 13,100 MW total power purchase from IPPs up to the year 2011, representing
30% of the total installed capacity at that time. To facilitate private sector investment
in IPP projects, EGAT will construct Transmission System Expansion Project No. 9
and TNB Stage II Inter Connection.
Project Description
3. Transmission System Expansion Project No. 9 is also prepared in response to
the Government's policy to continue the development of infrastructure to sustain the
economic growth of the country . TS 9 is a package of 26 subprojects of transmission
lines and substations expansion and reinforcement. The project involves the
construction and reinforcement of transmission lines totalling 1,890.0 circuit-kilomreters,
and 10 substations. The total amount of 5,900 MVA transformer capacity and 1,202.4
MVA reactive power compensation equipment installed at the existing substations are
also included.
4. TNB stageIl Interconnection consisits of two parts: the construction of HVDC
transmission, and internal system reinforcement.
Legal and Administrative
5. Environmental Impact Assessment (EIA) is not required under current
Thailand law and regulation for the Transmission System Expansion Project No. 9
and TNB Stagell Inter Connection. The EIA for the transmission system will be
expected only when all or a portion of the transmission line routes are located in
Watershed classification class 1 B (or wildlife sanctuary area, or national park area,
or mangrove area). The project routes do not traverse any of these. This report is a
focused environmental analysis of environmental impacts of project components and
their mitigation measures as required by the World Bank.
Analysis of Alternatives
6. Power system studies were reviewd based on the latest EGAT and TNB Power
Dhevelopment Planis (PDP) to firm up the 300 MW EGAT - TNB Stage II
Interconnection .The studies have been carried out for three options: (1) Without
EGAT - TNB Stage II Interconnection, (2) With EGAT - TNB HVAC Interconnection
and (3) With EGAT -TNB Stage II Interconnection. The EGAT PDP, revised PDP
ii
92-01 , and 1991 load forecast together with the updated version of TNB' s PDP and
load were adopted for the study .
Route Selection Criteria and Mitigation Strateeies
7. In selection of routes for transmission lines and substation sites, EGAT
uses design criteria to minimize environmental impacts on forest, wildlife, watershed
areas, populations, archaeological sites and scenery. Transmission line right of
ways are not to be located through: (a) restricted Class IA watershed area, according
to laws and regulations; and, (b) holy places, archeological sites and government
sites. Transmission line right of ways should also avoid: (a) watershed area class lB,
Addiional forest conservation areas (Class C),mangrove forest, national parks and
other conservation areas; (b) community and developed areas; (c) parallel with,
or close to telephone and telegraph cables for a long distance to avoid
8. Detailed Route Surveys: Before construction of the transmission system,
detailed route surveys will be performed by EGAT staff together with the Royal
Forest Department (RFD). The number of forest trees to be cut will be documented.
In addition, final route selection adjustments to avoid dwellings and circumvent other
areas of potential negative impact will be made, according to EGAT's environmental
design criteria.
9. Construction: EGAT's guidelines for construction activities are: (a) avoid
installation of new access roads for construction purposes; try to utilize existing
trails; (b) no cutting of trees over the limitations set by RFD; and, (c) clean up
construction sites upon completion of construction work.
10. Maintenance of the Right of Way: Along the valleys, only trees considered to
be hazardous to the stability of the transmission system would be cut down.
Landowners are permitted to cultivate economic crops under EGAT's criteria
along the right of way corridors. Upon completion of transmission line construction
iii
work, ground cover around the towers will be planted and land contouring will be
done as required to provide a protective covering for the earth and to prevent
soil erosion. No herbicides are used in right of way maintenance .
Environmental Issues:
11. Environmental Impact on Water Resources: Potential impacts of a
transmission system on water quality are related to construction activities: surface
run-off from construction sites; wastewater from the temporary office and
construction camps; and, wastewater contaminated with oil or grease from machinery
which will be mitigated . The construction sites, temporary office and construction
camp will locate more than 100 meters far from water resource or stream and all of
slope area is less than 45 degree. The construction will follow the EGAT'S
Environmental Guidelines for Transmission System.
12. Forest resources: There are 25 sub projects, with a length of approximately
159.55 kilometers, that pass through the reserve forest (non protected forest). There
are no watershed area class IA and 1B, wildlife sanctuary, national park ,mangrove
forest area or addition forest conservation area (C) near any transmission line of
subproject on Transmission System Expansion Project No. 9. TNB Stage II Inter
Connection Project comprises 3 tranmission lines ,a distance of approximately 213.5
kilometers, that pass through the reserve forest. Many of these 'forest areas' have
already been cleared for agriculture are other purposes . The attached route maps show
the actual conditions found in walk-throughs . There is no watershed area class 1A
and IB, wildlife sanctuary, national park ,mangrove forest area or addition forest
conservation area (C) near any transmission line of subprojects .
13. Wildlife: There are 159.55 kilometers of Transmission System Expansion
Project No. 9 and 213.5 kilometers of TNB Stage ii inter Connection Project fhat pass
through the reserve forest that are not significant for conservation. Many of the
reserve forest areas where the transmission lines traverse have already been cleared
iv
for agriculture and other purposes (see maps). The wildlife are mostly small in size
and they can adjust well to minor change in the environment.
14. Land Use: The project construction phase will cause the loss and limitation of
agricultural land use in the ROW; however, the impact is on a small total land area
because most of the crops have a short growing season and they do not exceed the
height restrictions for vegetation in the right of way. Transmission System Expansion
Project No. 9 and TNB Stage II Inter Connection Project have tranmission lines which
pass through the agricultural land totalling about 1,121.45 and 360.3 km . The
Maintenance of the right of way will follow the EGAT policy on post-project land
use.
15. Cultural and Esthetic Resources: There were no cultural or esthetic resources
that would potentially be impacted along the Transmission System Expansion ProjectMNr 0 nirA 'T'NTf St-g YT T,,+_. T 'fl--2
No nd B Sa II +.eCucion I roJect.
16. PCB Management: Transmission System Expansion Project No. 9 and TNB
Stage II Inter Connection Project will not involve replacement of equipment
potentially contaminated with PCB. EGAT has surveyed all potentially contaminated
electrical equipment.
17. Electromagnetic Frequency (EMF): A full discussion of EMF effects and
EGAT transmission lines is included in the Environmental Impact Analyses of the
Greater Bangkok Area, and the Environmental Report for 500 KV Transmission Line
for IPP's.
Mitigation Measures:
18. Natural Resources: Foundation towers and construction activities including
transportation of construction materials, material storage and worker housing would
be located at least 50 meters away from surface water resources to avoid soil erosion.
In case it is necessary to use areas closer to water resources, soil barriers would be
v
built to block erosion and sedimentation. Vegetative cover would be replaced along
streambanks and the surrounding project site if disturbed, to prevent soil erosion. In
all areas, sanitary latrines will be constructed for workforce and temporary offices,
and good housekeeping measures will minimize potential water contamination clue to
construction.
19. Forest Resources: The following mitigation measures would be followed: (i)
deforestation to be done only in the right of way ii) reforestation is the responsibility
of EGAT, the area of reforestation would be more than the area of national forest
reserve used for the ROW; iii) in case private land is used in construction, it is the
responsibility of EGAT to contact the owner and pay fair compensation. Many of the
'forest areas' along the routes have already been cleared for agriculture and other
purposes (see map section).
20. Wildlife: The impacts can be controlled by: i) deforestation only in the
right of way area; ii) prohibition on disturbing wildlife, including nests, eggs, holes,
hollows and other habitat; iii) prevention of noise pollution by limiting work hours
between 8.00 am and 16.00 pm., all work to be forbidden at night.
21. Land Use: EGAT would plan all the project activities including material
transportation, pole mounting and others in the dry season, because most of the crops
would already have been harvested. Removal of agricultural plants (particularly
perennials) would be done only as necessary and compensation paid. Farmers would
be allowed to grow short-lived crops with heights in the ROW under EGAT's Criteria
after construction.
Monitoring
22. The following monitoiirig plan will be adopted to track the effectiveness of
mitigation techniques, and to address recognized problems in an appropriate and
timely manner. This regular scheduled monitoring program will consist chiefly of
visual inspections during construction and operation for:
vi
o erosion along access roads, substation and transmission tower foundations;
o encroachment of settlements within rights of ways, encroachment of
settlements within protected areas via transmission line access roads,
exploitation of forest resources in protected areas via access roads;
o vegetation clearances below transmission lines, and invasion of exotic species
along right of ways;
o transformer fluid leakage and spills.
vii
TNB Stage II Inter Connection and
Transmission System Expansion Project No. 9
Environmental Guidelines for Planning, Construction and
Maintenance of Transmission Lines
1. Introduction
The Electricity Generating Authority of Thailand (EGAT) is a state enterprise under direct
supervision of the Office of the Prime Minister. EGAT was established on May 1, 1969 to
nationalize and consolidate the functions and responsibilities of three independent state
enterprises: the Yanhee Electricity Authority (YEA), the Lignite Authority (LA) and the
North-East Electricity Authority (NEEA). EGAT is now in the process of privatization.
EGAT has the responsibility to provide electricity for the entire Kingdom of Thailand by
generating, transmitting and selling bulk energy to two distributing entities, namely the
Metropolitan Electricity Authority (MEA) and the Provincial Electricity Authority (PEA).
It is certainly realized that the electric power, a source of energy, is an infrastructure in
strengthening the economic and social development of a country. To provide the adequate and
reliable supply of electricity is the predominant responsibility of EGAT. Following the
recovery from economic recession period in 1987, the electricity consumption in Thailand has
been increasing at the extremely high rate. The growth rates of peak generation requirement
were recorded at two digits, and expected to further increase at high levels (10.09 % for the 7th
NESDP and 7.90 % for the 8th NESDP). In line with the electricity requirement of the country,
EGAT's Power Development Plan (PDP) has been prepared and periodically revised. The PDP
always includes the investments for expansions of transmission system as well as the power
generation facilities, since the electricity once generated must be transmitted and distributed to
consumers. The transmission system expansion program involves the constructions of
1
transmission lines and substations for reinforcement of the electric power system to keep abreast
of the load growth and to expand the electricity services to remote areas.
Several Transmission System Expansion Projects (TS Projects) have been included in the PDPs
and implemented in successive stages. So far, eight transmission system expansion projects,
namely Transmission System Expansion Projects No.1 to Transmission System Expansion
Projects No.8 have been formulated. In addition to the normal transmission system expansion
projects, several accelerated transmission projects have also been formulated to increase the
power transfer capability of the interconnection between regions and to supply power for large
industrial loads and the unexpected fast increase in power demand.
Transmission System Expansion Projects No.9 (TS.9 project) has been listed as one of the
transmission system expansion projects in the Seventh National Economic and Social
Development Plan (the 7th NESDP). In the 7th NESDP, the Government has set the policy
guidelines to improve the power system reliability. One of the policy guidelines is to improve
transmission and distribution systems for more sufficient, reliable, high quality, and safety of
supply, especially for industrial and new economic development areas; and to reinforce the
power system interconnection with neighbouring countries to provide more energy interchange
capability for the economic and system reliability. The TS.9 Project is planned for
implementation during 1996-1998.
TNB Stage II Inter Connection is the power system interconnection between EGAT and TNB
(Tenaga Nasional Berhad) of Malaysia was first energized on February 1, 1981. The
interconnection consists of a 24.5 km single circuit 132 KV 240 mm2 ACSR transmission line
linking Sadao substation of EGAT and chuping Substation of TNB; and two 115/132 KV
transformers, rated 66.7 MVA each.
The existing EGAT-TNB interconnection are initially proposed for regular peak power
exchange, but operation of the systems indicated oscillatory damping and power swing
problems as the size of the interconnection is too small in relation to the size of the two systems.
The present power system is operated in such a way that parts of southern portion of EGAT
system or parts of northern region system of TNB will have to be disconnected with the rest of
its main grid and synchronized with the other system whenever the power exchange is required.
As the two systems cannot be fully synchronized, thus restricts its utilization, EGAT and TNB
therefore agreed to individually conduct the preliminary studies to strengthen the
interconnection and the possibility of upgrading the interconnection to gain the full benefits of
the interconnection. Since 1986, several meeting between EGAT's and TNB's system planning
staff have been held both in Thailand and Malaysia to review results of the preliminary studies
and pursued the joint study on the Stage II EGAT-TNB Interconnection Project aiming at the
maximum power exchange of 300 MW.
2. Project description
The land use classification are shown in the maps attacked to the project description. There are
two basic land use in the transmission line project areas: agricultural land and reserve forest.
The reserve forest areas have been broken down into areas for which land use permits have been
obtained, and areas for which land use permits are pending. As can be seen in the map, the
majority of the routes traverse agricultural area. These area are typically para rubber or rice. The
reserve forest areas are usually degraded forest (or converted to rubber plantation), as oppossed
to protected forest. There are no protected forest area involved in the project no. 9 or TNB.
The reserved forest areas through which the TNB project passes are almost exclusively
converted to rubber plantation. Only 10 % of the TNB project passes through reserve forest
areas.
. ~3
2.1 TNB Stage II Inter Connection
The EGAT-TNB stage II Interconnection consisits of two parts: the construction of HVDC
transmission, and the internal system reinforcement.
1. The HVDC transmission comprises:
(a) Due to the limited area of Hat Yai 2 substation , a new site is proposed at
Khlong Ngae for the installation of HVDC converter . The HVDC converter will be 250 KV
300 MW monopolar and upgradable at a later stage to bipolar for 600 MW.
(b) Construction of a 250 KV HVDC bipolar line from Khlong Ngae converter
station to the Thailand-Malaysia border, using 2x400 mm2 conductors per pole (pole 2
conductor will be used as metallic return for the initial stage monopolar), a distance of
approximately 24 km.
