permits

10
PERMITS YAWAR HASSAN KHAN 1

Upload: yawar-hassan

Post on 21-Jan-2015

113 views

Category:

Documents


6 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Permits

1

PERMITS

YAWAR HASSAN KHAN

Page 2: Permits

2

Types

Various work permits and forms are required for construction and construction-related

service activities such as:

• Penetration Checklist

• Utility Location and Excavation Permit

• Hot Work Permit

• Life Safety Aisle/Exit Impairment Permit

• Confined Space Entry Permit

• High Hazard Construction Safe Work Permit

• Permit for Energized Electrical Safety (PEET)

• Drain Connection / New Discharge Approved Form

• Fire Protection System Impairment

• High Voltage Pre-Job Safety Checklist / Electrical Shutdown

• Utilities Permit for Modification

Page 3: Permits

3

The Seller shall initiate all permits required to perform work at the Kansas City Plant

and identify permitting requirements in the Project Specific Safety Plan/Activity Hazard

Analysis (AHA) and Daily Hazard Analysis (DHA). The Seller shall complete required

permits and obtain all signatures prior to proceeding with construction work. All permits

shall be up to date and posted at the jobsite.

Hot Work Permits are issued by the KCP Fire Department. High Hazard Construction

Safe Work Permits, Aisle Impairment Permits, and Utility Location & Excavation

Permits are issued by Construction Management Associates. Many of these permits

require advanced notice and coordination prior to work

Page 4: Permits

4

High Hazard Construction Safe Work Permits

High Hazard Construction Safe Work Permits are issued for non-routine high hazard

operations such as but not limited to:

• Scaffold work (any height)

• Steel Erection

• Use of Cranes

• Helicopter Lifts

• Shoring

• Critical / Unusual lifts

• Concrete Masonry Wall Installation (> 8ft)

• High Voltage Work (Over 600V)

• Removal of roofing materials and /or the removal/installation of items that

penetrate the KCP roof.

Page 5: Permits

5

Permits may be issued on a daily, weekly, or monthly basis. Completion of this form

requires participation of contractors with ES&H, Project Engineer and area owner.

Page 6: Permits

6

Utility Location & Excavation Permit

The Utility Location & Excavation permit shall be completed any time construction

activity disturbs soil/sub grade, including penetrations through

slabs/floors/concrete/asphalt where the soil/sub grade will be disturbed.

Examples include internal or external excavation, trenching, soil borings, ground rod

installations, or any other construction activity that has the potential to disturb a buried

or encased utility in the soil.

Requesting a permit: Minimum 3-day advanced notice is required to adequately

research and identify hazards that may exist at the excavation site.

These permits are generally issued on a daily or weekly basis depending on the

operation. Permits may be issued for any period that is decided appropriate by the

Project Engineer. Excavations should be reviewed prior to entry and the permits

reviewed weekly as a minimum. Advanced notification is required to allow Buyer to

perform a basic review of potential utilities in the area. Seller is responsible for

performing work in a manner that recognizes utilities may exist that are not identified by

the Buyer’s utility locating equipment (

Page 7: Permits

7

Penetration Checklist

The penetration checklist replaces the class 2 penetration permit. The new checklist

allows the contractor to locate utilities and re-bar themselves in concrete 4 inches or

less in depth. The checklist shall be completed prior to any saw cutting, jack

hammering, drilling or penetration of asphalt, concrete ceilings, floors, columns, beams,

roof ribs, concrete & metal roofs, footings, foundations, exterior slab on grade (concrete

& asphalt) or suspended slabs (ramps, etc.) (See section 19 and Appendix Q.)

Exemption - Work under construction the Seller has installed as a part of the same

project does not require a penetration permi

Page 8: Permits

8

Life Safety Aisle/Exit Impairment Permits

Life Safety Aisle/Exit Impairment Permits are issued for tasks that will require the aisle

to be partially or totally blocked for a period of time. If an aisle must have on-going

work, then a permit will be issued to identify the work and materials that will be within

the life safety lines. Basically no more than one half of the aisle (minimum of 36”) may

be blocked for a partial and the partial impairment must last two hours to require

permitting. Total blockages require a 24-hour notice, considerable coordination and

are generally permitted only on off-shift to keep the risk levels lower. Remember, if you

block less than half the aisle for less than 2 hours, you do not need a permit.

Page 9: Permits

9

Utility System Modification Permit

Utility system modification permit is required for all utility modifications, including those

that install or remove equipment. The Seller/CM/Planner shall file a permit with the

designated Utility Engineer prior to construction. The permit shall identify the system,

location of work, type of work and estimated duration of the work. The Utility Engineer

shall review and return the request for approval within 3 working days. The permit shall

reside with the seller until the work is completed and post-installation testing is

performed. The Utility Engineer has the option to witness post-installation testing with

24-hour advance notice

Page 10: Permits

10

Revocation of Permits

Permits may be revoked for noncompliance violations. Upon revocation of the permit,

the Seller shall submit in writing to the Project Engineer the corrective action that will be

taken and action taken to prevent recurrence. If corrective action is acceptable,

another permit will be issued. Revocation of a permit will result in the issuance of a

citation.