zambia : national rural water supply and …evrd.afdb.org/documents/docs/en_pn10639.pdfcommunity...
TRANSCRIPT
ZAMBIA : NATIONAL RURAL WATER SUPPLY AND
SANITATION PROGRAM 1. BASIC INFORMATION
a. Basic project data
Project title: National Rural Water Supply and Sanitation Program
Project code: P-ZM-E00-009 Instrument number(s): 2100150013198
Project type: Public Operation Sector: Water And Sanitation
Country: Zambia Environmental categorization (1-3) : 2
Processing Milestones Key Events Disbursement and Closing date
Date approved: 27/112008 Cancelled amount: Original disbursement deadline:
31/03/2012
Date signed: 22/12/2008 Supplementary financing: NA Original closing date:31/12/2011
Date of entry into force :
29/01/2009
Restructuring: nA Revised disbursement deadline:
30/11/2015
Date effective for 1st
disbursement: 29/01/2009
Extensions (specify dates):
31/12/2011 to 30/06/2013
30/06/2013 to 31/12/2014
31/12/2014 to 31/03/2015
Revised closing date: 30/11/2015
Date of actual 1st : 18/04/2009
b. Financing sources
Financing source/ instrument
(MUA)
Approved amount
(MUA) :
Disbursed amount
(MUA) :
Percentage disbursed
(%):
Loan: ADF 12,063,968.00 12,063,968.00 80.43%
Grant:
Government:
Other (ex. Co-financiers):
TOTAL : 12,063,968.00 12,063,968.00 80.43%
Co-financiers and other external partners: -
Execution and implementation agencies: Ministry of Local Government and Housing
c. Responsible Bank staff
Position At approval At completion
Regional Director - Kennedy Mbekeani (OIC)
Sector Director Andrianarison Rakotobe Mohamed El Azizi
Sector Manager Sering Jallow Osward Chanda
Task Manager Mecuria Assefaw Herbert Chinokoro
Alternate Task Manager
PCR Team Leader Alex Gomani
PCR Team Members Herbert Chinokoro
d. Report data
PCR Date : 8/12/2015
PCR Mission Date: From: 26/10/2015 To: 3/11/2015
PCR-EN Date: 26/06/2018
Evaluator/consultant : Daniel VAN ROOIJEN Peer Reviewer/Task Manager: Ram Janakiram
PCR EVALUATION NOTE FOR PUBLIC SECTOR OPERATIONS
2. PROJECT DESCRIPTION Summary from Appraisal Report including addendum/corrigendum or loan agreement, and taking into account any modification that
occurred during the implementation phase.
The project entitled “National Rural Water Supply and Sanitation Program” was developed to support the
government of Zambia to improve water supply, sanitation and hygiene in rural areas of Zambia. The project
consisted of 4 major components; 1) improving access to water supply, improving access to sanitation and
hygiene, 3) support to improve the performance of the Rural Water Supply and Sanitation sub-sector, and 4)
programme management. The project agreement became effective in January 2009. The initial completion date of
31 December 20011 was extended three times with a final revised completion date of 30 November 2015.
a. Rationale and expected impacts:
The project rationale was that investments to improve rural access to water supply, sanitation and hygiene
practices combined with institutional capacity strengthening of the RWSS sector will reaching the MDG goal for
water as well as improving health and quality of live, and reducing poverty of the rural population of Zambia. The
expected impact from the project was 3-fold; 1) improved access to water and sanitation, 2) reduced infant and
maternal mortality, and 3) reduced incidence of worm infestation and diarrheal diseases among infants and
children in rural communities. The people expected to benefit from the project are the total rural population of
Zambia, all local authorities working in the RWSS sector and schools and associations, the private sector and
development agencies. The project deadline was extended 3 times during the execution phase, adding about 3
years to the planned duration of 5 years.
The main problems addressed by this project were (as stated in the appraisal report):
1. The water supply and sanitation infrastructure in many of the rural areas in Zambia were dilapidated;
2. Ineffective operation and maintenance leading to a large number of dysfunctional water points throughout the
rural parts of Zambia
3. The capacity of the water supply production and sanitation systems were inadequate to meet the demand of
the existing population and to cater to future growth of Zambia;
4. Low priority and declining budgetary allocation to rural water supply in the past were major constraints to
ensure the provision of secure water supply to the population
5. Un-coordinated government and donor projects often led to duplication of efforts
6. Over concentration of activities in a few provinces due to donor preferences for particular districts or
provinces
The expected impact from the project was 3-fold; 1) improved access to water and sanitation, 2) reduced infant
and maternal mortality, and 3) reduced incidence of worm infestation and diarrheal diseases among infants and
children in rural communities. The people expected to benefit from the project are the total rural population of
Zambia, all local authorities working in the RWSS sector and schools and associations, the private sector and
development agencies
b. Objectives/Expected Outcomes:
The main objective envisaged in the program was to provide equitable and sustainable access to water supply and
sanitation to meet basic needs for improved health and poverty alleviation for Zambia’s rural population and
contribute towards achievement of MDG for water and sanitation of respectively 75% and 60% coverage by 2015.
The specific objectives of the programme were to: 1) increase access to safe, reliable and convenient quantities of
water supply from present 37% to 55% of the rural population by 2010 and to 75 percent by 2015, 2) to increase
access to proper sanitation from 13% to 33% of the rural population by 2010 and to 60 percent by 2015. The
program also had comprehensive gender objectives aiming to increase participation women in trainings and
increasing the proportion of women in construction as well as operation and maintenance of water supply and
sanitation infrastructure.
The long term expected outcomes are:
- Improved access to water and sanitation
- Reduced infant and maternal mortality, and;
- Reduced incidence of diarrhoea diseases and worm infestation in infants and children in rural
communities.