(c) Installation of communication system.
2. The internal network reinforcement comprises:
(a) Construction of HVAC 230 KV Switchyard at Khlong Ngae to link the HVDC
converter station via two converter transformers with the 230 KV HVAC four lines, two lines
from Hat Yai 2 substation and two lines from Thung Song Substation.
(b) Construction of a double circuit 230 KV Hat Yai 2-Khlong Ngae linw, using 2
x1272 MCM ACSR conductor per phase, a distance of approximately 30 KM.
(c) Construction of a double circuit 230 KV Thung Song-Khlong Ngae lin, using 2
x1272 MCM ACSR conductor per phase, a distance of approximately 210 KM.
(d) Expansion of 230 KV Hat Yai 2 Substation for two outgoing lines to Khlong
Nage converter station.
(e) Expansion of 230 KV Thung Song Substation for two outgoing lines to Khlong
Ngae converter station
(f) Addition of communication system.
4
4 ' ' l ll:.abottloslsusl~~~~~~~~~~~~~~~~~~~~fllll;\
. 'n,<.'.:,.'>''-: :'':''';'.'. :'.: '' :' "; ,: .; ,.;.,':--''.c :, -
v~~~~~~~~~~~~~~~~~~~~~~~~7 ...... ' ,, .. ::.--!-...8.'>''. ;.... ', . -: ,' .. . -. v.-.1!.:. 4'W :- . ; .^=-i-- - .. ': ^ . !-
! 'At;( r;si, ......................................... ,. .. s , .... j,
; ! ,;+,. , ... X , : . . . . T- X ' . , . ' . ,, , . , . t
AW ::'trd'SL,-ErtiX I ',~~~~~~~~~~~~~~~~~~~~~~~~~~~~~:
. FffX~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
l < ' ;i '-'''} '\t;, J '+' '.'--!;1
' EEREFRSTAES(PRI ENIG i.S::,-X wi<'jg;ll,,, .,7_ : !' _ _ ~~~~~~AGRCTR RA tt !¢j;i'; ,-; tS{.'X> TOO.D9 tL
Z~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~~~~ :,.. t.,t ', ',jlO.OVRE TTDI /'
* rK' oDv!Jo -: _~~~~~~~~~~~~........ V_ _ _ ,~~ ~~~~~~~ ..... ._
Figure ronsmision Lne Roue For GAT-TtB Sto3_ Inte ............................................... r.recton Proec' .....IT..... r
TNB Stage II Inter Connection
Name of Transmission Lines Lenght Reserved Forest Passed Agriculture Land
1. 230 KV Klong Ngae-Thung Song 210 20.2 189.8
2. 230 KV Had Yai 2- Klong Ngae 24 24
3. 300 KV Klong Ngae - Borded (Thai-Malasia) 24 24
4. 230 KV Krabi-Thung Song 78.8 38.8 40
5. 500 KV Border (Namn Province) -Mae Moh 3 237 154.5 82.5
. - 6
2.2 Transmission System Expansion Project No.9
TS.9 project is also prepared in response to the Government's policy to continue the
development of infrastructure to sustain the economic growth of the country. The objectives of
the TS.9 project are therefore:
(i) to provide sufficient power for future demand;
(ii) to improve reliability of power supply particular in new industrial and
commercial areas;
(iii) to support the distribution system expansion to various remote areas.
The TS.9 project is a package of 25 subprojects of transmission lines and substations expansion
and reinforcement. The project involves the construction and reinforcement of transmission
lines totalling 1,890.0 circuit-kilometers, and 10 substations. The total amount of 5,900 MVA
transformer capacity and 1,202.4 MVA reactive power compensation equipment installed at the
. ~7
TRANMISSION SYSTEM EXPANSION PROJECT NO. 9
No. Name of Transmission Lines Lenght Reserved Forest Passed Private Land Passed Remarks
Km. Km. Km.
1. 230/115 KV BAN PONG 2 - BAN PONG I - NAKHON CHAISRI 43 43 old ROW
- SAM PHRAN 2 LINES
2. 115 KV BOR WIN - BAN BUNG LINE 27 27
3. 115 KV THATAGO - THA WUNG LINE 2 2
4. 115 KV THA]LAN 3 - SARABURI I LINE 15 15 old ROW
5. 115 KV THALAN 1 - THALAN 3 LINE 5 5
6. 115 KV RATCHABURI 2 - PHETCHABURI LINE 54 54
7. 115 KV PRACHIN BURI 2 - WATTHANA NAKHON LINE 67 41.2 25.8
8. 115 KV MUKDAHAN - THAT PHANOM LINE 36 25.95 10.05
9. 115 KV THAT PHANOM - NAKHON PHANOM LINES 59 59
10. 115 KV UDON THANI 2 - NONG BUA LAM PHU LINE 61 3.7 57.3
11. 115 KV ROI ET - PHAYAKKHAPHUM PHISAI LINE 84 84
12. 115 KV PHAYAKKHAPHUM PHISAI - SURIN LINE 80 20.15 59.85
13. 115 KV CHAIYAPHUM - BAMNET NARONG LINE 58 58
14. 115 KV UBON RATCHATHANI 2 -KANTHARALAK LINE 55 55
15. 115 KV SURIN - SANGKHA LINE 49 10.1 38.9
16. 230 KV THUNG SONG - NAKHON SI THAMMARAT LINE 54 54 old ROW
17. 230 KV SURAT THANI - THUNG SONG LINE 122 122 old ROW
18. 230 KV KHLONG NGAE - YALA LINE 120 1.5 118.5 old ROW
19. 2301115 KV PHlANGNGA - PHUKET JUNCTION - PHUKET 2 LINE 88 88 old ROW
20. 115 KV YALA -NARATHIWAT LINE 61 61
21. 115 KV SURAT THANI - BAN DON LINE 14 14
22. 115 KV LAN KRABU - KAMPHAENGPHET LINE 47 34.85 12.15
23. 115 KV MAE MOH 3 - LAMPANG 2 LINE 27 15.1 11.9
24. 115 KV CHIANG MAI 2 - MAE TAENG LINE AND SUBSTATIONS 42 7 35
25. 230 KV RATCHABURI 2 - PRACHAUB KHIRIKHUN LINE II I old ROW
SUBPROJECT NO.1
230/115 KV BAN PONG 2- BAN PONG 1- NAKHON CHAISRI
-SAM PHRAN 2 LINE
A. Objective
Objective of Subproject No.1, the 230/115 kV Ban Pong 2 - Ban Pong 1 - Nakhon Chaisi -
Sam Phran 2 lines and substations, is to provide sufficient and reliable power supply for the
increasing demand of industrial plants in the western area.
B. Proiect Scope and Description
Project Scove
The scope for the 230/115 kV Ban Pong 2 - Ban Pong 1 - Nakhon Chaisi -Sam Phran 2
lines and substations consists of the following constructions:
a) Construction of 115 kV temporary detour lines on the existing rights-of-way from
Ban Pong 1 to Nakhon Chaisi and from Nakhon Chaisi to Sam Phran 2, using 1272 MCM
ACSR conductor, and dismantling the existing 115 kV Ban Pong 2 - Ban Pong 1 Line No.2
(200 sq.mm TACSR/AW conductor) and the existing 115 kV Ban Pong 1 - Nakhon Chaisi -
Sam Phran 2 single circuit line.
b) Construction of 230 kV double circuit Ban Pong 2 - Ban Pong 1 - Nakhon Chaisi -
Sam Phran 2 transmission line, double circuit steel towers, using 2x1272 MCM ACSR
conductor per phase, a distance of approximately 43 km. The new 230 kV line designed
with differential insulation, will be constructed on the existing right-of-way of the
dismantled 115 kV single circuit Ban Pong 2 - Ban Pong 1 - Nakhon Chaisi - Sam Phran 2
line. The new 230 kV lines will be initially energized at 115 kV and one circuit will be
temporary terminated at 115 kV Ban Pong 1 Substation and both circuit will be terminated
at 115 kV Nakhon Chaisi Substation.
9
c) Expansion of 115 kV Ban Pong 2 Substation for one additional line.
d) Expansion of 115 kV Nakhon Chaisi Substation for two additional lines.
e) Expansion of 115 kV Sam Phran 2 Substation for one additional line.
f) Land procurement for the extension of Nakhon Chaisi Substation for future 230 kV
switchyard. However, if the adjoining piece of land would not be available, the new site of
230 kV switchyard, called Nakhon Chaisi 2, would be considered, and the four-circuit
transmission line for double circuit 230 kV line and double circuit 115 kV line on the same
tower would be constructed to link the new 230 kV Nakhon Chaisi 2 Substation to the
existing 115 kV substation.
g) Addition of communication system.
Project Description
At present, the transmission system which supply power demand in the western area
consists of a 115 kV loop among three major 230 kV substations, via 230/115 kV tie
transformers at Sam Phran 1, Ban Pong 2 and Ratchaburi 2 Substations. The demand in this
area has been increasing rapidly due to the industrial development. Part of 115 kV line
sections have been reinforced under ATP and TS.8 projects to maintain the power supply
reliability. The reconstruction of 115 kV Sam Phran 1 - Sam Phran 2 line from single
circuit to double circuit, using 2x795 MCM ACSR conductor per phase, is being
implemented under TS.8 project and expected to be commissioned by the end of 1995.
The combined peak power demand at Ban Pong 1, Nakhon Chaisi, and Sam Phran 2
Substation was 283.5 MW in 1993 which caused heavy line loading on 115 kVlines from
Ban Pong 2 to Sam Phran 1 Substations and it is anticipated that the line loading will reach
the transmission line capacity limit in near future. Since, most of the power demand in this
area is industrial load, therefore, high reliability of power supply is very important. The
transmission system reinforcement to cope with the increasing demand is therefore required.
Due to the difficulty to obtain a new right-of-way in these areas, the construction of a 230
kV double circuit Ban Pong 2 - Ban Pong 1 - Nakhon Chaisi - Sam Phran 2 line on the
existing rights-of-way and initially energized at 115 kV is proposed in view of long-term
planning consideration. The differential insulation should also be considered in the design
of the double circuit structure to reduce the probability of simultaneously trip of both
circuits due to lightning stroke.
Figure of the proposed line route of the Subproject is shown in appendix
C. Project Implementation
The proposed commissioning date is December 1997.
..~ i2i.
.20VTO 3RIflAGARINOD ~IIiK 6K !mN AEH' s-3K TOn 3.nRNOa,
s~~~ A 7* 7 Ljl L ~~~~~~~\ 1'~~~~~~~~~' ~ ~ ~ ~ ~ K--Ph
il.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ 1,4 ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~~~~~~~~1
11 CI..I S.
- flD4UJI 1 Zql ' qy 0
A.. - 41KV 1~~~~~~~~~U4~~TArI0bN I
SUBPROJECT NO. 1. 230/115KV BAN PONG 2~~~-BNPNG-NAONCASI-AMPRN2IE
SUBPROJECT NO.2
115 KV BOR WIN - BAN BUNG LINE
A. Objective
Objectives of Subproject No.2, 115 kV Bo Win - Ban Bung line and substations, are to
provide sufficient power supply for future demand and industrial loads and to improve
reliability of power supply in the Ban Bung area.
B. Project Scope and Description
Proiect Scope
The scope for the 115 kV Bo Win - Ban Bung line and substations consists of the following
constructions:
a) Construction of 115 kV double circuit Bo Win - Ban Bung line, double circuit steel
towers, using 2x795 MCM ACSR conductor, a distance of approximately 27 km.
b) Expansion of 115 kV Bo Win Substation for two outgoing lines.
c) Expansion of 115 kV Ban Bung Substation for two incoming lines.
d) Addition of communication system.
Project Description
The existing 115 kV Ban Bung Substation is connected with the 115 kV Si Racha
Substation via a 115 kV single circuit line, 33.2 km, using 477 MCM ACSR conductor.
The present peak demand at Ban Bung Substation is 49.6 MW and is expected to increase at
high growth rate due to the industrial developments in this area. Ban Bung is located in the
13
area which is classified by The Board of Investment (BOI) as the Investment Promotion
Zone 2 which has more privilege than Zone 1 where the Government has recently issued the
policy to limit the industrial developments in Zone 1, and also the policy to move out some
existing industries from the area of Zone 1. The area around Ban Bung is considered one of
the suitable locations to accommodate the industries and industrial estates. The new
transmission lines is therefore required to improve the reliability of power supply. The
construction of a 1 15 kV double circuit Bo Win - Ban Bung line is proposed.
Figure of the proposed line route of the Subproject is shown in appendix
C. Project Implementation
The proposed commissioning date is September 1997.
1 4
110
�M
A
U-1) Tr_� Y �Z'J_l
Ji .,I diV�I--i Z rhZ
4- 11!5 0/j_JT'0 31 RACtiA _b
44�41 L
7 IQY-
A-jv NIJ
�t V-1 N L
_2 V--- JrV
z�rl
LI
V' r sc -ftO AGRICUTUREAREALa
7 77 M,;
N_Y , 1 4slo xv lum a, I
N wnall
z3o- II15 I T:
4r `T( R
SUBPROJECT NO. 2. 115 KV BOR WIN - BAN BUNG LINE
SITBPROJECT NO.3
115 KV THA WUNG SUBSTATION AND LINE
(115 KV THATAGO - THA WUNG LINE)
A. Objective
Objectives of Subproject No.3, 115 kV Tha Wung substation and lines termination, are to
increase power supply capability to meet the increasing demand at Sing Buri and Lop Buri 1
Substations, to improve system reliability, and also to reduce transmission system losses.
