your solution to permanent hard armor erosion control armorform ® erosion control system utilizes...
TRANSCRIPT
The ARMORFORM® erosion
control system utilizes double-
layer woven geotextiles
engineered exclusively to serve
as forms for casting concrete
erosion control revetments and
linings. The forms are woven
from nylon and/or polyester
yarns and are designed with the
required mechanical and
hydraulic properties of a
superior textile form.
ARMORFORM, Inc.
PO Box 710
Jefferson, GA 30549
Ph/Fx (770) 237-0827
Best experienced with Click here to start.
Microsoft is a registered trademark and the Microsoft Internet Explorer Logo is a trademark of Microsoft.
Your Solution To Permanent Hard Armor Erosion Control
ARMORFORM Mat Being Pumped With Concrete
NEXT PAGE
ARMORFORM is positioned on the subgrade to be protected, where it is inflated with
pumpable fine aggregate concrete (structural grout) to form an erosion control mat.
ARMORFORM mats should be placed on a site-specific filter fabric.
ARMORFORM is available in various styles and thickness’. Uniform Section Mat
(USM), Filter Point Mat (FPM), Articulating Block Mat (ABM) and Armorbags are the
four standard styles of ARMORFORM. For the majority of applications, one of the
standard styles and thickness’ of ARMORFORM should prove adequate, however,
customized configurations and/or thickness’ can be manufactured. If required,
ARMORFORM mats can be produced to inflate to more than 24 inches thick or even
to allow revegetation of an eroded embankment.
CASE STUDIES
CONTACT US
ADVANTAGES
AVAILABLE
STYLES
FILTER POINT
MAT
UNIFORM
SECTION MAT
ARTICULATING
BLOCK MAT
ARMORBAGS
INSTALLATION
METHODS
CONCRETE
MIX DESIGN
grout mats grout bags concrete mats concrete blocks erosion control rip rap gabions ditch lining pond lining shoreline protection erosion mat mark torre concrete bags concrete pumping mirafi nicolon spillw ay usm fpm abm ucs fp ab grout pumping grout mats grout bags concrete mats concrete blocks erosion control rip rap gabions ditch lining pond lining shoreline protection erosion mat mark torre concrete bags concrete pumping mirafi nicolon spillw ay usm fpm abm ucs fp ab grout pumping grout mats grout bags concrete mats concrete
blocks erosion control rip rap gabions ditch lining pond lining shoreline protection erosion mat mark torre concrete bags concrete pumping mirafi nicolon spillw ay usm fpm abm ucs fp ab grout pumping grout mats grout bags concrete mats concrete blocks erosion control rip rap gabions ditch lining pond lining shoreline protection erosion mat mark torre concrete bags concrete pumping mirafi nicolon spillw ay usm fpm abm ucs fp ab grout pumping grout mats grout bags concrete mats concrete blocks erosion control rip rap gabions ditch
lining pond lining shoreline protection erosion mat mark torre concrete bags concrete pumping mirafi nicolon spillw ay usm fpm abm ucs fp ab grout pumping grout mats grout bags concrete mats concrete blocks erosion control rip rap gabions ditch lining pond lining shoreline protection erosion mat mark torre concrete bags concrete pumping mirafi nicolon spillw ay usm fpm abm ucs fp ab grout pumping grout mats grout bags concrete mats concrete blocks erosion control rip rap gabions ditch lining pond lining shoreline protection erosion
mat mark torre concrete bags concrete pumping mirafi nicolon spillw ay usm fpm abm ucs fp ab grout pumping grout mats grout bags concrete mats concrete blocks erosion control rip rap gabions ditch lining pond lining shoreline protection erosion mat mark torre concrete bags concrete pumping mirafi nicolon spillw ay usm fpm abm ucs fp ab grout pumping grout mats grout bags concrete mats concrete blocks erosion control rip rap gabions ditch lining pond lining shoreline protection erosion mat mark torre concrete bags concrete
pumping mirafi nicolon spillw ay usm fpm abm ucs fp ab grout pumping grout mats grout bags concrete mats concrete blocks erosion control rip rap gabions ditch lining pond lining shoreline protection erosion mat mark torre concrete bags concrete pumping mirafi nicolon spillw ay usm fpm abm ucs fp ab grout pumping grout mats grout bags concrete mats concrete blocks erosion control rip rap gabions ditch lining pond lining shoreline protection erosion mat mark torre concrete bags concrete pumping mirafi nicolon spillw ay usm fpm abm
ucs fp ab grout pumping grout mats grout bags concrete mats concrete blocks erosion control rip rap gabions ditch lining pond lining shoreline protection erosion mat mark torre concrete bags concrete pumping mirafi nicolon spillw ay usm fpm abm ucs fp ab grout pumping
O
Best viewed at
800 x 600
resolution
The ARMORFORMARMORFORMARMORFORMARMORFORM®®®® Advantage
ARMORFORM ARMORFORM ARMORFORM ARMORFORM is a unique product which has several advantages over more conventional methods of hard
armor, for instance:
U nlike conventional concrete, ARMORFORM ARMORFORM ARMORFORM ARMORFORM can be installed underwater.
