8DK 02 05 04 01 00 PCZZA ED 00 EFFECTIVE DATE : 10 SEPTEMBER 2007 XL - RND 1/33 XL – QA APPROVALS ALU - QA ALCATEL-LUCENT INDONESIA Evolution A9100 BTS Installation Standard ABSTRACT This document describes the installation standard for indoor and outdoor part of A9100 BTS product Domain : ALCATEL-LUCENT INDONESIA Process Owner : IMPLEMENTATION Type : INSTRUCTIONS, USER GUIDE Originator : DURMAWEL SAHARA Distrib. Codes : Internal: Y/N External: Y/N

Upload: tuan-nguyen

Post on 02-Nov-2014

29 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

1/33

XL – QA APPROVALS

ALU - QA

ALCATEL-LUCENT INDONESIA

Evolution A9100 BTS Installation Standard ABSTRACT This document describes the installation standard for indoor and outdoor part of A9100 BTS product

Domain : ALCATEL-LUCENT INDONESIA Process Owner : IMPLEMENTATION Type : INSTRUCTIONS, USER GUIDE Originator : DURMAWEL SAHARA Distrib. Codes : Internal: Y/N External: Y/N

Page 2: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

2/33

XL – QA APPROVALS

ALU - QA

TABLE OF CONTENTS

1 INSTALLATION INDOOR ........................................................................4

1.1 Indoor Tray (Top View).........................................................................4

1.1.1 Indoor Tray (Front View) ......................................................................5

1.2 GROUNDING SYSTEM ............................................................................6

1.2.1 Arrangement of Wiring Copper rod ..........................................................6

1.2.2 Connection Copper rod to Main Grounding Bar (MGB) ...................................7

1.2.3 Connection Grounding at BTS Radio, Transmission and Rectifier to MGB ...........8

1.3 FEEDER ENTRY ...................................................................................9

1.3.1 Installation Feeder Entry (height of feeder entry and dimension from base ........

floor of shelter (Inside view) ..................................................................9

1.3.2 Installation Feeder Entry (height of feeder entry and dimension from base ........

floor of shelter (Inside view) ................................................................ 10

1.3.3 Arrangement of Feeder Entry and Connection Grounding Arrester to Busbar ... 11

1.4 BTS INDOOR..................................................................................... 12

1.4.1 Connection Wiring Cable at the top BTS Radio.......................................... 12

1.4.2 Connection Wiring Board at BTS Radio Rack ............................................ 13

1.4.4 Connection Wiring Alarm and Traffic Cables at DDF External Alternative 1...... 14

1.4.5 Connection Wiring Alarm and Traffic Cables at DDF External Alternative 2...... 15

1.4.6 BTS Radio Installation (Side View) ......................................................... 16

1.5 POWER SUPPLY (RECTIFIER) ................................................................. 17

1.5.1 Connection Wiring Power Cable at Power Suply (Rectifier) .......................... 17

2 INSTALLATION OUTDOOR..................................................................... 18

2.1 Installation Position Feeder Coaxial at Vertical Tray of Tower and Installation ....

Feeder Clamp .................................................................................. 18

2.1.1 Installation Grounding Kit (at the top and bottom) .................................... 19

2.1.2 Installation Grounding Kit at Feeder Entry (Outdoor) ................................. 20

2.1.3 Installation Labelling, Wiring Jumper Cable and Grounding at Antenna........... 21 3 INSTALLATION ANTENNA TYPE APM 40.................................................... 22