B. Project Scope and Description
Project Scope
The scope for the 115 kV Tha Wung Substation and lines termination consists of the
following constructions:
a) Construction of new 115 kV Tha Wung Substation together with the termination of
1 1 5 kV double circuit Ang Thong 2 - Lop Buri 2 line and 115 kV single circuit Sing Buri -
Lop Buri 1 line at Tha Wung Substation. The power supply for station service will be
received from PEA distribution line or a small transformer relocated from the existing
system.
b) Land Procurement for the 115 kV Tha Wung Substation with provision for future
230 kV switchyard.
c) Addition of communication system.
16
Project Description
At present, the existing 1 15 kV Sing Buri Substation is connected with the 115 kV system
via a single circuit line with conductor size of 477 MCM ACSR, a distance of 28 km from
Takhli 2 Substation; and a single circuit line with small conductor size of 4/0 ACSR, a
distance of 33 km from 115 kV Ang Thong 1 Substation. The 115 kV line is also extended
from Sing Buri Substation with a single circuit using small conductor size of 4/0 AWG
ACSR to supply power radially to Lop Buri 1 Substation.
The existing 115 kV lines will not be sufficient to provide reliable power supply to the total
power demand at Sing Buri 1 and Lop Buri 1 in 1997. To cope with the increasing demand,
the system reinforcement in this area is necessary. According to the present transmission
network configuration, there is a line crossing between the double circuit 115 kV Ang
Thong 2 -Lop Buri 2 line and the 115 kV Sing Buri - Lop Buri 1 line at Tha Wung district,
therefore the construction of a new substation at Tha Wung with the termination of 115 kV
Ang Thong 2 - Lop Buri 2 line and 115 kV Sing Buri -Lop Buri 1 line at Tha Wung
Substation is proposed. This substation will improve the system reliability of power supply
at Sing Buri and Lop Buri 1 Substations.
Figure of the proposed line route of the Subproject is shown in appendix
C. Project Implementation
The proposed commissioning date is December 1997.
7 7
4-11!SKV TO TAKtiLl 2 O�CHAIBADAH J
OAXHON S t,,
Ji-j1ymA-j' ?-3qM-MTU_1% 0 A
K. V, Ta
.qI O,A;,o A-4
iL7
n pkjo (1- W 0
e gang iu f
Tj M11311 111.
lu 'Al Do.Mu'
Nu-
4.n 00,, D
J., n-iPk.
j
72 11A ab. I,
L bc Kqai iRA'P
f-*,,, va, LVI
CO A p B
t PIIR
wj) -,;v t,
W
Ampltc,IL S6warn�% IT', wl
ACRICUTURE A I Amph6e Phc
7---� A
"A
PI)i o 1&69 D6n S-�A
1131(v SU63TATMM 0C,
130.V 2USITAT143N bon.1-Thang Y., 4n
0,1 5;�se an
TRA"3.1331om Lifft :11 2, Kv I a -ti 1- B IK
IANG �OfW 1 500KVT0fjotj,3CHOK 4j I I
SUBPROJECT NO. 3, 115 KV THATAGO - TIJA WUNG LINE
SUIBPROJECT NO.4 5
115 KV TIHA LAN - SARA BURI LINE
A. Objective
Objective of Subproject No.4, 5, 115 kV Thalan - Saraburi line and substations, is to
improve reliability of power supply for Saraburi Province.
B. Proiect Scope and Description
Project Scope
The scope for the 115 kV Thalan 3 - Saraburi 1 line and substations consists of the
following constructions:
a) Construction of 115 kV temporary detour single circuit line from Thalan Junction
(near Thalan 3 Substation) on the existing right-of-way to Saraburi 1 Substation, using 477
MCM ACSR conductor stringing on concrete pole for a distance of approximately 13 km.
b) Dismantling the existing 115 kV line section from Saraburi 1 Substation to Thalan
Junction and reconnecting this temporary detour line with the remaining 115 kV line section
from Thalan Junction to Thalan 1 Substation.
c) Construction of 115 kV double circuit Thalan 3 - Saraburi 1 line, double circuit steel
towers, using 795 MCM ACSR conductor for a distance of approximately 15 km. The new
transmission line section from Thalan Junction to Saraburi 1 will be constructed on the
existing right-of-way. The Thalan Junction to Thalan 3 will require a new right-of-way.
d) Construction of 115 kV Thalan 3 - Thalan Junction - Thalan 1 line, single circuit on
double circuit steel towers, using 795 MCM ACSR conductor, for a distance of 5 km. The
new line section between Thalan Junction and Thalan 1 Substation will be constructed on
the right-of-way of the existing 115 kV line to Thalan 1 which will be dismantled. This line
section will form a new 1 15 kV Thalan 1 - Thalan 3 line.
. <- 49
e) Expansion of 115 kV Thalan 3 Substation for three outgoing lines.
f) Expansion of 1 1 5 kV Saraburi i Substation for one additional incoming line.
g) Addition of communication system.
Project Description
The power demand in Saraburi Province is mainly supplied from Saraburi 1 Substation
which is connected with Thalan 1 Substation via a 115 kV single circuit line. The present
peak demand is 44.4 MW and expected to increase at 10 % annually. Since there is only
one circuit that supplies power to Saraburi 1 Substation, additional transmission circuit is
required to improve reliability of supply. The construction of a new 115 kV double circuit
Thalan 3 - Saraburi 1 is therefore proposed.
To avoid the problems on right-of-way acquisition, the right-of-way of the existing 115 kV
line from Thalan 3 Junction, about 2 km south of Thalan 3 Substation (See Figure 4.4), to
Saraburi 1 substation will be used for the construction of the new transmission line. To
maintain power supply to Saraburi 1 Substation during the deenergization of the existing
line, construction of a temporary 115 kV detour line from Thalan 3 Junction to Saraburi 1
Substation is required.
To utilize the existing ritght-of-way of 115 kV line section from Thalan 3 Junction to
Thalan 1, the construction of 115 kV Thalan 1 - Thalan Junction - Thalan 3 line, single
circuit on double circuit steel towers, using 795 MCM ACSR conductor, is also
recommended. This line will increase power transfer capability between Thalan 1 and
Thalan 3 Substation.
Figure of the proposed line route ofthe Subproject is shown in appendix
C. Project Implementation
The proposed commissioning dates is July 1998.
20
-,4-230KV TO TliA ifi!.
4_�'3'OKVTO 4A, . . . . . . . ..
%V.,a u . . .
p Z71,14. U7 kIL
R�_ . . . . . . . ... . . . .. . . . . . . .. . . .L �tSTAT,;" . . . . . . . . .
TIIALAN -4, %UNCTION
. . . . . . . . . . . .XIII) .. ......2 vi,
(SULisi IW4-r7,
r 7b4b,",
VPt,/
. . . .7J1 �qf... :4 . . . . . J1461J.,. . . . . . . . . . iA
L2
A&. . . . . . . . . . NJ . . . . . .
it,Vvf,
x:. 7'
vu . . . . . . .... . . . . . . . . . . Nl�
.14t't�ls-j C,
UV:-SU .........
7t. z AGRICUTUREAREAS
4- 11 5 l(v
SUBPROJECT NO. 4. 11 5 KV TIIALAN 3 - SARABURI I LINE
SlJBPROJECT NO.6
115 KV RATCHABURI - PHETCHABURI LINE
A. Objective
Objectives of Subproject No.6, 115 kV Ratchaburi 2 - Phetchaburi line and substations, are
to maintain reliability of power supply at Phetchaburi Substation, and also to reduce system
losses.
B. Project Scope and Description
Project Scone
l-he scope for the 115 kV Ratchaburi 2 - Phetchaburi line and substations consists of the
following constructions:
a) Construction of 115 kV double circuit Ratchaburi 2 - Phetchaburi transmission line,
using 2x795 MCM ACSR conductor/per phase, a distance of 53.1 km, on the right-of-way-
of the existing 115 kV single circuit line which will be dismantled.
b) Expansion of 115 kV Ratchaburi 2 Substation for one additional outgoing line.
c) Expansion of 115 kV Phetchaburi Substation for one additional incoming line.
d) Addition of communication system.
C' ' )
Project Description
1Tne transmission network which supplies power in the areas of Ratchaburi 2, Phetchaburi,
Cha-Am and Hua Hin Substations is a loop tied between the two 230/115 kV Ratchaburi 2
and Hua Hin (under construction) terminal substations via a double circuit 230 kV line and
a single circuit 115 kV line from Hua Hin to Ratchaburi 2 via Cha-Am and Phetchaburi
Substations. Since the only one circuit of the 230 kV line from Ratchaburi 2 was planned to
be terminated at Hua Hin Substation; therefore, with the new projected increasing demand,
there will be overloaded problem in the 115 kV line when the 230 kV Ratchaburi 2 - Hua
Hin line tripping out. The reinforcement of the 115 kV line sections between Ratchaburi 2
and Hua Hin Substations is necessary, and the construction of a new double circuit 115 kV
Ratchaburi 2- Phetchaburi line is proposed.
Due to the difficulty of obtaining a new right-of-way in this area, the existing right-of-way
will be used for the construction of the new transmission line.
Figure of the proposed line route of the Subproject is shown in appendix
C. Project Implementation
The proposed commissioning date is February 1998.
2 3
. _ -I,: j, 2oKV To BAN PONtG 2M 4-I5KVtO BAN PONO I
3'-..:7- -r I.-
~~~~~~~~-.-.~ .
-\V
~~~~~~~~N ''S, ' _
SUBPROJECT NO. 6.~ ' 115 RATCHABURI ' - AHTCH ABURI 11
RATC-ABURI# cc '
rk.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~M,
07- -!- . -.4~
A '-.~~~ 4, J 'iA7i 51.a
SUBPROJECT NO. 6. 115 K~~~' RATCHABURI 2-- PHPETTHABURIRLINE
SUJBPROJECT NO.7
115 KV PRACHIN BURI 2 - WATTHANA NAKHON LINE
A. Objective
Objectives of Subproject No.7, 115 kV Prachin Buri 2- Watthana Nakhon line and
substations, are to provide sufficient and reliable power supply for future demand at
Watthana Nakhon Substation, and to reduce system losses.
B. Project Scope and Description
Project Scope
The scope for the 115 kV Prachin Buri 2 - Watthana Nakhon line and substations consists of
the following constructions:
a) Construction of 115 kV Prachin Buri 2 - Watthana Nakhon line, single circuit on
double circuit steel towers, using 2x795 MCM ACSR conductor per phase, a distance of
approximately 67 km.
b) Expansion of 115 kV Prachin Buri 2 Substation for one additional outgoing line to
Watthana Nakhon Substation.
c) Expansion of 115 kV Watthana Nakhon Substation for one additional incoming line
from Prachin Buri 2 Substation.
d) Addition of communication system.
Project Description
Tne existing 115 k-V Watthana Nakhon Substation is radiaiiy connected with the 115 kV
Prachin Buri 1 Substation via a single circuit line. Under TS.8 Project, the termination of
115 kV Prachin Buri 1 - Watthana Nakhon line at the new 230/115 kV Prachin Buri 2
terminal substation will be completed in 1995. Voltage regulation at Watthana Nakhon
Substation will be improved by receiving power from Prachin Buri 2 Substation. However,
the improvement of reliability of power supply is still needed, since Prachin Buri and Sra
Kaew provinces is also considered the suitable sites for the industrial estates to
accommodate the new industries and the industries which would be moved out from BOI's
Investment Promotion Zone 1. The construction of a new 115 kV line, single circuit on
double circuit, is therefore proposed.
Figure of the proposed line route of the Subproject is shown in appendix
C. Proiect Implementation
The proposed commissioning date is July 1998.
S 2S
-'*~~~~~~~~~~~~~~~~~~~~~~~~A
I ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~1
SU MNA iOrj ..11 " .
s I*-p1L~ ~~ ~~ I of.~CtU
C ~ •~ i ~ - s ~ ~ j ~ ~.
V -k -- .~, " IST UTIT TIO
A
J ~ ~~RSRE OETAREAS (PERMIT PENDING)
SUBPROJECT NO. 7. 115 KV PRACHIN BURI 2 - WATTHANA NAKHION LINE
SUBPROJECT NO.8 , 9
230/115 KV MUKDAHAN 2 SUBSTATION AND 115 KV MUKDAHAN 2
- THAT PHANOM - NAKHON PHANOM LINES
A. Objective
Objectives of Subproject No.8 , 9, 230/115 kV Mukdahan 2 Substation and 115 kV
Mukdahan 2 - That Phanom - Nakhon Phanom lines and substations are to improve
reliability and quality of power supply, to increase the power supply capability to Mukdahan
and Nakhon Phanom Provinces and to reduce system losses.
