year-end report124.107.243.174/uploads/rpmes/rpmes2016/rpmes2016yendrepor… · the overall...

6
Regional Development Council-1 Regional Project Monitoring Committee-1 Regional Project Moniotirng and Evaluation System HIGHLIGHTS OF OVERALL ACCOMPLISHMENTS A total of 29 entities, (18 line agencies, 6 state universities, 2 local government units and 3 government-owned-and-controlled cor- porations) participated in the RPMES during the year enrolling a total of 483 projects for monitoring by the Regional Project Monitoring Committee (RPMC). As 2016 came to a close, two thirds of the 483 enrolled pro- jects or 320 projects were completed and 163 were in various stages of completion. Of the 163 ongoing projects, 45, or 9.32 percent of the total, were behind schedule, 93, or 19.25 percent, were implemented on-time, while 25, or 5.18 percent of the total, were ahead of schedule. OVERALL PROJECT IMPLEMENTATION STATUS TOTAL NUMBER OF PROJECTS = 483 Overall, the region attained a physical accomplishment rate of 92.4 percent as of December 31, 2016. This is 7.6 percentage points short of the 100 percent target. The total amount spent reached 1 EXECUTIVE SUMMARY

Upload: ngokhanh

Post on 06-Mar-2018

223 views

Category:

Documents


4 download

TRANSCRIPT

Regional Development Council-1

Regional Project Monitoring Committee-1

Regional Project Moniotirng and Evaluation System

HIGHLIGHTS OF OVERALL ACCOMPLISHMENTS

A total of 29 entities, (18 line agencies, 6 state universities, 2 local government units and 3 government-owned-and-controlled cor-porations) participated in the RPMES during the year enrolling a total of 483 projects for monitoring by the Regional Project Monitoring Committee (RPMC).

As 2016 came to a close, two thirds of the 483 enrolled pro-jects or 320 projects were completed and 163 were in various stages of completion. Of the 163 ongoing projects, 45, or 9.32 percent of the total, were behind schedule, 93, or 19.25 percent, were implemented on-time, while 25, or 5.18 percent of the total, were ahead of schedule.

OVERALL PROJECT IMPLEMENTATION STATUS

TOTAL NUMBER OF PROJECTS = 483

Overall, the region attained a physical accomplishment rate of 92.4 percent as of December 31, 2016. This is 7.6 percentage points short of the 100 percent target. The total amount spent reached

1

EXECUTIVE SUMMARY

₱8.581 billion. This was equivalent to a fund utilization rate of 94.93 percent. The total amount released was 87.61 percent of the ₱10.318 billion programmed for CY 2016.

OVERALL PHYSICAL ACCOMPLISHMENT (%)

OVERALL FINANCIAL ACCOMPLISHMENT (P’000)

Sector Allocation Releases Expendi-tures

Funding Support

(%)

Fund Uti-lization

(%)

Environment 193,280 192,187 145,638 99.43 75.78

Governance 9,639 8,821 8,651 91.51 98.07

Infrastructure and Utilities

3,796,282 3,198,662 3,007,498 84.26 94.02

Social Development

5,149,298 4,677,847 4,458,460 90.84 95.31

Trade Industry and Tourism

32,639 25,432 25,417 77.92 99.94

Agribusiness 1,137,325 937,451 936,232 82.43 99.87

Total 10,318,464 9,040,402 8,581,900 87.61 94.93

2

A total of 150 projects supportive of the thrusts of the agri-business sector were monitored for 2016. As the year ended, 111 of these projects were completed, and the remaining 39 were in various stages of completion. Of the 39 ongoing projects, 5 projects were be-hind schedule, 31 were on-time and 3 were ahead of schedule as the year ended.

The sector attained an overall physical accomplishment rate of 90.12 percent, missing the 100 percent target by 9.88 percent. This was brought about by the 10.68 percent negative slippage incurred in the crops subsector. This is in spite of the overall physical accom-plishment rates in the subsectors on Livestock, and Science and Tech-nology at 104.37 and 104.09, respectively.

Among the major projects completed under this sector were the following:

National Stock Assessment Program, BFAR

Distribution of Fishing Gear/Paraphernalia, BFAR

Distribution of four wheel drive tractor, DA

Distribution of certified seeds, DA

Distribution of Vertical Dryer, DA

Establishment of Multiplier Farm and Tramline, DA

As for the overall financial status of the projects implemented under the agribusiness sector, ₱936.23 million were spent as the year ended. This is equivalent to 99.87 percent of the ₱937.45 million re-leases. The amount released comprised 87.61 percent of the CY 2016 programmed amount of ₱1.137 billion.