3.1 Installation Antenna and Mounting Hardware Part 1................................... 22

3.2 Installation Antenna and Mounting Hardware Part 2................................... 23

3.3 Installation Antenna and Mounting Hardware Part 3................................... 24

3.4 Installation Antenna and Mounting Hardware Part 4................................... 25

3.5 Installation Antenna and Mounting Hardware Part 5................................... 26

Page 3: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

3/33

XL – QA APPROVALS

ALU - QA

4 GENERAL MATERIALS.......................................................................... 27

4.1 Feeder Entry.................................................................................... 27

4.2 Heat Shrinkable Sleeve (Condom).......................................................... 27

4.3 Cable Ties (Tie Wrap) Type CS-300X ...................................................... 28

4.4 Cable Ties (Tie Wrap) Type CS-390L ...................................................... 28

4.5 Cable Ties (Tie Wrap) Type CS-200L ...................................................... 29

4.6 Cable Ties (Tie Wrap) Type CS-150T ...................................................... 29

4.7 Labelling......................................................................................... 30

4.8 Connector ....................................................................................... 30

4.9 HHD Cavity Anchor ........................................................................... 31

4.10 Cable Shoe 1x35 ............................................................................... 31

4.11 Protection Edge ................................................................................ 31

4.12 Clamp Copper rod (SIMEL CH 10.70)....................................................... 32

4.13 Clamp Copper rod (SIMEL BB 50-80) ....................................................... 32

APPENDIX ................................................................................................ 33

DOCUMENT MANAGEMENT............................................................................ 33

Page 4: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

4/33

XL – QA APPROVALS

ALU - QA

1 INSTALLATION INDOOR

1.1 Indoor Tray (Top View)

Tech room/ShelterHeight of Ceiling : 3.00Height of Tray : 2.40

2000

560

2500

150

500

880 560

AC 1ACPDBAlarmAbove AC 2

Air InletUnder AC 2

BTS

EVO

900

MH

z

RACK

TRA

NS

& D

DF

PWR

SUPP

LYAC

BEL

LTY

PE C

SM 2

0

600

AC 1H : 2000

FEEDERENTRY

Clamp (@0.5m)Copper Rod

MGB

1 2 3 4 5

6 7 8 9 10

FEEDER ENTRY

1. MW2. Spare3. Antenna Sector 1A (NA)4. Antenna Sector 2A (PA)5. Antenna Sector 3A (QA)6. Spare7. Spare8. Antenna Sector 1B (NB)9. Antenna sector 2B (PB)10.Antenna Sector 3B (QB)

MW

Copper Rod

SPARE NA

SPARE SPARE NB

PA QA

PB QB

Hol

es f

or C

able

Wir

ing

and

Edge

Rub

ber

Prot

ecti

on

FEEDERENTRY

INSIDE VIEW(from Inside of Shelter)

Bracket Tray

SECTION A

Cable Tray

Scale : NTS

Support Tray

Shelter Wall

A

"A"

"A"

Notes :"A" (See BTS Installtion Side View on Page 16)

Bracket Tray

Bracket Tray Bracket Tray

Bracket Tray

Bracket Tray

Bracket Tray

70

150

550

Hole for Cable Pwr SupplyEdge Rubber Protection

Hol

e fo

r Ca

ble

Pwr

Supp

lyEd

ge R

ubbe

r Pr

otec

tion

HHD Molly Anchor

70

150

7015

0

70

150

Page 5: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

5/33

XL – QA APPROVALS

ALU - QA

1.1.1 Indoor Tray (Front View)

AC

DC Fan

`

TEC HN IC A L R OO MIN SIDE

M ain G rou nd B ar(M G B )

B us b ar fo r G rou nd A rres te r

C la m p (@ 1 m )

C op per R od

C ab le T ra y

C op per R od

B ra cke t T ra y

G roun dC ab le B C 3 5

54

32

1

109

87

6

B ra cke t T ra y

B ra cke t T ra y

B ra cke t T ra yB ra cke t T ra y

B ra cke t T ra y

B racke t T

ray

FAP

MW

Rack

B TSE vo lium

R ectifie r

G roun d ca b leB c 35

Page 6: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

6/33

XL – QA APPROVALS

ALU - QA

1.2 GROUNDING SYSTEM

1.2.1 Arrangement of Wiring Copper rod

Tech room/ShelterHeight of Ceiling : 3.00Height of Tray : 2.40

AC 1ACPDBAlarmAbove AC 2

Air InletUnder AC 2

AC 1H : 2000

Clamp (@0.5m)Copper Rod

MGB

Copper Rod

Bracket Tray

SECTION A

Cable Tray

Scale : NTS

Support Tray

HHD Molly Anchor

Shelter Wall

A Bracket Tray

Bracket Tray Bracket Tray

Bracket Tray

Bracket Tray

Bracket Tray

Page 7: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

7/33

XL – QA APPROVALS

ALU - QA

1.2.2 Connection Copper rod to Main Grounding Bar (MGB)

AC

DC Fan

`B us bar

M ain G rou nd. B ar

DETAIL AScale : NTS

Clamp simel CH

Copper Rod

Copper Rod

Cable Tray

Copper Rod

Main Grounding Bar (MGB)