B. Project Scope and Description
Project Scope
The scope for the 230/115 kV Mukdahan 2 Substation and 115 kV Mukdahan 2 - That
Phanom - Nakhon Phanom lines and substations consists of the following constructions:
a) Construction of new 230/115 kV Mukdahan 2 Substation to accommodate two 3-
phase 230/115-22 kV tie transformers, rated OA/FA/FOA 120/160/200 MVA, together
with 230 kV bays for the termination of one circuuit of 230 kV Savannakhet -Roi Et line
(constructed under Nam Theun 2 hydroelectric project in Lao PDR), including 115 kV bays
for connection to the existing 115 kV Mukdahan 1 Savannakhet and That Phanom
Substations.
b) Construction of 115 kV Mukdahan 2 - That Phanom line, double circuit steel towers,
using 795 MCM ACSR conductor, a distance of approximately 36 km.
c) Construction of 115 kV That Phanom - Nakhon Phanom line, single circuit on
double circuit steel towers, using 795 MCM ACSR conductor, a distance of approximately
59 km.
d) Upgrading the existing 69 kV That Phanom Substation from 69 kV to 115 kV
substation. Two 3-phase, 115-22-11 power transformers, each rated OA/FA/FOA, 15/20/25
ivIvA (using spare transformer from the system) will be instailed with three ii5 KV iine
bays provided for 115 kV lines from Mukdahan 2 and one 115 kV line to Nakhon Phanom
Substation.
e) Upgrading the existing Nakhon Phanom Substation from 69 kV to 115 kV
Substation. Two 3-phase, 115-22-11 power transformers, each rated OA/FA/FOA,
15/20/25 MVA (using spare transformers from the system) will be installed with one 115
kV bay provided for the line from That Phanom Substation.
f) Expansion of the 115 kV Mukdahan 1 Substation for one line from the Mukdahan 2
Substation.
g) Addition of communication system.
h) Land Procurement for the 230 kV Mukdahan 2 Substation and for the expansion of
115 kV That Phanom Substation.
Proiect Description
At present, the power demand in Mukdahan Province is supplied from 115 kV Mukdahan
Substation which connected with Amnat Charoen Substation by a single circuit line. Due to
the long transmission line and the small conductor size, the unacceptable low voltage is
encountered at Mukdahan Substation. Therefore, the transmission system reinforcement is
required.
The present demand at Nakhon Phanom and That Phanom Substations was 19.38 and 10.52
MW respectively. Both are the end-substations; for which Nakhon Phanom Substation is
connected with the 115/69 kV Sakon Nakhon Substation by the 69 kV Sa-kon Nalchon -
Nakhon Phanom single circuit line with small conductor size of 95 sq.mm., for a distance of
89 km; and That Phanom Substation is connected with the 115/69 kV Sakon Nakhon
Substation by the 69 kV Sakon Nakhon - That Phanom line with small conductor size of 58
sq.mm., for a distance of 70 km.
Due to the increasing demand, the poor voltage regulation has been facing at both
substations, therefore to improve the voltage regulation and to increase the reliable power
supply capability to Mukdahan and Nakhon Phanom Provinces, the construction of a new
230/115 kV Mukdahan 2 Substation and construction of the 115 kV Mukdahan 2 - That
Phanom - Nakhon Phanom lines are proposed.
Figure of the proposed line route of the Subproject is shown in appendix
C. Project Implementation
The proposed commissioning date is August 1998.
30
X.,- ;--- '-Snh%L. -=_c. ---|SUBS-TATION I- V
O ~ ~ ' .;.--<-..'A. . -- '----'c--a
< _ \ , \ ,, ;; ,__~~HAIGW~44<
" s _' esv ___s w x ; > 1 - S - - -I' ,
CD
| Cto 'Xt,O ze "! Id KDHA sue -A *O. IIL
-i -- AGRIC-, stTUssstRESREFET AREAS (EMTPNIG
-ON
SUBPROJECT NO. 8. 115 hV MUhDAHAN - THAT PHANOMI LINE
SUBPROJECT NO. 9. 115 KY- THAT PHANOMl - NAKHION PHANOMl LINES
.... . .. ZM~~~~~~
7.~.
SUBPROJECT NO.10
115 KV UDON THANI 2 - NONG BUA LAM PH11U LINE
A. Objective
Objective of Subproject No.10, 115 kV Udon Thani 2 - Nong Bua Lam Phu line and
substations, is to improve reliability of power supply for Nong Bua Lam Phu and Loei
Provinces.
B. Project Scope and Description
Project Scope
The scope for the 115 kV Udon Thani 2 - Nong Bua Lam Phu line and substations consists
of the following constructions:
a) Construction of 115 kV Udon Thani 2 - Nong Bua Lam Phu line, single circuit on
double circuit steel towers, using 795 MCM ACSR conductor, a distance of approximately
61 km.
b) Expansion of 115 kV Udon Thani 2 Substation for one outgoing line.
c) Expansion of 115 kV Nong Bua Lam Phu Substation for one incoming line.
d) Addition of communication system.
Project Description
At present, the power demand in Nong Bua Lam Phu Province is supplied from Udon Thani
1, Udon Thani 2 and Loei substations via PEA 22 kV distribution lines. The Nong Bua
Lam Phu Substation is being constructed under TS.8 Project by terminating the existing 115
kV single circuit Udon Thani 1 - Loei line. The new 115 kV Nong Bua Lam Phu
Substation, which will be completed by the end of 1995, will increase the power supply
v .c)P..l'_
capability with better quality at an acceptable reliable services to the Nong Bua LTam Phu
Province and its vicinity. However, the power supply for Nong Bua Lam Phu and Loei
provinces is still supplied by a 115 kiV singie circuit line from Udon Thani 1 Substation.
Therefore, to cope with the future high peak demand, the improvement of reliability of
power supply is required to prevent the possibility of total blackout in these two provinces.
The construction of a new 115 kV Udon Thani 2 - Nong Bua Lam Phu line is proposed.
Figure of the proposed line route of the Subproject is shown in appendix
C. Project Implementation
The proposed commissioning dates is August 1998.
lj~~~. ~~~i ' ~ ~ ~ ~~ * sUB~~~STATIOIJ.
- ~~~~~ ~ ~ h YIr in
lIiflTh~~~1?~L, / )/1A 3- K.t q 1b1
g 3ufl ~ ~ I og~i~/ dl. SUOSTATICt
(\I IuKP
ij mb T. C.J --~1
ONGBPRUJLAT NOPII 1KVUO HN 2 OGBALAIPULN
SUBPROJECT NO.11, 12
115 KV ROI ET - PHAYAKKHAPHUM PHI SAI - SURIN LINE
A. Objective
Objective of Subproject No.12, 115 kV Roi Et - Phayakkhaphum Phisai -Surin lines and
substations, is to improve reliability of power supply at Phayakkhaphum Phisai and Surin
Substations.
B. Project Scope and Description
Project Scope
The scope for the 115 kV Roi Et - Phayakkhaphum Phisai - Surin lines and substations
consists of the following constructions:
a) Stringing the second circuit on the double circuit towers of the 115 kV Roi Et -
Phayakkhaphum Phisai line (under construction in TS.8 Project for commissioning by the
end of 1996), using 795 MCM ACSR conductor, a distance of approximately 84 km.
b) Construction of 115 kV Phayakkhaphum Phisai - Surin line, single circuit on double
circuit steel towers, using 795 MCM ACSR conductor, a distance of approximately 80 km.
c) Expansion of 115 kV Roi Et Substation for one outgoing line.
d) Expansion of 115 kV Phayakkhaphum Phisai Substation for two lines.
e) Expansion of 115 kV Surin Substation for one line.
f) Addition of communication system.
k nr~4 f~
Project Description
Atpresent, thLe powef deinwd in P-hrayaukkaphum Pnisai district and its vicinities is suppliedfrom several nearby 115 kV EGAT's substations via 22 kV PEA's distribution lines. A new
115 kV substation at Phayakkhaphum Phisai is being constructed, under TS.8 Project forcommissioning in 1996, to increase the capability of power supply to those areas at anacceptable reliability level and better power quality. However, since the new 115 kVPhayakkhaphum Phisai is still supplied by a single circuit line, therefore second circuit isrequired to further increase the reliability level.
For the same reason as mentioned above, the power at 115 kV to Surin Substation is stillsupplied from Buriram Substation via a 115 kV single circuit line, therefore, a new 115 kVline is required.
Stringing of the second 115 kV circuit on the underconstructed 115 kV double circuit lineRoi Et - Phayakkhaphum Phisai line and the construction of a new 115 kV PhayakkhaphumPhisai - Surin line is proposed.
Figure of the proposed line route of the Subproject is shown in appendix
C. Project Implementation
The proposed commissioning date is August 1998.
--A, 115KVTOKHOC KAEN I..- -U'ISVTOPHON THON
-I'KVT KA2L SI
.w , -_ *' z - ...,.'
4-_ ~~~~~~~. . /\ * - ' a
S O N 11. 115 *' HI E
SUBPROJECTNO. 12. 11 RA PBYAAP U ,--HIS.,- SUI LIE
II
ST.. BPROJEC NO 12 11 7N PHYKHPU HS1SURIN LN
SUBPROJECT NO.13
115 KV CHAIYAPHLUM - BAMNET NARONG LINE
A. Objective
Objectives of Subproject No.13, 115 kV Chaiyaphum - Bamnet Narong line and
substations, are to provide sufficient power supply to Bamnet Narong and nearby districts
with satisfactory voltage regulation and acceptable reliability of services and also to reduce
system losses.
B. Project Scope and Description
Proiect Scope
The scope for the 115 kV Chaiyaphum - Bamnet Narong line and substations consists of the
following constructions:
a) Construction of 115 kV Chaiyaphum - Bamnet Narong transmission line, single
circuit on double circuit steel towers, using 795 MCM ACSR conductor, a distance of
approximately 58 km.
b) Expansion of 115 kV Chaiyaphum Substation for one outgoing line.
c) Construction of new 115 kV Bamnet Narong Substation with two 3-phase, 115-22-
11 kV power transformers, each rated OA/FA/FOA 30/40/50 MVA (land for the substation
has been purchased in TS.8 project).
d) Addition of communication system.
Proi ect Description
The PEA 22 kV distribution lines which supply power to Bamnet Narong and nearby
districts are connected with EGAT's 115 kV Nakhon Ratchasima 1, Chaiyaphum and Sikhiu
substations at the distance of approximately 85, 70 and 90 km respectively. The high growth
of power demand is expected due to the establishment of the ASEAN Potash Mine Project.
Due to long distribution line, PEA has been facing with voltage drop problem and high
distribution losses. Automatic voltage regulators (AVR) have been installed on the 22 kV
distribution lines, however the excessive power losses still remain and the supply reliability
is not at the acceptable level.
The construction of a new 115 kV substation at Bamnet Narong will greatly increase
capability of power supply to cope with the increasing demand in this area at an acceptable
reliability level and satisfactory voltage regulation.
Figure of the proposed line route of the Subproject is shown in appendix
C. Proiect Implementation
The proposed commissioning date is November 1997.
~~:r~~~ , lj :;~~~~~~~~LQ ~'E 0~¾ZOVT KHON KAEN 3
~~~~~~~~~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ IAI
I ~~~~~~~~'-~~~~~~~~*:1' ~ ~ ~ ~ ~ ~ ~ -
I N ~~~~~~~~~~ ~~~~ Thy,.~~~~~~~~~~~~~ WKA
G;,) ''~ , ~5, T. ; 1 ¼ ', I I NAHNRTCISIA
t , I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~4 C ~~ ~-~sss -~~ .i* ~ ~ AGRICUTUREAREAS __ _ __ ,,.,,..,,~~~~~~ u..
SUBPOJET NO 13 11 KV HATAPHU - AMNT NAONGLIN
SUBPROJECT NO.14
115 KV UBON RATCHATHANI 2 - KANTHARALAK LINE
A. Objective
Objectives of Subproject No.14, 115 kV Ubon Ratchathani 2 - Kantharalak line and
substations, are to increase power supply capability to Kantharalak and nearby districts, to
improve reliability of services and voltage regulation, and to reduce system losses.
B. Project Scope and Description
Proiect Scope
The scope for the 115 kV Ubon Ratchathani 2 - Kantharalak line and substations consists of
the following constructions:
a) Construction of 115 kV Ubon Ratchathani 2 -Kantharalak transmission line, single
circuit on double circuit steel towers, using 795 MCM ACSR conductor, a distance of
approximately 55 km.
b) Expansion of 1 15 kV Ubon Ratchathani 2 Substation for one outgoing line.
c) Construction of new 115 kV Kantharalak Substation with two 3-phase, 115-22-11
kV power transformers, each rated OA/FA/FOA 30/40/50 MVA (land for the substation
has been purchased in TS.8 project).
d) Addition of communication system.
Project Description
The power supply for Kantharalak and nearby districts is available from the 115 kV Si Sa
Ket Substation via PEA 22 kV distribution lines at a distance of 65 km. Due to long
distribution line, PEA has therefore installed automatic voltage regulators (AVR) to boost
the voltage at the receiving end. However high power losses is still encountered and
reliability of power supply is not at the acceptable level.
The power demand in Kantharalak and nearby districts is expected to increase at high
growth rate, because PEA has planned to expand the distribution lines to serve more remote
villages. The construction of 115 kV Ubon Ratchathani 2 - Kantharalak line will support
the PEA's distribution project and increase reliability of the electric services in this area.
Figure of the proposed line route of the Subproject is shown in appendix
C. Project Implementation
The proposed commissioning date is August 1998.
.° \ ... 115 K T 3Y _ S C v O N i.-IIS 1: / 1'YS ONU KDAHA H AN N
X t o,]-.~ * \,,, -- N ~~ Z\,-' / L Th~~~~~. ~~ L'
N ~~~~~~~~UBON RATCHATHANI 11
~~~~~ ~ ~ ~ ~ ~ ~ ~ - -'~~~~~~~~~~-K
> '' I i i;:; 2
T~~~~~~~~\, / _ _
A I, ~ ~ ~ SUUST T[ TIO
WE~~~~~~~~~~~~~~~~~~~~N
-llVT0s KET . , / ,. A GRREA
fE~~~~~~~4 -w W ' t TwH~JIRiOs--e .' ............... J U 01
. "-(? ^ i~~~~~- ,..__,'r-.__ _ _. _ _ ___ ¶M EsltoirN CII|
SUBPROJECT NO. 14. 115 KV UBON RATCHATHANI 2- KANTHARALAK LINE 4;3
SUBPROJECT NO.15
115 KV SURIN - SAGKHA LINE
A. Objective
Objectives of Subproject No.15, 115 kV Surin - Sangkha line and substations, are to cope
with the increasing demand in Sangkha and nearby districts with satisfactory voltage
regulation and reliability, and also to reduce system losses.