U nlike rip rap, ARMORFORMARMORFORMARMORFORMARMORFORM is of consistent size and weight. ARMORFORMARMORFORMARMORFORMARMORFORM will also function as a mat
(with a fairly low Mannings “N” value) instead of individual units. This allows the designer to utilize an
ARMORFORMARMORFORMARMORFORMARMORFORM mat of considerably less thickness and weight to equal the performance of rip rap.
U nlike rip rap, gabions or precast concrete block mats, ARMORFORMARMORFORMARMORFORMARMORFORM can be installed without the use of
heavy equipment. Since the concrete is pumped into the mat through a hose, the trucks delivering the concrete
can also be parked up to several hundred feet away from the actual site. This allows for installations in even
the most inaccessible project sites.
U nlike most other hard armor systems, ARMORFORMARMORFORMARMORFORMARMORFORM is simply a form for concrete. Concrete is then
purchased from a local supplier of choice. By simply shipping the light-weight forms to the project site (and
not the actual armor unit itself) the client can save as much as 30% off of the overall cost of project simply due
to much lower freight costs. EXAMPLE: shipping 100,000 sq. ft. of 8 inch thick precast concrete block mats to
a project site would require over 200 flat-bed tractor-trailers at a cost $500.00 each, or more. That totals over
$100,000 simply to ship the units to the project. The same quantity of 8 inch ARMORFORMARMORFORMARMORFORMARMORFORM Articulating Block
Mat (ABM) would require less than 1 tractor-trailer.
W ith the introduction of our new ARMORFORMARMORFORMARMORFORMARMORFORM Vegetal Mat® (VGM) the system can be backfilled with
top soil and revegetated, providing a fully articulating hard armor system underneath.
NEXT
ARMORFORMARMORFORMARMORFORMARMORFORM®®®® is a proven product with literally tens of millions of square feet installed over the past 20+
years. We firmly believe in ARMORFORM ARMORFORM ARMORFORM ARMORFORM and its ability to provide a unique and proven solution to
permanent hard armor erosion control. The design approach for ARMORFORMARMORFORMARMORFORMARMORFORM is nearly the same as that of
poured concrete.
BACK ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc.
Available Styles
Articulating Block Mat (ABM) is formed with a double layer woven fabric,
joined together into a matrix of rectangular compartments each separated by a
narrow perimeter of interwoven fabric and containing interconnecting high
strength revetment cables. Relief of hydrostatic uplift pressure, caused by
entrapped and ground water, is provided through the narrow perimeter of
interwoven fabric.
Armor Bags are custom fabricated to fit job site requirements. Inlet valves,
attached by fabric flange to a slit in the surface of the bag, provide positive self
closure. Inlet tubes may be added to extend outside the bag if desired. Durable
nylon straps may be attached to the outside of Armor Bags to serve as
thickness controllers and to permit filling tapered or irregularly shaped bags.
BACK
Shown below are the standard syles of ARMORFORMARMORFORMARMORFORMARMORFORM available. “Click” on the
image to learn more about these specific styles.
