zavala.ed

54
Juggling Act: Re-planning & Building an Observatory…. Simultaneously!!!! Eddie Zavala – SOFIA Deputy Program Manager Patricia Daws – SOFIA Program Business Manager February 10, 2011 Used with permission

Upload: nasapmc

Post on 15-Nov-2014

13.054 views

Category:

Technology


0 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Zavala.ed

Juggling Act:Re-planning & Building an Observatory….

Simultaneously!!!!

Eddie Zavala – SOFIA Deputy Program ManagerPatricia Daws – SOFIA Program Business Manager

February 10, 2011

Used with permission

Page 2: Zavala.ed

Purpose

This presentation discusses how the SOFIA Program, in the midst of a re-plan and system development phase, executed multiple simultaneous planning and business initiatives/requirements and integrated them into improved project management processes without impacting technical progress.

Feb 10, 2011 22011 PM Challenge

Page 3: Zavala.ed

Overview• The SOFIA Mission

• Before the Re-plan

• The Juggling Act

• Managing the Chaos

• Engage Existing and New Jugglers

• The Results

• KEY BREAKTHROUGHS

• Conclusion

Feb 10, 2011 32011 PM Challenge

Page 4: Zavala.ed

The SOFIA Mission…

Feb 10, 2011 42011 PM Challenge

Page 5: Zavala.ed

Stratospheric Observatory For Infrared Astronomy (SOFIA)

Feb 10, 2011 52011 PM Challenge

Page 6: Zavala.ed

Feb 10, 2011 62011 PM Challenge

Page 7: Zavala.ed

Why SOFIA?• Infrared information is important

to gather astronomy science data – IR can see through dust– IR can detect cold gases

and dust, other cool stars, and planetary objects

– Forming stars have their light intensity peaks in the IR

– IR can detect the content of the early universe through red shift of distant objects

• Infrared is filtered by moisture in atmosphere

• At 41,000 ft, above more than 99% of the water vapor

• Spacecraft consume infrared required cryogens' in 3 to 4 years

• Mobility: anywhere, anytime• Long lifetime• A near-space observatory that

comes home after every flight

Feb 10, 2011 72011 PM Challenge

Page 8: Zavala.ed

The Orion Constellation

In Infrared LightIn Visible Light

Feb 10, 2011 82011 PM Challenge

Page 9: Zavala.ed

Before the re-plan…

Feb 10, 2011 92011 PM Challenge

Page 10: Zavala.ed

Program Background– The predecessor to SOFIA, the Kupier Airborne Observatory (KAO),

was decommissioned in 1995 to start SOFIA

– SOFIA established as a 80/20 partnership between US and Germany (NASA and DLR)• NASA receives 80% of available science time, DLR 20%

– Initial program model, was contractor led with NASA oversight (privatized)

– Program slated for cancellation in the spring of 2006

– Agency approves program for continued funding in the fall of 2006• Program restructured

– Government led contractor supported– Two projects, Science and Platform

» Science at Ames Research Center» Platform at Dryden Flight Research Center

Feb 10, 2011 102011 PM Challenge

Page 11: Zavala.ed

Program Restructure

Feb 10, 2011 112011 PM Challenge

Page 12: Zavala.ed

Incremental / Phased Development Approach

SRR

PDR

CDR

ΔORDΔPDRΔCDR ΔCDR ΔCDR

Flt Test

DataReview

ΔSAR ΔSAR ΔSAR

CDS/CDDS/CECSMCCS Build #1

User Need

A/C ModificationTA/CECS

ΔSAR

Final Upgrades

Ground Test

Original Requirements Baseline

Requirements Re-Baseline

ΔCDR

Status - Sept 2007

InstrumentationCECS Improvements

Flt Test

Data Review

Ground Test

Flt Test

Data Review

Ground Test

Flt Test

DataReview

Ground Test

Decomposition &

Definition Inte

grati

on &

Ver

ifica

tion

Fab. & Assemble

PartiallyComplete

Cavity Environmental Control System (CECS)