The expected outcomes in the medium term are:
- Increased proportion of the rural population with adequate and convenient supply of clean water;
- Increased number of rural families having constructed their own improved sanitation facilities and
effectively using them;
- All rural schools with access to adequate sanitation facilities;
- Improved awareness and attitudes on environmental cleanliness and personal hygienic practices;
- Effective RWSS planning and programming leading to equitable, transparent and efficient allocation of
resources;
- Rural Communities and LAs are gender responsive;
- The profile of the WSS sector raised in national planning and allocation of resources and increased
stakeholder participation and buy in into the RWSS programme, and;
- Improved functionality of rural water supply facilities.
c. Outputs and intended beneficiaries:
The programme has the following 8 outputs:
1. 1,585 new boreholes constructed;
2. 655 existing boreholes rehabilitated;
3. 10 water schemes reticulated;
4. 272 hand dug wells constructed;
5. 871 public sanitation facilities constructed;
6. improved capacity of MLGH and Districts in order to manage RWSS more effectively;
7. 24,400 VWASHE members trained, and;
8. 448 area pump menders trained.
The programme aims at providing safe water supply and sanitation in all rural areas of Zambia to people who are
currently lacking safe access. Other beneficiaries included the central and local government institutions will be
enhanced, the artisans trained and assisted to establish repair outlets for water supply and sanitation systems, and
the private sector. The prioritization and selection criteria for districts/provinces, took into account the baseline
access level of water supply and sanitation, population size and poverty indicators, such as infant mortality rate.
The Luapula Province and Northern Province were selected, based on their low coverage of water supply and
sanitation and worst poverty rates, relative to Zambia’s other provinces. Within these two provinces fifteen
districts were selected for programme intervention.
d. Principal activities/Components:
The appraisal report and PCR lists the following four components and associated activities:
(i) Water Infrastructure Development consisting of the following activities:
Rehabilitation, improvement, and new construction of rural water schemes;
Provision of rural sanitation for communities and public institutions
(ii). Sanitation and Hygiene Education
Community management training and capacity building for planning and management of water supply and
sanitation facilities and sanitation and hygiene education.
(iii).Institutional Support and Capacity Building
Develop and/or revise policies guidelines, tools, checklists;
Capacity building: human resources development, organization and operational capacity strengthening and
organizational systems improvements, gender mainstreaming and HIV/ AIDS mitigation at national and
district levels
Planning, support and supervision through technical support (TA) teams and NGOs
(iv).Program Management
Develop and maintain a comprehensive RWSS Information Management System (IMS);
Establish water sector indicators and benchmarks which include gender specific indicators;
Collect and analyze data and information generated for NRWSSP operations;
Develop O&M system and spare parts supply chain;
Program management capacity at national and district levels.
3. PROJECT PERFORMANCE ASSESSMENT
RELEVANCE
a. Relevance of the project development objective: The project’s development objectives, to improve access to water supply and sanitation and hygiene practices, is considered
very relevant with regards to the governments goals with regards to reducing poverty and improving health outcomes of the
rural population of Zambia. The project scope fits well with strategies and priorities by the Bank (e.g. water policy on
integrated water resources management). It is also well embedded into the water vision and sector strategies, principles and
policies by the Government of Zambia. The vision in Zambia’s Water policy states: “To optimally harness water resources
for the efficient and sustainable utilisation of this natural resource to enhance economic productivity and reduce poverty.” In
addition, the programme is aligned with the water act and other sector strategies.
The evaluator concurs with the PCR rating for this criterion and considers it as satisfactory (3).
b. Relevance of project design (from approval to completion):
According to the PCR the program was well designed to meet the objective of assisting the Borrower to improve
access for the rural population to safe, reliable and convenient quantities of water supply of quality meeting
national standards and to increase the access of the rural population to improved sanitation and improved health
& hygiene practices. The program components did reflect this well as they were all necessary and sufficient to
achieve the objective; and took into account lessons learnt from the past projects in order to enhance its impact on
the population. The main design elements included:
(i) formulation of the program through a participatory approach that involved representatives of all
stakeholders (women, communities, NGOs, private sector, local governments, Cooperating Partners
(CPs) and central government) and
(ii) formulation of the NRWSSP in line with the national strategies of the FNDP
(iii) the adoption of joint sector review mechanism for monitoring sector performance to reduce government
transaction costs, and
(iv) Adoption of a common operations and maintenance system and supply chain for spare parts.
(v) The community-based approach for implementation, and O&M was expected to contribute to
sustainability by creating community ownership.
The programme was designed in a straightforward and logic manner, consisting of separate components for water
supply, sanitation and hygiene promotion, institutional sector strengthening, and programme management. The
design is relevant with regards to the impact it is expected to make. From literature it is known that improvements
of access to water supply and sanitation has direct positive outcomes for health and poverty reduction. The
programme also follows a clear course based on previous interventions in the water and sanitation sector and
includes a clear gender focus. The multiple extensions granted during implementation phase would question the
quality of planning at project design phase. The substantial under-estimation of unit-costs for construction of
water supply schemes raises the question on what basis the initial calculations at programme design were done.
The risks assessment is adequate and the risks considered in the appraisal report are realistic and inclusive.
Environmental and social protection measures were anticipated through the development of an environmental and
social review template for the sub-project to be developed under the programme. Environmental protection
measures are centred on the protection of water sources from pollution and preventing the development of
breeding grounds for mosquitoes, flies and other insects at the water and sanitation sites. The appraisal reports
mentions the special attention to gender objectives as part of social protection, however there is no information
stating how priorities of vulnerable groups (such as the poor, elderly, disabled people, and children) are
considered in the programme or its sub-components. There is no clear indication that a pro-poor design was used.