ARMORFORM, Inc. ARMORFORM, Inc. ARMORFORM, Inc. ARMORFORM, Inc. NEXT
Filter Point Mat (FPM) fabric forms are constructed with spaced interwoven
filter points to form a lining of required average thickness, deeply cobbled
surface and specified weight to provide strength and erosion protection. Relief
of hydrostatic uplift pressure, caused by entrapped and ground water, is
provided by the woven filter points which are on 5”, 8” or 10” centers.
Uniform Section Mat (USM) fabric forms are constructed with spacer cords
on closely spaced centers to form a lining of required nominal thickness,
bonded cobbled surface and specified weight to provide strength and erosion
protection. Relief of hydrostatic uplift pressure, caused by entrapped and
ground water, may be provided by inserting plastic weep tubes through the mat
at specified centers.
Filter Point Mat (FPM)
Filter Point Mat (FPM) fabric forms are constructed with spaced interwoven filter points to form a lining
of required average thickness, deeply cobbled surface and specified weight to provide strength and erosion
protection. The design criterion for selection of lining thickness is the same as that used to determine the
thickness of conventional concrete slope paving. Relief of hydrostatic uplift pressure, caused by entrapped
and ground water, is provided by the woven filter points which are on 5”, 8” or 10” centers. Filter Point Mat
(FPM) is custom fabricated into multiple mill width panels, designed to fit actual site dimensions and
topography.
Filter Point Mat used to line a drainage ditch.
Filter Point Mat being pumped.
ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc. Available Styles BACK NEXT
FPM size Filter Point Spacing
Average Thickness
Weight/ sq. ft.
Coverage/ cu. yard of Concrete
5" FPM 5" 2.2" 26 lbs. 115 sq. ft.
8" FPM 8" 4.0" 47 lbs. 73 sq. ft.
10" FPM 10" 6.0" 70 lbs. 49 sq. ft.
FILTER POINT MAT (FPM)
DESIGN CONSIDERATIONS
FPM is used where velocities are
low, bedload and ice formations are
light and a roughness coefficient of
N= 0.025 to 0.030 is acceptable.
FPM is used where wave action is
light.
FPM is ideal for underwater
placement.
FPM should be installed on well
compacted soil conditions only.
Read interesting case studies of
ARMORFORM installations.
Uniform Section Mat (USM)
Uniform Section Mat (USM) fabric forms are constructed with spacer cords on closely spaced centers to
form a lining of required nominal thickness, bonded cobbled surface and specified weight to provide
strength and erosion protection. The design criterion for selection of lining thickness is the same as that
used to determine the thickness of conventional concrete slope paving. Relief of hydrostatic uplift pressure,
caused by entrapped and ground water, may be provided by inserting plastic weep tubes through the mat at
specified centers. Uniform Section Mat (USM) is custom fabricated into multiple mill width panels,
designed to fit actual site dimensions and topography.
Uniform Section Mat being pumped.
Uniform Section Mat used to line a high volume drainage ditch.
ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc. Available Styles BACK NEXT
USM size Nominal Thickness
Weight/ sq. ft.
Coverage/ cu. yard of Concrete
3" USM 3.0" 35 lbs. 97 sq. ft.
4" USM 4.0" 47 lbs. 73 sq. ft.
6" USM 6.0" 70 lbs. 49 sq. ft.
8" USM 8.0" 93 lbs. 36 sq. ft.
UNIFORM SECTION MAT (USM)
DESIGN CONSIDERATIONS
USM is used where velocities are low
to high, bedload and ice formations are
light and a roughness coefficient of N
= 0.015 is required.
USM is used where wave action is
light.
USM reduces seepage losses in
reservoirs, ponds, holding basins and
channels.
USM is ideal for underwater
placement.
USM is recommended for drainage
flumes and spillways.
USM should be installed on well
compacted soil conditions only.
Read interesting case studies of
ARMORFORM installations.
Articulating Block Mat (ABM)
Articulating Block Mat (ABM) is formed with a double layer woven fabric, joined together into a matrix
of rectangular compartments each separated by a narrow perimeter of interwoven fabric and containing
interconnecting high strength revetment cables. Articulating Block Mat forms are positioned on the area to
be protected, where they are filled with pumpable fine aggregate concrete (structural grout) to form a
mattress of individual blocks in a bonded block pattern. The high strength revetment cables become
embedded in the blocks to tie the blocks together and enable the revetment to resist tension in all directions.