Decomposition &

Definition Inte

grati

on &

Ver

ifica

tion

Fab. & Assemble

A/C ModificationTelescope Assembly

Cavity Door Drive System (CDDS)

Science Instruments (SI)

Complete

Remaining

Decomposition &

Definition Inte

grati

on &

Ver

ifica

tion

Fab. & Assemble

Decomposition &

Definition Inte

grati

on &

Ver

ifica

tion

Fab. & Assemble

Cavity Door System (CDS)

Decomposition &

Definition Inte

grati

on &

Ver

ifica

tion

Fab. & Assemble

Mission Control & Communications System (MCCS)

Decomposition &

Definition

Inte

grati

on &

Ver

ifica

tion

Fab. & Assemble

Status of 7 Science Instruments Varies Dependent on the Instrument

ORD

Closed Door Open DoorTA Characterization & Shared Purpose

Full OperationalCapability

Early ScienceFunctional/Ferry

Flt Test

DataReview

SAR

Ground Test

FRR

Flt Test

Data ReviewΔSAR

Ground Test

FRR

Final MCCS/CECS-LN2Science Instruments

MCCS for Early ScienceEarly Science Instruments

ΔSRR ΔSRR ΔSRRFRR FRR FRR ORRΔSRR

Segment 0 Segment 1 Segment 2 Segment 3 Segment 4

Rework Required

ΔPDR

12

Page 13: Zavala.ed

Approximate Aircraft Configuration at Program Restructure, 2006

Feb 10, 2011 132011 PM Challenge

Page 14: Zavala.ed

The Juggling…

Feb 10, 2011 142011 PM Challenge

Page 15: Zavala.ed

Introducing the Juggler…

System Engineering & Integration

Program Restructure

Incremental Observatory Development

The SOFIA Program

OfficeFeb 10, 2011 152011 PM Challenge

Page 16: Zavala.ed

Build a World-Class Observatory

Implementing the New Program Structure

Inter-leaving Development and Early Science(phased development approach)

Science Community Expectations

Integrating the New Team

Systems Engineering & Integration

Deploy working observatory capabilities and services

Feb 10, 2011 162011 PM Challenge

Page 17: Zavala.ed

New Challenges• Can you handle a few more balls in the air? • Subsystem development schedule delays

MCCS Development for Early Science

CDDS Technology Development Issues

Feb 10, 2011 172011 PM Challenge

Page 18: Zavala.ed

Working harder, but it’s

all under controlFeb 10, 2011 182011 PM Challenge

Page 19: Zavala.ed

The Impossible Act…

Feb 10, 2011 192011 PM Challenge

Page 20: Zavala.ed

The “fun” begins…

(but don’t drop any of the other balls!!)

Technical Re-plan

Clear the flight envelope

GAO Large Program Assessment/Audit

Standing Review Board (SRB)

Get to the Initiation of Science Flights

Feb 10, 2011 202011 PM Challenge

Page 21: Zavala.ed

And the fun keeps coming….

(but don’t drop any of the other balls!!)

Joint Cost & Schedule Confidence Level (JCL)

Earned Value Implementation

IG Pre Audit, Formal Audit, Recommendations

Feb 10, 2011 212011 PM Challenge

Page 22: Zavala.ed

Something’s gotta give!!!!

Feb 10, 2011 222011 PM Challenge

Page 23: Zavala.ed

Managing the Chaos…

Feb 10, 2011 232011 PM Challenge

Page 24: Zavala.ed

Take a timeout….

What’simportant?

Whatdon’t we know?

What’sfeasible?What’s

urgent?

How are we going to get this done ?!

What added value can we get from these new requirements?

Feb 10, 2011 242011 PM Challenge

Page 25: Zavala.ed

Managing the Chaos…

• Strategize….before you add more jugglers to the team, or even accept the balls

• Sequence the balls…don’t try to accept them all at once

• Leverage skill and experience of existing jugglers…

• Learn new “juggling skills”– “Jugglers” and “juggling skills” equate to process

improvement, functional groups, NOT additional staff

Feb 10, 2011 252011 PM Challenge

Page 26: Zavala.ed

Sequence the Balls• The timing of when new balls get thrown in the mix is critical to

keeping everything in the air

Technical Re-plan

• Technical re-plan required

Standing Review Board (SRB)

• SRB required…but urgent?