B. Project Scope and Description
Project Scope
The scone for the 115 kV Surin - Sanackha line and zihztntions consits nf the fn1In.xAna
constructions:
a) Construction of 115 kV Surin - Sangkha line, single circuit on double circuit steel
towers, using 795 MCM ACSR conductor, a distance of approximately 49 km.
b) Construction of new 115 kV Sangkha Substation, equipped with two 3-phase, 115-
22-11 kV power transformers, each rated OA/FA/FOA 30/40/50 MVA.
c) Expansion of 1 15 kV Surin Substation for one outgoing line.
d) Land procurement for Sangkha Substation.
e) Addition of communication system.
A 4
Project Description
At present, power demand in Sangkha and nearby districts is supplied from Surin and Si Sa
Ket Substations via PEA 22 kV distribution lines at distance of 50 and 60 km respectively.
However, large voltage drop and excessive distribution line losses have been encountered
due to long distribution line. To meet the increasing power demand, further reinforcement
of the distribution system will not be economical in long-term.
The construction of a new substation at Sangkha district is proposed to increase the power
supply capability to the areas of Sangkha and its vicinity. The better quality and reliability
of services will be provided. The distribution system operation will have more flexibility
and also the distribution line losses will be substantially reduced.
Figure of the proposed line route of the Subproject is shown in appendix
C. Project Implementation
The proposed commissioning date is August 1998.
itr
fl--�- 41 Irl>Y\
!-,,ftSkv?, sEUDS'l AY1,W4 vitpon
d%- t4 0
(L�-A7;
t 'SC-
CH vA-
Am6hus PranuSun- -4-
L t3 7)Vr
K.6py, uN1,
�7 3 t i.LIWLIIII I
0 17-4" 7�"g, 74 0
tow v fK..Q
L;OP-K" TK;;m C0 -/1
vT7 73 -
ph)- 'Zan
lyT.
Wes-10. RESERVE FOREST AREAS (PERMIT PENDING)
21.- AGRICUTURE AREASN.
-V
SUBPROJECT NO. 15. 115 KV SURIN - SANGKHA LINE
SUBPROJECT NO.16,17
230 KV SURAT TRANI - THUNG SONG - NAKHON SI THAMMARAT LINE
A. Objective
Objective of Subproject No.16 , 17 230 kV Surat Thani - Thung Song - Nakhon Si
Thammarat lines and substations, is to prevent line overloading on the 230 kV Khanom -
Nakhon Si Thammarat and the 115 kV Thung Song - Nakhon Si Thammarat lines.
B. Project Scope and Description
Proiect Scope
The scope for the 230 kV Surat Thani - Thung Song - Nakhon Si Thammarat lines and
substations consists of the following constructions:
a) Construction of 230 kV double circuit Surat Thani - Thung Song - Nakhon Si
Thammarat transmission line, double circuit steel towers, using 2x1272 MCM ACSR
conductor per phase for Surat Thani - Thung Song line section (122 km) and lx1272 MCM
ACSR conductor per phase for Thung Song - Nakhon Si Thammarat line section (54 km)
for a total distance of approximately 176 km, on the right-of-way of the existing 115 kV
Surat Thani - Thung Song - Nakhon Si Thammarat line which will be dismantled. The new
230 kV line will be terminated at a new 230 kV switchyard at Thung Song, and the line
section between Thung Song and Nakhon Si Thammarat will be initially energized at 115
kV.
b) Expansion of Thung Song Substation for a new 230 kV switchyard. The new 230
kV switchyard will be constructed with the installation of two 3-phase 230/115-33 kV tie
transformers, each rated OA/FA/FOA 120/160/200 MVA, to integrate with the existing 115
kV system; and two 230 kV bays for lines to Surat Thani. The two additional 115 kV bays
are provided for lines to Nakhon Si Thammarat.
a 7
c) Expansion of 230 kV Surat Thani Substation for two outgoing lines to Thung Song
Substation.
d) Expansion of 115 kV Nakhon Si Thammarat Substation for one additional line to
Thung Song Substation.
e) Temporary installation of 3x20 MVAr 115 kV Shunt Capacitor banks at Thung
Song Substation.
f) Land procurement for the extension of the existing Thung Song Substation.
g) Addition of communication system.
Project Description
The major transmission line which supply power to the lower part of Southern Thailand is
the 230 kV Surat Thani - Khanom - Nakhon Si Thammarat - Phatthalung -Hat Yai 2 double
circuit line. The power flow on these 230 kV lines is being increased due to the rapid
growth power demand at the lower Southern area and the cement factory expansion at
Thung Song. To maintain the reliability of power supply, the transmission system
reinforcement to cope with the increasing demand is therefore required. Due to the
difficulty to obtain a new right-of-way in these areas, the construction of 230 kV double
circuit Surat Thani - Thung Song - Nakhon Si Thammarat line on the existing right-of-way
is proposed based on the least cost solution.
To maintain the continuous power supply for Thung Song Substation, two line section of
this subproject should be constructed at two different schedules. Construction of the double
circuit 230 kV Nakhon Si Thammarat - Thung Song line section should be completed
before dismantling the 115 kV Surat Thani - Thung Song line section.
Figure of the proposed line route of the Subproject is shown in appendix
C. Proiect Implementation
The proposed commissioning dates are June 1997 for 230/115 kV Thung Song - Nakhon Si
Thammarat line and August 1998 for 230 kV Surat Thani - Thung Song line.
E .9
-,3PAC HUAP 14NDI KH, A -'
I.i
r 3RC ! q O z H - R ', H .T A L t * rdW- :- ^ - ^ ;. 1 U .' 5 ~ ~ ~ ~ ~ ~ ~ C W a, t, ,,; Y Z _t, 4 4 M ,
oI ns n os Tln ror rr" .=,L
ABR JC N .1S- O'-.'LS U B P R O J E CT N O . 1 6 . 2 3 0 l v A r T H U N G S O N G - N AhwH O N S l T H A .\ l i ! N
PHU N PtBAN DO
U~~~~~~~~~~~~~~~-~
T.CAMAL~ei ~ _
SUBPROJECTNO. 17. 23 K',' SURA THANI THU G SONG LIN
SUBROJCT O.16. 230KY HU G SNG 4K O'~SI BA~MA~T INE~A
SUBPROJECT NO.18
230 KV KHLONG NGAE - YALA 2 LINE
A. Objective
Objectives of Subproject No.18, 230 kV Khlong Ngae - Yala line and substations, are to
improve reliability of supply and to provide sufficient power supply for future demand, at
Yala, Pattani, Narathiwat and Sungai Kolok substations.
B. Project Scope and Description
Proiect Scope
Thp -cnnp fnr thp 9Ifl kV T(hlnno Nop _ Yala line nnai q11hgttinnq rnnQktq nf tht- fnllnwino
constructions:
a) Construction of 230 kV Khlong Ngae - Yala line, double circuit steel towers, using
1272 MCM ACSR conductor, a distance of approximately 120 km. Part of the right-of-way
of the existing 115 kV Hat Yai 2 - Yala single circuit line, which will be dismantled, will be
used for the construction of the new 230 kV lines.
b) Construction of 230 kV Yala Switchyard with the installation of two 3-phase
230/115-33 kV tie transformers, rated OA/FA/FOA 120/160/200 MVA, to integrate with
the existing 115 kV system. Two 230 kV line bays are also provided to receive power from
230 kV Khlong Ngae Substation.
c) Expansion of 230 kV Khlong Ngae Substation for two outgoing lines.
d) Land procurement for the extension of Yala Substation.
e) Addition of communication system.
Project Description
The power demand at Pattani, Yala, Narathiwat and Sungai Kolok Substations are supplied
from Bang Lang Dam and 230/115 kV Hat Yai 2 Substation via 115 kV Hat Yai 2 - Yala
single circuit line and 115 kV Hat Yai 2 - Pattani double circuit line. The peak demand of
Yala, Narathiwat and Sungai Kolok Substation is increased at 7.3 % annually. The
generation from Bang Lang Dam has been occasionally derated in case of low head of water
level or shutdown for maintenance, and the power supply for those areas rely on the long
transmission lines from Hat Yai 2 Substation. For such the cases the reliabily of supply is
not meet the criteria and the system reinforcement is therefore required. The Khlong Ngae
switching station, a new substation being implemented under the EGAT-TNB Stage II
Interconnection Project, is considered as a firm power source. The construction of the
Khlong Ngae - Yala line and substations is proposed to effectively improve the reliability of
power supply and provide sufficient power for the increasing demand in the areas of Pattani,
Yala and Narathiwat provinces.
Part of the existing right-of-way of the 115 kV Hat Yai 2 - Yala line (Hat Yai 2 Junction,
approximately 27 km. southeast of Hat Yai 2 Substation, to Yala line section, see Figure
4.14), which will be dismantled, will be used for the new proposed 230 kV line. The
remaining section of the 115 kV line from Hat Yai 2 Substation to Hat Yai 2 Junction will
be energized to maintain the right-of-way for the future use. During dismantling the 115 kV
line and constructing the new 230 kV line on this line section, the Bang Lang power plant
has to generate at least 40 MW all the time.
Figure of the proposed line route of the Subproject is shown in appendix
C. Project Implementation
The proposed commissioning date is April 1998.
~~~~~~Ir ~ ~ ~ ~ ~ ~ r
I-. ~~~~~~~~~~~~~~~~~~~N.
;7.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~r
7~~~~~~~~~~~Vi
___ /~~~~~~~~~~~~~~~~~~1
>~~~~~~~~~~~~ .w. Vy.\
A U0A
;ML SBPOEC N. 8 20 V HONGME EAL LN
SUBPROJECT NO.19
230/115 KV PHANG NGA - PHUKET JUNCTION - PHUKET 2 LINE
A. Objective
Objectives of Subproject No.19, the 230/115 kV Phangnga - Phuket Junction - Phuket 2
lines and substations, are to increase the power supply capability and to maintain the
reliability and quality of power supply to Phuket Province.
B. Project Scope and Description
Project Scope
The scope for 230/115 kV Phangnga - Phuket Junction - Phuket 2 lines and substations
consists of the following constructions:
a) Construction of 230 kV double circuit Phangnga - Phuket Junction (about 6 km
north of Phuket 1 Substation) transmission line, double circuit steel towers, using 1272
MCM ACSR conductor, initially energized at 115 kV, a distance of approximately 76 km.
This transmission line will be constructed on the right-of-way of the existing 115 kV single
circuit Phangnga - Phuket 2 line of which the line section from Phangnga to the Phuket
Junction will be dismantled. One circuit of this new double circuit line will be connected
with the remaining 115 kV line section to 115 kV Phuket 2 Substation and the other circuit
will be connected with the new 115 kV compact line to Phuket 2 Substation as described in
(b) below.
b) Construction of the 115 kV Phuket 2 - Phuket Junction compact line on one side of
the existing right-of-way of 115 kV Phuket 2 - Phuket Junction line section, which is 25
meters width from the centre to the edge of the right-of-way, single circuit using 2x795
MCM ACSR conductor, a distance of approximately 12 km. This transmission line will be
connected with one circuit of double circuit 230 kV Phangnga - Phuket Junction line as
described in (a) above.
53
c) Expansion of 115 kV Phuket 2 Substation for one incoming line from Phan-guiga.
d) Expansion of 115 kV Phangnga Substation for one additional line.
e) Land procurement for the future 230 kV substation in Phuket Province (near the
Phuket Junction).
f) Addition of communication system.
Project Description
The power demand in Phuket Province is supplied from Phuket 1 and Phuket 2 Substations
which receive power from Phangnga Substation via one 115 kV double circuit line strung
with 477 MCM ACSR conductor and one 115 kV single circuit line strung with 150 sq.mm
AAC conductor. The existing transmission system will not sufficient to serve the power
demand in the future which is expected to increase at high growth rate, since Phuket Island
is the very famous tourist spot known as Pearl of Andaman. In order to secure reliability
and quality of power supply in Phuket Province, the reinforcement of transmission system is
required.
The difficulties of obtaining a new right-of-way in the Phuket island is foreseen, therefore,
the use of existing right-of-way for the new transmission line has been planned.
Consequently, to maintain the power supply reliability during dismantling the existing
transmission line, early construction of the new transmission line is recommended, and the
construction of a double circuit 230 kV Phangnga - Phuket Junction - Phuket 2 line (initially
energized at 115 kV) on the right-of-way of the existing 1 15 kV single circuit line Phangnga
- Phuket 2 (Phuket Junction) is proposed.
Figure of the proposed line route of the Subprojeet is shown in appendix
C. Project Implementation
The proposed commissioning date is November 1997.