Patented separate cable duct design assures that the revetment cables will be positioned securely in the
center of each block. Relief of hydrostatic uplift pressure, caused by entrapped and ground water, is
provided through the narrow perimeter of interwoven fabric after the grout has hardened. Articulating
Block Mat (ABM) is custom fabricated into multiple mill width panels, designed to fit actual site
Articulating Block Mat being pumped.
Articulating Block Mat used to protect a retaining wall.
ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc. Available Styles BACK NEXT
ABM size Nominal Block
Dimensions
Weight/ Block
Weight/ sq. ft.
Coverage/ cu. yard of Concrete
4" ABM 20" X 14" X 4" 90 lbs. 47 lbs. 73 sq. ft.
6" ABM 20" X 20" X 6" 195 lbs. 70 lbs. 49 sq. ft.
8" ABM 30" X 22" X 8" 420 lbs. 93 lbs. 36 sq. ft.
ARTICULATING BLOCK MAT (ABM)
Read interesting case studies of
ARMORFORM installations.
DESIGN CONSIDERATIONS
ABM is used where velocities are low to
high, bedload and ice formations are
light to heavy and a roughness
coefficient of N = 0.045 to 0.050 is
acceptable.
ABM is used where wave action is light
to heavy.
ABM is ideal for underwater placement.
ABM is recommended where subgrade
deformation is expected.
ABM is available in custom sizes, other
than those shown on this web site.
Armor Bags
Armor Bags are custom fabricated to fit job site requirements. Inlet valves, attached by fabric flange to a
slit in the surface of the bag, provide positive self closure. Inlet tubes may be added to extend outside the
bag if desired. Durable nylon straps may be attached to the outside of Armor Bags to serve as thickness
controllers and to permit filling tapered or irregularly shaped bags.
Bags being used in conjunction with Articulating Block Mat
to prevent erosion of a steep slope.
Bags being used to absorb the energy of large waves at an off-
shore oil drilling island in the Arctic Circle.
ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc. Available Styles BACK NEXT
ARMORBAG APPLICATIONS
Ideal for underwater placement.
Building groins and breakwaters.
Protecting shorelines against heavy
wave erosion.
Protecting buried pipelines against
scour.
Supporting and weighting underwater
pipelines.
Repairing stone jetties.
Installation Methods Once a contractor has been chosen there are four basic steps to
be taken in any ARMORFORM® erosion control installation.
They are: site preparation, panel placement and field
assembly, inspection before filling and structural grout
pumping.
SITE PREPARATION: Slope grading equipment is used to
excavate to required depths, contour the slopes to the specified
slope ratio and form the anchor, toe and terminal trenches
around the periphery of the installation. The area to be
protected must be free of rock, brush, roots or large soil clods.
ARMORFORM® should be placed on a compacted subgrade
and stable slope. The fabric forms are usually anchored into a
trench approximately two feet deep, by one foot wide, at the
top of the slope. The trench should be located one to three feet
from the top edge of the slope.
PANEL PLACEMENT AND FIELD ASSEMBLY: Once
the slope and other related excavation conforms to finished
grade and elevation specifications, installation of the filter
fabric and the ARMORFORM fabric forms may begin. After a
site specific filter fabric has been installed, the custom sized
ARMORFORM panels are rolled down the slope and
positioned for unfolding. The panels are positioned according
to prepared drawings where each panel is identified for
placement. The panel is then unfolded by a work crew and
pulled into position. The ARMORFORM panels should be
positioned loosely along the slope.
Once positioned, the upper edge of the panel is folded into the
anchor trench atop the slope. The extra fabric provided for
contraction during pumping should be accumulated and held
at the top of the slope and gradually released as the panel is
filled. Adjacent panels are joined by field sewing or zippering
the double-layer fabric forms, bottom edge to bottom edge,
INSPECTION BEFORE FILLING: When inspecting the
panels prior to pumping, wrinkles and loose fabric should be
expected as they are necessary to compensate for form
contraction. As much as 10% contraction in each direction
may be expected during the filling process. ARMORFORM
Incorporated should be contacted to determine the appropriate
contraction factor for your site conditions. All field sewn
seams, zipper connections and lap joints must be carefully
inspected to assure that no holes in the forms are present.