"A "

Clamp simel CHCopper Rod

Copper Rod

Copper Rod

SIDE VIEWScale : NTS

to Main Grounding Bar

Cable Grounding

Cable Tray

Busbar

SS Bolt M8

Cable Shoe

M a in G ro u nd . B ar"B "

to Copper Rod

DETAIL BScale : NTS

to Busbar

Cable Grounding

SS Bolt M8

Cable Shoe

Cable Grounding

SS Bolt M8

Cable Shoe

G rou ndC a ble B C 35C o ppe r

R o d

HHD Molly Anchor Bracket Tray

HHD Molly Anchor

Cable Shoe

Busbar

Cable Tray

Ground Cable BC 35

Main Grounding Bar (MGB)

SIDE VIEWScale : NTS

SS Bolt M8

Cable Shoe

Bracket TrayHHD Molly Anchor

Page 8: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

8/33

XL – QA APPROVALS

ALU - QA

1.2.3 Connection Grounding at BTS Radio, Transmission and Rectifier to MGB

NOTES : This is Temporary Standard, The New Standard is on going validation by ALU & XL

Clamp simel CH

Copper Rod

Cable Tray

Cable Grounding BC35

SIDE VIEWScale: NTS

R e ctifie r

Clamp simel CH

Copper Rod

Cable Tray

Cable Grounding BC35

B T SE v o lium

R a d io T r a n s m is s io n

IDU

Rack 19"

AC

DC Fan

`

T E C H N IC A L R O O MIN S ID E

M ain G rou nd B a r(M G B )

B us b ar fo r G rou nd A rres te r

C la m p (@ 1 m )

C op per R od

C ab le T ra y

C op pe r R od

B ra cke t T ra y

G roun dC ab le B C 3 5

54

32

1

109

87

6

B ra cke t T ra y

B ra c ke t T ra y

B ra ck e t T ra yB ra cke t T ra y

B ra cke t T ra y

B racke t T

ray

FAP

MW

Rack

B TSE vo lium

R ectifie r

Clamp simel CH

Copper Rod

Cable Tray

Cable Grounding BC35

Bracket TrayBracket TrayBracket Tray

G roun d ca b leY /G B C 3 5

Page 9: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

9/33

XL – QA APPROVALS

ALU - QA

1.3 FEEDER ENTRY

1.3.1 Installation Feeder Entry (height of hole feeder entry and dimension from base floor of shelter (Inside View)

INSIDE VIEW(From The Inside Technical Room/Shelter)

1 2 3 4 5

6 7 8 9 10

FFEDER ENTRY

520

280

INSIDE VIEW

3000

2700

2400

1 2 3 4 5

6 7 8 9 10

500

Notes :

1. MW2. Spare3. Antenna Sector 1A (NA)4. Antenna Sector 2A (PA)5. Antenna Sector 3A (QA)6. Spare7. Spare8. Antena Sector 1B (NB)9. Antenna Sector 2B (PB)10. Antenna Sector 3B (QB)

1

5

40

45

50

55

60

65

70

75

80

1

2

3

4

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37

38

39

40

41

42

43

44

45

HO

LES

UN

ITS

10

15

20

30

35

25

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21MW RACK 19"

Distribution Module

Hariff

POWERSUPPLY

2500

MW Spare

Spare Spare

NA PA QA

NB PB QB

Page 10: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

10/33

XL – QA APPROVALS

ALU - QA

1.3.2 Installation Feeder Entry (height of hole feeder entry and dimension from base floor of shelter (Inside View – Isometric)