The evaluator concurs with the PCR rating for this criterion and considers it as satisfactory (3).
EFFECTIVENESS
c. Effectiveness in delivering outputs:
Based on the available information, it can be concluded that the project delivered with mixed results on its 8
intended outputs. While for some outputs, the target was met or exceeded, there are a few critical outputs on
water supply and public sanitation that did not perform as planned.
In the PCR, the justification in the narrative section of output 3 on construction of water schemes gives
inadequate sensitization about available water supply technologies as the prime reason why the target was not
met. However, it is not explained or justified why sensitization was inadequate. Under output 4, construction of
hand-dug wells, there is a lack of clarity on the exact reasons why just 44% of the target was met. Similar for
Output 5 on construction of public sanitation facilities, whereby less than 70% of the target was met, there is a
lack of information on the reasons why the target was not met, despite a number of project extensions. The
training components of the programme seems to have delivered well against the targets.
This criterion on effectiveness in delivering outputs is considered unsatisfactory (2) which is lower than the
PCR rating of satisfactory. The reviewer agrees with this revised rating of unsatisfactory (2).
d. Effectiveness in delivering outcomes:
The effectiveness in delivering results at the outcome level is mixed. An important outcome of the project is the
people benefiting from access to improved water supply and sanitation infrastructure and services. However,
there is a lack of information on the methods used to calculate the number of beneficiaries. The outcome level
indicators are shown as national access rates in %. Besides the national level outcome reporting, outcome 3 and 4
show progress at the regional level in the two regions of intervention (Luapula Province and Northern Province),
which is considered very useful to demonstrate actual progress made in these two regions which can be attributed
to the ADB-funded programme. There is insufficient detail providing reasons why access to public sanitation
facilities was not fully achieved against target. Also, there is no indicator on the number of people benefiting from
household sanitation, as a result of the use of the CLTS approach. Behavioural change and sensation as well as a
better quantification of capacity strengthening at the individual staff level could have been captured at the
outcome level reporting, for example through the use of a baseline and end line survey.
This criterion on effectiveness in delivering on outcomes is considered satisfactory (3) which is the same as
the PCR rating.
e. Project development outcome:
Based on the information available, it is evident that substantial progress has been made with regards to
improving access to water and sanitation in the target areas (2 provinces) in which the programme has focussed. It
is however not clear to what extent improved health and poverty alleviation, as well as behavioural change with
regards to hygiene practices was realised for Zambia’s rural population. Despite the fact that RWSS units have
been established and X no. of members have been trained, there is a lack of evidence demonstrating that local
authorities have increased their capacity to manage RWSS more effectively. The evaluator rates this criterion
as unsatisfactory (2), which is lower than the PCR rating of satisfactory.
f. Beneficiaries:
There is insufficient information detailing the methods used to calculate the number of beneficiaries for
sanitation. The calculation of beneficiaries was clarified by the task manager during final review, as follows:
The national rural program gives the population served per water point which is 250 people/BH or hand dug well. Water
reticulated schemes serve 3000 people at each scheme.
New BHs 1857 *250 = 461,750
Rehab 607*250 = 151,750
Hnd dug wells 121*250 = 30,250
Schemes 5*3000 = 15,000
Total beneficiaries in 658,750 (of clean water supplies)
The PCR includes a gender figure, however “>50%” is not an exact figure. It would be useful to know the exact
figure for future reference and for comparison with other projects.
g. Unanticipated additional outcomes (positive or negative, not taken into consideration in the project
logical framework):
The evaluator would generally agree with the additional outcomes listed in the PCR. However, some of these
would have already been known at project design phase and should therefore be considered as anticipated. These
are dignity for girls through access to improved sanitation, hygiene promotion and health outcomes for children.
The successful use of CLTS is listed as an unanticipated additional outcome, however achievements in household
access sanitation appears not to have been quantified which is considered a missed opportunity. Some of the
unanticipated additional outcomes listed could have been better documented, quantified and used as success
stories of the programme. The inclusion of two negative outcomes is welcomed, as this helped to a more balanced
and realistic report.
EFFICIENCY
h. Timeliness:
The project agreement became effective in January 2009. The initial completion date of 31 December 20011 was
extended three times with a final revised completion date of 30 November 2015. The 3 years in additional to the
planned duration of 5 years resulted in a total project duration of about 8 years. The ratio of planned and actual
implementation time is 0.62, which is in the category of be (<0.75 and ≥0.50) resulting in a rating of
unsatisfactory (2) for this criterion.
i. Resource use efficiency:
The calculated proportion between the median physical implementation rate (95.65%) and commitment rate
(80.43%) is 1.19. The short explanation given in the PCR is considered sufficient. This corresponds to a highly
satisfactory rating (4), which is higher than the PCR rating for this criterion (3).
j. Cost-benefit analysis:
The economic rate of return at project approval stage was 28% compared to 21% upon project completion. The
calculated ratio between the ERR at completion and the ERR at appraisal is 0.75 which is within the category
giving a satisfactory score (ratio within category of <1 and ≥0.75). Overall, the evaluator generally agrees with
the calculations made to arrive at the ERR in Annex 10 of the appraisal report. The subsequent satisfactory rate
given satisfactory (3) which is higher than the PCR score (2).
k. Implementation progress:
The information made available reports of late submission of documents to the ADB, delays and unfinished
construction of water and sanitation infrastructure, etc. Field reports from the bank and external audit reports
show a large number of areas and examples in which the executing agency has filed to comply with covenants
and procedures. At various times during the implementation phase, some of the issues raised were, poor book
keeping record, lack of community involvement to ensure ownership, issues with tendering of works, poor
financial management, poor M&E, project staffing issues, and motor bikes not having insurance. The evaluator
would rate this criterion as unsatisfactory (2), which is lower than the PCR rating of satisfactory.