AGRIBUSINESS SECTOR

ENVIRONMENT SECTOR

All of the 35 projects enrolled under the Environment Sector were completed. Some of the projects completed by the DENR were the fol-lowing:

Maintenance and Protection of Established Plantation CY 2014, 2015 & 2016

Seedling Production/Procurement CY 2016 3

Plantation Establishment including Social Mobilization CY 2016

Provision of Technical Assistance in Integrated Coastal Management

Land Disposition - Patent Issuance (Residential Free Patent - RA100231)

The overall physical accomplishment rate in the Environment Sector reached 104.24 percent which is 4.24 percentage points above the end-of-year target. Projects under the subsectors on Green Envi-ronment and Climate Change Adaptation / Mitigation, namely the var-ious projects under the National Greening Program of the DENR and the Trainings/Seminar on Disaster Risk Reduction Management/ In-formation Dissemination conducted by the University of Northern Philippines, were the main contributors to the above-par physical ac-complishment of the Environment Sector.

In terms of financial status, funding support for the sector reached 99.43 percent. This is equivalent to total releases of ₱192.73 million out of the programmed amount of ₱ 193.28 million. In addi-tion, the sector generated employment totaling 2,500 man-days.

A total of 93 projects were monitored under the Social Devel-opment Sector for CY 2016. Forty-seven of the 93 projects were al-ready completed, and 46 projects were in various stages of comple-tion. Thirteen of the 46 ongoing projects were delayed, while 26 pro-jects were on-time and seven were ahead of schedule as the year end-ed.

In terms of physical status, the Social Development Sector in-curred a negative slippage of 11.09 percent. Overall physical accom-plishment only reached 88.91 percent, which is below the year-end target. This was mainly due to the low physical accomplishment of projects under the subsectors on Social Services and Community De-velopment, and Education and Manpower Development. These sub-sectors’ overall physical accomplishments fell short of the target by

SOCIAL DEVELOPMENT SECTOR

4

13.51 and 5.57 percent, respectively. Projects completed under the sector, among others, were the following:

Provision and Maintenance of Basic Education Facilities, DepEd

Special Program for Employment of Students (SPES), DOLE

DOLE Integrated Livelihood and Emergency Employment Program (DILEEP) – Kabuhayan, DOLE

Regular Conditional Cash Transfer, DSWD

The sector had the highest programmed amount for the year, totaling ₱5.149 billion. More than half of this amount, ₱2.699 billion was programmed for the implementation of the Regular Conditional Cash Transfer Program, more commonly known as 4P’s, of the DSWD. A total of ₱4.667 billion were released equivalent to a funding support of 90.84 percent. Of the amount released, ₱4.458 billion were spent, equivalent to an expenditure rate of 95.31 percent.

The sector had the second highest in terms of job generation next to Infrastructure Development with an estimated 140 thousand man-days generated.

GOVERNANCE SECTOR

Nine projects implemented by the PNP were enrolled in the Governance Sector. All of these projects were under the Peace and Se-curity Subsector. Six out of the 9 projects were completed, and the re-maining three projects were in various stages of completion.

Compared to the other sectors, the Governance Sector achieved the highest physical accomplishment at 130.33 percent. It also recorded the highest positive slippage, surpassing its year-end target. The projects Community Information and Education Program, Community Affairs Program, and Community Organization and Mobi-lization Project were the main contributors to the high physical ac-complishment of the sector.

5

As of year’s end, the amount spent in the sector totaled ₱8.651 million. This was equivalent to 98.07 percent of the ₱8.821million re-leases. Total releases accounted for 91.51 percent of the ₱9.639 pro-grammed for the year.

Among the 6 sectors, the TIT sector incurred the highest nega-tive slippage at 19.01 percent attaining an overall physical accom-plishment rate of 80.99 percent. The main reason for the delay was the low accomplishment of the projects under the Tourism Subsector. The subsector incurred an overall negative slippage of 91.14 percent.

Ten projects were monitored under the TIT sector. Five pro-jects were completed as the year ended and the other five projects were in various stages of completion. Projects completed under the sector, among others, were the following:

Negosyo Center in La Union, Ilocos Sur, and Ilocos Norte, DTI

Small Enterprise Technology Upgrading (SETUP), DOST

The total amount programmed for the sector for 2016 was ₱32.639 million. Total releases reached ₱25.432 million. This was equivalent to a funding support of 77.92 percent. Almost all of the amount released were spent as total expenditures reached ₱25.417 million. The sector also generated around 2,200 man-days.