Colored thread is advised for all field sewn seams to facilitate
inspection. For detailed installation guidelines contact
ARMORFORM Incorporated.
STRUCTURAL GROUT PUMPING: The upper edge of
the ARMORFORM panel that has been placed into the anchor
trench should be weighted down with sandbags to prevent the
panel from sliding down the slope as it is pumped with grout.
Grout should then be injected into the lower mat area first,
proceeding gradually up the slope and into the upper anchor
trench until the entire panel has been filled. Structural grout is
injected into the ARMORFORM panels by inserting a 3”
diameter grout hose through a small slit cut in the upper layer
of fabric near the top of the slope. A grout-tight seal is formed
by wrapping the injection hose with burlap, or similar
material, while the grout is being injected. When the hose is
withdrawn, the burlap is stuffed into the hole where it remains
until the grout is no longer fluid. The burlap is then removed
and the concrete surface at the hole is smoothed by hand.
and top edge to top edge. When installing Articulating Block
Mat (ABM), transverse revetment cables should be spliced
together prior to joining of the top layers of fabric.
ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc. BACK NEXT
Concrete Mix Design
ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc. BACK NEXT
CONCRETE MIX DESIGN: A pumpable fine aggregate concrete (structural grout) is utilized in the
construction of all ARMORFORM revetments. As an aid to pumpability, a pozzolan grade fly ash may be
substituted for up to 35% of the cement. Mixes designed with 5% to 8% air content will have improved
pumpability and resistance to freeze-thaw. A retarding admixture may be used in hot weather.
Excess mixing water expelled through the permeable ARMORFORM fabric will reduce the volume of
fluid structural grout from 27 cu. ft. to approximately 25 cu. ft. of hardened grout and also reduce the
water / cement ratio from approximately 0.7 to approximately 0.4..
Fine aggregate concrete consistency should be in the 9-11 second range when passed though the 3/4”
orifice of the standard flow cone described in ASTM C-939-93. Tests utilizing a concrete slump cone are
not appropriate.
Material Mix Proportions Lbs./cu. Yd.
After Placement Lbs./cu. Yd.
Cement 750-850 810-920
Sand (FM 2.60) 2030-2120 2195-2290
Water 485-555 360-430
Air as required
Typical Range of Mix Proportions (approx. 3,000 psi)
ARMORFORMARMORFORMARMORFORMARMORFORM is pumped and formed
under pressure. This method provides
superior strength and durability when
compared to conventional concrete
forming. Tests show that structural grout
pumped into ARMORFORM is 1.5 to 1.75
times stronger, plus it absorbs 5% less
water.
The ARMORFORM system is ideal for
situations requiring resistance to mild
concentration of acid, alkali, salt or
petrochemicals. With minimal water
absorption, ARMORFORM also resists
freeze - thaw action.
Concrete that is pumped into ARMORFORM is 1.5 to 1.75 times
stronger than conventionally formed concrete.
Case Studies
PIPELINE PROTECTION A once buried pipeline that is now exposed can be of serious
concern. When Colonial Pipeline found out that a 16” diameter
pipeline that had once been buried well beneath Raccoon
Creek in North Georgia was now exposed they required
immediate action. Find out how ARMORFORM® Articulating
Block Mat was utilized to control the erosive forces of the
creek so that the pipeline would not be re exposed.
ARMORFORM has been utilized in many different applications. Wherever erosion is a
problem or of concern ARMORFORM can help. Here are just a few projects in which
ARMORFORM was selected as the solution to a serious erosion control problem.
COMING SOON LANDFILL CAPS
Providing erosion protection on steep landfill caps and
surrounding drainage channels.
