Sacramento, California In 2010, a US-based demonstration waste-to-energy system was commissioned in the Sacramento, CA area at a commercial research and development foundry named Technikon. Technikon desired a plasma gasification system to potentially treat US Army waste streams under Department of Defense and Department of Energy contracts. Locating and permitting a waste-to-energy system in California - arguably the most stringent air emission state in the US - illustrates the minimal environmental footprint associated with the plasma gasification technology.

Upload: emily-wilson

Post on 14-Jul-2015

26 views

Category:

Business


3 download

TRANSCRIPT

Page 1: Sacramento

Sacramento, California

In 2010, a US-based demonstration waste-to-energy system was commissioned in the

Sacramento, CA area at a commercial research and development foundry named Technikon.

Technikon desired a plasma gasification system to potentially treat US Army waste streams

under Department of Defense and Department of Energy contracts.

Locating and permitting a waste-to-energy system in California - arguably the most stringent air

emission state in the US - illustrates the minimal environmental footprint associated with the

plasma gasification technology.