DC Fan

B usba r

B usba r

54

32

1

109

87

6

FEEDER ENTRY

INSIDE VIEW ISOMETRICScale ~ NTS

2700

GroundingCable Y/G 1x35

Copper Rod

Copperbar

INSIDE VIEW(From The Inside Technical Room/Shelter)

FFEDER ENTRY

Notes :

1. MW2. Spare3. Antenna Sector 1A (NA)4. Antenna Sector 2A (PA)5. Antenna Sector 3A (QA)6. Spare7. Spare8. Antenna Sector 1B (NB)9. Antenna Sector 2B (PB)10. Antenna Sector 3B (QB)

1 2 3 4 5

6 7 8 9 10

520

280

MW Spare

Spare Spare

NA PA QA

NB PB QB

500

Page 11: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

11/33

XL – QA APPROVALS

ALU - QA

1.3.3 Arrangement of Feeder Entry and Connection Grounding Arrester to Busbar

C able En try

L ightn ing Arreste r

C la m p F eederTyp e Double

C onn ecto r 1 /2" - 7/ 16 m ale

C oa xia l Feeder 7/ 8" (6 feed er)

C onnec to r 7 /8 " - 7/1 6 fem a le

B ra cket L

70 0

NAPA

QA

NBPB

QB

C able Jum p er 1 /2" to BT S R adio

Cop per ba r in sta lled d irectlyto M ain G round B ar (M G B)

C able g round BC 35 in sta lled d irec tlyto M ain G round Bar (M G B)

G rounding B usb ar

G rounding C ab leArreste r

C op per rod

NAPA

QA

NAPA

QA

Labe l Labe l

Page 12: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

12/33

XL – QA APPROVALS

ALU - QA

1.4 BTS INDOOR

1.4.1 Connection Wiring Cable at the top BTS Radio

NOTES : This is Temporary Standard, The New Standard is on going validation by ALU & XL

Power Cable (black)

Cable Power(Blue Color)

JUMPER CABLE

LABEL

ALARM CABLE GREY

METAL SHIELDCONNECT TO BTS

CABLE TRAY

EDGE RUBBER PROTECTION

COPPER ROD

JUMPER CABLE

JUMPER CABLE

Cable Power (Blue)

Cable Abis (Grey)

CABLE TRAY

EDGE RUBBER PROTECTION

DETAIL WARING CABLE ALARAM, PCM, POWER & GROUNDING

METAL SHIELD

Cable Black (Black)

Cable Alarm (Grey)

HOLES FOR CABLE WIRING

PAPB

QA

QB

NA

NB

JUMPER CABLE

Ground CableY/G BC 35

Cable Power(Blue Color)Cable Traffic(Grey Color)