OVERFLOW SPILLWAY
In the summer of 1995, a large coal company in West Virginia,
was in the process of upgrading an overflow spillway at their
coal refuse slurry impoundment facility in Boone County,
West Virginia. The new spillway would need to be constructed
directly over coarse coal refuse, and provide a safe means of
transporting large volumes of water over a distance of
approximately 1,700 feet (520 meters).
COMING SOON
ARMORFORM FPM helps to remove flood waters in a
suburban Atlanta neighborhood.
ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc. BACK NEXT
Exposed Pipeline is Once Again Protected
Thanks to ARMORFORM
A once buried pipeline that is now exposed can
be of serious concern. When Colonial Pipeline
found out that a 16” diameter pipeline that had once
been buried well beneath Raccoon Creek in North
Georgia was now exposed they required immediate
action.
In December of 1995, shortly after the exposed
pipeline was discovered, Colonial Pipeline had a
crucial decision to make. The pipeline obviously
needed to be re buried. The options were to close
the pipe, refit it and re bury it below the now
relocated creek bottom or to simply move the creek
back to its original position. The first option
appeared to be the easiest thing to do, however,
shutting down the pipeline would cause serious
down time and there was no guarantee that the creek
would not relocate itself again and cause the
pipeline to be re exposed. Upon further inspection
of the site it was discovered that the outer bank of
the creek was now less than 20 feet away from a
500,000 volt electrical tower! It was obvious that
the creek would have to be moved.
ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc. CASE STUDIES BACK NEXT
It was decided to relocate a 250 feet long curved
section of the creek in order to re bury the exposed
pipeline and to protect the electrical tower. The
creek would have to be moved over 40 feet thus
creating a much sharper bend than that which was
formed naturally, and there was evidence in the
surrounding terrain that the creek frequently
overtopped its banks. It was obvious that there was
the potential for a serious erosion problem. Hard
armoring of the creek’s embankments would be
necessary.
Once it was decided what needed to be done
Colonial Pipeline was faced with another problem.
The application of the hard armor system would
have to be done without dewatering the site. Since
it was an active creek, flow conditions of 2 feet
deep at velocities of 5 fps were expected during
the construction. Any type of poured concrete or
shotcrete was immediately ruled out. Rip rap
seemed to be the obvious solution, but very large
stones would be needed and it was feared that the
sized of the stone would lower the capacity of the
creek and cause more water to spill out of its
banks. It was decided that an articulated concrete
block mat, or ACB, would be the best possible
solution. ARMORFORM® Articulating Block
Mat (ABM)
A preconstruction meeting was held at the project
site with Colonial Pipeline and ARMORFORM
representatives present. It was determined that the
creek should retain its current sectional area. The
creek would be relocated by cutting from the inside
embankment and filling the outside embankment.
Final geometry would be trapezoidal with a bottom
width of 20 feet, a depth of 12 feet, 1.5:1 side slopes
and a bed slope of approximately 1%. It was also
estimated that a discharge of 7,000 cfs would be
experienced frequently. This volume of water
equates to a unit discharge of over 180 cfs/ft at a
velocity of over 16 fps. Since the application area is
in a sharp curve, additional shear stresses can also
be expected. The size of ARMORFORM ABM that
was chosen is a 6” thick mat.
CONTINUED
Exposed 16” diameter pipeline caused by the
natural relocation of Raccoon Creek.
A 500,000 volt electrical ower is dangerously close to the the edge of the
creek’s outer embankment.
Pipeline case study (continued)
Since time was a critical issue the custom fabricated
ABM panels were assembled immediately and the
dirt work was commenced. Just a few days after the
preconstruction meeting the custom fabricated
ABM panels were delivered to the job site, and the
now relocated creek was ready for armoring.
After grading was completed the creek was effectively “moved” to re bury the
exposed pipeline. Also note that the electrical tower is now far away enough
from the outer embankment to be out of the photograph.
Once the side slopes were graded to the desired
angle, an “anchor” trench was cut at the top of each
slope. This trench is located approximately 1 foot
back from the top of the slope and its purpose is to
provide an anchor or “toe-in” for the
ARMORFORM mats. This anchor will help reduce
the possibility of the mat from sliding down the
slope, however, its primary function is to prevent
scour at the top of the slope caused by water
flowing outside of the creek’s banks when a flood
occurs. A geotextile filter fabric supplied by Mirafi
was installed directly over the subgrade to prevent
the loss of fines when water passes through the open
areas of the concrete mat. The ARMORFORM
panels were then placed on top of the geotextile and
temporarily held in place by placing sandbags
around the edges. During the inflation process the
sandbags are simply pushed off of the ABM as the
injected grout thickens the mat.