SUSTAINABILITY
l. Financial sustainability:
The PCR narrative for this section uses the experience with the V-WASHE Committees as good evidence of
financial sustainability. There seems to be a lack of systematic assessment of financial feasibility of water supply
schemes, for example through carrying out a willingness and capacity to pay for improved water services. The
positive example of Chipowe village is given, stating their relatively high contribution. Based on additional
information provided by the task manager, it is clear that the project experience in Chipowe village is similar to
other villages in other district where the programme has had an intervention. Based on additional information
provided by the task manager, it is clear the way local authorities manage their budgets to cover major
maintenance works (for costs exceeding ZMK 500). Only water supply is mentioned when it comes to financial
sustainability, however it is unclear what payment modalities exist for the sanitation facilities constructed at
public places such as market centres. The evaluator would rate this criterion as satisfactory (3) which is the
same as the PCR score of satisfactory.
m. Institutional sustainability and strengthening of capacities:
Based on the information available, staff in charge of running the water supply and sanitation systems in the two
provinces of intervention have received proper technical trainings in system operation and maintenance and have
been provided with tools and equipment. In addition there seems to be a good account of capacity building at the
level of local authorities whom seem to be better equipped to carry out their responsibilities. The D-WASHE
Committees, V-WASHE Committees and Area Pump Members are considered good entities to ensure community
participation at the local level. The evaluator rates this criterion as satisfactory (3) which is in line with the
PCR score.
n. Ownership and sustainability of partnerships:
The PCR narrative for this section raises a very valid point on the urgent need to ensure that communities are
sensitized on the multiple and long-term benefits of improved water supply and sanitation service delivery for
their lives. At least one of the audit reports mentioned vandalism in a number of cases which could be a sign of a
lack of community involvement and ownership. It will be essential for all development agencies working in the
WASH sector in Zambia, to use a common approach for interventions in the area of water supply, sanitation and
hygiene promotion. Zambia was the first African country in which the CLTS approach was successfully rolled
out, however it is very critical to coordinate efforts to maintain ownership and sustain associated benefits from
villages being free from open defecation. The role of media and civil society organisations can be instrumental.
The evaluator concurs with the PCR score and rates this section as satisfactory (3).
o. Environmental and social sustainability:
An environmental and social management plan has been developed for the programme and sets out the possible
environmental and social risks of the interventions. From the project appraisal report it can be noted that the
executing agency with support from the Bank has developed an Environmental and Social Streamlining Template
for Water and Sanitation to provide guidance for preparing the environmental and social impact assessment,
mitigation and monitoring at the local level, to be used during the design phase of sub-projects. These include
arrangements for water quality testing, consultations with the communities, the mobilisation of the various
committees, monitoring and arrangements for taking mitigation measures. The evaluator concurs with the PCR
score and rates this section as satisfactory (3).
4. PERFORMANCE OF STAKEHOLDERS
a. Bank performance:
The bank has overall performed satisfactory with regards to supervising this programme. The bank made use of
previous lessons learned from similar projects, for example the modality of using small contractors instead of
local authorities for construction was based on previous lessons learned. The Bank could perhaps have played a
stronger role in making sure that soft elements of interventions had been better captured in the monitoring and
evaluation framework, for example, capacity building and hygiene promotion and sensitization around benefits of
improved water supply.
The performance of the Bank is rated as Satisfactory (3).
b. Performance of the Borrower:
The Banks mission reports and external audit reports reflect a large number of issues during project
implementation which have negatively affected the performance of the borrower. Some of the issues are in the
areas of financial administration, reporting, staffing, supervision of consultants and recruitment of staff and
contractors. A number of critical activity areas could have been better utilised, for example gender mainstreaming
and sensitisation campaigns, use of mass media. There is a lack of evidence of sufficient measures put in place to
ensure financial sustainability of infrastructure and service put in place by the project. Based on the above, the
performance of the Borrower is rated as unsatisfactory (2) which is lower than the PCR score of
satisfactory (3). The reviewer concurs with the assessment made and the rating of unsatisfactory 2.
c. Performance of other stakeholders:
The performance of other stakeholders, being the contractors, is considered poor. The available information
clearly indicates that there have been large delays in implementation, the quality the works have been poor and
sometimes work was left unfinished. Based on the above, the performance of the Borrower is rated as
unsatisfactory (2), the same as the PCR score of unsatisfactory (2).
5. SUMMARY OF OVERALL PROJECT PERFORMANCE
a. Overall assessment:
The project’s development objectives, to improve access to water supply and sanitation and hygiene practices, is
considered very relevant with regards to the governments goals with regards to reducing poverty and improving
health outcomes of the rural population of Zambia. The programme was designed in a straightforward and logic
manner, consisting of separate components for water supply, sanitation and hygiene promotion, institutional
sector strengthening, and programme management. The programme also follows a clear course based on previous
interventions in the water and sanitation sector and includes a clear gender focus. Based on the information
available, it is evident that substantial progress was made with regards to improving access to water and sanitation
in the target areas (2 provinces) in which the programme has focussed.
The multiple extensions granted during implementation phase would question the quality of planning at project
design phase. The substantial under-estimation of unit-costs for construction of water supply schemes raises the
question on what basis the initial calculations at programme design were done. The risks assessment is adequate
and the risks considered in the appraisal report are realistic and inclusive. Special attention was planned to be
given to gender objectives as part of social protection, however there was no information stating how priorities of
vulnerable groups (such as the poor, elderly, disabled people, and children) are considered in the programme or
its sub-components. The Banks mission reports and external audit reports reflect a large number of issues during
project implementation which have negatively affected the performance of the borrower. There seems to be a lack
of systematic assessment of financial feasibility of water supply schemes and qualitative achievements such as
capacity building and hygiene promotion and sensitization have been insufficiently captured in progress
reporting.