TRADE, INDUSTRY AND TOURISM SECTOR

INFRASTRUCTURE AND UTILITIES SECTOR

The Infrastructure and Utilities Sector had the highest number of projects monitored for the year with 186. Out of these projects, 116 were completed and 70 were in various stages of completion. Thirty-eight of the 70 ongoing projects were delayed, 19 projects were on-time and 13 were ahead of schedule as the year ended.

The sector posted an overall physical accomplishment rate of 97.22 percent, missing its year-end target by 2.78 percent. The slip-page is due to the delayed implementation of 6 projects of the DPWH and one farm-to-market road of the DA.

6

On the financial side, the sector had the second highest pro-grammed amount for the year with ₱3.796 billion. Total releases reached ₱3.198 billion for a funding support of 84.26 percent. Ex-penditures on the other hand totaled ₱3.007 billion. This was 94.02 percent of the released amount as the year end.

STATUS OF MULTI-YEAR PROJECTS

The Agno River Irrigation System Extension Project (ARISEP) had an overall physical accomplishment of 21.13% as the year ended. Approximately, ₱425.183 million has been spent for the project to date.

Once operational, the project is expected to irrigate around 12,894 hectares of agricultural lands which will benefit an estimated 10,557 farm families.

7

Construction of Main Adris Canal (upper photo and Sabangan Sipon of Adris Canal

Source: National Irrigation Authority

For the Tarlac-Pangasinan-La Union Toll Expressway Project (TPLEX), Section 1 of the project, from Tarlac City, Tarlac to Rosales, Pangasinan, was opened to traffic on April 16, 2014. Section 2, from Rosales to Urdaneta City, Pangasinan, was opened to traffic on Febru-ary 17, 2015. For Section 3A, the Urdaneta City to Binalonan, Pan-gasinan section opened to traffic on July 28, 2016. The section to Pozorrubio on the other hand is scheduled to open in April, 2017. As of November 30, 2016, Section 3A was 81.11 percent complete, be-hind schedule by 0.05 percentage points. The last section of the pro-ject, Section 3B, from Binalonan, Pangasinan to Rosario, La Union, is scheduled for implementation in December, 2016 to April of 2018.

8

Tarlac-Pangasinan-La Union Toll Expressway Project

9

ROAD SECTION

ACTUAL ACCOMPLISHMENT

TARGET SLIPPAGE TO DATE

SECTION 1 97.76% 100.00% -2.24%

SECTION 2 98.41% 100.00% -1.59%

SECTION 3A 81.11% 81.06% 0.05%

SECTION 3B 0.00% 0.00% 0.00%

TARLAC-PANGASINAN-LA UNION TOLL EXPRESSWAY PROJECT STATUS

Installation of Rebars for App. Slabs , Sta. 71+340, NB, CMPCI (Upper Photo);

Completed Manaoag Underpass (Lower Photo)

Note:

1. The CY 2016 Year-End RPMES Monitoring Report was realized

through the support of the following participating Regional Line

Agencies (RLAs), State Colleges and Universities (SCUs), Local

Government Units (LGUs), and Government-Owned and Con-

trolled Corporations (GOCCs):

2. The list of the specific projects enrolled by project category can be

accessed at http://124.107.59.117

Category Entities

RLAs DENR, PNP, DA, DOH, DPWH, DSWD, ITRMC,

MMMHMC, R1MC, DepEd, DOLE, NCIP, PopCom,

SCUs MMSU, UNP, DMMMSU, ISPSC, NLPSC, PSU

LGUs PG-LU, PG-Pang

GOCCs NIA, NTA, PCA

10

Source: Department of Public Works and Highways & North Luzon Roadlink Joint Venture Co.

Primed Base Course at Sta. 71+400 to Sta. 71+560, NB, Expedway

The Project Monitoring and Evaluation Division

National Economic and Development Authority Regional Office 1

RDC-NEDA Building, Heroes Hill, Guerrero Road

City of San Fernando, La Union

Tel Nos. (072) 888-2679 * 888-2680 * 888-5501 local 109

Fax: (072) 888-2708

Email: [email protected] / [email protected]

Like us on Facebook: [email protected]