The ARMORFORM panels were installed starting
at the downstream end first. By working
downstream to upstream, panels could be
overlapped onto one another in the flow direction so
that water could not infiltrate the system. Access to
the project site was limited to 1 side of the creek,
however, the armoring was required on both
embankments. The work crews simply carried the
light weight ABM panels across the creek and
unrolled them into place. The grout was then
pumped through a hose and into the ABM from the
opposite side of the creek where the pump and the
trucks delivering the concrete were located.
ABM panels being inflated on the inside embankment. Note the geotextile filter
fabric on the slopes of the outer embankment in the foreground.
The installation of the ARMORFORM panels
continued into its second day with just under half of
the project completed. While the inflation of the
panels continued, a dozier backfilled the anchor
trenches of the mats that were installed the previous
day. The second day of installation proved to be
much more productive, and the project was
completed in the early hours of the evening. The
installation of the ARMORFORM panels went
without a single glitch. Over 400 cubic yards of fine
aggregate concrete was injected into the ABM
panels in just 2 days, and the project was completed
substantially under the amount budgeted by
Colonial Pipeline.
As the inflation of the ARMORFORM mats continues into the second day a
dozier can be seen in the background filling in the anchor trench of the mats
installed the previous day. Note the change in the color of the concrete. The freshly pumped concrete in the foreground is dark gray, while the concrete
that was installed the previous day has turned to a whitish color.
CONTINUED
NEXT BACK CASE STUDIES ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc.
Pipeline case study (continued)
Nearly four years after the installation of the 6”
Articulating Block Mat the creek still flows between
the ARMORFORM protected embankments with no
apparent damage to the system. The mats are
completely intact and are providing the necessary
protection to the creek’s embankments to insure that
the pipeline will not be re exposed.
Completed ARMORFORM 6” ABM installation (looking downstream)
ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc. Case Studies BACK NEXT
Other Installations
ARMORFORM has been utilized to protect a
pipeline or fiber optic cable in several projects.
If the pipeline or fiber optic cable crosses a
creek the potential for erosion of the creek bed
to expose the pipeline or cable is imminent.
Shown here are photographs of just a couple of
projects in which ARMORFORM was utilized
to protect these crossings.
ARMORFORM ABM being installed over a fiber optic cable
crossing in a shallow creek.
ARMORFORM ABM mat being installed over a
restored pipeline crossing
ABM mat before concrete injection
(looking upstream)
ABM Mat after concrete injection
(looking downstream)
ARMORFORM Protects Steep Landfill
Slopes Against Erosion.
SORRY, THIS PAGE IS STILL
UNDER CONSTRUCTION.
ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc. Case Studies BACK NEXT
ARMORFORM is Chosen to Protect
a High Volume Spillway
In the summer of 1995, A large coal company in
West Virginia was in the process of upgrading an
overflow spillway at their coal refuse slurry
impoundment facility. The new spillway would
need to be constructed directly over coarse coal
refuse, and provide a safe means of transporting
large volumes of water over a distance of
approximately 1,700 feet. The bed slope of the
spillway would vary from 1% to 10% with the 10%
section generating flow velocity of over 20 feet per
second and a corresponding shear stress of nearly 40
pounds per square foot during a severe storm event.
It was obvious that a substantial form of erosion
protection would be necessary to combat the
potentially destructive forces that would be present
during these hydraulic conditions.
The coal company enlisted the services of a local
consulting engineering firm to design the spillway
and confirm that the selected form of erosion
protection would be adequate. Rock riprap was
almost immediately ruled-out due to the large
diameter required to resist the expected flow
conditions, and the designer wanted a system that
was less restrictive than large boulders. Although a
properly installed (i.e. reinforced, freeze/thaw
resistant, expansion joints, etc.) poured concrete
spillway would provide sufficient hydraulic
stability, it was believed that the cost would be
higher than desired. With numerous, successful
spillway projects under their belt, the engineering
firm felt most comfortable in selecting
ARMORFORM Articulating Block Mat (ABM).