N.~~~~ 2
't ' l 9 t '; 9 '' ' %<- t a
VU. 't*~A v5 ;J
4 - ____~~~~~~~~~~~136-q
nn1~~~~~~~~~~~~~~~~~~~~~~~~~*. 4S!e n. 11EV L-~W
l~~~~~~~~~~~ LX6', o! -~*. =~XI-
tn~~~~~~~~~~~~~~~~~~~~~~~~~~~ P H 1 U KEY J USN C I' ON ,_
7-.r- n r-
PNUKVT 2 r.V-.,- S - no.,
ft ~ ~ ~ ~ J
!^;.iXy zrmu s; Inl: ^1v: ~~~~~~~~~~~~~~- L ao Y ,2/r
SUBPROJECT ~ -NO UKET JUNCKVPAGGA-PUETJNTON-PUT'LN
(6 r
SUBPROJECT NO.20
115 KV YALA - NARATHIWAT LINE
A. Obiective
Objective of Subproject No.20, 115 kV Yala - Narathiwat line and substations, is to
improve reliability of power supply for Narathiwat Province.
B. Project Scope and Description
Project Scope
The scope for the 115 kV Yala - Narathiwat line and substations consists of the following
constructions:
a) Construction of 115 kV Yala - Narathiwat line, single circuit on double circuit steel
towers, using 795 MCM ACSR conductor, a distance of approximately 61 km.
b) Expansion of 115 kV Yala Substation for one tutgoing line.
c) Expansion of 115 kV Narathiwat Substation for one incoming line.
d) Addition of communication system.
Proiect Description
At present, the power demand in Narathiwat including Sungai Kolok district is supplied
from Yala substation via 115 kV single circuit line. The present peak demand is 31.8 MW
and expected to increase at 8.2 % annually. New additional transmission circuit is therefore
required to cope with the future high peak demand and to improve the reliability of power
supply. The construction of a new 1 15 kV Yala - Narathiwat line is proposed.
Figure of the proposed line route of the Subproject is shown in appendix
C. Project Implementation
The proposed commissioning dates is April 1998.
56
4-115 KV T10 P Wr 1'A NI / ;1? .2I7lrlbt Y' ' 17 onl
YAL1~ ~~~~~.14- P-Po -. q h
228~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~2
S;jA ~ ~ 4/JInM! 9~A.
4-115KV TO 11ANG L~~~~~~~N0 DAM ___ l*fT 9
SUBPOJEC NO.20. 15 V YAA - ARATIWATLIN
SU'BPROJECT NO.21
115 KV SURAT THANI - BAN DON LINE
A. Objective
Objectives of Subproject No.21, 115 kV Surat Thani - Ban Don line and substations, are to
improve reliability of power supply, to provide sufficient power supply for future demand,
and to reduce system losses.
B. Project Scope and Description
Project Scope
The scope for the 115 kV Surat Thani - Ban Don line and substations consists of the
following constructions:
a) Stringing second circuit on the existing double circuit towers of the 115 kV Surat
Thani - Ban Don line, using 477 MCM ACSR conductor, a distance of 13.4 km.
b) Expansion of 115 kV Surat Thani Substation for one outgoing line.
c) Expansion of 115 kV Ban Don Substation for one incoming line.
Project Description
The existing 115 kV Ban Don Substation is connected with 230/115 kV Surat Thani
Substation by a single circuit on double circuit steel towers 115 kV line, 13.4 km, using 477
MCM ACSR conductor. The present peak demand at Ban Don Substation is 52.4 MW and
expected to increase at the average growth rate of 6.5 % per year for the next 10 years
period.
.. 53
The reason for stringing only one circuit at the beginning is due to the fact that the power
demand in Ban Don was not too high that PEA could maintain the continuous power supply
by 33 kV distribution lines from Phunphin Substation in an emergency case when the 115
kV line trips out. With the high increasing demand, it is beyond the capability of the 33 kV
line to serve the demand in such an emergency case, therefore the stringing of second circuit
on the existing double circuit steel tower of the 115 kV Surat Thani - Ban Don line is
proposed to ensure the reliable power supply in Surat Thani area.
Figure of the proposed line route of the Subproject is shown in appendix
C. Project Implementation
The proposed commissioning date is March 1998.
59
f-23OP(VTOPRACHtUAPKHiFilKliAN' I~I .iŽ .[~I~
I.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~N
Z., 7.7 A 3~~~~~~~~~~~~~~~~~~~~~ 2 3 /.
k ~~~~~~ ~ ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~-~4 -____
.I~~~~~~~~~~~~~~~~~~~~~=5
4: z~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~C~ ~ t5V~3TTO
-V..~~~~~~~~~.TPAPSMI DON UM
SUBPROJECT NO 21 15 KV SURAT TiSUNSTANTDON LINE
SUBPROJECT NO.22
115 KV LAN KRABU - KHAM PHAENG PHET LINE
A. Obiective
Objective of Subproject No.22, 115 kV Lan Krabu - Kamphaengphet line and substations is
to improve the reliability and quality of power supply at Tak 1 and Kamphaengphet
Substations.
B. Project Scope and Description
Proiect Scope
T.bs scope fior thek. 1 1 V IrxL T en vaoli 1a-.n., ;ht l "A minea slubtaofns- -cr.sts of t.eA
following constructions:
a) Construction of 115 kV Lan Krabu - Kamphaengphet line, double circuit steel
towers, using 795 MCM ACSR conductor, a distance of approximately 47 km.
b) Expansion of 115 kV Lan Krabu Switchyard for two outgoing lines.
c) Expansion of 1 15 kV Kamphaengphet Substation for two incoming lines.
d) Addition of communication system.
Project Description
At present, the power demand at 115 kV Tak 1 and Kamphaengphet Substations is supplied
from the two single circuit 115 kV lines linking Tak 1 Substation with the 230 kV
Bhumibol switchyard and 115 kV Sukhothai Substation which further connecting with 230
kV Phitsanulok 2 Substation. In case that the 115 kV Bhumibol -Tak 1 line trips out, the
power demand for these two substations will be supplied from the 230 kV Phitsanulok 2
61
Substation via the 115 kV Phitsanulok 2 - Sukhothai - Tak 1 single circuit line for a total
distances of 120 km. This case will lead to overload on the 115 kV Phitsanulok 2 -
Sukhothal line section and the unacceptable low voltage at Tak 1 and Kamphaengphet
Substations.
Furthermore, Kamphaengphet Substation is an end substation which connects with Tak 1
Substation by a single circuit 115 kV line. Therefore, there is the possibility of total
blackout in Kamphaengphet area if this line section trips out.
Therefore, the construction of 115 kV Lan Krabu - Kamphaengphet is recommended.
Figure of the proposed line route of the Subproject is shown in appendix
C. Project ImDlementation
The proposed commissioning date is November 1997.
.. 62
0~~~~~~~~~~~~~~~1
im,~~~~~~~~~~~~~~~~~~~~~~~-
W*' I4aMa.n - /~~~~a -ortf~~~~~~~~~~~~~
K~~~~~~~~~~~~~~iVIMLI
~~~1 ~ ~ ha~~ w.~~ rn.n *"
f~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~f
S~~~,a Tba.arag Sa,.n ~ ~ ~ ~ ~ ~ ~ ~ ~~D W.gph
L'IIJI~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
tfllaTT,a'~~~a
/~~~~IMDV0
< N h,~~~~~~~ naajahk V~T.~~su'on~o
.g~~~~~~ah~~~~~K~~~~4 ~~~~~~ 1 - "B . .W m '
'1/- ~~~~~~AWAN4~~~~ A2OIVTNAbIN5WA r, Inaawn
SUPRJCTNO 2.11 V ANKKA -KMPAPGHE LN
SUBPROJECT NO.23
115 KV MAE MOH 3 - LAMPANG 2 LINE
A. Objective
Objective of Subproject No.23, 115 kV Mae Moh 3 - Lampang 2 line and substations is to
increase power supply capability to cope with the increasing demand at Lampang 2 and
Lamphun 2 Substations.
B. Project Scope and Description
Project Scope
The scope for the 115 kV Mae Moh 3 - Lampang 2 line and substations consists of the
following constructions:
a) Construction of 115 kV Mae Moh 3 - Lampang 2 line, double circuit steel towers,
using 2x795 MCM ACSR conductor per phase, a distance of approximately 27 km.
b) Modification of 115 kV Mae Moh 3 Switchyard from Main & Transfer bus
arrangement to Breaker and a Half scheme and expansion for two outgoing line.
c) Modification of 115 kV Lampang 2 Substation from tapped substation to fully
equipped circuit breaker substation for terminating both circuits of the 115 kV double
circuit Mae Moh 2 - Lamphun 2 line and the expansion of 115 kV bays for two incoming
lines from Mae Moh 3 switchyard.
d) Addition of communication system.
64.
Proiect Description
At present, the power demand at the 115 kV Lampang 2 Substation is supplied from one
circuit of the 115 kV double circuit Mae Moh 2 - Lamphun 2 line. The power demand at
Lampang 2 Substation is increasing highly due to the requirement of the cement factory
which is being constructed in this area. The existing 115 kV line also transmits generated
power from Mae Moh Power Plant to Lamphun and Chiang Mai areas; therefore, with the
large power demand at Lampang 2 Substation, heavy line loading on the 115 kV Mae Moh
2 - Lampang 2 line section is observed, and overloading on this line section will occur if one
circuit of the double circuit trips out. Therefore, construction of a new 115 kV Mae Moh 3 -
Lampang 2 line is proposed together with the modification and expansion of Mae Moh 3
and Lampang 2 substations.
Figure of the proposed line route of the Subproject is shown in appendix
C. Project Implementation
The proposed commissioning date is December 1997.
65
0~~~~~~~~~~~~~~~~~~~~' oitI
-- _______________ / I~~~~~~~~~ ~~~~~~~~ F2 "L 1KV ('
5 MY 6.11 ~ ~ ~ ~ ~ ~ ~ ~ Og~~
W M~~~ - - - 11141~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~z
SUBPROJECT NO. 23. 115 KV MAE M01-1 3- LANIPANG 2 LINFY
SUBPROJECT NO.24
115 KV CHIANG MAI 2 - MAE TAENG LINE
A. Objective
Objectives of Subproject No.24, 115 kV Chiang Mai 2 - Mae Taeng line and substations,
are to provide more reliable power supply to Mae Taeng and nearby areas, to improve
quality of power supply and also to reduce system losses.
B. Project Scope and Description
Proiect Scope
The scope for the 115 kV Chiang Mai 2 - Mae Taeng line and substations consists of the
following constructions:
a) Construction of 115 kV Chiang Mai 2 - Mae Taeng transmission line, single circuit
on double circuit steel towers, using 795 MCM ACSR conductor, a distance of
approximately 42 km.
b) Expansion of 1 15 kV Chiang Mai 2 Substation for one outgoing line.
c) Construction of a new 1 1 kV Mae Taeng Substation, equipped with two 3-phase,
115-22 kV power transformers, each rated OA/FA/FOA 30/40/50 MVA.
d) Land Procurement for Mae Taeng Substation.
e) Addition of communication system.
67,
Project Description
Tne power demand in Mae Taeng and its vicinity is presently supplied from 1 15 kV Chiang
Mai 2 Substation and Mae Ngat small hydro power plant through PEA 22 kV distribution
system. According to the demand forecast in this area, the existing PEA system will not
meet the expected increasing demand, and will not be able to support the PEA's rural
electrification program to expand its distribution system to several remote villages in this
area.
To meet the increase of power demand at Mae Taeng and its vicinity with more reliable
power supply, the construction of 115 kV Chiang Mai 2 - Mae Taeng line and new
substation at Mae Taeng is proposed.
Figure of the proposed line route of the Subproject is shown in appendix
C. Project Implementation
The proposed commissioning date is June 1998.
3
d_WWNN RESERVE FOREST AREAS (PERMIT PENDING) ?. , u ivWs^..l _ ~~AGRICUTURE AREAS ; "
0~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ 12
s nS,: Hda t1 t~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~A
, X:TY ;ISTUTINCrwrt ura. \ .^x : = \r 2 *\ a- 2 1gl*,/* ;
SUBPOJEC NO.24. 15 hV CHANG TAI A TEGLNEADSBSAIN
-A-~h
SUBPROJECT NO.25
230 KV RATCHABURI 2 - PRACIIAUB KHIRIKlHUN LINE
A. Objective
Objectives of Subproject No.25, 230 KV RATCHABURI 2 - PRACHAUB KHIRIKHUN
LINE is to improve in old right of way.
B. Project Scope and Description
Project Scope
The scope for the 230 KV RATCHABURI 2 - PRACHAUB KHIRIKHUN LINE consists of
thPi fnfl%IC7tAnCin rAnIItQrticnn -
Construction of circuit steel towers, using 1272 MCM ACSR conductor, a distance
of approximately 11 km. on old right-of-way of the existing.
Figure of the proposed line route of the Subproject is shown in appendix.
79-
S<kS~~~ ~~~~ ~ ~ ~~~~~~~~ I, 'X
>-__, / _ oiS 4~~~~~~~~~~~~~~~~~~~~~~' 2-3 lOtie
/~~~~~~~~~~~~~~~~~~~~~
< LoosJoo 47 AIV '1 .
4,,4 -- o O 'S \
J, 11 4 + S , t
S-T NO. 2. 23 K A R 2 - P1 AB KT U LINE
4 _/_ / _ \ , >
o~ ~ g MU\^ g75 \ ! ,'= C I U UR RA
/ - n ~~~nil 3+805.06 ,
niin.nac r<n. ,a_ ntl - .^ _
SUBPROJECT NO. 25. 230 KV RATCIJABURI 2pRACHAUB KHIRIKHUN LINE
3. Legal and Administrative
Environmental Impact Assessment (EIA) is not required under current Thailand law and
regulation for the Transmission System Expansion Project No. 9 and TNB StageIl Inter
Connection. The EIA for the transmission system will be expected only when all or a
portion of the transmission line routes are located in Watershed classification class 1 B (or
wildlife sanctuary area, or national park area, or mangrove area). The project routes do not
traverse any of these. This report is a focused environmental analysis of environmental
impacts of project components and their mitigation measures as required by the World Bank.
