WP6 status report
A. Di Mauro (CERN)ITS plenary meeting 20.01.2014
WP6 status report - A. Di Mauro 2
Outline
• Update on development of FPC in Al• Summary of proposal of an automated HIC
assembly system from VEA• Planning of 2014 WP6 objectives
20/01/2014
WP6 status report - A. Di Mauro
Status of Al-FPC R&D• 7 prototypes have been etched
using DEPHIS Al-coated kapton (the first was shown in December); however last step (Ni/Au coating of contacts) failed due to issues with quality of Al layer (too porous). New foils are being prepared by DEPHIS by improving the Al processing.
• Two kapton foils coated (with 25 mm Al) by FHR were delivered last week and will be processed in the next two weeks.
320/01/2014
WP6 status report - A. Di Mauro 4
Al-FPC deformation- Nominal distance between first and last contact: 268.800 mm- Metrology checks along 5 trace lines
20/01/2014
C1
C2 C3
C4
C5
C6 C7
C9
C10 C11
C13
C14 C15
C17
C18 C19
C20
WP6 status report - A. Di Mauro 5
Al-FPC deformation
- Al coating and subsequent steps produce shrinking (observed up to ~400 mm):- Cu FPC (12/09/2013):
268.822, 268.827, 268.838, 268.824, 268.827- Al FPC (DEPHIS prototype, after etching, 16/12/2013):
268.562, 268.575, 268.545, 268.565, 268.528- Al FPC (FHR 15μm Al, before etching, 07/01/2014):
268.405, 268.396, 268.379, 268.366, 268.384- After finalization of the production procedure, will study various
solutions depending on reproducibility of effect and final deviation from nominal value:- Pad diameter larger than FPC holes (e.g., 250 mm pad can compensate
100 mm over 9 chip flex) - Modify holes position when drilling in order to achieve final nominal
values- Compensate by suitable adjustment of chips gap (variation of chips
position HIC by HIC!)
20/01/2014
WP6 status report - A. Di Mauro 6
Automated HIC assembly system from VEA
• The proposal has been reviewed and the system is conform to our requirements and suitable to the purpose.
• The main constraints are precision (final chip position tolerance ~ 5-10 mm) and time
• In order to achieve the required accuracy and repeatability Linear Positioning Stages (X,Y,Z) have been preferred to robotic arms (faster but less precise)
• The structures are simple and also the mathematical model to compensate errors due to thermal expansion is quite simple
• This machine allows the assembly of both modules for the inner layer (1 x 9 chips) and for the outer layer (2 x 7 chips) by simple replacement of the "assembly frame", the "FPC stack" and the “soldering balls grid“.
20/01/2014
WP6 status report - A. Di Mauro 720/01/2014
TOP VIEW
SIDE VIEW
X or Y Linear Positioning Stage- 200 mm/s- 0.05 mm unidirectional repeatability- 0.2 mm bidirectional repeatability
7
Z LPS with 0,1 μm unidirectional repeatability
Automated HIC assembly system from VEA
WP6 status report - A. Di Mauro 820/01/2014 8
Automated HIC assembly system from VEA
Ultra high-precision rotation stage- ± 1.7 mrad (0.0001o) repeatability
The assembly frame is positioned on a high precision rotation stage and it has vacuum suction to hold components.
WP6 status report - A. Di Mauro 920/01/2014 9
Automated HIC assembly system from VEACycle time estimation
Phase Normal time (s)
Pessimistic time
(s)
Chip placement 5.5 8.1
FPC placement 5.8 8.5
Soldering balls grid placement 5.8 8.5
Soldering balls placement (group of 22) 3.8 10.5
Laser soldering (time per contact) 5 10
Worst case scenarios:- 9 chips → 9x8.1 + 8.5 + 8.5 + 9x(4x10.5) + 9x(88x10) = 8388” = ~ 2 h 20’- 2x7 chips → 14x8.1 + 8.5 + 8.5 + 14x(4x10.5) + 14x(88x10) = 13039” = ~ 3 h 38’
Assuming 48+10% HICs for IB and 1604+10% HICs for OB and 16 h/ working day:8 days for IB + 397 days for OB
WP6 status report - A. Di Mauro 10
2014 WP6 objectives
20/01/2014
Task WP6 specific topic/ issue
Resource Milestone (TBC)
Finalization of IB geometry (with inputs from WP1 and WP2) and layout (with WP9 and WP10)
FPC extension for E-o-C row
A. JuniqueA. Di MauroC. Gargiulo
Mar 14
Finalization of design and characterization of FPC
- Al coating/etching- Trace params and
routing- Power and signal
connection
A. JuniqueM. Keil
Jun 14
Development of HIC assembly and test procedure and set-up (with WP4 and WP7-8)
Automated system
J. Van Beelen P. Ijzermans P. RiedlerA. Di Mauro
Jul 14
Development of prototype of IB staves based on “pad chips”, dimensional survey and characterization (mechanical and thermal) (joint project with WP9)
Sep 14
Development and characterization of stave based on FS-ALPIDE.
Nov 14
Document on dimensional and position survey procedure (joint with WP7, WP8 and WP9)
Nov 14
WP6 status report - A. Di Mauro 11
WP6 meetings
Weekly on Thursdays, 15:30 (Geneva Time) At CERN: 4-S-030
Next Meeting: Jan 30