-48 V 0 V

Page 13: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

13/33

XL – QA APPROVALS

ALU - QA

1.4.2 Connection Wiring Cables at BTS Radio Rack

TX

POWERENABLE

OFF

TEST

RX0

RX1

TXBCCHFAULTY

RSLOP

PWR TRE1

P ANT B

TX

POWERENABLE

OFF

TEST

RX0

RX1

TXBCCHFAULTY

RSLOPPWR

TX

POWERENABLE

OFF

TEST

RX0

RX1

TXBCCHFAULTY

RSLOPPWR

ON

OM ALARM

RX0AOUT2

RX1AOUT2

RX0BOUT2

RX1BOUT2

RX0BOUT1

RX1BOUT1

RX0AOUT1

RX1AOUT1

ANT A

ANT B

TXAIN1

TXAIN2

TXAOUT

TXBIN2

TXBIN1

TXBOUT

ON

OM ALARM

RX0AOUT2

RX1AOUT2

RX0BOUT2

RX1BOUT2

RX0BOUT1

RX1BOUT1

RX0AOUT1

RX1AOUT1

ANT A

ANT B

TXAIN1

TXAIN2

TXAOUT

TXBIN2

TXBIN1

TXBOUT

ON

OM ALARM

RX0AOUT2

RX1AOUT2

RX0BOUT2

RX1BOUT2

RX0BOUT1

RX1BOUT1

RX0AOUT1

RX1AOUT1

ANT A

ANT B

TXAIN1

TXAIN2

TXAOUT

TXBIN2

TXBIN1

TXBOUT

FANU FANU FANU

MNEMO

SERI

AL

ABIS1/2

BTS

CONNECT

ON

AREA

I

BTS

TERMINAL

TEST

OML

O&M

OMU

PS1

AB IS 1

AB IS 2

T RAN S F AU LT

PS2

FANU FANU FANU

FANU FANU FANU

Abis 1Abis 2Abis 3Abis 4XGPSXRTXBCB

Abis 1Abis 2Abis 3Abis 4

4 ABIS RELAYS

- 48 V 0 V

BTSINT

SR1

SR2

SR3

SR4

SR5

XGNDGND

XCLK2IN / OUT

XCLK1IN

XCLK1OUTALARMS INPUTS/OUTPUTS

TRE1

SU

MA

TRE1

Sector1

Sector2

ABIS CABLEfrom SU MA to Abis Port

RX C ABLEfrom TR E to AN C G

G SO 03 C ABLEfrom T RE to ANCG

G SO 04 C ABLEfrom AN CG to Top C onn. BT S

TO P C O NNEC TO R BTS

Q AN T B

Q AN T A

P ANT A

N ANT A

N ANT B

Sector3

Q ANT A

P ANT B

P ANT A

Q ANT B

N ANT B

N ANT A

Page 14: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

14/33

XL – QA APPROVALS

ALU - QA

1.4.3 Connection Wiring Alarm and Traffic Cables at DDF External Alternative 1

1

4

10

15

20

30

25

5

6

7

8

9

10

11

12

13

14

15

16

17

Grounding Cable

Alarm cable

Abis cable

Copper rod

CABLE TRAY INDOOR

DDF ALU

RADIO RACK 19"

DDF Additional

IDU

IDU

TX C

hann

el 1

-6 A

LU

RX C

hann

el 1

-6 A

LU

5

1

2

3

3 4 5 P6 7 8 9 10 11 12 13 P14 15 16 17P1 P2

Ala

rm 1

ALU

Ala

rm 2

ALU

Page 15: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

15/33

XL – QA APPROVALS

ALU - QA

1.4.4 Connection Wiring Alarm and Traffic Cables at DDF External Alternative 2

1

4

10

15

20

30

25

5

6

7

8

9

10

11

12

13

14

15

16

17

Grounding Cable

Alarm cable

Abis cable

Copper rod

CABLE TRAY INDOOR

DDF ALU

RADIO RACK 19"

DDF Additional

IDU

IDU

Alarm ALU

TX C

hann

el 1

-6 A

LU

RX C

hann

el 1

-6 A

LU

5

1

2

3

3 4 5 P6 7 8 9 10 11 12 13 P14 15 16 17P1 2

Alarm ALU

Page 16: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

16/33

XL – QA APPROVALS

ALU - QA

1.4.5 BTS Radio Installation (Side View)

32

2525

2

BTS EVO

Shelter Wall

HHD Molly Anchor

450

1800

"A"

DETAIL AScale : NTS

SIDE VIEWScale ~ 1:15

BTS EVO

ShelterWall

32

32

HHD Molly Anchor

Rail Z Support

DETAIL RAIL Z SUPPORTScale : NTS

ISOMETRIK VIEWScale : NTS

Page 17: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

17/33

XL – QA APPROVALS

ALU - QA

1.5 INSTALLATION OUTDOOR 1.5.1 Connection Wiring Power Cable at Power supply (Rectifier)

CABLE GROUNDING

CABLE TRAY

COPPER ROD

EDGE RUBBER PROTECTION

CABLE POWER BLACK

ABB

C50

NC 50 N

ON

ABB

C50

NC 50 N

ON

ABB

C50

NC 50 N

ON

ABB

C50

NC 50 N

ON

ABB

C50

NC 50 N

ON

ABB

C50

NC 50 N

ON

ABB

C50

NC 50 N

ON

ABB

C50

NC 50 N

ON

ABB

C50

NC 50 N

ON

ABB

C50

NC 50 N

ON

To BTS

Black Cable

Blue Cable

MCB50A

MCB50A

MCB50A

MCB50A

MCB50A

MCB50A

MCB50A

MCB50A

MCB50A

MCB50A

TERMINAL GROUNDING RECTIFIERCOPPER BAR

POWER CABLE

ABB

C50

NC 50 N

ON

MCB50A

Power Cable

"A"