Land Use Permits: Land use permits are required from the Royal Forest Department for
projects involving "forest areas." There are twice kinds of "forest" classification: protected
forest and reserved forest and economic. Environmental Impact Assessements are required in
order to obtain land use permits in protected forest. EIA's are not required to obtain land use
permits in reserve forest and economic.
EGAT obtains permits for land use in forest areas in the following manner:
i) Map sheets showing reserve and protected forest areas are obtained from the Royal
Forest Department.
ii) EGAT Power System Planning Division lays out the transmission line route on
1:250,000 scale maps.
iii) EGAT Survey Division translates these routes onto 1:50,000 maps and then
surveys the routes in the field . When the routes are laid out on 1:50,000 scale maps, the
reserve and protected forest areas, and other areas prohibited or to be avoided according to the
EGAT environmental route planning policy are identified, and the routes changed as
necessary. A ground survey of the line route is then done, and the line is again rerouted as
necessary to avoid structures, for instance.
iv) The information the on route is then sent to the EGAT land Division. The land
Division then applies to the Royal Forest Department for permits to traverse reserve or
protected forest areas. EGAT goes into the field with the Forest Officials to survey the
p ..
*1%
identified forest areas. This survey is required under Royal Forest Department regulations.
The information gathered in the joint EGAT/ Royal Forestry Department survey is used in the
permitting process. In certain cases, EGAT would be requested to pay for compensation to
the Royal Forest Department. All cases are reviewed by the Director General of the Royal
Forest Department and the Ministry of Agriculture and Cooperatives.
v) After the permit is granted by the Royal Forest Department, EGAT and the Royal
Forest Department do a detailed inventory of the forest resources, trees to be cut are marked,
and EGAT signs the survey report.
vi) The Forest Industry Organization (under the Department of Agriculture and
Cooperative) does the actual right of way clearing.
3.1 The Environmental Impact Assessment determined by the project features.
The Ministry of Science, Technology and Environment authorized through the Enhancement
and Conservation of Act B.E. 1992 has issued the announcement on types and scales of
project or activities to be undertaken by the government, state enterprise or private sectors
that require the analysis on environmental impacts assessment report in the first issue (1992)
of which the list attached as Table 2.
Moreover, The Ministry has further issued an addition notification for types and scales of
project or activities that are required for environmental impact assessment report in the
second issue (1992) wherein more details are stated as shown in Table 3
7 3
Table 2 Notification for Types and Sizes of Projects or Activities Requiredan Environmental Impact Assessment Report
Items Types of Project or Activities Scales1 Dam and Reservior Storage volume of 100 million cubic meters
(MCM) or more or storage surface area of15 square-kilometers or more
2 Irrigation Irrigation area of 80,000 rais (12,800hectares) or more
3 Commercial Airport All scales4 Commercial Port and Harbour With capacity for vessels of 500 tons-gross
or more5 Mass Transit System and Expressway as All scales
defined by the Mass Transit andExpressway Act or Project similar toExpressway or Rail Type Mass TransitSystem
6 Highway or road as defined by the All project with equivalents to or above theHighway Act, Passing through minimum standard of rural highwayfollowing areas: including roaded expansion(a) Wildlife Sanctuaries and WildlifeNon-Hunting Areas as defined by theWildlife Conservation and ProtectionAct.(b) National Park as defined by NationPark Act.(c) Watershed area classified as class 2by the Cabinet Resolution(d) Mangrove Forests Designated asNational Forest Reserve(e) Coastal Area within 50 meters fromthe Maximum Sea Level
7 Coastal Reclamnation All scales8 Mining as defined by the Mineral Act All scales9 Thermal Power Plant Capacity of 10 megawatt or more10 Hotel or Resort Facilities in areas 80 rooms or more
adjacant to rivers, coastal areas , lakes orbeaches or in the vicinity of NationalParks or Historical Parks
11 Building in areas adjacant to rivers, Height of 23 meters or more or total of allcoastal areas , lakes or beaches or in the floors area or area of any floor in the samevicinity of National Park or Historical building isPark 10,000 square meters or more
rp ,l
Table 2 (Con'd)Items Types of Project or Activities Scales
12 Residential Condominium as defined hv RO iinits or morethe Condominium Act.
13 Land appropriation for residential or Land plot is 500 units or more or total landcommercial purpose area exceed 100 rais (16 hectares)
14 Hospital or Nursing Home:(a) In case locates in area adjacant to (a) in-patient's bed of 30 beds or morerivers , coastal areas , lakes or beaches(b) In areas other Than (a) (b) in-patient's bed of 60 beds or more
15 All Project or Activities in Watershed All scalesarea classified as lB by the CabinetResolution
16 Industries(1) Petrochemical Industry Using raw materials which is produced from
oil refinery and/or natural gas seperationwith production capacity of 100 tons/day ormore
(2) Oil Refinery All scales(3) Natural Gas Seperation All scales(4) Chlor-Alkaline Industry requiring Production capacity of each or combinedNaCl as raw material for production of productes of 100 tons/day or moreNa2CO3 , NaOH, HCI, Cl2 , NaOCl andBleaching Powder(5) Irons and/or Steel Industry Pr6duction capacity of 100 tons/day
(production capacity calculated by usingproduction capacity of furnace in ton/hourmultiplied by 24 hours)
(6) Cement Industry All scales(7) Smelting Industry other than Iron Production capacity of 50 tons/day or moreand Steel(8) Pulp Industry Production capacity of 50 tons/day or more(9) Pesticide Industry or industry All scalesproducting Active Ingredient bychemical process(10) Chemical Fertilizer Industry using All scaleschemical process in production
Source : Notifications of Ministry of Science, Technology and Environmental, August 24,BE 2535 (1992) issued under the Enhancement and Conservation of National EnvironmentalQuality Act BE 2535 (1992)
r1Lr
Table 3 Additional Types and Scales of Projects or Activities to be required for anEnvironmental Impact Assessment Report
Items Types of Project or Activities Scales1 Sea dumping All scales2 Any building locating at the riversides, seashore Scale of building:
, seaside, lake or nearby National Park, (1) The height is above 23 m.Historical sites which would be affected on the (2) The total area of all storeys orenvironmental quality either one is equal to 10,000 sq.m.
and above3 Condominium specified in the law Those with over 80 rooms4 Land estate for residence or for commercial 500 plots and above or the area of
purpose plot is over 100 rais5 Hospital or Public health stations
(1) Those located at the riversides , seasides, 5.1 Having 30 patient beds and abovelakes or seashore which would affect on theenvironmental quality(2) Those are not in (1) 5.2 Having 60 patient beds and above
6 Industry with some toxic or pesticide through All scaleschemical process
7 Industry concerning the production of chemical All scalesfertilizer with chemical process
8 Highway or road as specified in the law and pass All scales equivalent or lower thanthrough: the standard of rural highway
including the embankment to beconstructed or the existing one
(1) Wildlife sanctuary and non-hunting area(2) National Park(3) Watershed area class II by the Cabinetresolution(4) Mangrove forest area identified as Nationalforest reserve(5) Coastal area within 50 m. from the maximumwater level
Source: Notifications of Ministry of Science, Technology and Environmental, September 9BE 2535 (1992) issued under the Enhancement and Conservation of National EnvironmentalQuality Act BE 2535 (1992)
3.2 The Environmental Impact Assessment or Initial Environmental
Examination determined by the area features
(a) Those areas required for the Environmental Impact Assessment is the
conservation forest area identified by law and the cabinet concerning the natural resource
conservation classified as 4 types:
1) Wildlife sanctuary announced through the Wildlife Preservation and
Protection Act 1992.
2) National Park through the Act concerned in 1961.
3) Watershed area class 1 specified by the NEB through the Cabinet
Resolution.
4) Conservation area specified for land utilization in mangrove forest area
of Thailand through the Cabinet Resolution dated December 15, 1987.
(b) Areas required for the Initial Environmental Examination is the addition
forest conservation area (C) and submit a report to the Royal Forest Department for
permission to use area of concern .
77y
4. Route Selection Criteria and Mitigation Strategies
4.1 EGAT'S Environmental Guidelines for Transmission System.
For the construction of transmission system i.e., in selecting the line routes for
transmission lines and substation sites, EGAT use to minimize the impact on the
environmental elements, like forest, wildlife, watershed area, population, archeological
sites and scenery to the most feasible environmental criteria. The EGAT's
environmental guidelines for transmission systems as follows:
4.1.1 Route Selection
1) Not locating a line through the following
(1) Restricted watershed area class 1A, wildlife sanctuary, national park and
mangrove forest area
(2) Holy places, archaeological sites and government site
2) Avoiding to locate a line through the following
(1) Watershed area class IB, the addition forest conservation area (C) by laws
and other conservation areas
(2) Community and developed areas
3) Avoiding to locate a line running parallel with, or close to telephone and
telegraph cables in a long distance.
4) Avoiding to locate a line near an airport.
73
4.1.2 Vegetation Clearance
Those trees existing in the area along the transmission line mentioned will be cut down in the
basis of necessity for the construction work and maintenance of the transmission line only
and in compliance with the above mentioned criteria. And those trees with possibility to fall
down into the transmission line area must be cut down since it would cause any danger to the
transmission system.
Tree cutting down will be considered in the area whereas the transmission system would be
possibly affected and it will be done in compliance with the criteria stated in the meeting
solution on the transmission line assembly.
1) Trees and plants will be cut down to the level of soil surface and not permitted to
grow furthermore in the area where located the transmission posts and the surrounding bases
within a distance of 4 meters except those to be stamped as stated in the Forest Regulations
can be kept the height at not exceeding 0.30 meters above ground.
2) Trees along the transmission lines will be completely cut for 6 meters wide (3 m.
far from each side started from the center of the transmission post).
3) Trees/plants outside the mentioned areas in (1) and (2) will be kept at 0.30 meters
high above ground.
4.2 EGAT Policy on Post-Project Land Use
According to EGAT regulations the landowners post-project rights on land use will vary
according to the degree of impact of the different components of a project. Land used as
premises land for substations and other fixed structures will be definitely bought from the
owners directly.
Land used as bases for transmission lines towers will remain property of the landowners but
will have to be permanently cleared of any crop and tree. Although these areas will remain
property of the landowners these latter will lose all cultivation rights on them. Also in this
case these areas will be compensated in full to their original owners or users.
Land included in the right of way of transmission lines instead, will be given back to their
previous owners after construction. After construction the landowners will retain annual crops
cultivation rights on these lands. However, the right to cultivate perennial crops and trees will
be subjected to a number of limitations. These are:
80
1. 115 kV AND 230 kV TRANSMISSION LINE (GENERAl)
Land include in the right of way of transmission line as a 24 meters wide corridor for 115 kVtransmission line and a 40 meters for 230 kV transmission line. The right to cultivateperennial crops and trees will be subjected to a number of limitations as follow.
1) No building of household and other structure in the right of way oftransmission line.
2) Trees and plants will be cut down to the level of soil surface and notpermitted to grow furthermore in the area where located the transmission posts and thesurrounding bases within a distance of 4 meters except those to be stamped as stated in theForest Regulations can be kept the height at not exceeding 0.30 meters above ground.
3) Trees along the transmission lines will be completely cut for 6 meters wide(3 meters each side started from the center of the transmission post) and kept the height at notexceeding 0.30 meters above ground.
4) Trees and plants outside the mentioned areas in 2) and 3) (3-12 meters eachside started from the center of the transmission post for 115 kV and 3-20 meters far fromeach side started from the center of the transmission post 230 kV Transmission Line) will bekept at 3 meters high above ground.
5) Those trees existing in the area along the transmission line mentioned willbe cut down in the basis of necessity for the construction work and maintenance of thetransmission line only and in compliance with the above mentioned criteria in (1), (2), (3) and(4) but it must not be the obstacle for the maintenance work.
6) Those trees with possibility to fall down into the transmission line areamust be cut down since it would cause any danger to the transmission system.
Criteria for Land Use and Vegetation Clearance230 KV Transmission Line System (40 m Right of Way)
_ ~~~~~~~~~~~~~~~~~~~~~~~~I
3m 3m 3mn 3m
(2) 3 173 ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~~3
20
1. No tree growing, except seasonal and grain crop are allowed within 3 m wide of corridor.2. Cash crop is allowed with height less than 3 m in the outter area of 3 m limited zone from mid line.
CO
I
Criteria for Land Use and Vegetation Clearance115 KV Transmission Line System (24 m Right of Way)
3m 3m 3 m 3m
3 12
1. No tree growing, except seasonal and grain crolp are allowed within 3 m wide of corridor.2. Cash crop is allowed with height less than 3 m in the outter area of 3 m limited zone from mid line.
2. 500 kV TRANSMISSION LINE (GENERAL)
Land include in the right of way of transmission line as a 30 meters wide corridor for 500 kVtransmission line. The right to cultivate perennial crops and trees will be subjected to anumber of limitations as follow.
I) No building of household and other structure in the right of way oftransmission line.
2) Trees and plants will be cut down to the level of soil surface and notpermitted to grow furthermore in the area where located the transmission posts and thesurrounding bases within a distance of 4 meters except those to be stamped as stated in theForest Regulations can be kept the height at not exceeding 0.30 meters above ground.
3) Trees along the transmission lines will be completely cut for 6 m. wide (3meters each side started from the center of the transmission post) and kept the height at notexceeding 0.30 meters above ground.