Overall the evaluation considers the project satisfactory albeit with a lower average score (2.63) than the
PCR (2.88)
b. Design, implementation and utilization of the M&E (appreciation of the evaluator):
There is no evidence of a solid monitoring and evaluation framework in place including qualitative achievements
such as capacity building and hygiene promotion and sensitization.
Based on additional feedback from the task manager, it should be noted that the Bank was supporting specific
activities in the national program and not all activities. Development of the M&E framework was not part of it,
just providing M&E training was the scope as at that time DANIDA was providing support to the development of
an IMS system for rural water which was not completed and was not functional.
The gender reporting is not accurate, the “>50%” is not an exact figure and should have been specified. There is
also no evidence than any system that did exist was used. Overall score: 1.42
6. EVALUATION OF KEY LESSONS LEARNED AND RECOMMENDATIONS
a. Lessons learned:
The three lessons learned with respect to the programme are not all considered valid. The first lesson learned is
actually a recommendation. With regards to the second lesson learned; it is noted that despite trainings giving for
local authorities, there are still capacity constraints noted at the district and national level. This would raise the
questions, whether the contents of these trainings have been appropriate, to what extend these trainings given
were sufficient and if the right agencies and individual were targeted. The third lesson learned also contains a
recommendation which is reformulated and added under the section of recommendations.
The Evaluation’s opinion of each lesson is given in summary below:
1. NOT VALIDATED, REFORMULATED AS A RECOMMENDATION
2. VALIDATED
3. VALIDATED
The evaluator has no additional lessons learned to add.
b. Recommendations:
The four key-recommendations made in the PCR are all considered relevant and valid, however some are quite
project specific. In addition, the evaluator would recommend to have a better M&E system in place that captures
progress made in capacity strengthening, hygiene promotion with or without CLTS and additional dimensions of
access to water supply (distance, time, water quality, etc).
The Evaluation’s opinion of each recommendation is given in summary below:
1. VALIDATED
2. NOT VALIDATED, TOO PROJECT SPECIFIC
3. VALIDATED
4. NOT VALIDATED, TOO PROJECT SPECIFIC
The evaluator would like to add the following 2 recommendations:
1) There is need for improved coordination between the key stakeholders to avoid compromising the outcomes of
the national program of this size and importance (follows from third lesson learned).
2) The evaluator would recommend for future projects with a similar design to have a better M&E system in
place that captures progress made in capacity strengthening, hygiene promotion and additional dimensions of
access to water supply.
7. COMMENTS ON PCR QUALITY AND TIMELINESS The overall PCR rating is based on all or part of the criteria presented in the annexe and other: The quality of the PCR is rated as highly
satisfactory (4), satisfactory (3), unsatisfactory (2), and highly unsatisfactory (1). Le timeliness of the PCR is rated as on time (4) or late
(1). The participation of the Borrower, co-financier, and the bank’s external office(s) are rated as follows: Very Good (4), Good (3), Fair
(2), Poor (1).
The extent of quality and completeness of the PCR evidence and analysis to substantiate the ratings of the various
sections is considered satisfactory. The extent of objectivity of PCR assessment score is considered satisfactory.
The extent of internal consistency of PCR assessment ratings; inaccuracies; inconsistencies; is considered
satisfactory. The extent of identification and assessment of key factors (internal and exogenous) and unintended
effects (positive or negative) affecting design and implementation is considered satisfactory. The adequacy of
treatment of safeguards, fiduciary issues, and alignment and harmonization is considered satisfactory. The extent
of soundness of data generating and analysis process (including rates of returns) in support of PCR assessment is
considered satisfactory. The overall adequacy of the accessible evidence (from PCR including annexure and other
data provided is considered satisfactory. The extent to which lessons learned (and recommendations) are clear and
based on the PCR assessment is considered satisfactory. The extent of overall clarity and completeness of the
PCR is considered satisfactory.
The quality of the PCR is rated as satisfactory (3.00). The narrative and numeric scoring are generally consistent
with each other and sufficient explanation has been provided.
The timeliness of the PCR is rated as on time (4), since it was produced within 6 months after project closure.
8. SUMMARY OF THE EVALUATION This is a summary of both the PCR and IDEV ratings with justification for deviations/comments. Appropriate section of the PCR
Evaluation should be indicated in the last column in order to avoid detailed comments. The evaluator must provide a reasonable
explanation for each criterion the PCR rating is not validated by IDEV. Consequently, the overall rating of the project could be “equally
satisfactory”.
Criteria PCR PCREN Reason for disagreement/
Comments
RELEVANCE 3 3 Satisfactory.
Relevance of project development objective 3 3 Satisfactory.
Relevance of project design 3 3 Satisfactory.
EFFECTIVENESS 3 2 Unsatisfactory.
Development objective (DO) 3 2 Unsatisfactory. Based on the
information available, it is evident that
substantial progress has been made with
regards to improving access to water
and sanitation in the target areas (2
provinces) in which the programme has
focussed. It is however not clear to what
extent improved health and poverty
alleviation, as well as behavioural
change with regards to hygiene practices
was realised for Zambia’s rural
population. Despite the fact that RWSS
units have been established and X no. of
members have been trained, there is a
lack of evidence demonstrating that
local authorities have increased their
capacity to manage RWSS more
effectively.
EFFICIENCY 2.50 2.75 Satisfactory.
Timeliness 2 2 Unsatisfactory.
Resource use efficiency 3 4 Highly satisfactory. The calculated
proportion between the median physical
implementation rate (95.65%) and
commitment rate (80.43%) is 1.19
(which is is ≥1). The short explanation
given in the PCR is considered
sufficient.