DETAIL A

Cable Pin Lug

MCB 50A

CABLE POWER BLUE

Page 18: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

18/33

XL – QA APPROVALS

ALU - QA

2 INSTALLATION OUTDOOR 2.1 Installation Position Feeder Coaxial at Vertical Tray of Tower and Installation Feeder Clamp

COAXIAL FEEDER 7/8"

LADDER TRAY

GROUNDING KITS

TIE WRAP

TIE WRAP

BUSBAR

ISOLATOR

FEEDER CLAMP FOR 7/8"Every 0.8 ~ 1.0 meter

To Antenna Sector 1B (NB)

To Antenna Sector 1A (NA)

To Antenna Sector 2B (PB).To Antenna Sector 2A (PA)

To Antenna Sector 3B (QB).

To Antenna Sector 3A (QA).

Page 19: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

19/33

XL – QA APPROVALS

ALU - QA

2.1.1 Installation Grounding Kit (at the top and bottom)

L i g h t n i n gP r o t e c t i o n

70.00m

B U SB A R 1

GR OU ND IN G KIT(BA C K TO BA CK ) T

O T

OW

ER

MG

B

AN

TE

NN

A S

UP

PO

RT

(BA

CK

TO

bA

CK

GR OU ND IN G KIT(BA C K TO BA CK ) SPA RE SP

AR

E

TO

TO

WE

R M

GB

D ETA ILB U SB A R 1

B U S B A R 2

D E T A IL BU SBA R 3A T H O R IZO N T A L T R A Y

ISO

LA

TO

R

ISO

LA

TO

R

ISO

LA

TO

R

ISO

LA

TO

R

TR

AY

BU

S B

AR

B U S B A R 3

D ET A IL B U SBA RA T V ER T IC A L T R A Y

TR

AY

BU

S B

AR

GR OU ND IN G TOA NTE NN A SEC TOR(BA C K TO BA CK )

D ETA ILB U SB A R 2

Page 20: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

20/33

XL – QA APPROVALS

ALU - QA

2.1.2 Installation Grounding Kit at Feeder Entry (Outdoor)

Busbar

HORIZONTAL TRAY

DETAIL BUSBAR AT HORIZONTAL TRAY & GROUNDING KIT

CABLE TIES (Tie Wrap)

Isolator

Wall

Feeder Hole

Heat Shringkable Sleeve(Condom)

10 cm

30 cm

To Antenna Sector 1A (NA)To Antenna Sector 1B (NB)To Antenna Sector 2A (PA)To Antenna Sector 2B (NB)To Antenna Sector 3A (QA)To Antenna Sector 3B (QB)

Coaxial Feeder

Grounding Kits

Vertical Tray

Cable Ground Kits

Busbar

Grounding Kits

Coaxial Feeder 7/8"

Horizontal Tray

CableGround

CABLE TIES

GROUNDING KITS

Cable Shoe

SS Bolt M8

Busbar

NA

Heat Shrinkable(Condom)

Feedery Entry

CoverFeeder Holes

Label

NB

NA

NB

PAQA

PBQB

Page 21: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

21/33

XL – QA APPROVALS

ALU - QA

2.1.3 Installation Labelling, Wiring Jumper Cable and Grounding at Antenna

NOTES : This is Temporary Standard, The New Standard is on going validation by ALU & XL

B U S B A R

G R O U N DIN G K IT(B A C K T O B A C K ) T

o T

OW

ER

MG

B

B U S B A R

ISO

LA

TO

R

ISO

LA

TO

R

D E T A IL B U S B A R A T V E R T IC A L T R A Y

TR

AY

A N T E N NA S E C T O R(B A C K T O B A C K )

