wsf hybrid electric ferry conversion project · 2018-05-03 · wsf hybrid electric ferry conversion...
TRANSCRIPT
WSF Hybrid Electric Ferry Conversion Project
PSRC CMAQ Regional Funding
April 26, 2018
Amy Scarton, WSDOT Assistant Secretary
Washington State FerriesMatt von Ruden, Director of Vessel Engineering and Maintenance
The Goal The Target
EXECUTIVE ORDER 18-01 directs the Washington State Ferry (WSF) system to begin the transition to a zero-carbon-emission ferry fleet, including the accelerated adoption of both ferry electrification and operational improvements that will conserve energy and cut fuel use.
Stationar
y Fuel
Use 18%
Ferry
Vessels 67%
Vehicle
Fleet
12%
WSDOT Greenhouse Gas
Emissions
The Opportunity
Class: Jumbo Mark II = largest 3 vessels 26% of the fleet’s total fuel consumption
Save up to 5 million gallons of fuel/year
Route: Seattle/Bainbridge and Edmonds/Kingston
Operate on the busiest passenger routes with some of the shortest runs
Propulsion: DIESEL-ELECTRIC (AC)Ready for 20 year propulsion systems replacement, easily upgraded
Years Built: 1997-1998Only 20 years old, so potential 40 years of remaining service period
Reduce operating and maintenance costs
Reduce WSF carbon emissions by ~25%
Challenges
• Multiple projects on 3 vessels, 4 terminals, with 3 utilities, each with different requirements and timelines
• Long lead time is brining the utility power to the docks
• Contracting strategy with currently funded preservation work while competing shipyard and terminal work
• Keeping current services levels while performing work
• Availability and flexibility of potential funding sources
• Lack of regulatory guidance and US experience
Next Steps and Potential TimelineContingent upon funding, subject to change
• Completed research and feasibility studies (February 2018)
• Develop preliminary cost and risk ranges (Summer 2018)
• Hire system integrator, begin preliminary design (Fall 2018)
• Finish design, issue multiple requests for proposals (2019)
• Start vessel and terminal preliminary engineering (2019-2020)
• First vessel retrofit (2020-2021) “hybrid” mode achieved!
• Start terminal work and second vessel retrofit (2021-2022)
• Additional vessels and terminals (2022 and beyond)
PSRC Funding Application Request
• WSF’s request: $7 million in 2018 FHWA CMAQ
Regional Funding
• The Project: Convert 2 Jumbo Mark II (JMII) vessels
serving the Seattle-Bainbridge Island route to hybrid
electric propulsion
• First step in WSF’s transition to a zero-carbon
emissions ferry fleet
• Needed to reduce GHG emissions, improve
regional air quality, and move the
Seattle-Bainbridge Island route toward meeting
zero-carbon mandates
6
Project Benefits: Support for Centers
Regional Growth Centers (RGC) Benefits
• Seattle’s Central Business District
• Uptown
• First Hill / Capitol Hill
Manufacturing/Industrial Centers (MIC) Benefits
• Duwamish (access via the Seattle CBD RGC)
• Ballard-Interbay (access via the Uptown RGC)
7
Project Benefits: Air Quality and Climate Change (Alternative Fuels or Technology)
MeasureCurrent
Conditions
Proposed
ProjectReduction
Percentage
Reduction
Annual Diesel Consumption (gallons)1 3,752,000 2,962,000 790,000 -21%
Annual CO2 emissions (pounds/year) 84,044,800 66,348,800 17,696,000 -21%
Annual CO2 emissions (metric tons/year) 38,123 30,096 8,027 -21%
Annual PM emissions (g/year) 75,574,429 59,661,903 15,912,526 -21%
Annual PM emissions (pound/year) 166,610 131,530 35,081 -21%
Annual Fuel and Emissions Reductions for Conversion of 2 JMII Vessels
8
Project Costs and Funding Sources
Preliminary Engineering
Funding Source Secured/Unsecured Amount
Other State Secured $250,000
Other State Secured $600,000
Other State Reasonably Expected $9,490,000
PE Total $10,340,000
Construction
Funding Source Secured/Unsecured Amount
Other State Reasonably Expected $56,000,000
CMAQ Unsecured $7,000,000
Construction Total $63,000,000
Total Project Cost $73,340,000
9
Questions?
Amy Scarton
and
Matt von Ruden
Director of Vessel Engineering and Maintenance
Washington State Ferries
206.515.3863
Initial Hybrid-Conversion Research• Vessel Study: Elliott Bay Design Group developed a concept design to convert
the vessels for full electric mode capability. The study also include a summary of worldwide vessel conversions and new builds incorporating hybrid technology, a review of potential costs and emissions reductions, and a regulatory review.
• Shore Infrastructure Study: WSF Terminal Engineering developed concept drawings, capacity analysis, and right of way analysis to install shore side improvements to support 4160 volt charging stations at Seattle, Bainbridge, Edmonds and Kingston terminals. All three affected utility providers (Seattle City Light, Puget Sound Energy, and Snohomish Co. PUD) participated.
• Ship-shore Interface Study: Glosten and Associates evaluated options for shore-based charging of electric ferries at WSF terminals. The study included the state of industry, requirements definition (e.g., safety, vessel motions, tidal fluctuations, and operating constraints), a concept design and cost review.
Agency-wide Sustainability Initiatives
Completed Considered In Progress Pursuing
B5 and B10 Biodiesel pilots
Hyak Electric-Hybrid Conversion
Energy Audits ofTerminal Buildings
Vessel Speed Guidance
PropellerImprovements
LNG Conversion of Issaquah Class
Vessel Noise Baseline Research
New Vessel Design
Speed Reductions on some routes
Automated Mooring
Efficiencies in lighting, solar,
pavement
Electrification of Existing Fleet
Project Readiness: Project Schedule
Project Schedule
Phase Start & Completion Dates
NEPA (CE) February 2019
Preliminary Engineering June 2020
PS&E Approval March 2020
Construction Advertisement December 2020
Estimated Completion of Project December 2022
13