Product Selection and Design
ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc. CASE STUDIES BACK NEXT
Due to the flow conditions that would be present at
the coal refuse facility, the engineering firm
determined that the ABM erosion protection would
be required for the 40 foot wide bottom and both
side slopes of the trapezoidal spillway. The
“finished” average thickness requirement of the
ABM will be 8 inches to produce individual block
sizes of approximately 24 inches x 24 inches and a
weight of 95 pounds per square foot. High strength,
3/8 inch diameter polyester cables, exhibiting a
nominal breaking strength of 10,000 pounds will be
inserted into the ABM at the factory. These cables
will provide additional tensile strength to the
system, as well as reinforcement during
articulation.
Entrance point of the spillway. ABM mat is buried in a 10 feet deep
trench at this location.
Completed spillway, looking downstream.
CONTINUED
ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc.ARMORFORM, Inc. CASE STUDIES BACK
Spillway case study (continued)
In prior applications, 8 inch thick ABM has
successfully withstood unit discharges in excess of
100 cubic feet per second/per foot, which is the
approximate equivalent to the expected discharge of
the spillway at this project site, however, as an
added factor of safety, it was decided that
intermediate anchoring would be necessary every
120 feet along the 10% slope section of the spillway
to resist drag forces. A poured concrete “deadman”
anchor, constructed approximately 5.5 feet below
grade, will secure each 120 foot long section of
ABM. Each subsequent ABM panel would then be
positioned to provide a 5 foot minimum overlap of
the previous panel to serve as an “expansion” joint.
The panels along the sides of the spillway would be
installed in a 3 feet deep terminal trench and
subsequently buried to provide additional
anchoring. The design analysis concluded that the 8
inch ABM, utilizing these methods of installation,
would produce a factor of safety greater than the
targeted 1.5 to 1.
referencing each panel, identified numerically, with a
panel layout plan prepared by ARMORFORM, Inc.
Construction
A local contractor, McGraw & Son Construction
Company, Inc., Glen Daniel, West Virginia, was
chosen to construct the spillway and install the ABM.
The installation of the ABM panels commenced at the
bottom of the spillway and proceeded upwards. This
“reverse-order” of installation was necessary to
properly construct the intermediate anchor trenches
and overlaps. More than 70 custom made panels of
ABM were shipped to the project via motor freight.
Each panel, up to 3,500 sq. feet in size, was fabricated
to fit a specific section of the spillway. Proper
placement of the panels was facilitated by cross-
ABM panels were unrolled into position and joined
together with a portable sewing machine prior to
filling with concrete. The ABM was installed directly
over a site specific geotextile filter to prevent the loss
of underlying material through the openings around
the perimeter of the blocks. For this project, a 5 ounce
per square yard nonwoven geotextile was selected. A
nonwoven geotextile was selected because it exhibited
a higher angle of friction and greater hydraulic
characteristics when compared to a woven geotextile.
The fine aggregate concrete, supplied by a local ready
mix plant, was injected into the panels, through a 3
inch diameter hose, utilizing a conventional grout
pump. Once the ABM was filled with concrete to the
required thickness and allowed to cure, coal refuse
was utilized to backfill the terminal trenches along the
sides of the spillway. The entire project required
approximately 45 days to complete with more than
5,000 cubic yards of concrete being injected into the
ABM panels.
For this high volume spillway, ARMORFORM ABM
appeared to be the only practical solution. Riprap was
not a viable option due to the extremely large diameter
stone that would be required, and to properly install a
poured concrete spillway would have been far too
costly. This coal company is just one of several end
users who have discovered the advantages of
ARMORFORM. Coal refuse facilities operated by
other firms have also benefited from this technology,
as have the owners/operators of landfills and
embankment dams.
This case study is a summarized version of an article “High
Tech for High Volume” which appeared in the May 1998 issue
of GFR magazine.
Summary
END OF WEB SITE