Cost-benefit analysis 2 3 Satisfactory. The economic rate of
return at project approval stage was 28%
compared to 21% upon project
completion. The calculated ratio
between the ERR at completion and the
ERR at appraisal is 0.75 which is within
the category giving a satisfactory score
(ratio within category of <1 and ≥0.75).
Overall, the evaluator generally agrees
with the calculations made to arrive at
the ERR in Annex 10 of the appraisal
report.
Implementation progress (IP) 3 2 Unsatisfactory. The information made
available reports of late submission of
documents to the ADB, delays and
unfinished construction of water and
sanitation infrastructure, etc. Field
reports from the bank and external audit
reports show a large number of areas
and examples in which the executing
agency has filed to comply with
covenants and procedures. At various
times during the implementation phase,
some of the issues raised were, poor
book keeping record, lack of community
involvement to ensure ownership, issues
with tendering of works, poor financial
management, poor M&E, project
staffing issues, and motor bikes not
having insurance.
SUSTAINABILITY 3 3 Satisfactory.
Financial sustainability 3 3 Satisfactory. The PCR narrative for this
section uses the experience with the V-
WASHE Committees as good evidence
of financial sustainability. There seems
to be a lack of systematic assessment of
financial feasibility of water supply
schemes, for example through carrying
out a willingness and capacity to pay for
improved water services. The positive
example of Chipowe village is given,
stating their relatively high contribution.
Based on additional information
provided by the task manager, it is clear
that the project experience in Chipowe
village is similar to other villages in
other district where the programme has
had an intervention. Based on additional
information provided by the task
manager, it is clear the way local
authorities manage their budgets to
cover major maintenance works (for
costs exceeding ZMK 500). Only water
supply is mentioned when it comes to
financial sustainability, however it is
unclear what payment modalities exist
for the sanitation facilities constructed at
public places such as market centres.
Institutional sustainability and strengthening
of capacities 3 3 Satisfactory.
Ownership and sustainability of partnerships 3 3 Satisfactory.
Environmental and social sustainability 3 3 Satisfactory.
OVERALL PROJECT COMPLETION
RATING 2.86 2.69
Bank performance: 3 3
Borrower performance: 3 2 Unsatisfactory. The Banks mission
reports and external audit reports reflect
a large number of issues during project
implementation which have negatively
affected the performance of the
borrower. Some of the issues are in the
areas of financial administration,
reporting, staffing, supervision of
consultants and recruitment of staff and
contractors. A number of critical activity
areas could have been better utilized, for
example gender mainstreaming and
sensitization campaigns, use of mass
media. There is a lack of evidence of
sufficient measures put in place to
ensure financial sustainability of
infrastructure and service put in place by
the project.
Performance of other shareholders: 2 2 Unsatisfactory.
Overall PCR quality: - 3 Satisfactory.
9. PRIORITY FOR FUTURE EVALUATIVE WORK: PROJECT FOR PERFORMANCE
EVALUTION REPORT, IMPACT EVALUTION, COUNTRY/SECTOR REVIEWS OR
THEMATIC EVALUATION STUDIES:
- Project is part of a series and suitable for cluster evaluation
- Project is a success story
- High priority for impact evaluation
- Performance evaluation is required to sector/country review
- High priority for thematic or special evaluation studies (Country)
- PPER is required because of incomplete validation rating
Major areas of focus for future evaluation work:
a) Performance evaluation is required for sector/ country review
b) Cluster evaluation (institutional support)
c) Sector evaluation (budgetary support or public finance management reforms)
Follow up action by IDEV: Identify same cluster or sector operations; organize appropriate work or consultation mission to
facilitate a), b) and/or c).
Division Manager clearance Director signing off
Data source for validation:
Task Manager/ Responsible bank staff interviewed/contacted (in person, by telephone or
email)
Documents/ Database reports
Attachment:
PCR evaluation note validation sheet of performance ratings
List of references
Appendice 1
PROJECT COMPLETION REPORT EVALUATION NOTE Validation of PCR performance ratings
PCR rating scale:
Score Description 4 Very Good – Fully achieved with no shortcomings 3 Good – Mostly achieved despite a few shortcomings 2 Fair – Partially achieved. Shortcomings and achievements are roughly balanced 1 Poor – very limited achievement with extensive shortcomings
UTS Unable to score/rate NA Non Applicable
Criteria Sub-criteria PCR
work
score
IDEV
review Reasons for deviation/comments
RELEVANCE Relevance of the
project development
objective (DO) during
implementation
3 3
Satisfactory.
Relevance of project
design (from approval
to completion)
3 3
Satisfactory.
OVERALL RELEVANCE SCORE 3.0 3.0 Satisfactory.
EFFECTIVENE
SS*
Effectiveness in delivering outcomes
Outcome 1: Increased
access to water supply
in target area (%)
No
score 2
Target was not met. There is insufficient
information on why the calculation of costs of
water supply schemes
Outcome 2: Increased
access to sanitation in
target area (%)
No
score 3 Target almost met.
Outcome 3: No. of
additional people with
access to water in
target area
No
score 3 Satisfactory.
Outcome 4: No. of
additional people with
access to improved
sanitation from
constructed sanitation
facilities in schools,
health centers and
No
score 2
Details stating the reasons why access to public
sanitation facilities was not fully achieved
against target was later provided in written by
the task manager. The ‘Annex 1’ which contains
these reasons was not available to the evaluator
at the time of the evaluation.
Criteria Sub-criteria PCR
work
score
IDEV
review Reasons for deviation/comments
markets.
Outcome 5: % of
functional VWASHE
Committees with
Women holding key
positions
No
score 3 Satisfactory.
Outcome 6: Improved
functionality of rural
Water supply
facilities.
No
score 3 Satisfactory.