Flight Test

• Same team preparing for initial flight test of the observatory

Feb 10, 2011 262011 PM Challenge

Page 27: Zavala.ed

Sequence the Balls

Technical Re-planFlight Test

Standing Review Board (SRB)

• KEY DECISION: Prioritize Flight Test over the SRB• Provided a pre-brief to the SRB to give them time to get

familiar with the program, but minimize impact to the project teams

• Top priority – Conduct Flight Test so that we can start science missions

• Reschedule formal SRB after initial flight test phase complete

Interimbaseline

• KEY DECISION: Index the program to an interim baseline pending SRB recommendations

Feb 10, 2011 272011 PM Challenge

Page 28: Zavala.ed

Engage Existing / New Jugglers…

Feb 10, 2011 282011 PM Challenge

Page 29: Zavala.ed

Engage Existing Jugglers…

• Leverage existing team members and groups instead of adding to the confusion with new players

• Introducing…

Feb 10, 2011 292011 PM Challenge

Page 30: Zavala.ed

Juggler #2

Owns the key skills to keep the act going…developing the observatory

Technical Coordination

Requirements Management

System Engineering & Integration

Mission Preparedness & Execution

Technical Risk Management

The Observato

ry IPT

Feb 10, 2011 302011 PM Challenge

Page 31: Zavala.ed

Juggler #3

CRM has a new key skill…the THREAT DATABASE

Makes it easier for team to identify threats “on the fly”

“any issue that keeps you up at night”

Threats linked to milestones with quantified cost / schedule impacts

Improved Program risk identification

Continuous Risk

Management

Feb 10, 2011 312011 PM Challenge

Page 32: Zavala.ed

The Threat Database…

Feb 10, 2011 322011 PM Challenge

Page 33: Zavala.ed

Communication of Concerns

SOFIA Team ConcernsSOFIA Team Concerns

ThreatsThreats

ScienceScience PlatformPlatform

ProgramProgram

Concerns are collected at the team level…

Threats “roll up” into formal Risks

“Significant” Risks tracked at Program Level

Traceability of concerns

maintained from top to bottom

Feb 10, 2011 332011 PM Challenge

Page 34: Zavala.ed

Risks, Threats, and the JCL

Concerns from SOFIA Team

The threat database is used to populate the JCL risk register and the Risk Action Matrix at the Project and Program Level

The threat database proved to be a good predictor of likely schedule impacts and helped focus mitigations

Feb 10, 2011 342011 PM Challenge

Page 35: Zavala.ed

Two Coordinated Jugglers

ThreatDB

Synchronized by tossing the Threat Database ball back and forthObservatory

IPTContinuous RiskManagement

Feb 10, 2011 352011 PM Challenge

Page 36: Zavala.ed

Juggler #4Tune up key juggling skills to manage more balls in the air at one time

By teaming with other Jugglers, tossing balls back and forth, sharing the load…

Leverage threat database for cost/risk integration (toss ball back and forth with CRM & Observatory IPT)

Leverage existing budget data for schedule/cost integration (coordinating with SPO)

Acquiring JCL implementation knowledge

Integrated technical and reserve management strategy

Integrated Schedule &

Budget

Feb 10, 2011 362011 PM Challenge

Page 37: Zavala.ed

Unencumbered

Threats UnknownsDistributed Unapproved

Approved

Reserves Management Strategy

Feb 10, 2011 372011 PM Challenge

Page 38: Zavala.ed

Integrated Schedule / Budget

Continuous RiskManagement

Three Coordinated Jugglers

ThreatDB

Synchronized by tossing the Threat Database and Schedule balls back and forth

ObservatoryIPT

Schedule

Feb 10, 2011 382011 PM Challenge

Page 39: Zavala.ed

Bring the New Juggler#5….Integrates cross-functional knowledge to create a new skill