4) Trees and plants outside the mentioned areas in 2) and 3) (3-18 meters eachside started from the center of the transmission post) will be kept at 3 meters high aboveground.
5) Some cash crops are excluded with the following conditions:
(1) those grown in a distance of 3 meters far from the center oftransmission post for both sides will be kept at not exceeding 3 meters high.
(2) those grown in a distance of 18 meters far from the center oftransmission post for both sides will be kept at not exceeding 5 meters high.
(3) those grown in a distance of 22 meters far from the center oftransmission post for both sides will be kept at not exceeding 7 meters high.
(3) those grown in a distance of 27 meters far from the center oftransmission post for both sides will be kept at not exceeding 10 meters high.
6) Those trees existing in the area along the transmission line mentioned willbe cut down in the basis of necessity for the construction work and maintenance of thetransmission line only and in compliance with the above mentioned criteria in (1), (2), and (3)but it must not be the obstacle for the maintenance work.
7) Those trees with possibility to fall down into the transmission line areamust be cut down since it would cause any danger to the transmission system.
84-
'1 L' 14tt IUt I LtdiIu Uav . llU V ULtatliul tk1ALd1 411ce
500 KV Transmission Line System (60 m Riglht of Way)
lOin 7m \~~~~~~~~~~~~~~~~~~<~~~~4 ,//~~~~~~~~( / 1~~~~~I0 ni__ _ _ _ __ _ _ _ __________ _ _ _ _ _ _ _ _ _ _
3 m -* mI) ~
X~~~~~~~~~~~~~~~~~~~-~4 5 3
(5) (4) (3) (2) (1)311 27 22 18 3 3 l I 222 27 30
1. No ti-ec gi-owilg, , except seasonal an(d grailn ClOp are allowed ivitiniti 3 in wide of corridor.
2. Cash crop is allovved with heighit less thani 3 In in the outter ar-ea of 3 in limited zone fi-om nmid line.3. Cash cl-oil is allowved withi hciglit less than 5 m in the outter arca of 18 in limited zone froni mind line.4. Cash clrop is allowed witih hicighit less thani 7 m in the outter area of 22 in limited zone froni mid line.
5. Cash cr-op) is allowed witih heighit less thian 10 m in the outter area of 27 mi limited zone from mind line.6. No planting of sugarcane in right of way
CID
3. 115 kV TRANSMISSION LINE IN SOUTHERN AREA
Land include in the right of way of transmission line as a 50 meters wide corridor for 115 kVtransmission line. The right to cultivate perennial crops and trees will be subjected to anumber of limitations as follow.
1) No building of household and other structure in the right of way oftransmission line. Except 12-25 meters far from each side started from the center of thetransmission post which were built before EGAT annoucment for construction thetransmission line.
2) Trees and plants will be cut down to the level of soil surface and notpermitted to grow furthermore in the area where located the transmission posts and thesurrounding bases within a distance of 4 meters except those to be stamped as stated in theForest Regulations can be kept the height at not exceeding 0.30 meters above ground.
3) Trees along the transmission lines will be completely cut for 6 m. wide (3meters each side started from the center of the transmission post) and kept the height at notexceeding 0.30 meters above ground.
4) Trees and plants outside the mentioned areas in 2) and 3) (3-12 meters eachside started from the center of the transmission post) will be kept at 3 meters high aboveground.
5) Some cash crops are excluded with the following conditions:
(1) those grown in a distance of 3 meters far from the center oftransmission post for both sides will be kept at not exceeding 3 meters high.
(2) those grown in a distance of 12 meters far from the center oftransmission post for both sides will be kept at not exceeding 7 meters high.
(3) those grown in a distance of 20 meters far from the center oftransmission post for both sides will be kept at not exceeding 10 meters high.
6) Those trees existing in the area along the transmission line mentioned willbe cut down in the basis of necessity for the construction work and maintenance of thetransmission line only and in compliance with the above mentioned criteria in (1), (2), and (3)but it must not be the obstacle for the maintenance work.
7) Those trees with possibility to fall down into the transmission line areamust be cut down since it would cause any danger to the transmission system.
Criteria for Land Use and Vegetation Clearance115 KV Transmission Line System, Southern Thailand (50 m Right of Way)
10 m lo10m______________________________________ _
7m 7m
(4) (3) (2) (1)25 20 12 3 3 .- - , 2 _ 2
1. No tree growing, except seasonal and grain crop are allowed within 3 m wide of corridor.2. Cash crop is allowe(d with height less than 3 in in the outter area of 3 m limited zone from mid linc.3. Cash crop is allowedl with height less than 7 m in the outter area of 12 m limited zone fronm mid line.4. Cash crop is allowved with height less than 10 m in the outter area of 20 m limited zone from mid line.
.-d
4. 230 kV TRANSMISSION LINE IN SOUTHERN AREA
Land include in the right of way of transmission line as a 50 meters wide corridor for 230 kVtransmission line. The right to cultivate perennial crops and trees will be subjected to anumber of limitations as follow.
1) No building of household and other structure in the right of way oftransmission line. Except 20-25 meters far from each side started from the center of thetransmission post which were built before EGAT annoucment for construction thetransmission line.
2) Trees and plants will be cut down to the level of soil surface and notpermitted to grow furthermore in the area where located the transmission posts and thesurrounding bases within a distance of 4 meters except those to be stamped as stated in theForest Regulations can be kept the height at not exceeding 0.30 meters above ground.
3) Trees along the transmission lines will be completely cut for 6 m. wide (3meters each side started from the center of the transmission post) and kept the height at notexceeding 0.30 meters above ground.
4) Trees and plants outside the mentioned areas in 2) and 3) (3-20 meters eachside started from the center of the transmission post) will be kept at 3 meters high aboveground.
5) Some cash crops are excluded with the following conditions:
(i) those grown in a distance of 3 meters far from the center oftransmission post for both sides will be kept at not exceeding 3 meters high.
(ii) those grown in a distance of 20 meters far from the center oftransmission post for both sides will be kept at not exceeding 10 meters high.
6) Those trees existing in the area along the transmission line mentioned willbe cut down in the basis of necessity for the construction work and maintenance of thetransmission line only and in compliance with the above mentioned criteria in (1) and (2) butit must not be the obstacle for the maintenance work.
7) Those trees with possibility to fall down into the transmission line areamust be cut down since it would cause any danger to the transmission system.
Criteria for Land Use and Vegetation Clearance230 KV Transmission Line System, Southern Thailand (50 m Right of Way)
10 m I ~~~~~~~~~~~~~~~~~~~~~~10 im
3 m
(3) (2) (1)25 20 3 3 17 21_
1. No tree growing, except seasonal and grain crop are allowed within 3 m wide of corridor.
2. Cash crop is allowed with height less than 3 m in the outter area of 3 m limited zone from mid line.
3. Cash crop is allowed with height less than 10 m in the outter area of 20 m limited zone from mid line.
CID
5. Environmental Issues
There is no watershed area class 1A and 1B, wildlife sanctuary, national park ,mangrove
forest area and the addition forest conservation area (C) near any transmission line of
subproject on Transmission System Expansion Project No. 9 and TNB Stage II Inter
Connection Project, so these lines are not required to have Environmental Impact
Assessments or Initial Environmental Examination. The transmission lines will not pass
through the environmentall , sensitive areas.
Environmental Impact on Water Resources: Potential impacts of a transmission system on
water quality are related to construction activities: surface run-off from construction sites;
wastewater from the temporary office and construction camps; and, wastewater contaminated
with oil or grease from machinery which will be mitigated . The construction sites, temporary
office and construction camp will locate more than 100 meters far from water resource or
stream and all of slope area is less than 45 degree. The construction will follow the EGAT'S
Environmental Guidelines for Transmission System.
Forest resources: There are 25, with a length of approximately 159.55 kilometers, that pass
through the forest. There are no watershed area class 1A and I B, wildlife sanctuary, national
park ,mangrove forest area or addition forest conservation area (C) near any transmission line
of subproject on Transmission System Expansion Project No. 9. TNB Stage II Inter
Connection Project is 3 tranmission lines ,a distance of approximately 213.5 kilometers, that
pass through the forest .Many of these 'forest areas' have already been cleared for agriculture
are other purposes . The attached route maps show the actual conditions found in walk-
throughs. There is no watershed area class 1A and IB, wildlife sanctuary, national park,
mangrove forest area or addition forest conservation area (C) near any transmission line of
subprojects .
Wildlife: There are 159.55 kilometers of Transmission System Expansion Project No. 9 and
213.5 kilometers of TNB Stage II Inter Connection Project that pass through the forest that
are not significant for conservation. Many of the reserve forest areas where the transmission
lines traverse have already been cleared for agriculture and other purposes (see maps). The
wildlife are mostly small in size and they can adjust well to various human activities.
Land Use: The project construction phase will cause the loss and limitation of agricultural land
use in the ROW; however, the impact is on a small total land area because most of the crops
have a short growing season and they do not exceed the height restrictions for vegetation in the
right of way. Transmission System Expansion Project No. 9 and TNB Stage II Inter
Connection Project have tranmission lines which pass through the agricultural land totalling
about 1,121.45 and 360.3 km . The Maintenance of the right of way will follow the EGAT
policy on post-project land use.
Cultural and Esthetic Resources: There were no cultural or esthetic resources that would
potentially be impacted along the Transmission System Expansion Project No. 9 and TNB
Stage II Inter Connection Project.
PCB Management: Transmission System Expansion Project No. 9 and TNB Stage II Inter
Connection Project will not involve replacement of equipment potentially contaminated with
PCB. EGAT has surveyed all potentially contaminated electrical equipment.
Electromagnetic Frequency (EMF): A full discussion of EMF effects and EGAT transmission
lines is included in the Environmental Impact Analyses of the Greater Bangkok Area, and the
Environmental Report for 500 KV Transmission Line for IPP's.
91
7. Mitigation Measures
Construction: the following mitigation measures are used during construction of the power
lines.
1. Avoiding to construct a new access for construction purpose, but trying to
utilize the existing tracts.
2. Not cutting the trees over EGAT's criteria.
3. Clean up the construction sites upon the completion of the construction work.
4. Along the valley, cutting down, only where necessary, the trees considerably to
be hazardous to the stability of the transmission system.
5. The landowners are permitted to cultivate the economic crops at EGAT 's
criteria along the right of way corridor.
6. Upon completion of transmission line construction work, ground cover around
the towers will be planted and also land contouring when required to provide a protective
covering for the earth and to prevent the soil erosion.
Natural Resources: Foundation towers and construction activities including transportation of .
construction materials, material storage and worker housing would be located at least 50
meters away from surface water resources to avoid soil erosion. In case it is necessary to use
areas closer to water resources, soil barriers would be built to block erosion and
sedimentation. Vegetative cover would be replaced along streambanks and the surrounding
project site if disturbed, to prevent soil erosion. In all areas, sanitary latrines will be
constructed for workforce and temporary offices, and good housekeeping measures will
minimize potential water contamination due to oily waste or chemicals.
Forest Resources: The following mitigation measures would be followed: (i) deforestation to
be done only in the right of way ii) reforestation is the responsibility of EGAT, the area of
reforestation would be more than the area of national forest reserve used for the ROW; iii) in
case private land is used in construction, it is the responsibility of EGAT to contact the owner
92)
anTd pay fair compensation. Many of the 'forest areas' along the routes have already been
cleared for agriculture and other purposes (see map section).
Wildlife: The impacts can be controlled by: i) deforestation only in the right of way
area; ii) prohibition on disturbing wildlife, including nests, eggs, holes, hollows and other
habitat; iii) prevention of noise pollution by limiting work hours between 8.00 am and 16.00
pm., all work to be forbidden at night.
Land Use: EGAT would plan all the project activities including material transportation, pole
mounting and others in the dry season, because most of the crops would already have been
harvested. Removal of agricultural plants (particularly perennials) would be done only as
necessary and compensation paid. Farmers would be allowed to grow short-lived crops with
heights of less than 3 meters in the ROW after construction.
Monitorini!:
The following monitoring plan will be adopted to track the effectiveness of mitigation
techniques, and to address recognized problems in an appropriate and timely manner. This
regular scheduled monitoring program will consist chiefly of visual inspections during
construction and operation for:
o erosion along access roads, substation and transmission tower foundations;
o encroachment of settlements within rights of ways, encroachment of settlements
within protected areas via transmission line access roads, exploitation of forest
resources in protected areas via access roads;
o vegetation clearances below transmission lines, and invasion of exotic species along
right of ways;
o transforner fluid leakage and spills.
ABBREVIATIONS
ACSR - Aluminum Conductor Steel Reinforced
cct-km - Circuit-Kilometer
DC/ST - Double Circuit/Steel Tower
DSM - Demand Side Management
EGAT - Electricity Generating Authority of Thailand
F.C. - Foreign Currency
IDC - Interest During Construction
IPP - Independent Power Producer
L.C. - Local Currency
MTHB - Million Baht
MEA - Metropolitan Electricity Authority
MCM - Thousand Circular Mils
MVA - Megavolt-ampare
MVAR - Megavolt-ampere Reactive
MW - Megawatt
NEPO - National Energy Policy Office
NESDB - National Economic and Social Development Board
NESDP - National Economic and Social Development Plan
PDP - Power Development Plan
PEA - Provincial Electricity Authority
TDRI - Thailand Development Research Institute
TLFS - Thailand Load Forecast Subcommittee
THB - Baht
TNB - Tenaga Nasional Berhad
USD - US Dollar
VAT - Value Added Tax
W/O - Without
9.4