G R O U N D IN G C A BL E

T IE W R A P

G R O U N D IN G C AB L E

T IE W RA P

F EE D E R C AB LE

T IE W RA P

F EE D E R C AB LE

T IE W RA P

NA

L A BE L

L AB E L L AB E L

TR

AYB

US

BA

R

NB

PA

PB

QA

QB

NAQB

PANB

Page 22: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

22/33

XL – QA APPROVALS

ALU - QA

3 INSTALLATION ANTENNA TYPE APM40 3.1 Installation Antenna and Mounting Hardware Part 1

Page 23: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

23/33

XL – QA APPROVALS

ALU - QA

3.2 Installation Antenna and Mounting Hardware Part 2

Page 24: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

24/33

XL – QA APPROVALS

ALU - QA

3.3 Installation Antenna and Mounting Hardware Part 3

Page 25: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

25/33

XL – QA APPROVALS

ALU - QA

3.4 Installation Antenna and Mounting Hardware Part 4

Page 26: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

26/33

XL – QA APPROVALS

ALU - QA

3.5 Installation Antenna and Mounting Hardware Part 5

Page 27: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

27/33

XL – QA APPROVALS

ALU - QA

4 GENERAL MATERIALS 4.1 Feeder Entry :

4.2 Heat Shrinkable Sleeve (Condom) :

Material from Steel grade ST 41 Dimension : 280 x 3 x 520

Material from Rubber Raychem Code : 75/22 ER 3310

Page 28: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

28/33

XL – QA APPROVALS

ALU - QA

4.3 Cable Ties (Tie Wrap) Type CS-300X :

4.4 Cable Ties (Tie wrap) Type CS-390L :

Code Material SIGMA TIES CS – 300X Dimension : 7.6 x 270 Function : Installation Outdoor (at Top Antenna)

Code Material SIGMA TIES CS – 390L Dimension : 4.8 x 270 Function : Installation Indoor (at Jumper Cable)

Page 29: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

29/33

XL – QA APPROVALS

ALU - QA

4.5 Cable Ties (Tie wrap) CS 200L :

4.6 Cable Ties (Tie wrap) CS 150 T :

Code Material SIGMA TIES CS – 200L Dimension : 3.6 x 180 Function : Installation Indoor (at Alarm & PCM Cable)

Code Material SIGMA TIES CS – 150L Dimension : 3.6 x 140 Function : Installation Indoor (for Connection cable at top BTS radio)

Page 30: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

30/33

XL – QA APPROVALS

ALU - QA

4.7 Labelling :

4.8 Connector :

Labelling, material from Acrilique Function : Label Identification

Heat shrinkable sleeve 1/2 DIN Male

7/8 DIN Female O-Ring

CONNECTOR 7/8 RFS

Page 31: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

31/33

XL – QA APPROVALS

ALU - QA

4.9 HHD Cavity Anchor : 4.10 Cable Shoe :

4.11 Protection Edge :

HHD CAVITY ANCHOR Specification Screw Ø5x45mm (Hilti) Function : Fixation for equipment, accessories and bracket cable tray at Gypsum wall.

Cable Shoe 1x35mm

PROTECTION EDGE Specification from Rubber L2000mm

Page 32: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

32/33

XL – QA APPROVALS

ALU - QA

4.12 Clamp Copper rod (SIMEL CH 10.70) :

4.13 Clamp Copper rod (SIMEL BB 50- 80) :

Page 33: XL- A9100 BTS Installation Standard_Ed 01a

8DK 02 05 04 01 00 PCZZA ED 00

EFFECTIVE DATE : 10 SEPTEMBER 2007

XL - RND

33/33

XL – QA APPROVALS

ALU - QA

APPENDIX

NA

RELEVANT DOCUMENTS AND WEB SITES

# Title of the document/web site Reference/Web link [1] Mounting HW APM40, Radio Frequency Systems http://www.rfsworld.com/ [2] Evolution A9100 BTS Installation Manual 3BK 17226 0001 RJZZA Ed.09

ABBREVIATIONS AND ACRONYMS

Wording Definition ALU Alcatel-Lucent

DOCUMENT MANAGEMENT

Location of the reference of this document (electronic copy): ISO9000\3.Work Instruction

HISTORY

Short description of significant changes to previous edition: Edition Originated