world trade center construction redevelopment subcommittee … · 2015-06-04 · block 169 / lot...

8
World Trade Center Construction Redevelopment Subcommittee April 29, 2010

Upload: others

Post on 20-Jun-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: World Trade Center Construction Redevelopment Subcommittee … · 2015-06-04 · block 169 / lot 2.02 7,000 sq. ft. nj transit storage harrison car maintenance facility lester m

World Trade Center ConstructionRedevelopment Subcommittee April 29, 2010

Page 2: World Trade Center Construction Redevelopment Subcommittee … · 2015-06-04 · block 169 / lot 2.02 7,000 sq. ft. nj transit storage harrison car maintenance facility lester m

Memorial Plaza – Architectural MetalsRecommended Authorization

Lowest Responsive Bidder AuthorizationSkyline Steel Corporation $ 7,101,556E t W k (8%) $ 568 124Extra Work (8%) $ 568,124Bovis Construction Management Services $ 706,179Total $ 8,375,859

Page 3: World Trade Center Construction Redevelopment Subcommittee … · 2015-06-04 · block 169 / lot 2.02 7,000 sq. ft. nj transit storage harrison car maintenance facility lester m

One World Trade Center – Scaffolding and Sidewalk Sheds Recommended Authorization

Lowest Responsive Bidder Authorization

Atlantic Hoist & Scaffolding LLC $ 14,600,000Extra Work (8%) $ 1,168,000Total $ 15,768,000

Page 4: World Trade Center Construction Redevelopment Subcommittee … · 2015-06-04 · block 169 / lot 2.02 7,000 sq. ft. nj transit storage harrison car maintenance facility lester m

One World Trade Center – Alternate Power Supply EquipmentAdditional Funding to Existing Electrical Trade Contract

Contractor: Five Star Electric CorporationTotal Current Board Authorization: $ 199,980,000

$Additional Funding: $ 5,500,000Extra Work (8%) $ 440,000Revised Total $ 205,920,000

Page 5: World Trade Center Construction Redevelopment Subcommittee … · 2015-06-04 · block 169 / lot 2.02 7,000 sq. ft. nj transit storage harrison car maintenance facility lester m

One World Trade Center – Steel Painting and Perimeter Safety System Supplemental Agreement to Existing Structural Steel Trade Contract

Contractor: DCM Erectors, Inc.Total Current Board Authorization $ 280,480,000Steel PaintingSteel PaintingBase Contract $ 7,050,000Extra Work (8%) $ 564,000Perimeter Safety SystemBase Contract $ 9,000,000Extra Work (8%) $ 720,000Revised Total $ 297,814,000

Page 6: World Trade Center Construction Redevelopment Subcommittee … · 2015-06-04 · block 169 / lot 2.02 7,000 sq. ft. nj transit storage harrison car maintenance facility lester m

DRP – Additional Funding for Program Management Support ServicesRecommended Authorization

Contractor: The Louis Berger GroupOriginal Authorized Amount $47,500,000Additi l F di (N t t E d) $30 000 000

Extension of original authorization to provide:

Additional Funding (Not to Exceed) $30,000,000Total $77,500,000

Uninterrupted program management services Intimate knowledge of site projectsClaims and change resolutionCost controlDocument controlSchedule integration and analysisFTA reportingFTA reportingFor WTC Transportation Hub, 1 WTC, WTC Memorial and Museum, WTC Vehicular Security Center, and other redevelopment projects

F t i d th h A il 2012For a two-year period through April 2012

Page 7: World Trade Center Construction Redevelopment Subcommittee … · 2015-06-04 · block 169 / lot 2.02 7,000 sq. ft. nj transit storage harrison car maintenance facility lester m

DRP – Additional Funding for Construction Management Consultant Services

Original Authorized Amount $ 79,112,979

Contractor: Parsons Brinckerhoff and URS CorporationRecommended Authorization

Additional Funding (Not to Exceed) $ 20,000,000Total $ 99,112,979

Extension of original authorization to provide:

Construction audits

Sit f t d t h i l iSite safety and technical servicesLogistics planning and implementationConstruction progress reportingInspection supportInspection supportTenant construction alteration review

For the period through December 2011

Page 8: World Trade Center Construction Redevelopment Subcommittee … · 2015-06-04 · block 169 / lot 2.02 7,000 sq. ft. nj transit storage harrison car maintenance facility lester m

PATH – Temporary Easement Agreement with Lester M. Entin AssociatesRecommended Authorization

WTCC WORK TRAIN STORAGE YARD LOCATION

ENTIN PROPERTY

ROUTE 280NORTHEAST CORRIDOR

NORTHEAST CORRIDOR

PATH

STORAGE YARD LOCATION43.600 +/‐ SQ. FT.

BLOCK 169 / LOT 2.027,000 SQ. FT.

NORTHEAST CORRIDOR

NJ TRANSIT STORAGE

PATHHARRISON CAR MAINTENANCE

FACILITY

LESTER M. ENTIN ASSOCIATES

PATH PROPERTYBLOCK 213 / LOT 5.04

15,000 SQ. FT.

NN

TOTAL PROJECT AREA

FUTURE ACCESS ROAD/LOADING AREA

56,600 +/‐ SQ. FT

TOTAL PROJECT AREA AVAILABLE TO PA

2.3 ACRES (100,200 +/‐ SQ. FT)