Effectiveness in delivering output
Output 1: 1,585 new
boreholes constructed
No
score 4
Highly satisfactory. Target was exceeded.
Output 2: 655 existing
boreholes
rehabilitated
No
score 3
Satisfactory. Target almost reached.
Justification considered adequate.
Output 3: 10 water
schemes reticulated
No
score 2
Unsatisfactory. Target not met. The justification
in the narrative section gives inadequate
sensitization about available water supply
technologies as the prime reason why the target
was not met. However, it is not explained or
justified why sensitization was inadequate.
Output 4: 272 hand
dug wells constructed
No
score 2
Unsatisfactory. Target not met. Also, there is a
lack of clarity on the exact reasons why just
44% of the target was met.
Output 5: 871 public
sanitation facilities
constructed
No
score 2
Unsatisfactory. There is a lack of information
on the reasons why the target was not met,
despite a number of project extensions.
Output 6: improved
capacity of MLGH
and districts in order
to manage RWSS
more effectively
No
score 3 Satisfactory.
Output 7: 24,400
VWASHE members
trained
No
score 3 Satisfactory.
Output 8: 448 area
pump menders trained
No
score 3 Satisfactory.
Development objective (DO)
Development
objective rating 3 2
Unsatisfactory. Based on the information
available, it is evident that substantial progress
has been made with regards to improving access
to water and sanitation in the target areas (2
provinces) in which the programme has focused.
Criteria Sub-criteria PCR
work
score
IDEV
review Reasons for deviation/comments
It is however not clear to what extent improved
health and poverty alleviation, as well as
behavioral change with regards to hygiene
practices was realized for Zambia’s rural
population. Despite the fact that RWSS units
have been established and X no. of members
have been trained, there is a lack of evidence
demonstrating that local authorities have
increased their capacity to manage RWSS more
effectively.
Beneficiaries
Beneficiary 1:
658,750
beneficiaries of clean
water supplies
97.1% 3
Satisfactory. The PCR includes a gender figure,
however “>50%” is not an exact figure. It
would be useful to know the exact figure for
future reference and for comparison with other
projects.
Beneficiary 2:
234,309 beneficiaries
accessing improved
public sanitation
facilities
65.8% 3
Satisfactory. It is unclear why household
sanitation was not captured under beneficiary
reporting.
Unanticipated outcomes (positive or negative not considered in the project logical
framework) and their level of impact on the project (high, moderate, low) Institutional
development
No
score
moder
ate Capacity strengthening of local authorities.
Gender
No
score high
It would be useful to know the exact figure of
%women for future reference and for
comparison with other projects.
Environment &
climate change
No
score -
Poverty reduction No
score -
Private sector
development
No
score moder
ate
Private firms and artisans have benefited from
construction of water supply and sanitation
infrastructure.
Regional integration No
score -
Other (specify)
EFFECTIVENESS OVERALL
SCORE
EFFICIENCY Timeliness (based on
the initial closing
date)
2 2 Unsatisfactory.
Resource used
efficiency
3 4 Highly satisfactory. The calculated proportion
between the median physical implementation
Criteria Sub-criteria PCR
work
score
IDEV
review Reasons for deviation/comments
rate (95.65%) and commitment rate (80.43%) is
1.19 (which is ≥1). The short explanation given
in the PCR is considered sufficient.
Cost-benefit analysis
2 3 Satisfactory. The economic rate of return at
project approval stage was 28% compared to
21% upon project completion. The calculated
ratio between the ERR at completion and the
ERR at appraisal is 0.75 which is within the
category giving a satisfactory score (ratio within
category of <1 and ≥0.75). Overall, the
evaluator generally agrees with the calculations
made to arrive at the ERR in Annex 10 of the
appraisal report.
Implementation
progress (from the
IPR)
3 2 Unsatisfactory. The information made available
reports of late submission of documents to the
ADB, delays and unfinished construction of
water and sanitation infrastructure, etc. Field
reports from the bank and external audit reports
show a large number of areas and examples in
which the executing agency has filed to comply
with covenants and procedures. At various times
during the implementation phase, some of the
issues raised were, poor book keeping record,
lack of community involvement to ensure
ownership, issues with tendering of works, poor
financial management, poor M&E, project
staffing issues, and motor bikes not having
insurance.
Other (specify)
OVERALL EFFICIENCY SCORE 2.50 2.75 Satisfactory.
SUSTAINABILIT
Y
Financial
sustainability
3 3 Satisfactory. The PCR narrative for this section
uses the experience with the V-WASHE
Committees as good evidence of financial
sustainability. There seems to be a lack of
systematic assessment of financial feasibility of
water supply schemes, for example through
carrying out a willingness and capacity to pay
for improved water services. The positive
example of Chipowe village is given, stating
their relatively high contribution. It is unclear to
what extend Chipowe village can be considered
representative for the other district where the
programme has had an intervention. It is unclear
to what extend local authorities have sufficient
budgets in place and earmarked to cover major
Criteria Sub-criteria PCR
work
score
IDEV
review Reasons for deviation/comments
maintenance works (for costs exceeding ZMK
500). Only water supply is mentioned when it
comes to financial sustainability, however it is
unclear what payment modalities exist for the
sanitation facilities constructed at public places
such as market centres.
Institutional
sustainability and
strengthening of
capacities
3 3 Satisfactory.
Ownership and
sustainability of
partnerships
3 3 Satisfactory.
Environmental and
social sustainability
3 3 Satisfactory.
*The rating of the effectiveness component is obtained from the development objective (DO) rating in the latest
IPR of the project (see Guidance Note on the IPR).