Integrated Master Schedule with:

Tie to Threat Database via JCL Risk Registry

Resource Loaded Tasks

JCL plug-in

Leverage JCL for EVM Implementation

Institutionalize value-added processes and analyses

Ensure continual improvement and sustaining processes through coordination with other jugglers

Schedule IPT

Feb 10, 2011 392011 PM Challenge

Page 40: Zavala.ed

Integrated Schedule / Budget

Continuous RiskManagement

Program-wide Coordination

ThreatDB

ObservatoryIPT

IMS

ScheduleIPT SOFIA Program Office

Feb 10, 2011 402011 PM Challenge

Page 41: Zavala.ed

Results

Feb 10, 2011 412011 PM Challenge

Page 42: Zavala.ed

Accomplishments• Can really work together and perform tricks!!!

Completed technical re-plan Successful First Flight with 100% open door Successful First Light through telescope in the

air Completed Envelope Expansion Completed JCL Successful SRB Completed Re-plan with APMC Completed EVM Implementation Completed Observatory testing with Integrated

MCCS/CDDS for Early Science.

Initiation of Science Flights on Nov 30 / Dec 1, 2010!!!

Feb 10, 2011 422011 PM Challenge

Page 43: Zavala.ed

Key Breakthroughs• Key decisions made to set down balls…not drop them

– Leveraged the results of technical re-plan – Re-sequenced SRB appropriately– Program indexed with an interim baseline

• Enhanced CRM processes– Threat database construct– Linking threats to specific activities, identify cost and

schedule impact– Use threat database as primary source for JCL inputs– Feeder to traditional risk management – augment, don’t

replace• Integrated Master Schedule

– Resources, threats, JCL/EVM enabled• Finding a way to dissolve traditional stovepipes

– Key relationships (Business Manager, CE, SPO, PMs…)– Integrated products that allow for cross-functional use and

enabled new teams to implement new requirementsFeb 10, 2011 432011 PM Challenge

Page 44: Zavala.ed

Conclusion

Feb 10, 2011 442011 PM Challenge

Page 45: Zavala.ed

Conclusion

• The SOFIA Program found ways to leverage existing roles in new ways to meet the requirements without creating unmanageable overhead. The team developed strategies and value added processes - such as improved risk identification, structured reserves management, cost/risk integration - so that the effort expended resulted in a positive return to the program.

Feb 10, 2011 452011 PM Challenge

Page 46: Zavala.ed

Obsv Capabilities

Program Risks / RAM

EVM

JCL

PPBE Resource

Loaded IMS

Threat Database

The Improved Operating Model

CRM

Observatory IPT

ISF

ScheduleIPT

SPO

SRB

FOC

Integrated Budget

GAO Audits

Reserves Mgt

SE&I

Feb 10, 2011 462011 PM Challenge

Page 47: Zavala.ed

Questions?

Feb 10, 2011 472011 PM Challenge

Page 48: Zavala.ed

SOFIA First Flight at Waco, April 26, 2007

Feb 10, 2011 482011 PM Challenge

Page 49: Zavala.ed

SOFIA Door Fully Open In-Flight, Dec 18, 2009

Feb 10, 2011 492011 PM Challenge

Page 50: Zavala.ed

Successful 100% Door Open Landing; April 14, 2010

Feb 10, 2011 502011 PM Challenge

Page 51: Zavala.ed

Telescope in Aft Cavity

Feb 10, 2011 512011 PM Challenge

Page 52: Zavala.ed

SOFIA First Light Image – JupiterMay 26, 2010

SOFIA infrared image (5.4, 24.2, and 37.1 m)

Feb 10, 2011 522011 PM Challenge

Page 53: Zavala.ed

SOFIA First Light Image – M82

SOFIA infrared image (19.7, 31.5, and 37.1 m)

Feb 10, 2011 532011 PM Challenge

Page 54: Zavala.ed

Initiation of Science FlightsNov 1 – Dec 1, 2010

Feb 10, 2011 542011 PM Challenge