The ratings for outputs and outcomes are determined based on the project’s progress towards realizing its targets,
and the overall development objective of the project (DO) is obtained by combining the ratings obtained for
outputs and outcomes following the method defined in the IPR Guidance Note. The following method is applied:
Highly satisfactory (4), Satisfactory (3), Unsatisfactory (2) and Highly unsatisfactory (1).
Criteria Sub-criteria PCR
Work
score
IDEV
review Reasons for deviation/comments
BANK
PERFORMANCE
Proactive identification and
resolution of problems at
different stage of the project
cycle
No
score 2
Unsatisfactory. The Bank could have been
more pro-active, especially in taking steps
to reduce delays.
Use of previous lessons
learned from previous
operations during design and
implementation
No
score 3
Satisfactory. The modality of using
small contractors instead of local
authorities for construction was based
on previous lessons learned.
Promotion of stakeholder
participation to strengthen
ownership
No
score 3
Satisfactory.
Enforcement of safeguard and
fiduciary requirements
No
score 3
Satisfactory.
Design and implementation of
Monitoring & Evaluation
system
No
score 3
Satisfactory. Based on additional
feedback from the task manager, it
should be noted that the Bank was
supporting specific activities in the
national program and not at all
activities related to M&E.
Quality of Bank supervision
(mix of skills in supervisory
teams, etc)
No
score 3
Satisfactory.
Timeliness of responses to
requests
No
score 2
Unsatisfactory. Some responses took
longer than required.
OVERALL BANK PERFORMANCE
SCORE 3.00 2.71
Satisfactory
BORROWER
PERFORMANCE
Quality of preparation and
implementation
No
score 2
Compliance with covenants,
agreements and safeguards
No
score 2
Provision of timely counterpart
funding
No
score 3
Responsiveness to supervision
recommendations
No
score 2
Measures taken to establish
basis for project sustainability
No
score 2
Timeliness of preparing
requests
No
score 3
OVERALL BORROWER PERFORMANCE
SCORE 3.00 2.33 Unsatisfactory
PERFORMANCE
OF OTHER
STAKEHOLDERS
Timeliness of disbursements
by co-financiers
No
score 2
Functioning of collaborative
agreements
No
score 2
Quality of policy dialogue
with co-financiers (for PBOs
only)
No
score 2
Quality of work by service
providers
No
score 2
Responsiveness to client
demands
No
score 2
OVERALL PERFORMANCE OF OTHER
STAKEHOLDERS 2.00 2.00 Unsatisfactory
The overall rating is given: Very Good, Good, Fair and Poor.
(i) Very Good (HS) : 4
(ii) Good (H) : 3
(iii) Fair (US) : 2
(iv) Poor (HUS): 1
DESIGN, IMPLEMENTAION AND UTILIZATION OF MONITIRING AND
EVALUATION (M&E)
Criteria Sub-criteria IDEV
Score Comments
M&E DESIGN M&E system is in place, clear,
appropriate and realistic 2
Monitoring indicators and
monitoring plan were duly
approved
2
Existence of disaggregated gender
indicator 2
The gender reporting is not accurate, the
“>50%” is not an exact figure and should
have been specified.
Baseline data were available or
collected during the design 3
Other, specify
OVERALL M&E DESIGN SCORE 2.25
M&E
IMPLEMENTA-
TION
The M&E function is adequately
equipped and staffed 1 No evidence of an M&E officer in place.
OVERALL M&E IMPLEMENTATION SCORE 1
M&E
UTILIZATION
The borrower used the tracking
information for decision 1 No evidence that this was used/in place.
OVERALL M&E UTILIZATION SCORE 1
OVERALL M&E PERFORMANCE SCORE 1.42
PCR QUALITY EVALUATION
Criteria
PCR-
EVN (1-
4)
Comments
QUALITY OF PCR
1. Extent of quality and completeness of the
PCR evidence and analysis to substantiate the
ratings of the various sections
3
2. Extent of objectivity of PCR assessment
score
3
3. Extent of internal consistency of PCR
assessment ratings; inaccuracies;
inconsistencies; (in various sections; between
text and ratings; consistency of overall rating
with individual component ratings)
3
4. Extent of identification and assessment of key
factors (internal and exogenous) and unintended
effects (positive or negative) affecting design
and implementation
3
5. Adequacy of treatment of safeguards,
fiduciary issues, and alignment and
harmonization
3
6. Extent of soundness of data generating and
analysis process (including rates of returns) in
support of PCR assessment
3
7. Overall adequacy of the accessible evidence
(from PCR including annexure and other data
provided)
3
8. Extent to which lessons learned (and
recommendations) are clear and based on the
PCR assessment (evidence & analysis)
3
9. Extent of overall clarity and completeness of
the PCR
3
Other (specify)
PCR QUALITY SCORE 3.0 No further comments.
PCR compliance with guidelines (PCR/OM ; IDEV)
1. PCR Timeliness (On time = 4; Late= 1) 4 PCR report was completed within 6 months
after project completion.
2. Extent of participation of borrower, Co-
financiers & field offices in PCR preparation
No information
3. Other aspect(s) (specify)
PCR COMPLIANCE SCORE
*** rated as Very Good (4), or Good (3), or Fair (2), or Poor (1)
References
African Development Bank Group, Policy for integrated water resources management, April 2000
African Development Bank Group, Staff Guidance on Project Completion Reporting and Rating, Quality
Assurance and Results Department (ORQR), Quality Assurance Division (ORQR.2), August 2012
African Development Bank Group, Policy for integrated water resources management, April 2000
Project Completion Report for National Rural Water Supply and Sanitation Program Zambia. December
2015
Government of the Republic of Zambia, National Water Policy, Ministry of Energy and Water
Development, February 2010.
Government of the Republic of Zambia, Water Act Ministry of Legal Affairs, 2006
Various other internal reports, memos, including trip reports, progress reports, etc